open access - home - southwest power pool · web view20.3 refund obligation for unfinished facility...

923
Southwest Power Pool FERC Electric Tariff Fourth Revised Volume No. 1 OPEN ACCESS TRANSMISSION TARIFF FOR SERVICE OFFERED BY SOUTHWEST POWER POOL The following sheets reflect all revisions approved by FERC in orders issued through October 1, 2004, and all revisions from compliance filings submitted through November 1, 2004. Issued by: L. Patrick Bourne, Manager Transmission and Regulatory Policy Issued on: October 27, 2000 Effective: November 1, 2000

Upload: others

Post on 24-Apr-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Southwest Power PoolFERC Electric TariffFourth Revised Volume No. 1

OPEN ACCESS

TRANSMISSION TARIFF

FOR SERVICE OFFERED BY

SOUTHWEST POWER POOL

The following sheets reflect all revisions approved by FERC in orders issued through October 1, 2004, and all revisions from compliance filings submitted through November 1, 2004.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 1FERC Electric TariffFourth Revised Volume No. 1

TABLE OF CONTENTS

I. COMMON SERVICE PROVISIONS.....................................................................................................................................71 Definitions....................................................................................................................................................71.1 Ancillary Services........................................................................................................................................71.2 Annual Transmission Cost...........................................................................................................................71.3 Application...................................................................................................................................................71.3a Attachment Facilities...................................................................................................................................71.4 Commission.................................................................................................................................................71.5 Completed Application................................................................................................................................71.6 Control Area.................................................................................................................................................71.7 Curtailment..................................................................................................................................................81.8 Delivering Party...........................................................................................................................................81.9 Designated Agent.........................................................................................................................................81.10 Direct Assignment Facilities........................................................................................................................81.10a Effective Date..............................................................................................................................................81.11 Eligible Customer........................................................................................................................................91.12 Facilities Study.............................................................................................................................................91.12a Feasibility Study........................................................................................................................................101.12b Federal Power............................................................................................................................................101.13 Firm Point-To-Point Transmission Service...............................................................................................101.13a Generation Interconnection Customer.......................................................................................................101.13b Generation Interconnection Request..........................................................................................................101.14 Good Utility Practice.................................................................................................................................101.14a Grandfathered Agreements or Transactions..............................................................................................111.15 Interruption................................................................................................................................................111.16 Load Ratio Share........................................................................................................................................121.17 Load Shedding...........................................................................................................................................121.18 Long-Term Firm Point-To-Point Transmission Service............................................................................121.18a Member......................................................................................................................................................121.19 Native Load Customers..............................................................................................................................121.20 Network Customer.....................................................................................................................................121.21 Network Integration Transmission Service...............................................................................................121.22 Network Load............................................................................................................................................131.23 Network Operating Agreement..................................................................................................................131.24 Reserved.....................................................................................................................................................131.25 Network Resource......................................................................................................................................131.26 Network Upgrades.....................................................................................................................................131.26a Next-Hour-Market Service.....................................................................................................................13A1.27 Non-Firm Point-To-Point Transmission Service.......................................................................................141.28 Open Access Same-Time Information System (OASIS)...........................................................................141.29 Part I...........................................................................................................................................................141.30 Part II.........................................................................................................................................................141.31 Part III........................................................................................................................................................141.31a Part IV........................................................................................................................................................141.32 Parties.........................................................................................................................................................141.33 Point(s) of Delivery....................................................................................................................................151.34 Point(s) of Receipt.....................................................................................................................................151.35 Point-To-Point Transmission Service........................................................................................................151.36 Power Purchaser.........................................................................................................................................151.37 Receiving Party..........................................................................................................................................151.38 Regional Transmission Group (RTG)........................................................................................................151.39 Reserved Capacity.....................................................................................................................................161.40 Service Agreement.....................................................................................................................................161.41 Service Commencement Date....................................................................................................................16

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Second Revised Sheet No. 2FERC Electric Tariff Superseding First Revised Sheet No. 2Fourth Revised Volume No. 1

1.42 Short-Term Firm Point-To-Point Transmission Service............................................................................161.42a SPP.............................................................................................................................................................161.42b SPP Membership Agreement.....................................................................................................................161.42c SPP Region................................................................................................................................................161.43 System Impact Study.................................................................................................................................161.44 Third-Party Sale.........................................................................................................................................171.44a Transition Period........................................................................................................................................171.45 Transmission Customer.............................................................................................................................171.45a Transmission Owner..................................................................................................................................171.46 Transmission Provider...............................................................................................................................171.47 Transmission Provider's Monthly Transmission System Peak..................................................................171.48 Transmission Service.................................................................................................................................181.49 Transmission System.................................................................................................................................181.49a Users..........................................................................................................................................................181.49b Wholesale Distribution Service.................................................................................................................181.50 Zone...........................................................................................................................................................18

2 Initial Allocation and Renewal Procedures................................................................................................................182.1 Initial Allocation of Available Transmission Capability...........................................................................182.2 Reservation Priority For Existing Firm Service Customers......................................................................19

3 Ancillary Services...................................................................................................................................................20A4 Open Access Same-Time Information System (OASIS)...........................................................................................215 Local Furnishing Bonds.............................................................................................................................................22

5.1 Transmission Owners That Own Facilities Financed by Local Furnishing Bonds or that are Tax Exempt Entities..........................................................................22

5.2 Alternative Procedures for Requesting Transmission Service 226 Reciprocity.................................................................................................................................................................237 Billing and Payment...................................................................................................................................................24

7.1 Billing Procedure.......................................................................................................................................247.2 Interest on Unpaid Balances....................................................................................................................25B7.2a Financial Assurance Escrow Accounts...................................................................................................25B7.3 Customer Default....................................................................................................................................25B

8 Accounting for Use of the Tariff...............................................................................................................................268.1 Reserved.....................................................................................................................................................268.2 Study Costs and Revenues.........................................................................................................................26

9 Regulatory Filings......................................................................................................................................................2610 Force Majeure and Indemnification...........................................................................................................................27

10.1 Force Majeure............................................................................................................................................2710.2 Indemnification..........................................................................................................................................27

11 Creditworthiness........................................................................................................................................................2812 Dispute Resolution Procedures..................................................................................................................................28

12.1 Internal Dispute Resolution Procedures.....................................................................................................2812.2 External Arbitration Procedures................................................................................................................2912.3 Arbitration Decisions.................................................................................................................................2912.4 Costs...........................................................................................................................................................3012.5 Rights Under The Federal Power Act........................................................................................................30

II. POINT-TO-POINT TRANSMISSION SERVICE................................................................................................................31Preamble ....................................................................................................................................................................3113 Nature of Firm Point-To-Point Transmission Service...............................................................................................31

13.1 Term...........................................................................................................................................................3113.2 Reservation Priority...................................................................................................................................3113.3 Use of Firm Transmission Service by the Transmission Owners..............................................................3213.4 Service Agreements...................................................................................................................................3213.5 Transmission Customer Obligations for Facility Additions

or Redispatch Costs....................................................................................................................................3313.6 Curtailment of Firm Transmission Service................................................................................................3413.7 Classification of Firm Transmission Service.............................................................................................3513.8 Scheduling of Firm Point-To-Point Transmission Service........................................................................37

14 Nature of Non-Firm Point-To-Point Transmission Service ......................................................................................3814.1 Term...........................................................................................................................................................3814.2 Reservation Priority...................................................................................................................................3814.3 Use of Non-Firm Point-To-Point Transmission Service by the Transmission Owner(s)..........................40

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 3FERC Electric TariffFourth Revised Volume No. 1

14.4 Service Agreements...................................................................................................................................4014.5 Classification of Non-Firm Point-To-Point Transmission Service............................................................4014.6 Scheduling of Non-Firm Point-To-Point Transmission Service................................................................4114.7 Curtailment or Interruption of Service.......................................................................................................42

15 Service Availability.................................................................................................................................................44A15.1 General Conditions.................................................................................................................................44A15.2 Determination of Available Transmission Capability............................................................................44A15.3 Initiating Service in the Absence of an Executed Service Agreement......................................................4515.4 Obligation to Provide Transmission Service that Requires

Expansion or Modification of the Transmission System...........................................................................4515.5 Deferral of Service.....................................................................................................................................4615.6 Other Transmission Service Schedules......................................................................................................4615.7 Real Power Losses.....................................................................................................................................46

16 Transmission Customer Responsibilities...................................................................................................................4616.1 Conditions Required of Transmission Customers.....................................................................................4616.2 Transmission Customer Responsibility for Third-Party Arrangements....................................................47

17 Procedures for Arranging Firm Point-To-Point Transmission Service.....................................................................4717.1 Application.................................................................................................................................................4717.1a Time Requirements....................................................................................................................................4817.2 Completed Application..............................................................................................................................4817.3 Deposit.......................................................................................................................................................4917.4 Notice of Deficient Application.................................................................................................................5017.5 Response to a Completed Application.......................................................................................................5117.6 Execution of Service Agreement...............................................................................................................5117.7 Extensions for Commencement of Service................................................................................................52

18 Procedures for Arranging Non-Firm Point-To-Point Transmission Service.............................................................5218.1 Application.................................................................................................................................................5218.2 Completed Application...........................................................................................................................52A18.3 Timing of Requests and Responses Regarding Reservation of

Non-Firm Point-To-Point Transmission Service.......................................................................................5418.4 Determination of Available Transmission Capability...............................................................................54

19 Additional Study Procedures For Firm Point-To-Point TransmissionService Requests........................................................................................................................................................5419.1 Notice of Need for System Impact Study..................................................................................................5419.2 System Impact Study Agreement and Cost Reimbursement.....................................................................5519.3 System Impact Study Procedures...............................................................................................................5619.4 Facilities Study Procedures........................................................................................................................5719.5 Facilities Study Modifications...................................................................................................................5819.6 Due Diligence in Completing New Facilities............................................................................................5819.7 Partial Interim Service...............................................................................................................................5919.8 Expedited Procedures for New Facilities...................................................................................................59

20 Procedures if The Transmission Provider is Unable to Complete NewTransmission Facilities for Firm Point-To-Point Transmission Service...................................................................6020.1 Delays in Construction of New Facilities..................................................................................................6020.2 Alternatives to the Original Facility Additions..........................................................................................6020.3 Refund Obligation for Unfinished Facility Additions...............................................................................61

21 Provisions Relating to Transmission Construction and Services on theSystems of Other Utilities..........................................................................................................................................6121.1 Responsibility for Third-Party System Additions......................................................................................6121.2 Coordination of Third-Party System Additions.........................................................................................62

22 Changes in Service Specifications.............................................................................................................................6322.1 Modifications On a Non-Firm Basis..........................................................................................................6322.1a Additional Charge To Prevent Abuse........................................................................................................6422.2 Modification On a Firm Basis....................................................................................................................64

23 Sale or Assignment of Transmission Service............................................................................................................6523.1 Procedures for Assignment or Transfer of Service....................................................................................6523.2 Limitations on Assignment or Transfer of Service....................................................................................6623.3 Information on Assignment or Transfer of Service...................................................................................66

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 4FERC Electric TariffFourth Revised Volume No. 1

24 Metering and Power Factor Correction at Receipt and Delivery Points(s)...............................................................6724.1 Transmission Customer Obligations..........................................................................................................6724.2 Transmission Provider Access to Metering Data.......................................................................................6724.3 Power Factor..............................................................................................................................................67

25 Compensation for Transmission Service...................................................................................................................6726 Stranded Cost Recovery.............................................................................................................................................6827 Compensation for New Facilities and Redispatch Costs...........................................................................................68

III. NETWORK INTEGRATION TRANSMISSION SERVICE...............................................................................................69Preamble ....................................................................................................................................................................6928 Nature of Network Integration Transmission Service...............................................................................................69

28.1 Scope of Service........................................................................................................................................6928.2 Transmission Provider and Transmission Owners Responsibilities..........................................................6928.3 Network Integration Transmission Service...............................................................................................7028.4 Secondary Service......................................................................................................................................7028.5 Real Power Losses.....................................................................................................................................7128.6 Restrictions on Use of Service...................................................................................................................71

29 Initiating Service........................................................................................................................................................7129.1 Condition Precedent for Receiving Service...............................................................................................7129.2 Application Procedures..............................................................................................................................7229.3 Technical Arrangements to be Completed Prior to

Commencement of Service.....................................................................................................................74A29.4 Network Customer Facilities.....................................................................................................................7529.5 Filing of Service Agreement......................................................................................................................75

30 Network Resources....................................................................................................................................................7530.1 Designation of Network Resources...........................................................................................................7530.2 Designation of New Network Resources...................................................................................................7530.3 Termination of Network Resources...........................................................................................................7630.4 Operation of Network Resources...............................................................................................................7630.5 Network Customer Redispatch Obligation................................................................................................7630.6 Transmission Arrangements for Network Resources Not Physically

Interconnected With The Transmission Provider......................................................................................7730.7 Limitation on Designation of Network Resources.....................................................................................7730.8 Use of Interface Capacity by the Network Customer................................................................................7730.9 Network Customer Owned Transmission Facilities..................................................................................77

31 Designation of Network Load....................................................................................................................................7831.1 Network Load............................................................................................................................................7831.2 New Network Loads Connected With the Transmission Provider............................................................7831.3 Network Load Not Physically Interconnected with the

Transmission Provider...............................................................................................................................7931.4 New Interconnection Points.......................................................................................................................7931.5 Changes in Service Requests.....................................................................................................................7931.6 Annual Load and Resource Information Updates......................................................................................80

32 Additional Study Procedures For Network Integration TransmissionService Requests........................................................................................................................................................8032.1 Notice of Need for System Impact Study..................................................................................................8032.2 System Impact Study Agreement and Cost Reimbursement.....................................................................8132.3 System Impact Study Procedures...............................................................................................................8232.4 Facilities Study Procedures........................................................................................................................82

33 Load Shedding and Curtailments...............................................................................................................................8433.1 Procedures..................................................................................................................................................8433.2 Transmission Constraints...........................................................................................................................8433.3 Cost Responsibility for Relieving Transmission Constraints....................................................................8533.4 Curtailments of Scheduled Deliveries.......................................................................................................8533.5 Allocation of Curtailments.........................................................................................................................8533.6 Load Shedding...........................................................................................................................................8633.7 System Reliability......................................................................................................................................86

34 Rates and Charges......................................................................................................................................................8734.1 Monthly Demand Charge...........................................................................................................................8734.2 Determination of Network Customer's Monthly Network Load...............................................................8834.3 Determination of Transmission Provider's Monthly Zone

Transmission Load..................................................................................................................................88A

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 5FERC Electric TariffFourth Revised Volume No. 1

34.4 Redispatch Charge..................................................................................................................................88A34.5 Stranded Cost Recovery.............................................................................................................................8934.6 SPP Costs...................................................................................................................................................89

35 Operating Arrangements............................................................................................................................................8935.1 Operation under the Network Operating Agreement.................................................................................8935.2 Network Operating Agreement..................................................................................................................8935.3 Reserved.....................................................................................................................................................91

36 Scheduling..................................................................................................................................................................91IV. SPECIAL RULES ON USE OF TARIFF.............................................................................................................................92

37 During Transition Period...........................................................................................................................................9237.1 Service Not Required for Bundled Customers or Customers Under

Retail Access Programs.............................................................................................................................9237.2 Availability of Network Integration Transmission Service.......................................................................9237.3 Unbundled Wholesale................................................................................................................................9237.4 Grandfathered Transactions.......................................................................................................................92

38 After Transition Period..............................................................................................................................................9338.1 Applicability to Retail Load Having Choice.............................................................................................9338.2 Applicability to All Retail Load................................................................................................................9338.3 Grandfathered Agreements........................................................................................................................93

39 Applicability of Non-Rate Terms and Conditions.....................................................................................................9339.1 Bundled Retail and Grandfathered Load...................................................................................................93

SCHEDULE 1Scheduling, System Control and Dispatch Service....................................................................................................94

SCHEDULE 1ATariff Administration Service....................................................................................................................................95

SCHEDULE 2Reactive Supply and Voltage Control from Generation Sources Service.................................................................97

SCHEDULE 3Regulation and Frequency Response Service............................................................................................................99

SCHEDULE 4Energy Imbalance Service.......................................................................................................................................100

SCHEDULE 5Operating Reserve - Spinning Reserve Service.......................................................................................................101

SCHEDULE 6Operating Reserve - Supplemental Reserve Service...............................................................................................102

SCHEDULE 7Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service.......................................................103

SCHEDULE 8Non-Firm Point-To-Point Transmission Service.....................................................................................................106

SCHEDULE 9Network Integration Transmission Service.............................................................................................................109

SCHEDULE 10Wholesale Distribution Service...............................................................................................................................112

ATTACHMENT AForm Of Service Agreement For Firm Point-To-Point Transmission Service........................................................113

ATTACHMENT BForm Of Service Agreement For Non-Firm Point-To-PointTransmission Service...............................................................................................................................................118

ATTACHMENT CMethodology To Assess Short-Term Available Transmission Capability..............................................................120

ATTACHMENT DMethodology for Completing a System Impact Study............................................................................................127

ATTACHMENT EIndex Of Point-To-Point Transmission Service Customers.....................................................................................129

ATTACHMENT FService Agreement For Network Integration Transmission Service.......................................................................132

ATTACHMENT GNetwork Operating Agreement................................................................................................................................145

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 6FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT HAnnual Transmission Revenue Requirement For Network Integration Transmission Service...............................161

ATTACHMENT IIndex Of Network Integration Transmission Service Customers............................................................................162

ATTACHMENT JRecovery Of Costs Associated With New Facilities...............................................................................................163

ATTACHMENT KRedispatch Procedures and Redispatch Costs..........................................................................................................165

ATTACHMENT LTreatment Of Revenues...........................................................................................................................................172

ATTACHMENT MLoss Compensation Procedure.................................................................................................................................176

ATTACHMENT NForm Of Service Agreement For Loss Compensation Service................................................................................181

ATTACHMENT OCoordinated Planning Procedures............................................................................................................................183

ATTACHMENT P ..........................................................................................................................................................................188ATTACHMENT Q

Form of Application For Short-Term Firm and Non-FirmTransmission Service...............................................................................................................................................191

ATTACHMENT RNorth American Electric Reliability Council Transmission LoadingRelief (“TLR”) Procedure........................................................................................................................................192

ATTACHMENT SProcedure for Calculation of MW-Mile Impacts for Use in RevenueAllocation and Determination of Losses..................................................................................................................211

ATTACHMENT TRate Sheets For Point-To-Point Transmission Service............................................................................................217

ATTACHMENT URate Schedule For Compensation For Rescheduled Maintenance Costs................................................................249

ATTACHMENT VCoordinated Generation Interconnection Procedures..............................................................................................258

ATTACHMENT W ...............................................................................................................................................................410AATTACHMENT X ..................................................................................................................................................................411ATTACHMENT Y

Flexible Use Transmission Service (Experimental)................................................................................................412ATTTACHMENT AA

Transmission Service Prepayment (Experimental)..................................................................................................425

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 7FERC Electric TariffFourth Revised Volume No. 1

I. COMMON SERVICE PROVISIONS

1 Definitions

1.1 Ancillary Services: Those services that are necessary to support the transmission

of capacity and energy from resources to loads while maintaining reliable

operation of the Transmission Provider's and Transmission Owner's(s)

Transmission System in accordance with Good Utility Practice.

1.2 Annual Transmission Cost: The total annual cost of the Transmission System

for purposes of Network Integration Transmission Service shall be the amount

specified in Attachment H until amended by the Transmission Provider or

modified by the Commission.

1.3 Application: A request by an Eligible Customer for transmission service

pursuant to the provisions of the Tariff.

1.3a Attachment Facilities: Facilities that serve to interconnect a generating unit with

a Transmission Owner’s transmission facilities.

1.4 Commission: The Federal Energy Regulatory Commission.

1.5 Completed Application: An Application that satisfies all of the information and

other requirements of the Tariff, including any required deposit.

1.6 Control Area: An electric power system or combination of electric power

systems to which a common automatic generation control scheme is applied in

order to:

(1) match, at all times, the power output of the generators within the electric

power system(s) and capacity and energy purchased from entities outside

the electric power system(s), with the load within the electric power

system(s);

(2) maintain scheduled interchange with other Control Areas, within the limits

of Good Utility Practice;

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 8FERC Electric TariffFourth Revised Volume No. 1

(3) maintain the frequency of the electric power system(s) within reasonable

limits in accordance with Good Utility Practice; and

(4) provide sufficient generating capacity to maintain operating reserves in

accordance with Good Utility Practice.

1.7 Curtailment: A reduction in firm or non-firm transmission service in response to

a transmission capacity shortage as a result of system reliability conditions.

1.8 Delivering Party: The entity supplying capacity and energy to be transmitted at

Point(s) of Receipt.

1.9 Designated Agent: Any entity that performs actions or functions required under

the Tariff on behalf of the Transmission Provider, a Transmission Owner, an

Eligible Customer, or the Transmission Customer.

1.10 Direct Assignment Facilities: Facilities or portions of facilities that are

constructed by any Transmission Owner(s) for the sole use/benefit of a particular

Transmission Customer or a particular group of customers or a particular

Generation Interconnection Customer requesting service under the Tariff. Direct

Assignment Facilities shall be specified in the Service Agreements that govern

service to the Transmission Customer(s) and Generation Interconnection

Customer(s) and shall be subject to Commission approval.

1.10a Effective Date: For Short-Term Firm and Non-Firm Point-To-Point

Transmission Service the Effective Date of this Tariff is June 1, 1998. For Long-

Term Firm Point-To-Point Transmission Service the Effective Date of this Tariff

is April 1, 1999. For Network Integration Transmission Service the Effective

Date of this Tariff is February 1, 2000.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Second Revised Sheet No. 9FERC Electric Tariff Superseding Sub First Revised Sheet No. 9Fourth Revised Volume No. 1

1.11 Eligible Customer: (i) Any electric utility (including the Transmission Owner(s)

and any power marketer), Federal power marketing agency, or any person

generating electric energy for sale for resale. Electric energy sold or produced by

such entity may be electric energy produced in the United States, Canada or

Mexico. However, with respect to transmission service that the Commission is

prohibited from ordering by Section 212(h) of the Federal Power Act, such entity

is eligible only if the service is provided pursuant to a state requirement that a

Transmission Owner offer the unbundled transmission service, or pursuant to a

voluntary offer of such service by a Transmission Owner. (ii) Any retail customer

or eligible person taking unbundled transmission service pursuant to a state

requirement that a Transmission Owner offer the transmission service, or pursuant

to a voluntary offer of such service by a Transmission Owner, is an Eligible

Customer under the Tariff.

1.12 Facilities Study: An engineering study conducted by the Transmission Provider

in collaboration with the affected Transmission Owner(s) to determine the

required modifications to the Transmission System, including the cost and

scheduled completion date for such modifications, that will be required to provide

the requested transmission service or Generation Interconnection Service. The

Transmission Provider shall have the ultimate responsibility for any such studies.

However, the Transmission Provider’s final decision must be consistent with

Good Utility Practice. Facilities studies for any facilities not under the

operational control of the Transmission Provider shall be performed by the

Transmission Owner or any entity it designates to perform the studies.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: August 8, 2001 Effective: June 1, 2001Filed to comply with Order of the Federal Energy Regulatory Commission, Docket No. ER01-1989-000, issued July 9, 2001, 96 FERC ¶ 61,034 (2001).

Southwest Power Pool Original Sheet No. 10FERC Electric TariffFourth Revised Volume No. 1

1.12a Feasibility Study: A coordinated preliminary determination by the Transmission

Provider and the affected Transmission Owner(s) of the Attachment Facilities,

other Direct Assignment Facilities, and system upgrades that are needed to accept

power into the grid at the interconnection receipt point, that will be necessary to

accommodate a Generation Interconnection Request made under Attachment V.

1.12b Federal Power: All power and energy generated at reservoir projects under the

control of the Department of Army in the marketing area of the Southwestern

Power Administration (Southwestern) plus power and energy delivered to

Southwestern from other sources for the purpose of fulfilling Southwestern’s

contractual obligations for the sale of power and energy pursuant to

Southwestern’s Federal power allocations.

1.13 Firm Point-To-Point Transmission Service: Transmission Service under this

Tariff that is reserved and/or scheduled between specified Points of Receipt and

Delivery pursuant to Part II of this Tariff.

1.13a Generation Interconnection Customer: An entity that submits a Generation

Interconnection Request under Attachment V.

1.13b Generation Interconnection Request: A request made under Attachment V to

connect a generating unit to the Transmission System or to increase the capacity

of a generating unit that is connected to the Transmission System.

1.14 Good Utility Practice: Any of the practices, methods and acts engaged in or

approved by a significant portion of the electric utility industry during the relevant

time period, or any of the practices, methods and acts which, in the exercise of

reasonable judgment in light of the facts known at the time the decision was

made, could have been expected to accomplish the desired result at a reasonable

cost consistent with good business practices,

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 11FERC Electric TariffFourth Revised Volume No. 1

reliability, safety and expedition. Good Utility Practice is not intended to be

limited to the optimum practice, method, or act to the exclusion of all others, but

rather to be acceptable practices, methods, or acts generally accepted in the

region.

1.14a Grandfathered Agreements or Transactions: Grandfathered Agreements or

Transactions include (1) agreements providing long term firm transmission

service executed prior to April 1, 1999 and Network Integration Transmission

Servic executed prior to February 1, 2000; (2) bundled wholesale contracts (that

reserve transmission as part of the contract); (3) short-term firm and non-firm

point-to-point transmission transactions which were accepted and confirmed prior

to the Effective Date; (4) existing or new contracts entered into by the

Southwestern Power Administration on behalf of the United States for the use of

transmission facilities of the Southwestern Power Administration that are

constructed or acquired by purchase or other agreement, as authorized under

Section 5 of the Flood Control Act of 1944, for the transmission of Federal

Power; and (5) contracts executed before the Effective Date, regardless of term,

entered into by the Southwestern Power Administration on behalf of the United

States for the transmission of power or energy across transmission facilities

owned and operated by the Southwestern Power Administration. These

agreements are set forth on the list which is Attachment W to this Tariff.

Umbrella service agreements are specifically not Grandfathered.

1.15 Interruption: A reduction in non-firm transmission service due to economic

reasons pursuant to Section 14.7.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 12FERC Electric Tariff Superseding Original Sheet No. 12Fourth Revised Volume No. 1

1.16 Load Ratio Share: Ratio of a Transmission Customer's Network Load in a Zone

to the total load in that Zone computed in accordance with Sections 34.2 and 34.3

of the Network Integration Transmission Service under part III of this Tariff and

calculated on a calendar year basis, for the prior calendar year.

1.17 Load Shedding: The systematic reduction of system demand by temporarily

decreasing load in response to transmission system or area capacity shortages,

system instability, or voltage control considerations under Part III of the Tariff.

1.18 Long-Term Firm Point-To-Point Transmission Service: Firm Point-To-Point

Transmission Service under Part II of the Tariff with a term of one year or more.

1.18a Member: A member of SPP.

1.19 Native Load Customers: The wholesale and retail power customers of the

Transmission Owner(s) on whose behalf the Transmission Owner(s), by statute,

franchise, regulatory requirement, or contract, has (have) undertaken an obligation

to construct or operate the Transmission Owner's(s') system(s) to meet the reliable

electric needs of such customers. In addition, Native Load Customers also may

include the customers of the Federal Government on whose behalf the

Government, by policy, statute, regulatory requirement, or contract, delivers

Federal capacity and energy to meet all or a portion of the reliable electric needs

of such customers.

1.20 Network Customer: An entity receiving transmission service pursuant to the

terms of the Transmission Provider's Network Integration Transmission Service

under Part III of the Tariff.

1.21 Network Integration Transmission Service: The transmission service provided

under Part III of the Tariff.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 13FERC Electric TariffFourth Revised Volume No. 1

1.22 Network Load: The load that a Network Customer designates for Network

Integration Transmission Service under Part III of the Tariff. The Network

Customer's Network Load shall include all load served by the output of any

Network Resources designated by the Network Customer. A Network Customer

may elect to designate less than its total load as Network Load but may not

designate only part of the load at a discrete Point of Delivery. Where an Eligible

Customer has elected not to designate a particular load at discrete points of

delivery as Network Load, the Eligible Customer is responsible for making

separate arrangements under Part II of the Tariff for any Point-To-Point

Transmission Service that may be necessary for such non-designated load.

1.23 Network Operating Agreement: An executed agreement that contains the terms

and conditions under which the Network Customer shall operate its facilities and

the technical and operational matters associated with the implementation of

Network Integration Transmission Service under Part III of the Tariff.

1.24 Reserved:

1.25 Network Resource: Any designated generating resource owned, purchased or

leased by a Network Customer under the Network Integration Transmission

Service Tariff. Network Resources do not include any resource, or any portion

thereof, that is committed for sale to third parties or otherwise cannot be called

upon to meet the Network Customer's Network Load on a non-interruptible basis.

1.26 Network Upgrades: All or a portion of the modifications or additions to

transmission-related facilities that are integrated with and support the

Transmission Provider's overall Transmission System for the general benefit of all

users of such Transmission System.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 13AFERC Electric TariffFourth Revised Volume No. 1

1.26a Next-Hour-Market Service: Non-firm transmission service that (a) is reserved

for one clock hour and (b) is requested within sixty (60) minutes before the start

of the next clock hour for service commencing at the start of that clock hour.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 14FERC Electric TariffFourth Revised Volume No. 1

1.27 Non-Firm Point-To-Point Transmission Service: Point-To-Point Transmission

Service under the Tariff that is reserved and scheduled on an as-available basis

and is subject to Curtailment or Interruption as set forth in Section 14.7 under Part

II of this Tariff. Non-Firm Point-To-Point Transmission Service is available on a

stand-alone basis for periods ranging from one hour to one month.

1.28 Open Access Same-Time Information System (OASIS): The information

system and standards of conduct contained in Part 37 of the Commission's

regulations and all additional requirements implemented by subsequent

Commission orders dealing with OASIS.

1.29 Part I: Tariff Definitions and Common Service Provisions contained in Sections

2 through 12.

1.30 Part II: Tariff Sections 13 through 27 pertaining to Point-To-Point Transmission

Service in conjunction with the applicable Common Service Provisions of Part I

and appropriate Schedules and Attachments.

1.31 Part III: Tariff Sections 28 through 36 pertaining to Network Integration

Transmission Service in conjunction with the applicable Common Service

Provisions of Part I and appropriate Schedules and Attachments.

1.31a Part IV: Tariff Sections 37 through 38 pertaining to special Tariff provisions

related to the applicability of the Tariff during and after the Transition Period.

1.32 Parties: The Transmission Provider and the Transmission Customer receiving

service under the Tariff.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 15FERC Electric TariffFourth Revised Volume No. 1

1.33 Point(s) of Delivery: Point(s) on the Transmission Provider's Transmission

System where capacity and energy transmitted by the Transmission Provider will

be made available to the Receiving Party under Part II of the Tariff. The Point(s)

of Delivery shall be specified in the Service Agreement for Long-Term Firm

Point-To-Point Transmission Service.

1.34 Point(s) of Receipt: Point(s) of interconnection on the Transmission Provider's

Transmission System where capacity and energy will be made available to the

Transmission Provider by the Delivering Party under Part II of the Tariff. The

Point(s) of Receipt shall be specified in the Service Agreement for Long-Term

Firm Point-To-Point Transmission Service.

1.35 Point-To-Point Transmission Service: The reservation and transmission of

capacity and energy on either a firm or non-firm basis from the Point(s) of

Receipt to the Point(s) of Delivery under Part II of the Tariff.

1.36 Power Purchaser: The entity that is purchasing the capacity and energy to be

transmitted under the Tariff.

1.37 Receiving Party: The entity receiving the capacity and energy transmitted by the

Transmission Provider to Point(s) of Delivery.

1.38 Regional Transmission Group (RTG): A voluntary organization of transmission

owners, transmission users and other entities approved by the Commission to

efficiently coordinate transmission planning (and expansion), operation and use

on a regional (and interregional) basis.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 16FERC Electric TariffFourth Revised Volume No. 1

1.39 Reserved Capacity: The maximum amount of capacity and energy that the

Transmission Provider agrees to transmit for the Transmission Customer over the

Transmission Provider's Transmission System between the Point(s) of Receipt

and the Point(s) of Delivery under Part II of the Tariff. Reserved Capacity shall

be expressed in terms of whole megawatts on a sixty (60) minute interval

(commencing on the clock hour) basis.

1.40 Service Agreement: The initial agreement and any amendments or supplements

thereto entered into by the Transmission Customer and the Transmission Provider

for service under the Tariff.

1.41 Service Commencement Date: The date the Transmission Provider begins to

provide service pursuant to the terms of an executed Service Agreement, or the

date the Transmission Provider begins to provide service in accordance with

Section 15.3 or Section 29.1 under the Tariff.

1.42 Short-Term Firm Point-To-Point Transmission Service: Firm Point-To-Point

Transmission Service under Part II of the Tariff with a term of less than one year.

1.42a SPP: The Southwest Power Pool, Inc.

1.42b SPP Membership Agreement: The Southwest Power Pool Membership

Agreement detailing the rights and obligations of the SPP and SPP Members.

1.42c SPP Region: The geographic area of the Transmission System.

1.43 System Impact Study: A coordinated assessment by the Transmission Provider

and the affected Transmission Owner(s) of (i) the adequacy of the Transmission

System to accommodate a request for either Firm Point-To-Point Transmission

Service or Network Integration Transmission Service or (ii) to determine the

Attachment Facilities, other Direct Assignment Facilities, and system upgrades

that are needed to accept power into the grid at

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 17FERC Electric TariffFourth Revised Volume No. 1

the interconnection receipt point, required to accommodate a request for

generation interconnection in accordance with Attachment V and (iii) whether any

additional costs may be incurred in order to provide transmission service or

generation interconnection.

1.44 Third-Party Sale: Any sale for resale in interstate commerce to a Power

Purchaser that is not designated as part of Network Load under the Network

Integration Transmission Service.

1.44a Transition Period: The period from the Effective Date of this Tariff for the

provision of Network Integration Transmission Service to the last day of the fifth

year thereafter.

1.45 Transmission Customer: Any Eligible Customer (or its Designated Agent) that

(i) executes a Service Agreement, or (ii) requests in writing that the Transmission

Provider file with the Commission, a proposed unexecuted Service Agreement to

receive transmission service under Part II of the Tariff. This term is used in the

Part I Common Service Provisions to include customers receiving transmission

service under Part II and Part III of this Tariff.

1.45a Transmission Owner: Each member of SPP whose transmission facilities (in

whole or in part) make up the Transmission System and has executed a

membership agreement as a Transmission Owner. Those Transmission Owners

that are not regulated by the Commission shall not become subject to Commission

regulation by virtue of their status as Transmission Owners under this Tariff;

provided, however, that service over their facilities classified as transmission and

covered by the Tariff shall be subject to Commission regulation.

1.46 Transmission Provider: The Southwest Power Pool, Inc., as agent for and on

behalf of the Transmission Owners.

1.47 Transmission Provider's Monthly Transmission System Peak: The maximum

firm usage of the Transmission Provider's Transmission System in a calendar

month.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 18FERC Electric TariffFourth Revised Volume No. 1

1.48 Transmission Service: Point-To-Point Transmission Service provided under

Part II of the Tariff on a firm and non-firm basis.

1.49 Transmission System: The facilities used by the Transmission Provider to

provide transmission service under Part II and Part III of the Tariff and are

reflected in the rates for Network Integration, Long-Term Firm, Short-Term Firm

and Non-Firm Point-to-Point Transmission Service under the Tariff as stated in

Attachments H and T.

1.49a Users: Transmission Customers or other entities that are parties to transactions

under the Tariff.

1.49b Wholesale Distribution Service: The provision of distribution service over a

Transmission Owner's Distribution Facilities necessary to effectuate a transaction

under this Tariff. To the extent such service is required, it shall be specified in the

Service Agreement for the associated service being provided under the Tariff.

The charges for Wholesale Distribution Service are described in Schedule 10.

1.50 Zone: The geographic area of the facilities of a Transmission Owner or a specific

combination of Transmission Owners as specified in Schedules 7,8, and 9.

2 Initial Allocation and Renewal Procedures

2.1 Initial Allocation of Available Transmission Capability: For purposes of

determining whether existing capability on the Transmission Provider's

Transmission System is adequate to accommodate a request for firm service under

this Tariff, all Completed Applications for new firm transmission service received

during the initial sixty (60) day period commencing with the Effective Date of the

Tariff will be deemed to have been filed simultaneously. A lottery system

conducted by the Transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Substitute First Revised Sheet No. 19FERC Electric Tariff Superseding Original Sheet No. 19Fourth Revised Volume No. 1

Provider shall be used to assign priorities for Completed Applications filed

simultaneously. All Completed Applications for firm transmission service

received after the initial sixty (60) day period shall be assigned a priority pursuant

to Section 13.2.

2.2 Reservation Priority For Existing Firm Service Customers: Existing firm

service customers (wholesale requirements and transmission-only, with a contract

term of one-year or more, and retail) of the Transmission Owner(s) or

Transmission Provider have the right to continue to take transmission service

from the Transmission Provider when the contract expires, rolls over or is

renewed. This transmission reservation priority is independent of whether the

existing customer continues to purchase capacity and energy from the

Transmission Owner(s) or elects to purchase capacity and energy from another

supplier. The existing customer must notify the Transmission Provider no later

than sixty (60) days prior to the end of the term of its firm transmission contract

that it is exercising its transmission reservation priority; otherwise it shall forfeit

the transmission reservation priority associated with the contract.

If at the time of this notification, the Transmission Provider's

Transmission System cannot accommodate all of the requests for transmission

service, the existing firm service customer must agree to accept a contract term at

least equal to the longest term competing request by any new Eligible Customer

and to pay the current just and reasonable rate, as approved by the Commission,

for such service. This transmission reservation priority for existing firm service

customers is an ongoing right that may be exercised in the manner specified

above at the end of all firm contract terms of one-year or longer. This reservation

priority only applies to the facilities of the Transmission Owner(s) where such

facility costs have been included as part of the firm service rates that the firm

service customer has been paying. If competing existing firm service

requirements customers apply for service that cannot be fully provided, the

priority rights will be ranked in accordance with first-come, first-served

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: August 8, 2001 Effective: June 1, 2001Filed to comply with Order of the Federal Energy Regulatory Commission, Docket No. ER01-1989-000, issued July 9, 2001, 96 FERC ¶ 61,034 (2001).

Southwest Power Pool Substitute First Revised Sheet No. 20FERC Electric Tariff Superseding Original Sheet No. 20Fourth Revised Volume No. 1

principles. If firm service customers tie, then the capacity for which they receive

priority rights under this Tariff shall be apportioned on a pro rata basis.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: August 8, 2001 Effective: June 1, 2001Filed to comply with Order of the Federal Energy Regulatory Commission, Docket No. ER01-1989-000, issued July 9, 2001, 96 FERC ¶ 61,034 (2001).

Southwest Power Pool Substitute Original Sheet No. 20AFERC Electric Tariff Superseding Original Sheet No. 20AFourth Revised Volume No. 1

3 Ancillary Services

As shown on Schedules 1 and 2, the Transmission Provider will provide Scheduling and

Tariff Administration Service and will facilitate and arrange for the supply of Reactive Supply

and Voltage Control from Generation Sources Service. In order to allow the Transmission

Provider to arrange for Reactive Supply and Voltage Control from Generation Sources Service,

each Transmission Owner shall maintain a schedule offering such service. All Transmission

Customers are required to purchase these two services from the Transmission Provider based on

the charges in Schedules 1 and 2. In addition, the Transmission Owners may continue to provide

Scheduling, System Control and Dispatch Services related to transmission service under this

Tariff. Each Transmission Owner must maintain a schedule showing the charges for such

services. Any amounts charged the Transmission Provider by a Transmission Owner for such

service shall be passed through to the Transmission Customer

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: August 8, 2001 Effective: June 1, 2001Filed to comply with Order of the Federal Energy Regulatory Commission, Docket No. ER01-1989-000, issued July 9, 2001, 96 FERC ¶ 61,034 (2001).

Southwest Power Pool Original Sheet No. 20BFERC Electric TariffFourth Revised Volume No. 1

without mark-up. Each Transmission Owner's schedules for Scheduling, System Control and

Dispatch Service and for Reactive Supply and Voltage Control from Generation Sources Service

shall be available through the SPP OASIS.

Each Transmission Owner also shall maintain schedules which offer (1) Regulation and

Frequency Response Service, (2) Energy Imbalance Service, (3) Operating Reserve - Spinning

Reserve Service, and (4) Operating Reserve - Supplemental Reserve Service. Transmission

Customers shall pay the Transmission Provider providing any of these services directly for the

service. Each Transmission Owner's schedules for these services also shall be available through

SPP OASIS. The Transmission Customer serving load within a

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 21FERC Electric TariffFourth Revised Volume No. 1

Transmission Owner's(s') Control Area(s) is required to acquire these four Ancillary Services,

whether from the Transmission Owner(s), from a third party, or by self-supply. The

Transmission Customer may not decline the Transmission Owner's(s') offer of Ancillary Services

unless it demonstrates that it has acquired the Ancillary Services from another source. The

Transmission Customer must list in its Application which Ancillary Services it will purchase

from the Transmission Owner(s). The Transmission Provider shall determine whether the

Transmission Customer has adequately demonstrated that it has acquired the Ancillary Services

from another source. If the Transmission Provider determines that the Transmission Customer is

taking Ancillary Services that it has not paid for from an SPP Member or otherwise has not made

adequate arrangements for Ancillary Services, then the Transmission Provider may impose a

penalty equal to 200% of the specific Ancillary Service charge for the host Control Area (i.e. the

Control Area where the load is located) for the entire length of the reserved period but not

exceeding one month. The Transmission Provider shall compensate any affected Control Areas

or generators for 100% of the specific Ancillary Service charge for the period for which they

have provided service. The penalty revenues in excess of that amount shall be used to reduce the

Transmission Provider’s administrative costs.

4 Open Access Same-Time Information System (OASIS)

Terms and conditions regarding Open Access Same-Time Information System and

standards of conduct are set forth in 18 CFR § 37 of the Commission's regulations (Open Access

Same-Time Information System and Standards of Conduct for Public Utilities). In the event

available transmission capability as posted on the OASIS is insufficient to accommodate a

request for firm transmission service, additional studies may be required as provided by this

Tariff pursuant to Sections 19 and 32.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 22FERC Electric TariffFourth Revised Volume No. 1

5 Local Furnishing Bonds

5.1 Transmission Owners That Own Facilities Financed by Local Furnishing

Bonds or that are Tax Exempt Entities: This provision is applicable only to

Transmission Owners that have financed facilities for the local furnishing of

electric energy with tax-exempt bonds, as described in Section 142(f) of the

Internal Revenue Code ("local furnishing bonds") or that are tax-exempt entities,

described in Section 501(c) of the Internal Revenue Code. Notwithstanding any

other provision of this Tariff, the Transmission Provider shall not be required to

provide transmission service to any Eligible Customer pursuant to this Tariff if

the provision of such transmission service would jeopardize the tax-exempt status

of any local furnishing bond(s) used to finance a Transmission Owner's facilities

that would be used in providing such transmission service or would jeopardize the

tax-exempt status of the tax-exempt entity.

5.2 Alternative Procedures for Requesting Transmission Service:

(i) If the Transmission Provider determines that the provision of transmission

service requested by an Eligible Customer would jeopardize the tax-

exempt status of any local furnishing bond(s) used to finance a

Transmission Owner’s facilities that would be used in providing such

transmission service or would jeopardize the tax-exempt status of the

Transmission Owner, the Transmission Provider shall advise the Eligible

Customer within thirty (30) days of receipt of the Completed Application.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 23FERC Electric TariffFourth Revised Volume No. 1

(ii) If the Eligible Customer thereafter renews its request for the same

transmission service referred to in (i) by tendering an application under

Section 211 of the Federal Power Act, the Transmission Provider and the

relevant Transmission Owner, within ten (10) days of receiving a copy of

the Section 211 application, will waive any rights to a request for service

under Section 213(a) of the Federal Power Act and to the issuance of a

proposed order under Section 212(c) of the Federal Power Act. The

Commission, upon receipt of the Transmission Provider's and/or

Transmission Owner’s waiver of rights to a request for service under

Section 213(a) of the Federal Power Act and to the issuance of a proposed

order under Section 212(c) of the Federal Power Act, shall issue an order

under Section 211 of the Federal Power Act. Upon issuance of the order

under Section 211 of the Federal Power Act, the Transmission Provider

shall be required to provide the requested transmission service over the

affected Transmission Owner’s facilities in accordance with the terms and

conditions of this Tariff.

6 Reciprocity

A Transmission Customer receiving transmission service under this Tariff agrees to

provide comparable transmission service that it is capable of providing to all the Transmission

Owners on similar terms and conditions over facilities used for the transmission of electric

energy in interstate commerce owned, controlled or operated by the Transmission Customer and

over facilities used for the transmission of electric energy in interstate commerce owned,

controlled or operated by the Transmission Customer's corporate affiliates. A Transmission

Customer that is a member of a power pool or Regional Transmission Group also agrees to

provide comparable transmission service to the members of such power pool and Regional

Transmission Group on similar

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Second Revised Sheet No. 24FERC Electric Tariff Superseding First Revised Sheet No. 24Fourth Revised Volume No. 1

terms and conditions over facilities used for the transmission of electric energy owned,

controlled or operated by the Transmission Customer and over facilities used for the

transmission of electric energy owned, controlled or operated by the Transmission Customer's

corporate affiliates.

This reciprocity requirement applies not only to the Transmission Customer that obtains

transmission service under the Tariff, but also to all parties to a transaction that involves the use

of transmission service under the Tariff, including the power seller, buyer and any intermediary,

such as a power marketer. This reciprocity requirement also applies to any Eligible Customer

that owns, controls or operates transmission facilities that uses an intermediary, such as a power

marketer, to request transmission service under the Tariff. If the Transmission Customer does

not own, control or operate transmission facilities, it must include in its Application a sworn

statement of one of its duly authorized officers or other representatives that the purpose of its

Application is not to assist an Eligible Customer to avoid the requirements of this provision.

7 Billing and Payment

7.1 Billing Procedure: Within a reasonable time after the first day of each month,

the Transmission Provider shall submit an invoice to the Transmission Customer

for the charges for all services furnished under the Tariff during the preceding

month. The invoice shall be paid by the Transmission Customer within fifteen

(15) days of receipt. All payments shall be made in immediately available funds

payable to the Transmission Provider, or by wire transfer to a bank named by the

Transmission Provider. Invoices may be issued using estimated data, to the extent

actual data is not available by the fifth (5th) working day of the month following

service. Adjustments reflecting the difference in billing between the estimated and

actual data will be included on the next regular invoice, with such adjustment

being due when that invoice is due.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool First Revised Sheet No. 24AFERC Electric Tariff Substitute Original Sheet No. 24AFourth Revised Volume No. 1

Any other corrections found to be necessary will be made on the next regular

monthly invoice.

Bills will be adjusted to correct for all provable meter errors. Billing adjustments

for reasons other than (a) the replacement of estimated data with actual data for

service provided, or (b) provable meter error, shall be limited to those corrections

and adjustments found to be appropriate for such service within one year after

rendition of the bill reflecting the actual data for such service. Adjustments shall

be made for any billing with a monetary impact in excess of 2% of the billing for

the relevant period for an individual Transmission Customer or any aggregation

thereof. At its sole discretion, the Transmission Provider may make billing

adjustments for lesser amounts.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 24BFERC Electric TariffFourth Revised Volume No. 1

7.2 Interest on Unpaid Balances: Interest on any unpaid amounts (not including

amounts placed in escrow as financial assurance) shall be calculated in

accordance with the methodology specified for interest on refunds in the

Commission's regulations at 18 C.F.R. § 35.19a(a)(2)(iii). Interest on delinquent

amounts shall be calculated from the due date of the bill to the date of payment.

When payments are made by mail, bills shall be considered as having been paid

on the date of receipt by the Transmission Provider.

7.2a Financial Assurance Escrow Accounts: All monies deposited by a Customer as

financial assurance will be held in escrow by the Transmission Provider in a

separate, interest-bearing, money market account and 100% of the interest earned

will accrue to the benefit of that Customer. Interest shall be calculated from the

date of the receipt of deposit until the date that the deposit is returned or

converted into another form of financial assurance. When deposits are made by

mail, they shall be considered having been paid on the date of receipt by the

Transmission Provider.

7.3 Customer Default: In the event the Transmission Customer fails, for any reason

other than a billing dispute as described below, to make payment to the

Transmission Provider on or before the due date as described above, and such

failure of payment is not corrected within ten (10) business days of receipt by the

Transmission Customer of a written notice to cure such failure sent by the

Transmission Provider via Certified Mail, a default by the Transmission Customer

shall be deemed to exist. Upon the occurrence of a default, the Transmission

Provider may initiate a proceeding with the Commission to terminate service but

shall not terminate service until the Commission so approves any such

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 24CFERC Electric TariffFourth Revised Volume No. 1

request. In the event of a billing dispute between the Transmission Provider and

the Transmission Customer, the Transmission Provider will continue to provide

service under the Service Agreement as long as the Transmission Customer

(i) continues to make all payments not in dispute, and (ii) pays into an

independent escrow account the portion of the invoice in dispute, pending

resolution of such dispute. If the Transmission Customer fails to meet these two

requirements for continuation of service, then the Transmission Provider may

provide notice to the Transmission Customer of its intent to suspend service in

sixty (60) days, in accordance with Commission policy.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 25FERC Electric TariffFourth Revised Volume No. 1

RESERVED FOR FUTURE USE

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 26FERC Electric TariffFourth Revised Volume No. 1

8 Accounting for Use of the Tariff

The Transmission Provider and Owner(s) shall record the following amounts, as outlined

below, where applicable.

8.1 Reserved.

8.2 Study Costs and Revenues: The Transmission Provider and each Transmission

Owner shall include in a separate transmission operating expense account or

subaccount, costs properly chargeable to expense that are incurred in the

performance of any System Impact Studies or Facilities Studies which the

Transmission Provider and/or the Transmission Owner(s) conduct or is(are)

involved in to determine if construction of new facilities or upgrades are required

for the uses of the Transmission Owner(s), including third party sales under the

Tariff. The Transmission Provider and each Transmission Owner shall include in

a separate operating revenue account or subaccount the revenues the Transmission

Provider and Transmission Owner(s) received for its (their) role in conducting

such System Impact Studies or Facilities Studies.

9 Regulatory Filings

Nothing contained in the Tariff or any Service Agreement shall be construed as affecting

in any way the right of the Transmission Provider or Transmission Owner(s) to unilaterally make

application to the Commission for a change in rates, terms and conditions, charges, classification

of service, Service Agreement, rule or regulation under Section 205 of the Federal Power Act

and pursuant to the Commission's rules and regulations promulgated thereunder; provided,

however, the Transmission Provider and the Transmission Owners are restricted in their ability

to make certain changes as detailed in the SPP Membership Agreement.

Nothing contained in the Tariff or any Service Agreement shall be construed as affecting

in any way the ability of any Party receiving service under the Tariff to exercise its rights under

the Federal Power Act and pursuant to the Commission's rules and regulations promulgated

thereunder.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 27FERC Electric TariffFourth Revised Volume No. 1

10 Force Majeure and Indemnification

10.1 Force Majeure: An event of Force Majeure means any act of God, labor

disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood,

explosion, breakage or accident to machinery or equipment, any Curtailment,

order, regulation or restriction imposed by governmental military or lawfully

established civilian authorities, or any other cause beyond a Party's control. A

Force Majeure event does not include an act of negligence or intentional

wrongdoing. Neither the Transmission Provider, the Transmission Owner(s), nor

the Transmission Customer will be considered in default as to any obligation

under this Tariff if prevented from fulfilling the obligation due to an event of

Force Majeure. However, a Party whose performance under this Tariff is

hindered by an event of Force Majeure shall make all reasonable efforts to

perform its obligations under this Tariff.

10.2 Indemnification: The Transmission Customer shall at all times indemnify,

defend, and save the Transmission Provider and Transmission Owner(s) harmless

from, any and all damages, losses, claims, including claims and actions relating to

injury to or death of any person or damage to property, demands, suits, recoveries,

costs and expenses, court costs, attorney fees, and all other obligations by or to

third parties, arising out of or resulting from the Transmission Provider's or

Transmission Owner’s(s’) performance of obligations under this Tariff on behalf

of the Transmission Customer, except in cases of negligence or intentional

wrongdoing by the Transmission Provider or a Transmission Owner. If the

Transmission Provider engages in negligence or intentional wrongdoing, but the

Transmission Owner(s) does (do) not, that will not affect the indemnification of

the Transmission Owner(s) under this Section 10.2 and vice-versa.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Substitute First Revised Sheet No. 28FERC Electric Tariff Superseding Original Sheet No. 28Fourth Revised Volume No. 1

11 Creditworthiness

For the purpose of determining the ability of the Transmission Customer to meet its

obligations related to service hereunder, the Transmission Provider may require compliance with

reasonable credit review procedures. This review shall be made in accordance with standard

commercial practices. In addition, the Transmission Provider may require the Transmission

Customer to provide and maintain in effect during the term of the Service Agreement, an

unconditional and irrevocable letter of credit as security to meet its responsibilities and

obligations under the Tariff, or an alternative form of security proposed by the Transmission

Customer and acceptable to the Transmission Provider and consistent with commercial practices

established by the Uniform Commercial Code that protects the Transmission Provider against the

risk of non-payment. The Transmission Provider shall develop creditworthiness standards and

publish them on the OASIS.

12 Dispute Resolution Procedures

12.1 Internal Dispute Resolution Procedures: Any dispute between a Transmission

Customer and the Transmission Provider involving transmission service under the

Tariff (excluding applications for rate changes or other changes to the Tariff, or to

any Service Agreement entered into under the Tariff, which shall be presented

directly to the Commission for resolution) shall be referred to a designated senior

representative of the Transmission Provider and a senior representative of the

Transmission Customer for resolution on an informal basis as promptly as

practicable. In

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: August 8, 2001 Effective: June 1, 2001Filed to comply with order of the Federal Energy Regulatory Commission,Docket No. ER01-1989-000, issued July 9, 2001, 96 FERC ¶ 61,034 (2001).

Southwest Power Pool Original Sheet No. 28AFERC Electric TariffFourth Revised Volume No. 1

the event the designated representatives are unable to resolve the dispute within

thirty (30) days [or such other period as the Parties may agree upon] by mutual

agreement, such dispute may be submitted to arbitration and resolved in

accordance with the arbitration procedures set forth below.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 29FERC Electric TariffFourth Revised Volume No. 1

12.2 External Arbitration Procedures: Any arbitration initiated under the Tariff

shall be conducted before a single neutral arbitrator appointed by the Parties. If

the Parties fail to agree upon a single arbitrator within ten (10) days of the referral

of the dispute to arbitration, each Party shall choose one arbitrator who shall sit on

a three-member arbitration panel, except that if more than two Parties are

involved, the Parties shall agree on procedures to choose these two arbitrators. If

the Parties are unable to agree, then the American Arbitration Association shall be

asked to appoint the arbitrator(s) who must be knowledgeable in matters

involving the electric power industry. The two arbitrators so chosen shall within

twenty (20) days select a third arbitrator to chair the arbitration panel. In either

case, the arbitrators shall be knowledgeable in electric utility matters, including

electric transmission and bulk power issues, and shall not have any current or past

substantial business or financial relationships with any party to the arbitration

(except prior arbitration). The arbitrator(s) shall provide each of the Parties an

opportunity to be heard and, except as otherwise provided herein, shall generally

conduct the arbitration in accordance with the Commercial Arbitration Rules of

the American Arbitration Association and any applicable Commission regulations

or Regional Transmission Group rules.

12.3 Arbitration Decisions: Unless otherwise agreed, the arbitrator(s) shall render a

decision within ninety (90) days of appointment and shall notify the Parties in

writing of such decision and the reasons therefor. The arbitrator(s) shall be

authorized only to interpret and apply the provisions of the Tariff and any Service

Agreement entered into under the Tariff and shall have no power to modify or

change any of the above in any manner. The decision of the arbitrator(s) shall be

final and binding upon the Parties, and

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 30FERC Electric TariffFourth Revised Volume No. 1

judgment on the award may be entered in any court having jurisdiction; provided,

however, that final decisions with the Federal Government as one of the parties

are nonbinding. The decision of the arbitrator(s) may be appealed solely on the

grounds that the conduct of the arbitrator(s), or the decision itself, violated the

standards set forth in the Federal Arbitration Act and/or the Administrative

Dispute Resolution Act. The final decision of the arbitrator must also be filed

with the Commission if it affects jurisdictional rates, terms and conditions of

service or facilities.

12.4 Costs: Each Party shall be responsible for its own costs incurred during the

arbitration process and for the following costs, if applicable:

(A) the cost of the arbitrator chosen by the Party or Parties to sit on the three

member panel and its equal share of the cost of the third arbitrator chosen; or

(B) its equal share of the cost of the single arbitrator jointly chosen by the

Parties.

12.5 Rights Under The Federal Power Act: Nothing in this section shall restrict the

rights of any party to file a Complaint with the Commission under relevant

provisions of the Federal Power Act.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 31FERC Electric TariffFourth Revised Volume No. 1

II. POINT-TO-POINT TRANSMISSION SERVICE

Preamble

The Transmission Provider will provide Firm and Non-Firm Point-To-Point

Transmission Service pursuant to the applicable terms and conditions of this Tariff. Point-To-

Point Transmission Service is for the receipt of capacity and energy at designated Point(s) of

Receipt and the transmission of such capacity and energy to designated Point(s) of Delivery.

13 Nature of Firm Point-To-Point Transmission Service

13.1 Term: The minimum term of Firm Point-To-Point Transmission Service shall be

one day and the maximum term shall be specified in the Service Agreement.

13.2 Reservation Priority: Long-Term Firm Point-To-Point Transmission Service

shall be available on a first-come, first-served basis i.e., in the chronological

sequence in which each Transmission Customer has reserved service.

Reservations for Short-Term Firm Point-To-Point Transmission Service will be

conditional based upon the length of the requested transaction and relative impact

on available transmission capability. If the Transmission System becomes

oversubscribed, requests for longer term service may preempt requests for shorter

term service up to the following deadlines: one day before the commencement of

daily service, one week before the commencement of weekly service, and one

month before the commencement of monthly service. This right of preemption

only applies, however, if the longer term service involves the same Points of

Receipt and Delivery as the shorter term service. Before the conditional

reservation deadline, if available transmission capability is insufficient to satisfy

all Applications, an Eligible Customer with a

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 31AFERC Electric TariffFourth Revised Volume No. 1

reservation for shorter term service has the right of first refusal to match any

longer term reservation before losing its reservation priority. A longer

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 32FERC Electric TariffFourth Revised Volume No. 1

term competing request for Short-Term Firm Point-To-Point Transmission

Service will be granted if the Eligible Customer with the right of first refusal does

not agree to match the competing request within 24 hours (or earlier if necessary

to comply with the scheduling deadlines provided in Section 13.8) from being

notified by the Transmission Provider of a longer-term competing request for

Short-Term Firm Point-To-Point Transmission Service. After the conditional

reservation deadline, service will commence pursuant to the terms of Part II of the

Tariff. Firm Point-To-Point Transmission Service will always have a reservation

priority over Non-Firm Point-To-Point Transmission Service under the Tariff or

non-firm transmission service under Grandfathered Agreements. All Long-Term

Firm Point-To-Point Transmission Service will have equal reservation priority

with Native Load Customers and Network Customers. Reservation priorities for

existing firm service customers are provided in Section 2.2.

13.3 Use of Firm Transmission Service by the Transmission Owners: Each

Transmission Owner will be subject to the rates, terms and conditions of Part II of

the Tariff when making Third-Party Sales under (i) agreements executed on or

after the Effective Date of the Tariff or (ii) agreements executed prior to the

aforementioned date that the Commission requires to be unbundled after the

Effective Date of the Tariff.

13.4 Service Agreements: The Transmission Provider shall offer a standard form

Firm Point-To-Point Transmission Service Agreement (Attachment A) to an

Eligible Customer when it submits a Completed Application for Long-Term Firm

Point-To-Point Transmission Service. The Transmission Provider shall offer a

standard form Firm Point-To-Point Transmission Service Agreement (Attachment

A) to an Eligible Customer when it first submits a Completed Application for

Short-Term Firm Point-To-Point Transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 33FERC Electric TariffFourth Revised Volume No. 1

Service pursuant to the Tariff. Transactions under the Short-Term Firm Point-To-

Point Transmission Service Agreement shall be arranged by providing the

information listed in Section 17.2 of the Tariff and on the confirmation sheet

contained in Attachment Q. Executed Service Agreements that contain the

information required under the Tariff shall be filed with the Commission in

compliance with applicable Commission regulations.

13.5 Transmission Customer Obligations for Facility Additions or Redispatch

Costs: In cases where the Transmission Provider determines that the

Transmission System is not capable of providing Firm Point-To-Point

Transmission Service without (1) degrading or impairing the reliability of service

to Native Load Customers, Network Customers and other Transmission

Customers taking Firm Point-To-Point Transmission Service, or (2) interfering

with a(the) Transmission Owner's(s’) ability to meet prior firm contractual

commitments to others, the relevant Transmission Owner(s) will be obligated to

expand or upgrade its (their) Transmission System(s) pursuant to the terms of

Section 15.4. The Transmission Customer must agree to pay the Transmission

Provider for any necessary transmission facility additions pursuant to the terms of

Section 27. To the extent a system constraint can be relieved more economically

by redispatching electric generating resources than through constructing Network

Upgrades, the procedures in Attachment K shall apply, provided that the Eligible

Customer agrees to compensate the Transmission Provider pursuant to the terms

of Section 27. Any redispatch, Network Upgrade or Direct Assignment Facilities

costs to be charged to the Transmission Customer on an incremental basis under

the Tariff will be specified in the Service Agreement prior to initiating service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 34FERC Electric TariffFourth Revised Volume No. 1

13.6 Curtailment of Firm Transmission Service: In the event that a Curtailment on

the Transmission Provider’s Transmission System, or a portion thereof, is

required to maintain reliable operation of such System and the systems directly

and indirectly connected with the Transmission System, Curtailments will be

made on a non-discriminatory basis to the transaction(s) that effectively relieve

the constraint. The Transmission Provider may elect to implement such

Curtailments pursuant to the Transmission Loading Relief procedures specified in

Attachment R. If multiple transactions require Curtailment, to the extent

practicable and consistent with Good Utility Practice, the Transmission Provider

will curtail (or cause to be curtailed) service to Network Customers and

Transmission Customers taking Firm Point-To-Point Transmission Service on a

basis comparable to the curtailment of service to the Transmission Owner’s(s’)

Native Load Customers, and to transmission customers taking firm transmission

service under Grandfathered Agreements. All Curtailments will be made on a

non-discriminatory basis; however, Non-Firm Point-To-Point Transmission

Service as well as any non-firm transmission service provided under

Grandfathered Agreements shall be subordinate to Firm Point-To-Point

Transmission Service. When the Transmission Provider determines that an

electrical emergency exists on the Transmission System and implements

emergency procedures to Curtail Firm Transmission Service, the Transmission

Customer shall make the required reductions upon request of the Transmission

Provider. However, the Transmission Provider reserves the right to Curtail or to

effect the Curtailment of, in whole or in part, any Firm Transmission Service

provided under the Tariff when, in the Transmission Provider's sole discretion, an

emergency or other unforeseen condition impairs or degrades the reliability of the

Transmission System. The Transmission Provider will notify all

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 35FERC Electric TariffFourth Revised Volume No. 1

affected Transmission Customers in a timely manner of any scheduled

Curtailments. In the event that the Transmission Customer fails to cease or

reduce service in response to a directive by the Transmission Provider, the

Transmission Customer shall pay any applicable charges and the following

penalty (in addition to the charges for all of the firm capacity used): 200% of the

Firm Point-to-Point Transmission Service charge for the entire length of the

reserved period but not exceeding one month. This penalty shall apply only to the

portion of the service that the Transmission Customer fails to curtail in response

to a Curtailment directive. These penalty revenues shall reduce the Transmission

Provider’s administrative costs.

13.7 Classification of Firm Transmission Service:

(a) The Transmission Customer taking Firm Point-To-Point Transmission

Service may (1) change its Receipt and Delivery Points to obtain service

on a non-firm basis consistent with the terms of Section 22.1 or (2) request

a modification of the Points of Receipt or Delivery on a firm basis

pursuant to the terms of Section 22.2.

(b) The Transmission Customer may purchase transmission service to make

sales of capacity and energy from multiple generating units that are on the

Transmission Provider's Transmission System. For such a purchase of

transmission service, the resources will be designated as multiple Points of

Receipt, unless (i) the multiple generating units are at the same generating

plant in which case the units would be treated as a single Point of Receipt,

or (ii) the generating units or plants are in the same Control Area of a

Transmission Owner in which case the units or plants also would be

considered as a single Point of Receipt; provided, however, that generation

which is dynamically scheduled

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 36FERC Electric TariffFourth Revised Volume No. 1

shall be considered as part of the Control Area where it is physically

located. In the event of a change in the ownership or control of generation

resources previously aggregated as a single Point of Receipt under this

provision, such generation may be disaggregated and treated as multiple

Points of Receipt, provided that all other terms of this Tariff and the

Service Agreement are met.

(c) The Transmission Provider shall provide firm deliveries of capacity and

energy from the Point(s) of Receipt to the Point(s) of Delivery. Each

Point of Receipt at which firm transmission capacity is reserved by the

Transmission Customer shall be set forth in the Firm Point-To-Point

Service Agreement for Long-Term Firm Transmission Service along with

a corresponding capacity reservation associated with each Point of

Receipt. Points of Receipt and corresponding capacity reservations shall

be as mutually agreed upon by the Parties for Short-Term Firm

Transmission. Each Point of Delivery at which firm transmission capacity

is reserved by the Transmission Customer shall be set forth in the Firm

Point-To-Point Service Agreement for Long-Term Firm Transmission

Service along with a corresponding capacity reservation associated with

each Point of Delivery. Points of Delivery and corresponding capacity

reservations shall be as mutually agreed upon by the Parties for Short-

Term Firm Transmission. The greater of either (1) the sum of the capacity

reservations at the Point(s) of Receipt, or (2) the sum of the capacity

reservations at the Point(s) of Delivery shall be the Transmission

Customer's Reserved Capacity. The Transmission Customer will be billed

for its Reserved Capacity under the terms of Schedule 7. The

Transmission Customer may not exceed its firm capacity

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 37FERC Electric Tariff Superseding Original Sheet No. 37Fourth Revised Volume No. 1

reserved at each Point of Receipt and each Point of Delivery except as

otherwise specified in Section 22. In the event that a Transmission

Customer (including Third-Party Sales by a Transmission Owner) exceeds

its firm reserved capacity at any Point of Receipt or Point of Delivery, the

Transmission Customer shall pay the following penalty (in addition to the

applicable charges for all of the firm capacity actually used): 200% of the

Firm Point-to-Point Transmission Service charge for the period for which

the additional service was actually used. The charges for the additional

service shall be based upon the duration of the period when the additional

capacity was used. For example, one hour would be billed at the charge

for weekday deliveries. The Transmission Provider shall compensate the

Transmission Owners for 100% of the Firm Point-to-Point Transmission

Service charge for the period for which they have provided service. The

penalty revenues in excess of that amount shall be used to reduce the

Transmission Provider’s administrative costs. For the amounts exceeding

reserved capacity, the Transmission Customer also must replace losses as

required by this Tariff.

13.8 Scheduling of Firm Point-To-Point Transmission Service: All scheduling

practices and schedules submitted by Transmission Customers will comply with

applicable North American Electric Reliability Council Policies and SPP Criteria.

Transmission Customers shall submit all schedules electronically in a form

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 37AFERC Electric TariffFourth Revised Volume No. 1

specified by the Transmission Provider. Schedules for the Transmission

Customer's Firm Point-To-Point Transmission Service must be submitted to the

Transmission Provider in accordance with the times in Attachment P. Schedules

submitted after the applicable time specified on Attachment P will be

accommodated, if practicable. Hour-to-hour schedules of any capacity and

energy that is to be delivered must be stated in increments of 1,000 kW per hour.

Transmission Customers within a Transmission Owner's

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 38FERC Electric TariffFourth Revised Volume No. 1

service (or control) area with multiple requests for Transmission Service at a

Point of Receipt, each of which is under 1,000 kW per hour, may consolidate their

service requests at a common point of receipt into units of 1,000 kW per hour for

scheduling and billing purposes. Scheduling changes will be accommodated as

provided in Attachment P. However, in the event of a system contingency such as

a generation or transmission outage, or curtailment or interruption of transmission

service, scheduling changes will be implemented as soon as practicable. The

Transmission Provider will furnish to the Delivering Party's system operator,

hour-to-hour schedules equal to those furnished by the Receiving Party (unless

reduced for losses) and shall deliver the capacity and energy provided by the

Delivering Party. Should the Transmission Customer, Delivering Party or

Receiving Party revise or terminate any schedule, such party shall immediately

notify the Transmission Provider, and the Transmission Provider shall have the

right to adjust accordingly the schedule for capacity and energy to be received and

to be delivered.

14 Nature of Non-Firm Point-To-Point Transmission Service

14.1 Term: Non-Firm Point-To-Point Transmission Service will be available for

periods ranging from one (1) hour to one (1) month. However, a Purchaser of

Non-Firm Point-To-Point Transmission Service will be entitled to reserve a

sequential term of service (such as a sequential monthly term without having to

wait for the initial term to expire before requesting another monthly term) so that

the total time period for which the reservation applies is greater than one month,

subject to the requirements of Section 18.3.

14.2 Reservation Priority: Non-Firm Point-To-Point Transmission Service shall be

available from transmission capability in excess of that needed for reliable service

to Native Load Customers,

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 39FERC Electric TariffFourth Revised Volume No. 1

Network Customers, and other Transmission Customers taking Long- Term and

Short-Term Firm Point-To-Point Transmission Service and customers under other

transmission tariffs or agreements taking network or firm point-to-point

transmission service from the Transmission Owner(s). A higher priority will be

assigned to reservations with a longer duration of service involving the same

Points of Receipt and Delivery. In the event the Transmission System is

constrained, competing requests of equal duration involving the same Points of

Receipt and Delivery will be prioritized based on the highest price offered by the

Eligible Customer for the Transmission Service; provided, however, this

provision assigning priority based upon the highest price offered shall not affect

the priority of transmission contracts not under this Tariff. Eligible Customers

that have already reserved shorter term service have the right of first refusal to

match any longer term reservation before being preempted. A longer term

competing request for Non-Firm Point-To-Point Transmission Service will be

granted if the Eligible Customer with the right of first refusal does not agree to

match the competing request: (a) immediately for hourly Non-Firm Point-To-

Point Transmission Service after notification by the Transmission Provider; and

(b) within 24 hours (or earlier if necessary to comply with the scheduling

deadlines provided in Section 14.6) for Non-Firm Point-To-Point Transmission

Service other than hourly transactions after notification by the Transmission

Provider. Transmission service for Network Customers and for network

customers under Grandfathered Agreements involving the affected Transmission

Owner(s) from resources other than designated Network Resources will have a

higher priority than any Non-Firm Point-To-Point Transmission Service. Non-

Firm Point-To-Point Transmission Service over secondary Point(s) of Receipt and

Point(s) of

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 40FERC Electric Tariff Superseding Original Sheet No. 40Fourth Revised Volume No. 1

Delivery will have the second lowest reservation priority under the Tariff, and

Non-Firm Point-To-Point Transmission Service used for Next-Hour-Market

Service will have the lowest reservation priority under the Tariff.

14.3 Use of Non-Firm Point-To-Point Transmission Service by the Transmission

Owner(s): Each Transmission Owner will be subject to the rates, terms and

conditions of Part II of the Tariff when making Third-Party Sales under (i)

agreements executed on or after the Effective Date of the Tariff or (ii) agreements

executed prior to the aforementioned date that the Commission requires to be

unbundled after the Effective Date of the Tariff.

14.4 Service Agreements: The Transmission Provider shall offer a standard form

Non-Firm Point-To-Point Transmission Service Agreement (Attachment B) to an

Eligible Customer when it first submits a Completed Application for Non-Firm

Point-To-Point Transmission Service pursuant to the Tariff. Transactions under

this Non-Firm Point-To-Point Transmission Service Agreement shall be arranged

by providing the information on the confirmation sheet which is contained in

Attachment Q. Executed Service Agreements that contain the information

required under the Tariff shall be filed with the Commission in compliance with

applicable Commission regulations.

14.5 Classification of Non-Firm Point-To-Point Transmission Service: Non-Firm

Point-To-Point Transmission Service shall be offered under terms and conditions

contained in Part II of the Tariff. The Transmission Provider and Transmission

Owners undertake no obligation under the Tariff to plan the Transmission System

in order to have sufficient capacity for Non-Firm Point-To-Point Transmission

Service. Parties requesting Non-Firm Point-To-Point

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 41FERC Electric Tariff Superseding Original Sheet No. 41Fourth Revised Volume No. 1

Transmission Service for the transmission of firm power do so with the full

realization that such service is subject to availability and to Curtailment or

Interruption under the terms of the Tariff. In the event that a Transmission

Customer (including Third-Party Sales by a Transmission Owner) exceeds its

non-firm capacity reservation, the Transmission Customer shall pay the following

penalty (in addition to the charges for all of the non-firm capacity used): 200% of

the Non-Firm Point-to-Point Transmission Service Charge for the entire length of

the reserved period not to exceed one month for the amount in excess of such

capacity reservation. The Transmission Provider shall compensate the

Transmission Owners for 100% of the Non-Firm Point-to-Point Transmission

Service charge for the period for which they have provided service. The penalty

revenues in excess of that amount shall be used to reduce the Transmission

Provider’s administrative costs. For the amounts exceeding the non-firm capacity

reservation, the Transmission Customer must replace losses as required by this

Tariff. Non-Firm Point-To-Point Transmission Service shall include transmission

of energy on an hourly basis and transmission of scheduled short-term capacity

and energy on a daily, weekly or monthly basis, but not to exceed one month's

reservation for any one Application, under Schedule 8.

14.6 Scheduling of Non-Firm Point-To-Point Transmission Service: All

scheduling practices and schedules submitted by Transmission Customers will be

consistent with applicable North American Electric Reliability Council Policies

and SPP Criteria. Transmission Customers shall submit all schedules

electronically in a form specified by The Transmission Provider. Schedules for

Non-Firm Point-To-Point Transmission Service, other than for Next-Hour-Market

Service, must be submitted to the Transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 42FERC Electric Tariff Superseding Original Sheet No. 42Fourth Revised Volume No. 1

Provider in accordance with the times in Attachment P. Schedules submitted after

the applicable time specified in Attachment P will be accommodated if

practicable. Schedules for Non-Firm Point-To-Point Transmission Service for

Next-Hour-Market Service must be submitted to the Transmission Provider no

later than 20 minutes and no earlier than 60 minutes before the start of the next

clock hour. Schedules submitted less than 20 minutes prior to the start of the next

clock hour will be accommodated, if practicable. Hour-to-hour schedules of

energy that is to be delivered must be stated in increments of 1,000 kW per hour.

Transmission Customers within a Transmission Owner's service area (or Control

Area) with multiple requests for Transmission Service at a Point of Receipt, each

of which is under 1,000 kW per hour, may consolidate their schedules at a

common Point of Receipt into units of 1,000 kW per hour. Scheduling changes

will be accommodated in accordance with Attachment P. The Transmission

Provider will furnish to the Delivering Party's system operator, hour-to-hour

schedules equal to those furnished by the Receiving Party (unless reduced for

losses) and shall deliver the capacity and energy provided by the Delivering Party.

Should the Transmission Customer, Delivering Party or Receiving Party revise or

terminate any schedule, such party shall immediately notify the Transmission

Provider, and the Transmission Provider shall have the right to adjust accordingly

the schedule for capacity and energy to be received and to be delivered.

14.7 Curtailment or Interruption of Service: The Transmission Provider reserves

the right to Curtail (or cause to be Curtailed), in whole or in part, Non-Firm Point-

To-Point Transmission Service provided under the Tariff for reliability reasons

when, an emergency or

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 43FERC Electric Tariff Superseding Original Sheet No. 43Fourth Revised Volume No. 1

other unforeseen condition threatens to impair or degrade the reliability of the

Transmission System or the systems directly or indirectly interconnected with the

Transmission Provider’s Transmission System. The Transmission Provider may

elect to implement such Curtailments pursuant to the Transmission Loading

Relief procedures specified in Attachment R. The Transmission Provider reserves

the right to Interrupt(or to effect the Interruption of), in whole or in part, Non-

Firm Point-To-Point Transmission Service provided under the Tariff for

economic reasons in order to accommodate (1) a request for Firm Transmission

Service under this Tariff or for firm transmission service provided by a

Transmission Owner under a Grandfathered Agreement, (2) a request for Non-

Firm Point-To-Point Transmission Service, from the same Point of Receipt to the

same Point of Delivery, of greater duration under this Tariff or for non-firm

transmission of greater duration provided by a Transmission Owner under a

Grandfathered Agreement, (3) a request for Non-Firm Point-To-Point

Transmission Service, from the same Point of Receipt to the same Point of

Delivery, of equal duration with a higher price under this Tariff or for non-firm

transmission of equal duration, from the same Point of Receipt to the same Point

of Delivery, with a higher price provided by a Transmission Owner under a

Grandfathered Agreement, or (4) transmission service for Network Customers

from non-designated resources under this Tariff or under a Grandfathered

Agreement. Point-to-Point Transmission Service for Next-Hour-Market Service

will always have the lowest priority. The Transmission Provider also will

discontinue or reduce service to the Transmission Customer to the extent that

deliveries for transmission are discontinued or reduced at the Point(s) of Receipt.

Where required, Curtailments or Interruptions will be

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 44FERC Electric Tariff Superseding Original Sheet No. 44Fourth Revised Volume No. 1

made on a non-discriminatory basis to the transaction(s) that effectively relieve

the constraint; however, Non-Firm Point-To-Point Transmission Service shall be

subordinate to Firm Transmission Service under this Tariff or firm transmission

service provided by a Transmission Owner under Grandfathered agreements. If

multiple transactions require Curtailment or Interruption, to the extent practicable

and consistent with Good Utility Practice, Curtailments or Interruptions will be

made first to Next-Hour-Market Service and then to remaining transactions

beginning with those to transactions of the shortest term (e.g., hourly non-firm

transactions will be Curtailed or Interrupted before daily non-firm transactions

and daily non-firm transactions will be Curtailed or Interrupted before weekly

non-firm transactions). Transmission service for Network Customers from

resources other than designated Network Resources will have a higher priority

than any Non-Firm Point-To-Point Transmission Service under the Tariff. Non-

Firm Point-To-Point Transmission Service over secondary Point(s) of Receipt and

Point(s) of Delivery will have a higher priority than Next-Hour-Market Service,

but will have a lower priority than any other Non-Firm Point-To-Point

Transmission Service under the Tariff. The Transmission Provider will provide

advance notice of Curtailment or Interruption where such notice can be provided

consistent with Good Utility Practice. In the event that the Transmission

Customer fails to cease or reduce service in response to a directive by the

Transmission Provider, the Transmission Customer shall pay any applicable

charges and the following penalty (in addition to the charges for all of the non-

firm capacity used):

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 44AFERC Electric TariffFourth Revised Volume No. 1

200% of the Non-Firm Point-to-Point Transmission Service Charge for the entire

length of the reserved period not to exceed one month for the amount in excess of

such capacity reservation. This penalty shall apply only to the portion of the

service that the Transmission Customer fails to curtail in response to a

Curtailment directive. These penalty revenues shall reduce the Transmission

Provider’s administrative costs.

15 Service Availability

15.1 General Conditions: The Transmission Provider will provide Firm and Non-

Firm Point-To-Point Transmission Service over, on or across its Transmission

System to any Transmission Customer that has met the requirements of Section

16.

15.2 Determination of Available Transmission Capability: A description of the

Transmission Provider’s specific methodology for assessing available

transmission capability posted on the Transmission Provider’s OASIS (Section 4)

is contained in Attachment C of the Tariff. In the event sufficient transmission

capability may not exist to accommodate a service request, the Transmission

Provider will respond by offering to perform or cause to be performed a System

Impact Study.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 45FERC Electric TariffFourth Revised Volume No. 1

15.3 Initiating Service in the Absence of an Executed Service Agreement: If the

Transmission Provider and the Transmission Customer requesting Firm or Non-

Firm Point-To-Point Transmission Service cannot agree on all the terms and

conditions of the Point-To-Point Service Agreement, the Transmission Provider

shall file with the Commission, within thirty (30) days after the date the

Transmission Customer provides written notification directing the Transmission

Provider to file, an unexecuted Point-To-Point Service Agreement containing

terms and conditions deemed appropriate by the Transmission Provider for such

requested Transmission Service. The Transmission Provider shall commence

providing Transmission Service subject to the Transmission Customer agreeing to

(i) compensate the Transmission Provider at whatever rate the Commission

ultimately determines to be just and reasonable, and (ii) comply with the terms

and conditions of the Tariff including posting appropriate security deposits in

accordance with the terms of Section 17.3.

15.4 Obligation to Provide Transmission Service that Requires Expansion or

Modification of the Transmission System: If the Transmission Provider

determines that it cannot accommodate a Completed Application for Firm Point-

To-Point Transmission Service because of insufficient capability on the

Transmission System, the Transmission Provider and the affected Transmission

Owner(s) will use due diligence to expand or modify the Transmission System to

provide the requested Firm Transmission Service, provided the Transmission

Customer agrees to compensate the Transmission Provider for such costs pursuant

to the terms of Section 27. The Transmission Provider and the affected

Transmission Owner(s) will conform to Good Utility Practice in determining the

need for new facilities and in the design and construction of such facilities.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 46FERC Electric TariffFourth Revised Volume No. 1

The obligation applies only to those facilities that the affected Transmission

Owner(s) has (have) the right to expand or modify.

15.5 Deferral of Service: The Transmission Provider may defer providing service

until construction is completed of new transmission facilities or upgrades needed

to provide Firm Point-To-Point Transmission Service whenever the Transmission

Provider determines that providing the requested service would, without such new

facilities or upgrades, impair or degrade reliability to any existing firm services.

15.6 Other Transmission Service Schedules: Eligible Customers receiving

transmission service under Grandfathered Transactions may continue to receive

transmission service under those agreements until such time as those agreements

may be modified by the Commission.

15.7 Real Power Losses: Real Power Losses are associated with all transmission

service. The applicable Real Power Loss factors are as specified in the loss

compensation matrices developed in accord with Attachment M. As stated on

Schedules 7 and 8, the Transmission Customer shall replace losses in accordance

with Attachment M.

16 Transmission Customer Responsibilities

16.1 Conditions Required of Transmission Customers: Point-To-Point

Transmission Service shall be provided under this Tariff only if the following

conditions are satisfied by the Transmission Customer:

a. The Transmission Customer has pending a Completed Application for

service;

b. The Transmission Customer meets the creditworthiness criteria set forth in

Section 11;

c. The Transmission Customer will have arrangements in place for any other

transmission service necessary to effect the

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 47FERC Electric TariffFourth Revised Volume No. 1

delivery from the generating source to the Transmission Provider prior to

the time service under Part II of the Tariff commences;

d. The Transmission Customer agrees to pay for any facilities constructed

and chargeable to such Transmission Customer under Part II of the Tariff,

whether or not the Transmission Customer takes service for the full term

of its reservation; and

e. The Transmission Customer has executed a Point-To-Point Service

Agreement or has agreed to receive service pursuant to Section 15.3.

16.2 Transmission Customer Responsibility for Third-Party Arrangements: Any

scheduling arrangements that may be required by other electric systems shall be

the responsibility of the Transmission Customer requesting service. The

Transmission Customer shall provide, unless waived by the Transmission

Provider, notification to the Transmission Provider identifying such systems and

authorizing them to schedule the capacity and energy to be transmitted by the

Transmission Provider pursuant to Part II of the Tariff on behalf of the Receiving

Party at the Point of Delivery or the Delivering Party at the Point of Receipt.

However, the Transmission Provider will undertake reasonable efforts to assist

the Transmission Customer in making such arrangements, including without

limitation, providing any information or data required by such other electric

system pursuant to Good Utility Practice.

17 Procedures for Arranging Firm Point-To-Point Transmission Service

17.1 Application: A request for Firm Point-To-Point Transmission Service for

periods of one year or longer must contain a written Application to: Southwest

Power Pool, 415 North McKinley, 700 Plaza West, Little Rock, AR 72205-3020,

at least sixty (60) days in advance of the calendar month in which service is to

commence

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 48FERC Electric TariffFourth Revised Volume No. 1

The Transmission Provider will consider requests for such firm service on shorter

notice when feasible. Requests for firm service for periods of less than one year

shall be subject to expedited procedures that shall be negotiated between the

Parties within the time constraints provided in Section 17.5. All Firm Point-To-

Point Transmission Service requests should be submitted by entering the

information listed in Section 17.2 on the Transmission Provider's OASIS.

17.1a Time Requirements: Attachment P lists the time requirements applicable to

when the requests must be made, the evaluation of the requests, and the

Transmission Customer responses.

17.2 Completed Application: A Completed Application shall provide all of the

information included in 18 CFR § 2.20 including but not limited to the following:

(i) The identity, address, telephone number and facsimile number of the

entity requesting service;

(ii) A statement that the entity requesting service is, or will be upon

commencement of service, an Eligible Customer under the Tariff;

(iii) The location of the Point(s) of Receipt and Point(s) of Delivery and the

identities of the Delivering Parties and the Receiving Parties;

(iv) The location of the generating facility(ies) supplying the capacity and

energy and the location of the load ultimately served by the capacity and

energy transmitted. The Transmission Provider will treat this information

as confidential except to the extent that disclosure of this information is

required by this Tariff, by regulatory or judicial order, by law or by

statute, for reliability purposes pursuant to Good Utility Practice or

pursuant to RTG transmission information sharing agreements. The

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 49FERC Electric TariffFourth Revised Volume No. 1

Transmission Provider shall treat this information consistent with the

standards of conduct contained in Part 37 of the Commission's regulations;

(v) A description of the supply characteristics of the capacity and energy to be

delivered;

(vi) An estimate of the capacity and energy expected to be delivered to the

Receiving Party;

(vii) The Service Commencement Date and the term of the requested

Transmission Service; and

(viii)The transmission capacity requested for each Point of Receipt and each Point

of Delivery on the Transmission Provider's Transmission System;

customers may combine their requests for service in order to satisfy the

minimum transmission capacity requirement.

The Transmission Provider shall treat this information consistent with the standards of

conduct contained in Part 37 of the Commission's regulations.

17.3 Deposit: A Completed Application for Firm Point-To-Point Transmission

Service also shall include a deposit of either one month's charge for Reserved

Capacity or the full charge for Reserved Capacity for service requests of less than

one month; provided, however, the Transmission Provider shall have the right to

waive deposits on a nondiscriminatory basis for service requests if the

Transmission Provider determines that the Transmission Customer is

creditworthy. If the Application is rejected by the Transmission Provider because

it does not meet the conditions for service as set forth herein, or in the case of

requests for service arising in connection with losing bidders in a Request For

Proposals (RFP), said deposit shall be returned with interest less any reasonable

costs incurred by the Transmission Provider in connection with the review of the

losing bidder's Application. The deposit also will be returned with interest less

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 50FERC Electric TariffFourth Revised Volume No. 1

any reasonable costs incurred by the Transmission Provider if the Transmission

Provider is unable to complete new facilities needed to provide the service. If an

Application is withdrawn or the Eligible Customer decides not to enter into a

Service Agreement for Firm Point-To-Point Transmission Service, the deposit

shall be refunded in full, with interest, less reasonable costs incurred by the

Transmission Provider to the extent such costs have not already been recovered

by the Transmission Provider from the Eligible Customer. The Transmission

Provider will provide to the Eligible Customer a complete accounting of all costs

deducted from the refunded deposit, which the Eligible Customer may contest if

there is a dispute concerning the deducted costs. Deposits associated with

construction of new facilities are subject to the provisions of Section 19. If a

Service Agreement for Firm Point-To-Point Transmission Service is executed, the

deposit, with interest, will be returned to the Transmission Customer upon

expiration or termination of the Service Agreement for Firm Point-To-Point

Transmission Service. Applicable interest shall be computed in accordance with

the Commission's regulations at 18 CFR § 35.19a(a)(2)(iii), and shall be

calculated from the day the deposit check is credited to the Transmission

Provider's account.

17.4 Notice of Deficient Application: If an Application fails to meet the requirements

of the Tariff, the Transmission Provider shall notify the entity requesting service

of the reasons for such failure within the applicable time period shown in

Attachment P for responding to Applications. The Transmission Provider will

attempt to remedy minor deficiencies in the Application through informal

communications with the Eligible Customer. If such efforts are unsuccessful, the

Transmission Provider shall return the Application, along with any deposit, with

interest. Upon receipt of a new or revised Application that fully complies with

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 51FERC Electric TariffFourth Revised Volume No. 1

the requirements of Part II of the Tariff, the Eligible Customer shall be assigned a

new priority consistent with the date of the new or revised Application.

17.5 Response to a Completed Application: Following receipt of a Completed

Application for Firm Point-To-Point Transmission Service, the Transmission

Provider shall make a determination of available transmission capability as

required in Section 15.2. The Transmission Provider shall notify the Eligible

Customer within the applicable times listed in Attachment P after the date of

receipt of a Completed Application either (i) if it will be able to provide service

without performing a System Impact Study or (ii) if such a study is needed to

evaluate the impact of the Application pursuant to Section 19.1. Responses by the

Transmission Provider must be made as soon as practicable to all Completed

Applications (including Applications by the Transmission Owner(s') own

merchant function) and the timing of such responses must be made on a

nondiscriminatory basis.

17.6 Execution of Service Agreement: Whenever the Transmission Provider

determines that a System Impact Study is not required and that the service can be

provided, it shall notify the Eligible Customer within the applicable time periods

allowed to determine available capacity as shown in Attachment P after receipt of

the Completed Application. Where a System Impact Study is required, the

provisions of Section 19 will govern the execution of a Service Agreement or the

confirmation of a Completed Application, whichever is applicable. Failure of an

Eligible Customer to execute and return the Service Agreement or request the

filing of an unexecuted service agreement pursuant to Section 15.3, or to confirm

a Completed Application (subject to completion of the System Impact Study),

whichever is applicable, within the time frames shown in Attachment P will be

deemed a withdrawal and

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Revised Sheet No. 52FERC Electric Tariff Superseding Original Sheet No. 52Fourth Revised Volume No. 1

termination of the Application and any deposit submitted shall be refunded with

interest. Nothing herein limits the right of an Eligible Customer to file another

Application after such withdrawal and termination.

17.7 Extensions for Commencement of Service: The Transmission Customer can

obtain up to five (5) one-year extensions for the commencement of service. The

Transmission Customer may postpone service by paying a non-refundable annual

reservation fee equal to one-month's charge for Firm Transmission Service for

each year or fraction thereof. For extensions of one (1) year or more, the

Transmission Customer must request the extension no later than ninety (90) days

before the Service Commencement Date. For extensions of less than one (1) year,

the Transmission Customer must request the extension no later than sixty (60)

days before the Service Commencement Date. If during any extension for the

commencement of service an Eligible Customer submits a Completed Application

for Firm Transmission Service, and such request can be satisfied only by releasing

all or part of the Transmission Customer's Reserved Capacity, the original

Reserved Capacity will be released unless the following condition is satisfied.

Within thirty (30) days, the original Transmission Customer agrees to pay the

Firm Point-To-Point transmission rate for its Reserved Capacity concurrent with

the new Service Commencement Date. In the event the Transmission Customer

elects to release the Reserved Capacity, the reservation fees or portions thereof

previously paid will be forfeited.

18 Procedures for Arranging Non-Firm Point-To-Point Transmission Service

18.1 Application: Eligible Customers seeking Non-Firm Point-To-Point Transmission

Service must submit a Completed Application to The Transmission Provider.

Applications should be submitted by

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 52AFERC Electric TariffFourth Revised Volume No. 1

entering the information listed below on the Transmission Provider’s OASIS.

18.2 Completed Application: A Completed Application shall provide all of the

information included in 18 CFR § 2.20 including but not limited to the following:

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 53FERC Electric TariffFourth Revised Volume No. 1

(i) The identity, address, telephone number and facsimile number of the

entity requesting service;

(ii) A statement that the entity requesting service is, or will be upon

commencement of service, an Eligible Customer under the Tariff;

(iii) The Point(s) of Receipt and the Point(s) of Delivery;

(iv) The maximum amount of capacity requested at each Point of Receipt and

Point of Delivery; and

(v) The proposed dates and hours for initiating and terminating transmission

service hereunder.

In addition to the information specified above, when required to properly evaluate

system conditions, the Transmission Provider also may ask the

Transmission Customer to provide the following:

(vi) The electrical location of the initial source of the power to be transmitted

pursuant to the Transmission Customer's request for service; and

(vii) The electrical location of the ultimate load.

The Transmission Provider will treat this information in (vi) and (vii) as

confidential at the request of the Transmission Customer except to the

extent that disclosure of this information is required by this Tariff, by

regulatory or judicial order, by law or statute, for reliability purposes

pursuant to Good Utility Practice, or pursuant to RTG transmission

information sharing agreements. The Transmission Provider shall treat

this information consistent with the standards of conduct contained in Part

37 of the Commission's regulations.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 54FERC Electric Tariff Superseding Original Sheet No. 54Fourth Revised Volume No. 1

18.3 Timing of Requests and Responses Regarding Reservation of Non-Firm

Point-To-Point Transmission Service: Attachment P lists the time requirements

applicable to when the requests must be made, the evaluation of the requests, and

the Transmission Customer responses and requests for Next-Hour-Market Service

shall be submitted no earlier than 60 minutes before the start of the next clock

hour. Requests for service, except for Next-Hour-Market Service, received later

than the applicable time prior to the day service is scheduled to commence and

requests for Next–Hour-Market Service submitted later than 20 minutes before

the start of the next clock hour will be accommodated if practicable.

18.4 Determination of Available Transmission Capability: Following receipt of a

tendered schedule, the Transmission Provider will make a determination on a non-

discriminatory basis of available transmission capability pursuant to Section 15.2.

Such determination shall be made in accordance with the applicable time periods

set forth in Attachment P.

19 Additional Study Procedures For Firm Point-To-Point Transmission Service

Requests

19.1 Notice of Need for System Impact Study: After receiving a request for service,

the Transmission Provider shall determine on a non-discriminatory basis whether

a System Impact Study is needed. A description of the methodology for

completing a System Impact Study is provided in Attachment D. If the

Transmission Provider determines that a System Impact Study is necessary to

accommodate the requested service, it shall so inform the Eligible Customer

within the applicable time period allowed to determine available capacity shown

in Attachment P. In such cases, the Transmission Provider shall within thirty (30)

days of receipt of a Completed Application, tender a System Impact Study

Agreement pursuant to

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 54AFERC Electric TariffFourth Revised Volume No. 1

which the Eligible Customer shall agree to reimburse the Transmission Provider

for performing the required System Impact Study including any costs of the

Transmission Owners where applicable. For a service request to remain a

Completed Application, the Eligible Customer shall execute the System Impact

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 55FERC Electric TariffFourth Revised Volume No. 1

Study Agreement and return it to the Transmission Provider within fifteen (15)

days. If the Eligible Customer elects not to execute the System Impact Study

Agreement, its Application shall be deemed withdrawn and its deposit, pursuant

to Section 17.3, shall be returned with interest.

19.2 System Impact Study Agreement and Cost Reimbursement:

(i) The System Impact Study Agreement will clearly specify the Transmission

Provider's estimate of the actual cost, and time for completion of the System

Impact Study. The charge shall not exceed the actual cost of the study. In

performing the System Impact Study, the Transmission Provider shall rely, to the

extent reasonably practicable, on existing transmission planning studies. The

Eligible Customer will not be assessed a charge for such existing studies;

however, the Eligible Customer will be responsible for charges associated with

any modifications to existing planning studies that are reasonably necessary to

evaluate the impact of the Eligible Customer's request for service on the

Transmission System.

(ii) If in response to multiple Eligible Customers requesting service in relation to the

same competitive solicitation, a single System Impact Study is sufficient for the

Transmission Provider to accommodate the requests for service, the costs of that

study shall be prorated among the Eligible Customers.

(iii) Each Transmission Owner shall pay the Transmission Provider for System Impact

Studies that the Transmission Provider conducts on the Owner's behalf in

instances where merchant employees of the Transmission Owner have requested

transmission service, the same as any non-Transmission Owning customer.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 56FERC Electric TariffFourth Revised Volume No. 1

19.3 System Impact Study Procedures: Upon receipt of an executed System Impact

Study Agreement, the Transmission Provider, in coordination with the appropriate

Transmission Owner(s), will use due diligence to complete the required System

Impact Study within a sixty (60) day period. The System Impact Study shall

identify any system constraints and redispatch options, additional Direct

Assignment Facilities or Network Upgrades required to provide the requested

service. In the event that the Transmission Provider is unable to complete the

required System Impact Study within such time period, the Transmission Provider

shall so notify the Eligible Customer and provide an estimated completion date

along with an explanation of the reasons why additional time is required to

complete the required studies. A copy of the completed System Impact Study

and related work papers shall be made available to the Eligible Customer. The

Transmission Provider will use the same due diligence in completing the System

Impact Study for an Eligible Customer as it would use when completing studies

for any Transmission Owner. The Transmission Provider shall notify the Eligible

Customer immediately upon completion of the System Impact Study if the

Transmission System will be adequate to accommodate all or part of a request for

service or that no costs are likely to be incurred for new transmission facilities or

upgrades. In these circumstances, in order for a request to remain a Completed

Application, the Eligible Customer must execute a Service Agreement or request

the filing of an unexecuted Service Agreement pursuant to Section 15.3, or

confirm an accepted Application for service, whichever is applicable, within 15

days of completion of the System Impact Study, or the Application shall be

deemed terminated and withdrawn.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 57FERC Electric TariffFourth Revised Volume No. 1

19.4 Facilities Study Procedures: If a System Impact Study indicates that additions

or upgrades to the Transmission System are needed to supply the Eligible

Customer's service request, the Transmission Provider, within thirty (30) days of

the completion of the System Impact Study, shall tender to the Eligible Customer

a Facilities Study Agreement pursuant to which the Eligible Customer shall agree

to reimburse the Transmission Provider and any affected Transmission Owner(s)

for performing the required Facilities Study. For a service request to remain a

Completed Application, the Eligible Customer shall execute the Facilities Study

Agreement and return it to the Transmission Provider within fifteen (15) days. If

the Eligible Customer elects not to execute the Facilities Study Agreement, its

Application shall be deemed withdrawn and its deposit, pursuant to Section 17.3,

shall be returned with interest. Upon receipt of an executed Facilities Study

Agreement, the Transmission Provider in coordination with the appropriate

Transmission Owner(s) will use due diligence to complete the required Facilities

Study within a sixty (60) day period. If the Transmission Provider together with

the affected Transmission Owner(s) are unable to complete the Facilities Study in

the allotted time period, the Transmission Provider shall notify the Transmission

Customer and provide an estimate of the time needed to reach a final

determination along with an explanation of the reasons that additional time is

required to complete the study. When completed, the Facilities Study will include

a good faith estimate of (i) the cost of Direct Assignment Facilities to be charged

to the Transmission Customer, (ii) the Transmission Customer's appropriate share

of the cost of any required Network Upgrades as determined pursuant to the

provisions of Part II of the Tariff, and (iii) the time required to complete such

construction and initiate the requested service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 58FERC Electric TariffFourth Revised Volume No. 1

The Transmission Customer shall provide the Transmission Provider with a letter

of credit or other reasonable form of security acceptable to the Transmission

Provider equivalent to the costs of new facilities or upgrades consistent with

commercial practices as established by the Uniform Commercial Code. Within

the time set out in Attachment P, the Transmission Customer shall execute a

Service Agreement or request the filing of an unexecuted Service Agreement and

provide the required letter of credit or other form of security or the request will no

longer be a Completed Application and shall be deemed terminated and

withdrawn.

19.5 Facilities Study Modifications: Any change in design arising from inability to

site or construct facilities as proposed will require development of a revised good

faith estimate. New good faith estimates also will be required in the event of new

statutory or regulatory requirements that are effective before the completion of

construction or other circumstances beyond the control of the Transmission

Provider or the affected Transmission Owner(s) that significantly affect the final

cost of new facilities or upgrades to be charged to the Transmission Customer

pursuant to the provisions of Part II of the Tariff.

19.6 Due Diligence in Completing New Facilities: The Transmission Provider and

the affected Transmission Owner(s) shall use due diligence to add necessary

facilities or upgrade the Transmission System within a reasonable time. The

Transmission Provider will not allow the upgrade to the existing or planned

Transmission System in order to provide the requested Firm Point-To-Point

Transmission Service if doing so would impair system reliability or otherwise

impair or degrade existing firm service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 59FERC Electric TariffFourth Revised Volume No. 1

19.7 Partial Interim Service: If the Transmission Provider determines that there will

not be adequate transmission capability to satisfy the full amount of a Completed

Application for Firm Point-To-Point Transmission Service, the Transmission

Provider nonetheless shall be obligated to offer and provide the portion of the

requested Firm Point-To-Point Transmission Service that can be accommodated

without addition of any facilities and through redispatch. However, the

Transmission Provider shall not be obligated to provide the incremental amount

of requested Firm Point-To-Point Transmission Service that requires the addition

of facilities or upgrades to the Transmission System until such facilities or

upgrades have been placed in service.

19.8 Expedited Procedures for New Facilities: In lieu of the procedures set forth

above, the Eligible Customer shall have the option to expedite the process by

requesting the Transmission Provider to tender at one time, together with the

results of required studies, an "Expedited Service Agreement" pursuant to which

the Eligible Customer would agree to compensate the Transmission Provider and

affected Transmission Owner(s) for all costs incurred pursuant to the terms of the

Tariff. In order to exercise this option, the Eligible Customer shall request in

writing an Expedited Service Agreement covering all of the above-specified items

within the time limits set forth in Attachment P from the time it receives the

results of the System Impact Study identifying needed facility additions or

upgrades or costs incurred in providing the requested service. While the

Transmission Provider and affected Transmission Owner(s) agrees (agree)to

provide the Eligible Customer with their best estimate of the new facility costs

and other charges that may be incurred, such estimate shall not be binding and the

Eligible Customer must agree in writing to compensate the Transmission Provider

and

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 60FERC Electric TariffFourth Revised Volume No. 1

affected Transmission Owner(s) for all costs incurred pursuant to the provisions

of the Tariff. The Eligible Customer shall execute and return such an Expedited

Service Agreement within fifteen (15) days of its receipt or the Eligible

Customer's request for service will cease to be a Completed Application and will

be deemed terminated and withdrawn.

20 Procedures if The Transmission Provider is Unable to Complete New Transmission

Facilities for Firm Point-To-Point Transmission Service

20.1 Delays in Construction of New Facilities: If any event occurs that will

materially affect the time for completion of new facilities, or the ability to

complete them, the Transmission Provider shall promptly notify the Transmission

Customer. In such circumstances, the Transmission Provider shall within thirty

(30) days of notifying the Transmission Customer of such delays, convene a

technical meeting with the Transmission Customer and affected Transmission

Owner(s) to evaluate the alternatives available to the Transmission Customer.

The Transmission Provider also shall make available to the Transmission

Customer studies and work papers related to the delay, including all information

that is in the possession of the Transmission Provider and affected Transmission

Owner(s) that is reasonably needed by the Transmission Customer to evaluate any

alternatives.

20.2 Alternatives to the Original Facility Additions: When the review process of

Section 20.1 determines that one or more alternatives exist to the originally

planned construction project, the Transmission Provider together with the affected

Transmission Owner(s) shall present such alternatives for consideration by the

Transmission Customer. If, upon review of any alternatives, the Transmission

Customer desires to maintain its Completed Application subject to construction

of the alternative facilities, it may request the Transmission Provider to submit a

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 61FERC Electric TariffFourth Revised Volume No. 1

revised Service Agreement for Firm Point-To-Point Transmission Service. If the

alternative approach solely involves Non-Firm Point-To-Point Transmission

Service, the Transmission Provider shall promptly tender a Service Agreement for

Non-Firm Point-To-Point Transmission Service providing for the service. In the

event the Transmission Provider concludes that no reasonable alternative exists

and the Transmission Customer disagrees, the Transmission Customer may seek

relief under the dispute resolution procedures pursuant to Section 12 or it may

refer the dispute to the Commission for resolution.

20.3 Refund Obligation for Unfinished Facility Additions: If the Transmission

Provider and the Transmission Customer mutually agree that no other reasonable

alternatives exist and the requested service cannot be provided out of existing

capability under the conditions of Part II of the Tariff, the obligation to provide

the requested Firm Point-To-Point Transmission Service shall terminate and any

deposit made by the Transmission Customer shall be returned with interest

pursuant to Commission regulations 35.19a(a)(2)(iii). However, the Transmission

Customer shall be responsible for all prudently incurred costs by the Transmission

Provider and the affected Transmission Owner(s) through the time construction

was suspended.

21 Provisions Relating to Transmission Construction and Services on the Systems of

Other Utilities

21.1 Responsibility for Third-Party System Additions: The Transmission Provider

and the Transmission Owners shall not be responsible for making arrangements

for any necessary engineering, permitting, and construction of transmission or

distribution facilities on the system(s) of any other entity or for obtaining any

regulatory approval for such facilities. The Transmission Provider and the

affected Transmission Owner(s) will undertake reasonable efforts

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 62FERC Electric TariffFourth Revised Volume No. 1

to assist the Transmission Customer in obtaining such arrangements, including

without limitation, providing any information or data required by such other

electric system pursuant to Good Utility Practice.

21.2 Coordination of Third-Party System Additions: In circumstances where the

need for transmission facilities or upgrades is identified pursuant to the provisions

of Part II of the Tariff, and if such upgrades further require the addition of

transmission facilities on other systems, the affected Transmission Owner(s) in

coordination with the Transmission Provider shall have the right to coordinate

construction on its (their) own system(s) with the construction required by others.

The Transmission Provider together with the affected Transmission Owner(s),

after consultation with the Transmission Customer and representatives of such

other systems, may defer construction of its new transmission facilities, if the new

transmission facilities on another system cannot be completed in a timely manner.

The Transmission Provider shall notify the Transmission Customer in writing of

the basis for any decision to defer construction and the specific problems which

must be resolved before construction of new facilities will be initiated or resumed.

Within sixty (60) days of receiving written notification by the Transmission

Provider of the intent to defer construction pursuant to this section, the

Transmission Customer may challenge the decision in accordance with the

dispute resolution procedures pursuant to Section 12 or it may refer the dispute to

the Commission for resolution.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 63FERC Electric TariffFourth Revised Volume No. 1

22 Changes in Service Specifications

22.1 Modifications On a Non-Firm Basis: The Transmission Customer taking Firm

Point-To-Point Transmission Service may request the provision of transmission

service on a non-firm basis over Receipt and Delivery Points other than those

specified in the Service Agreement for Long-Term Firm Transmission Service or

the confirmed Application for Short-Term Transmission Service ("Secondary

Receipt and Delivery Points"), in amounts not to exceed its firm capacity

reservation, without incurring an additional Non-Firm Point-to-Point

Transmission Service charge (except as provided in Section 22.1a) or executing a

new Service Agreement for Long-Term Firm Transmission Service or submitting

a new Application for Short-Term Firm Transmission Service, subject to the

following conditions.

(a) Service provided over Secondary Receipt and Delivery Points will be non-

firm only, on an as-available basis and will not displace any firm or non-

firm service reserved or scheduled by third-parties under the Tariff or

under any other transmission tariff or agreement where the service is being

provided by the Transmission Owner or by the Transmission Owner on

behalf of its (their) Native Load Customers.

(b) The sum of all Firm and Non-Firm Point-To-Point Transmission Service

provided to the Transmission Customer at any time pursuant to this

section shall not exceed the Reserved Capacity in the relevant Service

Agreement for Long-Term Firm Transmission or Application for Short-

Term Firm Transmission Service under which such services are provided.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 64FERC Electric TariffFourth Revised Volume No. 1

(c) The Transmission Customer shall retain its right to schedule Firm Point-

To-Point Transmission Service at the Receipt and Delivery Points

specified in the relevant Service Agreement for Long-Term Firm

Transmission or Application for Short-Term Firm Transmission Service in

the amount of its original capacity reservation.

(d) Service over Secondary Receipt and Delivery Points on a non-firm basis

shall not require the filing of an Application for Non-Firm Point-To-Point

Transmission Service under the Tariff. However, all other requirements of

Part II of the Tariff (except as to transmission rates) shall apply to

transmission service on a non-firm basis over Secondary Receipt and

Delivery Points.

22.1a Additional Charge To Prevent Abuse: If a Transmission Customer making the

modifications in Section 22.1 takes service over a transmission path that costs

more than the path the Transmission Customer initially reserved, then for the

service the Transmission Customer schedules, the Transmission Customer shall

pay in addition to the amounts based on its initial reservation the additional costs

(i.e., the difference between the zonal rates) associated with the new path. In

addition, the Transmission Customer shall replace losses (in accordance with

Attachment M) and pay for any redispatch costs (as determined in accordance

with Attachment K) based on the actual transmission path used.

22.2 Modification On a Firm Basis: Any request by a Transmission Customer to

modify Receipt and Delivery Points on a firm basis shall be treated as a new

request for service in accordance with Section 17 hereof, except that such

Transmission Customer shall not be obligated to pay any additional deposit if the

capacity reservation does not exceed the amount reserved in the existing Service

Agreement for Long-Term Firm Transmission Service or

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 65FERC Electric Tariff Superseding Original Sheet No. 65Fourth Revised Volume No. 1

confirmed Application for Short-Term Firm Transmission Service. While such

new request is pending, the Transmission Customer shall retain its priority for

service at the existing firm Receipt and Delivery Points specified in its Service

Agreement for Long-Term Firm Transmission Service or confirmed Application

for Short-Term Firm Transmission Service. In any instance where the remaining

term of service, after modification pursuant to this provision, is less than twelve

(12) months the transmission customer will maintain existing rights of reservation

priority on the original reservation.

23 Sale or Assignment of Transmission Service

23.1 Procedures for Assignment or Transfer of Service: Subject to Commission

approval of any necessary filings, a Transmission Customer may sell, assign, or

transfer all or a portion of its rights under its Service Agreement, but only to

another Eligible Customer (the Assignee). The Transmission Customer that sells,

assigns or transfers its rights under its Service Agreement is hereafter referred to

as the Reseller. Compensation to the Reseller shall not exceed the higher of (i)

the original rate paid by the Reseller, (ii) the maximum rate on file under this

Tariff at the time of the assignment, or (iii) the Reseller's opportunity cost capped

at the Transmission Provider's(s') cost of expansion. If the Assignee does not

request any change in the Point(s) of Receipt or the Point(s) of Delivery, or a

change in any other term or condition set forth in the original Service Agreement

for Long-Term Firm Transmission Service or original confirmed Application for

Short-Term Firm Transmission Service, the Assignee will receive the same

services as did the Reseller and the priority of

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 65AFERC Electric TariffFourth Revised Volume No. 1

service for the Assignee will be the same as that of the Reseller. A Reseller

should notify the Transmission Provider as soon as possible after any assignment

or transfer of service occurs but in any event, notification must be provided prior

to any provision of

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 66FERC Electric TariffFourth Revised Volume No. 1

service to the Assignee. The Assignee will be subject to all terms and conditions

of this Tariff. If the Assignee requests a change in service, the reservation priority

of service will be determined by the Transmission Provider pursuant to Section

13.2.

23.2 Limitations on Assignment or Transfer of Service: If the Assignee requests a

change in the Point(s) of Receipt or Point(s) of Delivery, or a change in any other

specifications set forth in the original Service Agreement for Long-Term Firm

Transmission Service or original confirmed Application for Short-Term Firm

Transmission Service, the Transmission Provider will consent to such change

subject to the provisions of the Tariff and the Transmission Customer's or the

Assignee's agreement to pay any additional charges consistent with Section 22 of

the Tariff, provided that the change will not impair the operation and reliability of

the Transmission Owner’s(s') generation, transmission, or distribution systems.

The Assignee shall pay the Transmission Provider for the costs of performing any

System Impact Study needed to evaluate the capability of the Transmission

System to accommodate the proposed change and any additional costs

resulting from such change. The Reseller shall remain liable for the performance

of all obligations under the Service Agreement, except as specifically agreed to by

the Parties through an amendment to the Service Agreement.

23.2 Information on Assignment or Transfer of Service: In accordance with

Section 4, Resellers may use Transmission Provider’s OASIS to post transmission

capacity available for resale.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 67FERC Electric TariffFourth Revised Volume No. 1

24 Metering and Power Factor Correction at Receipt and Delivery Points(s)

24.1 Transmission Customer Obligations: Unless otherwise agreed, the

Transmission Customer shall be responsible for the cost of installing and

maintaining compatible metering and communications equipment to accurately

account for the capacity and energy being transmitted under Part II of the Tariff

and to communicate the information to the Transmission Provider. Unless

otherwise specified in an agreement for the construction of facilities, such

equipment installed on the Transmission Customer's system shall remain the

property of the Transmission Customer. Unless otherwise specified in an

agreement for the construction of facilities, such equipment installed on the

Transmission Owner’s(s’) system shall remain the property of the Transmission

Owner(s).

24.2 Transmission Provider Access to Metering Data: The Transmission Provider

or its agent shall have access to metering data, which may reasonably be required

to facilitate measurements and billing under the Service Agreement.

24.3 Power Factor: Unless otherwise agreed, the Transmission Customer is required

to maintain a power factor within the same range specified by the Transmission

Provider, in consultation with the appropriate Transmission Owners, pursuant to

Good Utility Practices. The power factor requirements are specified in the

Service Agreement where applicable.

25 Compensation for Transmission Service

Rates for Firm and Non-Firm Point-To-Point Transmission Service are provided in the

Schedules appended to the Tariff: Firm Point-To-Point Transmission Service (Schedule 7); and

Non-Firm Point-To-Point Transmission Service (Schedule 8). In addition the Transmission

Customer also shall pay any applicable Ancillary Service Costs and Wholesale Distribution

Service charges.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 68FERC Electric TariffFourth Revised Volume No. 1

26 Stranded Cost Recovery

This Tariff does not affect in any way the right of any Transmission Owner to seek and

receive stranded cost recovery or the right of anyone to oppose such stranded cost recovery.

Thus, the Transmission Owner(s) may seek to recover stranded costs from the User(s) in

accordance with the terms, conditions and procedures set forth in FERC Order No. 888.

However, the Transmission Owner(s) must separately file any specific proposed stranded cost

charge under Section 205 of the Federal Power Act. If the Commission approves stranded cost

charges to be recovered through schedules to be implemented by the Transmission Provider, the

Transmission Provider as agent for the Transmission Owner(s) shall charge and collect the

appropriate charge(s) from the relevant User(s) and distribute the appropriate amounts directly to

the relevant Transmission Owner(s).

27 Compensation for New Facilities and Redispatch Costs

Whenever a System Impact Study performed by the Transmission Provider in connection

with the provision of Firm Point-To-Point Transmission Service identifies the need for new

facilities, the recovery of such costs shall be governed by Attachment J. Whenever a System

Impact Study performed by the Transmission Provider identifies capacity constraints that may be

relieved more economically by redispatching electric generating resources than by building new

facilities or upgrading existing facilities to eliminate such constraints, redispatch will be handled

in accordance with Attachment K. The Transmission Customer shall be responsible for the

redispatch costs as detailed in Schedule 7 and as determined by the procedures in Attachment K.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 69FERC Electric TariffFourth Revised Volume No. 1

III. NETWORK INTEGRATION TRANSMISSION SERVICE

Preamble

The Transmission Provider will provide Network Integration Transmission Service

pursuant to the applicable terms and conditions contained in the Tariff and Service Agreement.

Network Integration Transmission Service allows the Network Customer to integrate,

economically dispatch and regulate its current and planned Network Resources to serve its

Network Load in a manner comparable to that in which the Transmission Owners utilize the

Transmission System to serve their Native Load Customers. Network Integration Transmission

Service also may be used by the Network Customer to deliver economy energy purchases to its

Network Load from non-designated resources on an as-available basis without additional charge.

Transmission service for sales to non-designated loads will be provided pursuant to the

applicable terms and conditions of Part II of the Tariff.

28 Nature of Network Integration Transmission Service

28.1 Scope of Service: Network Integration Transmission Service is a transmission

service that allows Network Customers to efficiently and economically utilize

their Network Resources (as well as other non-designated generation resources) to

serve their Network Load located in a Transmission Owner's Control Area and

any additional load that may be designated pursuant to Section 31.3 of the Tariff.

The Network Customer taking Network Integration Transmission Service must

obtain or provide Ancillary Services pursuant to Section 3.

28.2 Transmission Provider and Transmission Owners Responsibilities: The

Transmission Provider and Transmission Owners will plan, operate, and cause to

be maintained its Transmission System in accordance with Good Utility Practice

in order to provide the Network Customer with Network Integration Transmission

Service over the Transmission System. The Transmission Owners, on behalf

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 70FERC Electric TariffFourth Revised Volume No. 1

of their Native Load Customers, shall be required to designate resources and loads

in the same manner as any Network Customer under Part III of this Tariff. This

information must be consistent with the information used by the Transmission

Provider to calculate available transmission capability. The Transmission

Provider shall include the Network Customer's Network Load in Transmission

System planning and shall, consistent with Good Utility Practice, endeavor to

cause to be constructed and placed into service sufficient transmission capacity to

deliver the Network Customer's Network Resources to serve its Network Load on

a basis comparable to the Transmission Owner(s') delivery of electric generating

and purchased resources to Native Load Customers.

28.3 Network Integration Transmission Service: The Transmission Provider will

provide firm transmission service over the Transmission System to the Network

Customer for the delivery of capacity and energy from its designated Network

Resources to service its Network Loads on a basis that is comparable to the

Transmission Owner(s') use of the Transmission System to reliably serve Native

Load Customers.

28.4 Secondary Service: The Network Customer may use the Transmission System

to deliver energy to its Network Loads from resources that have not been

designated as Network Resources. Such energy shall be transmitted, on an as-

available basis, with no additional charges imposed under Schedules 7, 8, or 9.

Deliveries from resources other than Network Resources will have a higher

priority than any Non-Firm Point-To-Point Transmission Service under Part II of

the Tariff or any non-firm point-to-point service under any other transmission

tariff or agreement where the service is being provided by a Transmission Owner.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 71FERC Electric TariffFourth Revised Volume No. 1

28.5 Real Power Losses: Real Power Losses are associated with all transmission

service. The applicable Real Power Loss factor is the factor for the Zone in which

the Network Load is located. These loss factors are stated in Appendix 1 to

Attachment M. The Network Customer is responsible for replacing losses

associated with all transmission service as determined in accordance with

Attachment M.

28.6 Restrictions on Use of Service: The Network Customer shall not use Network

Integration Transmission Service for (i) sales of capacity and energy to non-

designated loads, or (ii) direct or indirect provision of transmission service by the

Network Customer to third parties. All Network Customers taking Network

Integration Transmission Service shall use Point-To-Point Transmission Service

under Part II of the Tariff for any Third-Party Sale which requires use of the

Transmission Provider's Transmission System except for service where the

purchaser is a Network Customer of the Transmission Provider.

29 Initiating Service

29.1 Condition Precedent for Receiving Service: Subject to the terms and

conditions of Part III of the Tariff, the Transmission Provider will provide

Network Integration Transmission Service to any Eligible Customer, provided

that (i) the Eligible Customer completes an Application for service as provided

under Part III of the Tariff, (ii) the Eligible Customer and the Transmission

Provider in coordination with the affected Transmission Owner(s) complete(s) the

technical arrangements set forth in Sections 29.3 and 29.4, (iii) the Eligible

Customer executes a Service Agreement pursuant to Attachment F for service

under Part III of the Tariff

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 72FERC Electric TariffFourth Revised Volume No. 1

or requests in writing that the Transmission Provider file a proposed unexecuted

Service Agreement with the Commission, and (iv) the Eligible Customer executes

a Network Operating Agreement with the Transmission Provider pursuant to

Attachment G, or requests in writing that the Transmission Provider file a

proposed unexecuted Network Operating Agreement.

29.2 Application Procedures: An Eligible Customer requesting service under Part III

of the Tariff must submit an Application, with a deposit approximating the charge

for one month of service; provided, however, the Transmission Provider shall

have the right to waive deposits on a nondiscriminatory basis for service requests

if the Transmission Provider determines that the Transmission Customer is

creditworthy. Unless subject to the procedures in Section 2, Completed

Applications for Network Integration Transmission Service will be assigned a

priority according to the date and time the Application is received, with the

earliest Application receiving the highest priority. Applications should be

submitted by entering the information listed below on the Transmission Provider's

OASIS. A Completed Application shall provide all of the information included in

18 CFR § 2.20 including but not limited to the following:

(i) The identity, address, telephone number and facsimile number of the party requesting service;

(ii) A statement that the party requesting service is, or will be upon commencement of service, an Eligible Customer under the Tariff;

(iii) A description of the Network Load at each delivery point. This description should separately identify and provide the Eligible Customer's best estimate of the total loads to be served at each transmission voltage level, and the loads to be served from each Transmission Provider substation at the same transmission voltage level. The description should include a ten (10) year forecast of summer and winter load and resource requirements beginning with the first year after the service is scheduled to commence;

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 73FERC Electric Tariff Superseding Original Sheet No. 73Fourth Revised Volume No. 1

(iv) The amount and location of any interruptible loads included in the Network Load. This shall include the summer and winter capacity requirements for each interruptible load (had such load not been interruptible), that portion of the load subject to interruption, the conditions under which an interruption can be implemented and any limitations on the amount and frequency of interruptions. An Eligible Customer should identify the amount of interruptible customer load (if any) included in the 10 year load forecast provided in response to (iii) above;

(v) A description of Network Resources (current and 10-year projection), which shall include, for each Network Resource:- Unit size and amount of capacity from that unit to be designated as

Network Resource- VAR capability (both leading and lagging) of all generators - Operating restrictions- Any periods of restricted operations through-out the year- Maintenance schedules- Minimum loading level of unit- Normal operating level of unit- Any must-run unit designations required for system reliability or

contract reasons- Approximate variable generating cost ($/MWH) for redispatch

computations- Arrangements governing sale and delivery of power to third parties

from generating facilities located in the Transmission Provider Control Area, where only a portion of unit output is designated as a Network Resource

- Description of purchased power designated as a Network Resource including source of supply, Control Area location, transmission arrangements and delivery point(s) to the Transmission Provider's Transmission System;

(vi) Description of Eligible Customer's transmission system:- Load flow and stability data, such as real and reactive parts of the

load, lines, transformers, reactive devices and load type, including normal and emergency ratings of all transmission equipment in a load flow format compatible with that used by the Transmission Provider

- Operating restrictions needed for reliability- Operating guides employed by system operators- Contractual restrictions or committed uses of the Eligible Customer's

transmission system, other than the Eligible Customer's Network Loads and Resources

- Location of Network Resources described in subsection (v) above

- 10 year projection of system expansions or upgrades- Transmission System maps that include any proposed expansions or

upgrades

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 22FERC Electric TariffFourth Revised Volume No. 1

- Thermal ratings of Eligible Customer's Control Area ties with other Control Areas; and

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2001

Southwest Power Pool First Revised Sheet No. 74FERC Electric Tariff Superseding Original Sheet No. 74Fourth Revised Volume No. 1

(vii) Service Commencement Date and the term of the requested Network Integration Transmission Service. The minimum term for Network Integration Transmission Service is one year; however, if service is provided hereunder pursuant to a state retail pilot program, the minimum term may be the lesser of one year or the remainder of the pilot, but not less than one month.

Unless the Parties agree to a different time frame, the Transmission Provider must

acknowledge the request within ten (10) days of receipt. The acknowledgment

must include a date by which a response, including a Service Agreement, will be

sent to the Eligible Customer. If an Application fails to meet the requirements of

this section, the Transmission Provider shall notify the Eligible Customer

requesting service within fifteen (15) days of receipt and specify the reasons for

such failure. Wherever possible, the Transmission Provider will attempt to

remedy deficiencies in the Application through informal communications with the

Eligible Customer. If such efforts are unsuccessful, the Transmission Provider

shall return the Application without prejudice to the Eligible Customer filing a

new or revised Application that fully complies with the requirements of this

section. The Eligible Customer will be assigned a new priority consistent with the

date of the new or revised Application. The Transmission Provider shall treat this

information consistent with the standards of conduct contained in Part 37 of the

Commission's regulations.

The Transmission Provider may, on a non-discriminatory basis, waive the

requirements of subsections 29.2 (iii), (iv), (v) and (vi), to the extent such

information is not applicable or, in the case of service being requested for retail

access load, is unknown at the time of the application.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 74AFERC Electric TariffFourth Revised Volume No. 1

29.3 Technical Arrangements to be Completed Prior to Commencement of

Service: Network Integration Transmission Service shall not commence until the

Transmission Provider, the affected Transmission Owner(s), and the Network

Customer, or a third party, have completed installation of all equipment specified

under the Network Operating Agreement consistent with Good Utility Practice

and any additional requirements reasonably and consistently imposed to ensure

the reliable operation of the Transmission System. The Transmission Provider

and the affected Transmission Owner(s) shall exercise reasonable efforts, in

coordination with the Network Customer, to complete such arrangements as soon

as

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 75FERC Electric TariffFourth Revised Volume No. 1

practicable taking into consideration the Service Commencement Date.

29.4 Network Customer Facilities: The provision of Network Integration

Transmission Service shall be conditioned upon the Network Customer's

constructing, maintaining and operating the facilities on its side of each delivery

point or interconnection necessary to reliably deliver capacity and energy from

the Transmission Provider's Transmission System to the Network Customer. The

Network Customer shall be solely responsible for constructing or installing all

facilities on the Network Customer's side of each such delivery point or

interconnection.

29.5 Filing of Service Agreement: The Transmission Provider will file Service

Agreements with the Commission in compliance with applicable Commission

regulations.

30 Network Resources

30.1 Designation of Network Resources: Network Resources shall include all

generation owned, purchased or leased by the Network Customer designated to

serve Network Load under the Tariff. Network Resources may not include

resources, or any portion thereof, that are committed for sale to non-designated

third party load or otherwise cannot be called upon to meet the Network

Customer's Network Load on a non-interruptible basis. Any owned or purchased

resources that were serving the Network Customer's loads under firm agreements

entered into on or before the Service Commencement Date shall initially be

designated as Network Resources until the Network Customer terminates the

designation of such resources.

30.2 Designation of New Network Resources: The Network Customer may

designate a new Network Resource by providing the Transmission Provider with

as much advance notice as practicable. A designation of a new Network Resource

must be made by a request

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 76FERC Electric TariffFourth Revised Volume No. 1

for modification of service pursuant to an Application under Section 29.

30.3 Termination of Network Resources: The Network Customer may terminate the

designation of all or part of a generating resource as a Network Resource at any

time but should provide notification to the Transmission Provider as soon as

reasonably practicable.

30.4 Operation of Network Resources: The Network Customer shall not operate its

designated Network Resources located in the Network Customer's or

Transmission Owner’s(s') Control Area(s) such that the output of those facilities

exceeds its designated Network Load, plus non-firm sales delivered pursuant to

Part II of the Tariff, plus losses. This limitation shall not apply to changes in the

operation of a Transmission Customer's Network Resources at the request of the

Transmission Provider to respond to an emergency or other unforeseen condition

which may impair or degrade the reliability of the Transmission System.

30.5 Network Customer Redispatch Obligation: As a condition to receiving

Network Integration Transmission Service, the Network Customer agrees to

redispatch its Network Resources as requested by the Transmission Provider

pursuant to Section 33.2 and in accordance with Attachment K. The Network

Customer also shall submit an offer to redispatch in accordance with Attachment

K, Part I, with the charges subject to approval by the Commission where

appropriate. To the extent practical, the redispatch of resources pursuant to this

section shall be on a least cost, non-discriminatory basis between all Network

Customers, and the Transmission Owner(s). Transmission Owners and Network

Customers will not have any redispatch obligation to sustain Non-Firm

Transmission Service under this provision.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 77FERC Electric TariffFourth Revised Volume No. 1

30.6 Transmission Arrangements for Network Resources Not Physically

Interconnected With The Transmission Provider: The Network Customer

shall be responsible for any arrangements necessary to deliver capacity and

energy from a Network Resource not physically interconnected with the

Transmission System. The Transmission Provider will undertake reasonable

efforts to assist the Network Customer in obtaining such arrangements, including

without limitation, providing any information or data required by such other entity

pursuant to Good Utility Practice.

30.7 Limitation on Designation of Network Resources: The Network Customer

must demonstrate that it owns or has committed to purchase generation pursuant

to an executed contract in order to designate a generating resource as a Network

Resource. Alternatively, the Network Customer may establish that execution of a

contract is contingent upon the availability of transmission service under Part III

of the Tariff.

30.8 Use of Interface Capacity by the Network Customer: There is no specific

limitation upon a Network Customer's use of the Transmission System at the

interface(s) to the Control Area (where the Network Customer's load is located) to

integrate the Network Customer's Network Resources (or substitute economy

purchases) with its Network Loads. However, a Network Customer's use of the

interface capacity with other transmission systems may not exceed the Network

Customer's Load.

30.9 Network Customer Owned Transmission Facilities: The Network Customer

that owns existing transmission facilities that are integrated with the Transmission

Provider's Transmission System may be eligible to receive consideration either

through a billing credit or some other mechanism. In order to receive such

consideration the Network Customer must demonstrate that its transmission

facilities are integrated into the plans or

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 78FERC Electric TariffFourth Revised Volume No. 1

operations of a Transmission Owner to serve the Transmission Owner’s power

and transmission customers. For facilities constructed by the Network Customer

subsequent to the Service Commencement Date under Part III of the Tariff, the

Network Customer shall receive credit where such facilities are jointly planned

and installed in coordination with the Transmission Provider and/or Transmission

Owners. Calculation of the credit shall be addressed in either the Network

Customer's Service Agreement or any other agreement between the Parties. This

crediting provision does not apply to Network Customer transmission facilities

that are reflected in the rates for service under this Tariff.

31 Designation of Network Load

31.1 Network Load: The Network Customer must designate the individual Network

Loads on whose behalf the Transmission Provider will provide Network

Integration Transmission Service. The Network Loads shall be specified in the

Service Agreement.

31.2 New Network Loads Connected With the Transmission Provider: The

Network Customer shall provide the Transmission Provider with as much advance

notice as reasonably practicable of the designation of new Network Load that will

be added to its Transmission System. A designation of new Network Load must

be made through a modification of service pursuant to a new Application. The

Transmission Provider together with affected Transmission Owner(s) will use due

diligence to install any transmission facilities required to interconnect a new

Network Load designated by the Network Customer. The costs of new facilities

required to interconnect a new Network Load shall be determined in accordance

with the procedures provided in Section 32.4 and shall be charged to the Network

Customer in accordance with Commission policies.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 79FERC Electric TariffFourth Revised Volume No. 1

31.3 Network Load Not Physically Interconnected with the Transmission

Provider: This section applies to both initial designation pursuant to Section

31.1 and the subsequent addition of new Network Load not physically

interconnected with the Transmission System. To the extent that the Network

Customer desires to obtain transmission service for a load outside the

Transmission System, the Network Customer shall have the option of (1) electing

to include the entire load as Network Load for all purposes under Part III of the

Tariff and designating Network Resources in connection with such additional

Network Load, or (2) excluding that entire load from its Network Load and

purchasing Point-To-Point Transmission Service under Part II of the Tariff. To

the extent that the Network Customer gives notice of its intent to add a new

Network Load as part of its Network Load pursuant to this section the request

must be made through a modification of service pursuant to a new Application.

31.4 New Interconnection Points: To the extent the Network Customer desires to

add a new Delivery Point or interconnection point between the Transmission

System and a Network Load, the Network Customer shall provide the

Transmission Provider with as much advance notice as reasonably practicable.

31.5 Changes in Service Requests: Under no circumstances shall the Network

Customer's decision to cancel or delay a requested change in Network Integration

Transmission Service (e.g. the addition of a new Network Resource or

designation of a new Network Load) in any way relieve the Network Customer of

its obligation to pay the costs of transmission facilities caused to be constructed

by the Transmission Provider and charged to the Network Customer as reflected

in the Service Agreement. However, the Transmission Provider must treat any

requested change in Network Integration Transmission Service in a non-

discriminatory manner.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 80FERC Electric TariffFourth Revised Volume No. 1

31.6 Annual Load and Resource Information Updates: The Network Customer

shall provide the Transmission Provider with annual updates of Network Load

and Network Resource forecasts consistent with those included in its Application

for Network Integration Transmission Service under Part III of the Tariff. The

Network Customer also shall provide the Transmission Provider with timely

written notice of material changes in any other information provided in its

Application relating to the Network Customer's Network Load, Network

Resources, its transmission system or other aspects of its facilities or operations

affecting the Transmission Provider's ability to provide reliable service.

32 Additional Study Procedures For Network Integration Transmission Service

Requests

32.1 Notice of Need for System Impact Study: After receiving a request for service,

the Transmission Provider shall determine on a non-discriminatory basis whether

a System Impact Study is needed. A description of the Transmission Provider's

methodology for completing a System Impact Study is provided in Attachment D.

If the Transmission Provider determines that a System Impact Study is necessary

to accommodate the requested service, it shall so inform the Eligible Customer, as

soon as practicable. In such cases, the Transmission Provider shall within thirty

(30) days of receipt of a Completed Application, tender a System Impact Study

Agreement pursuant to which the Eligible Customer shall agree to reimburse the

Transmission Provider for performing the required System Impact Study

including any costs of the Transmission Owners where applicable. For a service

request to remain a Completed Application, the Eligible Customer shall execute

the System Impact

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 81FERC Electric TariffFourth Revised Volume No. 1

Study Agreement and return it to the Transmission Provider within fifteen (15)

days. If the Eligible Customer elects not to execute the System Impact Study

Agreement, its Application shall be deemed withdrawn and its deposit shall be

returned with interest.

32.2 System Impact Study Agreement and Cost Reimbursement:

(i) The System Impact Study Agreement will clearly specify the

Transmission Provider's estimate of the actual cost, and time for

completion of the System Impact Study. The charge shall not exceed the

actual cost of the study. In performing the System Impact Study, the

Transmission Provider shall rely, to the extent reasonably practicable, on

existing transmission planning studies. The Eligible Customer will not be

assessed a charge for such existing studies; however, the Eligible

Customer will be responsible for charges associated with any

modifications to existing planning studies that are reasonably necessary to

evaluate the impact of the Eligible Customer's request for service on the

Transmission System.

(ii) If in response to multiple Eligible Customers requesting service in relation

to the same competitive solicitation, a single System Impact Study is

sufficient for the Transmission Provider to accommodate the service

requests, the costs of that study shall be pro-rated among the Eligible

Customers.

(iii) Each Transmission Owner shall pay the Transmission Provider for System

Impact Studies that the Transmission Provider conducts on the

Transmission Owner's behalf, the same as any non-Transmission Owning

Customer.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 82FERC Electric TariffFourth Revised Volume No. 1

32.3 System Impact Study Procedures: Upon receipt of an executed System Impact

Study Agreement, the Transmission Provider, in coordination with the appropriate

Transmission Owner(s), will use due diligence to complete the required System

Impact Study within a sixty (60) day period. The System Impact Study shall

identify any system constraints and redispatch options, additional Direct

Assignment Facilities or Network Upgrades required to provide the requested

service. In the event that the Transmission Provider is unable to complete the

required System Impact Study within such time period, it shall so notify the

Eligible Customer and provide an estimated completion date along with an

explanation of the reasons why additional time is required to complete the

required studies. A copy of the completed System Impact Study and related work

papers shall be made available to the Eligible Customer. The Transmission

Provider will use the same due diligence in completing the System Impact Study

for an Eligible Customer as it uses when completing studies for Transmission

Owners. The Transmission Provider shall notify the Eligible Customer

immediately upon completion of the System Impact Study if the Transmission

System will be adequate to accommodate all or part of a request for service or that

no costs are likely to be incurred for new transmission facilities or upgrades. In

order for a request to remain a Completed Application, within fifteen (15) days of

completion of the System Impact Study the Eligible Customer must execute a

Service Agreement or request the filing of an unexecuted Service Agreement, or

the Application shall be deemed terminated and withdrawn.

32.4 Facilities Study Procedures: If a System Impact Study indicates that additions

or upgrades to the Transmission System are needed to supply the Eligible

Customer's service request, the Transmission Provider, within thirty (30) days of

the completion

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 83FERC Electric TariffFourth Revised Volume No. 1

of the System Impact Study, shall tender to the Eligible Customer a Facilities

Study Agreement pursuant to which the Eligible Customer shall agree to

reimburse the Transmission Provider and any affected Transmission Owner(s) for

performing the required Facilities Study. For a service request to remain a

Completed Application, the Eligible Customer shall execute the Facilities Study

Agreement and return it to the Transmission Provider within fifteen (15) days. If

the Eligible Customer elects not to execute the Facilities Study Agreement, its

Application shall be deemed withdrawn and its deposit shall be returned with

interest. Upon receipt of an executed Facilities Study Agreement, the

Transmission Provider in coordination with the affected Transmission Owner(s)

will use due diligence to complete the required Facilities Study within a sixty (60)

day period. If the Transmission Provider together with the affected Transmission

Owner(s) are unable to complete the Facilities Study in the allotted time period,

the Transmission Provider shall notify the Eligible Customer and provide an

estimate of the time needed to reach a final determination along with an

explanation of the reasons that additional time is required to complete the study.

When completed, the Facilities Study will include a good faith estimate of (i) the

cost of Direct Assignment Facilities to be charged to the Eligible Customer, (ii)

the Eligible Customer's appropriate share of the cost of any required Network

Upgrades, and (iii) the time required to complete such construction and initiate

the requested service. The Eligible Customer shall provide the Transmission

Provider with a letter of credit or other reasonable form of security acceptable to

the Transmission Provider equivalent to the costs of new facilities or upgrades

consistent with commercial practices as established by the Uniform Commercial

Code. The Eligible Customer shall have thirty (30)

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 84FERC Electric TariffFourth Revised Volume No. 1

days to execute a Service Agreement or request the filing of an unexecuted

Service Agreement and provide the required letter of credit or other form of

security or the request no longer will be a Completed Application and shall be

deemed terminated and withdrawn.

33 Load Shedding and Curtailments

33.1 Procedures: Prior to the Service Commencement Date, the Transmission

Provider, in coordination with the affected Transmission Owner(s), and the

Network Customer shall establish Load Shedding and Curtailment procedures

pursuant to the Network Operating Agreement with the objective of responding to

contingencies on the Transmission System and on systems directly and indirectly

interconnected with the Transmission System. The Parties including the affected

Transmission Owner(s) will implement such programs during any period when

the Transmission Provider determines that a system contingency exists and such

procedures are necessary to alleviate such contingency. The Transmission

Provider will notify all affected Network Customers and affected Transmission

Owners in a timely manner of any scheduled Curtailment.

33.2 Transmission Constraints: During any period when the Transmission Provider

determines that a transmission constraint exists on the Transmission System, and

such constraint may impair the reliability of the Transmission System, the

Transmission Provider will take whatever actions, consistent with Good Utility

Practice, that are reasonably necessary to maintain the reliability of the

Transmission System. To the extent the Transmission Provider determines that

the reliability of the Transmission System can be maintained by redispatching

resources, the Transmission Provider will initiate procedures pursuant to the

Network Operating Agreement to redispatch all Network Resources and the

Transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 85FERC Electric TariffFourth Revised Volume No. 1

Owners’ resources on a least cost basis without regard to the ownership of such

resources. Any redispatch under this section may not unduly discriminate

between the Transmission Owners’ use of the Transmission System on behalf of

their Native Load Customers and any Network Customer’s use of the

Transmission System to serve its designated Network Load.

33.3 Cost Responsibility for Relieving Transmission Constraints: Whenever the

Transmission Provider implements least cost redispatch procedures in response to

a transmission Constraint, all Transmission Owners and Network Customers, as

well as all other firm transmission service customers, will bear a proportionate

share of the total redispatch cost based on their respective Load Ratio Shares.

33.4 Curtailments of Scheduled Deliveries: If the Transmission Provider determines

that it is necessary to Curtail scheduled deliveries, the Parties and the affected

Transmission Owner(s) shall Curtail such schedules in accordance with the

Network Operating Agreement and pursuant to the Transmission Loading Relief

procedures specified in Attachment R.

33.5 Allocation of Curtailments: The Transmission Provider shall, on a non-

discriminatory basis, Curtail the transaction(s) that effectively relieve the

constraint. However, to the extent practicable and consistent with Good Utility

Practice, any Curtailment will be shared by the affected Transmission Owner(s)

and Network Customer in proportion to their respective Load Ratio Shares. The

Transmission Provider shall not direct the Network Customer to Curtail schedules

to an extent greater than the Transmission Provider would Curtail the

Transmission Owner's schedules under similar circumstances.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 86FERC Electric TariffFourth Revised Volume No. 1

33.6 Load Shedding: To the extent that a system contingency exists on the

Transmission Provider's Transmission System and the Transmission Provider

determines that it is necessary for the affected Transmission Owner(s) and the

Network Customer to shed load, the Parties shall shed load in accordance with

previously established procedures under the Network Operating Agreement.

33.7 System Reliability: Notwithstanding any other provisions of this Tariff, the

Transmission Provider reserves the right, consistent with Good Utility Practice

and on a not unduly discriminatory basis, to Curtail Network Integration

Transmission Service without liability on the Transmission Provider's or

Transmission Owner's part for the purpose of making necessary adjustments to,

changes in, or repairs on the Transmission Owner's lines, substations and

facilities, and in cases where the continuance of Network Integration

Transmission Service would endanger persons or property. In the event of any

adverse condition(s) or disturbance(s) on the Transmission System or on any

other system(s) directly or indirectly interconnected with the Transmission

System, the Transmission Provider, consistent with Good Utility Practice, also

may Curtail Network Integration Transmission Service in order to (i) limit the

extent or damage of the adverse condition(s) or disturbance(s), (ii) prevent

damage to generating or transmission facilities, or (iii) expedite restoration of

service. The Transmission Provider will give the Network Customer as much

advance notice as is practicable in the event of such Curtailment. Any

Curtailment of Network Integration Transmission Service will be not unduly

discriminatory relative to the Transmission Owner's use of the Transmission

System on behalf of its (their) Native Load Customers. In the event that the

Network Customer (or any Transmission Owner that is not a Network Customer

with regard to its bundled load) fails to respond to

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 87FERC Electric Tariff Superseding Original Sheet No. 87Fourth Revised Volume No. 1

established Load Shedding and Curtailment procedures or to cease or reduce

service in response to a directive by the Transmission Provider, the Network

Customer shall pay any applicable charges and the following penalty (in addition

to the charges for all of the service used): 200% of the Network Integration

Transmission Service charge for the applicable month. This penalty shall apply

only to the portion of the service that the Transmission Customer fails to curtail in

response to a Curtailment directive. The Transmission Provider shall compensate

the Transmission Owners for 100% of the Network Integration Transmission

Service charge for the period for which they have provided service. The penalty

revenues in excess of that amount shall be used to reduce the Transmission

Provider’s administrative costs.

34 Rates and Charges

The Network Customer shall pay the Transmission Provider for any Direct Assignment

Facilities, Ancillary Services, and applicable study costs, consistent with Commission policy,

along with the following:

34.1 Monthly Demand Charge for all Zones except Zone 1: Except as provided in

Section 34.1a, for all network load served by the Transmission Provider, other

than network load physically located within the Public Service Company of

Oklahoma and Southwestern Electric Power Company, Subsidiaries of American

Electric Power, Inc. Zone, the Network Customer shall pay a monthly Demand

Charge, which shall be determined by multiplying its Load Ratio Share times one

twelfth (1/12) of the Annual Transmission Revenue Requirement specified in

Attachment H for each Zone in which the Network Customer’s Network Load is

physically located. Where a Network Customer has designated Network Load not

physically interconnected with the Transmission System under Section 31.3,

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 88FERC Electric Tariff Superseding Original Sheet No. 88Fourth Revised Volume No. 1

the Network Customer shall pay a monthly Demand Charge, which shall be

determined by multiplying its Load Ratio Share times one twelfth (1/12) of the

Annual Transmission Revenue Requirement specified in Attachment H for the

Zone that is the basis for charges under Schedule 9.

34.1a Monthly Demand Charge – Zone 1: For all network load physically located

within the Public Service Company of Oklahoma and Southwestern Electric

Power Company, Subsidiaries of American Electric Power, Inc. Zone, the

Network Customer shall pay a monthly Demand Charge calculated as shown on

Addendum 1 to Attachment H.

34.2 Determination of Network Customer's Monthly Network Load: The Network

Customer's monthly Network Load is its hourly load (60 minute, clock-hour);

provided, however, the Network Customer's monthly Network Load will be its

hourly load coincident with the monthly peak of the Zone where the Network

Customer load is physically located. Where a Network Customer has Network

Load in more than one Zone, the monthly Network Load will be determined

separately for each Zone. Where a Network Customer has designated Network

Load not physically interconnected with the Transmission System under Section

31.3, the Network Customer's monthly Network Load will be its hourly load

coincident with the monthly peak of the Zone that is the basis for charges under

Schedule 9.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 88AFERC Electric TariffFourth Revised Volume No. 1

34.3 Determination of Transmission Provider's Monthly Zone Transmission

Load: The Transmission Provider's monthly Transmission System load shall be

determined for each Zone on a non-coincident basis. The Transmission

Provider’s monthly Zone transmission load is the Zone's Monthly Transmission

System Peak minus the coincident peak usage of all Firm Point-To-Point

Transmission Service customers pursuant to Part II of this Tariff plus the

Reserved Capacity of all Firm Point-To-Point Transmission Service customers.

34.4 Redispatch Charge: The Network Customer shall pay a Load Ratio Share of

any redispatch costs allocated between the Network Customer and the

Transmission Provider pursuant to Attachment K. To the extent that the

Transmission Provider incurs an obligation to the Network Customer for

redispatch costs in accordance with Section 33, such amounts shall be credited

against the Network Customer's bill for the applicable month.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 89FERC Electric TariffFourth Revised Volume No. 1

34.5 Stranded Cost Recovery: This Tariff does not affect in any way the right of any

Transmission Owner to seek and receive stranded cost recovery or the right of

anyone to oppose such stranded cost recovery. Thus, the Transmission Owner(s)

may seek to recover stranded costs from the User(s) in accordance with the terms,

conditions and procedures set forth in FERC Order No. 888. However, the

Transmission Owner(s) must separately file any specific proposed stranded cost

charge under Section 205 of the Federal Power Act, if FERC jurisdictional. If the

Commission approves stranded cost charges to be recovered through schedules to

be implemented by the Transmission Provider, the Transmission Provider as

agreed shall charge and collect the appropriate charge(s) from the relevant User(s)

and distribute the appropriate amounts directly to the relevant Transmission

Owner(s).

34.6 SPP Costs: The Network Customer shall pay SPP’s administrative costs in

accordance with Schedule 1.

35 Operating Arrangements

35.1 Operation under the Network Operating Agreement: The Network Customer

shall plan, construct, operate and maintain its facilities in accordance with Good

Utility Practice and in conformance with the Network Operating Agreement.

35.2 Network Operating Agreement: The terms and conditions under which the

Network Customer shall operate its facilities and the technical and operational

matters associated with the implementation of Part III of the Tariff shall be

specified in the Network Operating Agreement. The Network Operating

Agreement shall provide for the Parties, including the affected Transmission

Owner(s), to (i) operate and maintain equipment necessary for integrating the

Network Customer within the Transmission System (including, but not limited to,

remote terminal units, metering, communications equipment and relaying

equipment), (ii) transfer

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 90FERC Electric TariffFourth Revised Volume No. 1

data between the Transmission Provider and the Network Customer (including,

but not limited to, heat rates and operational characteristics of Network

Resources, generation schedules for units outside the Transmission System,

interchange schedules, unit outputs for redispatch required under Section 33,

voltage schedules, loss factors and other real time data), (iii) use software

programs required for data links and constraint dispatching, (iv) exchange data on

forecasted loads and resources necessary for long-term planning, and (v) address

any other technical and operational considerations required for implementation of

Part III of the Tariff, including scheduling protocols. The Network Operating

Agreement will recognize that the Network Customer shall either (i) operate as a

Control Area under applicable guidelines of the North American Electric

Reliability Council (NERC) and SPP Criteria, (ii) satisfy its Control Area

requirements, including all necessary Ancillary Services, by contracting with the

Transmission Provider, or (iii) satisfy its Control Area requirements, including all

necessary Ancillary Services, by contracting with another entity, consistent with

Good Utility Practice, which satisfies NERC Policies and SPP Criteria. The

Transmission Provider shall not unreasonably refuse to accept contractual

arrangements with another entity for Ancillary Services. The Network Operating

Agreement is included in Attachment G.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 91FERC Electric TariffFourth Revised Volume No. 1

35.3 Reserved

36. Scheduling

Each Network Customer shall submit an energy schedule daily for flows consistent with

the times for energy scheduling for Daily Firm Point-to-Point Transmission Service shown on

Attachment P. Each Network Customer also shall provide day ahead generating unit

commitment schedules.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 92FERC Electric Tariff Superseding Original Sheet No. 92Fourth Revised Volume No. 1

IV. SPECIAL RULES ON USE OF TARIFF

37. During Transition Period

37.1 Service Not Required for Bundled Customers or Customers Under Retail

Access Programs: A Transmission Owner shall not be obligated to take Network

Integration Transmission Service or Point-to-Point Transmission Service from the

Transmission Provider in accordance with this Tariff for (1) bundled retail load

not having a choice of power suppliers or (2) for bundled retail load it continues

to serve that had the right to choose a different power supplier under a state retail

access program or legislation and that was retail load served by the Transmission

Owner prior to the retail load receiving the right to choose a different supplier.

37.2 Availability of Network Integration Transmission Service: All Transmission

Owners shall have the option of electing Network Integration Transmission

Service for retail loads or customers whether or not such loads or customers have

the right to choose a different power supplier during the Transition Period.

37.3 Unbundled Wholesale: A Transmission Owner shall be obligated to take

Network Integration Transmission Service or Point-to-Point Transmission Service

from the Transmission Provider in accordance with this Tariff for any sales to

wholesale load the Commission requires to be unbundled unless such service is

arranged by another entity or is pursuant to a Grandfathered Agreement.

37.4 Grandfathered Transactions: During the Transition Period, transmission

provided pursuant to Grandfathered Agreements shall

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO OperationsFiled to comply with order of the Federal Energy Regulatory Commission, Docket No.RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶ 61,110

Southwest Power Pool Original Sheet No. 92AFERC Electric TariffFourth Revised Volume No. 1

continue to term in accordance with the provisions of the Grandfathered Agreement

unless the parties agree otherwise. Grandfathered Transactions are defined in Section

1.14a.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO OperationsFiled to comply with order of the Federal Energy Regulatory Commission, Docket No.RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶ 61,110

Southwest Power Pool First Revised Sheet No. 93FERC Electric Tariff Superseding Original Sheet No. 93Fourth Revised Volume No. 1

38 After Transition Period

38.1 Applicability to Retail Load Having Choice: Beginning on the first day after

the end of the Transition Period, this Tariff shall be applicable to all transmission

service over the Transmission System provided for retail loads having the right to

choose a different power supplier except for deliveries made pursuant to

Grandfathered Agreements.

38.2 Applicability to Retail Load Not Having Choice: Beginning at the end of the

fifth year after the last day of the Transition Period, the Transmission Owner shall

take Network Integration Transmission Service or Point-To-Point Transmission

Service from the Transmission Provider in accordance with this Tariff for sales to

retail customers not having the right to choose a different power supplier.

38.3 Grandfathered Agreements: Transmission Service provided pursuant to

Grandfathered Agreements shall continue to term in accordance with the

provisions of the Grandfathered Agreements rather than unless the parties agree

otherwise. Grandfathered Agreements are defined in Section 1.14a.

39 Applicability of Non-Rate Terms and Conditions

39.1 Bundled Retail and Grandfathered Load: Notwithstanding Sections 37 and 38

of this Tariff, each Transmission Owner (which is not otherwise taking Network

Integration Transmission Service) is subject to the non-rate and conditions of this

Tariff for: (1) its bundled retail load not having a choice of power suppliers; (2)

its bundled retail load that had the right to choose a different power supplier under

a state retail access program or legislation and that was retail load served by the

Transmission Owner

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 93AFERC Electric Tariff Superseding Substitute Original Sheet No. 93AFourth Revised Volume No. 1

prior to the retail load receiving the right to choose a different supplier; and (3) its

bundled load under Grandfathered Agreements. For purposes of this provision

the non-rate terms and conditions are those that would apply to Network

Customers. In addition, unless a Transmission Owner executes a Service

Agreement under this Part III, it will not be considered as taking Network

Integration Transmission Service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: November 1, 2004 Effective: January 1, 2005

Filed to comply with Order of the Federal Energy Regulatory Commission, Docket Nos. RT04-1-002 and ER04-48-002, issued October 1, 2004, 109 FERC ¶ 61,009 (2004).

Southwest Power Pool First Revised Sheet No. 94FERC Electric Tariff Superseding Original Sheet No. 94Fourth Revised Volume No. 1

SCHEDULE 1

Scheduling, System Control And Dispatch Service

Scheduling, System Control and Dispatch Service is required to schedule the movement

of power through, out of, within or into a Control Area. The Transmission Provider’s scheduling

process will be as follows:

a. For transactions that source and sink within the same Control Area, scheduling

will be performed by the operator of that Control Area and the Transmission

Provider.

b. For transactions that source and sink in two different Control Areas, both within

the Transmission System, scheduling will be performed by the operators of the

source and sink Control Area and the Transmission Provider, but not by any

intervening Control Area operators.

c. For transactions that source and sink in two different Control Areas, one internal

to the Transmission System and one external to the Transmission System,

scheduling will be performed by the Control Area operator of the internal Control

Area, the Transmission Provider, and the external Control Area that is the Point of

Receipt/Point of Delivery.

d. For transactions with a Point of Receipt and a Point of Delivery in Control Areas

external to the Transmission System and transmitted through the Transmission

System, scheduling will be performed by the Transmission Provider.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 94AFERC Electric TariffFourth Revised Volume No. 1

Individual Control Area operators within the Transmission System may perform the

functions necessary for the movement of power within, into, or out of the respective Control

Area as described above. In such instances the Transmission Owner(s) whose Control Area

operator(s) perform such functions may charge the Transmission Provider for its services as

necessary to effectuate the transaction and the Transmission Provider will pass through to the

Transmission Customer the actual charges for each transaction without any markup. The

Transaction Provider shall pass through the revenues it receives for this service to the

Transmission Owner(s) whose Control Area operator(s) provided the service. Each Control Area

Transmission Owner shall maintain a schedule showing its cost of providing this service. For the

Commission regulated Transmission Owners, these charges shall be pursuant to Commission

approved schedules.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool First Revised Sheet No. 95FERC Electric Tariff Superseding Original Sheet No. 95Fourth Revised Volume No. 1

SCHEDULE 1-A

Tariff Administration Service:

The Transmission Provider shall provide Tariff Administration Service to carry out its

responsibilities under this Tariff. The Transmission Customer must purchase this service from

the Transmission Provider. The charges for this Service are to be developed as shown below.

1. Administration Charge:

An administration charge shall be applied to all transmission service under this Tariff to

cover the Transmission Provider’s expenses related to administration of this Tariff. For Point-

To-Point Transmission Service this charge shall be up to $0.20 per MW per hour for all capacity

reserved. For Network Integration Transmission Service this charge shall be up to $0.20 per

MW per hour for the 12 month average of the Transmission Customer’s coincident Zonal

Demands used to determine the Demand Charges under Schedule 9 multiplied by the number of

all hours of the applicable month. The charge per MW per hour shall be the same for Point-to-

Point Transmission Service as for Network Integration Transmission Service.

For each calendar year, the Transmission Provider shall establish a rate for this

administration charge by dividing projected expenses based on its budget for the calendar year

divided by the projected annual Schedule 1-A billing units for the calendar year. The

Transmission Provider shall reconcile actuals to budgeted figures and shall adjust charges for the

following calendar year to reflect either over or under recoveries of its costs for the prior year to

allow the Transmission Provider to recover its actual costs. In projecting and recovering its

expenses, the Transmission Provider shall recover 100% of its total expenses through this charge

up to the cap of $0.20 per MW per hour for all transmission service under the Tariff.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool First Revised Sheet No. 96FERC Electric Tariff Superseding Original Sheet No. 96Fourth Revised Volume No. 1

2. Transmission Service Request Charges:

The Transmission Customer shall pay the Transmission Provider a charge for each new

Transmission Service Request as follows:

(i) For Firm Point-To-Point Transmission Service:

Reservations less than one month: $100

Reservations one month or longer: $200

(ii) For Non-Firm Point-To-Point Transmission Service:

Each Reservation: $0.

However, the Transmission Customer shall have this fee rebated to it once the

Transmission Customer becomes legally obligated to pay the applicable Firm Point-to-Point

Transmission Service charges under this Tariff or if the requested Firm Point-to-Point

Transmission Service is denied by the Transmission Provider.

3. Bad Debt Expense:

The Transmission Provider shall include in its charges under this Schedule a component

to cover estimated bad debts. The Transmission Provider shall reconcile actuals to estimates and

shall adjust future monthly charges to reflect either over or under recoveries.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 97FERC Electric TariffFourth Revised Volume No. 1

SCHEDULE 2

Reactive Supply and Voltage Control from Generation Sources Service

In order to maintain transmission voltages on the Transmission Provider's transmission

facilities within acceptable limits, generation facilities under the control of the Control Area

operator(s) are operated to produce (or absorb) reactive power. Thus, Reactive Supply and

Voltage Control from Generation Sources Service must be provided for each transaction on the

Transmission System. The amount of Reactive Supply and Voltage Control from Generation

Sources Service that must be supplied with respect to the Transmission Customer's transaction

will be determined based on the reactive power support necessary to maintain transmission

voltages within limits that are generally accepted in the region and consistently adhered to by the

Transmission Provider.

Reactive Supply and Voltage Control from Generation Sources Service is to be provided

by the Transmission Provider by making arrangements with the Control Area operator(s) that

perform(s) this service for the Transmission System. The Transmission Customer must purchase

this service from the Transmission Provider. The charges for such service will be based on the

rates set forth below.

For the purposes of determining the charge applicable to transactions under this Tariff

where the load is located within the SPP Region, the service under this Schedule 2 will be

provided by the Control Area operator within the SPP Region where the load is located. The

charge collected through this schedule shall represent a pass through of the costs charged by that

Control Area operator. The Transmission Provider shall pass through the revenues it receives for

the service to the Control Area operator providing the service.

In instances where the load is located outside the SPP Region, the charge for service

under this Schedule 2 shall be an average rate. The

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 98FERC Electric TariffFourth Revised Volume No. 1

average rate charged each month shall be calculated based on the weighted average of the

Transmission Owners' and Users' Reactive Supply and Voltage Control from Generator Source

rates effective for that month based on MVAr capability of the generators relevant to the

provision of this service. The Transmission Provider shall distribute revenues to generation

owners based on the MVAr capability of the generators relevant to the provision of the services.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 99FERC Electric TariffFourth Revised Volume No. 1

SCHEDULE 3

Regulation and Frequency Response Service

Regulation and Frequency Response Service is necessary to provide for the continuous

balancing of resources (generation and interchange) with load and for maintaining scheduled

Interconnection frequency at sixty cycles per second (60 Hz). Regulation and Frequency

Response Service is accomplished by committing on-line generation whose output is raised or

lowered (predominantly through the use of automatic generating control equipment) as necessary

to follow the moment-by-moment changes in load. The obligation to maintain this balance

between resources and load lies with the Control Area operator that performs this function for

the Transmission Provider. The Transmission Customer must either purchase this service from

the Transmission Provider or make alternative comparable arrangements to satisfy its Regulation

and Frequency Response Service obligation. Unless the Transmission Customer makes

alternative comparable arrangements, the Transmission Provider will obtain this service from the

affected Control Area operators, or elsewhere, where approved, and the Transmission Customer

shall pay the Transmission Provider for this service when the Transmission Provider provides the

services to the Transmission Customer. Charges to the Transmission Customer are to reflect

only a pass-through of the costs charged to the Transmission Provider by that Control Area

operator or other Suppliers. The Transmission Provider shall pass through the revenues it

receives for this service to the Control Area operator or other suppliers providing this service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 100FERC Electric TariffFourth Revised Volume No. 1

SCHEDULE 4

Energy Imbalance Service

Energy Imbalance Service is provided when a difference occurs between the scheduled

and the actual delivery of energy to a load located within a Control Area over a single hour. The

Transmission Customer must either purchase this service from the Transmission Provider or

make alternative comparable arrangements to satisfy its Energy Imbalance Service obligation.

Unless the Transmission Customer makes alternative comparable arrangements, the

Transmission Provider will obtain this service from the affected Control Areas or elsewhere,

where appropriate, and the Transmission Customer shall pay the Transmission Provider for this

service when the Transmission Provider provides this service to the Transmission Customer.

Charges to the Transmission Customer are to reflect only a pass-through of the costs charged to

the Transmission Provider by that Control Area operator or other suppliers. The Transmission

Provider shall pass through the revenues it receives for this service to the Control Area operator

or other suppliers providing the service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 101FERC Electric TariffFourth Revised Volume No. 1

SCHEDULE 5

Operating Reserve - Spinning Reserve Service

Spinning Reserve Service is needed to serve load immediately in the event of a system

contingency. Spinning Reserve Service may be provided by generating units that are on-line and

loaded at less than maximum output. The Transmission Customer must either purchase this

service from the Transmission Provider or make alternative comparable arrangements to satisfy

its Spinning Reserve Service obligation. Unless the Transmission Customer makes alternative

comparable arrangements, the Transmission Provider will obtain the service from the affected

Control Areas, and the Transmission Customer shall pay the Transmission Provider for this

service when the Transmission Provider provides this service to the Transmission Customer.

Charges to the Transmission Customer are to reflect only a pass-through of the costs charged to

the Transmission Provider by that Control Area operator or other suppliers. The Transmission

Provider shall pass through the revenues it receives for this service to the Control Area operator

or other supplier providing the service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 102FERC Electric TariffFourth Revised Volume No. 1

SCHEDULE 6

Operating Reserve - Supplemental Reserve Service

Supplemental Reserve Service is needed to serve load in the event of a system

contingency; however, it is not available immediately to serve load but rather within a short

period of time. Supplemental Reserve Service may be provided by generating units that are on-

line but unloaded, by quick-start generation or by interruptible load. The Transmission

Customer must either purchase this service from the Transmission Provider or make alternative

comparable arrangements to satisfy its Supplemental Reserve Service obligation. Unless the

Transmission Customer makes alternative comparable arrangements, the Transmission Provider

will obtain this service from the affected Control Areas, and the Transmission Customer shall

pay the Transmission Provider for this service when the Transmission Provider provides this

service to the Transmission Customer. Charges to the Transmission Customer are to reflect only

a pass-through of the costs charged to the Transmission Provider by that Control Area operator

or other supplier. The Transmission Provider shall pass through the revenues it receives for this

service to the Control Area operator or other suppliers providing the service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 103FERC Electric TariffFourth Revised Volume No. 1

SCHEDULE 7

Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below in addition to other

applicable charges specified in the Tariff. All effective rates under this schedule shall be posted

on the SPP OASIS.

1. Zonal Rates: The Transmission Customer shall pay the zonal rate (per kW of

reserved capacity) based upon the Zone where the load is located for Firm Point-to-Point

Transmission Service where the generation source is outside the SPP Region and the load is

located within the SPP Region and for Firm Point-to-Point Transmission Service where both the

generation source and the load are located within the SPP Region. For Firm Point-to-Point

Transmission Service where the generation source is located within the SPP Region and the load

is located outside of the SPP Region, and for Firm Point-to-Point Transmission Service where

both the generation source and the load are located outside of the SPP Region, the Transmission

Customer shall pay the zonal rate (per kW of reserved capacity) for the Zone interconnected with

the Control Area, external to the SPP Region, that is the designated Point of Delivery. Where

there is more than one Zone interconnected with such Control Area, the lowest zonal rate of the

interconnected Zones is applicable. The zonal rates are stated in Attachment T.

The Zones are as follows:

Zone 1: Public Service Company of Oklahoma and Southwestern Electric Power

Company, Subsidiaries of American Electric Power, Inc.

Zone 2: Cleco Corporation

Zone 3: City Utilities of Springfield, Missouri

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 104FERC Electric TariffFourth Revised Volume No. 1

Zone 4: Empire District

Zone 5: Grand River Dam Authority

Zone 6: Kansas City Power and Light Company

Zone 7: Oklahoma Gas & Electric Company

Zone 8: Mid-West Energy

Zone 9: Missouri Public Service

Zone 10: Southwestern Power Administration

Zone 11: Southwestern Public Service

Zone 12: Sunflower Electric Cooperative

Zone 13: Western Farmers Electric Cooperative

Zone 14: Western Resources, Inc. (Kansas Gas & Electric and Western Resources)

Zone 15: West Plains Energy

No changes in Zones shall be made without submitting a filing to the Commission.

2. Caps: The total demand charge in any week, pursuant to a reservation for Daily

delivery, shall not exceed the weekly rate times the highest amount in kilowatts of Reserved

Capacity in any day during such week.

3. Redispatch Costs: The redispatch costs shall be calculated in accordance with

the formula and protocols shown on Attachment K. The Transmission Provider shall provide an

estimate of such redispatch costs before service begins.

4. Losses: The Transmission Customer shall replace losses determined in

accordance with Attachment M.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 105FERC Electric TariffFourth Revised Volume No. 1

5. Direct Assignment Costs: Where a System Impact and/or Facilities Study

indicates the need to construct Direct Assignment Facilities to accommodate a request for

Transmission Service, the Transmission Customer shall be charged the full cost of such Direct

Assignment Facilities in addition to the charges specified in this Schedule and Tariff. The

annual costs of the facility shall be calculated by multiplying the levelized fixed charge rate of

the Transmission Owner by the nondepreciated cost of the facility. Each month the

Transmission Customer shall pay a charge based on such annual costs divided by twelve. Any

such charge will be filed with the Commission.

6. Wholesale Distribution Service: Where Wholesale Distribution Service is

provided to effectuate Firm Point-to-Point Transmission Service, the Transmission Customer

shall pay all charges levied pursuant to the Wholesale Distribution Service Agreement and

Schedule 10.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 106FERC Electric TariffFourth Revised Volume No. 1

SCHEDULE 8

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below in

addition to other applicable charges specified in the Tariff. All effective rates under this

schedule shall be posted on the SPP OASIS.

1. Zonal Rates: The Transmission Customer shall pay the zonal rate (per KW of

reserved capacity) based upon the Zone where the load is located for Non-Firm Point-to-Point

Transmission Service where the generation source is outside the SPP Region and the load is

located within the SPP Region and for Non-Firm Point-to-Point Transmission Service where

both the generation source and the load are located within the SPP Region. For Non-Firm Point-

to-Point Transmission Service where the generation source is located within the SPP Region and

the load is located outside of the SPP Region, and for Non-Firm Point-to-Point Transmission

Service where both the generation source and the load are located outside of the SPP Region, the

Transmission Customer shall pay the zonal rate (per KW of reserved capacity) for the Zone

interconnected with the Control Area, external to the SPP Region, that is the designated Point of

Delivery. Where there is more than one Zone interconnected with such Control Area, the lowest

zonal rate of the interconnected Zones is applicable. The zonal rates are stated in Attachment T.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 107FERC Electric TariffFourth Revised Volume No. 1

The Zones are as follows:

Zone 1: Public Service Company of Oklahoma and Southwestern Electric Power

Company, Subsidiaries of American Electric Power, Inc.

Zone 2: Cleco Corporation

Zone 3: City Utilities of Springfield, Missouri

Zone 4: Empire District

Zone 5: Grand River Dam Authority

Zone 6: Kansas City Power and Light Company

Zone 7: Oklahoma Gas & Electric Company

Zone 8: Mid-West Energy

Zone 9: Missouri Public Service

Zone 10: Southwestern Power Administration

Zone 11: Southwestern Public Service

Zone 12: Sunflower Electric Cooperative

Zone 13: Western Farmers Electric Cooperative

Zone 14: Western Resources, Inc. (Kansas Gas & Electric and Western Resources)

Zone 15: West Plains Energy

No changes in Zones shall be made without submitting a filing to the Commission.

2. Caps: The total demand charge in any week, pursuant to a reservation for Daily

delivery, shall not exceed the weekly rate times the highest amount in kilowatts of Reserved

Capacity in any day during such week. The total demand charge in any day, pursuant to a

reservation for Hourly delivery, shall not exceed the daily rate times the highest amount in

kilowatts of Reserved Capacity in any hour during such day. In addition, the total demand

charge in any week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the

weekly rate above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 108FERC Electric Tariff Superseding Original Sheet No. 108Fourth Revised Volume No. 1

3. Redispatch Costs: The redispatch costs shall be calculated in accordance with

the formula and protocols shown on Attachment K. The Transmission Provider shall provide an

estimate of such redispatch costs before service begins.

4. Discounts: The Transmission Provider may offer discounts under this Schedule.

Three principal requirements apply to discounts for transmission service as follows: (1) any

offer of a discount made by the Transmission Provider must be announced to all Eligible

Customers solely by posting on the OASIS, (2) any customer-initiated requests for discounts

must occur solely by posting on the OASIS, and (3) once a discount is negotiated, details must

be immediately posted on the OASIS. For any discount agreed upon for service on a path, from

Point(s) of Receipt to Point(s) of Delivery, the Transmission Provider must offer the same

discounted transmission service rate for the same time period to all Eligible Customers on all

unconstrained transmission paths that go to the same Point(s) of Delivery on the Transmission

System. In offering discounts, the Transmission Provider’s goal shall be to maximize

transmission revenues.

4(a) Next-Hour-Market Service: The basic charge shall be that agreed upon by the

Parties at the time this service is reserved and in no event shall exceed the applicable charges

posted on OASIS. In the event that transmission service is curtailed or interrupted by the

Transmission Provider, either acting directly or indirectly at the request of another transmission

provider or a Security Coordinator, the Transmission Customer shall be charged only for that

portion of the hour of actual transmission service used. The pro-rata portion must be agreed

upon between the transmission provider and the transmission customer.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 108AFERC Electric TariffFourth Revised Volume No. 1

5. Losses: The Transmission Customer shall replace losses determined in

accordance with Attachment M.

6. Wholesale Distribution Service: Where Wholesale Distribution Service is

provided to effectuate Non-Firm Point-to-Point Transmission Service, the Transmission

Customer shall pay all charges levied pursuant to the Wholesale Distribution Service Agreement

and Schedule 10.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 109FERC Electric Tariff Superseding Original Sheet No. 109Fourth Revised Volume No. 1

SCHEDULE 9

Network Integration Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Network

Integration Transmission Service at the applicable charges set forth below in addition to other

applicable charges specified in the Tariff.

1. Zonal Rates: The Transmission Customer taking Network Integration

Transmission Service shall pay a monthly demand charge for the Zone where the load is located.

Each month, the Transmission Customer shall pay the Transmission Provider the applicable

monthly zonal Demand Charge, determined in accordance with Section 34.1. If a Transmission

Customer has load in multiple Zones, the Transmission Customer shall pay the monthly demand

charge for each Zone in which its load is located (i.e. the rate for each Zone shall be multiplied

by the Transmission Customer's monthly Network Load in that Zone and the sum of the

calculation for each applicable Zone shall be the total charges paid by the Transmission

Customer). For load not physically interconnected with the Transmission System designated as

Network load pursuant to Section 31.3, the Network Customer shall pay the zonal Demand

Charge for the Zone interconnected with the Control Area, external to the SPP Region, that is the

designated Point of Delivery. Where there is more than one Zone interconnected with such

Control Area, the lowest zonal Demand Charge of the interconnected Zones is applicable. The

annual revenue requirements of each Zone is stated in Attachment H.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 110FERC Electric TariffFourth Revised Volume No. 1

The Zones are as follows:

Zone 1: Public Service Company of Oklahoma and Southwestern Electric Power

Company, Subsidiaries of American Electric Power, Inc.

Zone 2: Cleco Corporation

Zone 3: City Utilities of Springfield, Missouri

Zone 4: Empire District

Zone 5: Grand River Dam Authority

Zone 6: Kansas City Power and Light Company

Zone 7: Oklahoma Gas & Electric Company

Zone 8: Mid-West Energy

Zone 9: Missouri Public Service

Zone 10: Southwestern Power Administration

Zone 11: Southwestern Public Service

Zone 12: Sunflower Electric Cooperative

Zone 13: Western Farmers Electric Cooperative

Zone 14: Western Resources, Inc. (Kansas Gas & Electric and Western Resources)

Zone 15: West Plains Energy

No changes in Zones shall be made without submitting a filing to the Commission.

2. Redispatch Costs: The redispatch costs shall be calculated in accordance with

the formula and protocols shown on Attachment K. The Transmission Provider shall provide an

estimate of such redispatch costs before service begins.

3. Losses: The Transmission Customer shall replace losses determined in

accordance with Attachment M.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 111FERC Electric TariffFourth Revised Volume No. 1

4. Direct Assignment Costs: Where a System Impact and/or Facilities Study

indicates the need to construct Direct Assignment Facilities to accommodate a request for

Transmission Service, the Transmission Customer shall be charged the full cost of such Direct

Assignment Facilities in addition to the charges specified in this Schedule and Tariff. The

annual costs of the facility shall be calculated by multiplying the levelized fixed charge rate of

the Transmission Owner by the nondepreciated cost of the facility. Each month the

Transmission Customer shall pay a charge based on such annual costs divided by twelve.

5. Wholesale Distribution Service: Where Wholesale Distribution Service is

provided to effectuate Network Integration Transmission Service, the Network Customer shall

pay all charges levied pursuant to the Wholesale Distribution Service Agreement and Schedule

10.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 112FERC Electric TariffFourth Revised Volume No. 1

SCHEDULE 10

Wholesale Distribution Service

Wholesale Distribution Service will be provided by the individual Transmission Owners

as necessary to effectuate a transaction under this Tariff. The transaction-specific information,

including all customer-specific rates and charges, will be set forth in the Service Agreement

between the Transmission Provider and the Transmission Customer for the associated service

being provided pursuant to the Tariff. All rates and charges for Wholesale Distribution Service

shall be on file with the appropriate agency as required by law or regulation. To the extent that a

Service Agreement containing provisions for Wholesale Distribution Service is required to be

filed with the Commission, the Transmission Provider, in consultation with the appropriate

Transmission Owner, shall provide along with the filing, adequate cost support to justify the

customer-specific rates and charges being assessed thereunder.

Wholesale Distribution Service will be provided subject to the same scheduling deadlines

and procedures for alternative dispute resolution as apply to the associated service. Unless

otherwise specified, the provision of Wholesale Distribution Service will commence on the same

day as service for the associated transaction, and shall terminate on the same day as service for

the associated transaction.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 113FERC Electric TariffFourth Revised Volume No. 1

Page 1 of 5

ATTACHMENT A

Form Of Service Agreement For Firm Point-To-Point Transmission Service

1.0 This Service Agreement, dated as of _______________, is entered into, by and between

Southwest Power Pool, Inc. ("The Transmission Provider"), and ____________

("Transmission Customer").

2.0 The Transmission Customer has been determined by The Transmission Provider to have

a Completed Application for Firm Point-To-Point Transmission Service under the Tariff.

3.0 The Transmission Customer has provided to The Transmission Provider an Application

deposit in the amount of $_________, in accordance with the provisions of Section 17.3

of the Tariff.

4.0 Service under this agreement shall commence on the later of (l) the requested service

commencement date, or (2) the date on which construction of any Direct Assignment

Facilities and/or Network Upgrades are completed, or (3) such other date as it is

permitted to become effective by the Commission. Service under this agreement shall

terminate on such date as mutually agreed upon by The Transmission Provider and the

Transmission Customer.

5.0 The Transmission Customer agrees to supply information The Transmission Provider

deems reasonably necessary in accordance with Good Utility Practice in order for it to

provide the requested service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 114FERC Electric TariffFourth Revised Volume No. 1

Page 2 of 5

6.0 The Transmission Provider, as agent for the Transmission Owners, agrees to

provide and the Transmission Customer agrees to take and pay for Firm Point-To-

Point Transmission Service in accordance with the provisions of Part II of the

Tariff and this Service Agreement.

7.0 To the extent necessary to effectuate any transaction entered into pursuant to this

Service Agreement, the following Transmission Owner(s) shall provide

Wholesale Distribution Service over Distribution Facilities:

______________________________________________________

8.0 Any notice or request made to or by either Party regarding this Service

Agreement shall be made to the representative of the other Party as indicated

below.

Southwest Power Pool:

_____________________________________

415 N. McKinley,700 Plaza West

Little Rock, AR 72205

Transmission Customer:_____________________________________

_____________________________________

_____________________________________

9.0 The Tariff is incorporated herein and made a part hereof.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 115FERC Electric TariffFourth Revised Volume No. 1

Page 3 of 5

IN WITNESS WHEREOF, the Parties have caused this Service Agreement to be

executed by their respective authorized officials.

Southwest Power Pool: By:______________________ _______________ ______________ Name Title Date

Transmission Customer:

By:______________________ _______________ ______________ Name Title Date

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 116FERC Electric TariffFourth Revised Volume No. 1

Page 4 of 5

Specifications For Long-Term Firm Point-To-Point

Transmission Service

l.0 Term of Transaction: __________________________________

Start Date: ___________________________________________

Termination Date: _____________________________________

2.0 Description of capacity and energy to be transmitted by Transmission Provider including

the electric Control Area in which the transaction originates.

_______________________________________________________

3.0 Point(s) of Receipt:___________________________________

Delivering Party:______________________________________

4.0 Point(s) of Delivery:__________________________________

Receiving Party:_______________________________________

5.0 Maximum amount of capacity and energy to be transmitted (Reserved

Capacity):___________________________________

6.0 Designation of party(ies) subject to reciprocal service obligation:

________________________________________________________________________

________________________________________________________________________

________________________________________________________________________

7.0 Name(s) of any Intervening Systems providing transmission service:

_______________________________________________________________________

_______________________________________________________________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 117FERC Electric TariffFourth Revised Volume No. 1

Page 5 of 5

8.0 Service under this Agreement may be subject to some combination of the charges

detailed below. (The appropriate charges for individual transactions will be determined

in accordance with the terms and conditions of the Tariff.)

8.1 Transmission Charge:______________________________

__________________________________________________

8.2 System Impact and/or Facilities Study Charge(s):

__________________________________________________

__________________________________________________

8.3 Direct Assignment Facilities Charge:______________

__________________________________________________

8.4 Ancillary Services Charges: ______________________

__________________________________________________

__________________________________________________

__________________________________________________

__________________________________________________

__________________________________________________

__________________________________________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 118FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT B

Form Of Service Agreement For Non-Firm Point-To-Point Transmission Service

1.0 This Service Agreement, dated as of _______________, is entered into, by and between

Southwest Power Pool, Inc.("The Transmission Provider"), and ____________

(Transmission Customer).

2.0 The Transmission Customer has been determined by The Transmission Provider to be a

Transmission Customer under Part II of the Tariff and has filed a Completed Application

for Non-Firm Point-To-Point Transmission Service in accordance with Section 18.2 of

the Tariff.

3.0 Service under this Agreement shall be provided by The Transmission Provider upon

request by an authorized representative of the Transmission Customer.

4.0 The Transmission Customer agrees to supply information The Transmission Provider

deems reasonably necessary in accordance with Good Utility Practice in order for it to

provide the requested service.

5.0 The Transmission Provider, as agent for the Transmission Owners, agrees to provide and

the Transmission Customer agrees to take and pay for Non-Firm Point-To-Point

Transmission Service in accordance with the provisions of Part II of the Tariff and this

Service Agreement.

6.0 Any notice or request made to or by either Party regarding this Service Agreement shall

be made to the representative of the other Party as indicated below.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 119FERC Electric TariffFourth Revised Volume No. 1

Southwest Power Pool:

_____________________________________

415 N. McKinley,700 Plaza West

Little Rock, AR 72205

Transmission Customer:

_____________________________________

_____________________________________

_____________________________________

7.0 The Tariff is incorporated herein and made a part hereof.

IN WITNESS WHEREOF, the Parties have caused this Service Agreement to be

executed by their respective authorized officials.

Southwest Power Pool:

By:______________________ _____________________ _____________________Name Title Date

Transmission Customer:

By:______________________ _____________________ _____________________ Name Title Date

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 120FERC Electric Tariff Superseding Original Sheet No. 120Fourth Revised Volume No. 1

ATTACHMENT C

Methodology To Assess Short-Term Available Transmission Capability

The Transmission Provider will respond to a valid Application for Short-Term

transmission service under this Tariff by performing studies pursuant to this Attachment C to

assess whether sufficient transmission capability would be available to accommodate the service

requested in the Application. The assessment of Available Transmission Capability to sustain

Long-Term Firm Point-To-Point Transmission Service will be conducted pursuant to the

Southwest Power Pool Coordinated Planning Criteria, Attachment O.

These studies will be made using a flow based approach to determine the capability of the

interconnected network to accommodate the request for transmission service. A flow based

approach determines available transmission capability (ATC) of constrained facilities.

Constrained facility ATC represents capacity remaining on constrained facilities after reduction

for base flows, previously approved transmission service requests, and any appropriate

Transmission Reliability Margin (“TRM”) and Capacity Benefit Margin (“CBM”). For

constrained facilities within SPP, CBM is set to zero. For constrained facilities within SPP, SPP

does set aside capacity for TRM as necessary to ensure reliable short-term transmission

operation during the loss of any generating unit within the SPP operating reserve sharing group.

The TRM withheld is determined through an assessment conducted at least annually of the

transmission impact of the outage of each generating unit within the SPP Transmission System.

For the allocation of reserves that SPP expects to implement for each generation outage, SPP

assesses the incremental transmission loading on each constrained facility. The capacity

necessary to accommodate the greatest impact expected on each constrained facility is set aside

as TRM. For external constrained facilities monitored by SPP, SPP will use appropriate CBM

and TRM values provided and justified by the owner of the external

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: November 1, 2004 Effective: January 1, 2005

Filed to comply with order of the Federal Energy Regulatory Commission, Docket Nos. RP04-1-002 and ER04-48-002, issued October 1, 2004, 109 FERC ¶ 61009 (2004).

Southwest Power Pool Original Sheet No. 120AFERC Electric TariffFourth Revised Volume No. 1

constrained facility. Capacity required for TRM is made available to Transmission Customers

for Non-Firm Transmission Service.

Requests for transmission service are made on a Point-To-Point basis from source(s) to

sink(s). However, ATC is determined on a constrained facility basis. In order to evaluate a

transmission service request, response factors are used to decrement ATC of constrained

facilities. If ATC of all constrained facilities is positive after decrementing, the interconnected

network has capability to accommodate the request.

The transmission capability studies will analyze the impact of the proposed transmission

request on the thermal capability, voltage profile, and stability of the Transmission System(s) in

accordance with the reliability and transmission planning criteria of the North American Electric

Reliability Council (NERC) (or its successor organization) and SPP. The available

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: November 1, 2004 Effective: January 1, 2005

Filed to comply with order of the Federal Energy Regulatory Commission, Docket Nos. RP04-1-002 and ER04-48-002, issued October 1, 2004, 109 FERC ¶ 61009 (2004).

Southwest Power Pool Original Sheet No. 121FERC Electric TariffFourth Revised Volume No. 1

transmission capability for firm transactions will be the transmission capability determined under

the appropriate reliability criteria remaining after providing for prior contractual commitments

(including any transmission service contract(s) previously filed and pending Applications for

Firm Point-to-Point Transmission Service) and planned emergency generation import

requirements of Network Customers under this Tariff and Grandfathered Agreements, and also

accounting for power flows reasonably expected to occur on the Transmission System that

cannot be controlled by the Transmission Provider and/or the Transmission Owners (e.g.,

parallel path flows and inertial response power flows due to the tripping of a generator on the

interconnected system). The analysis will also consider the ability of the Transmission System to

withstand, under transfer conditions, a severe but credible disturbance without experiencing

cascading outages, voltage collapse or widespread blackouts.

In conducting studies, the Transmission Provider will adhere to Good Utility Practice,

including NERC (or its successor organization)Policies and SPP Criteria and the OASIS

Automation processes described as follows:

Available Transmission Capability (ATC)

The Transmission Provider has developed an automated process to determine ATC and to

respond to transmission service requests. This process is called OASIS Automation. OASIS

Automation automatically processes requests for transmission service using a flow-based

approach to determine ATC on constrained facilities. OASIS Automation is integrated with the

Transmission Provider’s energy management system and uses power flow models developed

from the real time data.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 122FERC Electric TariffFourth Revised Volume No. 1

OASIS Automation computes constrained facility hourly ATC for the first 7 days and

daily ATC for days 8 through 31. At midnight, a daily resynchronization occurs for the planning

horizon. This means hourly ATC will be determined for day 1 through day 7 and daily ATC will

be determined for day 8 through day 31 using the power flow model. Daily resynchronization

will take approximately 2 hours to complete and produces constrained facility ATCs that reflect

system and transmission service changes since the last resynchronization. After daily

resynchronization starts, OASIS Automation will continue to use the constrained facility ATC at

the start of resynchronization to process requests for transmission service. This means OASIS

Automation will continue to act on requests even when resynchronization is underway. If

requests were processed during resynchronization and they resulted in adjusting ATC in the

planning horizon, the ATC from the resynchronization will be "caught-up" to reflect ATC

adjustments once resynchronization is complete. This catch-up is performed by decrementing

ATC using response factors of certain designated constrained facilities for a Point of

Receipt/Point of Delivery (POD/POR) pair.

Similar to the daily resynchronization for the planning horizon, an hourly

resynchronization will occur at the beginning of the hour for the operating horizon. This means

hourly ATC for the first day will be determined prior to 2 p.m. After 2 p.m., hourly ATC for the

first and second day will be determined. Hourly resynchronization will take approximately 15

minutes to complete and produces constrained facility ATCs that reflect system and transmission

service changes since the last resynchronization. Similar to daily resynchronization, after hourly

resynchronization starts, OASIS Automation will continue to use the constrained facility ATC at

the start of resynchronization to process requests for transmission service. The ATC from the

resynchronization will be "caught-up" once resynchronization is complete.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 123FERC Electric TariffFourth Revised Volume No. 1

During the period between resynchronizations, ATC posted on the OASIS will be

continuously updated as requests are processed and ATC on the certain designated constrained

facilities are adjusted. At the time of resynchronization, the effects of all previously processed

requests are included in the resynchronization. This means newly approved transmission service

requests are included as part of the power flow base model and the effects of these newly

approved requests are not dependent on the use of response factors.

During the period between resynchronizations in both the operating horizon and the

planning horizon, events will occur that are not reflected in the latest ATC posted on the OASIS

(i.e., a change in system conditions) or a transmission service request will be processed and its

effects are limited to certain designated constrained facilities using response factors that assume

a linear relationship between ATC and the request. If the Tariff Administrator (TA) believes

either of these events have occurred and the ATC may no longer be valid, the TA can initiate a

resynchronization to occur at a time other than the normally scheduled time.

The flow-based approach being used to process requests under this Tariff requires

computing constrained facility ATC for the planning horizon and the operating horizon.

Constrained facility ATC represents remaining capacity available on a constrained facility.

Transmission Customers, however, are interested in ATC that is available between Points of

Receipt and Points of Delivery and not necessarily the capacity that is available on a constrained

facility. To meet the needs of customers, the Transmission Provider provides a Scenario

Analyzer as part of OASIS Automation which allows Transmission Customers to enter

transmission service requests for analysis of available capacity without submitting requests on

OASIS. The Scenario Analyzer evaluates availability of capacity on certain designated

constrained facilities for the POR/POD pair but does not decrement ATC since no request has

been submitted.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 124FERC Electric TariffFourth Revised Volume No. 1

Firm ATC

Oasis Automation computes firm ATC for the planning horizon only. Firm ATC is the

capacity that remains on the constrained facility after reducing its rating for serving native load,

Network Service and firm transactions. Firm ATC will be determined at least once a day during

the daily resynchronization. Resynchronization for the planning horizon solves a power flow

model that has both firm and non-firm transmission reservations. The flows on constrained

facilities should represent base flows that serve native load. After the power flow model has

been solved for a time segment, OASIS Automation takes the base flows of constrained facilities

and adjusts them to consider the effects of firm reservations in OASIS. Reservations in OASIS

have a POR/POD set. The certain designated constrained facilities that have a positive response

factor for a POR/POD pair will have their base flow decreased for non-firm reservations to

remove the non-firm reservation contribution to constrained facility loading. The certain

designated constrained facilities that have a negative response factor for a POR/POD pair will

have their base flow increased for firm and non-firm reservations to remove the firm and non-

firm reservation contribution to constrained facility loading. The non-firm contribution is

removed to totally remove the effects of non-firm reservations on firm ATC. The firm

contribution is removed because The Transmission Provider does not consider the effects of

counter flows associated with reservations.

After adjusting base flows for the effects of firm and non-firm reservations, OASIS

Automation uses the following formula to determine firm ATC:

Firm ATC Planning Horizon = Rating - TRM - CBM - Base FlowFirm

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 125FERC Electric TariffFourth Revised Volume No. 1

Non-Firm ATC

Oasis Automation computes non-firm ATC for both the planning horizon and the

operating horizon. Non-firm ATC is the capacity that remains on a constrained facility after

reducing its rating for serving native load, Network Service, firm transactions and non-firm

transactions. Non-firm ATC is computed in the planning horizon using the same power flow

solution as used for firm ATC. The certain designated constrained facilities that have a positive

response factor for a POR/POD pair will not have their base flow decreased for non-firm

reservations. The base flows of constrained facilities with positive response factors reflect

increased loading of both firm and non-firm reservations. The certain designated constrained

facilities that have a negative response factor for a POR/POD pair will have their base flow

increased for firm and non-firm reservation contribution to constrained facility loading. The firm

and non-firm contributions are removed because The Transmission Provider does not consider

the effects of counter-flows associated with reservations.

After adjusting base flows for the effects of firm and non-firm reservations, OASIS

Automation uses the following formula to determine non-firm ATC in the planning horizon:

Non-Firm ATC Planning Horizon = Rating - (A*TRM) - CBM - Base FlowsNon-Firm

Non-firm ATC is computed differently in the operating horizon than in the planning

horizon. The operating horizon consists of the current day 24 hours and after 2 p.m., the next

day 24 hours and deals exclusively with schedules. Firm Transmission Service cannot be

purchased in the operating horizon (a Transmission Customer cannot request firm Transmission

Service today with a begin date of today and a Transmission Customer cannot request firm

Transmission Service after 10:00 a.m. today with a begin date of tomorrow). Since the schedules

used in TrakR (The Transmission Provider scheduling software) do not distinguish between firm

and non-firm and because

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 126FERC Electric TariffFourth Revised Volume No. 1

there is not a commercial need to compute firm ATC in the operating horizon, a single

calculation is made to determine non-firm ATC. This calculation is made by including all

schedules in the power flow model, solving it and using the base flows of the constrained

facilities.

OASIS Automation uses the following formula to determine non-firm ATC in the

operating horizon:

Non-Firm ATC Operating Horizon = Rating - (B*TRM) - CBM - Base FlowsNon-Firm

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 127FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT D

Methodology for Completing a System Impact Study

Upon receipt of a Completed Application, the Transmission Provider will determine

whether transmission transfer capability ("Available Transfer Capability" or "ATC") will be

available to accommodate the transmission service requested in such Application. The

Transmission Provider will apply the criteria and practices described in Attachment C to

determine ATC for Short-Term Firm and Non-Firm Transmission Service requests. The

Transmission Provider’s Coordinated Planning Procedures, Attachment O, will be used to

determine ATC for Long-Term Firm and Network Integration Transmission Service requests. If

sufficient ATC will exist to support the transaction described in the Eligible Customer's

Application, as supplemented with necessary details such as the sources and sinks of the power

to be scheduled under the request, the Transmission Provider will so inform the Eligible

Customer. If the Transmission Provider determines that existing ATC is insufficient to provide

the requested service, the Transmission Provider will notify the Eligible Customer. Upon a

request by the Eligible Customer, the Transmission Provider will tender a Study Agreement to

the Eligible Customer for a System Impact Study.

Upon receipt of a completed Study Agreement, the Transmission Provider, in

coordination with the affected Transmission Owners, will perform a System Impact Study to

determine whether the request for transmission service can be accommodated through

construction of Direct Assignment Facilities or Network Upgrades or through redispatch, if

available. The System Impact Study will provide an estimate of the cost of redispatch.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 128FERC Electric TariffFourth Revised Volume No. 1

If the studies predict that a constraint will occur in the system of a non-SPP transmission

provider or non-SPP control area, the Transmission Provider will so inform the Eligible

Customer requesting service. The Transmission Provider and Eligible Customer will need to

work with the appropriate parties to determine if the limitation is valid and to determine the

facility additions or redispatch that may be required by others to support the transfer. The

Eligible Customer requesting service shall have the option to reduce the request to a level that

can be sustained without experiencing the constraint.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 129FERC Electric TariffFourth Revised Volume No. 1

Page 1 of 3

ATTACHMENT E

Index Of Point-To-Point Transmission Service Customers

Date of Customer Service Agreement

Ameren Services Company. 11/12/98American Electric Power Service Corp. 5/18/1998Amoco Energy Trading Corp. 6/05/1998Aquila Power Corporation 5/12/1998Associated Electric Cooperative, Inc. 7/16/1998 Arkansas Electric Cooperative 6/02/1998Avista Energy, Inc. 5/12/1998British Columbia Power Exchange Corp. 12/16/1998Cajun Electric 7/07/1998Cargill - Alliant 4/29/1998Carthage Water & Electric Plant 7/30/1998Central and South West Services, Inc. 5/21/1998Cinergy Services Inc. 5/21/1998Citizens Power Sales 5/12/1998City Power & Light Independence, MO 6/05/1998City Utilities of Springfield 5/28/1998CLECO Corporation 5/18/1998Columbia Energy Power Marketing Corp. 7/10/1998Columbia Water and Light Department 7/29/1999Commonwealth Edison Co. 6/30/1998ConAgra Energy Services, Inc. 5/28/1998Constellation Power Source, Inc. 9/28/1998Coral Power L.L.C. 7/06/1998Duke/Louis Dreyfus 4/27/1998El Paso Power Services Co. 10/15/1998Electric Clearinghouse, Inc. 6/01/1998Empire District Electric Company 5/18/1998Energy Clearinghouse Corp. 7/31/1998Energy Transfer Group 3/05/1999Engage Energy 4/17/1998Enron Power Marketing, Inc. 5/20/1998Entergy Power Marketing Corp. 5/18/1998

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 130FERC Electric TariffFourth Revised Volume No. 1

Page 2 of 3

Date of Customer Service Agreement

Entergy Services, Inc. 5/28/1998Grand River Dam Authority 5/12/1998Illinois Power Company 5/12/1998Jonesboro City Water & Light 5/18/1998Kansas City Power & Light 4/22/1998Kansas Municipal Energy Agency 1/14/1999Kansas City Board of Public Utilities 5/21/1998KOCH Energy Trading Inc. 6/17/1998Lafayette Utilities 7/16/1998LG&E Energy Marketing, Inc. 2/25/1999Merchant Energy Group of the Americas, Inc 7/22/1998Merrill Lynch Capital Services, Inc 1/02/1999Midwest Energy, Inc. 8/03/1998Morgan Stanley Capital Group, Inc. 7/16/1998Northern States Power Co. 6/30/1998OG&E Electric Services 4/21/1998OGE Energy Resources, Inc. 5/18/1998ONEOK Power Marketing Co. 7/16/1998PacifiCorp Power Marketing, Inc. 6/09/1998PanCanadian Energy Services, Inc. 9/18/1998PECO Energy Company 5/18/1998People's Electric Cooperative 6/02/1998PG&E Energy Trading 6/15/1998PP&L, Inc. 11/12/1998Public Service Company of Colorado 6/18/1999Rainbow Energy Marketing Corp. 4/29/1998Reliant Energy Services, Inc. 3/30/1999Sempra Energy Trading Corp. 7/02/1998Sikeston Board of Municipal Utilities 5/05/1998Sonat Power Marketing L.P. 5/28/1998Southern Company Energy Marketing 4/21/1998Southwestern Power Administration 5/21/1998Southwestern Public Service Co. 6/01/1998St. Joseph Power & Light Company 4/14/1998

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 131FERC Electric TariffFourth Revised Volume No. 1

Page 3 of 3

Date of Customer Service Agreement

Sunflower Electric CooperativeTenaska Power Services Company 4/17/1998Tennessee Power Company 4/29/1998Tennessee Valley Authority 6/09/1998The Energy Authority 8/20/1998Tractebel Energy Marketing, Inc. 6/26/1998Utilicorp United/Missouri Public Service 5/06/1998Utilicorp United/West Plains Energy 5/06/1998Vitol Gas & Electric 5/18/1998Wabash Valley Power Association, Inc. 6/02/1998Western Farmers Electric Cooperative 5/28/1998Western Resources Generation Services 5/18/1998Williams Energy Marketing and Trading Co. 1/02/1999

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 132FERC Electric Tariff Superseding Original Sheet No. 132Fourth Revised Volume No. 1

ATTACHMENT F

Service Agreement For Network Integration Transmission Service

This Network Integration Service Agreement ("Service Agreement") is entered into this

____ day of __________, ____, by and between _______________ ("Network Customer "), and

Southwest Power Pool, Inc. ("Transmission Provider"). The Network Customer and

Transmission Provider shall be referred to as "Parties."

WHEREAS, the Transmission Provider has determined that the Network Customer has

made a valid request for Network Integration Transmission Service in accordance with the

Transmission Provider’s Open Access Transmission Tariff ("Tariff") filed with the Federal

Energy Regulatory Commission ("Commission") as it may from time to time be amended;

WHEREAS, the Transmission Provider administers Network Integration Transmission

Service for Transmission Owners within the Southwest Power Pool and acts as agent for the

Transmission Owners in providing service under the Tariff; and

WHEREAS, the Network Customer has represented that it is an Eligible Customer under

the Tariff;

Whereas, the Parties intend that capitalized terms used herein shall have the same

meaning as in the Tariff.

NOW, THEREFORE, in consideration of the mutual covenants and agreements herein,

the Parties agree as follows:

1.0 The Transmission Provider agrees during the term of this Agreement, as it may be

amended from time to time, to provide Network Integration Transmission Service in

accordance with the Tariff to enable delivery of power and energy from the Network

Customer’s Network Resources that the Network Customer has committed to meet its

load.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 133FERC Electric Tariff Superseding Original Sheet No. 133Fourth Revised Volume No. 1

2.0 The Network Customer agrees to take and pay for Network Integration Transmission

Service in accordance with the provisions of Parts I and III of the Tariff and this

Agreement with attached Specifications.

3.0 The terms and conditions of such Network Integration Transmission Service shall be

governed by the Tariff, as in effect at the time this Agreement is executed by the Network

Customer, or as the Tariff is thereafter amended or by its successor tariff, if any. The

Tariff as it currently exists, or as it is hereafter amended is incorporated in this

Agreement by reference. In the case of any conflict between this Agreement and the

Tariff, the Tariff shall control. The Network Customer has been determined by the

Transmission Provider to have a Completed Application for Network Integration

Transmission Service under the Tariff. The Completed Specifications are based on the

information provided in the Application and are incorporated herein and made a part

hereof as Attachment 1.

4.0 Service under this Agreement shall commence on such date as it is permitted to become

effective by the Commission. This Agreement shall be effective through

__________________. Thereafter, it will continue from year to year unless terminated

by the Network Customer or the Transmission Provider by giving the other one-year

advance written notice or by the mutual written consent of the Transmission Provider and

Network Customer. Upon termination, the Network Customer remains responsible for

any outstanding charges including all costs incurred and apportioned or assigned to the

Network Customer under this Agreement.

5.0 The Transmission Provider and Network Customer have executed a Network Operating

Agreement as required by the Tariff.

6.0 The Network Customer agrees to take and pay for Network Integration Transmission

Service in accordance with the provisions of Parts I and III of the Tariff and this

Agreement with attached Specifications.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 134FERC Electric Tariff Superseding Original Sheet No. 134Fourth Revised Volume No. 1

7.0 Any notice or request made to or by either Party regarding this Agreement shall be made

to the representative of the other Party as indicated below. Such representative and

address for notices or requests may be changed from time to time by notice by one Party

or the other.

Southwest Power Pool:

_____________________________________

415 N. McKinley, 700 Plaza West _______

Little Rock, AR 72205 _ _

Transmission Customer:

_____________________________________

_____________________________________

_____________________________________

8.0 This Agreement shall not be assigned by either Party without the prior written consent of

the other Party, which consent shall not be unreasonably withheld. However, either Party

may, without the need for consent from the other, transfer or assign this agreement to any

person succeeding to all or substantially all of the assets of such Party. However, the

assigner shall be bound by the terms and conditions of this agreement.

9.0 Nothing contained herein shall be construed as affecting in any way the Transmission

Provider’s or a Transmission Owner’s right to unilaterally make application to the

Federal Energy Regulatory Commission, or other regulatory agency having jurisdiction,

for any change in the Tariff or this Agreement under Section 205 of the Federal Power

Act, or other applicable statute, and any rules and regulations promulgated thereunder; or

the Network Customer's rights under the Federal Power Act and rules and regulations

promulgated thereunder.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 135FERC Electric Tariff Superseding Original Sheet No. 135Fourth Revised Volume No. 1

10.0 By signing below, the Network Customer verifies that all information submitted to the

Transmission Provider to provide service under the Tariff is complete, valid and accurate,

and the Transmission Provider may rely upon such information to fulfill its

responsibilities under the Tariff.

IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by

their respective authorized officials.

TRANSMISSION PROVIDER TRANSMISSION CUSTOMER

Name Name

Title Title

Date Date

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 136FERC Electric Tariff Superseding Original Sheet No. 136Fourth Revised Volume No. 1

ATTACHMENT 1 TO THE NETWORK INTEGRATION TRANSMISSION SERVICE AGREEMENT

BETWEEN SOUTHWEST POWER POOL AND _______________SPECIFICATIONS FOR NETWORK INTEGRATION TRANSMISSION SERVICE

1.0 Network Resources

The Network Resources are listed in Appendix 1.

2.0 Network Loads

The Network Load consists of the bundled native load or its equivalent for

_______________.

The Network Customer’s Network Load shall be measured on an hourly integrated basis,

by suitable metering equipment located at each connection and delivery point, and each

generating facility. For a Network Customer providing retail electric service pursuant to

a state retail access program, profiled demand data, based upon revenue quality non-IDR

meters may be substituted for hourly integrated demand data. Measurements taken and

all metering equipment shall be in accordance with the Transmission Provider’s standards

and practices for similarly determining the Transmission Provider’s load. The actual

hourly network Loads, by delivery point, internal generation site and point where power

may flow to and from the Network Customer, with separate readings for each direction of

flow, shall be provided.

3.0 Affected Control Areas and Intervening Systems Providing Transmission Service

The affected control area is _______________ . The intervening systems providing

transmission service are _______________.

4.0 Electrical Location of Initial Sources

Initial Source Electrical Location

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 136AFERC Electric TariffFourth Revised Volume No. 1

5.0 Electrical Location of the Ultimate Loads

The loads of _______________ identified in Section 2.0 hereof as the Network Load are

electrically located within the ________________ Control Area.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 137FERC Electric TariffFourth Revised Volume No. 1

6.0 Delivery Points

The delivery points are the meters of _______________ identified in Section 2.0 as the

Network Load.

7.0 Receipt Points

The Points of Receipt are listed in Appendix 2.

8.0 Compensation

Service under this Agreement may be subject to some combination of the charges

detailed below. The appropriate charges for individual transactions will be determined in

accordance with the terms and conditions of the Tariff.

8.1 Transmission Charge

Monthly Demand Charge per Section 34.1 of the Tariff.

8.2 System Impact and/or Facility Study Charge

Studies may be required in the future to assess the need for system reinforcements in light

of the ten-year forecast data provided. Future charges, if required, shall be in accordance

with Section 32 of the Tariff.

8.3 Direct Assignment Facilities Charge

System reinforcements may be required in the future to support the load forecasts. Future

charges, if required, shall be in accordance with Section 32 of the Tariff.

8.4 Ancillary Service Charges

8.4.1 The following Ancillary Services are required under this Network Integration

Transmission Service Agreement.

a) Scheduling and Tariff Administration Service per Schedule 1 of the Tariff.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 138FERC Electric TariffFourth Revised Volume No. 1

b) Scheduling. System Control and Dispatch Service per

Schedule 1 of the _______________ tariff.

c) Reactive Supply and Voltage Control from Generation Sources Service

per Schedule 2 of the Tariff.

d) Regulation and Frequency Response Service per Schedule 3 of the Tariff.

e) Energy Imbalance Service per Schedule 4 of the Tariff.

f) Operating Reserve - Spinning Reserve Service per Schedule 5 of the

Tariff.

g) Operating Reserve - Supplemental Reserve Service per Schedule 6 of the

Tariff.

The ancillary services will be self-supplied by The Network Customer in

accordance with Sections 8.4.2 through 8.4.4, with the exception of the ancillary

services for Schedules 1 and 2.

8.4.2 With its annual forecasts, the Network Customer shall indicate its source for

Ancillary Services in accordance with the Tariff to be in effect for the upcoming

calendar year. If the Network Customer fails to include this information with its

annual forecasts, Ancillary Services will be provided for and charged in

accordance with the Tariff.

8.4.3 When the Network Customer elects to self provide ancillary services and is

unable to provide its own ancillary services, the Network Customer will pay the

Transmission Provider for such services and associated penalties in accordance

with the Tariff as a result of the failure of the Network Customer’s alternate

sources for required Ancillary Services.

8.4.4 All costs for the Network Customer to supply its own ancillary services shall be

the responsibility of the Network Customer.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 139FERC Electric TariffFourth Revised Volume No. 1

8.5 Real Power Losses

The Network Customer shall replace losses in accordance with Attachment M of the

Tariff.

8.6 Power Factor Correction Charge

8.7 Redispatch Charge

Redispatch charges shall be in accordance with Section 33.3 of the Tariff.

8.8 Wholesale Distribution Service Charge

8.9 Network Upgrade Charges

System reinforcements may be required in the future to support the load forecasts. Future

charges, if required, shall be in accordance with Section 32 of the Tariff.

8.10 Other Charges

9.0 Credit for Network Customer-Owned Transmission Facilities

10.0 Designation of Parties Subject to Reciprocal Service Obligation

11.0 Other Terms and Conditions

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 140FERC Electric TariffFourth Revised Volume No. 1

APPENDIX 1

Network Resources of

_______________

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 141FERC Electric TariffFourth Revised Volume No. 1

APPENDIX 1 _______________ NETWORK RESOURCES

Maximum Net Dependable Capacity

Network Resource Summer Winter Location

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 142FERC Electric TariffFourth Revised Volume No. 1

21

22

23

24

25

26

27

28

29

30

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 143FERC Electric TariffFourth Revised Volume No. 1

Appendix 2

Receipt Points of

_______________

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 144FERC Electric TariffFourth Revised Volume No. 1

APPENDIX 2 _______________ RECEIPT POINTS

Tieline / Plant Name Ownership Voltage (kV)

Rating (MVA)

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 145FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT G

Network Operating Agreement

This Network Operating Agreement ("Operating Agreement") is entered into this ____

day of __________, ____, by and between _______________ ("Network Customer "),

Southwest Power Pool, Inc. ("Transmission Provider") and ___________ ("Host Transmission

Owner"). The Network Customer, Transmission Provider and Host Transmission Owner shall

be referred to as "Parties."

WHEREAS, the Transmission Provider has determined that the Network Customer has

made a valid request for Network Integration Transmission Service in accordance with the

Transmission Provider’s Open Access Transmission Tariff ("Tariff") filed with the Federal

Energy Regulatory Commission ("Commission");

WHEREAS, the Transmission Provider administers Network Integration Transmission

Service for Transmission Owners within the Southwest Power Pool and acts as an agent for these

Transmission Owners in providing service under the Tariff;

WHEREAS, the Host Transmission Owner owns the transmission facilities to which the

Network Customer’s Network Load is physically connected or is the Control Area to which the

Network Load is dynamically scheduled;

WHEREAS, the Network Customer has represented that it is an Eligible Customer under

the Tariff;

WHEREAS, the Parties have entered into a Network Integration Transmission Service

Agreement under the Tariff; and

WHEREAS, the Parties intend that capitalized terms used herein shall have the same

meaning as in the Tariff unless otherwise specified herein;

NOW, THEREFORE, in consideration of the mutual covenants and agreements herein,

the Parties agree as follows:

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 146FERC Electric Tariff Superseding Original Sheet No. 146Fourth Revised Volume No. 1

1.0 Network Service

This Network Operating Agreement sets out the terms and conditions under which the

Transmission Provider, Host Transmission Owner, and Network Customer will cooperate

and the Host Transmission Owner and Network Customer will operate their respective

systems and specifies the equipment that will be installed and operated. The Parties shall

operate and maintain their respective systems in a manner that will allow the Host

Transmission Owner and the Network Customer to operate their systems and Control

Area and the Transmission Provider to perform its obligations consistent with Good

Utility Practice. The Transmission Provider may, on a non-discriminatory basis, waive

the requirements of Section 4.1 and Section 8.3 to the extent that such information is

unknown at the time of application or where such requirement is not applicable.

2.0 Designated Representatives of the Parties

2.1 Each Party shall designate a representative and alternate ("Designated

Representative(s)") from their respective company to coordinate and implement,

on an ongoing basis, the terms and conditions of the Network Operating

Agreement, including planning, operating, scheduling, redispatching,

curtailments, control requirements, technical and operating provisions, integration

of equipment, hardware and software, and other operating considerations.

2.2 The Designated Representatives shall represent the Transmission Provider, Host

Transmission Owner, and Network Customer in all matters arising under this

Network Operating Agreement and which may be delegated to them by mutual

agreement of the Parties hereto.

2.3 The Designated Representatives shall meet or otherwise confer at the request of

any Party upon reasonable notice, and each Party may place items on the meeting

agenda. All deliberations of the Designated Representatives shall be conducted

by taking into account the exercise of Good Utility Practice. If the Designated

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 146AFERC Electric TariffFourth Revised Volume No. 1

Representatives are unable to agree on any matter subject to their deliberation,

that matter shall be resolved pursuant to Section 12.0 of the Tariff, or otherwise,

as mutually agreed by the Network Customer, Host Transmission Owner, and

Transmission Provider.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 147FERC Electric TariffFourth Revised Volume No. 1

3.0 System Operating Principles

3.1 The Network Customer must design, construct, and operate its facilities safely

and efficiently in accordance with Good Utility Practice, NERC, SPP, or any

successor requirements, industry standards, criteria, and applicable

manufacturer’s equipment specifications, and within operating physical parameter

ranges (voltage schedule, load power factor, and other parameters) required by the

Host Transmission Owner and Transmission Provider.

3.2 The Host Transmission Owner and Transmission Provider reserve the right to

inspect the facilities and operating records of the Network Customer upon

mutually agreeable terms and conditions.

3.3 Electric service, in the form of three phase, approximately sixty hertz alternating

current, shall be delivered at designated delivery points and nominal voltage(s)

listed in the Network Integration Service Agreement. When multiple delivery

points are provided to a specific Network Load identified in Section ___ of

Attachment ___ to the Service Agreement, they shall not be operated in parallel

by the Network Customer without the approval of the Host Transmission Owner

and Transmission Provider. The Designated Representatives shall establish the

procedure for obtaining such approval. It shall also establish and monitor

standards and operating rules and procedures to assure that transmission system

integrity and the safety of customer, the public and employees are maintained or

enhanced when such parallel operations is permitted either on a continuing basis

or for intermittent switching or other service needs. Each Party shall exercise due

diligence and reasonable care in maintaining and operating its facilities so as to

maintain continuity of service.

3.4 The Host Transmission Owner and Network Customer shall operate their systems

and delivery points in continuous synchronism and in accord with applicable

NERC Policies and SPP Criteria and Good Utility Practice.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 148FERC Electric TariffFourth Revised Volume No. 1

3.5 If the function of any Party’s facilities is impaired or the capacity of any delivery

point is reduced, or synchronous operation at any delivery point(s) becomes

interrupted, either manually or automatically, as a result of force majeure or

maintenance coordinated by the Parties, the Parties will cooperate to remove the

cause of such impairment, interruption or reduction, so as to restore normal

operating conditions expeditiously.

3.6 The Transmission Provider and Host Transmission Owner, if applicable, reserve

the sole right to take any action necessary during an actual or imminent

emergency to preserve the reliability and integrity of the Transmission System,

limit or prevent damage, expedite restoration of service, ensure safe and reliable

operation, avoid adverse effects on the quality of service, or preserve public

safety.

3.7 In an emergency, the reasonable judgment of the Transmission Provider and Host

Transmission Owner, if applicable, in accordance with Good Utility Practice,

shall be the sole determinant of whether the operation of the Network Customer

loads or equipment adversely affects the quality of service or interferes with the

safe and reliable operation of the transmission system. The Transmission

Provider or Host Transmission Owner, if applicable, may discontinue

transmission service to such Network Customer until the power quality or

interfering condition has been corrected. Such curtailment of load, redispatching,

or load shedding shall be done on a non-discriminatory basis by Load Ratio

Share, to the extent practicable. The Transmission Provider or Host Transmission

Owner, if applicable, will provide reasonable notice and an opportunity to

alleviate the condition by the Network Customer to the extent practicable.

4.0 System Planning & Protection

4.1 No later than October 1 of each year, the Network Customer shall provide the

Transmission Provider and Host Transmission Owner the following information:

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 149FERC Electric TariffFourth Revised Volume No. 1

a) A ten (10) year projection of summer and winter peak demands with the

corresponding power factors and annual energy requirements on an

aggregate basis for each delivery point. If there is more than one delivery

point, the Transmission Customer shall provide the summer and winter

peak demands and energy requirements at each delivery point for the

normal operating configuration;

b) A ten (10) year projection by summer and winter peak of planned

generating capabilities and committed transactions with third parties

which resources are expected to be used by the Network Customer to

supply the peak demand and energy requirements provided in (a);

c) A ten (10) year projection by summer and winter peak of the estimated

maximum demand in kilowatts that the Network Customer plans to

acquire from the generation resources owned by the Network Customer,

and generation resources purchased from others; and

d) A projection for each of the next ten (10) years of transmission facility

additions to be owned and/or constructed by the Network Customer which

facilities are expected to affect the planning and operation of the

transmission system within the Host Transmission Owner’s control area.

This information is to be delivered to the Transmission Provider’s and Host

Transmission Owner’s Designated Representatives pursuant to Section 2.0.

4.2 Information exchanged by the Parties under this article will be used for system

planning and protection only, and will not be disclosed to third parties absent

mutual consent or order of a court or regulatory agency.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 150FERC Electric TariffFourth Revised Volume No. 1

4.3 The Host Transmission Owner, and Transmission Provider, if applicable, will

incorporate this information in its system load flow analyses performed during the

first half of each year. Following completion of these analyses, the Transmission

Provider or Host Transmission Owner will provide the following to the Network

Customer:

a) A statement regarding the ability of the Host Transmission Owner’s

transmission system to meet the forecasted deliveries at each of the

delivery points;

b) A detailed description of any constraints on the Host Transmission

Owner’s system within the five (5) year horizon that will restrict

forecasted deliveries; and

c) In the event that studies reveal a potential limitation of the Transmission

Provider’s ability to deliver power and energy to any of the delivery

points, a Designated Representative of the Transmission Provider will

coordinate with the Designated Representatives of the Transmission

Owner and the Network Customer to identify appropriate remedies for

such constraints including but not limited to: construction of new

transmission facilities, upgrade or other improvements to existing

transmission facilities or temporary modification to operating procedures

designed to relieve identified constraints. Any constraints within the

Transmission System will be remedied pursuant to the procedures of

Attachment O of the Tariff.

For all other constraints the Host Transmission Owner, upon

agreement with the Transmission Customer and consistent with good

utility practice, will endeavor to construct and place into service sufficient

capacity to maintain reliable service to the Network Customer.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 151FERC Electric TariffFourth Revised Volume No. 1

An appropriate sharing of the costs to relieve such constraints will

be determined by the Parties, consistent with the Tariff and with the

Commission’s rules, regulations, policies, and precedents then in effect. If

the Parties are unable to agree upon an appropriate remedy or sharing of

the costs, the Transmission Provider shall submit its proposal for the

remedy or sharing of such costs to The Commission for approval

consistent with the Tariff.

4.4 The Host Transmission Owner and the Network Customer shall coordinate with

the Transmission Provider: (1) all scheduled outages of generating resources and

transmission facilities consistent with the reliability of service to the customers of

each Party, and (2) additions or changes in facilities which could affect another

Party’s system. Where coordination cannot be achieved, the Designated

Representatives shall intervene for resolution.

4.5 The Network Customer shall coordinate with the Host Transmission Owner

regarding the technical and engineering arrangements for the delivery points,

including one line diagrams depicting the electrical facilities configuration and

parallel generation, and shall design and build the facilities to avoid interruptions

on the Host Transmission Owner’s transmission system.

4.6 The Network Customer shall provide for automatic and underfrequency load

shedding of the Network Customer Network Load in accordance with the SPP

Criteria related to emergency operations.

5.0 Maintenance of Facilities

5.1 The Network Customer shall maintain its facilities necessary to reliably receive

capacity and energy from the Host Transmission Owner’s transmission system

consistent with Good Utility Practice. The Transmission Provider or Host

Transmission Owner, as appropriate, may curtail service under this Agreement to

limit or prevent damage to generating or transmission facilities caused by

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 152FERC Electric TariffFourth Revised Volume No. 1

the Network Customer’s failure to maintain its facilities in accordance with Good

Utility Practice, and the Transmission Provider or Host Transmission Owner may

seek as a result any appropriate relief from The Commission.

5.2 The Designated Representatives shall establish procedures to coordinate the

maintenance schedules, and return to service, of the generating resources and

transmission and substation facilities, to the greatest extent practical, to ensure

sufficient transmission resources are available to maintain system reliability and

reliability of service.

5.3 The Network Customer shall obtain: (1) concurrence from the Transmission

Provider before beginning any scheduled maintenance of facilities which could

impact the operation of the transmission system over which transmission service

is administered by Transmission Provider; and (2) clearance from the

Transmission Provider when the Network Customer is ready to begin

maintenance on a transmission line or substation. The Transmission Provider

shall coordinate clearances with the Host Transmission Owner. The Network

Customer shall notify the Transmission Provider and the Host Transmission

Owner as soon as practical at the time when any unscheduled or forced outages

occur and again when such unscheduled or forced outages end.

6.0 Scheduling Procedures

6.1 Prior to the beginning of each week, the Network Customer shall provide to the

Transmission Provider expected hourly energy schedules for that week for all

energy flowing into the transmission system administered by Transmission

Provider.

6.2 In accordance with Section 36 of the Tariff, the Network Customer shall provide

to the Transmission Provider the Network Customer’s hourly energy schedules

for the next calendar day for all energy flowing into the transmission system

administered by the Transmission Provider. The Network Customer may modify

its hourly energy schedules up to twenty (20) minutes before the start of the next

clock hour provided that the Delivering Party and Receiving

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 153FERC Electric Tariff Superseding Original Sheet No. 153Fourth Revised Volume No. 1

Party also agree to the schedule modification. The hourly schedule must be stated

in increments of 1000 kW per hour. The Network Customer shall submit, or

arrange to have submitted, to the Transmission Provider a NERC transaction

identification Tag where required by NERC Policy 3. These hourly energy

schedules shall be used by the Transmission Provider to determine whether any

Energy Imbalance Service charges, pursuant to Schedule 4 of the Tariff apply.

7.0 Ancillary Services

7.1 The Network Customer must purchase in appropriate amounts all of the required

Ancillary Services described in the Tariff from the Transmission Provider or Host

Transmission Owner or, where applicable, self-supply or obtain these services

from other providers.

7.2 Where the Network Customer elects to self-supply or have a third party provide

Ancillary Services, the Network Customer must demonstrate to the Transmission

Provider that it has either acquired the Ancillary Services from another source or

is capable of self supplying the services.

7.3 The Network Customer must designate the supplier of Ancillary Services.

8.0 Metering

8.1 The Network Customer shall provide for the installation of meters, associated

metering equipment and telemetering equipment. The Network Customer shall

permit the Transmission Provider’s and Host Transmission Owner’s

representative to have access to the equipment at all reasonable hours and for any

reasonable purpose, and shall not permit unauthorized persons to have access to

the space housing the equipment.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet No. 154FERC Electric Tariff Superseding Original Sheet No. 154Fourth Revised Volume No. 1

8.2 The Network Customer shall provide for the testing of the metering equipment at

suitable intervals and its accuracy of registration shall be maintained in

accordance with standards acceptable to the Transmission Provider and consistent

with Good Utility Practice. At the request of the Transmission Provider or Host

Transmission Owner, a special test shall be made, but if less than two percent

inaccuracy is found, the requesting party shall pay for the test. Representatives of

the Parties may be present at all routine or special tests and whenever any

readings for purposes of settlement are taken from meters not having an

automated record. If any test of metering equipment discloses an inaccuracy

exceeding two percent, the accounts of the parties shall be adjusted. Such

adjustment shall apply to the period over which the meter error is shown to have

been in effect or, where such period is indeterminable, for one-half the period

since the prior meter test. Should any metering equipment fail to register, the

amounts of energy delivered shall be estimated from the best available data.

8.3 If the Network Customer is supplying energy to Retail load that has a choice in its

supplier, the Network Customer shall be responsible for providing all information

required by the Transmission Provider for billing purposes. Metering information

shall be available to the Transmission Provider either by individual retail

customer or aggregated retail energy information for that load the Network

Customer has under contract during the billing month. For the retail load that has

interval demand metering, the actual energy used by interval must be supplied.

For the retail load using standard kWh metering, the total energy consumed by

meter cycle, along with the estimated demand profile must be supplied. All rights

and limitations between parties granted in Sections 8.1, and 8.2 are applicable in

regards to retail metering used as the basis for billing the Network Customer.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 154AFERC Electric TariffFourth Revised Volume No. 1

9.0 Connected Generation Resources

9.1 The Network Customer’s connected generation resources that have automatic

generation control (AGC) and automatic voltage regulation (AVR) shall be

operated and maintained consistent with regional operating standards, and the

Network Customer or the operator shall operate, or cause to be operated, such

resources to avoid adverse disturbances or interference with the safe and reliable

operation of the transmission system.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 155FERC Electric TariffFourth Revised Volume No. 1

9.2 For all Network Resources of the Network Customer, the following generation

telemetry readings to the Host Transmission Owner are required:

1) Analog MW

2) Integrated MWHRS/HR

3) Analog MVARS

4) Integrated MVARHRS/HR

10.0 Redispatching, Curtailment and Load Shedding

10.1 In accordance with Section 33 of the Tariff, the Transmission Provider may

require redispatching of generation resources or curtailment of loads to relieve

existing or potential transmission system constraints. The Network Customer

shall submit verifiable incremental and decremental cost data from its Network

Resources to the Transmission Provider. These costs will be used as the basis for

least-cost redispatch. Information exchanged by the Parties under this article will

be used for system redispatch only, and will not be disclosed to third parties

absent mutual consent or order of a court or regulatory agency. The Network

Customer shall respond immediately to requests for redispatch from the

Transmission Provider. The Transmission Provider will bill or credit the Network

Customer as appropriate.

10.2 The Parties shall implement load-shedding procedures to maintain the reliability

and integrity for the Transmission System as provided in Section 33.1 of the

Tariff and in accordance with applicable NERC and SPP requirements and Good

Utility Practice. Load shedding may include (1) automatic load shedding, (2)

manual load shedding, and (3) rotating interruption of customer load. When

manual load shedding or rotating interruptions are necessary, the Host

Transmission Owner shall notify the Network Customer’s dispatcher or

schedulers of the required action and the Network Customer shall comply

immediately.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 156FERC Electric Tariff Superseding Original Sheet No. 156Fourth Revised Volume No. 1

10.3 The Network Customer will coordinate with the Host Transmission Owner to

ensure sufficient load shedding equipment is in place on their respective systems

to meet SPP requirements. The Network Customer and the Host Transmission

Owner shall develop a plan for load shedding which may include manual load

shedding by the Network Customer.

11.0 Communications

11.1 The Network Customer shall, at its own expense, install and maintain

communication link(s) for scheduling. The Communication link(s) shall be used

for data transfer and for voice communication.

11.2 A Network Customer self supplying Ancillary Services or securing Ancillary

Services from a third-party shall, at its own expense, install and maintain

telemetry equipment communicating between the generating resource(s)

providing such ancillary services and the Host Transmission Owner's Control

Area.

12.0 Cost Responsibility

12.1 The Network Customer shall be responsible for all costs incurred by the Network

Customer, Host Transmission Owner, and Transmission Provider to implement

the provisions of this Network Operating Agreement including, but not limited to,

engineering, administrative and general expenses, material and labor expenses

associated with the specification, design, review, approval, purchase, installation,

maintenance, modification, repair, operation, replacement, checkouts, testing,

upgrading, calibration, removal, and relocation of equipment or software, so long

as the direct assignment of such costs is consistent with Commission policy.

12.2 The Network Customer shall be responsible for all costs incurred by Network

Customer, Host Transmission Owner, and Transmission Provider for on-going

operation and maintenance of the facilities required to implement the provisions

of this Network Operating Agreement so long as the direct assignment of such

costs is consistent with Commission policy. Such work shall include, but

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 157FERC Electric TariffFourth Revised Volume No. 1

is not limited to, normal and extraordinary engineering, administrative and

general expenses, material and labor expenses associated with the specifications,

design, review, approval, purchase, installation, maintenance, modification,

repair, operation, replacement, checkouts, testing, calibration, removal, or

relocation of equipment required to accommodate service provided under this

Network Operating Agreement.

13.0 Billing and Payments

Billing and Payments shall be in accordance with Section 7 of the Tariff.

14.0 Dispute Resolution

Any dispute among the Parties regarding this Network Operating Agreement shall be

resolved pursuant to Section 12 of the Tariff, or otherwise, as mutually agreed by the

Parties.

15.0 Assignment

This Network Operating Agreement shall inure to the benefit of and be binding upon the

Parties and their respective successors and assigns, but shall not be assigned by any Party,

except to successors to all or substantially all of the electric properties and assets of such

Party, without the written consent of the other parties. Such written consent shall not be

unreasonably withheld.

16.0 Choice of Law

The interpretation, enforcement, and performance of this Network Operating Agreement

shall be governed by the laws of the State of Arkansas, except laws and precedent of such

jurisdiction concerning choice of law shall not be applied, except to the extent governed

by the laws of the United States of America.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 158FERC Electric TariffFourth Revised Volume No. 1

17.0 Entire Agreement

The Tariff and Network Integration Transmission Service Agreement, as they are

amended from time to time, are incorporated herein and made a part hereof. To the

extent that a conflict exists between the terms of this Network Operating Agreement and

the terms of the Tariff, the Tariff shall control.

18.0 Unilateral Changes and Modifications

Nothing contained in this Network Operating Agreement or any associated Service

Agreement shall be construed as affecting in any way the right of the Transmission

Provider or a Transmission Owner unilaterally to file with the Commission, or make

application to the Commission for, changes in rates, charges, classification of service, or

any rule, regulation, or agreement related thereto, under section 205 of the Federal Power

Act and pursuant to the Commission’s rules and regulations promulgated thereunder, or

under other applicable statutes or regulations.

Nothing contained in this Network Operating Agreement or any associated

Service Agreement shall be construed as affecting in any way the ability of any Network

Customer receiving Network Transmission Service under this Tariff to exercise any right

under the Federal Power Act and pursuant to the Commission’s rules and regulations

promulgated thereunder; provided, however, that it is expressly recognized that this

Network Operating Agreement is necessary for the implementation of the Tariff and

Service Agreement. Therefore, no Party shall propose a change to this Network

Operating Agreement that is inconsistent with the rates, terms and conditions of the Tariff

and/or Service Agreement.

19.0 Term

This Network Operating Agreement shall become effective on the date assigned by the

Commission (“Effective Date”), and shall continue in effect until the Tariff or the

Network Customer’s Network Integration Transmission Service Agreement is

terminated, whichever shall occur first.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 159FERC Electric TariffFourth Revised Volume No. 1

20.0 Notice

20.1 Except as herein otherwise provided, any notice that may be given to or made

upon any Party by any other Party under any of the provisions of this Operating

Agreement shall be in writing unless otherwise specifically provided herein and

shall be considered delivered when the notice is personally delivered or deposited

in the United States mail, certified or registered postage prepaid, to the following:

[Transmission Provider] [name][title][address][phone] [fax]

[Host Transmission Owner] [name][title][address] [phone] [fax]

[Network Customer] [name][title][address] [phone] [fax] Any Party may change its notice address by written notice to the other Parties in

accordance with this Article 20.

20.2 Any notice, request, or demand pertaining to operating matters may be delivered

in writing, in person or by first class mail, e-mail, messenger, telegraph, or

facsimile transmission as may be appropriate and shall be confirmed in writing as

soon as reasonably practical thereafter, if any Party so requests in any particular

instance.

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 160FERC Electric TariffFourth Revised Volume No. 1

21.0 Execution in Counterparts

This Network Operating Agreement may be executed in any number of counterparts with

the same effect as if all Parties executed the same document. All such counterparts shall

be construed together and shall constitute one instrument.

IN WITNESS WHEREOF, the Parties have caused this Network Operating Agreement to

be executed by their respective authorized officials, and copies delivered to each Party, to

become effective as of the Effective Date.

TRANSMISSION PROVIDER HOST TRANSMISSION OWNER

_____________________ ______________________Name Name

_____________________ _______________________Title Title

_______________________ _______________________Date Date

NETWORK CUSTOMER

_____________________Name

_____________________Title

_______________________Date

Issued by: L. Patrick Bourne, Manager, Transmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 161FERC Electric Tariff Superseding Original Sheet No. 161Fourth Revised Volume No. 1

ATTACHMENT H

Annual Transmission Revenue Requirement For Network Integration Transmission Service

1. The Annual Transmission Revenue Requirement for purposes of the Network Integration

Transmission Service within each Zone shall be:

Zone 1: Public Service Company of Oklahoma and Southwestern

Electric Power Company, Subsidiaries of American

Electric Power, Inc................................................................................$ 88,681,579

Zone 2: Cleco Corporation.................................................................................$ 29,328,000

Zone 3: City Utilities of Springfield, Missouri...................................................$ 8,651,509

Zone 4: Empire District......................................................................................$ 14,075,000

Zone 5: Grand River Dam Authority (Est.)........................................................$ 24,589,256

Zone 6: Kansas City Power and Light Company...............................................$ 35,461,776

Zone 7: Oklahoma Gas & Electric Company.....................................................$ 65,065,032

Zone 8: Mid-West Energy...................................................................................$ 4,197,347

Zone 9: Missouri Public Service........................................................................$ 18,884,642

Zone 10: Southwestern Power Administration.....................................................$ 7,427,000

Zone 11: Southwestern Public Service.................................................................$ 64,200,000

Zone 12: Sunflower Electric Cooperative............................................................$ 19,637,429

Zone 13: Western Farmers Electric Cooperative.................................................$ 20,719,639

Zone 14: Western Resources, Inc. (Kansas Gas & Electric and

Western Resources)..............................................................................$ 66,491,775

Zone 15: West Plains Energy...............................................................................$ 15,728,043

2. The amounts in (1) shall be effective until amended by the Transmission Owner or

modified by the Commission or other applicable regulatory authority.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 3, 2002 Effective: October 1, 2002

Southwest Power Pool Substitute Original Sheet No. 161AFERC Electric Tariff Superseding Original Sheet No. 161AFourth Revised Volume No. 1

ADDENDUM 1 TO ATTACHMENT H

MONTHLY DEMAND CHARGE CALCULATION FOR ZONE 1NETWORK INTEGRATION TRANSMISSION SERVICE

Unless a different rate is approved by the Commission, the monthly Demand Charge for

Zone 1 for Network Customers within that zone during the year 2001 shall be determined by

multiplying the Network Customer’s monthly Network Load, determined in accordance with the

provisions of Section 34.2, expressed in MW, times the rate per MW-month determined by

dividing the Zone 1 revenue requirement, specified in Attachment H, by the sum of the twelve

(12) coincident peak loads during the year 2000.

Until a different rate has been approved by the Commission, such rate for each

succeeding calendar year, to be effective on and after January 1, of such succeeding year, will be

calculated by dividing the Zone 1 revenue requirement, specified in Attachment H, by the sum of

the twelve (12) coincident peak loads during the preceding calendar year. The rate for 2001,

pursuant to the above, is $1,013.18 per MW-month.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: August 8, 2001 Effective: June 1, 2001Filed to comply with Order of the Federal Energy Regulatory Commission,Docket No. ER01-1989-000, issued July 9, 2001, 96 FERC ¶ 61,034 (2001).

Southwest Power Pool Original Sheet No. 162FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT I

Index Of Network Integration Transmission Service Customers

Date ofCustomer Service Agreement

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 163FERC Electric Tariff Superseding Original Sheet No. 163Fourth Revised Volume No. 1

ATTACHMENT J

Recovery Of Costs Associated With New Facilities

1. Direct Assignment Facilities

Where a System Impact and/or Facilities Study indicates the need to construct Direct

Assignment Facilities to accommodate a request for Transmission Service, the Transmission

Customer shall be charged the full cost of such Direct Assignment Facilities. Such costs shall be

specified in a Service Agreement.

2. Network Upgrades

a. The costs of completed Network Upgrades shall be handled as follows:

i. During the Transition Period:

The Transmission Customer(s) requesting Transmission Service which requires Network

Upgrades shall pay the costs associated with those Network Upgrades to the extent consistent

with Commission policy. Such costs shall be specified in a Service Agreement to be filed with

the Commission.

ii. After the Transition Period:

All Network Upgrades constructed for service under this Tariff shall be rolled-in with all

other transmission facilities. There shall be no direct assignment of Network Upgrade costs to

Transmission Customers. However, the Transmission Provider shall not allow the construction

and roll-in of a Network Upgrade when the Transmission Provider finds more economic or

efficient alternatives. This roll-in of Network Upgrade costs shall not include the portion of any

such Network Upgrades paid for during the Transition Period through direct assignment to

Transmission Customer(s).

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 164FERC Electric TariffFourth Revised Volume No. 1

b. The costs of Network Upgrades that are not completed shall be handled as

follows:

If a proposed Network Upgrade was included in a Transmission Provider-approved

Transmission Plan, required by the Transmission Provider, or otherwise accepted or approved by

the Transmission Provider, the Transmission Owner(s) that incurred the costs shall be

reimbursed for those costs by the Transmission Provider. These costs shall include, but are not

limited to: the costs associated with attempting to obtain all necessary approvals for the project

and studies and any construction costs. The Transmission Provider shall develop a mechanism

to recover those costs which will be filed with the Commission on a case by case basis.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 165FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT K

Redispatch Procedures and Redispatch Costs

I. Redispatch to Accommodate a request for Firm Transmission Service

A. Purpose

This Procedure shall apply only to entities that, when applying for Firm Point-To-Point or

Network Integration Transmission Service, were told that the service could be provided only if

redispatch occurs, and that agreed to pay redispatch costs. If an entity in these circumstances

does not agree to pay redispatch costs, then its request for Firm Point-to-Point or Network

Integration Transmission Service will be denied in whole or in part. To the extent the

Transmission Provider can relieve any system constraint for Firm Point-To-Point or Network

Integration Transmission Service by redispatching the generation resources of the Transmission

Owner(s) or other willing generators, it shall do so, provided that the Eligible Customer agrees to

compensate the Transmission Provider pursuant to the terms of Section 27 of this Tariff and this

procedure, and the Transmission Provider and/or the applicable Transmission Owner agree to

provide the service. The procedure under this Section I is not for the purpose of sustaining non-

firm service.

B. Obligations

The Transmission Provider shall arrange for the redispatch of the generation resources of

the Transmission Owner(s) or other willing generators for the stated purpose if it (they) have

agreed to provide the redispatch service. As a condition precedent to receiving Firm Point-to-

Point or Network Integration Transmission Service, a Transmission Customer agrees to pay (1)

the applicable Transmission Service charges described in Schedules 1 through 10; and (2) the

actual redispatch cost necessary to relieve transmission constraints. To the extent practical, the

redispatch of all such resources shall be on a least cost basis. The total charges to be paid by the

Transmission Customer under this Tariff shall not exceed the total charges the Transmission

Customer would have paid under the Transmission Service Tariffs of the Transmission Owners

for the Transmission Service in the same amount from the same Point of Receipt to the same

Point of Delivery unless any additional charges to the Transmission Customer are permitted by

Commission policy.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 166FERC Electric TariffFourth Revised Volume No. 1

C. Assessment Process

Upon receipt of an application for Firm Point-to-Point or Network Integration

Transmission Service, the Transmission Provider shall make a determination of the availability

of the requested Firm Transmission Service. The Transmission Provider's Security Coordination

Center will identify transmission constraints utilizing generally accepted power system analysis

techniques. Where the requested Firm Transmission Service is determined to be not fully

available because of transmission constraints, then the Transmission Provider will assess the

need for redispatch of generation and related modifications to schedules. If the Transmission

Provider concludes that redispatch can sustain the requested Firm Transmission Service, then the

Transmission Provider will provide estimates of the Redispatch Costs for the relief of

transmission constraints as required.

The procedure to be implemented is as follows:

1. Determine the available transmission capacity for the requested Firm Transmission

Service utilizing a load flow computer simulation of the transmission system recognizing

all firm uses of the system.

2. Determine the owned generation resources of the Transmission Owners or others that will

most cost effectively relieve the transmission constraint and the amount of transmission

capacity available through redispatch.

3. Determine the firm transmission reservations that if curtailed would affect or relieve the

transmission constraint and the amount of transmission capacity available through such

curtailment. Solicit from holders of these firm transmission rights the price at which they

would relinquish their rights subject to the applicable caps in this Tariff.

4. The Transmission Provider shall estimate the total incremental cost of redispatch that will

relieve the transmission constraint. In any instance where the redispatch prohibits, or

requires the curtailment of a sale of generation and such redispatch results in foregone

profits (opportunity cost), then the foregone profits of that sale as well as the incremental

production cost of the alternative generation will be identified.

5. The Transmission Provider shall inform the Eligible Customer of the estimated cost of

redispatch for the Firm Transmission Service requested.

6. Any disputes as to compensation for service under this Tariff shall go to dispute

resolution in accord with the provisions of this Tariff.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 167FERC Electric TariffFourth Revised Volume No. 1

D. Redispatch Costs

If redispatch services are provided pursuant to this Attachment K, the Transmission

Provider will in good faith attempt to relieve the constraint by the least cost means whether by

seeking a change in generation output from the Transmission Owners or from any other entity or

by other means including facilitating the payment of firm transmission customers to temporarily

give up their rights in order to relieve the constraint. Redispatch Costs for the Firm

Transmission Application shall be the total cost incurred by the Transmission Provider to

provide the requested service. For generation owned by the Transmission Owner(s) or others,

the redispatch cost shall include the higher of incremental or replacement fuel costs and

incremental operation and maintenance costs of generation facilities necessary to relieve

constraints on the Transmission System(s). Incremental operation and maintenance costs shall

be based on the most recent production cost analysis of the generation system(s) of the

Transmission Owner(s) or others. Incremental or replacement fuel costs will be based on best

available forecasted fuel prices for the effected generation facilities. The costs identified

(including the opportunity costs described in Section C.4 above) shall be the profits foregone for

a sale that is terminated, reduced, or rescheduled from one generator to another, when

appropriate.

For Transmission Customers seeking Firm Transmission Service for the next day, the

Transmission Provider shall provide a nonbinding estimate of the redispatch costs. All

Transmission Customers electing to pay redispatch costs shall pay the actual costs of redispatch

that the Transmission Provider pays in order to provide the Firm Point-to-Point Transmission

Service consistent with Attachment K. Upon receipt of such notice, the Transmission Customer

may elect to pay the redispatch costs or cancel the transaction. The Transmission Provider will

use its best efforts to provide the Transmission Customer with advance notice of the need for

redispatch and the costs of redispatch. In some instances, advance notice may not be possible.

In that event, at the time that redispatch begins for the continuation of service, the Transmission

Provider will give the Transmission Customer that elected to pay redispatch costs the option of

canceling service within an hour and not paying further for such redispatch costs. The

Transmission Provider will keep no revenues associated with relieving the constraint and simply

will pay the entity or entities whose action or actions resulted in the relief of the constraint.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 168FERC Electric TariffFourth Revised Volume No. 1

II. Redispatch To Prevent Curtailment of Firm Transmission Service

Under this provision, the Transmission Provider must take actions in order to keep

already scheduled Transmission Provider Firm Transmission Service and firm load including

bundled native load from being curtailed after non-firm transactions contributing to the

constrained conditions have been curtailed by ordering and/or arranging for the redispatch of

generating units. Such actions may only be taken in response to an emergency or unexpected

system operating condition.

Any redispatch costs, as defined in Section I above, incurred by the Transmission

Provider to prevent curtailment of Firm Transmission Service shall be distributed among all Firm

Transmission Customers, including native load, on the basis of the ratio of each Transmission

Customer’s transmission reservation; or, in the case of bundled native load, each Transmission

Owner’s use of the Transmission System to serve such bundled native load, to the sum of all

such Firm Transmission Service reservations and bundled native load uses.

The Transmission Provider shall contract in a manner that minimizes costs to the greatest

extent practicable to effectively relieve the constraint. SPP shall recover these costs consistent

with Section IV of this Attachment K.

III. Redispatch to Prevent Curtailment of Non-Firm Point-to-Point Transmission

Service

Under this provision, Generation Redispatch provided will only be for non-firm

transmission schedules. This service will be offered for same day and next day schedules. This

Generation Redispatch service for non-firm transmission service is voluntarily offered and

voluntarily purchased. The Transmission Owner(s) have no obligation to provide this service

and the Transmission Customer(s) have no obligation to purchase this service. Jurisdictional

redispatch providers shall provide this service only pursuant to rate schedules, agreements, or

tariffs on file with the Commission. The Transmission Provider will identify candidate units for

redispatch with the knowledge of non-firm and firm transmission service on paths at risk of

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 169FERC Electric TariffFourth Revised Volume No. 1

Curtailment. The total time required to implement this procedure, from the time that a need for

Curtailment is identified, is expected to be 4 hours. If less than 4 hours lead time is available in

advance of Curtailment, the Transmission Provider may Curtail schedules before implementing

the process.

A. Non Firm Redispatch Process

1. The Transmission Provider identifies a need for Curtailment or receives a request for

Curtailment from a control area operator; posts the fact that generation redispatch is

being assessed; and selects and evaluates candidate generating units for redispatch to

mitigate the problem.

2. After identifying feasible redispatch solutions, the Transmission Provider contacts

generating unit owners, dispatchers, or entities with merchant function responsibility as

applicable to solicit willingness to supply Generation Redispatch Service and to obtain

associated pricing and terms.

3. The Transmission Provider receives price quotes (including any cost of transmission

service) and associated terms; picks most economic alternative; allocates selected

alternative to submitted transmission schedules based on relative impacts on the affected

transmission facility; and contacts prospective Generation Redispatch purchasers with

pricing for purchasers to accept or reject. Notification of redispatch availability on

affected paths with schedules will be posted on the OASIS purchasers with schedules will

also be notified by phone or FAX.

4. Prospective Generation Redispatch purchasers accept or decline the Generation

Redispatch Service and pricing; deadline to respond is 1 hour before announced time of

Curtailment. If there is no response from a prospective Generation Redispatch purchaser,

then such purchaser will be deemed to have declined the service.

5. The Transmission Provider receives responses, notifies Generation Redispatch

provider(s) of the quantity of service to be provided directly to Generation Redispatch

purchaser(s). The deadline for the Transmission Provider notification to Generation

Redispatch provider is 50 minutes before announced time of Curtailment. Generation

Redispatch providers will be obligated to supply only that energy which the Generation

Redispatch purchasers have committed to buy.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 170FERC Electric TariffFourth Revised Volume No. 1

6. Provider(s) and purchaser(s) of Generation Redispatch Service fax and execute

transaction confirmations directly with each other to document their agreement. Any

terms and conditions peculiar to a specific service (e.g., minimum run time for a

designated unit, regardless of duration of Curtailment) will be specified on the transaction

confirmation. These confirmations will not go through the Transmission Provider. A

copy of the transaction confirmation will be faxed to the Transmission Provider by the

Generation Redispatch purchaser to provide verification that the service is being

purchased and provided.

7. Service is then provided by Generation Redispatch provider.

B. Redispatch Priorities

1. To the extent the quantity of Generation Redispatch Service purchased and supplied

offsets the effect of the transaction on the impacted transmission facilities, there will be

no further redispatch obligation on the Generation Redispatch purchaser.

2. To the extent that the Generation Redispatch purchaser has not purchased Generation

Redispatch Service to offset its total schedule, it continues to have an exposure to the

need for incremental redispatch or schedule curtailment.

IV. Recovery of Redispatch Costs by the Transmission Provider

The Transmission Provider shall be entitled to recover all redispatch costs, not otherwise

directly assigned to the Transmission Customers associated with the compensation of generation

owners, or Transmission Owners pursuant to this Attachment K. In order to recover these costs,

the Transmission Provider shall add an additional charge to the base transmission charges under

this Tariff calculated using the following formula:

Additional Monthly redispatch charge (per kW – month) =

Prior Month’s Redispatch Costs not otherwise recovered (Including Any Carrying Costs And Any True-Up)_______(Transmission System Peak for the same prior month) - (coincident peak usage of all Firm Point-to-Point Transmission Service) + (Reserved Capacity of all Firm Point-to-Point Transmission Service customers)

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 171FERC Electric TariffFourth Revised Volume No. 1

The Transmission Provider shall apply this charge to all point-to-point customers under

the Tariff in addition to the base transmission charge. The charge developed above is the rate for

monthly service. The rate for weekly service will be the product of the monthly rate and 12

divided by 52. The rate for daily service will be the product of the monthly rate and 12 divided

by 260. The rate for hourly service will be the product of the monthly rate and 12 divided by

4160. Network Customers shall pay a load ratio share of the prior month’s redispatch costs

based on their Network Load coincident with the Transmission System peak for that prior month

in which the redispatch expenses were incurred divided by the Transmission System peak for

that same month. For bundled retail load for which network service is not taken under this

Tariff, the Transmission Provider shall recover the remaining costs from the Transmission

Owners serving the bundled retail load, with the Transmission Owner allocated these remaining

amounts based upon their relative proportions of bundled retail load (for which network service

is not taken under this Tariff).

In deriving the charges, the Transmission Provider may estimate the redispatch costs it

owes or will owe. The Transmission Provider shall true-up that estimate in the month following

the subsequent month, with carrying costs, once actuals are available.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 172FERC Electric Tariff Superseding Original Sheet No. 172Fourth Revised Volume No. 1

ATTACHMENT L

TREATMENT OF REVENUES

I. Payments and Distribution of Revenues

Payment will be made in accord with Section 7 of the Tariff to the Transmission Provider

as agent for the Transmission Owners for all services provided under this Tariff. The

Transmission Provider will distribute the revenues received to the Transmission Owners in

accord with the provisions of this Attachment L.

II. Allocation of Base Transmission Revenues

A. Grandfathered Agreements

Except by mutual agreement of the Parties to Grandfathered Agreements, the

Transmission Provider shall have no claim to the revenues collected under such agreements, and

shall not collect or allocate any revenues for transmission service related to such transactions.

The Transmission Owner providing the transmission service under the Grandfathered

Agreements, therefore, will continue to receive payment directly from the customer under the

Grandfathered Agreement.

B. Network Integration Transmission Service

Revenues collected by the Transmission Provider for Network Integration Transmission

Service under Schedule 9 shall be fully allocated to the Transmission Owner(s) of the host Zone.

Where a Network Customer has designated Network Load not physically interconnected with the

Transmission System under Section 31.3, revenues collected by the Transmission Provider for

Network Integration Transmission Service for that network load shall be allocated to the

Transmission Owners on the same basis as Point-To-Point Transmission Service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Second Revised Sheet No. 173FERC Electric Tariff Superseding First Revised Sheet No. 173Fourth Revised Volume No. 1

C. Point-To-Point Transmission Service

Except to the extent required under Section IV of this Attachment L, revenues collected

by the Transmission Provider for Point-To-Point Transmission Service shall be allocated as

follows:

1. Revenues collected by the Transmission Provider for Point-To-Point

Transmission Service under Schedules 7 and 8 associated with power transactions where the

generation source(s) and load(s) are located within the host Zone shall be fully allocated to the

Transmission Owner of that host Zone whether the generation source is controlled by the

Transmission Owner or another entity.

2. All other Transmission Provider Point-To-Point Transmission Service revenues

under Schedules 7 and 8 collected by the Transmission Provider (i.e., other than those revenues

specified in paragraph C.1)are shared between all Zones fifty percent (50%) in proportion to

annual revenue requirements; and fifty percent (50%) based upon the MW-mile impacts incurred

by the Transmission Owners. The annual revenue requirements used shall be those stated in

Attachment H. The MW-mile impacts shall be determined by use of the procedures in

Attachment S.

3. Where there are Transmission Owners within a Zone whose facilities have not

been included in the rates stated in Attachments H and T, the Transmission Provider will further

allocate the Point-to-Point Transmission Service revenues allocated to that Zone among the

Zones Transmission Owners on the same basis as the revenues are allocated to the Zone. For the

application of this provision each Transmission Owner shall have an annual revenue requirement

filed with the Commission.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 12, 2003 Effective: February 21, 2003

Southwest Power Pool Original Sheet No. 173AFERC Electric TariffFourth Revised Volume No. 1

III. Allocation of Other Revenues

1. Revenues associated with redispatch service will be paid to the generation owner

providing the service for the Transmission Provider.

2. Revenues associated with Reactive Supply and Voltage Control from Generation

Sources Services under Schedule 2 will be paid to the generation owner providing

the service for the Transmission Provider consistent with the development of the

charges under Schedule 2.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 12, 2003 Effective: February 21, 2003

Southwest Power Pool First Revised Sheet No. 174FERC Electric Tariff Superseding Original Sheet No. 174Fourth Revised Volume No. 1

3. Energy or revenues received as compensation for transmission losses shall be

distributed consistent with Attachment M.

4. Revenues associated with Scheduling and Tariff Administration Service under

Schedule 1 will remain with the Transmission Provider to pay for the costs of

providing that service (except for the revenues for related services provided by

individual Control Areas for the movement of power within, into, or out of the

respective Control Areas which shall go to the appropriate Transmission

Owner(s)).

5. Payments associated with penalties imposed under this Tariff will be used to

reduce the Transmission Provider's Scheduling and Tariff Administration Service

costs (though the non-penalty portion of the charge will go back to the

Transmission Owner(s) that actually provided the service).

6. Transmission Owner costs associated with System Impact and Facilities Studies

compensated by the Transmission Customer shall go to the appropriate

Transmission Owner(s).

7. The revenues associated with Direct Assignment Facilities shall go directly to the

Transmission Owner(s) owning the facilities. The revenues associated with

Network Upgrades shall be first assigned to the Transmission Owner building the

Network Upgrades to meet the annual revenue requirements of such facilities. If

multiple Transmission Owners construct the facilities, the revenues shall be

shared in accordance with each Transmission Owner’s respective revenue

requirement for such facilities or as otherwise agreed by the Transmission

Owners. The remaining revenues shall be allocated in accordance with Section II

of this Attachment L.

8. The revenues associated with Wholesale Distribution Service shall go directly to

the Transmission Owner(s) owning the facilities consistent with Schedule 10.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Second Revised Sheet No. 175FERC Electric Tariff Superseding First Revised Sheet No. 175Fourth Revised Volume No. 1

9. Any additional revenues received under Section 22.1 shall be treated in the same

manner as revenues under Section II.D. of this Attachment L.

IV. Exception to the Provisions of Section II.C of this Attachment L

Pursuant to the Agreement of the Southwest Power Pool Transmission Owners and

Southwest Power Pool for the Upgrade for the LaCygne to Stilwell 345 kV Transmission Line

(“LaCygne-Stilwell Agreement”) submitted to the FERC on February 20, 2003 in Docket No.

ER03-547, and conditionally accepted by the Commission in an order dated April 10, 2003, the

Transmission Provider and the Transmission Owners agreed to create an exception to the

provisions of this Attachment L for the sole purpose of distributing revenues associated with

upgrades to the LaCygne to Stilwell 345 kV line, as set forth in the LaCygne-Stilwell

Agreement, which has been incorporated into this Attachment L.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 12, 2003 Effective: February 21, 2003

Southwest Power Pool Original Sheet No. 175AFERC Electric TariffFourth Revised Volume No. 1

Agreement of the Southwest Power Pool Transmission OwnersAnd Southwest Power Pool

ForThe Upgrade of The LaCygne to Stilwell 345 kV Transmission Line

This Agreement, entered into this 20th day of February, 2003, by and between Southwest

Power Pool, Inc. (“SPP”) and the Participating SPP Transmission Owners (collectively, “the

Parties”).

WHEREAS, SPP provides regional transmission service over the transmission systems of

the SPP Transmission Owners pursuant to an Open Access Transmission Tariff (“OATT”) filed

consistent with the Order No. 888 pro forma OATT;

WHEREAS, SPP did not foresee an obligation under the policies of the Federal Energy

Regulatory Commission (“FERC”) to renew a number of Firm Point-to-Point transmission

reservations previously granted under the SPP OATT;

WHEREAS, SPP does not presently have sufficient Available Transfer Capability

(“ATC”) on the LaCygne to Stilwell line (“the Circuit”) to renew Firm Point-to-Point

transmission service for such reservations;

WHEREAS, FERC’s recent order in Exelon Generation Co., LLC v. Southwest Power

Pool, Inc., 99 FERC ¶ 61,235, reh’g denied, 101 FERC ¶ 61,226 (2002), obligates SPP to renew

said firm transmission reservations, even though the SPP transmission system was not expanded

in anticipation of renewing said firm transmission reservations;

WHEREAS, SPP has experienced Level 5 Transmission Loading Relief due to the

Circuit limitation;

WHEREAS, the Parties desire to remedy system constraints posed by the Circuit by

reconductoring and upgrading its capacity from 1,251 MVA to 1,793 MVA;

WHEREAS, SPP anticipates a merger between it and the Midwest Independent

Transmission System Operator, Inc., forming the Resulting Company, that may occur before the

project costs are fully paid to Kansas City Power & Light Company (“Kansas City Power &

Light”) and

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 12, 2003 Effective: February 21, 2003

Southwest Power Pool Original Sheet No. 175BFERC Electric TariffFourth Revised Volume No. 1

that subsequent to the effective date of that merger, service will be provided to the Participating

SPP Transmission Owners under the Resulting Company OATT as successor to the SPP OATT;

WHEREAS, the elimination of the Circuit limitation will provide additional ATC and

allow the provision of additional point-to-point transmission service under the SPP OATT and

the Resulting Company OATT and provide significant additional revenue that would be

allocable to the Parties; and

WHEREAS, the Parties agree that capitalized terms used herein shall have the same

meaning as in the SPP OATT.

NOW, THEREFORE, in consideration of the mutual covenants and agreements herein,

the Parties agree as follows:

1.0 Kansas City Power & Light agrees to upgrade the Circuit by reconductoring it and

increasing the Circuit’s capacity. Kansas City Power & Light also agrees to use its best

efforts to complete the upgrade by July 1, 2003. Furthermore, Kansas City Power &

Light agrees to use its best efforts to not exceed the upgrade estimated cost of

$6,557,000.

2.0 The Parties agree to initially treat Kansas City Power & Light’s upgrade of the Circuit in

the same manner that a Direct Assignment Facility would be treated under the SPP

OATT and the revenue allocation provisions of Attachment L, Section III.7. The Parties

agree that the circumstances here are unique and that they are not by their Agreement

here agreeing in any way that this same treatment would be appropriate in other

circumstances. Future circumstances similar to this one will need to be evaluated on a

case-by-case basis.

3.0 The Parties agree that SPP and the Resulting Company shall allocate to Kansas City

Power & Light any and all transmission service revenues resulting from transmission

service agreements under Schedules 7 and 8 of the SPP Tariff entered into after the date

of this Agreement, that could not have been approved but for the reconductoring of the

Circuit. At such time as Kansas City Power & Light’s project

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 12, 2003 Effective: February 21, 2003

Southwest Power Pool Original Sheet No. 175CFERC Electric TariffFourth Revised Volume No. 1

cost (plus a return on invested capital) for the Circuit upgrade is recovered, subject to the

provisions of paragraph 4.0 below, SPP and the Resulting Company shall thereafter

allocate transmission service revenues from service agreements made possible by the

reconductoring of the Circuit pursuant to the applicable provisions of the SPP OATT or

the Resulting Company Transmission Owner Agreement.

4.0 In the event that the actual cost for the project exceeds the estimated project cost of

$6,557,000, the recognized project cost to Kansas City Power & Light shall be limited to

no more than $7,541,000 (115% of the estimated Cost). Any project expenditure in

excess $7,541,000 will be solely borne by Kansas City Power & Light. Additionally,

Kansas City Power & Light shall be allocated a return on invested capital at a rate of 8.25

percent per annum, applied and paid monthly on the outstanding capital balance.

5.0 Kansas City Power & Light agrees to provide the SPP, the Resulting Company and/or the

other Participating SPP Transmission Owners access to its books and records that pertain

to this project for the purpose of any necessary audit of the costs incurred in completing

the upgrade of the Circuit.

6.0 In the event that a Participating SPP Transmission Owner terminates its provision of

service under the SPP OATT or the Resulting Company OATT, such transmission owner

shall be under no further obligation pursuant to this agreement and the revenues

reallocated from the remaining Participating SPP Transmission Owners shall be adjusted

to reflect the revenue allocations that would result after the withdrawal of the terminating

Transmission Owner.

7.0 The SPP will provide monthly reports to each of the Participating SPP Transmission

Owners detailing the amount of transmission revenue allocated on behalf of each party to

Kansas City Power & Light for any month in which such revenues are allocated. The

SPP will provide monthly summary reports and quarterly detailed reports to each of the

Participating SPP Transmission Owners detailing the transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 12, 2003 Effective: February 21, 2003

Southwest Power Pool Original Sheet No. 175DFERC Electric TariffFourth Revised Volume No. 1

service agreements under Schedules 7 and 8 of the OATT entered into after the date of

the Agreement that could not have been approved but for the reconductoring of the

Circuit.

8.0 The Parties agree that consideration will be given to recognizing the contributions of each

Party to the construction of the facility upgrade at such time as the methodologies for

allocation of Financial Transmission Rights (“FTR’s”), Congestion Revenue Rights

(“CRR’s”), or other assigned transmission rights are developed, consistent with the

requirements of authorities having jurisdiction over such allocation.

9.0 [Reserved]

10.0 This Agreement shall be binding on the successors and assigns of the Parties.

11.0 Any notice or request made to or by a Party regarding this Agreement shall be made to

the representatives of all other Parties as indicated below. Such representative and

address for notices or requests may be changed from time to time by notice by any Party.

Southwest Power Pool:

415 N. McKinley, 800 Plaza West

Little Rock, AR 72205

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 12, 2003 Effective: February 21, 2003

Southwest Power Pool Original Sheet No. 175EFERC Electric TariffFourth Revised Volume No. 1

Transmission Owners:1. American Electric Power Service Corporation as agent for Public Service

Company of Oklahoma and Southwestern Electric Power Company

Sr. VP, Transmission825 Tech Center Dr.Gahanna, OH 43230

and

Director, Transmission & Interconnection Services1 Riverside PlazaColumbus, OH 43215

2. City Utilities of Springfield, Missouri301 E. Central StreetP.O. Box 551Springfield, MO 65801

3. Empire District Electric Company602 S. Joplin Ave.P.O. Box 127Joplin, MO 64801

4. Grand River Dam AuthorityP.O. Box 772Locust Grove, OK 74352

5. Kansas City Power & Light Company1201 WalnutP.O. Box 418679Kansas City, MO 64141-9679

6. Oklahoma Gas & Electric CompanyP.O. Box 321Oklahoma City, OK 73101-0321

7. Midwest Energy, Inc.1330 Canterbury Road

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 12, 2003 Effective: February 21, 2003

Southwest Power Pool Original Sheet No. 175FFERC Electric TariffFourth Revised Volume No. 1

P.O. Box 898Hays, KS 67601-1432

8. Southwestern Power AdministrationOne West Third StreetTulsa, OK 74103-3519

9. Xcel Energy Services Inc. as agent for Southwestern Public Service CompanySouthwestern Public Service CompanyAttn: Dave Grover600 Tyler StreetAmarillo, TX 79101

10. Western Farmers Electric CooperativeP.O. Box 429701 N.E. 7th StreetAnadarko, OK 73305-0429

11. Westar Energy, Inc.Tom StuchlikSenior Director, Transmission ServicesP.O. Box 889818 S. Kansas AvenueTopeka, KS 66601

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 12, 2003 Effective: February 21, 2003

Southwest Power Pool Original Sheet No. 176FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT M

LOSS COMPENSATION PROCEDURE

PURPOSE

This loss compensation procedure will be used to quantify transmission loss energy that

the Transmission Customer is required to replace to the Transmission Owner(s) under this Tariff.

The Transmission Customer shall be responsible for replacing the losses due on a real time basis.

The Transmission Customer shall deliver the loss energy to the Control Area(s) affected by the

transactions.

Each Transmission Owner shall maintain a schedule showing its allocation of loss energy

for the provision of transmission service on its system. For the Commission regulated

Transmission Owners, these allocations shall be pursuant to Commission approved schedules.

The average loss factor (LAVG) for each Transmission Owner are stated in Appendix 1 to this

Attachment M.

LOSS DETERMINATION - NETWORK INTEGRATION TRANSMISSION SERVICE

The Network Customer is responsible for replacing losses, associated with Network

Integration Transmission Service to its Network Load, to each Zone in which its Network Load

is located. The Network Customer’s loss responsibility is the product of the Zone loss factor and

the energy delivered within that Zone by the Network Customer.

Where a Network Customer has designated Network Load not physically interconnected

with the Transmission System under Section 31.3, the Network Customer is responsible for

replacing losses, associated with Network Integration Transmission Service to its Network Load,

for schedules from Network Resources (as well as other non-designated generation resources)

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 177FERC Electric TariffFourth Revised Volume No. 1

located within the Transmission System. These losses will be determined, and allocated to the

Transmission Owners, in the same manner as losses for Point-To-Point Transmission Service.

LOSS DETERMINATION - POINT-TO-POINT TRANSMISSION SERVICE

The Transmission Provider shall calculate a loss matrix twice each year to show the

composite loss factors for each transaction, as a percentage of the transaction, based on the total

of each Transmission Owner’s pro rata MW-mile impact multiplied by the applicable loss factor

for energy for such Transmission Owner. The factors for inclusion in the loss matrix shall be

determined as follows:

1) For each Transmission Owner, determine a Transaction Participation Factor

(TPF) which is the MW-mile impact on that Owner expressed as a percentage of

the MW-mile impacts on all Transmission Owners for the given transaction. The

MW mile impacts will be calculated in accordance with Attachment S.

2) The seasonal application of the individual Transmission Owner’s loss factors

under this Tariff shall be consistent with the Transmission Provider’s seasonal

calculation of the MW-Mile impact factors under Attachment S.

3) Calculate a weighted system loss factor for each transaction as the sum of the

products of: TPF x LAVG for the system of each Transmission Owner.

The amount of loss energy supplied to and to be replaced by each Transmission Customer for

each transaction will be determined by multiplying the MWh’s of the schedule by the composite

loss factor for the transaction. The amount of loss energy supplied by and to be replaced to each

Transmission Owner for each

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 178FERC Electric TariffFourth Revised Volume No. 1

transaction will be determined by multiplying the MW’s of the schedule by that Owner’s TPF

and loss factor (LAVG). The Transmission Customer shall replace the loss energy shown in the

loss matrix (as a percentage of the transaction) to the Transmission Owners for each transaction.

The Transmission Provider shall be responsible for allocating the replaced loss energy among the

Transmission Owners consistent with the above methodology.

OPTIONAL ANNUAL PURCHASE OF LOSS ENERGY

The Transmission Customer may meet its obligation to replace loss energy under the

Tariff by electing to purchase all loss energy for which it is responsible under this Tariff on an

annual basis. Such election will be for a full calendar year and shall be exercised by execution of

a Service Agreement for Loss Compensation Service, Attachment N, on or before December 1 of

the prior calendar year. Under this Agreement, the Transmission Customer will purchase the

specified quantity of loss energy for all transactions under this Tariff. New Transmission

Customers may make such election at the time they first execute Attachment A or Attachment B

under this Tariff, but in no event at a time later than the time at which they first take service

under the Tariff. In this circumstance, the term of the election will be for the remainder of the

calendar year. The Transmission Customers will fully pay for such losses. Compensation for

losses will be at a cost determined by multiplying the MWh of loss energy by a price index. The

price index will be determined by multiplying the price of commodity gas times an estimated

average heat rate of 10.5 MMBtu/MWh. The price of commodity gas will be determined each

month as the price published under the heading of "Houston Ship Channel/Beaumont, Texas

Index", "large packages only", under the subheading of Inside F.E.R.C.’s GAS MARKET

REPORT. The price will become effective on the day after the index is posted on the SPP

OASIS and remain effective until the day after the next posting of the index. This index is

updated monthly.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 179FERC Electric TariffFourth Revised Volume No. 1

(gpi/MMBtu) * 10.5 (MMBtu/Mwh) = $/Mwh

Where:gpi = the "Houston Ship Channel/Beaumont Texas Index."

The Transmission Provider shall be responsible for allocating the revenue from the sale of losses

among the Transmission Owners consistent with the above methodology and Attachment L.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 180FERC Electric TariffFourth Revised Volume No. 1

Appendix 1 to Attachment M

Zone 1: Public Service Company of Oklahoma and Southwestern

Electric Power Company, Subsidiaries of American Electric

Power, Inc...........................................................................................................2.90

Zone 2: Cleco Corporation...............................................................................................1.95

Zone 3: City Utilities of Springfield, Missouri................................................................2.00

Zone 4: Empire District....................................................................................................2.71

Zone 5: Grand River Dam Authority...............................................................................3.50

Zone 6: Kansas City Power and Light Company.............................................................1.90

Zone 7: Oklahoma Gas & Electric Company...................................................................3.00

Zone 8: Mid-West Energy................................................................................................7.20

Zone 9: Missouri Public Service

Delivery Voltage Summer Winter

345/161 kV 1.5% 1.0%

69/34 kV 2.0% 1.7%

Zone 10: Southwestern Power Administration..................................................................4.00

Zone 11: Southwestern Public Service...........................................................................3.0111

Zone 12: Sunflower Electric Cooperative..........................................................................4.50

Zone 13: Western Farmers Electric Cooperative...............................................................3.00

Zone 14: Western Resources, Inc. (Kansas Gas & Electric and

Western Resources)............................................................................................2.94

Zone 15: West Plains Energy

Delivery Voltage Summer Winter

230/138/115 kV 5.3% 2.9%

34.5 kV 6.0% 5.0%

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 181FERC Electric TariffFourth Revised Volume No. 1

Page 1 of 2

ATTACHMENT N

Form Of Service Agreement For Loss Compensation Service

1.0 This Service Agreement, dated as of _______________, is entered into, by and between

Southwest Power Pool, Inc. ("Transmission Provider"), and ________________

("Transmission Customer").

2.0 The Transmission Customer has been determined by The Transmission Provider to have

a Completed Application for Point-To-Point Transmission Service under the Tariff.

3.0 Service under this agreement shall commence on ______________. Service under this

agreement shall terminate on ______, the last calendar day of the year in which service

commences.

4.0 The Transmission Customer agrees to supply information the Transmission Provider

deems reasonably necessary in accordance with Good Utility Practice in order for it to

provide the requested service.

5.0 On behalf of the Transmission Owners, and as authorized by the Transmission Owners,

The Transmission Provider agrees to provide and the Transmission Customer agrees to

take and pay for Loss Compensation Service in accordance with the provisions of Part II

and Attachment M of the Tariff and this Service Agreement. All charges for Loss

Compensation Service shall be determined in accordance with the provisions of

Attachment M.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 182FERC Electric TariffFourth Revised Volume No. 1

Page 2 of 2

6.0 Any notice or requests made to or by either Party regarding this Service Agreement shall

be made to the representative of the other Party as indicated below.

Southwest Power Pool:

__________________________

415 N. McKinley, 700 Plaza West

Little Rock, AR 72205

Transmission Customer:

__________________________

__________________________

__________________________

7.0 The Tariff is incorporated herein and made a part hereof.

IN WITNESS WHEREOF, the Parties have caused this Service Agreement to be

executed by their respective authorized officials.

Southwest Power Pool:

By:______________________ _____________________ _____________________Name Title Date

Transmission Customer:

By:______________________ _____________________ _____________________Name Title Date

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 183FERC Electric Tariff Superseding Original Sheet No. 183Fourth Revised Volume No. 1

ATTACHMENT O

TRANSMISSION PLANNING AND EXPANSION PROCEDURES

These Procedures describe transmission planning and expansion procedures for the SPP

Transmission System. Transmission Owners are obligated to build facilities subject to

regulatory approval under the provisions of this Tariff. The Transmission Provider will not build

or own transmission facilities. These procedures neither obligate the Transmission Provider nor

Transmission Owners to build or own facilities within another Transmission Owner’s area where

a limit may exist. Transmission Owners may at any time voluntarily form associations and

partnerships between Members or with non-Members to jointly construct and finance new

transmission facilities provided such projects are subject to the assessment process of these

Procedures.

1.0 Planning Criteria

The individual planning criteria of each Transmission Owner shall be the basis for

determining whether a violation of criteria exists and when a need for new facilities should be

considered. This planning criteria shall, at a minimum, conform to SPP Criteria and NERC

Planning Standards. Transmission Owners shall submit their transmission planning criteria to the

Transmission Provider. This criteria may be modified at any time provided that, if the criteria is

made more stringent, the increased requirements shall not apply retroactively to transmission

planning studies previously completed nor studies already underway by the Transmission

Provider.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO OperationsFiled to comply with order of the Federal Energy Regulatory Commission, Docket No.RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶ 61,110

Southwest Power Pool First Revised Sheet No. 184FERC Electric Tariff Superseding Original Sheet No. 184Fourth Revised Volume No. 1

2.0 Planning and Assessment Studies

The Transmission Provider shall independently perform regional transmission planning studies.

These studies shall assess the reliability and economic operation of the SPP Transmission

System. Transmission planning studies may also be performed by individual Transmission

Owners. Members shall contact the Transmission Provider whenever new facilities that impact

interconnected operation are in the conceptual planning stage so that the optimal integration of

any new facilities and potentially benefiting parties can be identified. The Transmission

Provider shall periodically inform the Transmission Owners of identified operating constraints

that should be addressed in future studies. Seasonal transmission assessments shall be performed

by the Transmission Provider. These planning studies and seasonal assessments are for purposes

of identifying any planning criteria violations that may exist. Transmission Owners shall submit

their five-year transmission construction plans to the Transmission Provider.

In the event the assessment process identifies a violation, the violation shall be directed to the

associated Transmission Owner. The responsible Transmission Owner shall respond by

explaining why the violation is not valid or by identifying alterations in its transmission plan

which correct the criteria violation. The Transmission Owner with an identified limit shall be

responsible for performing studies to determine alternatives that remove the limit. If corrective

action causes regional impacts and is therefore subject to cost sharing, the Transmission

Provider’s Staff shall participate in these studies if requested by the Transmission Owner or

another Member.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO OperationsFiled to comply with order of the Federal Energy Regulatory Commission, Docket No.RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶ 61,110

Southwest Power Pool Original Sheet No. 184AFERC Electric TariffFourth Revised Volume No. 1

Recommendations developed by the responsible Transmission Owner to mitigate an

identified violation shall be presented for review and approval by the Transmission Provider.

This review shall evaluate study results for negative impacts on the transmission systems of other

Members. If such negative impacts are found, the Transmission Provider, the impacted Member

and the Transmission Owner shall participate in a joint effort to modify the recommendation to

the satisfaction of all

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO OperationsFiled to comply with order of the Federal Energy Regulatory Commission, Docket No.RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶ 61,110

Southwest Power Pool First Revised Sheet No. 185FERC Electric Tariff Superseding Original Sheet No. 185Fourth Revised Volume No. 1

involved Members. If negative impacts are not found, the Transmission Provider shall accept the

recommendation. If the Transmission Provider finds the study incomplete, the Transmission

Owner shall make further analysis to the satisfaction of the Transmission Provider. Once the

recommendation is shown to address the violation and any negative impacts have been mitigated

to the extent practicable, the Transmission Provider shall accept the recommendation. The

Transmission Provider shall independently make the final determination in the process, subject

to the Dispute Resolution Procedures and subject to review by the FERC or state regulatory

authorities where appropriate.

3.0 Need for New Facilities

Undue limitation on the maintenance of the Transmission System and the provision of firm

transmission service shall be deemed to create a need for new or upgraded facilities. Either

situation shall require submittal of a transmission plan for review by the Transmission Provider

to resolve the issue and may result in cost sharing among the entities that benefit from facility

additions or improvements. This review can be initiated by any Member requesting firm

transmission service under any applicable tariff. This review can also be initiated by any SPP

organizational group as a result of its performance of operational assessments.

If the Transmission Owner with an identified limit is unable to determine alternatives in a timely

manner, the Transmission Provider may establish a task force to determine appropriate options

and make a recommendation. Such task force roster shall include

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO OperationsFiled to comply with order of the Federal Energy Regulatory Commission, Docket No.RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶ 61,110

Southwest Power Pool Original Sheet No. 185AFERC Electric TariffFourth Revised Volume No. 1

representation from the Member with the limiting facility and Members with transmission

service or facilities that might be affected by the limiting facility or corrections. The task force

shall provide a recommendation, along with options considered to the Transmission Provider for

a review of impacts. Based on its review of the task force recommendations, the Transmission

Provider shall independently prepare a proposal for consideration by the SPP Board of Directors

to direct the appropriate Transmission Owners to begin implementation of the project.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO OperationsFiled to comply with order of the Federal Energy Regulatory Commission, Docket No.RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶ 61,110

Southwest Power Pool First Revised Sheet No. 186FERC Electric Tariff Superseding Original Sheet No. 186Fourth Revised Volume No. 1

4.0 Construction

a. Each Transmission Owner shall use due diligence to construct transmission facilities as

directed by the SPP Board of Directors subject to such siting, permitting, and environmental

constraints as may be imposed by state, local and federal laws and regulations, and subject to the

receipt of any necessary federal or state regulatory approvals. Such construction shall be

performed in accordance with Good Utility Practice, applicable SPP Criteria, industry standards,

each Transmission Owner’s specific reliability requirements and operating guidelines (to the

extent these are not inconsistent with other requirements), and in accordance with all applicable

requirements of federal or state regulatory authorities. Each Transmission Owner shall be fully

compensated to the greatest extent permitted by The Commission, for the costs of construction

undertaken by such Transmission Owner in accordance with this Tariff.

b. After a new transmission project has been approved, the Transmission Provider will

direct the appropriate Transmission Owners to begin implementation of the project. If the

project forms a connection between facilities of a single Transmission Owner, that Owner will be

designated to provide the new facilities. If the project forms a connection between facilities

owned by two different Transmission Owners or between a new facility and the facilities of a

Transmission Owner, both entities will be designated to provide the new facilities. The two

entities will agree between themselves how much of the project will be provided by each entity.

If agreement cannot be reached, the Transmission Provider will facilitate the ownership

determination process.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO OperationsFiled to comply with order of the Federal Energy Regulatory Commission, Docket No.RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶ 61,110

Southwest Power Pool First Revised Sheet No. 187FERC Electric Tariff Superseding Original Sheet No. 187Fourth Revised Volume No. 1

c. A designated provider for a project can elect to arrange for another entity or another

existing Transmission Owner to build and/or own the project in their place. If a designated

provider or providers do not or cannot agree to implement the project in a timely manner, the

Transmission Provider will solicit and evaluate proposals for the project from other entities and

select a replacement designated provider.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO OperationsFiled to comply with order of the Federal Energy Regulatory Commission, Docket No.RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶ 61,110

Southwest Power Pool Second Revised Sheet No. 188FERC Electric Tariff Superseding First Revised Sheet No. 188Fourth Revised Volume No. 1

ATTACHMENT P

TransmissionService Type

Term

Transmission Requests 2/

No No Later Earlier Than Than

SPPResponse toApplication

Determine System Capacity ImpactAvailable or Study

(From Date of Customer Commitment)

CustomerResponse 1/

Energy Scheduling 2/

Changes No No Later Later Than Than

Long TermFirm 1 Year or

More60 Days

Prior15 days 30 days 60 days 15 days 1200 day

prior20 mins prior

to hourShort-Term

Firm More than1 month

(monthly)

31 daysprior

120 daysprior

24 hrs 30 days 60 days 4 days 1200 dayprior

20 mins priorto hour

Short-TermFirm 1 mo

(monthly)8 daysprior

90 daysprior

24 hrs 30 days 60 days 4 days 1200 dayprior

20 mins priorto hour

Short-TermFirm More than 1

wk up to 1 month

(weekly)

8 daysprior

60 daysprior

24 hrs 30 days 60 days 48 hrs 1200 dayprior

20 mins priorto hour

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Second Revised Sheet No. 189FERC Electric Tariff Superseding First Revised Sheet No. 189Fourth Revised Volume No. 1

TransmissionService Type

Term

Transmission Requests 2/

No No Later Earlier Than Than

SPPResponse toApplication

Determine System Capacity ImpactAvailable or Study

(From Date of Customer Commitment)

CustomerResponse 1/

Energy Scheduling 2/

Changes

No No Later Later Than Than

Short-TermFirm 1 wk

(weekly)2 daysprior

30 daysprior

24 hrs 30 days 60 days 48 hrs 1200 dayprior

20 mins priorto hour

Short-TermFirm More than

1 day up to 1 wk

(daily)

2 daysprior

14 daysprior

24 hrs 30 days 60 days 24 hrs 1200 dayprior

20 mins priorto hour

Short-TermFirm 1 Day

(daily)1000 day

prior3 days prior 4/ 24 hrs queued > 24

hrs to start: 30 days

60 days queued > 24 hrs to start:

24 hrs

1200 day prior

20 mins prior to hour

queued < 24 hrs to start: best effort

queued < 24 hrs to start:

2 hrs

Non-Firm 1 month or greater

(monthly)

3 daysprior

60 daysprior

N/A 2 days N/A 24 hrs 1500 dayprior

20 minsprior to hour

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Second Revised Sheet No. 190FERC Electric Tariff Superseding First Revised Sheet No. 190Fourth Revised Volume No. 1

TransmissionService Type

Term

Transmission Requests 2/

No NoLater Earlier Than Than

SPPResponse toApplication

Determine System Capacity ImpactAvailable or Study

(From Date of Customer Commitment)

CustomerResponse 1/

Energy Scheduling 2/

Changes No No Later Later Than Than

Non-Firm1 wk up to

1 mo(weekly)

2 daysprior

14 daysprior

N/A 4 hrs N/A 24 hrs 1500 dayprior

20 minsprior to hour

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 190AFERC Electric TariffFourth Revised Volume No. 1

TransmissionService Type

Term

Transmission Requests 2/

No NoLater Earlier Than Than

SPPResponse toApplication

Determine System Capacity ImpactAvailable or Study

(From Date of Customer Commitment)

CustomerResponse 1/

Energy Scheduling 2/

Changes No No Later Later Than Than

Non-Firm1 day up to1 wk (daily)

1200 dayprior

2 daysprior 4/

N/A 30 mins N/A 2 hrs 1500 dayprior

20 minsprior to hour

Non-Firm 1 hour up to1 day

(hourly)

30 mins. prior

1200 dayprior

N/A Queued > 1 hr prior to

start:30 mins

N/A Queued day prior: 30 mins

1500 dayprior 6/

20 minsprior to hour

Queued < 1 hr prior to

startbest effort

Queuedcurrent day:

5 min 5/

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 190BFERC Electric TariffFourth Revised Volume No. 1

TransmissionService Type

Term

Transmission Requests 2/

No NoLater Earlier Than Than

SPPResponse toApplication

Determine System Capacity ImpactAvailable or Study

(From Date of Customer Commitment)

CustomerResponse 1/

Energy Scheduling 2/

Changes No No Later Later Than Than

Next Hour Market next-hour

(hourly)20 minsprior 3/

1 hourprior 3/

N/A Best Effort N/A N/A 3/ 20 minsprior to hour 3/

20 mins. prior tohour 3/

1/ For transactions not covered by an umbrella service agreement, the customer response must be execution of a service agreement or a request that an unexecuted service agreement be filed with the Commission pursuant to Section 15.3 of the Tariff. For transactions under an umbrella service agreement, the above times are the deadlines by which time the customer must notify The Transmission Provider of its acceptance of the offer to provide transmission.

2/ The Transmission Provider, in its discretion exercised on a non-discriminatory basis, may waive any of these requirements.

3/ All Next-Hour Market requests are submitted on schedule request and are deemed to be pre-confirmed.

4/ Excluding Sundays and NERC Holidays.

5/ Or 2300 of previous day if for first hour of day.

6/ Non-firm schedules will be accepted after 1500 day prior if there are no new reliability risks identified since the reservation was accepted. This includes but is not limited to NERC TLR in effect.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: March 30, 2004 Effective: April 1, 2004

Southwest Power Pool Original Sheet No. 191FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT Q

Form of Application For Short-Term Firm and Non-Firm Transmission Service

Email Address: Submit Reset

Customer Information Seller Information

Name Company

Comments

Company

DUNS

Paths and POR/POD Information Transmission Information

POR POD

Path Name1 Source 2 Sink

Capacity Type

Capacity Price

Pre-confirmed

Dates and Times Reference Numbers

Begin Date Time Time Zone

End Date Time Time Zone

Deal Request

Sale

1 Delivering Member 2 Receiving Member

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 192FERC Electric Tariff Superseding Original Sheet No. 192Fourth Revised Volume No. 1

ATTACHMENT R

The currently effective NERC TLR Procedures are those on file with andaccepted by the Federal Energy Regulatory Commission

[PRIOR VERSION OF ATTACHMENT R HASBEEN DELETED IN ITS ENTIRETY]

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool First Revised Sheet Nos. 193-210FERC Electric Tariff Superseding Original Sheet Nos. 193-210Fourth Revised Volume No. 1

Sheet Nos. 193-210 are reserved for future use

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 7, 2001 Effective: June 1, 2001

Southwest Power Pool Original Sheet No. 211FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT S

Procedure for Calculation of MW-Mile Impacts for Use in Revenue Allocation and Determination of Losses

1. Introduction

The purpose of this Attachment S is to provide written documentation of the procedures

for calculation of MW-mile impacts for use in revenue allocation and determination of losses as

implemented by the Transmission Provider. Definitions of the models and parameters used in

the calculations are presented, as well as a description of the calculations performed by the

"Megawatt-Mile Software". Details of the application of MW-mile impacts to the allocation of

revenues and the determination of losses are discussed in Attachments L and M respectively.

The megawatt-mile technique is a distance based method of calculating impacts for transmission

use considering that power will, to some extent, flow over all available paths from the generating

source to the load.

2. Definitions, Models and Parameters Used

2.1 Composition of the Network Model - The network models used in the

transmission service charge calculations are derived from loadflow models of SPP

system assembled annually by SPP. Prior to April 1 each year, data are

submitted, models assembled, modifications required for using the models in the

MW-mile impact calculations are made, and the impact tables for the upcoming

Summer and Winter seasons are computed.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 212FERC Electric TariffFourth Revised Volume No. 1

2.1.1 Seasonal Models - The seasonal models used in the calculations are the

Summer Peak Load Operating model and the Winter Peak Load Operating

model, as modified for use in the transmission service charge

computations. Modifications to the models include some AREA (SPP

Transmission Owners are represented by AREAs in the model)

renumbering and required changes to phase shifter representations as

outlined in section 2.1.4. Estimated MW-Mile impacts for future Summer

and Winter seasons may be calculated using the appropriate planning

model from the annual series of SPP models.

2.1.2 Transmission Elements Included in the Transmission Service Charge

Calculations - All transmission lines and terminal equipment reflected in

the Transmission Owners' transmission accounts and included in

transmission rates may be included in the network model.

2.1.3 Transmission Facility Rating Assumptions - The ratings used are the most

limiting rating reported in the then-current SPP operating model on the

normal continuous MVA ratings of transmission facilities for the

applicable season. For transmission lines, these are normally the lesser of

the conductor thermal rating and the rating of equipment such as switches,

wavetraps, etc. For transformers, these are normally the continuous rating

of the transformers. The corresponding ratings from the applicable SPP

planning model are used in estimating MW-mile impacts for future years.

2.1.4 Modeling Phase Shifters - Phase shifting transformers within SPP are

represented based on typical operations.

2.2 Timing of Formula Changes - Each May 1, the formula provided in Attachment H

will be modified to reflect actual data for the prior calendar year.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 213FERC Electric TariffFourth Revised Volume No. 1

2.3 Transmission Facility Ownership Representation - Transmission Owners are

required to update their transmission facility ownership representation annually.

This update shall reflect all new transmission facility additions and retirements for

the prior calendar year including any new network facilities constructed pursuant

to any regional transmission planning process.

2.3.1 Transmission Lines and Terminals - Each transmission line which is to

participate in the calculation of the MW-mile impacts has a record in a

branch ownership file. This file is required by the Megawatt-Mile

Software in order to calculate MW-mile impacts for use of every branch.

The ownership file contains two types of records for every transmission

line: one record contains the total line mileage; the other reflects the

percent of each Transmission Owner's "ownership" (i.e., for collecting

rents) of the line. If ownership percentages for a given branch are not

provided, the ownership will be divided equally to the AREA numbers in

which the buses on either end of the branch reside in the loadflow model.

If a transmission line does not have a mileage entry in the ownership file,

it will not participate in the calculation since the line mileage is not

known.

2.3.2 Transformers - The transformer ownership file is similar to the branch

ownership file, except that there is no mileage record associated with the

transformer. The records for transformers serve the same function as for

transmission lines. If ownership percentages for a given branch are not

provided, the ownership will be divided equally to the AREA numbers in

which the buses on either end of the branch reside in the loadflow model.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 214FERC Electric TariffFourth Revised Volume No. 1

2.3.3 Generation and Load - The ownership representation for generation and

load is maintained in generation and load ownership files. These files are

required by the Megawatt-Mile Software in order to model transactions.

For each bus that has either generation or load, a record in the ownership

file allocates to the AREAs their percent ownership. If no record is

entered for a load bus or generator bus, the ownership is allocated to the

AREA in which the bus resides in the loadflow model.

2.3.4 Representation of Utilities Outside of SPP - Utilities outside of SPP are to

be represented in the model as needed to result in accurate impact

calculations. Minimum representation for a non-Member involved in a

sale to a SPP Member is ownership of a generator bus in the non-

Member's system or a generator bus judged to be electrically close to the

non-Member's system. Similarly, minimum representation for a non-

Member involved in a purchase from a Member is ownership of a load bus

in the non-Member's system or a load bus judged to be electrically close to

the non-Member's system.

3. Calculating the Impact for Transmission Service

3.1 Explanation of the Impact Calculation - The megawatt-mile approach is a distance

based method of assessing transmission service impacts considering that power

will, to some extent, flow over all available paths from the generating source to

the load. The distribution of flows over each and every facility due to

transactions between each combination of potential parties is calculated. The

megawatt-mile method of calculating transmission service charges utilizes two

computer programs known as the Megawatt-Mile Software to accomplish the

necessary computations. A commercially available power systems analysis

package, PTI's PSS/E, performs the necessary network flow calculations through

activity MWMI, which was written specifically for this application. MWMI also

keeps track of cost information and branch, load, and generation ownership. A

second stand alone program is required to read the output of MWMI and to

develop allocation factors.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 215FERC Electric TariffFourth Revised Volume No. 1

3.2 The "Megawatt-Mile" Method

(a) The megawatt-mile technique starts from a solved loadflow model of the

system. Transactions are modeled between each combination of potential

parties by changing generation on the sending, or selling end, and

changing the load on the receiving, or buying end. The amount by which

the generation and load are changed is small. A linear analysis technique

is then used to determine the distribution of flows on each branch in the

network. This value is used in subsequent calculations.

(b) Individual branch charges are calculated given the flow on the branch due

to the transaction and the line mileage (for transmission lines) as described

in section 2.2 and 2.3. The individual branch impacts for transmission

lines are determined as follows:

Transmission Line Impacts = P * L [MW-miles]

where

P = calculated flow due to the transaction

L = line length in miles

(c) Similarly, the individual branch impacts for transformers are determined

as follows:

Transformer Impacts = P * mile [MW-miles]

where

P = calculated flow due to the transaction.

(d) The sum of all the individual branch impacts for each Transmission

Owner is calculated in units MW-miles. These charges can be

summarized, by Transmission Owner, for all combinations of power

transfers between Transmission Owner systems.

MW-mile Impacts = MW-miles [MW-miles]

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 216FERC Electric TariffFourth Revised Volume No. 1

3.4 Application to Service Charge Rates - Transmission service MW-mile impacts

using this MW-mile methodology shall be set forth in matrices developed by SPP

and posted on SPP OASIS. The matrices shall be changed twice per year. The

Summer season shall consist of the months of June through September inclusive.

The Winter season shall consist of the months of October through May inclusive.

3.5 Generator and Load Dispatch - All capacity transactions are simulated as coming

from all of a seller's on-line generation, except for that generation which is

already fully loaded, in proportion to unit MVA base (nameplate rating). The

transaction is simulated as delivered to all of the buyer's load.

Energy transactions are simulated as coming from all of the seller's on-line generation,

except for that generation which is already fully loaded, in proportion to the unit MVA base

(nameplate rating) and delivered to all of the buyer's load.

Each load on a bus at which the buyer represents load ownership picks up a proportionate

amount of the transaction. The portion of the transaction picked up at any given bus is the

amount of load owned by the buyer on that bus divided by the total load owned by the buyer.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 217FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT T

Rate Sheets For Point-To-Point Transmission Service

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 218FERC Electric TariffFourth Revised Volume No. 1

Public Service Company of Oklahoma andSouthwestern Electric Power Company,

Subsidiaries of American Electric Power, Inc.

Rate Sheet For Point-to-Point Transmission Service

Firm Point-to-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

1. Monthly delivery: $1050.00/MW of Reserved Capacity per month.

2. Weekly delivery: $ 241.64/MW of Reserved Capacity per week.

3. Daily delivery:

On-Peak: $ 48.33/MW of Reserved Capacity per day.

Off-Peak: $ 34.52/MW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in Section 2 above times the highest amount in megawatts of

Reserved Capacity in any day during such week. For the purpose of the rate specified in Section

3 above, the Off-Peak Period shall be Saturdays, Sundays, New Year’s Day, Memorial Day,

Independence Day, Labor Day, Thanksgiving Day, and Christmas Day and the On-Peak Period

shall be all days that are not in the Off-Peak Period.

Non-Firm Point-to-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

1. Monthly delivery: $1050.00/MW of Reserved Capacity per month.

2. Weekly delivery: $ 241.64/MW of Reserved Capacity per week.

3. Daily delivery:

On-Peak: $ 48.33/MW of Reserved Capacity per day.

Off-Peak $ 34.52/MW of Reserved Capacity per day.

4. Hourly delivery:

On-Peak: $ 3.02/MW of Reserved Capacity per hour.

Off-Peak $ 1.44/MW of Reserved Capacity per hour.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 219FERC Electric TariffFourth Revised Volume No. 1

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in Section 3 above times the highest amount in megawatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in Section 2 above times the highest amount in megawatts of Reserved Capacity in any hour

during such week.

For the purpose of the rate specified in Section 3 above, the Off-Peak Period shall be

Saturdays, Sundays, New Year’s Day, Memorial Day, Independence Day, Labor Day,

Thanksgiving Day, and Christmas Day and the On-Peak Period shall be all days that are not in

the Off-Peak Period.

For the purpose of the rate specified in Section 4 above, On-Peak is all hours between HE

0700 and HE 2200, inclusive, Central Time Zone, excluding Sundays and holidays. Holidays

shall be as defined by NERC, currently New Year’s Day, Memorial Day, Independence Day,

Labor Day, Thanksgiving Day, and Christmas Day. Off-Peak is all hours not designated as On-

Peak.

Discounts for Certain Through and Out Service Transactions Via the Public Service Company of Oklahoma and Southwestern Electric Power Company, Subsidiaries of American Electric Power, Inc. Pricing Zone:

For the purpose of this Section, the following definitions shall apply:

CPL: Central Power and Light Company.

AEP: American Electric Power, Inc. including its operating company affiliates located in the SPP region (Public Service Company of Oklahoma and Southwestern Electric Power Company.

AEP OperatingCompanies'Tariff: The open access transmission service tariff on file with the Commission

under which the AEP Operating Companies offer, among other services, ERCOT Regional Transmission Service.

ERCOT: The Electric Reliability Council of Texas.

ERCOT PowerSupplier: An electric utility that sells electricity for resale into ERCOT and takes

transmission service under Part IV of the AEP Operating Companies' Tariff for such sales.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 220FERC Electric TariffFourth Revised Volume No. 1

Load ServingEntity: Any electric utility operating in ERCOT that serves Native Load

Customers within ERCOT.

Native LoadCustomer: The wholesale and retail power customers of CPL and WTU on whose

behalf CPL and WTU, by statute, franchise, regulatory requirement, or contract, have undertaken an obligation to construct and operate the CPL and WTU systems to meet the reliable electric needs of such customers or the wholesale and retail power customers of a Load Serving Entity, by statute, franchise, regulatory requirement, or contract has undertaken an obligation to plan, construct and operate the Load Serving Entity's system to meet the reliable electric needs of such customers. Native Load Customers do not include load served outside of ERCOT.

PlannedResource: Any generation resource owned, controlled, or purchased by an ERCOT

Power Supplier or Load Serving Entity and designated as a Planned Resource for the purpose of serving load located in ERCOT.

UnplannedResource: Any generation resource owned or purchased by an ERCOT Power

Supplier or Load Serving Entity, used to serve loads within ERCOT and not designated as a Planned Resource.

WTU: West Texas Utilities Company.

Discount Provision:

A Load Serving Entity that takes ERCOT Regional Transmission Service under Part IV of the AEP Operating Companies' Tariff and also takes transmission service under Part II of this Tariff to import into ERCOT Planned Resources or Unplanned Resources to serve its Native Load Customers in ERCOT shall have its zonal rates under Schedules 7 and 8 reduced by 45.27% in instances when AEP is the applicable pricing zone under the SPP Tariff. This discount applies only to charges under Schedules 7 and 8 of the SPP Tariff.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 221FERC Electric TariffFourth Revised Volume No. 1

City Utilities of Springfield, Missouri

Rate Sheet for Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

1. Annual Deliveries: $13,128.24 per MW of reserved capacity.

2. Monthly delivery: $1,094.02/MW of Reserved Capacity per month.

3. Weekly delivery: $252.47/MW of Reserved Capacity per week.

4. Daily delivery: $50.49/MW of Reserved Capacity per day.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

1. Monthly delivery: $1,094.02/MW of Reserved Capacity per month.

2. Weekly delivery: $252.47/MW of Reserved Capacity per week.

3. Daily delivery: $50.49/MW of Reserved Capacity per day.

4. Hourly Deliveries: $2.70 per MW of Reserved Capacity per hour.

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the on-peak rate specified in section (3) above times the highest amount in kilowatts

of Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (2) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 222FERC Electric TariffFourth Revised Volume No. 1

Cleco Corporation

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

1. Yearly delivery: one-twelfth of the demand charge of $14.84/KW of Reserved Capacity

per year.

2. Monthly delivery: $1.24/KW of Reserved Capacity per month.

3. Weekly delivery: $.2854/KW of Reserved Capacity per week.

4. Daily delivery:

On-peak $.0571/KW of Reserved Capacity per day.

Off-peak $.0407/KW of Reserved Capacity per day.

For purposes of the above rate, on-peak days are defined as Monday through Friday, and

off peak days are defined as Saturday through Sunday. The total demand charge in any week,

pursuant to a reservation for Daily delivery, shall not exceed the rate specified in section (3)

above times the highest amount in kilowatts of Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

1. Monthly delivery: $1.24/KW of Reserved Capacity per month.

2. Weekly delivery: $.2854/KW of Reserved Capacity per week.

3. Daily delivery: On-peak $.0571/KW of Reserved Capacity per day.

Off-peak $.0407/KW of Reserved Capacity per day.

4. Hourly delivery: On-peak $ 3.57/MW of Reserved Capacity per hour.

Off-peak $1.69/MW of Reserved Capacity per hour.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 223FERC Electric TariffFourth Revised Volume No. 1

For purposes of this rate, on-peak periods are defined as hours beginning at 0700 and

continuing through 2200 on each Monday through Friday, and off peak periods are defined as all

other hours. The total demand charge in any day, pursuant to a reservation for Hourly delivery,

shall not exceed the on-peak rate specified in section (3) above times the highest amount in

kilowatts of Reserved Capacity in any hour during such day. In addition, the total demand charge

in any week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate

specified in section (2) above times the highest amount in kilowatts of Reserved Capacity in any

hour during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 224FERC Electric TariffFourth Revised Volume No. 1

Empire District Electric Co.

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

$ 15,382.514 /MW of Reserved Capacity per year.

$ 1,281.876 /MW of Reserved Capacity per month.

$ 295.817 /MW of Reserved Capacity per week.

$ 59.164 /MW of Reserved Capacity per day (on-peak).

$ 42.260 /MW of Reserved Capacity per day (off-peak).

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified for weekly delivery times the highest amount in megawatts of

Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

$ 15,382.514 /MW of Reserved Capacity per year

$ 1,281.876 /MW of Reserved Capacity per month

$ 295.817 /MW of Reserved Capacity per week

$ 59.164 /MW of Reserved Capacity per day (on-peak)

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 225FERC Electric TariffFourth Revised Volume No. 1

$ 42.260 /MW of Reserved Capacity per day (off-peak)

$ 3.698/MW of Reserved Capacity per hour (on-peak)

$ 1.756/MW of Reserved Capacity per hour (off-peak)

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified above for Daily delivery times the highest amount in Megawatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

for Weekly delivery times the highest amount in megawatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 226FERC Electric TariffFourth Revised Volume No. 1

Grand River Dam Authority

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

1. Yearly delivery: one-twelfth of the demand charge of $29.75/KW of Reserved Capacity

per year.

2. Monthly delivery: $2.48/kW of Reserved Capacity per month.

3. Weekly Delivery: $0.572/kW of Reserved Capacity per week.

4. Daily delivery: $0.114/kW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section 3 above times the highest amount in megawatts of

Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

he Transmission Customer shall compensate the Transmission Provider for Short Term

Non Firm Transmission Service as the sum of the applicable charges set forth below:

1. For Monthly delivery: $2.48/KW of Reserved Capacity per month.

2. For Weekly delivery: $0.572/KW of Reserved Capacity per week.

3. For Daily delivery: $0.082/KW of Reserved Capacity per day.

4. Hourly delivery: $0.00715/kW of Reserved Capacity per hour.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 227FERC Electric TariffFourth Revised Volume No. 1

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section 3 above times the highest amount in megawatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section 2 above times the highest amount in megawatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 228FERC Electric TariffFourth Revised Volume No. 1

Kansas City Power & Light

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

For 345 and 161 kV Service

1. Yearly delivery: one-twelfth of the demand charge of $10,560/MW of Reserved Capacity

per year.

2. Monthly delivery: $880/MW of Reserved Capacity per month.

3. Weekly delivery: $203/MW of Reserved Capacity per week.

4. Daily delivery: $41/MW of Reserved Capacity per day.

For 69 and 34 kV Service

1. Yearly delivery: one-twelfth of the demand charge of $12,120/MW of Reserved Capacity

per year.

2. Monthly delivery: $1,010/MW of Reserved Capacity per month.

3. Weekly delivery: $233/MW of Reserved Capacity per week.

4. Daily delivery: $47/MW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 229FERC Electric TariffFourth Revised Volume No. 1

For 345 and 161 kV Service

1. Monthly delivery: $830/MW of Reserved Capacity per month.

2. Weekly delivery: $191/MW of Reserved Capacity per week.

3. Daily delivery: $38/MW of Reserved Capacity per day.

4. Hourly delivery: $2.39/MW of Reserved Capacity per hour.

For 69/34 kV Service

1. Monthly delivery: $958/MW of Reserved Capacity per month.

2. Weekly delivery: $221/MW of Reserved Capacity per week.

3. Daily delivery: $44/MW of Reserved Capacity per day.

4. Hourly delivery: $2.76/MW of Reserved Capacity per hour.

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (2) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 230FERC Electric TariffFourth Revised Volume No. 1

Midwest Energy

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

1. Yearly delivery: one-twelfth of the demand charge of $24.5067/kW of Reserved Capacity

per year.

2. Monthly delivery: $2.0422/kW of Reserved Capacity per month.

3. Weekly delivery: $0.4713/kW of Reserved Capacity per week.

4. Daily delivery: $0.0943/kW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

he Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

1. Monthly delivery: $2.0422/kW of Reserved Capacity per month.

2. Weekly delivery: $0.4713/kW of Reserved Capacity per week.

3. Daily delivery: $0.0943/kW of Reserved Capacity per day.

4. Hourly delivery: $5.60/MW of Reserved Capacity per hour.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 231FERC Electric TariffFourth Revised Volume No. 1

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (2) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 232FERC Electric TariffFourth Revised Volume No. 1

Missouri Public Service

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

For 345/161 kV Service

1. Yearly delivery: one-twelfth of the demand charge of $10,704/MW of Reserved Capacity

per year.

2. Monthly delivery: $892/MW of Reserved Capacity per month.

3. Weekly delivery: $207.53/MW of Reserved Capacity per week.

4. Daily delivery: $41.51/MW of Reserved Capacity per day.

For 69/34 kV Service

1. Yearly delivery: one-twelfth of the demand charge of $26,844/MW of Reserved Capacity

per year.

2. Monthly delivery: $2,237/MW of Reserved Capacity per month.

3. Weekly delivery: $520.27/MW of Reserved Capacity per week.

4. Daily delivery: $104.05/MW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 233FERC Electric TariffFourth Revised Volume No. 1

For 345/161 kV Service

1. Monthly delivery: $892/MW of Reserved Capacity per month.

2. Weekly delivery: $207.53/MW of Reserved Capacity per week.

3. Daily delivery: $29.65/MW of Reserved Capacity per day.

4. Hourly delivery: $1.24/MW of Reserved Capacity per hour.

For 69/34 kV Service

1. Monthly delivery: $2,237/MW of Reserved Capacity per month.

2. Weekly delivery: $520.27/MW of Reserved Capacity per week.

3. Daily delivery: $74.32/MW of Reserved Capacity per day.

4. Hourly delivery: $3.10/MW of Reserved Capacity per hour.

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (2) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 234FERC Electric TariffFourth Revised Volume No. 1

OG&E Electric Services

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

1. Yearly delivery: one-twelfth of the demand charge of $13.3166/kW of Reserved

Capacity per year.

2. Monthly delivery: $1.1097/kW of Reserved Capacity per month.

3. Weekly delivery: $0.2561/kW Reserved Capacity per week.

4. Weekday delivery: $0.0512/kW of Reserved Capacity per day.

5. Weekend and Holiday delivery: $0.0366/kW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

1. Monthly delivery: $1.1097/kW of Reserved Capacity per month.

2. Weekly delivery: $0.2561/kW of Reserved Capacity per week.

3. Weekday delivery: $0.0512/kW of Reserved Capacity per day.

4. Weekend and Holiday delivery: $0.0366/kW of Reserved Capacity per day.

5. Hourly delivery: $1.5243/MW of Reserved Capacity per hour.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 235FERC Electric TariffFourth Revised Volume No. 1

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the Weekend and Holiday Delivery rate specified in section (3) above times the

highest amount in kilowatts of Reserved Capacity in any hour during such day. In addition, the

total demand charge in any week, pursuant to a reservation for Hourly or Daily delivery, shall

not exceed the rate specified in section (2) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 236FERC Electric Tariff Superseding Original Sheet No. 236Fourth Revised Volume No. 1

Southwestern Power Administration

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

Monthly: $0.73 per kilowatt of transmission capacity reserved in increments of one month

of service or invoiced in accordance with a longer term agreement.

Weekly: $0.183 per kilowatt of transmission capacity reserved in increments of one week

of service.

Daily: $0.0332 per kilowatt of transmission capacity reserved in increments of one day

of service.

Transmission Customers whose loads are directly connected to Southwestern's system

and are not within Southwestern's control area will be charged on the greatest of (1) the peak

demand at any particular point of delivery during a particular month, rounded up to the nearest

whole megawatt, or (2) the highest peak demand recorded at such point of delivery during any of

the previous 11 months, rounded up to the nearest whole megawatt, or (3) the capacity reserved

by contract, which amount shall be considered such transmission customer's reserved capacity.

Secondary Transmission Service for such Transmission Customers shall be limited during any

month to the most recent peak demand on which a particular Transmission Customer is billed or

to the capacity reserved by contract, whichever is greater.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 3, 2002 Effective: October 1, 2002

Southwest Power Pool First Revised Sheet No. 237FERC Electric Tariff Superseding Original Sheet No. 237Fourth Revised Volume No. 1

1. Monthly delivery: $ 0.584/KW of Reserved Capacity per month.

2. Weekly delivery: $ 0.146/KW of Reserved Capacity per week.

3. Daily delivery: $ .0265/KW of Reserved Capacity per day.

4. Hourly delivery: $ .00166/KW of Reserved Capacity per hour.

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (2) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 3, 2002 Effective: October 1, 2002

Southwest Power Pool Original Sheet No. 238FERC Electric TariffFourth Revised Volume No. 1

Southwestern Public Service Company

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Firm Point-To-Point Transmission Service up to the sum of the applicable charges set forth

below:

1. Monthly delivery: $1.380/kW of Reserved Capacity per month.

2. Weekly delivery: $0.318/kW of Reserved Capacity per week.

3. Daily delivery:

On-Peak: $0.053/kW of Reserved Capacity per day.

Off-Peak: $0.045/kW of Reserved Capacity per day.

4. Hourly delivery:

On-Peak: $3.32/MW of Reserved Capacity per hour.

Off-Peak: $1.89/MW of Reserved Capacity per hour.

Service in the opposite direction of the original schedule shall be considered a new and

separate service under this Tariff requiring payment of a separate charge.

On-Peak is all hours between HE 0700 and HE 2200, inclusive, Central Time Zone,

excluding Sundays and holidays. Holidays shall be as defined by NERC, currently New Year’s

Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day.

Off-Peak is all hours not designated as On-Peak.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section (2) above times the highest amount in kilowatts of

Reserved Capacity in any day during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 239FERC Electric TariffFourth Revised Volume No. 1

On-Peak Non-Firm Service: The Transmission Customer shall compensate the Transmission

Provider each month for Non-Firm Point-To-Point Transmission Service up to the sum of the

applicable charges set forth below. Service in the opposite direction of the original schedule

shall be considered a new and separate service under this Tariff requiring payment of a separate

charge.

1. Monthly delivery: $1.380/kW of Reserved Capacity per month.

2. Weekly delivery: $0.318/kW of Reserved Capacity per week.

3. Daily delivery:

On-Peak: $0.053/kW of Reserved Capacity per day.

Off-Peak: $0.045/kW of Reserved Capacity per day.

4. Hourly delivery:

On-Peak: $3.32/MW of Reserved Capacity per hour.

Off-Peak: $1.89/MW of Reserved Capacity per hour.

On-Peak is all hours between HE 0700 and HE 2200, inclusive, Central Time Zone,

excluding Sundays and holidays. Holidays shall be as defined by NERC, currently New Year’s

Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 240FERC Electric TariffFourth Revised Volume No. 1

Off-Peak is all hours not designated as On-Peak.

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section (6) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (5) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Capacity designations at the Point(s) of receipt will be inclusive of losses.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 241FERC Electric TariffFourth Revised Volume No. 1

Sunflower Electric Cooperative

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at up to the sum of the applicable charges set forth below:

1. Yearly delivery: $53,800/MW of Reserved Capacity per year.

2. Monthly delivery: $4,480/MW of Reserved Capacity per month.

3. Weekly delivery: $1,034.60/MW of Reserved Capacity per week.

4. Daily delivery: $147.80/MW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

1. Yearly delivery: $53,800/MW of Reserved Capacity per year.

2. Monthly delivery: $4,480/MW of Reserved Capacity per month.

3. Weekly delivery: $1,034.60/MW of Reserved Capacity per week.

4. Daily delivery: $147.80/MW of Reserved Capacity per day.

5. Hourly delivery: $6.14/MW of Reserved Capacity per hour.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 242FERC Electric TariffFourth Revised Volume No. 1

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section (4) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (3) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 243FERC Electric TariffFourth Revised Volume No. 1

UtiliCorp United - West Plains

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

For 115 kV and Above Service

1. Yearly delivery: one-twelfth of the demand charge of $16,176/MW of Reserved Capacity

per year.

2. Monthly delivery: $1,348/MW of Reserved Capacity per month.

3. Weekly delivery: $313.38/MW of Reserved Capacity per week.

4. Daily delivery: $62.68/MW of Reserved Capacity per day.

For 34.5 kV Service

1. Yearly delivery: one-twelfth of the demand charge of $32,328/MW of Reserved Capacity

per year.

2. Monthly delivery: $2,694/MW of Reserved Capacity per month.

3. Weekly delivery: $626.47/MW of Reserved Capacity per week.

4. Daily delivery: $125.29/MW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 244FERC Electric TariffFourth Revised Volume No. 1

For 115 kV and Above Service

1. Monthly delivery: $1,348/MW of Reserved Capacity per month.

2. Weekly delivery: $313.38/MW of Reserved Capacity per week.

3. Daily delivery: $44.77/MW of Reserved Capacity per day.

4. Hourly delivery: $1.87/MW of Reserved Capacity per hour.

For 34.5 kV Service

1. Monthly delivery: $2,694/MW of Reserved Capacity per month.

2. Weekly delivery: $626.47/MW of Reserved Capacity per week.

3. Daily delivery: $89.50/MW of Reserved Capacity per day.

4. Hourly delivery: $3.73/MW of Reserved Capacity per hour.

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (2) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 245FERC Electric TariffFourth Revised Volume No. 1

Western Resources

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

1. Yearly delivery: one-twelfth of the demand charge of $15.60/KW of Reserved Capacity

per year.

2. Monthly delivery: $1.30/KW of Reserved Capacity per month.

3. Weekly delivery: $0.30/KW of Reserved Capacity per week.

4. Daily delivery: $0.0427/KW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any day during such week.

Non-Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

1. Monthly delivery: $1.30/KW of Reserved Capacity per month.

2. Weekly delivery: $0.30/KW of Reserved Capacity per week.

3. Daily delivery: $0.0427/KW of Reserved Capacity per day.

4. Hourly delivery: $1.80/MWH of Reserved Capacity per hour.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 246FERC Electric TariffFourth Revised Volume No. 1

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (2) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 247FERC Electric TariffFourth Revised Volume No. 1

Western Farmers Electric

Rate Sheet For Point-To-Point Transmission Service

Firm Point-To-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider each month for

Reserved Capacity at the sum of the applicable charges set forth below:

1. Yearly delivery: one-twelfth of the demand charge of $24.72/kW of Reserved Capacity

per year.

2. Monthly delivery: $2.06/kW of Reserved Capacity per month.

3. Weekly delivery: $0.47538/kW of Reserved Capacity per week.

4. Daily delivery: $0.0671/kW of Reserved Capacity per day.

The total demand charge in any week, pursuant to a reservation for Daily delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any day during such week.

Non-Firm Point-to-Point Transmission Service

The Transmission Customer shall compensate the Transmission Provider for Non-Firm

Point-To-Point Transmission Service up to the sum of the applicable charges set forth below:

1. Monthly delivery: $2.060/kW of Reserved Capacity per month.

2. Weekly delivery: $0.47538/kW of Reserved Capacity per week.

3. Daily delivery: $0.06791/kW of Reserved Capacity per day.

4. Hourly delivery: $2.83/MW of Reserved Capacity per hour.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 248FERC Electric TariffFourth Revised Volume No. 1

The total demand charge in any day, pursuant to a reservation for Hourly delivery, shall

not exceed the rate specified in section (3) above times the highest amount in kilowatts of

Reserved Capacity in any hour during such day. In addition, the total demand charge in any

week, pursuant to a reservation for Hourly or Daily delivery, shall not exceed the rate specified

in section (2) above times the highest amount in kilowatts of Reserved Capacity in any hour

during such week.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 249FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT U

RATE SCHEDULE FOR COMPENSATION FOR RESCHEDULED MAINTENANCE

COSTS

This rate schedule is intended to provide for the payment by the Transmission Provider of

compensation to generation owners and Transmission Owners for the costs of rescheduling

previously scheduled generation or transmission maintenance, when such maintenance is

rescheduled pursuant to the Transmission Provider’s directive or pursuant to agreement of the

owner and Transmission Provider (in response to the Transmission Provider’s request), and for

the recovery by the Transmission Provider of the costs of such payments.

A. Compensation to Generation and Transmission Owners:

Generation owners within the SPP Region shall coordinate the maintenance of generating

units with the Transmission Provider to the extent such maintenance directly affects the capacity

or reliability of the Transmission System. The Transmission Provider shall review the

generating unit maintenance schedules submitted by generators. Any generation owner that

reschedules planned maintenance as a result of the Transmission Provider’s review or

coordination shall be fully compensated by the Transmission Provider for all additional costs

associated with any such rescheduling. Generation owners shall use best efforts to minimize

costs resulting from rescheduled maintenance.

Consistent with the SPP Membership Agreement, Transmission Owners are required to

coordinate with the Transmission Provider for all planned maintenance of Tariff Facilities. The

Transmission Provider shall notify a Transmission Owner of the need to change previously-

reviewed planned maintenance outages.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 250FERC Electric TariffFourth Revised Volume No. 1

If the planned maintenance is rescheduled, the Transmission Provider shall fully

compensate the Transmission Owner for any additional costs associated with any such

rescheduling of planned maintenance outages. Transmission Owners shall use best efforts to

minimize costs resulting from rescheduled maintenance.

The following are the costs associated with the rescheduling to be recovered by the

generation owner and the Transmission Owner:

(1) Additional labor costs: The labor costs to be recovered from the Transmission

Provider shall be the actual out-of-pocket additional labor costs faced by the

generation owner or Transmission Owner that were incurred only because of the

rescheduling of the maintenance. Unless overhead costs can be directly identified

as pertaining to this additional labor, any overhead cost adder shall be limited to

the typical overhead cost adder (a percentage adder) used by the generation owner

or Transmission Owner for similar work.

(2) Additional materials costs: The materials cost to be recovered from the

Transmission Provider shall be the actual out-of-pocket additional materials costs

that were incurred only because of the rescheduling of the maintenance.

(3) Opportunity costs: If the rescheduled maintenance results in the generation owner

or Transmission Owner foregoing generation sales revenues in excess of sales

revenues that would have been foregone if the maintenance had taken place as

originally scheduled, the affected generation owner or Transmission Owner shall

be allowed to recover that difference. No opportunity costs recovered under

Attachment K of the Tariff may be recovered under this provision.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 251FERC Electric TariffFourth Revised Volume No. 1

The following formula shall be used in deriving this difference:

C = A-B where:

C = The total opportunity cost to be recovered

A = A1 + A2 + A3. . .

where:

A1 = RA(1) x (SPA(1) - MSA(1))

A2 = RA(2) x (SPA(2) - MSA(2))

A3 = RA(3) x (SPA(3) - MSA(3)), . . .

The time period for this calculation is the time over which the rescheduled

maintenance actually occurs.

B = B1 + B2 + B3 . . .

where:

B1 = RB(1) x (SPB(1) – MSB(1))

B2 = RB(2) x (SPB(2) – MSB(2))

B3 = RB(3) x (SPB(3) – MSB(3)), . . .

The time period for this calculation is the time over which the maintenance was to

have taken place before it was rescheduled.

The generating unit sales and costs reflected in this calculation shall be the units

or portions of units from which sales are lost.

where:

RA(n) = sales in kWh estimated to have been lost for each transaction (n) as a

result of the rescheduled maintenance.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 252FERC Electric TariffFourth Revised Volume No. 1

SPA(n) = charge per kWh for each transaction (n) that the generation or

Transmission owner would have charged for the generation sales lost as a

result of the maintenance being rescheduled; and

MSA(n) = marginal running cost per kWh associated with each transaction (n) lost as

a result of maintenance being rescheduled, defined as the out-of-pocket

costs associated with generating the power for the lost sale, such costs to

include the cost of fuel and variable operation and maintenance expenses

of generating the next increment of power;

and where:

RB(n) = the actual sales in kWh for each transaction (n) during the period of the originally

scheduled, but changed, maintenance;

SPB(n) = charge per kWh for each transaction (n) reflected in B; and

MSB(n) = marginal running cost per kWh associated with each transaction (n) reflected in B,

defined as the out-of-pocket costs associated with generating the power for the

actual sale, such costs to include the cost of fuel and variable operation and

maintenance expenses of generating the next increment of power.

If a negative number is produced from this formula, that amount shall be used to offset any

additional labor and material costs until the compensation due is zero.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 253FERC Electric TariffFourth Revised Volume No. 1

(4)(a) All costs for which compensation is sought or provided under this section are to

be fully documented by the generation owner or Transmission Owner. The

generation owner or Transmission Owner shall provide the Transmission Provider

with information that the Transmission Provider believes is necessary to verify

the additional costs of rescheduling planned maintenance. The Transmission

Provider is to recover the costs of all payments made pursuant to this section as

set forth in section B below.

(b) The process to be followed is as follows:

i. The Transmission Provider will notify the generation owner or

Transmission Owner of its desire to have maintenance rescheduled.

ii. The generation owner or Transmission Owner shall provide the

Transmission Provider with a non-binding estimate of its costs recoverable

under this Attachment U using a template developed by the Transmission

Provider to provide and support the estimate.

iii. If the Transmission Provider and the owner agree (in response to the

Transmission Provider’s request) or if the Transmission Provider is

authorized to direct the rescheduled maintenance and the Transmission

Provider requires rescheduling, then the maintenance will be rescheduled.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 254FERC Electric TariffFourth Revised Volume No. 1

iv. For rescheduled maintenance, the Transmission Provider shall receive

bills reflecting actuals as soon as possible but no later than three months

after the end of the maintenance, unless good cause exists for delay.

These bills together with support shall be submitted using a template

developed by the Transmission Provider.

v. The Transmission Provider shall reflect these charges in monthly bills to

customers no later than two months after receiving bills or requests for

payment of the charges calculated pursuant to this Attachment U.

vi. The generation owner or Transmission Owner agree to allow the

Transmission Provider and Transmission Customers to audit their basis for

the charges under this Attachment U for a period of six months after the

final bill is sent to the Transmission Provider subject to the execution of

any appropriate confidentiality agreements.

vii. The Transmission Provider shall pay the generation owner or

Transmission Owner as soon as practicable after the Transmission

Provider is paid but, in any event, no later than 60 days of receiving an

invoice from a generation owner or transmission owner.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 255FERC Electric TariffFourth Revised Volume No. 1

B. Recovery of Compensation Costs by the Transmission Provider

The Transmission Provider shall be entitled to recover all costs associated with the

compensation of generation owners, or Transmission Owners pursuant to this Rate Schedule on a

monthly basis. In order to recover these costs, the Transmission Provider shall add an additional

monthly charge to the base transmission charges under this Tariff calculated using the following

formula:

X=Y/Z

Where:

X=Monthly maintenance reschedule charge adder(per kw/month)

Y=Rescheduled Maintenance Costs calculated in accordance with Section A above and

any true-up with interest on the true-up amount.

Z=Transmission System Peak for the same month minus coincident peak usage of all

Firm Point-to-Point Transmission Service plus reserved capacity of all Firm Point-to-

Point Transmission Service customers.

The Transmission Provider shall apply this charge to all customers under the Tariff in

addition to the base transmission charge. The charge developed above is the rate for monthly

service. The rate for weekly service will be the product of the monthly rate and 12 divided by

52. The rate for (on-peak)daily service will be the product of the monthly rate and 12 divided by

260. The rate for (on-peak) hourly service will be the product of the monthly rate and 12 divided

by 4160. The rate for off-peak daily service will be the product of the monthly rate and 12

divided by 365. The rate for off-peak hourly service will be the product of the monthly rate and

12 divided by 8760. The on-peak period shall be 6:00 a.m. - 10:00 p.m.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 256FERC Electric TariffFourth Revised Volume No. 1

Monday through Friday. The total charge paid by a customer under this Attachment U

pursuant to a reservation for hourly delivery shall not exceed the above on-peak daily rate times

the highest amount of reserved capacity in any hour during such day. In addition, the total

charge under this Attachment U in any week, pursuant to a reservation for hourly or daily

delivery, shall not exceed the above rate specified for weekly delivery times the highest amount

of reserved capacity in any hour during such week.

Each Transmission Customer taking Point-to-Point Transmission Service shall pay the

product of the applicable charge developed above multiplied by its applicable Point-to-Point

Transmission Service reservations. Each Network Customer shall pay the product of the

applicable charge developed above multiplied by the Network Customer’s load at the time of the

monthly peak. For purposes of this Attachment U, network load includes bundled load and load

under Grandfathered Agreements served by Transmission Owners for which the Transmission

Owners are not otherwise paying the Transmission Provider for Network Integration

Transmission Service. The Transmission Provider shall recover the costs arising under this

Attachment U that are not recovered from Point-to-Point Transmission Service customers or

from Network Customers paying the Transmission Provider for Network Integration

Transmission Service by charging the Transmission Owners serving such bundled and

grandfathered loads for such costs. The Transmission Owners shall be allocated these remaining

amounts based upon their relative proportions of these loads.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool Original Sheet No. 257FERC Electric TariffFourth Revised Volume No. 1

In deriving the charges, the Transmission Provider may estimate and bill the

compensatory costs it owes or will owe. The Transmission Provider shall true-up that estimate

in a later month, as provided below, with interest, calculated in accordance with Section 35.19

(a) of the Commission’s regulations once actuals are available (such interest will be credited to

the customer for over-estimates or to the generation owner or Transmission Owner that has

rescheduled maintenance for underestimates).

The Transmission Provider shall true-up on a monthly basis within two months after

receiving actuals for any part of rescheduled maintenance. Such true-ups will involve changes

based upon a further evaluation of estimates used for opportunity costs or revisions of bills

previously received by the Transmission Provider. The Transmission Provider shall make

available upon request the data and information supporting any rescheduled maintenance costs

for a period of one year after the amounts are billed. If a Transmission Customer disagrees with

the amounts charged, it may pursue the matter through dispute resolution procedures or by

complaint.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: October 27, 2000 Effective: November 1, 2000

Southwest Power Pool First Revised Sheet No. 258FERC Electric Tariff Superseding Original Sheet No. 258Fourth Revised Volume No. 1

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 258FERC Electric Tariff Superseding Original Sheet No. 258Fourth Revised Volume No. 1

ATTACHMENT V

STANDARD LARGE GENERATOR

INTERCONNECTION PROCEDURES (LGIP)

including

STANDARD LARGE GENERATOR

INTERCONNECTION AGREEMENT (LGIA)

and

AGREEMENT FOR THE

ALLOCATION OF RESPONSIBILITIES

WITH REGARD TO

LARGE GENERATOR INTERCONNECTION PROCEDURES

AND INTERCONNECTION AGREEMENT

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 259FERC Electric Tariff Superseding Original Sheet No. 259Fourth Revised Volume No. 1

Standard Large Generator

Interconnection Procedures (LGIP)

(Applicable to Generating Facilities that exceed 20 MW)

TABLE OF CONTENTSPage No.

Section 1. Definitions............................................................................................................260

Section 2. Scope and Application.........................................................................................268

2.1 Application of Standard Large Generator Interconnection

Procedures............................................................................................................268

2.2 Comparability......................................................................................................268

2.3 Base Case Data....................................................................................................268

2.4 No Applicability to Transmission Service...........................................................269

Section 3. Interconnection Requests.....................................................................................269

3.1 General.................................................................................................................269

3.2 Identification of Types of Interconnection Services............................................269

3.2.1 Energy Resource Interconnection Service...............................................270

3.2.1.1 The Product..............................................................................270

3.2.1.2 The Study.................................................................................270

3.2.2 Network Resource Interconnection Service.............................................270

3.2.2.1 The Product..............................................................................270

3.2.2.2 The Study.................................................................................271

3.3 Valid Interconnection Request.............................................................................271

3.3.1 Initiating an Interconnection Request......................................................271

3.3.2 Acknowledgment of Interconnection Request.........................................272

3.3.3 Deficiencies in Interconnection Request.................................................272

3.3.4 Scoping Meeting......................................................................................272

3.4 OASIS Posting.....................................................................................................273

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 259AFERC Electric Tariff Superseding Original Sheet No. 259AFourth Revised Volume No. 1

3.5 Coordination with Affected Systems...................................................................273

3.6 Withdrawal...........................................................................................................274

Section 4. Queue Position.....................................................................................................274

4.1 General.................................................................................................................274

4.2 Clustering.............................................................................................................275

4.3 Transferability of Queue Position........................................................................276

4.4 Modifications.......................................................................................................276

Section 5. Procedures for Interconnection Requests Submitted Prior to

Effective Date of Standard Large Generator Interconnection

Procedures............................................................................................................277

5.1 Queue Position for Pending Requests..................................................................277

5.2 New Transmission Provider.................................................................................278

Section 6. Interconnection Feasibility Study........................................................................279

6.1 Interconnection Feasibility Study Agreement.....................................................279

6.2 Scope of Interconnection Feasibility Study.........................................................280

6.3 Interconnection Feasibility Study Procedures.....................................................280

6.4 Re-Study..............................................................................................................281

Section 7. Interconnection System Impact Study.................................................................281

7.1 Interconnection System Impact Study Agreement..............................................281

7.2 Execution of Interconnection System Impact Study Agreement.........................281

7.3 Scope of Interconnection System Impact Study..................................................282

7.4 Interconnection System Impact Study Procedures..............................................283

7.5 Meeting with Transmission Provider...................................................................283

7.6 Re-Study..............................................................................................................283

Section 8. Interconnection Facilities Study..........................................................................284

8.1 Interconnection Facilities Study Agreement........................................................284

8.2 Scope of Interconnection Facilities Study...........................................................284

8.3 Interconnection Facilities Study Procedures........................................................285

8.4 Meeting with Transmission Provider...................................................................285

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 259BFERC Electric Tariff Superseding Original Sheet No. 259BFourth Revised Volume No. 1

8.5 Re-Study..............................................................................................................286

Section 9. Engineering & Procurement (‘E&P’) Agreement................................................286

Section 10. Optional Interconnection Study...........................................................................287

10.1 Optional Interconnection Study Agreement........................................................287

10.2 Scope of Optional Interconnection Study............................................................287

10.3 Optional Interconnection Study Procedures........................................................288

Section 11. Standard Large Generator Interconnection Agreement (LGIA)..........................288

11.1 Tender..................................................................................................................288

11.2 Negotiation...........................................................................................................288

11.3 Execution and Filing............................................................................................289

11.4 Commencement of Interconnection Activities....................................................290

Section 12. Construction of Transmission Provider’s Interconnection

Facilities and Network Upgrades.........................................................................290

12.1 Schedule...............................................................................................................290

12.2 Construction Sequencing.....................................................................................290

12.2.1 General..................................................................................................290

12.2.2 Advance Construction of Network Upgrades that are an

Obligation of an Entity other than Interconnection

Customers.............................................................................................290

12.2.3 Advancing Construction of Network Upgrades that are Part

of an Expansion Plan of the Transmission Provider.............................291

12.2.4 Amended Interconnection System Impact Study..................................291

Section 13. Miscellaneous......................................................................................................292

13.1 Confidentiality.....................................................................................................292

13.1.1 Scope.....................................................................................................292

13.1.2 Release of Confidential Information.....................................................293

13.1.3 Rights....................................................................................................293

13.1.4 No Warranties.......................................................................................293

13.1.5 Standard of Care...................................................................................293

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 259CFERC Electric Tariff Superseding Original Sheet No. 259CFourth Revised Volume No. 1

13.1.6 Order of Disclosure...............................................................................294

13.1.7 Remedies...............................................................................................294

13.1.8 Disclosure to FERC, its Staff or a State................................................294

13.2 Delegation of Responsibility................................................................................296

13.3 Obligation for Study Costs...................................................................................296

13.4 Third Parties Conducting Studies........................................................................296

13.5 Disputes................................................................................................................297

13.5.1 Submission............................................................................................297

13.5.2 External Arbitration Procedures...........................................................298

13.5.3 Arbitration Decisions............................................................................298

13.5.4 Costs......................................................................................................299

13.6 Local Furnishing Bonds.......................................................................................299

13.6.1 Transmission Providers that Own Facilities Financed by

Local Furnishing Bonds........................................................................299

13.6.2 Alternative Procedures for Requesting Interconnection

Service...................................................................................................299

Appendix 1 – Interconnection Request for a Large Generating Facility

Appendix 2 – Interconnection Feasibility Study Agreement

Appendix 3 – Interconnection System Impact Study Agreement

Appendix 4 – Interconnection Facilities Study Agreement

Appendix 5 – Optional Interconnection Study Agreement

Appendix 6 – Standard Large Generator Interconnection Agreement

Appendix 7 – Agreement for the Allocation of Responsibilities with Regard to Large Generator Interconnection Procedures and Interconnection Agreement

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 260FERC Electric Tariff Superseding Original No. 260Fourth Revised Volume No. 1

Section 1. Definitions

Adverse System Impact shall mean the negative effects due to technical or operational limits on conductors or equipment being exceeded that may compromise the safety and reliability of the electric system.

Affected System shall mean an electric system other than the Transmission Provider's Transmission System that may be affected by the proposed interconnection.

Affected System Operator shall mean the entity that operates an Affected System.

Affiliate shall mean, with respect to a corporation, partnership or other entity, each such other corporation, partnership or other entity that directly or indirectly, through one or more intermediaries, controls, is controlled by, or is under common control with, such corporation, partnership or other entity.

Ancillary Services shall mean those services that are necessary to support the transmission of capacity and energy from resources to loads while maintaining reliable operation of the Transmission Provider's Transmission System in accordance with Good Utility Practice.

Applicable Laws and Regulations shall mean all duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any Governmental Authority.

Applicable Reliability Council shall mean the reliability council applicable to the Transmission System to which the Generating Facility is directly interconnected.

Applicable Reliability Standards shall mean the requirements and guidelines of NERC, the Applicable Reliability Council, and the Control Area of the Transmission System to which the Generating Facility is directly interconnected.

Base Case shall mean the base case power flow, short circuit, and stability data bases used for the Interconnection Studies by the Transmission Provider or Interconnection Customer.

Breach shall mean the failure of a Party to perform or observe any material term or condition of the Standard Large Generator Interconnection Agreement.

Breaching Party shall mean a Party that is in Breach of the Standard Large Generator Interconnection Agreement.

Business Day shall mean Monday through Friday, excluding Federal Holidays.

Calendar Day shall mean any day including Saturday, Sunday or a Federal Holiday.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 261FERC Electric Tariff Superseding Original Sheet No. 261Fourth Revised Volume No. 1

Clustering shall mean the process whereby a group of Interconnection Requests is studied together, instead of serially, for the purpose of conducting the Interconnection System Impact Study.

Commercial Operation shall mean the status of a Generating Facility that has commenced generating electricity for sale, excluding electricity generated during Trial Operation.

Commercial Operation Date of a unit shall mean the date on which the Generating Facility commences Commercial Operation as agreed to by the Parties pursuant to Appendix E to the Standard Large Generator Interconnection Agreement.

Confidential Information shall mean any confidential, proprietary or trade secret information of a plan, specification, pattern, procedure, design, device, list, concept, policy or compilation relating to the present or planned business of a Party, which is designated as confidential by the Party supplying the information, whether conveyed orally, electronically, in writing, through inspection, or otherwise.

Control Area shall mean an electrical system or systems bounded by interconnection metering and telemetry, capable of controlling generation to maintain its interchange schedule with other Control Areas and contributing to frequency regulation of the interconnection. A Control Area must be certified by an Applicable Reliability Council.

Default shall mean the failure of a Breaching Party to cure its Breach in accordance with Article 17 of the Standard Large Generator Interconnection Agreement.

Dispute Resolution shall mean the procedure for resolution of a dispute between the Parties in which they will first attempt to resolve the dispute on an informal basis.

Distribution System shall mean the Transmission Provider's facilities and equipment used to transmit electricity to ultimate usage points such as homes and industries directly from nearby generators or from interchanges with higher voltage transmission networks which transport bulk power over longer distances. The voltage levels at which distribution systems operate differ among areas.

Distribution Upgrades shall mean the additions, modifications, and upgrades to the Transmission Provider's Distribution System at or beyond the Point of Interconnection to facilitate interconnection of the Generating Facility and render the transmission service necessary to effect Interconnection Customer's wholesale sale of electricity in interstate commerce. Distribution Upgrades do not include Interconnection Facilities.

Effective Date shall mean the date on which the Standard Large Generator Interconnection Agreement becomes effective upon execution by the Parties subject to acceptance by FERC, or if filed unexecuted, upon the date specified by FERC.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 262FERC Electric Tariff Superseding Original Sheet No. 262Fourth Revised Volume No. 1

Emergency Condition shall mean a condition or situation: (1) that in the judgment of the Party making the claim is imminently likely to endanger life or property; or (2) that, in the case of a Transmission Provider, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to Transmission Provider's Transmission System, Transmission Provider's Interconnection Facilities or the electric systems of others to which the Transmission Provider's Transmission System is directly connected; or (3) that, in the case of Interconnection Customer, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to, the Generating Facility or Interconnection Customer's Interconnection Facilities. System restoration and black start shall be considered Emergency Conditions; provided that Interconnection Customer is not obligated by the Standard Large Generator Interconnection Agreement to possess black start capability.

Energy Resource Interconnection Service shall mean an Interconnection Service that allows the Interconnection Customer to connect its Generating Facility to the Transmission Provider's Transmission System to be eligible to deliver the Generating Facility's electric output using the existing firm or nonfirm capacity of the Transmission Provider's Transmission System on an as available basis. Energy Resource Interconnection Service in and of itself does not convey transmission service.

Engineering & Procurement (E&P) Agreement shall mean an agreement that authorizes the Transmission Provider to begin engineering and procurement of long lead-time items necessary for the establishment of the interconnection in order to advance the implementation of the Interconnection Request.

Environmental Law shall mean Applicable Laws or Regulations relating to pollution or protection of the environment or natural resources.

Federal Power Act shall mean the Federal Power Act, as amended, 16 U.S.C. §§ 791a et seq.

FERC shall mean the Federal Energy Regulatory Commission (Commission) or its successor.

Force Majeure shall mean any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, any order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities, or any other cause beyond a Party's control. A Force Majeure event does not include acts of negligence or intentional wrongdoing by the Party claiming Force Majeure.

Generating Facility shall mean Interconnection Customer's device for the production of electricity identified in the Interconnection Request, but shall not include the Interconnection Customer's Interconnection Facilities.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 263FERC Electric Tariff Superseding Original Sheet No. 263Fourth Revised Volume No. 1

Generating Facility Capacity shall mean the net capacity of the Generating Facility and the aggregate net capacity of the Generating Facility where it includes multiple energy production devices.

Good Utility Practice shall mean any of the practices, methods and acts engaged in or approved by a significant portion of the electric industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good Utility Practice is not intended to be limited to the optimum practice, method, or act to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region.

Governmental Authority shall mean any federal, state, local or other governmental regulatory or administrative agency, court, commission, department, board, or other governmental subdivision, legislature, rulemaking board, tribunal, or other governmental authority having jurisdiction over the Parties, their respective facilities, or the respective services they provide, and exercising or entitled to exercise any administrative, executive, police, or taxing authority or power; provided, however, that such term does not include Interconnection Customer, Transmission Provider, or any Affiliate thereof.

Hazardous Substances shall mean any chemicals, materials or substances defined as or included in the definition of "hazardous substances," "hazardous wastes," "hazardous materials," "hazardous constituents," "restricted hazardous materials," "extremely hazardous substances," "toxic substances," "radioactive substances," "contaminants," "pollutants," "toxic pollutants" or words of similar meaning and regulatory effect under any applicable Environmental Law, or any other chemical, material or substance, exposure to which is prohibited, limited or regulated by any applicable Environmental Law.

Initial Synchronization Date shall mean the date upon which the Generating Facility is initially synchronized and upon which Trial Operation begins.

In-Service Date shall mean the date upon which the Interconnection Customer reasonably expects it will be ready to begin use of the Transmission Provider's Interconnection Facilities to obtain back feed power.

Interconnection Customer shall mean any entity, including the Transmission Provider, Transmission Owner or any of the Affiliates or subsidiaries of either, that proposes to interconnect its Generating Facility with the Transmission Provider's Transmission System.

Interconnection Customer's Interconnection Facilities shall mean all facilities and equipment, as identified in Appendix A of the Standard Large Generator Interconnection Agreement, that are located between the Generating Facility and the Point of Change of Ownership, including any modification, addition, or upgrades to such facilities and equipment necessary to physically and electrically interconnect the Generating Facility to the Transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 264FERC Electric Tariff Superseding Original Sheet No. 264Fourth Revised Volume No. 1

Provider's Transmission System. Interconnection Customer's Interconnection Facilities are sole use facilities.

Interconnection Facilities shall mean the Transmission Provider's Interconnection Facilities and the Interconnection Customer's Interconnection Facilities. Collectively, Interconnection Facilities include all facilities and equipment between the Generating Facility and the Point of Interconnection, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the Generating Facility to the Transmission Provider's Transmission System. Interconnection Facilities are sole use facilities and shall not include Distribution Upgrades, Stand Alone Network Upgrades or Network Upgrades.

Interconnection Facilities Study shall mean a study conducted by the Transmission Provider or a third party consultant for the Interconnection Customer to determine a list of facilities (including Transmission Provider's Interconnection Facilities and Network Upgrades as identified in the Interconnection System Impact Study), the cost of those facilities, and the time required to interconnect the Generating Facility with the Transmission Provider's Transmission System. The scope of the study is defined in Section 8 of the Standard Large Generator Interconnection Procedures.

Interconnection Facilities Study Agreement shall mean the form of agreement contained in Appendix 4 of the Standard Large Generator Interconnection Procedures for conducting the Interconnection Facilities Study.

Interconnection Feasibility Study shall mean a preliminary evaluation of the system impact and cost of interconnecting the Generating Facility to the Transmission Provider's Transmission System, the scope of which is described in Section 6 of the Standard Large Generator Interconnection Procedures.

Interconnection Feasibility Study Agreement shall mean the form of agreement contained in Appendix 2 of the Standard Large Generator Interconnection Procedures for conducting the Interconnection Feasibility Study.

Interconnection Request shall mean an Interconnection Customer's request, in the form of Appendix 1 to the Standard Large Generator Interconnection Procedures, in accordance with the Tariff, to interconnect a new Generating Facility, or to increase the capacity of, or make a Material Modification to the operating characteristics of, an existing Generating Facility that is interconnected with the Transmission Provider's Transmission System.

Interconnection Service shall mean the service provided by the Transmission Provider associated with interconnecting the Interconnection Customer's Generating Facility to the Transmission Provider's Transmission System and enabling it to receive electric energy and capacity from the Generating Facility at the Point of Interconnection, pursuant to the terms of the Standard Large Generator Interconnection Agreement and, if applicable, the Transmission Provider's Tariff.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 265FERC Electric Tariff Superseding Original Sheet No. 265Fourth Revised Volume No. 1

Interconnection Study shall mean any of the following studies: the Interconnection Feasibility Study, the Interconnection System Impact Study, and the Interconnection Facilities Study described in the Standard Large Generator Interconnection Procedures.

Interconnection System Impact Study shall mean an engineering study that evaluates the impact of the proposed interconnection on the safety and reliability of Transmission Provider's Transmission System and, if applicable, an Affected System. The study shall identify and detail the system impacts that would result if the Generating Facility were interconnected without project modifications or system modifications, focusing on the Adverse System Impacts identified in the Interconnection Feasibility Study, or to study potential impacts, including but not limited to those identified in the Scoping Meeting as described in the Standard Large Generator Interconnection Procedures.

Interconnection System Impact Study Agreement shall mean the form of agreement contained in Appendix 3 of the Standard Large Generator Interconnection Procedures for conducting the Interconnection System Impact Study.

IRS shall mean the Internal Revenue Service.

Joint Operating Committee shall be a group made up of representatives from Interconnection Customers and the Transmission Provider to coordinate operating and technical considerations of Interconnection Service.

Large Generating Facility shall mean a Generating Facility having a Generating Facility Capacity of more than 20 MW.

Loss shall mean any and all losses relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other Party's performance, or non-performance of its obligations under the Standard Large Generator Interconnection Agreement on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnifying Party.

Material Modification shall mean those modifications that have a material impact on the cost or timing of any Interconnection Request with a later queue priority date.

Metering Equipment shall mean all metering equipment installed or to be installed at the Generating Facility pursuant to the Standard Large Generator Interconnection Agreement at the metering points, including but not limited to instrument transformers, MWh-meters, data acquisition equipment, transducers, remote terminal unit, communications equipment, phone lines, and fiber optics.

NERC shall mean the North American Electric Reliability Council or its successor organization.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 266FERC Electric Tariff Superseding Original Sheet No. 266Fourth Revised Volume No. 1

Network Resource shall mean any designated generating resource owned, purchased, or leased by a Network Customer under the Network Integration Transmission Service Tariff. Network Resources do not include any resource, or any portion thereof, that is committed for sale to third parties or otherwise cannot be called upon to meet the Network Customer's Network Load on a non-interruptible basis.

Network Resource Interconnection Service shall mean an Interconnection Service that allows the Interconnection Customer to integrate its Large Generating Facility with the Transmission Provider's Transmission System (1) in a manner comparable to that in which the Transmission Provider integrates its generating facilities to serve native load customers; or (2) in an RTO or ISO with market based congestion management, in the same manner as all other Network Resources. Network Resource Interconnection Service in and of itself does not convey transmission service.

Network Upgrades shall mean the additions, modifications, and upgrades to the Transmission Provider's Transmission System required at or beyond the point at which the Interconnection Facilities connect to the Transmission Provider's Transmission System to accommodate the interconnection of the Large Generating Facility to the Transmission Provider's Transmission System.

Notice of Dispute shall mean a written notice of a dispute or claim that arises out of or in connection with the Standard Large Generator Interconnection Agreement or its performance.

Optional Interconnection Study shall mean a sensitivity analysis based on assumptions specified by the Interconnection Customer in the Optional Interconnection Study Agreement.

Optional Interconnection Study Agreement shall mean the form of agreement contained in Appendix 5 of the Standard Large Generator Interconnection Procedures for conducting the Optional Interconnection Study.

Party or Parties shall mean Transmission Provider, Transmission Owner, Interconnection Customer or any combination of the above.

Point of Change of Ownership shall mean the point, as set forth in Appendix A to the Standard Large Generator Interconnection Agreement, where the Interconnection Customer's Interconnection Facilities connect to the Transmission Provider's Interconnection Facilities.

Point of Interconnection shall mean the point, as set forth in Appendix A to the Standard Large Generator Interconnection Agreement, where the Interconnection Facilities connect to the Transmission Provider's Transmission System.

Queue Position shall mean the order of a valid Interconnection Request, relative to all other pending valid Interconnection Requests, that is established based upon the date and time of receipt of the valid Interconnection Request by the Transmission Provider.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 267FERC Electric Tariff Superseding Original Sheet No. 267Fourth Revised Volume No. 1

Reasonable Efforts shall mean, with respect to an action required to be attempted or taken by a Party under the Standard Large Generator Interconnection Agreement, efforts that are timely and consistent with Good Utility Practice and are otherwise substantially equivalent to those a Party would use to protect its own interests.

Scoping Meeting shall mean the meeting between representatives of the Interconnection Customer and Transmission Provider conducted for the purpose of discussing alternative interconnection options, to exchange information including any transmission data and earlier study evaluations that would be reasonably expected to impact such interconnection options, to analyze such information, and to determine the potential feasible Points of Interconnection.

Site Control shall mean documentation reasonably demonstrating: (1) ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the Generating Facility; (2) an option to purchase or acquire a leasehold site for such purpose; or (3) an exclusivity or other business relationship between Interconnection Customer and the entity having the right to sell, lease or grant Interconnection Customer the right to possess or occupy a site for such purpose.

Small Generating Facility shall mean a Generating Facility that has a Generating Facility Capacity of no more than 20 MW.

Stand Alone Network Upgrades shall mean Network Upgrades that an Interconnection Customer may construct without affecting day-to-day operations of the Transmission System during their construction. Both the Transmission Provider and the Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify them in Appendix A to the Standard Large Generator Interconnection Agreement.

Standard Large Generator Interconnection Agreement (LGIA) shall mean the form of interconnection agreement applicable to an Interconnection Request pertaining to a Large Generating Facility that is included in the Transmission Provider's Tariff.

Standard Large Generator Interconnection Procedures (LGIP) shall mean the interconnection procedures applicable to an Interconnection Request pertaining to a Large Generating Facility that are included in the Transmission Provider's Tariff.

System Protection Facilities shall mean the equipment, including necessary protection signal communications equipment, required to protect (1) the Transmission Provider's Transmission System from faults or other electrical disturbances occurring at the Generating Facility and (2) the Generating Facility from faults or other electrical system disturbances occurring on the Transmission Provider's Transmission System or on other delivery systems or other generating systems to which the Transmission Provider's Transmission System is directly connected.

Tariff shall mean the Transmission Provider's Tariff through which open access transmission service and Interconnection Service are offered, as filed with FERC, and as amended or supplemented from time to time, or any successor tariff.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 268FERC Electric Tariff Superseding Original Sheet No. 268Fourth Revised Volume No. 1

Transmission Owner shall mean an entity that owns, leases or otherwise possesses an interest in the portion of the Transmission System at the Point of Interconnection and may be a Party to the Standard Large Generator Interconnection Agreement to the extent necessary.

Transmission Provider shall mean the public utility (or its designated agent) that owns, controls, or operates transmission or distribution facilities used for the transmission of electricity in interstate commerce and provides transmission service under the Tariff. The term Transmission Provider should be read to include the Transmission Owner when the Transmission Owner is separate from the Transmission Provider.

Transmission Provider's Interconnection Facilities shall mean all facilities and equipment owned, controlled, or operated by the Transmission Provider from the Point of Change of Ownership to the Point of Interconnection as identified in Appendix A to the Standard Large Generator Interconnection Agreement, including any modifications, additions or upgrades to such facilities and equipment. Transmission Provider's Interconnection Facilities are sole use facilities and shall not include Distribution Upgrades, Stand Alone Network Upgrades or Network Upgrades.

Transmission System shall mean the facilities owned, controlled or operated by the Transmission Provider or Transmission Owner that are used to provide transmission service under the Tariff.

Trial Operation shall mean the period during which Interconnection Customer is engaged in on-site test operations and commissioning of the Generating Facility prior to Commercial Operation.

Section 2. Scope and Application

2.1 Application of Standard Large Generator Interconnection Procedures.

Sections 2 through 13 apply to processing an Interconnection Request pertaining to a Large Generating Facility.

2.2 Comparability.

Transmission Provider shall receive, process and analyze all Interconnection Requests in a timely manner as set forth in this LGIP. Transmission Provider will use the same Reasonable Efforts in processing and analyzing Interconnection Requests from all Interconnection Customers, whether the Generating Facilities are owned by Transmission Provider, its subsidiaries or Affiliates or others.

2.3 Base Case Data.

Transmission Provider shall provide base power flow, short circuit and stability databases, including all underlying assumptions, and contingency list upon request subject to confidentiality provisions in LGIP Section 13.1. Transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 269FERC Electric Tariff Superseding Original Sheet No. 269Fourth Revised Volume No. 1

Provider is permitted to require that Interconnection Customer sign a confidentiality agreement before the release of commercially sensitive information or Critical Energy Infrastructure Information in the Base Case data. Such databases and lists, hereinafter referred to as Base Cases, shall include all (1) generation projects and (ii) transmission projects, including merchant transmission projects that are proposed for the Transmission System for which a transmission expansion plan has been submitted and approved by the applicable authority.

2.4 No Applicability to Transmission Service.

Nothing in this LGIP shall constitute a request for transmission service or confer upon an Interconnection Customer any right to receive transmission service.

Section 3. Interconnection Requests

3.1 General.

An Interconnection Customer shall submit to Transmission Provider an Interconnection Request in the form of Appendix 1 to this LGIP and a refundable deposit of $10,000. Transmission Provider shall apply the deposit toward the cost of an Interconnection Feasibility Study. Interconnection Customer shall submit a separate Interconnection Request for each site and may submit multiple Interconnection Requests for a single site. Interconnection Customer must submit a deposit with each Interconnection Request even when more than one request is submitted for a single site. An Interconnection Request to evaluate one site at two different voltage levels shall be treated as two Interconnection Requests.

At Interconnection Customer's option, Transmission Provider and Interconnection Customer will identify alternative Point(s) of Interconnection and configurations at the Scoping Meeting to evaluate in this process and attempt to eliminate alternatives in a reasonable fashion given resources and information available. Interconnection Customer will select the definitive Point(s) of Interconnection to be studied no later than the execution of the Interconnection Feasibility Study Agreement.

3.2 Identification of Types of Interconnection Services.

At the time the Interconnection Request is submitted, Interconnection Customer must request either Energy Resource Interconnection Service or Network Resource Interconnection Service, as described; provided, however, any Interconnection Customer requesting Network Resource Interconnection Service may also request that it be concurrently studied for Energy Resource Interconnection Service, up to the point when an Interconnection Facility Study Agreement is executed. Interconnection Customer may then elect to proceed with

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 270FERC Electric Tariff Superseding Original Sheet No. 270Fourth Revised Volume No. 1

Network Resource Interconnection Service or to proceed under a lower level of interconnection service to the extent that only certain upgrades will be completed.

3.2.1 Energy Resource Interconnection Service.

3.2.1.1 The Product. Energy Resource Interconnection Service allows Interconnection Customer to connect the Large Generating Facility to the Transmission System and be eligible to deliver the Large Generating Facility's output using the existing firm or non-firm capacity of the Transmission System on an "as available" basis. Energy Resource Interconnection Service does not in and of itself convey any right to deliver electricity to any specific customer or Point of Delivery.

3.2.1.2 The Study. The study consists of short circuit/fault duty, steady state (thermal and voltage) and stability analyses. The short circuit/fault duty analysis would identify direct Interconnection Facilities required and the Network Upgrades necessary to address short circuit issues associated with the Interconnection Facilities. The stability and steady state studies would identify necessary upgrades to allow full output of the proposed Large Generating Facility and would also identify the maximum allowed output, at the time the study is performed, of the interconnecting Large Generating Facility without requiring additional Network Upgrades.

3.2.2 Network Resource Interconnection Service.

3.2.2.1 The Product. Transmission Provider must conduct the necessary studies and construct the Network Upgrades needed to integrate the Large Generating Facility (1) in a manner comparable to that in which Transmission Provider integrates its generating facilities to serve native load customers; or (2) in an ISO or RTO with market based congestion management, in the same manner as all other Network Resources. Network Resource Interconnection Service Allows Interconnection Customer 's Large Generating Facility to be designated as a Network Resource, up to the Large Generating Facility's full output, on the same basis as all other existing Network Resources interconnected to Transmission Provider's Transmission System, and to be studied as a Network Resource on the assumption that such a designation will occur.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 271FERC Electric Tariff Superseding Original Sheet No. 271Fourth Revised Volume No. 1

3.2.2.2 The Study. The Interconnection Study for Network Resource Interconnection Service shall assure that Interconnection Customer's Large Generating Facility meets the requirements for Network Resource Interconnection Service and as a general matter, that such Large Generating Facility's interconnection is also studied with Transmission Provider's Transmission System at peak load, under a variety of severely stressed conditions, to determine whether, with the Large Generating Facility at full output, the aggregate of generation in the local area can be delivered to the aggregate of load on Transmission Provider's Transmission System, consistent with Transmission Provider's reliability criteria and procedures. This approach assumes that some portion of existing Network Resources are displaced by the output of Interconnection Customer's Large Generating Facility. Network Resource Interconnection Service in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery.

3.3 Valid Interconnection Request.

3.3.1 Initiating an Interconnection Request.

To initiate an Interconnection Request, Interconnection Customer must submit all of the following: (i) a $10,000 deposit, (ii) a completed application in the form of Appendix 1, and (iii) demonstration of Site Control or a posting of an additional deposit of $10,000. Such deposits shall be applied toward any Interconnection Studies pursuant to the Interconnection Request. If Interconnection Customer demonstrates Site Control within the cure period specified in Section 3.3.3 after submitting its Interconnection Request, the additional deposit shall be refundable; otherwise, all such deposit(s), additional and initial, become non-refundable.

The expected In-Service Date of the new Large Generating Facility or increase in capacity of the existing Generating Facility shall be no more than the process window for the regional expansion planning period (or in the absence of a regional planning process, the process window for Transmission Provider's expansion planning period) not to exceed seven years from the date the Interconnection Request is received by Transmission Provider, unless Interconnection Customer demonstrates that engineering, permitting and construction of the new Large Generating Facility or increase in capacity of the existing Generating Facility will take longer than the regional expansion planning period. The In-Service Date

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 272FERC Electric Tariff Superseding Original Sheet No. 272Fourth Revised Volume No. 1

may succeed the date the Interconnection Request is received by Transmission Provider by a period up to ten years, or longer where Interconnection Customer and Transmission Provider agree, such agreement not to be unreasonably withheld.

3.3.2 Acknowledgment of Interconnection Request.

Transmission Provider shall acknowledge receipt of the Interconnection Request within five (5) Business Days of receipt of the request and attach a copy of the received Interconnection Request to the acknowledgement.

3.3.3 Deficiencies in Interconnection Request.

An Interconnection Request will not be considered to be a valid request until all items in Section 3.3.1 have been received by Transmission Provider. If an Interconnection Request fails to meet the requirements set forth in Section 3.3.1, Transmission Provider shall notify Interconnection Customer within five (5) Business Days of receipt of the initial Interconnection Request of the reasons for such failure and that the Interconnection Request does not constitute a valid request. Interconnection Customer shall provide Transmission Provider the additional requested information needed to constitute a valid request within ten (10) Business Days after receipt of such notice. Failure by Interconnection Customer to comply with this Section 3.3.3 shall be treated in accordance with Section 3.6.

3.3.4 Scoping Meeting.

Within ten (10) Business Days after receipt of a valid Interconnection Request, Transmission Provider shall establish a date agreeable to Interconnection Customer for the Scoping Meeting, and such date shall be no later than thirty (30) Calendar Days from receipt of the valid Interconnection Request, unless otherwise mutually agreed upon by the Parties.

The purpose of the Scoping Meeting shall be to discuss alternative interconnection options, to exchange information including any transmission data that would reasonably be expected to impact such interconnection options, to analyze such information and to determine the potential feasible Points of Interconnection. Transmission Provider and Interconnection Customer will bring to the meeting such technical data, including, but not limited to: (i) general facility loadings, (ii) general instability issues, (iii) general short circuit issues, (iv) general voltage issues, and (v) general reliability issues as may be reasonably required to accomplish the purpose of the meeting. Transmission Provider and Interconnection Customer will also bring to the meeting personnel and

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 273FERC Electric Tariff Superseding Original Sheet No. 273Fourth Revised Volume No. 1

other resources as may be reasonably required to accomplish the purpose of the meeting in the time allocated for the meeting. On the basis of the meeting, Interconnection Customer shall designate its Point of Interconnection, pursuant to Section 6.1, and one or more available alternative Point(s) of Interconnection. The duration of the meeting shall be sufficient to accomplish its purpose.

3.4 OASIS Posting.

Transmission Provider will maintain on its OASIS a list of all Interconnection Requests. The list will identify, for each Interconnection Request: (i) the maximum summer and winter megawatt electrical output; (ii) the location by county and state; (iii) the station or transmission line or lines where the interconnection will be made; (iv) the projected In-Service Date; (v) the status of the Interconnection Request, including Queue Position; (vi) the type of Interconnection Service being requested; and (vii) the availability of any studies related to the Interconnection Request; (viii) the date of the Interconnection Request; (ix) the type of Generating Facility to be constructed (combined cycle, base load or combustion turbine and fuel type); and (x) for Interconnection Requests that have not resulted in a completed interconnection, an explanation as to why it was not completed. The list will not disclose the identity of Interconnection Customer until Interconnection Customer executes an LGIA or requests that Transmission Provider file an unexecuted LGIA with FERC. Before holding a Scoping Meeting with its Affiliate, Transmission Provider shall post on OASIS an advance notice of its intent to do so. Transmission Provider shall post to its OASIS site any deviations from the study timelines set forth herein. Interconnection Study reports and Optional Interconnection Study reports shall be posted to Transmission Provider's OASIS site subsequent to the meeting between Interconnection Customer and Transmission Provider to discuss the applicable study results. Transmission Provider shall also post any known deviations in the Large Generating Facility's In-Service Date.

3.5 Coordination with Affected Systems.

Transmission Provider will coordinate the conduct of any studies required to determine the impact of the Interconnection Request on Affected Systems with Affected System Operators and, if possible, include those results (if available) in its applicable Interconnection Study within the time frame specified in this LGIP. Transmission Provider will include such Affected System Operators in all meetings held with Interconnection Customer as required by this LGIP. Interconnection Customer will cooperate with Transmission Provider in all matters related to the conduct of studies and the determination of modifications to Affected Systems. A Transmission Provider which may be an Affected System shall cooperate with Transmission Provider with whom interconnection has been

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 274FERC Electric Tariff Superseding Original Sheet No. 274Fourth Revised Volume No. 1

requested in all matters related to the conduct of studies and the determination of modifications to Affected Systems.

3.6 Withdrawal.

Interconnection Customer may withdraw its Interconnection Request at any time by written notice of such withdrawal to Transmission Provider. In addition, if Interconnection Customer fails to adhere to all requirements of this LGIP, except as provided in Section 13.5 (Disputes), Transmission Provider shall deem the Interconnection Request to be withdrawn and shall provide written notice to Interconnection Customer of the deemed withdrawal and an explanation of the reasons for such deemed withdrawal. Upon receipt of such written notice, Interconnection Customer shall have fifteen (15) Business Days in which to either respond with information or actions that cures the deficiency or to notify Transmission Provider of its intent to pursue Dispute Resolution.

Withdrawal shall result in the loss of Interconnection Customer's Queue Position. If an Interconnection Customer disputes the withdrawal and loss of its Queue Position, then during Dispute Resolution, Interconnection Customer's Interconnection Request is eliminated from the queue until such time that the outcome of Dispute Resolution would restore its Queue Position. An Interconnection Customer that withdraws or is deemed to have withdrawn its Interconnection Request shall pay to Transmission Provider all costs that Transmission Provider prudently incurs with respect to that Interconnection Request prior to Transmission Provider's receipt of notice described above. Interconnection Customer must pay all monies due to Transmission Provider before it is allowed to obtain any Interconnection Study data or results.

Transmission Provider shall (i) update the OASIS Queue Position posting and (ii) refund to Interconnection Customer any portion of Interconnection Customer's deposit or study payments that exceeds the costs that Transmission Provider has incurred, including interest calculated in accordance with section 35.19a(a)(2) of FERC's regulations. In the event of such withdrawal, Transmission Provider, subject to the confidentiality provisions of Section 13.1, shall provide, at Interconnection Customer's request, all information that Transmission Provider developed for any completed study conducted up to the date of withdrawal of the Interconnection Request.

Section 4. Queue Position

4.1 General.

Transmission Provider shall assign a Queue Position based upon the date and time of receipt of the valid Interconnection Request; provided that, if the sole reason an Interconnection Request is not valid is the lack of required information on the application form, and Interconnection Customer provides such information in

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 275FERC Electric Tariff Superseding Original Sheet No. 275Fourth Revised Volume No. 1

accordance with Section 3.3.3, then Transmission Provider shall assign Interconnection Customer a Queue Position based on the date the application form was originally filed. Moving a Point of Interconnection shall result in a lowering of Queue Position if it is deemed a Material Modification under Section 4.4.3.

The Queue Position of each Interconnection Request will be used to determine the order of performing the Interconnection Studies and determination of cost responsibility for the facilities necessary to accommodate the Interconnection Request. A higher queued Interconnection Request is one that has been placed "earlier" in the queue in relation to another Interconnection Request that is lower queued.

Transmission Provider may allocate the cost of the common upgrades for clustered Interconnection Requests without regard to Queue Position.

4.2 Clustering.

At Transmission Provider's option, Interconnection Requests may be studied serially or in clusters for the purpose of the Interconnection System Impact Study.

Clustering shall be implemented on the basis of Queue Position. If Transmission Provider elects to study Interconnection Requests using Clustering, all Interconnection Requests received within a period not to exceed one hundred and eighty (180) Calendar Days, hereinafter referred to as the "Queue Cluster Window" shall be studied together without regard to the nature of the underlying Interconnection Service, whether Energy Resource Interconnection Service or Network Resource Interconnection Service. The deadline for completing all Interconnection System Impact Studies for which an Interconnection System Impact Study Agreement has been executed during a Queue Cluster Window shall be in accordance with Section 7.4, for all Interconnection Requests assigned to the same Queue Cluster Window. Transmission Provider may study an Interconnection Request separately to the extent warranted by Good Utility Practice based upon the electrical remoteness of the proposed Large Generating Facility.

Clustering Interconnection System Impact Studies shall be conducted in such a manner to ensure the efficient implementation of the applicable regional transmission expansion plan in light of the Transmission System's capabilities at the time of each study.

The Queue Cluster Window shall have a fixed time interval based on fixed annual opening and closing dates. Any changes to the established Queue Cluster Window interval and opening or closing dates shall be announced with a posting on Transmission Provider's OASIS beginning at least one hundred and eighty

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 276FERC Electric Tariff Superseding Original Sheet No. 276Fourth Revised Volume No. 1

(180) Calendar Days in advance of the change and continuing thereafter through the end date of the first Queue Cluster Window that is to be modified.

4.3 Transferability of Queue Position.

An Interconnection Customer may transfer its Queue Position to another entity only if such entity acquires the specific Generating Facility identified in the Interconnection Request and the Point of Interconnection does not change.

4.4 Modifications.

Interconnection Customer shall submit to Transmission Provider, in writing, modifications to any information provided in the Interconnection Request. Interconnection Customer shall retain its Queue Position if the modifications are in accordance with Sections 4.4.1, 4.4.2 or 4.4.5, or are determined not to be Material Modifications pursuant to Section 4.4.3.

Notwithstanding the above, during the course of the Interconnection Studies, either Interconnection Customer or Transmission Provider may identify changes to the planned interconnection that may improve the costs and benefits (including reliability) of the interconnection, and the ability of the proposed change to accommodate the Interconnection Request. To the extent the identified changes are acceptable to Transmission Provider and Interconnection Customer, such acceptance not to be unreasonably withheld, Transmission Provider shall modify the Point of Interconnection and/or configuration in accordance with such changes and proceed with any re-studies necessary to do so in accordance with Section 6.4, Section 7.6 and Section 8.5 as applicable and Interconnection Customer shall retain its Queue Position.

4.4.1 Prior to the return of the executed Interconnection System Impact Study Agreement to Transmission Provider, modifications permitted under this Section shall include specifically: (a) a decrease of up to 60 percent of electrical output (MW) of the proposed project; (b) modifying the technical parameters associated with the Large Generating Facility technology or the Large Generating Facility step-up transformer impedance characteristics; and (c) modifying the interconnection configuration. For plant increases, the incremental increase in plant output will go to the end of the queue for the purposes of cost allocation and study analysis.

4.4.2 Prior to the return of the executed Interconnection Facility Study Agreement to Transmission Provider, the modifications permitted under this Section shall include specifically: (a) additional 15 percent decrease of electrical output (MW), and (b) Large Generating Facility technical parameters associated with modifications to Large Generating Facility

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 277FERC Electric Tariff Superseding Original Sheet No. 277Fourth Revised Volume No. 1

technology and transformer impedances; provided, however, the incremental costs associated with those modifications are the responsibility of the requesting Interconnection Customer.

4.4.3 Prior to making any modification other than those specifically permitted by Sections 4.4.1, 4.4.2, and 4.4.5, Interconnection Customer may first request that Transmission Provider evaluate whether such modification is a Material Modification. In response to Interconnection Customer's request, Transmission Provider shall evaluate the proposed modifications prior to making them and inform Interconnection Customer in writing of whether the modifications would constitute a Material Modification. Any change to the Point of Interconnection, except those deemed acceptable under Sections 4.4.1, 6.1, 7.2 or so allowed elsewhere, shall constitute a Material Modification. Interconnection Customer may then withdraw the proposed modification or proceed with a new Interconnection Request for such modification.

4.4.4 Upon receipt of Interconnection Customer's request for modification permitted under this Section 4.4, Transmission Provider shall commence and perform any necessary additional studies as soon as practicable, but in no event shall Transmission Provider commence such studies later than thirty (30) Calendar Days after receiving notice of Interconnection Customer's request. Any additional studies resulting from such modification shall be done at Interconnection Customer's cost.

4.4.5 Extensions of less than three (3) cumulative years in the Commercial Operation Date of the Large Generating Facility to which the Interconnection Request relates are not material and should be handled through construction sequencing.

Section 5. Procedures for Interconnection Requests Submitted Prior to Effective Date of Standard Large Generator Interconnection Procedures

5.1 Queue Position for Pending Requests.

5.1.1 Any Interconnection Customer assigned a Queue Position prior to the effective date of this LGIP shall retain that Queue Position.

5.1.1.1 If an Interconnection Study Agreement has not been executed as of the effective date of this LGIP, then such Interconnection Study, and any subsequent Interconnection Studies, shall be processed in accordance with this LGIP.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 278FERC Electric Tariff Superseding Original Sheet No. 278Fourth Revised Volume No. 1

5.1.1.2 If an Interconnection Study Agreement has been executed prior to the effective date of this LGIP, such Interconnection Study shall be completed in accordance with the terms of such agreement. With respect to any remaining studies for which an Interconnection Customer has not signed an Interconnection Study Agreement prior to the effective date of the LGIP, Transmission Provider must offer Interconnection Customer the option of either continuing under Transmission Provider's existing interconnection study process or going forward with the completion of the necessary Interconnection Studies (for which it does not have a signed Interconnection Studies Agreement) in accordance with this LGIP.

5.1.1.3 If an LGIA has been submitted to FERC for approval before the effective date of the LGIP, then the LGIA would be grandfathered.

5.1.2 Transition Period.

To the extent necessary, Transmission Provider and Interconnection Customers with an outstanding request (i.e., an Interconnection Request for which an LGIA has not been submitted to FERC for approval as of the effective date of this LGIP) shall transition to this LGIP within a reasonable period of time not to exceed sixty (60) Calendar Days. The use of the term "outstanding request" herein shall mean any Interconnection Request, on the effective date of this LGIP: (i) that has been submitted but not yet accepted by Transmission Provider; (ii) where the related interconnection agreement has not yet been submitted to FERC for approval in executed or unexecuted form, (iii) where the relevant Interconnection Study Agreements have not yet been executed, or (iv) where any of the relevant Interconnection Studies are in process but not yet completed. Any Interconnection Customer with an outstanding request as of the effective date of this LGIP may request a reasonable extension of any deadline, otherwise applicable, if necessary to avoid undue hardship or prejudice to its Interconnection Request. A reasonable extension shall be granted by Transmission Provider to the extent consistent with the intent and process provided for under this LGIP.

5.2 New Transmission Provider.

If Transmission Provider transfers control of its Transmission System to a successor Transmission Provider during the period when an Interconnection Request is pending, the original Transmission Provider shall transfer to the

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 279FERC Electric Tariff Superseding Original Sheet No. 279Fourth Revised Volume No. 1

successor Transmission Provider any amount of the deposit or payment with interest thereon that exceeds the cost that it incurred to evaluate the request for interconnection. Any difference between such net amount and the deposit or payment required by this LGIP shall be paid by or refunded to the Interconnection, as appropriate. The original Transmission Provider shall coordinate with the successor Transmission Provider to complete any Interconnection Study, as appropriate, that the original Transmission Provider has begun but has not completed. If Transmission Provider has tendered a draft LGIA to Interconnection Customer but Interconnection Customer has not either executed the LGIA or requested the filing of an unexecuted LGIA with FERC, unless otherwise provided, Interconnection Customer must complete negotiations with the successor Transmission Provider.

Section 6. Interconnection Feasibility Study

6.1 Interconnection Feasibility Study Agreement.

Simultaneously with the acknowledgement of a valid Interconnection Request Transmission Provider shall provide to Interconnection Customer an Interconnection Feasibility Study Agreement in the form of Appendix 2. The Interconnection Feasibility Study Agreement shall specify that Interconnection Customer is responsible for the actual cost of the Interconnection Feasibility Study. Within five (5) Business Days following the Scoping Meeting Interconnection Customer shall specify for inclusion in the attachment to the Interconnection Feasibility Study Agreement the Point(s) of Interconnection and any reasonable alternative Point(s) of Interconnection. Within five (5) Business Days following Transmission Provider's receipt of such designation, Transmission Provider shall tender to Interconnection Customer the Interconnection Feasibility Study Agreement signed by Transmission Provider, which includes a good faith estimate of the cost for completing the Interconnection Feasibility Study. Interconnection Customer shall execute and deliver to Transmission Provider the Interconnection Feasibility Study Agreement along with a $10,000 deposit no later than thirty (30) Calendar Days after its receipt.

On or before the return of the executed Interconnection Feasibility Study Agreement to Transmission Provider, Interconnection Customer shall provide the technical data called for in Appendix 1, Attachment A.

If the Interconnection Feasibility Study uncovers any unexpected result(s) not contemplated during the Scoping Meeting, a substitute Point of Interconnection identified by either Interconnection Customer or Transmission Provider, and acceptable to the other, such acceptance not to be unreasonably withheld, will be substituted for the designated Point of Interconnection specified above without loss of Queue Position, and Re-studies shall be completed pursuant to Section 6.4

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 280FERC Electric Tariff Superseding Original Sheet No. 280Fourth Revised Volume No. 1

as applicable. For the purpose of this Section 6.1, if Transmission Provider and Interconnection Customer cannot agree on the substituted Point of Interconnection, then Interconnection Customer may direct that one of the alternatives as specified in the Interconnection Feasibility Study Agreement, as specified pursuant to Section 3.3.4, shall be the substitute.

If Interconnection Customer and Transmission Provider agree to forgo the Interconnection Feasibility Study, Transmission Provider will initiate an Interconnection System Impact Study under Section 7 of this LGIP and apply the $10,000 deposit towards the Interconnection System Impact Study.

6.2 Scope of Interconnection Feasibility Study.

The Interconnection Feasibility Study shall preliminarily evaluate the feasibility of the proposed interconnection to the Transmission System.

The Interconnection Feasibility Study will consider the Base Case as well as all generating facilities (and with respect to (iii), any identified Network Upgrades) that, on the date the Interconnection Feasibility Study is commenced: (i) are directly interconnected to the Transmission System; (ii) are interconnected to Affected Systems and may have an impact on the Interconnection Request; (iii) have a pending higher queued Interconnection Request to interconnect to the Transmission System; and (iv) have no Queue Position but have executed an LGIA or requested that an unexecuted LGIA be filed with FERC. The Interconnection Feasibility Study will consist of a power flow and short circuit analysis. The Interconnection Feasibility Study will provide a list of facilities and a non-binding good faith estimate of cost responsibility and a non-binding good faith estimated time to construct.

6.3 Interconnection Feasibility Study Procedures.

Transmission Provider shall utilize existing studies to the extent practicable when it performs the study. Transmission Provider shall use Reasonable Efforts to complete the Interconnection Feasibility Study no later than forty-five (45) Calendar Days after Transmission Provider receives the fully executed Interconnection Feasibility Study Agreement. At the request of Interconnection Customer or at any time Transmission Provider determines that it will not meet the required time frame for completing the Interconnection Feasibility Study, Transmission Provider shall notify Interconnection Customer as to the schedule status of the Interconnection Feasibility Study. If Transmission Provider is unable to complete the Interconnection Feasibility Study within that time period, it shall notify Interconnection Customer and provide an estimated completion date with

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 281FERC Electric Tariff Superseding Original Sheet No. 281Fourth Revised Volume No. 1

an explanation of the reasons why additional time is required. Upon request, Transmission Provider shall provide Interconnection Customer supporting documentation, workpapers and relevant power flow, short circuit and stability databases for the Interconnection Feasibility Study, subject to confidentiality arrangements consistent with Section 13.1.

6.3.1 Meeting with Transmission Provider.

Within ten (10) Business Days of providing an Interconnection Feasibility Study report to Interconnection Customer, Transmission Provider and Interconnection Customer shall meet to discuss the results of the Interconnection Feasibility Study.

6.4 Re-Study.

If Re-Study of the Interconnection Feasibility Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 6.1 Transmission Provider shall notify Interconnection Customer in writing. Such Re-Study shall take not longer than forty-five (45) Calendar Days from the date of the notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.

Section 7. Interconnection System Impact Study

7.1 Interconnection System Impact Study Agreement.

Unless otherwise agreed, pursuant to the Scoping Meeting provided in Section 3.3.4, simultaneously with the delivery of the Interconnection Feasibility Study to Interconnection Customer, Transmission Provider shall provide to Interconnection Customer an Interconnection System Impact Study Agreement in the form of Appendix 3 to this LGIP. The Interconnection System Impact Study Agreement shall provide that Interconnection Customer shall compensate Transmission Provider for the actual cost of the Interconnection System Impact Study. Within three (3) Business Days following the Interconnection Feasibility Study results meeting, Transmission Provider shall provide to Interconnection Customer a non-binding good faith estimate of the cost and timeframe for completing the Interconnection System Impact Study.

7.2 Execution of Interconnection System Impact Study Agreement.

Interconnection Customer shall execute the Interconnection System Impact Study Agreement and deliver the executed Interconnection System Impact Study

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 282FERC Electric Tariff Superseding Original Sheet No. 282Fourth Revised Volume No. 1

Agreement to Transmission Provider no later than thirty (30) Calendar Days after its receipt along with demonstration of Site Control, and a $50,000 deposit.

If Interconnection Customer does not provide all such technical data when it delivers the Interconnection System Impact Study Agreement, Transmission Provider shall notify Interconnection Customer of the deficiency within five (5) Business Days of the receipt of the executed Interconnection System Impact Study Agreement and Interconnection Customer shall cure the deficiency within ten (10) Business Days of receipt of the notice, provided, however, such deficiency does not include failure to deliver the executed Interconnection System Impact Study Agreement or deposit.

If the Interconnection System Impact Study uncovers any unexpected result(s) not contemplated during the Scoping Meeting and the Interconnection Feasibility Study, a substitute Point of Interconnection identified by either Interconnection Customer or Transmission Provider, and acceptable to the other, such acceptance not to be unreasonably withheld, will be substituted for the designated Point of Interconnection specified above without loss of Queue Position, and restudies shall be completed pursuant to Section 7.6 as applicable. For the purpose of this Section 7.6, if Transmission Provider and Interconnection Customer cannot agree on the substituted Point of Interconnection, then Interconnection Customer may direct that one of the alternatives as specified in the Interconnection Feasibility Study Agreement, as specified pursuant to Section 3.3.4, shall be the substitute.

7.3 Scope of Interconnection System Impact Study.

The Interconnection System Impact Study shall evaluate the impact of the proposed interconnection on the reliability of the Transmission System. The Interconnection System Impact Study will consider the Base Case as well as all generating facilities (and with respect to (iii) below, any identified Network Upgrades associated with such higher queued interconnection) that, on the date the Interconnection System Impact Study is commenced: (i) are directly interconnected to the Transmission System; (ii) are interconnected to Affected Systems and may have an impact on the Interconnection Request; (iii) have a pending higher queued Interconnection Request to interconnect to the Transmission System; and (iv) have no Queue Position but have executed an LGIA or requested that an unexecuted LGIA be filed with FERC.

The Interconnection System Impact Study will consist of a short circuit analysis, a stability analysis, and a power flow analysis. The Interconnection System Impact Study will state the assumptions upon which it is based; state the results of the analyses; and provide the requirements or potential impediments to providing the requested interconnection service, including a preliminary indication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the interconnection. The Interconnection System

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 283FERC Electric Tariff Superseding Original Sheet No. 283Fourth Revised Volume No. 1

Impact Study will provide a list of facilities that are required as a result of the Interconnection Request and a non-binding good faith estimate of cost responsibility and a non-binding good faith estimated time to construct.

7.4 Interconnection System Impact Study Procedures.

Transmission Provider shall coordinate the Interconnection System Impact Study with any Affected System that is affected by the Interconnection Request pursuant to Section 3.5 above. Transmission Provider shall utilize existing studies to the extent practicable when it performs the study. Transmission Provider shall use Reasonable Efforts to complete the Interconnection System Impact Study within ninety (90) Calendar Days after the receipt of the Interconnection System Impact Study Agreement or notification to proceed, study payment, and technical data. If Transmission Provider uses Clustering, Transmission Provider shall use Reasonable Efforts to deliver a completed Interconnection System Impact Study within ninety (90) Calendar Days after the close of the Queue Cluster Window.

At the request of Interconnection Customer or at any time Transmission Provider determines that it will not meet the required time frame for completing the Interconnection System Impact Study, Transmission Provider shall notify Interconnection Customer as to the schedule status of the Interconnection System Impact Study. If Transmission Provider is unable to complete the Interconnection System Impact Study within the time period, it shall notify Interconnection Customer and provide an estimated completion date with an explanation of the reasons why additional time is required. Upon request, Transmission Provider shall provide Interconnection Customer all supporting documentation, workpapers and relevant pre-Interconnection Request and post-Interconnection Request power flow, short circuit and stability databases for the Interconnection System Impact Study, subject to confidentiality arrangements consistent with Section 13.1.

7.5 Meeting with Transmission Provider.

Within ten (10) Business Days of providing an Interconnection System Impact Study report to Interconnection Customer, Transmission Provider and Interconnection Customer shall meet to discuss the results of the Interconnection System Impact Study.

7.6 Re-Study.

If Re-Study of the Interconnection System Impact Study is required due to a higher queued project dropping out of the queue, a modification of a higher queued project subject to 4.4, or re-designation of the Point of Interconnection pursuant to Section 6.1 Transmission Provider shall notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 284FERC Electric Tariff Superseding Original Sheet No. 284Fourth Revised Volume No. 1

Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.

Section 8. Interconnection Facilities Study

8.1 Interconnection Facilities Study Agreement.

Simultaneously with the delivery of the Interconnection System Impact Study to Interconnection Customer, Transmission Provider shall provide to Interconnection Customer an Interconnection Facilities Study Agreement in the form of Appendix 4 to this LGIP. The Interconnection Facilities Study Agreement shall provide that Interconnection Customer shall compensate Transmission Provider for the actual cost of the Interconnection Facilities Study. Within three (3) Business Days following the Interconnection System Impact Study results meeting, Transmission Provider shall provide to Interconnection Customer a non-binding good faith estimate of the cost and timeframe for completing the Interconnection Facilities Study. Interconnection Customer shall execute the Interconnection Facilities Study Agreement and deliver the executed Interconnection Facilities Study Agreement to Transmission Provider within thirty (30) Calendar Days after its receipt, together with the required technical data and the greater of $100,000 or Interconnection Customer's portion of the estimated monthly cost of conducting the Interconnection Facilities Study.

8.1.1 Transmission Provider shall invoice Interconnection Customer on a monthly basis for the work to be conducted on the Interconnection Facilities Study each month. Interconnection Customer shall pay invoiced amounts within thirty (30) Calendar Days of receipt of invoice. Transmission Provider shall continue to hold the amounts on deposit until settlement of the final invoice.

8.2 Scope of Interconnection Facilities Study.

The Interconnection Facilities Study shall specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the Interconnection System Impact Study in accordance with Good Utility Practice to physically and electrically connect the Interconnection Facility to the Transmission System. The Interconnection Facilities Study shall also identify the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Transmission Provider's Interconnection Facilities and Network Upgrades necessary to accomplish the interconnection; and an estimate of the time required to complete the construction and installation of such facilities.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 285FERC Electric Tariff Superseding Original Sheet No. 285Fourth Revised Volume No. 1

8.3 Interconnection Facilities Study Procedures.

Transmission Provider shall coordinate the Interconnection Facilities Study with any Affected System pursuant to Section 3.5 above. Transmission Provider shall utilize existing studies to the extent practicable in performing the Interconnection Facilities Study. Transmission Provider shall use Reasonable Efforts to complete the study and issue a draft Interconnection Facilities Study report to Interconnection Customer within the following number of days after receipt of an executed Interconnection Facilities Study Agreement: ninety (90) Calendar Days, with no more than a +/- 20 percent cost estimate contained in the report; or one hundred eighty (180) Calendar Days, if Interconnection Customer requests a +/- 10 percent cost estimate.

At the request of Interconnection Customer or at any time Transmission Provider determines that it will not meet the required time frame for completing the Interconnection Facilities Study, Transmission Provider shall notify Interconnection Customer as to the schedule status of the Interconnection Facilities Study. If Transmission Provider is unable to complete the Interconnection Facilities Study and issue a draft Interconnection Facilities Study report within the time required, it shall notify Interconnection Customer and provide an estimated completion date and an explanation of the reasons why additional time is required.

Interconnection Customer may, within thirty (30) Calendar Days after receipt of the draft report, provide written comments to Transmission Provider, which Transmission Provider shall include in the final report. Transmission Provider shall issue the final Interconnection Facilities Study report within fifteen (15) Business Days of receiving Interconnection Customer's comments or promptly upon receiving Interconnection Customer's statement that it will not provide comments. Transmission Provider may reasonably extend such fifteen-day period upon notice to Interconnection Customer if Interconnection Customer's comments require Transmission Provider to perform additional analyses or make other significant modifications prior to the issuance of the final Interconnection Facilities Report. Upon request, Transmission Provider shall provide Interconnection Customer supporting documentation, workpapers, and databases or data developed in the preparation of the Interconnection Facilities Study, subject to confidentiality arrangements consistent with Section 13.1.

8.4 Meeting with Transmission Provider.

Within ten (10) Business Days of providing a draft Interconnection Facilities Study report to Interconnection Customer, Transmission Provider and Interconnection Customer shall meet to discuss the results of the Interconnection Facilities Study.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 286FERC Electric Tariff Superseding Original Sheet No. 286Fourth Revised Volume No. 1

8.5 Re-Study.

If Re-Study of the Interconnection Facilities Study is required due to a higher queued project dropping out of the queue or a modification of a higher queued project pursuant to Section 4.4, Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.

Section 9. Engineering & Procurement ('E&P') Agreement

Prior to executing an LGIA, an Interconnection Customer may, in order to advance the implementation of its interconnection, request and Transmission Provider shall offer the Interconnection Customer, an E&P Agreement that authorizes Transmission Provider to begin engineering and procurement of long lead-time items necessary for the establishment of the interconnection. However, Transmission Provider shall not be obligated to offer an E&P Agreement if Interconnection Customer is in Dispute Resolution as a result of an allegation that Interconnection Customer has failed to meet any milestones or comply with any prerequisites specified in other parts of the LGIP. The E&P Agreement is an optional procedure and it will not alter the Interconnection Customer's Queue Position or In-Service Date. The E&P Agreement shall provide for Interconnection Customer to pay the cost of all activities authorized by Interconnection Customer and to make advance payments or provide other satisfactory security for such costs.

Interconnection Customer shall pay the cost of such authorized activities and any cancellation costs for equipment that is already ordered for its interconnection, which cannot be mitigated as hereafter described, whether or not such items or equipment later become unnecessary. If Interconnection Customer withdraws its application for interconnection or either party terminates the E&P Agreement, to the extent the equipment ordered can be canceled under reasonable terms, Interconnection Customer shall be obligated to pay the associated cancellation costs. To the extent that the equipment cannot be reasonably canceled, Transmission Provider may elect: (i) to take title to the equipment, in which event Transmission Provider shall refund Interconnection Customer any amounts paid by Interconnection Customer for such equipment and shall pay the cost of delivery of such equipment, or (ii) to transfer title to and deliver such equipment to Interconnection Customer, in which event Interconnection Customer shall pay any unpaid balance and cost of delivery of such equipment.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 287FERC Electric Tariff Superseding Original Sheet No. 287Fourth Revised Volume No. 1

Section 10. Optional Interconnection Study

10.1 Optional Interconnection Study Agreement.

On or after the date when Interconnection Customer receives Interconnection System Impact Study results, Interconnection Customer may request, and Transmission Provider shall perform a reasonable number of Optional Studies. The request shall describe the assumptions that Interconnection Customer wishes Transmission Provider to study within the scope described in Section 10.2. Within five (5) Business Days after receipt of a request for an Optional Interconnection Study, Transmission Provider shall provide to Interconnection Customer an Optional Interconnection Study Agreement in the form of Appendix 5.

The Optional Interconnection Study Agreement shall: (i) specify the technical data that Interconnection Customer must provide for each phase of the Optional Interconnection Study, (ii) specify Interconnection Customer's assumptions as to which Interconnection Requests with earlier queue priority dates will be excluded from the Optional Interconnection Study case and assumptions as to the type of interconnection service for Interconnection Requests remaining in the Optional Interconnection Study case, and (iii) Transmission Provider's estimate of the cost of the Optional Interconnection Study. To the extent known by Transmission Provider, such estimate shall include any costs expected to be incurred by any Affected System whose participation is necessary to complete the Optional Interconnection Study. Notwithstanding the above, Transmission Provider shall not be required as a result of an Optional Interconnection Study request to conduct any additional Interconnection Studies with respect to any other Interconnection Request.

Interconnection Customer shall execute the Optional Interconnection Study Agreement within ten (10) Business Days of receipt and deliver the Optional Interconnection Study Agreement, the technical data and a $10,000 deposit to Transmission Provider.

10.2 Scope of Optional Interconnection Study.

The Optional Interconnection Study will consist of a sensitivity analysis based on the assumptions specified by Interconnection Customer in the Optional Interconnection Study Agreement. The Optional Interconnection Study will also identify Transmission Provider's Interconnection Facilities and the Network Upgrades, and the estimated cost thereof, that may be required to provide transmission service or Interconnection Service based upon the results of the Optional Interconnection Study. The Optional Interconnection Study shall be performed solely for informational purposes. Transmission Provider shall use Reasonable Efforts to coordinate the study with any Affected Systems that may be affected by the types of Interconnection Services that are being studied.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 288FERC Electric Tariff Superseding Original Sheet No. 288Fourth Revised Volume No. 1

Transmission Provider shall utilize existing studies to the extent practicable in conducting the Optional Interconnection Study.

10.3 Optional Interconnection Study Procedures.

The executed Optional Interconnection Study Agreement, the prepayment, and technical and other data called for therein must be provided to Transmission Provider within ten (10) Business Days of Interconnection Customer receipt of the Optional Interconnection Study Agreement. Transmission Provider shall use Reasonable Efforts to complete the Optional Interconnection Study within a mutually agreed upon time period specified within the Optional Interconnection Study Agreement. If Transmission Provider is unable to complete the Optional Interconnection Study within such time period, it shall notify Interconnection Customer and provide an estimated completion date and an explanation of the reasons why additional time is required. Any difference between the study payment and the actual cost of the study shall be paid to Transmission Provider or refunded to Interconnection Customer, as appropriate. Upon request, Transmission Provider shall provide Interconnection Customer supporting documentation and workpapers and databases or data developed in the preparation of the Optional Interconnection Study, subject to confidentiality arrangements consistent with Section 13.1.

Section 11. Standard Large Generator Interconnection Agreement (LGIA)

11.1 Tender.

Interconnection Customer shall tender comments on the draft Interconnection Facilities Study Report within thirty (30) Calendar Days of receipt of the report. Within thirty (30) Calendar Days after the comments are submitted, Interconnection Customer shall tender a draft LGIA, together with draft appendices completed to the extent practicable. The draft LGIA shall be in the form of Transmission Provider's FERC-approved standard form LGIA, which is in Appendix 6. Interconnection Customer shall execute and return the completed draft appendices within thirty (30) Calendar Days.

11.2 Negotiation.

Notwithstanding Section 11.1, at the request of Interconnection Customer Transmission Provider shall begin negotiations with Interconnection Customer concerning the appendices to the LGIA at any time after Interconnection Customer executes the Interconnection Facilities Study Agreement. Transmission Provider and Interconnection Customer shall negotiate concerning any disputed provisions of the appendices to the draft LGIA for not more than sixty (60)

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 289FERC Electric Tariff Superseding Original Sheet No. 289Fourth Revised Volume No. 1

Calendar Days after tender of the final Interconnection Facilities Study Report. If Interconnection Customer determines that negotiations are at an impasse, it may request termination of the negotiations at any time after tender of the LGIA pursuant to Section 11.1 and request submission of the unexecuted LGIA with FERC or initiate Dispute Resolution procedures pursuant to Section 13.5. If Interconnection Customer requests termination of the negotiations, but within sixty (60) Calendar Days thereafter fails to request either the filing of the unexecuted LGIA or initiate Dispute Resolution, it shall be deemed to have withdrawn its Interconnection Request. Unless otherwise agreed by the Parties, if Interconnection Customer has not executed the LGIA, requested filing of an unexecuted LGIA, or initiated Dispute Resolution procedures pursuant to Section 13.5 within sixty days of tender of completed draft of the LGIA appendices, it shall be deemed to have withdrawn its Interconnection Request. Transmission Provider shall provide to Interconnection Customer a final LGIA within fifteen (15) Business Days after the completion of the negotiation process.

11.3 Execution and Filing.

Within fifteen (15) Business Days after receipt of the final LGIA, Interconnection Customer shall provide Transmission Provider (A) reasonable evidence that continued Site Control or (B) posting of $250,000, non-refundable additional security, which shall be applied toward future construction costs. At the same time, Interconnection Customer also shall provide reasonable evidence that one or more of the following milestones in the development of the Large Generating Facility, at Interconnection Customer election, has been achieved: (i) the execution of a contract for the supply or transportation of fuel to the Large Generating Facility; (ii) the execution of a contract for the supply of cooling water to the Large Generating Facility; (iii) execution of a contract for the engineering for, procurement of major equipment for, or construction of, the Large Generating Facility; (iv) execution of a contract for the sale of electric energy or capacity from the Large Generating Facility; or (v) application for an air, water, or land use permit.

Interconnection Customer shall either: (i) execute two originals of the tendered LGIA and return them to Transmission Provider; or (ii) request in writing that Transmission Provider file with FERC an LGIA in unexecuted form. As soon as practicable, but not later than ten (10) Business Days after receiving either the two executed originals of the tendered LGIA (if it does not conform with a FERC-approved standard form of interconnection agreement) or the request to file an unexecuted LGIA, Transmission Provider shall file the LGIA with FERC, together with its explanation of any matters as to which Interconnection Customer and Transmission Provider disagree and support for the costs that Transmission Provider proposes to charge to Interconnection Customer under the LGIA. An unexecuted LGIA should contain terms and conditions deemed appropriate by

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 290FERC Electric Tariff Superseding Original Sheet No. 290Fourth Revised Volume No. 1

Transmission Provider for the Interconnection Request. If the Parties agree to proceed with design, procurement, and construction of facilities and upgrades under the agreed-upon terms of the unexecuted LGIA, they may proceed pending FERC action.

11.4 Commencement of Interconnection Activities.

If Interconnection Customer executes the final LGIA, Transmission Provider and Interconnection Customer shall perform their respective obligations in accordance with the terms of the LGIA, subject to modification by FERC. Upon submission of an unexecuted LGIA, Interconnection Customer and Transmission Provider shall promptly comply with the unexecuted LGIA, subject to modification by FERC.

Section 12. Construction of Transmission Provider's Interconnection Facilities and Network Upgrades

12.1 Schedule.

Transmission Provider and Interconnection Customer shall negotiate in good faith concerning a schedule for the construction of Transmission Provider's Interconnection Facilities and the Network Upgrades.

12.2 Construction Sequencing.

12.2.1 General.

In general, the In-Service Date of an Interconnection Customers seeking interconnection to the Transmission System will determine the sequence of construction of Network Upgrades.

12.2.2 Advance Construction of Network Upgrades that are an Obligation of an Entity other than Interconnection Customer.

An Interconnection Customer with an LGIA, in order to maintain its In-Service Date, may request that Transmission Provider advance to the extent necessary the completion of Network Upgrades that: (i) were assumed in the Interconnection Studies for such Interconnection Customer, (ii) are necessary to support such In-Service Date, and (iii) would otherwise not be completed, pursuant to a contractual obligation of an entity other than Interconnection Customer that is seeking interconnection to the Transmission System, in time to support such In-Service Date. Upon such request, Transmission Provider will use Reasonable

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 291FERC Electric Tariff Superseding Original Sheet No. 291Fourth Revised Volume No. 1

Efforts to advance the construction of such Network Upgrades to accommodate such request; provided that Interconnection Customer commits to pay Transmission Provider: (i) any associated expediting costs and (ii) the cost of such Network Upgrades.

Transmission Provider will refund to Interconnection Customer both the expediting costs and the cost of Network Upgrades, in accordance with Article 11.4 of the LGIA. Consequently, the entity with a contractual obligation to construct such Network Upgrades shall be obligated to pay only that portion of the costs of the Network Upgrades that Transmission Provider has not refunded to Interconnection Customer. Payment by that entity shall be due on the date that it would have been due had there been no request for advance construction. Transmission Provider shall forward to Interconnection Customer the amount paid by the entity with a contractual obligation to construct the Network Upgrades as payment in full for the outstanding balance owed to Interconnection Customer. Transmission Provider then shall refund to that entity the amount that it paid for the Network Upgrades, in accordance with Article 11.4 of the LGIA.

12.2.3 Advancing Construction of Network Upgrades that are Part of an Expansion Plan of the Transmission Provider.

An Interconnection Customer with an LGIA, in order to maintain its In-Service Date, may request that Transmission Provider advance to the extent necessary the completion of Network Upgrades that: (i) are necessary to support such In-Service Date and (ii) would otherwise not be completed, pursuant to an expansion plan of Transmission Provider, in time to support such In-Service Date. Upon such request, Transmission Provider will use Reasonable Efforts to advance the construction of such Network Upgrades to accommodate such request; provided that Interconnection Customer commits to pay Transmission Provider any associated expediting costs. Interconnection Customer shall be entitled to transmission credits, if any, for any expediting costs paid.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool First Revised Sheet No. 292FERC Electric Tariff Superseding Original Sheet No. 292Fourth Revised Volume No. 1

12.2.4 Amended Interconnection System Impact Study.

An Interconnection System Impact Study will be amended to determine the facilities necessary to support the requested In-Service Date. This amended study will include those transmission and Large Generating Facilities that are expected to be in service on or before the requested In-Service Date.

Section 13. Miscellaneous

13.1 Confidentiality.

Confidential Information shall include, without limitation, all information relating to a Party's technology, research and development, business affairs, and pricing, and any information supplied by either of the Parties to the other prior to the execution of an LGIA.

Information is Confidential Information only if it is clearly designated or marked in writing as confidential on the face of the document, or, if the information is conveyed orally or by inspection, if the Party providing the information orally informs the Party receiving the information that the information is confidential.

If requested by either Party, the other Party shall provide in writing, the basis for asserting that the information referred to in this Article warrants confidential treatment, and the requesting Party may disclose such writing to the appropriate Governmental Authority. Each Party shall be responsible for the costs associated with affording confidential treatment to its information.

13.1.1 Scope.

Confidential Information shall not include information that the receiving Party can demonstrate: (1) is generally available to the public other than as a result of a disclosure by the receiving Party; (2) was in the lawful possession of the receiving Party on a non-confidential basis before receiving it from the disclosing Party; (3) was supplied to the receiving Party without restriction by a third party, who, to the knowledge of the receiving Party after due inquiry, was under no obligation to the disclosing Party to keep such information confidential; (4) was independently developed by the receiving Party without reference to Confidential Information of the disclosing Party; (5) is, or becomes, publicly known, through no wrongful act or omission of the receiving Party or Breach of the LGIA; or (6) is required, in accordance with Section 13.1.6, Order of Disclosure, to be disclosed by any Governmental Authority or is otherwise required to be disclosed by law or subpoena, or is necessary in any legal proceeding establishing rights and obligations under the

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 293FERC Electric TariffFourth Revised Volume No. 1

LGIA. Information designated as Confidential Information will no longer be deemed confidential if the Party that designated the information as confidential notifies the other Party that it no longer is confidential.

13.1.2 Release of Confidential Information.

Neither Party shall release or disclose Confidential Information to any other person, except to its Affiliates (limited by the Standards of Conduct requirements), employees, consultants, or to parties who may be or considering providing financing to or equity participation with Interconnection Customer, or to potential purchasers or assignees of Interconnection Customer, on a need-to-know basis in connection with these procedures, unless such person has first been advised of the confidentiality provisions of this Section 13.1 and has agreed to comply with such provisions. Notwithstanding the foregoing, a Party providing Confidential Information to any person shall remain primarily responsible for any release of Confidential Information in contravention of this Section 13.1.

13.1.3 Rights.

Each Party retains all rights, title, and interest in the Confidential Information that each Party discloses to the other Party. The disclosure by each Party to the other Party of Confidential Information shall not be deemed a waiver by either Party or any other person or entity of the right to protect the Confidential Information from public disclosure.

13.1.4 No Warranties.

By providing Confidential Information, neither Party makes any warranties or representations as to its accuracy or completeness. In addition, by supplying Confidential Information, neither Party obligates itself to provide any particular information or Confidential Information to the other Party nor to enter into any further agreements or proceed with any other relationship or joint venture.

13.1.5 Standard of Care.

Each Party shall use at least the same standard of care to protect Confidential Information it receives as it uses to protect its own Confidential Information from unauthorized disclosure, publication or dissemination. Each Party may use Confidential Information

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 294FERC Electric TariffFourth Revised Volume No. 1

solely to fulfill its obligations to the other Party under these procedures or its regulatory requirements.

13.1.6 Order of Disclosure.

If a court or a Government Authority or entity with the right, power, and apparent authority to do so requests or requires either Party, by subpoena, oral deposition, interrogatories, requests for production of documents, administrative order, or otherwise, to disclose Confidential Information, that Party shall provide the other Party with prompt notice of such request(s) or requirement(s) so that the other Party may seek an appropriate protective order or waive compliance with the terms of the LGIA. Notwithstanding the absence of a protective order or waiver, the Party may disclose such Confidential Information which, in the opinion of its counsel, the Party is legally compelled to disclose. Each Party will use Reasonable Efforts to obtain reliable assurance that confidential treatment will be accorded any Confidential Information so furnished.

13.1.7 Remedies.

The Parties agree that monetary damages would be inadequate to compensate a Party for the other Party's Breach of its obligations under this Section 13.1. Each Party accordingly agrees that the other Party shall be entitled to equitable relief, by way of injunction or otherwise, if the first Party Breaches or threatens to Breach its obligations under this Section 13.1, which equitable relief shall be granted without bond or proof of damages, and the receiving Party shall not plead in defense that there would be an adequate remedy at law. Such remedy shall not be deemed an exclusive remedy for the Breach of this Section 13.1, but shall be in addition to all other remedies available at law or in equity. The Parties further acknowledge and agree that the covenants contained herein are necessary for the protection of legitimate business interests and are reasonable in scope. No Party, however, shall be liable for indirect, incidental, or consequential or punitive damages of any nature or kind resulting from or arising in connection with this Section 13.1.

13.1.8 Disclosure to FERC, its Staff, or a State.

Notwithstanding anything in this Section 13.1 to the contrary, and pursuant to 18 CFR section 1b.20, if FERC or its staff, during the course of an investigation or otherwise, requests information from

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 295FERC Electric TariffFourth Revised Volume No. 1

one of the Parties that is otherwise required to be maintained in confidence pursuant to the LGIP, the Party shall provide the requested information to FERC or its staff, within the time provided for in the request for information. In providing the information to FERC or its staff, the Party must, consistent with 18 CFR section 388.112, request that the information be treated as confidential and non-public by FERC and its staff and that the information be withheld from public disclosure. Parties are prohibited from notifying the other Party prior to the release of the Confidential Information to FERC or its staff. The Party shall notify the other Party to the LGIA when it is notified by FERC or its staff that a request to release Confidential Information has been received by FERC, at which time either of the Parties may respond before such information would be made public, pursuant to 18 CFR section 388.112. Requests from a state regulatory body conducting a confidential investigation shall be treated in a similar manner, consistent with applicable state rules and regulations.

13.1.9 Subject to the exception in Section 13.1.8, any information that a Party claims is competitively sensitive, commercial or financial information ("Confidential Information") shall not be disclosed by the other Party to any person not employed or retained by the other Party, except to the extent disclosure is (i) required by law; (ii) reasonably deemed by the disclosing Party to be required to be disclosed in connection with a dispute between or among the Parties, or the defense of litigation or dispute; (iii) otherwise permitted by consent of the other Party, such consent not to be unreasonably withheld; or (iv) necessary to fulfill its obligations under this LGIP or as a transmission service provider or a Control Area operator including disclosing the Confidential Information to an RTO or ISO or to a subregional, regional or national reliability organization or planning group. The Party asserting confidentiality shall notify the other Party in writing of the information it claims is confidential. Prior to any disclosures of the other Party's Confidential Information under this subparagraph, or if any third party or Governmental Authority makes any request or demand for any of the information described in this subparagraph, the disclosing Party agrees to promptly notify the other Party in writing and agrees to assert confidentiality and cooperate with the other Party in seeking to protect the Confidential Information from public disclosure by confidentiality agreement, protective order or other reasonable measures.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 296FERC Electric TariffFourth Revised Volume No. 1

13.1.10 This provision shall not apply to any information that was or is hereafter in the public domain (except as a result of a Breach of this provision).

13.1.11 Transmission Provider shall, at Interconnection Customer's election, destroy, in a confidential manner, or return the Confidential Information provided at the time of Confidential Information is no longer needed.

13.2 Delegation of Responsibility.

Transmission Provider may use the services of subcontractors as it deems appropriate to perform its obligations under this LGIP. Transmission Provider shall remain primarily liable to Interconnection Customer for the performance of such subcontractors and compliance with its obligations of this LGIP. The subcontractor shall keep all information provided confidential and shall use such information solely for the performance of such obligation for which it was provided and no other purpose.

13.3 Obligation for Study Costs.

Transmission Provider shall charge and Interconnection Customer shall pay the actual costs of the Interconnection Studies. Any difference between the study deposit and the actual cost of the applicable Interconnection Study shall be paid by or refunded, except as otherwise provided herein, to Interconnection Customer or offset against the cost of any future Interconnection Studies associated with the applicable Interconnection Request prior to beginning of any such future Interconnection Studies. Any invoices for Interconnection Studies shall include a detailed and itemized accounting of the cost of each Interconnection Study. Interconnection Customer shall pay any such undisputed costs within thirty (30) Calendar Days of receipt of an invoice therefor. Transmission Provider shall not be obligated to perform or continue to perform any studies unless Interconnection Customer has paid all undisputed amounts in compliance herewith.

13.4 Third Parties Conducting Studies.

If (i) at the time of the signing of an Interconnection Study Agreement there is disagreement as to the estimated time to complete an Interconnection Study, (ii) Interconnection Customer receives notice pursuant to Sections 6.3, 7.4 or 8.3 that Transmission Provider will not complete an Interconnection Study within the applicable timeframe for such Interconnection Study, or (iii) Interconnection Customer receives neither the Interconnection Study nor a notice under Sections 6.3, 7.4 or 8.3 within the applicable timeframe for such Interconnection Study, then Interconnection Customer may require Transmission Provider to utilize a third party consultant reasonably acceptable to Interconnection Customer and Transmission Provider to perform such Interconnection Study under the direction

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 297FERC Electric TariffFourth Revised Volume No. 1

of Transmission Provider. At other times, Transmission Provider may also utilize a third party consultant to perform such Interconnection Study, either in response to a general request of Interconnection Customer, or on its own volition.

In all cases, use of a third party consultant shall be in accord with Article 26 of the LGIA (Subcontractors) and limited to situations where Transmission Provider determines that doing so will help maintain or accelerate the study process for Interconnection Customer's pending Interconnection Request and not interfere with Transmission Provider's progress on Interconnection Studies for other pending Interconnection Requests. In cases where Interconnection Customer requests use of a third party consultant to perform such Interconnection Study, Interconnection Customer and Transmission Provider shall negotiate all of the pertinent terms and conditions, including reimbursement arrangements and the estimated study completion date and study review deadline. Transmission Provider shall convey all workpapers, data bases, study results and all other supporting documentation prepared to date with respect to the Interconnection Request as soon as practicable upon Interconnection Customer's request subject to the confidentiality provision in Section 13.1. In any case, such third party contract may be entered into with either Interconnection Customer or Transmission Provider at Transmission Provider's discretion. In the case of (iii) Interconnection Customer maintains its right to submit a claim to Dispute Resolution to recover the costs of such third party study. Such third party consultant shall be required to comply with this LGIP, Article 26 of the LGIA (Subcontractors), and the relevant OATT procedures and protocols as would apply if Transmission Provider were to conduct the Interconnection Study and shall use the information provided to it solely for purposes of performing such services and for no other purposes. Transmission Provider shall cooperate with such third party consultant and Interconnection Customer to complete and issue the Interconnection Study in the shortest reasonable time.

13.5 Disputes.

13.5.1 Submission.

In the event either Party has a dispute, or asserts a claim, that arises out of or in connection with the LGIA, the LGIP, or their performance, such Party (the "disputing Party") shall provide the other Party with written notice of the dispute or claim ("Notice of Dispute"). Such dispute or claim shall be referred to a designated senior representative of each Party for resolution on an informal basis as promptly as practicable after receipt of the Notice of Dispute by the other Party. In the event the designated representatives are unable to resolve the claim or dispute through unassisted or assisted negotiations within thirty (30) Calendar Days of the other Party's receipt of the Notice of Dispute, such claim or

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 298FERC Electric TariffFourth Revised Volume No. 1

dispute may, upon mutual agreement of the Parties, be submitted to arbitration and resolved in accordance with the arbitration procedures set forth below. In the event the Parties do not agree to submit such claim or dispute to arbitration, each Party may exercise whatever rights and remedies it may have in equity or at law consistent with the terms of this LGIA.

13.5.2 External Arbitration Procedures.

Any arbitration initiated under these procedures shall be conducted before a single neutral arbitrator appointed by the Parties. If the Parties fail to agree upon a single arbitrator within ten (10) Calendar Days of the submission of the dispute to arbitration, each Party shall choose one arbitrator who shall sit on a three-member arbitration panel. The two arbitrators so chosen shall within twenty (20) Calendar Days select a third arbitrator to chair the arbitration panel. In either case, the arbitrators shall be knowledgeable in electric utility matters, including electric transmission and bulk power issues, and shall not have any current or past substantial business or financial relationships with any party to the arbitration (except prior arbitration). The arbitrator(s) shall provide each of the Parties an opportunity to be heard and, except as otherwise provided herein, shall conduct the arbitration in accordance with the Commercial Arbitration Rules of the American Arbitration Association ("Arbitration Rules") and any applicable FERC regulations or RTO rules; provided, however, in the event of a conflict between the Arbitration Rules and the terms of this Section 13, the terms of this Section 13 shall prevail.

13.5.3 Arbitration Decisions.

Unless otherwise agreed by the Parties, the arbitrator(s) shall render a decision within ninety (90) Calendar Days of appointment and shall notify the Parties in writing of such decision and the reasons therefor. The arbitrator(s) shall be authorized only to interpret and apply the provisions of the LGIA and LGIP and shall have no power to modify or change any provision of the LGIA and LGIP in any manner. The decision of the arbitrator(s) shall be final and binding upon the Parties, and judgment on the award may be entered in any court having jurisdiction. The decision of the arbitrator(s) may be appealed solely on the grounds that the conduct of the arbitrator(s), or the decision itself, violated the standards set forth in the Federal Arbitration Act or the Administrative Dispute Resolution Act. The final decision of the arbitrator must also be filed with FERC if it affects jurisdictional

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 299FERC Electric TariffFourth Revised Volume No. 1

rates, terms and conditions of service, Interconnection Facilities, or Network Upgrades.

13.5.4 Costs.

Each Party shall be responsible for its own costs incurred during the arbitration process and for the following costs, if applicable: (1) the cost of the arbitrator chosen by the Party to sit on the three member panel and one half of the cost of the third arbitrator chosen; or (2) one half the cost of the single arbitrator jointly chosen by the Parties.

13.6 Local Furnishing Bonds.

13.6.1 Transmission Providers that Own Facilities Financed by Local Furnishing Bonds.

This provision is applicable only to a Transmission Provider that has financed facilities for the local furnishing of electric energy with tax-exempt bonds, as described in Section 142(f) of the Internal Revenue Code ("local furnishing bonds"). Notwithstanding any other provision of this LGIA and LGIP, Transmission Provider shall not be required to provide Interconnection Service to Interconnection Customer pursuant to this LGIA and LGIP if the provision of such Transmission Service would jeopardize the tax-exempt status of any local furnishing bond(s) used to finance Transmission Provider’s facilities that would be used in providing such Interconnection Service.

13.6.2 Alternative Procedures for Requesting Interconnection Service.

If Transmission Provider determines that the provision of Interconnection Service requested by Interconnection Customer would jeopardize the tax-exempt status of any local furnishing bond(s) used to finance its facilities that would be used in providing such Interconnection Service, it shall advise the Interconnection Customer within thirty (30) days of receipt of the Interconnection Request.

Interconnection Customer thereafter may renew its request for interconnection using the process specified in Article 5.2(ii) of the Transmission Provider’s OATT.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 300FERC Electric TariffFourth Revised Volume No. 1

APPENDIX 1 TO LGIP

INTERCONNECTION REQUEST FOR A

LARGE GENERATING FACILITY

1. The undersigned Interconnection Customer submits this request to interconnect its Large Generating Facility with Transmission Provider's Transmission System pursuant to a Tariff.

2. This Interconnection Request is for (check one):

_____ A proposed new Large Generating Facility.

_____ An increase in the generating capacity or a Material Modification of an existing Generating Facility.

3. The type of interconnection service requested (check one):

_____ Energy Resource Interconnection Service

_____ Network Resource Interconnection Service

4.  _____ Check here only if Interconnection Customer requesting Network Resource Interconnection Service also seeks to have its Generating Facility studied for Energy Resource Interconnection Service

5. Interconnection Customer provides the following information:

a. Address or location or the proposed new Large Generating Facility site (to the extent known) or, in the case of an existing Generating Facility, the name and specific location of the existing Generating Facility;

b. Maximum summer at ____ degrees C and winter at _____ degrees C megawatt electrical output of the proposed new Large Generating Facility or the amount of megawatt increase in the generating capacity of an existing Generating Facility;

c. General description of the equipment configuration;

d. Commercial Operation Date (Day, Month, and Year);

e. Name, address, telephone number, and e-mail address of Interconnection Customer's contact person;

f. Approximate location of the proposed Point of Interconnection (optional); and

g. Interconnection Customer Data (set forth in Attachment A)

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 301FERC Electric TariffFourth Revised Volume No. 1

6. Applicable deposit amount as specified in the LGIP.

7. Evidence of Site Control as specified in the LGIP (check one)

____ Is attached to this Interconnection Request

____ Will be provided at a later date in accordance with this LGIP

8. This Interconnection Request shall be submitted to the representative indicated below:

[To be completed by Transmission Provider]

9. Representative of Interconnection Customer to contact:

[To be completed by Interconnection Customer]

10. This Interconnection Request is submitted by:

Name of Interconnection Customer: ___________________________________

By (signature): ____________________________________________________

Name (type or print): _______________________________________________

Title:____________________________________________________________

Date:___________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 302FERC Electric TariffFourth Revised Volume No. 1

Attachment A to Appendix 1Interconnection Request

LARGE GENERATING FACILITY DATA

UNIT RATINGS

kVA_____________ °F ____________________Voltage ______________________Power Factor____________________Speed (RPM)___________________ Connection (e.g. Wye) ____________________Short Circuit Ratio _______________ Frequency, Hertz ________________________Stator Amperes at Rated kVA ___________ Field Volts ________________________Max Turbine MW___________ F ______

COMBINED TURBINE-GENERATOR-EXCITER INERTIA DATA

Inertia Constant, H =___________________________ sec/kVAMoment-of-Inertia, WR2 = ____________________ lb. ft.2

REACTANCE DATA (PER UNIT-RATED KVA)

DIRECT AXIS QUADRATURE AXIS

Synchronous – saturated Xdv ________ Xqv _______Synchronous – unsaturated Xdi ________ Xqi _______ Transient – saturated X'dv _________ X'qv _______Transient – unsaturated X'di _______ X'qi _______Subtransient – saturated X"dv _______ X"qv _______Subtransient – unsaturated X"di _______ X"qi _______Negative Sequence – saturated X2v _______Negative Sequence – unsaturated X2i _______Zero Sequence – saturated X0v _______Zero Sequence – unsaturated X0i ___________________Leakage ReactanceXlm _________________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 303FERC Electric TariffFourth Revised Volume No. 1

FIELD TIME CONSTANT DATA (SEC)

Open Circuit T'do T'qo

Three-Phase Short Circuit Transient T'd3 T'qLine to Line Short Circuit Transient T'd2

Line to Neutral Short Circuit Transient T'd1

Short Circuit Subtransient T"d T"q

Open Circuit Subtransient T"do T"qo

ARMATURE TIME CONSTANT DATA (SEC)

Three Phase Short Circuit Ta3

Line to Line Short Circuit Ta2

Line to Neutral Short Circuit Ta1

NOTE: If requested information is not applicable, indicate by marking "N/A."

MW CAPABILITY AND PLANT CONFIGURATIONLARGE GENERATING FACILITY DATA

ARMATURE WINDING RESISTANCE DATA (PER UNIT)

Positive R1

Negative R2

Zero R0

Rotor Short Time Thermal Capacity I22t = _______

Field Current at Rated kVA, Armature Voltage and PF = ____________ ampsField Current at Rated kVA and Armature Voltage, 0 PF = ___________ ampsThree Phase Armature Winding Capacitance = ________________ microfaradField Winding Resistance = _______ ohms _____ °CArmature Winding Resistance (Per Phase) = ______________ ohms _________ °C

CURVES

Provide Saturation, Vee, Reactive Capability, Capacity Temperature Correction curves. Designate normal and emergency Hydrogen Pressure operating range for multiple curves.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 304FERC Electric TariffFourth Revised Volume No. 1

GENERATOR STEP-UP TRANSFORMER DATA RATINGS

Capacity Self-cooled/Maximum Nameplate

_________________/________________ kVA

Voltage Ratio(Generator Side/System side/Tertiary)________________/_______________/_________________ kV

Winding Connections (Low V/High V/Tertiary V (Delta or Wye))______________/______________/_______________

Fixed Taps Available _____________________________________________________

Present Tap Setting _______________________________________________________

IMPEDANCE

Positive Z1 (on self-cooled kVA rating) _______________ % ____________ X/R

Zero Z0 (on self-cooled kVA rating) _______________ % _____________ X/R

EXCITATION SYSTEM DATA

Identify appropriate IEEE model block diagram of excitation system and power system stabilizer (PSS) for computer representation in power system stability simulations and the corresponding excitation system and PSS constants for use in the model.

GOVERNOR SYSTEM DATA

Identify appropriate IEEE model block diagram of governor system for computer representation in power system stability simulations and the corresponding governor system constants for use in the model.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 305FERC Electric TariffFourth Revised Volume No. 1

WIND GENERATORS

Number of generators to be interconnected pursuant to this Interconnection Request:

_____________

Elevation: _____________ _____ Single Phase _____ Three Phase

Inverter manufacturer, model name, number, and version:

_________________________________________________________________

List of adjustable setpoints for the protective equipment or software:

_________________________________________________________________

Note: A completed General Electric Company Power Systems Load Flow (PSLF) data sheet or other compatible formats, such as IEEE and PTI power flow models, must be supplied with the Interconnection Request. If other data sheets are more appropriate to the proposed device, then they shall be provided and discussed at Scoping Meeting.

INDUCTION GENERATORS

(*) Field Volts: _________________(*) Field Amperes: ______________(*) Motoring Power (kW): ________(*) Neutral Grounding Resistor (If Applicable): ____________(*) I2

2t or K (Heating Time Constant): ____________(*) Rotor Resistance: ____________(*) Stator Resistance: ____________(*) Stator Reactance: _____________(*) Rotor Reactance: _____________(*) Magnetizing Reactance: ___________(*) Short Circuit Reactance: ___________(*) Exciting Current: ________________(*) Temperature Rise: ________________(*) Frame Size: _______________(*) Design Letter: _____________(*) Reactive Power Required In Vars (No Load): ________(*) Reactive Power Required In Vars (Full Load): ________(*) Total Rotating Inertia, H: ________Per Unit on KVA Base

Note: Please consult Transmission Provider prior to submitting the Interconnection Request to determine if the information designated by (*) is required.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 306FERC Electric TariffFourth Revised Volume No. 1

APPENDIX 2 to LGIPINTERCONNECTION FEASIBILITY STUDY AGREEMENT

THIS AGREEMENT is made and entered into this _____ day of ________ 20___ by and between __________________, a __________________ organized and existing under the laws of the State of __________________, ("Interconnection Customer") and _________________________ a _____________________ under the laws of the State of _________________, ("Transmission Provider "). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties."

RECITALS

WHEREAS, Interconnection Customer is proposing to develop a Large Generating Facility or generating capacity addition to an existing Generating Facility consistent with the Interconnection Request submitted by Interconnection Customer dated ____________, and

WHEREAS, Interconnection Customer desires to interconnect the Large Generating Facility with the Transmission System; and

WHEREAS, Interconnection Customer has requested Transmission Provider to perform an Interconnection Feasibility Study to assess the feasibility of interconnecting the proposed Large Generating Facility to the Transmission System, and of any Affected Systems;

NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows:

1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated in Transmission Provider's FERC-approved LGIP.

2.0 Interconnection Customer elects and Transmission Provider shall cause to be performed an Interconnection Feasibility Study consistent with Section 6.0 of this LGIP in accordance with the Tariff.

3.0 The scope of the Interconnection Feasibility Study shall be subject to the assumptions set forth in Attachment A to this Agreement.

4.0 The Interconnection Feasibility Study shall be based on the technical information provided by Interconnection Customer in the Interconnection Request, as may be modified as the result of the Scoping Meeting. Transmission Provider reserves the right to request additional technical information from Interconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the Interconnection Feasibility Study and as designated in accordance with Section 3.3.4 of the LGIP. If, after the designation of the Point of Interconnection pursuant to Section 3.3.4 of the LGIP, Interconnection Customer modifies its Interconnection Request pursuant to

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 307FERC Electric TariffFourth Revised Volume No. 1

Section 4.4, the time to complete the Interconnection Feasibility Study may be extended.

5.0 The Interconnection Feasibility Study report shall provide the following information:

- preliminary identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection;

- preliminary identification of any thermal overload or voltage limit violations resulting from the interconnection; and

- preliminary description and non-bonding estimated cost of facilities required to interconnect the Large Generating Facility to the Transmission System and to address the identified short circuit and power flow issues.

6.0 Interconnection Customer shall provide a deposit of $10,000 for the performance of the Interconnection Feasibility Study.

Upon receipt of the Interconnection Feasibility Study Transmission Provider shall charge and Interconnection Customer shall pay the actual costs of the Interconnection Feasibility Study.

Any difference between the deposit and the actual cost of the study shall be paid by or refunded to Interconnection Customer, as appropriate.

7.0 Miscellaneous. The Interconnection Feasibility Study Agreement shall include standard miscellaneous terms including, but not limited to, indemnities, representations, disclaimers, warranties, governing law, amendment, execution, waiver, enforceability and assignment, that reflect best practices in the electric industry, and that are consistent with regional practices, Applicable Laws and Regulations, and the organizational nature of each Party. All of these provisions, to the extent practicable, shall be consistent with the provisions of the LGIP and the LGIA.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 308FERC Electric TariffFourth Revised Volume No. 1

IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written.

[Insert name of Transmission Provider or Transmission Owner, if applicable]

By: ________________________ By: ______________________________

Title: ________________________ Title: ______________________________

Date: ______________________________ Date: ______________________________

[Insert name of Interconnection Customer]

By: ________________________

Title: ________________________

Date: ________________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 309FERC Electric TariffFourth Revised Volume No. 1

Attachment A to Appendix 2Interconnection Feasibility

Study Agreement

ASSUMPTIONS USED IN CONDUCTING THEINTERCONNECTION FEASIBILITY STUDY

The Interconnection Feasibility Study will be based upon the information set forth in the Interconnection Request and agreed upon in the Scoping Meeting held on ______________

Designation of Point of Interconnection and configuration to be studied.

Designation of alternative Point(s) of Interconnection and configuration.

[Above assumptions to be completed by Interconnection Customer and other assumptions to be provided by Interconnection Customer and Transmission Provider]

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 310FERC Electric TariffFourth Revised Volume No. 1

APPENDIX 3 to LGIPINTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT

THIS AGREEMENT is made and entered into this ______ day of ___________ 20___ by and between ___________________ a ________________ and existing under the laws of the State of ___________________ ("Interconnection Customer") and _______________________ a ____________ under the laws of the State of _________________ ("Transmission Provider "). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties."

RECITALS

WHEREAS, Interconnection Customer is proposing to develop a Large Generating Facility or generating capacity addition to an existing Generating Facility consistent with the Interconnection Request submitted by Interconnection Customer dated _________________; and

WHEREAS, Interconnection Customer desires to interconnect the Large Generating Facility with the Transmission System;

WHEREAS, Transmission Provider has completed an Interconnection Feasibility Study (the "Feasibility Study") and provided the results of said study to Interconnection Customer (This recital to be omitted if Transmission Provider does not require the Interconnection Feasibility Study.); and

WHEREAS, Interconnection Customer has requested Transmission Provider to perform an Interconnection System Impact Study to assess the impact of interconnecting the Large Generating Facility to the Transmission System, and of any Affected Systems;

NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows:

1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated in Transmission Provider's FERC-approved LGIP.

2.0 Interconnection Customer elects and Transmission Provider shall cause to be performed an Interconnection System Impact Study consistent with Section 7.0 of this LGIP in accordance with the Tariff.

3.0 The scope of the Interconnection System Impact Study shall be subject to the assumptions set forth in Attachment A to this Agreement.

4.0 The Interconnection System Impact Study will be based upon the results of the Interconnection Feasibility Study and the technical information provided by Interconnection Customer in the Interconnection Request, subject to any modifications in accordance with Section 4.4 of the LGIP. Transmission Provider reserves the right to request additional technical information from Interconnection Customer as may reasonably become necessary consistent with Good Utility

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 311FERC Electric TariffFourth Revised Volume No. 1

Practice during the course of the Interconnection Customer System Impact Study. If Interconnection Customer modifies its designated Point of Interconnection, Interconnection Request, or the technical information provided therein is modified, the time to complete the Interconnection System Impact Study may be extended.

5.0 The Interconnection System Impact Study report shall provide the following information:

- identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection;

- identification of any thermal overload or voltage limit violations resulting from the interconnection;

- identification of any instability or inadequately damped response to system disturbances resulting from the interconnection and

- description and non-binding, good faith estimated cost of facilities required to interconnect the Large Generating Facility to the Transmission System and to address the identified short circuit, instability, and power flow issues.

6.0 Interconnection Customer shall provide a deposit of $50,000 for the performance of the Interconnection System Impact Study. Transmission Provider's good faith estimate for the time of completion of the Interconnection System Impact Study is [insert date].

Upon receipt of the Interconnection System Impact Study, Transmission Provider shall charge and Interconnection Customer shall pay the actual costs of the Interconnection System Impact Study.

Any difference between the deposit and the actual cost of the study shall be paid by or refunded to Interconnection Customer, as appropriate.

7.0 Miscellaneous. The Interconnection System Impact Study Agreement shall include standard miscellaneous terms including, but not limited to, indemnities, representations, disclaimers, warranties, governing law, amendment, execution, waiver, enforceability and assignment, that reflect best practices in the electric industry, that are consistent with regional practices, Applicable Laws and Regulations and the organizational nature of each Party. All of these provisions, to the extent practicable, shall be consistent with the provisions of the LGIP and the LGIA.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 312FERC Electric TariffFourth Revised Volume No. 1

IN WITNESS THEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written.

[Insert name of Transmission Provider or Transmission Owner, if applicable]

By: _________________________ By: ______________________________

Title: _________________________ Title: ______________________________

Date: _______________________________ Date: ______________________________

[Insert name of Interconnection Customer]

By: _________________________

Title: _________________________

Date: _________________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 313FERC Electric TariffFourth Revised Volume No. 1

Attachment A to Appendix 3Interconnection System Impact

Study Agreement

ASSUMPTIONS USED IN CONDUCTING THEINTERCONNECTION SYSTEM IMPACT STUDY

The Interconnection System Impact Study will be based upon the results of the Interconnection Feasibility Study, subject to any modifications in accordance with Section 4.4 of the LGIP, and the following assumptions:

Designation of Point of Interconnection and configuration to be studied.

Designation of alternative Point(s) of Interconnection and configuration.

[Above assumptions to be completed by Interconnection Customer and other assumptions to be provided by Interconnection Customer and Transmission Provider]

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 314FERC Electric TariffFourth Revised Volume No. 1

APPENDIX 4 to LGIPINTERCONNECTION FACILITIES STUDY AGREEMENT

THIS AGREEMENT is made and entered into this ____ of _____________ 20___ by and between _________________ a __________________ and existing under the laws of the State of __________________ ("Interconnection Customer") and ________________________ a _______________ under the laws of the State of _____________________ ("Transmission Provider "). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties."

RECITALS

WHEREAS, Interconnection Customer is proposing to develop a Large Generating Facility or generating capacity addition to an existing Generating Facility consistent with the Interconnection Request submitted by Interconnection Customer dated ____________, and

WHEREAS, Interconnection Customer desires to interconnect the Large Generating Facility with the Transmission System;

WHEREAS, Transmission Provider has completed an Interconnection System Impact Study (the "System Impact Study") and provided the results of said study to Interconnection Customer; and

WHEREAS, Interconnection Customer has requested Transmission Provider to perform an Interconnection Facilities Study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the Interconnection System Impact Study in accordance with Good Utility Practice to physically and electrically connect the Large Generating Facility to the Transmission System.

NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agreed as follows:

1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated in Transmission Provider's FERC-approved LGIP.

2.0 Interconnection Customer elects and Transmission Provider shall cause an Interconnection Facilities Study consistent with Section 8.0 of this LGIP to be performed in accordance with the Tariff.

3.0 The scope of the Interconnection Facilities Study shall be subject to the assumptions set forth in Attachment A and the data provided in Attachment B to this Agreement.

4.0 The Interconnection Facilities Study report (i) shall provide a description, estimated cost of (consistent with Attachment A), schedule for required facilities to interconnect the Large Generating Facility to the Transmission System and (ii)

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 315FERC Electric TariffFourth Revised Volume No. 1

shall address the short circuit, instability, and power flow issues identified in the Interconnection System Impact Study.

5.0 Interconnection Customer shall provide a deposit of $100,000 for the performance of the Interconnection Facilities Study. The time for completion of the Interconnection Facilities Study is specified in Attachment A.

Transmission Provider shall invoice Interconnection Customer on a monthly basis for the work to be conducted on the Interconnection Facilities Study each month. Interconnection Customer shall pay invoiced amounts within thirty (30) Calendar Days of receipt of invoice. Transmission Provider shall continue to hold the amounts on deposit until settlement of the final invoice.

6.0 Miscellaneous. The Interconnection Facility Study Agreement shall include standard miscellaneous terms including, but not limited to, indemnities, representations, disclaimers, warranties, governing law, amendment, execution, waiver, enforceability and assignment, that reflect best practices in the electric industry, and that are consistent with regional practices, Applicable Laws and Regulations, and the organizational nature of each Party. All of these provisions, to the extent practicable, shall be consistent with the provisions of the LGIP and the LGIA.

IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written.

[Insert name of Transmission Provider or Transmission Owner, if applicable]

By: _________________________ By: ______________________________

Title: _________________________ Title: ______________________________

Date: _______________________________ Date: ______________________________

[Insert name of Interconnection Customer]

By: _________________________

Title: _________________________

Date: _________________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 316FERC Electric TariffFourth Revised Volume No. 1

Attachment A To Appendix 4Interconnection Facilities

Study Agreement

INTERCONNECTION CUSTOMER SCHEDULE ELECTION FOR CONDUCTING THE INTERCONNECTION FACILITIES STUDY

Transmission Provider shall use Reasonable Efforts to complete the study and issue a draft Interconnection Facilities Study report to Interconnection Customer within the following number of days after of receipt of an executed copy of this Interconnection Facilities Study Agreement:

- ninety (90) Calendar Days with no more than a +/- 20 percent cost estimate contained in the report, or

- one hundred eighty (180) Calendar Days with no more than a +/- 10 percent cost estimate contained in the report.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 317FERC Electric TariffFourth Revised Volume No. 1

Attachment B to Appendix 4Interconnection Facilities

Study Agreement

DATA FORM TO BE PROVIDED BY INTERCONNECTION CUSTOMER WITH THEINTERCONNECTION FACILITIES STUDY AGREEMENT

Provide location plan and simplified one-line diagram of the plant and station facilities. For staged projects, please indicate future generation, transmission circuits, etc.

One set of metering is required for each generation connection to the new ring bus or existing Transmission Provider station. Number of generation connections:

On the one line diagram indicate the generation capacity attached at each metering location. (Maximum load on CT/PT)

On the one line diagram indicate the location of auxiliary power. (Minimum load on CT/PT) Amps

Will an alternate source of auxiliary power be available during CT/PT maintenance?

______ Yes _______ No

Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant generation? ______Yes ______ No (Please indicate on one line diagram).

What type of control system or PLC will be located at Interconnection Customer's Large Generating Facility?

_______________________________________________________________________

What protocol does the control system or PLC use?

_______________________________________________________________________

Please provide a 7.5-minute quadrangle of the site. Sketch the plant, station, transmission line, and property line.

Physical dimensions of the proposed interconnection station:

_______________________________________________________________________

Bus length from generation to interconnection station:

_______________________________________________________________________

Line length from interconnection station to Transmission Provider's transmission line.

_______________________________________________________________________Issued by: L. Patrick Bourne, Manager

Transmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 318FERC Electric TariffFourth Revised Volume No. 1

Tower number observed in the field. (Painted on tower leg)* ______________________

Number of third party easements required for transmission lines*:

_______________________________________________________________________

* To be completed in coordination with Transmission Provider.

Is the Large Generating Facility in the Transmission Provider's service area?

_____ Yes _____ No Local provider: ___________________________________

Please provide proposed schedule dates:

Begin Construction Date:____________________

Generator step-up transformer Date: ____________________

receives back feed power

Generation Testing Date: ____________________

Commercial Operation Date: ____________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 319FERC Electric TariffFourth Revised Volume No. 1

APPENDIX 5 to LGIPOPTIONAL INTERCONNECTION STUDY AGREEMENT

THIS AGREEMENT is made and entered into this _____ day of __________, 20___ by and between ________________, a _______________and existing under the laws of the State of ________________ ("Interconnection Customer") and ________________________ a ________________ under the laws of the State of ___________________ ("Transmission Provider "). Interconnection Customer and Transmission Provider each may be referred to as a "Party," or collectively as the "Parties."

RECITALS

WHEREAS, Interconnection Customer is proposing to develop a Large Generating Facility or generating capacity addition to an existing Generating Facility consistent with the Interconnection Request submitted by Interconnection Customer dated __________________

WHEREAS, Interconnection Customer is proposing to establish an interconnection with the Transmission System; and

WHEREAS, Interconnection Customer has submitted to Transmission Provider an Interconnection Request; and

WHEREAS, on or after the date when Interconnection Customer receives the Interconnection System Impact Study results, Interconnection Customer has further requested that Transmission Provider prepare an Optional Interconnection Study;

NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agree as follows:

1.0 When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated in Transmission Provider's FERC-approved LGIP.

2.0 Interconnection Customer elects and Transmission Provider shall cause an Optional Interconnection Study consistent with Section 10.0 of this LGIP to be performed in accordance with the Tariff.

3.0 The scope of the Optional Interconnection Study shall be subject to the assumptions set forth in Attachment A to this Agreement.

4.0 The Optional Interconnection Study shall be performed solely for informational purposes.

5.0 The Optional Interconnection Study report shall provide a sensitivity analysis based on the assumptions specified by Interconnection Customer in Attachment A

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 320FERC Electric TariffFourth Revised Volume No. 1

to this Agreement. The Optional Interconnection Study will identify Transmission Provider's Interconnection Facilities and the Network Upgrades, and the estimated cost thereof, that may be required to provide transmission service or interconnection service based upon the assumptions specified by Interconnection Customer in Attachment A.

6.0 Interconnection Customer shall provide a deposit of $10,000 for the performance of the Optional Interconnection Study. Transmission Provider's good faith estimate for the time of completion of the Optional Interconnection Study is [insert date].

Upon receipt of the Optional Interconnection Study, Transmission Provider shall charge and Interconnection Customer shall pay the actual costs of the Optional Study.

Any difference between the initial payment and the actual cost of the study shall be paid by or refunded to Interconnection Customer, as appropriate.

7.0 Miscellaneous. The Optional Interconnection Study Agreement shall include standard miscellaneous terms including, but not limited to, indemnities, representations, disclaimers, warranties, governing law, amendment, execution, waiver, enforceability and assignment, that reflect best practices in the electric industry, and that are consistent with regional practices, Applicable Laws and Regulations, and the organizational nature of each Party. All of these provisions, to the extent practicable, shall be consistent with the provisions of the LGIP and the LGIA.

IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written.

[Insert name of Transmission Provider or Transmission Owner, if applicable]

By: ________________________ By: ______________________________

Title: ________________________ Title: ______________________________

Date: ______________________________ Date: ______________________________

[Insert name of Interconnection Customer]

By: ________________________

Title: ________________________

Date: ________________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 321FERC Electric TariffFourth Revised Volume No. 1

Appendix 6 to the Standard LargeGenerator Interconnection Procedures

STANDARD LARGE GENERATOR

INTERCONNECTION AGREEMENT (LGIA)

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 322FERC Electric TariffFourth Revised Volume No. 1

TABLE OF CONTENTS

Page

Recital ..........................................................................................................................................331

Article 1. Definitions............................................................................................................332

Article 2. Effective Date, Term, and Termination...............................................................340

2.1 Effective Date......................................................................................................340

2.2 Term of Agreement..............................................................................................340

2.3 Termination Procedures.......................................................................................340

2.3.1 Written Notice..........................................................................................340

2.3.2 Default......................................................................................................340

2.4 Termination Costs................................................................................................341

2.5 Disconnection......................................................................................................342

2.6 Survival................................................................................................................343

Article 3. Regulatory Filings................................................................................................342

3.1 Filing....................................................................................................................342

Article 4. Scope of Service..................................................................................................342

4.1 Interconnection Product Options.........................................................................342

4.1.1 Energy Resource Interconnection Service...............................................342

4.1.1.1 The Product..............................................................................342

4.1.1.2 Transmission Delivery Service Implications...........................342

4.1.2 Network Resource Interconnection Service.............................................343

4.1.2.1 The Product..............................................................................343

4.1.2.2 Transmission Delivery Service Implications...........................344

4.2 Provision of Service.............................................................................................345

4.3 Performance Standards........................................................................................345

4.4 No Transmission Delivery Service......................................................................345

4.5 Interconnection Customer Provided Services......................................................346

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 323FERC Electric TariffFourth Revised Volume No. 1

Article 5. Interconnection Facilities Engineering, Procurement, and Construction............346

5.1 Options.................................................................................................................346

5.1.1 Standard Option.......................................................................................346

5.1.2 Alternate Option.......................................................................................346

5.1.3 Option to Build........................................................................................347

5.1.4 Negotiated Option....................................................................................347

5.2 General Conditions Applicable to Option to Build..............................................347

5.3 Liquidated Damages............................................................................................349

5.4 Power System Stabilizers.....................................................................................350

5.5 Equipment Procurement.......................................................................................350

5.6 Construction Commencement..............................................................................350

5.7 Work Progress......................................................................................................351

5.8 Information Exchange..........................................................................................351

5.9 Limited Operation................................................................................................351

5.10 Interconnection Customer’s Interconnection Facilities (‘ICIF’).........................351

5.10.1 Interconnection Customer’s Interconnection Facility Specifications......351

5.10.2 Transmission Provider’s Review.............................................................352

5.10.3 ICIF Construction....................................................................................352

5.11 Transmission Provider’s Interconnection Facilities Construction.......................352

5.12 Access Rights.......................................................................................................352

5.13 Lands of Other Property Owners.........................................................................353

5.14 Permits.................................................................................................................353

5.15 Early Construction of Base Case Facilities..........................................................353

5.16 Suspension...........................................................................................................354

5.17 Taxes....................................................................................................................354

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 324FERC Electric TariffFourth Revised Volume No. 1

5.17.1 Interconnection Customer Payments Not Taxable..................................354

5.17.2 Representative and Covenants.................................................................354

5.17.3 Indemnification for the Cost Consequences of Current Tax Liability Imposed Upon the Transmission Provider................................355

5.17.4 Tax Gross-Up Amount.............................................................................356

5.17.5 Private Letter Ruling or Change or Clarification of Law........................357

5.17.6 Subsequent Taxable Events.....................................................................357

5.17.7 Contents...................................................................................................357

5.17.8 Refund......................................................................................................358

5.17.9 Taxes Other Than Income Taxes.............................................................359

5.17.10 Transmission Owners Who Are Not Transmission Providers................360

5.18 Tax Status.............................................................................................................360

5.19 Modification.........................................................................................................360

5.19.1 General.....................................................................................................360

5.19.2 Standards..................................................................................................361

5.19.3 Modification Costs...................................................................................361

Article 6. Testing and Inspection.........................................................................................361

6.1 Pre-Commercial Operation Date Testing and Modifications..............................361

6.2 Post-Commercial Operation Date Testing and Modifications.............................361

6.3 Right to Observe Testing.....................................................................................362

6.4 Right to Inspect....................................................................................................362

Article 7. Metering...............................................................................................................362

7.1 General.................................................................................................................362

7.2 Check Meters.......................................................................................................362

7.3 Standards..............................................................................................................362

7.4 Testing of Metering Equipment...........................................................................363

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 325FERC Electric TariffFourth Revised Volume No. 1

7.5 Metering Data......................................................................................................363

Article 8. Communications..................................................................................................363

8.1 Interconnection Customer Obligations................................................................363

8.2 Remote Terminal Unit.........................................................................................364

8.3 No Annexation.....................................................................................................364

Article 9. Operations............................................................................................................364

9.1 General.................................................................................................................364

9.2 Control Area Notification....................................................................................364

9.3 Transmission Provider Obligations......................................................................364

9.4 Interconnection Customer Obligations................................................................365

9.5 Start-Up and Synchronization..............................................................................365

9.6 Reactive Power....................................................................................................365

9.6.1 Power Factor Design Criteria...................................................................365

9.6.2 Voltage Schedules....................................................................................365

9.6.2.1 Governors and Regulators............................................................366

9.6.3 Payment for Reactive Power....................................................................366

9.7 Outages and Interruptions....................................................................................366

9.7.1 Outages....................................................................................................366

9.7.1.1 Outage Authority and Coordination.......................................366

9.7.1.2 Outage Schedules...................................................................367

9.7.1.3 Outage Restoration.................................................................367

9.7.2 Interruption of Service.............................................................................367

9.7.3 Under-Frequency and Over Frequency Conditions.................................368

9.7.4 System Protection and Other Control Requirements...............................369

9.7.4.1 System Protection Facilities...................................................369

9.7.5 Requirements for Protection....................................................................370

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 326FERC Electric TariffFourth Revised Volume No. 1

9.7.6 Power Quality..........................................................................................370

9.8 Switching and Tagging Rules..............................................................................370

9.9 Use of Interconnection Facilities by Third Parties..............................................370

9.9.1 Purpose of Interconnection Facilities.......................................................370

9.9.2 Third Party Users.....................................................................................370

9.10 Disturbance Analysis Data Exchange..................................................................370

Article 10. Maintenance.........................................................................................................371

10.1 Transmission Provider Obligations......................................................................371

10.2 Interconnection Customer Obligations................................................................371

10.3 Coordination........................................................................................................371

10.4 Secondary Systems..............................................................................................371

10.5 Operating and Maintenance Expenses.................................................................372

Article 11. Performance Obligation.......................................................................................372

11.1 Interconnection Customer Interconnection Facilities..........................................372

11.2 Transmission Provider’s Interconnection Facilities.............................................372

11.3 Network Upgrades and Distribution Upgrades....................................................372

11.4 Transmission Credits...........................................................................................372

11.4.1 Repayment of Amounts Advanced for Network Upgrades.....................372

11.5 Provision of Security............................................................................................374

11.6 Interconnection Customer Compensation............................................................374

11.6.1 Interconnection Customer Compensation for Actions During Emergency Condition..............................................................................375

Article 12. Invoice..................................................................................................................375

12.1 General.................................................................................................................375

12.2 Final Invoice........................................................................................................375

12.3 Payment................................................................................................................375

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 327FERC Electric TariffFourth Revised Volume No. 1

12.4 Disputes................................................................................................................375

Article 13. Emergencies.........................................................................................................376

13.1 Definition.............................................................................................................376

13.2 Obligations...........................................................................................................376

13.3 Notice...................................................................................................................376

13.4 Immediate Action.................................................................................................376

13.5 Transmission Provider Authority.........................................................................377

13.5.1 General.....................................................................................................377

13.5.2 Reduction and Disconnection..................................................................378

13.6 Interconnection Customer Authority...................................................................379

13.7 Limited Liability..................................................................................................379

Article 14. Regulatory Requirements and Governing Law....................................................379

14.1 Regulatory Requirements.....................................................................................379

14.2 Governing Law....................................................................................................379

Article 15. Notices.................................................................................................................379

15.1 General.................................................................................................................379

15.2 Billings and Payments..........................................................................................380

15.3 Alternative Forms of Notice................................................................................380

15.4 Operations and Maintenance Notice....................................................................380

Article 16. Force Majeure......................................................................................................380

Article 17. Default..................................................................................................................381

17.1 Default..................................................................................................................381

17.1.1 General.....................................................................................................381

17.1.2 Right to Terminate...................................................................................381

Article 18. Indemnity, Consequential Damages and Insurances...........................................381

18.1 Indemnity.............................................................................................................381

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 328FERC Electric TariffFourth Revised Volume No. 1

18.1.1 Indemnified Person..................................................................................381

18.1.2 Indemnifying Party..................................................................................382

18.1.3 Indemnity Procedures..............................................................................382

18.2 Consequential Damages.......................................................................................382

18.3 Insurance..............................................................................................................383

Article 19. Assignment..........................................................................................................385

Article 20. Severability..........................................................................................................385

Article 21. Comparability......................................................................................................386

Article 22. Confidentiality.....................................................................................................386

22.1 Confidentiality.....................................................................................................386

22.1.1 Term.........................................................................................................386

22.1.2 Scope........................................................................................................386

22.1.3 Release of Confidential Information........................................................387

22.1.4 Rights.......................................................................................................387

22.1.5 No Warranties..........................................................................................387

22.1.6 Standard of Care......................................................................................387

22.1.7 Order of Disclosure..................................................................................387

22.1.8 Termination of Agreement.......................................................................388

22.1.9 Remedies..................................................................................................388

22.1.10 Disclosure to FERC, its Staff, or a State.................................................388

Article 23. Environmental Releases.......................................................................................389

Article 24. Information Requirements...................................................................................389

24.1 Information Acquisition.......................................................................................389

24.2 Information Submission by Transmission Provider............................................390

24.3 Updated Information Submission by Interconnection Customer.........................390

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 329FERC Electric TariffFourth Revised Volume No. 1

24.4 Information Supplementation..............................................................................390

Article 25. Information Access and Audit Rights..................................................................391

25.1 Information Access..............................................................................................391

25.2 Reporting of Non-Force Majeure Events.............................................................391

25.3 Audit Rights.........................................................................................................391

25.4 Audit Rights Periods............................................................................................392

25.4.1 Audit Rights Period for Construction-Related Accounts and Records....392

25.4.2 Audit Rights Period for All Other Accounts and Records.......................392

25.5 Audit Results........................................................................................................392

Article 26 Subcontractors......................................................................................................392

26.1 General.................................................................................................................392

26.2 Responsibility of Principal...................................................................................393

26.3 No Limitation by Insurance.................................................................................393

Article 27. Disputes................................................................................................................393

27.1 Submission...........................................................................................................393

27.2 External Arbitration Procedures..........................................................................393

27.3 Arbitration Decisions...........................................................................................394

27.4 Costs.....................................................................................................................394

Article 28. Representations, Warranties, and Covenants.......................................................394

28.1 General.................................................................................................................394

28.1.1 Good Standing.........................................................................................394

28.1.2 Authority..................................................................................................394

28.1.3 No Conflict...............................................................................................395

28.1.4 Consent and Approval..............................................................................395

Article 29. Joint Operating Committee..................................................................................395

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 330FERC Electric TariffFourth Revised Volume No. 1

Article 30. Miscellaneous......................................................................................................396

30.1 Binding Effect......................................................................................................396

30.2 Conflicts...............................................................................................................396

30.3 Rules of Interpretation.........................................................................................396

30.4 Entire Agreement.................................................................................................396

30.5 No Third Party Beneficiaries...............................................................................397

30.6 Waiver..................................................................................................................397

30.7 Headings..............................................................................................................397

30.8 Multiple Counterparts..........................................................................................397

30.9 Amendment..........................................................................................................397

30.10 Modification by the Parties..................................................................................397

30.11 Reservation of Rights...........................................................................................397

30.12 No Partnership.....................................................................................................398

Appendix A - Interconnection Facilities, Network Upgrades and Distribution Upgrades

Appendix B – Milestones

Appendix C – Interconnection Details

Appendix D – Security Arrangements Details

Appendix E – Commercial Operation Date

Appendix F – Addresses for Delivery of Notices and Billings

Appendix G – Requirements of Generators Relying on Newer Technologies

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 331FERC Electric TariffFourth Revised Volume No. 1

STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT

THIS STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT

("Agreement") is made and entered into this ____ day of ___________ 20__, by and between _______________________, a ____________________________ organized and existing under the laws of the State/Commonwealth of ________________ ("Interconnection Customer" with a Large Generating Facility), and __________________________________________, a ___________________________ organized and existing under the laws of the State/Commonwealth of ________________ ("Transmission Provider and/or Transmission Owner"). Interconnection Customer and Transmission Provider each may be referred to as a "Party" or collectively as the "Parties."

Recitals

WHEREAS, Transmission Provider operates the Transmission System; and

WHEREAS, Interconnection Customer intends to own, lease and/or control and operate the Generating Facility identified as a Large Generating Facility in Appendix C to this Agreement; and,

WHEREAS, Interconnection Customer and Transmission Provider have agreed to enter into this Agreement for the purpose of interconnecting the Large Generating Facility with the Transmission System;

NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein, it is agreed:

When used in this Standard Large Generator Interconnection Agreement, terms with initial capitalization that are not defined in Article 1 shall have the meanings specified in the Article in which they are used or the Open Access Transmission Tariff (OATT).

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 332FERC Electric TariffFourth Revised Volume No. 1

Article 1. Definitions

Adverse System Impact shall mean the negative effects due to technical or operational limits on conductors or equipment being exceeded that may compromise the safety and reliability of the electric system.

Affected System shall mean an electric system other than the Transmission Provider's Transmission System that may be affected by the proposed interconnection.

Affected System Operator shall mean the entity that operates an Affected System.

Affiliate shall mean, with respect to a corporation, partnership or other entity, each such other corporation, partnership or other entity that directly or indirectly, through one or more intermediaries, controls, is controlled by, or is under common control with, such corporation, partnership or other entity.

Ancillary Services shall mean those services that are necessary to support the transmission of capacity and energy from resources to loads while maintaining reliable operation of the Transmission Provider's Transmission System in accordance with Good Utility Practice.

Applicable Laws and Regulations shall mean all duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any Governmental Authority.

Applicable Reliability Council shall mean the reliability council applicable to the Transmission System to which the Generating Facility is directly interconnected.

Applicable Reliability Standards shall mean the requirements and guidelines of NERC, the Applicable Reliability Council, and the Control Area of the Transmission System to which the Generating Facility is directly interconnected.

Base Case shall mean the base case power flow, short circuit, and stability data bases used for the Interconnection Studies by the Transmission Provider or Interconnection Customer.

Breach shall mean the failure of a Party to perform or observe any material term or condition of the Standard Large Generator Interconnection Agreement.

Breaching Party shall mean a Party that is in Breach of the Standard Large Generator Interconnection Agreement.

Business Day shall mean Monday through Friday, excluding Federal Holidays.

Calendar Day shall mean any day including Saturday, Sunday or a Federal Holiday.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 333FERC Electric TariffFourth Revised Volume No. 1

Clustering shall mean the process whereby a group of Interconnection Requests is studied together, instead of serially, for the purpose of conducting the Interconnection System Impact Study.

Commercial Operation shall mean the status of a Generating Facility that has commenced generating electricity for sale, excluding electricity generated during Trial Operation.

Commercial Operation Date of a unit shall mean the date on which the Generating Facility commences Commercial Operation as agreed to by the Parties pursuant to Appendix E to the Standard Large Generator Interconnection Agreement.

Confidential Information shall mean any confidential, proprietary or trade secret information of a plan, specification, pattern, procedure, design, device, list, concept, policy or compilation relating to the present or planned business of a Party, which is designated as confidential by the Party supplying the information, whether conveyed orally, electronically, in writing, through inspection, or otherwise.

Control Area shall mean an electrical system or systems bounded by interconnection metering and telemetry, capable of controlling generation to maintain its interchange schedule with other Control Areas and contributing to frequency regulation of the interconnection. A Control Area must be certified by the Applicable Reliability Council.

Default shall mean the failure of a Breaching Party to cure its Breach in accordance with Article 17 of the Standard Large Generator Interconnection Agreement.

Dispute Resolution shall mean the procedure for resolution of a dispute between the Parties in which they will first attempt to resolve the dispute on an informal basis.

Distribution System shall mean the Transmission Provider's facilities and equipment used to transmit electricity to ultimate usage points such as homes and industries directly from nearby generators or from interchanges with higher voltage transmission networks which transport bulk power over longer distances. The voltage levels at which distribution systems operate differ among areas.

Distribution Upgrades shall mean the additions, modifications, and upgrades to the Transmission Provider's Distribution System at or beyond the Point of Interconnection to facilitate interconnection of the Generating Facility and render the transmission service necessary to effect Interconnection Customer's wholesale sale of electricity in interstate commerce. Distribution Upgrades do not include Interconnection Facilities.

Effective Date shall mean the date on which the Standard Large Generator Interconnection Agreement becomes effective upon execution by the Parties subject to acceptance by FERC, or if filed unexecuted, upon the date specified by FERC.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 334FERC Electric TariffFourth Revised Volume No. 1

Emergency Condition shall mean a condition or situation: (1) that in the judgment of the Party making the claim is imminently likely to endanger life or property; or (2) that, in the case of a Transmission Provider, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to Transmission Provider's Transmission System, Transmission Provider's Interconnection Facilities or the electric systems of others to which the Transmission Provider's Transmission System is directly connected; or (3) that, in the case of Interconnection Customer, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to, the Generating Facility or Interconnection Customer's Interconnection Facilities. System restoration and black start shall be considered Emergency Conditions; provided, that Interconnection Customer is not obligated by the Standard Large Generator Interconnection Agreement to possess black start capability.

Energy Resource Interconnection Service shall mean an Interconnection Service that allows the Interconnection Customer to connect its Generating Facility to the Transmission Provider's Transmission System to be eligible to deliver the Generating Facility's electric output using the existing firm or nonfirm capacity of the Transmission Provider's Transmission System on an as available basis. Energy Resource Interconnection Service in and of itself does not convey transmission service.

Engineering & Procurement (E&P) Agreement shall mean an agreement that authorizes the Transmission Provider to begin engineering and procurement of long lead-time items necessary for the establishment of the interconnection in order to advance the implementation of the Interconnection Request.

Environmental Law shall mean Applicable Laws or Regulations relating to pollution or protection of the environment or natural resources.

Federal Power Act shall mean the Federal Power Act, as amended, 16 U.S.C. §§ 791a et seq.

FERC shall mean the Federal Energy Regulatory Commission (Commission) or its successor.

Force Majeure shall mean any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, any order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities, or any other caused beyond a Party's control. A Force Majeure event does not include acts of negligence or intentional wrongdoing by the Party claiming Force Majeure.

Generating Facility shall mean Interconnection Customer's device for the production of electricity identified in the Interconnection Request, but shall not include the Interconnection Customer's Interconnection Facilities.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 335FERC Electric TariffFourth Revised Volume No. 1

Generating Facility Capacity shall mean the net capacity of the Generating Facility and the aggregate net capacity of the Generating Facility where it includes multiple energy production devices.

Good Utility Practice shall mean any of the practices, methods and acts engaged in or approved by a significant portion of the electric industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good Utility Practice is not intended to be limited to the optimum practice, method, or act to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region.

Governmental Authority shall mean any federal, state, local or other governmental regulatory or administrative agency, court, commission, department, board, or other governmental subdivision, legislature, rulemaking board, tribunal, or other governmental authority having jurisdiction over the Parties, their respective facilities, or the respective services they provide, and exercising or entitled to exercise any administrative, executive, police, or taxing authority or power; provided, however, that such term does not include Interconnection Customer, Transmission Provider, or any Affiliate thereof.

Hazardous Substances shall mean any chemicals, materials or substances defined as or included in the definition of "hazardous substances," "hazardous wastes," "hazardous materials," "hazardous constituents," "restricted hazardous materials," "extremely hazardous substances," "toxic substances," "radioactive substances," "contaminants," "pollutants," "toxic pollutants" or words of similar meaning and regulatory effect under any applicable Environmental Law, or any other chemical, material or substance, exposure to which is prohibited, limited or regulated by any applicable Environmental Law.

Initial Synchronization Date shall mean the date upon which the Generating Facility is initially synchronized and upon which Trial Operation begins.

In-Service Date shall mean the date upon which the Interconnection Customer reasonably expects it will be ready to begin use of the Transmission Provider's Interconnection Facilities to obtain back feed power.

Interconnection Customer shall mean any entity, including the Transmission Provider, Transmission Owner or any of the Affiliates or subsidiaries of either, that proposes to interconnect its Generating Facility with the Transmission Provider's Transmission System.

Interconnection Customer's Interconnection Facilities shall mean all facilities and equipment, as identified in Appendix A of the Standard Large Generator Interconnection Agreement, that are located between the Generating Facility and the Point of Change of Ownership, including any modification, addition, or upgrades to such facilities and equipment necessary to physically and electrically interconnect the Generating Facility to the Transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 336FERC Electric TariffFourth Revised Volume No. 1

Provider's Transmission System. Interconnection Customer's Interconnection Facilities are sole use facilities.

Interconnection Facilities shall mean the Transmission Provider's Interconnection Facilities and the Interconnection Customer's Interconnection Facilities. Collectively, Interconnection Facilities include all facilities and equipment between the Generating Facility and the Point of Interconnection, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the Generating Facility to the Transmission Provider's Transmission System. Interconnection Facilities are sole use facilities and shall not include Distribution Upgrades, Stand Alone Network Upgrades or Network Upgrades.

Interconnection Facilities Study shall mean a study conducted by the Transmission Provider or a third party consultant for the Interconnection Customer to determine a list of facilities (including Transmission Provider's Interconnection Facilities and Network Upgrades as identified in the Interconnection System Impact Study), the cost of those facilities, and the time required to interconnect the Generating Facility with the Transmission Provider's Transmission System. The scope of the study is defined in Section 8 of the Standard Large Generator Interconnection Procedures.

Interconnection Facilities Study Agreement shall mean the form of agreement contained in Appendix 4 of the Standard Large Generator Interconnection Procedures for conducting the Interconnection Facilities Study.

Interconnection Feasibility Study shall mean a preliminary evaluation of the system impact and cost of interconnecting the Generating Facility to the Transmission Provider's Transmission System, the scope of which is described in Section 6 of the Standard Large Generator Interconnection Procedures.

Interconnection Feasibility Study Agreement shall mean the form of agreement contained in Appendix 2 of the Standard Large Generator Interconnection Procedures for conducting the Interconnection Feasibility Study.

Interconnection Request shall mean an Interconnection Customer's request, in the form of Appendix 1 to the Standard Large Generator Interconnection Procedures, in accordance with the Tariff, to interconnect a new Generating Facility, or to increase the capacity of, or make a Material Modification to the operating characteristics of, an existing Generating Facility that is interconnected with the Transmission Provider's Transmission System.

Interconnection Service shall mean the service provided by the Transmission Provider associated with interconnecting the Interconnection Customer's Generating Facility to the Transmission Provider's Transmission System and enabling it to receive electric energy and capacity from the Generating Facility at the Point of Interconnection, pursuant to the terms of the Standard Large Generator Interconnection Agreement and, if applicable, the Transmission Provider's Tariff.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 337FERC Electric TariffFourth Revised Volume No. 1

Interconnection Study shall mean any of the following studies: the Interconnection Feasibility Study, the Interconnection System Impact Study, and the Interconnection Facilities Study described in the Standard Large Generator Interconnection Procedures.

Interconnection System Impact Study shall mean an engineering study that evaluates the impact of the proposed interconnection on the safety and reliability of Transmission Provider's Transmission System and, if applicable, an Affected System. The study shall identify and detail the system impacts that would result if the Generating Facility were interconnected without project modifications or system modifications, focusing on the Adverse System Impacts identified in the Interconnection Feasibility Study, or to study potential impacts, including but not limited to those identified in the Scoping Meeting as described in the Standard Large Generator Interconnection Procedures.

Interconnection System Impact Study Agreement shall mean the form of agreement contained in Appendix 3 of the Standard Large Generator Interconnection Procedures for conducting the Interconnection System Impact Study.

IRS shall mean the Internal Revenue Service.

Joint Operating Committee shall be a group made up of representatives from Interconnection Customers and the Transmission Provider to coordinate operating and technical considerations of Interconnection Service.

Large Generating Facility shall mean a Generating Facility having a Generating Facility Capacity of more than 20 MW.

Loss shall mean any and all losses relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other Party's performance, or non-performance of its obligations under the Standard Large Generator Interconnection Agreement on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnifying Party.

Material Modification shall mean those modifications that have a material impact on the cost or timing of any Interconnection Request with a later queue priority date.

Metering Equipment shall mean all metering equipment installed or to be installed at the Generating Facility pursuant to the Standard Large Generator Interconnection Agreement at the metering points, including but not limited to instrument transformers, MWh-meters, data acquisition equipment, transducers, remote terminal unit, communications equipment, phone lines, and fiber optics.

NERC shall mean the North American Electric Reliability Council or its successor organization.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 338FERC Electric TariffFourth Revised Volume No. 1

Network Resource shall mean any designated generating resource owned, purchased, or leased by a Network Customer under the Network Integration Transmission Service Tariff. Network Resources do not include any resource, or any portion thereof, that is committed for sale to third parties or otherwise cannot be called upon to meet the Network Customer's Network Load on a non-interruptible basis.

Network Resource Interconnection Service shall mean an Interconnection Service that allows the Interconnection Customer to integrate its Large Generating Facility with the Transmission Provider's Transmission System (1) in a manner comparable to that in which the Transmission Provider integrates its generating facilities to serve native load customers; or (2) in an RTO or ISO with market based congestion management, in the same manner as all other Network Resources. Network Resource Interconnection Service in and of itself does not convey transmission service.

Network Upgrades shall mean the additions, modifications, and upgrades to the Transmission Provider's Transmission System required at or beyond the point at which the Interconnection Facilities connect to the Transmission Provider's Transmission System to accommodate the interconnection of the Large Generating Facility to the Transmission Provider's Transmission System.

Notice of Dispute shall mean a written notice of a dispute or claim that arises out of or in connection with the Standard Large Generator Interconnection Agreement or its performance.

Optional Interconnection Study shall mean a sensitivity analysis based on assumptions specified by the Interconnection Customer in the Optional Interconnection Study Agreement.

Optional Interconnection Study Agreement shall mean the form of agreement contained in Appendix 5 of the Standard Large Generator Interconnection Procedures for conducting the Optional Interconnection Study.

Party or Parties shall mean Transmission Provider, Transmission Owner, Interconnection Customer or any combination of the above.

Point of Change of Ownership shall mean the point, as set forth in Appendix A to the Standard Large Generator Interconnection Agreement, where the Interconnection Customer's Interconnection Facilities connect to the Transmission Provider's Interconnection Facilities.

Point of Interconnection shall mean the point, as set forth in Appendix A to the Standard Large Generator Interconnection Agreement, where the Interconnection Facilities connect to the Transmission Provider's Transmission System.

Queue Position shall mean the order of a valid Interconnection Request, relative to all other pending valid Interconnection Requests, that is established based upon the date and time of receipt of the valid Interconnection Request by the Transmission Provider.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 339FERC Electric TariffFourth Revised Volume No. 1

Reasonable Efforts shall mean, with respect to an action required to be attempted or taken by a Party under the Standard Large Generator Interconnection Agreement, efforts that are timely and consistent with Good Utility Practice and are otherwise substantially equivalent to those a Party would use to protect its own interests.

Scoping Meeting shall mean the meeting between representatives of the Interconnection Customer and Transmission Provider conducted for the purpose of discussing alternative interconnection options, to exchange information including any transmission data and earlier study evaluations that would be reasonably expected to impact such interconnection options, to analyze such information, and to determine the potential feasible Points of Interconnection.

Site Control shall mean documentation reasonably demonstrating: (1) ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the Generating Facility; (2) an option to purchase or acquire a leasehold site for such purpose; or (3) an exclusivity or other business relationship between Interconnection Customer and the entity having the right to sell, lease or grant Interconnection Customer the right to possess or occupy a site for such purpose.

Small Generating Facility shall mean a Generating Facility that has a Generating Facility Capacity of no more than 20 MW.

Stand Alone Network Upgrades shall mean Network Upgrades that an Interconnection Customer may construct without affecting day-to-day operations of the Transmission System during their construction. Both the Transmission Provider and the Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify them in Appendix A to the Standard Large Generator Interconnection Agreement.

Standard Large Generator Interconnection Agreement (LGIA) shall mean the form of interconnection agreement applicable to an Interconnection Request pertaining to a Large Generating Facility that is included in the Transmission Provider's Tariff.

Standard Large Generator Interconnection Procedures (LGIP) shall mean the interconnection procedures applicable to an Interconnection Request pertaining to a Large Generating Facility that are included in the Transmission Provider's Tariff.

System Protection Facilities shall mean the equipment, including necessary protection signal communications equipment, required to protect (1) the Transmission Provider's Transmission System from faults or other electrical disturbances occurring at the Generating Facility and (2) the Generating Facility from faults or other electrical system disturbances occurring on the Transmission Provider's Transmission System or on other delivery systems or other generating systems to which the Transmission Provider's Transmission System is directly connected.

Tariff shall mean the Transmission Provider's Tariff through which open access transmission service and Interconnection Service are offered, as filed with FERC, and as amended or supplemented from time to time, or any successor tariff.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 340FERC Electric TariffFourth Revised Volume No. 1

Transmission Owner shall mean an entity that owns, leases or otherwise possesses an interest in the portion of the Transmission System at the Point of Interconnection and may be a Party to the Standard Large Generator Interconnection Agreement to the extent necessary.

Transmission Provider shall mean the public utility (or its designated agent) that owns, controls, or operates transmission or distribution facilities used for the transmission of electricity in interstate commerce and provides transmission service under the Tariff. The term Transmission Provider should be read to include the Transmission Owner when the Transmission Owner is separate from the Transmission Provider.

Transmission Provider's Interconnection Facilities shall mean all facilities and equipment owned, controlled or operated by the Transmission Provider from the Point of Change of Ownership to the Point of Interconnection as identified in Appendix A to the Standard Large Generator Interconnection Agreement, including any modifications, additions or upgrades to such facilities and equipment. Transmission Provider's Interconnection Facilities are sole use facilities and shall not include Distribution Upgrades, Stand Alone Network Upgrades or Network Upgrades.

Transmission System shall mean the facilities owned, controlled or operated by the Transmission Provider or Transmission Owner that are used to provide transmission service under the Tariff.

Trial Operation shall mean the period during which Interconnection Customer is engaged in on-site test operations and commissioning of the Generating Facility prior to Commercial Operation.

Article 2. Effective Date, Term, and Termination

2.1 Effective Date. This LGIA shall become effective upon execution by the Parties subject to acceptance by FERC (if applicable), or if filed unexecuted, upon the date specified by FERC. Transmission Provider shall promptly file this LGIA with FERC upon execution in accordance with Article 3.1, if required.

2.2 Term of Agreement. Subject to the provisions of Article 2.3, this LGIA shall remain in effect for a period of ten (10) years from the Effective Date or such other longer period as Interconnection Customer may request (Term to be specified in individual agreements) and shall be automatically renewed for each successive one-year period thereafter.

2.3 Termination Procedures.

2.3.1 Written Notice. This LGIA may be terminated by Interconnection Customer after giving Transmission Provider ninety (90) Calendar Days advance written notice, or by Transmission Provider notifying FERC after the Generating Facility permanently ceases Commercial Operation.

2.3.2 Default. Either Party may terminate this LGIA in accordance with Article 17.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 341FERC Electric TariffFourth Revised Volume No. 1

2.3.3 Notwithstanding Articles 2.3.1 and 2.3.2, no termination shall become effective until the Parties have complied with all Applicable Laws and Regulations applicable to such termination, including the filing with FERC of a notice of termination of this LGIA, which notice has been accepted for filing by FERC.

2.4 Termination Costs. If a Party elects to terminate this Agreement pursuant to Article 2.3 above, each Party shall pay all costs incurred (including any cancellation costs relating to orders or contracts for Interconnection Facilities and equipment) or charges assessed by the other Party, as of the date of the other Party's receipt of such notice of termination, that are the responsibility of the Terminating Party under this LGIA. In the event of termination by a Party, the Parties shall use commercially Reasonable Efforts to mitigate the costs, damages and charges arising as a consequence of termination. Upon termination of this LGIA, unless otherwise ordered or approved by FERC:

2.4.1 With respect to any portion of Transmission Provider's Interconnection Facilities that have not yet been constructed or installed, Transmission Provider shall to the extent possible and with Interconnection Customer's authorization cancel any pending orders of, or return, any materials or equipment for, or contracts for construction of, such facilities; provided that in the event Interconnection Customer elects not to authorize such cancellation, Interconnection Customer shall assume all payment obligations with respect to such materials, equipment, and contracts, and Transmission Provider shall deliver such material and equipment, and, if necessary, assign such contracts, to Interconnection Customer as soon as practicable, at Interconnection Customer's expense. To the extent that Interconnection Customer has already paid Transmission Provider for any or all such costs of materials or equipment not taken by Interconnection Customer, Transmission Provider shall promptly refund such amounts to Interconnection Customer, less any costs, including penalties incurred by Transmission Provider to cancel any pending orders of or return such materials, equipment, or contracts.

If an Interconnection Customer terminates this LGIA, it shall be responsible for all costs incurred in association with that Interconnection Customer's interconnection, including any cancellation costs relating to orders or contracts for Interconnection Facilities and equipment, and other expenses including any Network Upgrades for which Transmission Provider has incurred expenses and has not been reimbursed by Interconnection Customer.

2.4.2 Transmission Provider may, at its option, retain any portion of such materials, equipment, or facilities that Interconnection Customer chooses not to accept delivery of, in which case Transmission Provider shall be responsible for all costs associated with procuring such materials, equipment, or facilities.

2.4.3 With respect to any portion of the Interconnection Facilities, and any other facilities already installed or constructed pursuant to the terms of this LGIA, Interconnection Customer shall be responsible for all costs associated with the

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 342FERC Electric TariffFourth Revised Volume No. 1

removal, relocation or other disposition or retirement of such materials, equipment, or facilities.

2.5 Disconnection. Upon termination of this LGIA, the Parties will take all appropriate steps to disconnect the Large Generating Facility from the Transmission System. All costs required to effectuate such disconnection shall be borne by the terminating Party, unless such termination resulted from the non-terminating Party's Default of this LGIA or such non-terminating Party otherwise is responsible for these costs under this LGIA.

2.6 Survival. This LGIA shall continue in effect after termination to the extent necessary to provide for final billings and payments and for costs incurred hereunder, including billings and payments pursuant to this LGIA; to permit the determination and enforcement of liability and indemnification obligations arising from acts or events that occurred while this LGIA was in effect; and to permit each Party to have access to the lands of the other Party pursuant to this LGIA or other applicable agreements, to disconnect, remove or salvage its own facilities and equipment.

Article 3. Regulatory Filings

3.1 Filing. Transmission Provider shall file this LGIA (and any amendment hereto) with the appropriate Governmental Authority, if required. Interconnection Customer may request that any information so provided be subject to the confidentiality provisions of Article 22. If Interconnection Customer has executed this LGIA, or any amendment thereto, Interconnection Customer shall reasonably cooperate with Transmission Provider with respect to such filing and to provide any information reasonably requested by Transmission Provider needed to comply with applicable regulatory requirements.

Article 4. Scope of Service

4.1 Interconnection Product Options. Interconnection Customer has selected the following (checked) type of Interconnection Service:

4.1.1 Energy Resource Interconnection Service.

4.1.1.1 The Product. Energy Resource Interconnection Service allows Interconnection Customer to connect the Large Generating Facility to the Transmission System and be eligible to deliver the Large Generating Facility's output using the existing firm or non-firm capacity of the Transmission System on an "as available" basis. To the extent Interconnection Customer wants to receive Energy Resource Interconnection Service, Transmission Provider shall construct facilities identified in Attachment A.

4.1.1.2 Transmission Delivery Service Implications. Under Energy Resource Interconnection Service, Interconnection Customer will be eligible to inject power from the Large

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 343FERC Electric TariffFourth Revised Volume No. 1

Generating Facility into and deliver power across the interconnecting Transmission Provider's Transmission System on an "as available" basis up to the amount of MWs identified in the applicable stability and steady state studies to the extent the upgrades initially required to qualify for Energy Resource Interconnection Service have been constructed. Where eligible to do so (e.g., PJM, ISO-NE, NYISO), Interconnection Customer may place a bid to sell into the market up to the maximum identified Large Generating Facility output, subject to any conditions specified in the interconnection service approval, and the Large Generating Facility will be dispatched to the extent Interconnection Customer's bid clears. In all other instances, no transmission delivery service from the Large Generating Facility is assured, but Interconnection Customer may obtain Point-to-Point Transmission Service, Network Integration Transmission Service, or be used for secondary network transmission service, pursuant to Transmission Provider's Tariff, up to the maximum output identified in the stability and steady state studies. In those instances, in order for Interconnection Customer to obtain the right to deliver or inject energy beyond the Large Generating Facility Point of Interconnection or to improve its ability to do so, transmission delivery service must be obtained pursuant to the provisions of Transmission Provider's Tariff. The Interconnection Customer's ability to inject its Large Generating Facility output beyond the Point of Interconnection, therefore, will depend on the existing capacity of Transmission Provider's Transmission System at such time as a transmission service request is made that would accommodate such delivery. The provision of firm Point-to-Point Transmission Service or Network Integration Transmission Service may require the construction of additional Network Upgrades.

4.1.2 Network Resource Interconnection Service.

4.1.2.1 The Product. Transmission Provider must conduct the necessary studies and construct the Network Upgrades needed to integrate the Large Generating Facility (1) in a manner comparable to that in which Transmission Provider integrates its generating facilities to serve native load customers; or (2) in an ISO or RTO with market based congestion management, in the same manner as all Network Resources. To the extent Interconnection Customer wants to receive Network Resource Interconnection Service, Transmission Provider shall construct the facilities identified in Attachment A to this LGIA.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 344FERC Electric TariffFourth Revised Volume No. 1

4.1.2.2 Transmission Delivery Service Implications. Network Resource Interconnection Service allows Interconnection Customer's Large Generating Facility to be designated by any Network Customer under the Tariff on Transmission Provider's Transmission System as a Network Resource, up to the Large Generating Facility's full output, on the same basis as existing Network Resources interconnected to Transmission Provider's Transmission System, and to be studied as a Network Resource on the assumption that such a designation will occur. Although Network Resource Interconnection Service does not convey a reservation of transmission service, any Network Customer under the Tariff can utilize its network service under the Tariff to obtain delivery of energy from the interconnected Interconnection Customer's Large Generating Facility in the same manner as it accesses other Network Resources. A Large Generating Facility receiving Network Resource Interconnection Service may also be used to provide Ancillary Services after technical studies and/or periodic analyses are performed with respect to the Large Generating Facility's ability to provide any applicable Ancillary Services, provided that such studies and analyses have been or would be required in connection with the provision of such Ancillary Services by any existing Network Resource. However, if an Interconnection Customer's Large Generating Facility has not been designated as a Network Resource by any load, it cannot be required to provide Ancillary Services except to the extent such requirements extend to all generating facilities that are similarly situated. The provision of Network Integration Transmission Service or firm Point-to-Point Transmission Service may require additional studies and the construction of additional upgrades. Because such studies and upgrades would be associated with a request for delivery service under the Tariff, cost responsibility for the studies and upgrades would be in accordance with FERC's policy for pricing transmission delivery services.

Network Resource Interconnection Service does not necessarily provide Interconnection Customer with the capability to physically deliver the output of its Large Generating Facility to any particular load on Transmission Provider's Transmission System without incurring congestion costs. In the event of transmission constraints on Transmission Provider's Transmission System, Interconnection Customer's Large Generating Facility shall be subject to the applicable congestion management procedures in Transmission Provider's Transmission System in the same manner as all other Network Resources.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 345FERC Electric TariffFourth Revised Volume No. 1

There is no requirement either at the time of study or interconnection, or at any point in the future, that Interconnection Customer's Large Generating Facility be designated as a Network Resource by a Network Service Customer under the Tariff or that Interconnection Customer identify a specific buyer (or sink). To the extent a Network Customer does designate the Large Generating Facility as a Network Resource, it must do so pursuant to Transmission Provider's Tariff.

Once an Interconnection Customer satisfies the requirements for obtaining Network Resource Interconnection Service, any future transmission service request for delivery from the Large Generating Facility within Transmission Provider's Transmission System of any amount of capacity and/or energy, up to the amount initially studied, will not require that any additional studies be performed or that any further upgrades associated with such Large Generating Facility be undertaken, regardless of whether or not such Large Generating Facility is ever designated by a Network Customer as a Network Resource and regardless of changes in ownership of the Large Generating Facility. However, the reduction or elimination of congestion or redispatch costs may require additional studies and the construction of additional upgrades.

To the extent Interconnection Customer enters into an arrangement for long term transmission service for deliveries from the Large Generating Facility outside Transmission Provider's Transmission System, such request may require additional studies and upgrades in order for Transmission Provider to grant such request.

4.2 Provision of Service. Transmission Provider shall provide Interconnection Service for the Large Generating Facility at the Point of Interconnection.

4.3 Performance Standards. Each Party shall perform all of its obligations under this LGIA in accordance with Applicable Laws and Regulations, Applicable Reliability Standards, and Good Utility Practice, and to the extent a Party is required or prevented or limited in taking any action by such regulations and standards, such Party shall not be deemed to be in Breach of this LGIA for its compliance therewith. If such Party is a Transmission Provider or Transmission Owner, then that Party shall amend the LGIA and submit the amendment to FERC for approval.

4.4 No Transmission Delivery Service. The execution of this LGIA does not constitute a request for, nor the provision of, any transmission delivery service under Transmission Provider's Tariff, and does not convey any right to deliver electricity to any specific customer or Point of Delivery.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 346FERC Electric TariffFourth Revised Volume No. 1

4.5 Interconnection Customer Provided Services. The services provided by Interconnection Customer under this LGIA are set forth in Article 9.6 and Article 13.5.1. Interconnection Customer shall be paid for such services in accordance with Article 11.6.

Article 5. Interconnection Facilities Engineering, Procurement, and Construction

5.1 Options. Unless otherwise mutually agreed to between the Parties, Interconnection Customer shall select the In-Service Date, Initial Synchronization Date, and Commercial Operation Date; and either Standard Option or Alternate Option set forth below for completion of Transmission Provider's Interconnection Facilities and Network Upgrades as set forth in Appendix A, Interconnection Facilities and Network Upgrades, and such dates and selected option shall be set forth in Appendix B, Milestones.

5.1.1 Standard Option. Transmission Provider shall design, procure, and construct Transmission Provider's Interconnection Facilities and Network Upgrades, using Reasonable Efforts to complete Transmission Provider's Interconnection Facilities and Network Upgrades by the dates set forth in Appendix B, Milestones. Transmission Provider shall not be required to undertake any action which is inconsistent with its standard safety practices, its material and equipment specifications, its design criteria and construction procedures, its labor agreements, and Applicable Laws and Regulations. In the event Transmission Provider reasonably expects that it will not be able to complete Transmission Provider's Interconnection Facilities and Network Upgrades by the specified dates, Transmission Provider shall promptly provide written notice to Interconnection Customer and shall undertake Reasonable Efforts to meet the earliest dates thereafter.

5.1.2 Alternate Option. If the dates designated by Interconnection Customer are acceptable to Transmission Provider, Transmission Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of Transmission Provider's Interconnection Facilities by the designated dates.

If Transmission Provider subsequently fails to complete Transmission Provider's Interconnection Facilities by the In-Service Date, to the extent necessary to provide back feed power; or fails to complete Network Upgrades by the Initial Synchronization Date to the extent necessary to allow for Trial Operation at full power output, unless other arrangements are made by the Parties for such Trial Operation; or fails to complete the Network Upgrades by the Commercial Operation Date, as such dates are reflected in Appendix B, Milestones; Transmission Provider shall pay Interconnection Customer liquidated damages in

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 347FERC Electric TariffFourth Revised Volume No. 1

accordance with Article 5.3, Liquidated Damages, provided, however, the dates designated by Interconnection Customer shall be extended day for day for each day that the applicable RTO or ISO refuses to grant clearances to install equipment.

5.1.3 Option to Build. If the dates designated by Interconnection Customer are not acceptable to Transmission Provider, Transmission Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.2. Transmission Provider and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option.

5.1.4 Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Provider is responsible for the design, procurement and construction of Transmission Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Provider shall assume responsibility for the design, procurement and construction of Transmission Provider's Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.

5.2 General Conditions Applicable to Option to Build. If Interconnection Customer assumes responsibility for the design, procurement and construction of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades,

(1) Interconnection Customer shall engineer, procure equipment, and construct Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades (or portions thereof) using Good Utility Practice and using standards and specifications provided in advance by Transmission Provider;

(2) Interconnection Customer's engineering, procurement and construction of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades shall comply with all requirements of law to which Transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 348FERC Electric TariffFourth Revised Volume No. 1

Provider would be subject in the engineering, procurement or construction of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades;

(3) Transmission Provider shall review and approve the engineering design, equipment acceptance tests, and the construction of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades;

(4) prior to commencement of construction, Interconnection Customer shall provide to Transmission Provider a schedule for construction of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades, and shall promptly respond to requests for information from Transmission Provider;

(5) at any time during construction, Transmission Provider shall have the right to gain unrestricted access to Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades and to conduct inspections of the same;

(6) at any time during construction, should any phase of the engineering, equipment procurement, or construction of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades not meet the standards and specifications provided by Transmission Provider, Interconnection Customer shall be obligated to remedy deficiencies in that portion of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades;

(7) Interconnection Customer shall indemnify Transmission Provider for claims arising from Interconnection Customer's construction of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades under the terms and procedures applicable to Article 18.1 Indemnity;

(8) Interconnection Customer shall transfer control of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades to Transmission Provider;

(9) Unless Parties otherwise agree, Interconnection Customer shall transfer ownership of Transmission Provider's Interconnection Facilities and Stand-Alone Network Upgrades to Transmission Provider;

(10) Transmission Provider shall approve and accept for operation and maintenance Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades to the extent engineered, procured, and constructed in accordance with this Article 5.2; and

(11) Interconnection Customer shall deliver to Transmission Provider "as-built" drawings, information, and any other documents that are reasonably required by Transmission Provider to assure that the Interconnection Facilities and Stand-

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 349FERC Electric TariffFourth Revised Volume No. 1

Alone Network Upgrades are built to the standards and specifications required by Transmission Provider.

5.3 Liquidated Damages. The actual damages to Interconnection Customer, in the event Transmission Provider's Interconnection Facilities or Network Upgrades are not completed by the dates designated by Interconnection Customer and accepted by Transmission Provider pursuant to subparagraphs 5.1.2 or 5.1.4, above, may include Interconnection Customer's fixed operation and maintenance costs and lost opportunity costs. Such actual damages are uncertain and impossible to determine at this time. Because of such uncertainty, any liquidated damages paid by Transmission Provider to Interconnection Customer in the event that Transmission Provider does not complete any portion of Transmission Provider's Interconnection Facilities or Network Upgrades by the applicable dates, shall be an amount equal to ½ of 1 percent per day of the actual cost of Transmission Provider's Interconnection Facilities and Network Upgrades, in the aggregate, for which Transmission Provider has assumed responsibility to design, procure and construct.

However, in no event shall the total liquidated damages exceed 20 percent of the actual cost of Transmission Provider's Interconnection Facilities and Network Upgrades for which Transmission Provider has assumed responsibility to design, procure, and construct. The foregoing payments will be made by Transmission Provider to Interconnection Customer as just compensation for the damages caused to Interconnection Customer, which actual damages are uncertain and impossible to determine at this time, and as reasonable liquidated damages, but not as a penalty or a method to secure performance of this LGIA. Liquidated damages, when the Parties agree to them, are the exclusive remedy for the Transmission Provider's failure to meet its schedule.

No liquidated damages shall be paid to Interconnection Customer if: (1) Interconnection Customer is not ready to commence use of Transmission Provider's Interconnection Facilities or Network Upgrades to take the delivery of power for the Large Generating Facility's Trial Operation or to export power from the Large Generating Facility on the specified dates, unless Interconnection Customer would have been able to commence use of Transmission Provider's Interconnection Facilities or Network Upgrades to take the delivery of power for Large Generating Facility's Trial Operation or to export power from the Large Generating Facility, but for Transmission Provider's delay; (2) Transmission Provider's failure to meet the specified dates is the result of the action or inaction of Interconnection Customer or any other Interconnection Customer who has entered into an LGIA with Transmission Provider or any cause beyond Transmission Provider's reasonable control or reasonable ability to cure; (3) the interconnection Customer has assumed responsibility for the design, procurement and construction of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades; or (4) the Parties have otherwise agreed.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 350FERC Electric TariffFourth Revised Volume No. 1

5.4 Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider reserves the right to reasonably establish minimum acceptable settings for any installed Power System Stabilizers, subject to the design and operating limitations of the Large Generating Facility. If the Large Generating Facility's Power System Stabilizers are removed from service or not capable of automatic operation, Interconnection Customer shall immediately notify Transmission Provider's system operator, or its designated representative. The requirements of this paragraph shall not apply to wind generators.

5.5 Equipment Procurement. If responsibility for construction of Transmission Provider's Interconnection Facilities or Network Upgrades is to be borne by Transmission Provider, then Transmission Provider shall commence design of Transmission Provider's Interconnection Facilities or Network Upgrades and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

5.5.1 Transmission Provider has completed the Facilities Study pursuant to the Facilities Study Agreement;

5.5.2 Transmission Provider has received written authorization to proceed with design and procurement from Interconnection Customer by the date specified in Appendix B, Milestones; and

5.5.3 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.5 by the dates specified in Appendix B, Milestones.

5.6 Construction Commencement. Transmission Provider shall commence construction of Transmission Provider's Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:

5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;

5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission Provider's Interconnection Facilities and Network Upgrades;

5.6.3 Transmission Provider has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and

5.6.4 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.5 by the dates specified in Appendix B, Milestones.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 351FERC Electric TariffFourth Revised Volume No. 1

5.7 Work Progress. The Parties will keep each other advised periodically as to the progress of their respective design, procurement and construction efforts. Either Party may, at any time, request a progress report from the other Party. If, at any time, Interconnection Customer determines that the completion of Transmission Provider's Interconnection Facilities will not be required until after the specified In-Service Date, Interconnection Customer will provide written notice to Transmission Provider of such later date upon which the completion of Transmission Provider's Interconnection Facilities will be required.

5.8 Information Exchange. As soon as reasonably practicable after the Effective Date, the Parties shall exchange information regarding the design and compatibility of the Parties' Interconnection Facilities and compatibility of the Interconnection Facilities with Transmission Provider's Transmission System, and shall work diligently and in good faith to make any necessary design changes.

5.9 Limited Operation. If any of Transmission Provider's Interconnection Facilities or Network Upgrades are not reasonably expected to be completed prior to the Commercial Operation Date of the Large Generating Facility, Transmission Provider shall, upon the request and at the expense of Interconnection Customer, perform operating studies on a timely basis to determine the extent to which the Large Generating Facility and Interconnection Customer's Interconnection Facilities may operate prior to the completion of Transmission Provider's Interconnection Facilities or Network Upgrades consistent with Applicable Laws and Regulations, Applicable Reliability Standards, Good Utility Practice, and this LGIA. Transmission Provider shall permit Interconnection Customer to operate the Large Generating Facility and Interconnection Customer's Interconnection Facilities in accordance with the results of such studies.

5.10 Interconnection Customer's Interconnection Facilities ('ICIF'). Interconnection Customer shall, at its expense, design, procure, construct, own and install the ICIF, as set forth in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades.

5.10.1 Interconnection Customer's Interconnection Facility Specifications. Interconnection Customer shall submit initial specifications for the ICIF, including System Protection Facilities, to Transmission Provider at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Provider shall review such specifications to ensure that the ICIF are compatible with the technical specifications, operational control, and safety requirements of Transmission Provider and comment on such specifications within thirty (30) Calendar Days of Interconnection Customer's submission. All specifications provided hereunder shall be deemed confidential.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 352FERC Electric TariffFourth Revised Volume No. 1

5.10.2 Transmission Provider's Review. Transmission Provider's review of Interconnection Customer's final specifications shall not be construed as confirming, endorsing, or providing a warranty as to the design, fitness, safety, durability or reliability of the Large Generating Facility, or the ICIF. Interconnection Customer shall make such changes to the ICIF as may reasonably be required by Transmission Provider, in accordance with Good Utility Practice, to ensure that the ICIF are compatible with the technical specifications, operational control, and safety requirements of Transmission Provider.

5.10.3 ICIF Construction. The ICIF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Parties agree on another mutually acceptable deadline, Interconnection Customer shall deliver to Transmission Provider "as-built" drawings, information and documents for the ICIF, such as: a one-line diagram, a site plan showing the Large Generating Facility and the ICIF, plan and elevation drawings showing the layout of the ICIF, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with Interconnection Customer's step-up transformers, the facilities connecting the Large Generating Facility to the step-up transformers and the ICIF, and the impedances (determined by factory tests) for the associated step-up transformers and the Large Generating Facility. The Interconnection Customer shall provide Transmission Provider specifications for the excitation system, automatic voltage regulator, Large Generating Facility control and protection settings, transformer tap settings, and communications, if applicable.

5.11 Transmission Provider's Interconnection Facilities Construction. Transmission Provider's Interconnection Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Parties agree on another mutually acceptable deadline, Transmission Provider shall deliver to Interconnection Customer the following "as-built" drawings, information and documents for Transmission Provider's Interconnection Facilities [include appropriate drawings and relay diagrams].

Transmission Provider will obtain control of Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades upon completion of such facilities.

5.12 Access Rights. Upon reasonable notice and supervision by a Party, and subject to any required or necessary regulatory approvals, a Party ("Granting Party") shall furnish at no cost to the other Party ("Access Party") any

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 353FERC Electric TariffFourth Revised Volume No. 1

rights of use, licenses, rights of way and easements with respect to lands owned or controlled by the Granting Party, its agents (if allowed under the applicable agency agreement), or any Affiliate, that are necessary to enable the Access Party to obtain ingress and egress to construct, operate, maintain, repair, test (or witness testing), inspect, replace or remove facilities and equipment to: (i) interconnect the Large Generating Facility with the Transmission System; (ii) operate and maintain the Large Generating Facility, the Interconnection Facilities and the Transmission System; and (iii) disconnect or remove the Access Party's facilities and equipment upon termination of this LGIA. In exercising such licenses, rights of way and easements, the Access Party shall not unreasonably disrupt or interfere with normal operation of the Granting Party's business and shall adhere to the safety rules and procedures established in advance, as may be changed from time to time, by the Granting Party and provided to the Access Party.

5.13 Lands of Other Property Owners. If any part of Transmission Provider or Transmission Owner's Interconnection Facilities and/or Network Upgrades is to be installed on property owned by persons other than Interconnection Customer or Transmission Provider or Transmission Owner, Transmission Provider or Transmission Owner shall at Interconnection Customer's expense use efforts, similar in nature and extent to those that it typically undertakes on its own behalf or on behalf of its Affiliates, including use of its eminent domain authority, and to the extent consistent with state law, to procure from such persons any rights of use, licenses, rights of way and easements that are necessary to construct, operate, maintain, test, inspect, replace or remove Transmission Provider or Transmission Owner's Interconnection Facilities and/or Network Upgrades upon such property.

5.14 Permits. The LGIA shall specify the allocation of the responsibilities of Transmission Provider or Transmission Owner and Interconnection Customer to obtain all permits, licenses and authorizations that are necessary to accomplish the interconnection in compliance with Applicable Laws and Regulations. Transmission Provider or Transmission Owner and Interconnection Customer shall cooperate with each other in good faith in obtaining any such permits, licenses and authorizations. With respect to this paragraph, Transmission Provider or Transmission Owner shall provide permitting assistance to Interconnection Customer comparable to that provided to Transmission Provider's own, or an Affiliate's generation.

5.15 Early Construction of Base Case Facilities. Interconnection Customer may request Transmission Provider to construct, and Transmission Provider shall construct, using Reasonable Efforts to accommodate Interconnection Customer's In-Service Date, all or any portion of any Network Upgrades required for Interconnection Customer to be interconnected to the Transmission System which are included in the Base Case of the Facilities Study for Interconnection Customer, and which also are required to be constructed for another Interconnection Customer, but where such construction is not scheduled to be completed in time to achieve Interconnection Customer's In-Service Date.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 354FERC Electric TariffFourth Revised Volume No. 1

5.16 Suspension. Interconnection Customer reserves the right, upon written notice to Transmission Provider, to suspend at any time all work by Transmission Provider associated with the construction and installation of Transmission Provider's Interconnection Facilities and/or Network Upgrades required under this LGIA with the condition that Transmission System shall be left in a safe and reliable condition in accordance with Good Utility Practice and Transmission Provider's safety and reliability criteria. In such event, Interconnection Customer shall be responsible for all reasonable and necessary costs which Transmission Provider (i) has incurred pursuant to this LGIA prior to the suspension and (ii) incurs in suspending such work, including any costs incurred to perform such work as may be necessary to ensure the safety of persons and property and the integrity of the Transmission System during such suspension and, if applicable, any costs incurred in connection with the cancellation or suspension of material, equipment and labor contracts which Transmission Provider cannot reasonably avoid; provided, however, that prior to canceling or suspending any such material, equipment or labor contract, Transmission Provider shall obtain Interconnection Customer's authorization to do so.

Transmission Provider shall invoice Interconnection Customer for such costs pursuant to Article 12 and shall use due diligence to minimize its costs. In the event Interconnection Customer suspends work by Transmission Provider required under this LGIA pursuant to this Article 5.16, and has not requested Transmission Provider to recommence the work required under this LGIA on or before the expiration of three (3) years following commencement of such suspension, this LGIA shall be deemed terminated. The three-year period shall begin on the date the suspension is requested, or the date of the written notice to Transmission Provider, if no effective date is specified.

5.17 Taxes.

5.17.1 Interconnection Customer Payments Not Taxable. The Parties intend that all payments or property transfers made by Interconnection Customer to Transmission Provider for the installation of Transmission Provider's Interconnection Facilities and the Network Upgrades shall be non-taxable, either as contributions to capital, or as an advance, in accordance with the Internal Revenue Code and any applicable state income tax laws and shall not be taxable as contributions in aid of construction or otherwise under the Internal Revenue Code and any applicable state income tax laws.

5.17.2 Representations and Covenants. In accordance with IRS Notice 2001-82 and IRS Notice 88-129, Interconnection Customer represents and covenants that (i) ownership of the electricity generated at the Large Generating Facility will pass to another party prior to the transmission of the electricity on the Transmission System, (ii) for income tax purposes, the amount of any payments and the cost of any property transferred to Transmission

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 355FERC Electric TariffFourth Revised Volume No. 1

Provider for Transmission Provider's Interconnection Facilities will be capitalized by Interconnection Customer as an intangible asset and recovered using the straight-line method over a useful life of twenty (20) years, and (iii) any portion of Transmission Provider's Interconnection Facilities that is a "dual-use intertie," within the meaning of IRS Notice 88-129, is reasonably expected to carry only a de minimis amount of electricity in the direction of the Large Generating Facility. For this purpose, "de minimis amount" means no more than 5 percent of the total power flows in both directions, calculated in accordance with the "5 percent test" set forth in IRS Notice 88-129. This is not intended to be an exclusive list of the relevant conditions that must be met to conform to IRS requirements for non-taxable treatment.

At Transmission Provider's request, Interconnection Customer shall provide Transmission Provider with a report from an independent engineer confirming its representation in clause (iii), above. Transmission Provider represents and covenants that the cost of Transmission Provider's Interconnection Facilities paid for by Interconnection Customer will have no net effect on the base upon which rates are determined.

5.17.3 Indemnification for the Cost Consequences of Current Tax Liability Imposed Upon the Transmission Provider. Notwithstanding Article 5.17.1, Interconnection Customer shall protect, indemnify and hold harmless Transmission Provider from the cost consequences of any current tax liability imposed against Transmission Provider as the result of payments or property transfers made by Interconnection Customer to Transmission Provider under this LGIA for Interconnection Facilities, as well as any interest and penalties, other than interest and penalties attributable to any delay caused by Transmission Provider.

Transmission Provider shall not include a gross-up for the cost consequences of any current tax liability in the amounts it charges Interconnection Customer under this LGIA unless (i) Transmission Provider has determined, in good faith, that the payments or property transfers made by Interconnection Customer to Transmission Provider should be reported as income subject to taxation or (ii) any Governmental Authority directs Transmission Provider to report payments or property as income subject to taxation; provided, however, that Transmission Provider may require Interconnection Customer to provide security for Interconnection Facilities, in a form reasonably acceptable to Transmission Provider (such as a parental guarantee or a letter of credit), in an amount equal to the cost consequences of any current tax liability under this Article 5.17. Interconnection Customer shall reimburse

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 356FERC Electric TariffFourth Revised Volume No. 1

Transmission Provider for such costs on a fully grossed-up basis, in accordance with Article 5.17.4, within thirty (30) Calendar Days of receiving written notification from Transmission Provider of the amount due, including detail about how the amount was calculated.

The indemnification obligation shall terminate at the earlier of (1) the expiration of the ten year testing period and the applicable statute of limitation, as it may be extended by Transmission Provider upon request of the IRS, to keep these years open for audit or adjustment,

or (2) the occurrence of a subsequent taxable event and the payment of any related indemnification obligations as contemplated by this Article 5.17.

5.17.4 Tax Gross-Up Amount. Interconnection Customer's liability for the cost consequences of any current tax liability under this Article 5.17 shall be calculated on a fully grossed-up basis. Except as may otherwise be agreed to by the parties, this means that Interconnection Customer will pay Transmission Provider, in addition to the amount paid for the Interconnection Facilities and Network Upgrades, an amount equal to (1) the current taxes imposed on Transmission Provider ("Current Taxes") on the excess of (a) the gross income realized by Transmission Provider as a result of payments or property transfers made by Interconnection Customer to Transmission Provider under this LGIA (without regard to any payments under this Article 5.17) (the "Gross Income Amount") over (b) the present value of future tax deductions for depreciation that will be available as a result of such payments or property transfers (the "Present Value Depreciation Amount"), plus (2) an additional amount sufficient to permit Transmission Provider to receive and retain, after the payment of all Current Taxes, an amount equal to the net amount described in clause (1).

For this purpose, (i) Current Taxes shall be computed based on Transmission Provider's composite federal and state tax rates at the time the payments or property transfers are received and Transmission Provider will be treated as being subject to tax at the highest marginal rates in effect at that time (the "Current Tax Rate"), and (ii) the Present Value Depreciation Amount shall be computed by discounting Transmission Provider's anticipated tax depreciation deductions as a result of such payments or property transfers by Transmission Provider's current weighted average cost of capital. Thus, the formula for calculating Interconnection Customer's liability to Transmission Owner pursuant to this Article 5.17.4 can be expressed as follows: (Current Tax Rate x (Gross Income Amount – Present Value of Tax Depreciation))/(1-Current Tax Rate). Interconnection Customer's estimated tax liability in the event

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 357FERC Electric TariffFourth Revised Volume No. 1

taxes are imposed shall be stated in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades.

5.17.5 Private Letter Ruling or Change or Clarification of Law. At Interconnection Customer's request and expense, Transmission Provider shall file with the IRS a request for a private letter ruling as to whether any property transferred or sums paid, or to be paid, by Interconnection Customer to Transmission Provider under this LGIA are subject to federal income taxation. Interconnection Customer will prepare the initial draft of the request for a private letter ruling, and will certify under penalties of perjury that all facts represented in such request are true and accurate to the best of Interconnection Customer's knowledge. Transmission Provider and Interconnection Customer shall cooperate in good faith with respect to the submission of such request.

Transmission Provider shall keep Interconnection Customer fully informed of the status of such request for a private letter ruling and shall execute either a privacy act waiver or a limited power of attorney, in a form acceptable to the IRS, that authorizes Interconnection Customer to participate in all discussions with the IRS regarding such request for a private letter ruling. Transmission Provider shall allow Interconnection Customer to attend all meetings with IRS officials about the request and shall permit Interconnection Customer to prepare the initial drafts of any follow-up letters in connection with the request.

5.17.6 Subsequent Taxable Events. If, within 10 years from the date on which the relevant Transmission Provider's Interconnection Facilities are placed in service, (i) Interconnection Customer Breaches the covenants contained in Article 5.17.2, (ii) a "disqualification event" occurs within the meaning of IRS Notice 88-129, or (iii) this LGIA terminates and Transmission Provider retains ownership of the Interconnection Facilities and Network Upgrades, Interconnection Customer shall pay a tax gross-up for the cost consequences of any current tax liability imposed on Transmission Provider, calculated using the methodology described in Article 5.17.4 and in accordance with IRS Notice 90-60.

5.17.7 Contests. In the event any Governmental Authority determines that Transmission Provider's receipt of payments or property constitutes income that is subject to taxation, Transmission Provider shall notify Interconnection Customer, in writing, within thirty (30) Calendar Days of receiving notification of such determination by a Governmental Authority. Upon the timely written request by Interconnection Customer and at Interconnection Customer's sole expense, Transmission Provider may appeal, protest, seek abatement of, or

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 358FERC Electric TariffFourth Revised Volume No. 1

otherwise oppose such determination. Upon Interconnection Customer's written request and sole expense, Transmission Provider may file a claim for refund with respect to any taxes paid under this Article 5.17, whether or not it has received such a determination. Transmission Provider reserves the right to make all decisions with regard to the prosecution of such appeal, protest, abatement or other contest, including the selection of counsel and compromise or settlement of the claim, but Transmission Provider shall keep Interconnection Customer informed, shall consider in good faith suggestions from Interconnection Customer about the conduct of the contest, and shall reasonably permit Interconnection Customer or an Interconnection Customer representative to attend contest proceedings.

Interconnection Customer shall pay to Transmission Provider on a periodic basis, as invoiced by Transmission Provider, Transmission Provider's documented reasonable costs of prosecuting such appeal, protest, abatement or other contest. At any time during the contest, Transmission Provider may agree to a settlement either with Interconnection Customer's consent or after obtaining written advice from nationally-recognized tax counsel, selected by Transmission Provider, but reasonably acceptable to Interconnection Customer, that the proposed settlement represents a reasonable settlement given the hazards of litigation. Interconnection Customer's obligation shall be based on the amount of the settlement agreed to by Interconnection Customer, or if a higher amount, so much of the settlement that is supported by the written advice from nationally-recognized tax counsel selected under the terms of the preceding sentence. Any settlement without Interconnection Customer's consent or such written advice will relieve Interconnection Customer from any obligation to indemnify Transmission Provider for the tax at issue in the contest.

5.17.8 Refund. In the event that (a) a private letter ruling is issued to Transmission Provider which holds that any amount paid or the value of any property transferred by Interconnection Customer to Transmission Provider under the terms of this LGIA is not subject to federal income taxation, (b) any legislative change or administrative announcement, notice, ruling or other determination makes it reasonably clear to Transmission Provider in good faith that any amount paid or the value of any property transferred by Interconnection Customer to Transmission Provider under the terms of this LGIA is not taxable to Transmission Provider, (c) any abatement, appeal, protest, or other contest results in a determination that any payments or transfers made by Interconnection Customer to Transmission Provider are not subject to federal income tax, or (d) if Transmission Provider receives a refund from any taxing authority for any overpayment of tax attributable to any payment or

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 359FERC Electric TariffFourth Revised Volume No. 1

property transfer made by Interconnection Customer to Transmission Provider pursuant to this LGIA, Transmission Provider shall promptly refund to Interconnection Customer the following:

(i) any payment made by Interconnection Customer under this Article 5.17 for taxes that is attributable to the amount determined to be non-taxable, together with interest thereon,

(ii) on any amounts paid by Interconnection Customer to Transmission Provider for such taxes which Transmission Provider did not submit to the taxing authority, calculated in accordance with the methodology set forth in FERC's regulations at 18 CFR §35.19a(a)(2)(ii) from the date payment was made by Interconnection Customer to the date Transmission Provider refunds such payment to Interconnection Customer, and

(iii) with respect to any such taxes paid by Transmission Provider, any refund or credit Transmission Provider receives or to which it may be entitled from any Governmental Authority, interest (or that portion thereof attributable to the payment described in clause (i), above) owed to Transmission Provider for such overpayment of taxes (including any reduction in interest otherwise payable by Transmission Provider to any Governmental Authority resulting from an offset or credit); provided, however, that Transmission Provider will remit such amount promptly to Interconnection Customer only after and to the extent that Transmission Provider has received a tax refund, credit or offset from any Governmental Authority for any applicable overpayment of income tax related to Transmission Provider's Interconnection Facilities.

The intent of this provision is to leave the Parties, to the extent practicable, in the event that no taxes are due with respect to any payment for Interconnection Facilities and Network Upgrades hereunder, in the same position they would have been in had no such tax payments been made.

5.17.9 Taxes Other Than Income Taxes. Upon the timely request by Interconnection Customer, and at Interconnection Customer's sole expense, Transmission Provider may appeal, protest, seek abatement of, or otherwise contest any tax (other than federal or state income tax) asserted or assessed against Transmission Provider for which Interconnection Customer may be required to reimburse Transmission Provider under the terms of this LGIA. Interconnection Customer shall pay to Transmission Provider on a periodic basis, as invoiced by Transmission Provider, Transmission Provider's documented reasonable costs of prosecuting such

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 360FERC Electric TariffFourth Revised Volume No. 1

appeal, protest, abatement, or other contest. Interconnection Customer and Transmission Provider shall cooperate in good faith with respect to any such contest. Unless the payment of such taxes is a prerequisite to an appeal or abatement or cannot be deferred, no amount shall be payable by Interconnection Customer to Transmission Provider for such taxes until they are assessed by a final, non-appealable order by any court or agency of competent jurisdiction. In the event that a tax payment is withheld and ultimately due and payable after appeal, Interconnection Customer will be responsible for all taxes, interest and penalties, other than penalties attributable to any delay caused by Transmission Provider.

5.17.10 Transmission Owners Who Are Not Transmission Providers. If Transmission Provider is not the same entity as the Transmission Owner, then (i) all references in this Article 5.17 to Transmission Provider shall be deemed also to refer to and to include the Transmission Owner, as appropriate, and (ii) this LGIA shall not become effective until such Transmission Owner shall have agreed in writing to assume all of the duties and obligations of Transmission Provider under this Article 5.17 of this LGIA.

5.18 Tax Status. Each Party shall cooperate with the other to maintain the other Party's tax status. Nothing in this LGIA is intended to adversely affect any Transmission Provider's tax exempt status with respect to the issuance of bonds including, but not limited to, Local Furnishing Bonds.

5.19 Modification.

5.19.1 General. Either Party may undertake modifications to its facilities. If a Party plans to undertake a modification that reasonably may be expected to affect the other Party's facilities, that Party shall provide to the other Party sufficient information regarding such modification so that the other Party may evaluate the potential impact of such modification prior to commencement of the work. Such information shall be deemed to be confidential hereunder and shall include information concerning the timing of such modifications and whether such modifications are expected to interrupt the flow of electricity from the Large Generating Facility. The Party desiring to perform such work shall provide the relevant drawings, plans, and specifications to the other Party at least ninety (90) Calendar Days in advance of the commencement of the work or such shorter period upon which the Parties may agree, which agreement shall not unreasonably be withheld, conditioned or delayed.

In the case of Large Generating Facility modifications that do not require Interconnection Customer to submit an Interconnection Request, Transmission Provider shall provide, within thirty (30) Calendar Days (or

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 361FERC Electric TariffFourth Revised Volume No. 1

such other time as the Parties may agree), an estimate of any additional modifications to the Transmission System, Transmission Provider's Interconnection Facilities or Network Upgrades necessitated by such Interconnection Customer modification and a good faith estimate of the costs thereof.

5.19.2 Standards. Any additions, modifications, or replacements made to a Party's facilities shall be designed, constructed and operated in accordance with this LGIA and Good Utility Practice.

5.19.3 Modification Costs. Interconnection Customer shall not be directly assigned for the costs of any additions, modifications, or replacements that Transmission Provider makes to Transmission Provider's Interconnection Facilities or the Transmission System to facilitate the interconnection of a third party to Transmission Provider's Interconnection Facilities or the Transmission System, or to provide transmission service to a third party under Transmission Provider's Tariff. Interconnection Customer shall be responsible for the costs of any additions, modifications, or replacements to Interconnection Customer's Interconnection Facilities that may be necessary to maintain or upgrade such Interconnection Customer's Interconnection Facilities consistent with Applicable Laws and Regulations, Applicable Reliability Standards or Good Utility Practice.

Article 6. Testing and Inspection

6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, Transmission Provider shall test Transmission Provider's Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

6.2 Post-Commercial Operation Date Testing and Modifications. Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Generating Facility with the Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party's facilities, at the requesting Party's expense, as may be in accordance with Good Utility Practice.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 362FERC Electric TariffFourth Revised Volume No. 1

6.3 Right to Observe Testing. Each Party shall notify the other Party in advance of its performance of tests of its Interconnection Facilities. The other Party has the right, at its own expense, to observe such testing.

6.4 Right to Inspect. Each Party shall have the right, but shall have no obligation to: (i) observe the other Party's tests and/or inspection of any of its System Protection Facilities and other protective equipment, including Power System Stabilizers; (ii) review the settings of the other Party's System Protection Facilities and other protective equipment; and (iii) review the other Party's maintenance records relative to the Interconnection Facilities, the System Protection Facilities and other protective equipment. A Party may exercise these rights from time to time as it deems necessary upon reasonable notice to the other Party. The exercise or non-exercise by a Party of any such rights shall not be construed as an endorsement or confirmation of any element or condition of the Interconnection Facilities or the System Protection Facilities or other protective equipment or the operation thereof, or as a warranty as to the fitness, safety, desirability, or reliability of same. Any information that a Party obtains through the exercise of any of its rights under this Article 6.4 shall be deemed to be Confidential Information and treated pursuant to Article 22 of this LGIA.

Article 7. Metering

7.1 General. Each Party shall comply with the Applicable Reliability Council requirements. Unless otherwise agreed by the Parties, Transmission Provider shall install Metering Equipment at the Point of Interconnection prior to any operation of the Large Generating Facility and shall own, operate, test and maintain such Metering Equipment. Power flows to and from the Large Generating Facility shall be measured at or, at Transmission Provider's option, compensated to, the Point of Interconnection. Transmission Provider shall provide metering quantities, in analog and/or digital form, to Interconnection Customer upon request. Interconnection Customer shall bear all reasonable documented costs associated with the purchase, installation, operation, testing and maintenance of the Metering Equipment.

7.2 Check Meters. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check Transmission Provider's meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except as provided in Article 7.4 below. The check meters shall be subject at all reasonable times to inspection and examination by Transmission Provider or its designee. The installation, operation and maintenance thereof shall be performed entirely by Interconnection Customer in accordance with Good Utility Practice.

7.3 Standards. Transmission Provider shall install, calibrate, and test revenue quality Metering Equipment in accordance with applicable ANSI standards.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 363FERC Electric TariffFourth Revised Volume No. 1

7.4 Testing of Metering Equipment. Transmission Provider shall inspect and test all Transmission Provider-owned Metering Equipment upon installation and at least once every two (2) years thereafter. If requested to do so by Interconnection Customer, Transmission Provider shall, at Interconnection Customer's expense, inspect or test Metering Equipment more frequently than every two (2) years. Transmission Provider shall give reasonable notice of the time when any inspection or test shall take place, and Interconnection Customer may have representatives present at the test or inspection. If at any time Metering Equipment is found to be inaccurate or defective, it shall be adjusted, repaired or replaced at Interconnection Customer's expense, in order to provide accurate metering, unless the inaccuracy or defect is due to Transmission Provider's failure to maintain, then Transmission Provider shall pay. If Metering Equipment fails to register, or if the measurement made by Metering Equipment during a test varies by more than two percent from the measurement made by the standard meter used in the test, Transmission Provider shall adjust the measurements by correcting all measurements for the period during which Metering Equipment was in error by using Interconnection Customer's check meters, if installed. If no such check meters are installed or if the period cannot be reasonably ascertained, the adjustment shall be for the period immediately preceding the test of the Metering Equipment equal to one-half the time from the date of the last previous test of the Metering Equipment.

7.5 Metering Data. At Interconnection Customer's expense, the metered data shall be telemetered to one or more locations designated by Transmission Provider and one or more locations designated by Interconnection Customer. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.

Article 8. Communications

8.1 Interconnection Customer Obligations. Interconnection Customer shall maintain satisfactory operating communications with Transmission Provider's Transmission System dispatcher or representative designated by Transmission Provider. Interconnection Customer shall provide standard voice line, dedicated voice line and facsimile communications at its Large Generating Facility control room or central dispatch facility through use of either the public telephone system, or a voice communications system that does not rely on the public telephone system. Interconnection Customer shall also provide the dedicated data circuit(s) necessary to provide Interconnection Customer data to Transmission Provider as set forth in Appendix D, Security Arrangements Details. The data circuit(s) shall extend from the Large Generating Facility to the location(s) specified by Transmission Provider. Any required maintenance of such communications equipment shall be performed by Interconnection Customer. Operational communications shall be activated and maintained under, but not be limited to, the following events: system paralleling or separation, scheduled and unscheduled shutdowns, equipment clearances, and hourly and daily load data.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 364FERC Electric TariffFourth Revised Volume No. 1

8.2 Remote Terminal Unit. Prior to the Initial Synchronization Date of the Large Generating Facility, a Remote Terminal Unit, or equivalent data collection and transfer equipment acceptable to the Parties, shall be installed by Interconnection Customer, or by Transmission Provider at Interconnection Customer's expense, to gather accumulated and instantaneous data to be telemetered to the location(s) designated by Transmission Provider through use of a dedicated point-to-point data circuit(s) as indicated in Article 8.1. The communication protocol for the data circuit(s) shall be specified by Transmission Provider. Instantaneous bi-directional analog real power and reactive power flow information must be telemetered directly to the location(s) specified by Transmission Provider.

Each Party will promptly advise the other Party if it detects or otherwise learns of any metering, telemetry or communications equipment errors or malfunctions that require the attention and/or correction by the other Party. The Party owning such equipment shall correct such error or malfunction as soon as reasonably feasible.

8.3 No Annexation. Any and all equipment placed on the premises of a Party shall be and remain the property of the Party providing such equipment regardless of the mode and manner of annexation or attachment to real property, unless otherwise mutually agreed by the Parties.

Article 9. Operations

9.1 General. Each Party shall comply with the Applicable Reliability Council requirements. Each Party shall provide to the other Party all information that may reasonably be required by the other Party to comply with Applicable Laws and Regulations and Applicable Reliability Standards.

9.2 Control Area Notification. At least three months before Initial Synchronization Date, Interconnection Customer shall notify Transmission Provider in writing of the Control Area in which the Large Generating Facility will be located. If Interconnection Customer elects to locate the Large Generating Facility in a Control Area other than the Control Area in which the Large Generating Facility is physically located, and if permitted to do so by the relevant transmission tariffs, all necessary arrangements, including but not limited to those set forth in Article 7 and Article 8 of this LGIA, and remote Control Area generator interchange agreements, if applicable, and the appropriate measures under such agreements, shall be executed and implemented prior to the placement of the Large Generating Facility in the other Control Area.

9.3 Transmission Provider Obligations. Transmission Provider shall cause the Transmission System and Transmission Provider's Interconnection Facilities to be operated, maintained and controlled in a safe and reliable manner and in accordance with this LGIA. Transmission Provider may provide operating instructions to Interconnection Customer consistent with this LGIA and Transmission Provider's operating protocols and procedures as they may

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 365FERC Electric TariffFourth Revised Volume No. 1

change from time to time. Transmission Provider will consider changes to its operating protocols and procedures proposed by Interconnection Customer.

9.4 Interconnection Customer Obligations. Interconnection Customer shall at its own expense operate, maintain and control the Large Generating Facility and Interconnection Customer's Interconnection Facilities in a safe and reliable manner and in accordance with this LGIA. Interconnection Customer shall operate the Large Generating Facility and Interconnection Customer's Interconnection Facilities in accordance with all applicable requirements of the Control Area of which it is part, as such requirements are set forth in Appendix C, Interconnection Details, of this LGIA. Appendix C, Interconnection Details, will be modified to reflect changes to the requirements as they may change from time to time. Either Party may request that the other Party provide copies of the requirements set forth in Appendix C, Interconnection Details, of this LGIA.

9.5 Start-Up and Synchronization. Consistent with the Parties' mutually acceptable procedures, Interconnection Customer is responsible for the proper synchronization of the Large Generating Facility to Transmission Provider's Transmission System.

9.6 Reactive Power.

9.6.1 Power Factor Design Criteria. Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless Transmission Provider has established different requirements that apply to all generators in the Control Area on a comparable basis. The requirements of this paragraph shall not apply to wind generators.

9.6.2 Voltage Schedules. Once Interconnection Customer has synchronized the Large Generating Facility with the Transmission System, Transmission Provider shall require Interconnection Customer to operate the Large Generating Facility to produce or absorb reactive power within the design limitations of the Large Generating Facility set forth in Article 9.6.1 (Power Factor Design Criteria). Transmission Provider's voltage schedules shall treat all sources of reactive power in the Control Area in an equitable and not unduly discriminatory manner. Transmission Provider shall exercise Reasonable Efforts to provide Interconnection Customer with such schedules at least one (1) day in advance, and may make changes to such schedules as necessary to maintain the reliability of the Transmission System. Interconnection Customer shall operate the Large Generating Facility to maintain the specified output voltage or power factor at the Point of Interconnection within the design limitations of the Large Generating Facility set forth in Article 9.6.1 (Power Factor Design Criteria). If Interconnection Customer is unable to maintain the specified voltage or power factor, it shall promptly notify the System Operator.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 366FERC Electric TariffFourth Revised Volume No. 1

9.6.2.1 Governors and Regulators. Whenever the Large Generating Facility is operated in parallel with the Transmission System and the speed governors (if installed on the generating unit pursuant to Good Utility Practice) and voltage regulators are capable of operation, Interconnection Customer shall operate the Large Generating Facility with its speed governors and voltage regulators in automatic operation. If the Large Generating Facility's speed governors and voltage regulators are not capable of such automatic operation, Interconnection Customer shall immediately notify Transmission Provider's system operator, or its designated representative, and ensure that such Large Generating Facility's reactive power production or absorption (measured in MVARs) are within the design capability of the Large Generating Facility's generating unit(s) and steady state stability limits. Interconnection Customer shall not cause its Large Generating Facility to disconnect automatically or instantaneously from the Transmission System or trip any generating unit comprising the Large Generating Facility for an under or over frequency condition unless the abnormal frequency condition persists for a time period beyond the limits set forth in ANSI/IEEE Standard C37.106, or such other standard as applied to other generators in the Control Area on a comparable basis.

9.6.3 Payment for Reactive Power. Transmission Provider is required to pay Interconnection Customer for reactive power that Interconnection Customer provides or absorbs from the Large Generating Facility when Transmission Provider requests Interconnection Customer to operate its Large Generating Facility outside the range specified in Article 9.6.1, provided that if Transmission Provider pays its own or affiliated generators for reactive power service within the specified range, it must also pay Interconnection Customer. Payments shall be pursuant to Article 11.6 or such other agreement to which the Parties have otherwise agreed.

9.7 Outages and Interruptions.

9.7.1 Outages.

9.7.1.1 Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Party remove from service any of its respective Interconnection Facilities or Network Upgrades that may impact the other Party's facilities as necessary to perform maintenance or testing or to install or replace equipment. Absent an Emergency Condition, the Party scheduling a removal of such facility(ies)

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 367FERC Electric TariffFourth Revised Volume No. 1

from service will use Reasonable Efforts to schedule such removal on a date and time mutually acceptable to the Parties. In all circumstances, any Party planning to remove such facility(ies) from service shall use Reasonable Efforts to minimize the effect on the other Party of such removal.

9.7.1.2 Outage Schedules. Transmission Provider shall post scheduled outages of its transmission facilities on the OASIS. Interconnection Customer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Provider for a minimum of a rolling twenty-four month period. Interconnection Customer shall update its planned maintenance schedules as necessary. Transmission Provider may request Interconnection Customer to reschedule its maintenance as necessary to maintain the reliability of the Transmission System; provided, however, adequacy of generation supply shall not be a criterion in determining Transmission System reliability. Transmission Provider shall compensate Interconnection Customer for any additional direct costs that Interconnection Customer incurs as a result of having to reschedule maintenance, including any additional overtime, breaking of maintenance contracts or other costs above and beyond the cost Interconnection Customer would have incurred absent Transmission Provider's request to reschedule maintenance. Interconnection Customer will not be eligible to receive compensation, if during the twelve (12) months prior to the date of the scheduled maintenance, Interconnection Customer had modified its schedule of maintenance activities.

9.7.1.3 Outage Restoration. If an outage on a Party's Interconnection Facilities or Network Upgrades adversely affects the other Party's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party, to the extent such information is known, information on the nature of the Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

9.7.2 Interruption of Service. If required by Good Utility Practice to do so, Transmission Provider may require Interconnection Customer to interrupt or reduce deliveries of electricity if such delivery of electricity could adversely affect Transmission Provider's ability to

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 368FERC Electric TariffFourth Revised Volume No. 1

perform such activities as are necessary to safely and reliably operate and maintain the Transmission System. The following provisions shall apply to any interruption or reduction permitted under this Article 9.7.2:

9.7.2.1 The interruption or reduction shall continue only for so long as reasonably necessary under Good Utility Practice;

9.7.2.2 Any such interruption or reduction shall be made on an equitable, non-discriminatory basis with respect to all generating facilities directly connected to the Transmission System;

9.7.2.3 When the interruption or reduction must be made under circumstances which do not allow for advance notice, Transmission Provider shall notify Interconnection Customer by telephone as soon as practicable of the reasons for the curtailment, interruption, or reduction, and, if known, its expected duration. Telephone notification shall be followed by written notification as soon as practicable;

9.7.2.4 Except during the existence of an Emergency Condition, when the interruption or reduction can be scheduled without advance notice, Transmission Provider shall notify Interconnection Customer in advance regarding the timing of such scheduling and further notify Interconnection Customer of the expected duration. Transmission Provider shall coordinate with Interconnection Customer using Good Utility Practice to schedule the interruption or reduction during periods of least impact to Interconnection Customer and Transmission Provider;

9.7.2.5 The Parties shall cooperate and coordinate with each other to the extent necessary in order to restore the Large Generating Facility, Interconnection Facilities, and the Transmission System to their normal operating state, consistent with system conditions and Good Utility Practice.

9.7.3 Under-Frequency and Over Frequency Conditions. The Transmission System is designed to automatically activate a load-shed program as required by the Applicable Reliability Council in the event of an under-frequency system disturbance. Interconnection Customer shall implement under-frequency and over-frequency relay set points for the Large Generating Facility as required by the Applicable Reliability Council to ensure "ride through" capability of the Transmission System. Large Generating Facility response to frequency deviations of pre-determined magnitudes, both under-frequency and over-frequency deviations, shall be studied and coordinated with Transmission Provider in accordance with Good Utility Practice. The term "ride through" as

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 369FERC Electric TariffFourth Revised Volume No. 1

used herein shall mean the ability of a Generating Facility to stay connected to and synchronized with the Transmission System during system disturbances within a range of under-frequency and over-frequency conditions, in accordance with Good Utility Practice.

9.7.4 System Protection and Other Control Requirements.

9.7.4.1 System Protection Facilities. Interconnection Customer shall, at its expense, install, operate and maintain System Protection Facilities as a part of the Large Generating Facility or Interconnection Customer's Interconnection Facilities. Transmission Provider shall install at Interconnection Customer's expense any System Protection Facilities that may be required on Transmission Provider's Interconnection Facilities or the Transmission System as a result of the interconnection of the Large Generating Facility and Interconnection Customer's Interconnection Facilities.

9.7.4.2 Each Party's protection facilities shall be designed and coordinated with other systems in accordance with Good Utility Practice.

9.7.4.3 Each Party shall be responsible for protection of its facilities consistent with Good Utility Practice.

9.7.4.4 Each Party's protective relay design shall incorporate the necessary test switches to perform the tests required in Article 6. The required test switches will be placed such that they allow operation of lockout relays while preventing breaker failure schemes from operating and causing unnecessary breaker operations and/or the tripping of Interconnection Customer's units.

9.7.4.5 Each Party will test, operate and maintain System Protection Facilities in accordance with Good Utility Practice.

9.7.4.6 Prior to the In-Service Date, and again prior to the Commercial Operation Date, each Party or its agent shall perform a complete calibration test and functional trip test of the System Protection Facilities. At intervals suggested by Good Utility Practice and following any apparent malfunction of the System Protection Facilities, each Party shall perform both calibration and functional trip tests of its System Protection Facilities. These tests do not require the tripping of any in-service generation unit. These tests do, however, require that all protective relays and lockout contacts be activated.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 370FERC Electric TariffFourth Revised Volume No. 1

9.7.5 Requirements for Protection. In compliance with Good Utility Practice, Interconnection Customer shall provide, install, own, and maintain relays, circuit breakers and all other devices necessary to remove any fault contribution of the Large Generating Facility to any short circuit occurring on the Transmission System not otherwise isolated by Transmission Provider's equipment, such that the removal of the fault contribution shall be coordinated with the protective requirements of the Transmission System. Such protective equipment shall include, without limitation, a disconnecting device or switch with load-interrupting capability located between the Large Generating Facility and the Transmission System at a site selected upon mutual agreement (not to be unreasonably withheld, conditioned or delayed) of the Parties. Interconnection Customer shall be responsible for protection of the Large Generating Facility and Interconnection Customer's other equipment from such conditions as negative sequence currents, over- or under-frequency, sudden load rejection, over- or under-voltage, and generator loss-of-field. Interconnection Customer shall be solely responsible to disconnect the Large Generating Facility and Interconnection Customer's other equipment if conditions on the Transmission System could adversely affect the Large Generating Facility.

9.7.6 Power Quality. Neither Party's facilities shall cause excessive voltage flicker nor introduce excessive distortion to the sinusoidal voltage or current waves as defined by ANSI Standard C84.1-1989, in accordance with IEEE Standard 519, or any applicable superseding electric industry standard. In the event of a conflict between ANSI Standard C84.1-1989, or any applicable superseding electric industry standard, ANSI Standard C84.1-1989, or the applicable superseding electric industry standard, shall control.

9.8 Switching and Tagging Rules. Each Party shall provide the other Party a copy of its switching and tagging rules that are applicable to the other Party's activities. Such switching and tagging rules shall be developed on a non-discriminatory basis. The Parties shall comply with applicable switching and tagging rules, as amended from time to time, in obtaining clearances for work or for switching operations on equipment.

9.9 Use of Interconnection Facilities by Third Parties.

9.9.1 Purpose of Interconnection Facilities. Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Generating Facility to the Transmission System and shall be used for no other purpose.

9.9.2 Third Party Users. If required by Applicable Laws and Regulations or if the Parties mutually agree, such agreement not to be unreasonably withheld, to allow one or more third parties to use

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 371FERC Electric TariffFourth Revised Volume No. 1

Transmission Provider's Interconnection Facilities, or any part thereof, Interconnection Customer will be entitled to compensation for the capital expenses it incurred in connection with the Interconnection Facilities based upon the pro rata use of the Interconnection Facilities by Transmission Provider, all third party users, and Interconnection Customer, in accordance with Applicable Laws and Regulations or upon some other mutually-agreed upon methodology. In addition, cost responsibility for ongoing costs, including operation and maintenance costs associated with the Interconnection Facilities, will be allocated between Interconnection Customer and any third party users based upon the pro rata use of the Interconnection Facilities by Transmission Provider, all third party users, and Interconnection Customer, in accordance with Applicable Laws and Regulations or upon some other mutually agreed upon methodology. If the issue of such compensation or allocation cannot be resolved through such negotiations, it shall be submitted to FERC for resolution.

9.10 Disturbance Analysis Data Exchange. The Parties will cooperate with one another in the analysis of disturbances to either the Large Generating Facility or Transmission Provider's Transmission System by gathering and providing access to any information relating to any disturbance, including information from oscillography, protective relay targets, breaker operations and sequence of events records, and any disturbance information required by Good Utility Practice.

Article 10. Maintenance

10.1 Transmission Provider Obligations. Transmission Provider shall maintain the Transmission System and Transmission Provider's Interconnection Facilities in a safe and reliable manner and in accordance with this LGIA.

10.2 Interconnection Customer Obligations. Interconnection Customer shall maintain the Large Generating Facility and Interconnection Customer's Interconnection Facilities in a safe and reliable manner and in accordance with this LGIA.

10.3 Coordination. The Parties shall confer regularly to coordinate the planning, scheduling and performance of preventive and corrective maintenance on the Large Generating Facility and the Interconnection Facilities.

10.4 Secondary Systems. Each Party shall cooperate with the other in the inspection, maintenance, and testing of control or power circuits that operate below 600 volts, AC or DC, including, but not limited to, any hardware, control or protective devices, cables, conductors, electric raceways, secondary equipment panels, transducers, batteries, chargers, and voltage and current transformers that directly affect the operation of a Party's facilities and equipment which may reasonably be expected to impact the other Party. Each Party shall provide advance notice to the other Party before

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 372FERC Electric TariffFourth Revised Volume No. 1

undertaking any work on such circuits, especially on electrical circuits involving circuit breaker trip and close contacts, current transformers, or potential transformers.

10.5 Operating and Maintenance Expenses. Subject to the provisions herein addressing the use of facilities by others, and except for operations and maintenance expenses associated with modifications made for providing interconnection or transmission service to a third party and such third party pays for such expenses, Interconnection Customer shall be responsible for all reasonable expenses including overheads, associated with: (1) owning, operating, maintaining, repairing, and replacing Interconnection Customer's Interconnection Facilities; and (2) operation, maintenance, repair and replacement of Transmission Provider's Interconnection Facilities.

Article 11. Performance Obligation

11.1 Interconnection Customer Interconnection Facilities. Interconnection Customer shall design, procure, construct, install, own and/or control Interconnection Customer Interconnection Facilities described in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades, at its sole expense.

11.2 Transmission Provider's Interconnection Facilities. Transmission Provider or Transmission Owner shall design, procure, construct, install, own and/or control the Transmission Provider's Interconnection Facilities described in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades, at the sole expense of the Interconnection Customer.

11.3 Network Upgrades and Distribution Upgrades. Transmission Provider or Transmission Owner shall design, procure, construct, install, and own the Network Upgrades and Distribution Upgrades described in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades. The Interconnection Customer shall be responsible for all costs related to Distribution Upgrades. Unless Transmission Provider or Transmission Owner elects to fund the capital for the Network Upgrades, they shall be solely funded by Interconnection Customer.

11.4 Transmission Credits.

11.4.1 Repayment of Amounts Advanced for Network Upgrades. Interconnection Customer shall be entitled to a cash repayment, equal to the total amount paid to Transmission Provider and Affected System Operator, if any, for the Network Upgrades, including any tax gross-up or other tax-related payments associated with Network Upgrades, and not refunded to Interconnection Customer pursuant to Article 5.17.8 or otherwise, to be paid to Interconnection Customer on a

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 373FERC Electric TariffFourth Revised Volume No. 1

dollar-for-dollar basis for the non-usage sensitive portion of transmission charges, as payments are made under Transmission Provider's Tariff and Affected System's Tariff for transmission services with respect to the Large Generating Facility. Any repayment shall include interest calculated in accordance with the methodology set forth in FERC=s regulations at 18 C.F.R. '35.19a(a)(2)(ii) from the date of any payment for Network Upgrades through the date on which the Interconnection Customer receives a repayment of such payment pursuant to this subparagraph. Interconnection Customer may assign such repayment rights to any person.

Notwithstanding the foregoing, Interconnection Customer, Transmission Provider, and Affected System Operator may adopt any alternative payment schedule that is mutually agreeable so long as Transmission Provider and Affected System Operator take one of the following actions no later than five years from the Commercial Operation Date: (1) return to Interconnection Customer any amounts advanced for Network Upgrades not previously repaid, or (2) declare in writing that Transmission Provider or Affected System Operator will continue to provide payments to Interconnection Customer pursuant to this subparagraph until all amounts advanced for Network Upgrades have been repaid.

If the Large Generating Facility fails to achieve commercial operation, but it or another Generating Facility is later constructed and makes use of the Network Upgrades, Transmission Provider and Affected System Operator shall at that time reimburse Interconnection Customer for the amounts advanced for the Network Upgrades.

11.4.2 Special Provisions for Affected Systems. Unless Transmission Provider provides, under the LGIA, for the repayment of amounts advanced to Affected System Operator for Network Upgrades, Interconnection Customer and Affected System Operator shall enter into an agreement that provides for such repayment. The agreement shall specify the terms governing payments to be made by Interconnection Customer to the Affected System Operator as well as the repayment by the Affected System Operator.

11.4.3 Notwithstanding any other provision of this LGIA, nothing herein shall be construed as relinquishing or foreclosing any rights, including but not limited to firm transmission rights, capacity rights, transmission congestion rights, or transmission credits, that Interconnection Customer, shall be entitled to, now or in the future under any other agreement or tariff as a result of, or otherwise associated with, the transmission capacity, if any, created by the Network Upgrades, including the right to

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 374FERC Electric TariffFourth Revised Volume No. 1

obtain cash reimbursements or transmission credits for transmission service that is not associated with the Large Generating Facility.

11.5 Provision of Security. At least thirty (30) Calendar Days prior to the commencement of the procurement, installation, or construction of a discrete portion of a Transmission Provider's Interconnection Facilities, Network Upgrades, or Distribution Upgrades, Interconnection Customer shall provide Transmission Provider, at Interconnection Customer's option, a guarantee, a surety bond, letter of credit or other form of security that is reasonably acceptable to Transmission Provider and is consistent with the Uniform Commercial Code of the jurisdiction identified in Article 14.2.1. Such security for payment shall be in an amount sufficient to cover the costs for constructing, procuring and installing the applicable portion of Transmission Provider's Interconnection Facilities, Network Upgrades, or Distribution Upgrades and shall be reduced on a dollar-for-dollar basis for payments made to Transmission Provider for these purposes.

In addition:

11.5.1 The guarantee must be made by an entity that meets the creditworthiness requirements of Transmission Provider, and contain terms and conditions that guarantee payment of any amount that may be due from Interconnection Customer, up to an agreed-to maximum amount.

11.5.2 The letter of credit must be issued by a financial institution reasonably acceptable to Transmission Provider and must specify a reasonable expiration date.

11.5.3 The surety bond must be issued by an insurer reasonably acceptable to Transmission Provider and must specify a reasonable expiration date.

11.6 Interconnection Customer Compensation. If Transmission Provider requests or directs Interconnection Customer to provide a service pursuant to Articles 9.6.3 (Payment for Reactive Power), or 13.5.1 of this LGIA, Transmission Provider shall compensate Interconnection Customer in accordance with Interconnection Customer's applicable rate schedule then in effect unless the provision of such service(s) is subject to an RTO or ISO FERC-approved rate schedule. Interconnection Customer shall serve Transmission Provider or RTO or ISO with any filing of a proposed rate schedule at the time of such filing with FERC. To the extent that no rate schedule is in effect at the time the Interconnection Customer is required to provide or absorb any Reactive Power under this LGIA, Transmission Provider agrees to compensate Interconnection Customer in such amount as would have been due Interconnection Customer had the rate schedule been in effect at the time service commenced; provided, however, that such rate schedule must be filed at FERC or other appropriate Governmental Authority within sixty (60) Calendar Days of the commencement of service.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 375FERC Electric TariffFourth Revised Volume No. 1

11.6.1 Interconnection Customer Compensation for Actions During Emergency Condition. Transmission Provider or RTO or ISO shall compensate Interconnection Customer for its provision of real and reactive power and other Emergency Condition services that Interconnection Customer provides to support the Transmission System during an Emergency Condition in accordance with Article 11.6.

Article 12. Invoice

12.1 General. Each Party shall submit to the other Party, on a monthly basis, invoices of amounts due for the preceding month. Each invoice shall state the month to which the invoice applies and fully describe the services and equipment provided. The Parties may discharge mutual debts and payment obligations due and owing to each other on the same date through netting, in which case all amounts a Party owes to the other Party under this LGIA, including interest payments or credits, shall be netted so that only the net amount remaining due shall be paid by the owing Party.

12.2 Final Invoice. Within six months after completion of the construction of Transmission Provider's Interconnection Facilities and the Network Upgrades, Transmission Provider shall provide an invoice of the final cost of the construction of Transmission Provider's Interconnection Facilities and the Network Upgrades and shall set forth such costs in sufficient detail to enable Interconnection Customer to compare the actual costs with the estimates and to ascertain deviations, if any, from the cost estimates. Transmission Provider shall refund to Interconnection Customer any amount by which the actual payment by Interconnection Customer for estimated costs exceeds the actual costs of construction within thirty (30) Calendar Days of the issuance of such final construction invoice.

12.3 Payment. Invoices shall be rendered to the paying Party at the address specified in Appendix F. The Party receiving the invoice shall pay the invoice within thirty (30) Calendar Days of receipt. All payments shall be made in immediately available funds payable to the other Party, or by wire transfer to a bank named and account designated by the invoicing Party. Payment of invoices by either Party will not constitute a waiver of any rights or claims either Party may have under this LGIA.

12.4 Disputes. In the event of a billing dispute between Transmission Provider and Interconnection Customer, Transmission Provider shall continue to provide Interconnection Service under this LGIA as long as Interconnection Customer: (i) continues to make all payments not in dispute; and (ii) pays to Transmission Provider or into an independent escrow account the portion of the invoice in dispute, pending resolution of such dispute. If Interconnection Customer fails to meet these two requirements for continuation of service, then Transmission Provider may provide notice to Interconnection Customer of a Default pursuant to Article 17. Within thirty (30) Calendar Days after the resolution of the dispute, the Party that owes money to the other Party shall pay the amount due with interest

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 376FERC Electric TariffFourth Revised Volume No. 1

calculated in accord with the methodology set forth in FERC's regulations at 18 CFR § 35.19a(a)(2)(ii).

Article 13. Emergencies

13.1 Definition. "Emergency Condition" shall mean a condition or situation: (i) that in the judgment of the Party making the claim is imminently likely to endanger life or property; or (ii) that, in the case of Transmission Provider, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to the Transmission System, Transmission Provider's Interconnection Facilities or the Transmission Systems of others to which the Transmission System is directly connected; or (iii) that, in the case of Interconnection Customer, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to, the Large Generating Facility or Interconnection Customer's Interconnection Facilities' System restoration and black start shall be considered Emergency Conditions; provided, that Interconnection Customer is not obligated by this LGIA to possess black start capability.

13.2 Obligations. Each Party shall comply with the Emergency Condition procedures of the applicable ISO/RTO, NERC, the Applicable Reliability Council, Applicable Laws and Regulations, and any emergency procedures agreed to by the Joint Operating Committee.

13.3 Notice. Transmission Provider shall notify Interconnection Customer promptly when it becomes aware of an Emergency Condition that affects Transmission Provider's Interconnection Facilities or the Transmission System that may reasonably be expected to affect Interconnection Customer's operation of the Large Generating Facility or Interconnection Customer's Interconnection Facilities. Interconnection Customer shall notify Transmission Provider promptly when it becomes aware of an Emergency Condition that affects the Large Generating Facility or Interconnection Customer's Interconnection Facilities that may reasonably be expected to affect the Transmission System or Transmission Provider's Interconnection Facilities. To the extent information is known, the notification shall describe the Emergency Condition, the extent of the damage or deficiency, the expected effect on the operation of Interconnection Customer's or Transmission Provider's facilities and operations, its anticipated duration and the corrective action taken and/or to be taken. The initial notice shall be followed as soon as practicable with written notice.

13.4 Immediate Action. Unless, in Interconnection Customer's reasonable judgment, immediate action is required, Interconnection Customer shall obtain the consent of Transmission Provider, such consent to not be unreasonably withheld, prior to performing any manual switching operations at the Large Generating Facility or Interconnection Customer's Interconnection Facilities in response to an Emergency Condition either declared by Transmission Provider or otherwise regarding the Transmission System.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 377FERC Electric TariffFourth Revised Volume No. 1

13.5 Transmission Provider Authority.

13.5.1 General. Transmission Provider may take whatever actions or inactions with regard to the Transmission System or Transmission Provider's Interconnection Facilities it deems necessary during an Emergency Condition in order to (i) preserve public health and safety, (ii) preserve the reliability of the Transmission System or Transmission Provider's Interconnection Facilities, (iii) limit or prevent damage, and (iv) expedite restoration of service.

Transmission Provider shall use Reasonable Efforts to minimize the effect of such actions or inactions on the Large Generating Facility or Interconnection Customer's Interconnection Facilities. Transmission Provider may, on the basis of technical considerations, require the Large Generating Facility to mitigate an Emergency Condition by taking actions necessary and limited in scope to remedy the Emergency Condition, including, but not limited to, directing Interconnection Customer to shut-down, start-up, increase or decrease the real or reactive power output of the Large Generating Facility; implementing a reduction or disconnection pursuant to Article 13.5.2; directing Interconnection Customer to assist with blackstart (if available) or restoration efforts; or altering the outage schedules of the Large Generating Facility and Interconnection Customer's Interconnection Facilities. Interconnection Customer shall comply with all of Transmission Provider's operating instructions concerning Large Generating Facility real power and reactive power output within the manufacturer's design limitations of the Large Generating Facility's equipment that is in service and physically available for operation at the time, in compliance with Applicable Laws and Regulations.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 378FERC Electric TariffFourth Revised Volume No. 1

13.5.2 Reduction and Disconnection. Transmission Provider may reduce Interconnection Service or disconnect the Large Generating Facility or Interconnection Customer's Interconnection Facilities, when such, reduction or disconnection is necessary under Good Utility Practice due to Emergency Conditions. These rights are separate and distinct from any right of curtailment of Transmission Provider pursuant to Transmission Provider's Tariff. When Transmission Provider can schedule the reduction or disconnection in advance, Transmission Provider shall notify Interconnection Customer of the reasons, timing and expected duration of the reduction or disconnection. Transmission Provider shall coordinate with Interconnection Customer using Good Utility Practice to schedule the reduction or disconnection during periods of least impact to Interconnection Customer and Transmission Provider. Any reduction or disconnection shall continue only for so long as reasonably necessary under Good Utility Practice. The Parties shall cooperate with each other to restore the Large Generating Facility, the Interconnection Facilities, and the Transmission System to their normal operating state as soon as practicable consistent with Good Utility Practice.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 379FERC Electric TariffFourth Revised Volume No. 1

13.6 Interconnection Customer Authority. Consistent with Good Utility Practice and the LGIA and the LGIP, Interconnection Customer may take actions or inactions with regard to the Large Generating Facility or Interconnection Customer's Interconnection Facilities during an Emergency Condition in order to (i) preserve public health and safety, (ii) preserve the reliability of the Large Generating Facility or Interconnection Customer's Interconnection Facilities, (iii) limit or prevent damage, and (iv) expedite restoration of service. Interconnection Customer shall use Reasonable Efforts to minimize the effect of such actions or inactions on the Transmission System and Transmission Provider's Interconnection Facilities. Transmission Provider shall use Reasonable Efforts to assist Interconnection Customer in such actions.

13.7 Limited Liability. Except as otherwise provided in Article 11.6.1 of this LGIA, neither Party shall be liable to the other for any action it takes in responding to an Emergency Condition so long as such action is made in good faith and is consistent with Good Utility Practice.

Article 14. Regulatory Requirements and Governing Law

14.1 Regulatory Requirements. Each Party's obligations under this LGIA shall be subject to its receipt of any required approval or certificate from one or more Governmental Authorities in the form and substance satisfactory to the applying Party, or the Party making any required filings with, or providing notice to, such Governmental Authorities, and the expiration of any time period associated therewith. Each Party shall in good faith seek and use its Reasonable Efforts to obtain such other approvals. Nothing in this LGIA shall require Interconnection Customer to take any action that could result in its inability to obtain, or its loss of, status or exemption under the Federal Power Act, the Public Utility Holding Company Act of 1935, as amended, or the Public Utility Regulatory Policies Act of 1978.

14.2 Governing Law.

14.2.1 The validity, interpretation and performance of this LGIA and each of its provisions shall be governed by the laws of the state where the Point of Interconnection is located, without regard to its conflicts of law principles.

14.2.2 This LGIA is subject to all Applicable Laws and Regulations.

14.2.3 Each Party expressly reserves the right to seek changes in, appeal, or otherwise contest any laws, orders, rules, or regulations of a Governmental Authority.

Article 15. Notices

15.1 General. Unless otherwise provided in this LGIA, any notice, demand or request required or permitted to be given by either Party to the other

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 380FERC Electric TariffFourth Revised Volume No. 1

and any instrument required or permitted to be tendered or delivered by either Party in writing to the other shall be effective when delivered and may be so given, tendered or delivered, by recognized national courier, or by depositing the same with the United States Postal Service with postage prepaid, for delivery by certified or registered mail, addressed to the Party, or personally delivered to the Party, at the address set out in Appendix F, Addresses for Delivery of Notices and Billings.

Either Party may change the notice information in this LGIA by giving five (5) Business Days written notice prior to the effective date of the change.

15.2 Billings and Payments. Billings and payments shall be sent to the addresses set out in Appendix F.

15.3 Alternative Forms of Notice. Any notice or request required or permitted to be given by a Party to the other and not required by this Agreement to be given in writing may be so given by telephone, facsimile or email to the telephone numbers and email addresses set out in Appendix F.

15.4 Operations and Maintenance Notice. Each Party shall notify the other Party in writing of the identity of the person(s) that it designates as the point(s) of contact with respect to the implementation of Articles 9 and 10.

Article 16. Force Majeure

16.1 Force Majeure.

16.1.1 Economic hardship is not considered a Force Majeure event.

16.1.2 Neither Party shall be considered to be in Default with respect to any obligation hereunder, (including obligations under Article 4), other than the obligation to pay money when due, if prevented from fulfilling such obligation by Force Majeure. A Party unable to fulfill any obligation hereunder (other than an obligation to pay money when due) by reason of Force Majeure shall give notice and the full particulars of such Force Majeure to the other Party in writing or by telephone as soon as reasonably possible after the occurrence of the cause relied upon. Telephone notices given pursuant to this article shall be confirmed in writing as soon as reasonably possible and shall specifically state full particulars of the Force Majeure, the time and date when the Force Majeure occurred and when the Force Majeure is reasonably expected to cease. The Party affected shall exercise due diligence to remove such disability with reasonable dispatch, but shall not be required to accede or agree to any provision not satisfactory to it in order to settle and terminate a strike or other labor disturbance.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 381FERC Electric TariffFourth Revised Volume No. 1

Article 17. Default

17.1 Default.

17.1.1 General. No Default shall exist where such failure to discharge an obligation (other than the payment of money) is the result of Force Majeure as defined in this LGIA or the result of an act of omission of the other Party. Upon a Breach, the non-breaching Party shall give written notice of such Breach to the breaching Party. Except as provided in Article 17.1.2, the breaching Party shall have thirty (30) Calendar Days from receipt of the Default notice within which to cure such Breach; provided however, if such Breach is not capable of cure within thirty (30) Calendar Days, the breaching Party shall commence such cure within thirty (30) Calendar Days after notice and continuously and diligently complete such cure within ninety (90) Calendar Days from receipt of the Default notice; and, if cured within such time, the Breach specified in such notice shall cease to exist.

17.1.2 Right to Terminate. If a Breach is not cured as provided in this article, or if a Breach is not capable of being cured within the period provided for herein, the non-breaching Party shall have the right to declare a Default and terminate this LGIA by written notice at any time until cure occurs, and be relieved of any further obligation hereunder and, whether or not that Party terminates this LGIA, to recover from the breaching Party all amounts due hereunder, plus all other damages and remedies to which it is entitled at law or in equity. The provisions of this article will survive termination of this LGIA.

Article 18. Indemnity, Consequential Damages and Insurance

18.1 Indemnity. The Parties shall at all times indemnify, defend, and hold the other Party harmless from, any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other Party's action or inactions of its obligations under this LGIA on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnified Party.

18.1.1 Indemnified Person. If an Indemnified Person is entitled to indemnification under this Article 18 as a result of a claim by a third party, and the indemnifying Party fails, after notice and reasonable opportunity to proceed under Article 18.1, to assume the defense of such claim, such Indemnified Person may at the expense of the indemnifying Party contest, settle or consent to the entry of any judgment with respect to, or pay in full, such claim.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 382FERC Electric TariffFourth Revised Volume No. 1

18.1.2 Indemnifying Party. If an Indemnifying Party is obligated to indemnify and hold any Indemnified Person harmless under this Article 18, the amount owing to the Indemnified Person shall be the amount of such Indemnified Person's actual Loss, net of any insurance or other recovery.

18.1.3 Indemnity Procedures. Promptly after receipt by an Indemnified Person of any claim or notice of the commencement of any action or administrative or legal proceeding or investigation as to which the indemnity provided for in Article 18.1 may apply, the Indemnified Person shall notify the Indemnifying Party of such fact. Any failure of or delay in such notification shall not affect a Party's indemnification obligation unless such failure or delay is materially prejudicial to the indemnifying Party.

The Indemnifying Party shall have the right to assume the defense thereof with counsel designated by such Indemnifying Party and reasonably satisfactory to the Indemnified Person. If the defendants in any such action include one or more Indemnified Persons and the Indemnifying Party and if the Indemnified Person reasonably concludes that there may be legal defenses available to it and/or other Indemnified Persons which are different from or additional to those available to the Indemnifying Party, the Indemnified Person shall have the right to select separate counsel to assert such legal defenses and to otherwise participate in the defense of such action on its own behalf. In such instances, the Indemnifying Party shall only be required to pay the fees and expenses of one additional attorney to represent an Indemnified Person or Indemnified Persons having such differing or additional legal defenses.

The Indemnified Person shall be entitled, at its expense, to participate in any such action, suit or proceeding, the defense of which has been assumed by the Indemnifying Party. Notwithstanding the foregoing, the Indemnifying Party (i) shall not be entitled to assume and control the defense of any such action, suit or proceedings if and to the extent that, in the opinion of the Indemnified Person and its counsel, such action, suit or proceeding involves the potential imposition of criminal liability on the Indemnified Person, or there exists a conflict or adversity of interest between the Indemnified Person and the Indemnifying Party, in such event the Indemnifying Party shall pay the reasonable expenses of the Indemnified Person, and (ii) shall not settle or consent to the entry of any judgment in any action, suit or proceeding without the consent of the Indemnified Person, which shall not be reasonably withheld, conditioned or delayed.

18.2 Consequential Damages. Other than the Liquidated Damages heretofore described, in no event shall either Party be liable

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 383FERC Electric TariffFourth Revised Volume No. 1

under any provision of this LGIA for any losses, damages, costs or expenses for any special, indirect, incidental, consequential, or punitive damages, including but not limited to loss of profit or revenue, loss of the use of equipment, cost of capital, cost of temporary equipment or services, whether based in whole or in part in contract, in tort, including negligence, strict liability, or any other theory of liability; provided, however, that damages for which a Party may be liable to the other Party under another agreement will not be considered to be special, indirect, incidental, or consequential damages hereunder.

18.3 Insurance. Each party shall, at its own expense, maintain in force throughout the period of this LGIA, and until released by the other Party, the following minimum insurance coverages, with insurers authorized to do business in the state where the Point of Interconnection is located:

18.3.1 Employers' Liability and Workers' Compensation Insurance providing statutory benefits in accordance with the laws and regulations of the state in which the Point of Interconnection is located.

18.3.2 Commercial General Liability Insurance including premises and operations, personal injury, broad form property damage, broad form blanket contractual liability coverage (including coverage for the contractual indemnification) products and completed operations coverage, coverage for explosion, collapse and underground hazards, independent contractors coverage, coverage for pollution to the extent normally available and punitive damages to the extent normally available and a cross liability endorsement, with minimum limits of One Million Dollars ($1,000,000) per occurrence/One Million Dollars ($1,000,000) aggregate combined single limit for personal injury, bodily injury, including death and property damage.

18.3.3 Comprehensive Automobile Liability Insurance for coverage of owned and non-owned and hired vehicles, trailers or semi-trailers designed for travel on public roads, with a minimum, combined single limit of One Million Dollars ($1,000,000) per occurrence for bodily injury, including death, and property damage.

18.3.4 Excess Public Liability Insurance over and above the Employers' Liability Commercial General Liability and Comprehensive Automobile Liability Insurance coverage, with a minimum combined single limit of Twenty Million Dollars ($20,000,000) per occurrence/Twenty Million Dollars ($20,000,000) aggregate.

18.3.5 The Commercial General Liability Insurance, Comprehensive Automobile Insurance and Excess Public Liability Insurance policies shall name the other Party, its parent, associated and Affiliate companies and their respective directors, officers, agents, servants and employees ("Other

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 384FERC Electric TariffFourth Revised Volume No. 1

Party Group") as additional insured. All policies shall contain provisions whereby the insurers waive all rights of subrogation in accordance with the provisions of this LGIA against the Other Party Group and provide thirty (30) days advance written notice to the Other Party Group prior to anniversary date of cancellation or any material change in coverage or condition.

18.3.6 The Commercial General Liability Insurance, Comprehensive Automobile Liability Insurance and Excess Public Liability Insurance policies shall contain provisions that specify that the polices are primary and shall apply to such extent without consideration for other policies separately carried and shall state that each insured is provided coverage as though a separate policy had been issues to each, except the insurer's liability shall not be increased beyond the amount for which the insurer would have been liable had only one insured been covered. Each Party shall be responsible for its respective deductibles or retentions.

18.3.7 The Commercial General Liability Insurance, Comprehensive Automobile Liability Insurance and Excess Public Liability Insurance policies, if written on a Claims First Made Basis, shall be maintained in full force and effect for two (2) years after termination of this LGIA, which coverage may be in the form of tail coverage or extended reporting period coverage if agreed by the Parties.

18.3.8 The requirements contained herein as to the types and limits of all insurance to be maintained by the Parties are not intended to and shall not in any manner, limit or qualify the liabilities and obligations assumed by the Parties under this LGIA.

18.3.9 Within ten (10) days following execution of this LGIA, and as soon as practicable after the end of each fiscal year or at the renewal of the insurance policy and in any event within ninety (90) days thereafter, each Party shall provide certification of all insurance required in this LGIA, executed by each insurer or by an authorized representative of each insurer.

18.3.10 Notwithstanding the foregoing, each Party may self-insure to meet the minimum insurance requirements of Articles 18.3.2 through 18.3.8 to the extent it maintains a self-insurance program; provided that, such Party's senior secured debt is rated at investment grade or better by Standard & Poor's and that its self-insurance program meets the minimum insurance requirements of Articles 18.3.2 through 18.3.8. For any period of time that a Party's senior secured debt is unrated by Standard & Poor's or is rated at less than investment grade by Standard & Poor's, such Party shall

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 385FERC Electric TariffFourth Revised Volume No. 1

comply with the insurance requirements applicable to it under Articles 18.3.2 through 18.3.9. In the event that a Party is permitted to self-insure pursuant to this article, it shall notify the other Party that it meets the requirements to self-insure and that its self-insurance program meets the minimum insurance requirements in a manner consistent with that specified in Article 18.3.9.

18.3.11 The Parties agree to report to each other in writing as soon as practical all accidents or occurrences resulting in injuries to any person, including death, and any property damage arising out of this LGIA.

Article 19. Assignment

19.1 Assignment. This LGIA may be assigned by either Party only with the written consent of the other; provided that either Party may assign this LGIA without the consent of the other Party to any Affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this LGIA; and provided further that Interconnection Customer shall have the right to assign this LGIA, without the consent of Transmission Provider, for collateral security purposes to aid in providing financing for the Large Generating Facility, provided that Interconnection Customer will promptly notify Transmission Provider of any such assignment. Any financing arrangement entered into by Interconnection Customer pursuant to this article will provide that prior to or upon the exercise of the secured party's, trustee's or mortgagee's assignment rights pursuant to said arrangement, the secured creditor, the trustee or mortgagee will notify Transmission Provider of the date and particulars of any such exercise of assignment right(s), including providing the Transmission Provider with proof that it meets the requirements of Articles 11.5 and 18.3. Any attempted assignment that violates this article is void and ineffective. Any assignment under this LGIA shall not relieve a Party of its obligations, nor shall a Party's obligations be enlarged, in whole or in part, by reason thereof. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed.

Article 20. Severability

20.1 Severability. If any provision in this LGIA is finally determined to be invalid, void or unenforceable by any court or other Governmental Authority having jurisdiction, such determination shall not invalidate, void or make unenforceable any other provision, agreement or covenant of this LGIA; provided that if Interconnection Customer (or any third party, but only if such third party is not acting at the direction of Transmission Provider) seeks and obtains such a final determination with respect to any provision of the Alternate Option (Article 5.1.2), or the Negotiated Option (Article 5.1.4), then none of these provisions shall thereafter have any force or effect and the Parties' rights and obligations shall be governed solely by the Standard Option (Article 5.1.1).

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 386FERC Electric TariffFourth Revised Volume No. 1

Article 21. Comparability

21.1 Comparability. The Parties will comply with all applicable comparability and code of conduct laws, rules and regulations, as amended from time to time.

Article 22. Confidentiality

22.1 Confidentiality. Confidential Information shall include, without limitation, all information relating to a Party's technology, research and development, business affairs, and pricing, and any information supplied by either of the Parties to the other prior to the execution of this LGIA.

Information is Confidential Information only if it is clearly designated or marked in writing as confidential on the face of the document, or, if the information is conveyed orally or by inspection, if the Party providing the information orally informs the Party receiving the information that the information is confidential.

If requested by either Party, the other Party shall provide in writing, the basis for asserting that the information referred to in this Article 22 warrants confidential treatment, and the requesting Party may disclose such writing to the appropriate Governmental Authority. Each Party shall be responsible for the costs associated with affording confidential treatment to its information.

22.1.1 Term. During the term of this LGIA, and for a period of three (3) years after the expiration or termination of this LGIA, except as otherwise provided in this Article 22, each Party shall hold in confidence and shall not disclose to any person Confidential Information.

22.1.2 Scope. Confidential Information shall not include information that the receiving Party can demonstrate: (1) is generally available to the public other than as a result of a disclosure by the receiving Party; (2) was in the lawful possession of the receiving Party on a non-confidential basis before receiving it from the disclosing Party; (3) was supplied to the receiving Party without restriction by a third party, who, to the knowledge of the receiving Party after due inquiry, was under no obligation to the disclosing Party to keep such information confidential; (4) was independently developed by the receiving Party without reference to Confidential Information of the disclosing Party; (5) is, or becomes, publicly known, through no wrongful act or omission of the receiving Party or Breach of this LGIA; or (6) is required, in accordance with Article 22.1.7 of the LGIA, Order of Disclosure, to be disclosed by any Governmental Authority or is otherwise required to be disclosed by law or subpoena, or is necessary in any legal proceeding establishing rights and obligations under this LGIA. Information designated as Confidential Information will no longer be deemed confidential if the Party that designated the information as confidential notifies the other Party that it no longer is confidential.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 387FERC Electric TariffFourth Revised Volume No. 1

22.1.3 Release of Confidential Information. Neither Party shall release or disclose Confidential Information to any other person, except to its Affiliates (limited by the Standards of Conduct requirements), subcontractors, employees, consultants, or to parties who may be or considering providing financing to or equity participation with Interconnection Customer, or to potential purchasers or assignees of Interconnection Customer, on a need-to-know basis in connection with this LGIA, unless such person has first been advised of the confidentiality provisions of this Article 22 and has agreed to comply with such provisions. Notwithstanding the foregoing, a Party providing Confidential Information to any person shall remain primarily responsible for any release of Confidential Information in contravention of this Article 22.

22.1.4 Rights. Each Party retains all rights, title, and interest in the Confidential Information that each Party discloses to the other Party. The disclosure by each Party to the other Party of Confidential Information shall not be deemed a waiver by either Party or any other person or entity of the right to protect the Confidential Information from public disclosure.

22.1.5 No Warranties. By providing Confidential Information, neither Party makes any warranties or representations as to its accuracy or completeness. In addition, by supplying Confidential Information, neither Party obligates itself to provide any particular information or Confidential Information to the other Party nor to enter into any further agreements or proceed with any other relationship or joint venture.

22.1.6 Standard of Care. Each Party shall use at least the same standard of care to protect Confidential Information it receives as it uses to protect its own Confidential Information from unauthorized disclosure, publication or dissemination. Each Party may use Confidential Information solely to fulfill its obligations to the other Party under this LGIA or its regulatory requirements.

22.1.7 Order of Disclosure. If a court or a Government Authority or entity with the right, power, and apparent authority to do so requests or requires either Party, by subpoena, oral deposition, interrogatories, requests for production of documents, administrative order, or otherwise, to disclose Confidential Information, that Party shall provide the other Party with prompt notice of such request(s) or requirement(s) so that the other Party may seek an appropriate protective order or waive compliance with the terms of this LGIA. Notwithstanding the absence of a protective order or waiver, the Party may disclose such Confidential Information which, in the opinion of its counsel, the Party is legally compelled to disclose. Each Party will use Reasonable Efforts to obtain reliable assurance that

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 388FERC Electric TariffFourth Revised Volume No. 1

confidential treatment will be accorded any Confidential Information so furnished.

22.1.8 Termination of Agreement. Upon termination of this LGIA for any reason, each Party shall, within ten (10) Calendar Days of receipt of a written request from the other Party, use Reasonable Efforts to destroy, erase, or delete (with such destruction, erasure, and deletion certified in writing to the other Party) or return to the other Party, without retaining copies thereof, any and all written or electronic Confidential Information received from the other Party.

22.1.9 Remedies. The Parties agree that monetary damages would be inadequate to compensate a Party for the other Party's Breach of its obligations under this Article 22. Each Party accordingly agrees that the other Party shall be entitled to equitable relief, by way of injunction or otherwise, if the first Party Breaches or threatens to Breach its obligations under this Article 22, which equitable relief shall be granted without bond or proof of damages, and the receiving Party shall not plead in defense that there would be an adequate remedy at law. Such remedy shall not be deemed an exclusive remedy for the Breach of this Article 22, but shall be in addition to all other remedies available at law or in equity. The Parties further acknowledge and agree that the covenants contained herein are necessary for the protection of legitimate business interests and are reasonable in scope. No Party, however, shall be liable for indirect, incidental, or consequential or punitive damages of any nature or kind resulting from or arising in connection with this Article 22.

22.1.10 Disclosure to FERC, its Staff, or a State. Notwithstanding anything in this Article 22 to the contrary, and pursuant to 18 CFR section 1b.20, if FERC or its staff, during the course of an investigation or otherwise, requests information from one of the Parties that is otherwise required to be maintained in confidence pursuant to this LGIA, the Party shall provide the requested information to FERC or its staff, within the time provided for in the request for information. In providing the information to FERC or its staff, the Party must, consistent with 18 CFR section 388.112, request that the information be treated as confidential and non-public by FERC and its staff and that the information be withheld from public disclosure. Parties are prohibited from notifying the other Party to this LGIA prior to the release of the Confidential Information to FERC or its staff. The Party shall notify the other Party to the LGIA when it is notified by FERC or its staff that a request to release Confidential Information has been received by FERC, at which time either of the Parties may respond before such information would be made public, pursuant to 18 CFR section 388.112. Requests from a state regulatory body conducting a

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 389FERC Electric TariffFourth Revised Volume No. 1

confidential investigation shall be treated in a similar manner, consistent with the applicable state rules and regulations.

22.1.11 Subject to the exception in Article 22.1.10, any information that a Party claims is competitively sensitive, commercial or financial information under this LGIA ("Confidential Information") shall not be disclosed by the other Party to any person not employed or retained by the other Party, except to the extent disclosure is (i) required by law; (ii) reasonably deemed by the disclosing Party to be required to be disclosed in connection with a dispute between or among the Parties, or the defense of litigation or dispute; (iii) otherwise permitted by consent of the other Party, such consent not to be unreasonably withheld; or (iv) necessary to fulfill its obligations under this LGIA or as a transmission service provider or a Control Area operator including disclosing the Confidential Information to an RTO or ISO or to a regional or national reliability organization. The Party asserting confidentiality shall notify the other Party in writing of the information it claims is confidential. Prior to any disclosures of the other Party's Confidential Information under this subparagraph, or if any third party or Governmental Authority makes any request or demand for any of the information described in this subparagraph, the disclosing Party agrees to promptly notify the other Party in writing and agrees to assert confidentiality and cooperate with the other Party in seeking to protect the Confidential Information from public disclosure by confidentiality agreement, protective order or other reasonable measures.

Article 23. Environmental Releases

23.1 Each Party shall notify the other Party, first orally and then in writing, of the release of any Hazardous Substances, any asbestos or lead abatement activities, or any type of remediation activities related to the Large Generating Facility or the Interconnection Facilities, each of which may reasonably be expected to affect the other Party. The notifying Party shall: (i) provide the notice as soon as practicable, provided such Party makes a good faith effort to provide the notice no later than twenty-four hours after such Party becomes aware of the occurrence; and (ii) promptly furnish to the other Party copies of any publicly available reports filed with any Governmental Authorities addressing such events.

Article 24. Information Requirements

24.1 Information Acquisition. Transmission Provider and Interconnection Customer shall submit specific information regarding the electrical characteristics of their respective facilities to each other as described below and in accordance with Applicable Reliability Standards.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 390FERC Electric TariffFourth Revised Volume No. 1

24.2 Information Submission by Transmission Provider. The initial information submission by Transmission Provider shall occur no later than one hundred eighty (180) Calendar Days prior to Trial Operation and shall include Transmission System information necessary to allow Interconnection Customer to select equipment and meet any system protection and stability requirements, unless otherwise agreed to by the Parties. On a monthly basis Transmission Provider shall provide Interconnection Customer a status report on the construction and installation of Transmission Provider's Interconnection Facilities and Network Upgrades, including, but not limited to, the following information: (1) progress to date; (2) a description of the activities since the last report" (3) a description of the action items for the next period; and (4) the delivery status of equipment ordered.

24.3 Updated Information Submission by Interconnection Customer. The updated information submission by Interconnection Customer, including manufacturer information, shall occur no later than one hundred eighty (180) Calendar Days prior to the Trial Operation. Interconnection Customer shall submit a completed copy of the Large Generating Facility data requirements contained in Appendix 1 to the LGIP. It shall also include any additional information provided to Transmission Provider for the Feasibility and Facilities Study. Information in this submission shall be the most current Large Generating Facility design or expected performance data. Information submitted for stability models shall be compatible with Transmission Provider standard models. If there is no compatible model, Interconnection Customer will work with a consultant mutually agreed to by the Parties to develop and supply a standard model and associated information.

If Interconnection Customer's data is materially different from what was originally provided to Transmission Provider pursuant to the Interconnection Study Agreement between Transmission Provider and Interconnection Customer, then Transmission Provider will conduct appropriate studies to determine the impact on Transmission Provider Transmission System based on the actual data submitted pursuant to this Article 24.3. The Interconnection Customer shall not begin Trial Operation until such studies are completed.

24.4 Information Supplementation. Prior to the Operation Date, the Parties shall supplement their information submissions described above in this Article 24 with any and all "as-built" Large Generating Facility information or "as-tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Large Generating Facility as required by Good Utility Practice such as an open circuit "step voltage" test on the Large Generating Facility to verify proper operation of the Large Generating Facility's automatic voltage regulator.

Unless otherwise agreed, the test conditions shall include: (1) Large Generating Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode;

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 391FERC Electric TariffFourth Revised Volume No. 1

and (3) a five percent change in Large Generating Facility terminal voltage initiated by a change in the voltage regulators reference voltage. Interconnection Customer shall provide validated test recordings showing the responses of Large Generating Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Large Generating Facility's terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Large Generating Facility terminal or field voltages is provided. Large Generating Facility testing shall be conducted and results provided to Transmission Provider for each individual generating unit in a station.

Subsequent to the Operation Date, Interconnection Customer shall provide Transmission Provider any information changes due to equipment replacement, repair, or adjustment. Transmission Provider shall provide Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Transmission Provider-owned substation that may affect Interconnection Customer's Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Article 25. Information Access and Audit Rights

25.1 Information Access. Each Party (the "disclosing Party") shall make available to the other Party information that is in the possession of the disclosing Party and is necessary in order for the other Party to: (i) verify the costs incurred by the disclosing Party for which the other Party is responsible under this LGIA; and

(ii) carry out its obligations and responsibilities under this LGIA. The Parties shall not use such information for purposes other than those set forth in this Article 25.1 and to enforce their rights under this LGIA.

25.2 Reporting of Non-Force Majeure Events. Each Party (the "notifying Party") shall notify the other Party when the notifying Party becomes aware of its inability to comply with the provisions of this LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this LGIA.

25.3 Audit Rights. Subject to the requirements of confidentiality under Article 22 of this LGIA, each Party shall have the right, during normal business hours, and upon prior reasonable notice to the other Party, to audit at its own expense the other Party's accounts and records pertaining to either Party's performance or either Party's satisfaction of obligations under this LGIA. Such audit rights shall include audits of the other Party's costs, calculation of invoiced amounts,

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 392FERC Electric TariffFourth Revised Volume No. 1

Transmission Provider's efforts to allocate responsibility for the provision of reactive support to the Transmission System, Transmission Provider's efforts to allocate responsibility for interruption or reduction of generation on the Transmission System, and each Party's actions in an Emergency Condition. Any audit authorized by this article shall be performed at the offices where such accounts and records are maintained and shall be limited to those portions of such accounts and records that relate to each Party's performance and satisfaction of obligations under this LGIA. Each Party shall keep such accounts and records for a period equivalent to the audit rights periods described in Article 25.4.

25.4 Audit Rights Periods.

25.4.1 Audit Rights Period for Construction-Related Accounts and Records. Accounts and records related to the design, engineering, procurement, and construction of Transmission Provider's Interconnection Facilities and Network Upgrades shall be subject to audit for a period of twenty-four months following Transmission Provider's issuance of a final invoice in accordance with Article 12.2.

25.4.2 Audit Rights Period for All Other Accounts and Records. Accounts and records related to either Party's performance or satisfaction of all obligations under this LGIA other than those described in Article 25.4.1 shall be subject to audit as follows: (i) for an audit relating to cost obligations, the applicable audit rights period shall be twenty-four months after the auditing Party's receipt of an invoice giving rise to such cost obligations; and (ii) for an audit relating to all other obligations, the applicable audit rights period shall be twenty-four months after the event for which the audit is sought.

25.5 Audit Results. If an audit by a Party determines that an overpayment or an underpayment has occurred, a notice of such overpayment or underpayment shall be given to the other Party together with those records from the audit which support such determination.

Article 26. Subcontractors

26.1 General. Nothing in this LGIA shall prevent a Party from utilizing the services of any subcontractor as it deems appropriate to perform its obligations under this LGIA; provided, however, that each Party shall require its subcontractors to comply with all applicable terms and conditions of this LGIA in providing such services and each Party shall remain primarily liable to the other Party for the performance of such subcontractor.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 393FERC Electric TariffFourth Revised Volume No. 1

26.2 Responsibility of Principal. The creation of any subcontract relationship shall not relieve the hiring Party of any of its obligations under this LGIA. The hiring Party shall be fully responsible to the other Party for the acts or omissions of any subcontractor the hiring Party hires as if no subcontract had been made; provided, however, that in no event shall Transmission Provider be liable for the actions or inactions of Interconnection Customer or its subcontractors with respect to obligations of Interconnection Customer under Article 5 of this LGIA. Any applicable obligation imposed by this LGIA upon the hiring Party shall be equally binding upon, and shall be construed as having application to, any subcontractor of such Party.

26.3 No Limitation by Insurance. The obligations under this Article 26 will not be limited in any way by any limitation of subcontractor's insurance.

Article 27. Disputes

27.1 Submission. In the event either Party has a dispute, or asserts a claim, that arises out of or in connection with this LGIA or its performance, such Party (the "disputing Party") shall provide the other Party with written notice of the dispute or claim ("Notice of Dispute"). Such dispute or claim shall be referred to a designated senior representative of each Party for resolution on an informal basis as promptly as practicable after receipt of the Notice of Dispute by the other Party. In the event the designated representatives are unable to resolve the claim or dispute through unassisted or assisted negotiations within thirty (30) Calendar Days of the other Party's receipt of the Notice of Dispute, such claim or dispute may, upon mutual agreement of the Parties, be submitted to arbitration and resolved in accordance with the arbitration procedures set forth below. In the event the Parties do not agree to submit such claim or dispute to arbitration, each Party may exercise whatever rights and remedies it may have in equity or at law consistent with the terms of this LGIA.

27.2 External Arbitration Procedures. Any arbitration initiated under this LGIA shall be conducted before a single neutral arbitrator appointed by the Parties. If the Parties fail to agree upon a single arbitrator within ten (10) Calendar Days of the submission of the dispute to arbitration, each Party shall choose one arbitrator who shall sit on a three-member arbitration panel. The two arbitrators so chosen shall within twenty (20) Calendar Days select a third arbitrator to chair the arbitration panel. In either case, the arbitrators shall be knowledgeable in electric utility matters, including electric transmission and bulk power issues, and shall not have any current or past substantial business or financial relationships with any party to the arbitration (except prior arbitration). The arbitrator(s) shall provide each of the Parties an opportunity to be heard and, except as otherwise provided herein, shall conduct the arbitration in accordance with the Commercial Arbitration Rules of the American Arbitration Association ("Arbitration Rules") and any applicable FERC regulations or RTO rules; provided, however, in the event of a conflict between the Arbitration Rules and the terms of this Article 27, the terms of this Article 27 shall prevail.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 394FERC Electric TariffFourth Revised Volume No. 1

27.3 Arbitration Decisions. Unless otherwise agreed by the Parties, the arbitrator(s) shall render a decision within ninety (90) Calendar Days of appointment and shall notify the Parties in writing of such decision and the reasons therefor. The arbitrator(s) shall be authorized only to interpret and apply the provisions of this LGIA and shall have no power to modify or change any provision of this Agreement in any manner. The decision of the arbitrator(s) shall be final and binding upon the Parties, and judgment on the award may be entered in any court having jurisdiction. The decision of the arbitrator(s) may be appealed solely on the grounds that the conduct of the arbitrator(s), or the decision itself, violated the standards set forth in the Federal Arbitration Act or the Administrative Dispute Resolution Act. The final decision of the arbitrator must also be filed with FERC if it affects jurisdictional rates, terms and conditions of service, Interconnection Facilities, or Network Upgrades.

27.4 Costs. Each Party shall be responsible for its own costs incurred during the arbitration process and for the following costs, if applicable: (1) the cost of the arbitrator chosen by the Party to sit on the three member panel and one half of the cost of the third arbitrator chosen; or (2) one half the cost of the single arbitrator jointly chosen by the Parties.

Article 28. Representations, Warranties, and Covenants

28.1 General. Each Party makes the following representations, warranties and covenants:

28.1.1 Good Standing. Such Party is duly organized, validly existing and in good standing under the laws of the state in which it is organized, formed, or incorporated, as applicable; that it is qualified to do business in the state or states in which the Large Generating Facility, Interconnection Facilities and Network Upgrades owned by such Party, as applicable, are located; and that it has the corporate power and authority to own its properties, to carry on its business as now being conducted and to enter into this LGIA and carry out the transactions contemplated hereby and perform and carry out all covenants and obligations on its part to be performed under and pursuant to this LGIA.

28.1.2 Authority. Such Party has the right, power and authority to enter into this LGIA, to become a party hereto and to perform its obligations hereunder. This LGIA is a legal, valid and binding obligation of such Party, enforceable against such Party in accordance with its terms, except as the enforceability thereof may be limited by applicable bankruptcy, insolvency, reorganization or other similar laws affecting creditors' rights generally and by general equitable principles (regardless of whether enforceability is sought in a proceeding in equity or at law).

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 395FERC Electric TariffFourth Revised Volume No. 1

28.1.3 No Conflict. The execution, delivery and performance of this LGIA does not violate or conflict with the organizational or formation documents, or bylaws or operating agreement, of such Party, or any judgment, license, permit, order, material agreement or instrument applicable to or binding upon such Party or any of its assets.

28.1.4 Consent and Approval. Such Party has sought or obtained, or, in accordance with this LGIA will seek or obtain, each consent, approval, authorization, order, or acceptance by any Governmental Authority in connection with the execution, delivery and performance of this LGIA, and it will provide to any Governmental Authority notice of any actions under this LGIA that are required by Applicable Laws and Regulations.

Article 29. Joint Operating Committee

29.1 Joint Operating Committee. Except in the case of ISOs and RTOs, Transmission Provider shall constitute a Joint Operating Committee to coordinate operating and technical considerations of Interconnection Service. At least six (6) months prior to the expected Initial Synchronization Date, Interconnection Customer and Transmission Provider shall each appoint one representative and one alternate to the Joint Operating Committee. Each Interconnection Customer shall notify Transmission Provider of its appointment in writing. Such appointments may be changed at any time by similar notice. The Joint Operating Committee shall meet as necessary, but not less than once each calendar year, to carry out the duties set forth herein. The Joint Operating Committee shall hold a meeting at the request of either Party, at a time and place agreed upon by the representatives. The Joint Operating Committee shall perform all of its duties consistent with the provisions of this LGIA. Each Party shall cooperate in providing to the Joint Operating Committee all information required in the performance of the Joint Operating Committee's duties. All decisions and agreements, if any, made by the Joint Operating Committee, shall be evidenced in writing. The duties of the Joint Operating Committee shall include the following:

29.1.1 Establish data requirements and operating record requirements.

29.1.2 Review the requirements, standards, and procedures for data acquisition equipment, protective equipment, and any other equipment or software.

29.1.3 Annually review the one (1) year forecast of maintenance and planned outage schedules of Transmission Provider's and Interconnection Customer's facilities at the Point of Interconnection.

29.1.4 Coordinate the scheduling of maintenance and planned outages on the Interconnection Facilities, the Large Generating Facility and other

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 396FERC Electric TariffFourth Revised Volume No. 1

facilities that impact the normal operation of the interconnection of the Large Generating Facility to the Transmission System.

29.1.5 Ensure that information is being provided by each Party regarding equipment availability.

29.1.6 Perform such other duties as may be conferred upon it by mutual agreement of the Parties.

Article 30. Miscellaneous

30.1 Binding Effect. This LGIA and the rights and obligations hereof, shall be binding upon and shall inure to the benefit of the successors and assigns of the Parties hereto.

30.2 Conflicts. In the event of a conflict between the body of this LGIA and any attachment, appendices or exhibits hereto, the terms and provisions of the body of this LGIA shall prevail and be deemed the final intent of the Parties.

30.3 Rules of Interpretation. This LGIA, unless a clear contrary intention appears, shall be construed and interpreted as follows: (1) the singular number includes the plural number and vice versa; (2) reference to any person includes such person's successors and assigns but, in the case of a Party, only if such successors and assigns are permitted by this LGIA, and reference to a person in a particular capacity excludes such person in any other capacity or individually; (3) reference to any agreement (including this LGIA), document, instrument or tariff means such agreement, document, instrument, or tariff as amended or modified and in effect from time to time in accordance with the terms thereof and, if applicable, the terms hereof; (4) reference to any Applicable Laws and Regulations means such Applicable Laws and Regulations as amended, modified, codified, or reenacted, in whole or in part, and in effect from time to time, including, if applicable, rules and regulations promulgated thereunder; (5) unless expressly stated otherwise, reference to any Article, Section or Appendix means such Article of this LGIA or such Appendix to this LGIA, or such Section to the LGIP or such Appendix to the LGIP, as the case may be; (6) "hereunder", "hereof", "herein", "hereto" and words of similar import shall be deemed references to this LGIA as a whole and not to any particular Article or other provision hereof or thereof; (7) "including" (and with correlative meaning "include") means including without limiting the generality of any description preceding such term; and (8) relative to the determination of any period of time, "from" means "from and including", "to" means "to but excluding" and "through" means "through and including".

30.4 Entire Agreement. This LGIA, including all Appendices and Schedules attached hereto, constitutes the entire agreement between the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between the Parties with respect to the subject matter of this LGIA. There are no other agreements,

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 397FERC Electric TariffFourth Revised Volume No. 1

representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, either Party's compliance with its obligations under this LGIA.

30.5 No Third Party Beneficiaries. This LGIA is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and, where permitted, their assigns.

30.6 Waiver. The failure of a Party to this LGIA to insist, on any occasion, upon strict performance of any provision of this LGIA will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party.

Any waiver at any time by either Party of its rights with respect to this LGIA shall not be deemed a continuing waiver or a waiver with respect to any other failure to comply with any other obligation, right, duty of this LGIA. Termination or Default of this LGIA for any reason by Interconnection Customer shall not constitute a waiver of Interconnection Customer's legal rights to obtain an interconnection from Transmission Provider. Any waiver of this LGIA shall, if requested, be provided in writing.

30.7 Headings. The descriptive headings of the various Articles of this LGIA have been inserted for convenience of reference only and are of no significance in the interpretation or construction of this LGIA.

30.8 Multiple Counterparts. This LGIA may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument.

30.9 Amendment. The Parties may by mutual agreement amend this LGIA by a written instrument duly executed by the Parties.

30.10 Modification by the Parties. The Parties may by mutual agreement amend the Appendices to this LGIA by a written instrument duly executed by the Parties. Such amendment shall become effective and a part of this LGIA upon satisfaction of all Applicable Laws and Regulations.

30.11 Reservation of Rights. Transmission Provider shall have the right to make a unilateral filing with FERC to modify this LGIA with respect to any rates, terms and conditions, charges, classifications of service, rule or regulation under section 205 or any other applicable provision of the Federal Power Act and FERC's rules and regulations thereunder, and Interconnection Customer shall have the right to make a unilateral filing with FERC to modify this LGIA pursuant to section 206 or any other applicable provision of the Federal Power Act and FERC's rules and regulations thereunder; provided that each Party shall have the right to protest any such filing by the other Party and to participate fully in any proceeding before FERC in which such modifications may be considered. Nothing in this LGIA shall limit the rights of the Parties or of FERC under sections 205 or 206 of the Federal Power Act and FERC's rules

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 398FERC Electric TariffFourth Revised Volume No. 1

and regulations thereunder, except to the extent that the Parties otherwise mutually agree as provided herein.

30.12 No Partnership. This LGIA shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership between the Parties or to impose any partnership obligation or partnership liability upon either Party. Neither Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, the other Party.

IN WITNESS WHEREOF, the Parties have executed this LGIA in duplicate originals, each of which shall constitute and be an original effective Agreement between the Parties.

[Insert name of Transmission Provider or Transmission Owner, if applicable]

By: ________________________ By: ______________________________

Title: ________________________ Title: ______________________________

Date: ______________________________ Date: ______________________________

[Insert name of Interconnection Customer]

By: ________________________

Title: ________________________

Date: ________________________

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 399FERC Electric TariffFourth Revised Volume No. 1

APPENDIX A TO LGIA

Interconnection Facilities, Network Upgrades and Distribution Upgrades

1. Interconnection Facilities:

(a) [insert Interconnection Customer's Interconnection Facilities]:

(b) [insert Transmission Provider's Interconnection Facilities]:

2. Network Upgrades:

(a) [insert Stand Alone Network Upgrades]:

(b) [insert Other Network Upgrades]:

3. Distribution Upgrades:

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 400FERC Electric TariffFourth Revised Volume No. 1

Appendix B to LGIA

Milestones

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 401FERC Electric TariffFourth Revised Volume No. 1

APPENDIX C TO LGIA

Interconnection Details

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 402FERC Electric TariffFourth Revised Volume No. 1

Appendix D to LGIA

Security Arrangements Details

Infrastructure security of Transmission System equipment and operations and control hardware and software is essential to ensure day-to-day Transmission System reliability and operational security. FERC will expect all Transmission Providers, market participants, and Interconnection Customers interconnected to the Transmission System to comply with the recommendations offered by the President's Critical Infrastructure Protection Board and, eventually, best practice recommendations from the electric reliability authority. All public utilities will be expected to meet basic standards for system infrastructure and operational security, including physical, operational, and cyber-security practices.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 403FERC Electric TariffFourth Revised Volume No. 1

Appendix E to LGIA

Commercial Operation Date

This Appendix E is a part of the LGIA between Transmission Provider and Interconnection Customer.

[Date]

[Transmission Provider Address]

Re: _____________ Large Generating Facility

Dear _______________:

On [Date] [Interconnection Customer] has completed Trial Operation of Unit No. ___. This letter confirms that [Interconnection Customer] commenced Commercial Operation of Unit No. ___ at the Large Generating Facility, effective as of [Date plus one day].

Thank you.

[Signature]

[Interconnection Customer Representative]

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 404FERC Electric TariffFourth Revised Volume No. 1

Appendix F to LGIA

ADDRESSES FOR DELIVERY OF NOTICES AND BILLINGS

Notices:.

Transmission Provider:

[To be supplied.]

Interconnection Customer:

[To be supplied.]

Billings and Payments:

Transmission Provider:

[To be supplied.]

Interconnection Customer:

[To be supplied.]

Alternative Forms of Delivery of Notices (telephone, facsimile or email):

Transmission Provider:

[To be supplied.]

Interconnection Customer:

[To be supplied.]

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 405FERC Electric TariffFourth Revised Volume No. 1

Appendix G to LGIA

REQUIREMENTS OF GENERATORS RELYING ON NEWER TECHNOLOGIES

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 406FERC Electric TariffFourth Revised Volume No. 1

AGREEMENT FOR THE ALLOCATIONOF RESPONSIBILITIES WITH REGARD TO

LARGE GENERATOR INTERCONNECTION PROCEDURES AND INTERCONNECTION AGREEMENT

This Agreement for the Allocation of Responsibilities With Regard to Large Generator

Interconnection Procedures and Interconnection Agreement (“Agreement”), dated April ___,

2004, is entered into between Southwest Power Pool, Inc. (“SPP” or “Transmission Provider”)

and the Transmission-Owning Members of SPP (“Transmission Owners”) that have executed

this Agreement. SPP and the Transmission Owners are jointly referred to as the “Parties” and

individually, as a “Party.”

BACKGROUND

WHEREAS, SPP administers the provision of open access transmission service as

Transmission Provider under the terms and conditions of the SPP Open Access Transmission

Tariff (“SPP Tariff”) on file with the FERC;

WHEREAS, SPP has applied for, and conditionally received, approval from the Federal

Energy Regulatory Commission (“Commission” or “FERC”) to function as a Regional

Transmission Organization (“RTO”);

WHEREAS, the FERC, in Order No. 2003, Standardization of Generator Interconnection

Agreements and Procedures, FERC Stats. & Regs. ¶ 31,146 (2003), order on reh’g, Order No.

2003-A, 106 FERC ¶ 61,220 (2004), required amendment of open access transmission tariffs to

include Large Generator Interconnection Procedures (“LGIP”) and a pro forma Large Generator

Interconnection Agreement (“LGIA”), both applicable to Generating Facilities that exceed 20

megawatts;

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 407FERC Electric TariffFourth Revised Volume No. 1

WHEREAS, on January 20, 2004, SPP submitted revisions to the SPP Tariff, including

LGIP and a pro forma LGIA, intended to implement Order No. 2003 (“Order No. 2003

Compliance Filing”);

WHEREAS, on March 19, 2004, the FERC accepted SPP’s Order No. 2003 Compliance

Filing subject to suspension, to become effective August 21, 2004, or upon an earlier date as may

be specified by the FERC, and required SPP to adopt the LGIP and pro forma LGIA set forth in

Order No. 2003 (Southwest Power Pool, Inc., 106 FERC ¶ 61,254 (2004) (“March 19 Order”));

and

WHEREAS, as the FERC recognized in the March 19 Order, the LGIP and pro forma

LGIA set forth in Order No. 2003 do not allocate responsibilities between transmission owners

and transmission providers for the provision of Interconnection Service and suggested that SPP

and the SPP Transmission Owners enter into any agreement to allocate those responsibilities.

NOW THEREFORE, SPP and the Transmission Owners that have executed this

agreement agree to the following allocations of responsibilities:

I. DEFINITIONS.

Unless otherwise defined herein, all capitalized terms shall have the meaning set forth in

the SPP Tariff.

II. TERM OF AGREEMENT.

This Agreement shall become effective as of January 20, 2004, and shall remain in effect

until the FERC allows SPP’s Order No. 2003 Compliance Filing as it may be amended or revised

or any subsequent filing that includes an allocation of responsibilities

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Substitute Original Sheet No. 408FERC Electric Tariff Superseding Original Sheet No. 408Fourth Revised Volume No. 1

with regard to Generator Interconnection Procedures and Interconnection Agreement to take

effect.

III PROVISIONS FOR ALLOCATION OF RESPONSIBILITIES BETWEEN SPP AND THE TRANSMISSION OWNERS.

1.0 Interconnection Service: The Parties recognize that the Transmission Provider will

provide Interconnection Service pursuant to applicable terms of the SPP Tariff, and in

particular, the Provisions of Attachment V, Standard Large Generator Interconnection

Procedures and Agreement, as such provisions may be amended from time to time.

Interconnection Service provides for the interconnection of the Interconnection

Customer’s Generating Facility with the Transmission System. The Parties also

recognize that while SPP is the Transmission Provider under the SPP Tariff, SPP does

not own any Transmission Facilities, and Transmission Owners own the facilities to

which Large Generation Facilities are to be interconnected, and that the Transmission

Owners may construct or modify facilities to allow the interconnection. While the Parties

recognize that the Transmission Provider will be primarily responsible for undertaking

Interconnection Studies and similar studies, and for transmission planning, Transmission

Owners will be allowed to participate in these studies and activities to the extent

consistent with the terms of the SPP Tariff. The Parties also recognize that construction

activities and other construction-related matters may involve and be negotiated by the

Transmission Provider, the applicable Transmission Owners, and by the

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: June 29, 2004 Effective: April 26, 2004Filed to comply with order of the Federal Energy Regulatory Commission,Docket No. ER04-434-001, issued June 21, 2004, 107 FERC ¶ 61,286.

Southwest Power Pool Original Sheet No. 409FERC Electric TariffFourth Revised Volume No. 1

Interconnection Customer. SPP shall not enter into any Interconnection Agreement with

an Interconnection Customer that is contrary to these rights.

2.0 Conflicts Between Agreements:

In the event of any conflict between provisions of this Agreement and an individual

Interconnection Agreement entered into between SPP and an Interconnection Customer,

the provisions of that individual Interconnection Agreement shall control.

3.0 Transmission Owners’ Right to Participation in Studies, Committees and Meetings:

3.1 In the event that an Interconnection Customer proposes to interconnect a Large

Generation Facility with a Transmission Owner’s facilities, or a Transmission

Owner is an Owner of an Affected System, that Owner shall have the right to

participate in any Interconnection Facilities Study, Interconnection Feasibility

Study, Interconnection System Impact Study, or any other study undertaken in

connection with such request for Interconnection Service, to the extent necessary

to facilitate such Interconnection. Such Transmission Owner or Owners shall also

have the right to be a party to any Interconnection Facilities Study Agreement,

Interconnection Feasibility Study Agreement, Interconnection System Impact

Study Agreement, or any other agreement to perform studies, to the extent

necessary to facilitate such Interconnection.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 410FERC Electric TariffFourth Revised Volume No. 1

3.2 In the event that an Interconnection Customer proposes to interconnect a Large

Generation Facility with a Transmission Owner’s facilities, or a Transmission

Owner is an Owner of an Affected System, that Owner shall have the right to

participate in the following committees and meetings established pursuant to the

SPP LGIP and/or pro forma LGIA: the Joint Operating Committee, Scoping

Meetings.

4.0 Performance Standards: Each Party shall perform all of its obligations under the Large

Generator Interconnection Procedures and Interconnection Agreement in accordance with

Applicable Laws and Regulations, Applicable Reliability Standards, and Good Utility

Practice, and to the extent a Party is required or prevented or limited in taking any action

by such regulations and standards, such Party shall not be deemed to be in Breach of the

Interconnection Agreement for its compliance therewith. If such Party is the

Transmission Provider or Transmission Owner, the Interconnection Agreement shall be

amended and submitted to FERC for approval.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 410AFERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT W

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

1

GRDA/KAMO Generation Participation

Grand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

2 East MiamiGrand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

3 OMPA GenerationGrand River Dam Authority

Oklahoma Municipal Power Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

4 City of Springfield, MoGrand River Dam Authority

City Utilities of Springfield, MO Point To Point

Through 12/31/2010 with rollover provisions thereafter

5Byng & Chickasaw Nation

Grand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

6 City of SkiatookGrand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

7345/KV Transmission Agreement

Grand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

8345/KV Transmission Agreement

Grand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

9 OMPA GenerationGrand River Dam Authority

Oklahoma Municipal Power Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

10 WFEC/BANKGrand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410BFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

11 WFEC/BANKGrand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

12 City of Poplar BluffGrand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

13 City of ParagouldGrand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

14

CSWS/GRDA Network Load/Ramona

Grand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

15

CSWS/GRDA Network Load/Pryor Others

Grand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2010 with rollover provisions thereafter

16

AECI/GRDA Interconnect Agreement

Grand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2002 with rollover provisions thereafter

17

AECI/GRDA Interconnect Agreement

Grand River Dam Authority

Grand River Dam Authority Point To Point

Through 12/31/2002 with rollover provisions thereafter

18

Agreement between Western Farmers Electric Cooperative and the Anadarko Public Works Authority, Anadarko, Oklahoma

Western Farmers Electric Cooperative

Anadarko, Oklahoma Public Works Authority

All requirements wholesale power supply agreement

Agreement shall remain in effect until cancelled by either party giving written notice to the other delivered at least two years prior to July 31, 2007, or thereafter upon one years' written notice on any annual anniversary of agreement.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410CFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

19

Agreement between Western Farmers Electric Cooperative and the Broken Bow Public Works Authority, Broken Bow, Oklahoma

Western Farmers Electric Cooperative

Broken Bow, Oklahoma Public Works Authority

All requirements wholesale power supply agreement

Agreement shall remain in effect until cancelled by either party giving written notice to the other delivered at least two years prior to December 31, 2004, or thereafter upon one years' written notice on any annual anniversary of agreement.

20

Agreement between Western Farmers Electric Cooperative and the Clarksville Light and Water Co.

Western Farmers Electric Cooperative

Clarksville, Arkansas Light and Water Co.

All requirements wholesale power supply agreement

Agreement shall remain in effect until cancelled by either party giving written notice to the other delivered at least one years prior to May 31, 2003, or thereafter upon one years' written notice on any annual anniversary of agreement.

21

Agreement between Western Farmers Electric Cooperative and the New Cordell Utility Authority, Cordell, Oklahoma

Western Farmers Electric Cooperative

New Cordell Utility Authority

All requirements wholesale power supply agreement

Agreement shall remain in effect until cancelled by either party giving written notice to the other delivered at least two years prior to August 31, 2007, or thereafter upon one years' written notice on any annual anniversary of agreement.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410DFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

22

Interchange Agreement between Western Farmers Electric Cooperative and the City of Electra, Texas

Western Farmers Electric Cooperative City of Electra, Texas

All requirements wholesale power supply agreement

Agreement shall remain in effect until cancelled by either party giving written notice to the other delivered at least two years prior to May 31, 2007, or thereafter upon one years' written notice on any annual anniversary of agreement.

23

Wholesale Power Contract with Member Cooperatives

Western Farmers Electric Cooperative

Western Farmers Electric Cooperative and its Member Co-ops

All requirements wholesale power supply agreement (currently approximately 800 MW)

Agreement shall continue in effect until July 1, 2025, and thereafter until terminated by either party's giving to the other not less than six months' written notice of its desire to terminate.

24

Agreement between Western Farmers Electric Cooperative and the Mooreland Public Works Authority, Mooreland, Oklahoma

Western Farmers Electric Cooperative

Morland Public Works Authority

All requirements wholesale power supply agreement

Agreement shall remain in effect until cancelled by either party giving written notice to the other delivered at least one years prior to March 31, 2007, or thereafter upon one years' written notice on any annual anniversary of agreement.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410EFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

25

Transmission Service and Coordination Agreement

Western Farmers Electric Company

Oklahoma Municipal Power Authority

Network Integration and Long-Term Point-to-Point Transmission Service Agreement executed before February 1, 2000

Agreement shall remain in effect until cancelled by either party giving written notice to the other delivered at least four years prior to the end of the initial term or four years prior to such later specified date for termination.

26

Agreement between Western Farmers Electric Cooperative and the City of Watonga, Oklahoma

Western Farmers Electric Company

City of Watonga, Oklahoma

All requirements wholesale power supply agreement

Agreement shall remain in effect until cancelled by either party giving written notice to the other delivered at least one years prior to March 31, 2007, or thereafter upon one years' written notice on any annual anniversary of agreement.

27

Transmission Service Agreement between Southwestern Electric Power Company and City of Lafayette, Louisiana

Southwestern Electric Power Company

City of Lafayette, Louisiana n/a year-to-year

28

Transmission Service Agreement between KAMO Electric Cooperative, Inc. and Public Service Company of Oklahoma

Public Service Company of Oklahoma

KAMO Electric Cooperative, Inc. n/a year-to-year

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410FFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

29

Contract for Electric Service between Public Service Company of Oklahoma and South Coffeyville Public Works Authority

Public Service Company of Oklahoma

City of S. Coffeyville, Oklahoma n/a year-to-year

30

Transmission Service Agreement between Public Service Company of Oklahoma and Southwestern Public Service Company

Public Service Company of Oklahoma

Southwestern Public Service Company n/a

31

Agreement for Interchange of Electric Power and Energy between PSO and the United States of America, acting through the Secretary of Energy as presented by the Administrator, Southwestern Power Administration

Public Service Company of Oklahoma

Southwestern Power Administration n/a -

32

Contract for Electric Service between Public Service Company of Oklahoma and City of Collinsville, Oklahoma

Public Service Company of Oklahoma

City of Collinsville, Oklahoma n/a year-to-year

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410GFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

33

Electric System Interconnection Agreement Between Cajun Electric Power Cooperative, Inc. and Southwestern Electric Power Company

Southwestern Electric Power Company Louisiana Generation n/a year-to-year

34

Transmission Service Agreement between Western Farmers Electric Cooperative and Public Service Company of Oklahoma

Public Service Company of Oklahoma

Western Farmers Electric Cooperative n/a "network type"

year-to-year after 5/31/03 with 24 month notice to terminate

35

Power Supply Agreement between Southwestern Electric Power Co. and City of Minden, Louisiana

Southwestern Electric Power Company City of Minden, Louisiana

Network(via SWE) year-to-year

36

System Network Integration Service and Network Operating Agreement

Southwestern Electric Power Company

East Texas Electric Cooperative

Service Agreement No. 456 Network 12/31/2004

37

System Network Integration Service and Network Operating Agreement

Southwestern Electric Power Company

Northeast Texas Electric Cooperative

Service Agreement No. 398 Network 12/31/2004

38

Contract for Electric ServiceContract No. 3950003

Public Service Company of Oklahoma

Northeast Oklahoma Electric Cooperative, Inc. n/a

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410HFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

39

Amended Agreement for Interchange of Electric Power and Energy between Grand River Dam Authority and Public Service Company of Oklahoma

Public Service Company of Oklahoma

Grand River Dam Authority n/a until canceled

40

Amended Agreement for Interchange of Electric Power and Energy between Grand River Dam Authority and Public Service Company of Oklahoma

Grand River Dam Authority

Public Service Company of Oklahoma n/a until canceled

41Network Service Agreement

Central and Southwest Services Operating Companies

Oklahoma Municipal Power Authority Network

Dec. 31, 2003 with evergreen and twelve-month notice.

42

Agreement for Purchase and Sale of Electric Power and Energy between Southwestern Electric Power Co. and City of Hope, Arkansas

Southwestern Electric Power Company City of Hope, Arkansas n/a year-to-year

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410IFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

43

Flint Creek Power Plant Power Coordination, Interchange and Transmission Service Agreement between Arkansas Electric Cooperative Corporation and Southwestern Electric Power Company

Southwestern Electric Power Company

Arkansas Electric Cooperative Corporation 72 "network like"

year-to-year, but notice has been given.

44

Power Supply Agreement between Southwestern Electric Power Co. and City of Bentonville, Arkansas

Southwestern Electric Power Company

City of Bentonville, Arkansas n/a year-to-year

45

Power Supply Agreement between Southwestern Electric Power Co. and Tex-La Electric Cooperative of Texas, Inc.

Southwestern Electric Power Company

Tex-La Electric Cooperative of Texas 110

Network-like bundled svc. 12-31-04 (transmission)

46

Power Supply Agreement between Southwestern Electric Power Co. and Rayburn Country Electric Cooperative

Southwestern Electric Power Company Rayburn Country

Network-like bundled svc. year-to-year

47

Firm Point to Point Transmission Service Agreement

Central and Southwest Services Operating Companies City of Coffeyville, KS Point To Point none

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410JFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

48Network Service Agreement

Central and Southwest Services Operating Companies

Public Service Company of Oklahoma, Southwestern Electric Power Company Network year-to-year

49

Service Agreement For Network Integration Transmission Service Between South Plains Electric Cooperative, Inc and Southwestern Public Service Company

Southwestern Public Service Company

South Plains Electric Cooperative

Service Agreement No. 161 under FERC Electric Tariff, Second Revised Volume No. 1 Network

Year-to-year unless terminated by either party

50

Service Agreement For Network Integration Transmission Service Between Golden Spread Electric Cooperative, Inc. and Southwestern Public Service Company

Southwestern Public Service Company

Golden Spread Electric Cooperative

Service Agreement No. 151 under FERC Electric Tariff, Second Revised Volume No. 1 Network

Year-to-year unless terminated by either party

51

Interconnection Agreement between Public Service Company of New Mexico and Southwestern Public Service Company

Southwestern Public Service Company

Public Service Company of New Mexico

FERC Rate Schedule No. 102 Point To Point

Year-to-year unless terminated by either party

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410KFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

52

Electric Power Service Agreement between the Empire District Electric Company and Southwestern Public Service Company

Southwestern Public Service Company

Empire District Electric Company

FERC Rate Schedule No. 124Point To Point

Year-to-year unless terminated by either party

53

CONTRACT FOR THE SALE AND PURCHASE OF ELECTRIC POWER AND ENERGY between CITY OF SPRINGFIELD, MISSOURI and CITY OF FULTON, MISSOURI

City Utilities of Springfield, MO Fulton, MO Point To Point Yes

54

SPRINGFIELD - MALDEN POWER SALE AGREEMENT

City Utilities of Springfield, MO Malden, MO Point To Point Yes

55

ELECTRICAL POWER SUPPLY AGREEMENT BETWEEN MISSOURI JOINT MUNICIPAL ELECTRIC UTILITY COMMISSION AND CITY UTILITIES OF SPRINGFIELD, MISSOURI

City Utilities of Springfield, MO MJMEUC Point To Point Yes

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410LFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

56

ELECTRICAL CAPACITY, ENERGY, AND SERVICE SALES AGREEMENT BETWEEN CITIES OF NIXA AND SPRINGFIELD, MISSOURI

City Utilities of Springfield, MO Nixa, MO Point To Point Yes

57

AMENDED INTERCHANGE AGREEMENT BY AND AMONG ASSOCIATED ELECTRIC COOPERATIVE, INC., THE EMPIRE DISTRICT ELECTRIC COMPANY, GRAND RIVER DAM AUTHORITY, SOUTHWESTERN ELECTRIC POWER COMPANY, AND BOARD OF PUBLIC UTILITIES OF SPRINGFIELD, MISSOURI FOR THE GRDA COAL PLANT - FLINT CREEK POWER PLANT – BROOKLINE – MORGAN 345 KILOVOLT Point To Point

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410MFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination ProvisionsINTERCONNECTION

58

UNITED STATES DEPARTMENT OF ENERGY SOUTHWESTERN POWER ADMINISTRATION POWER SALES CONTRACT between UNITED STATES OF AMERICA and BOARD OF PUBLIC UTILITIES OF THE CITY OF SPRINGFIELD,

City Utilities of Springfield, MO

Southwestern Power Administration Point To Point 6/30/2015

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410NFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination ProvisionsMISSOURI

59

GRDA Bulk Transmission Service Contract

Grand River Dam Authority

Oklahoma Municipal Power Authority

Grand River Dam Authority agrees to receive and deliver energy and power pursuant to Section of the Unit Power Sales Agreement.

Contract will terminate when Unit Power Sales Agreement is no longer in effect.

60

Public Service Company of Oklahoma Interconnection and Power Supply Agreement

Public Service Company of Oklahoma

Oklahoma Municipal Power Authority

Transmission interconnections.

Either party may terminate on the anniversary of this agreement having given the other party 6 years written notice of its intention to terminate.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410OFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

61 Oklahoma Gas and Electric Company

Oklahoma Gas and Electric Co

Oklahoma Municipal Power Authority

Firm transmission supporting an agreement by OMPA to purchase power from OGE.

Requires mutual agreement.

62 Transmission Service Contract

Ponca City Utility Authority

Oklahoma Municipal Power Authority

Ponca City Utility Authority agrees to receive power energy not to exceed the Interconnection Capacity.

May be terminated by either party after December 31, 2014, on any December 31st with a 5 year prior written notice to the other party.

63SPA Transmission Service Contract

Southwestern Power Administration

Oklahoma Municipal Power Authority

Either party can terminate the contract provided they give 30 days notice to the other party.

64

Oklaunion Unit No. 1 Transmission (OKTS) Service Schedule

Public Service Company of Oklahoma

Oklahoma Municipal Power Authority

Firm power transmission service from the SPP side of the North HVDC Interconnection.

65

SWEPCO Transmission Service Agreement

Southwestern Electric Power Co

Oklahoma Municipal Power Authority

Transmission of the power and energy from generating units.

Agreement in effect as long as Ownership Agreement in either generating unit remains in effect.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410PFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

66

HVDC-TS Transmission Service Agreement

Public Service Co Oklahoma

Oklahoma Municipal Power Authority

Transmission of electric power at 60 Hertz, 3 phase, through the HVDC Tie.

67WFEC Transmission Service Agreement

Western Farmers Electric Cooperative

Oklahoma Municipal Power Authority

Long term firm transmission agreement allowing for delivery of power and energy from OMPA Network Resources to OMPA Network Load located in Western Farmers load control area Mutual Agreement.

68WTU Transmission Service Agreement West Texas Utilities

Oklahoma Municipal Power Authority

Transmission for the unit capacity entitlement in Oklaunion Unit No. 1 to the south terminal of the Oklaunion HVDC Tie.

Cessation of Oklaunion Unit No. 1 in terms of ownership or abandon and retirement.

69

Coordination Transmission Service Agreement

Southwestern Electric Power Co and Public Service Co of Oklahoma

Oklahoma Municipal Power Authority Mutual Agreement.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410QFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

70

Hydro Peaking Power Purchase contract - BPU and EDE

Empire District Electric Company

Board of Public Utilities, Kansas City , KS Point To Point 3 years after written notice

71

Hydro Peaking Power Purchase contract - Higginsville and EDE

Empire District Electric Company Higginsville, MO Point To Point 3 years after written notice

72

Hydro Peaking Power Purchase contract - KMEA and EDE

Empire District Electric Company KMEA Point To Point 3 years after written notice

73

Hydro Peaking Power Purchase contract - Kaw Valley and EDE

Empire District Electric Company Kaw Valley Point To Point 3 years after written notice

74

Hydro Peaking Power Purchase contract - KEPCO and EDE

Empire District Electric Company KEPCO Point To Point 5/31/2008 no rollover

75

Hydro Peaking Power Purchase contract - Coffeyville and EDE

Empire District Electric Company Coffeyville, KS Point To Point 3 years after written notice

76

Hydro Peaking Power Purchase contract - KMEA and EDE

Empire District Electric Company KMEA Point To Point 3 years after written notice

77Service Schedule JP KGE and EDE Westar Energy

Empire District Electric Company

FERC Rate Schedule No. 273Point To Point 5/31/2010

78Electric Interchange Agreement - Iatan

Kansas City Power and Light

Empire District Electric Company Point To Point year to year

79

OMPA Transmission Service Agreement (TSA)

Oklahoma Gas and Electric Company

Oklahoma Municipal Power Authority

FERC Rate Schedule No. 121

Pre- Order 888 Transmission Service Agreement

36 Month written Notice prior to December 20, 2003

80OMPA DLRA (Dispatch and Load

Oklahoma Gas and Electric Company

Oklahoma Municipal Power Authority

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410RFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination ProvisionsRegulation).

81Paris Ark. OATT, SWPA customer

Oklahoma Gas and Electric Company

City of Paris, Southwestern Power Administration

FERC Electric Tariff, Second

Revised Volume No.2- OATT NSA- SVC Agmnt #29,

NOA- SVC Agmnt # 30

OG&E OATT- Network SVC

The OATT Agreement listed is subject to OATT extension and termination provisions, There are no special provisions.

82Purcell Okla. OATT, SWPA customer

Oklahoma Gas and Electric Company

Purcell Public Works Authority, Southwestern Power Administration

FERC Electric Tariff, Second

Revised Volume No.2- OATT NSA- SVC Agmnt #27,

NOA- SVC Agmnt # 28

OG&E OATT- Network SVC

The OATT Agreement listed is subject to OATT extension and termination provisions, There are no special provisions.

83

Southwest Power Administration (SWPA) OATT

Oklahoma Gas and Electric Company

Southwestern Power Administration

FERC Electric Tariff, Second

Revised Volume No.2- OATT NSA-

SVC Agmnt, NOA- SVC Agmnt

OG&E OATT- Network SVC

The OATT Agreement listed is subject to OATT extension and termination provisions, There are no special provisions.

84 Geary Okla. OATTOklahoma Gas and Electric Company Geary Utilities Authority

FERC Electric Tariff, Second

Revised Volume No.2- OATT NSA- SVC Agmnt #43,

NOA- SVC Agmnt #43-Sup.#1

OG&E OATT- Network SVC

The OATT Agreement listed is subject to OATT extension and termination provisions, There are no special provisions.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410SFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

85 Orlando Okla. OATTOklahoma Gas and Electric Company

City of Orlando Public Works Authority

FERC Electric Tariff, Second

Revised Volume No.2- OATT

OG&E OATT- Network SVC

The OATT Agreement listed is subject to OATT extension and termination provisions, There are no special provisions.

86

OKLAHOMA GAS AND ELECTRIC COMPANY ELECTRIC SERVICE AGREEMENT (Wholesale for Resale)

Oklahoma Gas and Electric Company City of Watonga Okla.

FERC Electric Tariff 1st Revised

Volume No. 1 Rate Schedule

WM-1 Discounted Rate Option

Pre-Order 888- Full Requirements

24 month notice Given 2/16/99

87City of Paris Ark Maple Street

Oklahoma Gas and Electric Company City of Paris

FERC Electric Tariff 1st Revised

Volume No. 1 Rate Schedule

WM-1

Pre-Order 888- Full Requirements 24 month notice

88Mannford Okla. Public Works Authority

Oklahoma Gas and Electric Company City of Mannford

OG&E/KAMO Power Exchange

Agreement. FERC Rate

Schedule No. 125

Pre-Order 888- Full Requirements 12 month notice

89 KAMOOklahoma Gas and Electric Company KAMO

FERC Electric Tariff 1st Revised

Volume No. 1 Rate Schedule

WC-1

Pre-Order 888- Full Requirements

30 month notice by either Party

90

Arkansas Valley Electric Cooperative (AVEC)

Oklahoma Gas and Electric Company AVEC

FERC Electric Tariff 1st Revised

Volume No. 1 Rate Schedule

WC-1

Pre-Order 888- Full Requirements

30 month notice after 12/1/2001

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410TFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

91

Agreement Between Public Service Company of Oklahoma and Oklahoma Gas and Electric Company

Oklahoma Gas and Electric Company

Public Service Company of Oklahoma (AEP) N/A

OG&E OATT- Network SVC

6 month notice after 6/30/1983

92

Agreement Between Southwestern Electric Power Company and Oklahoma Gas and Electric Company Providing for Allocation of Fixed Charges and Costs of Operation and Maintenance of the 66 kV Element of Oklahoma Gas and Electric Company's Van Buren Interconnection Substation Near Van Buren, Arkansas

Oklahoma Gas and Electric Company

Southwestern Electric Power Company (AEP) N/A

OG&E OATT- Network SVC

12 months after December 8 of the year notice given to cancel contract

93 FederalSouthwestern Power Administration Augusta, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

94 FederalSouthwestern Power Administration Arkansas Electric Co-op

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410UFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

95 FederalSouthwestern Power Administration Arkansas Electric Co-op

Pre-Order 888 Service With Redirect Rights Firm in nature None

96 FederalSouthwestern Power Administration Arkansas Electric Co-op

Pre-Order 888 Service With Redirect Rights Firm in nature None

97 FederalArkansas Electric Co-op

Southwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

98 FederalArkansas Electric Co-op

Southwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

99 FederalSouthwestern Power Administration Arkansas Electric Co-op

Pre-Order 888 Service With Redirect Rights Firm in nature None

100 FederalArkansas Electric Co-op

Southwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

101 FederalArkansas Electric Co-op

Southwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410VFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

102 FederalSouthwestern Power Administration Associated Electric

Pre-Order 888 Service With Redirect Rights Firm in nature None

103 Federal Associated ElectricSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

104 FederalSouthwestern Power Administration Associated Electric

Pre-Order 888 Service With Redirect Rights Firm in nature None

105 Federal Associated ElectricSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

106 FederalSouthwestern Power Administration Associated Electric

Pre-Order 888 Service With Redirect Rights Firm in nature None

107 Federal AEP/WestSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

108 FederalSouthwestern Power Administration Associated Electric

Rate Sch NFTS-98D

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410WFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

109 FederalSouthwestern Power Administration AEP/West

Pre-Order 888 Service With Redirect Rights Firm in nature None

110 FederalSouthwestern Power Administration Anthony, KS

Pre-Order 888 Service With Redirect Rights Firm in nature None

111 FederalSouthwestern Power Administration Beauregard

Pre-Order 888 Service With Redirect Rights Firm in nature None

112 FederalSouthwestern Power Administration Bentonville, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

113 FederalSouthwestern Power Administration Brazos

Pre-Order 888 Service With Redirect Rights Firm in nature None

114 FederalSouthwestern Power Administration Brazos

Pre-Order 888 Service With Redirect Rights Firm in nature None

115 FederalSouthwestern Power Administration Carthage, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410XFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

116 FederalSouthwestern Power Administration Carthage, MO Car-409

Pre-Order 888 Service With Redirect Rights Firm in nature None

117 Federal Carthage, MOSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

118 FederalSouthwestern Power Administration Sikeston, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

119 FederalSouthwestern Power Administration Fulton, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

120 FederalSouthwestern Power Administration Claiborne

Pre-Order 888 Service With Redirect Rights Firm in nature None

121 FederalSouthwestern Power Administration Clarksville, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

122 FederalSouthwestern Power Administration Clarksville, AR

Rate Sch NFTS-98D

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410YFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

123 FederalSouthwestern Power Administration Coffeyville, KS

Pre-Order 888 Service With Redirect Rights Firm in nature None

124 FederalSouthwestern Power Administration Comanche, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

125 FederalSouthwestern Power Administration Concordia

Pre-Order 888 Service With Redirect Rights Firm in nature None

126 FederalSouthwestern Power Administration Copan, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

127 FederalSouthwestern Power Administration Dixie Electric

Pre-Order 888 Service With Redirect Rights Firm in nature None

128 FederalSouthwestern Power Administration DOD - McAlester

Pre-Order 888 Service With Redirect Rights Firm in nature None

129 FederalSouthwestern Power Administration Duncan, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410ZFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

130 FederalSouthwestern Power Administration Eldorado, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

131 FederalEmpire District Electric Company

Southwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

132 FederalSouthwestern Power Administration

Empire District Electric Company

Pre-Order 888 Service With Redirect Rights Firm in nature None

133 Federal ESSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

134 FederalSouthwestern Power Administration ES

Rate Sch NFTS-98D

Pre-Order 888 Service With Redirect Rights Firm in nature None

135 FederalSouthwestern Power Administration Fort Sill, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

136 FederalSouthwestern Power Administration Goltry, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410AAFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

137 FederalSouthwestern Power Administration Granite, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

138 FederalGrand River Dam Authority

Southwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

139 FederalSouthwestern Power Administration

Grand River Dam Authority

Pre-Order 888 Service With Redirect Rights Firm in nature None

140 FederalGrand River Dam Authority

Southwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

141 FederalSouthwestern Power Administration

Grand River Dam Authority

Pre-Order 888 Service With Redirect Rights Firm in nature None

142 FederalSouthwestern Power Administration

Grand River Dam Authority

Rate Sch NFTS-98D

Pre-Order 888 Service With Redirect Rights Firm in nature None

143 FederalSouthwestern Power Administration

Grand River Dam Authority

Rate Sch NFTS-98D

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410BBFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

144 FederalSouthwestern Power Administration

Grand River Dam Authority

Rate Sch NFTS-98D

Pre-Order 888 Service With Redirect Rights Firm in nature None

145 FederalSouthwestern Power Administration Hermann, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

146 FederalSouthwestern Power Administration Higginsville, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

147 FederalSouthwestern Power Administration Hominy, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

148 FederalSouthwestern Power Administration Jackson, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

149 FederalSouthwestern Power Administration Jefferson Davis

Pre-Order 888 Service With Redirect Rights Firm in nature None

150 FederalSouthwestern Power Administration Jonesboro, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410CCFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

151 FederalSouthwestern Power Administration Jonesboro, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

152 Federal Jonesboro, ARSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

153 FederalSouthwestern Power Administration Kansas City, KS

Pre-Order 888 Service With Redirect Rights Firm in nature None

154 FederalSouthwestern Power Administration Kaw Valley

Pre-Order 888 Service With Redirect Rights Firm in nature None

155 FederalSouthwestern Power Administration Kennett, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

156 FederalSouthwestern Power Administration Kennett, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

157 Federal Kennett, MOSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410DDFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

158 FederalSouthwestern Power Administration Kennett, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

159 FederalSouthwestern Power Administration Kennett, MO Ken-286

Pre-Order 888 Service With Redirect Rights Firm in nature None

160 FederalSouthwestern Power Administration KEPCO

Pre-Order 888 Service With Redirect Rights Firm in nature None

161 FederalSouthwestern Power Administration KMEA

Pre-Order 888 Service With Redirect Rights Firm in nature None

162 FederalSouthwestern Power Administration Lafayette, LA

Pre-Order 888 Service With Redirect Rights Firm in nature None

163 FederalSouthwestern Power Administration Lamar, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

164 FederalSouthwestern Power Administration

Louisiana Energy and Power Authority

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410EEFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

165 FederalSouthwestern Power Administration Lexington, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

166 FederalSouthwestern Power Administration Malden, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

167 FederalSouthwestern Power Administration Malden, MO Mal-238

Pre-Order 888 Service With Redirect Rights Firm in nature None

168 Federal Malden, MOSouthwestern Power Administration

Rate Sch NFTS-98D

Pre-Order 888 Service With Redirect Rights Firm in nature None

169 FederalSouthwestern Power Administration Malden, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

170 Federal Malden, MOSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

171 FederalSouthwestern Power Administration Malden, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410FFFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

172 FederalSouthwestern Power Administration Manitou, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

173 FederalSouthwestern Power Administration Minden, LA

Pre-Order 888 Service With Redirect Rights Firm in nature None

174 FederalSouthwestern Power Administration Natchitoches, LA

Pre-Order 888 Service With Redirect Rights Firm in nature None

175 FederalSouthwestern Power Administration Nemaha-Marshall

Pre-Order 888 Service With Redirect Rights Firm in nature None

176 FederalSouthwestern Power Administration New Madrid, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

177 FederalSouthwestern Power Administration New Madrid, MO

Rate Sch NFTS-98D

Pre-Order 888 Service With Redirect Rights Firm in nature None

178 FederalSouthwestern Power Administration Nixa, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410GGFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

179 FederalSouthwestern Power Administration Nixa, MO

Rate Sch NFTS-98D

Pre-Order 888 Service With Redirect Rights Firm in nature None

180 FederalSouthwestern Power Administration Northeast Louisiana

Pre-Order 888 Service With Redirect Rights Firm in nature None

181 FederalSouthwestern Power Administration

Northeast Texas Electric Cooperative

Pre-Order 888 Service With Redirect Rights Firm in nature None

182 FederalSouthwestern Power Administration

Northeast Texas Electric Cooperative

Pre-Order 888 Service With Redirect Rights Firm in nature None

183 FederalSouthwestern Power Administration

Northeast Texas Electric Cooperative NTEC-265

Pre-Order 888 Service With Redirect Rights Firm in nature None

184 FederalNortheast Texas Electric Cooperative

Southwestern Power Administration NTEC-265

Pre-Order 888 Service With Redirect Rights Firm in nature None

185 FederalSouthwestern Power Administration

Oklahoma Gas and Electric Company

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410HHFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

186 FederalOklahoma Gas and Electric Company

Southwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

187 FederalSouthwestern Power Administration Olustee, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

188 FederalSouthwestern Power Administration Paragould, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

189 FederalSouthwestern Power Administration Paragould, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

190 FederalSouthwestern Power Administration Paragould, ARs

Pre-Order 888 Service With Redirect Rights Firm in nature None

191 Federal Paragould, ARSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

192 FederalSouthwestern Power Administration Paris, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410IIFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

193 FederalSouthwestern Power Administration People's

Pre-Order 888 Service With Redirect Rights Firm in nature None

194 FederalSouthwestern Power Administration People's

Pre-Order 888 Service With Redirect Rights Firm in nature None

195 FederalSouthwestern Power Administration Piggott, AR Pig-288

Pre-Order 888 Service With Redirect Rights Firm in nature None

196 FederalSouthwestern Power Administration Piggott, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

197 FederalSouthwestern Power Administration Piggott, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

198 Federal Piggott, ARSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

199 FederalSouthwestern Power Administration Piggott, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410JJFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

200 FederalSouthwestern Power Administration Piggott, AR

Pre-Order 888 Service With Redirect Rights Firm in nature None

201 FederalSouthwestern Power Administration Pointe Coupee

Pre-Order 888 Service With Redirect Rights Firm in nature None

202 FederalSouthwestern Power Administration Poplar Bluff, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

203 FederalSouthwestern Power Administration Poplar Bluff, MO Pop-251

Pre-Order 888 Service With Redirect Rights Firm in nature None

204 Federal Poplar Bluff, MOSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

205 FederalSouthwestern Power Administration Poplar Bluff, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

206 FederalSouthwestern Power Administration Purcell, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410KKFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

207 FederalSouthwestern Power Administration Rayburn Country

Pre-Order 888 Service With Redirect Rights Firm in nature None

208 FederalSouthwestern Power Administration Ryan, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

209 FederalSouthwestern Power Administration Sam Rayburn Dam EC SRDEC-215

Pre-Order 888 Service With Redirect Rights Firm in nature None

210 FederalSouthwestern Power Administration Sam Rayburn MPA SRDEC-215

Pre-Order 888 Service With Redirect Rights Firm in nature None

211 FederalSouthwestern Power Administration Sikeston, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

212 FederalSouthwestern Power Administration Sikeston, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

213 FederalSouthwestern Power Administration Sikeston, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410LLFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

214 FederalSouthwestern Power Administration Sikeston, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

215 FederalSouthwestern Power Administration Skiatook, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

216 FederalSouthwestern Power Administration South Louisiana

Pre-Order 888 Service With Redirect Rights Firm in nature None

217 FederalSouthwestern Power Administration Southwest Louisiana

Pre-Order 888 Service With Redirect Rights Firm in nature None

218 FederalSouthwestern Power Administration Spiro, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

219 FederalSouthwestern Power Administration Springfield, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

220 FederalSouthwestern Power Administration Springfield, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410MMFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

221 Federal Springfield, MOSouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

222 FederalSouthwestern Power Administration

Tex-La & Rayburn Country Tes-La/Ray-435

Pre-Order 888 Service With Redirect Rights Firm in nature None

223 FederalSouthwestern Power Administration Tex-La of Texas Tex-La-327

Pre-Order 888 Service With Redirect Rights Firm in nature None

224 FederalSouthwestern Power Administration Thayer, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

225 FederalSouthwestern Power Administration Valley

Pre-Order 888 Service With Redirect Rights Firm in nature None

226 FederalSouthwestern Power Administration

Vance Air Force Base, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

227 FederalSouthwestern Power Administration Walters, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410NNFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

228 FederalSouthwestern Power Administration WAPA

Pre-Order 888 Service With Redirect Rights Firm in nature None

229 Federal WAPASouthwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

230 FederalSouthwestern Power Administration Washington-St Tammany

Pre-Order 888 Service With Redirect Rights Firm in nature None

231 FederalSouthwestern Power Administration West Plains, MO

Pre-Order 888 Service With Redirect Rights Firm in nature None

232 FederalSouthwestern Power Administration Wetumka, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

233 FederalSouthwestern Power Administration

Western Farmers Electric Cooperative

Pre-Order 888 Service With Redirect Rights Firm in nature None

234 FederalWestern Farmers Electric Company

Southwestern Power Administration

Pre-Order 888 Service With Redirect Rights Firm in nature None

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410OOFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

235 FederalSouthwestern Power Administration

Western Farmers Electric Cooperative

Pre-Order 888 Service With Redirect Rights Firm in nature None

236 FederalSouthwestern Power Administration

Western Farmers Electric Cooperative

Pre-Order 888 Service With Redirect Rights Firm in nature None

237 FederalSouthwestern Power Administration

Western Farmers Electric Cooperative

Pre-Order 888 Service With Redirect Rights Firm in nature None

238 FederalSouthwestern Power Administration

Western Farmers Electric Cooperative

Pre-Order 888 Service With Redirect Rights Firm in nature None

239 FederalSouthwestern Power Administration Yale, OK

Pre-Order 888 Service With Redirect Rights Firm in nature None

240

Amended Interchange Agreement for the Missouri-Kansas-Oklahoma 345 kV Interconnection

Kansas Gas and Electric

Associated Electric Cooperative Inc., Public Service Company of Oklahoma, Ameren-U.E

FERC rate schedule PSO-186, UE-79, KGE-130 Interconnection 4 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410PPFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

241

Agreement for Wholesale Electric Service Westar Energy City of Altamount, Kansas

FERC rate schedule 225

dockets ER85-210, ER92-357,

ER92-692, EL94-34, OA96-100

Full requirements wholesale power supply agreement 3/27/2005

242

Agreement for Wholesale Electric Service

Kansas Gas and Electric City of Arcadia

FERC rate schedule 178

dockets ER88-120, ER92-508,

OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

243

Agreement for Wholesale Electric Service

Kansas Gas and Electric City of Arma, Kansas

FERC rate schedule 168

dockets ER88-120, ER92-508,

OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

244

Generating Municipal Electric Service Agreement

Kansas Gas and Electric City of Augusta, Kansas

Ferc rate schedule 134

dockets E-8938, E-9485, ER77-578, ER80-259,

ER83-628, ER85-521, ER92-508,

ER92-733, ER97-1200, ER97-4028

Partial requirements wholesale power supply agreement None currently but contract provides for firm transmission service if requested and available

On-Going 30 months prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410QQFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

245

Agreement for Wholesale Electric Service Westar Energy City of Axtell, Kansas

Ferc rate schedule 227

dockets ER85-430, ER99-24,

ER92-357, ER92-692, EL94-34,

OA96-100

Full requirements wholesale power supply agreement 7/1/2010

246

Agreement for Wholesale Electric Service

Kansas Gas and Electric

City of Blue Mound, Kansas

Ferc rate schedule 171

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

247

Agreement for Wholesale Electric Service

Kansas Gas and Electric City of Bronson, Kansas

Ferc rate schedule 174

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

248

Generating Municipal Electric Service Agreement Westar Energy

City of Burlingame, Kansas

Ferc rate schedule 250

dockets ER88-307, ER89-455,

ER92-357, ER97-1143, ER92-696, EL94-34, OA96-100, ER97-1143,

ER00-2502

Partial requirements wholesale power agreement

5/31/07 & then year to year 2 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410RRFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

249

Generating Municipal Electric Service Agreement

Kansas Gas and Electric City of Burlington, Kansas

Ferc rate schedule 193

dockets ER96-1468, ER00-617

Partial requirements wholesale power supply agreement None currently but contract provides for firm transmission service if requested and available

5/31/04 & then year to year 3 yr prior notice

250Firm Transmission Service Agreement

Kansas Gas and Electric City of Burlington, Kansas

Service Agreement No. 7 under Western

Resources’ FERC Electric Tariff

Original Vol. No. 1 dockets ER96-

1468

Long-term firm transmission service to support purchase of participation power from Western Resources

5/31/04 Letter from city to continue service until 5/31/04 dated 3/20/98. City had to give 2 yrs. notice for the continuance.

251

Wholesale Municipal Electric Service Agreement Westar Energy City of Centralia, Kansas

Ferc rate schedule 248

dockets ER88-249, ER88-24,

ER92-357, ER92-692, EL94-34,

OA96-100

Full requirements wholesale power supply agreement 5/1/2008

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410SSFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

252

Generating Municipal Electric Service Agreement

Kansas Gas and Electric City of Chanute, Kansas

Ferc rate schedule 194

dockets ER96-587

Partial requirements wholesale power supply agreement None currently but contract provides for firm transmission service if requested and available

12/31/09 & then year to year 3 yr prior notice

253Firm Transmission Service Agreement Westar Energy City of Chanute, Kansas

Service Agreement No. 8 under Western

Resources’ FERC Electric Tariff,

Original Vol. No. 1 dockets ER96-587, ER96-2701

Long-term firm service agreement for 12.0 MW participation power purchased from Western Resources and 1.6 MW preference power purchased from Southwest Power Administration 12/31/2009

254

Wholesale Municipal Electric Service Agreement Westar Energy City of Chapman, Kansas

Ferc rate schedule 231

dockets ER86-17, ER88-24, ER92-357, ER92-692, EL94-34, OA96-

100

Full requirements wholesale power supply agreement 11/1/2005

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410TTFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

255

Generating Municipal Electric Service Agreement Westar Energy

City of Clay Center, Kansas

Ferc rate schedule 241

dockets ER87-441, ER88-24,

ER89-455, ER92-357, ER92-696,

ER94-991, EL94-34, OA96-100,

ER00-2502

Partial requirements wholesale power agreement

4/21/07 & then year to year 2 yr prior notice

256

Agreement for Wholesale Electric Service

Kansas Gas and Electric City of Elsmore, Kansas

Ferc rate schedule 170

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

257

Wholesale Municipal Electric Service Agreement Westar Energy City of Elwood, Kansas

Ferc rate schedule 253

dockets ER88-471, ER88-24,

ER92-357, ER92-692, EL94-34,

OA96-100

Full requirements wholesale power supply agreement 8/1/2008

258

Wholesale Municipal Electric Service Agreement Westar Energy City of Enterprise, Kansas

Ferc rate schedule 270

dockets ER85-734, ER88-24,

ER92-357, ER92-692, EL94-34,

OA96-100

Full requirements wholesale power supply agreement 9/25/2005

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410UUFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

259

Wholesale Municipal Electric Service Agreement Westar Energy City of Eudora, Kansas

Ferc rate schedule 236

dockets ER86-553, ER88-24,

ER92-357, ER92-377, ER93-528,

ER92-692, EL94-34, OA96-100

Full requirements wholesale power supply agreement 6/1/2013

260Transmission Service Agreement Westar Energy City of Fredonia, Kansas

Ferc rate schedule Service Agreement No.

129 under Western

Resources’ FERC Electric Tariff, 2nd

Rev. Vol. No. 5 dockets ER99-

3021

Long-term firm service agreement to support purchase of Nearman power from Kansas City Board of Public Utilities 5/31/2022

261

Generating Municipal Electric Service Agreement

Kansas Gas and Electric City of Girard, Kansas

Ferc rate schedule 182

dockets ER92-211, ER92-508,

ER92-828, ER92-655, ER93-231,

ER93-430, ER93-653, ER94-47,

ER96-2407, OA96-100, ER97-

4028

Partial requirements wholesale power supply agreement None currently but contract provides for firm transmission service if requested and available

2/1/07 & then On-Going 3 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410VVFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

262

Agreement for Wholesale Electric Service

Kansas Gas and Electric City of Haven, Kansas

Ferc rate schedule 176

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

263

Generating Municipal Electric Service Agreement Westar Energy City of Herington, Kansas

Ferc rate schedule 209

dockets ER83-37, ER88-24, ER89-455, ER92-357,

ER92-696, ER94-955, EL94-34,

OA96-100, ER00-2502

Partial requirement wholesale power agreement

3/2/12 2 yr prior notice

264

Wholesale Municipal Electric Service Agreement Westar Energy City of Hillsboro, Kansas

Ferc rate schedule 234

dockets ER86-404, ER88-24,

ER92-357, ER93-934, EL94-34,

OA96-100

Full requirements wholesale power supply agreement 5/31/2007

265

Generating Municipal Electric Service Agreement Westar Energy City of Holton, Kansas

Ferc rate schedule 226

dockets ER85-377, ER88-24,

ER89-455, ER92-357, ER92-696, EL94-34, OA96-100, ER97-1127,

ER00-2502

Partial requirements wholesale power supply agreement

6/1/05 & then year to year 2 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410WWFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

266

Generating Municipal Electric Service Agreement Westar Energy City of Horton, Kansas

Ferc rate schedule 261

dockets ER93-449, EL94-34,

OA96-100, ER00-2502

Partial requirements wholesale power supply agreement

Year to Year 3 yr prior notice

267

Agreement for Wholesale Electric Service

Kansas Gas and Electric City of LaHarpe, Kansas

Ferc rate schedule 169

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

268

Generating Municipal Electric Service Agreement Westar Energy City of Lindsborg, Kansas

Ferc rate schedule 280

dockets ER89-659, ER92-357, EL94-34, OA96-100, ER00-844

Partial requirements wholesale power supply agreement

5/31/10 & then year to year 5 yr prior notice

269

Wholesale Municipal Electric Service Agreement Westar Energy City of Marion, Kansas

Ferc rate schedule 228

dockets ER85-523, ER88-24,

ER92-357, ER92-692, EL94-34,

OA96-100

Full requirements wholesale power supply agreement 7/1/2005

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410XXFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

270

Electric Interconnection Agreement Westar Energy

City of McPherson, Kansas

Ferc rate schedule 127

dockets E-7893, ER78-196, ER78-626, ER80-527,

ER83-616, ER92-379

Long-term firm service agreement

5/31/27 & then year to year 3 yr prior notice

271

Agreement for Wholesale Electric Service

Kansas Gas and Electric

City of Mindenmines, Missouri

Ferc rate schedule 179

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

272

Generating Municipal Electric Service Agreement Westar Energy

City of Minneapolis, Kansas

Ferc rate schedule 211

dockets ER83-462, ER83-418, ER88-24, ER89-455, ER92-357,

ER92-696, EL94-34, OA96-100,

ER97-2377, ER00-2502

Partial Requirements Wholesale Power Supply Agreement

Year to Year 2 yr prior notice

273

Agreement for Wholesale Electric Service

Kansas Gas and Electric City of Moran, Kansas

Ferc rate schedule 172

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410YYFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

274

Wholesale Municipal Electric Service Agreement Westar Energy City of Morrill, Kansas

Ferc rate schedule 260

dockets ER90-382, ER92-357, EL94-34, OA96-100, ER99-3856

Full requirements wholesale power supply agreement 5/31/2005

275

Agreement for Wholesale Electric Service

Kansas Gas and Electric

City of Mount Hope, Kansas

Ferc rate schedule 177

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

2/1/08 & then on-going 3 yr prior notice

276

Agreement for Wholesale Electric Service

Kansas Gas and Electric City of Mulberry, Kansas

Ferc rate schedule 173

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

277

Service Agreement for Long Term Firm Point-to-Point Westar Energy City of Mulvane, Kansas

Ferc rate schedule Service Agreement No.

125 under Western

Resources’ FERC Electric Tariff, 2nd

Rev. Vol. No. 5 dockets ER99-

2457

Long-term firm service agreement to support purchase of Nearman power from Kansas City Board of Public Utilities 5/31/2022

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410ZZFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

278

Generating Municipal Electric Service Agreement

Kansas Gas and Electric City of Mulvane, Kansas

Ferc rate schedule 195

dockets ER96-587, OA96-100

Partial requirements wholesale power supply agreement None currently but contract provides for firm transmission service if requested and available

Year to Year 3 yr prior notice

279Firm Transmission Service Agreement Westar Energy City of Mulvane, Kansas

Ferc rate schedule Service Agreement No. 3 under Western

Resources’ FERC Electric Tariff,

Original Vol. No. 1 dockets ER94-1286, ER96-587,

ER96-2701, ER97-3528.

Moved to OATT Vol. 5

Long-term firm service agreement to support purchase of preference power from Southwest Power Administration

The term has been interpreted under Sections 205 and 206 of the Federal Power Act

280

Wholesale Municipal Electric Service Agreement Westar Energy City of Muscotah, Kansas

Ferc rate schedule 222

dockets ER85-169, ER88-24,

ER92-357, ER92-692, EL94-34,

OA96-100

Full requirements bundled wholesale service 1/3/2005

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410AAAFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

281

Long Term Firm Point-to-Point Transmission Service Westar Energy City of Neodesha, Kansas

Ferc rate schedule Service Agreement No.

130 under Western

Resources’ FERC Electric Tariff, 2nd

Rev. Vol. No. 5 ER99-3021

Long-term firm service agreement to support purchase of Nearman power from Kansas City Board of Public Utilities 5/31/2022

282

Generating Municipal Electric Service Agreement

Kansas Gas and Electric City of Neodesha, Kansas

Ferc rate schedule 196

dockets ER96-587, OA96-100

Partial requirements wholesale power supply agreement None currently but contract provides for firm transmission service if requested and available

Year to Year 3 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410BBBFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

283

Long Term Firm Point-to-Point Transmission Service Westar Energy City of Neodesha, Kansas

Ferc rate schedule Service Agreement No. 4 under Western

Resources’ FERC Electric Tariff,

Original Vol. No. 1 ER94-1286,

ER93-523, ER95-825, ER96-587,

ER96-2701, ER97-3528.

Moved to OATT Vol. 5

Long-term firm service agreement to support purchase of preference power from Southwest Power Administration

The term has been interpreted under Sections 205 & 206 of the Federal Power Act.

284

Generating Municipal Electric Service Agreement Westar Energy

City of Osage City, Kansas

Ferc rate schedule 249

dockets ER88-306, ER89-455,

ER92-357, ER92-696, ER93-537, EL94-34, OA96-100, ER00-2501,

ER00-2502

Partial requirement wholesale power supply agreement

6/1/08 & then year to year 2 yr prior notice

285

Wholesale Municipal Electric Service Agreement Westar Energy City of Robinson, Kansas

dockets ER86-231, ER88-24,

ER92-357, ER92-692, EL94-34,

OA96-100

Full requirements bundled wholesale service 4/1/2006

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410CCCFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

286

Generating Municipal Electric Service Agreement Westar Energy City of Sabetha, Kansas

dockets ER86-412, ER88-24,

ER89-455, ER92-357, ER92-696, EL94-34, ER96-1467, OA96-100,

ER00-2502

Partial requirements wholesale power supply agreement

6/1/07 & then year to year 2 yr prior notice

287

Agreement for Wholesale Electric Service

Kansas Gas and Electric

City of Savonburg, Kansas

dockets ER88-120, ER92-508,

ER92-732, OA96-100

Full requirements wholesale power supply agreement

On-Going 3 yr prior notice

288

Wholesale Municipal Electric Service Agreement Westar Energy City of St. Marys, Kansas

dockets ER87-666, ER88-24,

ER92-357 ER92-692, EL94-34,

OA96-100

Full requirements bundled wholesale service 11/1/2007

289

Wholesale Municipal Electric Service Agreement Westar Energy City of Toronto, Kansas

dockets ER90-188, ER92-357, EL94-34, OA96-

100

Full requirements bundled wholesale service 3/14/2010

290

Wholesale Municipal Electric Service Agreement Westar Energy City of Troy, Kansas

dockets ER88-393, ER92-357,

ER94-308, EL94-34, OA96-100

Full requirements bundled wholesale service 5/31/2004

291

Wholesale Municipal Electric Service Agreement Westar Energy City of Vermillion, Kansas

dockets ER88-116, ER88-24,

ER92-357, ER92-692, EL94-34,

OA96-100

Full requirements bundled wholesale service 2/1/2008

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410DDDFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

292

Generating Municipal Electric Service Agreement Westar Energy City of Wamego, Kansas

dockets ER86-595, ER88-24,

ER89-455, ER92-357, ER93-504, EL94-34, OA96-100, ER00-2501,

ER00-2502

Partial requirements wholesale power supply agreement

6/30/12 & then year to year 2 yr prior notice

293

Generating Municipal Electric Service Agreement

Kansas Gas and Electric City of Wellington, Kansas

dockets ER96-587

Partial requirements wholesale power supply agreement None currently but contract provides for firm transmission service if requested and available

Year to Year 3 yr prior notice

294Firm Transmission Service Agreement Westar Energy City of Wellington, Kansas

Service Agreement No. 9 under Western

Resources’ FERC Electric Tariff,

Original Vol. No. 1 dockets ER96-587, ER96-2701

Long-term firm service agreement to support purchased preference power from Southwest Power Administration 6/30/2002

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410EEEFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

295

Long Term Point-to-Point Transmission Service Westar Energy City of Winfield, Kansas

Service Agreement No.

126 under Western

Resources’ FERC Electric Tariff 1st

Rev. Vol. No. 5

Long-term Firm service agreement to support Winfield customers located outside of Winfield 4/30/2009

296

Generating Municipal Electric Service Agreement

Kansas Gas and Electric City of Winfield, Kansas

198 dockets ER96-

587

Partial requirements wholesale power supply agreement None currently but contract provides for firm transmission service if requested and available

Year to Year 3 yr prior notice

297

Long Term Point-to-Point Transmission Service Westar Energy City of Winfield, Kansas

Service Agreement No. 5 under Western

Resources’ FERC Electric Tariff,

Original Vol. No. 1 dockets ER94-1286, ER96-587

Long-term firm service agreement to support purchase of 1.6 MW preference power from Southwest Power Administration and 12.5 MW Nearman power from Kansas City Board of Public Utilities 2/28/2003

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410FFFFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

298Participation Power Agreement Westar Energy

Empire District Electric Company

Ferc rate schedule 273

dockets ER95-615

Participation Power Agreement5/31/2010

299

Agreement Respecting Certain Eastern Kansas Transmission Installations

Kansas Gas and Electric

Empire District Electric Company

Line lease agreement 3 yr prior notice

300

Agreement for Interchange of Power and Interconnected Operation

Kansas Gas and Electric

Empire District Electric Company

Ferc rate schedule EDE-69,

KGE-83 InterchangeOn-Going 3 yr prior notice

301

Agreement for Interchange of Power and Interconnected Operation -Service Schedule SP

Kansas Gas and Electric

Empire District Electric Company

Ferc rate schedule

Supplement No. 22 to 83 ER94-

1010

Long-term firm service agreement

Early termination permitted depending on continuous availability of certain base load generating units

302 Lease AgreementKansas Gas and Electric

Kansas City Power and Light

Ferc rate schedule KGE-

160 dockets ER85-386

Line lease; Wolf Creek to LaCygne 345 kV

Year to Year 2 yr prior notice

303Electric Interchange Agreement Westar Energy

Kansas City Power and Light

Ferc rate schedule KCPL-

55, Western Resources-83 Interchange

5/31 of any year 36 months prior notice

304Interchange Agreement

Kansas Gas and Electric

Kansas City Power and Light

Ferc rate schedule KCPL-

34, KGE-99 Interchange5/31 of any year 42 months prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410GGGFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

305MOKAN Coordination Agreement Westar Energy

Kansas City Power and Light Kansas Gas and Electric Company, Utilicorp-MPS

Ferc rate schedule KGE-186, KCPL-110,

MPS-95, Western Resources-266

This Agreement shall continue in full force and effect during the term of the General Participation Agreement and shall, as supplement thereto, terminate concurrently, therewith.

306Border Customer Agreement Westar Energy BPU-Kansas City, KS

Service to border customers

307

Electrical Interconnection Agreement Westar Energy BPU-Kansas City, KS

Ferc rate schedule Western

Resources-272 dockets ER94-

125 Interconnection4/26/06 and then year to year 10 yr prior notice

308

Electric Power, Transmission and Service Contract Westar Energy

Kansas Electric Power Cooperative

Ferc rate schedule 264

dockets ER93-683, ER94-969,

ER94-1116, ER95-841,ER96-1371, ER97-168,

ER97-2154, ER98-2173, ER98-2389, ER98-2907, ER99-3026, ER99-3418,

ER00-406, ER00-545, ER00-2572

Network Transmission Agreement

This contract shall terminate upon 6 years written notice given by either Party to the other; provided that the Contract shall not be terminated prior to December 31 of the calendar year Wolf Creek Generating Station 1 (WCGS-1) ceases commercial operation, or December 31, 2001, whichever is later

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410HHHFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

309

Electric Power, Transmission and Service Contract

Kansas Gas and Electric

Kansas Electric Power Cooperative, Inc

Ferc rate schedule 183

dockets ER93-683, ER94-969,

ER94-1116, ER95-841, ER96-1371, ER97-168,

ER97-2154, ER98-2173, ER98-2389, ER98-2907, ER99-3026, ER99-3418,

ER00-406, ER00-545, ER00-2572

Partial Requirements Wholesale Power Supply Agreement

This contract terminates on May 31, 2003 if KEPCo has opted to convert its transmission service to a regional Open Access Transmission Tariff; otherwise, it shall terminate upon 6 years written notice given by either Party to the other; provided that the Contract shall not be terminated prior to December 31 of the calendar year Wolf Creek Generating Station 1 (WCGS-1) ceases commercial operation, or December 31, 2001, whichever is later.

310

Electric Interconnect Contract – Schedule M Westar Energy Kansas Gas and Electric

Supplement No. 15 to No. 93

ER83-527 with 32 subsequent

dockets Interconnection 2 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410IIIFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

311

Jeffrey Energy Center Transmission Agreement Westar Energy Kansas Gas and Electric

dockets ER89-485, ER90-235,

ER90-300, ER90-478, ER90-500, ER92-29, ER92-239, ER96-1728,

ER96-1728 Interconnection

This agreement supports the Joint Ownership of the Jeffrey Energy Center Terminates upon the retirement of the last generating unit in which KGE has an ownership share at the Jeffrey Energy Center or upon the transfer of any or all of KGE’s interest in the Jeffrey Energy Center pursuant to the ownership agreement, whichever comes first

312

Electric Interconnection Contract Westar Energy Kansas Gas and Electric

Ferc rate schedule KGE-

93, Western Resources-6 Interconnection

Year to Year 3 yr prior notice

313Interconnection Agreement Westar Energy Kansas Gas and Electric

Ferc rate schedule KGE-

25, Western Resources-9 Interconnection

On-Going 6 months prior notice

314Transmission Service Agreement Westar Energy Midwest Energy, Inc

Ferc rate schedule 265

dockets ER93-849, OA96-100

Long-term firm service agreement 60.5 MW @ POR, 60.0 MW @ POD 5/31/2008

315

Electric Interconnection Contract – Service Schedule P Westar Energy Midwest Energy, Inc

Ferc rate schedule

Supplement No. 21 to 123 dockets

ER91-357

long term firm service agreement

Year to Year 3 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410JJJFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

316

Agreement for Wholesale Electric Service

Kansas Gas and Electric

Missouri Public Service Company

Ferc rate schedule 152

dockets ER81-519, ER82-519,

ER85-521, ER92-508, OA96-100

Full requirements wholesale power supply agreement for ultimate delivery to the cities of Eve, Missouri and Richards, Missouri

Year to Year 90 days not less than 60 days prior notice

317

Electric Interconnection and Interchange Agreement Westar Energy

Nebraska Public Power District

Ferc rate schedule not

assigned or filed

Interconnection has not been established

5/1/14 4 yr prior notice

318

Wholesale Contract Service - Rural Electric Coop. Westar Energy

Doniphan Electric Cooperative Association, Inc.; Kaw Valley Electric Cooperative, Inc.; and Nemaha-Marshall Electric Cooperative Association, Inc.

Westar Energy FERC Electric

Tariff No. 7

Partial requirements wholesale power supply agreement including long-term firm transmission service to support purchase of 1.0 MW preference power from Southwest Power Administration

5/31/07 & then on-going 3 yr prior notice

319

Agreement for Sale of Power and Interconnected Operation

Kansas Gas and Electric

Oklahoma Gas and Electric Company

Ferc rate schedule OGE-

32, KGE-75 InterconnectionOn-Going 3 yr prior notice

320

Amended Electric Interconnection Contract Westar Energy

Omaha Public Power District

Ferc rate schedule Western

Resources-277 OA97-314 Interconnection

Year to Year 3 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410KKKFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

321

Service Agreement for Long Term Firm Point-To-Point Transmission Service Westar Energy

Public Service Company of Oklahoma

Service Agreement

No.124 under Western

Resources’ FERC Electric Tariff , 1st. Rev. Volume No. 5. Dockets ER98-

3617

Long term firm transmission service agreement none stated

322

Service Agreement for Long Term Firm Point-To-Point Transmission Service Westar Energy

Public Service Company of Oklahoma

Service Agreement

No.121 under Western

Resources’ FERC Electric Tariff , 1st. Rev. Volume No. 5. Dockets ER98-

2533

Long term firm transmission service agreement none stated

323

Agreement for Interchange of Power and Interconnected Operation

Kansas Gas and Electric

Public Service Company of Oklahoma

Ferc rate schedule PSO-161, KGE-97 Interchange

On-Going 3 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410LLLFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

324

Second Firm Transmission Service Agreement Westar Energy

The State of Oklahoma through Oklahoma Municipal Power Authority

Service agreement No.

131 under Western

Resources’ FERC Electric Tariff,

Original volume No. 5 dockets

ER96-592, ER96-2701, ER00-2465

long term firm transmission supporting an agreement by OMPA to purchase participation power from Western Resources

Agreement automatically terminates December 31, 2013, unless extended by mutual agreement

325Transmission Service Agreement Westar Energy

The State of Oklahoma through the Oklahoma Municipal Power Authority

dockets ER93-613, ER93-523,

ER94-957

Long term firm transmission service supporting an agreement by OMPA to purchase participation power from Western Resources.

Agreement automatically terminates December 31, 2013, unless extended by mutual agreement.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410MMMFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

326

Jeffrey Energy Center Transmission Agreement Westar Energy

UtiliCorp United, Inc.’s Missouri Public Service Division

dockets ER89-485, ER90-235,

ER90-300, ER90-478, ER90-500, ER92-29, ER92-239, ER96-1728,

ER96-1728 Interconnection

This agreement supports the Joint Ownership of the Jeffrey Energy Center Terminates upon the retirement of the last generating unit in which UtiliCorp United has an ownership share at the Jeffrey Energy Center or upon the transfer of any or all of UtiliCorp United’s interest in the Jeffrey Energy Center pursuant to the ownership agreement, whichever comes first.Up to 8% of the output of the Jeffrey Energy Center plus reassigned amounts. Current year amount is 338 MW.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410NNNFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

327

Jeffrey Energy Center Transmission Agreement Westar Energy

UtiliCorp United, Inc.’s WestPlains Division

dockets ER89-485, ER90-235,

ER90-300, ER90-478, ER90-500, ER92-29, ER92-239, ER96-1728,

ER96-1728 Interconnection

This agreement supports the Joint Ownership of the Jeffrey Energy Center Terminates upon the retirement of the last generating unit in which UtiliCorp United has an ownership share at the Jeffrey Energy Center or upon the transfer of any or all of UtiliCorp United’s interest in the Jeffrey Energy Center pursuant to the ownership agreement, whichever comes first.Up to 8% of the output of the Jeffrey Energy Center plus reassigned amounts. Current year amount is 338 MW.

328Power Interchange Agreement

Kansas Gas and Electric Utilicorp-MPS

Ferc rate schedule MPS-19, KGE-106 Interchange

Year to Year 3 yr prior notice

329Electric Interchange Agreement Westar Energy Utilicorp-MPS

Ferc rate schedule MPS-

18, Western Resources-84 Interchange

Year to Year 36 mos prior notice

330

Electric Interconnection Contract Westar Energy

Utilicorp-WestPlains Energy WPE-7, KGE-72 Interconnection

5/31/13 & then year to year 5 yr prior notice

331

Electric Interconnection Agreement

Kansas Gas and Electric Utilicorp-WPD WPE-6, KGE-101 Interconnection

Year to Year 3 yr prior notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410OOOFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

332 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS Firm TS Sch 7 Network

5/31/2009 - Ongoing per KCPL OATT

333 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS Firm TS Sch 7 Network

12/31/2003 - Ongoing per KCPL OATT

334Transmission Service Agreement

Kansas City Power & Light AECI

Firm TS Sch 89 ER94-1101-002 Network year to year, 18 mo notice

335Transmission Service Agreement

Kansas City Power & Light AECI

Firm TS Sch 89 ER94-1101-002 Network year to year, 18 mo notice

336 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS Firm TS Sch 7 Network

12/31/2003 - Ongoing per KCPL OATT

337 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS 107 Network

12/31/2002 - Ongoing per KCPL OATT

338 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS 107 Network

12/31/2002 - Ongoing per KCPL OATT

339 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS 107 Network

12/31/2002 - Ongoing per KCPL OATT

340 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS 107 Network

12/31/2002 - Ongoing per KCPL OATT

341 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS Network

12/31/2002 - Ongoing per KCPL OATT

342

Municipal Participation Agreement

Kansas City Power & Light Baldwin

85 - ER94-1101-002 Point To Point year to year, 42 mo notice

343Interchange Agreement (UE)

Kansas City Power & Light AMRN

104 - ER94-1101-002 Point To Point year to year, 36 mo notice

344

Municipal Participation Agreement

Kansas City Power & Light Garnett

78 - ER94-1101-002 Point To Point year to year, 42 mo notice

345

Municipal Participation Agreement

Kansas City Power & Light Osawatomie

77 - ER94-1101-002 Point To Point year to year, 42 mo notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410PPPFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

346

Municipal Participation Agreement

Kansas City Power & Light Ottawa

90 - ER94-1101-002 Point To Point year to year, 42 mo notice

347

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS 108 Network year to year, 42 mo notice

348

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS 105 Network year to year, 42 mo notice

349Wholesale Firm Power Contract

Kansas City Power & Light

Kansas City Power & Light 74 - ER96-1736 Point To Point year to year, 18 mo notice

350Municipal Firm Power Contract

Kansas City Power & Light

Kansas City Power & Light 82 - ER98-3089 Point To Point year to year, 18 mo notice

351Cooperative Firm Power Contract

Kansas City Power & Light

Kansas City Power & Light 69 - ER98-4469 Point To Point year to year, 12 mo notice

352Cooperative Firm Power Contract

Kansas City Power & Light

Kansas City Power & Light 84 - ER98-4468 Point To Point year to year, 18 mo notice

353

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS 108 - ER96-1225 Point To Point year to year, 42 mo notice

354Municipal Firm Power Contract

Kansas City Power & Light

Kansas City Power & Light 76 - ER96-1448 Point To Point year to year, 18 mo notice

355Municipal Firm Power Contract

Kansas City Power & Light

Kansas City Power & Light 98 - ER96-689 Point To Point year to year, 18 mo notice

356

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS 77 - ER96-2218 Point To Point year to year, 42 mo notice

357

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS 78 - ER96-2099 Point To Point year to year, 42 mo notice

358

Municipal Participation Agreement

Kansas City Power & Light Ottawa

90 - ER94-1101-002 Point To Point year to year, 42 mo notice

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410QQQFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

359

Municipal Participation Agreement

Kansas City Power & Light Osawatomie

77 - ER94-1101-002 Point To Point year to year, 42 mo notice

360

Municipal Participation Agreement

Kansas City Power & Light Higginsville

108 - ER94-1101-002 Point To Point year to year, 42 mo notice

361

Municipal Participation Agreement

Kansas City Power & Light Garnett

78 - ER94-1101-002 Point To Point year to year, 42 mo notice

362 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 116 - ER99-2203 Point To Point

3/31/2004 - Ongoing per KCPL OATT

363 KCPL OATTKansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 119 - ER99-2202 Point To Point

12/31/2003 - Ongoing per KCPL OATT

364

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 117 - ER99-2204 Point To Point

5/31/2005 - Ongoing per KCPL OATT

365

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 128 -

ER00-1247-000 Point To Point1/31/2003 - Ongoing per KCPL OATT

366

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 128 -

ER00-1247-000 Point To Point1/31/2007 - Ongoing per KCPL OATT

367

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 128 -

ER00-1247-000 Point To Point1/31/2010 - Ongoing per KCPL OATT

368

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 130 -

ER00-1247-000 Point To Point1/31/2003 - Ongoing per KCPL OATT

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410RRRFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

369

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 130 -

ER00-1247-000 Point To Point1/31/2007 - Ongoing per KCPL OATT

370

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 130 -

ER00-1247-000 Point To Point1/31/2010 - Ongoing per KCPL OATT

371

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 131 -

ER00-1247-000 Point To Point1/31/2003 - Ongoing per KCPL OATT

372

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 131 -

ER00-1247-000 Point To Point1/31/2007 - Ongoing per KCPL OATT

373

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 131 -

ER00-1247-000 Point To Point1/31/2010 - Ongoing per KCPL OATT

374

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 134 -

ER00-1247-000 Point To Point1/31/2003 - Ongoing per KCPL OATT

375

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 134 -

ER00-1247-000 Point To Point1/31/2007 - Ongoing per KCPL OATT

376

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 134 -

ER00-1247-000 Point To Point1/31/2010 - Ongoing per KCPL OATT

377

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 135 -

ER00-1247-000 Point To Point1/31/2003 - Ongoing per KCPL OATT

378

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 135 -

ER00-1247-000 Point To Point1/31/2010 - Ongoing per KCPL OATT

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410SSSFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

379

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 129 -

ER00-1247-000 Point To Point1/31/2003 - Ongoing per KCPL OATT

380

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 129 -

ER00-1247-000 Point To Point1/31/2007 - Ongoing per KCPL OATT

381

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 129 -

ER00-1247-000 Point To Point1/31/2010 - Ongoing per KCPL OATT

382

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 132 -

ER00-1247-000 Point To Point1/31/2010 - Ongoing per KCPL OATT

383

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 133 -

ER00-1247-000 Point To Point1/31/2003 - Ongoing per KCPL OATT

384

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 133 -

ER00-1247-000 Point To Point1/31/2007 - Ongoing per KCPL OATT

385

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 133 -

ER00-1247-000 Point To Point1/31/2010 - Ongoing per KCPL OATT

386

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 136 -

ER00-1247-000 Point To Point1/31/2003 - Ongoing per KCPL OATT

387

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 136 -

ER00-1247-000 Point To Point1/31/2007 - Ongoing per KCPL OATT

388

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 136 -

ER00-1247-000 Point To Point1/31/2010 - Ongoing per KCPL OATT

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410TTTFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

389

Municipal Participation Agreement

Kansas City Power & Light

Kansas City Power & Light-PS

KCPL OATT Vol 3, Sup 93 - ER00-

1247-000 Point To Point12/31/2010 - Ongoing per KCPL OATT

390Electric Interchange Agreement

Kansas City Power & Light

Empire District Electric Company

88 - ER94-1101-002 Point To Point year to year, 36 mo notice

391

Municipal Participation Agreement

Kansas City Power & Light

Board of Public Utilities - Kansas City Kansas

54 - ER94-1101-002 Point To Point year to year, 42 mo notice

392Electric Interchange Agreement

Kansas City Power & Light Westar Energy

55 - ER94-1101-002 Point To Point year to year, 36 mo notice

393Missouri Interconnection 111 - ER94-411

394MOKAN Interconnection 110 - ER94-411 Term of GPA

395MPS Multiple Interconnection 58 - ER91-682 year to year, 48 mo notice

396KCPL Network Service

KCPL OATT Vol. 3, Supp. 127 -

ER00-1132-000

397WC-LaCygne 345kV Line Lease

Westar's KGE 160 - ER91-391 Concurrent with supply

398Facilities Use Agreement

107 - ER91-41-000

399

Cooper-Fairport-St.Joseph Interconnection (MINT)

107 - ER91-41-000 year to year, 48 mo notice

400 Sched P Westar Energy Midwest Energy

FERC Rate Schedule

Supplement No. 21 to 123, Docket

No. ER91-357

Transmission Service Agreement 5/31/2010

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410UUUFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisions

401 Sched PPA Westar Energy Midwest Energy

OASIS:272409-FERC Rate

Schedule 265, Docket Nos.

ER93-849, OA96-100

Transmission Service Agreement 5/31/2008

402 HolcombSunflower Electric Power Midwest Energy

Interconnection & Transmission Service Agreement

Through 5/31/2006 with renewal provisions thereafter

403 MTS-Colby Midwest Energy City of ColbySupp 5 to FERC

No. 6

Transmission Service Agreement None

404 MTS-Oakley Midwest Energy City of OakleySupp 5 to FERC

No. 4

Transmission Service Agreement None

405 MFS-Radium Midwest Energy City of RadiumFERC Rate

Schedule No. 13

Bundled Wholesale Sales Service None

406 MFS-Seward Midwest Energy City of SewardFERC Rate

Schedule No. 12

Bundled Wholesale Sales Service None

407 NF Colby Midwest Energy City of ColbySA 2 to FERC

Tariff Vol. 4 Point To Point None

408 NF Oakley Midwest Energy City of OakleySA 16 to FERC

Vol. 4 Point To Point None

409 NF LaCrosse Midwest Energy City of LaCrosseSA 17 to FERC

Vol. 4 Point To Point None

410 NF Jetmore Midwest Energy City of JetmoreSA 15 to FERC

Vol. 4 Point To Point None

411Sunflower Interconnect

Sunflower Electric Company Midwest Energy Network

Through 6/30/2010 with renewal provisions

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 410VVVFERC Electric TariffFourth Revised Volume No. 1

Line No. Contract Title Selling Party Buying PartyFERC Rate

Schedule No. Type of Service Termination Provisionsthereafter

412Sunflower Interconnect Midwest Energy

Sunflower Electric Company Network

Through 6/30/2010 with renewal provisions thereafter

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 3, 2004 Effective: Commencement of SPP RTO Operations Filed to comply with order of the Federal Energy Regulatory Commission, Docket No. RT04-1-000, et al., issued February 10, 2004, 106 FERC ¶61,110.

Southwest Power Pool Original Sheet No. 411FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT X

Sheet No. 411 is reserved for future use.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 412FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT Y

Flexible Use Transmission Service (Experimental)

1. Introduction

1.1 Definitions

In addition to the definitions set out in Section I.1. of this Tariff, the following

definitions apply to this Attachment Y.

1.1.1. Constrained Flowgate - a flowgate whose loading or projected loading

exceeds its rating less any appropriate margins.

1.1.2. Counter-Flow Reservation - a new request for transmission service or

existing transmission reservation that has an unloading effect on the

Constrained Flowgate. A Counter-Flow Reservation is a Relieving

Reservation to the extent that it is used simultaneously with the Restricted

Reservation.

1.1.3. Positive-Flow Reservation – an existing transmission reservation that has

a loading effect on the Constrained Flowgate in the same direction as a

Restricted Reservation. A Positive-Flow Reservation is a Relieving

Reservation to the extent that its use is foregone simultaneously with the

use of a Restricted Reservation.

1.1.4. Relieving Reservation – a new or existing firm reservation for

transmission service that effectively removes the constraining flow caused

by the Restricted Reservation on the Constrained Flowgate(s). Such

reservation may be one

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 413FERC Electric TariffFourth Revised Volume No. 1

that the Customer owns or has made the necessary arrangements to use for

such purpose or one which has been redirected pursuant to Section 22 of

this Tariff for the purpose of obtaining new service under this Attachment

Y.

1.1.5. Restricted Reservation – a request for regional transmission service that

cannot be accepted by SPP due to lack of ATC on one or more flowgates,

but that may be accepted under the provisions of this Attachment Y.

1.2 Nature of Service

If a Firm Point-To-Point Transmission Service request cannot be accommodated

by SPP due to lack of ATC on one or more flowgates the Customer may submit or

designate a Relieving Reservation that removes the constraining effects of the

Restricted Reservation. The Relieving Reservation is analyzed for its effect on

the Constrained Flowgate(s) and all other flowgates to ensure that it sufficiently

offsets the impact of the Restricted Reservation and does not cause any other

flowgates to become constrained. If the Relieving Reservation is approved, the

Restricted Reservation will be approved also. When the Restricted Reservation is

scheduled, SPP will determine how much, if any, of the Relieving Reservation

must be or can be scheduled on a day-ahead basis to maintain flows on the

constraint within its loading limits. SPP will not approve the Restricted

Reservation schedule until the appropriate Relieving Reservation schedule is

approved (in the case of a Relieving Reservation, submittal of the reduced

schedule will suffice).

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 414FERC Electric TariffFourth Revised Volume No. 1

There are two types of Relieving Reservations that may be used to allow

acceptance of the Restricted Reservation. The Customer may create a Relieving

Reservation by submitting one or more requests with counter-flow impacts equal

to or greater than the impacts of the Restricted Reservation on the Constrained

Flowgate(s). This type is a Counter-Flow Reservation and may be submitted as a

new request for service or a commitment to use an existing reservation. When

necessary, a Counter-Flow Reservation must be scheduled simultaneously with

the Restricted Reservation. The Customer may use the second type of Relieving

Reservation by identifying an existing confirmed reservation owned by the

Customer with positive-flow effects that are equal to or greater than the

constraining effects of the Restricted Reservation on the Constrained Flowgate(s).

This type is a Positive-Flow Reservation that, when necessary, will not be

scheduled for use simultaneously with the use of the Restricted Reservation.

Only SPP reservations will be eligible for consideration as a Relieving

Reservation. Service under this Attachment Y shall be provided only for point-to-

point transactions.

2. Experiment Description

This Flexible Use Transmission Service is hereby implemented on an experimental basis.

During the experiment, Restricted and Relieving reservation pairs will be limited

to monthly, and weekly firm reservations having service periods which end not later than

the end of the experiment.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 415FERC Electric TariffFourth Revised Volume No. 1

The duration of the experiment shall be one (1) year after the effective date of this

Attachment Y. In the course of the experiment, SPP will assess the merit of continued

offering of this service.

3. Use of Paired Reservations

3.1 Establishing Paired Reservations

There are two types of paired reservations, a Restricted Reservation associated

with a corresponding Counter-Flow Relieving Reservation and a Restricted

Reservation associated with a corresponding Positive-Flow Relieving

Reservation.

3.2 Paired Reservation Submittal Procedures

The Customer may submit a Relieving Reservation in the form of a Counter-Flow

Reservation. The Counter-Flow Reservation may either be a new request

submitted by the Customer or it may be an existing reservation that the Customer

already owns or has made the necessary arrangements to use. If an existing

reservation is to be used as a Counter-Flow Reservation the Customer must

inform SPP by including the OASIS reference number of the existing Counter-

Flow Reservation and the capacity to be assigned as a counter-flow along with the

Restricted Reservation request. The capacity, or any fraction thereof, of a

Counter-Flow Reservation may be linked to only one Restricted Reservation.

As an alternative to submitting a Counter-Flow Reservation, a Customer

may submit an existing reservation with positive flow effects on the Constrained

Flowgate(s) that are equal to or greater than the constraining effects of the

Restricted Reservation. The Positive-Flow Reservation should be one that the

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 416FERC Electric TariffFourth Revised Volume No. 1

Customer owns or has been assigned. By using a Positive-Flow Reservation as

the Relieving Reservation, the Customer is giving up rights to use that reservation

concurrently with the Restricted Reservation when necessary.

If a Positive-Flow Reservation is to be used as a Relieving Reservation,

the Customer must inform SPP by including the OASIS reference number of the

Positive-Flow Reservation and the capacity to be assigned as a Relieving

Reservation along with the Restricted Reservation request. The capacity, or any

fraction thereof, of a Positive-Flow Reservation may be linked to only one

Restricted Reservation.

4. Charges for Flexible Use Transmission Service

Customers shall be billed for all reservations made or used pursuant to the provisions of

this Attachment Y, as well as associated losses and ancillary services, in accordance with

this Tariff.

5. Scheduling Requirements

When a Customer schedules against a Restricted Reservation, a tag must be submitted to

SPP by the scheduling deadline for firm transmission service. SPP will not approve the

tag until all firm schedules are known. After the scheduling deadline, SPP will use

OASIS Automation to determine if the Constrained Flowgate(s) for which the Restricted

Reservation has been purchased is (are) projected to be constrained for the next day. If

the flowgate(s) is (are) projected to be constrained and a Counter-Flow Reservation is

linked with the Restricted Reservation, SPP will establish the hourly counter-flow

schedule profile

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 417FERC Electric TariffFourth Revised Volume No. 1

necessary to relieve the Constrained Flowgate(s). The amount of constraining flow that

must be relieved is the product of the amount by which the Constrained Flowgate is

overloaded by firm transactions and the ratio of the contribution to flowgate loading of

the Restricted Reservation schedule to the total contribution to flowgate loading of all

Restricted Reservation schedules. If OASIS Automation does not project the Constrained

Flowgate to be overloaded for the next day, no counter-flow schedule will be required. If

OASIS Automation indicates that a counter-flow schedule will be required for the next

day, the hourly profile of that schedule will be capped at the capacity of the Counter-

Flow Reservation. The NERC MRD tag format or other similar format will be used to

schedule the Counter-Flow Reservation. The Counter-Flow Reservation schedule must

be submitted by the scheduling deadline for non-firm transmission service. If a Counter-

Flow Reservation schedule is not received by that deadline, the Restricted Reservation

schedule will be canceled.

If the Constrained Flowgate(s) is (are) projected to be constrained, and a tag using

the Positive-Flow Reservation was submitted and approved prior to the scheduling

deadline, SPP will establish the maximum hourly Restricted Reservation schedule profile

that may flow simultaneous with the Positive-Flow Reservation schedule. The amount of

constraining flow that must be relieved is the product of the amount the Constrained

Flowgate is overloaded by firm transactions and the ratio of the contribution to flowgate

loading of the Restricted Reservation schedule to the total contribution to flowgate

loading of all Restricted Reservation schedules. This amount of relief will be achieved

by curtailing the appropriate amount of the Positive-Flow Reservation schedule or the

Restricted Reservation schedule. If no tag using the

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 418FERC Electric TariffFourth Revised Volume No. 1

Positive-Flow Reservation was submitted and approved or if OASIS Automation does

not project the Constrained Flowgate(S) to be overloaded, the Restricted Reservation

schedule will be allowed to flow. Once the amount of Restricted Reservation and

Positive-Flow Reservation that can be simultaneously scheduled is set, SPP will not

approve any additional simultaneously scheduled amount.

6. Curtailment of Restricted and Relieving Reservations

If TLR occurs on the Constrained Flowgate for which a Restricted Reservation schedule

and its associated Counter-Flow Reservation schedule are flowing, SPP will not curtail

the transaction unless it is determined that the counter-flow is not effective. In this case,

it would be curtailed proportionately with all other firm transactions. If the Restricted

Reservation schedule is curtailed, the Customer will have the choice of interrupting the

Counter-Flow Reservation schedule. If the Counter-Flow Reservation schedule is

curtailed due to TLR, the Restricted Reservation schedule will also be curtailed. If the

Restricted Reservation schedule is curtailed due to TLR on a flowgate other than the

flowgate(s) for which the Counter-Flow Reservation is arranged to protect, the Customer

will have the option of interrupting the Counter-Flow Reservation schedule.

7. Redirection of Service Provided Hereunder

Firm Relieving and Restricted Reservations may be redirected to any unconstrained path,

pursuant to Section 22 of this Tariff. Additionally, such reservations may be redirected to

a constrained path, provided that a corresponding new Relieving Reservation is

established.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: April 19, 2004 Effective: April 26, 2004

Southwest Power Pool Original Sheet No. 419FERC Electric TariffFourth Revised Volume No. 1

[Sheet Nos. 419 through 424 are reserved]

Reserved for future use.

Issued by: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued on: May 11, 2004 Effective: July 1, 2004

Southwest Power Pool Original Sheet No. 425FERC Electric TariffFourth Revised Volume No. 1

ATTACHMENT AA

TRANSMISSION SERVICE PREPAYMENT (Experimental)

1.0 Transmission Service Prepayment

This Attachment allows Transmission Customers to make Transmission Service

prepayments for the Transmission Provider’s use in expanding the Transmission System.

The total individual Transmission Customer prepayment shall be capped at the greater of

either $50,000 or the largest monthly aggregate charge paid by the Customer for services

under Schedules 7 and 8 during the prior 6 months. Transmission Customers must have

had at least $50,000 in total charges during the prior calendar year to participate.

2.0 Treatment of Service Prepayment

The Transmission Provider shall use the prepayment made to improve the transmission

system. The Transmission System improvements made shall relieve constraints that limit

transmission service and shall be based on upgrading Available Transfer Capability. The

Transmission Provider shall maintain a list of system upgrades that would improve

Available Transfer Capability. The Transmission Customer can designate the system

upgrades for which the service prepayment is requested to be used or allow the

Transmission Provider and the Transmission Owners to determine which system

upgrades to complete first. The Transmission Provider shall direct the Transmission

Owner to construct the determined system upgrades. The Transmission Provider and the

Transmission Owner will coordinate the timing, costs, payment schedule and conditions

for the upgrade. The Funds provided by the Transmission Customer under this procedure

shall be deposited in an escrow account.

Issued By: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued On: May 11, 2004 Effective: July 1, 2004

Southwest Power Pool Original Sheet No. 426FERC Electric TariffFourth Revised Volume No. 1

3.0 Transmission Service Credit for Prepayment

The Transmission Customers who make a prepayment shall receive future credit for

transmission services provided under Schedules 7 and 8. The credit shall be provided at

the same time and in the same amount as expenditures are made from the escrow account

for the upgrades. If construction expenditures have not been made, the crediting shall

begin one year after the date of receipt. The Transmission Customer shall receive a credit

on all portions of schedule 7 and 8 service that do not already provide for system

upgrades. This shall continue on a monthly basis until the Transmission Customer has

received full credit back for the amount of prepayment made. Transmission Customers

shall receive interest on the balance in the escrow account.

4.0 Experiment Description

This Transmission Service Prepayment Procedure is hereby implemented on an

experimental basis and will terminate one year after its effective date unless extended by

further order of the FERC. Credits for prepayments will continue until such time as the

Transmission Customer has been completely reimbursed. In the course of the

experiment, SPP will assess the merit of continued offering of this service and will

request FERC authorization for any proposed extension beyond the one year

experimental term.

Issued By: L. Patrick Bourne, ManagerTransmission and Regulatory Policy

Issued On: May 11, 2004 Effective: July 1, 2004