part 9: project cost estimates

56
Technical Guidelines for the Development of Small Hydropower Plants DESIGN Part 9: Project Cost Estimates SHP/TG 002-09:2019

Upload: others

Post on 13-Jun-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Part 9: Project Cost estimates

Technical Guidelines for the Development of Small Hydropower PlantsDesign

Part 9: Project Cost estimates

sHP/Tg 002-09:2019

Page 2: Part 9: Project Cost estimates

D I S C L A I M E R

This document has been produced without formal United Nations editing. The designations and the presentation of the material in this document do not imply the expression of any opinion whatsoever on the part of the Secretariat of the United Nations Industrial Development Organization (UNIDO) concerning the legal status of any country, territory, city or area of its authorities, or concerning the delimitation of its frontiers or boundaries, or its economic system or degree of development. Designations such as “developed”, “industrialized” and “developing” are intended for statistical convenience and do not necessarily express a judgement about the stage reached by a particular country or area in the development process. Mention of company names or commercial products does not constitute an endorsement by UNIDO. Although great care has been taken to maintain the accuracy of information herein, neither UNIDO nor its Member States assume any responsibility for consequences which may arise from the use of the material. This document may be freely quoted or reprinted but acknowledgement is requested.

© 2019 UNIDO / INSHP- All rights reserved

Page 3: Part 9: Project Cost estimates

Technical Guidelines for the Development of Small Hydropower PlantsDesign

Part 9: Project Cost estimates

sHP/Tg 002-09:2019

Page 4: Part 9: Project Cost estimates

ACKNOWLEDGEMENTS

The technical guidelines (TGs) are the result of a collaborative effort between the United Nations Industrial Development

Organization (UNIDO) and the International Network on Small Hydro Power (INSHP). About 80 international experts and 40

international agencies were involved in the document’s preparation and peer review, and they provided concrete comments

and suggestions to make the TGs professional and applicable.

UNIDO and the INSHP highly appreciate the contributions provided during the development of these guidelines and in

particular those delivered by the following international organizations:

- The Common Market for Eastern and Southern Africa(COMESA)

- The Global Network of Regional Sustainable Energy Centres (GN-SEC), particularly the ECOWAS Centre for Renewable

Energy and Energy Efficiency (ECREEE), the East African Centre for Renewable Energy and Energy Efficiency (EACREEE),

the Pacific Centre for Renewable Energy and Energy Efficiency (PCREEE) and the Caribbean Centre for Renewable Energy

and Energy Efficiency (CCREEE).

The Chinese government has facilitated the finalization of these guidelines and was of great importance to its completion.

The development of these guidelines benefited greatly from the valuable inputs, review and constructive comments as well as

contributions received from Mr. Adnan Ahmed Shawky Atwa, Mr. Adoyi John Ochigbo, Mr. Arun Kumar, Mr. Atul Sarthak, Mr.

Bassey Edet Nkposong, Mr. Bernardo Calzadilla-Sarmiento, Ms. Chang Fangyuan, Mr. Chen Changjun, Ms. Chen Hongying , Mr.

Chen Xiaodong, Ms. Chen Yan, Ms. Chen Yueqing, Ms. Cheng Xialei, Ms. Chileshe Kapaya Matantilo, Ms. Chileshe Mpundu

Kapwepwe, Mr. Deogratias Kamweya, Mr. Dolwin Khan, Mr. Dong Guofeng, Mr. Ejaz Hussain Butt, Ms. Eva Kremere, Ms. Fang

Lin, Mr. Fu Liangliang, Mr. Garaio Donald Gafiye, Mr. Guei Guillaume Fulbert Kouhie, Mr. Guo Chenguang, Mr. Guo Hongyou,

Mr. Harold John Annegam, Ms. Hou ling, Mr. Hu Jianwei, Ms. Hu Xiaobo, Mr. Hu Yunchu, Mr. Huang Haiyang, Mr. Huang

Zhengmin, Ms. Januka Gyawali, Mr. Jiang Songkun, Mr. K. M. Dharesan Unnithan, Mr. Kipyego Cheluget, Mr. Kolade Esan, Mr.

Lamyser Castellanos Rigoberto, Mr. Li Zhiwu, Ms. Li Hui, Mr. Li Xiaoyong, Ms. Li Jingjing, Ms. Li Sa, Mr. Li Zhenggui, Ms. Liang

Hong, Mr. Liang Yong, Mr. Lin Xuxin, Mr. Liu Deyou, Mr. Liu Heng, Mr. Louis Philippe Jacques Tavernier, Ms. Lu Xiaoyan, Mr. Lv

Jianping, Mr. Manuel Mattiat, Mr. Martin Lugmayr, Mr. Mohamedain SeifElnasr, Mr. Mundia Simainga, Mr. Mukayi Musarurwa,

Mr. Olumide TaiwoAlade, Mr. Ou Chuanqi, Ms. Pan Meiting, Mr. Pan Weiping, Mr. Ralf Steffen Kaeser, Mr. Rudolf Hüpfl, Mr. Rui

Jun, Mr. Rao Dayi, Mr. Sandeep Kher, Mr. Sergio Armando Trelles Jasso, Mr. Sindiso Ngwenga, Mr. Sidney Kilmete, Ms. Sitraka

Zarasoa Rakotomahefa, Mr. Shang Zhihong, Mr. Shen Cunke, Mr. Shi Rongqing, Ms. Sanja Komadina, Mr. Tareqemtairah, Mr.

Tokihiko Fujimoto, Mr. Tovoniaina Ramanantsoa Andriampaniry, Mr. Tan Xiangqing, Mr. Tong Leyi, Mr. Wang Xinliang, Mr.

Wang Fuyun, Mr. Wang Baoluo, Mr. Wei Jianghui, Mr. Wu Cong, Ms. Xie Lihua, Mr. Xiong Jie, Ms. Xu Jie, Ms. Xu Xiaoyan, Mr. Xu

Wei, Mr. Yohane Mukabe, Mr. Yan Wenjiao, Mr. Yang Weijun, Ms. Yan Li, Mr. Yao Shenghong, Mr. Zeng Jingnian, Mr. Zhao

Guojun, Mr. Zhang Min, Mr. Zhang Liansheng, Mr. Zhang Zhenzhong, Mr. Zhang Xiaowen, Ms. Zhang Yingnan, Mr. Zheng Liang,

Mr. Mr. Zheng Yu, Mr. Zhou Shuhua, Ms. Zhu Mingjuan.

Further recommendations and suggestions for application for the update would be highly welcome.

Page 5: Part 9: Project Cost estimates

TableofContents

Foreword Ⅱ……………………………………………………………………………………………………

Introduction Ⅲ………………………………………………………………………………………………

1 Scope 1……………………………………………………………………………………………………

2 Normativereferences 1…………………………………………………………………………………

3 Termsanddefinitions 1…………………………………………………………………………………

4 Generalprovisions 1………………………………………………………………………………………

5 Projectdivision 2…………………………………………………………………………………………

5.1 Overview 2……………………………………………………………………………………………

5.2 Compositionoftheconstructionpart 2……………………………………………………………

5.3 Divisionoftheconstructionpart 7…………………………………………………………………

6 Costsandunitprice 7……………………………………………………………………………………

6.1 Overview 7……………………………………………………………………………………………

6.2 Constructionandinstallationcosts 8………………………………………………………………

6.3 Equipmentexpenses 11……………………………………………………………………………

6.4 Formulationofunitcostofconstructionandinstallationengineering 11………………………

7 Engineeringbudgetpreparation 12………………………………………………………………………

7.1 Constructiontemporaryworks 12…………………………………………………………………

7.2 Constructionproject 13………………………………………………………………………………

7.3 Electromechanicalequipmentandinstallationproject 14…………………………………………

7.4 Hydromechanicalstructureandinstallation 15……………………………………………………

7.5 Miscellaneouscosts 15………………………………………………………………………………

7.6 Reservefundsandfinancinginterestduringconstructionperiod 17……………………………

8 Compositionofcostestimatedocuments 19…………………………………………………………

8.1 Preparationinstructions 19…………………………………………………………………………

8.2 Projectcostestimatetable 20………………………………………………………………………

9 Preparationofinvestmentestimationfortheconstructionpart 20…………………………………

9.1 Preparationmethodandcalculationstandards 20…………………………………………………

9.2 Reservefundsandfinancinginterestduringtheconstructionperiod 21………………………

9.3 Compositionofinvestmentestimationdocuments 21……………………………………………

AppendixA(Normative) Projectdivisioninconstructionpart 23……………………………………

AppendixB(Normative) Projectcostestimatetable 44………………………………………………

SHP/TG002-9:2019

Page 6: Part 9: Project Cost estimates

Foreword

TheUnitedNationsIndustrialDevelopmentOrganization(UNIDO)isaspecializedagencyundertheUnitedNationssystemtopromotegloballyinclusiveandsustainableindustrialdevelopment(ISID).TherelevanceofISIDasanintegratedapproachtoallthreepillarsofsustainabledevelopmentisrec-ognizedbythe2030AgendaforSustainableDevelopmentandtherelatedSustainableDevelopmentGoals(SDGs),whichwillframeUnitedNationsandcountryeffortstowardssustainabledevelop-mentinthenextfifteenyears.UNIDO’smandateforISIDcoverstheneedtosupportthecreationofsustainableenergysystemsasenergyisessentialtoeconomicandsocialdevelopmentandtoimpro-vingqualityoflife.Internationalconcernanddebateoverenergyhavegrownincreasinglyoverthepasttwodecades,withtheissuesofpovertyalleviation,environmentalrisksandclimatechangenowtakingcentrestage.

INSHP(InternationalNetworkonSmallHydroPower)isaninternationalcoordinatingandpromotingorganizationfortheglobaldevelopmentofsmallhydropower(SHP),whichisestablishedontheba-sisofvoluntaryparticipationofregional,subregionalandnationalfocalpoints,relevantinstitutions,

utilitiesandcompanies,andhassocialbenefitasitsmajorobjective.INSHPaimsatthepromotionofglobalSHPdevelopmentthroughtriangletechnicalandeconomiccooperationamongdevelopingcountries,developedcountriesandinternationalorganizations,inordertosupplyruralareasinde-velopingcountrieswithenvironmentallysound,affordableandadequateenergy,whichwillleadtotheincreaseofemploymentopportunities,improvementofecologicalenvironments,povertyallevi-ation,improvementoflocallivingandculturalstandardsandeconomicdevelopment.

UNIDOandINSHPhavebeencooperatingontheWorldSmallHydropowerDevelopmentReportsinceyear2010.Fromthereports,SHPdemandanddevelopmentworldwidewerenotmatched.Oneofthedevelopmentbarriersinmostcountriesislackoftechnologies.UNIDO,incooperationwithINSHP,

throughglobalexpertcooperation,andbasedonsuccessfuldevelopmentexperiences,decidedtodeveloptheSHPTGstomeetdemandfromMemberStates.

TheseTGsweredraftedinaccordancewiththeeditorialrulesoftheISO/IECDirectives,Part2(seewww.iso.org/directives).

AttentionisdrawntothepossibilitythatsomeoftheelementsoftheseTGsmaybesubjecttopa-tentrights.UNIDOandINSHPshallnotbeheldresponsibleforidentifyinganysuchpatentrights.

SHP/TG002-9:2019

Page 7: Part 9: Project Cost estimates

Introduction

SmallHydropower(SHP)isincreasinglyrecognizedasanimportantrenewableenergysolutiontothechallengeofelectrifyingremoteruralareas.However,whilemostcountriesinEurope,NorthandSouthAmerica,andChinahavehighdegreesofinstalledcapacity,thepotentialofSHPinmanyde-velopingcountriesremainsuntappedandishinderedbyanumberoffactorsincludingthelackofgloballyagreedgoodpracticesorstandardsforSHPdevelopment.

TheseTechnicalGuidelinesfortheDevelopmentofSmallHydropowerPlants(TGs)willaddressthecurrentlimitationsoftheregulationsappliedtotechnicalguidelinesforSHPPlantsbyapplyingtheexpertiseandbestpracticesthatexistacrosstheglobe.Itisintendedforcountriestoutilizethesea-greeduponGuidelinestosupporttheircurrentpolicy,technologyandecosystems.Countriesthathavelimitedinstitutionalandtechnicalcapacities,willbeabletoenhancetheirknowledgebaseinde-velopingSHPplants,therebyattractingmoreinvestmentinSHPprojects,encouragingfavourablepoliciesandsubsequentlyassistingineconomicdevelopmentatanationallevel.TheseTGswillbevaluableforallcountries,butespeciallyallowforthesharingofexperienceandbestpracticesbe-tweencountriesthathavelimitedtechnicalknow-how.

TheTGscanbeusedastheprinciplesandbasisfortheplanning,design,constructionandmanage-mentofSHPplantsupto30MW.

● TheTermsandDefinitionsintheTGsspecifytheprofessionaltechnicaltermsanddefinitionscommonlyusedforSHPPlants.

● TheDesignGuidelinesprovideguidelinesforbasicrequirements,methodologyandprocedureintermsofsiteselection,hydrology,geology,projectlayout,configurations,energycalculations,

hydraulics,electromechanicalequipmentselection,construction,projectcostestimates,eco-nomicappraisal,financing,socialandenvironmentalassessments—withtheultimategoalofa-chievingthebestdesignsolutions.

● TheUnitsGuidelinesspecifythetechnicalrequirementsonSHPturbines,generators,hydrotur-binegoverningsystems,excitationsystems,mainvalvesaswellasmonitoring,control,pro-tectionandDCpowersupplysystems.

● TheConstructionGuidelinescanbeusedastheguidingtechnicaldocumentsfortheconstructionofSHPprojects.

● TheManagementGuidelinesprovidetechnicalguidanceforthemanagement,operationandmain-tenance,technicalrenovationandprojectacceptanceofSHPprojects.

SHP/TG002-9:2019

Page 8: Part 9: Project Cost estimates

TechnicalGuidelinesfortheDevelopmentofSmallHydropowerPlants-DesignPart9:ProjectCostEstimates

1 Scope

ThispartoftheDesignGuidelinesspecifieshowtoformulatecostestimationsforsmallhydropower(SHP)projectsanddetailshowtopreparecostestimationdocuments.

2 Normativereferences

Thefollowingdocumentsarereferredtointhetextinsuchawaythatsomeoralloftheircontentconstitutesrequirementsofthisdocument.Fordatedreferences,onlytheeditioncitedapplies.Forundatedreferences,thelatesteditionofthereferenceddocument(includinganyamendments)ap-plies.

SHP/TG001,Technicalguidelinesforthedevelopmentofsmallhydropowerplants—Termsanddef-initions.

3 Termsanddefinitions

Forthepurposesofthisdocument,thetermsanddefinitionsgiveninSHP/TG001apply.

4 Generalprovisions

4.1 Costestimationsofprojectsshallbeformulatedaccordingtothepriceandpoliciesinthefor-mulationyear.Inthecaseofmajorchangestothedesignplan,quantitiesofitemsandcostlevelinthecommencementyearoftheproject,thecostestimationshallberevisedaccordingly.

4.2 Investmentforsocialandenvironmentalprotection(includingthefeesoflandacquisition,re-settlement,environmentalprotection,soilandwaterconservation,etc.)shallbecalculatedinac-cordancewithrelevantprovisionsofsocialandenvironmentalimpactassessment,andthenincludedinthetotalprojectinvestment.

4.3 Investmentfortransmissionengineeringbetweenahydropowerstationtothesubstationofthepowergridshallnotbeincorporatedinthetotalprojectinvestment.

1

SHP/TG002-9:2019

Page 9: Part 9: Project Cost estimates

4.4 TheprojectcostestimationatthefeasibilitystudystageshallbepreparedinaccordancewiththeprovisionsofChapters5to8ofthisdocument,andtheinvestmentestimationatthepre-feasi-bilitystudystageshallbepreparedinaccordancewiththeprovisionsofChapter9ofthisdocument.

5 Projectdivision

5.1 Overview

Costestimationsofahydropowerprojectmaybedividedintotheconstructionpartandsocialandenvironmentalprotectionpart,ofwhichtheconstructionpartmayincludeconstructionoftemporaryworks,constructionofcivilworks,electromechanicalequipmentandinstallation,hydromechanicalstructureandinstallation,andmiscellaneouscosts,asshowninFigure1:

Hydropower project

Construction

ConstructionoftemporaryworksConstructionofcivilworksElectromechanicalequipmentandinstallationHydromechanicalstructureandinstallationMiscellaneouscosts

ì

î

í

ïïïï

ïïïï

Socialandenvironmentalprotection

ì

î

í

ïïï

ïïï

Figure1 Divisionofcostestimationofhydropowerproject

5.2 Compositionoftheconstructionpart

5.2.1 Constructionoftemporaryworks

Thisreferstothetemporaryworksbuilttoassisttheconstructionofthemainworks,whichcanbecomposedofthefollowingcomponents:

a) Riverdiversion

Thismayincludeopendiversionchannel,diversiontunnel,bottomdiversionoutlet,construc-tioncofferdam (includingriverclosure),reservoirimpoundmentandtemporarydownstreamwatersupplyworksduringstorageperiod,hydromechanicalstructureandinstallation,etc.

b) Transportationforconstruction

Thetemporarytransportationfacilitieswithinandoutsidetheconstructionsiteservingthepro-jectconstructionmayincludehighways,bridges,constructionadits,waterwayworks,bridgeandculvertandroadreinforcement,aerialcableways,ramphoistways,andthemaintenanceandmanagementofpermanenttransportationworksandtemporarytransportationfacilitiesdur-2

SHP/TG002-9:2019

Page 10: Part 9: Project Cost estimates

ingtheconstructionperiodofthepowerstation.

c) Powersupplyforconstruction

Thismayincludehigh-voltagetransmissionlinessupplyingpowerfromtheexistingpowergridtotheconstructionsite,transmissionlinesof10kVandaboveontheconstructionsite,andpowersupplyfacilitiesworksof10kVandaboveoftheoutgoinglines,etc.Thepowersupplyfacilitiesmayincludetheconstructionofsubstations,substationequipmentandinstallation,aswellasthesupportingfacilities.

d) Housesforconstructionandconstructionmanagement

Thisreferstothehousingconstructionprojectsandsupportingfacilitiesrequiredforthecon-structionandconstructionmanagementduringtheprojectconstruction;itmayincludesitelev-elling,constructionwarehouses,auxiliaryprocessingplant,workingandlivingcamp,outdoorworks,aswellasthemaintenanceandmanagementofpermanentandtemporarybuildingsdur-ingtheconstructionperiodofthepowerstation.Thesearespecifiedasfollows:

1) Sitelevellingreferstoearth-rockexcavation,filling,masonryandotherworkswithintheplannedareaforthepurposeofconstructionandconstructionmanagementofhousesandoutdoorworks.

2) Construction warehousesincludesgeneralwarehousesandspecialwarehouses.Generalwarehousesareusedforequipment,materialsandtools,andspecialwarehousesareusedforoildepotsandexplosivesdepots.

3) Auxiliaryprocessingplantincludeswoodprocessingplant,rebarprocessingplant,steelpipeprocessingplant,hydromechanicalstructureprocessingplant,mechanicalrepairplantandconcreteprecastcomponentsplant.

4) Workingandlivingcampreferstothehousesandsupportingfacilitiesbuiltontheconstruc-tionsiteforworkingandlivingofthepersonnelinvolvedinconstructionmanagement,su-pervision,anddesignandconstruction.Alltheassociatedrentalexpensesincurredontheconstructionsiteduringtheconstructionperiodshallbeincludedinthisitem.

e) Otherconstructiontemporaryworks

Thisreferstoalltemporaryworksotherthanthoselistedabove,andmainlyincludesconstruc-tionwatersupply(largepumphousesandmainspipes),airsupply,aggregateproductionsys-tem,concretemixingandpouringsystem,installationandremovaloflargeheavymachinery,

floodprevention,iceprevention,drainagesystemandcommunication.Othertemporarycon-structionprojectsincludedintheproject,suchashighcostorlargequantitiesmaybelistedseparatelyaccordingtotheactualneedsoftheproject.

3

SHP/TG002-9:2019

Page 11: Part 9: Project Cost estimates

5.2.2 Constructioncivilworks

Constructioncivilworksreferstothemaincivilstructuresandotherpermanentstructures,whicharecomposedofthefollowingitems,amongwhichitemsa)toi)arethemainconstructionworks:

a) Waterretaining(impoundment)structure

Thisincludesallkindsofdams(weirs/barrages/storagedams)andfoundationtreatmentengi-neeringtoretainwaterintheriver.

Thedamsectionoftheintake,thespillwaysection,theseepageproofingofdamfoundationandabutment,andtheseepageproofingengineeringofthereservoirbankarealllistedunderthisitem.Thenon-overflowdamsection,thedischargedamsection,theintakedamsectionandthefoundationtreatmentengineeringshallbelistedrespectivelyunderconcretedam (sluice);thewater-retainingdamsection,dambodydrainagestructures,andfoundationtreatmentengineer-ingshallbelistedrespectivelyunderearth(rockfill)dam.Theslopeexcavationandsupportsta-bilizationwithintheexcavationareaofwaterretaining(impoundment)structuresareincludedinthisitem.

b) Drainageandenergydissipationstructure

Thisincludesstructuresforflooddischargesuchasspillway,flooddischargetunnel,sedimentflushingtunnelandpressurereliefholes(intunnels),aswellastheenergydissipationandanti-erosionstructuresalongthesideslopesoftheintakeandoutlet,theslopeandbanksofthespill-wayanddownstreamofthedrainagefacilitiesbehindthedam.Energydissipationandanti-ero-sionstructurescanbedividedintoenergydissipationengineering(plungepoolandstillingba-sin),auxiliaryenergydissipationengineering(baffleblocks,stillingtoothandauxiliaryweir),

apronextension,anti-scouringtrench,pre-excavationandbankslopeprotection,etc.

c) Waterconductorstructure

Thisincludesopendiversionchannels,waterinlets(includinggatechambers),diversiontun-nels,surgechambers(shafts)orpressureforebays,penstocks,tailwatersurgechambers(shafts),tailwatertunnels(channels),tailwateroutletsandotherstructures.

d) Powergenerationstructure

Thisincludespowerhousefoundations,powerhouse,groutingtunnels,drainagetunnels,venti-lationtunnels(shafts)andotherstructuresforthevariouspowergenerationworksonthesur-faceandunderground.

e) Substationstructure4

SHP/TG002-9:2019

Page 12: Part 9: Project Cost estimates

Thisincludessubstation(surfaceorunderground),bustunnels,ventilationtunnels,outgoinglinetunnels(well),outgoingfieldstructures(orswitchyardbuildings),etc.Ifthereisacon-verterstationproject,itshallbeplacedparalleltothesubstationprojectasafirst-levelproject.Thesteelframeofthesubstationstructuresisincludedinthisitem.

f) Fishpassage

Thismaybelistedseparatelyaccordingtothelayoutofthemainstructures.Thepartcombinedwiththebarragemayalsobeapartofthebarrageengineering.

g) Headworkoftheirrigationchannel

Thesecanbelistedseparatelyaccordingtothelayoutofthemainstructures.Thepartcombinedwiththebarragecanalsobeapartofthebarrageengineering.

h) Treatmentprojectoftheslopenearthedambank

Thismainlyincludesthetreatmentoftheslopenearthedambankandlandslidesthathaveanim-pactonthesafetyofhydraulicstructures,aswellasthedownstreambankslopeprotectionworksaffectedbythedissipationandscouringofdischargedwaterandtailwater.Thetreatmentofthelargeaccumulationbody,landslidebody,highslopandmudslidesshouldbelistedsepa-rately.

i) Transportation

Thisincludesthetransportationworksfornewroads,bridges,tunnels,waterwaysandotherpermanenttrafficprojectsaccessingtothedamthepowerhouseandtheoutside,aswellasthereconstructionandreinforcementoftheexistingroadsandbridges.

j) Housingconstruction

Thisreferstotheconstructionofpermanenthousingforon-siteproduction,operationandman-agementservices,includingsitelevelling,ancillaryworkshops,warehouses,officebuildings,

on-dutyapartmentsandancillaryfacilitiesandoutdoorworks.

k) Otherconstructionworks

Otherconstructionworksincludesafetymonitoringfacilities,powerlines,lightinglines,com-municationlines,andpublicfacilitiesincludingwatersupply,heatinganddrainagewithintheplantanddamarea,laboursafetyandindustrialhygienefacilities,hydrologicalandsedimentmonitoringfacilities,automaticwaterregimemonitoringsystemandothers.Thesearespecifiedasfollows:

5

SHP/TG002-9:2019

Page 13: Part 9: Project Cost estimates

1) Safetymonitoringfacilitiesrefertoallcivilworkscarriedouttocompletethepermanentsafetymonitoringsystem.

2) Powerlinesengineeringreferstotheoverheadpowerlinesandcabletrenchengineeringfromthepowerhousetoeachproductionsite.Thepowercablesfromthepowerhousetoeachproductionsiteshallbeincludedintheelectromechanicalequipmentandinstallationengineering.

3) Lightinglineengineeringreferstolightinglinesandthefacilitiesintheplantanddamarea(includingthelightingofoutdoorsubstations),excludingthelightingfacilitieswhichhavebeenlistedrespectivelyinthedetailsofhydraulicstructures,suchasbarragedams,spill-ways,anddiversionandpowergenerationsystems.

4) Communicationlineengineeringincludesinternalandexternaloverheadcommunicationlinesandoutdoorcommunicationcableengineering,aswellasthespecialcommunicationlineen-gineeringfromtheprojecttothehydrologicstationandweatherstationsubordinatetothepowerstation(reservoir).

5) Laboursafetyandindustrialhygienefacilitiesrefertothepermanentlaboursafetyandin-dustrialhygieneconstructionfacilitiesspeciallybuilttoavoidhazardsandharmfulfactorsduringtheproductionandoperationperiod,mainlyincludingsafetysigns,safetyprotectionfacilities,operating-environmentsafety-testinginstruments,noisecontrolandemergencyfacilities.

5.2.3 Electromechanicalequipmentandinstallation

Electromechanicalequipmentandinstallationreferstoalltheelectromechanicalequipmentandinstal-lationworksthatconstitutethefixedassetsofthepowerstation,including:

a) Powergenerationequipmentandinstallation

Thismayincludeturbinegeneratorunitsandancillaryequipment,mainvalves,liftingequip-ment,hydraulicmachineryauxiliaries,electricalequipment,controlandprotectionequipment,

communicationequipmentandinstallation.

b) Substationequipmentandinstallation

Thismayincludemaintransformer,highvoltageelectricalequipmentandprimarycableconnec-tionandinstallation.

c) Publicutilitiesandinstallation

Thismayincludecommunicationsequipment,ventilationandheatingequipment,mechanicalre-6

SHP/TG002-9:2019

Page 14: Part 9: Project Cost estimates

pairingequipment,computermonitoringsystem,industrialtelevisionsystem,managementau-tomationsystem,earthingandprotectionnetworkforthewholeplant,elevators,feedequip-mentinthedamarea,watersupply,drainageandheatingequipmentintheplantanddamarea,

hydrologyandsedimentmonitoringequipment,automaticwaterregimemonitoringsystem,

videosecuritymonitoringequipment,safetymonitoringequipment,firesafetyequipment,la-boursafetyandindustrialhygieneequipment,transportationequipment,andotherequipmentandinstallation.

5.2.4 Hydromechanicalstructureandinstallation

Hydromechanicalstructureandinstallationreferstoallthehydromechanicalequipmentandinstalla-tionworksthatconstitutethefixedassetsofthepowerstation.Thecomponentsofthehydrome-chanicalequipmentandtheirinstallationshallcorrespondtothecomponentsoftheconstructionpro-

ject,includinggates,hoistsandtrashracks,thefabricationandinstallationofpenstocks,valvesandotherhydromechanicalequipmentandinstallation.

5.2.5 Miscellaneousexpenses

Miscellaneousexpensesshallincludeconstructionmanagementfees,scientificresearchandexperi-mentexpenses,designfees,engineeringsurveyfees,constructionsupervisionfees,economicandtechnologicalconsultancyfees,projectinsurancepremiumandanti-terrorism measuresexpenses,

etc.

5.3 Divisionoftheconstructionpart

ThedivisionoftheconstructionpartoftheprojectshallcomplywiththeprovisionsofAppendixA.

6 Costsandunitprice

6.1 Overview

ThecompositionofcostsfortheconstructionpartisshowninFigure2:

Costs

EngineeringcostsConstructionandinstallationcostsEquipmentcosts{

MiscellaneouscostsReservefundsFinancinginterestduringtheconstruction

ì

î

í

ïï

ïï

Figure2 Compositionofcostestimatesforconstruction

7

SHP/TG002-9:2019

Page 15: Part 9: Project Cost estimates

6.2 Constructionandinstallationcosts

6.2.1 Directcosts

Directcostsrefertothelabourandcapitaldirectlyconsumedintheconstructionandinstallationpro-jects.Theyshallbecomposedofbasicdirectcostsandotherdirectcosts.Basicdirectcostsshallin-cludelabourcosts,materialcostsandconstructionmachinerycosts.Otherdirectcostsshallincludeadditionalcostsforconstructionduringwinterandrainyseasons,additionalcostsforconstructionatnight,additionalcostsforconstructioninspecialareas,amortizationcostsforsmallandtemporaryfacilities,measureexpenseofsafetyandcivilizationconstruction,etc.

a) Basicdirectcosts

1) Labourcosts

Thisreferstovariouscostsincurredbyproductionworkersdirectlyengagedinthecon-structionandinstallation.Theproductionworkersaregenerallycomposedofself-ownedworkers(skilledworkers)oftheconstructioncompanyandlocalworkers(generalwork-ers).Therefore,theunitcostoflabourshallbecalculatedaccordingtotheproportionofthenumberofself-ownedworkersandlocalworkers.

2) Materialcosts

Materialestimatedpriceshallbeformulatedforthekeymaterialsconsumedinlargequanti-tiesand/orwhichhaveaconsiderableinfluenceontheprojectinvestment,suchassteel,

timber,cement,asphalt,admixture,oil,fireworkproducts,cablesandbusbars.Materialestimatedprice=[material’soriginalprice+packingexpenses+(freightandmiscellaneousexpenses×grossweightcoefficient)]×(1+procurementandstoragecostrate)+transpor-tationinsurancepremium-packagingrecyclingvalue,where:

1) Originalpricereferstothemarkettransactionpriceofthenearbylargematerialsupplycompany,materialtradingcenter,ofthefactorypriceofthemanufacturerselectedac-cordingtothedesignrequirementsintheprojectarea.

2) Packingexpensesshallbecalculatedaccordingtothetype,specification,packingcostandnormaldepreciationamortizationofpackingmaterials.Wheretheoriginalpriceofmaterialsdoesnotcoverthepackingexpenses,butthematerialsthatmustbepackedinthecourseoftransportationandstorageshallbeincludedinthepackingcosts.Transportationinsurancepremiumreferstotheinsurancepremiumformaterialsintransportation,whichiscalculatedaccordingtotherelevantregulationsoftheinsur-ancecompanyormarketsurvey.

3) Freightandmiscellaneousexpensesrefertothetotalcostsincurredinmovingmateri-8

SHP/TG002-9:2019

Page 16: Part 9: Project Cost estimates

alsfromthedesignateddeliveryplacetothewarehouseorequivalentstockpileareas,

includingtransportation,loadingandunloading,dispatchingandotherincidentalcosts.

4) Thegrossweightofmaterialsreferstothetransportweightofmaterialsincludingtheweightofpackages.Theratioofthegrossweighttothenetweightofmaterialsisthegrossweightcoefficient.Materialprocurementandstoragecostsrefertoallthecostsincurredduringtheprocessofmaterialprocurement,supplyandstorage.

5) Packagingrecyclingvaluereferstotherecyclingcostsofpackaging,suchascementbags,carstakes,cablereels,etc.

6) Theothermaterialestimatedpricemaybedeterminedbyreferringtotheactualpriceofmaterialsofsimilarhydropowerprojectsinthesameregion.

3) Constructionmachinerycosts

Thisreferstothedepreciation,maintenance,andpowerfuelcostsoftheconstructionma-chineryusedinconstructionandinstallationworks.Itmayincludethebasicdepreciationex-penses,theequipmentrepairexpenses,theinstallationanddisassemblyexpenses,theon-boardlabourexpensesandthepowerfuelexpenses,where:

1) Basicdepreciationexpensesrefertothedepreciationandamortizationexpensesoftherecoveryoftheoriginalvalueoftheconstructionmachinerywithinthespecifiedperiodofuse.

2) Equipmentrepairexpensesrefertothecostsofrepairingandreplacingequipment,andtheattachmentsofequipmentandtools,lubricatingmaterialsrequiredfordailymain-tenance,cleaningaccessoriesandmachinerystoragecostsincurredto maintainthenormalfunctionoftheconstructionmachinery.

3) Installationanddisassemblyexpensesrefertotheamortizedcostsforinstallationanddisassemblyoftheconstructionmachinery,testrun,on-sitetransferandauxiliaryfa-cilitiescominginandoutthesite.

4) On-boardlabourexpensesrefertotheexpenseofthepersonnelassignedtotheopera-tionoftheconstructionmachinery.

5) Powerfuelexpensesrefertothecostsofair(compressedair),water,electricity,oilandcoalrequiredfornormaloperation.

b) Otherdirectexpenses

Thismayincludeadditionalcostsforconstructionduringwinterandrainyseasons,additional9

SHP/TG002-9:2019

Page 17: Part 9: Project Cost estimates

costsforconstructionatnight,additionalcostsforconstructioninspecialareas,amortizationcostsforsmallandtemporaryfacilities,measureexpenseofsafetyandcivilizationconstruc-tion,etc.

1) Additionalcostsforconstructionduringwinterandrainyseasonsrefertotheadditionalcostsrequiredtoguaranteeengineeringqualityandsafeproductionduringthewinterandrainyseasons,includingthecostsforadditionalconstructionprocesses,theconstructionofrainproof,heatpreservationanddrainagefacilities,theincreasedpowerandfuelcon-sumptionandtheincreasedcostsduetothedecreaseoflabourandmechanicalefficiency.

2) Additionalcostsforconstructionatnightrefertothesubsidyfeesfornightshiftsincurredduetotheconstructionduringthenight,amortizationofconstructionlightingequipmentontheconstructionsiteandconstructionroads,aswellaslightingelectricitycosts.

3) Additionalcostsforconstructioninspecialareasrefertotheincreasedcostsforconstruc-tioninspecialareassuchashighaltitude,naturalforest,hotweatherandsandstorms.

4) Amortizationexpensesofsmallandtemporaryfacilitiesrefertotheamortizationexpensesofsmallandtemporaryfacilitiesusedatworkareasduringthenormalconstructionoftheproject,includingerectionanddismantlingofscatteredscaffolds,scatteredsitelevelling,

installationandremovalofair,waterandelectricitydistributionlines,on-siteconstructiondrainage,maintenanceofserviceroads,anderectionanddismantlingoftemporarydutyrooms.

5) Measureexpensesofsafetyandcivilizationconstructionrefertothecostsincurredbytheconstructionenterpriseswhenpurchasingsafetyprotectiveappliances,implementingsafe-tyconstructionmeasures,improvingsafetyproductionconditionsandstrengtheningsafetyproductionmanagement.

6) Othercostsincludeconstructiontoolsandinstrumentsusagefees,inspectionandtestex-penses,engineeringpositioningandretestingexpenses(construction measurementandcontrolnetworkexpenses),expensesforprojectdeliveryandacceptance,cleaningexpen-sesuponcompletion,maintenancecostsincurredbeforetheprojecthandover.

Constructiontoolsandinstrumentsusagefeesrefertotheprocurement,amortizationandmaintenancecostsfortherequiredproductiontools,testandinspectioninstrumentswhicharenotincludedwithinthefixedassets,aswellasthesubsidyfeesfortheuseoftoolsownedbytheworkers,where:

1) Testandinspectionexpensesrefertothecostsofgeneralidentificationandinspectionofbuildings,materials,componentsandinstallationsconductedbyconstructionenter-prises,inaccordancewithrelevantstandards,includingthecostsofmaterialsusedbyexternallaboratories.

01

SHP/TG002-9:2019

Page 18: Part 9: Project Cost estimates

2) Otherdirectcostsshallbecalculatedbasedondirectengineeringcosts,andthecalcula-tionrateshallbe5percentto8percent;therateshallbeselectedaccordingtothecomplexityofthemainengineeringprojectandthetemporaryfacilities.

6.2.2 Indirectexpenses

Thisreferstotheadministrativeexpensesofconstructionenterprisemanagementpersonnelcarryingoutofficework,training,travel,labourprotection,foreignaffairsactivities,performanceguaran-teeandworkpermitsforforeignpersonnel.

6.2.3 Profit

Thisreferstotheprofitthatshallbeincludedintheconstructionandinstallationcostsaccordingtothemarketconditionsofhydropowerconstructionproject.

6.2.4 Taxes

Thisreferstobusinesstax,valueaddedtaxorotherrelatedcoststhatshallbeincludedinthecon-structionandinstallationcostsinaccordancewiththenationaltaxlawandrelevantprovisions.

6.3 Equipmentexpenses

Equipmentcostsmayincludetheoriginalpriceoftheequipment,domestictransportationexpensesandtransportationinsurancepremiuminequipmentmanufacturingcountry,internationaltransporta-tionexpensesandinsurancepremium,tariffsandothercosts,localtransportationcostsandinsur-ancepremium,andprocurementandstoragecosts.Iftheequipmentispurchaseddirectlyfromthedomesticmarket,onlylocaltransportationcostsandinsurancepremium,andprocurementandstor-agecostsarecalculated.

6.4 Formulationofunitcostofconstructionandinstallationengineering

Theunitpriceofconstructionandinstallationprojectshallbecalculatedusingthecomprehensiveunitpricemethod.Theunitpriceofconstructionandinstallationprojectshallincludedirectcosts,

indirectcosts,profitandtax.Directcosts,indirectcosts,profitandtaxshallbelistedintheunitestimationtable.Theunitpriceofconstructionandinstallationworksshallbecalculatedaccordingtothefollowingprocedures:

a) Directcosts

Basicdirectcostsincludelabourcosts,materialcostsandmachinerycosts.

Otherdirectcosts=directengineeringcosts×otherdirectcostrate.11

SHP/TG002-9:2019

Page 19: Part 9: Project Cost estimates

b) Indirectcosts=directcosts×indirectcostrate

c) Profit= (directcosts+indirectcosts)×profitrate

d) Tax= (directcosts+indirectcosts+profit)×taxrate

e) Unitpriceofconstructionproject=directcosts+indirectcosts+profit+tax

7 Engineeringbudgetpreparation

7.1 Constructiontemporaryworks

7.1.1 Riverdiversion

Thisshallbecalculatedaccordingtothedesignworkquantitymultipliedbytheunitprice.

7.1.2 Transportationforconstruction

Thisshallbecalculatedaccordingtothedesignworkquantitymultipliedbytheunitprice,anditmayalsobeformulatedusinganescalatedunitcostindex,accordingtothecostindexintheprojectareaorrelatedactualdata.

7.1.3 Powersupplyforconstruction

Thismaybecalculatedaccordingtothedesignworkquantitymultipliedbytheunitprice,anditmayalsobeformulatedusinganescalatedunitcostindex,byadoptingthecostindexintheprojectareaorbyanalysingrelatedactualdataaccordingtothedesignvoltagegrade,lineerectionlengthandtherequirementsoftransformerdistributionfacilities.

7.1.4 Housesforconstructionandconstructionmanagement

Thesitelevelingprojectcostsshallbecalculatedaccordingtothedesignworkquantitymultipliedbytheunitprice.Constructionwarehouseandauxiliaryprocessingplantcostsshallbecalculatedac-cordingtothedesignworkquantitymultipliedbytheunitcostindex.Theconstructionareaofhou-sesmaybedeterminedbytheconstructionplanning.Theunitcostindexofbuildingconstructionmayemploythecostindexoftemporaryhousesintheregionwheretheprojectislocated,orbedeter-minedbasedontheanalysisofactualdata.Investmentinworkingandlivingcampshallbedeter-minedbythedesignworkquantitymultipliedbytheunitcostindex.

7.1.5 Otherconstructiontemporaryworks

Otherconstructiontemporaryworksshallbecalculatedaccordingtothepercentagerateofthein-21

SHP/TG002-9:2019

Page 20: Part 9: Project Cost estimates

vestmentinconstructionandinstallationprojects(excludingotherconstructiontemporaryworks);

arateof2percentto3percentshouldbeadopted.Ifthereisaprojectwithhighcostandlargeamountofwork,itshallbelistedseparatelyaccordingtotheactualrequirementsoftheproject,andthepercentageratementionedaboveshouldbedecreasedaccordingly.

7.2 Constructionproject

7.2.1 Mainconstructionproject

Constructionofthemainstructureshallbeformulatedaccordingtothedesignedworkquantitiesmultipliedbyunitprice.

7.2.2 Transportationproject

Thisshallbecalculatedaccordingtothedesignedworkquantitiesmultipliedbyunitprice,orformu-latedwiththeescalatedunitcostindexaccordingtocostindexintheprojectareaorrelatedactualdata.

7.2.3 Housingconstructionproject

7.2.3.1 Theunitcostindexforpermanenthousesshallbedeterminedaccordingtothecorrespond-inglocalconstructioncostlevel.

7.2.3.2 Outdoorhousingconstructionworksshouldgenerallybecalculatedas15percentto20percentoftheinvestmentinhousingconstructionproject.

7.2.4 Otherfacilities

Thecostofsafetymonitoringfacilitiesshallbecalculatedaccordingtothedesigninformation.Ifthedesigninformationisnotavailable,thecostshouldbecalculatedonthebasisofthepercentageoftheinvestmentintheconstructionofthemainconstructionprojectaccordingtothedamtypeorotherengineeringtype.

Dambuiltwithlocalmaterials:0.9%to1.1%

Concretedam:1.1%to1.3%

Diversionhydropowerstation(diversionstructures):1.1%to1.3%

Theinvestmentoftransmissionlines,lightinglinesandcommunicationlinesshallbecalculatedbymultiplyingthedesignedworkquantitiesbytheunitprice,ortheescalatedunitcostindexshallbeadopted.

31

SHP/TG002-9:2019

Page 21: Part 9: Project Cost estimates

Alltheotheritemsshallbeanalysedandcalculatedaccordingtothedesignrequirements.

7.3 Electromechanicalequipmentandinstallationproject

7.3.1 Equipmentcost

Equipmentcostismainlycomposedofthefollowingitems:

a) Originalcostofequipmentreferstothefactorypriceortheinquirymadebythedesignunitafteranalysisanddemonstration.

b) Domesticfreightandmiscellaneouscostsofequipmentinitsproductioncountryrefertoallthetransportationcostsofequipmentshippedfromthemanufacturertoadomesticport,mainlyin-cludingtransportationexpenses,vehicledispatchingexpenses,loadingandunloadingexpenses,

packingandbindingexpenses,nitrogenchargingexpensesfortransformersandotherpossibleincidentalcosts.

c) Domestictransportationinsurancepremiumreferstotheinsurancepremiumarisingfromthetransportationprocessoftheequipment.Transportationinsurancepremiumsoftheequipmentshallbecalculatedbasedonthepercentageoftheoriginalpriceoftheequipment,andtheinsur-ancerateshallbecalculatedaccordingtotheprovisionsofrelevantauthorities.

d) Internationaltransportationcostsrefertoallthetransportationcostsincurredbytheequipmentshippedfromthesupplierporttotherelevantprojectport.

e) Internationaltransportationinsurancepremiumreferstotheinsuranceexpensesarisingfromtheinternationaltransportationoftheequipment.

f) Tariffandothercostsrefertothetariff,value-addedtax,bankfinanceexpenses,foreigntradecommission,importcommodityinspectionexpensesandportchargesimposedontheimportoftheequipment.

g) Localfreightandmiscellaneouscostsrefertoallthetransportationcostsincurredbytheequip-mentshippedfromthedomesticport(orthemanufacturer)totheprojectsite.

h) Localtransportationinsurancepremiumreferstotheinsuranceexpensesoftheequipmentinthetransportationprocess,whichshallbecalculatedaccordingtothemarketsurvey.

i) Procurementandstorageexpenserefertoallthecostsarisingfromtheprocurementandstorageoftheequipment,mainlyincludingprocurementexpenses,warehouseexpenses,sitestorageexpenses,depreciationcostsofmiscellaneousfixedassets,measurecostsfortechnicalsafety,

andthecostofequipmentinspectionandtesting.41

SHP/TG002-9:2019

Page 22: Part 9: Project Cost estimates

j) Otherconsiderations:

1) DuetotheweakeconomicfoundationofmanycountrieswhereSHPprojectsarecarriedout,attentionshallalsobepaidtowhethertherelevantportinthecountryhassufficientloadingandunloadingcapacity,whetheradditionalhoistingmachineryisneededandwheth-ertheroadinfrastructureofthecountrymeetstherequirementsfortransportinglargeequipment.

2) Thefieldassemblyandprocessingcostsforthecomponentsofthemainframe,afterbeingtransportedtothesite,shallbeincludedintheoriginalpriceoftheequipment.Ifanassem-blyyardneedstobesetup,itsconstructioncostshallalsobeincludedintheoriginalpriceoftheequipment.

3) Iftheequipmentispurchaseddirectlyfromdomesticmarket,onlythelocaltransportationandinsurancepremium,andprocurementandstorageexpenses,needtobecalculated.

7.3.2 Installationprojectexpenses

Investmentininstallationprojectsshallbecalculatedbymultiplyingthequantityoftheequipmentbytheunitpricetheinstallation.

7.4 Hydromechanicalstructureandinstallation

Theformulationmethodisthesameasthatin7.3.

7.5 Miscellaneouscosts

Miscellaneouscostsaremainlycomposedofthefollowingitems:

a) Constructionmanagementexpensesrefertothemanagementexpensesrequiredfortheentire

process,fromprojectpreparationtocompletionacceptance,inordertoconductanormalcon-structionproject.Theymayincludethepreliminaryprojectinspection,formofconstructionor-

ganization,managementequipmentandequipmentpurchase,managementstaffwagesandben-efits,andothermanagementcosts.Consensus-buildingcostswithstakeholders(includinglocalresidentsandcommunities)maybeincludedwithinconstructionmanagementexpenses.Theyareincludedinthecostestimationonthebasisofactualcostsincurred,andmayalsobecalcu-latedas2percentto3percentoftheinvestmentcoveredby7.1to7.4ifthereisnorelevantinformation.

b) Scientificresearchandexperimentexpensesrefertothecostsrequiredtocarryoutnecessaryscientificresearchandtestsduringtheconstructionprocesstosolvetechnicalproblemsassoci-

51

SHP/TG002-9:2019

Page 23: Part 9: Project Cost estimates

atedwiththeproject.Itisincludedinthecostestimationonthebasisofactualcostsincurred,

anditmaybecalculatedas0.5percentoftheinvestmentinconstructionandinstallationcov-eredby7.1to7.4ifthereisnorelevantinformation.

c) Designexpensesincludethecostsoftheprovisionofschemes,pre-feasibilitystudyandcostestimation,feasibilitystudyandcostestimation,detaildesigndrawingsandbillsofquantities,

technicalpresentation,handlingofdesignproblemsduringconstruction,preparationofas-builtdrawingsandotherservices,aswellasthecostsofexternaldesignreviewandtravelcostsfordesignpersonnel.Itshallbeincludedinthecostestimationonthebasisofactualcostsorbyref-erencetosimilarprojects.

d) Engineeringinvestigationexpensesrefertothecostsofengineeringgeologicalexplorationandsurveyingandmapping,whichshallbeincludedinthecostestimationonthebasisofactualcostsorwithreferencetosimilarprojects.

e) Constructionsupervisionexpensesincludethecostsofthecompletesupervisionandcontrolserviceforconstructionquality,safety,progressandthecostofthepartsoftheprojectunderdirectsupervision,aswellasthecostsofon-siteconstructionsupervisionengineers,whichareincludedinthecostestimation,onthebasisofactualcostsorwithreferencetosimilarpro-

jects.

f) Economicandtechnicalconsultancycostsrefertothecostsincurredbyentrustingqualifiedin-stitutionsoremployingexpertstocarryoutconsultation,reviewandevaluationonthespecial

projecttechnology,economyandlaw,suchasthesafety,reliability,advancementandecono-myoftheprojectconstruction,accordingtotheproject-managementobjectives.Itshallincludespecialconsultationonsurveysanddesignoutcomes,engineeringsafetyandtechnicalappraisal,

specialexaminationofconstructionanddesignchanges,specialassessmentofqualityproblemsduringtheconstructionandwarrantyperiod,laboursafetyandindustrialhygienetestingandevaluation,finalaccountsofcompletionandpost-projectevaluationreports,andotherconsult-ingcosts.

g) Projectinsurancepremiumrefertotheinsurancepremiumforconstruction,equipmentandin-stallationworksduringtheconstructionperiodinordertoobtaineconomiccompensationforthelossescausedbynaturaldisasterssuchasfire,floodandaccidents.Itshallbeincludedinthecostestimationonthebasisofactualcostsincurred,anditmaybecalculatedas0.5percentoftheinvestmentcoveredby7.1to7.4ifthereisnorelevantinformation.

h) Anti-terrorism measuresfeereferstotheexpensesofsecuritypersonnelandsafetyfacilitiesdesignedtoguaranteethepersonalandpropertysafetyoftheengineering,technicalandman-agementpersonnel,dependingonthenationalsafetyrequirements.

61

SHP/TG002-9:2019

Page 24: Part 9: Project Cost estimates

7.6 Reservefundsandfinancinginterestduringconstructionperiod

7.6.1 Reservefunds

a) Basicreservefund

Thebasicreservefundmainlycoverstheincreasedinvestmentindesignchangesandtheadjust-mentofrelevanttechnicalstandardsduringconstruction,aswellasthelossescausedbygeneralnaturaldisasters,andthecostsofmeasuresadoptedforpreventionofnaturaldisasters.Itmaybecalculatedas5to10percentofthetotalinvestmentoftheprojectcoveredby7.1to7.4.

b) Reservefundforpricedifferences

Thereservefundforpricedifferencesmainlycoverstheincreasedinvestmentduringthecon-structionprocessduetotheincreaseinlabourwages,materialsandequipmentpricesandtheadjustmentofexpensestandards.Dependingontheconstructionperiod,thestaticinvestment(includingthebasicreservefunds)shallbetakenasthecalculationbaseandcalculatedbythefollowingformulas.

1) Whentheannualcostindicesarethesame,thereservefundforannualcostdifferenceiscalculatedbythefollowingformula:

Ei=Fi 1+p( ) i-1-1 …………………………(1)

2) Whentheannualcostindicesaredifferent,thereservefundforannualcostdifferenceiscalculatedbythefollowingformula:

Ei=Fi 1+p2( ) 1+p4( ) … 1+pi( ) -1[ ] ………………(2)

3) Thereservefundforpricedifferencesisthesumofannualreservefundsforcostdiffer-ences:

E=∑N

i=1Ei …………………………(3)

where

E isthereservefundforcostdifferences;

Ei isthereservefundforcostdifferenceintheithyear;

N istheconstructionperiod;71

SHP/TG002-9:2019

Page 25: Part 9: Project Cost estimates

i istheyearsofconstruction;

Fi istheannualinvestmentintheithyear(includingbasicreservefund);

p istheaveragepriceindex(applicabletothesameannualpriceindices);

pi isthepriceindexintheithyear(applicabletodifferentannualpriceindices).

Thereservefundforcostdifferenceshallbecalculatedfromthenextyearofthecostlevelyearadoptedtoformulatebudgets.

7.6.2 Financinginterestduringtheconstructionperiod

Itshallbecalculatedonthebasisofthesumofannualinvestment,basicreservefundandreservefundforpricedifferencecoveredby7.1to7.4accordingtothereasonableconstructionperiodandthefinancialpoliciesandcapitalsystem.

Estimationformula:

S=∑N

n=1∑n

m=1Fmbm -

12Fnbn

æ

èç

ö

ø÷+∑

n-1

m=0Sm

é

ëêê

ù

ûúúi ………………(4)

where

S isthefinancinginterestduringconstructionperiod;

N isthereasonableconstructionperiod;

n istheconstructionyears;

m istheinterestrepaymentyears;

Fn、Fm istheinvestmentofthenthandmthyearinthecapitalflowtableduringconstructionperiod;

bn、bm istheproportionofthefinancingamountforeachconstructionyearinvestedinthesameyear;

i isthefinancinginterestrateduringconstructionperiod;

Sm istheinterestrepaymentamountinthemthyear.

Otherfinancingcostssuchascommissionfee,commitmentfee,administrativefee,andcreditin-surancepremiumincurredthroughthefinancingofdebtshallbeanalysedandcalculatedaccordingto

81

SHP/TG002-9:2019

Page 26: Part 9: Project Cost estimates

relevantprovisionsandshallbeincludedinfinancinginterestduringtheconstructionperiod.

8 Compositionofcostestimatedocuments

8.1 Preparationinstructions

8.1.1 Projectprofileshallinclude:

a) Theriversystem wheretheprojectislocated,constructionsite,accessibility,projectscale,

projectbenefit,projectlayout,workquantitiesofmainstructures,mainmaterialconsumption,

totalconstructionperiodandscheduleforpowergenerationofthefirst(batch)unit.

b) Theprojectprofileshallexplainthesourcesoftheinvestmentforprojectconstructionandtheproportionoftheinvestment.

c) Theprofileshallexplainthetotalinvestmentandstaticinvestmentoftheproject,reservefundforcostdifferences,financinginterestduringtheconstructionperiod,investmentperkW,in-vestmentperunitofelectricity,andthetotalinvestmentandstaticinvestmentwhenthefirst(batch)unitstartspowergeneration.

8.1.2 Preparationprincipleandbasisshallinclude:

a) Therelevantnationalandregionallawsandregulationsadoptedinthepreparationofthecostes-timation;

b) Therelevantregulations,normsandprovisionsusedinthepreparationofthecostestimation;

c) Theprice-levelyearforthepreparationofthecostestimation;

d) Designdocumentsanddrawings;

e) Otherrelevantprovisions.

8.1.3 Basicpriceshallinclude:

a) Estimatedunitcostsoflabour,theestimatedcostofthemainmaterials,andthebasicunitcostsofelectricityandwaterusedforconstruction;

b) Pricesofmajorequipment;

c) Expensecalculationstandards.91

SHP/TG002-9:2019

Page 27: Part 9: Project Cost estimates

8.1.4 Otherconsiderationsshallbelistedinthepreparationofthecostestimation.

8.1.5 Summarytableofthemaintechnicalandeconomicindices:

Themaintechnicalandeconomicindicesoftheprojectshallbelistedinthistable.

8.2 Projectcostestimatetable

Theprojectcostestimatetableshallincludethegeneralcostestimatetable,constructiontemporaryworkcostestimatetable,costestimatetablefortheconstructionproject,costestimatetableforequipmentandinstallationproject,costestimatetableformiscellaneousexpenses,annualinvest-mentsummarytableandthesummarytableofthemaintechnicalandeconomicindices.SeeAppen-dixBfortheformoftablesandrequirements.

9 Preparationofinvestmentestimationfortheconstructionpart

9.1 Preparationmethodandcalculationstandards

9.1.1 Basicunitcost

Thepreparationofthebasicunitcostshallbethesameasthatusedinbudgetaryestimation.

9.1.2 Unitcostofconstructionandinstallationprojects

Thepreparationmethodforunitcostofconstructionandinstallationprojectsshallbethesameasthatusedinbudgetaryestimation.

9.1.3 Preparationofsubunitprojectestimations

Estimationofsubunitprojectsmaybedividedintothreeparts,namelytemporaryconstructionpro-jects,theconstructionproject,andtheelectromechanicalequipmentandinstallationproject.Thepreparationmethodshallmeetthefollowingrequirements:

a) Fortemporaryconstructionprojects,thepreparationmethodandcalculationstandardsarees-sentiallythesameasthoseusedinthecostestimation.

b) Forconstructionprojects,thepreparationoftheinvestmentestimationforthemainconstruc-tionworks,transportengineeringandbuildingconstructionshallbebasicallythesameasthatincostestimation.Otherprojectsmaybeestimatedas2percentto4percentoftheinvestmentinthemainconstructionworks,dependingontheparticularnatureandscaleoftheproject.

c) Forelectromechanicalequipmentandinstallation,themethodforpreparationofestimationof02

SHP/TG002-9:2019

Page 28: Part 9: Project Cost estimates

majorelectromechanicalequipmentandinstallationworksshallbethesameasthatinthecostestimation.Theequipmentandinstallationcostsofotherelectromechanicalequipmentmaybecalculatedaccordingtothepercentageofthemainelectromechanicalequipmentcostorunitkilo-wattindex.Majorelectromechanicalequipmentincludesturbinesandancillaryequipment,gen-eratorsandancillaryequipment,mainvalves,liftingequipment,generatorcircuitbreakers,

busbars,maintransformerandhighvoltageelectricalequipment(whichincludeshighvoltagecircuitbreakers,highvoltagecombinedelectricalequipment,andhighvoltagepowercables).Otherelectromechanicalmayincludehydraulicmachineryancillaryequipment,electricalequip-ment,controlandprotectionequipment,communicationsequipment,ventilationandheatingequipment,mechanicalrepairequipment,othersubstationequipment,elevators,feederequip-mentinthedamarea,watersupplyanddrainageandheatingsupplyequipmentintheplantanddamareas,permanenthydrologicaltelemetryequipment,permanentsafetymonitoringequip-ment,laboursafetyandindustrialhygieneequipment,firefightingequipment,transportationequipment,plantearthing,etc.

d) Forthehydromechanicalstructureandinstallationworks,thepreparationmethodandcalcula-tionstandardsshallbeessentiallythesameasthoseusedincostestimation.

e) Formiscellaneousexpenses,thepreparationmethodandcalculationstandardsshallbeessential-lythesameasthoseusedincostestimation.

9.2 Reservefundsandfinancinginterestduringtheconstructionperiod

Therequirementsforthecalculationofreservefundsandfinancinginterestduringtheconstructionperiodareasfollows:

a) Basicreservefunds:arateof10percentto15percentmaybeused,withconsiderationofdif-ferentdesigndepth.

b) Reservefundforcostdifferences:thecalculationmethodisthesameasthatusedforcostesti-mation.

c) Financinginterestduringconstructionperiod:thecalculationmethodhereisthesameasthatusedforcostestimation.

9.3 Compositionofinvestmentestimationdocuments

Theinvestmentestimationdocumentsarecomposedofthepreparationinstructionsandtheinvest-mentestimationtable.Thetableformandcontentsareessentiallythesameasthoseusedinthecostestimation.

NOTE:Theprojectinvestmentestimationshallbepreparedtomakeaninformeddecisionforthedevelopmentofthe

projectintheearlystagesoftheproject.Investmentestimationisessentiallythesameaspreparingthecostes-

12

SHP/TG002-9:2019

Page 29: Part 9: Project Cost estimates

timationintermsofcontents,projectdivisionandexpensescomposition.However,duetothedifferentlevelsofdetailinthesetwokindsofestimations,thepreparationmethodsandestimationstandardsforeacharedif-ferent.Investmentestimationshallthereforesimplify,mergeandadjustsomeofthecontentusedfortheprepa-rationofthecostestimation.

22

SHP/TG002-9:2019

Page 30: Part 9: Project Cost estimates

AppendixA(Normative)

Projectdivisioninconstructionpart

TableA.1 Item1—Temporaryconstructionproject

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

I Diversionproject

1 Opendiversionchannelproject

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofre-bar

*/kg

Shotcrete */m3

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Reinforcedgabion */m3

Compositegeomembrane */m2

2 Diversiontunnel

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

Pluggingconcrete */m3

Fabricationandplacementofre-bar

*/kg

Shotcrete */m3

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

32

SHP/TG002-9:2019

Page 31: Part 9: Project Cost estimates

TableA.1(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Grouting */(t、m、m2)

Waterstop */m

Others

3 Diversionbottomtunnel

4 Earth-rockcofferdamproject

Earthexcavation */m3

Rockexcavation */m3

Weirfilling */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofre-bar

*/kg

Seepageproofing

Removalofweirbody */m3

Closure

Others

5 Concretecofferdamproject

Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

Fabricationandplacementofre-bar

*/kg

Seepageproofing

Removalofweirbody */m3

Others

6Downstream temporary watersupplyduringtheimpoundment

period

7Hydro mechanicalstructureandinstallation

IIConstructiontransportation

project

1 Road */km

2 Railway */km

42

SHP/TG002-9:2019

Page 32: Part 9: Project Cost estimates

TableA.1(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

3 Bridge */m

4 Constructionadit

Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

Blockingconcrete */m3

Fabricationandplacementofre-bar

*/kg

Shotcrete */m3

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Others

5 Aerialropeway */m

6 Slopehoistingway */m

7Reinforcementofbridgeandcul-vertandroads

*/km

8 Railwaytransferstation */Item

9 Waterway */Item

10Maintenanceandmanagementoffacilities

*/Item

IIIConstruction powersupplyproject

Highvoltagepowersupplylines

*/km

Substation */each

IVHousesforconstruc-tion and construc-tionmanagement

Sitelevelling */m2

Generalconstructionwarehouse */m2

Explosivestorage */Item

52

SHP/TG002-9:2019

Page 33: Part 9: Project Cost estimates

TableA.1(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Oildepot */Item

Auxiliaryprocessingplant */m2

Workingandlivingcamp */m2

Outdoorproject */Item

Maintenanceandmanagementoffacilities

*/Item

VOther temporaryconstructionproject

NOTE:“*”indicatesthecurrencyunit

TableA.2 Item2—Constructioncivilworks

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

IWaterretaining(impoundment)

structures

1 Concretedam(gate)

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Protectivemesh */m2

Cutoffwalltrenching */m2

Cutoffwallconcrete */m3

Drilledgrouthole */m

Grouting */(t、m、m2)

Groutingorificepipe */m

62

SHP/TG002-9:2019

Page 34: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Drainagehole */m

Steelplatelining */kg

Hoistroom */m2

Temperature control meas-ures

*/m3(concrete)

Detailstructure */m3

2 Earth(rock)dam

Earthexcavation */m3

Rockexcavation */m3

Earthfilling */m3

Sand-gravelfilling */m3

Sloping(core)wallearthfill-ing

*/m3

Filter material and gradedmaterialfilling

*/m3

Damrockfilling */m3

Blanketfilling */m3

Geomembrane */m2

Stonemasonry */m3

Asphaltconcrete */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Waterstop */m

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Protectivemesh */m2

Cutoffwalltrenching */m2

Cutoffwallconcrete */m3

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

72

SHP/TG002-9:2019

Page 35: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Detailstructure */m3

3Reservoirbankseepageproo-fingproject

Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Protectivemesh */m2

Cutoffwalltrenching */m2

Cutoffwallconcrete */m3

Drilledgrouthole */m

Grouting */(t、m、m2)

Groutingorificepipe */m

Drainagehole */m

IIDrainageandenergydis-sipationstructures

1 Spillway

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Protectivemesh */m2

82

SHP/TG002-9:2019

Page 36: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

Steelplatelining */kg

Temperature control meas-ures

*/m3(Concrete)

Detailstructure */m3

2 Flooddischargingtunnel

Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

Steelplatelining */kg

Detailstructure */m3

3 Scouringoutlet(tunnel)

Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

92

SHP/TG002-9:2019

Page 37: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Drainagehole */m

Detailstructure */m3

4Relievinghole(tunnel)pro-

ject

Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

Detailstructure */m3

5Plungepool,auxiliaryweirandstillingbasin

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Protectivemesh */m2

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

03

SHP/TG002-9:2019

Page 38: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Steelplatelining */kg

Detailstructure */m3

IIIWater conductor struc-tures

1 Opendiversionchannel

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drainagehole */m

Detailstructure */m3

2 Inlet(intake)project

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Protectivemesh */m2

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

13

SHP/TG002-9:2019

Page 39: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Detailstructure */m3

3 Diversiontunnel Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

Detailstructure */m3

4 Surgeshaft(chamber) Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Grouting */m2

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

Detailstructure */m3

5 Forebay

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Concrete */m3

23

SHP/TG002-9:2019

Page 40: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

Detailstructure */m3

6 Penstock

Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

FabricationandPlacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Detailstructure */m3

7 TailwatertunnelRefertodiversiontunnelengineering

series

8Tailwater surge chamber(shaft)

Refertosurgeshaft(chamber)

series

9 Tailrace

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

33

SHP/TG002-9:2019

Page 41: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Detailstructure */m3

10 TailwateroutletRefertothelisteditemsofinlet(intake)project

IVPowergenerationstructures

1 Surfacepowerhouse

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

Temperaturecontrolmeasures

*/m3(concrete)

Structuredecoration */m2

Detailstructure */m3

V Substationstructures

43

SHP/TG002-9:2019

Page 42: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

1 Surfacesubstation

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Brickmasonry */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Structuredecoration */m2

Detailstructure */m3

VIIrrigationcanalheadworks

Earthexcavation */m3

Rockexcavation */m3

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Drainagehole */m

Detailstructure */m3

VIISlope protection (nearthedam)

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

53

SHP/TG002-9:2019

Page 43: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Stonemasonry */m3

Concrete */m3

Fabricationandplacementofreinforcement

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Protectivemesh */m2

Drilledgrouthole */m

Grouting */(t、m、m2)

Drainagehole */m

Others

VIII Transportationprojects

1 Roads

Earthexcavation */m3

Rockexcavation */m3

Earth-rockfilling */m3

Stonemasonry */m3

Concrete */m3

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */each

Protectivemesh */m2

Others

2 Railway */km

3 Bridge */m

4Accesstunnel(includingac-cesstunneltotheplant)

Earthexcavation */m3

Rockexcavation */m3

Concrete */m3

63

SHP/TG002-9:2019

Page 44: Part 9: Project Cost estimates

TableA.2(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Fabricationandplacementofrebar

*/kg

Shotcrete */m3

Wiremeshrebar */kg

Anchorbolt(beam) */each

Anchorcable */eachk

Drilledgrouthole */m

Grouting */(t、m、m2)

Detailstructure */m3

5 Waterway */Item

IXHousesconstruction

project

Sitelevelling */Item

Auxiliarymanufacturingplant

*/m2

Warehouse */m2

Office */m2

On-dutyapartmentandancil-laryfacilities

*/m2

Outdoorprojects %

XOtherconstruction pro-

jects

Safetymonitoringfacilities

Powerline */km

Lightingline */km

Communicationsline */km

Laboursafetyandindustrialhygienefacilities

Water level and sedimentmonitoringfacilities

Automaticwaterregimemo-nitoringsystem

Others

NOTE “*”indicatesthecurrencyunit

73

SHP/TG002-9:2019

Page 45: Part 9: Project Cost estimates

TableA.3 Item3—Electromechanicalequipmentandinstallationproject

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

IGeneratingequipmentandinstallationproject

1Turbineequipmentandin-stallation

Turbine */Unit

Governor */Unit

Oilpressuredevice */Set

Automationelement */Set

Turbineoil */kg

2Generatorequipmentandinstallation

Generator */Unit

Excitationsystem */Set

Automationelement */Set

3Mainvalveequipmentandinstallation

Butterflyvalve */Unit

Sphericalvalve */Unit

Oilpressuredevice */Set

4Hoistingequipmentandin-stallation

Bridgecrane */Unit

Balancebeam */kg(Pair)

Track */Pair10m

Trackblocker */kg

Trolleyconductor */Threephase10m

5Hydraulicmachineryauxiliaryequipmentandinstallation

Oilsystem

Compressedairsystem

Watersystem

Hydraulicmeasuringsystem

Pipeline (pipe, fittingsandvalve)

*/kg

83

SHP/TG002-9:2019

Page 46: Part 9: Project Cost estimates

TableA.3(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

6Electricalequipmentandin-stallation

Powergenerationvoltagedevice

Variablefrequencystaringdevice

Busbar */Singlephase100m

Plantservicepowersup-

plysystem

Testingequipment

Powertransmissioncable */km

Cabletray(cableandbus-bar)

*/kg

Others

7Controlprotectionequipmentandinstallation

Computermonitoringsystem

Protectionsystem

Industrialvideosystem

Directcurrentsystem

Controlandprotectionca-ble

*/km

Others

8Communicationequipmentandinstallation

Satellitecommunication

Opticalfibrecommunica-tion

Microwavecommunication

Carrierwavecommunica-tion

Mobilecommunication

93

SHP/TG002-9:2019

Page 47: Part 9: Project Cost estimates

TableA.3(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

Manufacturing dispatchingcommunication

Manufacturing manage-mentcommunication

IISubstationequipmentandinstallation

1Main transformer equip-mentandinstallation

Transformer */Unit

Track */Pair10m

Trackblocker */kg

2Highvoltageelectricalequipmentandinstallation

Highvoltagecircuitbreaker

*/Unit

Currenttransformer */Unit

Voltagetransformer */Unit

Isolationswitch */Unit

Lightningarrester */Unit

Highvoltagecombinedelectricalequipment

*/Interval

Highvoltagepowercable */Threephase100m

Fabricationandinstallationofhighvoltagepowerca-blehead

*/Threephaseset

3Primary cable connectionand other installationworks

IIISafetymonitoringequipmentandinstallation

project

IVHydrologicaltelemetryequipmentandinstallation

project

VFirefightingequipmentandinstallationproject

04

SHP/TG002-9:2019

Page 48: Part 9: Project Cost estimates

TableA.3(continued)

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

VILaboursafetyandindus-trial hygiene equipmentandinstallationproject

VIIOtherequipmentandin-stallationproject

1Elevatorequipmentandin-stallation

2Feederequipmentindamareaandinstallation

Transformer */Unit

Powerdistributiondevice

3Watersupplyanddrainageequipment in plant anddamareaandinstallation

4Heatingequipmentinplantanddamareaandinstalla-tion

5Ventilationandheatingequipmentandinstallation

6Machinery repair equip-mentandinstallation

7 Trafficequipment */Vehicle(Unit)

8 Plantearthing */kg

9 Others */Item

NOTE “*”indicatesthecurrencyunit

14

SHP/TG002-9:2019

Page 49: Part 9: Project Cost estimates

TableA.4 Item4-Hydromechanicalequipmentandinstallationproject

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

IWaterretaining(impoundment)structures

1 Gatesandinstallation

Plainbattengate */kg

Archgate */kg

Embeddedparts */kg

Gateweights */kg

2 Hoistequipmentandinstallation

Winchhoist */Unit

Gantrycrane */Unit

Oilpressurehoist */Unit

Track */Pair10m

Trackblocker */kg

3Trashholdingequipmentandinstal-lation

Trashrack */kg

Trashremover(cleaner) */kg(Set)

IIDrainageandenergydissi-pationstructures

1 Gatesandinstallation

2 Hoistequipmentandinstallation

3Trashholdingequipmentandinstal-lation

III Waterconductorsystem

1 Gatesandinstallation

2 Hoistequipmentandinstallation

3Trashholdingequipmentandinstal-lation

4Steelpipe (penstock)fabricationandinstallation

IV Switchyardstructures

Steelframework */kg

VStructuresatheadofirrigationchannel

1 Gatesandinstallation

2 Hoistequipmentandinstallation

NOTE “*”indicatesthecurrencyunit

24

SHP/TG002-9:2019

Page 50: Part 9: Project Cost estimates

TableA.5 Item5—Miscellaneouscosts

No. Level-1project Level-2project Level-3projectTechnicaland

economicindex

1Construction management ex-

pense

2Scientificresearchtesting ex-

pense

3 Designexpense

4 Engineeringsurveyexpenses

5Constructionsupervisionexpen-ses

6Economicandtechnicalconsul-tationexpenses

7 Insurancepremiumofproject

8Anti-terrorism measuresexpen-ses

NOTE1 Intheprojectdivision,threelevels—Level-1,Level-2andLevel-3—arecompletedforeachitem;thesecanbetailoredtotheprojectrequirements,butLevel-1andLevel-2itemsshallnotbemerged.Itemsnotspeci-fiedinthetablecanbelisteddependingonactualprojectrequirements.

NOTE2 Onlyrepresentativesub-itemsarelistedunderLevel-3items.Whenthedesignbudgetaryestimationispre-pared,thefollowingitemsshallbesubdividedasnecessary:

① Openexcavationandundergroundexcavation,earthexcavation,andsandandgravelexcavationshallbelistedseparatelyunderearthexcavation.

② Openexcavationandundergroundexcavation,aswellastheexcavationofadits,inclinedshaftsandverticalshaftsshallbelistedseparatelyunderrockexcavation.

③Earthfillingandrockfillingshallbelisted,respectively,underearth-rockfilling.④ Differentconstructionpositions,differentstrengthlevelsanddifferentgradesoftheconcreteworks

shallbelisted,respectively.⑤ Drystonemasonry,cement-laidstonemasonry,riprapandwire(reinforcement)cageblockstoneshall

belisted,respectively,understonemasonry.⑥ Boreholegroutingshallbelistedseparatelyaccordingtothepurposesandthedifferentdrillingmachines

employed.⑦ Groutingprojectsshallbelistedaccordingtodifferentgroutingtypes,suchascontactgrouting,consoli-

dationgrouting,curtaingroutingandbackfillgrouting.⑧ Shotcrete-boltsupportwork,steelfibreshotcreteandplainshotcrete,anchorboltandanchorcable,as

wellasanydifferentspecificationsamongthem,shallbelistedseparately.⑨Electromechanicalequipmentandinstallation,aswellashydromechanicalstructuresandinstallation,

shallbelistedonebyone,accordingtotheequipmentlistrequiredbythedesignandtheitemdivisionrequirements.

⑩ Generalsteelpipe,branchpipe,anddifferentpipediametersandthicknessesshallbelistedseparatelyforsteelpipefabricationandinstallation.

NOTE3 Thecompositionofeachpartoftheecologicalsubstationshallbeincludedwithinthecorrespondingitemsofthemainproject,accordingtotheirattributes.

NOTE4 “*”indicatesthecurrencyunit

34

SHP/TG002-9:2019

Page 51: Part 9: Project Cost estimates

AppendixB(Normative)

Projectcostestimatetable

TableB.1 Totalcostestimatetable Unit:*

No. DescriptionofprojectorexpenseConstruction

andinstallationexpense

Equipment

procurementexpense

Miscellaneousexpense

Total

Ⅰ Investmentintheconstructionpart

1 Temporaryconstructionworks

2 Construction

3 Electromechanicalequipmentandinstallation

4 Hydromechanicalequipmentandinstallation

5 Miscellaneousexpenses

Totalinvestment:Item1toItem5

Basicreservefund

Totalcapitalinvestment

Ⅱ Socialandenvironmentalprotectionpart

Investmentinsocialandenvironmentalprotec-tion

Basicreservefund

Totalcapitalinvestment

ⅢTotalinvestmentinengineering(TotalofIandII)

Totalcapitalinvestment

Reservefundforpricedifferences

Financinginterestduringconstructionperiod

Totalinvestment

NOTE “*”indicatesthecurrencyunit

44

SHP/TG002-9:2019

Page 52: Part 9: Project Cost estimates

TableB.2 Costestimatetableoftemporaryconstructionproject(orconstructioncivilworks) Unit:*

No. Descriptionofprojectorexpense Unit Quantity Unitprice Total

NOTE1 LevelIIIitemsarelistedinthistableaccordingtotheprojectdivision,andthistableisapplicabletotempo-raryconstructionprojectsandconstructioncivilworks.

NOTE2 “*”indicatesthecurrencyunit

TableB.3 Costestimatetableforequipmentandinstallationprojects Unit:*

No.Descriptionandspecification

Unit QuantityUnitprice Total

Equipment Installation Equipment Installation

NOTE1 LevelIIIitemsarelistedinthistableaccordingtotheprojectdivisionandthistableisapplicabletoelectro-mechanicalequipmentandinstallationaswellashydromechanicalequipmentandinstallationprojects.

NOTE2 “*”indicatesthecurrencyunit

TableB.4 Costestimatetableformiscellaneousexpense Unit:*

No. Descriptionofprojectorexpense Estimationformula Amount

NOTE “*”indicatesthecurrencyunit

54

SHP/TG002-9:2019

Page 53: Part 9: Project Cost estimates

TableB.5 Unitcostestimatetable

UnitpriceNo.

Projectname

Constructionmethod

Items Unit Unitprice(*) Quantity Totalprice(*)

Labour

Material

Constructionmachinery

Subtotalofbasicdirectexpenses *

Otherdirectexpenses * %

Indirectexpenses * %

Profit * %

Tax * %

Total *

Unitprice *

NOTE “*”indicatesthecurrencyunit

64

SHP/TG002-9:2019

Page 54: Part 9: Project Cost estimates

TableB.6 Annualinvestmentsummarytable Unit:*

No. Descriptionofprojectorexpense TotalConstructionperiod(year)

1 2 3 ……

Ⅰ Investmentinconstructionpart

1 Constructiontemporaryworks

2 Constructioncivilproject

3 Electromechanicalequipmentandinstallation

4 Hydromechanicalstructureandinstallation

5 Miscellaneousexpenses

Totalinvestment:totalofItems1to5

Basicreservefund

Totalcapitalinvestment

Ⅱ Socialandenvironmentalprotectionpart

Investmentinenvironmentalprotection

Basicreservefund

Totalcapitalinvestment

Ⅲ Totalinvestmentofproject(totalofIandII)

Totalcapitalinvestment

NOTE “*”indicatesthecurrencyunit

74

SHP/TG002-9:2019

Page 55: Part 9: Project Cost estimates

TableB.7 Maineconomicandtechnicalindextable

Riversystem

Constructionlocation

Designer

Projectowner

Reservoir

Normalpoollevel m

Totalpoolcapacity m3

Livecapacity m3

Submergedcultivatedland

Hectare

Resettlementofresidents

Person

Resettlementcost *

Unitindex */Person

Powerstation

Type

Size of powerhouse (length ×width×height)

m×m×m

Turbinemodel

Installedcapacity(unitcapacity×set)

kW

Guaranteedoutput kW

Annualoutput kW·h

Annualutilizationofhours h

Construction engineering invest-ment

*

ConstructionengineeringperunitkWindex

*/kW

Investmentinpowergeneratione-

quipment*

Powergeneration equipmentperunitkWindex

*/kW

Riverweir(Gate)

Diversiontunnel

Type

The maximum ofdam height/lengthofdamcrest

m

Damvolume m3

Investment *

Unitindex */m3

Type

Diameter m

Length/Number

Investment *

Unitindex */m

Engineeringquantitiesof

mainconstruction

Quantityofmain

materialsused

Excavation

Openearth-rockexcavation

m3

Rock excavation intunnel

m3

FillingEarthandrock m3

Concrete m3

Cement t

Rebarandsteel t

Timber m3

Flyash t

Explosives t

Fuelmaterial t

Statictotalinvestmentintheengi-neering

*

Totalinvestmentofproject *

CapitalinvestmentinunitkW *

Totalnumberofpersonnel

Personnelinpeakperiod Person

Average Person

TotallabourhoursLabourhours

84

SHP/TG002-9:2019

Page 56: Part 9: Project Cost estimates

TableB.7(continued)

Investmentofunitannualoutput *

Capitalinvestmentinthefirsttur-binegeneratorunitforpowergen-eration

*

Totalinvestmentinthefirsttur-binegeneratorunitforpowergen-eration

*

Interestduringconstruction *

Investmentintransmission engi-neering

*

ProductionDepartmentPersonnel Persons

Totalconstruction

progress

Projectpreparationperiod Month

Constructionpreparationperiod Month

Mainconstructionperiod Month

Projectcompletionperiod Month

Constructionperiodforpowergener-ationofthefirstturbinegeneratoru-nit

Month

Totalconstructionperiod Month

NOTE “*”indicatesthecurrencyunit

94

SHP/TG002-9:2019