partnership to advance clean energy deployment …
TRANSCRIPT
ii
Technical Assistance Program
NTPC Solar Wind Hybrid at
Kudgi
Approach for Measurement and Metering
of Wind-solar Hybrids
iii
TABLE OF CONTENTS
Figures and Tables ______________________________________________________________ iv
Acronyms______________________________________________________________________ v
Executive Summary ____________________________________________________________ vii
About This Document ____________________________________________________________ x
1 Introduction ________________________________________________________________ 1
1.1 Metering Levels In Independent Solar And Wind Projects _______________________ 1
2 Possible Placements of Tariff Meters in Wind-Solar Hybrid ___________________________ 3
2.1 Measurement at Interconnection Point (Levels 3 & 4) __________________________ 4
2.2 Metering At Generator Level (Level 2) ______________________________________ 7
2.3 At Wind Turbine Generator Or Solar Block Level (Level 1) ______________________ 7
3 Proposed Measurement and Metering Approach for Hybrid Plants _____________________ 9
4 Case Study: Metering For A Hybrid Project In Karanataka __________________________ 10
5 Loss Allocation Approaches __________________________________________________ 12
5.1 Loss Allocation to Power Generators in a Hybrid Project _______________________ 12
5.2 Loss Allocation To Wind And Solar Components _____________________________ 12
6 Policy Recommendations ____________________________________________________ 14
7 Conclusion________________________________________________________________ 15
Annexure 1 Existing Policies for Wind-solar Hybrid Projects _____________________________ 16
Annexure 2 Location of Renewable Energy Meter as per CEA regulation and RPO ___________ 18
iv
FIGURES AND TABLES
Figure 1 Different possible metering levels ...................................................................................... 4 Figure 2 Proposed metering approach for wind-solar hybrid project ............................................. 10 Figure 3 Case study: Metering at Kudgi project ............................................................................. 11 Figure 4 Location of Renewable Energy Meter .............................................................................. 18
Table 1 Example of metering levels for wind and solar projects ____________________________ 1 Table 2 Scenario wise proposed metering approaches __________________________________ 9
v
ACRONYMS
ABT Availability Based Tariff
AC Alternating Current
AEP Annual Energy Prediction
ALDC Area Load Dispatch Centre
APTRANSCO Andhra Pradesh Transmission Company
CEA Central Electricity Authority
CERC Central Electricity Authority
CUF Capacity Utilization Factor
DC Direct Current
Discom Distribution Company, delivering power to a consumer
DPR Detailed Project Report
EE Energy Efficiency
EVI Emergent Ventures India
F&S Forecasting and Scheduling
GETCO Gujarat Electricity Transmission Company
GOI Government of India
GW Giga Watt = 10^9 Watt; a unit of electric power
GWh Giga Watt Hour = 1 GW of power delivered for 1 hour.
HV High Voltage
INR Indian Rupee
kV Kilovolt or 1000 Volt.
kW Kilo Watt = 10^3 Watt; a unit of electric power
kWh Kilo Watt Hour = 1 kW of power delivered for 1 hour.
KERC Karnataka Electricity Regulatory Commission
KREDL Karnataka Renewable Energy Development Limited
MNRE Ministry of New and Renewable Energy
MOP Ministry of Power
MW Megawatt = 10^6 Watts; a unit of electric power
MWh Megawatt hour; a unit of electric energy, equivalent to 1 MW electric power delivered for 1 hour.
NIWE National Institute of Wind Energy
vi
NTPC National Thermal Power Corporation
OA Open Access
OEM Original Equipment Manufacturer
PACE-D Partnership to Advance Clean Energy Deployment
PE Plant Evacuation
PLF Plant Load Factor
PPA Power Purchase Agreement
PV Photovoltaic
RE Renewable Energy
REC Renewable Energy Certificates
RPO Renewable Purchase Obligations
SERC State Electricity Regulatory Commission
SLD Single Line Diagram
SLDC State Load Dispatch Centre
SNA State Nodal Agency
SS Substation
STU State Transmission Utility
Unit In informal description of electric energy consumed; equal to 1 kWh
USAID United States Agency for International Development
WTG Wind Turbine Generators
vii
Executive Summary
Background
India has an abundance of wind and solar energy resources. Successive governments
have recognized the benefits of renewable energy as key contributor and enabler to
India’s growth, and made developing these sectors a priority. A rich and diverse
ecosystem of wind and solar companies, enabled by mature regulations has resulted
in the creation of a vibrant market, buoyed by rapid investment in these sectors. As
wind and solar technologies scale to a significant fraction of India’s energy mix, it
becomes critical to take into account their footprint in the form of land use, and use of
power evacuation infrastructure, and seek avenues for increased utilization and
efficiency of common resources. While so far, the focus for both, solar as well as wind
projects have been on technology, project implementation and policy, a more
integrated approach is needed to develop the sectors in the future. Wind-Solar1 Hybrid
projects are a new and emerging concept globally, and offer an approach to make this
resource use optimization possible. Hybrids offer several benefits such as:
1. Increased generation per square meter area of land utilized
2. Savings from shared transmission costs
3. Savings from common generation infrastructure cost
4. Reduced operating costs due to shared services
5. Balanced power mix for sale
Recognizing their potential in helping scale up renewable energy, the Government of
India has set a target to install 10 GW of wind-solar hybrid power plants by 2022 as
per the draft National Wind-solar hybrid policy.2 The states of Gujarat and Andhra
Pradesh brought out draft policies for development of Wind-Solar Hybrids. Although
hybrid projects are simply an approach to co-locating wind and solar energy projects at
a single site, the combination of the two technologies on one site presents a certain
level of complexity, which must be addressed. Sites must be chosen in a manner to
optimize generation from both types of sources, and planning must be done while
taking into account specific needs of both, wind and solar generation. These general
issues have been discussed in detail in a separate publication.
One of the most complex issues affecting hybrids is the metering of power generation,
due to issues related to energy accounting and regulatory compliance. Each state has
specific procedures for metering of independent wind and solar projects. Because
these approaches have been developed with a single developer, technology, or small
1 Through this report, when reference is made to solar, it refers to solar photovoltaic (PV) technology.
2 http://mnre.gov.in/file-manager/UserFiles/Draft-Wind-Solar-Hybrid-Policy.pdf; For further details about
the existing policies refer Annexure 1
viii
plants in mind, current approaches do not directly apply to hybrid projects. New
approaches therefore must be developed for hybrid projects given their complexity.
The paper presents key considerations in developing the metering methodology for
measuring of hybrid power generation from wind-solar sites. The paper analyzes
present practices of metering of independent solar and wind projects and the issues
that arise if similar metering approach is adopted for wind-solar hybrid projects. This
paper also presents a case study of metering implemented for a hybrid wind-solar
project installation in Karnataka.
Problem statement
While regulatory and metering regimes for independent solar and wind projects are
well developed, several challenges arise when the two are combined and common
evacuation infrastructure is used. Wind and solar generation fall under separate
regulatory regimes, with separate quotas for renewable purchase obligation for end
users, and are priced differently in the energy markets. Typically, metering for power
generation takes place at the point of feeding into the main grid, at a transmission sub-
station. A hybrid project must ensure similar metering at the grid-injection stage. But in
addition, it must also deploy a second level of metering to capture generation at solar
or wind project level. Additional complexity emerges when multiple operators own one
or more solar or wind projects co-located within a single farm. Hybrid projects can
operate in a number of situations, which necessitate a new metering approach, e.g.
The buyers of wind and solar generation from the hybrid plant are different;
The tariffs of wind and solar generation from the hybrid plant are different;
The end buyer or developer needs to meet its RPO obligations, and needs to
account for purchase from individual sources separately;
The forecasting and scheduling (F&S) norms for wind and solar are different,
with differences in permissible error band and penalties imposed for deviations;
or
Transmission and wheeling charges are different for wind and solar power.
The situations listed above are just some examples of conditions where metering of
power hybrid plants becomes critical.
Proposed Solution
This paper outlines a feasible approach for independent metering of solar and wind
generation, even when they use common evacuation infrastructure. Renewable energy
farms are often spread across large areas, at locations that are far from the point of
interconnection with utility grid. Like other projects, hybrid projects utilize shared
evacuation infrastructure to inject power into the grid, and incur transmission losses
between the point of generation (block level) and the point of grid interconnection.
Accounting for power generation at each of these levels, and intermediate levels
between generation and grid feed is critical from the perspective of proper accounting
for purpose of sale and cost allocation.
ix
The paper recommends scenario based multilevel metering, which can be a
combination of the generator level (wind turbine generator and solar block), ownership
level, the plant level and grid level metering. The four levels can be described as
follows, and are depicted in the schematic presented in Figure 1.
Level 1 - Metering at generator block level: Design of blocks in a solar plant is done
based on technical considerations, and metering at this level allows the most granular
reporting of power generation. This level of metering is required when segregation of
wind and solar generation is necessary, and can help facilitate splitting of generation at
the project level for wind and solar technologies.
Level 2 - Metering at individual plants owned by different developers within a
farm: This approach to metering becomes necessary, if there are several plants
owned by different entities in a large wind-solar hybrid park or zone. This level of
metering can consist of one or more blocks in a plant located within a farm. Level 2
metering of net energy exported from each owner forms the basis for allocation of
proportionate energy loss attributable to shared evacuation infrastructure across
projects.
Level 3 - Metering at the wind-solar hybrid park or farm level: This level of
metering is at the farm level, and measures the total renewable energy generation
from all sources, including solar and wind generation in the entire hybrid farm.
Metering at this level is net of internal losses.
Level 4 - Metering at grid substation level: This level of metering is done at the
location where power is injected into the grid at a utility substation. Wind solar hybrid
farms may be situated at locations remote from the grid, and often require evacuation
infrastructure to access the grid. In addition to losses incorporated within metering at
level 3, this level of also reflects transmission losses between the point of generation
and the point of grid injection. Typically, metering at this level is critical from a financial
accounting perspective, as it typically forms the basis of compensation to power
generators.
Depending on state regulations regarding the interconnection point, level 3 or level 4
metering, at a minimum, is typically made mandatory for all projects. Additionally, it
would probably benefit hybrid projects to also require metering for generation by each
owner, necessitating metering at level 2 or in case even greater granularity is desired,
at the block level, or level 1.
x
ABOUT THIS DOCUMENT
This document has been prepared for the United States Agency for International
Development (USAID) Partnership to Advance Clean Energy Deployment (PACE-D)
Technical Assistance (TA) program.
This document is second in part of a series of publications drawing from the
experience of designing a wind-solar hybrid plant by National Thermal Power
Corporation (NTPC), in Kudgi, Karnataka. The first publication, ‘White Paper on
Design Approach for Wind-Solar Hybrids’ focuses on design aspects such as layout,
planning and policy aspects of hybrids. This publication focuses on the metering
aspects governing the measurement and accounting of energy generation from
projects. The paper has been prepared based on meetings with stakeholders,
including Original Equipment Manufacturers (OEMs) for wind power, Ministry of New
and Renewable Energy (MNRE), Regulators (CERC, SERC), Indian Wind Turbine
Manufacturers Association (IWTMA), The Energy and Resources Institute (TERI), and
CSTEP. Stakeholder comments and suggestions on the metering approach have been
taken into account and analyzed, and recommendations are offered for metering
approaches for wind-solar hybrid projects.
1
1 Introduction
Wind and solar PV are well established and mature technologies. At present, solar and
wind projects are installed on a standalone basis, under separately defined policies and
regulations. Accounting of energy generation is a critical aspect for any power project
and over the years, a robust policy framework has been developed for metering in the
context of both, solar as well as wind projects. Metering and grid interconnection points
are typically defined for each state by the respective State Electricity Regulatory
Commission (SERC). In turn, these are developed based on guideline regulations
specified by the Central Electricity Authority (CEA)3.
1.1 Metering Levels In Independent Solar And Wind Projects
In case of independent wind and solar projects, the widely accepted metering level is at
the interconnection point of the project with the grid. Some wind projects are also
allowed to meter the generation at wind turbine generator level, if they fall under the
cluster scheme. Metering level for a specific project is subjected to state policy and
acceptance by the distribution company. The table below describes the identified
metering points for solar and wind projects in different states.
Table 1 Example of metering levels for wind and solar projects
State Policy Metering level
Gujarat solar
power policy4
Electricity generated is metered on 15-
minute time block by STU/Discom/SLDC/
ALDC at the 11 kV system of Discom.
ABT-complaint meters must be installed
for purpose of energy accounting of solar
generating projects.
Interface metering shall conform to CEA
Regulation 2014.
STU/Discom shall stipulate specifications
Grid interconnection
point
Gujarat wind
power policy5
Metering point is at 66/132/220 kV
pooling sub-station located at the wind
farm site
Interconnection point shall be the point of
connection at the nearest GETCO sub-
Plant site (outgoing
feeder)
3 Please refer to Refer to annexure 2. For more detail, visit
http://www.cea.nic.in/reports/regulation/amend_15122014.pdf 4 https://geda.gujarat.gov.in/policy_files/gujarat_solar_power_policy_2015.pdf
5 https://geda.gujarat.gov.in/policy_files/Gujarat%20Wind%20Power%20Policy-2016.pdf
2
station.
ABT complaint meter must be installed for
purpose of energy accounting, as per
GERC order.
Interface metering shall conform to CEA
Regulation 2014.
GETCO stipulates specifications
The electricity generated from the WTGs,
shall be metered and readings taken.
Andhra
Pradesh Power
Evacuation
from Captive
Generation,
Cogeneration
and Renewable
Energy Source
Power Plants6
Energy accounting for projects connected
to EHT pooling substation shall be based
on metering at the HV bus bar side in the
pooling substation.
For single owner Solar/Wind Projects
connected through a 33 kV (11 kV) line
with a pooling bus of 33 kV (11 kV) at the
project, metering for energy accounting
shall be provided at the outgoing feeder
of pooling bus. If pooling bus is not
available, metering for energy accounting
shall be provided at incoming feeder of
the 33 kV (11kV) bus bar side of the grid
substation.
Multiple Solar/Wind project developers
having meters at HV (33 kV) side of
individual generator(s) with a pooling bus
at the project, common metering point for
energy accounting shall be provided at
the outgoing feeder of pooling bus. If
pooling bus is not available, the common
metering point for energy accounting shall
be provided at incoming feeder i.e, just
before the 33 kV bus bar side of the grid
substation.
Each Solar/Wind power project will have
two metering points, one at project’s
switchyard and another metering point is
common metering point.
At plant as well as grid
interconnection point
To understand the applicability of similar methodology to a wind-solar hybrid project, let
us consider a wind-solar hybrid project in state of Gujarat. If injected power is metered at
6 http://www.aperc.gov.in/aperc1/assets/uploads/files/8d9e9-power-evac_reg_-3of2017.pdf
3
the wind-solar hybrid farm level (as per the Gujarat wind power policy), segregation of
generation for each owner and further segregation into wind and solar generation is not
possible. Similar issues will arise, if metering is done at grid interconnection point (as per
the Gujarat solar power policy). This inability to segregate leads to challenges outlined in
the next section.
2 Possible Placements of Tariff Meters in Wind-Solar Hybrid
This section outlines the different possible designs for hybrid metering. The best design
of a hybrid plant metering is decided on the basis of requirements of the consumer, the
generator and the distribution utility. Levels 1-4 define the different level of metering
possible for any wind/solar project. These levels are depicted in Figure 1 below.
Level 1 - Metering at generator block level: Design of blocks in a solar plant is done
based on technical considerations, and metering at this level allows the most granular
reporting of power generation. This level of metering is required when segregation of
wind and solar generation is necessary, and can help facilitate splitting of generation for
wind and solar technologies. This can be useful for the purpose of accounting of power
generation.
Level 2 - Metering at individual plant(s) level: This approach to metering becomes
necessary, if there are several plants owned by different entities in a large wind-solar
hybrid park or zone. This level of metering can consist of one or more blocks in a plant
located within a farm. Level 2 metering of net energy exported from each owner forms
the basis for allocation of proportionate energy loss attributable to shared evacuation
infrastructure across projects, further downstream from the plant till the point of feeding
into the grid.
Level 3 - Metering at the wind-solar hybrid park or farm level: This level of metering
is at the farm level, where electricity from all the generators is pooled this metering
reflects the total renewable energy generation from all sources, including solar and wind,
in the entire hybrid farm. Metering at this level is net of internal losses. In States, such as
Gujarat this is the interconnection point from where the transmission grid picks the
electricity.
Level 4 - Metering at grid substation level: This level of metering is done at the
location where power is injected into the grid at a utility substation. Wind solar hybrid
farms may be situated at locations remote from the grid, and often require evacuation
infrastructure to access the grid. This level of metering reflects transmission losses
between the point of generation and the point of grid injection. Typically, metering at this
level is critical from a financial accounting perspective, as it forms the basis of
compensation to power generators. This is currently the most widely accepted metering
level for both wind and solar projects across states.
4
Figure 1 Different possible metering levels
The following section discusses key features and challenges associated with metering at
all possible levels, beginning at the highest level (levels 3 or 4), and going down to the
most granular level of metering (level 1). As we see in the sections below, the ideal
solution for metering is a combination of metering at two levels or more – as this
approach provides the greatest flexibility and accuracy in measurement of generation,
while at the same time facilitating proper accounting of internal losses, transmission
losses upstream of the point of grid interconnection, and for purposes of electricity sale.
2.1 Measurement at Interconnection Point (Levels 3 & 4)
At this level the total hybrid power generation in the farm is metered prior to the
interconnection point. According to existing state level policies metering is either allowed
at level 3 (farm level pooling), or at level 4 (grid sub-station). This is the minimum
metering required by the distribution company, as it is the basis upon which, the
accounting for power sale and purchase occurs. Whether level 3 or level 4 metering is
accepted, varies from state to state.
If metering is carried out only at level 3 or level 4 for a hybrid wind-solar project, it results
in certain specific challenges that do not affect generation from wind-only or solar-only
sites. The following challenges emerge, which must be addressed through the metering
framework.
5
There is no basis for the utility or project developers to segregate power
exported by generator/owner.
There is no basis for segregation of generated power into solar or wind
components, which results in attendant challenges when it comes to accounting
for RPOs, and other obligations, as discussed below.
Challenge Discussion
Inability to segregate power injected into the grid by each generator
In absence of generator level segregation, billing for power exported by each generator is not possible. In such a case, the hybrid plant will be built without any sharing of infrastructure, resulting in erosion of savings.
Inability to segregate power into wind and solar components
If the power injected can’t be segregated into wind and solar components this results in challenges relating to
Wind and solar RPO compliance
REC qualification
Determination of transmission and wheeling charges
Determination of forecasting and scheduling compliance
Determination of Tariff
Different fiscal incentives
Challenges associated with wind and solar RPO compliance
RPO for each obligated entity is defined for solar and non-solar categories. RPO is defined in terms of % of total energy consumed by the entity. Obligated companies will not be able to utilize power purchased from hybrid farms. E.g. in 2018-19, Indian Railways, an obligated entity, is required to meet 6.75% power from solar energy, and 10.25% electricity use from non-solar sources of generation.
REC qualifications RECs and can be bought by obligated entities to meet their RPO requirements. They are sold on two power exchanges active in India, and can command significant value, currently trading with a floor price of INR 1500/MWh for both solar and non-solar RECs. A wind-solar hybrid plant, if it is not selling power to meet its own RPO target, can sell RECs. However, it will not be able to qualify unless it is able to specify how much of the total power injected into the grid comes from solar and non-solar source.
Different Fiscal Incentives Fiscal benefits vary depending on the technology, e.g. wind generators used to get Generation Based Incentive under Feed in Tariff schemes, which are not available to solar projects. In case states offer differing benefits to wind or solar, segregation of output into wind and solar may be needed.
Transmission, Wheeling and Banking Charges
Energy bought by an Open Access (OA) customer is delivered using the discom’s transmission infrastructure, and attracts transmission, wheeling and banking charges. In addition, electricity duty is payable on the variable electricity cost paid by end buyers. Transmission, wheeling, banking and electricity duty provisions differ for wind and solar power and are state specific.
Forecasting and Scheduling The Grid Code defines Forecasting and Scheduling (F&S)
6
requirements for renewable energy generators and imposes penalty if deviation from a schedule is beyond a defined limit. The schedules are 15-minute, day-ahead schedules. Up to 16 revisions in the schedule are allowed in a day. The F&S requirement varies from state to state and is often different for wind and solar generation. This requires segregation of generation into solar and wind components.
Buyer requirement or preference
A buyer of renewable energy may want to purchase specific quantum of wind or solar power, e.g. a discom may want to buy specific quantum of solar and wind because
• It has individual internal targets for wind and solar • Generation costs are different for wind and solar • It is buying electricity under feed-in-tariff programs which
have different tariffs for wind and solar • It has invited bids for wind and solar separately • PPA conditions define minimum and maximum power
injection permitted, based on technology
The table above demonstrates the range of challenges necessitating two tiered metering
for hybrid projects. Each of the regulatory requirements above are treated differently by
specific state regulation. Some examples of state specific treatment of wind and solar
energy is summarized in the table below.
Policy Area State Differential Treatment for Solar and Wind
Transmission, wheeling and banking charges
Madhya Pradesh
For solar projects, transmission, wheeling charges up to 4% are waived off and electricity duty is waived for 10 years.
100% banking is allowed up to 1 year with banking charges of 2%.
For wind projects, similar benefits are granted. However, if wind energy is sold to a third-party buyer other than discom or the generator itself, transmission and wheeling charge waiver is not available.
Haryana All transmission, wheeling, banking and electricity duty charges are waived off for solar projects, but no waivers are granted for other forms of renewables.
Karnataka Karnataka had granted complete waiver for all open access charges and losses for solar till March 2018 but has a charge of 5% for wind transmission and wheeling.
Forecasting and scheduling
Gujarat F&S requirement in the state of Gujarat define the permissible deviation depending on year of installation of wind projects, and separately for solar projects.
7 Penalties for
deviation too, vary for wind and solar.
7 The F&S Requirement in Gujarat allows deviation of ±12% for old wind projects (commissioned before
30.01.2010), ±8% for new wind projects (under section 7.5), ±7% for solar project (under section 7.7). The initial penalty for wind is INR 0.35/kWh, increasing to INR 0.70/kWh and INR1.05/kWh, and for solar, the
7
As can be seen, metering at level 3 or level 4 alone may result in several practical and
policy related challenges in implementation. These levels of metering are only suitable
if a hybrid project doesn’t require separate tariffs for wind and solar energy, is not
focused on meeting RPO or qualifying for REC, or the project site is located in a state
where F&S requirement are same for wind and solar projects. In most cases, additional
metering at a lower level would be required. We discuss those approaches below.
2.2 Metering At Generator Level (Level 2)
Metering at this level enables generator level segregation of energy, injected into the
grid from a hybrid farm. The segregation will be achieved as outlined in section 5.1. This
approach is necessary for those hybrid parks that have many generators owning
different generating plants and using the common evacuation infrastructure. For
supporting billing by each generator, level 2 metering must to be added in addition to
metering at level 3 or level 4, as desired. Metering at this level may not be required if the
entire hybrid farm has only one generator or if generators don’t use shared evacuation
infrastructure within the farm. At this level of metering, it is not possible to segregate the
wind and solar components and therefore, same challenges as outlined above are
applicable.
Level 2 metering is necessary, in conjunction with metering at level 3 or level 4, if the
hybrid farm has many generators and they use a shared evacuation infrastructure. If
there is only a single generator, metering at this level becomes redundant.
2.3 At Wind Turbine Generator Or Solar Block Level (Level 1)
With level 1 metering, coupled with metering at level 3 or level 4, separate accounting of
wind and solar generation is possible. This can be achieved using the loss allocation
approach outlined in section 5.1. The benefits of this approach are:
o Solar and non-solar RPO can be met
o Solar and non-solar REC can be issued
initial penalty is INR0.60/kWh, increasing to INR1.2/kWh and INR1.8/kWh. See Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources Regulations, 2017; available at http://gercin.org/uploaded/document/8f42601e-b8dd-4f6f-9a08-f6d3f08dc662.pdf
8
o Power sale and tariff determination for solar and wind is possible, individually.
o Individual F&S requirement of wind and solar generation can be met
o Special fiscal and financial incentives for solar projects and wind projects can be
availed.
One of the challenges associated with this approach is that the number of meters to be
installed increase. For example, in a hybrid plant of 300 MW, with 75 MW of wind and
225 MW of solar, there may be 38-40 wind generators and 38-40 solar blocks. Level 1
metering in such a farm will result in installation of 80 meters, a significantly large
number. An approach of clustering wind turbine generators and solar blocks may be
adopted, especially in large hybrid farms, to minimize number of meters installed.
Currently, metering at level 1 is only allowed for clustered, independent wind and solar
projects but not widely practiced. Policy changes are required to permit wind turbine
solar block level metering for hybrid projects. An optimization approach may also be
required, in order to optimally cluster solar and wind blocks in a manner that manages
the number of metering locations, while keeping the benefits of shared evacuation
intact.
9
3 Proposed Measurement and Metering Approach for Hybrid Plants
From the above discussion and analysis, it can be inferred that the metering for wind-
solar hybrid projects should facilitate segregation of energy generation for different
generators into wind and solar components. Key factors such as ownership by one or
more developers within the farm, requirements of buyer of the power generated, and
state specific regulation all must be taken into account to develop the optimum approach
for metering. This section provides the best-fit approach to resolve the issues discussed
in the previous section and present some examples of scenarios where specific metering
approaches become necessary. A few commonly encountered scenarios, and
appropriate metering approaches are listed in Table 3.
Table 2 Scenario wise proposed metering approaches
Scenario Metering Recommendation
Generator: Single
Buyer: Single (indifferent to type of resource)
Delivery point: plant sub-station/ grid sub-station
F&S requirement: Same for wind & solar
REC: Not claimed
For delivery at plant substation:
Level 3
For delivery at grid substation:
Level 4
Generator: Single
Buyer: Single (without RPO requirement)
Delivery point: Plant or grid sub-station
F&S requirement: Different for wind & solar
RECs: Generator can claim
For delivery at plant substation:
Level 3 and Level 1
For delivery at grid substation:
Level 4 and Level 1
Generator: Single
Buyer: Multiple (with RPO requirement)
Delivery point: Consumer’s grid connection
Generator can use technology specific provisions for
wheeling, transmission, banking, generation-based
incentives
At Level 4 and Level 1
Generator: Multiple
Buyer: Multiple (with RPO requirement)
Delivery point: Consumer’s grid connection
Generator can use technology specific provisions for
wheeling, transmission, banking, generation-based
incentives
At Level 4, Level 2 and Level 1
Discoms currently only accept level 3 or level 4 metering for billing purposes. Additional
metering at level 1 or level 2 will allow segregation of power generated from wind and
solar, as well for different owners. Net energy generation can be calculated by
apportionment of evacuation loss to each wind generator and solar block.
Refer section 5.1 for loss apportioning approach in case of wind-solar hybrid project.
10
Figure 2 Proposed metering approach for wind-solar hybrid project
This metering approach can be used for projects where AC side outputs from wind and
solar blocks are integrated i.e. common feeder lines take electricity generated from wind
turbines and solar blocks to the pooling substation. This allows savings on evacuation
infrastructure costs. This approach will not work in case of DC side integration and solar
and wind generators (DC output of solar feeding DC input into the wind generator).
However such combinations are rare.
4 Case Study: Metering For A Hybrid Project In Karanataka
To clarify various considerations involved in developing a metering plan, let us consider
a hybrid farm of 300 MWp capacity in Karnataka.
The farm has single owner (generator).
The delivery point is at plant substation, where the grid interconnection is
provided.
Because there are other industrial facilities inside the farm boundary, the hybrid
capacity is developed on vacant land available in 2 clusters.
While designing it was found that the capacity mix of wind and solar generation in the 2
clusters is such that number and capacity of evacuation cables will not change
significantly even when wind and solar power, from each cluster, is taken independently
to the plant-pooling substation. Hence in this project, metering is carried out as follows
Level1 – cluster level. The total number of wind and solar clusters metered are 8.
11
Level 2 metering is not needed as the farm is owned by a single owner.
The grid interconnection point is at the plant itself, hence Level 3 metering is
planned and level 4 metering is not required.
At the 33kV side of pooling sub-station, 8 (Level 1) energy meters are installed, which
are measuring wind and solar power. On HT side (220 kV) of pooling sub-station the
final tariff meters are installed (Level 3). These tariff meters account for total energy
evacuated from the entire farm. The loss allocation is based on the 8 energy meter
installed at 33 kV side. The loss allocation allows segregation of final injected power into
wind and solar generation.
Figure 3 Case study: Metering at Kudgi project
12
5 Loss Allocation Approaches
5.1 Loss Allocation to Power Generators in a Hybrid Project
This is possible in case of hybrid projects that incorporate a combination of metering at
level 3 or 4, with level 2. Segregation of final power injected from a hybrid farm, into
generator level power can be achieve as follows:
Where,
Mt - Total delivered energy at interconnection point (level 3/4 measurement)
Mi - Total power delivered by a plant owner ‘I' into the shared evacuation
infrastructure (level 2 measurement)
N – Number of generators
For example, in a hybrid farm, there are 2 generators each generating 280 MWh
(recorded at level 2 metering). They use a common infrastructure to evacuate to the
farm substation (level3), and energy injected into the grid is recorded at 550 MWh.
Loss Li = (280+280- 550)/(280+280) = 1.78%
Actual hybrid generation delivered by each generator at the interconnection point ~
280*(1-1.78%) = 275 MWh
That is, the total loss of 1.78 percent is allocated to the generators proportionately as per
their contribution to the total generation.
5.2 Loss Allocation To Wind And Solar Components
Segregation of final power generated from a hybrid generator/owner, into solar and wind
components can be achieved as follows:
13
Where,
Mi - Total power metered by a Plant Owner infrastructure (level 2 measurement)
M – Number of solar and wind blocks for generator i
Msi = measurement for solar generation at a solar block (level 1), for generator i
Mwi = measurement for wind generation at a wind block (level 1), for generator i
The total solar energy injection for generator i SMSi = ΣMSi x Li
The total wind energy injection for generator I SMWi = ΣMWi x Li
For example the total generation from wind generator (ΣMw) is 100 Mwh and from solar
blocks is (ΣMs) 200 MWh
Total energy delivered (Mi) is recorded as 280 MWh
Therefore, Loss Lwsi = (200+100-280)/(200+100) = 6.6%
Solar generation at generator level = 200 x (1- 0.066) = 186.8 units
Wind generation at generator level = 100 x (1-0.066) = 93.4 units
Solar energy injected by the Generator into the grid = 186.8*(1-1.78%) = 183.5 MWh
Wind energy injected by the Generator into the grid = 93.4*(1-1.78%) = 91.8 MWh
14
6 Policy Recommendations
As is evident from the discussion in sections above, hybrid projects present several
accounting and generation apportionment challenges in the context of a policy
framework that treats solar and wind generation differently, and a scenario where
generation from renewable energy sources is priced differently. As India progresses
along its path towards greater deployment of hybrid projects, several policy changes can
be developed in a manner which is cognizant of such arrangements, and streamline
implementation, thereby making it easier to develop hybrid projects. There are two
possible approaches to solve the solar wind hybrid metering issues.
Acceptance of multi-level metering as part of the policy framework: The
multi-level metering approach described in this document, can segregate the
energy injected into various components as required by different policy regimes
in the country.
This approach will need to be formally accepted in all states.
Convergence in policy treatment of solar and wind: As wind and solar
capacities scale up in India, it is seen that policy treatment for the two is
converging, e.g. tariffs discovered in bidding for wind and solar bids in 2017
have both discovered levels of INR 2.44-2.47 per kilowatt-hour. Several other
factors strengthen this case, e.g.
o States are opting for similar open access policies for solar and wind, with
differences being reduced. Special support to solar is now being withdrawn.
o Forecasting and scheduling standards are now being harmonized across
wind and solar and many states have same standards for both technologies.
o In discussion with policy makers, it appears that the difference between non-
solar and solar RPO will be eliminated in near future, and there will be greater
flexibility to meet RPOs by either technology.
In such cases, it may be useful to consider total injected power as renewable, not
requiring segregation into wind or solar, or allowing flexibility to treat injected power as
wind or solar depending on the commercial needs. Such a policy will however require
deeper consideration at center and state levels and may not be immediately
implementable.
15
7 Conclusion
Hybrid projects are a new concept internationally and in India, and present several
challenges which must be addressed by a collaborative approach between developers,
state and central government, and regulators. Hybrid projects can help maximize the
generation from a given land area, and help drive lower cost of generation. Hybrid
projects also result in savings in terms of common utilization of capital expenditures, e.g.
cost of evacuation infrastructure.
Issues related to energy accounting, Renewable Portfolio Obligations, Renewable
Energy Certificates, Forecasting and Scheduling, Open Access charges etc. can be
handled by segregating solar and wind generation, and the paper recommends a bi-level
metering approach that can be developed to address unique challenges of using
common evacuation infrastructure.
It is proposed that regulators take an approach for metering of wind-solar hybrids in a
manner so as to permit wind and solar level segregation of injected power, and allow fair
loss allocation approaches to both sources, as recommended in the paper.
In the long run, India would benefit if policymakers increasingly focus on technology
neutral regulation, and make active attempts to align approaches to forecasting and
scheduling, wheeling and distribution, as well as develop incentive mechanisms such as
generation based incentive or net metering in a manner that is suitable for multiple
technologies, especially solar and wind. Market signals such as pricing discovered in
recent bids, and a convergence of prices of renewable power from multiple sources in
recent months further strengthens the argument for treatment of solar and wind
technology on an equal footing.
Government of India targets addition of 10 GW of hybrid capacity by 2022. This
ambitious target needs strong policy support, and can help become a significant driver
for implementation of hybrid projects across the country. Discussions presented in this
paper, and accompanying publication ‘White paper on Design Approach for Wind-solar
Hybrids’, being made available alongside this document make a strong case for the
critical role hybrid projects can play in effective utilization of resources.
16
ANNEXURE 1 EXISTING POLICIES FOR WIND-SOLAR HYBRID PROJECTS
National Wind-solar Hybrid Policy Draft, 20168
The draft National Wind-solar Hybrid Policy sets a goal of 10 GW capacity by 2022. It
allows the implementation configuration to be based on AC or DC integration. The policy
allows existing wind and solar plants to be hybridized (known as Brownfield projects),
and also includes provisions for development of new hybrid plants (knows as Greenfield
projects). Under the policy, hybrid power can be procured through a transparent bidding
process under different mechanisms. Parameters that may be considered for bidding
include total capacity, capacity utilization facto (CUF) and unit price of electricity. Hybrid
power generation can be used by distribution companies to offset their solar and non-
solar Renewable Purchase Obligations (RPOs). All fiscal and financial incentives
available for independent wind and solar power projects can be made available for the
wind-solar hybrid projects. The policy envisions making low cost financing available for
projects through Indian Renewable Energy Development Agency (IREDA), multilateral
banks, and other financial institutions.
Andhra Pradesh Wind-solar Hybrid Power Policy Draft – 20169
Under this draft policy, Government of Andhra Pradesh (GoAP) has described the
complementary power generation profile of wind and solar in the Rayalaseema belt. The
policy remains in force for five years or till the next policy issuance. This policy sets the
basis for a way forward for wind-solar hybrid projects in Andhra Pradesh. The
configuration of projects is defined as combined generation or co-located or co-injection.
The plants will be categorized on the basis of their allocation before and after issuance
of policy and named as type A and type B hybrid plants. Type A is for existing,
operational, under-construction and allotted wind or solar power plants and type B is for
proposed wind or solar power plants.
In the case of new allocated projects, the choice of capacity split between wind and solar
lies with the developer. The capacity mix (wind:solar) can vary from floor ratio of 1:0.6
and ceiling ratio of 1:1.5. Solar and wind power are separately metered. For these
projects, grid connectivity with the Andhra Pradesh Transmission Company
(APTRANSCO) is proposed to be based on Ampacity i.e., limiting the amperes that
would flow in the transmission network, in opposition to MVA/MW connectivity. This
provides ease to developers in optimizing the sizing of the wind-solar hybrid project.
Tariff for sale of power to Andhra Pradesh distribution companies (APDISCOMs) will be
8 http://mnre.gov.in/file-manager/UserFiles/Draft-Wind-Solar-Hybrid-Policy.pdf
9 http://ukmspower.com/attachment/Draft_wind_solar_hybrid_policy_2016.pdf
17
based on Feed- in- Tariff (FIT). Incentives available for independent solar and wind
projects are expected to be given. These projects avail the must run status similar to
other renewable energy power plants.
GoAP incentives remain in force for 25 years from the date of commissioning of the
project. Details of the incentives:
a. Power Evacuation: Projects will be exempt from paying supervision charges to
APTRANSCO/DISCOM towards the internal evacuation infrastructure within the plant site
and up to pooling sub-station.
b. Distribution Losses are exempt for feeding power at 33 kV or less.
c. There will be NO transmission and distribution charges for wheeling of power within the
state, and for sale outside the state, wheeling charges will be according to APERC.
d. Banking of 100% of energy shall be permitted during all 12 months of the year (April-
March). Banking charges shall be adjusted in kind at 2% of the energy delivered at the
point of drawl.
e. The cross subsidy surcharge shall be exempt for third party sale within the state for a
period of five years from Commercial Operation Date (COD). All hybrid power projects
are exempt from paying Electricity Duty for selling power to APDISCOMs.
Gujarat Wind-solar Hybrid Power Policy Draft - 201710
The Gujarat draft wind-solar hybrids policy remains in force for five years from the date
of issuance. Projects developed under the policy become eligible for availing benefits for
twenty five years from the date of commissioning. The policy suggests that the project
will be under AC integration configuration i.e., AC output of wind and solar generation
will be integrated at the pooling end sub-station, and wind and solar generation will be
metered separately. Projects are categorized as Type A (existing or under construction
wind/solar projects) and Type B (new wind-solar hybrid projects). The capacity mix
planning is kept open for the developer. Installation of the availability based tariff (ABT)
meter is mandatory on each turbine and solar project. Internal connectivity between
solar and wind capacity is not allowed prior to pooling end sub-station. The tariff will be
decided by competitive bidding (reverse bidding wherever required) for both Type A and
Type B projects, undertaken by DISCOMs separately for wind and solar. Transmission
charges applicable are similar to any normal open access consumer for captive use or
third-party sale.
10 https://gujepd.gujarat.gov.in/uploads/DRAFT%20GUJARAT%20WIND%20SOLAR%20HYBRID.pdf
18
ANNEXURE 2 LOCATION OF RENEWABLE ENERGY METER AS PER CEA
REGULATION AND RPO
Figure 4 Location of Renewable Energy Meter
Main Meter is a meter which will primarily be used for accounting and billing of
electricity.
Check Meter is a meter which shall be connected to the same core of the Current
Transformer (CT) and Voltage Transformer (VT) to which the main meter is connected
and shall be used for accounting and billing of electricity in case of failure of main meter.
Interface Meter is a meter used for accounting and billing of electricity, connected at the
point of interconnection between electrical systems of generating company, licensee and
consumers, directly connected to the Inter-State Transmission System or Intra-State
Transmission System (covered under ABT and has been permitted open access by the
appropriate commission).