paul y. construction company, limited
TRANSCRIPT
Paul Y. Construction
Company, Limited
West Island Line Contract No. 713
Re-Provisioning of Kennedy Town Swimming Pool (Phase 2)
NEC3 Option A - Project Mid-Term Report Card : 10th November 2015
Nov 2015
Page 2
Content
Part 1: Project Information
Part 2: Project Constraints & Challenges
Part 3: Adoption of NEC3 Option A with MTRCL Amendments
Part 4: NEC3 Project Workflow
Part 5: Implementation of NEC3 to enhance productivity
Part 6: Typical Presentation Materials used in Risk Reduction
Meetings
Part 7: NEC3 Benefits & Challenges
Part 8: NEC3 Project Experience Sharing
Part 9: Mid-term Achievements
Nov 2015
Page 4
Project Information Summary
Phase 1 Phase 2
Contract No. Contract 710 Contract 713
Contract Start Date 14th July 2009 1st September 2014
Contract Completion Date 14th March 2011 30th October 2016
Contract Period 20 months 26 months
Form of Contract MTR Lump Sum Contract NEC3 Option A (with relevant clauses of MTR Conditions of
Contract)
Contract Sum (Approx.) HK$ 311 million HK$ 671 million
Total Gross Floor Area 13,494 m2 7,058 m2
Final Account Agreement April 2011 November 2016 (envisaged)
Project Name Re-Provisioning of Kennedy Town Swimming Pool
Nov 2015
Page 5
Scope of Work Summary
1. Bored Piles and Pile Caps 2. Superstructure – RC and Structural Steel 3. Architectural Building Works and Finishes 4. Phase 1 Interfacing and Improvement Works 5. Building Services 6. Built-in Furniture 7. Landscaping
Nov 2015
Page 6
19
1/F Plan +13.500 mPD : Pool Deck
Phase 2 Phase 1
Multipurpose Pool
15m x 25m
Training Pool
12.5m x 15m
Jacuzzis
Main Changing Rooms
on Split Levels
Family cum Disabled
Changing Rooms
Project Information – Building Facilities
15 30
Leisure Park
Zone1 Zone2 Zone3
G/F Floor Plan + 4.5 mPD : Leisure Park
Nov 2015
Page 7
Project Information - Completed Roof 3D Layout
• 3D View
PTFE Layer
VM Zinc Roof Cladding
Sunshading Area
Structural
Steel Frame
Nov 2015
Page 8 Duranta repens golden
假連翹
Tabebuia rosea
紅花風鈴木
Tabebuia tabebuia chrysantha
黃花風鈴木
Timber Benching Granite paving varying in color and size
Project Information – Leisure Park
Nov 2015
Page 11
Project Constraints & Challenges:
1. Previous Experience on NEC3 – NONE! 1st NEC3 Contract for both MTRCL &
Paul Y.
2. NEC3 training – Extensive NEC3 training given to MTRCL and Paul Y staff
during early part of the Project.
3. Only 1 site logistic route.
4. Triangular Shape Site – surrounded by busy roads.
5. Tight working schedule – Contract period = 26 months.
6. Interface work to integrate Phases 1 and 2 – Tight work schedule - to complete
in 10 months (Dec 15 to Sept 16) to comply with LCSD Phase 1 operation
requirement.
Nov 2015
Page 12
Project Constraints & Challenges (Cont.):
7. Stakeholder involvements –
• Leisure and Culture Service Department (LCSD)
• Architectural Service Department (ASD)
• Electrical and Mechanical Service Department (EMSD)
• Drainage Service Department (DSD)
• Railway Development Office (RDO)
• Central & Western District Council (C&WDC)
• Local residents
Nov 2015
Page 14
Purposes of Amending NEC3 Clauses
i. Suit MTRCL Practice
ii. Meet Local Practice
iii. Satisfy Current Project Nature
Nov 2015
Page 15
Purpose of Amending NEC3 Clauses
• Revise the date for PM to certify Completion from within 1
week to within 1 month of Completion
• Suit MTRCL’s required time in processing Completion
application
Example 1: Clause 30.2
i. Suit MTRCL Practice
• Original • Amendment
Suit MTRCL’s Practice
Clause 30.2
• “The Project Manager decides the date of
Completion. The Project Manager certifies
Completion within one week of Completion.”
• “The Project Manager decides the date of
Completion. The Project Manager certifies
Completion within one month of
Completion.”
Nov 2015
Page 16
Purpose of Amending NEC3 Clauses
• Code of Conduct is one of MTRCL’s core values
• To ensure this commitment, relevant clauses are added
Example 2: Clause 91.8 added
i. Suit MTRCL Practice
• “The Contractor, any subcontractor or any employee does not offer, given or
taken any gratuity, bonus, discount, bribe or loan of any sort to an employee of
the Employer, to the Project Manager or to any member of the Project
Manager’s staff or to the Supervisor or to any member of the Supervisor’s staff.
If so discovered the Employer forthwith requires the dismissal and removal from
the Site of such subcontractor or employee and holds the Contractor liable for
any loss or damages which the Employer sustains. In the event the Contract
that defaults then the Employer may terminate forthwith the Contractor’s
obligation to Provide the Works as if for any of the reasons R1-R15 under
Clause 91, and hold the Contractor liable for any loss or damage which the
Employer may thereby sustain.”
Nov 2015
Page 17
Purpose of Amending NEC3 Clauses
• Parent Company Guarantee and Performance Bonds are to be
provided before payment made by MTRCL
Example 3:
i. Suit MTRCL Practice
Clause X4.3 added
• “No payments which may otherwise have become due under the
Contract shall be made by the Employer to the Contractor until such
time as the guarantee referred to in Clause X4.1 has been accepted by
to the Employer.”
Clause X13.2 added
• “No payments which may otherwise have become due under the
Contract shall be made by the Employer to the Contractor until such
time as the bond referred to in Clause X13.1 has been accepted by to
the Employer.”
Nov 2015
Page 18
Purpose of Amending NEC3 Clauses
• Additional clauses are added to make sure the guarantee is
submitted by individual JV partners of the Contractor if
applicable.
Example 4: Clause X4.2 added
i. Suit MTRCL Practice
• “If the Contractor comprises two or more companies acting in
partnership, joint venture or otherwise, the Contractor gives to the
Employer a parent company guarantee in respect of all companies
acting in partnership, joint venture or otherwise and additionally a joint
and several guarantee executed by all such companies both in respect
of the Contractor’s performance and in the forms set out in the Works
Information. If the guarantees were not given by the Contract Date, it is
given to the Employer within four weeks of the Contract Date.”
Nov 2015
Page 19
Purpose of Amending NEC3 Clauses
• NEC3 Contract is originally published in United
Kingdom (UK)
• Weather conditions are based on UK’s climate
• Contract clauses are amended based on local
weather conditions in Hong Kong
ii. Meet Local Practice
Nov 2015
Page 20
Original
• “A weather measurement is recorded
– Within a calendar month,
– Before the Completion Date for the
whole of the works and
– At the place stated in the Contract
Data
The value of which, by comparison with
the weather data, is shown to occur on
average less frequently than once in ten
years.
Only the difference between the weather
measurement and the weather which the
weather data show to occur on average
less frequently than once in ten years is
taken into account in assessing a
compensation event.”
Amendment
• “A weather measurement is
recorded as one or more of the
following weather conditions:
– The hoisting of tropical
cyclone warning signal No.
8 or above, or
– A Black Rainstorm
Warning.”
Purpose of Amending NEC3 Clauses
ii. Meet Local Practice
Example 5: Clause 60.1(13)
Nov 2015
Page 21
Purpose of Amending NEC3 Clauses
Contract Data Part One was amended to cover re-
measurement of piling works
• Piling works are subject to ground conditions which
may vary from design assumptions based on site
investigations
• Actual quantities cannot be determined during the
design stage
• Re-measurement of piling works are a fair system
to pay contractor based on actual works done on
site.
iii. Satisfy Current Project Nature
Nov 2015
Page 23
Traditional (Non NEC) MTR Work Flow
- Contractor to raise RFI for queries
- MTR to reply RFI with required info
- Not an Engineer’s Instruction
Request for Information
(RFI)
Design Queries
Design Changes/ Variations
Drawing Issue Sheet
(DIS)
Major amendments to drgs
Minor amendments to drgs
Drawing Amendment
Sheet (DAmS)
Engineer’s
Instruction (EI)
- Major amendments to drgs
- EIs to cover DamS/ DIS
• Significant cost implication *
• Affect other interface contracts
MTR to seek prior approval
before issue EI/ DAmS
• Affect site safety
• Affect site progress & cause delay
• Small cost implication *
MTR to issue EI/
DAmS/ DIS directly
Form C Approval MTR to issue
EI/ DAmS
Form C Approval Form C Approved
Retrospectively
* Usually internal assessment without prior agreement with the Contractor
Design Meeting
- Discuss design issues
- Resolve Contractor’s queries
Scenario 1
Scenario 2
Nov 2015
Page 25
Potential Early Warning (PEW) System
MTR to Issue PEW when:
1) Potential Design Change affects Scope of Work &
Construction Method
Paul Y to Issue PEW when:
1) Discrepancies between Works Information,
Construction Drawing and/or Specifications
2) Outstanding Design Information
3) Design Change Technical Queries
Nov 2015
Page 26
Potential Early Warning (PEW) System
Design Technical Meeting Every Wednesday Morning
Nov 2015
Page 27
Potential Early Warning (PEW) System
Based on the Agreed Technical Solutions, Paul Y
will develop the Construction Methodologies:
1) Change in scope of work,
2) Revised Construction Method,
3) Programme effect,
Afterwards, Paul Y will issue an Early Warning (EAR).
Nov 2015
Page 28
Early Warning (EAR) in Risk Reduction Meeting
Risk Reduction Meeting Every Tuesday (Based on EAR)
Paul Y will then assess the cost & time implications and present
them to MTR.
Nov 2015
Page 29
MTRCL – issue PMI to reply the Early Warning to
seek time and cost quotation for Paul Y to reply
within 3 weeks.
Paul Y – concurrently prepares detailed cost & time
estimates to respond to PMI when received.
Deadline to reply to PMI is within 2 weeks.
Project Manager Instruction (PMI) and Compensation Event (CE)
Nov 2015
Page 30
MTRCL – issue Compensation Event based on the
agreed time and cost quotation.
Paul Y – No further action needed. Item closed.
Project Manager Instruction (PMI) and Compensation Event (CE)
Nov 2015
Page 31
Compensation Event (CE) In CE Meeting
Compensation Event Meeting
Weekly CE Meeting to discuss the CE items:
1) Paul Y to advise likely time & cost effects of CE items.
2) MTRCL and Paul Y to discuss & agree the time and cost effects of the CE items.
Nov 2015
Page 33
Via Sharepoint
by Thur noon
Risk Reduction Meeting
(2 hours)
Design Meeting
(2 hours)
Internal Meeting
(1 hour)
Compensation Event Meeting
(1 hour)
Early Warning Register
PEW Summary
CE Register
• Works / CM Meetings to be held bi-weekly on Tuesdays before Risk Reduction Meetings
• Sketch/ DamS/ DIS Register is contained in PEW Summary
Mon Tue Wed Thur Fri
KPI Summary
• Update EAR Register
• Add any PEW / EAR items
By email
• Review EAR Register
• Review PEW Summary
• Add any PEW from DDC
Submit EAR via ePMS
• Review quotations
• Update CE Register
Risk Reduction
& Mitigation
Cost/ Time Assessment
Prepare DamS
Update EAR/ PEW
Register
Project Management
Update KPI Summary for
Weekly PM Report
Report Writing
NEC3 Work Flow – Regular Meeting Schedule
Nov 2015
Page 34
Assessment of Compensation Events
During Design Meetings
• An ideal platform for MTRCL, Consultants and Paul Y to have open discussions on how changes can best be technically accommodated in the Works.
During Risk Reduction Meetings
• Aimed at expediting the construction and commercial approval process, Paul Y prepares PICTORIAL diagrams to illustrate the construction method and effects on working schedule.
During CE Meetings
• MTRCL & Paul Y commercial teams to discuss and agree on the cost effects of the CE items basing upon the agreed construction method and programme impacts.
Nov 2015
Page 35
Statistical Comparison
KPI Phase 1 Phase 2 *
Request for Information (RFI) 717 83 (Discontinued 4 months after contact commencement because it has duplicated EAR functions)
Early Warnings (EAR) - 131
Drawing Amendment Sheet (DAmS) 65 40
Engineer’s Instruction (EI) (no agreed time and cost quotations, to be settled
later)
63 -
Project Manager’s Instruction (PMI) (seek Paul Y’s time and cost quotations within 3
weeks from day of issue and MTRCL to agree within
2 weeks upon receipt of quotations)
- 105
Compensation Event (CE) (to conclude PMI within 5 weeks of issue)
- 92
* Up to of 26 October 2015
Nov 2015
Page 36
KPI Monitoring Summary Early Warning and Compensation Event Summary
Current status: 1) CE events quotation – 98% agreed. 2) Early Warning - 90% closed out. 3) MTRCL’s response to Paul Y submissions = Average 10 days.
Nov 2015
Page 37
Project Management – More Benefits in NEC3 workflow when compare with
traditional workflow
Issues Traditional Workflow NEC3 Workflow
Submission of technical query to
the Engineer / PM
Request For Information (RFI) (No time
limit set for response)
Early Warning (EAR) (Target to respond
within 14 days under Contract 713)
Contents in the submission Usually concentrate on current
construction issues.
All current / future issues affecting
project time and cost.
Engineer / PM feedback 1) Response usually without contractor’s
input.
2) Limited resources, slow response.
3) Usually prioritize response to urgent
issues. Other un-resolved issues keep
piling up.
1) Integrated response achieved based
on coordination among the Engineer,
PM, Contractor and Consultant
2) Adequate resources are provided up
front.
3) Sort out all issues according to the
agreed action dates.
Effects on project 1) The purpose is to solve the
immediate construction issue without
affecting site progress.
2) Works changes are carried out
without any prior agreement reached
on time and cost implications.
1) Register all issues affecting the
project in a systematic manner.
2) No changes of works are carried
out without any prior agreement in
principle reached on time and cost
implications.
Nov 2015
Page 40
Additional Works Due to Design Change
A. EAR0068
• Contract drawings do
not provide RC detail
for the following E&M
fitting installations:
1. Spa Jet Fitting
2. Supply Inlet Fitting
3. Vacuum Fitting
4. Sampling Fitting
5. Level Sensor Fitting
Nov 2015
Page 41
Location Plan For Additional Recess
Swimming Pool plan showing the original and additional RC recess locations
Nov 2015
Page 42
Elevation of Multi-Purpose Pool
Multi-purpose pool - Pool basin
elevation showing the original and
additional RC recess locations
Nov 2015
Page 43
Elevation of Multi-Purpose Pool
Additional Recesses
E3
E4
Multi-purpose pool - Pool basin
elevation showing the original and
additional RC recess locations
Nov 2015
Page 44
Elevation of Training Pool
Training Pool - Pool Basin
Elevation showing the original and
additional RC recess locations
Nov 2015
Page 45
Elevation of Training Pool
Training Pool - Pool Basin
Elevation showing the original and
additional RC recess locations
Nov 2015
Page 46
Additional Recesses in Pool Slab & Wall
Summary
Pool Type Original
Recesses
Additional
Recesses
Revised Total
Recesses
Multi-Purpose Pool (Zone1) 18 19 37
Multi-Purpose Pool (Zone2) 14 15 29
Training Pool 16 24 40
Jacuzzi 0 24 24
Nov 2015
Page 47
Typical Example: Pictorial Presentation – change in work sequence to
mitigate project risks 1) Pictorial Presentation Method to illustrate the methodology 2) Bar Chart Presentation Method to illustrate the time Justification
Finally, Come to a mutually agreed solution
Nov 2015
Page 49
NEC3 Benefits
1. Potential project risks are identified through the Early Warning System.
2. Communication enhanced amongst project team members through frequent discussions on potential time and cost implications.
3. Thorough understanding of the project through team members’ direct participation in the preparation of presentation materials.
4. Potential risks are effectively mitigated through the Risk Reduction System.
5. Relevant details are captured contemporaneously through the Compensation Event System to expedite the agreement on time and cost effects in a timely manner.
Nov 2015
Page 50
NEC3 Benefits (cont.)
6. Construction productivity is significantly improved as most risks have been mitigated.
7. Early agreement on CE items enables early conclusion of final account.
8. Project cash flow and cost control are improved through early agreement and payment on CE items.
9. Agreement on CE items are expedited as quotations are prepared concurrently with MTR’s preparation of PMI once the construction methodology on a CE item is agreed in Risk Reduction Meeting.
Nov 2015
Page 51
NEC3 Challenges
1. MTRCL & Paul Y team members are required to attend extensive NEC3 trainings.
2. Great challenge for team members to adapt to NEC3 philosophy in the beginning.
3. Considerable amount of time is spent in coordination workshops which are not very productive initially.
4. Extra resources are required to prepare programmes & pictorial presentations on CE items.
Nov 2015
Page 52
NEC3 Challenges (cont.)
5. A significant amount of technical documents are required to substantiate changes and the resultant effects (both time and cost).
6. Tight schedule specified for preparation of quotation and commercial justifications = within 3 weeks.
7. Prior to the building up of trust between MTRCL and Paul Y in the beginning of the Contract, open-minded discussions appear difficult. This was overcome once mutual trust is established within a short time .
Nov 2015
Page 54
Facilities / Resource
provided for 713 project Effectiveness
1 Joint Site Office All issue can be discussed and solved
immediately on site
2 Joint PM Office All technical, programme and contractual
issues can be discussed and resolved
immediately
3 Joint Whatsapp Group Creative communication for urgent issues
4 Additional Staff Resource Provision of additional resources to meet the
project need
Project Facilities and Resources to enhance Communication
Nov 2015
Page 56
Design
Consultant
MTRCL
Engineer
Joint PM Office
Paul Y. Engineer
PM Office, 27/F
PM Office, 36/F
Paul Y. Management Staff
MTRCL
Management Staff
Nov 2015
Page 57
Joint WhatsApp Groups for integrated communication
WhatsApp Groups Listed below:
1. MTR713 Safety Group
2. MTR713 RC Structure Group
3. MTR713 Steel structure Group
4. MTR713 ABWF Group
5. MTR713 Survey Group
Nov 2015
Page 59
Item Challenges Real Situation facing during
NEC3 system running Solution
1 Fixed time frame
for response
Time rush in different stages for
different groups of team members:
a) To prepare technical solution
b) To prepare methodology
presentation
c) To submit quotation
d) To access quotation and issue
CE item
1) Additional resources (Engineer,
QS, Programmer, Administrator)
during Project Operation.
2) Close coordination between
team members for early
preparation of documents at
each stages
2 Not fully familiar
with NEC3
workflow procedure
1) Workflow is complex to follow
2) To understand the NEC3
workflow requirements for
document preparation.
1) NEC3 training given to the
working team
2) Acquired NEC3 working
experience through sharing
sessions with project team
members as well as to learn
from other NEC3 projects
3 Lack of trust and
cooperation in
early stage of
project
1) Natural human thinking to
protect the interest of his/her
organization
1) Worked hard to change the mind
set of all the team members.
2) Early involvement and support
of management to build up trust
and cooperation.
NEC3 Project Lessons Learnt Summary
Nov 2015
Page 60
Item Challenges Real Situation facing during
NEC3 system running Solution
4 Numbers of regular
meetings required 1) Meetings are time-
consuming.
1) Define the purpose of each
meeting for time efficiency
2) Preparation in advance for
easy understanding (such
as Time comparison
program, pictorial change in
working sequences, etc)
5 Creative
Communication 1) Communications are not
limited to only progress
meetings, e-mails, formal
memos and letters.
1) Joint site and the PM office
for immediate discussion.
2) WhatsApp for immediate
information sharing
NEC3 Project Lessons Learnt Summary
Nov 2015
Page 61
PART 9
Mid-Term Achievements :
1. Time
2. Cost
3. Quality
4. Safety
5. Social Services
Nov 2015
Page 62
Time Achievement
Early Assessment on Major Time impacts
Typical Case: Revised Pile Cap Level
Effect: Time Implication
Solution: Agreed time recovery measures by increasing resources to mitigate delay due to the revision in pile cap level.
Nov 2015
Page 64
Cost Achievement
Early Discussion on cost saving items
Typical Example: To revise lighting design to suit the revised Landscape layout
Effect: Cost Implication
Result: Optimum lighting design to meet government requirements for landscape area at the least cost option.
Nov 2015
Page 66
First Change of Lighting By Landscape Architect (Costly Option)
Cost Estimation (Costly Option): Interim cost
of HK$2.76M based on government
requirements using floor mounted light on
the revised landscape design.
Nov 2015
Page 67
Further Change of Lighting Layout (Cost Saving Option)
After presenting to Government the cost of HK$2.76M for using floor mounted
light, Government accepted an optimum lighting design of using ceiling
mounted light only which has greatly lowered the lighting cost.
Cost Estimation (Cost Saving Option): Final Cost of HK$0.3M
The cost reduction was achieved by the early warning system
which Paul Y raised the cost quotation to MTR for review. MTR,
Paul Y and Consultant worked together to find an optimum
lighting design solution with least cost which still meet
government requirement.
Nov 2015
Page 68
Quality Achievement
Early Discussions on Quality Enhancement Issues
Typical Example: Additional Steelwork Protective cladding
Effect: To reduce potential risks to FRP Paint
Result: MTR agrees Paul Y to provide additional protective cladding (which is not specified in the Contract) to safe-guard against undesirable damages to the FRP paints.
Nov 2015
Page 70
A few years after the Phase 1 pool
become operational, FRP paint
system started to peel off.
FRP Protective Coating Peeled Off at Pool Deck Area in Phase 1:
FRP Peel Off at Pool Deck Area in Phase 1
FRP Peeled Off
Nov 2015
Page 72
EAR-031 raised by
Paul Y. in Jan 2015
Early Warning Register
Main Causes and
Consequences
Early Warning
Nov 2015
Page 75
Adopt NEC Working Spirt in Site Safety
Early Discussion
Joint Inspection
Evaluation
Continuous Improvement
• Conduct workshops to
discuss Method Statement &
latest Safety Requirements
• Weekly Safety Inspection
• Understand site constraints
• Ensure site works are carried
out as per method statement
• Regular monitoring
• Identify areas for improvement
• Discussion with MTR/ front
line staff/ sub-contractors
• Implement recommended
measures
Nov 2015
Page 76
MTR Safety Awards in March 2015
MTR Safety Award in March 2015
Construction Industry Safety Award by Labour Department
List of Award
Silver Safety Award
Lowest Reportable
Accident Frequency Rate
Award
Best Site Condition Award
Supervisor Safety Award
Winner
Supervisor Safety Award
Runner-up
List of Award
Meritorious Prize in the
Safety Team
Bronze Prize in Civil
Engineering Sites – Sub-
contractors category
Best Site Condition Award
Nov 2015
Page 77
22nd Considerate Contractors Site Award Scheme 1st Site Assessment on 8th July 2015
DEVB Assessment Form MTR Assessment Form
Development Bureau gave
FULL marks (7 nos. “BEST”)
MTR gave 7 nos. “BEST” &
3 nos. “Very Good”
Nov 2015
Page 78
MTRC Quality , Safety & Environmental and
Stakeholder Engagement Awards in October 2015
Gold Safety Award
West Island Line
Gold Safety Award
Nov 2015
Page 79
00.20.4
Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15
WIL 713 Accident Rate Summary (Sept 2014 – Oct 2015) Accident rate per 100,000 man-hours
Accident Rate per 100,000 man-hours
Zero Accident
Zero
Accident
Ceremony Stanley Lo Paul Y.
Director and
General Manager,
Group Legal Counsel
Man Wai Ming Paul Y.
Chief Operating
Officer
Stanley Wong Paul Y.
Chief Executive
Officer &
Executive Director
Stephen Hugh Hamill MTR
Project Manager(Civil) of
WIL Project