page 16 • november 27, 2019 • www ...archive.constructionequipmentguide.com › web_edit...nov...

1
Page 16 • November 27, 2019 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide With the excess decay, the amount of chipping was limited to small areas to keep structural integrity of the bridge while maintaining traffic above.” “The job was challenging because of the vol- ume of traffic and limited access for pier rehabil- itation work,” said Scott Stevens, R.S. Audley bridge engineer. “We used an Anderson Hydra Platform under bridge access device, which was more flexible than a crane-mounted man basket, which we’ve used before.” The company also is using a Grove RT760E rough-terrain crane and a Blast It All Mfg. Workhorse Skid Steer Scraper. Vaughan said the pier work on the southbound bridge is complete and the northbound bridge should be completed by Thanksgiving. The top decks of both bridges will be started in April, 2020 and should be completed by September. The bridges were built in 1958 and widened and re-decked in 1991, according to Jason Tremblay, senior project engineer of NHDOT’s Bureau of Bridge Design. He said an inspection of the bridges showed that expansion joints were failing, which set up the current job. “We chipped away to replace sections piece by piece so as not to degrade the extension joints,” Vaughan said. “The piers have safety devices built in, so there is no danger to traffic.” The water leak from the expansion joints caused cracking along the lower piers. To extend the life of the bridges, the expansion joints needed be replaced, the concrete deck improved and proper bridge piers installed. “It should be 20-plus years before we have to preserve the bridge again,” Tremblay said. CEG R.S. Audley Leads Bridge RehabilitationProject in N.H. The work is being done on the Route I-293 northbound and southbound bridges over the Merrimack River in Bedford and Manchester. BRIDGES from page 1 R.S. Audley of Bow, N.H., is the contractor on the $4.7 million project. The old joints had been leaking for some time with substantial decay in the concrete. The water leak from the expansion joints caused cracking along the lower piers. To extend the life of the bridges, the expansion joints needed be replaced, the concrete deck improved and proper bridge piers installed. The company also is using a Grove RT760E rough-ter- rain crane and a Blast It All Mfg. Workhorse Skid Steer Scraper. The pier work on the southbound bridge is complete and the northbound bridge should be completed by Thanksgiving.

Upload: others

Post on 28-Jan-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Page 16 • November 27, 2019 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

    With the excess decay, the amount of chippingwas limited to small areas to keep structuralintegrity of the bridge while maintaining trafficabove.”

    “The job was challenging because of the vol-ume of traffic and limited access for pier rehabil-itation work,” said Scott Stevens, R.S. Audleybridge engineer. “We used an Anderson HydraPlatform under bridge access device, which wasmore flexible than a crane-mounted man basket,which we’ve used before.”

    The company also is using a Grove RT760Erough-terrain crane and a Blast It All Mfg.Workhorse Skid Steer Scraper.

    Vaughan said the pier work on the southboundbridge is complete and the northbound bridgeshould be completed by Thanksgiving. The topdecks of both bridges will be started in April,2020 and should be completed by September.

    The bridges were built in 1958 and widenedand re-decked in 1991, according to JasonTremblay, senior project engineer of NHDOT’sBureau of Bridge Design. He said an inspectionof the bridges showed that expansion joints were failing,which set up the current job.

    “We chipped away to replace sections piece by piece so asnot to degrade the extension joints,” Vaughan said. “Thepiers have safety devices built in, so there is no danger totraffic.”

    The water leak from the expansion joints caused crackingalong the lower piers. To extend the life of the bridges, theexpansion joints needed be replaced, the concrete deckimproved and proper bridge piers installed.

    “It should be 20-plus years before we have to preserve thebridge again,” Tremblay said. CEG

    R.S. Audley Leads Bridge Rehabilitation Project in N.H.

    The work is being done on the Route I-293 northbound and southbound bridges over the Merrimack River in Bedfordand Manchester.

    BRIDGES from page 1

    R.S. Audley of Bow, N.H., is the contractor on the $4.7million project.

    The old joints had been leakingfor some time with substantialdecay in the concrete.

    The water leak from the expansion joints causedcracking along the lower piers. To extend the life ofthe bridges, the expansion jointsneeded be replaced, the concretedeck improved and properbridge piers installed.

    The company also is using a Grove RT760E rough-ter-rain crane and a Blast It All Mfg. Workhorse Skid SteerScraper.

    The pier work on the southbound bridge is complete and the northboundbridge should be completed by Thanksgiving.