our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of...
TRANSCRIPT
![Page 1: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/1.jpg)
Our ref: 01.08.10.04/462C
VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY
ACT 1989 CONSTRUCTION AND OPERATION OF A COMBINED CYCLE GAS
FIRED TURBINE ELECTRICITY GENERATING STATION OF UP TO 1250 MW
AT THE MANORWAY, STANFORD-LE-HOPE, ESSEX
COMPRISING EITHER:
(i) UP TO TWO COMBINED CYCLE GAS TURBINE UNIT (S) OR
(ii) ONE COMBINED CYCLE GAS TURBINE UNIT WITH OPEN CYCLE
GAS TURBINE UNIT(S) OF LESS THAN 300MW
The Secretary of State in exercise of the powers conferred on him by section 36C of
the Electricity Act 1989 hereby varies the consent granted for the combined cycle gas
turbine gas fired electricity generating station at The Manorway, Stanford-le-Hope in
the County of Essex in accordance with the variations shown in italic text in the
Annex.
November 2014[Insert date of variation consent] Giles Scott
Head of National Infrastructure Consents
Department of Energy and Climate Change
![Page 2: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/2.jpg)
DEPARTMENT OF ENERGY AND CLIMATE CHANGE
CONSTRUCTION AND OPERATION OF A COMBINED CYCLE GAS
TURBINE FIRED ELECTRICITY GENERATING STATION OF UP TO 1250 MW
AT THE MANORWAY,
STANFORD-LE-HOPE, ESSEX
COMPRISING EITHER:
(i) UP TO TWO COMBINED CYCLE GAS TURBINE UNIT (S) OR
(ii) ONE COMBINED CYCLE GAS TURBINE UNIT WITH OPEN CYCLE
GAS TURBINE UNIT(S) OF LESS THAN 300 MW
CONSENT UNDER SECTION 36 OF THE ELECTRICITY ACT 1989
1. Pursuant to section 36 of the Electricity Act 1989 the Secretary of State for
Energy and Climate Change (“the Secretary of State”) hereby consents to the
construction, on the area of land outlined red on FIGURE 63114-PBP-0025, attached
hereto, of a combined cycle gas turbine gas fired electricity generating station at The
Manorway, Stanford-le-Hope in the County of Essex (“the Development”), and to the
operation of that generating station. This consent is granted to Gateway Energy
Centre Limited, its assigns and successors (“the Company”).
2. The Development shall be about 1 900 MW up to 1250 MW capacity and
comprise:
(a) Either:
(i) One or more Up to two Combined Cycle Gas Turbine (“CCGT”) units (including for each CCGT unit: a gas turbine; a heat recovery steam generator; steam turbine plant; and, associated equipment); or,
(ii) One up to two (1) One CCGT unit (including: a gas turbine; a heat recovery steam generator; steam turbine plant; and associated equipment), and (2) one or more Open Cycle Gas Turbine (“OCGT”) units with the OCGT units having a combined rated electrical output of less than 300 MW2 (including for each OCGT unit: a gas turbine; and, associated equipment);
(a) one or more gas turbines;
(b) one or more steam turbines;
(c) one or more heat recovery steam generators;
(bd) air cooled condensers and auxiliary cooling;
1 A tolerance of up to 5% is permitted
2 300MW refers to the OCGT(s) not the CCGT and the OCGT(s)
![Page 3: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/3.jpg)
(ce) gas receiving facility;
(df) one or more electrical switchyards;
(eg) ancillary plant and equipment; and
(fg) the necessary buildings (including administration offices) and civil
engineering works.
3. The Development shall be designed so as to have the capability for extracting
steam from the electricity generating cycle.
4. This consent is granted subject to the following conditions:
(1) The Development shall be constructed and operated in accordance with the
details contained in paragraph 2 of this consent and the application dated
26 February 2010 as varied by the application dated 12 August 2014 and
25 February 2016, subject to any minor changes which may be approved
by the LPA pursuant to the requirements of deemed planning permission.
(2) The commencement of the Development shall not be later than five years
from the date of this consent4 August 2011 [insert the date of the variation
consent], or such longer period as the Secretary of State may hereafter
direct in writing.
(3) The following definitions apply for the purposes of Conditions (4) to (10):
(a) “capture equipment” means the plant and equipment required to
capture the target carbon dioxide and identified as such in the
current CCS proposal;
(b) “CCS proposal” means a proposal for the capture, transport and
storage of the target carbon dioxide, which identifies the
proposed technology, transport route and storage location;
(c) “current CCS proposal” means:
(i) the CCS proposal set out in the Feasibility Study and
assessed in accordance with the guidance entitled
“Carbon Capture Readiness (CCR) A guidance note for
Section 36 Electricity Act 1989 consent applications3;
or
(ii) if a revised CCS proposal has been identified under
3
http://www.decc.gov.uk/Media/viewfile.ashx?FilePath=What%20we%20do\UK%20energy%20supply\Development%20consents%20and%20planning%20reform\electricity\1_20091106164611_e_@@_ccrguidance.pdf&filetype=4
![Page 4: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/4.jpg)
Condition (9), the proposal which has most recently
been so identified;
(d) “designated site” means the land hatched yellow on FIGURE 3-
B, annexed hereto, as the area where the Company proposes to
locate the capture equipment;
(e) “Feasibility Study” means the documents entitled Gateway
Energy Centre CCR Feasibility Study and dated February 2010,
the Gateway Energy Centre Updated CCR Feasibility Study
dated July 2014, and the Assessment of the CCR Compliance of
the Proposed Gateway Energy Centre Report dated July 2014;
(f) “target carbon dioxide” means as much carbon dioxide emitted
by the Development when it is operating at full capacity as it is
reasonably practicable to capture for the purposes of permanent
storage, having regard to the state of the art in carbon capture and
storage technology; and
(g) “the report” means the report to be submitted in accordance with
Condition (5).
(4) Until such time as the Development is decommissioned, the Company
shall not, without the written consent of the Secretary of State:
(a) dispose of any interest in the designated site; or
(b) except for use as a laydown area during the construction of the
Development and ending at the commissioning of the
Development, do any other thing or allow any other thing to be
done or to occur, which may reasonably be expected to diminish
the Company’s ability, within two years of such occurrence, to
prepare the designated site for the installation and operation of
the capture equipment.
(5) The Company shall make a report to the Secretary of State:
(a) on or before the date on which three months have passed from
the commissioning of the Development; and
(b) within one month of the second anniversary, and each subsequent
even-numbered anniversary, of that date.
(6) The report shall provide evidence that the Company has complied with
Condition (4):
(a) in the case of the first report, since this consent was granted; and
![Page 5: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/5.jpg)
(b) in the case of any subsequent report, since the making of the
previous report and explain how the Company expects to
continue to comply with Condition (4) over the next two years.
(7) The report shall state whether the Company considers that some or all of
the technology referred to in the current CCS proposals will not work, and
explain the reasons for any such conclusion.
(8) The report shall identify any other impediment of which the Company is
aware, as a result of which it considers that any aspect of what is proposed
in the current CCS proposals is likely or certain not to be technically
feasible.
(9) Reports which identify such an impediment shall state, with reasons,
whether the Company considers it technically feasible to overcome the
impediment (referred to in Condition 4(8) above) by adopting revised CCS
proposals, and, if so, include such proposals.
(10) The report shall state, with reasons, whether the Company has decided to
seek any additional regulatory clearances, or to modify any existing
regulatory clearances, in respect of its current CCS proposals in the period
referred to in Condition (6)(a) or (b), as appropriate.
(11) Conditions (3) to (10) shall cease to have effect as soon as any of the
following events occurs:
(a) the capture equipment is installed; or
(b) the Development is decommissioned; or
(c) the Secretary of State’s consent not to install capture equipment
has been obtained in writing the Secretary of State’s consent not
to install capture equipment has been obtained in writing.
![Page 6: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/6.jpg)
DIRECTION UNDER SECTION 90(2ZA) OF THE TOWN AND COUNTRY
PLANNING ACT 1990 TO VARY THE CONDITIONS OF THE DEEMED
PLANNING PERMISSION CONSTRUCTION AND OPERATION OF A
COMBINED CYCLE GAS FIREDTURBINE ELECTRICITY GENERATING
STATION OF UP TO 1250MW AT THE MANORWAY, STANFORD-LE-HOPE,
ESSEX
COMPRISING EITHER:
(i) UP TO TWO COMBINED CYCLE GAS TURBINE UNIT (S) OR
(ii) ONE COMBINED CYCLE GAS TURBINE UNIT WITH OPEN CYCLE
GAS TURBINE UNIT(S) OF LESS THAN 300MW
The Secretary of State in exercise of the powers conferred on him by section 90(2ZA)
(a) and (b) of the Town and Country Planning Act 1990 hereby directs that the
conditions subject to which the planning permission for the combined cycle gas
turbine gas fired electricity generating station at The Manorway, Stanford-le-Hope,
Essex was deemed to be granted be subject to the variations shown in in italic text in
the Annex.
November 2014 [Insert the date of the variation consent]
Giles Scott
Head of National Infrastructure Consents
Department of Energy and Climate Change
![Page 7: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/7.jpg)
DIRECTION TO DEEM PLANNING PERMISSION TO BE GRANTED UNDER
SECTION 90 OF THE TOWN AND COUNTRY PLANNING ACT 1990
CONSTRUCTION AND OPERATION OF A 900MW COMBINED CYCLE GAS
TURBINE FIRED ELECTRICITY GENERATING STATION OF UP TO 1250 MW
AT THE MANORWAY,
STANFORD-LE-HOPE, ESSEX
COMPRISING EITHER:
(i) UP TO TWO COMBINED CYCLE GAS TURBINE UNIT (S) OR
(ii) ONE COMBINED CYCLE GAS TURBINE UNIT WITH OPEN CYCLE
GAS TURBINE UNIT(S) OF LESS THAN 300MW
5. The Secretary of State in exercise of the powers conferred on him by section
90(2) of the Town and Country Planning Act 1990 hereby directs that planning
permission for the Development be deemed to be granted subject to the following
conditions:
Definitions
(1) In these Conditions unless the context otherwise requires –
"BS 4142 1997" means British Standard 4142: 1997 - Method for
rating industrial noise affecting mixed residential and industrial
areas;
"Bank Holiday" means a day that is, or is to be observed as, a Bank
Holiday or a holiday under the Banking and Financial Dealings Act
1971;
“CEEQUAL” means the assessment and awards scheme for
improving sustainability in civil engineering and the public realm
(http://www.ceequal.co.uk/index.html);
“CHPQA Standard issue 3” means the CHPQA Standard
document issued in January 2009 which sets out the definitions,
criteria and methodologies for the operation of the UK’s CHP
Quality Assurance (CHPQA) programme;
“the commencement of the Development” means the date on which
work on the Development agreed with the LPA shall be taken to be
begun initiatedin accordance with section 56 of the Town and
Country Planning Act 1990, as amended;
"the commissioning of the Development" means the date on which,
following completion of the testing of the Development, the
Development first supplies electricity on a commercial basis;
![Page 8: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/8.jpg)
"the Company" means Gateway Energy Centre Limited and its
assigns and successors;
“the Development” means a gas fired electricity generating station
of the 900 MW up to 1250 MW combined and open cycle gas
turbine generating station atLondon Gateway The Manorway,
Stanford-le-Hope, Essex, comprising either;
(i) Up to two combined cycle gas turbine (“CCGT”) unit(s) or;
(including for each CCGT unit: a gas turbine; a heat
recovery steam generator; steam turbine plant; and,
associated equipment); or:
(ii) (1) One CCGT unit (including: a gas turbine; a heat recovery steam generator; steam turbine plant; and associated equipment), and
(2) one or more Open Cycle Gas Turbine (“OCGT”) units with the OCGT units having a combined total rated output of less than 300 MW (including: a gas turbine; and, associated equipment);
"emergency" means circumstances in which there is reasonable
cause for apprehending imminent injury to persons, serious damage
to property or danger of serious pollution to the environment;
“Environment Agency” means the Environment Agency and its
successors;
"heavy commercial vehicle" has the meaning given by section 138
of the Road Traffic Regulation Act 1984;
“Highways England”Agency” means the Executive Agency of the
Department for Transport responsible for operating, maintaining
and improving the strategic road network in England and its
successors;
“the LPA” means Thurrock Council and/or Thurrock Thames
Gateway Development Corporation, as applicable, and their
successors;
"the main Development" means the construction work
commencing with the placing of the first concrete for the main
plant foundations of the Development;
“Natural England” means Natural England and its successors;
“operating weight” in relation to a goods vehicle has the meaning
given by section 138 of the Road Traffic Act 1984;
![Page 9: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/9.jpg)
“outage” means major maintenance, modification and
rehabilitation programmes which involve the delivery and/or
removal of material to and from the Site;
“Permitted Preliminary Works” means:
(i) erection of signage;
(ii) installation and diversion of utility services within the
Site;
(iii) surveys and geotechnical surveys;
(iv) decontamination measures approved pursuant to
Condition (45);
(v) temporary fencing of the Site;
(vi) provision of wheel cleansing facilities required pursuant
to Condition (4);
(vii) construction of a new access road;
(viii) preparation of contractors’ laydown area(s) within the
Site;
(ix) installation of contractors’ accommodation within the
Site; and
(x) provision for temporary contractors’ facilities necessary
for (i) to (ixi) above within the Site;
"the Site" means the area of land outlined red on FIGURE 63114-
PBP-0025, annexed hereto; and.
“SuDS” means a sustainable drainage system comprising all
treatment and drainage systems including any pipework, swales,
reed beds, ponds, filter trenches, attenuation tanks and detention
basins.
The Site
(2) The construction of the Development shall only take place within
the Site.
Reason: To ensure that no construction takes place beyond the
boundary of the area which is the subject of this planning
permission.
![Page 10: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/10.jpg)
Time Limits
(3) The commencement of the Development shall take place before the
expiry of five years from the4 August 2011 [insert date of
Variation]
Reason: To ensure that there is sufficient time to allow the person
with the benefit of the consent to undertake all necessary strike a
balance between the time it may take to put in place the necessary
pre-commencement construction measures required, including
forexample– participating in capacity auction, tendering, obtaining
the necessary financing, design of the proposal (including its layout
and main plant foundations); and minimising the impact of any
period of uncertainty for those who may be affected pending the
decision to begin construction works.
Suppression of Dust and Dirt
(4) Except for the Permitted Preliminary Works, the commencement of
any phase of the Development shall not take place until there has
been submitted to, approved in writing by, and deposited with the
LPA a scheme for the provision of wheel cleansing facilities for
heavy commercial vehicles and any mobile plant which has an
operating weight exceeding three tonnes. Such approved facilities
shall be installed in accordance with a timescale to be approved in
writing by the LPA and shall be maintained throughout the period
of the construction of the Development except in so far as any
variation of the scheme has been approved in writing by the LPA.
(5) All heavy commercial vehicles and any mobile plant which has an
operating weight exceeding three tonnes associated with the
construction of the Development leaving the Site, other than those
vehicles exclusively using tarmacadam or concrete roads, shall on
each occasion, prior to leaving, pass through the wheel cleansing
facilities provided pursuant to Condition (4).
(6) Except for the Permitted Preliminary Works, the commencement of
the Development shall not take place until there has been submitted
to, approved in writing by, and deposited with the LPA a scheme
employing all reasonable measures for the suppression of dust
during the period of the construction of the Development.
The measures approved in the scheme shall be employed
throughout the period of construction except in so far as any
variation to it has been approved in writing by the LPA.
(7) All open bodied heavy commercial vehicles carrying dry loose
aggregate, cement or soil into and/or out of the Site shall be
sheeted.
![Page 11: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/11.jpg)
Reason: To ensure that mud and deleterious material is not
deposited on the public highway.
Layout and Design
(8) Except for the Permitted Preliminary Works, the commencement
of the Development shall not take place until there has been
submitted to, approved in writing by, and deposited with the LPA
a scheme which shall include provisions for:
(i) details of the siting, design, external appearance and
dimensions of all new or modified buildings and
structures which are to be retained following the
commissioning of the Development;
(ii) details of the colour, materials and surface finishes in
respect of those buildings and structures referred to in (i)
above;
(iii) details of vehicular circulation roads, parking,
hardstandings, turning facilities and loading and
unloading facilities on the Site;
(iv) details of ground levels and heights of all permanent
buildings and structures together with cross-sections
through the Site showing existing and proposed ground
levels;
(v) details of all new or modified permanent fencing and
gates required on the Site;
(vi) details of artificial lighting required during the operation
of the Development; and
(vii) phasing of works included in the scheme.
(9) The scheme approved pursuant to Condition (8) shall follow the
principles set out within section 3 of the document entitled
“Gateway Energy Centre Environmental Statement Revised Design
and Access Statement December 2010”.
(10) Notwithstanding any details approved by the LPA pursuant to
Condition (8), and subject to due consideration of cost,
constructability and safe maintenance and operation at the detailed
design stage, the Development shall be constructed to achieve a
CEEQUAL rating of “very good”, or such standards that may
replace CEEQUAL in whole or in part prior to the commencement
of the Development providing that such changes are no more
onerous on the costs of constructing the Development.
![Page 12: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/12.jpg)
(11) The use of columns for artificial lighting shall not exceed the
obtrusive light limitations of sky glow, light into windows, source
intensity and building luminance specified in the Institution of
Lighting Engineers document “Guidance Notes for the Reduction
of Obtrusive Light: GNO1 2005”, nor shall such lighting be
arranged so that danger or inconvenience is caused to users of the
nearby public highways.
(12) The Development shall proceed only in accordance with the
scheme approved pursuant to Condition (8) except in so far as any
variation to it has been approved in writing by the LPA.
Reasons: Condition (8) is to enable the Council to exercise
reasonable and proper control over the design and appearance of
the Development. Condition (9) is for the Development to be
designed to a high standard and blend in with neighbouring
developments. Condition (10) is ensure that the environmental
sustainability of the development is maximised. Condition (11) is
to reduce light pollution and disturbance to ecological interests and
highway safety.
Travel Plan
(13) The commencement of the Development shall not take place until a
Travel Plan has been submitted to and approved in writing by the
LPA. Such Plan shall include the following provisions:
(i) provisions for pedestrian and cycle access to the Site;
(ii) the planning of working practice to minimise peak travel
flows;
(iii) the appointment of a co-ordinator responsible for the
implementation and review of the Travel Plan;
(iv) discussions with a public transport provider for the
provision of public transport to and from the Site during
the construction of the Development and during outages;
(v) travel arrangements for persons employed during the
construction of the Development and during outages;
(vi) the Travel Plan to be reviewed on a monthly basis during
construction and on an annual basis during operation,
unless otherwise agreed in writing with the LPA;
(vii) any amendments to the Travel Plan (whether or not
following a periodic review pursuant to (vi) above) shall
not be implemented without the written agreement of the
LPA;
![Page 13: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/13.jpg)
(viii) details of incentives to personnel to encourage them to
reduce the use of single occupancy cars as the means of
getting to and from the Site during the construction of the
Development and during outages; and
(ix) details of how on-Site parking will be managed and
monitored during the construction of the Development
and during outages.
The approved Travel Plan shall be implemented when personnel are first
on Site and shall remain in force throughout the period of the operation of
the development or any earlier period as may be approved in writing by
the LPA.
Reason: To encourage the use of sustainable transport methods.
Monitoring of Traffic Movements
(14) Except for the Permitted Preliminary Works, the commencement of
the Development shall not take place until a scheme for monitoring
and reporting vehicular traffic movements associated with the
construction and operation of the Development and any outages,
has been submitted to and approved in writing by the LPA, in
consultation with the Highways England Agency and Local
Highways Authority. The approved scheme shall include the
details and measures identified in the document entitled “Gateway
Energy Centre Transport Report December 2010” and “Gateway
Energy Centre Transport Report Addendum January 2016”, and be
adhered to throughout the period of the construction and operation
of the Development and any outages, any variation has been
approved in writing by the LPA, in consultation with the Highways
England Agency and the Local Highways Authority.
Reason: To encourage the use of sustainable transport methods.
Use of Water for the Delivery of Materials and Plant
(15) Except for the Permitted Preliminary Works, the construction of
the Development shall not take place until the Company has carried
out an investigation as to whether direct or near direct access to the
River Thames can be utilised for the transportation of materials and
plant (such as bulk loose cement and aggregates, and abnormal and
indivisible loads) associated with the construction and
decommissioning of the Development. The results of the
investigation shall be submitted to, approved in writing by, and
deposited with the LPA.
(16) In the event that the results of the investigation approved pursuant
to Condition (15) conclude that it is viable and economic, then the
material and plant indentified shall be not be transported to the Site
![Page 14: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/14.jpg)
via public roads, unless otherwise agreed in writing by the LPA, in
consultation with the Highways EnglandAgency
Reason: To alleviate the impact of heavy commercial traffic on the
arterial and local road networks if transportation by water is a
viable option.
Use of Rail for the Delivery of Materials and Plant
(17) Except for the Permitted Preliminary Works, the construction of
the Development shall not take place until the Company has carried
out an investigation as to whether the rail network can be utilised
or the transportation of materials and plant (such as bulk loose
cement, aggregates and steel) associated with the construction and
decommissioning of the Development. The results of the
investigation shall be submitted to, approved in writing by, and
deposited with the LPA.
(18) In the event that the results of the investigation approved pursuant
to Condition (17) concludes that it is viable and economic, then the
material and plant indentified shall be not be transported to the Site
via public roads, unless otherwise agreed in writing by the LPA, in
consultation with the Highways EnglandAgency.
Reason: To alleviate the impact of heavy commercial traffic on the
arterial and local road networks if transportation via the rail
network is a viable option.
Construction and Outage Heavy Commercial Vehicle Traffic
(19)
(20) No heavy commercial vehicle traffic shall enter or leave the Site on
any Saturday during December and the first week in January.
(21) Without prejudice to the restrictions specified in Conditions(19)
and (20) no heavy commercial vehicles associated with the
construction of the Development or an outage shall enter or leave
the Site on any Sunday or Bank Holiday or on any other day except
between the following hours:
Monday to Saturday 1000 – 1600
unless such movement:
(a) is associated with an emergency; or
(b) entering the Site originates in the administrative area of the
LPA; or
![Page 15: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/15.jpg)
(c) leaving the Site has its final destination in the administrative
area of the LPA; or
(d) is with the prior written approval of the LPA; or
(d) is an abnormal or indivisible load authorised by the Highways
England Agency pursuant to the Road Vehicles
(Authorisation of Special Types) (General) Order 2003.
.
(22) Without prejudice to the restrictions specified in Conditions (19),
(20) and (21) no traffic associated with the construction of the
Development or an outage shall enter or leave the Site on any
Sunday or Bank Holiday or on any other day during the following
hours:
Monday to Friday 0700 – 0900 and 1700 - 1800
Saturday 0700 – 0800 and 1700 - 1800
unless such movement:
(a) is associated with an emergency; or
(b) entering the Site originates in the administrative area of
the LPA; or
(c) leaving the Site has its final destination in the administrative
area of the LPA; or
(d) is with the prior written approval of the LPA.
(23) Except for the Permitted Preliminary Works, the commencement of
the Development shall not take place until a Transport
Management Plan has been submitted to, approved in writing by,
and deposited with the LPA, in consultation with the Highways
England Agency and the Local Highways Authority. The approved
plan shall include the measures detailed in section 14 of the
document entitled “Gateway Energy Centre Transport Report
December 2010” and “Gateway Energy Centre Transport Report
Addendum January 2016” be adhered to throughout the period of
the construction of the Development and any outage until such time
as the Development is decommissioned, except in so far as any
variation to the plan has been approved in writing by the LPA, in
consultation with the Highways EnglandAgency and the Local
Highways Authority.
(24) Except for the Permitted Preliminary Works, the commencement of
the Development shall not take place until a scheme detailing the
route(s) which traffic would take to and from the Site has been
submitted to, approved in writing by, and deposited with the LPA,
in consultation with the Highways EnglandAgency and the Local
![Page 16: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/16.jpg)
Highways Authority. The approved scheme shall include provision
for notices of any route(s) approved to be displayed at the Site
entrance and exit and notified to drivers. The approved scheme
shall be adhered to throughout the period of the construction of the
Development and any outage until such time as the Development is
decommissioned, except in so far as any variation to the scheme
has been approved in writing by the LPA, in consultation with the
Highways EnglandAgency and the Local Highways Authority or
the traffic movement originates in the administrative area of the
LPA.
(24A) Where the words ‘is with the prior written approval of the LPA’
appear in Conditions (21) and (22), such approval may only be
given in relation to immaterial changes where it has been
demonstrated to the satisfaction of the LPA that the approval is
unlikely to give rise to any materially new or materially different
effects from traffic entering or leaving the site on the days and
hours specified in those Conditions.
Reason: To ensure the safe and efficient use of the strategic road
network and local roads.
Construction and Construction Noise
(25) Except for the Permitted Preliminary Works, the commencement of
the Development shall not take place until there has been submitted
to, approved in writing by, and deposited with the LPA a
Construction Environmental Management Plan. The Construction
Environmental Management Plan shall include details of how
noise, airborne pollutants, vibration, smoke, and odour from
construction work will be controlled and mitigated. The
Construction Environmental Management Plan will utilise the
Considerate Constructors Scheme
(www.considerateconstructorsscheme.org.uk). The construction of
the Development shall be completed in accordance with the
approved Plan except in so far as any variation to the plan has been
approved in writing by the LPA.
(26) No construction work associated with the Development shall take
place on the Site on any Sunday or Bank Holiday, or on any other
day except between the following hours:
Monday to Saturday 0700 – 1900
unless such work –
(a) is associated with an emergency;
(b) is carried out with the prior written approval of the LPA; or
![Page 17: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/17.jpg)
(c) such work does not cause existing ambient background
noise levels to be exceeded.
(27) Without prejudice to the restriction specified in Condition (26) no
impact piling shall take place on the Site on any Sunday or Bank
Holiday or on any other day except between the following hours:
Monday to Friday 09.00 – 18.00
Saturday 09.00 – 13.00
unless such work –
(a) is associated with an emergency; or
(b) is carried out with the prior written approval of the LPA.
(28) In any instance where a time limitation referred to in Conditions
(26) and (27) is not adhered to, the Company shall as soon as
possible notify the LPA and follow up the notification with a
written statement detailing the nature of the emergency and the
reason why the time limitation could not be observed.
(29) All activities associated with the construction of the Development
shall be carried out in accordance with British Standard 5228, 2009
+ A1 2014: Code of practice for noise and vibration control on
construction and open sites – Part 1 – Noise, Part 2 - Vibration.
(29A) Where the words ‘is carried out with the prior written approval of
the LPA’ appear in Conditions (26) and (27), such approval may
only be given in relation to immaterial changes where it has been
demonstrated to the satisfaction of the LPA that the approval is
unlikely to give rise to any materially new or materially different
effects from work undertaken on the days and hours specified in
those Conditions.
Reason: To ensure reasonable and proper control to be exercised
over the methods of construction of the Development.
Operational Noise
(30) The commissioning of the Development shall not take place until
there has been submitted to, approved in writing by, and deposited
with the LPA a programme for the monitoring and control of noise
generated by the normal commercial operation of the
Development. The programme shall specify the locations from
which noise will be monitored, the method of noise measurement
(which shall be in accordance with BS 4142 1997) and the
maximum permissible levels of noise at each such monitoring
location. The programme shall make provision for such noise
measurements to be taken by the Company as soon as possible
![Page 18: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/18.jpg)
following requests by the LPA and such measurements shall be
given to the LPA as soon as they are available. At the approved
measurement locations noise levels during the operation of the
Development shall not exceed the levels specified in the approved
programme, except in so far as any variation has been approved in
writing by the LPA or in an emergency. Such noise shall exhibit no
tonal or impulse content at these locations in any weather
conditions.
(31) In any instance where a noise level approved pursuant to Condition
(30) is exceeded because of an emergency the Company shall as
soon as possible, and in any case within two working days, provide
the LPA with a written statement detailing the nature of the
emergency and the reason why the noise level could not be
observed. If the emergency period is expected to be for more than
twenty-four hours then the Company shall inform those residents
and businesses affected by the emergency of the reasons for the
emergency and the expected duration.
(32) Except in an emergency, the Company shall give at least 24 hours
prior notice in writing to the LPA of any proposed operation of
emergency pressure relief valves or similar equipment. So far as is
reasonably practicable any such operation should take place
between the hours of 09.00 and 17.00 hours and on a day other
than a Saturday, Sunday, Bank Holiday or public holiday.
Reason: To ensure the proper control of noise during the operation
of the Development.
Noise Complaints Procedure
(33) If a local resident or local business complains direct to the
Company or the Company has been notified in writing by the LPA
of any complaint about noise generated by the construction and/or
operation of the Development the Company shall carry out
investigations to establish the justification, or otherwise, of the
complaint, the likely cause and possible remedial measures. A
written report to the complainant, copied to the LPA, shall be made
as soon as reasonably practicable following the investigation and/or
remedial work. The Company shall keep all such reports in
an appropriate file and such file shall be made available to the LPA
on request.
Reason: To ensure that any complaints on the grounds of noise are
properly dealt with so as to reduce the impact of the Development
on local residents.
SuDS
![Page 19: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/19.jpg)
(34) Except for the Permitted Preliminary Works, the commencement of
the Development shall not take place until there has been submitted
to, approved in writing by, and deposited with the LPA, in
consultation with the Environment Agency, a scheme for SuDS.
Such SuDS shall include the details and measures contained in the
document entitled “Gateway Energy Centre Supplementary Flood
Risk Assessment December 2010” and identified on FRA FIGURE
1 of that document and be put in place in accordance with the
approved scheme.
Reason: To ensure that a sustainable drainage system is put in
place.
Prevention of Contamination of Watercourses
(35) Except for the Permitted Preliminary Works, the commencement of
the Development shall not take place until there has been submitted
to, approved in writing by, and deposited with the LPA, in
consultation with the Environment Agency, a scheme showing the
method and working of drainage facilities on the Site. Such
facilities shall be put in place in accordance with the approved
scheme.
(36) The scheme referred to in Condition (35) shall include:
(i) measures to ensure that no leachate or any contaminated
surface water from the part of the Site relevant to the
particular phase shall be allowed at any time to enter directly
or indirectly into any watercourse or underground strata or
onto adjoining land;
(ii) provision for trapped gullies in car parks, hardstandings and
roadways;
(iii) measures to ensure that all foul sewage drains to an approved
foul sewerage and/or sewage disposal system, or be removed
to an off-Site licensed facility for treatment;
(iv) provisions to distinguish between temporary and permanent
parts of the works; and
(v) phasing of works.
![Page 20: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/20.jpg)
(37) Any surface water contaminated by hydrocarbons which are used
during the construction of the Development shall be passed through
oil/grit interceptor(s) prior to being discharged to any public sewer
or watercourse or to any other surface water disposal system
approved by the Environment Agency.
(38) All facilities required for the storage of hydrocarbons, process
chemicals or similar liquids which are used during the construction
of the Development must be sited on impervious bases and
surrounded by impervious bund walls. The size of the bunded
compound(s) shall be at least equivalent to the capacity of the
largest tank plus 10%. All filling points, vents and sight glasses
must be located within the bund and there must be no drain through
the bund floor or walls.
(39) All bunded compound(s) referred to in Condition (38) containing
acids, alkalis or sulphides in addition to being contained in suitable
facilities shall have appropriate protective lining applied to the
inner walls of the bunds.
(40) Any storage facility to which Conditions (38) or (39) refer shall be
completed in accordance with the requirements of those Conditions
before being brought into use.
Reason: To ensure proper drainage of the Site and that proper
containment facilities are built.
Flood Risk
(41) The Development shall be carried out in accordance with the
details and measures contained in the document entitled “Gateway
Energy Centre Supplementary Flood Risk Assessment December
2010” and shall include for the provision of safe route(s) into and
out of the Site and for any place of refuge for Site staff or visitors
to be provided at a minimum of 3.7 metres AOD, the details of
which shall be submitted to and approved in writing by the LPA.
Reason: To ensure there is no increase in the risk of flooding, both
at the Site and to third parties, as result of the Development, and to
accord with Planning Policy Statement 25 “Development and
Flood Risk”.
Archaeology
(42) The commencement of the Development shall not take place until
there has been submitted to, approved in writing by, and deposited
with the LPA, a scheme of archaeological investigation and an
associated implementation programme.
(43) The scheme approved pursuant to Condition (42) shall provide for:
![Page 21: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/21.jpg)
(i) archaeological field evaluation works in accordance with a
specification and written timetable approved by the LPA;
(ii) archaeological field evaluation works to be completed and
reported on prior to finds of national importance being
evaluated and, where practicable, preserved in
situ; and
(iii) phasing of works.
(44) Any further investigations and recording of such finds as are
considered necessary by the LPA shall be undertaken prior to the
construction of any part of the Development on that part of the Site
where such finds are identified, and in the case of finds of national
importance in accordance with the phasing of works approved
pursuant to Condition (43)(iii), unless otherwise except in so far as
approved in writing by the LPA.
Reason: To allow the surveying of the site for archaeological
artefacts and the recovery of any important archaeological
discovery before construction of the main Development begins.
Contamination
(45) The commencement of the development shall not take place until a
scheme to deal with the risks associated with contamination of the
Site has been submitted to, approved in writing by, and deposited
with the LPA. The scheme shall include details of the following
matters:
(a) a preliminary risk assessment identifying · all previous uses
potential contaminants associated with those uses
a conceptual model of the site indicating sources, pathways
and receptors
potentially unacceptable risks arising from contamination at
the site;
(b) a site investigation scheme based on (a) to provide
information for an assessment of the risk to all receptors that
may be affected, including those off-Site; and
(c) the results of the Site Investigation and risk assessment
pursuant to (b) and a method statement based on those results
giving full details of the remediation measures required, how
they are to be undertaken and the timing of the remediation
measures; and
![Page 22: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/22.jpg)
(d) a verification plan providing details of the data that will be
collected in order to demonstrate that the works set out in (c)
are complete and identifying any requirements for longer-
term monitoring of pollutant linkages, maintenance and
arrangements for contingency action.
(46) The measures approved pursuant to Condition (45) shall be
adhered to except in so far as any variation to them has been
approved in writing by the LPA.
(47) Prior to commencement of the main Development, a verification
report demonstrating completion of the works set out in the
approved remediation strategy pursuant to Condition (45)(c) and
the effectiveness of the remediation shall be submitted to and
approved, in writing, by the LPA. The report shall include results
of sampling and monitoring carried out in accordance with the
approved verification plan to demonstrate that the Site remediation
criteria have been met. It shall also include any plan for longerterm
monitoring of pollutant linkages, maintenance and arrangements
for contingency action, as identified in the verification plan, and for
the reportng of this to the LPA.
(48) Reports on monitoring, maintenance and any contingency action
carried out in accordance with a long-term monitoring and
maintenance plan shall be submitted to the LPA in accordance with
that plan. On completion of the monitoring programme a final
report demonstrating that all long-term Site remediation criteria
have been met and documenting the decision to cease monitoring
shall be submitted to and approved in writing by the LPA. In the
event that the verification report to be submitted pursuant to
Condition (47) indicates that the remediation was not effective the
Company shall submit a programme of contingency action for
approval in writing by the LPA.
(49) In the event that contamination is found at any time when carrying
out the approved development that was not previously identified
under Condition (45), work on that part of the Site shall cease
immediately and shall be reported in writing to the LPA. A Desk
Study, Site Investigation, Risk Assessment and where necessary a
Remediation Strategy in respect of such contamination must be
undertaken and submitted to and approved in writing with the LPA
prior to the resumption of work on that part of the Site.
Reason: To ensure that contamination is controlled and not allowed
to cause harm to the health of human beings nor impact on the
integrity of environmentally sensitive areas nor pose a risk to
controlled waters.
![Page 23: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/23.jpg)
Landscaping
(50) Except for Permitted Preliminary Works the commencement of
Development shall not take place until a scheme of landscaping,
which shall take into account sections 11 and 12 of the document
entitled “ Gateway Energy Centre Environmental Statement
Volume 1 February 2010” has been submitted to and approved in
writing by the LPA.
(51) The scheme referred to in Condition (50) shall deal with the
general provision of screening, shrub and tree planting and grassed
areas and means of integrating the Development with the
surrounding landscape and shall include details of the following
matters:
(i) planting (which should be mainly of locally native species,
ideally with a local provenance);
(ii) management of existing and new planted areas including
protection of existing planting during construction;
(iii) restoration of areas affected by construction works;
(iv) details of grass seed mix for areas of the Site to be restored to
grassland;
(v) details of the height, type, size and species of the shrubs and
trees to be planted; and
(vi) phasing of works included in the scheme.
(52) The landscaping and planting, including grass sowing, shall take
place in accordance with the phasing of works referred to in
Condition (51)(vi) and no later than the appropriate planting or
sowing season following the completion of the construction of the
Development and shall be carried out in accordance with the
scheme approved under Condition (50), unless any variation has
been approved in writing by the LPA. Any trees or shrubs,
including hedges, which die, become seriously damaged or
diseased or are removed within five years from the date of planting
shall be replaced in the next planting season with others of a
similar size and species, unless otherwise approved in writing by
the LPA.
(53) Upon completion of the scheme of landscaping approved pursuant
to Condition (50) a schedule of landscape maintenance and/or a
landscape management plan shall be submitted for approval in
writing by the LPA. The measures contained in the approved
schedule and/or plan shall be adhered to throughout the operation
![Page 24: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/24.jpg)
of the Development subject to any variation that has been approved
in writing by the LPA.
Reason: To ensure proper landscaping for the Development.
Biodiversity Enhancement Measures
(54) The commencement of the Development shall not take place until a
scheme of Environmental Enhancement Measures (incorporating a
management plan), which shall take into account section 12 of the
document entitled “Gateway Energy Centre Environmental
Statement Further Information Document December 2010, has
been submitted to and approved in writing by the LPA, in
consultation with Natural England and the Environment Agency.
The approved measures shall be adhered to in accordance with the
approved scheme except in so far as any variation to them has been
approved in writing by the LPA, in consultation with Natural
England and the Environment Agency.
Reason: To ensure that any adverse impact on wildlife is properly
compensated for.
Air Pollution Monitoring
(55) The commissioning of the Development shall not take place until
there has been submitted to, approved in writing by and deposited
with the LPA a scheme for the monitoring of nitrogen oxide (NOx)
in the area. The scheme shall include the measurement location or
locations from which air pollution will be monitored, the
equipment and methods to be used and the frequency of
measurement. The scheme shall provide for the first measurement
to be taken not less than 24 months prior to the commissioning of
the Development and for the final measurement to be taken not
more than 24 months after the Development is commissioned. The
Company shall work with the LPA, supplying full details of the
measurements obtained in accordance with the scheme, as soon as
possible after they become available, and ensure that such
monitoring is integrated within the LPA's air quality strategy. In
addition, the Company shall support the annual modelling for the
air quality review and assessment process whilst the Development
is in operation.
Reason. In the interest of air quality.
Decommissioning Management Plan for the Site
(56) Within 6 months of the Development ceasing to be used for the
purposes of electricity generation the Company shall submit to the
LPA, for approval in writing, a scheme for the demolition of the
Development.
![Page 25: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/25.jpg)
(57) The scheme referred to in Condition (56) shall include:
(i) details of all structures and buildings which are to be
demolished;
(ii) details of the means of removal of materials resulting from
the demolition;
(iii) the phasing of the demolition and removal;
(iv) details of any proposed restoration works; and
(v) the phasing of the restoration works.
Reason: To ensure the Site is not allowed to become derelict after
the cessation of electricity generation.
Use of Waste Heat
(58) The commissioning of the Development shall not take place until
sufficient plant and pipework has been installed to facilitate the
future supply of heat to the boundary of the Site under Condition
(59) at a later date if opportunities to do so are identified pursuant
to Condition (59).
Reason: To ensure that waste heat is available for use to the
benefit of the local domestic, commercial and industrial users
when the demand arises.
(59) Prior to the commissioning of the Development, an updated CHP
Feasibility Review assessing potential opportunities for the use of
heat from the Development shall be submitted to, approved in
writing by, and deposited with, the LPA. This shall provide for the
ongoing monitoring and full exploration of potential opportunities
to use heat from the Development as part of a Good Quality CHP
scheme (as defined in the CHPQA Standard issue 3), and for the
provision of subsequent reviews of such opportunities as necessary.
Where viable opportunities for the use of heat in such a scheme are
identified, a scheme for the provision of the necessary plant and
pipework to the boundary of the site shall be submitted to,
approved in writing by, and deposited with, the LPA. Any plant and
pipework installed to the boundary of the Site to enable the use of
heat shall be installed in accordance with the approved details.
Reason: To ensure that waste heat is available for use to the
benefit of the local domestic, commercial and industrial users
when the demand arises.
![Page 26: Our ref: 01 · 2019-11-13 · our ref: 01.08.10.04/462c variation of consent under section 36c of the electricity act 1989 construction and operation of a combined cycle gas fired](https://reader033.vdocuments.net/reader033/viewer/2022042005/5e6fc1d7e282525c3802ec85/html5/thumbnails/26.jpg)
Immaterial Changes to Conditions by the Council
(60) Where the words, “unless otherwise agreed in writing by the
Council” or “with the prior written approval of the Council”
appear, such agreement or approval may only be given in relation
to immaterial changes where it has been demonstrated to the
satisfaction of the Council that the agreement or approval is
unlikely to give rise to any materially new or materially different
environmental effects from those assessed in the environmental
statement.
Reason: To make clear that where provision is made for the
Council to agree to variations to the application of planning
conditions, the scope of any such variations will be limited to
immaterial changes.
Environmental Statement
(61) The environmental effects of the Development must not exceed those
assessed in the Environmental Statement.
Reason: To ensure that the development consented has no greater
environmental impact than that considered in the original
application dated 26 February 2010, December 2010, as varied by
the application dated 12August 2014 4 August 2011 and the
variation application of 25 February 2016 7 May 2015.
Date: [Insert date of Variation]
Giles Scott
Head Development
Consents and Planning
Reform Department of
Energy and Climate
Change