PROJECT PROGRESS REPORT
IN LIEU OF PRE-FEASIBILITY REPORT
of LANCO AMARKANTAK POWER LTD
1X660 MW (UNIT- 3) SUPERCRITICAL COAL BASED THERMAL POWER PLANT
SITUATED NEAR
PATHADI VILLAGE, KORBA DISTRICT, CHHATTISGARH.
MAY- 2018
Page 2 of 34
Index
Sr. No. Activity Page No.
1 Statutory Approvals & Clearances 3 2 Progress of Project 4-8
3 Details of All activities- Civil, Structural, Mechanical, Electrical, Transmission line and C&I
9-14
4 Project Snaps 15-33
Page 3 of 34
LANCO Amarkantak Power Limited (LAPL) is operating 600 MW (2 X 300 MW) and is constructing (1X660MW) capacity coal based thermal power plants near Pathadi, Korba Tehsil, Korba District, Chhattisgarh. Another 1x660Mw project is also under construction. Project execution is in very advance stage. Many of the milestones achieved and rest are under execution. Boiler Hydrotest Completed and is ready for Chemical Cleaning. Turbine is Boxed up. Lanco Amarkantak has taken all statutory clearance from concerned Govt authorities.
1.0 Statutory Clearances:-
Sr.No. Clearance/Registration Present Status
1 Water allocation 18 MCM Available
2 Coal allocation 2.497 MTPA is allocated
3 EC Clearance from MOEF
Available
4 Fuel FSA executed with SECL.
5 Consent for Establishment
Available
6 Construction Power 1.0 MVA Available
7 Aviation clearance for Chimney
Available
8 Essentiality certificate & Registration of project
Essentiality certificate received and project registered.
9 Power Evacuation PGCIL has approved LTOA and BPTA signed.
10 400 KV Transmission line
Clearance obtained for Right of way (ROW), Civil aviation clearance, defense authority clearance, Forest clearance, PTCC approval, PLCC approval, approval for highway crossing, HT line crossing (12/14 nos), and River crossing.
11 Financial Closure Completed
Page 4 of 34
2.0 Progress of Project:-
(RCC Quantity Unit # 3):-
Areas in Civil Unit # 3 UoM Scope Completion till 31.05.2018
Balance as on 31.05.2018
Main Plant Unit # 3 Cum 31758 31688 70 Cooling Tower # 3 Cum 11320 11058 262
Total for Unit # 3 Cum 43078 42746 332
(RCC Quantity for Common system Unit # 3 & 4):-
Areas in Civil UoM Scope Completion till 31.05.2018
Balance as on 31.05.2018
Common System - Unit # 3 & 4 Cum 9404 7946 1458 DM & PT Plant Cum 20430 19567 863 CW & ACW Pump House and Forebay, CW Channel , CW Chlorination Building, CW Pipe Encasing
Cum 29186 25457 3729
CT PMCC Room Unit # 3 & 4 Cum 471 471 0 Coal Handling Plant (CHP) Cum 55031 41979 13052 Coal Handling Plant (CHP) - Extension
Cum 19520 908 18612
Chimney Cum 16288 16237 51 Pipe Rack & Pedestals Cum 7250 7077 173 Ash handling plant including Pipe pedestal
Cum 12809 9328 3481
Fuel Oil Handing System Cum 2828 2764 64 Road & Drain Cum 44291 26418 17873 Misc. Civil Work Cum 36556 24809 11747 Paving & Flooring works Cum 22787 21653 1134 River water intake system Cum 4709 4317 392 Transmission Line Cum 12650 10681 1969 Ash dyke Cum 9580 0 9580 Ash Pipe Pedestal Cum 1200 0 1200 Railway Siding Cum 19000 0 19000
Total RCC in M 3 Cum 323990 219612 104378
Page 5 of 34
(Mechanical Erection Unit # 3):-
Packages for Unit # 3 UoM Scope Completion till 31.05.2018
Balance as on 31.05.2018
BTG Area MT 37307 34286 3021 Boiler # 3 Structure MT 6875 6875 0 Boiler # 3 Non Pressure Parts MT 1744 1447 297 Boiler # 3 Ducting MT 3076 2984 92 APH # 3 MT 1860 1860 0 Boiler Pressure Parts # 3 MT 5600 5600 0 Coal Piping MT 846 588 258 Boiler Side Critical Piping MT 131 131 0 Insulation & Refractory MT 1500 184 1316 Pumps, Tank & Piping MT 150 47 103 Coal Mills MT 2030 2030 0 Feeders & Connecting Pipes MT 100 53 47 PA, FD & ID Fans MT 405 405 0 Boiler Elevator MT 110 73 37 Pressure Parts Welding Joints Nos. 43661 43661 0 ESP # 3 MT 7480 7178 302 TG # 3 MT 1774 1732 42 TG Critical Piping # 3 MT 852 684 168
TG IP/ LP Piping Unit # 3 MT 740 527 213
Condenser # 3 MT 721 721 0 TG Auxiliaries Unit # 3 MT 1313 1167 146 Structural Erection Unit # 3 MT 10615 10436 177 PHB # 3 Structure MT 3269 3269 0 Mill Bunker CD Bay MT 3717 3715 0 Mill Bunker (Silo) # 3 MT 1130 1128 2 Duct Support Structures MT 1478 1478 0 D Row Brackets MT 241 241 0 Staircase MT 146 136 10 Bolts & Extra Splice MT 172 167 5 Air Washer Room (AWR) MT 90 80 10 Mill Reject Handling System (MRHS)
MT 150 0 150
ESP # 3 Control Room MT 222 222 0
Total Erection for U # 3 MT 47922 44722 3198
Page 6 of 34
(Common System for Unit # 3 & 4):-
Packages (Common for Unit # 3 & 4) UoM Scope Completion till
31.05.2018 Balance as on
31.05.2018 Common Structures for Unit # 3 & 4 MT 2939 2896 43
A Row Cantilever MT 292 249 43 Electrical bay (Grid -11-14) MT 1140 1140 0
Unit Control Building Structures MT 1507 1507 0
Miscellaneous Cranes & Hoists (BTG) Nos. 30 4 26
Compressed Air System MT 122 80 42 Compressor House Truss MT 29 29 0 Compressor house - Compressor
MT 48 48 0
Compressor house - Dryer MT 3 3 0 Compressor house - Air Receiver MT 42 42
CHP Structures, Equipments & Sheeting/ Cladding MT 15142 9003 6139
Structure Fabrication MT 6800 4962 1838 Conveyor - Structures MT 4848 4848 0 TP's (6,7,8,9,10 & 11) and Drive House
MT 2009 1758 251
MH-1 & MH-2 MT 185 16 169 Track Hopper MT 350 330 20
Crusher House Structure MT 2036 1441 595
Crusher House Equipment & Paddle Feeders
MT 200 0 200
TPs & Conveyor system (Equipments) MT 1839 585 1254
Other Comp. (DE, DS etc.) MT 900 0 900
CHP - Cladding & Sheeting MT 275 25 250
CHP Extension: TPs & Conveyor Erection
MT 2500 0 2500
Ash Handling Plant MT 2058 279 1779
Fabrication - BAH Structure, Buffer hopper Structure and Structure for hydrobin (1, 2 & 3) & Hydrobin shell (1, 2 & 3)
MT 1593 138 1455
Page 7 of 34
Packages (Common for Unit # 3 & 4) UoM Scope Completion till
31.05.2018 Balance as on
31.05.2018
Erection - BAH Structure, Refractory, BAH Liners & Buffer hopper structure
MT 786 95 691
Erection of Hydrobin supporting structure (1,2 & 3) and Hydrobin shell (1,2 & 3)
MT 1238 175 1063
AHP Piping Unit # 3 & 4 Mtr 26847 0 26847
Ash Slurry Pump House MT 27 7 20 Ash Water Pump House MT 7 2 5 Fuel Oil Handling System MT 112 112 0
HFO Storage Tank MT 78 78 0
LDO Storage Tank MT 34 34 0
FOHS Piping Mtr 11500 8050 3450
Equipments (Pumps, Strainers, Heaters, Cooler, CFT, Monorail etc.)
Nos. 39 35 4
DM Plant & PT Plant MT 863 541 322 DM Plant Structure -Fabrication MT 226 226 0
DM Plant Structure - Erection MT 226 226 0
DM Plant Structure (Chinese Truss)
MT 46 0 46
DM Plant Mech. Equipment & DM water storage tanks MT 511 280 231
PT Plant Equipment MT 80 35 45
CW & ACW System MT 4469 3270 1199 CW Pipe MT 3315 2903 412 ACW Pipe MT 175 151 24 CW Pumps MT 450 40 410 ACW Pumps MT 76 76 0 Chlorination System MT 83 0 83 CW Pump house Structure MT 330 100 230 CWST Roof Structure MT 40 0 40
IDCT (Cooling Towers) MT 2104 295 1809
CT - Mechanical package (Fills & Equipments) MT 1400 0 1400
CT - Package (Piping) MT 704 295 409
Pipe Rack Structure MT 2483 2394 89
Pipe Rack Fabrication MT 2483 2211 272
Pipe Rack Erection MT 2483 2394 89
Page 8 of 34
Packages (Common for Unit # 3 & 4) UoM Scope Completion till
31.05.2018 Balance as on
31.05.2018
Cable Rack Structure MT 81 81 0
Cable Rack Fabrication MT 81 81 0
Cable Rack Erection MT 81 81 0
Chimney MT 1691 901 790
Chimney Flue Can Fabrication MT 1162 1076 86 Chimney Flue Can Erection MT 1162 501 661
Chimney Structure Erection MT 529 400 129
River water intake systems Nos.
River water intake pumps Nos. 3 0 3
Raw water Pipe Line (Inside Plant) Mtr 1900 1535 365
Raw water - Cross Country Piping (Outside Plant) Mtr 4600 4007 593
Miscellaneous Cranes & Hoists (BOP) MT 85 0 85
Fire Detection & Protection System MT 20 7 13
Fire Protection - Piping Mtr 38986 10136 28850
Fire Protection - Mechanical Equipments MT 20 7 13
Miscellaneous Tanks MT 64 64 0
Misc. Tanks (CST, Service water tanks, Potable water tanks etc.)
MT 64 64 0
CPU Regeneration System MT 122 122 0
CPU Equipments MT 84 84 0
Regeneration Equipment MT 38 38 0
LP Piping
LP Piping (Pipe Rack) Mtr 42955 11604 31351
HVAC System
Ducting - Air Conditioning system Sqm 8711 3404 5307
Ducting - Ventilation system Sqm 16400 4282 12118
Total Erection for Unit # 3 & 4 MT 32355 20045 12310
Page 9 of 34
3.0 Details of all activities: - Civil Works
Main Plant: - Civil work for following area has been completed: • Boiler Unit # 3 • Power house building (PHB) and PHB auxiliaries foundations Unit # 3 • TG deck and TG hall equipments foundations Unit # 3 • Condenser Unit # 3 • CW & CEP Pit Unit # 3 • PA, FD & ID Fans Unit # 3 • Mill foundations & Mill bunker (CD bay) Unit # 3 • Flue gas duct supports Unit # 3 • ESP Unit # 3 • ESP Control Room Unit # 3 • Transformer Yard Unit # 3 • CST (Condensate Storage Tank) Unit # 3 • DG Set foundation Unit # 3 • Unit Control Building Unit # 3 & 4 • Fire Station Building Unit # 3 & 4 • Compressor house building Unit # 3 & 4 • Switchyard tower, equipments foundations Unit # 3 & 4 • Switchyard Control Building Unit # 3 & 4
Ash Handling Plant (AHP):- • Bottom ash hopper foundation Unit # 3 civil works completed. • Civil works completed in Ash slurry pump house (ASHP) and Ash water pump
house (AWPH). • Civil works completed in Hydrobin, Surge tank and Settling Tank. • Civil works are under progress in Ash Silos (45% completed) and Ash Silo
utility buildings (74% completed). • Ash Pond excavation and bund preparation work 34% completed.
Coal Handling Plant (CHP):-
• All Civil works completed from Track hopper to bunker and nearing complete and overall progress is 74%.
• RCC Road work is under progress in CHP area. • Civil works are under progress in Stacker Reclaimer and Wagon Trippler.
Pre Treatment (PT) Plant:-
• Aerator & Distribution chamber – All civil works completed. • Sludge Pit - All civil works completed. • Chemical house – All civil works completed. • HRSCR A & B - All civil works completed. • Clarifier water Pump House - All civil works completed. • Clarifier & Fire water pump house – All civil works completed. • Paving & finishing works are under progress in PT plant area.
Page 10 of 34
DM Plant:- • DM Plant Building – Equipment foundations and grade slab work completed.
Finishing works are under progress. • Overhead water tank – Civil works completed. • DM water storage tanks foundations – Foundation works completed for 2/3
nos tanks. • N-Pit- RCC works completed.
Cooling Tower Unit # 3:- • 99% civil works completed. • Hot water channels and deck slab works completed for all 24 cells. • Cleaning, finishing, grouting and painting works are under progress.
CT PMCC Room:-
• All civil works completed.
CW & ACW Piping works:- • 86% civil works completed.
CW & ACW Pump house:-
• CW Pump house, forebay and MCC building civil works completed. Finishing works are under progress.
Chimney:-
• External Painting Completed. Balance finishing work is under progress. Fuel Oil Handling System (FOHS):-
• All civil works completed in fuel oil handling system. Compressed Air System:-
• Compressor house building - All civil works completed. River water intake system:-
• Civil works completed for intake water pump house. Finishing work is under progress.
Mechanical Erection:-
Boiler and Auxiliaries Unit # 3:- • Boiler Structural erection of Unit # 3 completed. • Pressure parts erection, welding & NDT completed. • Hydro test for Boiler Unit # 3 completed. • Non-pressure part 83% completed. • Boiler ducting 97% completed. • APH erection completed. • All 8 Nos coal mills erection 100% completed.
Page 11 of 34
• Coal feeders’ erection & alignment completed. Final connection with bunker and mills are under progress.
• All FD, PA & ID fans erection 100% completed. • Boiler side critical piping erection 100% completed. • Boiler insulation and refractoriness works are under progress. • Arrangement for chemical cleaning of Boiler Unit # 3 completed. • Auxiliary steam line and DM water line interconnection with Unit # 1 & 2
completed. • ESP erection 96% completed. ATT of Pass - B & C completed. Insulation
works are under progress. • Structures erection 100% completed for Unit control building, Power house
building, Mill bunker building (CD bay) Duct support structures, A row cantilever, D row bracket and ESP Control Room Building.
• Structures erection 89% completed for Air Washer Room.
TG and Auxiliaries Unit # 3:- • Main Turbine- HIP & LP Turbine final box up completed. • Generator Rotor Insertion, Seal body installation and Final alignment
completed. • Critical Piping (TG) erection, welding & NDT completed, ready for hydro test. • TG integral Piping erection 71% completed. • Condenser – Erection & hydro test completed. • Erection of all auxiliaries for Turbine and generator completed except BFP
Turbine. • Turbine lube oil system erection, welding & NDT completed, ready for oil
flushing. Ash Handling Plant (AHP):-
• Structural erection for bottom ash hopper Unit # 3 completed. Equipments erection is under progress.
• Buffer hopper structural erection is under progress. • Fabrication for 1/6 nos hydrobin shell completed.
Coal Handling Plant:-
• Track Hopper - Structural erection, sheeting & cladding works are completed. • TP # 6 & Crusher House - Structural erection are under progress. • BC # 2C/2D, 6C/6D & 7C/7D - Structural erection works are under progress. • TP # 11, 7,8 & 9 - Structural erection completed. Equipments erection under
progress. • BC # 1C/1D, 3C/3D, 4C/4D & 5C/5D - Structural erection completed.
Equipment erection under progress.
Pre Treatment (PT) Plant:- • HRSCR – A & DM water clarifier bridge erection completed.
Page 12 of 34
• Erection, alignment & grouting of central gear box of HRSCR- A & DM water clarifier completed.
• Distribution chamber to HRSCR-A and HRSCR –B connecting pipe erection completed.
• All connected piping works for PT plant are under progress. • Clarified and fire water pump house - all pumps erection completed.
DM Plant:-
• DM Plant building - Structure erection completed. Equipments erection is under progress.
• Erection, alignment & grouting of vessels (DMF, ACF, SAC, SBA, MB & MBTWT) completed for one stream.
• Erection of 4 no bulk acid storage tank and 3 no bulk caustic storage tank are completed.
• Erection of DG water transfer pump, UF feed pump & UF backwash pump, MB blower & DMF blower erection completed.
• DM water storage tanks – Erection of 1 no tank completed and work in progress for balance 2 no of tanks.
Cooling Towers Unit # 3:- • Hot water channel and deck slab completed for all 24 cells. • Cleaning, finishing, grouting & painting works are under progress. • Fabrication of hot water duct is completed. • Erection work for hot water piping is in progress. • Gearbox, Motors, Fan blade assembly supplies completed. • Supply of FRP fan stacks, fills, distribution pipes and drift eliminators are in
progress. • 6 Nos fan stacks erection completed in CT Unit # 3. Fill pack assembly for 3
no shells completed. • Gear box and motor assembly with shaft alignment completed for 5 nos of
shells.
CW & ACW System:– • CW & ACW Pump house – 30% Structure erection completed. • Erection & alignment of 3/3 nos ACW pumps are completed. • Erection of 1/5 nos CW pumps is under progress. • Erection of Gates and screens for CW & ACW systems are under progress. • CW Piping - 88% erection, welding & NDT completed. Final connection with
pump house and condenser unit # 3 is in progress. • ACW Piping - 86% erection, welding & NDT completed. End connection with
pumps is balance. Chimney:–
• Flue can erection work completed for Unit # 3. Final connection with ID fan flue duct is under progress.
• Structure erection 100% completed for Unit # 3.
Page 13 of 34
• Stack Elevator erection, alignment & commissioning completed. Fuel oil handling system:-
• Erection of HFO tank, LDO tank, DOT, Pumps, Line heaters and coolers are completed.
• Piping erection 70% completed. • Overall 90% work completed.
Compressed Air System:-
• Erection of Compressor house Structure & roof sheeting completed. • All compressors & Driers erection and alignment completed.
Fire detection & Protection System (FDPS):-
• 26% hydrant & Spray piping works completed in entire plant area. • FDA System & Energent system erection works completed in Unit Control
building. • Fixing of water monitors and Spray valves completed in switchyard and
transformer areas. • 7/7 nos fire pumps erection completed in fire water pump house.
LP Piping:-
• 27% piping works completed in entire plant area. HVAC System:-
• Switchyard Control Building - All works completed & AC system is in operation.
• Unit Control Building - (A) 200 TR Chiller Plant: - Erection works completed, Commissioning works are under progress. (B) Package AC system at + 7.4 Mtr Unit Control Building: - All equipments & duct erection completed.
• ESP Control Room Unit # 3 (Package Air Conditioning System) - All Indoor units are erected and duct erection are under progress.
• Roof Extractor Fans: - Erection of all roof extractor fans (19 Nos) are completed in PHB Unit # 3 & 4 (AB bay).
• Supply Air Fans & Exhaust Air Fans: - Fixing of 65 nos of fans completed. • ESP Control Room Unit # 3:- UAF Units and its Centrifugal fans with motors
erection completed. Ventilation duct erection 90% completed. • Air Washer Units at +21.4 Mtr of Unit Control Building: - Centrifugal fans
erection completed. Ventilation duct erection is under progress in CCB & Unit # 3 CD bay.
• CHP Tunnel & Pent house: - Foundation works completed for supply air fans & Exhaust air fans in track hopper area. Ventilation duct erection work is 80% completed in CHP tunnel & pent house area.
Page 14 of 34
Electrical Works:-
400 KV Switchyard:- • Structure, Equipment erection including stringing completed. • Testing of all equipment completed. • SCADA commissioned in Switchyard. • Switchyard is ready for charging with SCADA facility.
400 KV Transmission Corridors -
• 14 out of 14 No of towers erection completed in 400 KV Switchyard Corridor. • Conductor stringing work of switchyard and transmission corridor for GT Unit
# 3 and for startup circuit completed. • Approvals for energization of switchyard interconnection corridor are received
from CEA.
Electrical Packages – • Cables (HT, LT & Control) - 95 % Supply completed and total 64 KM cable
tray & 123 KM cable laying work completed. • Station (Start up Transformers) - Testing of startup Transformer completed.
Charging permission from CEA obtained for Startup Transformer & Start up board. Start up transformer and SA board is ready for charging.
• HT Switchgear (Unit # 3) - 3UA & 3UB are ready for charging and charging permission from CEA obtained.
• Unit Auxiliary Transformers (UAT) - All 4 no transformers received & erected. • Unit Transformers (UTs) - 2 no received & erected. • Generator Transformers- All 3 no of GT received at site and erected for Unit #
3. • Auxiliary Transformers -Total 61 no Aux. Transformers are received & 34 no
are erected. • DC System - DC system for Unit # 3 commissioned. • GCB - Erection of GCB for Unit # 3 completed.
400 KV D/C Transmission Line –
• 119 out of 144 nos civil foundations for Tower completed. • 108 out of 144 nos Tower Structure erected. • 11.5 KM out of 47 KM stringing completed. • Balance Foundation, Tower structure erection & stringing work are in
progress.
Control & Instrumentation Works:- • DCS - Supply of Unit # 3 completed. • Erection of DCS Panels for Unit # 3 completed. • UPS panel erection & commissioning completed for Unit # 3. • Batteries for UPS system of Unit # 3 erected. • Total 120 KM cable lying completed. • Erection of panels and field instruments are under progress in Boiler and
Turbine. .
Page 15 of 34
Overall Project Completion
TIME REQUIRED FOR COMPLETION OF THE PROJECT AND COM MISSIONING OF UNIT # 3
The Project shall be completed in 15-18 months from restart which also includes Lenders approval and re-mobilization.
Area % Progress Main Plant -BTG 95% Balance of Plant 75%
Page 22 of 34
Coal Handling System -Track Hopper
Erection work completed
Coal Handling Plant-Conveyor
Page 30 of 34
Transformer Yard - Unit Aux. Transformer
Startup Transformer
HT & LT Switchgears Start up Switchgear
1
NOTE ON CURRENT ENVIRONMENTAL BASELINE STATUS AROUND
LANCO POWER PLANT
PATHADI, PAHANDA, KHODDAL & SARAGBUNDIA VILLAGES
KORBA TEHSIL, KORBA DISTRICT, CHHATTISGARH.
UNIT 3 – 1X660 MW
(COAL BASED SUPERCRITICAL POWER PLANT)
JUNE, 2018
Promoted By
LANCO AMARKANTAK POWER LTD.,
GURGAON
2
BACKGROUND:
Lanco Amarkantak Power Limited (LAPL) is setting up coal based supercritical power generation
unit of 660 MW capacity (Unit No. 3) near Korba in Chhattisgarh State which is at an advanced
stage of construction.
The Project is 95% complete in respect of the Main Plant (Boiler, Turbine-Generator), and
progress in respect of the Balance of Plant (BOP) comprising Coal and Ash Handling Systems,
Cooling Water (CW) System, Electrical Systems, etc. is about 70%.. PL is regularly submitting
Compliance Reports to MoEF&CC Regional office, MoEF&CC-Delhi, CECB-Raipur and uploading
on the Ministry website as per the conditions laid down in the EC.
Environment Clearance (EC) for Unit-3 was received on 31.12.2007 vide EC No J-13011/44/2007-
IA.II(T) for 600 MW capacity which was subsequently amended on 04.09.2008 for 660 MW unit
capacity vide EC No J-13011/44/2008-IA.II(T). The EC was received with validity period of 5 years
to start of production by the Power Plant i.e., till 31.12.2012. The validity of the EC was further
extended for a period of 5 years up to 30th Dec 2017.
Permission to Establish by Chhattisgarh Energy Conservation Board (CECB), Raipur was issued
vide its letter dated 04.06.2008 (For 600 MW Capacity) which was amended for 660 MW capacity
on 11.02.2010 i.e., after around 2 years from the date of EC.
The Project was started with Notice to Proceed to EPC Contractor in June 2010. In the first 18
months, the project was on fast track and achieved significant construction progress in Main
Plant as well as Balance of Plant (BOP) areas.
The project got delayed due to reasons beyond the control of LAPL of which, the major reasons
are enumerated below:
• Delay in obtaining physical possession of land for certain BOP facilities due to frequent
disturbances by locals interrupting the construction activities.
• Midway changes in plant layout and re-engineering due to the above delay in obtaining
physical possession of land and additional conditions imposed by CECB and Indian
Railways
• Midway changes in Mega Power Policy which impacted Customs clearance and imported
equipment supplies.
• Deteriorating macroeconomic factors, overall economic slowdown have adversely
affected the power sector in general, also led to delay of the Amarkantak Project
About 95% of the Boiler, Turbine and Generator works are completed and 70% of Balance of
Plant (BOP) has been completed as on date.
3
This report summarises the baseline air quality data recorded during the preparation of the
REIA report for Unit 3 during 2007 and the ambient air quality data recorded in the past three
years in the surrounding villages of the power plant complex especially with respect to Pathadi
village.
LOCATION OF THE PLANT
The plant site is located at Pathadi Village in Korba Tehsil, Korba District of Chhattisgarh and is
located at 82o43’14” E longitude and 22o14’45” N latitude with an average msl of about 285 m.
Nearest railway line connecting Korba – Champa line is located at 500 m from the site. Nearest
village, Pathadi is located at about 0.3 km in the northern direction of the site. Hasdeo River is
located at about 1.7 km.
Korba city is located at about 13 km from the proposed plant site. The location of the Lanco
Power Plant on Google Earth Imagery is given below:
4
The various industries located beyond 14 km from the project site is given below:
Nearest Industries
1. NTPC
2. CSEB – Korba (East)
3. CSEB – Korba (West)
4. BALCO captive power plant
5. BALCO
(all the industries are located beyond 14 km from the project site)
5
STUDY AREA – 10 KM RADIUS WITH RESPECT TO LANCO POWER PLANT DRAWN AS PER SOI
TOPOSHEET.
ANALYSIS OF HISTORICAL BASELINE DATA GENERATED AT THE TIME OF PREPARATION OF THE
EIA REPORT OF UNIT-3 WITH THE CURRENT BASLINE DATA GENERATED IN THE LAST THREE
YEARS
The baseline status recorded during the preparation of the REIA report for Unit-3 is compared
with the baseline data generated in the last three years.
LAPL has carried out EIA studies for 2 x 300 MW i.e., Unit-1 and Unit-2 during summer 2004 covering the
months of March ’04 – May ’04. No industrial activities have come up in the 10 km radius of the study
area from the year 2004 to 2007 except for construction activity of LAPL’s 2 X 300 MW.
The following is the summary of the baseline data collected for the preparation of the EIA report of Unit
3 (1x660MW) during the period March – May 2007. (Source: REIA Report of Unit-3)
Pathadi village is located nearer to the plant site at 0.35 Km with respect to Colony and 0.9 km
with respect to main plant (aerial distances). To assess the existing ambient air status in this
village, AAQ stations were located at these locations also. Based on the above, the AAQ stations
have been identified and data recorded at the following of ambient air quality stations are
presented in the following table:
SUMMARY OF AMBIENT AIR QUALITY (µg/m3)
CODE NO LOCATION NAME 98TH PERCENTILE VALUES
RPM SPM SO2 NOx
A1 Darrabhantha Village 125.6 49.9 16.4 18.6
A2 Urga Village 136.2 51.1 14.2 15.6
A3 Mashan Village 134.5 49.8 15.3 15.3
A4 Pataddi Village 140.2 48.9 14.2 15.6
A5 Pahanda Village 132.1 50.6 14.6 16.0
A6 Dhandhani Village 140.1 52.2 14.5 15.9
A7 Bhaisamura Village 136.4 52.1 14.5 15.7
A8 Baraidih Village 135.5 50.9 13.9 15.2
A9 Korba 143.3 52.2 14.2 15.4 Note: CO values were observed to be less than 1 ppm during study period
The following is the Overall Scenario with the implementation of the Unit -3 (1x660MW) power
plant as given in the REIA Report.
OVERALL SCENARIO WITHIN STUDY AREA (µg/m3)
(UNIT #1 OF 300 MW + Unit #2 of 300 MW + Unit #3 of 660 MW)
24-Hourly Concentrations Suspended
Particulate
Matter (SPM)
Sulphur
Dioxide (SO2)
Oxides Of Nitrogen
(NOx)
Baseline Scenario 140.2 16.4 18.6
6
Predicted Ground level
Concentration (Max)
1.176 39.30 17.66
Overall Scenario
(worst case)
141.376 {200} 55.7 {80} 36.26 {80}
NOTE: The values in parentheses is the CPCB limit for rural and residential areas.
OBSERVATIONS:
The above table clearly shows that the baseline scenario captured the operation of the existing
2x300 MW power plants (i.e) Unit 1 and Unit 2 and the likely contribution of the Unit-3 under
the predicted ground level concentrations.
LANCO has been continuously recording the baseline data at 4 locations outside the plant
(village – Pathadi, Saragbundia, Sandel and Khoddle) and at 4 locations inside the plant (
Switchyard, DM Plant,Ash Pond and Admin Building) and submitting the monthly reports to
MOEF&CC and the CECB as part of the compliance to the EC conditions. The following is the
trend graph plotted from the data recorded at Patadi village which is nearest to the plant in
the past three years namely 2014-15, 2015-16 and 2016-17.
0.00
10.00
20.00
30.00
40.00
50.00
Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15
AA Q DATA - PATHADI VILLAGE - 2014-15
PM 10 (µg/m3) PM 2.5 (µg/m3) SO2 (µg/m3)
Nox (µg/m3) CO (mg/m3)
7
It may be observed from the above graphs of the ambient air quality recorded at Pathadi village
that there is no significant increase in the ambient air quality. This is summarized in the
following table:
S.NO AMBIENT AIR QUALITY RECORDED AT
PATADI VILLAGE DURING THE REIA
(2007) (98TH PERCENTILE)
AMBIENT AIR QUALITY RECORDED AT
PATADI VILLAGE IN THE LAST 3 YEARS
BETWEEN 2014 -20017
1 RPM = 140 µg/m3 ( ~PM10) PM10 = 14.5 TO 59 @
2 SO2 = 14.2 SO2 = 10.82 TO 14.85
3 NOX = 15.6 NOX = 11.1 TO 24.4
@ = This is as per the new Ambient Air Quality Standards 2009.
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16
AAQ - PATHADI VILLAGE -2015-16
PM 10 (µg/m3) PM 2.5 (µg/m3) SO2 (µg/m3)
Nox (µg/m3) CO (mg/m3)
0.00
10.00
20.00
30.00
40.00
50.00
60.00
Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17
AAQ-PATHADI VILLAGE -2016-2017
PM 10 (µg/m3) PM 2.5 (µg/m3) SO2 (µg/m3)
Nox (µg/m3) CO (mg/m3)
8
CONCLSUION
The above table clearly shows that there is no significant increase in the baseline status
between the period 2007 to 2017 though the two units of LANCO namely Unit 1 and Unit 2 are
in operation.
It also shows that there are no new industries which have come up within 10 km radius of the
LANCO Power plant complex.
It may also be noted that the Korba town is beyond 13 km (aerial distance) and the MOEF&CC
has lifted the ban on the industries located in KORBA after improvement in the CEPI Index.
REQUEST
LANCO has been consistently monitoring the baseline data and complying with the conditions
stipulated in the Environmental Clearances granted for the project.
The project study area has not witnessed any industrial actitvity other than the power plants
of LANCO.
Considering the above, LANCO requests the MOEF&CC to permit submission of an updated EIA
report and exempt the conduct of Public Hearing for renewing the Environmental Clearance
for Unit-3.
9
EXHIBIT -1
SUMMARY OF BASELINE DATA – PATADI VILLAGE
Pathadi
Month
PM 10
(µg/m3)
PM 2.5
(µg/m3)
SO2
(µg/m3)
Nox
(µg/m3)
CO
(mg/m3)
Apr-14 45.50 24.60 15.90 25.40 0.60
May-14 46.50 19.10 12.70 19.10 1.10
Jun-14 43.00 22.40 16.10 25.00 0.50
Jul-14 14.50 9.30 11.70 14.20 0.40
Aug-14 29.00 18.00 12.50 16.20 0.50
Sep-14 28.30 18.40 12.70 16.70 0.50
Oct-14 29.70 18.70 13.00 17.00 0.50
Nov-14 31.20 20.00 14.50 18.40 0.60
Dec-14 29.70 19.40 14.00 17.50 0.70
Jan-15 32.90 22.10 15.30 17.90 0.70
Feb-15 34.50 23.90 14.50 17.20 0.60
Mar-15 35.60 25.10 15.60 18.40 0.60
Pathadi
Month
PM 10
(µg/m3)
PM 2.5
(µg/m3)
SO2
(µg/m3)
Nox
(µg/m3)
CO
(mg/m3)
Apr-15 50.33 21.00 16.46 19.07 0.49
May-15 59.10 26.00 17.10 19.80 0.50
Jun-15 41.90 16.10 12.10 13.40 0.40
Jul-15 40.50 15.40 11.30 12.50 0.50
Aug-15 42.00 16.23 11.50 13.25 0.50
Sep-15 39.86 16.23 12.13 13.53 0.45
Oct-15 39.96 16.58 12.58 14.24 0.48
Nov-15 38.60 16.41 12.30 14.40 0.46
Dec-15 37.93 16.01 12.64 14.64 0.56
Jan-16 38.13 15.78 13.01 14.09 0.53
Feb-16 40.23 17.06 12.24 13.93 0.43
Mar-16 41.13 17.19 12.02 14.01 0.50
10
Pathadi
Month
PM 10
(µg/m3)
PM 2.5
(µg/m3)
SO2
(µg/m3)
Nox
(µg/m3)
CO
(mg/m3)
Apr-16 42.20 18.40 12.30 14.00 0.50
May-16 42.70 18.80 12.60 14.30 0.50
Jun-16 42.10 18.60 12.60 14.30 0.60
Jul-16 41.80 18.10 12.80 14.10 0.60
Aug-16 41.00 17.80 12.70 14.50 0.60
Sep-16 40.39 17.42 13.17 15.54 0.62
Oct-16 39.87 17.30 13.47 15.61 0.60
Nov-16 40.12 17.48 13.58 15.69 0.59
Dec-16 40.91 19.17 14.19 15.74 0.59
Jan-17 41.47 19.95 14.51 16.03 0.55
Feb-17 42.65 21.56 14.85 16.64 0.61
Mar-17 50.06 26.69 14.82 16.81 0.62