Social Monitoring Report
Semestral Report July 2013
PAK: MFF Power Transmission Enhancement
Investment Program Tranche 2
Prepared by M/s Building Standards Consultants, Lahore for the National Transmission &
Despatch Company Limited Pakistan, Islamic Republic of Pakistan and the Asian Development
Bank.
ABBREVIATIONS
AP EA GOP G/S IA LAR MFF NTDC
– – – – – – – –
affected executing agency Government of Pakistan grid station implementing agency land acquisition and resettlement multitranche financing facility National Transmission & Despatch Company Limited Pakistan
SRP – subproject resettlement plan T/L – transmission line
MEASURES
kv MVA
– –
kilovolt mega volt ampere
This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
National Transmission & Despatch Company Limited (NTDC) Pakistan
MONITORING OF ENVIRONMENTAL AND SOCIAL SAFE GUARD MATTERS OF SUBPROJECTS OF NTDC
NETWORK EXPANSION PROGRAM TRANCHE-II
ID TERM REPORT Social Safeguards Compliance
Implementation of Resettlement Plans
By
M/s Building Standards Consultants, Lahore.
July - 2013
Building Standards Geo Environmental and Social Consulting 5-B/H-Block Commercial, Architects Engineers Housing Scheme, Near
ShaukatKhanamHospitalLahore. Ph: 042-35034235-6, 35954850
1
Mid Term Report Social Safeguard Compliance
External Social Monitoring
Ref. No.: BS/130717-001 Date: 17/07/13
TABLE OF CONTENTS
Sr.# DESCRIPTION PAGE #
1.0 Introduction 03
1.1 Background 03
2.0 Tranche-2 Subprojects and Status of Implementation 03
3.0 220Kv Okara G/S & TL 08
3.1 Land Acquisition and other Impacts 08
3.2 Status of Compensation Payments 08
3.3 Findings of External Monitoring: Gaps or Weaknesses and
Recommendations 08
4.0 220Kv Toba Tek Singh G/S & T/L 08
4.1 Land Acquisition and other Impacts 09
4.2 Status of Compensation Payments 09
4.3 Findings of External Monitoring: Gaps or Weaknesses and
Recommendations 09
5.0 New 500Kv D.G Khan Grid Station with Transmission Line 09
5.1 Land Acquisition and other Impacts 09
5.2 Status of Compensation Payments 10
5.3 Findings of External Monitoring: Gaps or Weaknesses and Recommendations 10
6.0 New 200kv Rohri Grid Station and Line Bay Extension at 220Kv Shikarpur G/Station with Associated T/Lines 10
6.1 Land Acquisition and other Impacts 10
6.2 Status of Compensation Payments 11
6.3 Findings of External Monitoring: Gaps or Weaknesses and Recommendations 11
7.0 132Kv New Rohri — Ghambat T/1. 11
7.1 Land Acquisition and other Impacts 11
7.2 Status of Compensation Payments 11
7.3 Findings of External Monitoring: Gaps or Weaknesses and
Recommendations 12
2
Mid Term Report Social Safeguard Compliance
External Social Monitoring
•
TABLE OF CONTENTS
Sr.# DESCRIPTION PAGE #
8.0 Jarwar — Sadiqabad 132Kv T/L 12
8.1 Land Acquisition and other Impacts 12
8.2 Status of Compensation Payments 12
8.3 Findings of External Monitoring: Gaps or Weaknesses and
Recommendations 12
9.0 Conclusions 13
10.0 Recommendations 14
Appendices 15
•
2
Mid Term Report Social Sokguard l'ompliance
kxlernal Social Mointormg
1. INTRODUCTION:
This is the Mid-term external monitoring report of social safeguards and
implementation of resettlement plans of the sub-projects of Tranche-II. As required by
ADB's safeguard policy on Involuntary Resettlement, this monitoring report has been
prepared by the Building Standards Pvt. Ltd, the monitoring firm of the project, for the
National Transmission and Dispatch Company (NTDC), the project executing agency
(EA). The report covers the status of payment of compensation to the affectees of
subprojects of Tranche II of ADB funded Multi-tranche Financing Facility (MFF) of NTDC
investment program.
The following paragraphs provide brief background of the subprojects of Tranche 2
which have impacts of land acquisition and resettlement, and results of external
monitoring of the implementation of resettlement plans including any gaps or
weaknesses in implementation and recommendations given to ensure full
implementation of resettlement plans to overcome all such gaps and weaknesses.
1.1 Project Background
The Government of Pakistan (GOP) received funding from ADB for implementing the
Power Transmission Enhancement Investment Program (the Program) which is to be
executed through a "Multi-tranche Financial Facility (MFF)" subdivided into 4 tranches
and with the Ministry of Water and Power and the National Transmission and Dispatch
Company (NTDC) as the Executing Agency (EA) and the Implementing Agency (IA)
respectively. Each tranche constituted a project but included multiple subprojects
having varying scope of work as construction of new substations, extension and
augmentation/up-gradation of existing sub stations and installation of transmission
lines. This monitoring report covers the entire Tranche 2 (10 subprojects). More details
are given below.
2. TRANCHE-2 SUBPROJECTS AND STATUS OF IMPLEMENTATION
220/132kV 4 —
220kV Dia 6 - 132
kV LineBays in and
out of existing
Yousafwala -
Sarfraz Nagar 220
kV D/C
Transmission Line
In and out of
existing
Nishatabad -
Multan 220 kV
D/C Transmission
Line at T.T Singh
Category B
Requires land
acquisition and
has
resettlement
impacts
Category B
Requires land
acquisition and
has
resettlement
impacts
30-05-11
11-10-10
Mid Term Report Social Safeguard Compliance
External Social Monitoring
As explained above, Tranche 2 comprise of 10 subprojects with scope of work varying
from extension and augmentation of existing substations/grid stations and construction
of new grid stations and installation of transmission lines. As shown in the below table,
4 subprojects fall in category C and did not require any resettlement monitoring work.
However the remaining 6 projects fall in category B and required implementation and
monitoring of resettlement plans. The status of their implementation is as under:
Table 1: Tranche-IISubprojects and Implementation Status
Sr.
No.
Category of
subproject
Date of
Contract
award Project Scope of Work Date of commissioning
March, 12
1
2
New 220 Kv
Okara Grid
Station with
Transmission
Line
New 220 KV
Toba Tek
Singh Grid
Station with
Tra nsmission
Line
ADB approved SRP on 5-
12-2011 and SRP has
been implemented fully.
All APs of TL have been
compensated fully, The
TL has been completed
and the payment
completion report
submitted to ADB on 31-
1-2013
December, 11
ADB approved SRP on
01-04-2011 and SRP has
been implemented fully.
All APs of TL have been
compensated fully, The
TL has been completed
and the payment
completion report
submitted to ADB on 31-
1-2013
Category B
Requires land
acquisition and
has
19-03-12 1
New 500 KV
D.G Khan Grid
3 Station with
Transmission
Line
In and out of
existing Guddu-
Muzaffargarh 500
kV Transmission
Line at DG Khan
December,13
ADB approved SRP in
November 1, 2012 and
SRP is Under
implementation.
4
Mid Term Report Social Sali!guard l'ompliance
External Social Monitoring
ew 220KV
Rohri Grid
Station and
Line Bay
Extension at
220 KV
Shikarpur
G/station with
associated
T/Lines for
dispersal of
power from
IPPs (Engro
Energy &
Dharki CCPP
132 kv New
Rohri-
Ghambat T/L
Rohri New at
Engro CCPP 2.
220kV D/C Rohri
New Shikarpur
T/Line
1. 220kV D/C
Rohri New -
Dharki CCPP &
220kV D/C T/Line
for In & out of
Dharki CCPP
Date of Category of
subproject Contract
award
resettlement
impacts
Category B
Requires land
acquisition and
has
resettlement
impacts
Category B
Requires land
acquisition and
has
resettlement
impacts
Date of commissioning
27-06-12
ADB approved SRP in
December 2007 and SRP
is under implemented.
27-06-12
ESIC has submitted the
updated SRP to ADB on
27-02-2013. SRP is
under implementation.
Dec 2009
Jarwar —
Sadiq a bad
132 kv line TL
ADB approved SRP in
December 2007 and SRP
has been implemented
fully.All APs of TL have
been compensated fully,
The TL has been
completed and the
payment completion
report submitted to ADB
on 28-10-2010
132 kV D/C Jarwar
— Sadiqabad
Transmission Line
Category B
Requires land
acquisition and
has
resettlement
impacts
18-08-11
1
18-08-11
TL
20-08-8
4
5
6
Addition of
500/220 kV
600 MVA,
Auto -
transformer
Bay at Ghazi
1x600 MVA
(3x200),
500/220kV
Category C
No land
acquisition and
resettlement
(LAR) impacts
7 30-05-11 29-03-12
5
9
Barotha Grid station
New Loralai
220 kv Sub-
Station
Installation of SVC at 220 kV
New Kot Lakhpat
Gridstation
Lahore
Procurement
of Tools,
10 i Testing and
Measuring Equipment
Scope of Work
2x250 MVA,
220/132kV 1x6.3
MVA, 132/11kV 2
— 220kV Dia 6 —
132kV Line Bays
Installation of
450MVAR
Date of Contract
award
Category C
No land
acquisition and 29-10-10
resettlement
(LAR) impacts
Category C No land
acquisition and
resettlement
(LAR) impacts
Category C No land
acquisition and
resettlement (LAR) impacts
Date of commissioning
02-11-12
17-01-2014
Category of subproject
26-07- 2012
As above table indicates, there were only 6 subprojects in Tranche 2 which needed
payment of compensation and which had temporary impacts related with crops and
removal of trees. The overall status of implementation of resettlement plans of these 6
subprojects has been explained below:
Table 2: Overall status of payments
Sr.
No Subproject APs
Types of Impacts
Total Tower Land Crops Tree
1
New 220 Kv Okara
Grid Station with
Transmission Line
Total 59 33 nil 319 k 283
Paid 59 33 nil 319 k 283
Unpaid nil nil nil nil nil
2
New 220 KV Toba
Tek Singh Grid
Station with
Transmission Line
Total 18 12 nil 20 k 7
Paid 18 12 nil 20 k 7
Unpaid nil nil nil nil nil
3 New 500 KV D.G
Khan Grid Station
Total 138 82 nil 1110 k 150
Paid Compensation payments for foundation work
have been made in April-May 2013 to all
6
Mid Term Report Social Safeguard Compliance
External Social Monitoring
Mid Term Report Social safeguard 'amp! iiame
Erlernal St. Momionng
with Transmission
Line
affetees.
Unpaid The compensation payments for errection and stringing work are being assessed and will be
paid to APs by end of Nov.2013
4
New 220KV Rohri
Grid Station and
Line Bay Extension
at 220 KV
Shikarpur G/station
with associated
T/Lines for
dispersal of power
from IPPs (Engro
Energy & Dharki
CCPP)
Total 1279 878 6 1403 k 292
Paid 1252 860 6 1380 k 292
Unpaid 27 18 23 k nil
5 132 kv New Rohri-
Ghambat T/L
Total 1264 380 nil 1059 k 1996
Paid 1024 295 nil 802 1845
Unpaid 240 95 nil 257 151
6 Jarwar — Sadiqabad
132 kv line TL
Total 180 297 nil 3202 k 98
Paid 180 297 nil 3202 k 98
Unpaid nil nil nil nil nil
7 Total
Total 2938 1682 6 7113 2826
Paid 2533 1200 6 5723 2525
Unpaid 405 482 nil 1390 301
The table shows that:
• A total of 405 out of 2938 APs (13.7%) are still unpaid.
• Of the total unpaid 8.16% are from New Rohri-Ghambat TL, 0.91% from New
Rohri- Shikarpurand 4.7% are from 500KV D.G.Khan IN/OUT T/L.
• The work for the above mentioned 3 Sub-projects was scheduled to be
completed by (New Rohri-Ghambat 27-06-2012, New Rohri- Shikarpur -27-06-
2012and 500KV D.G.Khan IN/OUT T/L by Dec. 2013.
• However the payments for the remaining towers of New Rohri-Ghambat and
New Rohri- Shikarpur will be completed by end of Sep. 2013, while on 500KV
D.G.Khan IN/OUT T/L the payments will be completed by the end of December
2013.
7
Mid Term Report Social Safeguard Compliance
External Social Monitoring
• 220kv Okara G/S & T/L, 220kv T.T.Singh and 132 kv Jarwar-Sadiqabad
Subprojects have been completed and all APs have been paid and
compensations are all cleared and compensation payment reports have been
submitted to ADB on 28-10-2010 and on 31-01-2013 respectively.
3. SUBPROJECT: 220KV OKARA G/S & T/L
The 220kv Okara G/S &TL subproject includes the construction of a 220KV Grid Station
and transmission line (TL) that will pass through parts of different villages. TL required
33 towers to be erected.
3.1 Land Acquisition and other Impacts
The external monitors reviewed the resettlement plan and visited the project site in
May 2013. The project impacts included Crops and Trees. In total these impacts had
affected 59 people which included 29 APs affected by towers, 20 by crops and 10 by
trees. Payment status is given below:
3.2 Status of Compensation Payments
Project Impacts Qty/nos.
ff affected Total APs
No. of APs Remarks
Paid Unpaid
Land nil nil nil nil nil
Structures nil nil nil nil nil
Trees 283 10 10 nil Fully paid
Crops 319 k 49 49 nil Fully paid
Total All paid
3.3 Findings of External Monitoring: Gaps or Weaknesses and Recommendations
The sub-project has been completed and all compensations are cleared. There is no outstanding
issue.
4. SUBPROJECT: 220KV TOBA TEK SINGH G/S & T/L
The 220kv Toba Tek Singh G/S & T/L subproject includes the construction of a 220kV G/S
and transmission line (TL) that will pass through parts of different villages. TL required
12 towers to be erected.
8
Mid Term Report Social Suleguemi Compliance
Erlenwl Social Mon/Wring
4.1 Land Acquisition and other Impacts
The external monitors reviewed the resettlement plan and visited the project site in
May 2013. The project impacts included Crops and Trees. In total these impacts had
affected 18 people which included 12 APs affected by towers, 4 by crops and 2 by trees.
Payment status is given below:
4.2 Status of compensation payments
Project Impacts Qty/nos.
affected Total Aps
No. of APs Remarks
Paid Unpaid
Land nil Nil nil nil nil
Structures nil Nil nil nil nil
Trees 7 2 2 nil Fully paid
Crops 20 k 16 16 nil Fully paid
Total 18 18 nil All paid
4.3 Findings of External Monitoring: Gaps or Weaknesses and Recommendations
The sub-project has been completed and all compensations are cleared. There is no
outstanding issue.
S. SUBPROJECT: NEW 500KV D.G KHAN GRID STATION WITH TRANSMISSION LINE
The New 500 KV D.G Khan Grid Station with Transmission Line subproject includes the
construction of a 500 kV G/S and transmission line (IL) that will pass through parts of
different villages. TL required 82 towers to be erected.
5.1 Land Acquisition and Other Impacts
The external monitors reviewed the resettlement plan and visited the project site in
May 2013. The project impacts included Crops and Trees. In total these impacts had
affected 138 people which included 75 APs affected by towers, 39 by crops and 24 by
trees. . Payment status is given below:
9
Mid Term Report Social Safeguard Compliance
External Social Monitoring
•
5.2 Status of Compensation payments
Project Impacts Qty/nos. affected
Total APs No. of APs
Remarks Paid Unpaid
Land nil nil nil nil nil
Structures nil nil nil nil nil
Trees 150 24 138 nil The
compensation payments for
foundation work
have been made in April-May
2013 to all
affetees.
Crops 1110 k 114 138 nil
Total 138 138 nil paid
5.3 Findings of External Monitoring: Gaps or Weaknesses and Recommendations
The sub-project is under implementation. The compensation payments for foundation
work have been made in April-May 2013 to all affetees. There is a need to accelerate
the process of compensation assessment and payments for stringing work should be
complete by end of July, 2013.
6. SUBPROJECT: NEW 220KV ROHRI GRID STATION AND LINE BAY EXTENSION AT
220KV SHIKARPUR G/STATION WITH ASSOCIATED MINES
The subproject includes the construction of a New 220KV Rohri Grid Station and Line
Bay Extension at 220 KV Shikarpur G/station with associated T/Lines that will pass
through parts of different villages. TL required 878 towers to be erected.
6.1 Land Acquisition and other Impacts:
The external monitors reviewed the resettlement plan and visited the project site in
May 2013. The project impacts included Crops and Trees. In total these impacts had
affected 1279 people which included 768 APs affected by towers, 6 by land, 331 by
crops and 174 by trees. . Payment status is given below:
1 0
Mid Term Report Social Safeguard ('ompliance
External Social Monitoring
6.2 Status of Compensation Payments:
Project Impacts Qty/nos. affected
Total APs No. of APs
Remarks Paid Unpaid
Land 62 Acres 6 6 nil Fully paid Structures nil nil nil nil Fully paid
Trees 292 174 174 nil Fully paid Crops 1403 k 1099 1072 27 Partially paid Total All paid
6.3 Findings of External Monitoring: Gaps or Weaknesses and Recommendations
The sub-project is under implementation. The assessment of compensation payments
for stringing work is in process. There is a need to accelerate the process of
compensation assessment and payments for stringing work should be complete by end
of July, 2013.
7. SUBPROJECTS: 132KV NEW ROHRI-GHAMBAT T/L:
The subproject includes the construction of a 132 kV transmission line (TL) that will pass
through parts of different villages. TL required 380 towers to be erected.
7.1 Land Acquisition and other Impacts
The external monitors reviewed the resettlement plan and visited the project site in
May 2013. The project impacts included Crops and Trees. In total these impacts had
affected 1264 people which included 297 APs affected by towers, 975 by crops and 977
by trees. Payment status is given below:
7.2 Status of Compensation Payments
Project Impacts Qty/nos.
affected Total APs
No. of APs Remarks
Paid Unpaid Land nil nil nil nil nil
Structures nil nil nil nil nil Trees 1996 977 865 112 Partially paid Crops 1059 k 975 847 128 Partially paid Total All paid
11
Mid Term Report Social Safeguard Compliance
External Social Monitoring
7.3 Findings of External Monitoring: Gaps or Weaknesses and Recommendations
The sub-project is under implementation. The assessment of compensation payments
for stringing work is in process. There is a need to accelerate the process of
compensation assessment and payments for errection work should be complete by
end of July, 2013.
8. SUBPROJECT: JARWAR — SADIQABAD 132KV TL
The subproject includes the construction of a 132 kV transmission line (TL) that will pass
through parts of different villages. TL required 297 towers to be erected.
•
8.1 Land Acquisition and other Impacts
The external monitors reviewed the resettlement plan and visited the project site in
May 2013. The project impacts included Crops and Trees. In total these impacts had
affected 180 people which included 116 APs affected by towers, 34 by crops and 30 by
trees. Payment status is given below:
8.2 Status of Compensation Payments
Project Impacts Qty/nos.
ff affected Total APs
No. of APs Remarks
Paid Unpaid
Land nil nil nil nil nil
Structures nil nil nil nil nil
Trees 98 30 30 nil Fully paid
Crops 3202 k 150 150 nil Fully paid
Total 180 180 All paid
8.3 Finding of External Monitoring: Gaps or Weakness and Recommendations
The sub-project has been completed and all compensations are cleared. There is no
outstanding issue.
Land Acquisition:The land was acquired by land acquisition collector by Copy of the
instruction memo is attached as Appendix 4.
Action Recommendation:Transmission Line: Payment to APs. During fresh
consultations and interviews with APs in May 2013, the external monitors found that
total 3 out of 6 sub-projects (220kv Okara. 220kv Toba Tek Singh and 132kv Jarwar-
12
Mid Term Report Social Safeguard Compliance
External Social Monitoring
Sadiqabad) have been completed and compensation payments are all cleared. The
remaining 3 sub-projects (500kv D.G.Khan, 220KV New Rohri-Shikarpur and 132KV
Rohri-Ghambat are under implementation and payment process is still going on.
Actions Taken: The issue regarding delay in the payments process was raised with ESIC-
PMU during the consultations. The ES1C consulted with the concerned APs and the PIU.
PIU (XEN SUKKUR) informed that the demand for compensation payments for the sub-
projects i) 200kv New Rohri-Shikarpur and ii) 132KV Rohri-Ghambat has been submitted
to Chief Engineer EHV-II office in April 2013 for release of payments. The approval
process will take almost 6 months and probably the payments will be made to affectees
by the end of Oct. 2013. The sub-project of 500kv D.G.Khan IN/OUT as the process of
towers errection and APs identification is ongoing. The compensation payments for
foundation work have been complete and PIU NTDC agreed that the second installment
of compensation payment for tower erection will be paid to APs by the end of August,
2013.
9. CONCLUSIONS
The external monitoring indicates that SRP implementation for 3 subprojects including
220kv Okara, T.T.Singh and 132kv Jarwar-Sadiqabad are 100% complete and there are
no outstanding payments and hence no further need for external monitoring. The
project completion reports for Jarwar-Sadiqabad was submitted to ADB on 28-10-2010
and for Okara and T.T.Singh the reports were also submitted to ADB on 31-1-2013.
The subproject 200kv New Rohri-Shikarpur and 132KV Rohri-Ghambat all APs have been
identified and assessment has been made and submitted for approval. 500KV D.G.Khan
compensation payments for foundation work have been paid to all affectees. Now the
towers are being erected and APs are being identified. The expected time of completion
for this project is June, 2014.
13
Mid Term Report Social Safeguard Compliance
External Social Monitoring
10. RECOMMENDATIONS
It is recommend that for the subprojects of New Rohri-Shikarpur and 132KV Rohri-
Ghambat as the Transmission lines of these sub-projects has already been completed
and the payments for stringing work were not paid to the remaining APs so far. 240 out
of 1264 APs of Rohri-Shikarpur and 27 out of 1279 APs have not been paid so far. It was
recommended that the process for remaining payment should be accelerated and
completed by the end of August, 2013.
•
•
Mid Term Report Social Safeguard Compliance
External Social Monitoring
NATIONAL TRANSMISSION & DISIWI'CII CO. LTD. ol - VICE OF THE
MANAGL]:R, ENVIRONMENT & SOCIAL IMPAC:
NTDC HOU;c:»E, 31 INDUSTRIAL AREA, CULEERG III. LAHORE
Datcd:301071:010
TP.1.: 36300679 FAX:992024.4
:E&SIONTDC/RAS)
1- CLIO CISC (South): DC: I Intn.e,
Lahore.
2- (.:lief 17:7111-1 Con,aruction P-ojec-ts, NTDC I louse, Lahore.
SUBJECT:- LAND ACQUISITION AND COMPENSATION PROCF.SS ON AI pRaireTs OF NTDC, N L'OLO BY ADB — SOCIAL SAFI:GI-ARV RELA'rED ISSUES
During tic rccca: visit of the ADD Lou. Revive/ Mission, ADD expressed ecnic.orn3 over prokAii.:0..... Lind a:dais:lion and payinuut of cutupent..ntiotia. tat P41111114 aublaiuj~ t. 1t was absorvect Mat di:plicate land acquisition pp:ice-tot was tellowinEi i.c. private negotiation aci well us under die Land Acquisition A.t seutitia 17(4) (6).
A', per A1)B Resettlement Poly' dciire,i that:
I . I.urid will not be at:q.t.:red tho.)ugli emergency clause of Laid Acquisit.ort Act szction :7(4)(6) (except in situation of e::trcnt. urgency),
2. Nu Nvork onier will be issued before prior Approval i)f A.131-1. and 3, Land will riot be posscqsed and. civil wnrls will no. be initiated before full disPursentent oC
the compensation and impleatentaJoit of the Resettlement Plan and contiru)ntion bti
rytealtni A.e.s-ney
In view of the above. tl i ernphnsiml that sot:411 .1,:7lep.orel 1641tle& on al 9.1.bprojects where the lund toeltaisitiou mid etarirtemationa are involved should be address,zel as pt,...r ADI3 Rescuttatt.m4 Policy io avoid the situation that resulted in can of BEncial.r. subpruicct,
It k also requested that during the pit.1.11.1NS Lank: etZ41111SILiCtIl fitid 1:a}-tuanL 7f
•orripensatioa late utt,:lersigned may iinttiCCtiat:ly he assticinicil addivssite saleptia:d
issues as per ADB c=,ctrement Pe I iey
KRA 1...1U1) tt I H .?14 0 D Ivlaultker
Envirummiit & Sock]. !;i4ittgilird VDC., nom:
C I: 1. (i.N.1.1:Pro. ...., W.A111)A
Instruction Memo to Chief Engineers regarding Land Acquisition Process
16
)NAL
TRANSMISSION AND DESPATCH COMPANY
WAPDA •
01
S. N141i vie. 2,1,1 in -4: 0,4■••■1,,1.
F. 5oo1i,4a O'f••• traft,"..p..... (..1-■
64,"/. '41t4J7
a • . okrc,:mt
- •
grA36i,
Splint 14,- D24.11 laments Net. of rota b ht1;erIll Mime
(P/.1;'Ij A1
03.
224 24 l4''
1:111,0 . ks••••
15)14.
ii!
- 61'
Od !•:. •
sorgl_.tAntle.. - rid
ElIV. 1•2,kaa
ria.1•44.-Pk.r.las.1.3.(21), - • •
— su .rtgneet „wile (c) sivt. t! NT DC. Mu itan
. oat..
s ma ei ro-o itiv4 IAN &trli.",6PATCH COMPANY
. • WAPDA "
s....m. .. ,-...,,,,i4yr.i.,, S. si,::,...,:t......5,7: N. •4•• 0.41,,,,,, Pp f!,-■ 41: s.e C,:t• ,,,,,..:1_._C a. ,
2 52,,....1. i.,e1,:. _ 2,,,MIX •,,,,,t•-•• . i •:15.1•,
..... n outiet _62./t/fr )
S4a-le .l 1.4. 24 a P a
; .
f• ?:........_.... , •, 1
.
Tem.. te Ila Olt., .4 0.. 2.
Igi
Id / •7,4t
Lied. e..40,61.
_*v ) S!Ci.)n-i I NTilb. Muttan ."`• SC‘,•2e, kflu •-•-t 5"frY-33.......Dals#414.4,14, ■ ,
,,,,, I I r. 6 DI II, ., re; .4.t2, 1 i
. . n.,.. „El iv.,.. . a...,. . ....... . '
. ' -- .... . ..._
81,1211.te --1
ot plyta .
18N31.
: . Eltt.-,. "IP,. •
. .
..,......._.,..__
o,oGgFdEiw
,..0
ea Clime
EM• rxi...■ IOC ;171•
•
U....10.• Oa Pt(Ovnt 01,1, V7Is , •
/Z1 %40.2gO
Mid Term Report Sm.tal Sukguarcl ("ornplicnice
External Social /1../wnwmg
Sample of compensation payments vouchers
17
Mid Term Report Social Safeguard Compliance
External Social Monitoring
Samples of Complaints Register
18
OFFICE oF THE CHIEF ENGINEER (EHV-Ij
NTDC, 34-If IDIJSTPIAL r REA
LAHORE
Tel: 042-99263246
Fax 042-99263247
NATIONAL TRANSMISSION & DESPATCH COMPANY LIMITED
No.2, c\ /CE/E.HVi Dated - 14-05-2009
OFFICE ORDER
A Grievance Redressal Commrrtee corripri.:Init:: on the follov,iing NTDC officers
is constituted to redress all complaints- from Affected Persons of the sub-projects under
EHV-I of NTDC.
1 Project Director (FH
2. Manager (ESIC) Member
3. XEN (EHV-I) Member
4. SDO (EHV-I) 7,1ember
5. ALO (EHV-I) fiember
6. APs Representative Member
This issues with the approval of GM GSC NTDC Lahore
CHIEF ENGINEEP EHNe-t
NTDC LAHORE
CC: 1. General Manager (P }, Lahore
Mid Term Report Social Saftguard Compliance
External Social Monitoring
Office Order for GRC
19