ohio #3,2013
DESCRIPTION
Ohio #3,2013TRANSCRIPT
The official start of winter means the shutting down ofmany construction projects across the state, including theNelsonville Bypass. Although work on the 8.5 mi. (13.7 km) long bypass will
start back up next spring, 2012 was a highly productive andsuccessful year for the $138 million project.“We couldn’t be more pleased with the progress we’ve
made this year,” said ODOT District 10 Deputy DirectorSteve Williams. “Once we open the bypass next year, this major corridor
and busy truck route will not only be safer to travel but willfurther enhance economic development opportunities insoutheastern Ohio.” ODOT broke ground on Phase II and III on Oct. 13, 2009.
The entire bypass is scheduled to open by fall 2013. From January 2012 to November 2012, contractors
Kokosing Construction Company (Phase II) and BeaverExcavating (Phase III) along with their subcontractorslogged more than 160,000 hours combined on the two phas-es — that’s equivalent to working 24 hours a day for 18years.
2012 Phase II StatsPhase II of the Nelsonville Bypass includes more than 3
mi. (4.8 km) of highway earth work and 4.56 mi. (7.4 km)
of four-lane paving. Phase II also consists of construction ofthe west interchange as well as the construction of fourbridges.• Poured four bridge decks for a total of 1,304 cu. yds.
(997 cu m) of concrete• Installed 19,000 ft. (5,791 m) of guardrail — equivalent
to the length of nearly 53 football fields• Placed more than 52,000 tons (47,174 t) of aggregate
base — equivalent to the weight of the Titanic• Paved 8,646 cu. yds. (6610 cu m) of asphalt• Placed more than 475,000 sq. yds. (363,164 sq m) of
seeding and mulching• Installed 89,000 ft. (27,127 m) of drainage pipe —
approximately 17 mi. (27.4 km) longOne of the greatest accomplishments made this year was
the opening of 3.8 miles of Phase II — nearly nine monthsahead of schedule. “The opening of phase two ahead of schedule is incredi-
ble and illustrates the hard work ODOT and the contractorshave been doing since we broke ground in 2009,” said PhaseII Project Engineer Audrey Seals. “Motorists can now getinto and out of Nelsonville much safer than before.”
2012 Phase III StatsPhase III begins near Doanville and includes construction
of 3.87 mi. (6.2 km) of four-lane highway. Also included inPhase III is the construction of the U.S. 33 / SR 78 / SR 691interchange. The project will reroute SR 78 1.63 mi. (2.6km) through the Happy Hollow area to form the interchange.• Excavated the final 400,000 cu. yds. (305,822 cu m) of
dirt and placed the last 170,000 cu. yds. (129,974 cu m) ofembankment• Placed 15,000 cu. yds. (11,468 cu m) of grout — that’s
enough to fill four-and-a-half Olympic sized pools• Installed 111,000 ft. (33,832 m) of drainage pipe —
approximately 21 mi. (33.8 km) long• Placed 75,000 tons (68,038 t) of aggregate base — the
weight of nearly three-and-a-half Great Sphinx• Paved 70,000 sq. yds. (58,529 sq m) of concrete pave-
ment — equal to nearly 14-and-a-half acres• Poured 5 bridge decks for a total of 2,165 cu. yds. (1,655
cu m) of concrete• Placed 437,000 sq. yds. (365,388 sq m) of seeding and
mulching“We accomplished our goals this year of finishing the
excavation work, mine grouting and pouring the concretedecks,” said Phase III Project Engineer Daniel McDonald.“Next year we’ll focus on paving, finishing the State Route78 interchange and installing safety items such as pavementmarkings, signs and lighting.”
Nelsonville Bypass Sees Successful, Productive Year
OHIO STATE EDITION A Supplement to:
Your Ohio Connection: Ed Bryden, Strongsville, OH • 1-800-810-7640
“The Nation’s Best Read Construction Newspaper… Founded in 1957.”
February 22013
Vol. XVIII • No. 3
624
199
23
4
4
3030 30
422
68
68
22
22
50
3525
50
52
6
6
27
22
80
80
90
7671
7175
70
75
71
77
77
74
70
70
Phase II of the Nelsonville Bypass includes more than 3 mi. (4.8 km) of highwayearth work and 4.56 mi. (7.4 km) of four-lane paving.
From January 2012 to November 2012, contractors Kokosing ConstructionCompany (Phase II) and Beaver Excavating (Phase III) along with their subcon-tractors logged more than 160,000 hours combined on the two phases — that’sequivalent to working 24 hours a day for 18 years.
Page 2 • February 2, 2013 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide
The Ohio State Department of Transportation received bidsfor transportation-related improvement projects.The following is a list of some of the projects let.
Project No: 120561Type: Bridge replacement (1 bridge).Location:HIG-SR-138-18.48.State Estimate: $1,140,000Contractors and Bid Amounts:
• Righter Company Inc., Columbus, Ohio —$1,067,700
• Complete General Construction Company, Columbus,Ohio — $1,138,552
• Eagle Bridge Company, Sidney, Ohio — $1,178,031• Double Z Construction Company, Columbus, Ohio —
$1,191,580• Rietschlin Construction Inc., Crestline, Ohio —
$1,214,728• Shelly & Sands Inc., Columbus, Ohio — $1,220,848• John R Jurgensen Company, Cincinnati, Ohio —
$1,223,328• D G M Inc., Beaver, Ohio — $1,230,608• Sunesis Construction Company, West Chester, Ohio
— $1,245,239• Ratzlaff Construction Company Inc., Chillicothe, Ohio
— $1,249,926• Ford Development Corp., Cincinnati, Ohio —
$1,272,020Completion Date: Sept. 30, 2013
Project No: 120578Type: Intersection.Location:HOC-US-33-7.74.State Estimate: $4,920,000Contractors and Bid Amounts:
• Complete General Construction Company, Columbus,Ohio — $5,289,222
• Shelly & Sands Inc., Columbus, Ohio — $5,326,846• George J Igel & Company Inc., Columbus, Ohio —
$5,574,142• Trucco Construction Company Inc., Delaware, Ohio
— $5,746,804Completion Date:Oct. 18, 2013
Project No: 120580Type: Two lane resurfacing.Location:ADA-SR-125-16.30.State Estimate: $1,631,000Contractors and Bid Amounts:
• Shelly Company, Thornville, Ohio — $1,664,623• Brown County Construction Company Inc.,
Aberdeen, Ohio — $1,676,555Completion Date:Oct. 31, 2013
Project No: 120583Type: Two lane resurfacing.Location: COL-SR-7-11.98.State Estimate: $3,782,000Contractors and Bid Amounts:
• Shelly Company, Thornville, Ohio — $3,671,967
• Shelly & Sands Inc., Columbus, Ohio — $3,742,213• Karvo Paving Company, Stow, Ohio — $3,883,695• Diorio Paving Company Inc., Girard, Ohio —
$3,930,852• Central-Allied Enterprises Inc., Canton, Ohio —
$3,953,577Completion Date:Aug. 31, 2013
Project No: 120591Type: Bridge replacement (1 Bridge).Location: STA-SR-21-5.25, PART 1;STA-21-0.00, PART2.State Estimate: $4,089,000Contractors and Bid Amounts:
• Mosser Construction Inc., Fremont, Ohio —$3,747,260
• Beaver Excavating Company, Canton, Ohio —$3,844,595
• J D Williamson Construction Company Inc.,Tallmadge, Ohio — $3,859,880
• Karvo Paving Company, Stow, Ohio — $4,098,722• Great Lakes Construction Company, Hinckley, Ohio
— $4,098,848• Kenmore Construction Company Inc., Akron, Ohio —
$4,122,481• Ruhlin Company, Sharon Center, Ohio — $4,163,572
Completion Date:Oct. 15, 2013
Project No: 120585Type: Culvert replacement.Location: BUT-VA-INVERTS-FY2013.State Estimate: $2,002,000Contractors and Bid Amounts:
• BCC Ohio Inc., New London, Ohio — $1,827,618• Barrett Paving Materials Inc., Middletown, Ohio —
$2,113,577• Ford Development Corporation, Cincinnati, Ohio —
$2,156,055Completion Date: Sept. 30, 2013
Project No: 123010Type: Interchange.Location:MAD-IR-70-10.27.State Estimate: $3,145,000Contractors and Bid Amounts:
• George J Igel & Company Inc., Columbus, Ohio —$3,543,525
• Double Z Construction Company, Columbus, Ohio —$3,544,250
• Shelly & Sands Inc., Columbus, Ohio — $3,646,850• Fechko Excavating Inc., Medina, Ohio — $4,041,890• John R Jurgensen Company, Cincinnati, Ohio —
$4,227,167• Complete General Construction Company, Columbus,
Ohio — $5,655,500Completion Date: June 15, 2014
Wood • Hamilton • Stark • Henry • Greene • Knox • Franklin • Clermont • Crawford • Union • Cuyahoga • Brown • Licking • Medina• Williams • Harrison • Adams • Mercer • Butler • Clark • Ashtabula • Sandusky • Portage • Athens • Logan • Lake • Erie • Wyandot• Warren • Fairfield • Miami • Paulding • Darke • Muskingum • Ottawa • Holmes • Jefferson • Trumbull • Summit • Washington • VanVert • Licking • Wood • Hamilton • Stark • Henry • Greene • Knox • Franklin • Clermont • Crawford • Union • Cuyahoga • Brown •Licking • Medina • Williams • Harrison • Adams • Mercer • Butler • Clark • Ashtabula • Sandusky • Portage • Athens • Logan • Lake
Ohio...
‘Buckeye State’ Highway Lettings
Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • February 2, 2013 • Page 3
WWW.RUDDEQUIPMENT.COM CALL: 1-877-DIG-RUDD
If there’s one thing more hardworking and reliable than Rudd’s equipment, it’s Rudd’s service and maintenance. Rudd’s freight system and 13 service branches across nine states, together with our award-winning master technicians, mean we can deliver replacement parts, equipment and service to your site by the next morning. It’s that kind of 24/7 service that proves how committed Rudd is to going the distance for you.
Unearth a better way to do business.
The Ohio Aggregates and Industrial Minerals Association(OAIMA) held its 2012 Annual Meeting and Trade Showrecently in Columbus, Ohio.More than 450 industry personnel were in attendance
along with more than 60 exhibitors.Highlighting the kick-off of the event was a visit from
Ohio Lt. Gov. Mary Taylor. The lieutenant governor spoke of economic development
and jobs for Ohioans and recognized the OAIMA’s role as anassociation and an industry in achieving positive results.
She also thanked members for their support of theCommon Sense Initiative and for their continuing efforts tohelp streamline government including OAIMA’s continuinginvolvement with the CSI office.During the event, several long-time OAIMA and industry
leaders were honored at the 2012 Annual Meeting including: • Tom Milligan (Western Ohio Cut Stone) — Hall of
Fame Award • Chris Scala (American Sand & Gravel) — Hall of Fame
Award
• Marlene Oster (OsterSand & Gravel) — Ed HoleAward
• State Rep. Dave Hall — Robert A. Wilkinson Award Brian Barger (Brady, Coyle & Schmidt) — Rocky AwardA total of 7 Reclamation Achievement and Pride Awards
were presented as well, from representatives of NationalLime and Stone, The Shelly Company and Oscar BrugmannSand & Gravel.In addition to awards, Tony Kruse, nominating committee
chairman (National Lime & Stone), announced the 2013OAIMA Board of Directors:• President, Tony Price (National Lime & Stone)• First Vice President, Hugh Gunn (East Fairfield Coal
Co., Limestone Division)• Second Vice President, Todd Young (Mar-Zane
Materials, Inc.)• Immediate Past President, Dennis Philips (Philips
Companies)• Treasurer, Jack KersjesFor more information, visit www.oaima.org.
2012 Annual Meeting, Trade Show...
Lt. Governor Mary Taylor Addresses OAIMA Members
Lt. Gov. Mary Taylor spoke of economic developmentand jobs for Ohioans and recognized the OAIMA’s roleas an association and an industry in achieving posi-tive results.
Page 4 • February 2, 2013 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide
Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • February 2, 2013 • Page 5
PRE-OWNED, JOB READY EQUIPMENT NOW AVAILABLE! Cincinnati • Mt. Orab • Columbus • Lexington • Louisville
Call Brad Kent at 513-266-7761 or on our USED EQUIPMENT HOTLINE: 888.BOBCATS
Parts • Sales • Service • Rental • Training
To See More Machines, Please visit us online at www.bobcat-ent.com
2006 S175 Bobcat Loader, 1500 Hrs, Open ROPS, (4 Available), CN 85625..................................................$17,000
2006 S160 Bobcat Skid Steer Loader, 1000 Hrs, Cab Heat &Air, (3 Available) CN 84030 ............................................$22,500
2010 S630 Bobcat Loader, 1840 Hrs, Open ROPS, CN 84437..........................................................................................$25,500
2005 S250 Bobcat Loader, 1300 Hrs, Cab & Heat, HandControls, CN 83132 ........................................................$27,500
2007 S330 Bobcat Loader, 260 Hrs, Gold Pkg. Joysticks, 2 Spd, CN 85338..............................................................$34,000
2006 T190 Bobcat Track Loader, 1360 Hrs, Gold Package, CN 84096..........................................................................$30,000
2007 T250 Bobcat Track Loader, 690 Hrs, Gold Package,Joystick Controls, CN 83436 ........................................$36,000
2007 T300 Bobcat Track Loader, 1655 Hrs, Open ROPS, CN 83325..........................................................................$32,000
Stamp of Approval...
Indiana Department of TransportationFinalizes Deal for Ohio River BridgeBy Tom DaviesASSOCIATED PRESS
INDIANAPOLIS (AP) The Indiana Department ofTransportation announced Dec. 28 that the state had finalizedits agreement with the partnership group that will build a newOhio River bridge between Indiana and Kentucky for $763million. The step represents a final decision on the selection of the
WVB East End Partners consortium that the Indiana FinanceAuthority preliminarily approved in November. Indiana is overseeing construction of the so-called East End
bridge that will complete an interstate loop around Louisville,Ky., with a crossing between Utica, Ind., and Prospect, Ky.Kentucky officials are handling construction of a secondbridge for Interstate 65 at downtown Louisville and upgradesto the current bridge. Kentucky Transportation Cabinet offi-cials said that the agency gave notice to proceed to WalshConstruction Co., which will build the downtown crossing. Motorists will pay tolls to use all three of the spans after
they’re completed. The WVB East End Partners group can now complete
design work on the East End bridge that is scheduled for com-
pletion in late 2016, Indiana highway department spokesmanWill Wingfield said. “We’re thinking it’s likely construction crews will start
mobilizing this summer,” Wingfield said. The $763 million bid from WVB East End Partners is 23
percent below the project’s previous $987 million cost esti-mate, which doesn’t include costs for land acquisition andrelocating utilities. WVB East End Partners includes WalshInvestors, VINCI Concessions and Bilfinger Berger and 21other entities. The Indiana Finance Authority formally finalized the deal
Dec. 27 after Gov. Mitch Daniels gave it his approval earlierin the month, Wingfield said. Kentucky is financing its bridge projects through tradition-
al state bonding. In contrast, Indiana is using a public-privatearrangement under which WVB East End Partners will lineup its own financing for the East End bridge and receive annu-al payments from the state for 35 years after the bridge opens. “At this point, the team needs to secure their financing for
the project,” Wingfield said. “We are moving forward with theproject now.” Wingfield said Indiana and Kentucky officials will later
choose a private company to manage tolling on the bridges.
Palfinger PurchasesTiffin Loader CraneBuilding, PropertyPalfinger, a leading truck equipment manufacturer
employing more than 1,000 employees across NorthAmerica, purchased a property and building in Tiffin,Ohio, on Dec. 27, 2012. Tiffin Loader Crane began selling and installing
knuckle boom cranes in 1985 and quickly built a reputa-tion for developing innovative solutions to its customers’material handling needs, according to the company. The Tiffin location also serves as a manufacturing site
of the new Palfinger GT brand of truck-mounted forklifts.The relationship between Palfinger and Tiffin Loader
Crane’s dates back to 1991 when Tiffin Loader Cranebecame the largest independent dealer of Palfinger. Sincethen, the relationship has continued to strengthen asPalfinger acquired the company in 2000, making Tiffin itsU.S. home. Palfinger managing directors Michael Berger and
Mark Woody agreed that, “the future is never easy toforesee with new challenges just around the corner but itis reassuring to know that Palfinger will always be able tocall Tiffin, Ohio, our home.” For more information, visit www.palfinger.com, or
www.palfleet.com.
By Marcus GreenTHE COURIER-JOURNAL
UTICA, Ind. (AP) The East End Bridge is getting a newlook. With Indiana’s approval, the companies in charge of
designing and building the span rejected the style selected bya committee of elected and community leaders more than sixyears ago. Instead of the needle-like towers that had been originally
proposed to support cables carrying the bridge deck, thecables now connect to two bulkier arches rising above theroadway.
Indiana officials say the new design helped WVB EastEnd Partners cut the overall cost of the eastern bridge and itsapproach roads by more than $220 million, and more close-ly matches the choice of a public vote held before a groupheaded by Indiana Gov. Mitch Daniels and former KentuckyGov. Ernie Fletcher in December 2006 chose the needle tow-ers. The popular design — favored by about 51 percent of the
2,800 people who voted online and at four meetings for theeastern span in 2006 — had arches that came to a point,while the new design’s supports are squared at the top. But, “We feel as if we were able to meet the wishes of the
public while also saving dollars for taxpayers and toll pay-
ers,” Will Wingfield, spokesman of the Indiana Departmentof Transportation, told The Courier-Journal in an interview. Indiana didn’t widely publicize the change, which
Wingfield said could undergo more revisions. Wingfield and Ron Heustis, Indiana’s project manager,
said the state made clear at various stakeholder meetingsover the past year that it would be open to a new design. AndWingfield noted that the design had been publicly availableon the Indiana Finance Authority’s Web site, where it’s foundin WVB’s technical proposal for the bridge. “It’s been up there for more than a month at this point,”
Wingfield said. The 18-month bridge design process culminated in 2006
with a selection committee choosing the designs for bothspans. The three-tower design for the new downtown bridgehasn’t changed, according to the Kentucky TransportationCabinet. Wingfield said the selection occurred before the states
decided to allow the same firms to design and build the east-ern bridge, rather than taking construction bids on a setdesign. He cited those changes as helping reduce the cost andconstruction schedule. But the new look has its critics, including the architect of
the bridge’s previous design. Miguel Rosales had favored the narrow tower look as
compact and minimal for the bridge’s largely undevelopedsetting. Rosales, who was paid for his work, said he isn’t sur-prised by the change because of its cost savings, although heis disappointed by what he calls a “standard design.” “It doesn’t really reflect the conditions that we thought
were important at that location,” said Rosales, principal atRosales + Partners in Boston. Prospect resident David Warner, who lives in the
Bridgepointe subdivision near the bridge’s Kentuckyapproach, said the new design is “not unattractive” andunderstands the financial reasons for the change. Still, he said, needle-like tower “is much more attractive,
and a piece of artwork.” The cost of the bridge itself is redacted in WVB’s finan-
cial plan, which was submitted to the finance authority alongwith its design proposal in late October. The previous designwas projected to cost $284 million as of last March. Rosales said he wasn’t consulted about the design change
and Wingfield said all of the previous design work was pro-vided to WVB. Former Jeffersonville Mayor Dale Orem, a member of the
2006 committee that selected the bridge design, said he wasunaware of the change until notified by a reporter. Orem said he isn’t concerned that his committee’s choice
was discarded, saying he still believes the bridge will have anice “silhouette.” “At least they kept the total idea,” Orem said. “They did-
n’t go ... to a box girder or any obtrusive thing. To the EastEnd, I think this still will be attractive.” The new design has greater resistance to “wind, seismic
and other load demands, and is a more redundant and robuststructure,” according to WVB’s proposal. The bridge’s cable system is designed to last for up to 75
years, and the individual strands can be removed for testingor other inspection without affecting traffic on the span,according to the proposal. Among other features, the bridgewould have an “inspection catwalk” allowing crews to walkthe structure’s entire 2,510 ft. below the deck. Construction on both portions of the project is expected to
start later this summer.
Indiana Gives Approval for East End Bridge MakeoverPage 6 • February 2, 2013 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide
www.hyundaiamericas.com
Industry’s Best Total Coverage Warranty: 3-year / 3,000-hour full machine warranty & 5-year / 10,000-hour structural warranty
H
Y U N D A
I
W
AR R A N
TY
VALUECash is king – Make more money & spend less with Hyundai 9 Series machines.• More Standard Features
• Industry-Best Total Coverage Warranty
• Hi-mate Remote Management service – FREE for 3 years
• Industry-Leading Fuel Economy
• Industry-Leading Cycle Times
Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • February 2, 2013 • Page 7
ODOT, Gov. Launch ‘Jobsand Transportation Plan’Gov. John R. Kasich recently embarked on a two-day state tour as he, Ohio Department
of Transportation (ODOT) Director Jerry Wray, Ohio Turnpike Director Rick Hodges andothers unveil a first-of-its-kind plan to generate approximately $3 billion for highway roadconstruction without leasing the Ohio Turnpike and without Turnpike employee layoffs.The Ohio Jobs and Transportation Plan would generate $1.5 billion in new funds for Ohio
highways from bonds issued by the Ohio Turnpike Commission and backed by future tollrevenues. Up to an additional $1.5 billion could be generated from matching local and federal funds
coming to a combined total of approximately $3 billion for Ohio’s major highway construc-tion projects.“This plan just makes sense as we continue Ohio’s economic resurgence, grow jobs and
make our state prosperous once again,” Kasich said. “Billions of dollars in new highwayfunds further strengthens Ohio’s jobs-friendly climate and keeps our state moving by deliv-ering more projects faster.”“Bonding against future Turnpike revenue generates enough money to erase our highway
budget deficit,” Wray said. “Combined with ODOT’s work to reduce our cost of doing busi-ness and improve service to the state’s motoring public, this plan puts the resources we needinto our major construction budget.”Details of the Ohio Jobs and Transportation Plan include:• No long-term, private lease;• A continued public, independent Turnpike with expanded authority and renamed the
“Ohio Turnpike and Infrastructure Commission”;• More than 90 percent of new bond money will go directly to northern Ohio highway
projects, including the Turnpike itself;• Rebuilding the Ohio Turnpike will occur decades sooner than planned;• Tolls for local passenger trips paid with an EZ Pass are frozen for 10 years;• All other toll rates are capped at inflation, which is significantly less than historic toll
increases;• No Turnpike employee lay-offs are anticipated.“Maintaining public control and an independent Turnpike Commission helps keep tolls
low and workers on the job,” Hodges said. “Plus, with this new plan we can get to workrebuilding the entire Turnpike decades sooner than we once had planned.”ODOT has cut the agency’s $1.6 billion highway budget deficit by $400 million thanks to
new savings and operational efficiencies, but more money and more innovation is needed. Money generated from the Ohio Jobs and Transportation Plan will help fill budget deficit
without raising taxes that would kill jobs. The launch of the new plan concludes a year-longstudy of options for better using the revenue generated by the Ohio Turnpike.
Ohio Attorney General DeWineIssues Opinion on Truck WeightsOhio Attorney General Mike DeWine has
issued an opinion on the 7.5 percent weighttolerance for vehicles hauling aggregate onOhio’s public highways and streets. In part itstates:“The term ‘surface mining truck,’ as used
in R.C. 5577.043(A)(1), means a ‘vehicle’ asdefined in R.C. 4501.01(A), used to haulminerals upon Ohio’s improved public high-ways and streets.”This definition is important as several
local law enforcement agencies had claimed
that a “surface mining truck” was a largertruck that hauled aggregate within a plantproperty such as an articulated haul truck ora 100 ton (91 t) ore truck. Much of these claims were based on
images obtained from “Wikipedia” or“Google” searches online. The simple clari-fication that a “surface mining truck” isindeed a “vehicle” should eliminate anyfuture issues. For more information, visit
www.oaima.org.
Page 8 • February 2, 2013 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide