Orion II Construction, Inc. Attachment “A” to RFP: Selective Demolition Cornerstone Architects Project #:12.114 Package #: 0201
CWD-50 LOUIS RENOVATION SELECTIVE DEMOLITION
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects project #12.114 This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Roof Area: Remove the three existing penthouse structures completely below the roof deck level. Remove the stairs , coping , railing ,etc per plans. The removal is to be phased , see the project schedules
2. Entry Lobby and Lower Lobby: Remove ceilings, walls, floor coverings, fixtures, laminate tops, etc. as shown on the project drawings. The brick at the lobby east stairway that is scheduled to be removed must be salvaged for re-use and turned over to ORIONs.Superintendent.to be stored on site.
3. The existing Entry Lobby glass window and entry door systems will be removed by the Glass and Glazing contractor.
4. Parking Ramp Connector: Cut and remove the existing floorcovering, deck and framing and stairway to allow installation of the new ramp structure as detailed on the drawings.
5. Parking Ramp Connector:Cut and remove the required opening through the exterior masonry wall for the exit door to the ramp.
6. Service Area.Remove the masonry shaftway and other items on the 1st,2nd , 3rd, 4th and 5th floors per plans. The freight elevator and equipment will be removed by others.
7. Core Demolition-Remove all walls, ceilings, fixtures, etc. on the 2nd , 3rd, 4th and 5th floors.
8. 5th Floor Adjacent to Connector: Remove existing toilet room and all adjacent construction per plan.
9. Furnish company safety manual, certificate of workers compensation
insurance and liability insurance to the job superintendent prior to starting work.
10. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
11. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
________________________________
Subcontractor Signature.
12. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
13. All work is to comply with Orion Constructions safety manual. 14. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 15. Clean up debris and place in the trash receptacle to be provided by Orion. 16. If clean up is not performed on a daily basis, Orion Construction reserves
the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
17. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
18. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
19. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
20. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
21. Dumpsters will be furnished by ORION 22. Subcontractor shall remain in contact with the superintendent to review
scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
SELECTIVE DEMOLITION PACKAGE: #0201
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements
prepared by Cornerstone Architects & Orion Construction Project # 12.114, we
have also reviewed the proposed project schedule and have attended the pre-
bid meeting and become familiar with the location of the project and the
existing conditions on site as well as the conditions and logistics of the areas
where the work will be performed.
We fully understand the scope of work required, the quality of work required
and the quantity of labor, materials, permits & fees & equipment and all other
costs required completing the Selective Demolition Scope of Work. Therefore
we offer the following proposal:
Bidding Company Name & Address
A. Roof Area
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Entry Lobby
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
C. Lower Lobby
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
D. Parking Ramp Connector
1. Labor ________________________________________________
2. Equipment_______________________________________________
3. Total ________________________________________________
E. Service Areas 1st
, 2nd
, 3rd
,4th
& 5th
Floors:
1.Labor_______________________________________________________
2. Equipment__________________________________________________
3. Total_______________________________________________________
F. Core Demolition 2nd
,3rd
,4th
& 5th
Floors
1. Labor ________________________________________________
2. Equipment_______________________________________________
3. Total ________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
___________________________________________________________________
___________________________________________________________________
List Standard Hourly Labor Rates:
___________________________________________________________________
___________________________________________________________________
List Overtime & Weekend Labor Rates:
___________________________________________________________________
___________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
Signed:
_________________________________________________________
Signature Date
__________________________________________________________
Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: CONCRETE Cornerstone Architects Project #: 12.114 Bid Package #: 0301
CWD – 50 LOUIS RENOVATION CONCRETE
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects project # 12.114 This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Entry Lobby:Remove and replace the sidewalk in the exterior door and window openings at the Entry Lobby as per plans. Install new concrete window sills at the west wall per plans.
2. Fifth Floor Ramp Connector:Furnish labor and materials to install the concrete infill at the Fifth floor ramp connector as shown on the plans.
3. Fire Stairway to Roof Lobb y Expansion:Furnish labor and materials to install the concrete infill in the new steel pan stairway expansion and landings from the 7th floor to the new elevator equipment room.
4. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the ORION prior to starting work
5. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
6. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
7. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
8. All work is to comply with Orion Constructions safety manual.
9. Comply with all federal, state and local codes and ordinances including OSHA and MIOSHA.
10. Clean up debris and place in the trash receptacle to be provided by others.
11. If clean up is not performed on a daily basis, Orion Construction reserves the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
________________________________ _______________
Subcontractor Signature Date
12. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
13. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
14. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
15. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to re-gain lost time and maintain the schedule.
16. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
17. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
18. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
19. Subcontractor shall remain in contact with the superintendent to review scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
20. Supply approval drawings, as-built drawings, and operation manuals.
21. Contractor is to provide all layout associated with this scope of work
22. Furnish and install all wire mesh reinforcing steel, rods, expansion material, support steel, and chairs required per plans and specifications.
23. Furnish all hoisting and pumping as required for your work.
24. Strip and store form work per direction of Project Superintendent. Clean all concrete and debris to dumpster at direction of Project Superintendent.
25. Furnish and install an approved concrete curing compound to all exposed concrete.
26. Contractor is Responsible for Excavation/Backfill
27. Contractor is to provide mix designs and rebar drawings within 5 days of award of contract.
28. Contractor is responsible for taking proper care/precaution of work including tenting for rain, heating for cold, frost blankets, etc
29. Pour Sequencing is to be approved or provided by the superintendent.
________________________________ _______________
Subcontractor Signature Date
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
CONCRETE PACKAGE #0301
Cornerstone Architects Project: # 12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements prepared by
Cornerstone Architects & Orion Construction Project # 12.114, we have also reviewed the
proposed project schedule and have attended the pre-bid meeting and become familiar with
the location of the project and the existing conditions on site as well as the conditions and
logistics of the areas where the work will be performed.
We fully understand the scope of work required, the quality of work required and the
quantity of labor, materials, permits & fees & equipment and all other costs required
completing the Exterior Masonry Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address:
A. Work at Entry Lobby
1. Labor
2. Materials
3. Total
B. Work at Ramp Connector
1. Labor
2. Materials
3. Total
C. Work at elevator lobby stairway extension
1. Labor
2. Materials
3. Total ______
D. Floor infill at Service Area-removed freight elevator 1st
floor
1. Labor______________________________________________________
2. Materials____________________________________________________
3. Total________________________________________________________
Listed Material Suppliers Below:
List Proposed Subcontractors:
______________________________________________________________________________
______________________________________________________________________________
List Standard Hourly Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
List Overtime & Weekend Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
Signed:
_________________________________________________________
Signature Date
__________________________________________________________
Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Structural Steel Fabrication & Erection Cornerstone Architects Project #: 12.114 Bid Package #: 0501
CWD – 50 LOUIS RENOVATION Structural Steel Fabrication & Erection
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project # 12.114. This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Chiller Relocation:Furnish and install the structural steel support system for the Chiller Relocation.
2. Roof Deck assembly:Furnish and install the structural steel support system for the roof deck assembly.
3. Fire Stairway Extension:Furnish and install the Stair System extension to the roof/elevator penthouse-equipment room.
4. Replacement of Elevators:Provide Elevator Hoist Beams and Pit Ladders for the new elevator systems.
5. Parking Ramp Connector:Furnish and install the steel deck & beam floor and tube and beam structural system at the Parking Ramp Connector.
6. Proposed Entry Canopy:Furnish only the steel beam lintel , steel tube and deck assembly for the East elevation Proposed Entry Canopy
7. Furnish all structural steel lintels and beam lintels and associated components.
8. Provide all Hoisting and Lifting Equipment. 9. Furnish company safety manual, certificate of workers compensation
insurance and liability insurance to the job superintendent prior to starting work.
10. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
11. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
12. All work is to comply with Orion Constructions safety manual. 13. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 14. Clean up debris and place in the trash receptacle to be provided by
others.
________________________________ Subcontractor Signature.
15. If clean up is not performed on a daily basis, Orion Construction reserves the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
16. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
17. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
18. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
19. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
20. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
21. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
22. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
23. All permits and bonds associated with the work are to be included. 24. Subcontractor shall remain in contact with the superintendent to review
scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
25. This is a Design Assist / Build project. The Contractor is expected to work with the A/E with issues, ideas, layouts, loads etc
26. Supply approval drawings, as-built drawings, and operation manuals. 27. Contractor is to provide all layout associated with this scope of work 28. Receive, Unload, and Sort all steel. Store in an area approved by the
Project Superintendent.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
STRUCTURAL STEEL FABRICATION & ERECTION: #0501
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements prepared by Cornerstone Architects & Orion Construction Project # 12.114, we have also reviewed the proposed project schedule and have attended the pre-bid meeting and become familiar with the location of the project and the existing conditions on site as well as the conditions and logistics of the areas where the work will be performed.
We fully understand the scope of work required, the quality of work required and the quantity of labor, materials, permits & fees & equipment and all other costs required completing the Structural Steel Fabrication & Erection Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address:
A. Roof Structure for Chiller & Deck
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Stairway Extension
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
C. Parking Ramp Connector
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
D. Entry Canopy Frame & Turnbolts
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
____________________________________________________________________________________________________________________________________________________________
List Standard Hourly Labor Rates:
____________________________________________________________________________________________________________________________________________________________
List Overtime & Weekend Labor Rates:
____________________________________________________________________________________________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
______________________________________________________________________________
Voluntary Alternates:
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Signed:
_________________________________________________________ Signature Date
__________________________________________________________ Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: PLUMBING Cornerstone Architects Project #:12.114 Package #: 0502
CWD-50 LOUIS RENOVATION MISC. STEEL FABRICATION & ERECTION
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project # 12.114. This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Lobby Renovation: Furnish and install the SS handrail system at the Lobby Renovation.
2. Fire Stairway Extension:Furnish and install the steel pipe railing system at the stairway extension to the roof elevator lobby.
3. Elevator Lobby and Roof Deck structure: Provide and install the galvanized steel post, rail & wire system at the roof deck assembly.
4. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the job superintendent prior to starting work.
5. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
6. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
7. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
8. All work is to comply with Orion Constructions safety manual. 9. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 10. Clean up debris and place in the trash receptacle to be provided by
others. 11. If clean up is not performed on a daily basis, Orion Construction reserves
the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
12. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
13. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
14. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
________________________________ Subcontractor Signature.
15. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
16. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
17. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
18. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
19. All permits and bonds associated with the work are to be included. 20. Subcontractor shall remain in contact with the superintendent to review
scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
21. Supply approval drawings, as-built drawings, and operation manuals. 22. Contractor is to provide all layout associated with this scope of work. 23. Provide all Hoisting and Lifting Equipment for your work.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
MISC. STEEL FABRICATION & ERECTION: #0502
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements prepared by Cornerstone Architects & Orion Construction Project # 12.114, we have also reviewed the proposed project schedule and have attended the pre-bid meeting and become familiar with the location of the project and the existing conditions on site as well as the conditions and logistics of the areas where the work will be performed.
We fully understand the scope of work required, the quality of work required and the quantity of labor, materials, permits & fees & equipment and all other costs required completing the Misc. Steel Fabrication & Erection Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address:
A. Railings at Roof Deck
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Railings at Stairway Extension
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
C. Railings at Entry Lobby
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
____________________________________________________________________________________________________________________________________________________________
List Standard Hourly Labor Rates:
____________________________________________________________________________________________________________________________________________________________
List Overtime & Weekend Labor Rates:
____________________________________________________________________________________________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
______________________________________________________________________________
Voluntary Alternates:
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Signed:
_________________________________________________________ Signature Date
__________________________________________________________ Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Carpentry Cornerstone Architects Project #:12.114 Package #: 0601
CWD – 50 LOUIS RENOVATION CARPENTRY
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project #12.114 This work will be completed on a lump sum basis and includes but is not limited to the following items: 1. Materials: Furnish all materials required for this package including
framing materials, blocking, sheating and all others as required. All required fasteners and hardware shall also be included. Cabinets and millwork will provided under Package #0602
2. Blocking and backing: as required at all work phase locations shall be furnished and installed by this subcontractor.
3. Temporary barricades: Furnish, install and remove all temporary barricades required for the Main Lobby Renovation, Lower Lobby Renovation and the Entry Canopy. A schedule of required temporary barricades shall be provided by ORION.
4. New Roof Penthouse structure & deck: Construct the deck & subfloor
framing.Install the composite decking and plywood floor deck & accessories. Construct the flower boxes including siding and trim. Furnish &install the prefinished Metal siding panels, trim and composite fascia. Install HM doors, frames & hdwr. furnished by others. Install toilet accessories-furnished by others.
5. New Membrane Roof System: Install all roof nailers, blocking and backing as required. Close coordination with the membrane roofing contractor is required.
6. Bridge Ramp Connector:Cut and remove the sections of existing floor and deck framing as required for the ramped connector.Install the new wood joist and deck system.
7. Main Lobby Renovation: Install blocking as required for new handrail and trim. Install maple panels, base & misc trim furnished by others.
8. Lower Lobby: Install new HM frames, wood doors and hardware-furnished by others. Install solid surface vanity and work tops furnished by others.
Install toilet accessories, cabinets,FE cabinets mailboxes and other specialties furnished by others.
________________________________
Subcontractor Signature.
9. Service Areas: 1st, 2nd, 3rd, 4th & 5th Floors- Install the floor framing and plywood deck systems per plans.
10. Core Areas: 2nd ,3rd,4th & 5th Floors: Install HM frames, wd. doors and hdwr. furnished by others. Install Solid surface counter tops furnished by others. Install new toilet partitions and accessories furnished by others. Include all required backing & blocking.
11. Entry Canopy: Install the steel framed canopy structure and tie rods
furnished by others. Include temporary bracing. Furnish and install the wood blocking, Tongue and groove soffit and trim. Furnish labor and materials to construct the flower box-Copper cladding will be installed by others.
12. Caulking –Include labor and material for caulking all solid surface tops. 13. Furnish company safety manual, certificate of workers compensation
insurance and liability insurance to the job superintendent prior to starting work.
14. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
15. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
16. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
17. All work is to comply with Orion Constructions safety manual. 18. Comply with all federal, state and local codes and ordinances including OSHA
and MIOSHA. 19. Clean up debris and place in the trash receptacle to be provided by ORION. 20. If clean up is not performed on a daily basis, Orion Construction reserves the
right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
21. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
22. Provide project superintendent with close out documents within ten (10) days of completion of project. Three (3) copies of each.
23. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
24. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
25. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
26. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City
________________________________
Subcontractor Signature.
Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
27. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
28. Subcontractor shall remain in contact with the superintendent to review scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
29. Contractor is to provide all layout associated with this scope of work
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
CARPENTRY PACKAGE: #0601
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements
prepared by Cornerstone Architects & Orion Construction Project # 12.114, we
have also reviewed the proposed project schedule and have attended the pre-
bid meeting and become familiar with the location of the project and the
existing conditions on site as well as the conditions and logistics of the areas
where the work will be performed.
We fully understand the scope of work required, the quality of work required
and the quantity of labor, materials, permits & fees & equipment and all other
costs required completing the Carpentry Scope of Work. Therefore we offer the
following proposal:
Bidding Company Name & Address
A. Temporary Barricades
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
B. New Roof Elevator penthouse structure & deck
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
C. New Membrane roof system
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
D. Parking Ramp Connector
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
E. Main Lobby Renovation
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
F. Lower Lobby Renovation
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
G. Service Areas 1st
, 2nd
, 3rd
,4th
& 5th
floors
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
H. Core & Toilet Rooms 2nd
, 3rd
,4th
& 5th
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
I. Entry Canopy
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
______________________________________________________________________________
______________________________________________________________________________
List Standard Hourly Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
List Overtime & Weekend Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Signed:
_________________________________________________________
Signature Date
__________________________________________________________
Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Casework & Millwork Cornerstone Architects Project #:12.114 Package #: 0602
50 LOUIS RENOVATION CASEWORK MILLWORK
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project # 12.114. This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Solid Surface Tops : For Toilets Rooms on the 2nd 4th&5th floor toilet rooms, the lower lobby toilet rooms and the lower lobby work tops.
2. Cabinets,Casework, Maple paneling, base and trim: for the Main Lobby and stairway to the lower lobby and maple base for the 3rd floor Lobby.
3. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the job superintendent prior to starting work.
4. Orion will require as a condition to making any payment to Supplier, that Supplier furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
5. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
6. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
7. All work is to comply with Orion Constructions safety manual. 8. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 9. Furnish shop drawings, designs, catalogs and submittals as required
within ten (10) days of award of contract. 10. Provide project superintendent with close out documents within ten (10)
days of completion of project. One (3) copies of each. 11. Supplier is to provide signed one (1) year warranty letter, Maintenance
Manuals, etc. before retainage is paid. 12. Supplier is to provide enough equipment and manpower to maintain the
agreed upon schedule. If behind the agreed upon schedule the supplier will work over time on weekends at their expense to meet required delivery dates.
________________________________
Subcontractor Signature.
13. Supplier is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
14. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
15. Supplier shall remain in contact with the superintendent to review scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
CASEWORK & MILLWORK PACKAGE: #0602
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements
prepared by Cornerstone Architects & Orion Construction Project # 12.114, we
have also reviewed the proposed project schedule and have attended the pre-
bid meeting and become familiar with the location of the project and the
existing conditions on site as well as the conditions and logistics of the areas
where the work will be performed.
We fully understand the scope of work required, the quality of work required
and the quantity of labor, materials, permits & fees & equipment and all other
costs required completing the Casework & Millwork Scope of Work. Therefore
we offer the following proposal:
Bidding Company Name & Address
A. Solid Surface Tops
1. 2nd
Floor ___________________________________________________
2. 4th
Floor ___________________________________________________
3. 5th
Floor ___________________________________________________
4. Lower Lobby & Toilet Rooms __________________________________
B. Cabinets &Millwork
1. Entry Lobby & West Stairway _________________________________
2. 3rd
Floor Lobby ____________________________________________
List Material Suppliers Below:
Signed:
_________________________________________________________
Signature Date
__________________________________________________________
Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: ROOFING Cornerstone Architects Project #:12.114 Package #: 0702
CWD – 50 LOUIS RENOVATION ROOFING
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the preceding contract documents prepared for Orion Construction. This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Demolition of existing roof system and related flashings and accessories is required.Complete removal per plans.
2. Membrane Roofing System:Furnish and Install a complete membrane roofing system including everything on the drawings. Wood blocking, nailers & backers will be furnished and installed by others.
3. Provide all equipment for hoisting material. 4. All roof penetrations and equipment curbs are the responsibility of this
trade. 5. Furnish and Install all metal coping, flashing and trim 6. Furnish and Install all tapered insulation to ensure proper drainage 7. Furnish and Install all necessary sealants to ensure a proper working
system 8. Provide Walk way pads where shown on the drawings. 9. Provide extra material to place under gas piping blocks 10. Furnish and Install Roof hatches as needed 11. Furnish and Install a membrane roof system & flashing on the 1st Floor
Entry Canopy 12. Furnish company safety manual, certificate of workers compensation
insurance and liability insurance to the job superintendent prior to starting work.
13. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
14. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
15. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
16. All work is to comply with Orion Constructions safety manual. 17. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA.
________________________________ Subcontractor Signature.
18. Clean up debris and place in the trash receptacle to be provided by others.
19. If clean up is not performed on a daily basis, Orion Construction reserves the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
20. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
21. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
22. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
23. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
24. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
25. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be listed on the plans.
26. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
27. All permits and bonds associated with the work are to be included. 28. Subcontractor shall remain in contact with the superintendent to review
scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
29. This is a Design Assist / Build project. The Contractor is expected to work with the A/E with issues, ideas, layouts, loads etc
30. Supply approval drawings, as-built drawings, and operation manuals. and warranties as required.
31. Contractor is to provide all layout associated with this scope of work 32. Contractor is responsible for DAILY clean up to ensure trash does not
blow around or off the project site.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
MEMBRANE ROOFING PACKAGE: #0702
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements prepared by Cornerstone Architects & Orion Construction Project # 12.114, we have also reviewed the proposed project schedule and have attended the pre-bid meeting and become familiar with the location of the project and the existing conditions on site as well as the conditions and logistics of the areas where the work will be performed.
We fully understand the scope of work required, the quality of work required and the quantity of labor, materials, permits & fees & equipment and all other costs required completing the Membrane Roofing Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address
A. Main Roof Structure & Penthouse 1. Labor ___________________________________________________
2. Materials __________________________________________________
3. Total ___________________________________________________
Provide Alternate Costs to Use:
1. White Membrane ______________________________________
2. Tan Membrane ______________________________________
B. Entry Canopy
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
Provide Alternate Costs to Use:
1. White Membrane ______________________________________
2. Tan Membrane ______________________________________
List Material Suppliers Below:
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
List Proposed Subcontractors:
______________________________________________________________________________________________________________________________________
List Standard Hourly Labor Rates:
______________________________________________________________________________________________________________________________________
List Overtime & Weekend Labor Rates:
______________________________________________________________________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Signed:
_________________________________________________________ Signature Date
__________________________________________________________ Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Sheet Metal Fabrications Cornerstone Architects Project #:12.114 Package #: 0703
CWD-50 LOUIS RENOVATION SHEET METAL FABRICATIONS
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project #12.114. This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. East Entry Canopy: Furnish and install the decorative Fascia metal and trims.
2. Furnish and install the decorative panels and copper cladding and trim on the new flower box at the proposed Entry Canopy.
3. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the job superintendent prior to starting work.
4. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
5. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
6. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
7. All work is to comply with Orion Constructions safety manual. 8. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 9. Clean up debris and place in the trash receptacle to be provided by
others. 10. If clean up is not performed on a daily basis, Orion Construction reserves
the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
11. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
12. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
13. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
________________________________ Subcontractor Signature.
14. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
15. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
16. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
17. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
18. All permits and bonds associated with the work are to be included. 19. Subcontractor shall remain in contact with the superintendent to review
scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately
20. Contractor is responsible for DAILY clean up to ensure trash does not accumulate, blow around or off the project site.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
SHEET METAL FABRICATIONS PACKAGE: #0703
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements prepared by Cornerstone Architects & Orion Construction Project # 12.114, we have also reviewed the proposed project schedule and have attended the pre-bid meeting and become familiar with the location of the project and the existing conditions on site as well as the conditions and logistics of the areas where the work will be performed.
We fully understand the scope of work required, the quality of work required and the quantity of labor, materials, permits & fees & equipment and all other costs required completing the Sheet Metal Fabrications Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address
A. Fast Entry Canopy Decorative Fascia
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
B. Flower Box Copper Cladding, Trim & Decorative face panel.
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
______________________________________________________________________________________________________________________________________
List Standard Hourly Labor Rates:
______________________________________________________________________________________________________________________________________
List Overtime & Weekend Labor Rates:
______________________________________________________________________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
_____________________________________________________________________________
Voluntary Alternates:
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Signed:
_________________________________________________________ Signature Date
__________________________________________________________ Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Doors, Frames, Hardware, Specialties Cornerstone Architects Project #:12.114 Package #: 0801 & 1001-02
CWD – 50 LOUIS RENOVATION DOORS, FRAMES, HARDWARE, SPECIALTIES
SCOPE OF WORK
Furnish all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project #12.114 These materials will be supplied on a lump sum basis and includes but is not limited to the following items:
1. Finish Hardware:Furnish all finish hardware including but not limited to hinges, locksets, cylinders, mortise locksets, door closures, door mutes, push/pulls, door sweeps, kick plates, door stops, pivots, thresholds, weather stripping, door bottoms, panic exit devices, alarmed exit devices, and ALL other miscellaneous items related to the finish hardware trade. Hardware for Alum. Storefront door systems is NOT included in this Package.
2. Doors & Frames: Furnish all HM frames & doors and wood doors per plans.
3. Toilet & Bath Accessories:Furnish all Toilet & bath accessories & toilet partitions per plans.
4. Fire Extinguishers & Cabinets:Furnish fire extinguishers, cabinets, and signs per specification
5. Provide all hardware per ADA code where necessary. 6. Provide key schedule, key file, and diagram for owner upon completion. 7. . 8. If items are called out on the drawings but the quantities are not picked up
on schedules it is the suppliers responsibility to supply all necessary items.
9. Orion will require as a condition to making any payment to Supplier, that Supplier furnish a Sworn Statement listing all its vendors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid
10. Comply with all federal, state and local codes and ordinances including OSHA and MIOSHA.
11. Furnish shop drawings, schedules, catalogs and submittals as required within ten (10) days of award of contract.
12. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
13. Supplier is to provide signed one (1) year warranty letter, Installation review and approval documentation, Owner Manuals, etc. before retainage is paid.
________________________________ Subcontractor Signature.
14. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
15. The Supplier is expected to work with Cornerstone Architects/ORION with issues, ideas, layouts, methods, materials, etc.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
HM DOORS, FRAMES, Wd. DOORS & HARDWARE & TOLIET ACCESSORIES – FIRE
EXTINGUISHERS / CABINETS PACKAGE: #0801 & 1001-02
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements
prepared by Cornerstone Architects & Orion Construction Project # 12.114, we
have also reviewed the proposed project schedule and have attended the pre-
bid meeting and become familiar with the location of the project and the
existing conditions on site as well as the conditions and logistics of the areas
where the work will be performed.
We fully understand the scope of work required, the quality of work required
and the quantity of labor, materials, permits & fees & equipment and all other
costs required completing the HM Doors, Frames, Wd. Doors & Hardware &
Toilet Accessories – Fire Extinguishers / Cabinets Scope of Work. Therefore we
offer the following proposal:
Bidding Company Name & Address
___________________________________________________________________
1. HM Doors & Frames (List Quantity & Location)
Total: ________________________________________________________
2. Wood Doors (List Quantity & Location)
Total: ________________________________________________________
3. Finish Hardware (List Quantity & Location)
Total: ________________________________________________________
4. Toilet & Bath Accessories (List Quantity & Location)
Total: ________________________________________________________
5. Fire Extinguishers & Cabinets (List Quantity & Location)
Total: ________________________________________________________
6. Toilet Partitions
A. 2nd
Floor Men’s Toilet
Total: ______________________________________________________
B. 2nd
Floor Women’s Toilet
Total: ______________________________________________________
C. 4th
Floor Men’s Toilet
Total: ______________________________________________________
D. 4th
Floor Women’s Toilet
Total: ______________________________________________________
E. 5th
Floor Men’s Toilet
Total: ______________________________________________________
F. 5th
Floor Women’s Toilet
Total: ______________________________________________________
List Proposed Material Suppliers Below:
Signed:
_________________________________________________________
Signature Date
__________________________________________________________
Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Alum. Doors, Frames, Curtain Walls, Glass & Glazing Cornerstone Architects Project #:12.114 Package #: 0802
50 LOUIS RENOVATION Alum. Doors, Frames, Curtain Walls, Glass & Glazing
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project # 12.114. This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Entry Canopy & Roof Elevator Lobby:Furnish and install all aluminum framed glass and door systems including all required hardware and interior and exterior caulking. Install systems at the Entry Lobby, and the Roof Deck Lobby per plans.
2. Entry Lobby Forms & Surfaces System:Provide and install the glass panel and aluminum frame and stainless steel decorative wall panel system at the elevator wall from Forms & Surfaces.
3. Parking Ramp Connector:Furnish and install the Kawneer system at the Parking Ramp Connector.
4. New window Alternate:Provide alternate pricing to furnish and install the fixed and operable windows as shown on the drawings. Sheet A203
5. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the job superintendent prior to starting work.
6. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
7. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
8. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
9. Allwork is to fully comply with ORIONs safety manual. 10. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 11. Clean up debris and place in the trash receptacle to be provided by
others. 12. If clean up is not performed on a daily basis, Orion Construction reserves
the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
________________________________ Subcontractor Signature.
13. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
14. Provide project superintendent with close out documents within ten (10) days of completion of project. Three (3) copies of each.
15. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
16. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to regain and maintain schedule.
17. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
18. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
19. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
20. Subcontractor shall remain in contact with the superintendent to review scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
21. Supply approval drawings, as-built drawings, and operation manuals. 22. Contractor is to provide all layout associated with this scope of work 23. Receive, Unload, and store all materials. Store in an area approved by
the Project Superintendent.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
ALUM. DOORS, WINDOWS, CURTAIN WALLS,
GLASS & GLAZING PACKAGE: #0802
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements prepared by Cornerstone Architects & Orion Construction Project # 12.114, we have also reviewed the proposed project schedule and have attended the pre-bid meeting and become familiar with the location of the project and the existing conditions on site as well as the conditions and logistics of the areas where the work will be performed.
We fully understand the scope of work required, the quality of work required and the quantity of labor, materials, permits & fees & equipment and all other costs required completing the Alum. Doors, Windows, Curtain Walls, Glass & Glazing Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address
A. Roof Lobby
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
B. Parking Connector
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
C. Entry Lobby
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
D. Forms & Surfaces Wall Panel System at Elevator
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
E. New Aluminum Windows Alternate per Plan Sheet A203
Type 1
1. Labor __________________________________________________ 2. Materials __________________________________________________ 3. Total __________________________________________________
Type 2
1. Labor __________________________________________________ 2. Materials __________________________________________________ 3. Total __________________________________________________
Type 3
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
Type 4
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
Type 5
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
Type 6
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
Type 7
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
____________________________________________________________________________________________________________________________________________________________
List Standard Hourly Labor Rates:
____________________________________________________________________________________________________________________________________________________________
List Overtime & Weekend Labor Rates:
____________________________________________________________________________________________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Signed:
_________________________________________________________ Signature Date
__________________________________________________________ Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Drywall, Metal Stud, Acoustical Ceiling Cornerstone Architects Project #:12.114 Package #: 0901
CWD – 50 LOUIS RENOVATION DRYWALL, METAL STUD, ACOUSTICAL CEILING
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project # 12.114. This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Furnish and Install all labor, material, and equipment to install all drywall, furring, hard lids, bulkheads, control joints etc.
2. Furnish and Install all labor, material, and equipment to finish all drywall surfaces per specifications
3. Furnish and Install all labor, material, and equipment to install all acoustical ceiling systems per the drawings
4. Contractor is responsible for all unloading, hoisting, and storage of their materials
5. Furnish and Install all drywall ceilings and walls and associated accessories
6. Provide all sanding and finishing of drywall. At completion of finished drywall, the foreman, painter, and CM will walk and determine acceptance of walls
7. Furnish and Install all necessary metal stud framing,bracing, fasteners, channels, angles, etc. as required
8. Provide and maintain temporary protection as necessary associated with this trade
9. Provide ceiling pad cuts and ceiling tiles for other trades 10. Provide all wall and ceiling finishes including texturing as required 11. Include proper UL ratings where required 12. Provide all specified thermal/sound batt insulation in exterior and interior
walls 13. Provide additional lighting to ensure adequate visibility for drywall
finishing. 14. Furnish company safety manual, certificate of workers compensation
insurance and liability insurance to the job superintendent prior to starting work.
15. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence
________________________________ Subcontractor Signature.
satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
16. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
17. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
18. All work is to comply with Orion Constructions safety manual. 19. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 20. Clean up debris and place in the trash receptacle to be provided by
others. 21. If clean up is not performed on a daily basis, Orion Construction reserves
the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
22. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
23. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
24. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
25. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
26. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
27. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
28. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
29. All permits and bonds associated with the work are to be included. 30. Subcontractor shall remain in contact with the superintendent to review
scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
31. This is a Design Assist / Build project. The Contractor is expected to work with the A/E with issues, ideas, layouts, loads etc
32. Supply approval drawings, as-built drawings, and operation manuals. 33. Contractor is to provide all layout associated with this scope of work
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
DRYWALL, METAL STUD FRAMING & SUSP. ACOUSTICAL
CEILINGS PACKAGE: #0901
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements
prepared by Cornerstone Architects & Orion Construction Project # 12.114, we
have also reviewed the proposed project schedule and have attended the pre-
bid meeting and become familiar with the location of the project and the
existing conditions on site as well as the conditions and logistics of the areas
where the work will be performed.
We fully understand the scope of work required, the quality of work required
and the quantity of labor, materials, permits & fees & equipment and all other
costs required completing the Drywall , Metal Stud Framing & Acoustical
Ceilings Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address
A. Roof Elevator Lobby & Penthouse
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Parking Ramp Connector
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
C. Main Lobby Renovation & Entry Canopy
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
D. Lower Lobby Renovation & Toilet Rooms
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
E. Service Areas 1st
, 2nd
, 3rd
, 4th
& 5th
floors
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
F. Core & Toilet Rooms 2nd
, 3rd
, 4th
& 5th
floors
1. Labor _________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
______________________________________________________________________________
______________________________________________________________________________
List Standard Hourly Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
List Overtime & Weekend Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Signed:
_________________________________________________________
Signature Date
__________________________________________________________
Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Floor Covering Cornerstone Architects Project #:12.114 Package #: 0902
CWD – 50 LOUIS RENOVATION FLOOR COVERING SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the preceding plans and specifications prepared by Cornerstone Architects Project # 12.114. This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Roof Lobby & adjacent areas: Install new floorcovering and base per
plans and specifications. 2. Parking Connector: Install new floorcovering and base per plans and
specifications. specifications.
3. Main Lobby: Install new floorcovering and base per plan and specifications.
4. Lower Lobby and toilet rooms: Install new floorcovering and base per plans and specifications.
5. Core Area & toilet rooms 2nd , 3rd, 4th & 5th floors:Install new floorcovering and base per plans and specifications.
6. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the job superintendent prior to starting work.
7. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
8. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
9. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
10. All work is to comply with Orion Constructions safety manual. 11. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 12. Clean up debris and place in the trash dumpsters to be provided by
ORION.
________________________________
Subcontractor Signature.
13. If clean up is not performed on a daily basis, Orion Construction reserves the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
14. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
15. Provide project superintendent with close out documents within ten (10) days of completion of project. Three (3) copies of each.
16. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
17. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
18. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
19. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
20. Subcontractor shall remain in contact with the superintendent to review scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
21. This is a Design Assist / Build project. The Contractor is expected to work with Cornerstone Architects/ORION with issues, ideas, layouts, materials, etc.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
FLOOR COVERING PACKAGE: #0902
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements prepared by Cornerstone Architects & Orion Construction Project # 12.114, we have also reviewed the proposed project schedule and have attended the pre-bid meeting and become familiar with the location of the project and the existing conditions on site as well as the conditions and logistics of the areas where the work will be performed.
We fully understand the scope of work required, the quality of work required and the quantity of labor, materials, permits & fees & equipment and all other costs required completing the Floor Covering Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address
A. Roof Lobby 1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Parking Connector
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
C. Main Lobby
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
D. Lower Lobby & Toilet Rooms
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
E. Toilet Rooms
1. 2nd Floor Mens
1. Labor _________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
2. 2nd Floor Womens
1. Labor ___________________________________________
2. Materials ___________________________________________
3. Total ___________________________________________
3. 4th Floor Mens
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
4. 4th Floor Womens
1. Labor ___________________________________________
2. Materials ___________________________________________
3. Total ___________________________________________
5. 5th Floor Mens
1. Labor ___________________________________________
2. Materials ___________________________________________
3. Total ___________________________________________
6. 5th Floor Womens
1. Labor ___________________________________________
2. Materials ___________________________________________
3. Total ___________________________________________
F. Upper Lobbies
1. 2nd Floor
1. Labor _____________________________________
2. Materials ______________________________________
3. Total ______________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
____________________________________________________________________________________________________________________________________________________________
List Standard Hourly Labor Rates:
____________________________________________________________________________________________________________________________________________________________
List Overtime & Weekend Labor Rates:
____________________________________________________________________________________________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Signed:
_________________________________________________________ Signature Date
__________________________________________________________ Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Painting & Coating Cornerstone Architects Project #:12.114 Package #: 0903
CWD – 50 LOUIS RENOVATION PAINTING & Coating
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project # 12.114 This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Strip and sandblast the Chicago Common brick in the Entry Lobby 2. Tuckpoint and repair the now exposed brick after sandblasting. 3. Furnish and Install all Painting and finishing per drawings both interior and
exterior. The painting required for the exterior masonry façade renovation is not included in this package.
4. Provide Painting on all walls indicated on the drawings including doors, frames, window frames, access panels, etc
5. Finish woodwork with stain and varnish per specifications including intumescent coatings per plans..
6. Include ‘touch up painting’ as necessary 7. The Painting contractor MUST walk with the drywall contractor and project
superintendent to review all finishes for acceptance by painting contractor 8. Provide necessary1 primer, and 2 finish coats as needed. 9. All overspray, Spills, Splatters, Drips etc are to be cleaned daily. 10. Provide Protection of other work not intended to be covered in paint. 11. Paint all roof top mechanical equipment exposed gas piping. 12. Paint storage is to be an area designated by the superintendent. 13. Furnish company safety manual, certificate of workers compensation
insurance and liability insurance to the job superintendent prior to starting work.
14. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
15. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
16. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
17. All work is to comply with Orion Constructions safety manual.
________________________________ Subcontractor Signature.
18. Comply with all federal, state and local codes and ordinances including OSHA and MIOSHA.
19. Clean up debris and place in the trash receptacle to be provided by others.
20. If clean up is not performed on a daily basis, Orion Construction reserves the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
21. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
22. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
23. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
24. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
25. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
26. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
27. Subcontractor shall remain in contact with the superintendent to review scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
28. This is a Design Assist / Build project. The Contractor is expected to work with the A/E with issues, products, etc.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
PAINTING & COATING PACKAGE: #0903
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements
prepared by Cornerstone Architects & Orion Construction Project # 12.114, we
have also reviewed the proposed project schedule and have attended the pre-
bid meeting and become familiar with the location of the project and the
existing conditions on site as well as the conditions and logistics of the areas
where the work will be performed.
We fully understand the scope of work required, the quality of work required
and the quantity of labor, materials, permits & fees & equipment and all other
costs required completing the Painting & Coating Scope of Work. Therefore we
offer the following proposal:
Bidding Company Name & Address
A. Roof Lobby & Stair Extension
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Parking Connector
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
C. Main Lobby & entry canopy
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
D. Lower Lobby & Toilet Rooms
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
E. Core areas-Toilet Rooms-2nd
, 3rd
, 4th
& 5th
floors
1. Labor _________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
______________________________________________________________________________
______________________________________________________________________________
List Standard Hourly Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
List Overtime & Weekend Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Signed:
_________________________________________________________
Signature Date
__________________________________________________________
Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Elevators Cornerstone Architects Project #:12.114 Package #: 1401
CWD-50 Louis Renovation ELEVATORS
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and Specifications prepared by Cornerstone Architects Project # 12.114. This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Removal and replacement of the existing passenger elevator systems per specifications. The existing shafts are to remain in place with modifications if required for the new systems installation.
2. Removal of the Freight Elevator system after the construction process is finished. Including all components completely removed off site.
3. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the job superintendent prior to starting work.
4. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
5. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
6. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
7. All work is to comply with Orion Constructions safety manual. 8. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 9. Clean up debris and place in the trash receptacle to be provided by
ORION 10. If clean up is not performed on a daily basis, Orion Construction reserves
the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
11. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
12. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
13. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
________________________________
Subcontractor Signature.
14. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
15. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
16. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
17. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
18. Subcontractor shall remain in contact with the superintendent to review scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
19. Supply approval drawings, as-built drawings, and operation manuals. 20. Provide start-up lesson for owner and/or owner’s rep. upon completion. 21. This is a design-build system, and is expected to meet all codes and
operate as intended by owner and local authorities. 22. Work closely with ORION/ Cornerstone Architects to formulate a complete
specification and plan set as required to obtain permits.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
ELEVATOR PACKAGE: #1401
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements prepared by Cornerstone Architects & Orion Construction Project # 12.114, we have also reviewed the proposed project schedule and have attended the pre-bid meeting and become familiar with the location of the project and the existing conditions on site as well as the conditions and logistics of the areas where the work will be performed.
We fully understand the scope of work required, the quality of work required and the quantity of labor, materials, permits & fees & equipment and all other costs required completing the Elevator Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address
A. Remove Existing & Install New Elevator Systems in both Elevator Shafts
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Remove Existing Freight Elevator System
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
____________________________________________________________________________________________________________________________________________________________
List Standard Hourly Labor Rates:
____________________________________________________________________________________________________________________________________________________________
List Overtime & Weekend Labor Rates:
____________________________________________________________________________________________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Signed:
_________________________________________________________ Signature Date
__________________________________________________________ Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Fire Protection Cornerstone Architects Project #:12.114 Package #: 2100
CWD – 50 LOUIS RENOVATION FIRE PROTECTION SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project # 12.114 This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Supply, install, and test Fire Suppression System per Code at all new construction areas.
2. Modify existing Fire Suppression System at renovated areas as required per code.
3. Supply approval drawings, as-built drawings, and operation manuals. 4. Provide start-up orientation for owner and/or owner’s rep. upon
completion. 5. This is a design-build system, and is expected to meet all codes
and operate as intended by owner and local authorities. 6. Furnish and install a complete fire protection system which shall
include all piping, hangers, fasteners, alarm bells, flow switches, test locks, sprinkler heads, Siamese connections, fittings, valves, tamper switches, service riser and other items as necessary to fulfill the requirements of the municipality and other governing agencies having jurisdiction, including owner’s insurance carrier.
7. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the Project Manager prior to starting work.
8. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
9. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
10. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
11. All work is to comply with Orion Constructions safety manual. 12. Comply with all federal, state and local codes and ordinances
including OSHA and MIOSHA.
________________________________ Subcontractor Signature.
13. Clean up debris and place in the trash receptacle to be provided by others.
14. If clean up is not performed on a daily basis, Orion Construction reserves the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
15. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
16. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
17. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
18. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
19. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
20. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
21. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
22. Subcontractor shall remain in contact with the superintendent to review scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
23. Provide all layouts for work.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
FIRE PROTECTION PACKAGE: #2100
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements
prepared by Cornerstone Architects & Orion Construction Project # 12.114, we
have also reviewed the proposed project schedule and have attended the pre-
bid meeting and become familiar with the location of the project and the
existing conditions on site as well as the conditions and logistics of the areas
where the work will be performed.
We fully understand the scope of work required, the quality of work required
and the quantity of labor, materials, permits & fees & equipment and all other
costs required completing the Fire Protection Scope of Work. Therefore we offer
the following proposal:
Bidding Company Name & Address
A. Roof & Lobby
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Parking Connector
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
C. Main Lobby
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
D. Lower Lobby & Toilet Rooms
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
E. Core-Toilet Room 2nd
, 3rd
, 4th
& 5th
floors
1. Labor _________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
______________________________________________________________________________
______________________________________________________________________________
List Standard Hourly Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
List Overtime & Weekend Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Signed:
_________________________________________________________
Signature Date
__________________________________________________________
Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Plumbing Cornerstone Architects Project #:12.114 Package #: 2200
CWD – 50 LOUIS RENOVATION PLUMBING
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specs. prepared by Cornerstone Architects Project #12.114 This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. New Membrane Roof system: Remove existing drains from removed roofing system. Install new roof drains and tie into existing plumbing drain system as required by roof plans.
2. Roof Lobby: Furnish and install rough and finish plumbing at the toilet rooms. Furnish and install roof drains per plans.
3. Core-Toilet Rooms 2nd, 3rd, 4th & 5th Floors: Remove existing sinks, faucets, supply and drain lines. Install new sinks, supply and drain lines. Caulking of the new plumbing fixtures is also included.
4. Front entry canopy: Install the drain and piping for the new flower box. 5. Lower Lobby &Toilet Room Renovation: Furnish and install new sinks.
toilets and associated piping as required. 6. This is a design –build project and is expected to meet all applicable
codes and requirements. The plumbing contractor is required to furnish sealed plumbing plans as required for permits.
7. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the job superintendent prior to starting work.
8. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
9. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
10. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
11. All work is to comply with Orion Constructions safety manual. 12. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA. 13. Clean up debris and place in the trash receptacle to be provided by
others. 14. If clean up is not performed on a daily basis, Orion Construction reserves
the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
________________________________
Subcontractor Signature.
15. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
16. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
17. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
18. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
19. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
20. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
21. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
22. All permits and bonds associated with the work are to be included. 23. Subcontractor shall remain in contact with the superintendent to review
scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
24. This is a Design Assist / Build project. The Contractor is expected to work with the A/E with issues, ideas, layouts, loads etc
25. Supply approval drawings, as-built drawings, and operation manuals. 26. Contractor is to provide all layout associated with this scope of work.
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
PLUMBING PACKAGE: #2200
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements prepared by Cornerstone Architects & Orion Construction Project # 12.114, we have also reviewed the proposed project schedule and have attended the pre-bid meeting and become familiar with the location of the project and the existing conditions on site as well as the conditions and logistics of the areas where the work will be performed.
We fully understand the scope of work required, the quality of work required and the quantity of labor, materials, permits & fees & equipment and all other costs required completing the Plumbing Scope of Work. Therefore we offer the following proposal:
Bidding Company Name & Address
A. Membrane Roof Systems 1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Roof Lobby
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
C. Lower Lobby Toilet Rooms
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
D. Entry Canopy Drain System
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
E. Toilet Rooms-Upper floors
1. 2nd Floor Mens
1. Labor _________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
2. 2nd Floor Womens
1. Labor ___________________________________________
2. Materials ___________________________________________
3. Total ___________________________________________
3. 4th Floor Mens
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
4. 4th Floor Womens
1. Labor ___________________________________________
2. Materials ___________________________________________
3. Total ___________________________________________
5. 5th Floor Mens
1. Labor ___________________________________________
2. Materials ___________________________________________
3. Total ___________________________________________
6. 5th Floor Womens
1. Labor ___________________________________________
2. Materials ___________________________________________
3. Total ___________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
____________________________________________________________________________________________________________________________________________________________
List Standard Hourly Labor Rates:
____________________________________________________________________________________________________________________________________________________________
List Overtime & Weekend Labor Rates:
____________________________________________________________________________________________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
__________________________________________________________________
Voluntary Alternates:
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Signed:
_________________________________________________________ Signature Date
__________________________________________________________ Printed Name, Title Date
Orion II Construction, Inc. Attachment “A” to RFP: Electrical Cornerstone Architects Project #:12.114 Package #: 2601
CWD – 50 LOUIS RENOVATION ELECTRICAL
SCOPE OF WORK
Furnish and/or install all materials, labor, equipment and supervision necessary to complete the following scope of work for the above referenced project. All work must be completed in strict accordance with the plans and specifications prepared by Cornerstone Architects Project #12.114 This work will be completed on a lump sum basis and includes but is not limited to the following items:
1. Remove and relocate the existing electrical equipment for the chiller relocation.
2. Remove and terminate service to the abandoned electrical equipment per the project drawings. All abandoned electrical equipment shall be removed from the project site.
3. Disconnect and reconnect all mechanical equipment scheduled to remain on the roof to facilitate the new roof system installation.See the project schedules for required coordination.
4. Provide new electrical switch gear and MDP for the new elevator systems as required.
5. Provide new lighting fixtures, wiring, piping and circuiting as required for the New Roof Top penthouse & deck, The Core Areas,Toilet Rooms and Lobby renovations, the Entry and lower Lobby renovations and the proposed Entry Canopy.
6. This project is design- build and must meet all applicable codes and requirements . Furnishing sealed Electrical drawings for the electrical permit is required.
7. Furnish company safety manual, certificate of workers compensation insurance and liability insurance to the job superintendent prior to starting work.
8. Orion will require as a condition to making any payment to Subcontractor, that Subcontractor furnish a Sworn Statement listing all its subcontractors, suppliers, and material, waivers of lien, and such other evidence satisfactory to Orion that persons who may be entitled to assert such liens or claims have been paid.
9. Furnish all necessary taxes, insurance and signed contract (payment will not be made if these items are not supplied to Orion Construction).
10. Furnish all permits, fees, assessments, licenses, etc. which may be required to complete this scope of work.
11. All work is to comply with Orion Constructions safety manual. 12. Comply with all federal, state and local codes and ordinances including
OSHA and MIOSHA.
________________________________
Subcontractor Signature.
13. Clean up debris and place in the trash receptacle to be provided by others.
14. If clean up is not performed on a daily basis, Orion Construction reserves the right to hire the clean up and back charge the subcontractor at a rate of $75/per hour.
15. Furnish shop drawings, designs, catalogs and submittals as required within ten (10) days of award of contract.
16. Provide project superintendent with close out documents within ten (10) days of completion of project. One (3) copies of each.
17. Subcontractor is to provide signed one (1) year warranty letter, as builts, Owner Manuals, etc. before retainage is paid.
18. Subcontractor is to provide enough equipment and manpower to maintain the agreed upon schedule. If behind the agreed upon schedule the subcontractor will work over time on weekends at their expense to maintain schedule.
19. Subcontractor is responsible for scheduling all inspections required by the City, County, and State. Be on site during inspections of the work you performed.
20. Subcontractor is required to complete the work that is involved in their trade and is required to complete the job as directed by any inspector or City Official which is common practice in the profession and area where the work is taking place but may not be part of the plans.
21. All potential change orders to be approved by Orion Project Manager prior to the work being performed and/or materials ordered. Orion site Superintendent does not have the authority to authorize change orders.
22. All permits and bonds associated with the work are to be included. 23. Subcontractor shall remain in contact with the superintendent to review
scheduling on a continual basis. Any problems are to be relayed to Orion Construction’s superintendent immediately.
24. This is a Design Assist / Build project. The Contractor is expected to work with the A/E with issues, ideas, layouts, etc
25. Supply approval drawings, as-built drawings, and operation manuals. 26. Contractor is to provide all layout associated with this scope of work
*END OF SCOPE*
BID PROPOSAL FORM FOR:
The Trade Center Building Renovation, 50 Louis NW, Grand Rapids, MI 49503
ELECTRICAL PACKAGE: #2601
Cornerstone Architects Project: #12.114
To: ORION II CONSTRUCTION ATTN: Jim Droge-Project Manager
We have reviewed the Plans and Project Manual and work scope requirements
prepared by Cornerstone Architects & Orion Construction Project # 12.114, we
have also reviewed the proposed project schedule and have attended the pre-
bid meeting and become familiar with the location of the project and the
existing conditions on site as well as the conditions and logistics of the areas
where the work will be performed.
We fully understand the scope of work required, the quality of work required
and the quantity of labor, materials, permits & fees & equipment and all other
costs required completing the Electrical Scope of Work. Therefore we offer the
following proposal:
Bidding Company Name & Address
A. Chiller Relocation
1. Labor ________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
B. Roof Lobby
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
C. Parking Connector
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
D. Elevator Replacement-Freight elevator removal
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
E. Entry Lobby
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
F. Lower Lobby & Toilet Rooms
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
G. Entry Canopy
1. Labor __________________________________________________
2. Materials __________________________________________________
3. Total __________________________________________________
H. Core Area & Toilet Rooms-2nd
n, 3rd
, 4th
& 5th
Floors
1. Labor _________________________________________________
2. Materials ________________________________________________
3. Total ________________________________________________
List Material Suppliers Below:
List Proposed Subcontractors:
______________________________________________________________________________
______________________________________________________________________________
List Standard Hourly Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
List Overtime & Weekend Labor Rates:
______________________________________________________________________________
______________________________________________________________________________
Provide the Cost to Furnish a PLM Bond for Project:
___________________________________________________________________
Voluntary Alternates:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Signed:
_________________________________________________________
Signature Date
__________________________________________________________
Printed Name, Title Date