Off The Shelf?

Graeme Van Leer

Electronic Systems

Page 2: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

2

Electronic Systems

Proprietary Information

L-3 Electronic Systems

• 45 years Experience with facilities in Halifax & Toronto

– Display Solutions

– Vetronics

– Weapon Systems Support

– Repair & Overhaul

– Systems Engineering

• Halifax

– Avionics test

– Repair & overhaul

– Build to Print

– ILS

Page 3: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

3

Electronic Systems

Proprietary Information

Scope of Logistics Capabilities

New System Design

• Develop Logistics Databases (LSAR)

• Reliability, Maintainability, Availability Analysis

• Logistics Support Analysis (Sparing, LORA, LCC, FMECA, Maintenance Task Analysis, RCMA)

• Logistics Products (Maintenance Plans and schedules, Provisioning data, Technical Publications, Facilities, Training, Spares)

In-Service Support

• Life Cycle Management

• On-going Logistics Supportability Studies

• Technical Publications Management

• Support to R&O

• Materiel Management

• Life Cycle Cost Analysis

Page 4: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

4

Electronic Systems

Proprietary Information

Halifax Class Modernization

• $2b Contract

– Design & Build

– In-Service Support

• Design & Build

– CCS

– 2D Radar

– 3D Radar

– Nav Radar

– ESM

– Fire Control Radar

– MultiLink

– IFF

Page 5: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

5

Electronic Systems

Proprietary Information

Halifax Class Modernization

• Prime - Lockheed Martin Canada

– L-3 ES Tier 1 Partner

• ILS

• Logistics Engineering

• Reliability

• Maintainability

• LSAR

• Technical Publications

• Support to: – Training

– Test & Trials

Page 6: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

6

Electronic Systems

Proprietary Information

Off the Shelf

• Why is this a good decision?

– Risk Reduction

• Cost

• Time

• Compatibility

– Lower overall procurement cost

– Proven Technology

– Existing field data

– Existing documentation

Page 7: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

7

Electronic Systems

Proprietary Information

ILS & Off-The-Shelf…

Good Bad

Page 8: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

8

Electronic Systems

Proprietary Information

LSAR

Level 3

Level 2 Level 1

A Proposed Solution

Mature ILS Data

Existing. Fully

Developed LSAR Immature ILS Data

or no LSAR Data.

Processing

Required

No LSA input Data.

Classical ILS

Approach required

Page 9: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

9

Electronic Systems

Proprietary Information

LSAR

Level 3

Level 2 Level 1

The Reality

Mature ILS Data

Existing. Fully

Developed LSAR Immature ILS Data

or no LSAR Data.

Processing

Required

No LSA input Data.

Classical ILS

Approach required

Page 10: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

10

Electronic Systems

Proprietary Information

The reality cont’d

• 7 Different OEMs

• 7 Different methods of delivery

• 7 Different interpretations of the DIDs

• 7 Different countries (including Canada)

• 7 Different explanations of the same issues…

• 1 headache

Page 11: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

11

Electronic Systems

Proprietary Information

The Reality cont’d

• Unrealistic ILS Requirements

– Renegotiation to account for OTS solution

• No redesign

– DED List undefined

• Non-specific Data Item Descriptions (DIDs)

• Commonality needed

– Templates created for collating the data and ultimate upload into OmegaPS. Status Tool

Page 12: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

12

Electronic Systems

Proprietary Information

LSAR Status

Creating the upload templates in

Excel allows a status of

completion to be created for

monthly reporting requirements.

Page 13: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

13

Electronic Systems

Proprietary Information

The Reality cont’d

• Unrealistic ILS Requirements

– Renegotiation to account for OTS solution

• No redesign

– DED List undefined

• Non-specific Data Item Descriptions (DIDs)

• Commonality needed

– Templates created for collating the data and ultimate upload into OmegaPS.

– FMECA/RCMA Tool

Page 14: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

14

Electronic Systems

Proprietary Information

L-3 Developed FMECA/RCMA Tool

Page 15: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

15

Electronic Systems

Proprietary Information

The Reality cont’d

• Unrealistic ILS Requirements

– Renegotiation to account for OTS solution

• No redesign

– DED List undefined

• Non-specific Data Item Descriptions (DIDs)

• Commonality needed

– Templates created for collating the data and ultimate upload into OmegaPS.

– FMECA/RCMA Tool

– LCC Spreadsheet - Analyzer

Page 16: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

16

Electronic Systems

Proprietary Information

LCC Objectives

System LCC analysis using Pennant Analyzer to

Prove compliance to the LCC requirements

Identification of significant cost drivers in each system and sub-system.

As time goes on, monitoring trends in support costs to identify possible supportability issues.

Page 17: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

17

Electronic Systems

Proprietary Information

Why LSAR?

• Logistics Supportability Studies

• Sparing Analysis and LORA

• LCC

Source and repository for

logistics analysis data

• Synchronized data exchange

• CM Controlled

Data exchange and integration from multiple

sources

• Can be accessed via website search tool

Data Source for All StakeHolders

Page 18: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

18

Electronic Systems

Proprietary Information

LSAR Data Search

Page 19: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

19

Electronic Systems

Proprietary Information

How will COTS affect where ILS is going

It is not going away..

Page 20: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

20

Electronic Systems

Proprietary Information

Current Environment (1)

• Constantly Changing Requirements

– Fleet role, fleet structure, fleet size

– Address thru agile, flexible logistics and maintenance

• More emphasis on Systems

– Systems vs. components

– Simpler maintenance chain but more dependence on 1st line effectiveness

– More dependence on 3rd line repair

• Increasing System complexity

– Evolving Technology changes

– Open Architecture drives tech refresh

Page 21: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

21

Electronic Systems

Proprietary Information

Current Environment (2)

• Extended System Life Cycles –shorter technology life cycle

– Obsolescence management

• Greater Utilization of COTS

– Driven by lower initial cost

– Supply Chain and maintenance shifts downstream

– IP – on-going issue when seeking support alternatives

• More outsourcing

– OEM driven from original contractual arrangements

– Alternatives may be opaque given IP

Page 22: Off The Shelf? - Pennant International Group plc The Shelf... · 2017-04-13 · Off the Shelf •Why is this a good decision? –Risk Reduction •Cost •Time •Compatibility –Lower

22

Electronic Systems

Proprietary Information

Questions / Comments?