pcssd construction masterplan--southeast area

16
MAY 2015 We take your child’s education PROPOSED CONSTRUCTION PLAN SOUTHEAST PULASKI COUNTY AREA PLAN

Upload: pulaski-county-special-school-district

Post on 21-Jul-2016

216 views

Category:

Documents


0 download

DESCRIPTION

May 2015 Proposed Construction Masterplan for the elementary schools, middle school and high school in the Southeast Pulaski County area or Mills Feeder Pattern.

TRANSCRIPT

Page 1: PCSSD Construction Masterplan--Southeast Area

MAY 2015

We take your child’s education

PROPOSED CONSTRUCTION PLAN

SOUTHEAST

PULASKI COUNTY

AREA PLAN

Page 2: PCSSD Construction Masterplan--Southeast Area

We take your child’s education

Since being appointed Superintendent of Pulaski County Special School District in 2011, I have had the honor of leading the District through remarkable improvements in many areas. Two of the most challenging were the historic settlement of the more than 30-year desegregation case and the separation of the Jacksonville area schools from the PCSSD. Without a doubt, these changes will help improve the educational environment for students in the Central Arkansas region for years to come.

A key component to settling the desegregation case is attaining unitary status with respect to facilities. Our students deserve a better educational environment, and we are committed to that challenge. As such, my team streamlined District operations -- reallocating money to address the most pressing facility needs at no additional cost to the taxpayer. Our efforts are making a noticeable difference.

Although we have made monumental strides with respect to facilities, replacement of outdated and undersized schools is not possible without an increase to our current millage rate. The construction masterplan outlined in this document addresses undersized and antiquated schools remaining in the PCSSD after the Jacksonville separation and helps us reach facility parity -- a critical factor to PCSSD being fully released from court supervision.

With this in mind, our Commissioner of Education approved a millage election set for May 12, 2015. This ballot issue seeks an increase of 5.6 mils to address the budgetary requirements necessary to fix school capacity issues, to replace our outdated facilities and to reach facility parity across the remaining PCSSD.

Yours in education,

P C S S D | P R O P O S E D C O N S T R U C T I O N P L A N | M A Y 2 0 1 5

From the Superintendent

Page 3: PCSSD Construction Masterplan--Southeast Area

PCSSD schools average 44 years old with the oldest built in 1952. Due to the age of the schools and limited funds

available, the District maintains a large backlog of deferred maintenance. This obsolete and aging infrastructure is

increasingly more expensive to maintain and highlights an inequity with respect to school facilities across the District.

Over the past four years, the PCSSD aggressively streamlined operations to ensure effective use of available

revenue. For instance, closure of four schools, demolition of three antiquated campuses and consolidation of

administrative functions over the past four years have helped focus limited resources on the most pressing needs

by reducing unnecessary or expensive-to-maintain infrastructure. As a result of these and other improvements, the

District was able to increase the annual building fund budget for facility restoration and modernization projects and

has accomplished an additional $28 million in critical repairs and improvements over this same timeframe. Through

the help of improved operations, an increase to the facility sustainment budget by $750,000 annually helps address

obsolete systems and aging infrastructure needs throughout the school year.

To help ensure transparency and the best use of precious resources, the District implemented a facility prioritization

process. This model-process and the associated funding reallocation are having a major impact on the District’s

facilities. Improved roofing systems, parking lot overlays, restroom renovations, HVAC upgrades, painting of

interiors and exteriors of facilities and various other infrastructure projects are visible throughout the District. These

Interior and exterior improvements to building systems and finishes are having a huge impact. Unfortunately, space

deficiencies and curriculum shortfalls can only be overcome through large scale construction projects and facility

parity is not attainable without significant investment.

This masterplan calls for construction of a new high school to replace the current Mills High School, conversion

of the current Mills High School into a middle school and demolition of the existing Fuller Middle School. It also

provides for a new high school to replace the current Robinson High School, conversion of the current Robinson

High School into a middle school and demolition of the current Robinson Middle School. The plan builds a high

school on the current Sylvan Hills High School campus and renovates the existing high school to meet the demand

of recent and future growth in the Sherwood area. At Maumelle High School, a track complex, lights and bleachers

for the softball and baseball fields, an indoor multipurpose facility and additional parking are planned.

The District plans to construct a new elementary school in the I-440 corridor to replace antiquated facilities in the

area, as well as a new elementary school to replace the Robinson Elementary open-space school and provide

capacity for recent growth in the surrounding community. The plan addresses traffic concerns on all campuses

to improve safety for the students, staff and patrons and adds capacity where necessary to negate the need for

portable classrooms. The District intends for every elementary school to have a multipurpose facility/gymnasium

with climate control and upgraded playgrounds where necessary. Other interior and exterior improvements will be

made to the campuses as bid savings and/or lower bond rates are realized.

Only the schools that remain in the PCSSD after the split of the Jacksonville North Pulaski area schools are covered

by the masterplan. The Jacksonville area patrons are not eligible to vote in the PCSSD millage election on May

12, 2015 nor will any of the revenue from this millage increase go to the Jacksonville North Pulaski schools. The

separating Jacksonville North Pulaski District will address long-range facility needs in the Jacksonville area schools

at a later date.

This construction masterplan was developed through a group effort. Maintenance technicians, teachers, support

staff, parents, community members, school leadership and district leadership have all had input into development

of this plan. The graphical representations of additions, renovations and construction are notional. Actual placement

and size will depend upon design considerations developed in conjunction with a team of school, community and District

representation. This plan addresses needs on all schools that remain in the District after the Jacksonville separation.

Foreword

Page 4: PCSSD Construction Masterplan--Southeast Area

PCSSD schools average 44 years old with the oldest built in 1952. Due to the age of the schools and limited funds

available, the District maintains a large backlog of deferred maintenance. This obsolete and aging infrastructure is

increasingly more expensive to maintain and highlights an inequity with respect to school facilities across the District.

Over the past four years, the PCSSD aggressively streamlined operations to ensure effective use of available

revenue. For instance, closure of four schools, demolition of three antiquated campuses and consolidation of

administrative functions over the past four years have helped focus limited resources on the most pressing needs

by reducing unnecessary or expensive-to-maintain infrastructure. As a result of these and other improvements, the

District was able to increase the annual building fund budget for facility restoration and modernization projects and

has accomplished an additional $28 million in critical repairs and improvements over this same timeframe. Through

the help of improved operations, an increase to the facility sustainment budget by $750,000 annually helps address

obsolete systems and aging infrastructure needs throughout the school year.

To help ensure transparency and the best use of precious resources, the District implemented a facility prioritization

process. This model-process and the associated funding reallocation are having a major impact on the District’s

facilities. Improved roofing systems, parking lot overlays, restroom renovations, HVAC upgrades, painting of

interiors and exteriors of facilities and various other infrastructure projects are visible throughout the District. These

Interior and exterior improvements to building systems and finishes are having a huge impact. Unfortunately, space

deficiencies and curriculum shortfalls can only be overcome through large scale construction projects and facility

parity is not attainable without significant investment.

This masterplan calls for construction of a new high school to replace the current Mills High School, conversion

of the current Mills High School into a middle school and demolition of the existing Fuller Middle School. It also

provides for a new high school to replace the current Robinson High School, conversion of the current Robinson

High School into a middle school and demolition of the current Robinson Middle School. The plan builds a high

school on the current Sylvan Hills High School campus and renovates the existing high school to meet the demand

of recent and future growth in the Sherwood area. At Maumelle High School, a track complex, lights and bleachers

for the softball and baseball fields, an indoor multipurpose facility and additional parking are planned.

The District plans to construct a new elementary school in the I-440 corridor to replace antiquated facilities in the

area, as well as a new elementary school to replace the Robinson Elementary open-space school and provide

capacity for recent growth in the surrounding community. The plan addresses traffic concerns on all campuses

to improve safety for the students, staff and patrons and adds capacity where necessary to negate the need for

portable classrooms. The District intends for every elementary school to have a multipurpose facility/gymnasium

with climate control and upgraded playgrounds where necessary. Other interior and exterior improvements will be

made to the campuses as bid savings and/or lower bond rates are realized.

Only the schools that remain in the PCSSD after the split of the Jacksonville North Pulaski area schools are covered

by the masterplan. The Jacksonville area patrons are not eligible to vote in the PCSSD millage election on May

12, 2015 nor will any of the revenue from this millage increase go to the Jacksonville North Pulaski schools. The

separating Jacksonville North Pulaski District will address long-range facility needs in the Jacksonville area schools

at a later date.

This construction masterplan was developed through a group effort. Maintenance technicians, teachers, support

staff, parents, community members, school leadership and district leadership have all had input into development

of this plan. The graphical representations of additions, renovations and construction are notional. Actual placement

and size will depend upon design considerations developed in conjunction with a team of school, community and District

representation. This plan addresses needs on all schools that remain in the District after the Jacksonville separation.

Foreword

Page 5: PCSSD Construction Masterplan--Southeast Area

MILLS HIGH SCHOOL REPLACEMENT

• Construct new campus to replace current high school

• Improve athletic facilities and fields

FULLER MIDDLE (MILLS CONVERSION)

• Convert existing high school into a middle school

• Improve academic and support spaces to enhancemiddle school curriculum

• Remove obsolete classroom structures

Mills Attendance Zone | Campus Need

P C S S D | P R O P O S E D C O N S T R U C T I O N P L A N | M A Y 2 0 1 5

CONVERTED TO MIDDLE SCHOOL

ACADEMIC/SUPPORT SPACE

NEW HIGH SCHOOL

PARKING

INDOOR/MULTIPURPOSE

PARKING

PARKING

PARKING

2

Page 6: PCSSD Construction Masterplan--Southeast Area

MILLS HIGH SCHOOL REPLACEMENT

• Construct new campus to replace current high school

• Improve athletic facilities and fields

FULLER MIDDLE (MILLS CONVERSION)

• Convert existing high school into a middle school

• Improve academic and support spaces to enhancemiddle school curriculum

• Remove obsolete classroom structures

Mills Attendance Zone | Campus Need

P C S S D | P R O P O S E D C O N S T R U C T I O N P L A N | M A Y 2 0 1 5

CONVERTED TO MIDDLE SCHOOL

ACADEMIC/SUPPORT SPACE

NEW HIGH SCHOOL

PARKING

INDOOR/MULTIPURPOSE

PARKING

PARKING

PARKING

Page 7: PCSSD Construction Masterplan--Southeast Area

ADDITIONAL PARKING

ADDITIONAL PARKING

PE / MULTIPURPOSE

ADDITIONAL PARKING

BATES ELEMENTARY SCHOOL

LANDMARK ELEMENTARY SCHOOL

• Increase parking capacity

• Playground improvements

• Increase parking capacity

• Physical education/multipurpose space

• Playground improvements

Mills Attendance Zone | Campus Need

P C S S D | P R O P O S E D C O N S T R U C T I O N P L A N | M A Y 2 0 1 5 4

Page 8: PCSSD Construction Masterplan--Southeast Area

COLLEGE STATION ELEMENTARY SCHOOL

• Enclose corridors

• Add central circulation and administration area

• Add bus lane and loop

P C S S D | P R O P O S E D C O N S T R U C T I O N P L A N | M A Y 2 0 1 5

Add parent drop off/pick up lane and ADA parking•

Renovate interior portions to include media center expansion•

Page 9: PCSSD Construction Masterplan--Southeast Area

Robinson Attendance Zone

I-440 CORRIDOR ELEMENTARY SCHOOL

• Construct new elementary school to replace Scott Elementary (site to be determined)

Mills Attendance Zone | Campus Need

ACADEMIC SPACE

PE/MULTIPURPOSE

PARENT DROP

PARKINGBUS DROP

PLAYGROUNDS

6

Page 10: PCSSD Construction Masterplan--Southeast Area

ADDITIONAL PARKING

ADDITIONAL PARKING

PE / MULTIPURPOSE

ADDITIONAL PARKING

BATES ELEMENTARY SCHOOL

LANDMARK ELEMENTARY SCHOOL

• Increase parking capacity

• Playground improvements

• Increase parking capacity

• Physical education/multipurpose space

• Playground improvements

Mills Attendance Zone | Campus Need

P C S S D | P R O P O S E D C O N S T R U C T I O N P L A N | M A Y 2 0 1 5

Page 11: PCSSD Construction Masterplan--Southeast Area

Recommendation for a 5.6 Mil Increase to the PCSSD Debt Service Millage Rate

The special election date is May 12, 2015. The administration of PCSSD is asking the voters of PCSSD to approve the extension of its current 14.8 debt service mils, restructure certain outstanding bonds and a 5.6 mil increase to its debt service millage rate in order to issue new refunding and construction bonds needed to make district-wide improvements to its facilities. This will have no effect on the new JNPSD or the taxpayers within its borders. A 5.6 mil increase will bring the PCSSD total millage rate to 46.3 mils. The 46.3 mils will include 25.0 mils for Maintenance and Operation, .9 mils for Technology and 20.4 mils for Debt Service. The total millage rate for the Little Rock School District is 46.4 and the total millage rate for the North Little Rock School District is 48.3. Therefore even with this increase, PCSSD would have the lowest millage rate of the three Pulaski County school districts. A mil is one-tenth of a cent and taxes are assessed on twenty-percent of market value. For example, a house valued at $100,000 is assessed at $20,000 and 5.6 mils of tax would equal $112 per year or $9.33 per month.

Based on assessments for 2013 of $2,644,995,204, and assuming that the new Jacksonville-North Pulaski School District includes 15% of this total, 5.6 mils of additional tax would generate annual revenue of $12,086,570 assuming a 96% collection rate. If bonds were sold today, the expected interest rate would be approximately 4.0%. Though future interest rates cannot be predicted with any degree of certainty, the administration has used an assumed rate of 4.5%, and therefore expects a 5.6 mil increase would support 30-year bonds that would net the district approximately $213,000,000 for construction projects.

In addition to the amount of bonds that could be issued, the district will have available $20,804,500 of state desegregation revenue that must be used for the construction of academic facilities. Part of this amount is to be

allocated to the new Jacksonville-North Pulaski School District. The exact manner of allocation has not yet been decided but, if based on student population alone, the new district would receive approximately 26% or $5,409,170 of the $20,804,500 leaving $15,395,330 available for Pulaski County Special School District.

Current cost estimates for the needed district-wide facilities improvements total approximately $221,000,000. If interest rates and costs are lower than current estimates, the district could issue shorter-term bonds, make additional improvements to facilities, or ear-mark a larger annual amount for future sustainment, renovation and modernization of facilities. However, if interest rates exceed 4.50% and/or building costs exceed $221,000,000, it will be necessary to either scale back the new construction or issue second lien bonds that can be supported through growth in property assessments.

Although future interest rates and construction costs cannot be predicted with certainty, based on information obtained from the district’s fiscal agent and district architects and construction managers, the administration believes a millage increase of 5.6 mills will provide sufficient revenue to support much needed district-wide facility improvements totaling approximately $221,000,000.

Therefore the administration will ask the PCSSD voters, at a special school millage rate election to be held May 12, 2015, to approve a 5.6 mill increase to its debt service millage rate, extend its current 14.8 debt service mills, restructure the June 15, 2009, February 15, 2010, October 15, 2010 and January 1, 2011 bond issues, and authorize new 30-year refunding and construction bonds that will be used for new construction and other district-wide facility improvments.

The anticipated expenses associated with the current construction masterplan are as follows:

High Schools | $150.5 MThis category includes construction of three high schools, renovation of current high school space where necessary,

demolition of obsolete facilities, addition of extracurricular and athletic facilities and indoor multipurpose facilities.

Middle Schools | $12.7 MThe middle school category includes renovating and converting existing high school space into middle schools,

adding restroom facilities for the extracurricular fields and climate control on a gymnasium.

Elementary Schools | $57.8 MThe program for elementary schools includes construction of two new elementary schools, addition of classroom

space to meet space deficiencies, construction of multipurpose/gymnasiums, playground improvements, interior

improvements and traffic safety improvements on the campuses.

Financials

P C S S D | P R O P O S E D C O N S T R U C T I O N P L A N | M A Y 2 0 1 5 30

Page 12: PCSSD Construction Masterplan--Southeast Area

Recommendation for a 5.6 Mill Increase to the PCSSD Debt Service Millage Rate

The special election date is May 12, 2015. The administration of PCSSD is asking the voters of PCSSD to approve the extension of its current 14.8 debt service mills, restructure certain outstanding bonds and a 5.6 mill increase to its debt service millage rate in order to issue new refunding and construction bonds needed to make district-wide improvements to its facilities. This will have no effect on the new JNPSD or the taxpayers within its borders. A 5.6 mill increase will bring the PCSSD total millage rate to 46.3 mills. The 46.3 mills will include 25.0 mills for Maintenance and Operation, .9 mills for Technology and 20.4 mills for Debt Service. The total millage rate for the Little Rock School District is 46.4 and the total millage rate for the North Little Rock School District is 48.3. Therefore even with this increase, PCSSD would have the lowest millage rate of the three Pulaski County school districts. A mill is one-tenth of a cent and taxes are assessed on twenty-percent of market value. For example, a house valued at $100,000 is assessed at $20,000 and 5.6 mills of tax would equal $112 per year or $9.33 per month.

Based on assessments for 2013 of $2,644,995,204, and assuming that the new Jacksonville-North Pulaski School District includes 15% of this total, 5.6 mills of additional tax would generate annual revenue of $12,086,570 assuming a 96% collection rate. If bonds were sold today, the expected interest rate would be approximately 4.0%. Though future interest rates cannot be predicted with any degree of certainty, the administration has used an assumed rate of 4.5%, and therefore expects a 5.6 mill increase would support 30-year bonds that would net the district approximately $213,000,000 for construction projects.

In addition to the amount of bonds that could be issued, the district will have available $20,804,500 of state desegregation revenue that must be used for the construction of academic facilities. Part of this amount is to be

allocated to the new Jacksonville-North Pulaski School District. The exact manner of allocation has not yet been decided but, if based on student population alone, the new district would receive approximately 26% or $5,409,170 of the $20,804,500 leaving $15,395,330 available for Pulaski County Special School District.

Current cost estimates for the needed district-wide facilities improvements total approximately $221,000,000. If interest rates and costs are lower than current estimates, the district could issue shorter-term bonds, make additional improvements to facilities, or ear-mark a larger annual amount for future sustainment, renovation and modernization of facilities. However, if interest rates exceed 4.50% and/or building costs exceed $221,000,000, it will be necessary to either scale back the new construction or issue second lien bonds that can be supported through growth in property assessments.

Although future interest rates and construction costs cannot be predicted with certainty, based on information obtained from the district’s fiscal agent and district architects and construction managers, the administration believes a millage increase of 5.6 mils will provide sufficient revenue to support much needed district-wide facility improvements totaling approximately $221,000,000.

Therefore the administration will ask the PCSSD voters, at a special school millage rate election to be held May 12, 2015, to approve a 5.6 mil increase to its debt service millage rate, extend its current 14.8 debt service mils, restructure the June 15, 2009, February 15, 2010, October 15, 2010 and January 1, 2011 bond issues, and authorize new 30-year refunding and construction bonds that will be used for new construction and other district-wide facility improvments.

The anticipated expenses associated with the current construction masterplan are as follows:

High Schools | $150.5 MThis category includes construction of three high schools, renovation of current high school space where necessary,

demolition of obsolete facilities, addition of extracurricular and athletic facilities and indoor multipurpose facilities.

Middle Schools | $12.7 MThe middle school category includes renovating and converting existing high school space into middle schools,

adding restroom facilities for the extracurricular fields and climate control on a gymnasium.

Elementary Schools | $57.8 MThe program for elementary schools includes construction of two new elementary schools, addition of classroom

space to meet space deficiencies, construction of multipurpose/gymnasiums, playground improvements, interior

improvements and traffic safety improvements on the campuses.

Financials

P C S S D | P R O P O S E D C O N S T R U C T I O N P L A N | M A Y 2 0 1 5

Page 13: PCSSD Construction Masterplan--Southeast Area

PCSSDStrategic Facilities Plan Schedule

APR

MA

Y

JUN

E

JULY

AU

G

SEPT

OC

T

NO

V

DEC

JAN

FEB

MA

R

APR

MA

Y

JUN

E

JULY

AU

G

SEPT

OC

T

NO

V

DEC

JAN

FEB

MA

R

APR

MA

Y

JUN

E

JULY

AU

G

SEPT

OC

T

NO

V

DEC

JAN

FEB

MA

R

APR

MA

Y

JUN

E

JULY

AU

G

SPECIAL ELECTION

MILLS HIGH REPLACEMENT

ROBINSON HIGH REPLACEMENT

MAUMELLE HIGH

SYLVAN HILLS HIGH

MAUMELLE MIDDLE

SYLVAN HILLS MIDDLE

MILLS HIGH / MIDDLE

ROBINSON HIGH / MIDDLE

I-440 CORRIDOR ELEM

BAKER ELEMENTARY

ROBINSON ELEM

CATO ELEMENTARY

CHENAL ELEMENTARY

CRYSTAL HILL ELEM

DAISY BATES ELEM

LANDMARK ELEM DESIGN

LAWSON ELEM

OAK GROVE ELEM

OAKBROOKE ELEM

PINE FOREST ELEM

SHERWOOD ELEM

SYLVAN HILLS ELEM

CLINTON ELEM

MOVECONSTRUCTION

MOVENEW CONSTRUCTION - I-440 CORRIDOR ELEMENTARYDESIGN

DEMO MOVENEW CONSTRUCTION

DESIGN CONSTRUCTION MOVE

DESIGN CONSTRUCTION MOVE

DESIGN CONSTRUCTION MOVE

DESIGN CONSTRUCTION MOVE

DESIGN CONSTRUCTION MOVE

DESIGN CONSTRUCTION MOVE

DESIGN CONSTRUCTION MOVE DESIGN CONSTRUCTION MOVE

DESIGN CONSTRUCTION MOVE DESIGN CONSTRUCTION MOVE

DESIGN

DESIGN CONSTRUCTION MOVE

DESIGN

DESIGN

DESIGN CONSTRUCTION MOVE

DESIGN

DESIGN CONVERSION - MILLS HIGH SCHOOL TO MIDDLE SCHOOL

ELEMENTARY SCHOOLS

MOVE IN

CONVERSION - ROBINSON HIGH SCHOOL TO MIDDLE SCHOOL MOVE IN

DESIGN CONSTRUCTION

CONSTRUCT NEW ADDITION / IMPROVE EXISTING FACITLITIES

ATHLETIC ADD (INDOOR PRAC / TRACK / BLEACHERS / LIGHTS / ETC.)

MIDDLE SCHOOLS

MOVE IN

MOVE IN

MOVE

MOVE

MOVE

2018

HIGH SCHOOLS

PROJECT

2015 2016 2017

DESIGN

DESIGN NEW CONSTRUCTION - REPLACEMENT SCHOOL

NEW CONSTRUCTION - REPLACEMENT SCHOOL

CONSTRUCTIONDESIGN

DESIGN

MOVEDESIGN

CONSTRUCTION MOVE

DESIGN MOVECONSTRUCTION

CONSTRUCTION MOVE

DESIGN CONSTRUCTION

MAY 12, 2015

FAQs

Timeline

32

HARRIS ELEM

COLLEGE STATION ELEM

DESIGN CONSTRUCTION MOVE DESIGN CONSTRUCTION MOVE

DESIGN CONSTRUCTION MOVE DESIGN CONSTRUCTION MOVE

Page 14: PCSSD Construction Masterplan--Southeast Area

MILLAGE/VOTER INFORMATION

The Pulaski County Special School District will be asking voters to pass a millage that would allow for new buildings, renovation and improvements at all schools in the PCSSD, not including the Jacksonville-North Pulaski area schools. Some of the frequently asked questions related to the millage, and the upcoming election, are listed below. For answers to additional, specific questions, please go to www.pcssd.org, scroll to the bottom of the page, and write to us in the “contact us” form.

Q: When is the election?

A: There will be a special election to vote on the proposed millage increase on May 12, 2015.

Q: Where will I vote?

A: It will be held at your regular voting/polling location or if the location changes, you will be notified by the county clerk.

Q: How soon do I have to register to vote so I can vote in the May millage election?

A: Per the Arkansas Secretary of State website or voter registration form, voters must be registered at least 30 days prior to the election in question.

Q: Where can I get a registration form?

A: See this link: http://www.sos.arkansas.gov/elections/Documents/Voter_Reg_Ap_6-11.pdf

Q: Can the patrons in the new Jacksonville-North Pulaski attendance area vote in this election?

A: No.

Q: What part of Pulaski County does this millage affect?

A: Only those areas in the PCSSD attendance zone (not including those in the new JNPSD attendance zone).

Q: Does any of this millage money go to the Jacksonville area schools?

A: No; these funds will be strictly for facilities purposes on the PCSSD schools not in the Jacksonville area.

Q: How will the 5.6 mils affect my property taxes?

A: The tax will be $112 per year on every $100,000 of property value.

Q: How long will the millage last?

A: 30 years.

FAQs

34

Page 15: PCSSD Construction Masterplan--Southeast Area

MILLAGE/VOTER INFORMATION

The Pulaski County Special School District will be asking voters to pass a millage that would allow for new buildings, renovation and improvements at all schools in the PCSSD, not including the Jacksonville-North Pulaski area schools.. Some of the frequently asked questions related to the millage, and the upcoming election, are listed below. For answers to additional, specific questions, please go to www.pcssd.org, scroll to the bottom of the page, and write to us in the “contact us” form.

Q: When is the election?

A: There will be a special election to vote on the proposed millage increase on May 12, 2015.

Q: Where will I vote?

A: It will be held at your regular voting/polling location or if the location changes, you will be notified by the county clerk.

Q: How soon do I have to register to vote so I can vote in the May millage election?

A: Per the Arkansas Secretary of State website or voter registration form, voters must be registered at least 30 days prior to the election in question. So, April 10, 2015, appears to be the safe date.

Q: Where can I get a registration form?

A: See this link: http://www.sos.arkansas.gov/elections/Documents/Voter_Reg_Ap_6-11.pdf

Q: Can the patrons in the new Jacksonville-North Pulaski attendance area vote in this election?

A: No.

Q: What part of Pulaski County does this millage affect?

A: Only those areas in the PCSSD attendance zone (not including those in the new JNPSD attendance zone).

Q: Does any of this millage money go to the Jacksonville area schools?

A: No; these funds will be strictly for facilities purposes on the PCSSD schools not in the Jacksonville area.

Q: How will the 5.6 mils affect my property taxes?

A: The tax will be $112 per year on every $100,000 of property value.

Q: How long will the millage last?

A: 30 years.

FAQs

Page 16: PCSSD Construction Masterplan--Southeast Area

9 2 5 E D I X O N R D , L I T T L E R O C K , A R 7 2 2 0 6 | 5 0 1 . 2 3 4 . 2 0 0 0 | p c s s d . o r g

P R O P O S E D

C O N S T R U C T I O N

P L A N

M A Y 2 0 1 5

SOUTHEAST

PULASKI COUNTY

AREA PLAN