payment schedule_piramal vaikunth
DESCRIPTION
payment scheduleTRANSCRIPT
Sr No Milestones Payment Due (%)
1
On Submission of Request Form for Reservation
(RFR), Reservation Fees Rs. 150,000
2 Within 21 days of RFR
10% less
Reservation Fees
3 Within 45 days of RFR 9.9%
4 On receiving Commencement Certificate (C.C) 10.1%
5 On initiation of foundation 5%
6 On initiation of plinth 5%
7 On initiation of 3rd slab 5%
8 On initiation of 6th slab 5%
9 On initiation of 9th slab 5%
10 On initiation of 12th slab 5%
11 On initiation of 15th slab 5%
12 On initiation of 18th slab 5%
13 On initiation of 21st slab 5%
14 On initiation of 24th slab 5%
15 On initiation of top slab 5%
16 On initiation of flooring (internal) 5%
17 On initiation of plumbing (internal) 5%
18 On possession 5%
Total 100%