ny psc report on october 2011 nor'easter response

Upload: daily-freeman

Post on 05-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    1/29

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    2/29

    TABLE OF CONTENTS

    EXECUTIVE SUMMARY ......................................................................................... 1

    HURRCANE IRENE AND TROPICAL STORM LEE OUTSTANDING

    IMPROVEMENT OPPORTUNITIES ....................................................................... 4

    PERFORMANCE ASSESSMENT .............................................................................. 6

    Overview .......................................................................................................... 6

    Orange and Rockland ..................................................................................... 10

    New York State Electric and Gas .................................................................... 15

    Central Hudson .............................................................................................. 18

    Con Edison ..................................................................................................... 20

    CONCLUSION AND RECOMMENDATIONS .......................................................... 22

    Attachment 1 Hurricane Irene Recommendations ......................................... 25

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    3/29

    EXECUTIVESUMMARY

    On Friday, October 28, 2011, initial weather forecasts indicated that a

    Northeaster was in route to our region and it was expected to bring snow to the

    Catskills, the Hudson Valley, and the Taconic region of the State.1 A winter storm

    warning was issued by the National Weather Service on Saturday, October 29. It

    forecast significant amounts of heavy, wet snowup to seven inches in areas along the

    Hudson River and up to ten inches in the southeastern portion of the state. The

    forecasts predicted widespread power outages as a result of snow accumulations on

    foliage-laden tree branches.

    Snow began to fall mid-day Saturday and continued through the night. By

    Saturday evening, the utility companies had begun to report numerous electric service

    interruptions due to heavy snow and wind gusts. This Northeaster was the third major

    weather event to hit the region in three months. In some areas, the October storm

    caused greater tree damage and power outages than Hurricane Irene and Tropical

    Storm Leestorms that occurred in August and September of 2011, respectively. In

    total, service to over 400,000 customers was disrupted due to branches and trees

    sagging and breaking on utility infrastructure. Overall, this service restoration effort

    took eight days to complete.

    Following the October storm, Staff investigated the performances of the

    Consolidated Edison Company of New York (Con Edison), New York State Electric and

    Gas (NYSEG), Central Hudson Gas and Electric (Central Hudson), and Orange and

    Rockland Utilities (Orange and Rockland)all of which sustained customer outages that

    lasted greater than 72 hours. Staffs investigation also assessed whether the utilitieswere properly prepared for the Northeaster; whether they responded appropriately in

    its aftermath; whether they have identified the lessons learned from this storm; and,

    whether they are taking all necessary corrective actions. We have also examined the

    1New York City was also forecast to be hit by the storm but to a lesser extent than the upstate

    regions.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    4/29

    CASE 11-M-0595

    -2-

    communications they used to inform customers, the media, and government officials of

    the service restoration efforts. Our review of the October snowstorm has found utility

    company deficiencies similar to those indentified by our performance review of the

    utility company efforts for Hurricane Irene and Tropical Storm Lee. Thus, the

    recommendations presented in the Utility Performance Report Following Hurricane

    Irene and Tropical Storm Lee likewise pertain to the utility responses to this storm.2

    Our investigation generally found (except for Orange and Rockland) that

    the utility companies did not have substantial difficulties acquiring the crews they

    needed to perform the service restoration work, and they maintained adequate

    communications with the public, the media, and public officials via traditional

    communication channels; however, the utilities still could do more to take advantage or

    alternative communication technologies, such as social media, to communicate with

    customers. We did find, however, that NYSEG should have issued some of its estimated

    times of restoration (ETRs) sooner than it did in those Divisions that were less affected

    by the storm. We also found that NYSEG failed to contact its customers using life

    support equipment ahead of the storm. Further, for some Divisions, NYSEG needs to

    train additional personnel to serve as wire guards.

    With respect to Orange and Rockland, our investigation found that the

    utility did not perform well in several respects. Issues that existed with the Companys

    Hurricane Irene restoration efforts also existed for this storm. During Hurricane Irene,

    Orange and Rockland was able to manage the storms effects better than it did for the

    October snowstorm because it had supplemented and pre-staged personnel prior to its

    arrival. In October, Orange and Rockland was overwhelmed by the damage caused by

    the heavy snow and did not respond as well to the storm conditions it faced this time

    around. We found that the Company was slow to supplement crew levels with either

    2 See Attachment 1 to this report which lists the Hurricane Irene and Tropical Storm Lee

    related recommendations that are applicable here.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    5/29

    CASE 11-M-0595

    -3-

    the mutual assistance available from other utility companies or by using independent

    contractors. Also, Orange and Rockland was unable to respond properly to the

    numerous down wire conditions that were reported to it. Limited telephone calling

    capacity at the utilitys call center resulted in some customers being unable to contact

    the Company to report their service conditions or to obtain information. Orange and

    Rockland also failed to provide customers localized, estimated restoration times which

    likely increased the number of customer calls to the Company seeking service

    restoration information. Consequently, this report contains specific recommendations

    for Orange and Rockland which are intended to improve its future performance.

    In the following Chapters, we provide the results of our examination of

    each utility companys service restoration performances. Recommendations for

    improvements are presented, as necessary, to obtain better storm responses in the

    future. The recommendations presented here are designed to build upon those made

    in our performance report following Hurricane Irene and Tropical Storm Lee. The

    recommendations emanating from the Irene and Lee Report are summarized in

    Attachment 1 to this report.

    A copy of this report is being sent to the New York utility companies by the

    Director of the Office of Electric, Gas, and Water. All New York electric and gas utilities

    should review this report and, to the extent they have similar conditions and

    circumstances, they should implement the recommendations provided here. The

    companies are expected to implement recommendations applicable to their operations

    by no later than 30 days from the issuance of this Report. The Companies should report

    to Staff within 30 days on their progress in implementing the recommendations and

    every three months thereafter, until such time as Staff determines implementation is

    complete and reporting is no longer necessary. In addition, Staff expects each progress

    report to include the status of implementing the Companys own recommendations

    identified in their self-assessments.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    6/29

    CASE 11-M-0595

    -4-

    HURRCANEIRENEANDTROPICALSTORMLEE

    OUTSTANDINGIMPROVEMENTOPPORTUNITIES3

    The October 2011 storm occurred only about a month and a half after

    Hurricane Irene and Tropical Storm Lee struck New York State. When the October storm

    hit, the utility companies encountered many of the same issues they had experienced

    during the earlier storms. This is largely due to the close timing of the three storms.

    When the October storm began, the utilities were in the process of

    finalizing their Irene and Lee self-assessment reports for submission to Staff.4

    Thus, the

    utilities had initially begun to identify their planned improvements from their

    assessments of the performance during Irene and Lee storms. In October, many of the

    identified improvements were only able to be implemented in a provisional or partial

    manneror not at all given the short time and limited opportunity between the initial

    identification of improvements and the implementation of the resolutions. Without

    sufficient time to implement the self-identified improvements drawn from Irene and

    Lee, the earlier identified concerns remained matters of concern for the October

    snowstorm. Thus, Staff expects the corrective actions identified for Irene and Lee to

    also apply to the October storm.

    3 The Staff report addressing Irene and Lee describes, in detail, the utility companies storm-

    related functions. It also describesthe Departments overall responsibility to review the

    adequacy of the utility companies emergency plans, their storm preparations, stormresponses and service restoration efforts. Given the comprehensive description of these

    functions contained in the Irene and Lee Report, this report does not reiterate that

    information that is conveniently available in our companion report. This report concentrates

    on the analysis of the utility performances for the October storm and only briefly refers to

    the information available to the reader in the Irene and Lee Report.

    4The utilities were granted filing extensions for the Irene and Lee self-assessments to allow

    them to remain focused on their recovery efforts for the October snowstorm.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    7/29

    CASE 11-M-0595

    -5-

    Staffs investigation of the companies performances during Irene and Lee

    culminated in a comprehensive report containing 30 recommendations. Nearly all the

    recommendations applicable to the electric utilities also apply to their performances for

    the October storm.5

    The successful implementation of the recommendations contained

    in the Irene and Lee Report will also resolve the similar concerns that were identified in

    connection with the October storm. Attachment 1 to this report contains the

    recommendations first generated by our review of Irene and Lee that apply equally to

    our review of the October 2011 storm.

    5Case 11-M-0481 In the Matter of the Outages Caused by Hurricane Irene and Tropical

    Storm Lee. In the report, Staff made recommendations for enhancing communications, as

    well as improving the restoration of electric, gas, and telecommunications services.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    8/29

    CASE 11-M-0595

    -6-

    PERFORMANCEASSESSMENT

    OVERVIEW

    The October 2011 Northeaster was the third major storm to hit our region

    in the span of three months. This storm hit many of the areas that were impacted

    earlier by Hurricane Irene and Tropical Storm Leein some locations causing more tree

    damage and power outages than did the prior storms.

    This storm was an unusually early snowfall for October. It produced more

    than 20 inches of heavy, wet snow accumulations in some areas. In at least 20 cities,

    the snowfall broke daily and monthly records. Wind gusts, in excess of 30 miles an hour,

    were common throughout southeastern New York. These conditions, combined with

    substantial amounts of foliage still in place, produced widespread tree damage.

    Significant amounts of tree damage, and associated damage to the electric

    infrastructure, occurred across the southeastern region of New York, including locations

    south and east of the I-88 corridor that runs from Schenectady to Binghamton. As the

    storm progressed, customer interruptions climbed on Saturday evening and overnight

    into Sunday morning. In all, approximately 400,000 New York State customers lost their

    electric service.

    Some areas sustained more damage from the Northeaster than they had

    from Hurricane Irene. Out-of-state line crews were brought in both before and after the

    storm to help with the restoration. To complete the service restorations following this

    storm took about a week; the restorations progressed steadily during this period. As

    shown in Figure 1, below, fifty percent of customers statewide had their service

    restored within three days; ninety percent had their service restored within five days.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    9/29

    CASE 11-M-0595

    -7-

    Figure 1: Customer Outages Statewide

    The utility companies had restoration crews standing ready for the

    October snowstorms arrival. On Saturday, October 29, over 360 crews were available;

    over half of the crews were provided by contractors and mutual assistance programs.

    By Monday, October 31, over 1,000 line, tree and service crews were working to restore

    electric service to customers. The companies retained the contractors who were

    working in their service territories, and they obtained additional contractor crews. The

    utilities reached out to other utility companies in New York and in states in the Mid-

    Atlantic and New England regions, using their established mutual assistance groups.

    With more than three million customers in the Northeast affected by this storm,

    available line crews were in short supply as many utilities throughout the region were

    also in need of mutual assistance support. Nevertheless, the New York utilities were

    able to acquire the crews they needed to mount an effective restoration, with the single

    exception of Orange and Rockland whose circumstances are discussed below.

    All the companies had sufficient materials and equipment for their service

    restoration efforts. The companies damage assessors were available on Saturday. But

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    10/29

    CASE 11-M-0595

    -8-

    given the storms timing, duration, and the road conditions, full-scale damage

    assessments could not begin until daybreak Sunday. Con Edison, Central Hudson, and

    Orange and Rockland supplemented their damage assessment personnel by using

    contractors; NYSEG supplemented its damage assessment force using assessors from its

    unaffected Divisions, including personnel provided by its sister company, Rochester Gas

    and Electric. As the restoration efforts progressed, the companies relocated their

    damage assessors and sent them to heavily-damaged areas to assist in the assessments

    and circuit sweeps at those locations. All the companies performed adequate damage

    assessments.

    In total, over 15,800 down wires were reported for the October storm

    more than half ofthe down wires occurred in Orange and Rocklands service area. As

    part of our review, we identified that the process of responding to down wire reports is

    not as detailed and organized as it could be. Most notable is that the restoration

    priority tends to be based on information provided at the time of the down wire report,

    which may be limited in facts, and does methodically account for known information

    based on its location. As a result, we recommend that all utilities Emergency Plans

    should identify the priority for energized wires during an active storm and the priorities

    for repair work post storm, taking into account the potential for public harm (including,

    for example, population density, pedestrian access, public uses of an area, and the

    proximity of the electric facilities to public facilities such as schools) and the safety of

    utility employees. We also determined that companies should be more aggressive when

    planning for the number of wire guards, particularly when circumstances promote the

    likelihood of downed wires, as was the case during Hurricane Irene. As part of the Irene

    and Lee Report, Staff recommends that the utilities better defined staffing requirements

    for wire guards and identify means to obtain supplemental wire guards to be used in

    emergencies in order to meet the staffing requirements. These recommendations also

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    11/29

    CASE 11-M-0595

    -9-

    apply to this snowstorm and should help improve the overall response to down wires

    going forward.

    During the event, the companies communicated with news reporters, the

    media, elected officials, and emergency response organizations. The utilities engaged in

    proactive media efforts by issuing multiple press releases daily and by posting available

    information on their websites. The utility press releases contained pertinent

    information on the outage numbers, crew counts, the estimated times of restoration

    (ETRs), the locations for dry ice and bottled water distributions, emergency contact

    numbers, and they provided safety precautions about downed wires.6

    We found that

    the utilities, except for Orange and Rockland, maintained effective communications with

    their customers. Although Orange and Rockland did engage in similar outreach

    activities as described above, the lack of detailed information, particularly regional and

    localized ETRs, reduced the effectiveness of this effort in meeting customer needs.

    About 473,000 pounds of dry ice was distributed following the storm. In

    addition to distributing dry ice to its own customers, NYSEG supplied dry ice and bottled

    water to others for distribution in Dutchess, Putnam, and Westchester County. Con

    Edison was challenged in its efforts to secure adequate quantities of dry ice, as dry ice

    was in short supply due to high demands from all areas affected. The Company resorted

    to distributing ordinary, wet ice to customers in addition to providing dry ice. In the

    Irene and Lee Report, Staff has recommended that the utilities identify additional dry ice

    suppliers. That recommendation applies as well to the circumstances of the October

    storm.

    In general, our investigation found that the utilities maintained proper

    contacts with critical care facilities and with customers who depend on life support

    6 The utilities also regularly provide bill inserts to customers that include information on how

    to report the loss of power; how to obtain updates during storms; and, the dangers

    presented by downed wires and how to safely avoid the wires.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    12/29

    CASE 11-M-0595

    -10-

    equipment (LSE customers). For example, Con Edison monitored the status of facility-

    specific emergency generation and provided the three critical care facilities assistance

    following the snowstorm to keep their emergency generators operational until their

    services were restored. As discussed below, NYSEG did not initiate the required pre-

    storm calls, as defined in its procedures, to LSE customers who were on the identified

    storm path.

    Staff found that Central Hudson was unable to reach three LSE customers,

    either by phone or by field visits. The Company properly sought the assistance of

    municipal emergency services as a means to contact the unreachable customers.

    Central Hudson, however, failed to ascertain whether the emergency services actually

    made such contact. The Irene and Lee Report contains a recommendation to the

    utilities that they address this concern by using follow-up efforts to verify contacts made

    by emergency services during storms.

    ORANGE AND ROCKLAND

    The peak number of customers without electric service in Orange and

    Rocklands service territory was 71,141, or 33% companywide. Orange and Rockland

    was hit hardest in its Eastern and Central Divisions, with 43% and 30% of the customers

    in these divisions without electric service at peak, respectively.

    Orange and Rockland performed poorly in acquiring restoration crews.

    The Company had 39 line crews and 16 tree crews ready to perform restoration on

    Saturday, October 29. While the number of crews it had at the onset of the storm was

    comparable to the other utilities, Orange and Rockland failed to adequately supplement

    the initial crew levels to support the restoration effort given the amount of damage

    experienced and the number of down wires reported.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    13/29

    CASE 11-M-0595

    -11-

    The Company added to its crews, and brought in some contractor and

    mutual aid crews, to assist in the restoration effort on Sunday and it continued to

    acquire crews over the next five days. On Monday, October 31, the Company had 121

    line crews (89 of which were provided by contractors and mutual aid), 65 tree crews,

    and 78 service crews. While the majority of crews were assigned to work in the hard hit

    Eastern Division, this workforce level was still insufficient given the storm impact in the

    service area.

    Crew levels peaked on Friday, November 4 when Orange and Rockland

    had 374 line, 80 tree, and 154 service crews working to restore service. The Company

    completed restoration on Sunday, November 6. We recommend that Orange and

    Rockland develop more proactive protocols and procedures for seeking external

    contractor and mutual aid crews, from within and outside the State, to ensure that

    sufficient crews are requested and acquired before and during emergency response

    efforts. The protocols should be incorporated into the Companys Emergency Plan and

    contain appropriate actions for the conditions applicable to each of the three storm

    event classifications.

    Orange and Rockland received reports of over 8,100 down wire incidents

    during the course of the stormmore than half the total number of incidents statewide.

    To address the large volume of down wires and to mitigate public safety concerns, the

    Company increased the number of site safety personnel it had in the field.7

    Our review

    indicates that Orange and Rockland had 70 site safety personnel available33 were

    assigned to the Eastern Division, 13 to the Central Division, and 12 to the Western

    Division. In addition, Orange and Rockland employed 76 contractors to assist it in the

    site safety work. At peak, the total number of site safety personnel working was 102.

    7 Site safety personnel are used to guard hazardous conditions until crews are available to

    perform repairs or make the area safe. Therefore, workforce levels provided are in addition

    to personnel used when establishing crew counts.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    14/29

    CASE 11-M-0595

    -12-

    Post storm assessments indicate there were over 5,000 down wire reports

    received from emergency responders and from customers during the first three days.

    Approximately 390 of the reports were addressed by the Companys site safety group.

    Despite the Companys efforts to supplement its workforce, the number of down wire

    reports it received overwhelmed the Company and the site safety personnel available.

    Orange and Rocklands Emergency Plan does not indicate a minimum

    staffing level for the site safety group. It merely states that the site safety group should

    be mobilized and adjusted accordingly. As recommended in the Hurricane Irene and

    Tropical Storm Lee Report, the Company needs to establish minimum staffing levels for

    its site safety personnelwith greater staffing provided for those situations that are

    likely to cause a high volume of down wires. To increase its workforce resources,

    Orange and Rockland is now establishing standard contract terms and conditions with

    its contractors for site safety services. This is a positive step in view of the size of the

    Company. We also recommend that Orange and Rockland should continue to identify

    and train additional in-house personnel to serve as wire guards.

    Orange and Rockland uses an outage management system to provide and

    monitor job assignments for known down wire incidents. Trouble calls are generated

    and updated and this provides a way to assign, track, and report each job. For the

    October storm, we requested the Companys data on the number of down wire

    incidents that were known to be energized during and after the storm. Orange and

    Rockland could not provide Staff this information with any degree of certainty.

    Company personnel are dispatched based on all known information.

    Depending on how a call is received, the Company obtains some information about a

    down wire when it receives the initial report that allows it to prioritize the response

    needed. Sometimes an initial report indicates that the down wire is energized;

    however, the system used does not effectively reflect the risk of a situation that should

    receive a high priority , such as a wire down in a high pedestrian area. Additionally, the

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    15/29

    CASE 11-M-0595

    -13-

    Companys Emergency Plan does not specify the priority that down, energized wires

    should receive during an active storm or what priority repair work related to down wires

    should receive post storm. This is an area that should be improved based on our

    previous recommendation for all Companies to define how down wires are prioritized

    for repair. As part of this effort, Orange and Rockland should also improve the

    communication process between its site safety group and crew dispatching group to

    ensure all information regarding a down line is readily known.

    Orange and Rockland was unable to establish proper ETRs for this event.

    The Company received initial damage assessment reports on the evening of October 30

    that it used to establish its global ETR for days end Wednesday, November 2. However,

    due to the substantial tree damage, numerous downed wires and the large number of

    repairs required, Orange and Rockland had underestimated the restoration effort and

    was unable to meet this initial projection. As a result, on Tuesday, November 1, the

    Company extended its global ETR to days end November 3. The modified global ETR

    was achieved for over 90% of the customers affected.

    Orange and Rockland did not develop its ETRs on a regional or local basis

    for this storm. This is a significant concern to Staff where the Company used the same

    approach following Hurricane Irene. This approach and omission fails to adequately

    inform the public and it overstates the damage and service restoration efforts for some

    areas. By not providing local ETRs, the Company promoted the perception that it was

    not restoring services effectively and customers likely placed more calls to the Company

    to obtain specific information applicable to their individual service interruption. It is

    common for customer frustration to be exacerbated when they need to contact

    multiple sources to obtain information that should be readily available. As a result, we

    recommend that Orange and Rockland develop and provide to Staff a protocol for

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    16/29

    CASE 11-M-0595

    -14-

    developing and providing customers localized ETRs for future storm events.8

    The

    Company should also report to Staff on how it plans to ensure the protocol is followed

    properly and it should clearly identify personnel within the organizations that are

    responsible for its execution.

    Orange and Rocklands slow initial response, and its limited ability to

    address down lines, resulted in substantial frustration for customers and local public

    officials. The comments the Department received during the course of this

    investigation, the numerous news reports and media articles we have seen, and the

    impassioned comments made at a public statement hearing held for Orange and

    Rocklands recent rate case, all demonstrate the dissatisfaction that customers

    experienced with the Companys performance during the October storm.

    A review of the Companys call center performance data indicates that

    customers had difficulty reaching customer service agents to obtain information. We

    found that only about 75% of the calls queued for agents were answered.9

    As had

    occurred during Hurricane Irene, the telephone call volumes Orange and Rockland

    received during the October storm exceeded the Companys capabilities. This resulted

    in some customers being unable to contact a live agent at the Company. Staff observed

    and noted this deficiency in its Hurricane Irene and Tropical Storm Lee Report, which

    contains a recommendation for improved call center capabilities.

    Orange and Rockland reported to us that it has taken steps to improve its

    call centers capabilities early in 2012 and has additional improvements planned for the

    future. So far, the improvements include: increased inbound call capabilities (doubling

    the number of telephone circuits since Hurricane Irene); contracting with Twenty First

    Century Communications to process the overflow of storm calls; sending overflow calls

    8 A similar recommendation is also included in the Irene and Lee Report.

    9 Orange and Rockland had a 96% overall answer rate, which includes calls answered by

    customer agents and calls handled by the Interactive Voice Response System.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    17/29

    CASE 11-M-0595

    -15-

    to Con Edison for handling by their representative who have been specifically trained by

    Orange and Rocklands staff; and, an improved Interactive Voice Response System that

    interfaces with the Companys Outage Management System to provide customers

    accurate, up-to-the-minute storm information. Orange and Rockland states that

    additional call center enhancements will be forthcoming during the second half of 2012,

    followed by a complete redesign of its call center technology by mid-2014.

    While these steps move in the right direction, we recommend that the

    Company provide Staff updates providing the status of the call center improvements

    and system testing that has been performed. After the 30 day reporting requirement,

    the updates should continue quarterly until the Companys call center capabilities are

    demonstrated to be sufficient to handle a large scale event.

    Finally, the information Orange and Rockland provided Staff at the time of

    the storm did not accurately state the crew levels the Company possessed. The

    Company pointed to inconsistencies in the methods it used to record this information as

    a basis for its reporting errors. To manage its resources effectively, a utility must know

    the number of crews that are arriving so it can plan their work in advance and arrange

    for such logistics as hotel rooms and meals. Staff recommends that Orange and

    Rockland improve its methods of managing crew information and develop a formal

    process to report accurately its crewing status during an event. The Company has

    indicated to us that it is developing a standardized form to collect all necessary

    information regarding incoming crews. This will help in this regard and it can also assist

    in the development of ETRs.

    NEW YORKSTATE ELECTRIC AND GAS

    NYSEG experienced outages in four of its Division. At peak, 86,672

    customers (10% of the total customers served by NYSEG) were without electric service.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    18/29

    CASE 11-M-0595

    -16-

    The majority of the electric service outages occurred in the Brewster Division where, at

    peak, 73,605 customers (87% of the Division) experienced a loss of service. On October

    31, or two days after the storm, NYSEG completed its service restorations to

    approximately 13,000 customers who were affected by the storm in the Liberty and

    Mechanicville Divisions. On Saturday, November 5, with the completion of the service

    restorations in the Brewster Division, all customers were restored to service.

    NYSEG was prepared for the storm with 105 line crews and 58 tree crews

    ready to work on Saturday, October 29. Nearly half of the line crews were Company

    personnel either stationed locally or brought into the area from other regions that were

    unaffected by the storm. NYSEG quickly ramped up its number of crews and it had 205

    line crews and 70 tree crews working by October 30, the first day after the storm. By

    Monday, October 31, NYSEG had over 350 crews at work in the Brewster Division.

    NYSEGs performance during this storm event was a great improvement over some past

    performances where supplemental crews were slower to arrive.

    There were 4,097 down wires in NYSEGs Brewster Division. A large

    number of the circuits affected by the storm were automatically shut down by

    protective devices. Of the 4,097 down wires reported, 3,916 were on circuits that were

    confirmed to be locked out, which eliminated the immediate dangers associated with

    these down wires. As a result, 70 wire guards were assigned in the Brewster Division to

    guard the other 181 down wire locations until they could be made safe.

    Of the 70 wire guards used in the Brewster Division, only 17 were local;

    the remaining guards were brought in from other Division. While NYSEG properly used

    employees from its unaffected areas to serve as wire guards, a more widespread storm

    may limits its ability to share its personnel. Also, the number of wire guards available

    may not be sufficient for future storms if there are less circuit lockouts and more

    energized down wires situations. Therefore, we recommend that NYSEG provide and

    train more personnel to serve as wire guards for future storms. The training of more

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    19/29

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    20/29

    CASE 11-M-0595

    -18-

    customers; it conducted field visits to investigate when telecommunication could not be

    established. While the Company acted properly following the storm, NYSEG should

    have provided pre-storm notifications and it should review its storm preparation

    procedures and provide a report to Staff on the steps it will take to help ensure that all

    such steps are completed in the future.

    CENTRAL HUDSON

    Central Hudson sustained the largest number of customer outages during

    this storm. At the peak, 147,958 customers (49% of the total customers served) were

    without service. Several of Central Hudsons Divisions sustained severe damage. The

    Fishkill Division experienced a 74% loss of electric service to customers; 65% of the

    customers in the Poughkeepsie and Newburgh Divisions were without service. Despite

    such large numbers of customers without service, Central Hudson was able to restore

    service quickly. It was the first of the four utilities to complete its service restoration

    efforts.

    Central Hudson was ready for the storm on Saturday, October 29, with 56

    line crews, 37 tree crews, and 12 service crews. It acquired more crews as the service

    restoration efforts progressed. By Monday, October 31, Central Hudson had 150 line

    crews (100 provided by contractors and mutual assistance), 88 tree crews, and 15

    service crews. Central Hudson was able to restore service to all customers by Friday,

    November 4.

    Central Hudson reported 1,698 down wires during the October

    Northeaster. Of this amount, 59% were received the first day of the storm. The

    Company had 105 site safety personnel available from its various organizations In

    addition, Central Hudson obtained 10 contractors to supplement its wire guard staff.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    21/29

    CASE 11-M-0595

    -19-

    The number of down wires during this major storm exceeded the number

    of wire guards that Central Hudson had available. The Company has since embarked on

    a project to better manage down wires and to fulfill the need for more wire guards.

    Central Hudson has an agreement with a local vendor to supply trained and equipped

    personnel who can respond to reports of down wires. Individuals will be trained to

    identify the types of electric conductors that are down; others will be trained to guard

    the public from the down wires. These additional resources will increase Central

    Hudsons ability to respond to a greater number of down wires than it is currently able

    to do.

    In February 2012, Central Hudson initiated a pilot program that is

    investigating the use of GIS-based and mobile applications to assist its wire responders.

    This project uses a software program to prioritize, to dispatch personnel, and to track

    reports of down wires. Central Hudson is testing this new technology, and the use of

    GIS and street map data, to group the down wire reports and to eliminate duplicate

    responses. It hopes to develop a down wire report database that can be quickly

    updated and accessed by field crews and office personnel. We consider both of these

    projects encouraging. If successful, they should be evaluated for application throughout

    its service territory.

    Central Hudson effectively communicated with local public officials during

    the storm event. The Companys first global and regional ETRs were established within

    a reasonable amount of time and with a reasonable degree of accuracy. As stated in the

    Companys report, the ETR process can be improved by obtaining the information

    learned by the damage assessors and the crew guides as frequently as possible. The

    Company is pursuing the use of mobile data collectors to allow them to communicate

    with the central office more often than they did during this snowstorm. The use of

    technology to aid in the communication of information during a storm is also a

    recommendation in the Irene and Lee Report and we support this effort.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    22/29

    CASE 11-M-0595

    -20-

    CON EDISON

    Con Edisons service area was the first in the State to be hit by the

    Northeaster. On Saturday evening, at its peak, 92,616 customers were without service.

    Of these, 79,355 were located in Westchester where 23% of customers were without

    service. Con Edison had 27 line crews, 15 tree crews, and 19 service crews ready on

    Saturday, October 29. By Monday, October 31, the Company had 154 line crews, 76

    tree crews, and 120 service crews working to restore electric service to customers. The

    majority of these crews, over 80%, were located in Westchester. As service to

    customers in the Bronx, Brooklyn, Manhattan, Queens, and Staten Island was restored,

    crews were moved to Westchester to support the restoration efforts there. By

    Wednesday, November 2, Con Edison had nearly 400 crews working in Westchester. On

    Friday, November 4, service was restored to all customers.

    During the storm, Con Edisons records show that it received 1,817 down

    wires reports. Of this amount, 473 reports were provided by emergency responders,

    including 911 operators, fire departments, police departments and local public works

    departments. Damage assessors and tree crews were assigned to verify the reports of

    down wires and the reports of trees on wires.

    In anticipation of the expected damage, Con Edison supplemented its site

    safety group with 139 contractors who were used to respond to the reports of downed

    wires. The contractors, combined with Con Edisons more than 350 wire guards,

    provided adequate safety personnel to guard the 1,817 down wires reported. We are,

    however, concerned about the Corporate policy for responding to events. For example,

    Orange and Rockland received more than four times the number of wire down reports

    when compared to Con Edison. As previously stated, Orange and Rockland used

    approximately 150 site safety personnel to respond to down wire reports. By contrast,

    Con Edisons used nearly 500 site safety personnel to respond. We believe this disparity

    is something that needs to be reviewed and addressed to ensure that the Companies

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    23/29

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    24/29

    CASE 11-M-0595

    -22-

    CONCLUSIONANDRECOMMENDATIONS

    The October storm occurred approximately a month and a half after

    Hurricane Irene and Tropical Storm Lee. The electric utility companies encountered

    many of the same issues in all three storms because of their close proximity to one

    another. Not surprisingly, our investigation found that several of the issues identified in

    the October snowstorm also existed during the Hurricane Irene and Tropical Storm Lee

    restoration. As a result, the recommendations presented here build upon those made

    by Staff in the performance report we provided following Irene and Lee.

    Except for Orange and Rockland, we did not find that the utilities had

    difficulties acquiring the crews needed to perform service restorations. Nor did the

    utilities (except for Orange and Rockland) encounter difficulties communicating with the

    customers, the media, and public officials via traditional communications channels. We

    found that NYSEG should have issued estimated restoration times earlier in its less

    affected Divisions; it needs to take additional steps to ensure LSE customers are

    contacted prior to a storm; and, the Company should train additional personnel to serve

    as wire guards in certain Divisions.

    Orange and Rockland was overwhelmed by the damage caused during the

    October storm. We found that it was slow to supplement its crewing levels and it was

    unable to respond properly to the numerous down wire conditions reported to it. As a

    result of the limited capacity of the Companys call center, customers were unable to

    contact the Company to report their service conditions or to obtain information.

    Orange and Rockland also failed to provide localized estimated restoration times, which

    added to customer calls to the Company to obtain information specific to them.

    This Report presents our recommendations for corrective actions, as

    summarized below. The recommendations are designed and intended to improve the

    utilities future storm responses. This Report will be provided to all New York utilities

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    25/29

    CASE 11-M-0595

    -23-

    for them to review and determine whether they have similar conditions that warrant

    their attention. To the extent that they do, they too should implement improvements

    to address future storms adequately. A copy of this Report is being sent to all the major

    electric utility companies by the Director of the Office of Electric, Gas, and Water. They

    are expected to implement all recommendations, as appropriate, no later than 60 days

    from their receipt of the Report.

    Staff Recommendations:

    All utilities should define in its Emergency Plan how down energized wires areto be prioritized during an active storm and in what priority repair work related

    to down energized wires should be performed post storm, taking into accountthe potential for public harm (including for example, the population density of

    the area, the level of pedestrian access and use of the area, and the proximity

    of facilities such as schools) and the safety of utility employees.

    Orange and Rockland should develop more proactive protocols and proceduresfor seeking external, contractor, and mutual aid crews from inside and outside

    of the State to ensure that crews are requested and acquired prior to and

    during emergency response efforts. The protocols should reflect appropriate

    actions based on conditions applicable to each of the three storm event

    classifications described in its Emergency Plan and be provided to Staff. Orange and Rockland should provide quarterly updates regarding all call center

    improvements and system testing performed. These updates will continue until

    Staff is satisfied with the Companys call center capabilities.

    Orange and Rockland should develop and provide to Staff a protocol on how itwill develop localized ETR on a forward going basis.

    Orange and Rockland should continue to identify and train additional in-housepersonnel to serve as wire guards. The Company should provide Staff a report

    indicating the number of new personnel identified, training schedules, and

    forecasted number of wire guards available by month through December 31,

    2013.

    Orange and Rockland should develop a formal process to manage crewinformation such that it will be able to accurately report its crewing status

    during an event.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    26/29

    CASE 11-M-0595

    -24-

    Orange and Rockland should also improve the communication process betweenits site safety group and crew dispatching group to ensure all information

    regarding a down line is readily known.

    NYSEG should strive to issue regional and local ETRs earlier during an event.The Company should provide Staff a report on the actions and verification

    processes it will be taking to ensure the ETRs will be issued in a timelier

    manner.

    NYSEG should identify and train personnel in the Brewster, Lancaster, Liberty,and Oneonta Divisions to serve as wire guards during future storms. The

    Company should provide Staff a report indicating the number of new personnel

    identified, training schedules, and forecasted number of wire guards available

    by month through December 31, 2013.

    NYSEG should review its storm preparation procedures and provide a report toStaff on steps it will take to help ensure that pre-storm calls to LSE customersare completed in the future.

    Con Edison and Orange and Rockland should provide a report to Staffidentifying corporate level policies that ensure that the Companies responses

    are adequate and generally consistent with each other.

    Central Hudson should continue to investigate the use of GIS-based and mobileapplications to assist in optimizing the response of wire responders and should

    be evaluated throughout its entire service territory to determine the

    applicability.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    27/29

    CASE 11-M-0595

    -25-

    ATTACHMENT 1HURRICANE IRENE RECOMMENDATIONS

    The following is a summary of the recommendations included in the

    Hurricane Irene and Tropical Storm Lee Report that apply to the electric utilities.

    COMMUNICATIONS

    Utility Call Centers

    Orange and Rockland should provide to Staff a report outlining the steps it will taketo improve overall call center technology and performance during storms.

    Media and Customer Communications

    Central Hudson and NYSEG should report on their enhancements for the provision ofETRs and their presentation on website maps.

    NYSEG should provide a local presence in severely impacted areas and identifyalternative means to improve communication with county offices.

    Communications with Public Officials

    All utilities should extend invitations to local and state elected officials representingdistricts in their service territories to be included on their municipal call lists.

    Alternative Communication Technologies

    All utilities should investigate ways to continue to expand the use of newertechnologies to communicate with customers during outages (i.e., email, text

    messaging, and social media) and report their findings to Staff.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    28/29

    CASE 11-M-0595

    -26-

    ELECTRIC SERVICE

    Restoration

    Orange and Rocklands emergency plan should formally incorporate the CorporateCoastal Storm Plan. The electric utilities should formalize agreements with property owners to

    temporarily stage crews, materials, and equipment during restoration at strategic

    locations that would be useful for future restoration efforts.

    Each electric company should develop procedures relating to the use of contracteddamage assessors, including training requirements. Their Emergency Plans should

    identify when these procedures would be used.

    National Grid and Con Edison should investigate the use of mobile data collection fordamage assessment by company and contracted personnel and report their finding

    to Staff.

    Each electric utility should expand its emergency plan to include procedures forobtaining crews from distant states. The emergency plans should include contact

    information for utilities, contractors, and mutual assistance groups and acknowledge

    travel and rest time restrictions before the crews can be deployed into the field.

    All electric utilities should better define minimum staffing requirements for thenumber of wire guards to be used in their emergency plans. The requirements

    should also identify alternate staffing levels when conditions, such as a hurricane,

    will likely cause an increase in the number of down wires.

    All electric utilities should modify their Emergency Plans to identify the means toobtain supplemental wire guards through contractors during or prior to an

    emergency when employees may not be available to serve as guards because they

    are needed for alternate functions.

    All electric utilities should modify their Emergency Plans to define when it would beappropriate to use municipal field liaisons or a similar process to facilitate the

    removal of hazardous conditions.

  • 7/31/2019 NY PSC Report on October 2011 Nor'Easter Response

    29/29

    CASE 11-M-0595

    NYSEG should examine its Company as a whole to establish an optimal crewdeployment to achieve restoration for the largest number of customers in the least

    amount of time.

    As the restoration progresses, Orange and Rockland and NYSEG should revise theirpractices to provide ETRs that are different from the global projection for regional

    sections of their territories, which may be smaller than their divisions, and continue

    to refine the ETRs until all localities have their own ETRs.

    All electric utilities should continue to work with referral entities to strengthenfollow-up processes and to ensure that feedback regarding LSE customers that have

    been referred for contact assistance are obtained and recorded.

    To ensure better availability of dry ice in future events, all electric utilities shouldreview their procurement procedures and identify additional contractors, further

    inland, who can provide dry ice in the event of a storm impacting the East Coast.

    Reporting

    Guidelines for writing self-assessment reports should be developed through acollaborative process including Staff and the electric utilities to ensure future reports

    contain all appropriate information and provide a comprehensive discussion of key

    decisions and actions taken. The resulting guidelines shall apply to all electricutilities.

    All electric utilities should provide comprehensive reports that discuss all aspects ofthe restoration when required to submit storm updates.

    System Reliability and Resiliency

    All electric companies should review facilities that are susceptible to outside factors,such as flooding, excessive tree damage, or limited access, to determine whether

    reasonable infrastructure improvement or increased maintenance could be made to

    reduce the customer impact of a storm or facilitate the ability of the utility to restore

    service.