orr - environmental recommendations

137
FINAL RECOMMENDATIONS OF THE OFFICE OF REGULATORY REINVENTION REGARDING ENVIRONMENTAL REGULATIONS December 23, 2011

Upload: others

Post on 11-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

      FINAL 

      

   

RECOMMENDATIONS   

OF THE  

OFFICE OF REGULATORY REINVENTION  

REGARDING  

ENVIRONMENTAL REGULATIONS       

December 23, 2011

FINAL 

Environmental Advisory Rules Committee Recommendations 

2

Office of Regulatory Reinvention Environmental Advisory Rules Committee 

  

Richard Barr Attorney, Environmental Law Department Honigman Miller Schwartz and Cohn LLP  Skiles Boyd Vice President of Environmental Management and Resources DTE Energy  John Caudell (Co‐Chair, Air Subcommittee) Senior Consultant FTC&H  James Clift Policy Director Michigan Environmental Council  Troy Cumings (Chair, Remediation Subcommittee) Attorney & Lobbyist Warner Norcross & Judd LLP  Randy Gross Director of Policy and Legislative Affairs Department of Environmental Quality      

David Gustafson Regulatory Affairs Leader The Dow Chemical Company  Linda Hilbert Manager of Renewable Energy Consumers Energy  Carol Isaacs Chief Deputy Attorney General State of Michigan  John McCulloch (Chair, Water Subcommittee) Water Resources Commissioner Oakland County  Rob Nederhood (Committee Chair) Deputy Director Office of Regulatory Reinvention  Andrew Such (Co‐Chair, Air Subcommittee) Director of Environmental and Regulatory Affairs Michigan Manufacturers Association  Brian Warner Director of Environmental Services Wolverine Power Cooperative 

      *The ORR would also like to thank David Fiedler, Regulatory Affairs Officer for the Department of Environmental Quality, for his work on behalf of the Committee. 

FINAL 

Environmental Advisory Rules Committee Recommendations 

3

Table of Contents  

  SECTION                  PAGE 1. Executive Summary                4 2. Recommendations                5 

a. Air Quality Recommendations          5 b. Remediation Recommendations          12 c. Resource Management Recommendations        20   d. Water Resources Recommendations         23 e. General Recommendations            29 f. Additional Rule Rescissions and Amendments      31 

 Appendix A: Final Issue Papers              A‐1 

 

Environmental Advisory Rules Committee Recommendations 

4

1. EXECUTIVE SUMMARY  

a. Background  

This  report contains  the  recommendations of  the Office of Regulatory Reinvention  for changes to Michigan’s environmental regulations.   These recommendations consist of the final recommendations  of  the  Environmental  Advisory  Rules  Committee  (ARC),  an  additional recommendation from the ORR, and additional rule rescissions and amendments recommended by the ORR and Department of Environmental Quality (DEQ).   

 The  Environmental  ARC  was  created  by  the  Office  of  Regulatory  Reinvention  in 

accordance with Executive Order 2011‐5.   The mission of the ORR  is to ensure that Michigan’s regulatory  environment  is  simple,  fair,  efficient,  and  conducive  to  business  growth  and  job creation. The purpose of the Environmental ARC was to produce advisory recommendations to the ORR for changes to Michigan’s existing environmental regulations.   

 NOTE: This document  is not part of the rulemaking process.   Any proposed changes to 

administrative  rules  recommended  by  this  report  will  be  made  as  part  of  the  rulemaking process, and any proposed changes to Michigan statute will be made through the legislature.    

b. Scope  

The Environmental ARC was  tasked with evaluating and making  recommendations  for changes  to Michigan’s environmental  regulations,  including existing administrative  rules, non‐rule  regulatory  actions,  regulatory  processes,  and  as  necessary,  statutes.    Evaluations  and recommendations were based on  the  application of  the  seven  factors described  in  Executive Order 2011‐5.  Those seven factors are as follows: 

 1. Health or safety benefits of the rules; 2. Whether  the  rules  are  mandated  by  any  applicable  constitutional  or  statutory 

provision; 3. The cost of compliance with the rules, taking into account their complexity, reporting 

requirements and other factors; 4. The extent  to which  the  rules  conflict with or duplicate  similar  rules or  regulations 

adopted by the state or federal government; 5. Extent to which the regulations exceed national or regional compliance requirements 

or other standards; 6. Date  of  last  evaluation  of  the  rules  and  the  degree,  if  any,  to  which  technology, 

economic conditions or other factors have changed regulatory activity covered by the rules since the last evaluation; and 

7. Other changes or developments  since  implementation  that demonstrate  there  is no continued need for the rules. 

  Recommendations range from the general (e.g., identification of processes which need 

improvement) to the specific (e.g., language changes to existing rules).  Because of the size and scope  of Michigan’s  environmental  regulations,  the  Environmental  ARC  focused  its work  on specific areas within the existing regulations.   

Environmental Advisory Rules Committee Recommendations 

5

 c. Process 

 The Environmental ARC met for the first time on June 15, 2011, and immediately formed 

three subcommittees – Air Quality (co‐chaired by Andrew Such and John Caudell), Remediation (chaired  by  Troy  Cumings),  and Water  (chaired  by  John McCulloch)  –  to  address  the  issues identified  by  the  committee members.    The members  of  the  Environmental ARC  also  began soliciting  other members  of  the  regulated  community  (including  trade  groups,  chambers  of commerce, companies, and  local governments) to  identify existing Michigan regulations which were duplicative, obsolete, or unduly burdensome. 

 Over the course of the next five months, the committee members submitted over 100 

potential recommendations for consideration by the Environmental ARC, organized in individual “Issue  Papers”  and  categorized  as  a  “General,”  “Air  Quality,”  “Resource  Management,” “Remediation,” or “Water” issues.  Between June 15 and November 17, the Environmental ARC and its subcommittees held 33 meetings, during which they discussed and developed potential recommendations,  and  rejected  certain  proposals.    The  Environmental  ARC was  granted  an extension by  the ORR  to  continue  its work beyond  its  initial 120 day  term, which expired on October 15. 

 At  its meetings on October 6, October 20, October 27, November 3, November 8, and 

November  17,  the  Environmental  ARC  approved  a  total  of  79  recommendations, which  are contained in this report. 

  

2. RECOMMENDATIONS  

The following pages contain the final recommendations of the Environmental ARC.  The recommendations  are  categorized  by  topic  area.    In  order  to  provide  guidance  for implementation,  the  recommendations  within  each  category  have  been  listed  in  order  of priority, based on  the  importance of  the  recommendation  to  the state’s  future. Copies of  the final  Issue Papers, providing background and rationale for each recommendation, are  included in Appendix A to this report.  

a. AIR QUALITY RECOMMENDATIONS  

Recommendation A‐1  Subject:  Air Toxics Rules  Recommendation:   The Committee makes the following recommendations regarding Air Toxics rules:  

The parts of R 336.1224 dealing with  compounds  that are  considered volatile organic compounds (VOCs) should be rescinded.  Portions of R 336.1224 are redundant because R 336.1702 requires a control technology review for VOCs.  VOC‐based emission control is more effective under R 336.1702 and this entire regulation exceeds federal standards.  

Environmental Advisory Rules Committee Recommendations 

6

  R 336.1225 should be amended and specifically include the following: 

Limit  permit  modification  reviews  to  those  increases  in  a  Hazard  Index exceeding 10% above the previously permitted baseline. 

Exempt sources that are identified in a MACT source category.  Exempt clean fuels such as natural gas, low sulfur #2 fuel oil, and non‐chemically 

treated biofuels.  Exempt  pollution  control  projects  for  existing  sources  from  the  air  toxic 

regulations.  Limit the number of air toxics to the federal HAPS list.  Make the acceptable exposure limits consistent with other nearby states.  Stop  requiring  permit  holders  to  conduct  elaborate  and  costly  stack  tests  to 

provide emissions  research data,  since  the DEQ does not use  this  information for subsequent permit reviews.   

R 336.1228 should be rescinded. This rule allows the Air Quality Division to go beyond the requirements of the rule for any reason. 

 Justification:  See Issue Paper “A‐1” in Appendix A on Pg. A‐4.    * James Clift did not concur in this recommendation.  Recommendation A‐2  Subject:  Mercury Rules: Part 15 Rules, (R 336.2501 – 2514)  Recommendation:   Amend Part 15  rules  to add a  statement  that  stays compliance with Rules 336.2512, 336.2503(2)(a) & (6), 336.2509(1) and 336.2513(1)(a) & (3) until January 1, 2015.  The Michigan Mercury Rules requirements will be effective on this date unless an applicable federal rule to control mercury has been published in the Federal Register.  Once the applicable federal rule to control mercury has been published, the Michigan Mercury Rules should be rescinded.  Justification:  See Issue Paper “A‐2” in Appendix A on Pg. A‐7.  * James Clift did not concur in this recommendation.  Recommendation A‐3  Subject:  Additional Rule 201 (Permit to Install) Exemptions  Recommendation:   Michigan  should  adopt  a  new  exemption  rule  for minor  sources with  de minimis potential to emit. This exemption rule should be similar to the minor new source review thresholds adopted by the U.S. Environmental Protection Agency (USEPA) for its own permitting program in Indian Country (40 CFR, Subpart C), and should read as follows:  “New sources with a potential  to emit  less  than  the  following amounts  in an attainment area would be exempt from the requirement to obtain a permit to install: 

Environmental Advisory Rules Committee Recommendations 

7

CO        10 tpy NOx        10 tpy SO2        10 tpy VOCs  (non‐carcinogenic)   5 tpy PM        10 tpy PM10         5 tpy PM2.5         3 tpy Lead        0.1 tpy Fluorides       1 tpy Sulfuric Acid Mist     2 tpy Hydrogen Sulfide     2 tpy Total Reduced Sulfur      2 tpy Reduced S Compounds      2 tpy MSW Combustors     2 tpy MSW Landfills      10 tpy 

 In non‐attainment areas, the NAA compound‐specific thresholds would be: 

CO        5 tpy NOx        5 tpy SO2        5 tpy VOCs (non‐carcinogenic)  2 tpy PM        5 tpy PM10        1 tpy PM2.5        0.6 tpy Lead        0.1 tpy” 

 Justification:  See Issue Paper “A‐3” in Appendix A on Pg. A‐8.  * James Clift did not concur in this recommendation.  Recommendation A‐4  Subject:  Rule 206 Process Deadlines  Recommendation:    R  336.1206  must  be  more  specific  and  must  include  a  definition  for “administratively complete”. The rule should be amended to:  

Include a definition of “administratively complete” in Part 1.  Require  the  Air  Quality  Division  (AQD)  to  make  an  “administratively  complete” 

determination within 10 days of the receipt of the application.  Require AQD to act (issue or deny) on all minor source Permit to Install (PTI) applications 

within 180 days of receipt. This should include “opt‐out” PTIs.  Require  AQD  to  act  (issue  or  deny)  all  major  source  and  major  modification  PTI 

applications within 240 days from the date of receipt.  Allow  for  the  extension  of  these  deadlines  with  the  mutual  consent  of  both  the 

applicant and the DEQ.  

Environmental Advisory Rules Committee Recommendations 

8

Justification:  See Issue Paper “A‐4” in Appendix A on Pg. A‐10.  * James Clift did not concur in this recommendation.  Recommendation A‐5  Subject:  Dispersion Modeling Guidance Document  Recommendation:  The DEQ should organize a stakeholders group by January 1, 2012 to develop a new Policy Guidance Document  (PGD)  that  considers  the new National Ambient Air Quality (short‐term) Standards (NAAQS) for NOx and SO2.  Finalization of the new PGD should become effective  no  later  than  March  1,  2012.    This  PGD  should  be  modified,  with  stakeholder consensus, within 90 days of USEPA’s promulgation of any subsequent new or revised NAAQS.  Justification:  See Issue Paper “A‐5” in Appendix A on Pg. A‐11.  Recommendation A‐6  Subject:  Averaging Times and Compliance Testing – AQD Operational Memorandum No. 18  Recommendation:  The DEQ should review Air Quality Division’s Operational Memorandum No. 18 to ensure it is consistent with federal test methods and make changes to the Memorandum if necessary.  Stakeholder input should be included in any change to the Memorandum.  Justification:  See Issue Paper “A‐6” in Appendix A on Pg. A‐12.  Recommendation A‐7  Subject:  Rule 801, Rule 803 and State Implementation Plan  Recommendation:  The Air Quality Division (AQD) should amend R 336.1801 and R 336.1803 and the SIP, to only include electrical generating units (EGU’s) that contribute electricity to the grid.  A  stakeholder  group  should  commence  rules  development  activities  by  January  1,  2012  and submit a proposed rules package for public comment by no later than April 1, 2012.  Justification:  See Issue Paper “A‐7” in Appendix A on Pg. A‐13.  * James Clift did not concur in this recommendation.  Recommendation A‐8  Subject:  Michigan Continuous Emission Monitoring Rules (Part 11)  Recommendation:   R 336.2170 should be amended to be consistent with the federal reporting requirements and  limited  to semi‐annual  reporting of excess emissions. The present Michigan rule requires quarterly reporting.  

Environmental Advisory Rules Committee Recommendations 

9

Justification:  See Issue Paper “A‐8” in Appendix A on Pg. A‐14.  Recommendation A‐9  Subject:  Visible and Particulate Emission Limitations    Recommendation:   The Air Quality Division (AQD) should develop a Policy Guidance Document addressing the use of visible emissions limits of less than 20% opacity in permit conditions. The process for developing the document should include stakeholder input and require any opacity limits  that  are  more  stringent  than  what  is  allowed  by  R  336.1301(1)(a)  to  be  negotiated between  the applicant and  the AQD. The guidance document should be developed by  June 1, 2012.  Justification:  See Issue Paper “A‐9” in Appendix A on Pg. A‐15.  Recommendation A‐10  Subject:  R 336.1330  Recommendation:    The Air Quality Division  should  engage with USEPA  to  determine what  it would take to get USEPA approval to rescind R 336.1330.   Based upon that feedback, the DEQ should engage with stakeholders to determine whether to rescind or modify the rule, or take no further action.  Justification:  See Issue Paper “A‐10” in Appendix A on Pg. A‐16.  Recommendation A‐11  Subject:  R 336.1901 ‐ General Nuisance Rule  Recommendation:   With stakeholder  involvement,  rulemaking should be undertaken  to clarify how R 336.1901 is to be used in the Permit to Install process.  R 336.1901 should be limited to responding to and resolving known odor  issues and other nuisances.   As part of this review, all templates and standard language will be reviewed to assure the appropriate use of R 336.1901.  Justification:  See Issue Paper “A‐11” in Appendix A on Pg. A‐17.  * James Clift did not concur in this recommendation.  Recommendation A‐12  Subject:  Electronic Application for New Source Review  Recommendation:  Develop and implement an electronic Permit to Install application system by December 31, 2012. Development of this system should be done primarily by the private sector with  quality  assurance  and  regulatory  guidance  from  the  DEQ.  The  funding  for  this  project should be found outside of the current DEQ budget. 

Environmental Advisory Rules Committee Recommendations 

10

 Justification:  See Issue Paper “A‐12” in Appendix A on Pg. A‐18.  Recommendation A‐13  Subject:  Stakeholder Involvement in SIP Development  Recommendation:   The Air Quality Division of  the DEQ should conduct stakeholder  reviews  to solicit more non‐agency input in drafting State Implementation Plans (SIPs).   Justification:  See Issue Paper “A‐13” in Appendix A on Pg. A‐20.  Recommendation A‐14  Subject:  Addition of New Permit to Install Exemptions and Clarification of Existing Exemptions  Recommendation:  Amend the R 336.1201 permitting requirements to add new exemptions, and further clarify the current exemptions included in R 336.1278 – R 336.1290.  Justification:  See Issue Paper “A‐14” in Appendix A on Pg. A‐21.  Recommendation A‐15  Subject:  VOC Emissions from Pharmaceuticals (R 336.1625)  Recommendation:  Amend R 336.1625 to provide that if a MACT standard applies to the sources identified  in  R  336.1625  and  also  establishes  VOC  limitations,  then  the  requirements  in  R 336.1625 are not applicable.  Justification:  See Issue Paper “A‐15” in Appendix A on Pg. A‐22.  Recommendation A‐16  Subject:  Volatile Organic Compounds (VOCs) – R 336.1611 and R 336.1707(3)‐(4)  Recommendation:    The  DEQ  should  work  with  stakeholders  to  simplify  the  process  for demonstrating compliance with these rules for Renewable Operating Permit facilities.  Justification:  See Issue Paper “A‐16” in Appendix A on Pg. A‐23.  Recommendation A‐17  Subject:  Rule 703, Gasoline Storage Tanks (>2000 gal)  Recommendation:   Amend R 336.1703 to be clear and consistent with new USEPA regulations, while ensuring continued attainment of air quality standards.  

Environmental Advisory Rules Committee Recommendations 

11

Justification:  See Issue Paper “A‐17” in Appendix A on Pg. A‐24.  Recommendation A‐18  Subject:  R 336.1349  Recommendation:  R 336.1349 is obsolete and should be rescinded.  Justification:  See Issue Paper “A‐18” in Appendix A on Pg. A‐25.  Recommendation A‐19  Subject:  Limiting Compounds Required For Annual MAERS Report  Recommendation:  Continue to use the existing default MAERS air toxics emission factors as an optional calculation tool for  industry, but clearly  identify which air toxics have been calculated using USEPA‐supplied  emission  factors  in  the  annual MAERS  reports.    Furthermore,  the DEQ should be prohibited from developing new air toxics rules using D and E‐rated emission factors.   Justification:  See Issue Paper “A‐19” in Appendix A on Pg. A‐26.  * James Clift did not concur in this recommendation.  Recommendation A‐20  Subject:  Putting a Hold on the 18‐Month Construction Window for A PTI  Recommendation:  Amend R 336.1201(4) to provide for a “hold” on the 18‐month timeframe if a permit  decision  has  been  appealed.    The  following  bold  language  should  be  added  to  Rule 336.1201(4):  

“If the installation, reconstruction, or relocation of the equipment,  for which a permit has been  issued, has not commenced within, or has been  interrupted for,  18  months,  then  the  permit  to  install  shall  become  void,  unless  (a) otherwise authorized by the department as a condition of the permit to install, or (b) the installation permit is the subject of an appeal by a party other than the owner or operator of  the air contaminant  source  that  is  the  subject of the installation permit, in which case the date of termination of the permit is not  later  than eighteen months after  the effective date of  the permit plus the number of days between the date in which the permit was appealed and the date on which all appeals concerning the permit have been resolved. 

 Justification:  See Issue Paper “A‐20” in Appendix A on Pg. A‐27.  * James Clift did not concur in this recommendation. 

Environmental Advisory Rules Committee Recommendations 

12

b. REMEDIATION RECOMMENDATIONS  The rules currently organized under  the Remediation Division consist of 16 separate rule sets.  These sets can be categorized based on subject matter as follows:  

Part 201 program – Six sets.  Fire Prevention Code – Six sets.  Underground Storage Tank program – Three sets.  Site reclamation grant and loan program – One set. 

 The committee  reviewed  these  rule sets according  to  the criteria set  forth  in Executive Order 2011‐5.  Based on that review, the committee recommends rescission of three rule sets because they  provide  little  to  no  value  or  were  otherwise  never  used.    In  addition,  the  committee recommends that the rule sets related to fire safety and promulgated under the Fire Prevention Code be transferred from the DEQ to the Bureau of Fire Services and revised to conform to the referenced national codes.   Also,  the committee recommends a  full review of all  the rule sets relating to the Part 201 and Underground Storage Tank programs and offers recommendations on  specific  issues  that  should  be  addressed  within  these  rules.    Finally,  the  committee recommends various statutory and  implementation  improvements that should be made to the Part 201 and 213 programs.  Recommendation R‐1  Subject:  Groundwater/Surface‐Water Interface (GSI)  Recommendation:    Seek  amendments  to  Part  31,  Part  201,  and  R  299.5716  to  address  the following goals regarding the GSI pathway:  

1. GSI compliance evaluation should be based on surface water and not groundwater. 2. Prohibit excessive data demands. 3. Focus on designated uses  and  surface‐water‐quality  standards  in  the  surface water 

and not in groundwater or pore water. 4. Expand the bases for site‐specific criteria, including non‐numeric criteria. 5. Evaluate  appropriate  plume  characteristics,  such  as  using  plume‐average 

concentrations except where there is, or will likely be, an acutely toxic effect occurring in surface water. 

6. Expressly  recognize  that  natural  attenuation  may  be  acceptable  in  lieu  of  active treatment.  Generally describe what is needed to show natural attenuation. 

7. Use sustainability parameters in the response‐activity choice factors. 8. Expressly state that no permit is needed under Part 31 for a GSI response activity. 9. Surface water subject to GSI regulation should not include all wetlands or storm‐water 

retention ponds. 10. Develop new rule provisions or statutory changes for groundwater plumes infiltrating 

storm sewers based on the quality of the water exiting the storm sewer outfall and its impact on surface waters.  

 Justification:  See Issue Paper “R‐1” in Appendix A on Pg. A‐28. 

Environmental Advisory Rules Committee Recommendations 

13

* James Clift did not concur in this recommendation.  Recommendation R‐2  Subject:  Part 201/213 Vapor Intrusion Criteria  Recommendation:  The DEQ should carefully address the important vapor intrusion pathway in a manner which protects human health consistent with  the best scientific evidence available.  In doing  so,  the DEQ  should:  (i)  allow  the  initial  use  of  a  conceptual  site model  and  other  site evaluation  techniques  before  concluding  the  presence  of  a  complete  exposure  pathway  and vapor intrusion risk; (ii) allow data collection and evaluation processes consistent with the needs of  business  transactions,  which  may  include  greater  use  of  real‐time  sampling  techniques; (iii) prioritize the compilation and comparison to  initial screening  levels (not generic criteria) of Michigan‐based data  from  the many  sites which  are  known  to  exist  and  are  available  to  the DEQ; and  (iv) develop generic  vapor  intrusion  criteria  (with  variations based on  soil  type and other  site  specific  features) with meaningful  input  from  resources  outside  of  the  DEQ with particular expertise in this important area.   Justification:  See Issue Paper “R‐2” in Appendix A on Pg. A‐31.  Recommendation R‐3  Subject:  Revising Part 201 Cleanup Criteria    Recommendation:  The DEQ should evaluate the algorithms, exposure assumptions, and toxicity values used to establish generic cleanup criteria and screening  levels under Section 20120a of the Part 201  statute and  the Part 7  rules and  revise  those algorithms, exposure assumptions, and  toxicity  values  as  necessary  based  on  best  practices  from  other  states,  reasonable  and realistic conditions, and good science.  Consistent with any such revisions, the DEQ should then revise the generic cleanup criteria and screening levels established in the Part 7 rules.   Justification:  See Issue Paper “R‐3” in Appendix A on Pg. A‐35.  Recommendation R‐4  Subject:  Part 201 Rules  Recommendation:  On or before April 1, 2013, the DEQ should rescind all rules (Parts 1, 4, 5, 7, 9,  and  10)  promulgated  under  Part  201  except  the  portion  of  the  Part  7  rules  related  to establishing  generic  cleanup  criteria and  screening  levels.   Concurrent with  this process, DEQ should promulgate a streamlined and efficient rule package that contains only rules that are:  

necessary for program implementation; and  performance‐based rather than prescriptive. 

 Justification:  See Issue Paper “R‐4” in Appendix A on Pg. A‐36.  

Environmental Advisory Rules Committee Recommendations 

14

* James Clift did not concur in this recommendation.  Recommendation R‐5  Subject:  Risk‐Based Closures and Site‐Specific Criteria    Recommendation:   Consistent with the  increased flexibility to create site‐specific criteria under the 2010 Part 201 amendments, the DEQ should encourage the  increased use and approval of risk‐based site‐specific closure limits in order to facilitate closure of more sites.  In addition, Part 201 and the Part 201 rules should be amended to allow for non‐numeric site‐specific criteria.    Justification:  See Issue Paper “R‐5” in Appendix A on Pg. A‐38.  * James Clift did not concur in this recommendation.  Recommendation R‐6  Subject:  Effective Solubility and Free Phase Contamination    Recommendation:    

1. The  DEQ  should  immediately  discontinue  applying  the  unpromulgated  alternative criteria for gasoline that are based on USEPA effective‐solubility formulas and that are attached  to  the DEQ Draft Q&A document dated May 12, 2011, and should use  the existing promulgated criteria.   

2. To  the  extent  the DEQ  believes  that  new  criteria  are  appropriate  for  “free  phase” contamination,  it must seek the appropriate changes to Part 213 or promulgate new criteria under Part 201 pursuant to the Administrative Procedures Act.   

3. In developing any new criteria to address free‐phase contamination, the DEQ should use science and look to national best practices.   

4. The DEQ  should  allow  regulatory  flexibility when evaluating  “free phase”  situations where there is no demonstrated impact to groundwater present.  

  Justification:  See Issue Paper “R‐6” in Appendix A on Pg. A‐39.  Recommendation R‐7a  Subject:    Underground  Storage  Tank  Inspection  Delegation  and  Certification  (R  29.2071  –  R 29.2077)  Recommendation:  The rule set relating to Underground Storage Tank Inspection Delegation and Certification (R 29.2071 – R 29.2077) should be rescinded.    Justification:  See Issue Paper “R‐7a” in Appendix A on Pg. A‐41.    

Environmental Advisory Rules Committee Recommendations 

15

Recommendation R‐7b  Subject:  Part 211 – Underground Storage Tank (UST) Regulations   Recommendation:  The DEQ should review the current rules relating to Part 201 ‐ Underground Storage Tank Regulations  (R 29.2101 – R 29.2174)  to determine  the use and  relevance of  the current rules.   If  the  department  determines  the  rules  are  relevant  and  should  be  kept  in  place  then  they should review the rules with stakeholders to determine if particular rules should be updated or modified and if they exceed federal standards.   When  these determinations are made,  the DEQ  should work with  stakeholders  to modify  the rules  and  eliminate  those  rules  that  exceed  the  federal  standards,  unless  the  DEQ  can demonstrate  that  state‐specific  rules  are  necessary  to  protect  human  health  and  the environment.      Justification:  See Issue Paper “R‐7b” in Appendix A on Pg. A‐42.  Recommendation R‐7c  Subject:  Transportation of Flammable and Combustible Liquids (R 29.2201 – R 29.2234)  Recommendation:    The  rule  set  relating  to  Transportation  of  Flammable  and  Combustible Liquids  (R  29.2201  –  R  29.2234)  should  be  rescinded  because  it  is  redundant  with  existing transportation regulations.    Justification:  See Issue Paper “R‐7c” in Appendix A on Pg. A‐43.  Recommendation R‐7d  Subject:  Compressed Natural Gas (CNG) Vehicular Fuel Systems (R 29.4601 – R 29.4652)  Recommendation:    The  Compressed  Natural  Gas  (CNG)  Vehicular  Fuel  Systems  program  (R 29.4601 – R 29.4652)  is  related  to  fire  safety and  should be  transferred  from  the DEQ  to  the Bureau of Fire Services (within LARA) through an executive order.  Further, the Michigan‐specific amendments to the national codes should be rescinded and the current national codes should be adopted by reference.    Justification:  See Issue Paper “R‐7d” in Appendix A on Pg. A‐44.  Recommendation R‐7e  Subject:  Production, Storage, and Handling of Liquefied Natural Gas (R 29.4671 – R 29.4672)  Recommendation:    The  rule  set  relating  to  Production,  Storage,  and  Handling  of  Liquefied Natural  Gas  (R  29.4671  –  R  29.4672)  should  be  rescinded  because  there  are  no  applicable 

Environmental Advisory Rules Committee Recommendations 

16

facilities (existing or planned) in the state.    Justification:  See Issue Paper “R‐7e” in Appendix A on Pg. A‐45.  Recommendation R‐7f  Subject:  Storage and Handling of Flammable and Combustible Liquids (R 29.5101 – R 29.5516)  Recommendation:    

1. Transfer  the  Storage  and Handling  of  Flammable  and  Combustible  Liquids  program (including  Rules  29.5101  –  R  29.5516)  from  the  DEQ  back  to  the  Bureau  of  Fire Services (within LARA) through an executive order.   

2. The Bureau of Fire Services should amend these rules to rescind the current Michigan‐specific amendments to the national codes and then adopt by reference the current national codes (without state‐specific amendments). 

3. Concurrent with the rulemaking by the Bureau of Fire Services in Recommendation #2 above,  the  DEQ  should  determine  if  there  are  remaining  environmental  concerns specifically  related  to  the PIPP Part 5  rules  (R 324.2001 – R 324.2099) pertaining  to aboveground storage tanks.  If environmental concerns are identified, they should be evaluated  against  the  best  practices  in  neighboring  states  to  determine  whether additional regulations by the DEQ are truly necessary.   

   Justification:  See Issue Paper “R‐7f” in Appendix A on Pg. A‐46.  Recommendation R‐7g  Subject:  Liquefied Petroleum Gas (LPG) (R 29.6001 – R 29.6097)  Recommendation:    The  Liquefied  Petroleum  Gas  (LPG)  program  (R  29.6001  –  R  29.6097)  is related  to  fire  safety and  should be  transferred  from  the DEQ  to  the Bureau of  Fire  Services (within LARA)  through an executive order.   Further,  the Michigan‐specific amendments  to  the national  codes  should  be  rescinded  and  the  current  national  codes  should  be  adopted  by reference.    Justification:  See Issue Paper “R‐7g” in Appendix A on Pg. A‐48.  Recommendation R‐7h  Subject:    Storage  and Handling  of  Gaseous  and  Liquefied Hydrogen  Systems  (R  29.7001  –  R 29.7199)  Recommendation:   The Storage and Handling of Gaseous and Liquefied Hydrogen program  (R 29.7001 – R 29.7199)  is  related  to  fire  safety and  should be  transferred  from  the DEQ  to  the Bureau of Fire Services (within LARA) through an executive order.  Further, the Michigan‐specific amendments to the national codes should be rescinded and the current national codes should be adopted by reference.   

Environmental Advisory Rules Committee Recommendations 

17

Justification:  See Issue Paper “R‐7h” in Appendix A on Pg. A‐49.  Recommendation R‐8  Subject:    Definition  of  “Background”  Concentrations  for  Hazardous  Substance  in  Soil  and Groundwater  Recommendation:  The DEQ should consider “industrial background” concentrations (otherwise known  as  anthropogenic  contamination)  when  establishing  cleanup  goals  for  all  hazardous substances.   Specifically, the Part 201 statute, Rule 299.5701, and the Part 5 and Part 10 rules should  be  amended,  as  necessary,  to  create  a  process whereby  the DEQ will work with  the regulated  community  in  areas  containing  anthropogenic  contamination.    This  process  should include:  

1. The DEQ should make existing data regarding anthropogenic contamination across the state available to the regulated community. 

2. The  DEQ  should  allow  flexibility  for  the  regulated  community  to  develop  data regarding anthropogenic contamination for particular sites. 

3. At sites where anthropogenic contamination exists, there should be no obligation for an owner/operator to clean‐up the contamination.  Rather the DEQ should work with the owner/operator to develop a due‐care plan for the site. 

  Justification:  See Issue Paper “R‐8” in Appendix A on Pg. A‐50.  Recommendation R‐9  Subject:  Due Care for Indoor Air Inhalation at a Property Subject To MIOSHA Standards  Recommendation: The Part 201  inhalation criteria and due care related rules (R 299.5714(6), R 299.5724(6) and R 299.51013(5)), and if necessary, Part 201, should be modified and amended so that indoor air inhalation risk at workplaces could be addressed at the option of an owner or operator of property by applying MIOSHA and federal (USEPA) workplace exposure criteria for both workers  and non‐workers  in workplaces  in  lieu of  generic Part 201  criteria  and without regard  to  whether  or  the  extent  to  which  the  chemical  in  question  is  being  used  in  the workplace. This would include the deletion of the limitations contained in R 299.5714(6)(a)‐(c), R 299.5724(6)(a)‐(c)  and  R  299.51013(5)(a)‐(c).  In  addition,  if  generic  soil  gas  criteria  are promulgated, the criteria should be based on indoor air or inhalation exposure limits established under MIOSHA if established for the chemical in question.   Justification:  See Issue Paper “R‐9” in Appendix A on Pg. A‐51.  * James Clift did not concur in this recommendation.  Recommendation R‐10  Subject:  Soil Relocation Statute (MCL 324.20120c) and Associated Rules  

Environmental Advisory Rules Committee Recommendations 

18

Recommendation:    The  DEQ  should  implement  Section  20120c  to  permit  the  relocation  of contaminated  soils  within  facility  or  property  so  long  as  due  care  or  other  measures  are implemented which prevent human exposure or harm to the environment. In addition, the state should amend MCL 324 20120c and amend R 299.5542 to adopt proposed revised R 299.4110(l) in order  to  reduce  regulatory burdens  in  connection with  the proper  relocation of  soil under Part 201.  Justification:  See Issue Paper “R‐10” in Appendix A on Pg. A‐53.  Recommendation R‐11  Subject:  Source Control Requirements under MCL 324.20114(1) and R 299.5526(4)  Recommendation:   R 299.5526(4) should be amended to facilitate a clear understanding of the requirements of MCL 324.20114(1), including what constitutes a “source” subject to the Section.  Justification:  See Issue Paper “R‐11” in Appendix A on Pg. A‐55.  Recommendation R‐12  Subject:  Relationship between Part 201 & Part 213  Recommendation:  Combine Parts 201 and 213 into one statute and one program, merge staffs and  focus on one  set of  administrative  rules  to  govern  the  cleanup of  contaminated  sites  in Michigan.  Justification:  See Issue Paper “R‐12” in Appendix A on Pg. A‐56.  Recommendation R‐13  Subject:  Part 201 Due‐Care Plans Submitted As Response‐Activity Plans For SBA Loans  Recommendation:   Develop a Policy Guidance Document  that creates an expedited period  for reviews of due‐care plans in the SBA‐loan context.  Further, it would be helpful to the regulated community if the DEQ created a Policy Guidance Document outlining the content that the DEQ believes would comply with the due‐care‐plan requirement for SBA loans.    Justification:  See Issue Paper “R‐13” in Appendix A on Pg. A‐57.  Recommendation R‐14  Subject:  Boron Standard for Groundwater (R 299.5744)  Recommendation:   Amend R  299.5744  to use  the drinking water  standard  as  the  criteria  for boron.   Prior  to determining  to  the applicability of  the drinking water  standard at a  site,  the pathway must be reviewed to determine if the impacted portion of the receiving waters is being used for purposes of irrigation.  If the impacted portion of the receiving waters is being directly 

Environmental Advisory Rules Committee Recommendations 

19

used  for  irrigation,  then a  lower  standard may be  set at  the discretion of  the DEQ  to protect potentially sensitive crops.    Justification:  See Issue Paper “R‐14” in Appendix A on Pg. A‐58.  Recommendation R‐15  Subject:  Quality Review Team  Recommendation:   Discontinue  the DEQ’s Quality  Review  Team  process,  focusing  instead  on educating District  staff  and monitoring  appropriately.    The DEQ’s  process  to  educate District staff and monitor decision‐making  should  focus on achieving consistency, quality control, and collaboration with the regulated community.  Justification:  See Issue Paper “R‐15” in Appendix A on Pg. A‐59.  Recommendation R‐16  Subject:  Flexibility When Site Exceeds Only Secondary Non‐Health‐Based Standards    Recommendation:  The Part 201 statute and the Part 5 rules should be amended to provide the DEQ with  the  flexibility to approve a  limited closure at a site where hazardous substances are migrating  onto  adjoining  properties  at  levels  that  exceed  only  secondary  non‐health‐based standards and where  the affected property  is hooked up  to municipal water.   Specifically,  the amendments  should  authorize  the DEQ  to  approve  a  closure  at  these  sites  according  to  the following process:  

1. The owner/operator develops data regarding the plume‐migration characteristics and information  regarding  property  owners  within  the  plume  that  are  hooked  up  to municipal water. 

2. The owner/operator  sends notice  to  all  identified  property owners  informing  them that  contamination  exceeding  secondary  non‐health‐based  standards  is  migrating onto  their property and  that  the owner/operator has  requested a no‐further‐action letter from the DEQ, and the property  is a “Facility” subject to disclosure obligations under Part 201 or Part 213. 

3. The  notice  should  provide  each  landowner  a  period  of  time  (such  as  21  days)  to respond if they feel that the DEQ should not issue the no‐further‐action letter. 

4. If the DEQ does not receive any responses within that time period, the DEQ may move forward with  issuing the no‐further‐action  letter.   On the other hand,  if one or more landowners respond, the DEQ must review each response to determine whether the migrating contamination  is reasonably anticipated to  impair the use of the property.  If no such  impairment  is  found at any of  the properties,  the DEQ may  issue  the no‐further‐action letter. 

5. The  Part  201  statute  and  rules  should  explicitly  state  that  this  process  in  no way affects or limits any rights of a property owner. 

   Justification:  See Issue Paper “R‐16” in Appendix A on Pg. A‐60. 

Environmental Advisory Rules Committee Recommendations 

20

 Recommendation R‐17  Subject:  Review Part 201 Cross‐References  Recommendation:    The DEQ  and Attorney General’s office  should  review  all  cross‐references contained in the Part 201 rules and correct any errors.    Justification:  See Issue Paper “R‐17” in Appendix A on Pg. A‐61.  

c. RESOURCE MANAGEMENT RECOMMENDATIONS  Recommendation RM‐1  Subject:  Liquid Industrial Waste Regulations  Recommendation:   The DEQ  should develop  rules and/or  changes  to  the  statute(s) governing liquid  industrial waste  to make  the process of handling  these materials more streamlined and cost effective for the regulated community while protecting human health and the environment.  In the development of these rules and recommendations, the department should  look at what rules can be eliminated and how the various rules can be consolidated.  This rules package and/or statutory change recommendations must be evaluated in comparison to the federal standards and should be consistent with the programs in surrounding Great Lakes States. Any rules package and statutory changes should be presented to the Office of Regulatory Reinvention (ORR) by September 1, 2012.  The development of the liquid industrial waste recommendations must consider:  

The role of manifests in the hauling and disposal process.  The development of an electronic manifesting system.  De minimis and threshold quantities in determining applicability of the law or rule.   Duplicative rules and standards between the various parts of the Act(s) governing liquid 

industrial waste.  Whether certain insignificant materials such as used oil, wash water and other small or 

insignificant materials should be included in the Act.  How liquid industrial waste is handled under the present laws and rules.  Registration/licensing of liquid industrial waste haulers.  The reasons for using a licensed hauler.  Reasonable  insurance  and  financial  assurance  requirements  that  reflect  real  risk  and 

actual costs.  Whether the current list of materials in the Act should continue to be listed.  The option of regulating used oil as a universal waste.  Consider regulating other LIW wastes streams as universal waste. 

 Justification:  See Issue Paper “RM‐1” in Appendix A on Pg. A‐62.  

Environmental Advisory Rules Committee Recommendations 

21

 Recommendation RM‐2  Subject:  Beneficial Reuse  Recommendation:   The DEQ should develop, based on recommendations  from stakeholders, a new comprehensive Beneficial Reuse Act.  The recommendations of the stakeholder workgroup should be completed by April 1, 2012 and legislation prepared by May 1, 2012.  Justification:  See Issue Paper “RM‐2” in Appendix A on Pg. A‐63.  Recommendation RM‐3  Subject:  Michigan Hazardous Waste Regulations  Recommendation:    The DEQ  should  conduct  a  systematic  review  –  including  stakeholder  and public comment – of the chemicals and wastes  listed  in R 299.9226, Table 205c (“U”  listed); R 299.9219, Table 202  (“S”  characteristic); and R 299.9223, Table 204b  (“K”  listed). The  review should consider new  information about  the chemicals and wastes  to determine  if  they should remain on the lists or be removed.  Justification:  See Issue Paper “RM‐3” in Appendix A on Pg. A‐64.  * James Clift did not concur in this recommendation.  Recommendation RM‐4  Subject:  Rescind/Repeal Michigan PCB Regulations  Recommendation:   Michigan’s PCB rules (R 299.3301 – R 299.3319) should be rescinded. Make statutory  amendments  necessary  to  remove  PCB  regulations  from  Michigan  statute  (MCL 324.14701 – 324.14705).  Justification:  See Issue Paper “RM‐4” in Appendix A on Pg. A‐65.  Recommendation RM‐5  Subject:    Hazardous  Waste  Biennial  Reporting  Required  Under  the  Federal  Resource Conservation Recovery Act (RCRA) of 1976  Recommendation:    The DEQ  should  convene  a  stakeholder workgroup  to  develop  electronic biennial  reporting  for  hazardous  waste  generators  to  streamline  the  process  and  eliminate duplicative reporting.    Justification:  See Issue Paper “RM‐5” in Appendix A on Pg. A‐66.   

Environmental Advisory Rules Committee Recommendations 

22

 Recommendation RM‐6  Subject:  Financial Assurance for Landfills  Recommendation:    Part  115  should  be  amended  to  allow  for  additional  financial  assurance mechanisms,  and  to  streamline  and  create  a more  cost  effective method  of  assuring  proper funds are available for landfill emergencies and closure.   Justification:  See Issue Paper “RM‐6” in Appendix A on Pg. A‐67.  Recommendation RM‐7  Subject:  Hazardous Waste User Charge and Manifest Systems  Recommendation:    The DEQ  should  convene  a  stakeholder  group  to  redesign  the  hazardous waste user charge system to make it fair, simple and timely, and to develop electronic methods for minimizing the paperwork associated with the verification of hazardous waste manifests.     Justification:  See Issue Paper “RM‐7” in Appendix A on Pg. A‐68.  Recommendation RM‐8  Subject:  Medical Waste Storage Accumulation Limitation (Sharps Containers) Part 138, Medical Waste Regulatory Act, 1978 PA 368, As Amended  Recommendation:    Amend  the  Act  and/or  rules  governing  the  disposal  of medical waste  to require disposal of sharps that are used strictly for non‐medical procedures (a) when the storage container  is  full, or  (b) annually, whichever occurs  first. The sector(s)  receiving  this exemption should  be  defined  in  the  rules  to  avoid  having  sharps  containers  with  different  storage requirements within the same facility.  Justification:  See Issue Paper “RM‐8” in Appendix A on Pg. A‐69.  Recommendation RM‐9  Subject:  Conformance Bond or Statement of Financial Responsibility Requirements for Mineral Well (Disposal Well) Operators; Part 625, R 299.2330  Recommendation:    DEQ,  with  input  from  stakeholders,  should  attempt  to  enter  into  a memorandum of understanding with  the USEPA  to utilize  the same conformance bond, and  if successful, should rescind any duplicative rules.  Justification:  See Issue Paper “RM‐9” in Appendix A on Pg. A‐70.    

Environmental Advisory Rules Committee Recommendations 

23

 d. WATER RECOMMENDATIONS 

 Recommendation W‐1  Subject:    Part  5,  Spillage  of  Oil  and  Polluting  Materials,  of  the  NREPA  (PIPP,  TRQs,  911 Notification, Release Reporting Related To Secondary Containment)  Recommendation:    

1. Increase  the  threshold management  quantity  (TMQ) which  triggers  the  need  for  a Pollution Incident Prevention Plan (PIPP) from 440 pounds (about 1 barrel) to a more reasonable level of 500 gallons.  (R 324.2002(f)(iv)). 

2. Revise the threshold reporting quantities (TRQs) in Table 1 to make all TRQs similar to the  federal  CERCLA  RQs  (many  are  currently  only  1/10th  of  the  federal  level),  or eliminate Table 1 and reference the existing CERCLA RQs for the reporting thresholds.  (R 324.2009 Table 1). 

3. Revise MCL 324.3111b to eliminate the requirement to call local 911.  When reporting is necessary, calls are already required to the National Response Center and the DEQ PEAS hotline.   

4. Eliminate  the  reporting  requirements  related  to  releases  that  go  to  secondary containment.  (R 324.2002(b)(i)). 

5. Significantly  increase  the  reporting  threshold  for salt  to 1,000 pounds  for solids and 1,000 gallons for liquids.  (R 324.2002(g)(iii)). 

6. Increase the mixture threshold from its current 1% level to more of a 25 – 50% range.  (R 324.2002(a)(iv)). 

7. In general, revise Part 5 rules to make them easier to understand and follow.   Work with  regulated  community  to  establish  rules  that  are  understandable,  technically feasible, and will achieve intended results. 

8. Revise the conditional exemption in R 324.2003(1)(b) to reference the current version of  the SPCC  regulations at 40 CFR Part 112, currently dated October 14, 2010.   The current  rule  reference  is  the  1997  SPCC  regulation, making  the  current  conditional exemption useless. (R 324. 2003(1)(b)). 

 Justification:  See Issue Paper “W‐1” in Appendix A on Pg. A‐71.  * James Clift did not concur with parts of this recommendation.  Recommendation W‐2  Subject:  Mercury Rule for National Pollutant Discharge Elimination System (NPDES) Permits  Recommendation:  Allow an NPDES permittee with a water quality‐based effluent limit (WQBEL) for mercury in the permit to account for inlet loading concentration when their contribution to the effluent is negligible.  Language should be added to R 323.1211(7)(a) that states: 

 “If the mean effluent concentration is less than 10% greater than the mean inlet 

Environmental Advisory Rules Committee Recommendations 

24

concentration  (using 24  consecutive months of monitoring data) and does not exceed the mean  inlet concentration by more than 0.5 PPT, then the permittee should  be  exempt  from  the  PMP  requirements  and  subject  to  annual monitoring.”

Justification:  See Issue Paper “W‐2” in Appendix A on Pg. A‐76.  Recommendation W‐3  Subject:    R  299.2933(4)  Promulgated Under  Part  41,  Sewerage  Systems,  of  the NREPA  (MCL 324.4101 et seq.)      Recommendation:  R 299.2933(4) should be rescinded.  Justification:  See Issue Paper “W‐3” in Appendix A on Pg. A‐77.  Recommendation W‐4  Subject:  Part 22 Rules for Groundwater Discharges      Recommendation:  R 323.2210 should list types of discharges which do not require groundwater permits –  similar  to what  is done  in  the  storm water  regulations.   That  listing  should address issues  such  as:  potable  water,  fire  protection  water,  irrigation  drainage,  lawn  watering,  air conditioning condensate, and foundation or footing drains.    Justification:  See Issue Paper “W‐4” in Appendix A on Pg. A‐78.  Recommendation W‐5  Subject:  Part 301 (Section 30105) Inland Lakes and Streams; Part 303 (Section 30312) Wetlands Protection; and Part 325 (Section 32512) Great Lakes Submerged Lands of the NREPA  Recommendation:   Amend Michigan’s  Inland Lakes & Streams, Great Lakes Submerged Lands, and Wetlands programs to adopt the USACE Nationwide permitting approach of allowing non‐reporting general permits for minor projects below certain thresholds and individual permits for projects  above  those  thresholds.  Amend  the  Minor/General  Permit  Category  revisions accordingly.    To  ensure  consistent  program  implementation,  these  activities  should  be coordinated with any proposals from the Wetland Advisory Council.  Justification:  See Issue Paper “W‐5” in Appendix A on Pg. A‐79.  * James Clift did not concur in this recommendation.  Recommendation W‐6  Subject:    Implementation of General Federal Nationwide permits:   State 401 and Coastal Zone Management Certification of U.S. Army Corps of Engineers (USACE) Nationwide Permits    

Environmental Advisory Rules Committee Recommendations 

25

 Recommendation:    The  DEQ  should  review,  with  stakeholder  involvement,  all  44  USACE Nationwide Permits to determine  if the current MDEQ Nationwide permit denials or additional conditions make sense or  if they are more stringent than the federal requirements.   To ensure consistent program  implementation, these activities should be coordinated with any proposals from the Wetland Advisory Council.  Justification:  See Issue Paper “W‐6” in Appendix A on Pg. A‐80.  * James Clift did not concur in this recommendation.  Recommendation W‐7  Subject:  Sanitary Sewer Overflows Control    Recommendation:   Revise the Part 21 rules (R 323.2101 et seq.) to explicitly direct the DEQ to permit the diversion of separate sanitary flow to a combined sewer retention treatment facility for settling, screening, disinfection and discharge  in order to prevent sanitary sewer overflows (SSOs),  provided  such  discharge  to  a  combined  sewer  retention  treatment  facility  does  not violate water quality standards.  In addition, the DEQ should permit a sewage system operator that is under an administrative order to abate storm water infiltration and inflow to its sanitary collection  system,  to  divert  flow  from  the  separate  sanitary  system  to  a  combined  sewer retention treatment facility to provide the operator time to rehabilitate the sanitary collection system.  Justification:  See Issue Paper “W‐7” in Appendix A on Pg. A‐81.  Recommendation W‐8  Subject:  Agricultural Activities under Parts 301 and 303 of the NREPA  Recommendation:    The  DEQ  should work with  the  agricultural  community  to  resolve  issues related to the manner in which certain agricultural activities are regulated under Parts 301 and 303.  These include:  

the  extent  to  which  permits  are  required  for  activities  directly  relating  to  exempt activities, such as fencing for grazing; 

the cutting of trees and bushes within wetlands; and  whether  it  is appropriate to  limit the USEPA’s position regarding the Huggett ruling to 

only federal wetlands.    The primary consideration  in resolving these  issues should be to streamline the permit 

process, especially for activities that have a minimal impact on the environment.    Justification:  See Issue Paper “W‐8” in Appendix A on Pg. A‐83.  * James Clift did not concur in this recommendation. 

Environmental Advisory Rules Committee Recommendations 

26

 Recommendation W‐9  Subject:  Groundwater Discharge ‐ Part 22, Groundwater Quality Rules      Recommendation:   The DEQ  should pursue changes  to  the groundwater‐discharge program  in the Part 31 statute and the Part 5 and Part 22 rules to  focus on specific, significant threats to groundwater.    These  changes  should  include  expanding  the  permit‐by‐rule  categories  and eliminating categories requiring groundwater‐discharge permits for projects with minimal or no impact on groundwater.    Justification:  See Issue Paper “W‐9” in Appendix A on Pg. A‐84.  Recommendation W‐10  Subject:  Part 5, Spillage of Oil and Polluting Materials Rules  Recommendation:   Delete  the condition  in R 324.2003(1)(b) requiring  facilities  to submit SPCC plans in order to remain exempt from the Part 5 rules.      Justification:  See Issue Paper “W‐10” in Appendix A on Pg. A‐85.  * James Clift did not concur in this recommendation.  Recommendation W‐11  Subject:    Unduly  Restrictive  Requirements  for  NPDES  Permitting  of  Storm Water  Runoff  at Airports   Recommendation:   Provide DEQ with  additional  flexibility  in helping airports manage ADFs  in storm  water.  Adopt  rules  that  require  DEQ  to  develop  a  sector‐specific  general  permit  for airports  consistent with  federal  regulations  and USEPA’s Multi‐Sector General  Permit  for  Air Transportation  facilities  (Sector  S‐air  transportation  facilities)  and  that  don’t  impose requirements stricter than required under federal law.    Justification:  See Issue Paper “W‐11” in Appendix A on Pg. A‐86.  * James Clift did not concur in this recommendation.  Recommendation W‐12  Subject:  Wetland Mitigation Banks      Recommendation:    

1. The DEQ should expand the service area of mitigation banks to encourage more bank development (including in urban areas) and increase access to mitigation banks while 

Environmental Advisory Rules Committee Recommendations 

27

maintaining watershed protection.   2. The DEQ should seek US Army Corps of Engineers approval of smaller mitigation banks 

if deemed economically feasible.   3. The  DEQ  should  increase  the  on‐line  reporting  of  information  on  the  program, 

including trading information, to foster greater utilization of the banking program.   Justification:  See Issue Paper “W‐12” in Appendix A on Pg. A‐88.  Recommendation W‐13  Subject:  DEQ Annual Wastewater Report     Recommendation:    Rescind  R  299.9001  –  R  299.9007,  which  require  annual  wastewater reporting to the DEQ.  Justification:  See Issue Paper “W‐13” in Appendix A on Pg. A‐89.  Recommendation W‐14  Subject:  Local Regulation Of Wetlands:  MCL 324.03308, MCL 324.30309, and MCL 323.30310  Recommendation:   Amend Sections 324.03308, 324.30309, and 323.30310 of Act 451 of 1994 (NREPA), so that there is no authority for local wetland regulations.    Justification:  See Issue Paper “W‐14” in Appendix A on Pg. A‐90.  * James Clift did not concur in this recommendation.  Recommendation W‐15  Subject:  Coordinating Storm Water Operators for Construction Sites with Local Enforcement of Soil Erosion and Sedimentation Control  Recommendation:  Amend R 323.2190 to provide construction site owners the option of utilizing the  services  of  the  local  Part  91  Soil  Erosion  and  Sediment  Control  Inspectors  to  fulfill  the inspection and compliance reporting requirements.  Justification:  See Issue Paper “W‐15” in Appendix A on Pg. A‐91.  Recommendation W‐16  Subject:  NPDES Permitting for Construction Sites      Recommendation:   The Part 21 rules governing storm water discharges from construction sites should be amended to allow for a process that will exempt sites where it can be demonstrated that  there will be no discharge of  sediment  to a  surface water body.   This will eliminate  the requirement that a certified storm water operator be hired for sites that are between 1 and 5 

Environmental Advisory Rules Committee Recommendations 

28

acres where it has been demonstrated that there will be no discharge of sediment to a surface water body, and will eliminate the requirement of a submittal and approval of an “application” for sites over 5 acres, in instances where there is no anticipated impact to surface waters.    Justification:  See Issue Paper “W‐16” in Appendix A on Pg. A‐92.  Recommendation W‐17   Subject:    Safe Drinking Water – Cross Connection  Inspections of Residential, Commercial  and Industrial Properties       Recommendation:  Amend R 325.10113 to set a standard for the frequency of testing residential cross‐connections.     The  standard  should be based on data  that  is  compiled and analyzed  to determine the number and frequency of failures and identification of cross connection problems in  residential,  commercial  and  industrial  properties.  A  cost/benefit  analysis  should  be undertaken as well.   Justification:  See Issue Paper “W‐17” in Appendix A on Pg. A‐93.  Recommendation W‐18  Subject:  NPDES Water Treatment Additives    Recommendation:   The DEQ should create a “notification only” process for well‐defined water treatment additives (WTA) conditions that pose minimal toxicity concerns (e.g., the WTA would not  be  present  at  the  discharge  point  to  navigable  waters  in  toxic  amounts,  including  a conservative safety factor).  Justification:  See Issue Paper “W‐18” in Appendix A on Pg. A‐95.  Recommendation W‐19  Subject:  Mercury Standard for Groundwater   Recommendation:   DEQ  should work with  the USEPA  to  revise  the Great  Lakes  Initiative with respect  to  the  groundwater/surface  water  interface  criterion/wildlife  protection  value  for mercury of 1.3 ng/l, by applying current science.  Justification:  See Issue Paper “W‐19” in Appendix A on Pg. A‐96.  Recommendation W‐20  Subject:  Part 301 ‐ Inland Lakes and Streams – Permits Required For Drawdown Activities That Are Already Subject To Federal Energy Regulatory Commission (FERC) Authority    Recommendation:    Eliminate  the  Part  301  permitting  requirements  related  to  temporary drawdown activities for entities that are already subject to a FERC license. 

Environmental Advisory Rules Committee Recommendations 

29

 Justification:  See Issue Paper “W‐20” in Appendix A on Pg. A‐97.  

e. GENERAL RECOMMENDATIONS  Recommendation G‐1  Subject:  Rules More Stringent Than Federal    Recommendation:    Identify  existing DEQ  state  rules  and  specific  requirements  that  are more stringent than federal.  Evaluate these rules and specific requirements to determine the benefits received versus the additional cost of compliance. Then systematically review (based on priority) to revise or eliminate unjustified rules or specific requirements.    Justification:  See Issue Paper “G‐1” in Appendix A on Pg. A‐99.  Recommendation G‐2  Subject:  Treatment of DEQ Non‐Rule Regulatory Actions  Recommendation:    Take  the  following  actions  with  regard  to  DEQ  guidance  documents, educational documents and forms by the stated deadlines.  

Guidance Documents  

Rescind  DEQ  Policy  and  Procedures  No.  01‐019  (Policy  Development,  Revision  and Rescission  [1/12/07])  and  No.  09‐012  (Policy  Guidance  Document  Development, Revision, and Use [12/30/09]).  Complete by December 31, 2011. 

 Develop  a new  comprehensive DEQ policy  that  addresses department policy, division policy, guidance documents and guidelines.  For the most part, department and division policies  will  address  internal  administrative  or  personnel  procedures.    “Guidance documents” will  contain  all  rule  and  statute  interpretations,  and/or will  contain  any policy/procedure  that  provides  guidance  to  those  regulated  by  the  DEQ.    Guidance documents will  provide  a  particular  path  to  compliance with  a  rule  or  statute.    The regulated  community  may  choose  this  path  or  follow  a  different  one.  If  the  issue involves an  interpretation of a rule and/or statute, stakeholder  input will be obtained. For consistency, a template for guidance documents will be created and utilized by the divisions.  Finally, the new DEQ policy will provide an alternative approach to a guidance document which is a “Guideline” as defined by Administrative Procedures Act, 1969 PA 306, as amended.  Complete by December 31, 2011. 

  Create a DEQ Web page for guidance documents which will be categorized by division or 

office.  Complete by December 31, 2011.  

For those division policies that are draft or interim, the division should either rescind or finalize through the guidance document process.  Complete by June 1, 2012. 

Environmental Advisory Rules Committee Recommendations 

30

  Each division shall review their existing non‐rule regulatory actions.  Those meeting the 

definition of a guidance document (i.e., of  interest to the regulated community and/or interpret regulations) shall be converted into the new template and posted on the Web page.    If a division policy  interprets rules or statute and had stakeholder  input and no other substantive changes are being made, it can be directly converted into a guidance document without going through stakeholder  input for a second time.   Note: The DEQ Executive  Division  will  provide  each  Division  a  spreadsheet  containing  all  of  the division’s non‐rule regulatory actions that was compiled for the ORR in July 2011.  Those division  polices  not  converted  by  the  deadline  shall  not  be  relied  on.  Complete  by December 31, 2012.  

  Divisions  shall  review  internal  memos,  letters  and  other  documents  and  where 

appropriate,  convert  them  into  a  guidance  document  following  the  procedures identified above. Ongoing. 

 Educational Documents and Forms 

  Develop  two new DEQ policies providing  guidance  to DEQ  staff on  the production of 

educational publications and forms. Complete by December 31, 2011.  Update the DEQ Forms and DEQ Educational Publication online databases.  Complete by 

June 1, 2012.  Justification:  See Issue Paper “G‐2” in Appendix A on Pg. A‐100.  Recommendation G‐3  Subject:  Administrative Rule Approval Process  Recommendation:   The Committee recommends setting an expectation or requirement for the DEQ to take no more than 12 months for a proposed environmental administrative rule change.  The  process  should  incorporate  steps  to  ensure  adequate  public  comments  and  other discussions with stakeholders over accelerated schedules, as well as the use of innovative public input tools to increase public input and awareness of the proposed rulemaking.  Justification:  See Issue Paper “G‐3” in Appendix A on Pg. A‐102.  Recommendation G‐4  Subject:  DEQ Citation of Legal Authority  Recommendation:  When making a written determination which affects the rights of a Michigan citizen or business, the DEQ should always cite the applicable legal basis (statute, administrative rule, or common law) for its determination.  Justification:  See Issue Paper “G‐4” in Appendix A on Pg. A‐103.  

Environmental Advisory Rules Committee Recommendations 

31

 f. ADDITIONAL RULE RESCISSIONS AND AMENDMENTS 

 In addition to the foregoing recommendations, the DEQ already has or will be rescinding or amending the rules identified in the tables below.  Reasons for rescinding include: the rules are no longer enforceable; the statute providing promulgation authority has been repealed; or the rules are outdated and/or duplicative of federal regulation. 

 IDENTIFIED RULE RESCISSIONS 

PROGRAM  RULES  SUMMARY Air Quality R 336.1420  Rule 420 was promulgated under the former federal Clean Air 

Interstate Rule (CAIR), which has been vacated by the court.  Air Quality R 336.1933  This rule sets emission limitations for hospital/medical/infectious 

waste incinerators, including a mercury emission limitation more stringent than in the Clean Air Act Section 111(d) emission guidelines for State Implementation Plans (SIPs). There are no longer any sources in Michigan subject to this rule.  

Air Quality R 336.2830 and R 336. 2910 

Rule 1830 authorizes a person to request a contested case hearing if the person wants to challenge a DEQ permit decision for a major source of air pollution that is subject to the requirements for the prevention of significant deterioration (PSD) of air quality. The Michigan Court of Appeals determined that Rule 1830 was invalid. The Air Quality Division initiated deletion of this rule and Rule 1910 with similar opportunity for a contested case hearing upon learning the Court of Appeals decision. These rules were rescinded on June 29, 2011. 

Remediation  R 299.5201 ‐ R 299.5219 

Part 201, Part 2. Site Identification and Tracking rules were rescinded on May 20, 2011. 

Remediation  R 299.5601 –  R 299.5607 

Part 201, Part 6. Selection of Remedial Action rules were rescinded on May 20, 2011. 

Remediation  R 299.5801‐  R 299.5823 

Part 201, Part 8. Site Assessment Model rules were rescinded on May 20, 2011. 

Remediation  R 299.5901‐R299.5919 

Part 9. Baseline Environmental Assessments rules were made obsolete due to the Part 201 amendments enacted in December 2010. 

Remediation  R 324.1401‐ R 324.1422 

Environmental Laboratory Recognition Program rules were rescinded on August 1, 2011. 

Remediation  R 324.21501 –  R 324.21516 

Michigan Underground Storage Tank Qualified Consultants and Certified Professionals rules should be rescinded due to the administrative burden it places on the DEQ and the professionals. 

Resource Management R 299.4801 – 

R 299.4807 

Solid Waste Management Act Administrative Rules, Part 8. Grants. Funds have not been appropriated for the grants under these rules for more than 20 years. 

Environmental Advisory Rules Committee Recommendations 

32

Resource Management

R 299.12101 – R 299.12701 

Solid Waste Alternatives Program – Funds are no longer available and the program has been completed.  

Resource Management

R 325.421 –  R 325.426 

Outhouses.  Rules are obsolete.  

Resource Management

R 325.2581 – R 325.2591 

Marina Facilities.  Act repealed. 

Resource Management

R 325.5111a, b  and c and more 

Ionizing Radiation Rules are no longer needed due to the change in the U.S. Atomic Energy Act. 

Resource Management

R 325.5901  Peacetime Nuclear Incident rules have not been enforced since the federal regulations are more comprehensible.  

Water Resources 

R 281.816  Part 301, Inland Lakes and Streams. These rules address minor project categories which may become obsolete due to statutory changes.  

Water Resources

R 322.1013  Part 325, Great Lakes Submerged Lands. These rules address minor project categories which may become obsolete due to statutory changes. 

Water Resources

R 323.3001 – R 323.3027 

Water Quality Trading. These rules are overly complex and result in an ineffective and inefficient program. 

Water Resources

Portions of R 323.3104  and R 323.3107 

Aquatic Nuisance Control  

Water Resources

R 324.2003  Part 5. Spillage of Oil and Polluting Materials. Delete statement that the owner or operator of such a facility shall submit a copy of the facility’s spill prevention, control, and countermeasure plan in accordance with R 324.2006(d) 

Water Resources

R 324.2003(b)  SPCC regulations have been modified since the Part 5 rules were promulgated, so conditional exemption is no longer applicable. 

  

IDENTIFIED RULE AMENDMENTS PROGRAM  RULES  SUMMARY 

Air Quality  R 336.1119 and 336.1122 

General Provisions. The rule revision modifies existing definitions for the addition of PM2.5 requirement pertaining to PSD and for the definition of VOC. 

Air Quality  R 336.1401, 336.1401a, 336.1402 and 336.1404‐1407 

Emission Limitations and Prohibitions—Sulfur‐Bearing Compounds. Rule revisions will correct the deficiencies that the USEPA has identified in the rules where the Wayne County ordinance sulfur limits are incorporated. 

Air Quality  R 336.1420  

Emission Limitations and Prohibitions‐‐Sulfur‐Bearing Compounds. Rule revisions to incorporate new federal Transport Rule provisions. 

Environmental Advisory Rules Committee Recommendations 

33

Air Quality  R 336.1610‐1618  

Emission Limitations and Prohibitions—Existing Sources of Volatile Organic Compound Emissions. Rule revisions will remove primer surfacer and topcoat emission limits at auto assembly plants because now covered by federal limits, and will revise the asphalt paving rule for purposes of clarification. 

Air Quality  R 336.1801‐1834 

Emission Limitations and Prohibitions – Oxides of Nitrogen. Rule revisions to incorporate new federal Transport Rule provisions. 

Air Quality  R 336.1931, 336.1932, 336.1948, 336.1949 and 336.1950 

Emission Limitations and Prohibitions‐‐ Miscellaneous. Rule revisions for municipal solid waste landfills and municipal solid waste combustors will be needed to bring state rules in line with federal rules. Three proposed new rules will be needed to adopt federal rules by reference for state implementation of the federal area source regulations for iron and steel foundries, electric arc furnace steelmaking facilities, and aluminum, copper, and other nonferrous foundries. 

Air Quality  R 336.2801‐2823  

Prevention of Significant Deterioration (PSD) of Air Quality. Rule revisions to complete implementation of PM2.5, NO2, and SO2 permitting requirements. 

Air Quality  R 336.2901‐2908  

New Source Review for Major Sources Impacting Nonattainment Areas. Rule revisions to complete implementation of PM2.5, NO2, and SO2 permitting requirements. 

OEA 

R 324.14501‐14508  

Small Business Pollution Prevention Assistance Loan. These rules update and clarify the requirements for participation in the Small Business Pollution Prevention Loan Program, including applicability, eligibility, binding agreements, obligations, and procedures. Program changes as a result of Public Acts 333 and 334 of 2004, will be incorporated into these rule revisions. 

Remediation 

R 29.2101 et seq. 

Michigan Underground Storage Tank Rules (MUSTR). The RD has developed updates to the administrative rules promulgated pursuant to Part 211, Underground Storage Tank Regulations, of Act 451. Requires certification of underground storage tank owners and operators. The rule amendments require that the owners/operators of underground storage tanks obtain certification through the International Code Council, by August 8, 2012. The rule changes enable Michigan to comport with the current federal USEPA energy act requirements. 

Resource Management 

R 299.901 et seq. 

Hazardous Waste Management. Michigan is authorized by the USEPA to administer the state’s Hazardous Waste Management Program in lieu of the federal Hazardous Waste Management Program. Pending resolution of legal action at the federal level regarding the redefinition of solid waste provisions and draft legislation at the state level, the RMD anticipates initiating work on a rules package to address rules promulgated at the federal level since January 2008, and to reflect recent legislative changes regarding the former Site Review Board and the consolidation of the construction permit and operating license processes. 

Environmental Advisory Rules Committee Recommendations 

34

Resource Management 

R 325.1541 et seq. 

Medical Waste Producing Facilities. The RMD intends to develop rules to administer proposed amendments to Part 138, Medical Waste, of Act 368. Pending legislative action, a stakeholder work group will be convened by December 2011 to review draft rules for promulgation by August 2012. 

Resource Management 

R 324.102, 324.103 and 324.301 

Supervisor of Wells. These rules classify wells for storage of gas, including LPG, in salt caverns or other artificially‐created underground caverns, as “oil and gas” wells. They need to be reclassified as storage wells under Part 625. 

Resource Management 

R 299.2304  Mineral Wells, Part 625. We want to reclassify wells for storage of gas, including LPG, in salt caverns or other artificially‐created underground caverns, from “oil and gas” wells subject to Part 615 to “storage wells” subject to Part 625. 

Water Resources 

R 281.811‐46  Inland Lakes and Streams, Part 301. A RFR has been submitted and approved for these rules. The rule amendments include clarifying definitions and exemptions, updating and deleting outdated construction practices, modifying stream mitigation requirements, and updating the permit application review process and other permit related rules. Some of the revisions are required to maintain Michigan’s Section 404 of the Clean Water Act program assumption. 

Water Resources 

R 281.921‐25  

Wetlands Protection Program, Part 303. A RFR has been submitted and approved for these rules. These amendments include clarifying and updating the permit application and review process, wetland identification and assessment, and mitigation requirements. Many of the revisions are required to maintain Michigan’s Section 404 of the Clean Water Act program assumption. 

Water Resources 

R 299.6013  Aboriginal Records and Antiquities, Part 761. A RFR has been submitted and approved for these rules. The proposed rule would establish the West Michigan Great Lakes Bottomland Preserve to protect, promote, and preserve historical shipwrecks in the Great Lakes. The proposed rule would be the actual legal description of the preserve boundaries. 

Environmental Advisory Rules Committee Recommendations 

A‐1

APPENDIX A  

ISSUE PAPERS FOR FINAL RECOMMENDATIONS  

AIR QUALITY RECOMMENDATIONS NUMBER  SUBJECT                PAGE 1    Air Toxics Rules               A‐4 2    Mercury Rules: Part 15 Rules, (R 336.2501 – 2514)      A‐7 3    Additional Rule 201 (Permit to Install) Exemptions      A‐8 4    Rule 206 Process Deadlines            A‐10 5    Dispersion Modeling Guidance Document        A‐11 6    Averaging Times and Compliance Testing – AQD Operational     A‐12     Memorandum No. 18 7    Rule 801, Rule 803 and State Implementation Plan      A‐13 8    Michigan Continuous Emissions Monitoring Rules (Part 11)    A‐14 9    Visible and Particulate Emission Limitations        A‐15 10    R 336.1330                A‐16 11    R 336.1901 – General Nuisance Rule          A‐17 12    Electronic Application for New Source Review        A‐18 13    Stakeholder Involvement in SIP Development        A‐20 14    Addition of New Permit to Install Exemptions and Clarification    A‐21     of Existing Exemptions 15    VOC Emissions from Pharmaceuticals (R 336.1625)      A‐22 16    Volatile Organic Compounds (VOCs) – R 336.1611 and R 336.17(3)(4)  A‐23 17    Rule 703, Gasoline Storage Tanks (>2000 gal)        A‐24 18    R 336.1349                A‐25 19    Limiting Compounds Required for Annual MAERS Report    A‐26 20    Putting a Hold on the 18‐Month Construction Window for PTI    A‐27      

REMEDIATION RECOMMENDATIONS NUMBER  SUBJECT                PAGE 1    Groundwater/Surface‐Water Interface (GSI)        A‐28 2  Part 201/213 Vapor Intrusion Criteria          A‐31 3  Revising Part 201 Cleanup Criteria          A‐35 4  Part 201 Rules                A‐36 5  Risk‐Based Closures and Site‐Specific Criteria        A‐38 6  Effective Solubility and Free Phase Contamination      A‐39 7a  Underground Storage Tank Inspection Delegation and       A‐41   Certification (R 29.2071 – R 29.2077) 7b  Part 211 – Underground Storage Tank (UST) Regulations     A‐42 7c  Transportation of Flammable and Combustible Liquids (R 29.220 –   A‐43 

R 29.2234) 7d  Compressed Natural Gas (CNG) Vehicular Fuel Systems (R 29.4601 –  A‐44   R 29.4652) 7e  Production, Storage, and Handling of Liquefied Natural Gas     A‐45 

(R 29.4671 – R 29.4672) 

Environmental Advisory Rules Committee Recommendations 

A‐2

7f  Storage and Handling of Flammable and Combustible Liquids     A‐46 (R 29.5101 – R 29.5516) 

7g    Liquefied Petroleum Gas (LPG) (R 29.6001 – R 29.6097)      A‐48 7h    Storage and Handling of Gaseous and Liquefied Hydrogen Systems  A‐49     (R 29.7001 – R 29.7199) 8  Definition of “Background Concentrations for Hazardous Substance in  A‐50   Soil and Groundwater 9  Due Care for Indoor Air Inhalation at a Property Subject to MIOSHA  A‐51   Standards 10  Soil Relocation Statute (MCL 324.20120c) and Associated Rules    A‐53 11  Source Control Requirements under MCL 324.20114(1) and     A‐55 

R 299.5526(4) 12  Relationship between Part 201 & Part 213        A‐56 13  Part 201 Due‐Care Plans Submitted as Response‐Activity Plans for SBA  A‐57   Loans 14  Boron Standard for Groundwater (R 299.5744)        A‐58 15  Quality Review Team              A‐59 16  Flexibility When Site Exceeds Only Secondary Non‐Health‐Based   A‐60   Standards 17  Review Part 201 Cross‐References          A‐61 

 RESOURCE MANAGEMENT RECOMMENDATIONS 

NUMBER  SUBJECT                PAGE 1  Liquid Industrial Waste Regulations          A‐62 2  Beneficial Reuse              A‐63 3  Michigan Hazard Waste Regulations          A‐64 4  Rescind/Repeal Michigan PCB Regulations        A‐65 5  Hazardous Waste Biennial Reporting Required Under the     A‐66   Federal Resource Conservation Recovery Act (RCRA) Of 1976 6  Financial Assurance for Landfills          A‐67 7  Hazardous Waste User Charge and Manifest Systems    A‐68 8  Medical Waste Storage Accumulation Limitation (Sharps    A‐69   Containers) Part 138, Medical Waste Regulatory Act, 1978 PA    368, as Amended 9  Conformance Bond or Statement of Financial       A‐70   Responsibility Requirements for Mineral Well (Disposal Well)   Operators; Part 625, R 299.2330  

WATER RECOMMENDATIONS NUMBER  SUBJECT                PAGE 1    Part 5, Spillage of Oil and Polluting Materials, of the NREPA     A‐71 

(PIPP, TRQs, 911 Notification, Release Reporting Related To  Secondary Containment) 

2    Mercury Rule for National Pollutant Discharge Elimination System   A‐76 (NPDES) Permits 

Environmental Advisory Rules Committee Recommendations 

A‐3

3    R 299.2933(4) Promulgated Under Part 41, Sewerage Systems,     A‐77 of the NREPA (MCL 324.4101 et seq.) 

4    Part 22 Rules for Groundwater Discharges        A‐78 5    Part 301 (Section 30105) Inland Lakes and Streams; Part 303     A‐79 

(Section 30312) Wetlands Protection; and Part 325 (Section 32512)  Great Lakes Submerged Lands of the NREPA 

6    Implementation of General Federal Nationwide Permits:  State 401   A‐80 and Coastal Zone Management Certification of U.S. Army Corps of  Engineers (USACE) Nationwide Permits 

7    Sanitary Sewer Overflows Control          A‐81 8    Agricultural Activities Under Parts 301 and 303 of the NREPA    A‐83 9    Groundwater Discharge ‐ Part 22, Groundwater Quality Rules    A‐84 10    Part 5, Spillage of Oil and Polluting Materials Rules      A‐85 11    Unduly Restrictive Requirements for NPDES Permitting of Storm   A‐86 

Water Runoff at Airports 12    Wetland Mitigation Banks            A‐88 13    DEQ Annual Wastewater Report           A‐89 14    Local Regulation of Wetlands:  MCL 324.03308, MCL 324.30309,   A‐90 

and MCL 323.30310 15  Coordinating Storm Water Operators for Construction Sites with Local   A‐91   

Enforcement of Soil Erosion and Sedimentation Control 16    NPDES Permitting for Construction Sites         A‐92 17    Safe Drinking Water – Cross Connection Inspections of Residential,   A‐93 

Commercial and Industrial Properties 18    NPDES Water Treatment Additives            A‐95 19    Mercury Standard for Groundwater           A‐96 20    Part 301 ‐ Inland Lakes and Streams – Permits Required for Drawdown   A‐97 

Activities That Are Already Subject to Federal Energy Regulatory  Commission (FERC) Authority 

 GENERAL ISSUES RECOMMENDATIONS 

NUMBER  SUBJECT                PAGE 1    Rules More Stringent Than Federal           A‐99 2    Treatment of DEQ Non‐Rule Regulatory Actions        A‐100 3    Administrative Rule Approval Process          A‐102 4    DEQ Citation of Legal Authority            A‐103

Environmental Advisory Rules Committee Recommendations 

A‐4

Air Quality Recommendations  No. A–1  Subject:  Air Toxics Rules Regulation: R 336.1224 – R 336.1232 Remedy:     Process    Rules    Statute  Background/Issue:    In 1992, Michigan  approved  state‐only  air  toxics  regulations  and,  for  the most part,  they  remain  in effect  today.   The  rule development and approval process  required several years of prior discussions with industrial and environmental groups, well before passage of the federal 1990 Clean Air Act (CAA) amendments.  Prior to passage of the CAA amendments, the  federal  regulations  concerning  potential  air  toxics  were  limited  to  approximately  5 compounds.  Title  III of  the 1990 Clean Air Act Amendments  established  a national  regulatory program  to minimize  the emissions of  the most significant air  toxics.   Since passage of  the 1990 CAA,  the federal government has developed numerous Maximum Achievable Control Technology (MACT) determinations  for  a  wide  variety  of  processes  that  typically  emit  hazardous  air  pollutants (HAPS).    Any  MACT‐subject  source  is  required  to  comply  with  (1)  the  federal  emission limitations, (2) specified emissions control technologies, and (3) specific monitoring, testing, and reporting  requirements.     Therefore, Michigan’s outdated air  toxics  regulations are  in need of significant reform.  In developing each MACT standard, USEPA focused on the most significant HAPS emitted from a specific process  type,  then developed emission  control  strategies  that are as  stringent as  the control  systems  required  to  meet  the  intent  of  Michigan  Rule  224.    Not  all  potential  air pollutants were evaluated by USEPA during development of  the MACT  standards, nor  should they have been.   The USEPA regulations focus on specific organic and non‐organic HAPS, while the  Michigan  program  focuses  on  each  individual  pollutant.  The  emission  control  systems required by MACT are as stringent as those required by Rule 224, although MACT uses emission surrogates such as CO and PM  to certify reductions  in potential HAPS, whereas Michigan’s air toxics regulations review each potential pollutant  individually.   The end results for determining the adequacy of a proposed emissions control system is essentially the same.   Recommendations:  The Committee makes the following recommendations regarding Air Toxic rules:  

The parts of R 336.1224 dealing with  compounds  that are  considered volatile organic  compounds  (VOCs)  should  be  rescinded.    Portions  of  R  336.1224  are redundant because R 336.1702 requires a control technology review for VOCs. VOC‐based emission control is more effective under R 336.1702 and this entire regulation exceeds federal standards.   

Rule 336.1225 should be amended to specifically include the following:  Limit permit modification reviews to those  increases  in a Hazard  Index 

exceeding 10% above the previously permitted baseline.  Exempt sources that are identified in a MACT source category. 

Environmental Advisory Rules Committee Recommendations 

A‐5

Exempt clean fuels such as natural gas, low sulfur #2 Fuel Oil, and non‐chemically treated biofuels. 

Exempt pollution control projects for existing sources from the air toxic regulations. 

Limit the number of air toxics to the federal HAPS list.  Make  the  acceptable  exposure  limits  consistent  with  other  nearby 

states.  Stop  requiring  permit  holders  to  conduct  elaborate  and  costly  stack 

tests  to provide emissions  research data,  since  the DEQ does not use this information for subsequent permit reviews.   

R 336.1228 should be rescinded. This rule allows the Air Quality Division to go beyond the requirements of the rule for any reason. 

 Rationale/Comments:    These  proposed  revisions  to Michigan’s  air  toxics  regulations  would serve  to  level  the  playing  field with  other  states  vying  for  additional  industrial  growth,  and would not result  in a back‐sliding of the environmental programs (see supplemental document Issue  A‐1,  Attachment  1).    The  current  system  of  reviewing  the  impacts  of  every  feasible, potential air toxic results in nothing more than a “numbers game” that only serves to heighten public anxiety  , delay permit  issuance and waste several hundreds of  thousands of dollars  for stack  testing  that could be put  to better use  for  industrial expansions, process  improvements and  other  more  beneficial  programs.  Please  review  supplemental  document  Issue  A‐1, Attachments  2  and  2a  related  to  the  Public  Participation  Document  for  Frontier  Renewable Resources PTI 166‐09.  You can see that only 6 of the 37 identified air toxics (based on the firing of  natural  gas)  have  a  predicted  air  quality  impact  at  least  50%  of  their  individual  ambient limitations.    Furthermore,  the  Permit  to  Install  document  for  the  Mancelona  Renewable Resources project contained in Issue A‐1, Attachment 3 requires the company to spend tens of thousands of additional dollars to perform stack testing for 28 potential air toxics (the majority of  which  are  predicted  to  be  emitted  in  trace  levels)  generated  from  the  burning  of  non‐chemically treated biomass (wood).     This has also been a consistent issue for Michigan’s Asphalt Plant industry for the past 20+ years (see supplemental document Issue A‐1, Attachment 4).  The AQD has required stack testing for compounds that have proven to have ambient impacts well below any state or federal standard.  Had the AQD invested the time to compile the results of these historical stack tests, which have been consistently submitted to AQD for the past 20+ years, it would be readily apparent that the vast majority of these air toxics of concern would no longer be an issue.  This would result in a more  expedited  air  permitting  process,  reduce  stack  testing  requirements  for  new  Asphalt Plants and save companies several thousands of dollars in unnecessary stack testing.   Supplemental document Issue A‐1, Attachment 5, provides a summary of issues related to a 2+ year delay in issuance of an air permit for use of Biodiesel in a large utility boiler when the same fuel is widely used in this company’s fleet vehicles.  Supporting document Issue A‐1, Attachments 6 and 6a relate to air toxics issues for raw material and  fuel  substitutions  that  can  be  expanded  to  several  other  types  of  manufacturing  and combustion processes.     As noted  in our final recommendations, we believe a Hazard  Indexing 

Environmental Advisory Rules Committee Recommendations 

A‐6

methodology be established by  rule  to allow  for  raw material  /  fuel  substitutions  that do not have a detrimental ambient  impact.   This  is consistent with our  recommendation  in A‐1, Rule 336.1225.     James Clift Comments:  The environmental community believes that a company or person who wants to emit a toxic chemical into the environment should have the duty to demonstrate that emission of that toxic chemical will not adversely impact natural resources or public health.  By requiring testing before chemical are released, we are providing companies with the  incentive to develop safer alternatives through green chemistry.      If  the  federal government has developed a MACT, BACT or LEAR  standard  for a chemical, we support that standard being applied as the Michigan standard. However, if such a standard has not  been  developed,  we  believe  the  source  should  be  subject  to  T‐BACT.    Exempting  all chemicals  not  on  the  list  federal  list  of  hazardous  air  pollutants  could  provide  an  unwise incentive  for  companies  to  use  chemicals  for which  there  has  been  less  testing  and  analysis versus the use of less toxic alternatives.    We  support  Rule  228  which  is  designed  to  protect  Michigan  citizens  from  persistent bioaccumative toxic chemicals.    

Environmental Advisory Rules Committee Recommendations 

A‐7

No. A‐2 Subject: Mercury Rules: Part 15 Rules, (R 336.2501 – 2514) Regulation: Part 15 Rules, (R 336.2501 – R 336.2514) Remedy:  Process    Rules     Statute  Background/Issue:  The Michigan Mercury Rules became effective in 2009 and contain mercury emission  limitations  for  coal‐fired  utility  boilers.  Eighteen  other  states  have  also  adopted regulation  reducing mercury  from power plants,  including  Illinois, Wisconsin, Minnesota,  and New York.  Many of the provisions in the Michigan Mercury Rules will be redundant with federal electric generating units (EGU) Maximum Achievable Control Technology (MACT) expected to be issued in fourth quarter 2011.    The current Michigan rule also requires expensive and expansive planning efforts and reporting on  those plans  to  the DEQ with penalty deadlines which may not be  required by EGU MACT.  The  first  of  these  requirements  has  a  deadline  in  2012.    It  is  anticipated  that  the Michigan Mercury Rule will be in effect for one year before EGU MACT becomes effective.    Proposed Solution:   Amend Part 15 rules to add a statement that stays compliance with Rules 336.2512, 336.2503(2)(a) & (6), 336.2509(1) and 336.2513(1)(a) & (3)  until January 1, 2015.  The Michigan Mercury Rules’ requirements will be effective on this date unless an applicable federal rule to control mercury has been published in the Federal Register.  Once the applicable federal rule to control mercury has been published, the Michigan Mercury Rules should be rescinded.  Rationale  for Change/Additional Comments:   USEPA proposed  the EGU MACT  that will cover mercury emissions on March 16, 2011. It is anticipated the proposed EGU MACT will be finalized fourth quarter in 2011 and it will require the same type of control equipment to control mercury emissions as the Michigan Mercury Rules.  A recent analysis demonstrated that the EGU MACT, as currently proposed, would reduce state‐wide mercury emissions  from coal‐fired plants  to a greater  extent  than  the Michigan Mercury  Rules.  For  that  reason we  should  not  spend  any resources  (DEQ  or  the  regulated  community)  on  developing,  submitting,  reviewing  and approving compliance plans and mercury permits (as required by the Michigan Mercury Rule as early as 2012) until the EGU MACT is final.  It is also anticipated that all the substantive federal requirements to control mercury will be effective on January 1, 2015 so that is the rationale for using that date as a backstop for the Michigan Mercury Rule requirements.  James Clift Comments:  The environmental community believes that when the federal rule has been finalized it should be compared with the Michigan rule.  After that review, we can support modification of the rule to eliminate any redundant provisions which are included in the federal rule.      

Environmental Advisory Rules Committee Recommendations 

A‐8

No. A‐3  Subject: Additional Rule 201 (Permit to Install) Exemptions    Regulation: New Rule Remedy:     Process    Rules    Statute  Background/Issue:  By rule (R 336.1201), any process that “may emit” an air contaminant must first  obtain  a  pre‐construction  permit  (“permit  to  install”)  unless  it  is  covered  by  a  specific exemption  contained  in  R  336.1278  –  R  336.1290.    There  are  too many  categories  of minor emission sources for DEQ to issue specific exemptions for all of them.  The broadest exemption (R 336.1290) is limited to VOC and PM emissions and is too cumbersome and complex for many facilities to understand and use.    USEPA  is  also  very  slow  and  somewhat  reluctant  to  approve  revisions  to  DEQ’s  permit exemption  rules.   USEPA has not approved  revisions  to permit  to  install exemptions  for many years.  Some exemptions have been pending since 1992.  Sources relying on permit exemptions adopted  since  1980  are  currently  in  a  legal  limbo  –  exempt  under  state  law,  but  arguably required to get a permit under the State Implementation Plan (SIP).    Proposed Solution:   Michigan  should adopt a new exemption  rule  for minor  sources with de minimis potential to emit. This exemption rule should be similar to the minor new source review thresholds  adopted by  the USEPA  for  its own permitting program  in  Indian Country  (40 CFR, Subpart C), and should read as follows:  “New sources with a potential  to emit  less  than  the  following amounts  in an attainment area would be exempt from the requirement to obtain a permit to install: 

CO        10 tpy NOx        10 tpy SO2        10 tpy VOCs  (non‐carcinogenic)   5 tpy PM        10 tpy PM10         5 tpy PM2.5         3 tpy Lead        0.1 tpy Fluorides       1 tpy Sulfuric Acid Mist     2 tpy Hydrogen Sulfide     2 tpy Total Reduced Sulfur   2 tpy Reduced Sulfur Compounds   2 tpy MSW Combustors     2 tpy MSW Landfills      10 tpy 

 In non‐attainment areas, the NAA compound‐specific thresholds would be: 

CO        5 tpy NOx        5 tpy SO2        5 tpy VOCs (non‐carcinogenic)  2 tpy PM        5 tpy 

Environmental Advisory Rules Committee Recommendations 

A‐9

PM10        1 tpy PM2.5        0.6 tpy Lead        0.1 tpy 

 Rationale/Comments:  The proposed exemption would supplement the existing permit to install exemptions,  so  sources  relying  on  existing  exemptions  can  continue  to  use  the  existing exemptions contained  in R 336.1278 – R 336.1290.   R 336.1278  is an effective  tool  to avoid a conflict with the federal Major Source applicability requirements.    The proposed exemption would apply to a broad spectrum of small emission sources, alleviating the need  for  industry and DEQ  to  spend  limited  resources on permits  for  sources and  source changes that are really too small to warrant a permit review process.  USEPA should not object to  including  this exemption  in  the State  Implementation Plan because USEPA has  included an exemption based on these emission thresholds in its own rules for minor new source review in Indian Country ((see 40 CFR 49.153 (76 Fed. Reg. 38748 – July 1, 2011)).  James  Clift  Comments:    The  environmental  community  does  not  support  an  exemption  for facilities that annually emit 2 to 5 tons of volatile organic compounds.       

Environmental Advisory Rules Committee Recommendations 

A‐10

No. A‐4  Subject: Rule 206 Process Deadlines�Regulation:  R 336.1206 Remedy:  Process    Rules     Statute  Background/Issue:   R 336.1206  is worded too generally and needs more specificity. Major and minor permit decisions must be made  in a  timely manner.   Currently,  the AQD’s performance goal is to act on final permits within 180 days of receipt of an application.  In addition, there are no Part 1 definitions  for administratively and/or  technically complete as  these  terms relate  to the Permit to Install (PTI) program.      Proposed  Solution:    R  336.1206  must  be  more  specific  and  must  include  a  definition  for “administratively complete”. The rule should be amended to: 

Include a definition of “administratively complete” in Part 1.  Require  the  Air  Quality  Division  (AQD)  to  make  an  “administratively  complete” 

determination within 10 days of the receipt of the application.  Require AQD to act (issue or deny) on all minor source Permit to Install (PTI) applications 

within 180 days of receipt. This should include “opt‐out” PTIs.  Require  AQD  to  act  (issue  or  deny)  all  major  source  and  major  modification  PTI 

applications within 240 days from the date of receipt.  Allow  for  the  extension  of  these  deadlines  with  the  mutual  consent  of  both  the 

applicant and the DEQ.    Rationale for Change/Additional Comments:  The current wording within the rule is too vague and Rule 206 should be revised for permit action by specific deadlines, for both minor and major source  PTI  based  upon  date  of  receipt  of  the  permit  application.    This would  provide more regulatory  certainty,  and  speed  the  issuance  of  permits.    Historically,  the  term  “technical completeness”  has  been  somewhat  arbitrarily  determined  as  supported  by  lack  of documentation within existing PTI application  files.   Basing permit decisions on an application receipt date is more definitive.  Note:   The electronic permit application process  recommended as part of  this  Issues package (Issue A‐14) would help alleviate any confusion concerning whether a permit application is or is not administratively complete, as evidenced  in  the existing ROP application submittal process.  In addition, an electronic permit application process, currently available in several other states, would help promote a more consistent agency  technical  review process because  the  required technical data as identified within the permitting forms would limit the technical inconsistencies amongst the agency’s permitting staff.  James  Clift  Comments:    The  environmental  community  notes  that  applicants  for  permit  to install in Michigan pay no permit fees.  Many of our neighboring states collect significant permit fees  and  are  thus  able  to  issue  permits  in  a  timely manner.    The  environmental  community believes that state should institute new permit fees in this area to provide prompt attention to new applications.     

Environmental Advisory Rules Committee Recommendations 

A‐11

No.  A‐5 Subject:  Dispersion Modeling Guidance Document Regulation:  Remedy:     Process    Rules    Statute  Background/Issue:   For minor source air permits (i.e., those not classified as a major source or major modification),  the  AQD's  old  policy  (as  elaborated  in  the  internal  AQD memorandum revised  on March  19.  1998,  available  on AQD’s web  site) was  that  air  quality modeling was generally  only  required  if  the  potential  annual  emissions  increase  was  greater  than  the significant emission rate (SER) thresholds (i.e., 40 tons/year for NOx and SO2, 100 tons/year for CO, etc.).    With  the  recent promulgation of 1‐hour National Ambient Air Quality  Standards  (NAAQS)  for both NOx and SO2,  the AQD  is often  requiring air quality modeling even  though  the emission increases  are well  below  the  SER  thresholds.    This  is  contrary  to  the  current AQD Guidance Document, as well as  federal guidance  issued over  the  last year or so  regarding  these new 1‐hour  NAAQS.    This  has  unfortunately  resulted  in  leaving  the modeling  decision  to  the  DEQ permit engineer assigned to review the permit.  This obviously creates confusion on the part of the applicant, as they are not sure whether the application should include modeling.  The costs of conducting the modeling exercises are highly variable and largely depend upon the complexity of the associated site and whether existing sources must also be  included.   Rule of thumb estimates to complete these modeling efforts are typically between $7,500 and $50,000, including  the  preparation  and  submittal  of  a  modeling  protocol  document  and  obtaining detailed  hourly  background  concentration  data  for  use  in  more  sophisticated  dispersion modeling techniques.   Proposed  Solution:    The  DEQ  should  organize  a  stakeholders  group  by  January  1,  2012  to develop a new Policy Guidance Document  (PGD)  that considers  the new National Ambient Air Quality (short‐term) Standards (NAAQS) for NOx and SO2.   Finalization of the new PGD should become effective no later than March 1, 2012.  This PGD should be modified, with stakeholder consensus, within 90 days of USEPA’s promulgation of any subsequent new or revised NAAQS.  Rationale  for Change/Additional Comments:    Implementation of  this  recommendation would increase consistency for permit application development and submittals.    

Environmental Advisory Rules Committee Recommendations 

A‐12

No. A‐6 Subject:  Averaging Times and Compliance Testing ‐ AQD Operational Memo No. 18 Regulation:  Remedy:     Process    Rules    Statute  Background/Issue:   On February 26, 2004,  the AQD  issued Operational Memorandum No. 18 requiring companies to accept emission limits based on shorter averaging periods (1‐hour versus 24‐hour) or accept longer testing times to match the averaging time period.  This was strictly an internal agency policy decision and not required by federal  law.   As a result, companies had to eliminate potential operational flexibility by agreeing to shorter  (emission) averaging times, or face extended (costly) compliance testing that was unnecessary to demonstrate compliance.  Proposed Solution:  The DEQ should review Air Quality Division’s Operational Memorandum No. 18 to ensure it is consistent with federal test methods and make changes to the Memorandum if necessary.  Stakeholder input should be included in any change to the Memorandum.  Rationale  for  Change/Additional  Comments:    The  recommendation  will  provide  companies with  operational  flexibility without  having  to  repeat  costly  and  excessive  stack  testing.    The current (Option 3) proposal in Operational Memorandum No. 18 essentially requires a company to restrict operational flexibility for the sake of minimizing costs for compliance demonstrations.  Other  Great  Lakes  states  do  not  have  such  a  policy  and  typically  follow  the  recommended USEPA Test Method protocols for compliance. 

Environmental Advisory Rules Committee Recommendations 

A‐13

No. A‐7 Subject:  Rule 801, Rule 803 and State Implementation Plan Regulation:  Rule 801, Rule 803 and State Implementation Plan Remedy:  Process    Rules     Statute  Background/Issue:   Michigan pulls  large  generating units  (that do not produce  electricity  for sale)  into  the rule, making  it more stringent  than  federal requirements. The  federal rules only pull in units that also contribute electricity to the grid.  Proposed Solution:   The Air Quality Division  (AQD) should amend R 336.1801 and R 336.1803 and the State Implementation Plan (SIP), to only include electrical generating units (EGU’s) that contribute  electricity  to  the  grid.   A  stakeholder  group  should  commence  rules development activities by  January 1, 2012 and  submit a proposed  rules package  for public comment by no later than April 1, 2012.  Rationale for Change/Additional Comments:  Michigan pulls large generating units into the rule (that do not produce electricity for sale), making it more stringent than federal requirements.  James Clift Comments:   The environmental community believes that all  large generating units should be  subject  to  regulations designed  to  reduce  their public health  impacts on Michigan residents.   Whether  the  electricity  is  sold  onto  the  grid  should  be  irrelevant  to  the  issue  of determining reasonable control measures.  

Environmental Advisory Rules Committee Recommendations 

A‐14

No. A‐8 Subject: Michigan Continuous Emission Monitoring Rules (Part 11) Regulation: R 336.2170 Remedy:  Process    Rules     Statute  Background/Issue:    This  rule  provides  that  an  Excess  Emissions  Report  is  required  to  be submitted quarterly.  Federal rules only require semi‐annual submission.    Proposed Solution:  R 336.2170 should be amended to be consistent with the federal reporting requirements and  limited  to semi‐annual  reporting of excess emissions. The present Michigan rule requires quarterly reporting.  Rationale for Change/Additional Comments:  Consistency with federal requirements.  

Environmental Advisory Rules Committee Recommendations 

A‐15

No. A‐9  Subject: Visible and Particulate Emission Limitations Regulation:  R 336.1301(c) and R 336.1331(b)  Remedy:  Process    Rules     Statute  Background/Issue:   Currently  the AQD  is allowed, by  rule,  to  lower opacity and PM emission limitations below the levels established within other applicable air rules.  Proposed Solution:   The Air Quality Division  (AQD) shall develop a Policy Guidance Document addressing  the use of visible emissions  limits  less  than 20% opacity  in permit  conditions. The process  for  developing  the  document will  include  stakeholder  input  and will  require  opacity limits  that  are  more  stringent  than  what  is  allowed  by  R  336.1301(1)(a)  to  be  negotiated between  the applicant and  the AQD. The guidance document should be developed by  June 1, 2012.  Rationale for Change/Additional Comments:   These rules allow AQD to  lower opacity and PM emission limitations below the levels noted within each rule. This can lead to arbitrary decisions, and additional guidance will provide clarity to the regulated community. 

Environmental Advisory Rules Committee Recommendations 

A‐16

No. A‐10 Subject: R 336.1330 Remedy:  Process    Rules     Statute  Background/Issue:    R  336.1330  provides  performance  criteria  for  electrostatic  precipitators (ESPs).  The rule is part of the State Implementation Plan (SIP), and thus rescission would require USEPA approval.  Proposed Solution:   The Air Quality Division  should engage with USEPA  to determine what  it would take to get USEPA approval to rescind R 336.1330. Based upon that  feedback, the DEQ should engage with stakeholders to determine whether to repeal or modify the rule, or take no further action.  Rationale  for  Change/Additional  Comments:    This  performance  criterion  is  outdated  and current Rule 910 is suitable for this purpose.   

Environmental Advisory Rules Committee Recommendations 

A‐17

No. A‐11 Subject: R 1336.1901 – General Nuisance Rule Regulation: R 1336.1901 Remedy:  Process    Rules     Statute  Background/Issue:   This  regulation  is a very broad and general  rule  that  is  intended  to  target emissions that constitute a common law nuisance.  R 336.1901 (“Rule 901”) prohibits emissions that, in fact, cause injurious effects or unreasonable interference; it does not prohibit emissions that merely  “may”  cause  injurious  effects or unreasonable  interference.   Although  there  is  a long‐standing remedy in court for such nuisances, AQD has historically claimed that Rule 901 is essential for dealing with citizen complaints of odors and air pollution nuisances.  However, AQD has  not  limited  the  application  of  Rule  901  to  responding  to  citizen  complaints  and  actual nuisance conditions.   Historically, AQD has used Rule 901 for the establishment of stack height and emission rate conditions for air toxics in permits to install and this practice continues at the present time.  A review of recent proposed AQD permits shows that Rule 901 is being used as a citation  for  applicable  requirements  on  sources  that  have  never  been  found  to  have  caused nuisance conditions.    Installation  permits  should  be  based  on  clear  and  objective  standards  that  are  applied  in  a uniform manner.    Therefore,  Rule  901  should  be  rescinded  or,  if  it  is  retained,  it  should  be limited  in  scope  to  responding  to  known  nuisance  conditions  and  not  for  prospectively regulating activities and emissions based on AQD’s  suspicion  that  they may  result  in nuisance conditions.  Proposed Solution:  With stakeholder involvement, rulemaking should be undertaken to clarify how R 336.1901 is to be used in the Permit to Install process.  R 336.1901 should be limited to responding to and resolving known odor  issues and other nuisances.   As part of this review, all templates and standard language will be reviewed to assure the appropriate use of R 336.1901.  Rationale  for Change/Additional Comments:    If nuisance conditions  such as odors or  fugitive emissions occur that require remedial measures, the remedial measures can be addressed  in a Consent Order.  In such cases, there is an objective basis for establishing the requirements in a Consent Order because a nuisance has, in fact, been verified.  James Clift Comments:   The environmental community supports the consideration of Rule 901 in permitting for those industries that have a track record of odor problems with neighbors.    

Environmental Advisory Rules Committee Recommendations 

A‐18

No. A‐12 Subject:  Electronic Application for New Source Review Remedy:  Process    Rules     Statute  Background/Issue:  The AQD Permit to Install (NSR) process could be substantially improved for more  consistent  (process‐specific)  data  requirements,  resulting  in  a more  consistent  permit development and  submittal process, and a more consistent  regulatory  review process, by  the use of an electronic permitting system.  “Administrative Completeness” based upon completion of the general and process‐specific informational needs, as identified on electronic forms, would be more  or  less  a  formality  –  as  with Michigan’s  current  Renewal  Operating  Permit  (ROP) program within the AQD.  Administrative Completeness would begin the agency clock for permit issuance.   Like the ROP program, the AQD could provide all permit applicants with a notice of administrative completeness within 10 working days of receipt of the application, or  identify a complete list of the remaining technical information required to complete AQD’s permit review within 10 working days of achieving the administrative completeness designation.  The current regulatory process for reviewing air permit applications and issuing final permits can be  further  improved  by  requiring  consistent  information  from  each  individual  AQD  permit engineer.   Limiting the amount of  individual permit engineer variability during the AQD permit review process would  create  a  far more  efficient,  consistent  and  fair  system.  Several nearby states  that  directly  compete  for  manufacturing  jobs  with  Michigan  have  electronic  permit application development and submittal systems in place, and have so for many years.   A checklist could be made part of the electronic permitting system.   For example, all technical information  templates  could  be  developed  for  natural  gas  peaking  power  plant  applications.  Upon electronic submittal of all basic site, process and emissions‐related  information  to AQD, the electronic application program should be capable of submitting an electronic confirmation of administrative completeness could be electronically sent to the permit applicant.  We  believe  a  user‐friendly  electronic  permit  application  development  and  submittal  system would  require  no more  than  12 months  to  develop  (using  some  of  the  templates  already developed by the DEQ’s Office of Environmental Assistance) upon selection of an outside  firm (or combination of firms).   This can be accomplished by the private sector  in far  less time than what was  required  for  the  failed MiTAPS attempt  in 2004, with  the cooperation of DEQ.   For example, a private  sector  team of Michigan  consulting  firms  collectively developed  the  initial electronic ROP (PASS) software when the DEQ had determined that such a system would require too  much  agency  staff  effort  and  financial  resources.    Development  of  the  PASS  software required  less  than  a  year  of  donated  private  sector  effort.    An  efficient  PTI  electronic development and submittal system can be accomplished within 12 months.  This should become a very high priority on DEQ’s list of goals for FY 2012.  Proposed Solution:   Develop and  implement an electronic Permit to  Install application system by December 31, 2012. Development of  this  system  should be done primarily by  the private sector  with  quality  assurance  and  regulatory  guidance  from  the  DEQ.  The  funding  for  this project should be found outside of the current DEQ budget. 

 Rationale for Change/Additional Comments:  The benefit of the electronic permit development 

Environmental Advisory Rules Committee Recommendations 

A‐19

and submittal process would be to (1)  identify the general and process‐specific data necessary for  review  of  the  application,  (2)  limit  the  amount  of  AQD  permit  engineer  individualism experienced within the current system, and (3) provide a more responsive system to Michigan businesses.     Several  nearby  states  that  directly  compete  for  manufacturing  jobs  with  Michigan  have electronic permit application development and submittal systems in place, and have so for many years. 

Environmental Advisory Rules Committee Recommendations 

A‐20

No. A‐13 Subject:  Stakeholder Involvement in SIP Development Remedy:  Process    Rules     Statute  Background/Issue:    Historically,  the  SIP  development  process  has  used  limited  stakeholder involvement, well  before  the  final  documents  are  released  for  public  review,  comment  and USEPA consideration.   The  limited use of stakeholder  input and review  in the SIP development process can result in DEQ commitments within a proposed SIP that may increase the regulatory burden to Michigan businesses, and yet are not essential for USEPA approval.   Proposed Solution:  The Air Quality Division of the DEQ should conduct stakeholder reviews to solicit more non‐agency input in drafting State Implementation Plans (SIPs).  Rationale  for  Change/Additional  Comments:    Stakeholder  involvement  and  effective communication of  important policy decisions  is critical to the success of the AQD. Even though stakeholder involvement may take time and additional effort for development and submittal of SIPs,  it will  lead  to  a more  transparent  process  and  limit Michigan’s  regulatory  burdens  on businesses. 

Environmental Advisory Rules Committee Recommendations 

A‐21

No. A‐14 Subject:  Addition of New Permit to Install Exemptions and Clarification of Existing Exemptions Regulation: R 336.1278 – R 336.1290 Remedy:    Process    Rules    Statute  Background/Issue:  The existing Permit to Install (PTI) exemptions contained  in R 336.1278 – R 336.1290 are somewhat confusing and have occasionally led to hindsight enforcement activities.  The  AQD  has  also  held  firm  to  the  position  that  it  will  not  make  written  determinations concerning possible PTI exemptions on a case‐by‐case basis.   Proposed Solution:   Amend  the R 336.1201 permitting  requirements  to add new exemptions, and further clarify the current exemptions included in R 336.1278 – R 336.1290.  Rationale for Change/Additional Comments:  Revised rules will provide clarity to the regulated community.  

Environmental Advisory Rules Committee Recommendations 

A‐22

No. A‐15  Subject:  VOC Emissions from Pharmaceuticals (R 336.1625) Regulation: R 336.1625  Remedy:  Process    Rules     Statute  Background/Issue:    The  rule  imposes  additional  requirements  for  control  devices  in  volatile organic compound  (VOC) service.    If a process unit  is a major source and already subject  to a MACT standard, the additional state recordkeeping is redundant and unnecessary.   Proposed  Solution:    Amend  R  336.1625  to  provide  that  if  a MACT  standard  applies  to  the sources identified in R 336.1625 and also establishes VOC limitations, then the requirements in R 336.1625 are not applicable.   Rationale  for  Change/Additional  Comments:    Rules  impose  unnecessary  recordkeeping requirements for air pollution control equipment if subject to MACT. 

Environmental Advisory Rules Committee Recommendations 

A‐23

No. A‐16 Subject:  Volatile Organic Compounds (VOCs) – R 336.1611 and R 336.1707(3)‐(4) Regulation: R 336.1611 and R 336.1707(3)‐(4) Remedy:  Process    Rules     Statute   Background/Issue:  R 336.1611 and R 336.1707(3)‐(4) apply to very small emission sources (such as parts cleaners and cold washers) at numerous manufacturing facilities in Michigan.   Proposed  Solution:    The  DEQ  should  work  with  stakeholders  to  simplify  the  process  for demonstrating compliance with these rules for Renewable Operating Permit (ROP) facilities.  Rationale  for Change/Additional Comments:   These  rules pertain  to VERY  small  air emission sources and contain nearly three pages of regulatory requirements within every ROP. For some companies, these rules literally double the number of "applicable" requirements within an ROP.  

Environmental Advisory Rules Committee Recommendations 

A‐24

No. A‐17 Subject: Rule 703, Gasoline Storage Tanks (>2000 gal) Regulation: R 336.1703 Remedy:  Process    Rules     Statute  Background/Issue:    R  336.1703  pertains  to  vapor  balance  controls  to  prevent  the  escape  of gasoline vapors during the filling of gasoline storage tanks. The complexity of the rule makes  it difficult to understand the compliance requirements. It is difficult to interpret which gas stations are  subject  since  the  USEPA  recently  promulgated  a  standard  with  different  applicability requirements.  Proposed Solution:  Amend R 336.1703 to be clear and consistent with new USEPA regulations, while ensuring continued attainment of air quality standards.  Rationale for Change/Additional Comments:  Current regulations are very difficult to read and determine applicability, although  the DEQ’s Office of Environmental Assistance has generated some guidance documents.   Clarifications within the rule would be beneficial to the regulated community. 

Environmental Advisory Rules Committee Recommendations 

A‐25

No. A‐18 Subject: Rule 336.1349 Regulation: R 336.1349 Remedy:  Process    Rules     Statute  Background/Issue:  Rule 349 specifies compliance with Rules 350 – 357 on or before December 1982 (nearly 30 years ago).   Proposed Solution:  Rule 349 is obsolete and should be rescinded. 

Environmental Advisory Rules Committee Recommendations 

A‐26

No. A‐19 Subject:  Limiting Compounds Required for Annual MAERS Report   Regulation: R 336.202(2) Remedy:    Process    Rules    Statute  Background/Issue:  R 336.202(2) states, “The Department shall require an annual report from a commercial,  industrial,  or  governmental  source  of  emission  of  an  air  contaminant  if,  in  the judgment  of  the  department,  information  on  the  quantity  and  composition  of  an  air contaminant  emitted  from  the  source  is  considered  by  the  department  as  necessary  for  the proper  management  of  the  air  resources…The  information  shall  include  factors  deemed necessary by  the department  to  reasonably estimate quantities of air contaminant discharges and their significance…”  Currently,  the department  requires MAERS subject companies  to use either stack  test data or state‐supplied default emission factors.   The majority of  these  state‐supplied emission  factors were derived  from USEPA databases of very questionable quality, and  typically  include a very  lengthy  list of potential  trace air  toxics.  The only other alternative  is to have a company  invest a very substantial amount of money to develop process‐specific emission  factors based on  stack  testing  for  these  “theoretical”  trace compounds that have no adverse environmental impacts at their maximum predicted emission rates.   This would be a very costly alternative  for Michigan businesses with no environmental benefit.  Proposed Solution:  Continue to use the existing default MAERS air toxics emission factors as an optional calculation tool for  industry, but clearly  identify which air toxics have been calculated using USEPA‐supplied  emission  factors  in  the  annual MAERS  reports.    Furthermore,  the DEQ should be prohibited from developing new air toxics rules using D and E‐rated emission factors.  Rationale/Comments:    In  the  past  10+  years,  the DEQ  has  significantly  expanded  the  list  of reportable compounds, with very  little supporting  justification other than a blanket statement concerning  the  potential  use  of  this  information  for  the  development  future  air  toxics  rules.  Using low‐quality emission factors with an USEPA rating below a C rating results in a false read of Michigan’s statewide and source‐specific annual emission  levels and should not be used for regulatory planning purposes or any other intended agency use.    James  Clift  Comments:    The  environmental  community  believes  that  a  company  or  person should report all chemicals that it is, or may be, emitting into our environment.  We believe the burden  falls on  them  to  characterize  the nature of  their emissions  and not on  the  state  and federal  government.    Therefore,  the  quality  of  emission  factors  should  not  be  a  basis  of  an exclusion from reporting.  

Environmental Advisory Rules Committee Recommendations 

A‐27

No.  A‐20 Subject:  Putting a Hold on the 18‐Month Construction Window for a PTI Regulation: R 336.1201 Remedy:  Process    Rules     Statute Lead(s):   Background/Issue:    R  336.1201(4)  requires  construction  under  a  PTI  to  commence within 18 months of issuance or the permit becomes void.  The Air Quality Division (AQD) recently issued an 18‐month extension on a Prevention of Significant Deterioration  (PSD) permit  for a  source that is tied up in litigation.  We have been sued over this decision.    Proposed Solution:  Amend R 336.1201(4) to provide for a “hold” on the 18‐month timeframe if a  permit  decision  has  been  appealed.    The  following  bold  language  should  be  added  to R1201(4):  

“If the  installation, reconstruction, or relocation of the equipment,   for which a permit has been issued, has not commenced within, or has been interrupted for, 18 months,  then  the  permit  to  install  shall  become  void,  unless  (a)  otherwise authorized by the department as a condition of the permit to  install, or (b) the installation permit is the subject of an appeal by a party other than the owner or operator of the air contaminant source that is the subject of the installation permit,  in which case  the date of  termination of  the permit  is not  later  than eighteen months after the effective date of the permit plus the number of days between the date in which the permit was appealed and the date on which all appeals concerning the permit have been resolved. 

Rationale  for Change/Additional Comments:   Ohio has a provision  in  their Revised Code  that provides for a  'hold' on the 18‐month timeframe  if a permit decision has been appealed.   This recommendation would prevent already granted permits from becoming void.  James  Clift  Comments:    The  environmental  community  believes  that  the  purpose  of  the deadline  is  to protect public health and ensure  the best available  control  technology  is being utilized.   We are concerned that an applicant could appeal the  issuance of  its own permit and extend the time period between issuance and construction.  This new proposed rule should not apply  to  an  electrical  generating  unit  subject  to  the  certificate  of  need  process  under MCLA 460.6s, but has failed to receive such certificate before applying for a permit to install.   

Environmental Advisory Rules Committee Recommendations 

A‐28

Remediation Recommendations  

No.  R‐1 Subject:  Groundwater/Surface‐Water Interface (GSI) Regulation:  Part 31, Part 201, and R 299.5716 Remedy:  Process    Rules     Statute  Background/Issue:    In  a  report  issued  by  Public  Sector  Consultants,  Inc.  on  April  2,  2007 following a review of the Part 201 program, it was stated: 

 “The GSI pathway has been  identified by  the DEQ and  the  regulated  community as a 

pathway  that  can  significantly  slow  the  review  and  approval  process  of  a  RAP  or  an  interim response designed  to meet  criteria because under  the  current  Part 201 procedures,  facilities must go through a highly detailed process to demonstrate whether the GSI is or is not a relevant pathway.” See PSC Report at page 20.   

 Unfortunately, little has changed in the more than four years since the report was issued.  

In 2010, the legislature amended Part 201 to address some of the issues associated with regulating the GSI.  Although those amendments contained some important improvements, the DEQ staff has since refused to make any changes in the manner in which they regulate the GSI.  The current method of regulating the GSI  is not working.   Rather,  it  is unnecessarily driving up the cost of compliance. This is contrary to the intent behind the 2010 amendments, which were focused  on  streamlining  processes,  creating  compliance  flexibility,  reducing  unnecessary response costs, and increasing site closures.  As explained in the 2007 PSC report, the GSI issue is driving many cleanups across  the state—making  this  issue vitally  important  to getting more sites closed. 

 Fortunately,  the statutes and  rules can be  improved so  that more sites will be closed.  

Further, where  complexity  exists, DEQ  staff  actions  should  reflect  a  problem‐solving  culture, seeking  the best  available  solution  to move  the project  forward,  thereby  avoiding  regulatory paralysis.    Specifically,  amendments  to  the  relevant  statutes  and  rules  should  address  the following:  

1.  GSI Compliance Evaluation Based on Surface Water and Not Groundwater.   Revise  Rule  716  (and  if  necessary,  Parts  31  and  201)  to  clearly  allow  the  need  for 

plume control or cleanup relative to GSI to be based on the  impact of the plume on the  surface water  and  to provide  for  a  clear opportunity  for  the PRP  to determine response activity.  A “convenience” approach of only using on‐land well data would be retained but only as an option for the PRP.   This keys on the compliance point(s) for the  GSI.    Acceptable  monitoring  methods  would  be  specified  and  additional monitoring methods could be proposed by the PRP and approved by DEQ. 

2.  Prohibit  Excessive  Data  Demands.    Effectively  prohibit  the  DEQ  from  requiring unreasonable amounts of data to support a compliance point(s) at the true GSI, in the surface water, and elsewhere. 

3.  Focus on Designated Uses and Surface Water Quality Standards.   No cleanup action would be required for a venting plume if the designated uses of the surface water are 

Environmental Advisory Rules Committee Recommendations 

A‐29

not  impaired and  surface water criteria are not exceeded as a  result of  the venting plume.    Mixing  zones  would  be  available  for  the  venting  plume.    Sentinel  well monitoring may be required if necessary in some circumstances to provide a warning as to changes in groundwater conditions that would imply adverse impacts on surface water quality standards are likely to occur. 

4.  Site‐Specific Criteria.   Expand the bases for site‐specific GSI criteria to reflect (1) and (3)  above,  allow  non‐numerical  criteria  and  criteria  based  on  in  situ  bioassays  and biological community assessments. 

5.  Plume  Characteristics.    Use  plume‐average  concentrations  and  not  point‐by‐point plume  data,  except  to  the  extent  there  is  a  demonstrated  acutely  toxic  effect occurring  at  the  GSI.   Whole  effluent  toxicity  testing  would  not  be  a  compliance criterion in on‐land wells. 

6.  Natural  Attenuation  Acceptance.    Include  an  express  recognition  that  natural attenuation of the venting plume is acceptable in lieu of active treatment. 

7.  Sustainability  Parameters.    Inclusion  of  sustainability  parameters  in  the  response action choice  factors – energy consumption,  impacts on other environmental media and land use impacts. 

8.  No  Permit  Needed.    Under  Part  31,  no  permit  would  be  needed  for  venting groundwater and a venting plume would not be a new or  increased  loading for Rule 98. 

9.  Clarity on surface waters subject to GSI.  Surface water for purposes of GSI regulation should not include all wetlands that are currently regulated under Parts 301 and 303.  Specifically,  the GSI  should not apply  to wetlands of a magnitude  that do not merit protection  to  surface‐water  standards.    For  example,  the  GSI  should  not  apply  to wetlands where standing water is not present for more than 6 months in a typical year and which does not  support biological  resources  typical of  surface waters.   Further, the GSI  regulations  should be evaluated  to determine  that appropriateness of  their applicability to storm‐water retention ponds. 

10.  Storm  Sewers  and  GSI.    Means  to  resolve  the  storm‐sewer/GSI  issue  should  be considered.    Unfortunately,  the  DEQ  staff  uses  a  hyper‐conservative  approach regarding  the compliance point  for a groundwater plume  that  is  infiltrating a  storm sewer.    Indeed,  storm‐sewer  flow  is  intermittent—making  it  difficult  in  some circumstances to monitor the water discharging into a surface water from the storm‐sewer outfall.  But such monitoring is possible.  In addition, in some large and intricate storm sewers, it is possible to determine that the infiltration of a groundwater plume is  insignificant  in  terms of  the mass and  rate and  the plume’s eventual  impact on a surface water.      Further, where  end‐of‐pipe monitoring  does  not  produce  relevant surface‐water  quality  criteria  exceedances  or  it  is  shown  that  an  infiltration  is otherwise  insignificant  to  a  sewer’s  impact on  a  surface water, no  response  action should be required.  The owners of impacted and potentially‐impacted storm systems, rather than the DEQ, should decide if plume control, cleanup, or other measures such as monitoring, maintenance,  and  system  improvements  are  necessary  for  plumes which infiltrate their storm sewers. 

 Proposed  Solution:    Seek  amendments  to  Part  31,  Part  201,  and R  299.5716  to  address  the following goals regarding the GSI pathway:  

Environmental Advisory Rules Committee Recommendations 

A‐30

1.  GSI compliance evaluation should be based on surface water and not groundwater. 2.  Prohibit excessive data demands. 3.  Focus on designated uses  and  surface‐water‐quality  standards  in  the  surface water 

and not in groundwater or pore water. 4.  Expand the bases for site‐specific criteria, including non‐numeric criteria. 5.  Evaluate  appropriate  plume  characteristics,  such  as  using  plume‐average 

concentrations except where there is, or will likely be, an acutely toxic effect occurring in surface water. 

6.  Expressly  recognize  that  natural  attenuation  may  be  acceptable  in  lieu  of  active treatment.  Generally describe what is needed to show natural attenuation. 

7.  Use sustainability parameters in the response‐activity choice factors. 8.  Expressly state that no permit is needed under Part 31 for a GSI response activity. 9.  Surface water subject to GSI regulation should not include all wetlands or storm‐water 

retention ponds. 10.  Develop new rule provisions or statutory changes for groundwater plumes infiltrating 

storm sewers based on the quality of the water exiting the storm sewer outfall and its impact on surface waters. 

 Rationale for Change/Additional Comments:    

Cost  of  compliance  unnecessarily  high  for  projects  involving  Ground  water  Surface water interface (GSI). 

Cleanup criteria conflict with values used in other disciplines/programs.  Environmental  monitoring  techniques  exist  to  protect  surface  water  without 

unnecessary response activity and unreasonable data demands.    A problem solving DEQ staff is desirable.  Approaches to GSI compliance by other states and the USEPA should be analyzed.  The goal  is  to protect surface waters without unnecessary GSI  investigation and other 

response activities.  James Clift Comments:   The environmental community  supports efforts  to  transfer  focus and resources  to  cleanup  activities  versus  ongoing monitoring  requirements.    However,  we  are concerned  that  greater  use  of  site‐specific  criteria  and  non‐numerical  criteria  are  also  staff intensive  activities  for  a department  that  is  significantly underfunded.    Lastly, we oppose  an across the board exclusion of the consideration of the impacts that a discharge could have on a wetland ecosystem.

Environmental Advisory Rules Committee Recommendations 

A‐31

No.  R‐2 Subject:  Part 201/213 Vapor Intrusion Criteria  Regulation: Part 201; Part 213 Remedy:  Process    Rules     Statute  Background/Issue:    The  Remediation Division  (RD)  of  the DEQ  has  indicated  that  it  plans  to change its approach to regulation of the vapor intrusion (VI) pathways (as to both soil criteria in R  299.5724  and  groundwater  criteria  in  R  299.5714).  The  regulated  community  concurs  that change is required. It is important that the new approach to these pathways be developed very carefully  because  of  the  critical  importance  of  the  VI  pathway  both  from  a  public  health perspective and because of the  increasing understanding of how the relevance and risk of this pathway can vary commensurate with the widely varying conditions of properties.  

 The  continued  inability  of  both  liable  and  non‐liable  parties  to  identify  a  reliable  path  to completing the  investigation of a site and  implementation of appropriate remedial and/or due care measures  strongly  discourages  parties  from  engaging  in  the  Part  201/213  program  and often delays and increases the cost to redevelop and reuse property.  

 The  RD  is  proposing  the  development  of  soil  gas  criteria  (SGC)  to  replace  the  current  soil volatilization to indoor air inhalation criteria (SVIIC).  The regulated community concurs that soil gas  is  a more  representative medium  to  evaluate  than  soil  data,  as  vapor  is  the  (inhalation) exposure medium. 

 The  SGC  are  derived  by  dividing  an  acceptable  indoor  air  concentration  (AIAC)  by  a  vapor attenuation coefficient.  The vapor attenuation coefficient is a reduction factor, representing the decrease in vapor concentrations from the subsurface to the indoor air of a building.  That is, the vapor attenuation coefficient  is the  indoor air concentration divided by the subsurface soil gas concentration –  the  fraction of  soil gas present  in  indoor air.   The RD  is expected  to propose “default” vapor attenuation coefficients based on  the U.S. Environmental Protection Agency’s (USEPA) VI database to develop Part 201/213 SGC. 

 There  are many  issues with  applying  the USEPA  default  vapor  attenuation  coefficients.    The indoor  air  and  subsurface  groundwater  and  soil  gas data  in  the USEPA database  are  limited, hence not  sufficiently  representative of VI conditions  (particularly  in Michigan), and  therefore are not appropriate data  to  support development of Part 201/213 generic VI criteria.   USEPA uses the default attenuation coefficients from their VI database to derive screening levels – the screening levels trigger whether further evaluation of VI pathway risk is necessary.  Reasons why the USEPA VI database of attenuation coefficients are not adequately representative to support development of Part 201 generic VI criteria include: (1) a majority of the data are from a limited number of sites, most of which are  in  the western U.S. and eastern U.S., with very  little data from the Midwest, (2) approximately 85% of the data are from residential homes and therefore are  not  representative  of  non‐residential  land  uses,  (3)  97%  of  the  data  are  for  chlorinated hydrocarbons, and  therefore are not representative of VI  for petroleum hydrocarbons,  (4)  the subsurface and indoor air sample data represent the environmental and building conditions on only  one  day  of  the  year  and  (inappropriately)  used  to  represent  daily  long‐term  exposures when  in  reality  concentrations  can  change  significantly  on  a  daily  basis  due  to  varying meteorological and building operation conditions, (5) further, these “snapshot‐in‐time” data are 

Environmental Advisory Rules Committee Recommendations 

A‐32

extrapolated into the context of risk criteria equations that are based on long‐term daily human exposure  assumptions  (e.g.,  30  years),  and  (6)  the  indoor  air  measurements,  which  are necessary  for  deriving  the  attenuation  coefficients,  are  affected  by  background  indoor  air contaminants  such  that  indoor  air  concentration measurements  of  the  same  volatile  organic compounds (VOCs) as those of concern in the subsurface may falsely indicate vapor intrusion.   

 There  are  generally  three  areas  of  variability  associated  with  the  VI  pathway,  subsurface, building and meteorological conditions, and  the  interaction among  these variables can  create significantly varying VI conditions for houses immediately adjacent to one another.  As a result, the  list of  issues against developing generic criteria could go on; what has been  learned about the VI pathway over the past decade  is that every VI pathway evaluation must be customized, possibly within a flexible regulatory framework, to effectively manage the  inherent variabilities of subsurface, building and long‐term exposure conditions associated with the pathway at each site.  Proposed Solution:  The DEQ should carefully address the important vapor intrusion pathway in a manner which protects human health consistent with the best scientific evidence available. In doing  so,  the DEQ  should:  (i)  allow  the  initial  use  of  a  conceptual  site model  and  other  site evaluation  techniques  before  concluding  the  presence  of  a  complete  exposure  pathway  and vapor intrusion risk; (ii) allow data collection and evaluation processes consistent with the needs of  business  transactions,  which  may  include  greater  use  of  real‐time  sampling  techniques; (iii) prioritize the compilation and comparison to  initial screening  levels (not generic criteria) of Michigan‐based data  from  the many  sites which  are  known  to  exist  and  are  available  to  the DEQ; and  (iv) develop generic  vapor  intrusion  criteria  (with  variations based on  soil  type and other  site  specific  features) with meaningful  input  from  resources  outside  of  the  DEQ with particular expertise in this important area.   Rationale  for  Change/Additional  Comments:    Too  often  confounding  data  are  gathered  for situations that do not warrant an evaluation of the VI pathway.  A process should be applied to pre‐empt sample data collection and comparison to criteria.   As described above, the  inherent variabilities of the pathway creates uncertainties in the decision‐making.  As a result, an efficient process to effectively screen out these situations  is necessary to determine  if VI assessment  is needed.    Data  collection  and  evaluation  processes  need  to  match  the  time  frames  of  property transactions; there is not the luxury to sample each season or quarter to gather data to make a decision, as  is typically required by the RD.    If the VI pathway  is of potential concern, develop information gathering options specific to the current/future use context to validate the concern, rather than unnecessarily gathering additional data from samples.    Viable options are to allow the  conduct  of  real‐time  testing with mobile  lab,  use  of  passive  diffusive  samplers,  conduct pumping  tests  on  the  sub‐slab  plenum  air,  etc.  to  address  the  snapshot‐in‐time  concern.  Available  background/historical  information  for  the  site  or  in  the  immediate  area  should  be applied  to  ground  truth  the  concern.    [Development  of  a  conceptual  site model must  be  an integral part of this process, and  if data collection  is necessary, use of the USEPA Data Quality Objectives (DQO) process must also be considered.]  Sample  data  gathering  options  should  only  ensue  after  a  thorough  exercise  of  the  above 

Environmental Advisory Rules Committee Recommendations 

A‐33

conceptually  described  qualitative  screening  process  is  completed,  and which  supports  that additional data are necessary to complete a quantitative evaluation of the risk.   (The option to design,  install,  and  operate  a mitigation  system  remains)  The  quantitative  evaluation  results would  then  be  compared  to  “initial  screening  levels”.    The  initial  VI  screening  levels  should represent  available Michigan  VI  site  data  in  addition  to  some  of  the  USEPA  VI  data  that  is properly  screened.        Additionally,  the  process  should  include  conducting  a  simple  radon attenuation evaluation at sites where concentrations exceed “initial screening  levels”  to assist with actual building‐specific attenuation (if a building is present), and/or collection of indoor air samples if contribution of background indoor air sources can be reliably prevented.  The RD should prioritize the compilation of data from the many sites which are known to exist (both  private  party  sites  and  sites  investigated  by  the  RD)  to  determine  the  efficacy  of  its hypotheses related to the VI issue. The continued development of such an important regulatory approach  for  the VI  issue without a serious effort  to compile and analyze data  from Michigan properties will undermine confidence in the RD’s efforts to regulate this issue.  Other key considerations should include:  Regulatory  approaches  for  determining when  the  VI  pathway  is  relevant  and  complete  and when mitigation is necessary, whether developed by the USEPA or DEQ, must acknowledge and incorporate the following realities:  

The science around the issue is continually evolving.  Knowledge  and understanding of  the VI pathway  is  advancing over  short  timeframes 

relative to typical rulemaking processes.  Responsible parties need  certainty  that  assessment  and mitigation of  the VI pathway 

have  end  points  and  a  clear  and  understandable  process  for  determining  those  end points. 

 The  process  for  development  of  a  new  VI  regulatory  program  in Michigan must  include  the following  elements  to  be  viable,  reasonable,  and  facilitate  cooperative  participation  by  the regulated community: 

  The  resulting  regulatory program must be  less proscriptive and prescriptive and more 

flexible,  allowing  for  incorporation  of  new  science  and  technology without  requiring additional rulemaking (Benchmark ‐ USEPA). 

The  regulatory  development  process must  include  a  thorough  consideration without bias of the approaches used by other states and the USEPA. 

The  RD must  significantly  increase  the  transparency  and  openness  of  the  regulatory development  process.    Use  of  new  interactive  tools,  such  as  open  blogs  (e.g.,  see http://indoorairproject.wordpress.com  for  the Massachusetts  approach),  is needed  to generate  real‐time  interactions  with  and  comments  from  stakeholders  as  ideas  and approaches are developed.  The RD also needs to be more forthcoming in explaining the thought  processes  and  technical  bases  at  each  step  of  the  regulatory  development process so stakeholders have an opportunity to provide comment and input during the process,  not  just  at  the  end.    The  current  process  of  developing  rules  internally  and accepting  comments  only  after  rules  packages  are  developed  is  not  a  transparent 

Environmental Advisory Rules Committee Recommendations 

A‐34

process.(Benchmark ‐ other states, such as Massachusetts)  The  involvement  and  contribution  of  stakeholders  to  the  rules  development  process 

must be  improved to  include more  input from a  larger universe of stakeholders.   Input must be interactive and consistent throughout the process (see transparency discussion above).   There must be  room  for all  stakeholders  that want  to participate, not  just a handful selected by the RD. 

It must be based on the best science currently available.  The  absence  of  scientific  data  and  certainty  cannot  result  in  overly  conservative 

approaches to avoid using reasonable risk assumptions and best judgment.  

Interim Steps:  It  is expected that take at  least one year for the RD to complete the process of replacing its current approach to the VI pathway. In the meantime, attention should be paid to facilitating the prompt resolution of sites where application of existing default VI criteria  is not currently  permitted  by  the  RD  due  to  failure  of  conditions  to  the  application  of  the  default criteria (such as the presence of shallow groundwater or sumps).  

Environmental Advisory Rules Committee Recommendations 

A‐35

No.  R‐3 Subject:  Revising Part 201 Cleanup Criteria Remedy:  Process    Rules     Statute  Background/Issue:   In 2010, the  legislature amended Part 201.   Those amendments  included a requirement that the DEQ evaluate and revise the cleanup criteria not later than December 14, 2012.  MCL 324.20120a(18) states:  

(18) Not  later than 2 years after the effective date of the 2010 amendatory act that amended this section, the department shall evaluate and revise the cleanup criteria derived under  this  section. The evaluation  shall  incorporate knowledge gained through research and studies in the areas of fate and transport and risk assessment. Following  this  revision,  the department  shall periodically evaluate whether new  information  is available  regarding  the  cleanup  criteria and  shall make revisions as appropriate. The department shall prepare and submit to the legislature a  report detailing any  revisions made  to cleanup criteria under  this section. 

 The DEQ should fulfill this requirement by undertaking a stakeholder process to determine the relevant  knowledge  and  data  that  should  inform  any  revisions  to  the  cleanup  criteria.    The stakeholder process and the criteria revisions should take into account best practices from other states  and  appropriate  risk  assessment.    Further,  the  stakeholder  process  should  revisit  the generic  algorithms  and  exposure  assumptions  and  determine whether  those  algorithms  and exposure  assumptions  reflect  reasonable  and  realistic  conditions,  good  science,  and  normal rational human habits.  Appropriate revisions should be made.  Proposed  Solution:    The  DEQ  should  evaluate  the  algorithms,  exposure  assumptions,  and toxicity  values  used  to  establish  generic  cleanup  criteria  and  screening  levels  under  Section 20120a  of  the  Part  201  statute  and  the  Part  7  rules  and  revise  those  algorithms,  exposure assumptions,  and  toxicity  values  as  necessary  based  on  best  practices  from  other  states, reasonable and realistic conditions, and good science.   Consistent with any such revisions, the DEQ should then revise the generic cleanup criteria and screening levels established in the Part 7 rules.  

Environmental Advisory Rules Committee Recommendations 

A‐36

No.  R‐4 Subject:  Part 201 Rules Remedy:  Process    Rules     Statute  Background/Issue:  At the end of 2010, the legislature substantially amended Part 201, but this effort actually began  in early 2009.   At  that  time,  the  regulated  community united  to pursue amendments  that were  sorely  needed.    To  fully  understand  the  intent  behind  the  effort  to amend Part 201, some background is appropriate.  

 In 1995, the Michigan legislature enacted Part 201 which, among other changes, fundamentally shifted Michigan’s  liability  standard  from  strict  liability  to  causation‐based.    This  change  and others contained in Part 201 have been successful.  But over the years, the DEQ and businesses have  identified problems with the Part 201 program.   So  in 2006, the DEQ asked Public Sector Consultants  (PSC)  to  facilitate  a  stakeholder‐driven  process  to  discuss  and  identify  potential improvements  to  the programs.   A group of experienced  individuals met periodically between 2006 and early 2007  to  identify and discuss problems and  improvements  to  the Part 201 and brownfield programs.  PSC then issued a report in April, 2007 documenting that process.    Unfortunately,  by  2009  nothing  had  been  done  yet  to  address  improving  Part  201.   Many problems  identified  in the PSC report and other problems  identified since that report continue to substantially bar  increased  investment  in remediation and redevelopment  in Michigan.   The over‐arching theme representing the greatest barrier was conservative decision‐making by the DEQ.   This  tendency  imposed an environmental and economic cost  to  the State. Creative and practical evaluations were squelched.  The incentive for investment was significantly diminished. The  economic  and  environmental  consequences  of  ultra‐conservatism  were  clear:  the environment does not benefit from  investment and the State does not benefit from  increased economic activity and the commensurate tax revenue.  Furthermore,  over  the  previous  six months,  the  DEQ  had  “rolled  out”  a  set  of  conceptual changes  to  Part  201.    Unfortunately,  many  of  the  DEQ’s  conceptual  changes  would  have discouraged people  looking  to do business  in Michigan, directed  the State’s  limited  resources toward  looking  for  problems  where  none  were  known  to  exist,  and  increased  regulatory burdens  and  transaction  costs  without  providing  much  improvement  to  Michigan’s environment.  In addition, the DEQ’s conceptual changes did not address the major  issues that the regulated community had been voicing.   Consequently,  there was  little  support  for  the DEQ’s  conceptual  changes.    But  the  Part  201 program still needed be reformed for Michigan to move forward and maintain its “cutting edge” approach and appeal to those interested in investing in brownfields.  To that end, the regulated community  came  together  to  pursue  comprehensive  changes  to  the  Part  201  program  that addressed many of the issues identified in the PSC report and also other issues that had arisen since.    The  themes of  these  changes were  to  simplify  and  streamline  the  Part  201 program; create transparency; promote regulatory flexibility; and provide incentives for the DEQ to make less‐conservative decisions.  A  two‐year  process  of  broad‐based  work‐group  meetings  ensued  culminating  in  the amendments  that  were  passed  in  December,  2010.    These  amendments  require  certain 

Environmental Advisory Rules Committee Recommendations 

A‐37

conforming  amendments  to  the  Part  201  rules.    But  they  also  raise  the  larger  issue  of  the continued need  for many of  the Part 201  rules.    Similar  to  the  state of  the Part 201  statute before  the  2010  amendments,  the  Part  201  rules  over  time  have  become  cumbersome  and overly restrictive.  Indeed an overhaul of the Part 201 rules is in order.   Proposed Solution:  On or before April 1, 2013, the DEQ should rescind all rules (Parts 1, 4, 5, 7, 9,  and  10)  promulgated  under  Part  201  except  the  portion  of  the  Part  7  rules  related  to establishing  generic  cleanup  criteria and  screening  levels.   Concurrent with  this process, DEQ should promulgate a streamlined and efficient rule package that contains only rules that are:  

necessary for program implementation; and  performance‐based rather than prescriptive. 

 Rationale  for  Change/Additional  Comments:    The  Part  201  rules  have  over  time  become unnecessarily restrictive or simply unnecessary.  More response activities would take place and more brownfields will be redeveloped if the rules allowed more flexibility.  In addition, the Part 201 rules must be consistent with the authorizing statute.  James Clift Comments: The environmental community does not  support  the  rescission of any rules until a comprehensive package of revised rules has been prepared.   We think the statute and  the  rules  should  specifically  identify  the duties of owner  and operators of  contaminated property  and when possible  specific  timelines  for undertaking  cleanup  activities or measures designed to minimize exposure risks to the public. We think that an owner or operator who has knowledge that their property is contaminated should have the duty to disclose the existence of that site to neighbors and appropriate state and local officials.       

Environmental Advisory Rules Committee Recommendations 

A‐38

No.  R‐5 Subject:  Risk‐Based Closures and Site‐Specific Criteria Remedy:  Process    Rules     Statute  Background/Issue:    In  2010,  the  legislature  amended  Part  201  in  part  to  provide  further flexibility  in  developing  site‐specific  criteria  for  sites  and  to  otherwise  promote  risk‐based cleanups.    Indeed,  several  risk‐based  models  exist  that  could  be  utilized  by  the  Part  201 program.   For example,  the Risk‐Based Corrective Action  (RBCA) approach can be an effective process  to  develop  remedial  objectives.   Further,  the  site‐specific‐criteria  option  would  be further enhanced  if the criteria could be both numeric and nonnumeric depending on the site.  Unfortunately, the DEQ has historically not allowed for a risk‐based site‐specific closure option.   This  is  contrary  to  the  intent  behind  the  2010  Part  201  amendments.   Proposed Solution:  Consistent with the increased flexibility to create site‐specific criteria under the 2010 Part 201 amendments, the DEQ should encourage the  increased use and approval of risk‐based site‐specific closure limits in order to facilitate closure of more sites.  In addition, Part 201 and the Part 201 rules should be amended to allow for non‐numeric site‐specific criteria.  Rationale  for  Change/Additional  Comments:   Allowing more  use  of  site‐specific  criteria  and training staff regarding site‐specific criteria will  lead to more closures while still protecting the environment.  James Clift Comments:   The environmental  community  is  concerned with  the  labor‐intensive nature  of  these  cleanups  and  diverts  resources  away  from work  at  other  sites.    The  statute should be amended to allow for the DEQ to recover costs through fees in these instances.  

Environmental Advisory Rules Committee Recommendations 

A‐39

No. R‐6 Subject:  Effective Solubility and Free Phase Contamination Remedy:  Process    Rules     Statute  Background and Description of Issue:   Csat  is an estimate of the concentration at which soil  is saturated with  a particular hazardous  substance.   The DEQ has promulgated  generic  cleanup criteria to address Csat.  But Csat concentrations do not account for multiple contaminants (RD Op Memo 1, Technical Support Document – Attachment 8) such as may be present at petroleum contaminated  sites.    To  address  this  issue,  the DEQ  has  developed  informal,  unpromulgated “alternative criteria” for gasoline based on USEPA effective solubility formulas.  The alternative consists of analyzing soils  for gasoline  range organics  (GRO)  for screening and  if GRO exceeds 350 ppm, then a comparison to the alternative criteria based on soil type needs to be made to further evaluate  for  the presence of  free phase  contamination.    If  the alternative  criteria are exceeded,  the  DEQ  will  consider  free  phase  contamination  to  be  present  which  “must”  be addressed.    There  is  no  statutory  basis  under  Part  201  or  Part  213  for  such  an  “alternative criteria” to be established or enforced in this manner.  Neither  Part  213  nor  its  regulations  contain  any  requirement  applicable  to  “free  phase” contamination.    Part  213  does,  however,  regulate  “free  product” which means  “a  regulated substance in a liquid phase equal to or greater than 1/8 inch of measurable thickness, that is not dissolved in water, and that has been released into the environment.”  MCL 324.21302(f).    The  Part  201  regulations  confirm  that  “The  generic  cleanup  criteria  shown  in  R  299.5744,  R 299.5746, and R 299.5748 and identified under subrule (14) of this rule may be used and known as  risk‐based  screening  levels  for  corrective  actions  required under  the part 213 of  the  act.”  R299.5706a(4).   The generic cleanup criteria shown  in the referenced rules  include the generic Csat  concentrations.    Consequently,  the  risk‐based  screening  levels  that  apply  to  Part  213 cleanups would include the promulgated, generic Csat concentrations.  DEQ, however, believes that  the  generic  Csat  concentrations  may  not  be  sufficiently  protective  under  certain circumstances.  DEQ Draft Q&A document, dated May 12, 2011, addresses the issue with a regulatory analysis of the  relationship  between  free  phase  contamination  and  statutory  requirements.    These alternative criteria are significantly different from the generic Csat criteria and are being applied by the DEQ as if they were promulgated, binding criteria.  If the DEQ considers “free phase” to be present DEQ’s position  is  that generic criteria would not be  relevant.   DEQ has  repeatedly taken  the position  that Final Assessment Reports and other reports submitted under Part 213 are “inadequate” or “do not satisfy statutory requirements,” if they do not address “free phase” concerns,  even  in  the  absence  of  any  identified  free  product  (as  defined)  or  exceedances  of promulgated  criteria.    The Draft Q&A document  states  that  the Remediation Division will be willing to accept site specific evaluations, but no additional justification or guidance is provided.    DEQ’s Draft Q&A document also provides “screening levels” for diesel range organics (DRO) and oil range organics (ORO) and are discussed further in the Draft Q&A document.  Again, however, these screening levels are not authorized by either statute and have not been promulgated. RO) and oil range organics (ORO) and are discussed further in the Draft Q&A document.  

Environmental Advisory Rules Committee Recommendations 

A‐40

The  recent  amendments  to  Part  201  re‐confirmed  that  “A  guideline,  bulletin,  interpretive statement, or operational memorandum under this part shall not be given the force and effect of  law.”    Since DEQ’s Draft Q&A has not even been  “finalized” by  the Department,  let  alone actually promulgated as required by the Administrative Procedures Act, case law, and now Part 201, the use of this document by the DEQ and the assertion to the regulated community that it is a legal requirement is contrary to law.  Moreover, the presence of “free phase” contamination as described by DEQ does not necessarily  even pose  a health or  environmental  risk.    If DEQ believes that additional “free phase” criteria are necessary, then such criteria must be formally promulgated  in accordance with the Administrative Procedures Act, and receive the full public scrutiny, review and comment required by the APA.  In addition, if “free phase” contamination is going to be regulated under Part 213, then the statute would require amendment to revise the definition of “free product” or add a completely new definition of “free phase.” 

Further, the DEQ should allow flexibility when evaluating a “free phase” situation when there is no demonstrated  impact  to groundwater present.    In  that  situation,  it may be appropriate  to approve a no further action letter that includes a reopener for future discovery of free product. 

Proposed Solution:  1. The  DEQ  should  immediately  discontinue  applying  the  unpromulgated  alternative 

criteria for gasoline that are based on USEPA effective‐solubility formulas and that are attached  to  the DEQ Draft Q&A document dated May 12, 2011, and should use  the existing promulgated criteria.   

2. To  the  extent  the DEQ  believes  that  new  criteria  are  appropriate  for  “free  phase” contamination,  it must seek the appropriate changes to Part 213 or promulgate new criteria under Part 201 pursuant to the Administrative Procedures Act.   

3. In developing any new criteria to address free‐phase contamination, the DEQ should use science and look to national best practices.   

4. The DEQ  should  allow  regulatory  flexibility when evaluating  “free phase”  situations where there is no demonstrated impact to groundwater present.  

Environmental Advisory Rules Committee Recommendations 

A‐41

No.  R‐7a Subject:    Underground  Storage  Tank  Inspection  Delegation  and  Certification  (R  29.2071  –  R 29.2077)  Regulation:  R 29.2071 – R 29.2077 Remedy:  Process    Rules     Statute  Background/Issue:   These  rules established criteria  for  the delegation of authority  to enforce the act (and rules promulgated under the act) and to establish qualifications for certification of individuals as underground storage tank inspectors.  The department may delegate enforcement responsibilities.   Delegation  is  to be based on minimum  staffing  requirements,  regulated  tank population within the area of jurisdiction, and the level of support provided by the local unit of government.  Proposed Solution:   The  rule  set  relating  to Underground Storage Tank  Inspection Delegation and Certification (R 29.2071 – R 29.2077) should be rescinded.    Rationale for Change/Additional Comments:  These rules no longer provide value and have not been used since the 1990s. 

Environmental Advisory Rules Committee Recommendations 

A‐42

No.  R‐7b Subject:  Part 211 – Underground Storage Tank (UST) Regulations Regulation:  R 29.2101 – R 29.2174 Remedy:  Process    Rules     Statute  Background/Issue:  These rules prescribe requirements for installation, removal, and operation and maintenance of underground storage tank systems storing regulated substances.  Regulated substances are defined as petroleum (such as diesel and gasoline) and hazardous substances.  The  provisions  of  40  CFR  Part  280,  subparts  A‐H  (2006),  entitled  “Technical  Standards  and corrective Action Requirements for Owners and Operators of Underground Storage Tanks,” (as amended by 54 F.R. November 9, 1989, p. 47081‐47092, and as amended by 58 F.R. February 18, 1993, p. 9050‐9059), are adopted by reference  in these rules.   DEQ adopted the federal rules, but  incorporated  Michigan‐specific  amendments  leading  to  a  mixed  rule  set  that  is  about seventy‐nine pages long. The extent of the DEQ amendments is unclear.  USEPA 40 CFR Part 280 allows the use of national codes as an option for compliance (required in some cases) but does not alter the referenced code. Where compliance with the national code is required, multiple code options are typically included.  Proposed  Solution:    The  DEQ  should  review  the  current  rules  relating  to  Part  201  – Underground  Storage  Tank  Regulations  (R  29.2101  –  R  29.2174)  to  determine  the  use  and relevance of the current rules.   If  the  department  determines  the  rules  are  relevant  and  should  be  kept  in  place  then  they should review the rules with stakeholders to determine if particular rules should be updated or modified and if they exceed federal standards.   When  these determinations are made,  the DEQ  should work with  stakeholders  to modify  the rules  and  eliminate  those  rules  that  exceed  the  federal  standards,  unless  the  DEQ  can demonstrate  that  state‐specific  rules  are  necessary  to  protect  human  health  and  the environment.      Rationale for Change/Additional Comments:  Eliminating the Michigan‐specific amendments to the rules that exceed federal standards will result in less complex and more efficient regulations. 

Environmental Advisory Rules Committee Recommendations 

A‐43

No.  R‐7c Subject:  Transportation of Flammable and Combustible Liquids (R 29.2201 – R 29.2234) Regulation:  R 29.2201 – 29.2234 Remedy:  Process    Rules     Statute  Background/Issue:   Public Act 265 of 1995 amended  the Motor Carrier Safety Act of 1963 by adopting new federal regulations that govern the transport of hazardous materials and provide for general motor‐carrier safety.  This Act rescinded the associated rules but failed to rescind the rule set related to Transportation of Flammable and Combustible Liquids.  Based on the content of this rule set, the legislature’s failure to rescind the rules was an oversight.  Therefore, the rule set  pertaining  to  Transportation  of  Flammable  Combustible  Liquids  (R  29.2201  –  R  29.2234) should be rescinded.    Proposed  Solution:    The  rule  set  relating  to  Transportation  of  Flammable  and  Combustible Liquids  (R  29.2201  –  R  29.2234)  should  be  rescinded  because  it  is  redundant  with  existing transportation regulations.  Rationale for Change/Additional Comments:   These rules are related to transportation  issues. These  rules  make  Michigan  specific  amendments  to  the  NFPA  code  and  incorporate  by reference NFPA Code 385, 386, and Pamphlet 10.  DEQ’s analysis has determined these rules are redundant with existing regulations and should be rescinded.   

Environmental Advisory Rules Committee Recommendations 

A‐44

No.  R‐7d Subject:  Compressed Natural Gas (CNG) Vehicular Fuel Systems (R 29.4601 – R 29.4652) Regulation:  R 29.4601 – R 29.4652 Remedy:  Process    Rules     Statute  Background/Issue:  These rules apply to the design and installation of CNG engine fuel systems on  vehicles  and  associated  fuel‐dispensing  systems.  The  Fire  Protection  Code  authorizes  the promulgation  of  these  rules  but  requires  that:    “Rules  promulgated  under  this  act  shall  be consistent  with  recognized  good  practice  as  evidenced  by  standards  adopted  by  nationally recognized authorities  in  the  field of  fire protection. Experiences  identified  in  the  fire  incident reports received by this state may be considered by the board and the bureau when reviewing rules promulgated or considering promulgation of new rules under this act.”  (MCL 29.3c(4))  In 1998, the authority to promulgate these rules was transferred from the Department of State Police  (specifically  the  State  Fire  Marshal)  to  the  Department  of  Environmental  Quality  by executive order.   At  the  time,  the  thought was  that  transferring  the duties  to  the DEQ would lead  to “efficient administration and effectiveness of government  to  regulate  the storage and handling of  these hazardous materials within one department.”    (MCL 29.641). Unfortunately, the  transfer  has  not  led  to  efficient  administration  and  effectiveness  of  government  for  this program.    Rather,  the  program  has  become  even more  complex  and  cumbersome  for  the regulated community.  Proposed  Solution:    The  Compressed Natural Gas  (CNG)  Vehicular  Fuel  Systems  program  (R 29.4601 – R 29.4652)  is  related  to  fire  safety and  should be  transferred  from  the DEQ  to  the Bureau of Fire Services (within LARA) through an executive order.  Further, the Michigan‐specific amendments to the national codes should be rescinded and the current national codes should be adopted by reference.  Rationale for Change/Additional Comments:   These rules regulate vehicle engine fuel systems and  fuel  dispensing  systems  and  are  related  to  fire  safety  issues,  and  would  be  best administered by the Bureau of Fire Services.  These rules make Michigan specific amendments to numerous national codes and  incorporate by reference ANSI/ASME, ASTM, CGA, CSA, NFPA Code 37, 52, 54, 59A, 68, 70, 220, 259, 496. The  NFPA  52  version  cited  is  the  1992  edition,  which  has  since  been  superseded  by  five subsequent NFPA Code editions.     Eliminating  the Michigan‐specific amendments  to  the  rules that exceed federal standards will result in less complex and more efficient regulations.  

Environmental Advisory Rules Committee Recommendations 

A‐45

No.  R‐7e Subject:  Production, Storage, and Handling of Liquefied Natural Gas (R 29.4671 – R 29.4672) Regulation:  R 29.4671 – R 29.4672 Remedy:  Process    Rules     Statute  Background/Issue:    These  rules were  promulgated  in  response  to  the  pre‐siting  of  Liquefied Natural Gas (LNG) production facilities within the state by certain private entities.   For reasons unknown,  the  LNG  production  facilities  were  never  built,  nor  have  any  ever  been  built  in Michigan.   Therefore, there  is no continued need  for these rules as written.    If an LNG  facility was  to  locate and build within  this state, a newer version of  the standard  should be adopted that would be more in line with current technologies and practices.    Proposed  Solution:    The  rule  set  relating  to  Production,  Storage,  and  Handling  of  Liquefied Natural  Gas  (R  29.4671  –  R  29.4672)  should  be  rescinded  because  there  are  no  applicable facilities (existing or planned) in the state.    Rationale for Change/Additional Comments:  These rules were intended to regulate fire safety issues at Liquefied Natural Gas facilities.   DEQ has determined these rules should be rescinded since there are no plants in the state.   

Environmental Advisory Rules Committee Recommendations 

A‐46

No.  R‐7f Subject:  Storage and Handling of Flammable and Combustible Liquids (R 29.5101 – R 29.5516) Regulation:  R 29.5101 – R 29.5516 Remedy:  Process    Rules     Statute  Background/Issue:    These  rules  apply  to  the  storage  and  handling  of  flammable  and combustible liquids (FL/CL) in above ground storage tanks (AST) and underground storage tanks (UST) and are  intended  to protect against  fire and explosion hazards. Compliance with  these rules does not excuse compliance with other applicable state and federal statutes and rules and regulations promulgated thereto.  In 1998, the authority to promulgate these rules was transferred from the Department of State Police  (specifically  the  State  Fire  Marshal)  to  the  Department  of  Environmental  Quality  by executive order.   At  the  time,  the  thought was  that  transferring  the duties  to  the DEQ would lead  to “efficient administration and effectiveness of government  to  regulate  the storage and handling of  these hazardous materials within one department.”    (MCL 29.641). Unfortunately, the  transfer  has  not  led  to  efficient  administration  and  effectiveness  of  government  for  this program.    Rather,  the  program  has  become  even more  complex  and  cumbersome  for  the regulated community.  Michigan is the only state in the region that makes state‐specific amendments to national codes (e.g., National Fire Protection Association codes).  For example, the 2003 rule package added 80 pages of DEQ‐specific amendments to the actual NFPA Code and also incorporated by reference NFPA  Code  30,  30A,  31,  37,  70,  59A,  57,  10,  90A,  54,  211,  82,  9501,  8502,  55  and  NFPA Pamphlets 15 and 704. The national codes referenced by the 2003 DEQ rules have been updated by newer editions.   The DEQ  format  currently used  to amend  the national  code  is extremely detailed and evaluates/modifies the national code on a paragraph‐by‐paragraph basis.    Where appropriate, other states also tend to allow the owner to choose from multiple national codes in order to satisfy requirements of their rules.  Since these states adopt national codes by reference (without making state‐specific amendments), they can use a streamlined approach to incorporate a newer version of codes by simply proposing to change the date of the referenced code  in a proposed  rulemaking.   Of  course,  if  the newer  revised code only contains minor or insignificant changes then no changes would be necessary.    Proposed Solution:   

1. Transfer the Storage and Handling of Flammable and Combustible Liquids program (R 29.510  –  R  29.5516)  from  the  DEQ  to  the  Bureau  of  Fire  Services  (within  LARA) through an executive order.   

2. The  Bureau  of  Fire  Services  should  revise  these  rules  (R  29.5101  –  R  29.5516)  to rescind  the  current Michigan‐specific  amendments  to  the  national  codes  and  then adopt by reference the current national codes (without state‐specific amendments). 

3. Concurrent  with  the  Bureau  of  Fire  Services  rulemaking  in  Proposed  Solution  #2 above,  the  DEQ  should  determine  if  there  are  remaining  environmental  concerns specifically  related  to  the PIPP Part 5  rules  (R 324.2001 – R 324.2099) pertaining  to aboveground storage tanks.  If environmental concerns are identified, they should be evaluated  against  the  best  practices  in  neighboring  states  to  determine  whether 

Environmental Advisory Rules Committee Recommendations 

A‐47

additional regulations by the DEQ are truly necessary.    

Rationale  for  Change/Additional  Comments:    The  primary  focus  of  this  program  is  fire  and explosion protection, and therefore belongs in the Bureau of Fire Services.    Michigan is the only state in the Greats Lakes region that makes amendments to national code. Compliance requires reviewing the stand‐alone DEQ rule beside all of the  individual applicable NFPA Codes  reference above.   Other states  reference  the code, without making state‐specific amendments, which makes it much easier to change the reference for new code editions where warranted.    Eliminating  the Michigan‐specific  amendments  to  the  rules  that  exceed  federal standards will result in less complex and more efficient regulations.  Most other states in the Great Lakes region regulate AST in the State Fire Marshal’s office (or a non‐environmental agency) since the regulations are focused on fire and explosion safety.  The regulation of UST are mixed, with some states authorizing the environmental agency and other states authorizing the Fire Marshal’s office or similar agency.  DEQ goes beyond accepted fire protection industry standards by requiring aboveground storage tanks  (AST) containing  flammable and combustible  liquids  to comply with the spill and overfill protection  requirements  found  in  the  federal  (and Michigan) underground  storage  tank  (UST) regulations.  These requirements are redundant in purpose to federal and DEQ rules which also regulate AST (federal SPCC and Michigan PIPP).   

Environmental Advisory Rules Committee Recommendations 

A‐48

No.  R‐7g Subject:  Liquefied Petroleum Gas (LPG) (R 29.6001 – R 6097) Regulation:  R 29.6001 – R 29.6097 Remedy:  Process    Rules     Statute  Background/Issue:   These  rules apply  to  the operation of all  liquefied petroleum gas  (LP gas) systems. A person shall comply with these rules, other applicable state and federal statutes, and rules and regulations promulgated under the statutes.  The purpose of these rules is to provide for the prevention of fires and the protection of persons and property from the exposure to the dangers of fire or explosions.  In 1998, the authority to promulgate these rules was transferred from the Department of State Police  (specifically  the  State  Fire  Marshal)  to  the  Department  of  Environmental  Quality  by executive order.   At  the  time,  the  thought was  that  transferring  the duties  to  the DEQ would lead  to “efficient administration and effectiveness of government  to  regulate  the storage and handling of  these hazardous materials within one department.”    (MCL 29.641). Unfortunately, the  transfer  has  not  led  to  efficient  administration  and  effectiveness  of  government  for  this program.    Rather,  the  program  has  become  even more  complex  and  cumbersome  for  the regulated community.  Proposed  Solution:    The  Liquefied  Petroleum Gas  (LPG)  program  (R  29.6001  –  R  29.6097)  is related  to  fire  safety and  should be  transferred  from  the DEQ  to  the Bureau of  Fire  Services (within LARA)  through an executive order.   Further,  the Michigan‐specific amendments  to  the national  codes  should  be  rescinded  and  the  current  national  codes  should  be  adopted  by reference.  Rationale  for  Change/Additional  Comments:    The  purpose  of  this  rule  is  to  provide  for  the prevention  of  fires  and  the  protection  of  persons  and  property  from  the  exposure  to  the dangers  of  fire  or  explosions,  and  should  be  transferred  to  the  Bureau  of  Fire  Services.    In addition,  they  make  Michigan  specific  amendments  to  the  NFPA  and  NACE  Codes  and incorporate by reference NFPA Code 58, NACE RP0285 and RP0169.   Eliminating the Michigan‐specific amendments to the rules that exceed federal standards will result  in  less complex and more efficient regulations. 

Environmental Advisory Rules Committee Recommendations 

A‐49

No.  R‐7h Subject:    Storage  and Handling  of Gaseous  and  Liquefied Hydrogen  Systems  (R  29.7001  –  R 29.7199) Regulation:  R 29.7001 – R 29.7199 Remedy:  Process    Rules     Statute  Background/Issue:   These  rules apply  to  the operation of all gaseous and  liquefied hydrogen systems. A person  is  required  to  comply with  these  rules, other  applicable  state  and  federal statutes, and  rules and  regulations promulgated under  the  statutes.   These  rules address  fire safety issues regarding the storage and handling of hydrogen.  In 1998, the authority to promulgate these rules was transferred from the Department of State Police  (specifically  the  State  Fire  Marshal)  to  the  Department  of  Environmental  Quality  by executive order.   At  the  time,  the  thought was  that  transferring  the duties  to  the DEQ would lead  to “efficient administration and effectiveness of government  to  regulate  the storage and handling of  these hazardous materials within one department.”    (MCL 29.641). Unfortunately, the  transfer  has  not  led  to  efficient  administration  and  effectiveness  of  government  for  this program.    Rather,  the  program  has  become  even more  complex  and  cumbersome  for  the regulated community.  Proposed Solution:   The Storage and Handling of Gaseous and Liquefied Hydrogen program (R 29.7001 – R 29.7199)  is  related  to  fire  safety and  should be  transferred  from  the DEQ  to  the Bureau of Fire Services (within LARA) through an executive order.  Further, the Michigan‐specific amendments to the national codes should be rescinded and the current national codes should be adopted by reference.  Rationale for Change/Additional Comments:   These rules are related to fire safety  issues of a flammable material, and should therefore be transferred to the Bureau of Fire Services.  In addition, these rules make Michigan‐specific amendments to NFPA Code 50A and are the only rules  in this  issue subsection that  incorporate the actual copyrighted NFPA Code 50A  language into the DEQ amendments. These rules make reference  to NFPA 10, 13, 69, 70, 220, 704, and ANSI/ASME, ASTM, and CGA.   Eliminating  the Michigan‐specific amendments  to  the rules  that exceed federal standards will result in less complex and more efficient regulations.  In 2005, NFPA incorporated the provisions of NFPA 50A and 50B into NFPA 55 (Storage, Use, and Handling  of  Compressed  Gases  and  Cryogenic  Fluids  in  Portable  and  Stationary  Containers, Cylinders, and Tanks).  NFPA 50A and 50B codes have been discontinued. 

Environmental Advisory Rules Committee Recommendations 

A‐50

No. R‐8 Subject:    Definition  of  “Background”  Concentrations  for  Hazardous  Substance  in  Soil  and Groundwater  Remedy:  Process    Rules     Statute  Background/Issue:  Under Part 201, liable parties are required to remediate soil to background levels.   This would be reasonable  if “background” was defined (loosely) as what was  in the soil before a release occurred.  However, the Part 201 rules define background as "not attributable to any release at or near the site."   In essence, this requires soil to be cleaned up to “pristine” conditions.  For obvious reasons, this is simply impossible for most property in industrial areas.   It is widely recognized that soils in urban areas typically have elevated concentrations of certain substances  –  both  naturally‐occurring  (e.g.,  lead,  nickel,  zinc)  and  not  (dioxins,  polycyclic aromatic hydrocarbons) – due to a century or more of industrial operations that released these substances  to  the  air,  land,  and water.    At  the  same  time,  it was  common  practice  to  use foundry sand, slag, cinders, ash, demolition debris, and other “inert” solid wastes as fill material, especially on  industrial property.   As a  result, soil  in virtually all urban‐industrial centers have concentrations of metals, PAHs, and other chemicals that are well above what would be typical for  unimpacted  soil.    Even  the  USEPA  has  said  these  compounds  are  “ubiquitous  in environmental media  throughout  the  world”  (USEPA  2000)  and  encourages  practitioners  to carefully  consider  “industrial background”  concentrations when establishing  cleanup goals  for all  hazardous  substances.    They  write,  “Anthropogenic  chemicals  may  be  detected  in  soil samples far removed from point sources. It is important to be able to differentiate the natural or regional concentrations of hazardous substances  from those that are associated with a source and pathway at a specific site.”  The DEQ’s current approach to anthropogenic contamination should be changed.  It is patently unfair to expect property owners to undertake “never‐ending” environmental studies and costly cleanups to address contamination that they did not cause.    Proposed  Solution:    The  DEQ  should  consider  “industrial  background”  concentrations (otherwise  known  as  anthropogenic  contamination)  when  establishing  cleanup  goals  for  all hazardous substances.  Specifically, the Part 201 statute, Rule 299.5701, and the Part 5 and Part 10 rules should be amended, as necessary, to create a process whereby the DEQ will work with the regulated community in areas containing anthropogenic contamination.  This process should include:  

1. The DEQ should make existing data regarding anthropogenic contamination across the state available to the regulated community. 

2. The  DEQ  should  allow  flexibility  for  the  regulated  community  to  develop  data regarding anthropogenic contamination for particular sites. 

3. At sites where anthropogenic contamination exists, there should be no obligation for an owner/operator to clean‐up the contamination.  Rather the DEQ should work with the owner/operator to develop a due‐care plan for the site. 

Environmental Advisory Rules Committee Recommendations 

A‐51

No.  R‐9 Subject:  Due Care for Indoor Air Inhalation at a Property Subject to MIOSHA Standards Regulation: R 299.51013(5)(b) and R 299.51013(5)(c) Remedy:  Process    Rules     Statute  Background/Issue:  Vapor intrusion into structures has been identified as an issue of increasing concern.    Rule  1013  clearly  acknowledges  a  distinction  between  residential  properties  and commercial/industrial properties regulated by MIOSHA worker protection laws and regulations.  However, sections (5)(b) and (5)(c) place restrictions upon the property owner’s ability to rely on the  MIOSHA  laws  to  regulate  employee  exposures  in  facilities  where  soil  or  groundwater contamination may pose a vapor intrusion (indoor air inhalation) risk.  Rule 1013(5)(b) states that the MIOSHA (OSHA) workplace exposure standards may be used as part of  site‐specific evaluation in connection with a Part 201 due‐care evaluation if the chemical of concern is also being used in a process in the structure.  This limitation on use of the MIOSHA standards  ignores  the  fact  that  the MIOSHA workplace  standards  apply  to  ALL work  places where  chemical  exposure  is  an  issue,  regardless  of  source.    It  also  ignores  the  fact  that  the USEPA concurs with that interpretation and accepts OSHA criteria for indoor air exposures in all work places regulated by OSHA.   Rule  1013(5)(c)  requires  that  exposure  for  non‐worker  populations  (e.g.  customers  of  a commercial/retail facility) still be evaluated on a site‐specific basis or using a criterion developed by the department. Currently, the department often  is not accepting use of the generic  indoor air  criteria  promulgated  in  Part  201  rules  and  is  requiring  use  of Operational Memorandum criteria, which can be as much as 9,000,000 times more restrictive than OSHA criteria.  This can lead to the following scenarios: 

If only workers are  in a  facility,  the MIOSHA  standards can apply, but  if a customer enters,  an  exposure  criteria over 1,000,000  times more  restrictive may  apply,  even though  the  exposure duration  is much  shorter  than  for  the workers.    This  can  add hundreds of thousands of dollars in due care compliance costs. 

The exposure criteria for a customer of a dry cleaner, where chlorinated solvents are used, can be 9,000,000 times as high as for the same customer in an office building or other retail store on a contaminated site subject to Part 201 due care. 

 Proposed Solution:  The Part 201 inhalation criteria and due care related rules (R 299.5714(6), R 299.5724(6) and R 299.51013(5)), and if necessary, Part 201, should be modified and amended so that indoor air inhalation risk at workplaces could be addressed at the option of an owner or operator  of  property  by  applying MIOSHA  and  USEPA  workplace  exposure  criteria  for  both workers and non‐workers in workplaces in lieu of generic Part 201 criteria and without regard to whether or  the extent  to which  the chemical  in question  is being used  in  the workplace. This would include the deletion of the limitations contained in R 299.5714(6)(a)‐(c), R 299.5724(6)(a)‐(c) and R 299.51013(5)(a)‐(c). In addition, if generic soil gas criteria are promulgated, the criteria should  be  based  on  indoor  air  or  inhalation  exposure  limits  established  under  MIOSHA  if established for the chemical in question.  James Clift Comments:    The  environmental  community opposes  the use of MIOSHA  rules  to dictate cleanup standards.   Part 201 standards are health‐based and designed to be consistent 

Environmental Advisory Rules Committee Recommendations 

A‐52

across the board.  

Environmental Advisory Rules Committee Recommendations 

A‐53

No.  R‐10 Subject:  Soil Relocation Statute (MCL 324.20120c) and Associated Rules Regulation:  MCL 324.20120c; Rule 299.5542(2) Remedy:  Process    Rules     Statute  Background/Issue:  MCL 324.20120c limits the relocation of soil both within a facility and from a facility to other  locations. The  law and corresponding R 299.5542 are complicated and difficult to understand and implement and result in (i) non‐compliance by those who do not understand their legal obligations, and (ii) decisions by owners and operators to not engage in the Part 201 response activity process, including compliance with section 7a due care obligations, due to the unpredictable requirements of the law and rules.  Both  MCL  324.20120c  and  R  299.5542  should  be  revised  to  establish  requirements  which provide  environmental  protection  in  an  easily  understood  manner  which  does  act  as  an unreasonable constraint on the use and redevelopment of property and encourages compliance with the law and rules.   MCL 324.20120c should be  interpreted more  liberally, consistent with the goal of encouraging remedial  activities which  reduce  or  eliminate  human  exposure  to  hazardous  substances  and protect  the  environment.  The DEQ’s  current  interpretation  of MCL  324.20120c  prohibits  the relocation of soil from one portion of a property to another portion of the property that  is not similarly contaminated, even if the property owner or operator handles the soil in a manner that reduces  or  eliminates  human  exposures,  such  as  by  relocating  the  soils  to  berms  that  are properly  capped  with  clay  or  top  soil  and  ground  cover.  This  interpretation  unnecessarily increases the cost of remedial activities, for example, by requiring expensive landfill disposal of soils that present minimal environmental risk, all of which can be economically managed on‐site if MCL 324.20120c was interpreted more liberally or amended to eliminate any ambiguities that the DEQ believes exist in the law.  The rules also contain requirements beyond that required by MCL 324.20120c. For example, R 299.5542(2)  improperly  applies  the MCL  324.20120c  soil  relocation  limitations  to  soils  that exceed  criteria  intended  to  protect  an  aquifer,  but  even  if  an  aquifer  is  not  present  at  the facility,  instead  of  considering  the  criteria  under  “section  20120a(1)  or  (2)  that  apply  to  the location to which the soil will be moved or relocated…” By  ignoring whether  the groundwater protection pathway  is  complete  and  relevant,  this  rule  could  lead  to  increased  remedial  and operating costs. Additional ambiguities and inconsistencies exist in both the law and rules.   In addition, the interface between MCL 324.20120c and Part 115 needs to be improved as past attempts  to  reconcile and coordinate  the  regulation of  soil  relocation under  the Part 201 and Part  115  programs  has  not  been  fully  successful  after many  years  of  attempts.  In  particular, proposed revisions to Part 115’s Rule 110 (R 299.4110(l)) by revision of the definition of “other wastes regulated by statute” under Part 115 would facilitate a more flexible and cost effective application of these concepts.   Proposed Solution:   The DEQ  should  implement MCL 324.20120c  to permit  the  relocation of contaminated  soils  within  facility  or  property  so  long  as  due  care  or  other  measures  are implemented which prevent human exposure or harm to the environment. In addition, the state 

Environmental Advisory Rules Committee Recommendations 

A‐54

should  amend  MCL  324.20120c  and  amend  R  299.5542  and  adopt  proposed  revised R 299.4110(l) in order to reduce regulatory burdens in connection with the proper relocation of soil under Part 201.   Rationale for Change/Additional Comments:  Revising this statute and R 299.5542 will provide clarity and certainty  to  the  regulated community, and will  result  in  increased compliance and participation in the Part 201 response activity process.  

Environmental Advisory Rules Committee Recommendations 

A‐55

No. R‐11 Subject:  Source Control Requirements Under MCL 324.20114(1) and R 299.5526(4) Regulation:  MCL 324.20114(1) and R 299.5526(4) Remedy:  Process    Rules     Statute  Background and Description of Issue:  MCL 324.20114(1) requires a liable party to take actions including: (i) “immediately stop or prevent the release at the source” (MCL 324.20114(1)(c)), (ii) “immediately  implement source control or removal measures to remove or contain hazardous substances that are released after [June 5, 1995] if those measures are technically practical, cost effective,  and  provide  protection  to  the  environment”  (MCL  324.20114(1)(d)),  and  (iii) immediately  initial  removal  of  a  hazardous  substance  that  is  in  a  liquid  phase,  that  is  not dissolved in water, and that has been released.” (MCL 324.20114(1)(f)).  There  is significant confusion about the meaning of these requirements,  including whether the term “source” is intended to mean an active source such as a leaking drum, free product, spill or other location of hazardous substances that have not yet been released into soil or water. This lack of  clear understanding  results  in  insufficient  actions being  taken  in  some  cases, while  in others  the  Remediation  Division  requires  response  activities  that  are  not  required  by MCL 324.20114(1) due to its belief that sources are present and must be removed by a liable party.   Only Rule 299.5526(4)(c) appears to address any of these situations by establishing an obligation of a liable party to implement source removal for free phase liquids.   Proposed Solution:  R 299.5526(4) should be amended to facilitate a clear understanding of the requirements of MCL 324.20114(1), including what constitutes a “source” subject to the Section. 

Environmental Advisory Rules Committee Recommendations 

A‐56

No.  R‐12 Subject:  Relationship Between Part 201 & Part 213  Regulation:  Part 201; Part 213 Remedy:  Process    Rules     Statute  Background/Issue:    Part  201  is  the  program  specifically  designed  to  govern  the  cleanup  of contaminated property across the state.   The program was  formed by Public Act 307 of 1982, and significantly expanded in 1990.  In 1988, in response to federal legislation, Michigan created a separate program governing the cleanup of leaking underground storage tanks. The governing statute was amended in 1993 and 1995.  The registration and UST regulatory program became Part 211 of the NREPA when Michigan's environmental  laws were codified (451 PA 1994).   The program  for cleaning up  leaking USTs became Part 213, when Michigan’s environmental  laws were codified (451 PA 1994).    Between 1988 and 1995  the  state operated a program  to assist  leaking underground  storage tank owners  in remediating contaminated sites (Michigan Underground Storage Tank Financial Assurance Fund).  Due to funding shortfalls the program terminated in 1995, although the state continues  to  collect  7/8  cents  per  gallon.    That  program  required  the  use  of  “qualified consultants” to do work that funded by the state.   Those consultants are still utilized today for the Part 213 program, but not the Part 201 program.    There  is a significant overlap between department administration of Parts 201 and 213.   Both cover the cleanup of contaminated sites, utilize the same  liability standard and must meet the same  standards  regarding  the  cleanup  of  the  contaminated  sites.  However,  each  program maintains  its own  staff and  supervisors, and has  separate administrative  rules, and  they have both separate and common funding sources.   The end result is the state is operating two different programs even though the contaminates of concern,  risks  to  public  health,  and  the  strategies  and  techniques  for  investigation  and remediation  at  any  particular  site  may  be  identical.    Merging  the  programs  would  more efficiently utilize scarce public resources.    Proposed Solution:  Combine Parts 201 and 213 into one statute and one program, merge staffs and  focus on one  set of  administrative  rules  to  govern  the  cleanup of  contaminated  sites  in Michigan.  Rationale  for  Change/Additional  Comments:    Combining  Parts  201  and  213 would  increase efficiency and result in cost savings for the department and the regulated community. 

Environmental Advisory Rules Committee Recommendations 

A‐57

No.  R‐13 Subject:  Part 201 Due‐Care Plans Submitted as Response‐Activity Plans for SBA Loans Remedy:  Process    Rules     Statute  Background/Issue:   One of  the 2010 amendments  to Part 201 was  to eliminate  the provision regarding DEQ approval of BEAs.  This created an issue for loans made by the U.S. Small Business Administration (SBA).  With the 2010 changes, SBA was no longer willing to fund loans for sites with BEAs without DEQ  involvement.   After negotiations, the SBA agreed that a due‐care‐plan reviewed  by  the  DEQ  as  a  response‐activity  plan  was  an  acceptable  alternative.    Moving forward,  to  ensure  the  due‐care‐plan  review  process  associated  with  SBA  loans  remains  a functioning part of  the Part 201 program,  steps  should be  taken  to address expedited  review times and appropriate reviews.  Specifically, the department should be provided up to 30 or 45 days to complete a due‐care‐plan review in this context.  The statutory limit of 150 days would not allow transactions to proceed in a commercially‐reasonable timeframe.  Also, to ensure the regulated community provides the information needed to obtain an affirmed due care plan, the DEQ could develop a guidance document outlining the content that the DEQ believes would  comply with  a due‐care‐plan  requirement  for  SBA  loans.    This  guidance must account for the fact the due‐care‐plans are being prepared by non‐liable parties and not subject them  to  the  same  level  of  investigation  or  response‐activity  requirements  as  a  liable  party.  Provisions  should  also  be  in  place  for  making  reasonable  assumptions  based  on  expected contaminant levels and locations as well as applicable pathways.    Proposed Solution:  Develop a Policy Guidance Document that creates an expedited period for reviews of due‐care plans in the SBA‐loan context.  Further, it would be helpful to the regulated community if the DEQ created a Policy Guidance Document outlining the content that the DEQ believes would comply with the due‐care‐plan requirement for SBA loans.  Rationale for Change:  By ensuring the timing and technical review issues are addressed, small and medium‐sized  businesses  deploying  SBA‐backed  loans  to meet  their  business  needs will continue to help the state move forward in its economic recovery.  

Environmental Advisory Rules Committee Recommendations 

A‐58

No.  R‐14 Subject:  Boron Standard for Groundwater (R 299.5744) Regulation: R 299.5744 Remedy:  Process    Rules     Statute  Background/Issue:   The use of 500 ug/l boron, a phytotoxicological  standard based on celery leaf  damage,  as  the  Part  201  drinking  water  standard  instead  of  the  actual  drinking  water standard of 1900 ug/l should be discontinued. This lower standard puts dischargers statewide in remedial action when there is no threat to drinking water and there is almost always no celery farm to protect.   Proposed Solution:   Amend R 299.5744  to use  the drinking water standard as  the criteria  for boron.   Prior  to determining  to  the applicability of  the drinking water  standard at a  site,  the pathway must be reviewed to determine if the impacted portion of the receiving waters is being used for purposes of irrigation.  If the impacted portion of the receiving waters is being directly used  for  irrigation,  then a  lower  standard may be  set at  the discretion of  the DEQ  to protect potentially sensitive crops.    Rationale  for Change/Additional Comments:   The current standard of 500 ug/l was set based on a study that showed damage to certain crops (celery, beans, onions, grapes, and fruit trees) when irrigation water was used with boron concentrations above 500 ug/l.  Other crops, such as corn, thrive with irrigation water with higher concentrations of boron as boron is a nutrient for these  plants.    It  is  a  rare  circumstance  that  industrial  groundwater  discharges  are  used  for irrigation  purposes.    It  is  rarer  still  for  these  discharges  to  be  used  for  irrigation water  for sensitive crops.  Consequently, it makes sense to use the drinking water standard for boron for the vast majority of groundwater discharges.  It does not make sense to set the standard at the lowest  recommended  level,  but  to  reserve  that  determination  only when  irrigation  is  being applied.  If irrigation is being applied, the DEQ has the discretion to set a lower standard based on the expected use of that irrigation water, including the potential for crop rotation.   

Environmental Advisory Rules Committee Recommendations 

A‐59

No.  R‐15 Subject:  Quality Review Team  Remedy:  Process    Rules     Statute  Background/Issue:   The Quality Review Team  is non‐transparent and  inefficient.   District office representatives present interim and final remediation and due‐care plans to senior Remediation Division  staff  in a closed‐door meeting.   Decisions are not delegated  to  the districts;  they are issued by Lansing management and often take weeks.  Although  there  is benefit  to  consistent  regulation  across  the  state,  this  can be  accomplished through more appropriate means, such as educating the district staff.  To the extent needed, the senior  Remediation  Division  staff may  engage  on major  decisions.    But  senior  Remediation Division staff should not be required to approve most decisions.    Proposed  Solution:    Discontinue  the  Quality  Review  Team  process,  focusing  instead  on educating district staff and monitoring appropriately. The DEQ’s process to educate District staff and  monitor  decision‐making  should  focus  on  achieving  consistency,  quality  control,  and collaboration with the regulated community.  Rationale for Change:   Elimination of the Quality Review Team will streamline the process and should create transparency. 

Environmental Advisory Rules Committee Recommendations 

A‐60

No.  R‐16 Subject:  Flexibility When Site Exceeds Only Secondary Non‐Health‐Based Standards Remedy:  Process    Rules     Statute  Background/Issue:  Michigan’s rules do not allow for appropriate flexibility to close a site where there  is  off‐site migration  of  groundwater  exceeding  secondary  non‐health  based  standards.  Specifically, the requirement to obtain landowner signatures on restrictive covenants should not be automatically required when a landowner is hooked up to municipal water.  Proposed Solution:  The Part 201 statute and the Part 5 rules should be amended to provide the DEQ with  the  flexibility to approve a  limited closure at a site where hazardous substances are migrating  onto  adjoining  properties  at  levels  that  exceed  only  secondary  non‐health‐based standards and where  the affected property  is hooked up  to municipal water.   Specifically,  the amendments  should  authorize  the DEQ  to  approve  a  closure  at  these  sites  according  to  the following process:  

1. The owner/operator develops data regarding the plume‐migration characteristics and information  regarding  property  owners  within  the  plume  that  are  hooked  up  to municipal water. 

2. The owner/operator  sends notice  to  all  identified  property owners  informing  them that  contamination  exceeding  secondary  non‐health‐based  standards  is  migrating onto  their property and  that  the owner/operator has  requested a no‐further‐action letter from the DEQ, and the property  is a “Facility” subject to disclosure obligations under Part 201 or Part 213. 

3. The  notice  should  provide  each  landowner  a  period  of  time  (such  as  21  days)  to respond if they feel that the DEQ should not issue the no‐further‐action letter. 

4. If the DEQ does not receive any responses within that time period, the DEQ may move forward with  issuing the no‐further‐action  letter.   On the other hand,  if one or more landowners respond, the DEQ must review each response to determine whether the migrating contamination  is reasonably anticipated to  impair the use of the property.  If no such  impairment  is  found at any of  the properties,  the DEQ may  issue  the no‐further‐action letter. 

5. The  Part  201  statute  and  rules  should  explicitly  state  that  this  process  in  no way affects or limits any rights of a property owner. 

 Rationale  for Change/Additional Comments:   These changes will  lead  to more closures while still protecting the rights of adjoining landowners.  

Environmental Advisory Rules Committee Recommendations 

A‐61

No.  R‐17 Subject:  Review Part 201 Cross‐References Regulation: Part 201; R 299.5532 Remedy:  Process    Rules     Statute  Background/Issue:  Certain sections of R 299.5532 cross reference parts of the statute that has been  amended,  and  the  cross  reference  no  longer  makes  sense,  e.g.,  299.5532(2)(a)  and 299.5532(11)(i)(i).    Part  201  was  amended  in  December  of  2010  and  there  may  be  other incorrect cross references.   Proposed Solution:   The DEQ and Attorney General’s office should review all cross references contained in the Part 201 rules and correct any errors.   

Environmental Advisory Rules Committee Recommendations 

A‐62

Resource Management Recommendations  

No. RM‐1 Subject:  Liquid Industrial Waste Regulations   Recommendation: The DEQ  should develop  rules  and/or  changes  to  the  statute(s)  governing liquid  industrial waste  to make  the process of handling  these materials more streamlined and cost effective for the regulated community while protecting human health and the environment.  In the development of these rules and recommendations, the department should  look at what rules can be eliminated and how the various rules can be consolidated.  This rules package and/or statutory change recommendations must be evaluated in comparison to the federal standards and should be consistent with the programs in surrounding Great Lakes States.    Any  rules  package  and  statutory  changes  should  be  presented  to  the  Office  of Regulatory Reinvention (ORR) by September 1, 2012.  The development of the liquid industrial waste recommendations must consider: 

The role of manifests in the hauling and disposal process.  The development of an electronic manifesting system.  De minimis and threshold quantities in determining applicability of the law or rule.   Duplicative rules and standards between the various parts of the Act(s) governing liquid 

industrial waste.  Whether certain insignificant materials such as used oil, wash water and other small or 

insignificant materials should be included in the Act.  How liquid industrial waste is handled under the present laws and rules.  Registration/licensing of liquid industrial waste haulers.  The reasons for using a licensed hauler.  Reasonable  insurance  and  financial  assurance  requirements  that  reflect  real  risk  and 

actual costs.  Whether the current list of materials in the Act should continue to be listed.  The option of regulating used oil as a universal waste.  Consider regulating other LIW wastes streams as universal waste. 

  

Environmental Advisory Rules Committee Recommendations 

A‐63

No. RM‐2 Subject:  Beneficial Reuse Remedy:  Process    Rules     Statute  Background/Issue:  Current  definitions  of  solid  waste  and  inertness  do  not  facilitate  the beneficial reuse of high volume/low  impact materials such as paper mill sludge,  foundry sand, etc.  Application of Part 201 cleanup criteria are inappropriate and discourage beneficial reuse.  Recommendation:   The DEQ should develop, based on recommendations from stakeholders, a new comprehensive Beneficial Reuse Act.  The recommendations of the stakeholder workgroup should be completed by April 1, 2012 and legislation prepared by May 1, 2012.  Rationale  for Change:   Many suitable by‐products are  regarded as waste by  the DEQ and are buried or burned.  Michigan should be a leader in innovation and beneficial reuse of by‐products from the manufacturing industries in our state. 

Environmental Advisory Rules Committee Recommendations 

A‐64

No. RM‐3 Subject: Michigan Hazardous Waste Regulations Regulation:  Part  111,  Hazardous  Waste  Management,  of  the  Natural  Resources  and Environmental Protection Act (NREPA), 1994 PA 451, as amended Remedy:  Process    Rules     Statute  Background/Issue:   Michigan’s  lists of hazardous wastes  included  in Table 205c of R 299.9226 are more  restrictive  than  federal Resource Conservation Recovery Act  (RCRA)  standards.   No additional treatment standards are required for these wastes.   Michigan’s rules exceed federal standards but do not provide additional environmental protections. There  is confusion created by different state and federal listing codes for hazardous substances.  DEQ collects manifests  from RCRA permitted  facilities and generators of hazardous waste.   At one point DEQ had three FTEs performing data entry. The data  is still being entered.   The only use for the data of which we are aware is to generate a draft biennial report for generators. This burden (creation of biennial reports) should be borne by the generator, not the state/taxpayer.  Eliminating the data entry seems reasonable.  Michigan has  lists of hundreds of  chemicals  that  go well beyond  the USEPA  listed hazardous waste.  These  lists  are  located  in  Rule  219  (Table  202), Rule  223  (  Table  204b)  and  Rule  226 (Table 205c).  Proposed Solution:   The DEQ should conduct a systematic  review  ‐  including stakeholder and public comment  ‐ of  the chemicals and wastes  listed  in R 299.9226, Table 205c  (“U”  listed); R 299.9219, Table 202  (“S” characteristic); and R 299.9223, Table 204b  (“K”  listed).   The  review should consider new  information about  the chemicals and wastes  to determine  if  they should remain on the lists or be removed.  Rationale  for  Change/Additional  Comments:    By  going  above  and  beyond  the  federal  RCRA requirements,  Michigan  industries  have  to  comply  with  and  fund  the  implementation  of requirements that are not required of industries in other states.  Also, by not incorporating the federal RCRA regulations by reference, DEQ delays  implementation of federal requirements by having  to  implement  its own  rulemaking process.    Favorable  federal  regulatory  changes may never  be  adopted  since  states  are  not  required  to  adopt  less  stringent  requirements.    For example, Michigan has not, and may not adopt, the revised definition of solid waste that would allow  increased opportunities for reuse and recycling of certain materials by reclassifying their status to non‐hazardous (for example, spent purge solvent from automotive paint shops).  James Clift Comments:   The environmental  community  supports public  transparency when  it comes  to  hazardous  wastes  that  are  generated,  stored  and  transported  through  Michigan communities.  Unfortunately, many chemicals in wide use today have also not been fully tested regarding their potential impact on public health.  We therefore oppose restricting the number of chemicals covered by the current reporting systems.     

Environmental Advisory Rules Committee Recommendations 

A‐65

No. RM‐4  Subject: Rescind/Repeal Michigan PCB Regulations Regulation:    Part  147,  Chemical  Compounds,  Subpart  1,  PCB  Compounds  (MCL  324.14701  – 324.14705) of Act 451 and administrative rules (R 299.3301 – R 299.3319) Remedy:  Process    Rules    Statute  Background/Issue:   Michigan’s PCB regulations are no  longer necessary given the existence of detailed  USEPA  PCB  regulations.    PCB  regulations  are  regulated  under  Part  147  and administrative  rules  (R  299.3301  –  R  299.3319).    These  rules  are  outdated  and  have  been superseded  by  USEPA  PCB  regulations  (40  C.F.R.  Part  761)  enacted  under  the  U.S.  Toxic Substances  Control  Act.    Michigan  PCB  rules  are  no  longer  enforced,  but  remain  in  the administrative code.  Proposed Solution:  Michigan’s PCB rules (R 299.3301 – R 299.3319) should be rescinded. Make statutory  amendments  necessary  to  remove  PCB  regulations  from  Michigan  statute  (MCL 324.14701 – 324.14705).  Rationale  for Change/Additional Comments:   Most  interpret  the TSCA pre‐emption clause as not allowing  states  to  regulation PCBs above and beyond USEPA  regulations.   Michigan  is no longer  supporting  or  enforcing  these  regulations,  but  leaving  them  on  the  books  opens regulated community up to potential risk and causes confusion. 

Environmental Advisory Rules Committee Recommendations 

A‐66

No. RM‐5 Subject:  Hazardous  Waste  Biennial  Reporting  Required  Under  the  Federal  Resource Conservation Recovery Act (RCRA) Of 1976 Regulation:    Section  3002(a)(6)  of  the  Resource  Conservation  Recovery  Act  (RCRA)  of  1976 requires USEPA  to  develop  a  program  for  hazardous waste  generators  to  report  the  nature, quantities  and  disposition  of  hazardous  waste  generated  at  least  once  every  two  years.  In addition, Section 3002(a)(2) requires treatment, storage, and disposal facilities (TSDFs) to submit a report on the wastes they receive from off‐site. Remedy:  Process    Rules     Statute  Background/Issue:    Biennial  reporting  and  the  RCRA  Permitting  process  are  bulky  and redundant.     The DEQ collects the biennial reporting  information on behalf of the USEPA.   The USEPA defines the data points that must be collected and transmitted to the federal database.  The ability for generators and treatment storage and disposal facilities to file electronic biennial reports would  be  ideal.    Currently,  the  state  does  not  have  the  resources  to  implement  an electronic data collection system.   The state has been using  the Waste Data System  (WDS)  to help prepare biennial reports and with the latest update to WDS, all the data is available on‐line.  The  state  has  also  been  advocating  on  behalf  of  the  regulated  community  to  reduce  the reporting burden of the biennial report to only those data points that are required by rule.  The DEQ is amenable to further discussions on how to streamline the collection of biennial reporting information, but this is a federal requirement.  DEQ has  tried  to assist  large quantity generators  (LQGs) and  treatment,  storage and disposal facilities  (TSDFs) with biennial  reporting  via  information packets  as outlined on  the  following Web site: http://www.michigan.gov/deq/0,1607,7‐135‐3312_4118_4240‐181382‐‐,00.html.   An electronic biennial system would be a great benefit to generators.  Proposed Solution:   The DEQ  should  convene a  stakeholder workgroup  to develop electronic biennial  reporting  for  hazardous  waste  generators  to  streamline  the  process  and  eliminate duplicative reporting.  

Environmental Advisory Rules Committee Recommendations 

A‐67

No. RM‐6 Subject: Financial Assurance for Landfills Regulation: Part 115 (MCL 324.11501, et seq.) Remedy:  Process    Rules    Statute  Background/Issue:    The  current  regulation  has  distinct  financial  assurance  requirements  for Type III and Type II  landfills; however, proposed changes to Part 115 would require some non‐hazardous  Type  III  landfills  to  meet  the  same  financial  assurance  requirements  of  Type  II landfills.  Proposed  Solution:    Part  115  should  be  amended  to  allow  for  additional  financial  assurance mechanisms,  and  to  streamline  and  create  a more  cost  effective method  of  assuring  proper funds are available for landfill emergencies and closure.   Rationale  for Change/Additional Comments:    Increases  in  the  amount of  financial  assurance required  drives  up  cost  –  especially  for  companies  struggling with  credit  restrictions  in  this difficult economy. 

Environmental Advisory Rules Committee Recommendations 

A‐68

No. RM‐7 Subject: Hazardous Waste User Charge and Manifest Systems Regulation: User charges are established under Part 111, Hazardous Waste Management, of the NREPA and underwent revision pursuant to PA 403 of 2008.  Manifest requirements are found in both Part 111 and Part 121, Liquid Industrial Waste, of the NREPA. Remedy:  Process    Rules     Statute  Background/Issue:    The  required  manifesting  system  is  paper  intensive  and  burdensome. Hazardous  waste  user  fees  are  awkward  and  arbitrary.  Both  should  encourage  appropriate behavior: reduced volume of hazardous waste generated.  Proposed Solution:   The DEQ  should  convene a  stakeholder group  to  redesign  the hazardous waste user charge system to make it fair, simple and timely, and to develop electronic methods for minimizing the paperwork associated with the verification of hazardous waste manifests.     Rationale  for  Change/Additional  Comments:    A  more  efficient  system  would  result  in  the elimination  of  paperwork.    There  is  no  reason  for  generators  to  review  DEQ  data  entry  for accuracy  as part of  this  report.    In  addition,  generators  should not have  to  add unprocessed manifests from the current year to the report.   The  invoice sent to the generators should have all manifests for that year that DEQ processed. 

Environmental Advisory Rules Committee Recommendations 

A‐69

No. RM‐8 Subject: Medical Waste Storage Accumulation Limitation (Sharps Containers) Part 138, Medical Waste Regulatory Act, 1978 PA 368, as Amended Regulation: MCL 333.13809(1)(h); R 325.1541 – R 325.1549 Remedy:  Process    Rules     Statute  Background/Issue:   The state mandates "use"  limitation of 90 days for sharps containers.   This limitation results in many containers being disposed of that are not full. In addition the tracking and  labeling  requirements  are  burdensome.    Current medical waste  rules  treat  all  sharps  as medical waste.  Proposed  Solution:   Amend  the  act  and/or  rules  governing  the disposal of medical waste  to require disposal of sharps that are used strictly for non‐medical procedures (a) when the storage container  is full, or (b) annually, whichever occurs first.  The sector(s) receiving this exemption should  be  defined  in  the  rules  to  avoid  having  sharps  containers  with  different  storage requirements within the same facility.  Rationale  for Change/Additional Comments:   Would eliminate disposing of partial containers, which would  result  in  a  cost  savings,  increased  sustainability,  and  reduction  in  burdensome tracking/labeling/removal workflow.   

Environmental Advisory Rules Committee Recommendations 

A‐70

No. RM‐9 Subject: Conformance Bond or Statement of Financial Responsibility Requirements for Mineral Well (Disposal Well) Operators; Part 625, R 299.2330 Regulation: Part 625, R 299.2330 Remedy:  Process    Rules     Statute  Background/Issue:    USEPA  Underground  Injection  Control  (UIC)  regulations  also  require financial responsibility requirements which are the same as the states but are not on the same form.   The USEPA annual financial test requirements for the same wells should be sufficient to meet the state’s requirements.   Proposed  Solution:    DEQ,  with  input  from  stakeholders,  should  attempt  to  enter  into  a memorandum of understanding with  the USEPA  to utilize  the same conformance bond, and  if successful, should rescind any duplicative rules.  Rationale  for Change/Additional Comments:   The DEQ  requirements  for  conformance bonds are redundant with the federal regulatory program.  

Environmental Advisory Rules Committee Recommendations 

A‐71

Water Recommendations  

No.  W‐1 Subject:  Part  5,  Spillage  of  Oil  and  Polluting  Materials,  of  the  NREPA  (PIPP,  TRQs,  911 Notification, Release Reporting Related to Secondary Containment) Regulation: R 324.2001 – R 324.2009; MCL 324.3111b Remedy:  Process    Rules     Statute  Background/Issue:  As a whole, this rule set is more stringent than federal requirements.  To a certain degree, these rules can be viewed as an example of the state accepting the stewardship responsibility  of  protecting  the  Great  Lakes.    However, much  of  the  increased  burden  and stringency  created  at  the  state  level  is  excessive  and  provides  little  in  way  of  additional protection.    Portions of  the  rule  are  related  to  the  federal  Spill  Prevention  Control,  and Countermeasure (SPCC)  program which  requires  a  spill  prevention  control  plan.    But where  the  SPCC  plan  is focused  primarily  on  oil,  the  state  has  created  an  extensive  20‐page  list  of  state‐specific chemicals  (about  900  chemicals),  including  salt,  that  would  require  a  pollution  incident prevention  plan  if  the  threshold  management  quantity  (TMQ)  is  exceeded.    For  outdoor locations,  a  TMQ  of  only  440  pounds  is  all  that  is  necessary  to  trigger  the  requirement  to generate a state plan.  Another area of excessive state stringency is related to the threshold reporting quantity (TRQ) of polluting materials in Table 1 of Part 5, Rule 9.  The Table 1 list appears to closely resemble the federal  Comprehensive  Environmental  Response,  Compensation,  and  Liability  Act  (CERCLA) reportable quantity  (RQ)  list  in  terms of  the  listed  chemicals.   However,  the major difference when comparing the two lists is that the state TRQ level is uniformly only 10% of the CERCLA RQ (for any chemicals where the CERCLA RQ is 100 pounds or greater).  For example:  

The CERCLA RQ  for  sodium hypochlorite  is  100 pounds  and  the  state  TRQ  is only  10 pounds. 

The CERCLA RQ for propylene oxide is 100 pounds and the state TRQ is 10 pounds.    The  CERCLA  RQ  for  potassium  hydroxide  is  1,000  pounds  and  the  state  TRQ  is  100 

pounds.  The CERCLA RQ for quinoline is 5,000 pounds and the state TRQ is 500 pounds. 

 When a facility subject to Part 5 has a release that exceeds the state TRQ, the spill notification process must be initiated, but as demonstrated above, at a level only 1/10th of the federal spill notification  requirements  for  many  compounds.    The  federal  Emergency  Planning  and Community  Right‐To‐Know  Act  (EPCRA  reporting)  thresholds  for  spill  reporting  have  been  in existence  for  years  and  are  effective.    Having  a  different  state  reporting  threshold  that  is arbitrarily  set  at  only  1/10th  of  the  federal  RQ  is  not  reasonable  and  only  complicates  the notification process.    In addition to the state TRQ levels being more stringent that federal RQ, the state also requires that releases must be reported to local 911.  The 911 reporting requirement was passed into law in 2004, primarily as a reaction to releases that originated in Canada.  Why releases, originating in  Canada,  resulted  in  imposing  additional  requirements  on Michigan  businesses  is  still  not 

Environmental Advisory Rules Committee Recommendations 

A‐72

clearly understood.   Releases already  trigger  the potential need  to promptly  call  the National Response  Center  (if  the  RQ  is  exceeded)  and  the  DEQ  Pollution  Emergency  Alerting  System (PEAS)  Hotline  (if  the  TRQ  is  exceeded).    The  additional  call  to  911  detracts  from  the  true emergency intent for the local 911 for the vast majority of situations.    The  Pollution  Incident  Prevention  Plan  (PIPP)  also  has  other  unusual  and  unreasonable requirements.  For example, the release of more than 1,000 gallons of a “polluting material” into a  secondary  containment  area must  be  reported  even when  fully  contained  and  there  is  no impact on  the environment.   Further, even a  release of  less  than 1,000 gallons of a polluting material  into a secondary containment area must be reported if the cleanup is not initiated with 24 hours (and completed within 72 hours) even when fully contained and there is no impact on the  environment.    This  requirement  is  unnecessary,  it  only  impacts Michigan  and  should  be eliminated.    The TRQs related to salt, either as a solid or in liquid solution, also need to be revised to be more realistic.  In a northern climate where literally tons and tons of salt are dumped on the roads on winter  days,  it’s  quite  extreme  to  require  that  salt  releases  be  reported  (by  stationary businesses) if they exceed 50 pounds as a solid or 50 gallons as a liquid.     Another  concern  is  the  definition  of  “polluting material”,  which  includes  any  compound  or product that contains 1% or more of oil, salt or any of the ~900 compounds specified in Table 1 of R 324.2009.   The concept of using a percentage threshold seems valid due to mixtures, but 1%  is  a  very  small percentage  to pull  the  entire mixture  into  the  Part  5  rules.    Increase  this threshold to a more reasonable level of 25 – 50%.  Finally, there are certain aspects and guidance references in the rules that may force regulated community  to  accept  certain  risks  that  are  not  otherwise  considered  acceptable,  e.g., referencing the management and storage guidance for rail cars.  Proposed Solutions:  

1. Increase  the  threshold management  quantity  (TMQ) which  triggers  the  need  for  a PIPP from 440 pounds (about 1 barrel) to a more reasonable  level of 500 gallons.   (R 324.2002(f)(iv)). 

2. Revise the threshold reporting quantities (TRQs) in Table 1 to make all TRQs similar to the  federal  CERCLA  RQs  (many  are  currently  only  1/10th  of  the  federal  level),  or eliminate Table 1 and reference the existing CERCLA RQs for the reporting thresholds.  (R 324.2009 Table 1). 

3. Revise MCL 324.3111b to eliminate the requirement to call local 911.  When reporting is necessary, calls are already required to the National Response Center and the DEQ PEAS hotline.   

4. Eliminate  the  reporting  requirements  related  to  releases  that  go  to  secondary containment.  (R 324.2002(b)(i)). 

5. Significantly  increase  the  reporting  threshold  for salt  to 1,000 pounds  for solids and 1,000 gallons for liquids.  (R 324.2002(g)(iii)). 

6. Increase the mixture threshold from its current 1% level to more of a 25 – 50% range.  (R 324.2002(a)(iv)). 

7. In general, revise Part 5 rules to make them easier to understand and follow.   Work 

Environmental Advisory Rules Committee Recommendations 

A‐73

with  regulated  community  to  establish  rules  that  are  understandable,  technically feasible, and will achieve intended results. 

8. Revise the conditional exemption in R 324.2003(1)(b) to reference the current version of  the SPCC  regulations at 40 CFR Part 112, currently dated October 14, 2010.   The current  rule  reference  is  the  1997  SPCC  regulation, making  the  current  conditional exemption useless. (R 324. 2003(1)(b)). 

 Rationale for Change/Additional Comments:  This program is not required by Federal law, and is  redundant  to  federal  SPCC,  CERCLA,  and  EPCRA  regulations.  (See  summary  of  federal requirements  in  Addendum  on  the  following  page  which  summarize  the  health  and environmental  criteria  that  is  evaluated  in  order  to  establish  federal  RQ  levels).    The  911 requirement  puts  undue  stress  on  already  busy  and  understaffed  police  and  fire  operators.  CERCLA / EPCRA reporting already require notification to Local Emergency Planning Committees (LEPC) to trigger local response, if needed.  The cost of compliance is unnecessarily high due to state  specific  standards,  such  as  those  relating  to  Pollution  Incident  Prevention  Plans  (PIPP).  These rules exceed  federal requirements and  those of other states  in  the region.    In addition, they are complex and do not address concerns in a common sense manner or approach.  James Clift Comments:   The environmental community supports attempting to streamline  the reporting process and building off federal requirements.  We also support eliminating the use of 911  in  non‐emergency  situations  and  substituting  other  appropriate  local  officials.  The environmental  community  does  not  support  reducing  the  threshold  quantities  for  release reporting to the state.    

Environmental Advisory Rules Committee Recommendations 

A‐74

Addendum to Recommendation W‐1  

USEPA Reportable Quantity Adjustments 

The following information is from USEPA’s website at: 

 http://www.epa.gov/superfund/policy/release/rq/index.htm#method 

What Is the Purpose of RQ Adjustments?  

Why adjust the CERCLA statutory RQs? 

Statutory  RQs  are  often  those  set  provisionally  by  Congress  (usually  at  one  pound),  pending  detailed scientific analysis by USEPA and adjustment through notice and comment rulemaking. They often do not reflect the relative hazard posed to public health and the environment. By adjusting the RQs, the Agency is able  to  focus  its  resources on  those  releases  that are more  likely  to pose potential  threats  to public health  or  welfare  or  the  environment,  while  relieving  the  regulated  community  and  government emergency response personnel from the burden of making and responding to reports of releases that are less likely to pose such threats.  

How Does the RQ Adjustment Methodology Work?  

What  properties  of  CERCLA  hazardous  substances  are  evaluated  for  purposes  of  adjusting  the RQs  for these substances?  

The Agency evaluates the properties of hazardous substances (other than radionuclides) in a two‐step process:  

Step 1: Primary Criteria 

RQ adjustment begins with an evaluation of the intrinsic physical, chemical, and toxicological properties of each substance. These intrinsic properties called "primary criteria" are aquatic toxicity, acute mammalian toxicity  (oral,  dermal,  and  inhalation),  ignitability,  reactivity,  chronic  toxicity,  and  potential carcinogenicity.  USEPA  ranks  hazardous  substances  for  each  intrinsic  property  (except  potential carcinogenicity) on a five‐tier scale, associating a specific range of values on each scale with a particular RQ value,  from one  to 5,000 pounds. For hazardous substances evaluated  for potential carcinogenicity, each substance is assigned a hazard ranking of "high," "medium," or "low," corresponding to RQ levels of 1, 10,  and 100 pounds,  respectively. Each  substance  receives  several  tentative RQ  values based on  its particular  intrinsic properties  the  lowest of all  the  tentative RQs becomes  the "primary criteria RQ"  for that substance. (See "How were the RQs for radionuclides determined?" for radionuclides.)  

Step 2: Secondary Criteria 

After  the primary  criteria RQs are assigned,  substances are  further evaluated  for  their  susceptibility  to certain  degradative  processes,  which  are  used  as  secondary  adjustment  criteria.  These  natural degradative  processes  are  biodegradation,  hydrolysis,  and  photolysis  (BHP).  In  general,  if  a  hazardous substance degrades relatively rapidly in the environment to a less hazardous form by one or more of the BHP processes, its primary criteria RQ is raised one level. Conversely, if a hazardous substance degrades to a more hazardous product after its release, the original substance is assigned an RQ equal to the RQ for 

Environmental Advisory Rules Committee Recommendations 

A‐75

the more hazardous substance.

Environmental Advisory Rules Committee Recommendations 

A‐76

No.  W‐2 Subject:   Mercury  Rule  for National  Pollutant Discharge  Elimination  System  (NPDES)  Permits Regulation: R 323.1211(7)(a) Remedy:  Process    Rules     Statute  Background/Issue:    This  unique  Michigan  policy  is  ineffective  in  addressing  environmental concerns  as  it  does  not  address  atmospheric  deposition  from  global  sources.    The  cost  of compliance is very high with no commensurate benefit to Michigan.  The  rule  does  not  allow  the  DEQ  to  include  net  intake  concentration  in  the development/calculation  of  a water quality‐based  effluent  limit  (WQBEL)  applied  at  a  plant's external effluent.   As a result,  industry or an NPDES permittee with a WQBEL for mercury or a toxic substance  in the  permit will  be  responsible  to  remove,  treat  or  control  that  substance  that  is  otherwise coming in from the intake (as background) whether it is present in the water by natural means or by other sources upstream of the plant, and is not related to plant operations.    Alternatively, DEQ will require a plant to improve the plant's Pollution Minimization Plan (PMP) to  include  an  employee  education  component  to  assist  in  possibly  lowering  the  presence  of mercury  in  noncontact  (condenser  cooling  water)  discharge  even  more.    Intake  mercury concentrations account for 92% of loading discharged at some sites.  This has tremendous cost implications with negligible environmental gains.     If intake loading is not allowed to be accounted for in the Part 8 WQBEL calculation, it will force permittees (including municipalities) to install treatment technologies to remove a loading that they are not otherwise responsible in contributing.  This is one more rule that ratchets down on point source discharges at an expense to account for nonrelated source contributors upstream.  Proposed  Solution:    Allow  an  NPDES  permittee  with  a  water  quality‐based  effluent  limit (WQBEL)  for  mercury  in  the  permit  to  account  for  inlet  loading  concentration  when  their contribution  to  the effluent  is negligible.   Language should be added  to R 323.1211(7)(a)  that states: 

 “If the mean effluent concentration  is  less than 10% greater than the mean  inlet concentration (using  24  consecutive  months  of  monitoring  data)  and  does  not  exceed  the  mean  inlet concentration  by  more  than  0.5  PPT,  then  the  permittee  should  be  exempt  from  the  PMP requirements and subject to annual monitoring.”  Rationale  for  Change/Additional  Comments:    This  unique  Michigan  policy  is  ineffective  in addressing environmental concerns as  it does not address atmospheric deposition from global sources.   The cost of compliance  is very high with no commensurate benefit to Michigan. The environmental community believes focus should remain on atmospheric deposition of mercury, and any requirements placed on the NPDES permittee should be specifically designed to reduce mercury discharges.  

Environmental Advisory Rules Committee Recommendations 

A‐77

No.  W‐3 Subject:    R  299.2933(4)  Promulgated Under  Part  41,  Sewerage  Systems,  of  the NREPA  (MCL 324.4101 et seq.) Regulation: R 299.2933(4) Remedy:  Process    Rules     Statute  Background/Issue:    R  299.2933(4)  promulgated  under  Part  41,  Sewerage  Systems,  of  the NREPA,  MCL  324.4101  et  seq.,  requires  an  applicant  for  a  private  wastewater  system  to demonstrate that the  local unit of government has committed to assume responsibility for the system if the applicant fails to operate and maintain it.  The rule was found invalid by the Court of Appeals in Lake Isabella Development Inc. v. Village of Isabella, 259 Mich App 393 (2003).  Proposed Solution:  R 299.2933(4) should be rescinded.  Rationale for Change/Additional Comments:  The rule is obsolete. 

Environmental Advisory Rules Committee Recommendations 

A‐78

No.  W‐4 Subject:  Part 22 Rules for Groundwater Discharges Regulation: R 323.2210 Remedy:  Process    Rules     Statute  Background/Issue:    The  rules  are  vague,  causing  the  regulated  community  to make  inquiries regarding whether various “discharges” to the ground or groundwater would require permitting.  When  approaching  the  agency,  the  regulated  community  has  experienced  inconsistent interpretation.   Proposed  Solution:    R  323.2210  should  list  types  of  discharges  which  do  not  require groundwater  permits  –  similar  to what  is  done  in  the  storm water  regulations.    That  listing should  address  issues  such  as: potable water,  fire protection water,  irrigation drainage,  lawn watering, air conditioning condensate, and foundation or footing drains.  Rationale for Change/Additional Comments:  Property owners and businesses need regulatory certainty about what discharges to the ground or groundwater require permits. 

Environmental Advisory Rules Committee Recommendations 

A‐79

No.  W‐5 Subject:  Part 301 (Section 30105) Inland Lakes and Streams; Part 303 (Section 30312) Wetlands Protection; and Part 325 (Section 32512) Great Lakes Submerged Lands of the NREPA Remedy:  Process    Rules     Statute  Background/Issue:    Michigan  has  three  programs  –  Inland  Lakes  and  Streams,  Wetlands Protection, and Great Lakes Submerged Lands – that roughly equate to the U.S. Army Corps of Engineers’  (USACE)  404  program.    Michigan  programs  pre‐date  the  USACE  programs  and regulate different activities in a different manner than the USACE.  The USACE and USEPA have identified deficiencies  in the DEQ program because  it did not permit certain activities that are covered  in  the Corps Nationwide Program. The USACE Nationwide Program  regulates a  lot of inconsequential activities, but does so in an unobtrusive manner by allowing coverage through a permit by  rule.   The DEQ has  just passed a new  set of  requirements  that  referred  to General Permits  and Minor  Projects  that  regulate  all  of  these  new  activities;  however,  rather  than allowing  a  permit‐by‐rule,  the DEQ  requires  time  consuming  individual  permits.    There  is  no benefit  in  requiring  individual  permits.    Major  construction  projects  are  delayed  while inconsequential permits must first be obtained.  Moreover, the Nationwide Permits specify the desired behavior and a permit‐by‐rule is just as effective in requiring construction according to a set of proscribed practices.  Proposed Solution:  Amend Michigan’s Inland Lakes & Streams, Great Lakes Submerged Lands, and Wetlands programs to adopt the USACE Nationwide Permitting approach of allowing non‐reporting general permits for minor projects below certain thresholds and individual permits for project  above  those  thresholds.    Amend  the  Minor/General  Permit  Category  revisions accordingly.        To  ensure  consistent  program  implementation,  these  activities  should  be coordinated with any proposals from the Wetland Advisory Council.  Rationale  for  Change/Additional  Comments:    Recently,  a  new  proposed  set  of  Rules/Permit Categories were developed which are more stringent than what the DEQ has been using.   This would result in significant increases in the number of permit applications, longer waiting periods for issued permits and additional requirements for Public Notification / Comments.  USEPA will not  accept  a  “permit  by  rule”  approach,  but  could  support  something  like  a  USACE  “non‐reporting general permit” approach.  James Clift Comments:   The environmental community supports the current process of review of this program by the legislatively created Wetland Advisory Council.  We think changes in the program, including the scope of exemptions, should be designed to ensure continued delegation of  the  Clean Water Act  404  program.   Adoption  of  nationwide  permits  categories  should  be crafted in a manner that is consistent with other program requirements.   

Environmental Advisory Rules Committee Recommendations 

A‐80

No.  W‐6 Subject:  Implementation of General Federal Nationwide Permits:   State 401 and Coastal Zone Management Certification Of U.S. Army Corps of Engineers (USACE) Nationwide Permits Remedy:  Process    Rules     Statute  Background/Issue:   Nationwide Permits used by the USACE to authorize activities which singly or  cumulatively  have  minimal  adverse  effects  on  the  aquatic  environment  require  State certification  under  Section  401  (water  quality  certification)  and  Coastal  Zone  Management portions of the federal Clean Water Act.  Of the 44 Nationwide Permits that could be issued by the USACE, the State has denied or partially denied certification for 11 nationwide permits and imposed additional conditions on 19 permits. These denials result in applicants having to submit individual  permit  applications  rather  than  enjoying  the  permit‐by‐rule  procedure  that  other states  allow  under  the Nationwide  permits.    These  denials/conditions  should  be withdrawn. They  provide  no  environmental  benefit. All  of  the  44 Nationwide  Permits  specify  proscribed construction techniques that are protective of the environment and there is nothing other than delay associated with a requirement for the Corps to issue an individual permit.   Proposed  Solution:    The  DEQ  should  review,  with  stakeholder  involvement,  all  44  USACE Nationwide Permits to determine  if the current MDEQ Nationwide permit denials or additional conditions make sense or  if they are more stringent than the federal requirements.   To ensure consistent program  implementation, these activities should be coordinated with any proposals from the Wetland Advisory Council.  Rationale for Change/Additional Comments:  DEQ’s denials provide no environmental benefit. All of the 44 Nationwide Permits specify proscribed construction techniques that are protective of the environment and there is nothing other than delay associated with a requirement for the Corps to issue an individual permit.  This vetting of the 44 Nationwide Permits has not been done with stakeholder  input to ensure that the public interest is being served.  Some of the denials and conditions may be in the best interest  of  the  State  while  some  may  merely  add  burden  for  Michigan  business  with  no environmental benefit.  Rationale for Change/Additional Comments:    James Clift Comments:   The environmental community supports the current process of review of this program by the legislatively created Wetland Advisory Council.  We think changes in the program, including the scope of exemptions, should be designed to ensure continued delegation of  the  Clean Water Act  404  program.   Adoption  of  nationwide  permits  categories  should  be crafted in a manner that is consistent with other program requirements.   

Environmental Advisory Rules Committee Recommendations 

A‐81

No.  W‐7 Subject:  Sanitary Sewer Overflows Control Remedy:  Process    Rules     Statute  Background/Issue:    Sanitary  sewers  are  designed  to  carry  sewage  (and  only  sewage)  to  a wastewater  treatment plant  (WWTP).   In practice, however, storm water enters  the collection system  during  rain  events  causing  the  system  to  exceed  its  design  capacity.   To  prevent basement flooding, this excess water  is discharged to the nearby waterways.  These overflows (known  as  sanitary  sewer  overflows  or  SSOs)  violate  the  federal  Clean  Water  Act  (CWA).  Unfortunately,  compliance  is  very  costly  and  care must  be  taken  to  assure  that  the  funding committed to SSO control is sufficient to fulfill the requirements of the law while minimizing the costs to the rate payers.  Combined sewers are designed to carry both sewage and storm water.  When it is not raining, a combined system sends the sewage to a WWTP for treatment.  When it does rain, the collection system  collects both  sewage and  storm water  (i.e.,  combined  flow) and  the  flow  is  sent  to a WWTP, and/or  to a  combined  sewage overflow  retention  treatment basin  (i.e., CSO RTB)  for treatment.  Sometimes, a rain event  is so  large that the excess combined flow  is discharged to nearby waterways.  Such discharges are permitted and (generally) do not result in violations of the CWA.  Combined sewage systems are typically found in older well‐developed communities, such as the city of Detroit.  Whether  it  is  a  sanitary  sewer  or  combined  sewer,  both  types  of  systems  are  limited  by  its particular design capacity.  There will always be a larger storm that exceeds the ability to control an overflow.  In the case of a large rain event, the system must be relieved by discharging to the river, or basements will  flood.  No  system  can be designed  to manage all  sizes of  storms.  To eliminate SSOs, one viable and less costly solution would be to permit system operators, where available, to commingle "wet" sanitary flow with combined sewage flow.  Basically, this involves a process of diverting  "wet"  sanitary  flow  to an existing CSO RTB, where  it will be  stored  for subsequent treatment at a WWTP, or discharged with partial treatment (i.e. settling, screening and disinfection) from the CSO RTB.  Using existing CSO RTB capacity would allow communities to quickly eliminate SSOs  (because  the  capacity  is already  in  the ground) and would  serve as “emergency capacity” when events that exceed the design standards occur.  The problem is that current DEQ policy prohibits the commingling of the flows from different systems.   Proposed Solution:  Revise the Part 21 rules (R 323.2101 et seq.) to explicitly direct the DEQ to permit the diversion of separate sanitary flow to a combined sewer retention treatment facility for settling, screening, disinfection and discharge  in order to prevent sanitary sewer overflows (SSOs),  provided  such  discharge  to  a  combined  sewer  retention  treatment  facility  does  not violate water quality standards.  In addition, the DEQ should permit a sewage system operator that is under an administrative order to abate storm water infiltration and inflow to its sanitary collection  system,  to  divert  flow  from  the  separate  sanitary  system  to  a  combined  sewer retention treatment facility to provide the operator time to rehabilitate the sanitary collection system.  Rationale  for  Change/Additional  Comments:    Using  existing  CSO  RTB  capacity  would  allow communities  to  quickly  eliminate  SSOs  (because  the  capacity  is  already  in  the  ground)  and 

Environmental Advisory Rules Committee Recommendations 

A‐82

would serve as “emergency capacity” when events that exceed the design standards occur.   There  is  no  federal  or  state  law  or  EPA  policy  that  prohibits  the  co‐mingling  (diversion)  of separate sanitary sewage flow and combined sewage flow. Indeed, EPA Region 5 acknowledges that  in almost every region of the country where there are combined sewer  facilities, that co‐mingling with separate sanitary flow occurs. The EPA Region 5 was not able to identify a single major combined sewer area that did not currently accept separate sanitary sewage flow. Cities such Cleveland, Chicago, Milwaukee and Pittsburgh, are all  cities  that have  combined  sewers accepting  flow  from  separate  sanitary  systems.  EPA  has  also  acknowledged  that  eliminating separate sewage from combines systems is costly, impracticable and in many cases impossible.  The only state that expressly prohibits the co‐mingling of the two types of flows via policy (not by  statute  or  rule)  is  the  State  of Michigan  through  its DEQ. DEQ  admits  that  they will  use enforcement  discretion  when  it  comes  to  controlling  SSOs  in  this  manner.  This  leads  to uncertainty in the regulated community.   Controlling and eliminating SSOs without causing basement flooding, is very expensive. Sanitary retention tanks (SRTs) can cost municipalities hundreds of millions of dollars. And for what? To control  overflows  that  occur  less  than  four  times  a  year. Many  communities  have  already invested in large combined sewer retention facilities to control and treat overflows before such flows  are discharged  to our  rivers  and  streams. Where  available,  allowing  the  co‐mingling of flows as part of a comprehensive plan to control and eliminate SSOs will save taxpayers millions, which should be used for needed operation and maintenance.  

Environmental Advisory Rules Committee Recommendations 

A‐83

No.  W‐8 Subject:  Agricultural Activities Under Parts 301 and 303 of the NREPA Regulation:  Part 301 and Part 303 Remedy:  Process    Rules     Statute  Background/Issue:  The agricultural community has raised several issues related to the manner in which  certain  agricultural  activities  are  regulated  under  Parts  301  and  303.    For  example, there  is confusion over  the extent  to which a permit  is required  for activities  that are directly related  to exempt  agricultural  activities,  such  as  fencing  associated with  grazing.   Also,  there appears  to  be  inconsistent  interpretations  related  to  whether  a  permit  is  required  for  the cutting of trees or bushes in wetlands associated with agricultural activities.  Finally, the USEPA recently  pronounced  that  the Michigan  Supreme  Court’s  ruling  in  Huggett  v  Department  of Natural Resources, 464 Mich 711 (2001)  is  inconsistent with federal  law.   In Huggett, the court held  that  "the  farming  activities  exemption  is  not  limited  to  'land  in  established  use  for agriculture'....[E]ven  if  the  activity  was  not  previously  established,  it  will  fall  within  the exemption  for  farming activities and  the wetland permit  requirements will not apply."    Id. at 721, 722.  The USEPA takes the position that agricultural activities must be established in use to be exempt.    Since  the Michigan wetlands program  regulates wetlands  that are not  regulated under  the  federal program,  the USEPA’s position  regarding Huggett could be  limited  to state‐only wetlands.   Proposed  Solution:    The DEQ  should work with  the  agricultural  community  to  resolve  issues related to the manner in which certain agricultural activities are regulated under Parts 301 and 303.  These include: 

the  extent  to  which  permits  are  required  for  activities  directly  relating  to  exempt activities, such as fencing for grazing; 

the cutting of trees and bushes within wetlands; and  whether  it  is appropriate  to  limit  the USEPA’s position regarding the Huggett ruling to 

only federal wetlands.    The primary consideration  in resolving these  issues should be to streamline the permit 

process, especially for activities that have a minimal impact on the environment.    Rationale  for Change/Additional Comments:   By requiring  individual permit reviews  for  these types of minimal  impacts, the DEQ places an unnecessary burden on the  industry and requires additional DEQ staff involvement for administration of the program.    James Clift Comments:   The environmental community supports the current process of review of this program by the legislatively created Wetland Advisory Council.  We think changes in the program, including the scope of exemptions, should be designed to ensure continued delegation of  the  Clean Water Act  404  program.   Adoption  of  nationwide  permits  categories  should  be crafted in a manner that is consistent with other program requirements.    

Environmental Advisory Rules Committee Recommendations 

A‐84

No.  W‐9 Subject:  Groundwater Discharge – Part 22, Groundwater Quality Rules Remedy:  Process    Rules     Statute  Background/Issue:  The groundwater‐discharge program is a state‐directed program that is not required by federal law.  Unfortunately, the program has had a history of permit backlogs.  And the program’s permit requirements can be overly burdensome, particularly for the agricultural industry.    Michigan’s  groundwater‐discharge  program  would  operate  more  effectively  by adapting to focus on specific, significant threats to groundwater.   This could be accomplished by expanding  the  permit‐by‐rule  categories  and  eliminating  categories  requiring  groundwater‐discharge permits for projects with minimal or no environmental impact.  Proposed Solution:  The DEQ should pursue changes to the groundwater‐discharge program in the Part 31 statute and the Part 5 and Part 22 rules to  focus on specific, significant threats to groundwater.    These  changes  should  include  expanding  the  permit‐by‐rule  categories  and eliminating categories requiring groundwater‐discharge permits for projects with minimal or no impact on groundwater.    Rationale  for  Change/Additional  Comments:    The  DEQ  must  focus  limited  resources  on protecting Michigan’s most important resources while servicing customers and participating as a full partner in economic development.  To focus resources, DEQ must limit the application of the best professional judgment of staff to those issues that have significant environmental impact.  

Environmental Advisory Rules Committee Recommendations 

A‐85

No.  W‐10 Subject:  Part 5, Spillage of Oil and Polluting Materials Rules Regulation:  R 324.2003(1)(b) Remedy:  Process    Rules     Statute  Background/Issue:   Rule 324.2003(1)(b) creates a conditional exemption from the Part 5 rules for  certain  on‐land  or  oil  storage  facilities  subject  to  the  federal  oil‐pollution‐prevention requirements of 40 CFR Part 110 or 112.   One of  the conditions  to  this exemption  is  that  the "[t]he owner or operator of such a facility shall submit a copy of the facility's spill prevention, control,  and  countermeasure  plan  in  accordance with  R  324.2006(2)."    This  condition  is  not required by the federal rules and is an unnecessary burden.  Proposed Solution:  Delete the condition in R 324.2003(1)(b) requiring facilities to submit SPCC plans in order to remain exempt from the Part 5 rules.    Rationale  for  Change/Additional  Comments:    DEQ  staff  has  made  various,  sometimes inconsistent, statements about whether SPCC plans need to be submitted.  Federal rules do not require  that  such plans be  submitted –  they  just need  to be made available.   That  is already covered in DEQ rules so this statement can be deleted.  James Clift Comments:  The environmental community believes the public and local emergency responders should be fully apprised of a facility’s spill prevention, control and countermeasure plan, and thus support broad sharing of the plan.  

Environmental Advisory Rules Committee Recommendations 

A‐86

No.  W‐11 Subject:    Unduly  Restrictive  Requirements  for  NPDES  Permitting  Of  Storm Water  Runoff  at Airports  Remedy:  Process    Rules     Statute  Background/Issue:    DEQ  and  federal  Clean  Water  Act  regulations  require  that  airports discharging  storm  water  obtain  a  National  Pollutant  Discharge  Elimination  System  (NPDES) permit.  Unlike  USEPA,  DEQ  does  not  currently  have  a  sector‐specific  industrial  storm water permit that allows airports to discharge storm water that contains aircraft deicing fluids (ADFs). The DEQ is therefore limited in its ability to allow airports to otherwise comply with USEPA and Michigan  rules  through  a  general  permit.  Airports  could  operate  more  cost‐effectively  if Michigan adopted regulations that required DEQ to develop a sector‐specific general permit for airports consistent with USEPA regulations.  Deicing  aircraft  and  airfield  pavement  is  essential  for  safe  wintertime  operations.  Winter operations  safety  is  strictly  regulated  by  the  Federal  Aviation  Administration  (FAA),  which provides  airports  and  aircraft operators with  specific policies  and procedures  for deicing  and anti‐icing  aircraft  and  airfield  pavements.  FAA  also  regulates  the  performance  and characteristics  of  all  aircraft  and  airfield  pavement  deicing  products.  Only  SAE  International Aerospace Materials  Specifications  (AMS)  certified products may be used. Currently,  the only aircraft  fluids  that  meet  these  technical  specifications  are  formulated  from  a  base  fluid consisting  mostly  of  ethylene  glycol,  propylene  glycol,  or  glycerin.  Because  the  airlines  (or aircraft  operators,  not  the  airports)  are  responsible  for  the  safe  operation  of  their  aircraft, airports must allow them to use this select group of approved products which are categorized as Type  I,  II,  III,  and  IV  fluids.  Airports  have  some  ability  to  establish  the  base‐fluid  type  and locations for the airlines to apply aircraft deicing fluids. Safety requirements also limit the types of best management practices (BMPs) that airports can use to manage their storm water runoff. Finding cost‐effective measures to eliminate the presence of ADFs in airport storm water runoff can be extremely challenging. The discharges can, however, often be controlled through a mix of appropriate storm water management measures, BMPs, and other efforts (such as treatment).  The  Flint  Bishop  International  Airport  and most  other  airports  in Michigan  have  historically operated under an  industrial storm water permit under Michigan’s general permit. The permit requires that the facility prepare a Storm Water Pollution Prevention Plan (SWPPP), implement BMPs, and meet other requirements to comply with Michigan regulations.  DEQ staff has indicated that Michigan’s industrial storm water permit prohibits the discharge of any deicer‐contaminated storm water. Staff indicated that the airport would eventually need an individual permit, which usually results in strict numeric limits for the discharges and can lead to more costly compliance monitoring and reporting. DEQ staff is willing to continue to work with the airport, but our concern is that without a change in regulations, DEQ’s ability to provide the needed flexibility for the airport will be unduly limited.  In  contrast,  USEPA’s  Multi‐Sector  General  Permit  for  Air  Transportation  facilities  requires permittees to develop a SWPPP, practice good house‐keeping measures, and implement control measures during the deicing season.  Samples of contaminated storm water are to be collected and compared  to benchmark concentrations  for  specific  contaminants  so  that permittees  can 

Environmental Advisory Rules Committee Recommendations 

A‐87

assess how well BMPs are working.  If a similar process was used  in Michigan, smaller airports could be authorized to discharge storm water that contains minor levels of ADFs that cannot be captured, including to an impaired waterway, without numeric effluent limits.   Proposed Solution:   Provide DEQ with additional flexibility  in helping airports manage ADFs  in storm  water.  Adopt  rules  that  require  DEQ  to  develop  a  sector‐specific  general  permit  for airports  consistent with  federal  regulations  and USEPA’s Multi‐Sector General  Permit  for  Air Transportation  facilities  (Sector  S‐air  transportation  facilities)  and  that  don’t  impose requirements stricter than required under federal law.  Rationale:   The current regulations exceed the federal standards.   The proposal would provide the DEQ with additional flexibility in helping airports manage ADFs in storm water.  James Clift Comments:  The environmental community will oppose adoption of USEPA’s Multi‐Sector General  Permit  for Air  Transportation  facilities  (Sector  S‐air  transportation  facilities)  if they  cannot  be  demonstrated  to  ensure  compliance with water  quality  standards  and  anti‐degradation requirements.  

Environmental Advisory Rules Committee Recommendations 

A‐88

No.  W‐12 Subject: Wetland Mitigation Banks Regulation:  R 281.954 (Rule 4) Remedy:  Process    Rules     Statute  Background/Issue:   Michigan’s wetland mitigation bank program has attracted the creation of very few mitigation banks, many of which are not privately owned. Michigan’s program appears to be very  immature compared to other states, such as Minnesota. The DEQ should take steps to  increase  the  viability  of  wetland  mitigation  banks  so  as  to  facilitate  more  economically efficient wetlands mitigation projects. For example, R 281.954 (Rule 4(7)) establishes a minimum of 10 acres for a wetlands mitigation bank, while providing that the new wetland may consist of multiple  sites  that  are  a minimum  size  of  1  acre  each  that  are  administered  under  a  single banking agreement. However, these size minimums are inconsistent with the need to establish mitigation  banks  in  urban  and  suburban  settings where  available  lands  are  not  sufficient  to satisfy these minimum size requirements, even though  it has been demonstrated at many on‐site mitigation sites that smaller wetland mitigation areas can be created and maintained on an economically  feasible  basis.   By  lowering  or  eliminating  the minimum  size  requirements,  the pool of potential sites and “bankers,” including small businesses, private and public landowners, would be expanded.  This would also help to avoid concentration of banks in certain areas of the watershed, and allow more even area distribution.  Proposed Solution:  

4. The DEQ should expand the service area of mitigation banks to encourage more bank development (including in urban areas) and increase access to mitigation banks while maintaining watershed protection.   

5. The DEQ should seek US Army Corps of Engineers approval of smaller mitigation banks if deemed economically feasible.   

6. The  DEQ  should  increase  the  on‐line  reporting  of  information  on  the  program, including trading information, to foster greater utilization of the banking program.  

 Rationale  for  Change/Additional  Comments:    By  lowering  or  eliminating  the minimum  size requirements, the pool of potential sites and “bankers,” including small businesses, private and public landowners, would be expanded.  This would also help to avoid concentration of banks in certain areas of the watershed, and allow more even area distribution. 

Environmental Advisory Rules Committee Recommendations 

A‐89

No.  W‐13 Subject:  DEQ Annual Wastewater Report Regulation: R 299.9001 – R 299.9007 Remedy:  Process    Rules     Statute  Background/Issue:  These rules require annual wastewater reporting to the DEQ.  The DEQ and industry agree  that  this  report  is duplicative and unnecessary.   DEQ  suspended  the  reporting requirements  in 2009  and  said  they would not  enforce  against  the  requirement until  further notice, but it’s still on the books.  Proposed  Solution:    Rescind  R  299.9001  –  R  299.9007,  which  require  annual  wastewater reporting to the DEQ.  Rationale for Change/Additional Comments:  This report is duplicative and unnecessary.   

Environmental Advisory Rules Committee Recommendations 

A‐90

No.  W‐14 Subject:  Local Regulation of Wetlands:  MCL 324.03308, MCL 324.30309, and MCL 323.30310 Regulation: Sections 324.03308, 324.30309, and 323.30310 of Act 451 of 1994 (NREPA) Remedy:  Process    Rules     Statute  Background/Issue:  These sections of the NREPA provide for the regulation of wetlands by local units of government  in a manner that can be more restrictive than state or federal regulation.  These  sections  of  the  act  should  either  be  repealed  or  modified  to  assure  that  wetland regulation on the local level is no more restrictive than federal standards.  Another layer of local permitting adds no environmental value and simply adds timing and cost burden to companies that want to do business in Michigan.   Proposed Solution:   Amend sections 324.03308, 324.30309, and 323.30310 of Act 451 of 1994 (NREPA), so that there is no authority for local wetland regulations.  Rationale  for  Change/Additional  Comments:    Another  layer  of  local  permitting  adds  no environmental  value  and  simply  adds  timing  and  cost  burden  to  companies  that want  to  do business in Michigan.  James Clift Comments:  The environmental community supports the current authority for local wetland regulations.   

Environmental Advisory Rules Committee Recommendations 

A‐91

No.  W‐15 Subject:  Coordinating Storm Water Operators for Construction Sites with Local Enforcement of Soil Erosion and Sedimentation Control Regulation: R 323.2190(2)(d) and (e) Remedy:  Process    Rules     Statute  Background/Issues:    The  federal  Clean  Water  Act  requires  industries  with  storm  water discharges  to  surface  waters  to  obtain  a  storm  water  permit  under  the  National  Pollutant Discharge Elimination System (NPDES).  The DEQ has been given the authority to administer this program.  In Michigan, permitting  for  construction  sites one  acre or  larger  is  regulated under permit‐by‐rule.  Construction  site  owners must  comply with  the  permit‐by‐rule  requirement, which includes employing a certified storm water operator for construction sites. Certified storm water  operators  are  required,  among  other  things,  to  conduct  weekly  construction  site inspections, as well as inspections within 24‐hours of a rain or snowmelt event.   In  addition  to  employing  a  storm water  operator,  construction  site  owners must  obtain  and comply  with  a  Soil  Erosion  and  Sedimentation  Control  (SESC)  permit  from  county  or  local enforcing agent pursuant to Part 91 of the Natural Resources and Environmental Protection Act (NREPA). Throughout Michigan,  this  function  (i.e. enforcement of Part 91 SESC)  is carried out either by a  county or  local municipality.  In Oakland County  this  function  is performed by  the Office of the Oakland County Water Resources Commissioner.  SESC inspectors receive the same training  as  certified  storm  water  operators,  and  further,  conduct  regular  inspections  of constructions  site  to  ensure  compliance  with  Part  91.  These  two  distinct  requirements (employing a certified storm water operator and compliance with an SESC permit) are so similar that  counties  or  local municipalities  could  process  and  issue  the  present  permit‐by‐rule  on behalf of the DEQ as part of the normal SESC permit process. 

 Proposed  Solution:    Amend  R  323.2190  to  provide  construction  site  owners  the  option  of utilizing the services of the local Part 91 SESC Inspectors to fulfill the inspection and compliance reporting requirements.  Rationale  for  Change/Additional  Comments:    This  recommendation  would  create  a  more harmonious  relationship  between  the  regulator  and  regulated  community,  decreasing intimidation and negative impactful behaviors as well as creating motivation for compliance.  

 In addition, it would result in reduced costs to the regulated community by allowing a developer to utilize the services (through the SESC permitting process) the local SESC inspector to fulfill the certified  storm  water  operator  duties.    This  would  provide  cost  savings  to  developers, particularly smaller developers. 

Environmental Advisory Rules Committee Recommendations 

A‐92

No.  W‐16 Subject:  NPDES Permitting for Construction Sites Regulation: Part 21, Wastewater Discharge Permits Rules (R 323.2101 – R 323.2197) Remedy:  Process    Rules     Statute  Background/Issue:   The Part 21 rules, promulgated under Part 31 of the NREPA, require storm water discharge permits for construction sites over 1 acre.  These sites are addressed through a “permit by rule,” which means that smaller sites do not need to wait for approval from DEQ to begin activities.   Under the rules, a site between 1 and 5 acres will automatically be covered  ‐ not requiring any submittal to DEQ ‐  if  it has received approval from an approved  local agency under Part 91, Soil Erosion and Sedimentation Control, of  the NREPA.  Sites between 1 and 5 acres  are  also not  required  to  submit  any paperwork  to DEQ, but must  still  comply with  the requirements of the “permit by rule,” including hiring a certified storm water operator to make regular inspections and reports.  Sites over 5 acres must submit what amounts to an application and have their activities approved by the DEQ before conducting construction activities.   The rules assume that any construction activities on sites over 1 acre will result in discharges to surface waters.   But  there may be  instances where construction activities are  so  far  removed from a surface water body that they will not discharge to surface waters.  The current regulatory scheme  does  not  provide  for  a  certification  process  that would  exempt  certain  construction activities from the Part 31 storm water regulations  if  it can be demonstrated that construction activities will not impact surface waters.  Proposed Solution:  The Part 21 rules governing storm water discharges from construction sites should be amended to allow for a process that will exempt sites where it can be demonstrated that  there will be no discharge of  sediment  to a  surface water body.   This will eliminate  the requirement that a certified storm water operator be hired for sites that are between 1 and 5 acres where it has been demonstrated that there will be no discharge of sediment to a surface water body, and will eliminate the requirement of a submittal and approval of an “application” for sites over 5 acres, in instances where there is no anticipated impact to surface waters.    Rationale  for  Change/Additional  Comments:    This  proposal  would  eliminate  the  costs  for construction site owners to employ certified storm water operators  for sites between 1 and 5 acres, or submit an “application” to the DEQ for sites over 5 acres, in instances where there is no anticipated impact to surface waters. 

Environmental Advisory Rules Committee Recommendations 

A‐93

No.  W‐17 Subject:   Safe Drinking Water – Cross Connection  Inspections of Residential, Commercial and Industrial Properties   Regulation: R 325.10113 Remedy:  Process    Rules     Statute  Background/Issue:   The DEQ  is authorized by  the Michigan Safe Drinking Water Act, 1976 PA 399,  as  amended,  to  promulgate  rules  necessary  to  continuously  provide  safe  and  adequate supply  of water  to  the  users  of  public water  supply  systems.  Pursuant  to  Act  399  and  the administrative rules, a water utility or water system owner is responsible for development of a local  program  to  eliminate  all  cross  connections  to  public  water  supply  systems.  A  cross connection  is  an  arrangement  of  piping  which  could  allow  undesirable  water,  sewage  or chemical solution  to enter  the draining  (potable) water supply system as a result of backflow, that can result in illness or death. Cross connections pose one of the most serious public health threats to a drinking water supply systems.  In Michigan, cross connections with potable piping systems are prohibited by the state plumbing codes.  In addition, as noted above, Act 399 requires water utilities to have a cross connection control  inspection program of  their water  customers  to  identify, eliminate  and prevent  cross connections of residential, commercial and industrial water customers.  Currently, DEQ guidelines recommend that a water utility owner or operator inspect residential properties  (connected  to  public water  supply  system)  for  cross  connections,  at  least  every  3 years. For  commercial and  industrial  it  is  recommended each  time a plumber  is  contacted  to perform work or annually whichever is sooner.  The problem  is  that  there  seems  to be  inconsistency  in  the  requirements  from community  to community  throughout  the state. Many commercial and  industrial customers believe  that  the program  is  unduly  burdensome  and/or  frustrating  because  of  the  inconsistency  in  the requirements  for  compliance  (e.g.  testing  frequency  from  community  to  community  and/or plumber  to  plumber).  Moreover,  the  basis  for  state  recommended  frequency  of  cross‐connection  inspection of  residential properties does not appear  to be  supported by  sufficient data. That is, it appears to be arbitrary rather than supported by analysis of failure rates. Indeed, under  the  current  program,  there  does  not  seem  to  be  sufficient  information  to  perform  a statistical analysis of failure rates because water utilities are not made aware of the failures by the homeowner or their hired plumber.  Typically, the only  information provided to the water utility is the completed testing forms that show passing results.  Proposed  Solution:    Amend  R  325.10113  to  set  a  standard  for  the  frequency  of  testing residential  cross‐connections.      The  standard  should  be  based  on  data  that  is  compiled  and analyzed  to  determine  the  number  and  frequency  of  failures  and  identification  of  cross connection problems in residential, commercial and industrial properties. A cost/benefit analysis should be undertaken as well.   Rationale for Change/Additional Comments:  There is no scientific basis for the reduction in the frequency  of  inspections.  Water  customers  –  residential,  commercial  and  industrial  –  are responsible for the costs of  inspections and repairs. The current program has  led to additional 

Environmental Advisory Rules Committee Recommendations 

A‐94

unwarranted costs to consumers. 

Environmental Advisory Rules Committee Recommendations 

A‐95

No.  W‐18 Subject:  NPDES Water Treatment Additives  Remedy:  Process    Rules     Statute  Background/Issue:  Water treatment additives (WTA) require prior approval by the DEQ before they  can be used and discharged  through a NPDES permitted outfall.   Significant  lead  time  is needed, which can hold up projects or process improvements.   The DEQ has been responsive to the concerns that have been expressed related to long approval times.    Current  response  times  are  very  prompt,  not  exceeding  a  month  if  the  toxicity information is available.  The major reason for current delays is the absence of product toxicity information.  The DEQ’s goal is to respond to requests in 6‐8 weeks.  That time frame is affected when  the DEQ does not  receive complete requests or needs to obtain additional  toxicity data (i.e. pH adjusted data, etc.).   Proposed Solution:  The DEQ should create a “notification only” process for well‐defined water treatment additives (WTA) conditions that pose minimal toxicity concerns (e.g., the WTA would not  be  present  at  the  discharge  point  to  navigable  waters  in  toxic  amounts,  including  a conservative safety factor).  

Environmental Advisory Rules Committee Recommendations 

A‐96

No.  W‐19 Subject:  Mercury Standard for Groundwater Regulation:   Part 201, Environmental Response, of the NREPA,  ‐ Environmental Contamination Response Activity Rules, R 299.5744; and Part 31, Water Resources Protection, of the NREPA – Part 4. Water Quality Standards, R 323.1057 Remedy:  Process    Rules     Statute  Background/Issue:  The groundwater/surface water interface criterion/wildlife protection value for mercury of 1.3 ng/l was adopted  from  the Great Lakes  Initiative.   The  criterion  should be recalculated  using  current  toxicological  methods.    The  criterion  is  lower  than  ambient concentrations in most inland waters.   Proposed Solution:   DEQ should work with the USEPA to revise the Great Lakes  Initiative with respect  to  the  groundwater/surface  water  interface  criterion/wildlife  protection  value  for mercury of 1.3 ng/l, by applying current science.   

Environmental Advisory Rules Committee Recommendations 

A‐97

No.  W‐20 Subject:  Part 301 ‐ Inland Lakes and Streams – Permits Required for Drawdown Activities That Are Already Subject to Federal Energy Regulatory Commission (FERC) Authority  Remedy:  Process    Rules     Statute  Background/Issue:   Under  the Federal Energy Regulatory Commission  (FERC) process, when a hydroelectric  generation  facility  proposes  to  drawdown  the  elevation  of  the  flowage  beyond what  is allowed  in  the FERC  license,  the  licensee  is  required  to consult and obtain comments from  governmental  natural  resource  protection  agencies  prior  to  conducting  maintenance activities or deviations in operations.  The specific agencies differ for every FERC license, but the State  of  Michigan  is  always  represented  either  through  the  Department  of  Environmental Quality (DEQ) or the Department of Natural Resources (DNR).  For large construction projects, the licensee prepares an Environmental Report that identities all of the potential environmental impacts and describes proposed mitigation measures that avoid or  minimize  potential  impacts.    For  these  same  larger  projects,  FERC  also  develops  an Environmental Assessment to assess the potential environmental  impacts. The DEQ and/or the DNR  participate  in  the  environmental  review  process  and  specify  environmental  protection conditions to be incorporated into the FERC project approval.   It should be noted that even for smaller projects that require a drawdown, entities are required to  prepare  a  drawdown  plan  and  obtain  agency  comments.    Even with  all  of  its  previously prescribed measures  in place to avoid and minimize negative  impacts to natural resources, the DEQ also  requires  that FERC  licensees apply  for a Part 301  (Inland Lakes and Streams) permit when conducting a drawdown for hydroelectric activities.    Proposed  Solution:    Eliminate  the  Part  301  permitting  requirements  related  to  temporary drawdown activities for entities that are already subject to a FERC license.  Rationale for Change/Additional Comments:  When a FERC licensee proposes to drawdown the elevation of the flowage beyond what is allowed in the FERC license, the licensee first consults with  the  appropriate  government  agencies  and  then  obtains  FERC  approval with  comments from the agencies considered.  All of the details of the drawdown are determined through this FERC process. When all of these details are finalized through the FERC process ‐‐ which the state is part of  ‐‐ a Part 301 permit  is  then pursued.   Since all of  the details of  the drawdown are worked out through the FERC process, the Part 301 permit becomes basically a document.  If the DEQ  objects  to  the  drawdown  and  denies  the  permit  for  the  drawdown,  FERC  has  federal preemption and could simply over rule the DEQ decision and mandate that the drawdown take place.  Requiring this additional state permitting layer for federal projects not only adds additional time to the project schedule but additional costs to critical dam safety projects.    It  is not out of the ordinary  for  the complete project approval  to be held up while waiting  for a Part 301 permit.   Complications  are  increased when  there  is  a  change  in  the  drawdown  specifics.      Instead  of obtaining FERC approval and proceeding, the licensee must first obtain FERC approval and then amend the DEQ drawdown permit prior to proceeding.   Once again, FERC approval must occur first because  this  federal agency has ultimate  control.    Subsequently,  it makes  little  sense  to 

Environmental Advisory Rules Committee Recommendations 

A‐98

pursue an amendment with the state until a licensee knows that FERC approves of the change.               Other states have already recognized this duplication  in efforts and do not require permits for drawdowns governed by the FERC process.   This duplication of effort consumes valuable time of state staff and the FERC regulated entity, and results in additional financial burdens that need to be expended through  the Part 301 process  (to regulate activities already covered by the FERC process).    Agencies  like  the  DEQ  and  DNR  are  already  involved  and  participate  in  the  FERC process.   Eliminating the need for entities to apply for a Part 301 permit would streamline the process  (and  save  time  and  money  for  the  state,  as  well  as  FERC  licensees),  while  still maintaining the state’s ability to engage in the process. 

Environmental Advisory Rules Committee Recommendations 

A‐99

General Issues Recommendations  No. G‐1 Subject:  Rules More Stringent Than Federal Remedy:  Process    Rules     Statute  Background/Issue:    A  considerable  amount  of  time,  effort  and  expense  is  expended  at  the federal level to create a very broad base of national standards.  There is a fully documented and public record of the minimum “floor determinations”, background  information documents and response to public comment” to help justify and explain the intent of the rulemaking.  Michigan, like  all  states  retains  its  right  to  set  its  own  standards when  it  is  in  the  best  interest  of  its residents.  However, Michigan should defer to the federal standard as a default and only exceed them when there is a clear and convincing reason.  Proposed Solutions:   Identify existing DEQ state rules and specific requirements that are more stringent than federal.  Evaluate these rules and specific requirements to determine the benefits received versus the additional cost of compliance. Then systematically review (based on priority) to revise or eliminate unjustified rules or specific requirements. 

Environmental Advisory Rules Committee Recommendations 

A‐100

No. G‐2 Subject: Treatment of DEQ Non‐Rule Regulatory Actions  Remedy:  Process    Rules     Statute  Background/Issue:  

Guidance Documents  The  DEQ  has  two  procedures  for  the  development  of  three  types  of  formal  policy 

documents:  department  polices,  division  policies,  and  policy  guidance  documents. Department and division policies provide direction on the management of the programs either at a department or division level.  If these policies describe how the department or  division  interprets  or  applies  a  rule  or  statute,  it must  be  in  the  form  of  a  policy guidance document which requires stakeholder input.  

  Currently  the DEQ has hundreds of division policies,  sixty‐seven DEQ policies and  two 

policy guidance documents. The policy guidance document procedure  is relatively new which is the main reason for the small number.  

  Each division uses a variety of templates for their division policies. 

  The  DEQ  does  not  have  a  central  location  on  the  Internet  for  Department  policies, 

division policies and policy guidance documents.    

Some division policies have an interim or draft status.  

Educational Publications  The DEQ has a number of educational publications such as  fact sheets and  frequently 

asked questions (FAQs) that help the regulated community improve their understanding of  the  regulations. Educational publications are only a  restatement of  the  information contained in a regulation, policy guidance document, division policy, and/or department policy,  and  they  do  not  require  stakeholder  input  in  the  development  process.  The searchable  online  database  that  houses  the  DEQ’s  educational  publications  needs updating and no procedure exists  for ensuring consistent development of educational publications among the divisions.   

 Forms  To  streamline  the  collection  of  data  for  permitting,  reporting,  planning,  and 

recordkeeping  purposes,  the  DEQ  has  over  the  years  created  numerous  forms  and instructions.   The searchable online database that contains the forms  is also  in need of updating and no procedure exists for ensuring consistent development of forms.  

 Proposed  Solution:    Take  the  following  actions  with  regard  to  DEQ  guidance  documents, educational documents and forms by the stated deadlines.  

Guidance Documents  

Rescind  DEQ  Policy  and  Procedures  No.  01‐019  (Policy  Development,  Revision  and 

Environmental Advisory Rules Committee Recommendations 

A‐101

Rescission  [1/12/07])  and  No.  09‐012  (Policy  Guidance  Document  Development, Revision, and Use [12/30/09]).  Complete by December 31, 2011. 

 Develop  a new  comprehensive DEQ policy  that  addresses department policy, division policy, guidance documents and guidelines.  For the most part, department and division policies  will  address  internal  administrative  or  personnel  procedures.    “Guidance documents” will  contain  all  rule  and  statute  interpretations,  and/or will  contain  any policy/procedure  that  provides  guidance  to  those  regulated  by  the  DEQ.    Guidance documents will  provide  a  particular  path  to  compliance with  a  rule  or  statute.    The regulated  community  may  choose  this  path  or  follow  a  different  one.  If  the  issue involves an  interpretation of a rule and/or statute, stakeholder  input will be obtained. For consistency, a template for guidance documents will be created and utilized by the divisions.  Finally, the new DEQ policy will provide an alternative approach to a guidance document which is a “Guideline” as defined by Administrative Procedures Act, 1969 PA 306, as amended.  Complete by December 31, 2011. 

  Create a DEQ Web page for guidance documents which will be categorized by division or 

office.  Complete by December 31, 2011.  

For those division policies that are draft or interim, the division should either rescind or finalize through the guidance document process.  Complete by June 1, 2012. 

  Each division shall review their existing non‐rule regulatory actions.  Those meeting the 

definition of a guidance document (i.e., of  interest to the regulated community and/or interpret regulations) shall be converted into the new template and posted on the Web page.    If a division policy  interprets rules or statute and had stakeholder  input and no other substantive changes are being made, it can be directly converted into a guidance document without going through stakeholder  input for a second time.   Note: The DEQ Executive  Division  will  provide  each  Division  a  spreadsheet  containing  all  of  the division’s non‐rule regulatory actions that was compiled for the ORR in July 2011.  Those division  polices  not  converted  by  the  deadline  shall  not  be  relied  on.  Complete  by December 31, 2012.  

  Divisions  shall  review  internal  memos,  letters  and  other  documents  and  where 

appropriate,  convert  them  into  a  guidance  document  following  the  procedures identified above. Ongoing. 

 Educational Documents and Forms 

  Develop  two new DEQ policies providing  guidance  to DEQ  staff on  the production of 

educational publications and forms. Complete by December 31, 2011.  Update the DEQ Forms and DEQ Educational Publication online databases.  Complete by 

June 1, 2012. 

Environmental Advisory Rules Committee Recommendations 

A‐102

No. G‐3 Subject:  Administrative Rule Approval Process Remedy:  Process    Rules     Statute  Background/Issue:    An  ORR  review  of  the  approval  time  of  administrative  rule  packages indicated that the time to prepare and complete promulgation of a DEQ rules package from over the past 12 years averaged 644 days, or almost 20 months.   This exceeds the time required by many other departments also with more than 10 rule packages processed during this same time period,  such  as  Education  (322 days),  Community  Health  (382  days), Natural  Resources  (391 days), State Police (399 days), Treasury (426 days) and Licensing & Regulatory Affairs (467 days), and is similar to Agriculture and Rural Development (606 days) and Human Services (669 days).  This timeline appears to be driven by two excessively long steps during the process: an average of 245 days for the DEQ to provide adequate draft rules following approval of the Request for Rulemaking (“RFR”) and 433 days between approval of the RFR and the last public hearing date.  This length of time to process a rule change is out of step with the rapid pace of extensive new federal rule making, new environmental technology and the rapid changes occurring in Michigan and the world business environment.    Without a more compressed  rule change process  the  implementation of  recommendations of Committee could be  significantly delayed.    Important  reforms necessary  for  the protection of the environmental and business development would be,  in effect, set aside due to the  lack of timely implementation.  The administrative rule process can be streamlined without limiting the quality  of  the  development  of  recommended  rule  change  or  the  ability  of  the  public  to  be involved in the rule change process.  Proposed Solution:  The Committee recommends setting an expectation or requirement for the DEQ to take no more than 12 months for a proposed environmental administrative rule change.  The  process  should  incorporate  steps  to  ensure  adequate  public  comments  and  other discussions with stakeholders over accelerated schedules, as well as the use of innovative public input tools to increase public input and awareness of the proposed rulemaking.  

Environmental Advisory Rules Committee Recommendations 

A‐103

No.  G‐4 Subject:  DEQ Citation of Legal Authority Remedy:  Process    Rules     Statute  Background/Issue:    The DEQ  has,  in  the  past, made written  determinations,  such  as  permit denials, without citing the  legal standard on which they were relying  in making their decision.  Regardless of the  legitimacy of the basis for the DEQ’s decision, a failure to cite  legal authority leaves the regulated community with the impression that the decision was made arbitrarily and without any legal basis or, as in one case shared with the ORR, because the DEQ simply “didn’t like” the way the applicant was doing things.  Proposed  Solution:    When  making  a  written  determination  which  affects  the  rights  of  a Michigan  citizen  or  business,  the DEQ  should  always  cite  the  applicable  legal  basis  (statute, administrative rule, or common law) for its determination.     Rationale for Change/Additional Comments:   Requiring the DEQ to provide a legal basis for all decisions will give confidence to the regulated community that decisions are made based on the law, and not on the interpretations or feelings of state employees.