old wallgrove road widening (roberts road to wallgrove ... · 21/21162/179605 old wallgrove road...
TRANSCRIPT
Appendix F
Traffic assessment
ENVIFACTORS
MONTH/YEAR
(blank page)
Roads and Maritime Services
Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
30 April 2012
121/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
This - Traffic and Transport Report for the Upgrade of Old Wallgrove Road Upgrade between Roberts Road and the M7 Motorway (“Report”):
1. has been prepared by GHD Pty Ltd or (“GHD”) for the NSW Roads and Maritime Services (“RMS”);
2. may only be used and relied on by the RMS;
3. must not be copied to, used by, or relied on by any person other than the RMS without the prior written consent of GHD;
4. may only be used for the purpose of informing State Government on potential future network traffic volumes, intersection performance and concept design requirements for key intersections situated along Old Wallgrove Road (and must not be used for any other purpose).
GHD and its servants, employees and officers otherwise expressly disclaim responsibility to any person other than the RMS arising from or in connection with this Report.
To the maximum extent permitted by law, all implied warranties and conditions in relation to the services provided by GHD and the Report are excluded unless they are expressly stated to apply in this Report.
The services undertaken by GHD in connection with preparing this Report:
were limited to those specifically detailed in Section 1.4 of this Report;
did not include development of options for Southern Link Road Network connection which was taken from the Department of Planning and Infrastructure;
did not include traffic modelling outside of the defined Old Wallgrove Road study area;
did not include modification of intersection design beyond those specified by RMS and its nominated Road Design Contractor; and
did not include the provision or assessment of detailed land use data for the WSEA precincts or precinct level road networks beyond those boundering the Old Wallgrove Road and Mini Corridor.
The opinions, conclusions and any recommendations in this Report are based on assumptions made by GHD when undertaking services and preparing the Report (“Assumptions”), including (but not limited to):
approach identified in Sections 4.2, 4.3, 4.4 and 4.5;
worst case trip generation assumptions and general travel demand trends and profiles;
specified surrounding road network upgrade assumptions over time;
regional traffic demand trends as supplied by the RMS Sydney Metropolitan Area EMME Model; and
physical design constraints identified by the project design team in various workshops and in previous studies that had a close relationship with the future planning and design of the Old Wallgrove Road corridor.
GHD expressly disclaims responsibility for any error in, or omission from, this Report arising from or in connection with any of the Assumptions being incorrect.
Subject to the paragraphs in this section of the Report, the opinions, conclusions and any recommendations in this Report are based on conditions encountered and information reviewed at the time of preparation and may be relied on until 12 months, after which time, GHD expressly disclaims responsibility for any error in, or omission from, this Report arising from or in connection with those opinions, conclusions and any recommendations.
21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
List of Acronyms
ADT Average Daily Traffic
AADT Average Annual Daily Traffic
BTS Bureau of Transport Statistics
DoP Department of Planning
DoPI Department of Planning and Infrastructure
DoS Degree of Saturation
EA Environmental Assessment
ELDP Employment Lands Development Program
EMME Equilibre Multimodal / Multimodal Equilibrium (Strategic Transport Network Modelling
Software used by the RTA)
EP&A Environmental Planning and Assessment Act 1979
EPLRN Erskine Park Link Road Network
EPLR Erskine Park Link Road
Km/h kilometres per hour
LGA Local Government Area
LoS Level of Service
NECS National Environmental Consulting Services
NSW New South Wales
NWGC North West Growth Centre
OWR Old Wallgrove Road
REF Review of Environmental Factors
RTA New South Wales Roads & Traffic Authority
RMS New South Wales Roads and Maritime Services
SEPP Strategic Environmental Planning Policy
SIDRA Signalised & unsignalised Intersection Design and Research Aid (Intersection Modelling
Software)
SLRN Southern Link Road Network
SWGC South West Growth Centre
Veh/h vehicles per hour
VCR Volume Capacity Ratio
WSEA Western Sydney Employment Area
21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Contents
List of Acronyms 1
1. Introduction 1
1.1 Background 1
1.2 The Project 1
1.3 Benefits of the Project 5
1.4 Study Objectives 5
1.5 Study Process 6
1.6 Report Structure 7
2. Planning Context 8
2.1 Overview 8
2.2 Regional Context 8
2.3 Transport Context 9
2.4 Planning Policy Context 11
2.5 Consistency with the EPLRN Concept Plan 15
3. Existing Conditions 16
3.1 Overview 16
3.2 Existing Land Uses 16
3.3 Existing Transport Network 17
3.4 Travel Characteristics 18
3.5 Existing Road Network Performance 26
3.6 Existing Road Safety Trends 32
4. Traffic Model Development 35
4.1 Overview 35
4.2 Future Land Use and Developable Areas 36
4.3 Trip Generation 38
4.4 Future Road Network 40
4.5 Strategic Traffic Modelling 42
4.6 Microsimulation Modelling 45
4.7 Approach to Traffic Forecasts and Assessments 45
5. Appraisal of Future Transport Impacts 46
5.1 Overview 46
5.2 Development of Traffic Forecasts 46
5.3 Modelling Approach 47
21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
5.4 Desired Levels of Service Criteria 47
5.5 Future Road Network Performance 49
5.6 Summary of key findings 52
5.7 Future Intersection Performance (2021) 55
5.8 Public Transport 58
5.9 Freight Transport 59
5.10 Active Transport 60
5.11 Construction Traffic Impacts 62
5.12 Cumulative Impacts 66
5.13 Mitigation Measures 67
6. Summary and Conclusions 68
6.1 Overview 68
6.2 Key Findings 68
6.3 Recommendations 69
Table Index
Table 1 Functional Classification of Roads 21
Table 2 Bus Services to Western Sydney Employment Area 25
Table 3 Average Daily Traffic (ADT) Data – February 2011 27
Table 4 Peak Hour Traffic Volumes (2011) 27
Table 5 Travel Time Survey Results (2011) 29
Table 6 Level of Service Criteria for Intersections (RTA 2002) 30
Table 7 Existing Intersection Operations (2011) 31
Table 8 Crash History – Wallgrove Road (2005-2009) 33
Table 9 Crash History – Old Wallgrove Road (2007-2010) 34
Table 10 WSEA Future land Use 38
Table 11 Traffic Generation – 2021 AM (2 Hour Peak) 39
Table 12 Traffic Generation – 2031 AM (2 Hour Peak) 39
Table 13 Volume to Capacity Ratio Thresholds 48
Table 14 Capacity Thresholds for Links 48
Table 15 Level of Service Definitions 49
Table 16 Base Case: Road Link Performance (Year 2021) 50
Table 17 Base Case: Road Link Performance (Year 2031) 50
Table 18 Measures of Effectiveness – AM Peak Model Runs 51
Table 19 Measures of Effectiveness – PM Peak Model Runs 52
Table 20 2021 Performance –Intersection Layout 57
Table 21 Heavy Vehicle Traffic Generation 65
Table 22 Summary of Peak Construction Traffic Activity 66
21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Figure Index
Figure 1 Metropolitan Plan for Sydney 2036 and WSEA 2
Figure 2 WSEA and the Proposed Old Wallgrove Road Corridor 4
Figure 3 Traffic Modelling Process 6
Figure 4 Precincts in the Western Sydney Employment Area 8
Figure 5 Regional Catchment and Spatial Relationships 9
Figure 6 SEPP Designated Strategic Road Network 10
Figure 7 Modified EPLRN Concept Plan (2009) 13
Figure 8 Modified EPLRN Concept Plan for Cycling 13
Figure 9 Development Footprints and Location of the WSEA 16
Figure 10 Road Network Surrounding WSEA 17
Figure 11 Journey to Work Mode Share (Penrith LGA) 18
Figure 12 Journey to Work Mode Share (Blacktown LGA) 18
Figure 13 Origin of Employees Working (Penrith LGA) 19
Figure 14 Origin of Employees Working (Blacktown LGA) 19
Figure 15 Average Travel Time per Trip Purpose (Penrith LGA) 19
Figure 16 Average Travel Time per Trip Purpose (Blacktown LGA)20
Figure 17 Car Ownership by LGA 20
Figure 18 Current WSEA Bus Service Routes 24
Figure 19 Link Count Locations 26
Figure 20 Travel Time Survey Routes 28
Figure 21 Old Wallgrove Rd/ Wallgrove Rd Intersection Layout 32
Figure 22 Modelling Approach 36
Figure 23 Potential Precinct Density and Spatial Relationships 37
Figure 24 SEPP Arterial Road Network (WSEA) 40
Figure 25 2021 Old Wallgrove Rd Sub Area Model Network 41
Figure 26 2031 Old Wallgrove Rd Sub Area Model Network 42
Figure 27 Model Coverage Area – EMME and Paramics 43
Figure 28 Developable Areas and Sub-Precincts 44
Figure 29 Recommended Mid-Block Lane Configuration 54
Figure 30 Intersections Assessed 55
Figure 31 Year 2021 Interim Stage Intersection Layouts 56
Figure 32 Strategic Bus Corridors 59
Figure 33 Planning of Employment Lands and Intermodal Terminals60
Figure 34 Erskine Park Link Road Shared Cycle/Pedestrian Path 61
Figure 35 M7 Motorway Shared Path Plan 61
Figure 36 Potential Construction Haulage Routes 63
21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Appendices
A Recommended Intersection Layouts
B Intersection Analysis – Existing Conditions
C Calibration and Validation and Modelling Results
D Intersection Analysis – 2021
121/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
1. Introduction
1.1 Background
The Western Sydney Employment Area1 (WSEA) has been planned as an industrial and employment
area as part of the Sydney Metropolitan Strategy: A City of Cities prepared by the NSW Government
in 2005. It encompasses 2,450 hectares spanning across four local government areas – Penrith,
Blacktown, Holroyd and Fairfield – that would accommodate up to 36,000 jobs. Figure 1 shows the
location of the WSEA.
In December 2010, the NSW Government developed a plan that sets actions for delivering the
directions identified in the 2005 Sydney Metropolitan Strategy. This is known as the Metropolitan Plan
for Sydney 2036, and was accompanied by the Metropolitan Transport Plan (which was released
earlier in 2010) and the NSW State Plan 2010. Both plans list a number of short to medium term
commitments which form part of a 10-year plan. The WSEA has been referenced in a number of
studies and associated with investigation lands situated to the south.
The area is strategically located near the M4 and M7 Motorways. The opportunities for employment
and the synergies which are established through its relationship with the M4 and M7 Motorways will
result in a truly unique industrial employment area for Western Sydney.
The WSEA has been rezoned as employment lands under the provisions of State Environmental
Planning Policy (SEPP) for WSEA, which includes the construction of a road that would link the
existing Erskine Park Employment Area and the Westlink M7 Motorway.
The Roads and Maritime Services (RMS) developed a Concept Plan for the road network connecting
the employment areas in the Fairfield, Blacktown and Penrith Local Government Areas with the M4
and M7 Motorways and Mamre Road and is known as the Erskine Park Link Road Network. In
February 2008, the NSW Government exhibited the Western Sydney Employment Hub Proposed
Erskine Park Link Road Network Concept Plan Environmental Assessment (the Concept Plan), which
assessed the entire network of roads in the WSEA. Following exhibition, a Submissions Report and
Preferred Project Report were prepared outlining changes to the proposal and the Minister for
Planning granted approval on 11 August 2009 for the Concept Plan, subject to further environmental
assessment being undertaken and includes upgrades to Old Wallgrove Road.
1.2 The Project
The Roads and Maritime Services (RMS) proposes to upgrade the existing Old Wallgrove Road
corridor (east-west section) between the approved Erskine Park Link Road (currently under
construction) at Roberts Road and the interchange with Wallgrove Road and M7 Motorway. The
project, for the purposes of this report, is the eastern section of the east-west route identified as part
of the Erskine Park Link Road (known as Old Wallgrove Road). The upgrade to Old Wallgrove Road
is intended to provide a suitable eastern gateway to the WSEA at the interchange with Wallgrove
Road and the M7 Motorway, as shown in Figure 2.
1 The Western Sydney Employment Area (WSEA) has also been referenced as the “Western Sydney Employment Hub (WSEH)”, or “The Hub” in a number of planning documents. Reference to the WSEA shall also be taken to mean the WSEH
in this report, and vice versa. For consistency, this report uses the term “Western Sydney Employment Area” or WSEA.
221/2
116
2/1
79
605
Old
Wa
llg
rov
e R
oa
d U
pg
rad
e (
Ro
bert
s R
oa
d -
M7 M
oto
rway)
Tra
ffic
and T
ransport
Report
Fig
ure
1
Metr
op
olita
n P
lan
fo
r S
yd
ney
2036
an
d W
SE
A
Sourc
e: H
igh
lighte
d fro
m M
etr
opo
litan P
lan f
or
Syd
ney 2
036 O
verv
iew
Map (
NS
W G
overn
me
nt, 2
01
0)
We
ste
rn S
yd
ney
E
mp
loy
men
t A
rea
M7
M4
321/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
The proposed upgrade to the Old Wallgrove Road corridor would play an important role in unlocking
and supporting development in the employment area. The current design of the Old Wallgrove Road
corridor is not suitable to accommodate this need and requires upgrading. The upgrade should be
designed to serve as both a main gateway from the strategic road network and consider its other
function, as a spinal road supporting local road access and the future development in WSEA.
The upgrade of Old Wallgrove Road includes the following key components:
Replacement of the existing undivided two lane road along the east-west section of Old Wallgrove
Road corridor with a four lane divided carriageway approximately 1.3 kilometres in length.
Reservation of a 40m wide road corridor for a future six lane divided carriageway road2, which can
support future road and intersection upgrades and additional bus infrastructure resulting from the
further development of WSEA.
Tie-ins with Erskine Park Link Road in the west and Wallgrove Road in the east.
A new 0.3 kilometre of four lane divided carriageway road, known as Mini Link, connecting Old
Wallgrove Road at Quarry Road with Wallgrove Road and the northbound carriageway of the M7
Motorway.
Capacity improvements to Wallgrove Road and M7 Motorway on and off ramp approaches at the
eastern end of the corridor.
A shared pedestrian and cycleway on the northern side of the road.
Bus stop infrastructure along the northern and southern side of the road.
The upgrade of six intersections to accommodate the future access needs of WSEA, and in
particular Eastern Creek and former Wonderland employment precincts in the WSEA. These
upgrades include:
– The conversion of an existing giveway controlled T-Intersection at Old Wallgrove Road with
Roberts Road to a signalised controlled three-way intersection.
– The conversion of a giveway controlled T-Intersection at Old Wallgrove Road with Eastern
Creek Drive to a signalised three-way intersection.
– The conversion of a giveway T-Intersection at Old Wallgrove Road with Southridge Street to a
signalised four-way intersection, which includes a new local road to the north.
– The consolidation of the existing staggered giveway controlled T-Intersections at Old
Wallgrove Road with Quarry Road and Capicure Drive to a signalised four-way intersection at
the existing alignment with Quarry Road. This includes the removal of the Capicure Drive
approach to the south and replacement with a new Mini Link approach and inclusion of a dual
right turn facility from Old Wallgrove Road west to Mini Link.
2Department of Planning and Infrastructure, Status Report Presentation dated 31 March 2010, ‘Western Sydney Employment
Area - Old Wallgrove Road Corridor (East – West Section)’. Taken from http://planning.nsw.gov.au/LinkClick.aspx?fileticket=eCn_2hR2HFE%3D&tabid=366&language=en-AU
421/2
116
2/1
79
605
Old
Wa
llg
rov
e R
oa
d U
pg
rad
e (
Ro
bert
s R
oa
d -
M7 M
oto
rway)
Tra
ffic
and T
ransport
Report
Fig
ure
2
WS
EA
an
d t
he
Pro
po
sed
Old
Wallg
rove
Ro
ad
Co
rrid
or
Sourc
e: E
xtr
acte
d f
rom
Revie
w o
f E
nvir
onm
en
tal F
acto
rs –
Ers
kin
e P
ark
Lin
k R
oad
(R
TA
, 20
10).
Sy
dn
ey
Wate
r
Pip
elin
e
M4 M
oto
rway
M7 M
oto
rway
Wall
gro
ve R
oa
d
Old
Wall
gro
ve R
oa
d C
orr
ido
r (e
ast-
we
st
se
cti
on
)
521/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
– The removal of direct access driveways allowing all movements and reconfiguration to either
left in and left out arrangements or reallocated access points to a new surrounding local road
network.
– Capacity enhancements to approaches at the existing four-way signalised intersection of
Wallgrove Road with Old Wallgrove Road and M7 Motorway southbound on and off ramps.
This includes the removal of the right turn movement on the Old Wallgrove Road approach
and diverting traffic to the Mini Link route for traffic travelling to the south of Old Wallgrove
Road.
– Capacity enhancements and conversion of an existing three-way signalised intersection of
Wallgrove Road with M7 Motorway northbound on and off ramps to a new signalised four-way
intersection. This includes the Mini Link approach to the west and a dual right turn facility
from Wallgrove Road south to the M7 Motorway northbound on ramp.
– The inclusion of a new left in and left out stop signposted controlled T-intersection for access
to Capicure Drive from the new Mini Link road corridor.
1.3 Benefits of the Project
Completion of the upgrade to Old Wallgrove Road between Roberts Road and the Interchange with
Wallgrove Road and M7 Motorway would provide the following benefits and is consistent with the
Concept Plan approval granted for the Erskine Park Link Road Network:
Join Erskine Park Link Road and Wallgrove Road and provide a vital connection between the
Western Sydney Employment Area and the M7 and M4 motorways.
Reinforce the Western Sydney Employment Area as a significant employment hub.
Provide a suitable travel environment for transport users of the Western Sydney Employment
Area and assist in reducing industrial traffic use of the existing Erskine Park Road and adjoining
local roads.
Improve traffic flow in western Sydney with direct connection to and from the M7 Motorway.
Provide for new bus infrastructure and for road upgrade in the future.
Provide a new shared cycle/pedestrian path.
Reduce transport costs for industry located in the Western Sydney Employment Area.
Figure 2 shows the Old Wallgrove Road corridor in the context of the Western Sydney Employment
Area.
1.4 Study Objectives
The Roads and Maritime Services (RMS), the Department of Planning and Infrastructure (DoPI) and
the Transport for NSW are working together on transportation planning and management of the land
transport network throughout the Western Sydney Employment Area (WSEA). The over-arching aim
is to ensure that a safe, integrated, responsive and sustainable land transport system is provided that
has considered the transportation needs of a number of potential development areas within the
WSEA.
The proposal which is the subject of the REF shows the level of infrastructure required to meet the
projected traffic demand up to and including an interim development scenario (projected year: 2021).
The impacts of the proposal under 2021 traffic conditions have been assessed under this study. Land
use assumptions adopted for Western Sydney Employment Area (WSEA) under an interim
621/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
development scenario are as follows:
Eastern Creek Precinct 100%
Ropes Creek Precinct 67%
Erskine Park Employment Area 100%
Lands south of SW Pipelines 53%
It is also assumed that full development potential of WSEA would be reached by year 2031 (ultimate)
and the corridor has been reserved for the longer term need.
The study has primarily assessed traffic and transport requirements to meet the interim development
scenario. However, the fully completed WSEA land use assumptions were tested to make sure that
any future widening and/or upgrade of Old Wallgrove Road and associated works could be
constructed within the REF site boundary.
It should be noted that for the ultimate development case, works outside the current proposal site may
be required, such as works within the M7 Motorway corridor. Such works do not form part of the
current environmental assessment for Old Wallgrove Road Upgrade and would form part of a
separate traffic and environmental assessment.
1.5 Study Process
Traffic modelling is a core component of this study and is used to predict and evaluate the traffic
impacts of both future land use patterns and planned road network improvement for WSEA and Old
Wallgrove Road respectively.
Figure 3 below outlines the process of developing strategic demand and subsequently applying the
changes drawn from the strategic model to both intersection and microsimulation models.
Figure 3 Traffic Modelling Process
The modelling approach is based on the strategic RMS model developed using EMME transport
modelling suite and has been used to evaluate specific traffic and land use patterns. This approach
721/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
will account for potential future wider re-routing impacts on Old Wallgrove Road, Mink Link and the
surrounding road network.
The modelling outputs from the strategic model provided an understanding of both turn movement
growth at intersections and link traffic demand and were used to inform the intersection and
microsimulation models respectively.
Testing of the performance of Old Wallgrove Road, Mini Link and the surrounding road network was
carried out by imposing the forecast traffic movement generated by the strategic model at key
intersections. PARAMICS microsimulation modelling and SIDRA intersection models were then used
to review the operational performance of intersections and to select preferred intersection layouts and
traffic signal configurations that could be used in the next stage of the appraisal process.
Once suitable intersection layouts were developed using the SIDRA models, the individual
intersections were then modelled as connected and real time coordinated corridors. PARAMICS
microsimulation modelling was used to review the performance of the coordinated corridors under
future traffic forecasts produced through the strategic modelling process.
Paramics models were then used to understand localised performance and corridor operating
constraints. The refinement of traffic demand and route choice undertaken in the Paramics models
was also fed back into SIDRA intersection models to identify the most optimal intersection
configuration layouts and traffic signal phasing at intersections situated along both Old Wallgrove
Road and Mini Link.
1.6 Report Structure
The report is developed and explained through the following sections:
Section Two – Planning Context: reviews strategic planning documents to confirm the strategic
planning basis for the study and its surroundings.
Section Three – Existing Conditions: summarises the existing conditions along Old Wallgrove
Road and its surrounds and the future background conditions that will influence development
within WSEA.
Section Four – Traffic Model Development: reports on the potential traffic impacts on Old
Wallgrove Road and the adjoining road network.
Section Five – Appraisal of Future Transport Impacts: discusses the results of the transport
evaluation process.
Section Six – Summary and Conclusions: presents a summary of the study findings and sets out
the principal conclusions for the study.
821/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
2. Planning Context
2.1 Overview
This section reviews the relevant planning, policies and controls affecting both Old Wallgrove Road
and the Western Sydney Employment Area (WSEA). The review establishes the transport and land
use context in order to achieve the complex, interrelated aims of integrated land use and
transportation for the study.
2.2 Regional Context
Old Wallgrove Road is located within the Western Sydney Employment Area (WSEA)3, which is a key
component of the Metropolitan Plan for Sydney 2036.
The WSEA has been planned as an industrial zone / employment area to accommodate freight and
logistics-type industries and is identified as a key employment area within the Sydney Metropolitan
Strategy prepared in 2005. It encompasses 2,450 hectares spanning across four local government
areas – Penrith, Blacktown, Holroyd and Fairfield. The employment target is to accommodate up to
36,000 jobs.
The WSEA is comprised of ten precincts, as shown in Figure 4. These precincts have seen significant
development and growth in the past few years particularly after the opening of the Westlink M7
Motorway in December 2005. This growth has been forecast to continue over the next 20 years.
Figure 4 Precincts in the Western Sydney Employment Area
Source: NSW Department of Planning, 2008
3 The WSEA is also referred to in a number of planning documents as the Western Sydney Employment Hub (WSEH), or “The Hub”.
921/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Five of the ten precincts are relevant to the development of the Old Wallgrove Road corridor and are
concentrated in the Eastern Creek and Erskine Park areas. These precincts are bounded by the M4
Motorway on the north, the Westlink M7 Motorway on the east, Mamre Road on the west and the
Western Sydney Employment Lands Investigation Area to the south. The five precincts are either
under development or planned for significant growth in the short to medium term and consist of the
former Wonderland precinct, the Eastern Creek precinct, the Erskine Park Employment Area, the
Ropes Creek precinct and lands south of the Sydney Water Pipeline.
Figure 5 provides a spatial understanding of travel distances and spatial relationship between the
WSEA, regional cities and major centres, the major transport network and the planned North West
and South West Growth Centres.
Figure 5 Regional Catchment and Spatial Relationships
Source: GHD, 2011
The potential catchment for the subject employment lands apart from Blacktown and Penrith Local
Government Area (LGAs) includes:
South West and North West Growth Centres;
M4 and M7 Motorway traffic ; and
Parts of Liverpool, Fairfield and Holroyd LGAs.
All of these catchments are within 15 kilometres of the centre of the site and may attract movement to
the north, south and east of the WSEA.
2.3 Transport Context
Figure 6 shows the general location of the strategic road network proposed for the WSEA precincts.
The strategic road network concept plan to support the transport needs of the WSEA comprises of the
following elements:
Blacktown
Penrith
North WestGrowth Centre
ParramattaWSEA
South West Growth Centre
Liverpool
M7 Motorway
M5 Motorway
M4 Motorway
M2 Motorway
10 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Main east-west route linking Mamre Road with Old Wallgrove Road and the Westlink M7
interchange.
Two north-south link roads connecting Erskine Park Road and Old Wallgrove Road with lands
south of the Sydney Water Pipeline.
Northern access road linking with Archbold Road across the M4 Motorway and connecting with
the Great Western Highway, including a new interchange with the Western Motorway (M4)
provided with east-facing ramps.
Southern strategic road network running east to west and serving the planned employment
precinct situated south of the Sydney Water Pipeline.
These key elements of the road network particularly the role of Old Wallgrove Road will assist in
enhancing access to the WSEA and linkages to the adjoining road and Motorway network.
It is understood that the concept plan study considered a number of network options and modelling
scenarios. However, the investigation was undertaken at a high level and concentrated on general
corridor alignments against traffic, engineering, and environmental criteria. The individual road
components of the network are subject to separate approval processes, which will be informed by
more detailed assessment and investigation, including traffic modelling and studies covering specific
intersection treatment options. This study forms part of that process and is intended to contribute
towards intersection configurations and the concept design of OWR, to inform the REF processes.
Figure 6 SEPP Designated Strategic Road Network
Source: NSW Department of Planning and Infrastructure, 2008
11 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
2.4 Planning Policy Context
This section provides an overview of the strategic planning policies that influence transport planning
for the Western Sydney Employment Area and the Old Wallgrove Road corridor. It contains a review
of the relevant state and local council plans and policies as follows:
May 2004 announcement by the NSW Premier.
Metropolitan Strategy – City of Cities: A Plan for Sydney’s Future (NSW Government, 2005) and
its update, the Metropolitan Plan for Sydney 2036 (NSW Government, December 2010).
NSW State Plan 2010.
Draft North West Sub Regional Strategy (Department of Planning, 2007).
Erskine Park Link Road Network Concept Plan (NSW Roads and Traffic Authority, 2009)
State Environment Planning Policy (Western Sydney Employment Lands, 2009).
Guide to the Western Sydney Employment Lands (August 2009).
Erskine Park Link Road: Review of Environmental Factors (July 2010).
Southern Link Road Network Strategic Transport Assessment (Nov 2010 and April 2011).
Employment Lands Development Program (ELDP) 2010 Overview Report.
2.4.1 May 2004 Announcement
The Premier’s announcement (May 2004) indicated that land would be rezoned for employment and
to enable a road to be built to link Erskine Park Employment Area to the Westlink M7.
2.4.2 NSW Government’s Metropolitan Strategy City of Cities: A Plan for Sydney’s Future(2005)
The 2005 Sydney Metropolitan Strategy and the subsequent 2007 releases focused on rezoning and
network establishment through the creation of the SEPP (Western Sydney Employment Lands) and
the more detailed planning of the Western Sydney Employment Lands respectively. The 2007 release
identified development precincts, target number for jobs and broadly available developable lands. It
indicated that in the medium to long-term, the WSEA will be transformed from semi-rural into a major
hub for employment and economic activity. The area is predicted to be 2,450 hectares in size
(consisting of 1,521 hectares of existing zoning and 929 hectares newly zoned areas) and predicted
to provide up to 36,000 jobs.
2.4.3 Metropolitan Plan for Sydney 2036 (Dec 2010)
The Plan identified that the Department of Planning will prepare a structure plan for the broader
Western Sydney Employment Area (Strategic Direction E5.3). This will incorporate the former
Badgerys Creek Airport site; take into account of desired employment types and numbers,
infrastructure needs, development staging and appropriate governance and resourcing.
The structure plan was not available for this study. However, further development of lands to the
south is likely to impact on the study area, but is beyond the scope of this study.
12 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
2.4.4 NSW State Plan 2010
The NSW State Plan 2010 is the NSW Governments long-term plan for delivering services. It sets
priorities and targets in a number of areas that seek to guide government policy direction and
resource allocation. The first priority area is delivering better transport and liveable cities, which
covers targets on improving the public transport system, the road network, and road safety. It sets
clear objectives in areas to focus on, and identifies strategies to achieve objectives and targets.
2.4.5 Draft North West Sub Regional Strategy (2007)
Identifies specific actions and provides detailed information on employment types and developable
land targets. The employment growth breakdown identifies the potential of each employment precinct
in the Western Sydney Employment Area and indicates the following:
An employment type of Freight and Logistics within the Eastern Creek precinct, which has an area
of 703.6 hectares (including Lot 11):
Freight and Logistics/Manufacturing–Light, Manufacturing–Heavy in the Erskine Park precinct,
which has an area of 495.4 hectares; and
Under scheduled future industrial employment lands it identifies Ropes Creek precinct will provide
an additional 215.7 hectares of employment land.
2.4.6 Proposed Erskine Park Link Road Network Concept Plan (2009)
The Environment Assessment for the Proposed Erskine Park Link Road Network Concept Plan was
undertaken by the National Environmental Consulting Services on behalf of the NSW Roads and
Maritime Services (formerly known as the NSW Roads and Traffic Authority) in February 2008. This
plan was developed to support the planning work for the Western Sydney Employment Hub. The
document described the network and the network elements, including road design criteria,
intersections and interchanges, shared path and bus access needs, and implementation staging
requirements. Refer to Figure 7 and Figure 8 for an understanding of the approved Concept Plan for
the road network and shared path cycle connections.
13 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Figure 7 Modified EPLRN Concept Plan (2009)
Figure 8 Modified EPLRN Concept Plan for Cycling
14 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
2.4.7 State Environment Planning Policy (Western Sydney Employment Lands) 2009
Sets the planning instrument for the formation of development control plans to be prepared by Penrith
and Blacktown City Councils for the industrial release areas, and maps the strategic transport and
arterial road network for the area and land use zoning. In the mapping of the transport network, it
identifies the need for regional infrastructure including the Erskine Park Link Road, Old Wallgrove
Road and a southern east west link road south of the Sydney Water Pipeline, between Mamre Road
and Wallgrove Road (refer to Figure 6).
2.4.8 Guide to the Western Sydney Employment Lands (August 2009)
Supports the State Environment Planning Policy (SEPP) and provides clarification of the key facts
presented in the SEPP mapping, such as highlighting that:
The rezoning consists of lands for general industrial uses or protected for conservation purposes.
Ropes Creek and South of Sydney Water Pipeline are the new rezoned areas (826 hectares and
potentially 16,500 jobs) and will support the already zoned areas of Erskine Park and Eastern
Creek (1,400 hectares).
The need to establish the Erskine Park Road east west link road between Lenore Lane and Old
Wallgrove Road with a purpose of assisting to take industrial traffic off residential streets.
2.4.9 Erskine Park Link Road: Review of Environmental Factors (August 2010)
The purpose of the report was to define the project and appraise the environmental impacts of the
Erskine Park Link Road (3.1 kilometres long) between Lenore Lane to the West and Old Wallgrove
Road to the East. This road would support the WSEA and forms the western section of the east to
west Old Wallgrove Road corridor.
The assessment findings indicated:
Mini Link connection would need to be constructed by 2016;
Old Wallgrove Road would need to be widened to four lanes by 2016;
Four-lane carriageway on Erskine Park Link Road would be required by 2031;
The eastern two blocks of Old Wallgrove Road (west of the Mini Link to Wallgrove Road) would
have to be widened to six lanes by 2031; and
The current Wallgrove Road/Old Wallgrove Road intersection is required to be upgraded by 2016
with further upgrades by 2031.
2.4.10 Southern Link Road Network - Strategic Transport Assessment (April 2011)
The Southern Link Road Network Strategic Transport Assessment; Final Report was produced by
AECOM on behalf of the Department of Planning and the NSW Government. The study identified
opportunity and constraints for different corridor options and considered 2031 demand in the
formation of a preferred alignment for the southern link road network. The southern link road network
offers a key east-west route, running parallel to Old Wallgrove Road and forms part of the proposed
Erskine Park Link Road Network. This network will be required to support the employment area South
of the Sydney Water Pipeline and other investigation lands to the south.
15 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
2.5 Consistency with the EPLRN Concept Plan4
The proposal is generally consistent with the requirements of the Concept Plan. The only changes are
external to the road corridor and were included for modelling purposes. These nominated changes
were developed in consultation with NSW Government departments, Local Council and the operator
of the M7 Motorway. These changes under the 2021 future scenario included;
The downgrading of north-south section of Old Wallgrove Road and the inclusion of a new north-
south road link between the intersection of Archbold Road with Erskine Park Link Road and the
planned alignment of the Southern Road Link Network;
The inclusion of three traffic lanes in each direction on Old Wallgrove Road between Wallgrove
Road and Mini Link;
Banning of right turn movements from Wallgrove Road to Old Wallgrove Road; and
The inclusion of capacity improvements along Wallgrove Road and M7 Motorway approaches
(additional traffic lanes on approaches) to intersections with Old Wallgrove Road and Mini Link.
These additions are consistent with the EPLRN Concept Plan approval.
The proposal forms part of the east-west route of the EPLR Network and has been assessed in
accordance with the future requirements provided under the conditions of consent of the Concept
Plan Approval (refer to Section 2.4.6). The proposed Old Wallgrove Road (east-west section) upgrade
would extend to meet with the proposed Erskine Park Link Road in the west and provide additional
capacity enhancements and connectivity with the M7 Motorway and Wallgrove Road in the east. The
Old Wallgrove Road upgrade would be designed to cater for the development of new access roads,
including Mini Link and a new northern Southridge Road connection and have been included in this
assessment to meet 2021 traffic demand.
Old Wallgrove Road has been planned to provide appropriate connections to the external road
network in terms of supporting an efficient and safe flow of traffic within the EPLR Network. In this
context, the Concept Plan is generally consistent with the scope and intent of the concept plan and is
generally consistent with any strategic planning documents outlined in Section 2.
4 Environment Assessment - Proposed Erskine Parl Link Road Network Concept Plan, National Environmental Consulting Services, February 2008.
16 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
3. Existing Conditions
3.1 Overview
This section reviews the existing traffic, transport and land use conditions that influence the future
development of Old Wallgrove Road and WSEA.
3.2 Existing Land Uses
The current development status of Western Sydney Employment Area (WSEA) and its relationship
with Old Wallgrove Road is shown in Figure 9. In terms of regional positioning and its relationship with
Metropolitan Sydney (refer to Figure 5) it is located about (40 kilometres) west of Sydney Central
Business District and has good connectivity with the M7 and M4 Motorways, providing access to the
North West and South West Growth Centres along with Port Botany.
The existing land use in WSEA comprises of rural unused land recently zoned to accommodate
industrial-type land uses. These areas are interspersed with a mix of large-scale industrial and
warehouse distribution land uses (refer to Figure 9 for an understanding of footprint sizes).
Figure 9 Development Footprints and Location of the WSEA
Source: NSW Roads and Maritime Services and Department of Planning and Infrastructure, 2011
Former Wonderland
Precinct
M4 Motorway
Old Wallgrove
Road
17 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
A review of the study area identified the following significant existing land use developments
including:
Two brick making facilities (Austral and PGH) on Old Wallgrove Road.
A number of overhead transmission lines traversing the study area which converge on the
TransGrid Sydney West sub-station site on Old Wallgrove Road.
Large-scale industrial and warehouse distribution facilities along Old Wallgrove Road, Rousell
Road (Eastern Creek), the former Wonderland precinct, and in the Erskine Park Employment
Area.
3.3 Existing Transport Network
The road network surrounding the WSEA and their characteristics is shown in Figure 10.
Figure 10 Road Network Surrounding WSEA
Source: Google Maps, 2011
The road network surrounding WSEA serves several different functions and these are reviewed in the
M7 Motorway
M4 Motorway
Old Wallgrove Road
Wallgrove Road
18 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
following sections.
3.4 Travel Characteristics
The analysis of 2006 Journey-to-Work data was undertaken to develop an initial understanding of the
travel patterns in the region. This information has been used to develop a broad understanding of the
likely demand for different modes for the existing situation in order to check regional and/or external
travel movements in future horizon years 2021 and 2031 by the strategic model.
Figure 11 and Figure 12 show the mode shares for journey-to-work trips in Penrith and Blacktown
LGAs, respectively.
Figure 11 Journey to Work Mode Share (Penrith LGA)
Source: Journey to Work (2006), NSW Bureau of Transport Statistics
Figure 12 Journey to Work Mode Share (Blacktown LGA)
Source: Journey to Work (2006), NSW Bureau of Transport Statistics
The above figures indicate that car driver and car passenger are the predominant journey-to-work
modes, and together comprise more than 80 per cent of all work trips.
Figure 13 and Figure 14 indicate the origins of journey to work trips of workers in Penrith and Blacktown LGAs, respectively.
Train
4,368
7%
Bus
531
1%
Taxi
119
0%
Car, as driver
51,685
77%
Car, as passenger
5,195
8%
Truck
2,095
3%Motorbike /
motorscooter
418
1%Bicycle
303
0%
Other
393
1%
Walked only
1,614
2%
Train
9,911
10%
Bus
1,472
2%
Ferry
6
0%
Tram
13
0%
Taxi
323
0%
Car, as driver
70,354
74% Car, as passenger
8,016
8%
Truck
1,974
2%
Motorbike /
motorscooter
436
1%Bicycle
391
0%
Other
398
1%
Walked only
2,010
2%
19 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Figure 13 Origin of Employees Working (Penrith LGA)
Source: Journey to Work (2006), NSW Bureau of Transport Statistics
Figure 14 Origin of Employees Working (Blacktown LGA)
Source: Journey to Work (2006), NSW Bureau of Transport Statistics
Figure 15 and Figure 16 show the average trip durations for work and non-work trips to Penrith and Blacktown LGAs, respectively.
Figure 15 Average Travel Time per Trip Purpose (Penrith LGA)
Source: 2006 Census Data, Australian Bureau of Statistics
2%9%
12%
1% 1% 2% 4%1% 2% 1%
59%
2%
0%
10%
20%
30%
40%
50%
60%
70%
1% 1%
8%
45%
3%1% 1% 1%
3% 4% 3% 2% 2% 4%
14%
1% 1% 1%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
35
15
19 Average work trip duration
(mins)
Average non-work trip
duration (mins)
Average Trip duration - all
purposes (mins)
20 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Figure 16 Average Travel Time per Trip Purpose (Blacktown LGA)
Source: 2006 Census Data, Australian Bureau of Statistics
Trends presented in figures 11-14 highlight that about 45 per cent of workers in Blacktown and 59 per
cent in Penrith reside within the same LGA in which they work. Furthermore, there is continual
potential to restrict trip lengths with planned growth in these regions and this would align with the
Metropolitan Plan objectives for managing journey-to-work travel.
Figure 17 provides an understanding of car ownership levels for selected LGAs.
Figure 17 Car Ownership by LGA
Source: 2006 Census Data, Australian Bureau of Statistics
Current car ownership levels in Blacktown and Penrith and the level of service currently offered by
public transport to this largely green field site (taken from Erskine Park Link Road REF) with planned
large scale industrial development indicates that private vehicles will continue to be the primary mode
of travel in the short to medium term.
Further analysis of data contained in the 2006 Census indicated the following:
In 2006, 88 per cent of households within Penrith LGA had access to at least one motor vehicle.
55 per cent of households within Penrith LGA owned two or more cars, which is significantly
higher than the average figure for the Sydney statistical division (about 44 per cent).
In 2006, 85 per cent of households within Blacktown LGA had access to at least one motor
34
17
21Average work trip duration
(mins)
Average non-work trip
duration (mins)
Average Trip duration - all
purposes (mins)
72646
3879444091
25008
41637 40672
49798
34572
0
10000
20000
30000
40000
50000
60000
70000
80000
To
tal
Ca
rs
inLG
A
LGA Name
21 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
vehicle; and
48 per cent of households within Blacktown LGA owned two or more cars.
3.4.1 Classification of Roads
The classification of roads on the existing road network can be used as an indication of the functional
role each road plays with respect to the volume of traffic they should appropriately carry. RMS has
developed a set of road hierarchy classifications detailed in Table 1 indicating typical nominal
volumes expressed in terms of average annual daily traffic (AADT) serviced by various classes of
roads.
Table 1 Functional Classification of Roads
Type of Road Traffic Volume (vpd) Peak Hour Volume (vph)
Motorways/Freeways >15,000 >5,600
Arterial Road >15,000 1,500 – 5,600
Sub-Arterial Road 5,000 – 20,000 500 – 2,000
Collector Road 2,000 – 10,000 200 – 1,000
Local Road <2,000 0 – 200
Source: NSW Roads and Maritime Service (formerly NSW RTA), Road Design Guide and AMCORD
3.4.2 Old Wallgrove Road
Old Wallgrove Road performs the function of a collector road located in Eastern Creek, and connects
with Wallgrove Road and the Westlink M7 (southbound on- and off-ramps).
The carriageway is around 15 metres wide with two 3.5 metres wide traffic lanes in each direction
between Wallgrove Road and Capicure Road, and is around 7 metres wide with one 3.5 metres wide
traffic lane in each direction west of Capicure Road.
The posted speed limit on Old Wallgrove Road is 70 km/h and carries around 9,400 vehicles per day
(vpd).
22 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Old Wallgrove Road viewed westward from the Wallgrove Road intersection
3.4.3 Wallgrove Road
Wallgrove Road is a four lane, two way road which connects Elizabeth Drive and the Great Western
Highway. Wallgrove Road is classified as an arterial road and runs parallel to the M7 Motorway with
direct connections to both the M7 and M4 Motorways. The road is divided to the north of Old
Wallgrove Road and undivided running south of the Wallgrove Road-M7 Motorway intersection.
The speed limit on Wallgrove Road in the vicinity of Old Wallgrove Road intersection is 70 km/h and
carries around 30,000 vehicles per day.
Wallgrove Road viewed southward from the Wonderland Drive intersection
3.4.4 M4 Motorway
The M4 Motorway provides intra-regional links from Strathfield to Penrith and forms the main east-
west route across Sydney. It is an important freight corridor and has three lanes with a divided
carriageway near the M7 interchange.
23 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
The speed limit on the M4 Motorway in the vicinity of the Old Wallgrove Road study area is 100 km/h, and carries around 100,000 vehicles per day.
Westbound on the M4 Motorway - Source: http://www.ozroads.com.au/
3.4.5 Westlink M7 Motorway
The M7 Motorway is a high capacity road link of national significance and was built to accommodate
future traffic growth. The M7 Motorway provides a key western link between the M2 Motorway (to the
north) and the M5 Motorway (to the south). In the vicinity of the study area the M7 Motorway has four
traffic lanes with a divided carriageway and a major interchange at the M4 Motorway.
The speed limit on the M7 Motorway in the vicinity of the Old Wallgrove Road study area is 100 km/h,
and carries around 70,000 vehicles per day.
Westlink M7 Motorway viewed northward approaching the Old Wallgrove Road (southbound) ramps
24 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
3.4.6 Public Transport
Rail services
CityRail’s Western Line runs to the north of the WSEA, linking Penrith and Richmond with Sydney
CBD and the North Shore, running via Parramatta and Strathfield.
Rooty Hill and Mount Druitt stations along the Western Line are located some four kilometres to the
north of the WSEA. There are around six to eight services per hour to the CBD in the morning peak
serving Mount Druitt Station, and around four per hour to Penrith.
Bus services
Figure 18 provides an understanding of existing bus services serving the WSEA and operating in the
vicinity of Old Wallgrove Road and Wallgrove Road.
Figure 18 Current WSEA Bus Service Routes
Sources: http://www.busways.com.au and http://www.cdcbus.com.au
The information in Table 2 indicates the two bus routes provide two to three hourly services in the
weekday peak. Future growth will require a regular review of the adequacy of bus service provision, in
accordance with the Metropolitan Bus Service Planning Guidelines developed by the Department of
Transport.
25 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 2 Bus Services to Western Sydney Employment Area
Bus Route Number and Operator
Servicing Area Weekday Peak Frequency
Weekday Non-Peak Frequency
Weekend Frequency
779 (Westbus)
Mamre Road
(James Erskine Drive to Erskine Park Road)
AM:
30 Minutes
PM:
30 Minutes
AM
6:23 – 7:53 Inbound only
PM
3:40 – 5:10 Outbound only
N/A
Erskine Park Road
(Mamre Road to Lenore Lane)
AM:
30 Minutes
PM:
30 Minutes
AM
6:23 – 7:53 Inbound only
PM
3:40 – 5:10 Outbound only
N/A
738 (Busways)
Wallgrove Road
(Capicure Drive/ Old Wallgrove Rd to M4)
AM:
20 Minutes
PM:
20 Minutes
AM:
6:30 – 8:50 Inbound and Outbound
PM:
3:23 – 5:43
Inbound and Outbound
30 Minutes (4:50am
– 10am, 2:23pm – 7:23pm)
Inbound and Outbound
Wallgrove Road
(Horsley Park to M4)
N/A N/A 10:07 am Inbound and Outbound
2:14 pm Inbound and Outbound
Sources: http://www.busways.com.au and http://www.cdcbus.com.au
3.4.7 Pedestrian and Cycle Facilities
There are currently limited pedestrian facilities in the study area, due to the nature of current land
uses. Where pedestrian infrastructure has been provided, it is intermittent and does not allow for
continuous connectivity across the site. This is demonstrated at:
Wonderland Drive.
Southridge Street.
Capicure Drive.
Lenore Lane.
Signalised pedestrian crossing facilities at Wallgrove Road – M7 intersection and at the
Wonderland Drive – Wallgrove Road intersection.
There are a number of cycling facilities in the area, which includes:
An existing off road regional shared path travelling along the eastern side of M7 Motorway to the
south of Old Wallgrove Road and along the western side to the north; and
A short section of an off road cycle path situated on the western side of Wallgrove Road to the
south of Old Wallgrove Road.
26 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
The Erskine Park Link Road, which is currently under construction, incorporates a shared
pedestrian/cycle path that would run along the northern side of the corridor. This will provide links with
existing cycle facilities along Lenore Lane.
3.5 Existing Road Network Performance
3.5.1 Existing Traffic Volumes
Traffic volumes of the road system within this study area were derived from average daily traffic
volumes (ADT) counts, obtained from RMS and surveys undertaken for the study in February 2011.
Classified link counts were conducted from the 21 – 23 February 2011 at the following locations:
Wallgrove Road - Between M4 Motorway and Interchange Drive (North and Southbound).
Wallgrove Road - Between the Eastern Creek Waste Management Centre access road and the
Sydney Water Pipeline (North and Southbound).
Old Wallgrove Road – Between Capicure Drive and Wallgrove Road (West and Eastbound).
M7 Motorway – North and Southbound.
The location of the classified link counts is shown in Figure 19.
Figure 19 Link Count Locations
Source: Google Maps, 2011
Link Count Locations
27 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
A summary of traffic volume data is detailed in Table 3 below.
Table 3 Average Daily Traffic (ADT) Data – February 2011
Location ADT
M7 Motorway – North and Southbound 68,400
Wallgrove Road – Between M4 Motorway and Interchange Drive (North and Southbound) 30,600
Wallgrove Road – Between the Eastern Creek Waste Management Centre access road and the Sydney Water Pipeline (North and Southbound)
23,900
Old Wallgrove Road – Between Capicure Drive and Wallgrove Road (West and Eastbound) 9,400
Source: February 2011 M7 Motorway and GHD Traffic Volume Counts
At the time the traffic surveys were undertaken in February 2011, Capicure Drive was closed and
therefore typical daily traffic data could not be obtained for this road link.
The daily traffic volumes indicate that significant volumes are already accommodated on the M7
Motorway and Wallgrove Road. It also highlights that Old Wallgrove Road is carrying traffic volumes
that are close to its current functional classification hierarchy.
3.5.2 Existing Peak Hour Traffic
The traffic assessment undertaken for this study focuses on impacts during the AM and PM peak
periods, when demand for traffic capacity in the surrounding network is perceived to be at its highest.
The existing peak hour traffic volumes are outlined in Table 4.
Table 4 Peak Hour Traffic Volumes (2011)
Road Location Peak Total Vehicles
(two-way in veh/h*)
HCVs*(per cent)
Old Wallgrove Road West of Wallgrove Road AM (0800-0900) 694 39%
PM (1400-1500) 778 39%
M7 Access At Old Wallgrove Road AM (0700-0800) 4877 18%
PM (1700-1800) 4988 11%
Wallgrove Road North of Old Wallgrove Road AM (0800-0900) 2388 15%
PM (1700-1800) 2305 15%
Wallgrove Road South of Old Wallgrove Road AM (0700-0800) 1769 10%
PM (1700-1800) 2016 10%
Source: February 2011 GHD Traffic Volume Classification and Intersection Movement Count Data
* Note: HCV – Heavy & commercial vehicles and veh/h is measured as vehicles per hour.
The observed traffic volumes during peak periods indicates the surrounding road network and Old
28 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Wallgrove Road act as freight corridors for both local and regional traffic.
3.5.3 Travel Time
Travel time and delay surveys were obtained by the floating car method to assess the accuracy of the
microsimulation model to compare surveyed and modelled journey times along key routes in the study
area.
Three routes were covered using the floating car method:
Route One (1) – Old Wallgrove Road (at Sydney West Substation) to Wallgrove Road (at the
interchange with the M4 Motorway).
Route Two (2) – Wallgrove Road between Sydney Water Pipeline and M4 Motorway (at the
interchange with the Wallgrove Road).
Route Three (3) – M7 Motorway between Sydney Water Pipeline and M4 Motorway (at the
interchange).
The aforementioned routes are illustrated in Figure 20 below.
Figure 20 Travel Time Survey Routes
Source: Google Maps, 2011
Route 1
Route 2
Route 3
M4
Motorway
Sydney West
Substation
Sydney Water
Pipeline
29 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 5 Travel Time Survey Results (2011)
Route Direction Distance
(km)
AM Peak PM Peak
Run 1* Run 2* Run 1* Run 2*
1 Northbound 3.25 5m55s 5m08s 7m20s 9m06s
1 Southbound 3.25 5m20s 8m15s 3m40s 5m00s
2 Northbound 2.5 3m26s 4m07s 4m20s 3m25s
2 Southbound 2.5 3m15s 3m20s 3m00s 2m59s
3 Northbound 2.5 1m45s 1m53s 1m53s 1m50s
3 Southbound 2.5 1m49s 1m46s 1m53s 1m47s
Source: February 2011, GHD Typical Weekday AM and PM Peak Period Travel Time Surveys
*3m15s – represents three minutes and fifteen seconds
The survey results shown in Table 5 indicate that Wallgrove Road experiences delays in the
northbound direction in the PM Peak, which was identified by the survey team to be directly linked to
operational deficiencies at intersections with the M4 Motorway ramps. In the AM Peak, delays and
capacity issues were identified for the right turn into Old Wallgrove Road at the intersection with
Wallgrove Road for a proportion of the peak hour period. This intersection has been upgraded
recently to provide designated right turn lanes as part of the traffic management upgrade programme.
3.5.4 Assessment Criteria (Level of Service)
The performance of the existing road network is largely dependent on the operating performance of
key intersections that are critical capacity control points on the road network. The capacity of a road
network is generally governed by the operation of its intersections. It is therefore appropriate to
consider intersection operation as a measure of capacity of the road network.
The ‘Level of Service’ (or LoS) is the standard measure used to understand the operational
performance of the network and intersections. In general there are six levels of service from LoS A to
LoS F, with LoS A representing the best performance and LoS F the worst. For the purposes of this
study, an exceedance of LoS D will be used to determine the need for upgrading and/or mitigation.
The assessment of intersection operation is based on criteria outlined in Table 6, as defined by the
NSW Roads and Traffic Authority (Guide to Traffic Generating Developments, RTA 2002).
30 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 6 Level of Service Criteria for Intersections (RTA 2002)
Level of Service
Average Delay per Vehicle (secs/veh)
Traffic Signals, Roundabouts Give Way & Stop Signs
A < 14 Good operation Good operation
B 15 to 28 Good with acceptable delays & spare capacity
Acceptable delays & spare capacity
C 29 to 42 Satisfactory Satisfactory, but accident study required
D 43 to 56 Operating near capacity Near capacity & accident study required
E 57 to 70 At capacity; at signals, incidents will cause excessive delays
Roundabouts require other control modes
At capacity, requires other control mode
F > 70 Over Capacity Unstable operation
Over Capacity Unstable operation
Source: RTA Guide to Traffic Generating Developments (2002)
Notes: 1. The average delay assessed for signalised intersections is over all movements.
2. For roundabouts and priority control intersections (with Stop and Give Way signs or operating under the T-junction rule), the critical criterion for assessment is the movement with the highest delay per vehicle. Average delay is
expressed in seconds per vehicle.
3.5.5 Existing Intersection Operations
The capacity and Level of Service (LoS) analysis has been carried out for key intersections during
peak period conditions (AM and PM peak) using the SIDRA intersection model. SIDRA model
calculates capacities, queue lengths and delays for traffic signals, roundabouts and priority controlled
intersections.
Table 7 below presents the level of service, average vehicle delay and degree of saturation for the
subject intersections.
31 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 7 Existing Intersection Operations (2011)
Intersection AM Peak PM Peak
Average Delay
*LoS Control
Type Degree of Saturation
Average Delay*
LoS Control Type
Degree of Saturation
Wallgrove Rd–Wonderland Dr
26.2 B Signalised 0.857 12.5 A Signalised 0.755
Wallgrove Rd–Old Wallgrove Rd–M7 (NB)
45.7 D Signalised 1.129 16.3 B Signalised 0.825
Wallgrove Rd- M7 (SB) 21.4 B Signalised 0.564 23.4 B Signalised 0.587
Old Wallgrove Rd -Quarry Rd
17.3 B Priority 0.329 19.0 B Priority 0.237
Old Wallgrove Rd–Southridge St
43.7 D Priority 0.366 22.4 B Priority 0.520
Old Wallgrove Rd–Eastern Creek Dr
15.8 B Priority 0.199 12.1 A Priority 0.104
Old Wallgrove Rd–Roberts Rd
24.1 B Priority 0.175 13.8 A Priority 0.179
Source: Source: SIDRA Model Performance Outputs, GHD 2011.
Note: * Average delay is given in seconds per vehicle.
The results indicate that generally, all intersections are operating with a satisfactory level of service,
with the exception of the Wallgrove Road – Old Wallgrove Road – M7 Motorway intersection.
Refer to Appendix B for further detail on the performance of the above intersections under existing
conditions.
Traffic management improvements have been implemented recently to the intersection of Old
Wallgrove Road and Wallgrove Road to address historical operational and safety deficiencies. The
current intersection configuration is shown in Figure 21.
32 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Figure 21 Old Wallgrove Rd/ Wallgrove Rd Intersection Layout
Source: SIDRA Model Layout, GHD 2011.
3.6 Existing Road Safety Trends
The project will impact on the operations of Wallgrove Road, Old Wallgrove Road and surrounding
intersections. Historical crash data has been evaluated as part of this study to obtain an
understanding of current characteristics and trends.
3.6.1 Wallgrove Road
RMS Crash Analysis Section has supplied GHD with crash statistics for Wallgrove Road from 100
metres south of the Great Western Highway to the Sydney Water pipeline for the years 2005 – 2009
and is shown in Table 8. The crash data was used to determine the main factors contributing to
crashes along Old Wallgrove and Wallgrove Roads.
33 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 8 Crash History – Wallgrove Road (2005-2009)
Year Non-Injury Injury Fatal Total
2005 18 12 0 30
2006 15 21 0 36
2007 8 13 0 21
2008 13 22 0 35
2009 8 21 0 29
Total 62 89 0 151
Source: RMS Crash Data (2011)
The crash data reveals the following:
In total 151 crashes occurred along the surveyed section of Wallgrove Road over a five-year
period, which is an average of 0.08 per day or 30.2 per year.
59 per cent of the crashes resulted in an injury and there were no fatalities recorded.
87 per cent were multi-vehicle crashes.
81 per cent occurred on a weekday.
25 per cent occurred in wet conditions and 40 per cent in poor visibility or darkness.
Speed and fatigue were contributing factors in 15 per cent of the crashes.
58 per cent of crashes occurred at intersections with 39 per cent being rear end crashes and 17
per cent opposing vehicles turning.
The crash statistics indicate that a relatively higher number of crashes occurred at intersections and
involved a vehicle turning right colliding with a vehicle travelling in the opposite direction. The recent
upgrade of the Old Wallgrove Road with Wallgrove Road and the M7 Motorway intersection was
targeted at addressing this trend and related safety issues. The proposal will focus on providing
sufficient capacity and to adequately separate traffic flows so that growth is complimented by
appropriate network enhancements.
3.6.2 Old Wallgrove Road
RMS Crash Analysis Section has supplied GHD with crash statistics for Old Wallgrove Road for the
years 2007 – 2010 and is shown in Table 9.
34 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 9 Crash History – Old Wallgrove Road (2007-2010)
Year Non-Injury Injury Fatal Total
2007 0 1 0 1
2008 4 3 0 7
2009 1 5 0 6
2010 5 1 0 6
Total 10 10 0 20
Source: RMS Crash Data (2011)
The crash data reveals the following:
In total, 20 crashes occurred along the surveyed section of Old Wallgrove Road over a four-year
period, which is an average of 0.01 per day or 5 per year.
50 per cent of the crashes resulted in an injury and there were no fatalities recorded.
60 per cent on crashes occurred in a 70 km/h speed zone, 30 per cent in a 60 km/h speed zone
and 10 per cent in an 80 km/h speed zone.
95 per cent of crashes involved more than one vehicle and 45 per cent of crashes involved a
heavy vehicle.
90 per cent of crashes occurred on a weekday.
25 per cent of crashes occurred in wet conditions and 15 per cent in darkness.
85% of crashes occurred at intersections, including 35 per cent involving opposing vehicles
turning, 20 per cent of crashes on adjacent approaches and 10 per cent the result of rear-end
collisions.
40 per cent of crashes occurred during AM and PM peak periods.
The crash statistics indicate a relatively low crash rate along Old Wallgrove Road, with a high
proportion of crashes recorded involving the following characteristics:
Heavy vehicles;
Peak periods; and
Collisions at intersections.
The proposed upgrade Wallgrove Road to a divided dual-carriageway arrangement with signalised
intersections is expected to improve the traffic conditions that may be associated with the above
trends.
35 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
4. Traffic Model Development
4.1 Overview
Strategic traffic modelling of the surrounding regional road network is a core part of this study and is
used to assess the impacts of proposed land use developments in the Western Sydney Employment
Area, and determine infrastructure required to accommodate the expected growth in traffic on key
corridors, such as Old Wallgrove Road.
The modelling approach has been built on and is consistent with previous strategic modelling
undertaken by RMS. The RMS strategic model is developed in EMME software platform. This model
is updated regularly with the latest BTS land use data and trip tables, and is commonly accepted as a
reliable tool for estimating future traffic impacts from future development across the Sydney region.
RMS’s strategic EMME model was cordoned and the land use zoning system was refined, together
with updating existing and proposed network characteristics to allow the model to more accurately
derive performance needs related to the future growth in WSEA and planned upgrade of Old
Wallgrove Road and surrounding road links. This modelling approach will focus the model outputs on
understanding and identifying design solutions that can assist in managing the effects of increased
demand, altered traffic patterns and flows along the Old Wallgrove Road corridor.
The study has used a three-tiered modelling approach in the assessment of intersection
arrangements for Old Wallgrove Road. Modelling has been undertaken at the following levels:
Strategic modelling using a sub-area model in EMME;
Micro simulation model of the corridor using Paramics; and
Intersection modelling of key intersections using SIDRA.
The steps taken in developing and appraising the intersection designs and its performance are as
follows:
1. Land use assumptions and broader network changes modelled in the strategic model (EMME sub
area);
2. Paramics sub-area trip table extracted from strategic model and assigned on micro simulation
model (Paramics);
3. Micro simulation model adjusted to maximise flows;
4. Assigned flows from micro simulation model used as input flows for intersection modelling;
5. Signal settings derived from intersection model were input to the micro simulation model as a
cross check;
6. Intersection analysis and assessment was undertaken on the basis of average delays and
intersection Level of Service from SIDRA.
The three-tiered approach to modelling was undertaken in order to refine the strategic model traffic
assignment using micro simulation before extracting turning movement flows for use in detailed
intersection modelling.
The overall modelling process adopted for the study is broadly outlined in Figure 22 and details of the
calibration and validation of both sub-area strategic and microsimulation models are provided in
Appendix C.
36 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Figure 22 Modelling Approach
4.2 Future Land Use and Developable Areas
This section identifies land suitable for future growth within WSEA and Old Wallgrove Road study
area which is expected to be developed over the next 20 years. The information used in this appraisal
was confirmed for consistency purposes with previous NSW Government studies, Department of
Planning and Infrastructure (DoPI), and through discussions with RMS to establish and/or confirm the
latest future development area strategies for WSEA.
4.2.1 Precinct Planning Process and Land Use Assumptions
In order to overcome potential issues relating to traffic forecasts arising from discrepancies in land
uses, GHD undertook a high level spatial appraisal of land use and potential known constraints in
order to identify appropriate traffic generation estimates for WSEA.
This approach reviewed the distinction between employment precinct types, employment type,
intensity and location.
This appraisal was undertaken to provide a strategic understanding of the land use potential within
the WSEA for transport assessment purposes. The assessment was based on publicly available
information and data that have been identified through previous studies and through consultation with
project team stakeholders.
The overall objective of the spatial planning assessment was to identify an appropriate structure plan
for WSEA that would allow the project team to understand long term infrastructure needs and the
ultimate road network pattern. This was necessary as the structure plan for the area is still being
clarified.
37 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
The high level master plan identifying likely future land uses considered the development of
constraints such as those relating to natural terrain features, water channels, environmentally
sensitive areas, known conservation areas and requirements for corridor reservations for services.
The developable areas were then assessed in terms of opportunities for high exposure for land
development and transport access, and constraints such as environmentally sensitive areas and
corridor reservations. Considerations regarding urban design and market drivers were also applied to
arrive at a likely land use development scenario, shown in Figure 23.
Figure 23 Potential Precinct Density and Spatial Relationships
Source: Background Digital Data from NSW Department of Planning and Infrastructure (2008)
This is currently viewed as a long term vision for the planning of the area and will be further refined in future studies.
4.2.2 Developable Area Adopted for WSEA
In order to understand the worst case developable land scenario for the planned staged
implementation of the Western Sydney Employment Area (WSEA), the previously adopted RMS land
use areas for industrial uses were adopted. It should be acknowledged that these developable areas
are indicative only and may be subject to changes as the precinct plan develops and further detailed
investigations are conducted. A summary of land use areas are shown in Table 10 and are consistent
with land use data applied in previous studies and will be applied in the traffic modelling in order to
understand the potential network impacts.
Key Road Corridors
High Density Usage (i.e. Business Parks)
Low Density Usage (i.e. Warehousing)
38 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 10 WSEA Future land Use
Precinct Land Use Type
Developable Area (Hectares)
2021 2031
Eastern Creek Industrial 550 550
Ropes Creek Industrial 115 173
Erskine Park Employment Area
Industrial 326 326
Lands south of pipeline Industrial 270 507
Total 1261 1556
Source: RMS WSEA Traffic Generation Rates with pro rata adjustments for 2021
For the purposes of assessing the staged impacts from the proposed gradual development of WSEA
on Old Wallgrove Road, the following staging has been adopted:
100 per cent of developable lands for Eastern Creek are taken up in both 2021 and 2031.
67 per cent and 100 per cent of developable lands for Ropes Creek is taken up by 2021 and
2031, respectively.
100 per cent of developable lands for Erskine Park Employment Area are delivered in both 2021
and 2031.
53 per cent and 100 per cent of developable lands for lands south of the Sydney Water Pipeline
is taken up by 2021 and 2031, respectively.
In total, the traffic modelling for 2021 and 2031 has included 1115 or 1261 hectares and 1556
hectares for the WSEA, respectively.
4.3 Trip Generation
The trip generation rates for this study are consistent with that used on similar studies and based on
surveyed trip rates for existing WSEA development.
The following rates have previously been accepted by RMS, as well as Penrith and Blacktown
Councils:
Eastern Creek Precinct: 21 trips per hectare for two-hour peak period.
Ropes Creek Precinct: 10 trips per hectare for two-hour peak period.
Erskine Park Employment Area: 10 trips per hectare for two-hour peak period.
Lands south of Sydney Water Pipeline: 21 trips per hectare for two-hour peak period.
For the AM peak, it is also assumed that the directional split for new traffic will be 80 per cent inbound
and 20 per cent outbound. This directional split assumption has been reversed for the PM peak.
39 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 11 and Table 12 provide total trip rates for 2021 and 2031 AM and PM peaks, which are based
on the land use areas shown in Table 10 and trip generation rates presented in Section 4.3.
Table 11 Traffic Generation – 2021 AM (2 Hour Peak)
Precincts Developed Area (Hectares)
Per cent of Total Area
2-hour AM Peak Vehicle Trips
In Out Total
Eastern Creek Precinct 550 100% 9,240 2,310 11,550
Ropes Creek Precinct 115 67% 920 230 1,150
Erskine Park Employment
Area 326 100% 2,608 652 3,260
Lands South of Pipeline 270 53% 4,536 1,134 5,670
Total Area 1,261 81% 17,304 4,326 21,630
Source: RMS WSEA Traffic Generation Rates with pro rata adjustments for 2021
Table 12 Traffic Generation – 2031 AM (2 Hour Peak)
Precinct
Developed Area (Hectares)
Per cent of Total Area
2-hour AM Peak Vehicle Trips
In Out Total
Eastern Creek Precinct 550 100% 9,240 2,310 11,550
Ropes Creek Precinct 173 100% 1,384 346 1,730
Erskine Park Employment Area 326 100% 2,608 652 3,260
Lands south of Pipeline 507 100% 8,518 2,129 10,647
Total Area 1,556 100% 21,750 5,437 27,187
Source: RMS WSEA Traffic Generation Rates with pro rata adjustments for 2021
40 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
4.4 Future Road Network
4.4.1 Background
The effects of future planned road network proposals within the study area have been included within
the traffic modelling process. The future year road network used in the model followed the framework
of the arterial road network nominated in the State Environmental Planning Policy (Western Sydney
Employment Lands) and is shown in Figure 24.
Figure 24 SEPP Arterial Road Network (WSEA)
Source: Department of Planning and Infrastructure (2009)
Previous assessments undertaken by RMS and other studies within WSEA appear to have used
consistent 2021 and 2031 network configuration and capacity assumptions however, the alignment of
some internal road links sometimes differ from what is now present in the SEPP and used in study
modelling process.
4.4.2 Proposed Model Road Network
A review of the WSEA network assumptions indicated that the road network used in previous
assessments was broad and required further refinement to reflect expected WSEA network conditions
and traffic movement and flows along the Old Wallgrove Road corridor. In this regard, GHD
considered the following road network modifications:
Realignment of the North-South link road to form a four way intersection with the extended and
upgraded Archbold Road.
41 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Inclusion of Southern Link Road Network by 2031.
Develop the precinct collector road network in finer detail to capture and better understand
expected traffic movement and volumes along Old Wallgrove Road corridor relating to the
planned development of the precincts.
Left-in/Left-out arrangement for Capicure Drive at Mini Link Road.
All collector roads were assumed to be two-lane, two-way roads in the initial modelling runs until
performance deficiencies resulting in capacity upgrades are identified.
Proposed road network configurations for 2021 and 2031 were then developed by collating and
synthesising all previous planned road network enhancements. The future year road network,
adopted in the traffic modelling followed similar principles to those used in the RMS network model
assumptions.
The future year road networks for 2021 and 2031 are shown in Figure 25 and Figure 26 respectively.
Figure 25 2021 Old Wallgrove Rd Sub Area Model Network
Source: Sub Regional EMME Traffic Model Output
42 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Figure 26 2031 Old Wallgrove Rd Sub Area Model Network
Source: Sub Regional EMME Traffic Model Output
4.5 Strategic Traffic Modelling
This sub-section provides a brief summary of the sub-area model development undertaken in
developing strategic traffic flows within the Old Wallgrove Road Study Area.
4.5.1 Data Sources
Primary sources of data for development and calibration of the sub-area traffic model comprised:
Developable land use assumptions for WSEA from RMS and DoPI.
Travel demand matrices for 2021 from RMS’s EMME strategic model.
Various road and intersection counts undertaken by GHD and RMS.
Future road network planning information from RMS.
Journey time surveys undertaken for key road corridors.
Trip generation rates from RMS.
43
21/2
116
2/1
79
605
Old
Wa
llg
rov
e R
oa
d U
pg
rad
e (
Ro
bert
s R
oa
d -
M7 M
oto
rway)
Tra
ffic
and T
ransport
Report
Fig
ure
27
Mo
del
Co
vera
ge A
rea –
EM
ME
an
d P
ara
mic
s
Sourc
e: G
oo
gle
Ma
ps, 2
01
1
44 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
4.5.2 Initial Model Establishment
(i) Model Coverage
The strategic model prepared for this study covers the network between Wallgrove Road and the M7
Motorway including interchanges, between the Sydney Water Pipeline and the M4 Motorway, Mini
Link Road and the Old Wallgrove Road, as shown in Figure 27. It should be noted that the sub-area
EMME modelled area is significantly wider than that used for microsimulation modelling, so as to
enable EMME model to inform the microsimulation model of changes in traffic pattern.
(ii) Zoning System
A “fine grained” approach has been adopted for both the creation of the zoning system and the road
network to accommodate WSEA needs for planning capability that extends to the collector/distributor
road network in addition to the higher order road network.
The zoning system has also recognised the spatial sub-precincts that would need to be created within
the WSEA. The final sub-area zoning system includes 18 internal zones as shown in Figure 28.
Figure 28 Developable Areas and Sub-Precincts
(iii) Network Selection
The proposed road network discussed in Section 4.4.2 has been used to develop the 2021 and 2031
sub-area model road networks.
The detail of future road networks has taken into consideration the land use zoning system and roads
that could be used for inter-zonal travel. All roads that could provide an important connection between
zones have been included.
Erskine Park Employment Area (326 ha) Penrith LGA
Ropes Creek Precinct (190 ha) Blacktown LGA
Lands South of Sydney Water Pipeline (656 ha) Penrith LGA
Former Wonderland Precinct (81 ha) Blacktown LGA
Eastern Creek Precinct (500 ha) Blacktown LGA
Huntingwood Precinct Blacktown LGA
45 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
(iv) Modelled Period
The EMME sub-area model for the Old Wallgrove Road study area has been undertaken for the
critical two-hour AM (0700 – 0900) and PM (1600-1800) period for 2011, 2021 and 2031.
AM and PM peak time periods were determined from the appraisal of traffic volumes collected during
the daily link counts on the M7 Motorway, Wallgrove Road, Old Wallgrove Road and Capicure Drive
and peak period intersection counts undertaken at existing intersections situated along Wallgrove
Road and Old Wallgrove Road.
(v) Modelled Refinement
A meaningful cordon was developed and refined using data from RMS strategic traffic model. The
following model refinements were undertaken as part of the traffic modelling process:
Recoding the network within the study area in sufficient detail to enable turning flows at each
intersection along Old Wallgrove Road.
Splitting model zones to accommodate land use zoning and network connectivity that would
enable meaningful turning flows to be produced for each intersection along Old Wallgrove Road.
Network coding adjustments to better replicate observed link loadings and turning movements.
4.6 Microsimulation Modelling
The study includes microsimulation testing of planned corridor operations under 2021 AM and PM
peak period future operational scenarios and some preliminary testing for 2031. This modelling task is
intended to further refine the findings and demand predictions obtained from the strategic modelling
(EMME) assessment and detailed SIDRA intersection analysis (isolated intersections) that were used
to determine potential intersection configurations. The purpose of this microsimulation assessment is
to assess the proposed individual intersection designs as an integrated network to identify any
deficiencies that may not have been apparent when considering each intersection in isolation.
4.7 Approach to Traffic Forecasts and Assessments
It is anticipated future development within WSEA (refer to Section 4.2) will be completed by 2031.
Accordingly, the two horizon years have been chosen to be assessed are:
2021 - representing the REF assessment or near-term horizon, which is generally used to
indicate what is required in the medium term and its potential impact on the future performance
of the local and regional road network under predicted traffic loads.
2031 - representing a longer-term horizon, which assesses the ability of road infrastructure under
a full development scenario (preliminary model test runs for the purpose of testing broadly the
capacity of the corridor and for setting the corridor reservation boundaries).
46 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
5. Appraisal of Future Transport Impacts
5.1 Overview
This section examines the transport network impacts on Old Wallgrove Road and its surrounding road
network from predicted growth in the Western Sydney Employment Area (WSEA). In doing so, it
identifies appropriate midblock and intersection configurations that can be used to support the
concept design for upgrading Old Wallgrove Road. This assessment of traffic impacts focuses on
2021 future traffic volumes on Old Wallgrove Road and Mini Link, and uses a desired assessment
criterion to test the ability of the design, in terms of the performance of the strategic road network and
intersections situated along the proposal.
5.2 Development of Traffic Forecasts
The EMME strategic traffic model has been used to identify the demand and road capacity limitations
throughout the Old Wallgrove Road study area. As discussed in Section 4.5, a sub-area model has
been developed to understand traffic demand and growth across the road network and in particular
how this would impact on movement at each intersection along Old Wallgrove Road and Mini Link.
This information was used as traffic demand inputs to the micro level Paramics (for understanding
corridor operations) and SIDRA (determining performance) modelling, which are used to inform and
appraise of intersection configurations for 2021. All intersection layouts have been developed in
consultation with RMS.
The road network within the Old Wallgrove Road study area was developed for 2031 (ultimate
development scenario) using the sub-area traffic model, and then scaled back to examine the traffic
implications for 2021 (interim stage and focus of this REF). This process was undertaken in order to
understand what upgrades along Old Wallgrove Road are required and when, and to determine if the
future corridor reservation and configuration can cater for the longer term.
5.2.1 Testing of alternative Schemes
The following measures of effectiveness were used to assess the strategic merits of alternative
proposed solutions both in the medium and longer term against a defined reference case:
Travel distance (kilometres).
Travel time (hours).
Average trip length (kilometres).
Average speed (kilometres per hour).
Percentage of links with a Volume to Capacity Ratio (VCR) greater than 0.85.
Comparisons of measures of effectiveness were used to select an optimum design solution for the
configuration of Old Wallgrove Road. The results of the preferred design are reported in Section 5.5.2.
The chosen solutions for 2021 and the preliminary results for 2031 form the basis for reserving the
Old Wallgrove Road corridor.
47 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
5.3 Modelling Approach
The capacity and Level of Service (LoS) analysis along the Old Wallgrove Road corridor has been
carried out using SIDRA intersection models and the sub-area EMME model. The sub area model
was used for determining the performance of road links and understanding the operating conditions
across the entire study area road network.
SIDRA model was used for analysis of individual intersections controlled by traffic signals along Old
Wallgrove Road. The SIDRA intersection model is capable of predicting capacities limitations, queue
lengths and delays at critical intersections, which are determined through the optimisation of traffic
signal timings.
Given the complex nature of the road network at the eastern end of Old Wallgrove Road, RMS
requested that microsimulation modelling using PARAMICS be undertaken. This was completed to
further assess and understand corridor wide traffic operating conditions, and its impacts on localised
improvements within the study area.
5.4 Desired Levels of Service Criteria
The desired assessment criteria for road network planning for the Old Wallgrove Road study area
relate to:
Provision of an orderly and legible road network.
Provision of adequate capacity on the higher order road network to cater for predicted traffic.
Minimise impacts on the operation of adjacent Motorways (i.e. M4 and M7).
Minimise queue length spillback impacts along the Old Wallgrove Road and Wallgrove Road
corridors.
Provision of optimum intersection configurations accounting for physical constraints and land
ownership.
Provision for future bus priority measures along the Old Wallgrove Road corridor.
5.4.1 Link Level Performance
In assessing the adequacy of the road network to meet future demands, the concept of ‘Volume to
Capacity Ratios’ (VCR’s) have been adopted to provide an indication of acceptable operation of the
various parts of the study area road network.
In defining volume to capacity ratios for each link, peak hour assignments were compared with peak
hour capacities. Target maximum VCR’s were then set to ensure that the future road network
provided a level of service that would be acceptable. The targets are shown in Table 13.
.
48 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 13 Volume to Capacity Ratio Thresholds
Volume to Capacity Ratio Implications for Road Network Planning
0 to 0.85 (0.85 target) Satisfactory level of service
0.85 to 1.00 Need for intervention, approaching capacity.
1.00 to 1.10 At or over capacity with marked delays and constrained travel speeds
1.10 to 1.50 Exceeds capacity with substantial delays and heavily constrained travel
Source: Modified from AustRoads Guide to Traffic Management – Part 3 Traffic Studies and Analysis (2009)
Typical mid-block capacities provided by the EMME sub area traffic model for various road types are provided in Table 14.
Table 14 Capacity Thresholds for Links
Road Type Capacity (veh/hr/lane)
Motorway 2000
Arterial 1200
Collector 900
Source: RMS Strategic Modelling Outputs & AustRoads Guide to Traffic Management – Part 3 Traffic Studies and Analysis
(2009)
Note: veh/hr/lane represents the capacity of a traffic lane, which is measured by the number of vehicles per hour per traffic
lane.
Based on the above, the target maximum VCR of 0.85 has been adopted for the study. A VCR 0.85
will be the threshold criteria indicating a road requires widening.
5.4.2 Intersection Level Performance
The performance of a road network is largely dependent on the operating performance of key
intersections, which are critical capacity control points on the road network. The capacity of an urban
road network is generally governed by the operation of its intersections. It is therefore appropriate to
consider intersection operation as a measure of capacity of the road network.
The criteria for evaluating the operational performance of intersections is provided by the RTA ‘Guide
to Traffic Generating Developments, (2002)’ reproduced in Table 15. The criteria for evaluating the
operational performance of intersections is based on a qualitative measure (i.e. level of service),
which is applied to each average vehicle delay band. Then average vehicle delay is equated to a
corresponding LoS from A (best) and F (worst).
49 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 15 Level of Service Definitions
Level of Service Average Delay
(seconds per vehicle)
Traffic Signals
A Less than 14 Good operation
B 15 to 28 Good with acceptable delays and spare capacity
C 29 to 42 Satisfactory
D 43 to 56 Operating near capacity
E 57 to 70 At capacity; incidents will cause excessive delays
F Greater than 70 Over capacity, unstable operation, excessive queuing
Source: RTA Guide to Traffic Generating Developments (2002)
Based on the above, the Level of Service threshold for intersections of LoS D (or better) has been
adopted for the Old Wallgrove Road corridor for peak period conditions for future intersection
performance.
5.5 Future Road Network Performance
Testing of the future road network has been carried out by imposing additional traffic loads associated
with the development of WSEA onto the base case road network.
The purpose of this stage of the traffic modelling task was to investigate and identify the performance
of the network. In doing so, it provided an understanding of what road enhancements are required to
support future year traffic growth. The test case model runs were reviewed and the road network has
been refined based on the outcomes to ensure that the possible impacts in the future are minimal and
that the safe and efficient operation of the Old Wallgrove Road corridor is achieved. The modelling
approach has attempted to be consistent with that used in the development of the EPLRN, and where
assumptions have changed these have been identified and recorded in Section 2.5.
5.5.1 Volume to Capacity Ratios
Review of 2011 traffic conditions indicated that the Wallgrove Road study area road network performs
satisfactory with some isolated capacity constraints and delay experienced along Wallgrove Road at
the M4 and along the access ramps between the M4 and M7 Motorways. Future year road network
plots showing volume to capacity ratios were coded in accordance with the VCR limits shown in Table
13. Table 16 and Table 17 provide an understanding of link capacity deficiencies from applying 2021
and 2031 traffic demand along the base case model network.
50 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Table 16 Base Case: Road Link Performance (Year 2021)
VCR AM Peak PM Peak
0.85 – 1.0 M4 (EB) – East and West of Wallgrove Road
Wallgrove Road (SB) – North of M4 (WB) Off Ramps
M4 On Ramp (EB) - At Wallgrove Road
M4 Off Ramps (EB) – To Wallgrove Road
M7 Off Ramps (NB) – To M4 Eastbound
Wonderland Drive (WB) - At Wallgrove Road
Great Western Highway (EB)
M4 (WB) – East and West of Wallgrove Road
M4 Off Ramp (WB) – To M7
M7 (SB) – South of Old Wallgrove Road
Great Western Highway (WB) – East of M7
Wallgrove Road – Between M4 and Great Western Highway
1.0 – 1.10 M7 Off Ramp (SB) – to Old Wallgrove Road
M4 Off Ramp (WB) – to M7 (SB)
M7 On Ramps (SB) – At Old Wallgrove Road
M7 Off Ramp (NB) – To M4 (WB)
M4 On Ramp (EB) – At Wallgrove Road
Wallgrove Road (NB) – North of Interchange Drive
>1.10 M7 On Ramp (NB) – At Mini Link
M7 Off Ramp (NB) – To M4 (EB)
The results highlight that capacity improvements are required across the wider road network to
support the planned development of the WSEA. These capacity needs are mostly contained to
strategic road links to the east and north of WSEA in 2021 and are expanded to the west as the area
and region is further developed.
Table 17 Base Case: Road Link Performance (Year 2031)
VCR AM Peak PM Peak
0.85 – 1.0 M4 Off Ramps (EB) – To Wallgrove Road
M4 (WB) – West of Wallgrove Road
M7 (SB) – North of Great Western Highway
M7 (SB) – Between Old Wallgrove Road and M4
M7 (NB) – South of M4
Mamre Road (SB) – North of Erskine Park Road
Mamre Road (NB) – South of Bakers Lane
Wallgrove Road (NB) – South of Southern Link Road (Ferrers Road)
Wallgrove Road (SB) – Between Old Wallgrove Road and Wonderland Drive
Old Wallgrove Road (WB) – Between Southridge Road and Mini Link
M7 (NB) – North of Great Western Highway
M7 (SB) – South of M4
M7 (NB) – Between Old Wallgrove Road and M4
M4 (WB) – West of Wallgrove Road
Wallgrove Road – South of Mini Link
Wallgrove Road – Between Wonderland Drive and Interchange Drive
Old Wallgrove Road – Between Southridge Road and Mini Link
1.0 – 1.10 M4 (EB) – West of Wallgrove Road
M4 Off Ramps (EB & WB) – To M7 (SB)
M4 On Ramps (EB) – At Wallgrove Road
M4 Off Ramps (WB) – To M7 (SB)
M4 (WB) – West of M7
M4 Off Ramps (WB) – to M7 (SB)
Great Western Highway (WB) – East of M7
Wallgrove Road (NB) – Between M4 and Great
51 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
VCR AM Peak PM Peak
Great Western Highway (EB) – East of M7
Wallgrove Road (SB) – Between Great Western Highway and M4
Western Highway
Mamre Road (NB) – North of Erskine Park Road
Mamre Road (SB) – South of Bakers Lane
>1.10 M7 Off Ramps (NB)-To M4 (EB)
M7 Off Ramps (SB) - At Old Wallgrove Road
M4 (EB) – East of Wallgrove Road
Wallgrove Road (SB) – between Wonderland Drive and M4
M4 (WB) – East of M7
M4 On Ramps – From Wallgrove Road
M7 On Ramps (NB) – At Mini Link
M7 On Ramps (SB) – at Old Wallgrove Road
M7 off Ramps (NB) – To M4 (WB)
M7 Off Ramps (NB) – to M4 (EB)
Wallgrove Road (NB) – Between Interchange Drive and M4
The main road corridors affected by inadequate traffic carrying capacity for 2021 and 2031 include:
M7 Motorway (between the M4 Motorway and Old Wallgrove Road Interchanges).
M4 Motorway (near the vicinity of the M7 Interchange).
Wallgrove Road (between Great Western Highway and Old Wallgrove Road).
Old Wallgrove Road (between proposed Mini Link Road and Southridge Street).
5.5.2 Model Test Results
The EMME sub-area model was used to test the relative merits of introducing capacity enhancement
improvements along Wallgrove Road and the M7 Motorway. The results from this appraisal were
included as part of 2021 and 2031 model runs and measured in terms of the effectiveness of the
modelled network. The results of the assessment are summarised in Table 18 and Table 19.
Table 18 Measures of Effectiveness – AM Peak Model Runs
AM Peak Two Hour Period 2011 2021 2031
Total number of trips (vehicles) 50,376 64,595 78,848
Vehicle Kilometres Travelled (VKT) 169,847 299,915 367,852
Aggregate Travel Time (hours) 2,697 6,050 8,662
Average Travel Distance (km) 3.37 4.64 4.67
Average Speed (km/h) 63.0 49.6 42.5
Average Capacity Utilisation (%) 62.4% 56% 47%
Total Network link length (km): 125 135 149
52 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
AM Peak Two Hour Period 2011 2021 2031
% of link length with Measures V/C > 0.85 0.5% 13% 11%
% of link length with Measures V/C 0.40 - 0.84 8.9% 41% 34%
The above results indicate the following:
AM peak vehicle trips along the network increase by 28 per cent by 2021 and 55 per cent by
2031 in comparison to 2011 model forecast.
AM peak vehicle kilometres travelled along the network increase by 77 per cent by 2021 and 117
per cent by 2031 in comparison to 2011 model forecast. These increases relate to both regional
through traffic movements and the development of WSEA.
AM peak network travel times are increased and average vehicle speeds are reduced network
wide and is influenced by the estimated traffic volumes, travel distances and the provision of new
road capacity. In all cases an average speed of above 40 km/h is achieved.
Table 19 Measures of Effectiveness – PM Peak Model Runs
PM Peak Two Hour Period 2011 2021 2031
Total number of trips (vehicles) 50,654 65,283 79,596
Vehicle Kilometres Travelled (VKT) 168,504 302,697 371,447
Aggregate Travel Time (hours) 2,568 6,117 9,030
Average Travel Distance (km) 3.33 5 4.67
Average Speed (km/h) 65.6 50 41
Average Capacity Utilisation (%) 61.9% 56% 47%
Total Network link length (km): 125 135 149
% of link length with Measures V/C > 0.85
0% 16% 12%
% of link length with Measures V/C 0.40 - 0.84
8% 37% 36%
The above results indicate similar results to those presented for the AM peak.
5.6 Summary of key findings
The results from the performance analysis of critical road links under future traffic volumes are
summarised below:
53 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
Wallgrove Road presents capacity issues between Old Wallgrove Road and the M4 Motorway
during 2021 and 2031 peak periods.
Old Wallgrove Road needs to be widened at Wallgrove Road to cater for traffic demand pressures
from the M7 Motorway approaches by 2021.
Mini Link is required by 2021 under the predicted traffic demand and will allow Old Wallgrove
Road to operate as the primary eastern gateway for the WSEA from the M7 Motorway and
Wallgrove Road for the medium term.
Without the introduction of the Southern Link Road Network, the Mini Link Road functions as the
primary east-west road connection for traffic travelling to and from the WSEA and accommodates
traffic from the South East. The planned delivery of the Southern Link Road Network in 2031
results in Old Wallgrove Road traffic reducing between 2021 and 2031.
The M7 and M4 Motorway ramps and carriageways in the peak direction perform close to capacity
during both peaks by 2021, and this further declines as traffic increases in 2031. This situation is
noted to improve when road capacity improvements along Wallgrove Road and the M7 Motorway
are introduced.
Old Wallgrove Road Lane Configuration
Based on future link capacity performance for Old Wallgrove Road, the following enhancements have
been identified as being critical for ensuring that the road network operates efficiently (up to 2021):
The implementation of three traffic lanes in each direction between Wallgrove Road and Mini Link
with Quarry Road intersection by 2021.
The implementation of two traffic lanes in each direction between Mini Link with Quarry Road
intersection and the new Erskine Park Link Road by 2021.
The implementation of a new Mini Link road connection between the intersections of Old
Wallgrove Road with Quarry Road (in the north) and Wallgrove Road with the M7 Motorway
northbound carriageway on and off ramps (in the east) by 2021 with two traffic lanes in each
direction and a new limited movement intersection (left in and left out) with Capicure Drive.
The final mid-block road configuration for the proposed upgraded to the Old Wallgrove Road corridor
is shown in Figure 29.
54
21/2
116
2/1
79
605
Old
Wa
llg
rov
e R
oa
d U
pg
rad
e (
Ro
bert
s R
oa
d -
M7 M
oto
rway)
Tra
ffic
and T
ransport
Report
Fig
ure
29
Reco
mm
en
ded
Mid
-Blo
ck L
an
e C
on
fig
ura
tio
n
Sourc
e:
RM
S C
oncept
Desig
n a
nd S
patial D
ata
Set
55 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)Traffic and Transport Report
5.7 Future Intersection Performance (2021)
The future intersection performance of the Old Wallgrove Road corridor was analysed using the
SIDRA intersection model for peak period conditions (AM and PM peak) for horizon year 2021. The
analysis of the operating conditions was based on the intersection performance criteria previously
described in Section 5.4.2 and Table 15. The results of the analysis are summarised in Table 20 with
more detailed information provided in Appendix D.
The intersections modelled for the study area are shown in Figure 30.
Figure 30 Intersections Assessed
Source: Google Maps 2009
To facilitate future traffic loads that will be generated by the progressive development of land use
within WSEA, it will be necessary to upgrade the capacity of intersections. Figure 31 provides
proposed intersection layouts that can support the planned upgrade of Old Wallgrove Road, and are
deemed to be necessary to achieve a reasonable level of service and cater for expected volumes
over the next 10 years.
The preferred intersection configurations have been developed and tested during a series of
workshops, which was used to refine the design and account for operational performance, physical
constraints, future needs and constructability issues.
56
21/2
116
2/1
79
605
Old
Wa
llg
rov
e R
oa
d U
pg
rad
e (
Ro
bert
s R
oa
d -
M7 M
oto
rway)
Tra
ffic
and T
ransport
Report
Fig
ure
31
Year
2021 I
nte
rim
Sta
ge In
ters
ecti
on
Layo
uts
Wall
gro
ve R
oad
/Wo
nd
erl
an
d D
rive
Wall
gro
ve R
oad
/Old
Wallg
rove R
oad
(n
ort
hern
)
Wall
gro
ve
Ro
ad
/M7/M
ini L
ink
Ro
ad
(S
ou
thern
)
Old
Wallg
rove R
oad
/Qu
arr
y R
oad
/
Min
i L
ink
Ro
ad
Old
Wall
gro
ve R
oad
/Easte
rn C
reek D
rive
Old
Wall
gro
ve R
oad
/Ro
bert
s R
oad
Cap
icu
re D
rive/M
ini L
ink R
oad
Old
Wall
gro
ve R
oad
/So
uth
rid
ge S
treet
57 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
5.7.1 Year 2021 Intersection Performance and Configurations
Table 20 summarises the performance of preferred intersection layouts under 2021 traffic flows. The
intersection configuration details are shown in Figure 31 and the detailed results from SIDRA analysis
are provided in Appendix D.
Table 20 2021 Performance –Intersection Layout
Intersection
AM Peak PM Peak
Avg delay
(sec/veh)
Level of Service
Degree of Satn
Avg Delay
(sec/veh)
Level of Service
Degree of Satn
Wallgrove Rd-Wonderland Dr 20.6 B 0.829 10.8 A 0.783
Wallgrove Rd-Old Wallgrove Rd 32.3 C 0.833 24.5 B 0.726
Wallgrove Rd-M7 NB-Mini Link 52.6 D 1.004 42.7 D 0.839
Old Wallgrove Rd-Mini Link 50.5 D 0.976 41.9 C 0.975
Old Wallgrove Rd-Southridge St 26 B 1 41.8 C 1.004
Old Wallgrove Rd-Eastern Creek Dr 25.4 B 0.793 26.7 B 0.855
Old Wallgrove Rd-Roberts Rd 15.2 B 0.638 13.4 A 0.634
Note: Based on agreed intersection layout as per workshop between GHD, RMS and Road Design Contractor (AECOM) held 30 June 2011 and subsequent work undertaken as part of 2011/12 additional Traffic Modelling work and design
workshop for the upgrade of the eastern section of the Old Wallgrove Road corridor.
The results of the analysis in Table 20 indicate that all intersection configurations would operate
satisfactorily under future 2021 traffic loads generated by the staged development of land use within
WSEA.
5.7.2 2021 Peak Hour Paramics Corridor Operational Observations
Examination of 2021 corridor operations presented the following:
The inclusion of an additional northbound and southbound lane on Wallgrove Road between
Wonderland Drive and the M4 Interchange is warranted under the predicted 2021 demand to
serve northbound and southbound flows along Wallgrove Road.
Flows onto the M7 from Wallgrove Road, particularly on the northbound ramp reach their capacity
by 2021, such that queuing on this ramp frequently extends to the intersection, although not
blocking it. This suggests that this ramp will likely require widening to mitigate impacts it may have
on the surrounding network.
58 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
5.7.3 2031 Initial Findings
Initial results from the modelling assessments of demand under a 2031 future year scenario has
indicated that the future development of the Southern Link Road Network has the potential to reduce
traffic demand along the corridor.
The Southern Link Road Network is part of the EPLRN and forms a key east-west route across the
WSEA. The road alignment runs parallel and to the south of Old Wallgrove Road. This route has the
potential to provide an attractive alternative access route to Wallgrove Road and the M7 Motorway
from the employment area situated south of the Sydney Water Pipeline.
Based on planning undertaken to date it is likely that access to the north and east and the strategic
road network, such as the M7 (north) and M4 (east) Motorways would be via Wallgrove Road and has
the potential to impact in the future on the performance of Wallgrove Road intersections. These
findings are also reflected as part of the recent studies that have been undertaken to conform with the
granted conditions of approval for Erskine Park Link Road Network Concept Plan, i.e. Erskine Park
Link Road: Review of Environmental Factors (RMS, July 2010) and Southern Link Road Network
Strategic Transport Assessment (DoPI, April 2011).
Appraisal of the corridor undertaken to date based on 2031 traffic demand, indicates that the corridor
and intersection layouts can be modified to accommodate the predicted future demand and these
intersection layouts will be further appraised and refined as part of future studies.
5.8 Public Transport
5.8.1 State Plan Targets
The NSW State Plan 2010 sets targets and priorities for encouraging jobs to be situated within 30
minutes of travel and a shift towards more sustainable transport modes. These are presented in the
form of travel time and mode shift targets, and encouraging investment in improving public transport
services and networks, and supporting bus services through prioritising movement in congested
areas.
The WSEA offers the opportunity to increase the number of jobs closer to the rapidly growing
residential areas in Western Sydney, and at the same time, it would assist to achieve the State Plan
targets by supporting accessibility by planned public transport services and routes. There is an
identified opportunity to increase public transport services to the WSEA in the future. This would be
achieved through the provision of additional regional services that can help to better connect key
regional centres, growth centres and transport interchanges to this planned employment area.
5.8.2 Strategic Bus Corridors
A number of additional strategic bus corridors identified in the Metropolitan Transport Plan 2010
(Transport NSW, 2010) are planned to serve WSEA, as shown in Figure 32.
59 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
Figure 32 Strategic Bus Corridors
Source: Metropolitan Plan for Sydney 2036.
The Erskine Park Link Road Environmental Assessment indicated that the construction of this new
east west link road running across WSEA would provide an opportunity for extending existing bus
routes that currently serve WSEA. This includes bus route numbers 738, 739 and 779, which currently
offer services that run into or within proximity of WSEA from transport interchanges and centres at
Penrith, Mt Druitt, Rooty Hill and Blacktown.
Further to these bus service improvements, the development of Old Wallgrove Road in conjunction
with of Erskine Park Link Road provides an opportunity to introduce a strategic bus corridor that would
serve WSEA.
5.8.3 Regional Linkages
The WSEA is expected to play a significant role as a regional employment hub and should be planned
to maximise accessibility by public transport from adjacent residential areas and areas planned for
growth, such as Penrith LGA, Blacktown LGA, Fairfield LGA, the North West and South West Growth
Centres. In view of the above, it is recommended that the upgrade to Old Wallgrove Road has the
ability to accommodate bus priority measures at signalised intersections and plans the location of bus
stops on the departure side of the intersections. This will allow for bus priority to be implemented in
the future and would support the efficient movement of bus services as WSEA is further developed.
5.9 Freight Transport
The Metropolitan Plan for Sydney 2036 provides reference to potential transport planning
opportunities with the aim of reserving corridors for roads, public transport connectivity and rail
improvements. Funding for these schemes or the detailed arrangements or the alignment is not
identified and will be linked to the ability to achieve forecast growth targets in surrounding areas. An
example of potential schemes is shown in Figure 33, which identifies the WSEA (Number one in
Figure 33) as a significant freight industrial cluster and potential site for a proposed intermodal
60 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
terminal and freight rail link.
Figure 33 Planning of Employment Lands and Intermodal Terminals
Source: Metropolitan Plan for Sydney 2036.
Figure 33 indicates that there is potential in the future for a new freight link, which would run east and
provide connection with Wetherill Park and Villawood before linking in with the existing main line and
continuing on to Chullora, Enfield and Port Botany. Until this occurs, the road network should be
planned with sufficient capacity to accommodate anticipated freight movement within WSEA.
5.10 Active Transport
The design of the Erskine Park Link Road (EPLR) incorporates a shared path on the north side of the
road alignment, which would link to existing facilities on Lenore Lane and the local road network in St
Clair and Erskine Park. Figure 34 shows a segment of the Erskine Park Link Road alignment
indicating the location of the shared cycle/pedestrian path.
61 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
Figure 34 Erskine Park Link Road Shared Cycle/Pedestrian Path
Source: Erskine Park Link Road Community Update. (RTA, August 2010)
Review of the current status of existing and planned routes and infrastructure in Western Sydney and
was based on published information on Fairfield City Council, Blacktown City Council and NSW
Government (www.bicycleinfo.nsw.gov.au) websites. The only documented cycle route associated
with access to the WSEA from the east is identified in Figure 35.
Figure 35 M7 Motorway Shared Path Plan
Source: http://www.westlinkm7.com.au/maps.php
Planning associated with the upgrade of Old Wallgrove Road acknowledges and has taken into
consideration planned bike infrastructure and routes. It also acknowledges that the information
currently available for the planning of a new bike network that supports the future development of
WSEA is limited, and needs to take into consideration active transport requirements throughout this
planned employment and freight distribution hub. This should include connectivity to the local and
62 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
surrounding regional road networks via signalised intersections and pedestrian crossings. Future
connections could potentially include a possible future shared path connection along the western side
of Wallgrove Road to the Southern Link Road Network serving the employment precinct south of the
Sydney Water Pipeline and possibly beyond.
The NSW Bike Plan acknowledges under action 2.1 that the lead agency (the former Roads and
Traffic Authority) should consider parallel cycleways as part of rail construction and upgrade projects.
Based on this direction and other planned infrastructure for the area it is recommended that the
shared path on the north side of Erskine Park Link Road be extended to connect with the M7
Motorway regional cycleway along the Old Wallgrove Road alignment and that access to other
existing and planned regional links be achieved through the provision of a shared path on the south
west side of Mini Link. These new shared paths will be supported by appropriate signal controlled
crossings along the Old Wallgrove Road and Mini Link.
5.11 Construction Traffic Impacts
5.11.1 Overview
A construction traffic impact assessment has been undertaken to obtain an understanding of the likely
impacts from construction scheduling and sequencing.
The staging and sequencing of construction assumes that Old Wallgrove Road would be constructed
to connect Erskine Park Link Road with Wallgrove Road and involves upgrading the existing
intersections of Old Wallgrove Road with:
Roberts Road;
Eastern Creek Drive;
Southridge Street;
Mini Link/Quarry Road; and
Wallgrove Road.
It also includes the upgrading of the intersection of Wallgrove Road with the M7 Motorway NB and
new Mini Link.
The construction program for the entire project has not yet been finalised. However, an indicative
construction methodology was available which formed the basis of this preliminary construction traffic
assessment. The duration of the construction period is estimated to last 24 months.
At this point in time, the exact detail of the staging and sequencing is still to be confirmed and as a
result it is recommended that RMS undertake further assessments on the traffic impacts at key
intersections once further construction details become available.
The remainder of this report presents the likely impacts resulting from the likely staging and
sequencing of the Old Wallgrove Road, Mini Link and related Wallgrove Road enhancement works.
5.11.2 Potential Haulage Routes
Potential construction vehicle haulage routes would be via Old Wallgrove Road, Wallgrove Road and
the Motorway network or Great Western Highway. The completion of the Erskine Park Link Road,
which is currently under construction, would also provide an alternative construction access for Old
Wallgrove Road. Potential construction access routes to the site are shown in Figure 36.
63 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
Figure 36 Potential Construction Haulage Routes
Source: Erskine Park Link Road: Review of Environmental Factors (July 2010)
It is likely that a combination of haulage routes shown in Figure 36 would be used. The Old Wallgrove
Road project would generate extra truck movements along these routes. However, given that these
roads already carry high volumes of haulage vehicular traffic, it is not anticipated that the project
would have a high degree of impact above what is currently experienced. It is not known if local roads
would be required to be used for construction purposes, however if this occurs, pre-construction
condition surveys would be undertaken.
The movement of materials would be managed through the scheduling of deliveries and availability of
fleet, and would aim to minimise the number of haulage and delivery vehicles required. Earthworks
quantities would be balanced as far as practicable during detailed design to ensure that the transfer of
material along the external road network is minimised.
5.11.3 Proposed Working Hours
The construction workforce would vary depending on the phase of construction and associated
64 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
activities and includes both construction and design personnel. An on-site workforce of around 200
people is expected to be engaged at any given time during the construction period.
Construction would be undertaken during standard working hours which are assumed to be as
follows:
Monday to Friday: 7 am–6 pm.
Saturday: 8 am–1 pm.
Sunday and public holidays: No work.
It may be necessary to undertake night works to minimise disruption and disturbance to surrounding
land owners and businesses, which is deemed to be feasible given the current characteristics of the
land use and its distance from existing residential areas.
All night works would be undertaken in accordance with the RTA’s Environmental Noise Management
Manual (RTA 2001): Practice Note VII — Road works outside normal working hours.
5.11.4 Construction Traffic Operations
The main traffic generated through the construction phase would be from equipment and material
deliveries, such as:
Delivery of materials;
Spoil removal;
Delivery and removal of construction equipment and machinery; and
Movement of construction personnel, including contractors, site labour force and specialist
supervisory personnel.
Light Vehicle Traffic (Employee)
Light vehicle traffic generation would be associated with staff movements to the site. Staff would
comprise of project managers, various trades, and general construction staff. Over the full
construction period, the peak construction workforce is estimated to be around 200 people and
represents the worst case scenario in terms of vehicle movement impact on the AM or PM road
network. It is assumed the majority of the workforce would arrive between 6:30 am and 7:00 am and
depart generally between 5:00 pm and 5:30 pm. The workforce arrival and departure periods
represent the peak construction traffic generation periods. It is likely that the construction traffic
generation peak periods would occur outside the existing road network AM and PM peak hours.
Allowing for some vehicle sharing, it is expected that 184 daily two-way trips (assuming 1.1 people per
vehicle) would be generated by light vehicles during the peak period. Taking a conservative approach,
it is expected that up to 148 vehicle movements would be generated (assuming 80 per cent of the
workforce arrive during peak hours) during each of the morning and afternoon construction peak
arrival and departure periods.
During the construction traffic peak periods, the workforce traffic movements are likely to be
distributed based on a 100/0 arrival and departure split in the morning peak period, and the reverse
during the afternoon peak period.
Heavy Vehicle Traffic
Heavy vehicle traffic would mainly be generated by activities associated with the removal of
excavated material, delivery of construction equipment and delivery of material for construction works.
Where possible, the proposal has been designed to achieve an overall balance of earthworks, which
65 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
minimises excess spoil and/or the need to import large quantities of fill. The current design would
produce a total material deficiency of up to around 28,000 m3. Current planning indicates that 15,000
m3, or 35 per cent of the total 43,000 m
3 material calculated to be required as fill, will be taken from
other parts of the corridor.
The number of trucks is dependent on site operations and travelling distance required to obtain
materials that will be used as fill for the project. It is anticipated under a worst case scenario that 3
trucks with a 20 tonne holding capacity would be required per day to deliver 28,000 m3
of material,
which would take on average about 132 working days. In addition, 1 truck with a 20 tonne holding
capacity would be required to re-distribute 15,000 m3 of excess material to other project site locations.
The following assumptions have been made in order to determine heavy vehicle movements along
the Old Wallgrove Road corridor under a worst case scenario:
Construction will occur over a six month period (i.e. for bulk earthworks), with 22 working days
apportioned for each month.
10 hour working days excluding breaks.
100 minute turn-around cycle time for off-site movements, allowing for breaks and hold-ups.
30 minute turn-around cycle time for on-site movements, allowing for breaks and hold-ups.
Each truck has a carrying capacity of 20 tonne.
It is anticipated that a fleet of four trucks is likely to be required to achieve the construction program
targets. This is based on the above worst-case scenario assumptions which estimate that some 31
truck cycles, or 62 individual trips per day are likely to be generated along Old Wallgrove Road. These
are expected to be evenly distributed throughout the working day at an average of seven trips per
hour.
Table 21 Heavy Vehicle Traffic Generation
FillMaterial
(m3)
Fill Material (to
be distributed to other site locations)
(m3)
On-Site/Off-
Sitemovement
Cycle Time
(mins)
Truck Cycles/
Average Working
Day/Truck
Trucks Required
Truck
Movements Required Per
Day
(Two-Way)
Potential
Truck Movements
Per Day
(One-Way)
28,000 Off-Site 100 5 3 15 30
15000 On-Site 30 16 1 16 32
Total 4 31 62
Summary of Construction Traffic Generation
For the proposed works the construction traffic generation is summarised in Table 22. It should be
noted that in traffic terms it has been assumed each truck is equivalent to two Passenger Car Units
(PCU’s). Truck haulage to and from Old Wallgrove Road study area has been calculated to equate to
124 PCU equivalent trips per day or 13 car equivalent trips per hour.
66 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
Table 22 Summary of Peak Construction Traffic Activity
Vehicle Movements Daily Movements Estimated Peak Hour Volume (vehicles)
Inbound Outbound
Light Vehicles 184 vehicle movements per day
148 148
Heavy vehicles 62 truck movements per day 5 2
Total 153 150
5.11.5 Impacts on Existing Developments
One of the more significant impacts from the construction of Old Wallgrove Road project is the
disruption to existing developments that use Old Wallgrove Road for access. Consideration will need
to be given to the staging of works as part of the planned 24 month construction program and strategy
developed to minimise impacts as part of the detailed design stage.
5.11.6 Construction Mitigation Measures
The following proposed traffic management principles would be adopted during construction:
Traffic control would need to be provided to manage and regulate traffic movements during
construction.
Disruption to all road users during construction would be kept to a minimum.
In most cases property access would be maintained throughout the construction period and if this
cannot be achieved, then suitable alternative access arrangements will be provided.
Construction and delivery vehicles entering or leaving the site compound and/or stockpile sites
would use Wallgrove Road, Old Wallgrove Road, Lenore Lane and Erskine Park Link Road
under traffic control. These movements would be restricted to non-peak traffic periods.
5.12 Cumulative Impacts
Cumulative impacts would occur as a result of current and planned continuous development of
industrial and commercial uses in the WSEA, as well as the future upgrades to the Old Wallgrove
Road corridor and other associated road links. From a traffic and transport prospective, this change
would be typical of areas planned for urbanisation to industrial and employment uses. In this regard,
the traffic composition associated with construction activity is unlikely to differ from that generated by
current or future users of the road network in and around this part of the WSEA.
The operational performance modelling of the Old Wallgrove Road network takes into account the
known cumulative impacts from the development of WSEA and the likely growth in regional traffic
along the strategic road network surrounding the project. These impacts are detailed in Section 4.2
(proposed land use and staging), 4.4 (future network), and 5.5 to 5.10 (network performance and
infrastructure provision).
The Old Wallgrove Road corridor is directly connected to the strategic road network via Wallgrove
Road and the M7 Motorway and activity associated with its upgrade are unlikely to have a detrimental
effect on more sensitive land uses beyond what currently fronts the corridor. It is acknowledged that
the upgrade to intersections along Wallgrove Road will have to be managed with consideration and
attention to maintaining safety and efficient traffic flow during peak periods. The impacts from
67 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
construction will be managed through a construction traffic management plan, which is further
discussed in Section 5.11.6.
The cumulative impacts associated with future development of WSEA, the EPLRN and the
employment area to the south of the Sydney Water Pipeline have been acknowledged in this
assessment with the adoption of network changes as highlighted in Section 2.4.10. This study has
broadly accounted for the capacity needs for a future 2031 scenario, however, the detail associated
with the configuration of future network and its likely development impacts beyond 2021 will be further
assessed as part of future studies.
5.13 Mitigation Measures
Mitigation measures associated with the construction phase of the project are addressed in Section
5.11.6. These impacts should also take into consideration the potential cumulative impacts from the
staged development of WSEA and the opening of roads that are connected or planned to be
connected to the Old Wallgrove Road corridor in the future. Particular focus should be given to the
opening of Erskine Park Link Road and the impact on Old Wallgrove Road upgrade construction
activity, pedestrian and cyclists and access from existing local roads. This will be addressed as part
of the detailed design for the upgrade of Old Wallgrove Road and its supporting construction planning
stages.
An understanding of network performance in 2021 has been provided in sections 5.6 and 5.7, and
account for the cumulative impacts from growth in regional traffic and the staged development of
WSEA. The findings indicate that the mid-block road configuration for Old Wallgrove Road and Mini
Link shown in Figure 29 and the intersection configurations shown in Figure 31 are required to be
introduced when opening the corridor to traffic and will allow for predicted 2021 traffic demand.
More localised improvements have also been identified along Old Wallgrove Road (east), including
the banning of the right turn from Old Wallgrove Road to Wallgrove Road (south). This restriction in
movement is required to improve the operation of the intersection of Old Wallgrove Road and
Wallgrove Road, and would be supported by traffic management and signage that will direct traffic
along the new Mini Link connection to access areas to the south. Appropriate directional signage is
recommended to encourage a right turn movement along Mini Link from Old Wallgrove Road (west).
In addition, the intersection of Old Wallgrove Road with Wallgrove Road and M7 Motorway would be
designed to allow for the possible future introduction of this right turn movement, if it is deemed to be
required in the future.
Appraisal of the wider network has also indicated that external road network improvements will be
required to maintain traffic flow and minimise delay across the regional network. A failure to improve
the network in the longer term may have implications on access to and from the Old Wallgrove Road
corridor in the longer term (after 2021). It is recommended that all improvements identified in Section
6.3 are incorporated in the proposed design for the upgrade of Old Wallgrove Road.
68 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
6. Summary and Conclusions
6.1 Overview
This traffic modelling study has examined a wide range of issues in a complex land use and transport
planning environment. The purpose of the study was to assess the road corridor requirements for
upgrading Old Wallgrove Road and identify possible improvements required to surrounding
infrastructure. It is acknowledged that the need for improvements along the corridor and its supporting
strategic road and Motorway network is directly linked to accommodating additional travel demands
generated by the development of the Western Sydney Employment Area (WSEA), continued growth
in regional background traffic and a change in travel patterns linked to the opening of a new east-west
corridor.
From a traffic and transport point of view, the study has sought to address the following key issues:
Understand broader land use and transport context to ensure a coordinated and efficient
approach to land use planning, environmental management and transport infrastructure
investment is taken.
Assess existing traffic conditions along the surrounding road network and identify road network
performance, road capacity and safety measures.
Estimate future strategic traffic volumes for both Old Wallgrove Road and the wider road network
and provide an understanding of the likely re-routing and network performance impacts.
Assess the transportation impacts from the staged delivery of land use and road infrastructure
improvements within the Western Sydney Employment Area (WSEA).
Understand the potential impact from the introduction of different land use densities, types and
development patterns.
Develop preferred intersection layouts for Old Wallgrove Road that can serve the ultimate
development of WSEA, support regional transport network operations and maximise future
accessibility.
Develop a staged approach for the upgrade of Old Wallgrove Road with an aim of balancing short
term needs and sustainable longer term objectives in the delivery of sustainable transport network
upgrades.
Provide a design that supports the use of public transport, cycling and walking and helps NSW
Government achieve broader strategic planning objectives through better integration of land use
and transport.
6.2 Key Findings
The study adopted worst case scenario WSEA traffic generation rates and applied these in the
evaluations of future regional road network operations. The key findings from this Traffic Study can be
summarised as follows:
There is a need for capacity enhancements on the M4 Motorway, the M7 Motorway and Wallgrove
Road in the future, which impacts on the arrival patterns of traffic to WSEA and the efficient
operation of the network as a whole.
The capacity assessment indicates that the mid-block lane configuration for Old Wallgrove Road
and Mini Link would require:
69 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
– Three lanes per direction along Old Wallgrove Road between Wallgrove Rd and Mini Link to
cater for 2021 traffic demand.
– Old Wallgrove Road west of the Mini Link with Quarry Road intersection would require two
traffic lanes in each direction for 2021 traffic demand.
– The entire length of Mini Link is required to be two traffic lanes in each direction for 2021
traffic demand.
2021 future year intersection layouts align with the mid-block configuration and were
demonstrated to perform satisfactorily under peak operating conditions.
The development of the 2021 corridor arrangement and intersections should consider the ultimate
stage corridor spatial requirements and reserve land and configure carriageway to support future
upgrades.
The network experiences significant growth in traffic along Wallgrove Road and M7 Motorway
near the interchange with Old Wallgrove Road.
The review of long term project needs under a 2031 future year modelling scenario highlights:
There is a need for capacity enhancements on the M4 Motorway, M7 Motorway and Wallgrove
Road corridors.
Additional land to the South of WSEA could potentially be developed beyond 2031 and is the
subject of current investigation by the DoPI.
The Metropolitan Plan indicates long term plans to develop a strategic bus network that would link
the WSEA with regional cities and the planned North-West and South-West Growth Centres.
In order to safeguard for the future provision of bus priority facilities, and account for associated
localised widening at intersection approaches, it is preferable to reserve as part of the ultimate
design a continuous three-lane carriageway configuration in both directions throughout the entire
stretch of Old Wallgrove Road between Wallgrove Road and Roberts Road.
The introduction of the Southern Link Road Strategic Network changes traffic levels on Wallgrove
Road and M7 Motorway at Old Wallgrove Road.
6.3 Recommendations
6.3.1 Project Mid-Block Configuration
Based on the traffic assessment findings, it is recommended that the following road design
requirements are adopted:
The implementation of three traffic lanes in each direction between Wallgrove Road and Mini Link
/ Quarry Road intersection by the Year 2021.
The implementation of two traffic lanes in each direction between Mini Link/Quarry Road and
Erskine Park Link Road by the Year 2021.
The upgrading of Old Wallgrove Road between Mini Link Road and Southridge Street from two
traffic lanes in each direction in 2021 to a dual three lane traffic configuration with turning lanes by
2031 (refer to Figure 29).
The construction of a new road link (Mini Link) between the intersection of Old Wallgrove Road
with Quarry Road in the north and Wallgrove Road and the M7 Motorway northbound on-ramps
and off-ramps in the east.
70 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
The Old Wallgrove Road concept design provides an allowance for a continuous three traffic lane
configuration in each direction between Mini Link and Erskine Park Link Road intersections. This
supports any future redevelopment or expansion of the WSEA, as well as accommodating identified
future road based public transport enhancements.
6.3.2 Intersection Layouts
The recommended intersection layouts for the future year 2021 assessment are as shown in
Appendix A. Initial modelling for the 2031 future year scenario has indicated that all intersections can
operate satisfactory with capacity enhancements and widening within the reserved corridor footprint.
6.3.3 Regional Network
The EMME strategic modelling identified the potential need for road capacity enhancements at:
M4 Motorway westbound and eastbound at the M7 Motorway with Wallgrove Road Interchange.
M7 Motorway northbound and southbound between M4 Motorway and Old Wallgrove Road
interchanges.
Wallgrove Road northbound and southbound between the Great Western highway and the
Southern Road Link Network.
Mamre Road north of Erskine Park Road and south of Bakers Lane.
The PARAMICS microsimulation modelling highlights potential corridor operational capacity
deficiencies at:
M4 Motorway westbound off-ramp to southbound Wallgrove Road.
Wallgrove Road Southbound between M4 Motorway Interchange and Wonderland Drive.
M7 Motorway northbound ramps (on-ramp and off-ramp) at the intersection of Wallgrove Road
and Mini Link.
This will be subject to further investigation and a separate project and environmental assessment
process.
6.3.4 Traffic Management
It is recommended due to the planned speed environment, estimated traffic volumes, previously
identified crash history, and characteristics of the traffic likely to be generated by the WSEA that:
All intersections are signalised with appropriate turning bay provision and signal phasing; and
Direct private access driveways on Old Wallgrove Road are removed and redirected to the WSEA
local road network.
6.3.5 Bus Priority Measures
The State Plan targets increasing journey to work travel mode share on public transport and reducing
dependency on private cars. The design of the Old Wallgrove Road corridor considers this need and
has allowed for the future provision of a strategic bus corridor and more frequent bus services in the
Western Sydney Employment Area.
It is recommended that the concept and detailed design for the upgrade of Old Wallgrove Road takes
into account the opportunity to provide bus priority measures at intersections, such as bus queue
jumps, and considers this as part of developing the detailed design.
71 21/21162/179605 Old Wallgrove Road Upgrade (Roberts Road - M7 Motorway)
Traffic and Transport Report
6.3.6 Shared Cycle/Pedestrian path
It is recommended that the design provides appropriate design provision to connect the planned
shared cycle/pedestrian path on the north side of Erskine Park Link Road with the regional cycle
facility along the M7 Motorway and planned DCP local connection within Eastern Creek. It is also
recognised that the southern side of Mini Link will offer a parallel shared path route as part of the
proposed upgrade works, which will be integrated with the existing shared path facility situated on
Wallgrove Road – M7 Motorway. These proposed design improvements will include appropriate
crossing facilities to offer attractive and safe link across proposed signalised intersections across the
Old Wallgrove Road corridor, as shown in the concept design.
6.3.7 Freight Movement
It is recommended that the design provides appropriate provision to allow for future enhancements in
heavy vehicle technology and increases in vehicle sizes. This should be concentrated on moving
trucks towards strategic regional Motorway corridors such as the M4 and M7.
6.3.8 Construction Traffic
The assessment of the additional traffic demand as a consequence of construction works indicate that
it would be modest when distributed on the surrounding road network and would not result in any
adverse effects on operational performance of key intersections.
Traffic management issues would need to be addressed with the preparation of a Traffic Management
Plan (TMP), which will be advanced as part of the construction staging package in the detailed design
project phase. This will require a number of mitigation measures to be implemented to ensure that
traffic impacts arising from construction activities are minimised. These additional measures may
include:
The installation of general warning signposting along Old Wallgrove Road and Wallgrove Road
on approaches to construction sites and activities. These will identify the change in operating
conditions and warn road users to observe construction related heavy vehicle movement and
changes in speed controls.
Development of suitable vehicle detour routes (if required) during specific construction activities.
Installation of specific warning signs at entrances to the construction site to warn existing road
users of entering and exiting construction traffic.
Installation of appropriate traffic control and warning signs for areas identified to have potential
safety risks.
Management of the transportation of construction materials to maximise operational efficiencies
and minimise heavy vehicle movements.