pdf page 1 of 37

37
TransCanada PipeLines Limited Eastern Mainline Project Application Section 4 Compression October 2014 Page 4-1 4.0 COMPRESSION This section provides details regarding the compression requirements for the Project. The information is based on preliminary design and is supported by initial results from hydraulic modelling and field investigation programs. Revisions and refinements are expected as additional data are collected and assessed and as engineering progresses through detailed design. 4.1 FACILITY OVERVIEW The Project involves adding nine 11 MW (ISO-rated power output) gas turbine compressor packages and associated systems at the following five existing TransCanada compressor sites: Stations 134, 136, 139, 142 and 144. The five existing compressor sites are located in the: Municipality of Clarington (Station 134 – Bowmanville) Township of Alnwick-Haldimand (Station 136 – Cobourg) Township Tyendinaga (Station 139 – Belleville) City of Kingston (Station 142 – Kingston) Township of Augusta (Station 144 – Brockville) The compressor unit additions at existing compressor sites are required to offset pressure losses as the gas travels through the pipeline. Once in service, these units will provide the necessary compression at the stations. The existing compressor units will remain available for use during commissioning and initial operation of the compressor unit additions to provide capacity as required. TransCanada will apply to deactivate the older units at a future date as required. The compressor packages will be equipped with dry low-emission reduction technology and noise-attenuation equipment, and will be housed in a new compressor building in a fully fenced station yard. The building will be erected on concrete footings and foundations. Additional prefabricated, skid-mounted buildings will be erected on pilings and used to house the power generator units, electrical and mechanical equipment, the air system, the utility gas equipment and station personnel, as required. Suction and discharge yard piping will be installed to connect the compressor stations to the Project pipeline, as well as the existing Montréal Line. For detailed information on the proposed compression facilities, see Table 4-1. PDF Page 1 of 37

Upload: others

Post on 25-Mar-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

TransCanada PipeLines Limited Eastern Mainline Project Application

Section 4 Compression

October 2014 Page 4-1

4.0 COMPRESSION

This section provides details regarding the compression requirements for the Project. The information is based on preliminary design and is supported by initial results from hydraulic modelling and field investigation programs. Revisions and refinements are expected as additional data are collected and assessed and as engineering progresses through detailed design.

4.1 FACILITY OVERVIEW

The Project involves adding nine 11 MW (ISO-rated power output) gas turbine compressor packages and associated systems at the following five existing TransCanada compressor sites: Stations 134, 136, 139, 142 and 144. The five existing compressor sites are located in the:

Municipality of Clarington (Station 134 – Bowmanville) Township of Alnwick-Haldimand (Station 136 – Cobourg) Township Tyendinaga (Station 139 – Belleville) City of Kingston (Station 142 – Kingston) Township of Augusta (Station 144 – Brockville)

The compressor unit additions at existing compressor sites are required to offset pressure losses as the gas travels through the pipeline. Once in service, these units will provide the necessary compression at the stations. The existing compressor units will remain available for use during commissioning and initial operation of the compressor unit additions to provide capacity as required. TransCanada will apply to deactivate the older units at a future date as required.

The compressor packages will be equipped with dry low-emission reduction technology and noise-attenuation equipment, and will be housed in a new compressor building in a fully fenced station yard. The building will be erected on concrete footings and foundations. Additional prefabricated, skid-mounted buildings will be erected on pilings and used to house the power generator units, electrical and mechanical equipment, the air system, the utility gas equipment and station personnel, as required. Suction and discharge yard piping will be installed to connect the compressor stations to the Project pipeline, as well as the existing Montréal Line.

For detailed information on the proposed compression facilities, see Table 4-1.

PDF Page 1 of 37

Section 4 Compression

TransCanada PipeLines LimitedEastern Mainline Project Application

Page 4-2 October 2014

Table 4-1: Details of Proposed Compressor Unit Additions

Compressor Station Name Legal Location

Total New Power Rating

(MW) Construction

Start Date In-Service

Date

Approximate Size of New Facility Site

(ha)

Station 134 –Bowmanville

Lot 32, Con 5 Township of Darlington, County of Durham, PIN 26710-0049

1 x 11.0 Q2 2016 Q2 2017 2.25

Station 136 –Cobourg

Lot 15, Con 3 Township of Haldimand, County of Northumberland, PIN 51130-0278

2 x 11.0 Q2 2016 Q2 2017 2.25

Station 139 –Belleville

Lot 9, Con 2 Township of Tyendinaga, County of Hastings, PIN 40556-0087

2 x 11.0 Q2 2016 Q2 2017 2.25

Station 142 –Kingston

Lot 12 & 13, Con 5 Township of Pittsburgh, County of Frontenac, PIN 36328-0041

2 x 11.0 Q2 2016 Q2 2017 2.25

Station 144 –Brockville

Lot 24 & 25, Con 2 Township of Augusta, County of Grenville, PIN 68181-0052

2 x 11.0 Q2 2016 Q2 2017 2.25

4.2 PRELIMINARY LOCATIONS

The proposed compressor unit additions will be located on existing TransCanada-owned land at Stations 134, 136, 139, 142 and 144 (see Table 4-2). For topographical maps of the proposed compressor unit additions, see Appendix 4-1.

Table 4-2: Proposed Locations for Compressor Unit Additions

Compressor Station Name Province Easting Northing UTM DMS/DecDeg

Station 134 – Bowmanville ON 675080.8 4869775.6 17 N43.960273W78.817718

Station 136 – Cobourg ON 739797.9 4881330.8 17 N44.045928W78.006773

Station 139 – Belleville ON 321813.7 4899997.7 18 N44.231422W77.231167

Station 142 – Kingston ON 391321.8 4910997.2 18 N44.344108W76.363429

Station 144 – Brockville ON 450720.8 4948078.8 18 N44.684386W75.621844

PDF Page 2 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Section 4 Compression

October 2014 Page 4-3

4.3 COMPRESSION PROJECT COMPONENTS

Based on the preliminary design, the proposed compressor unit additions will each include the following key systems and components, which are subject to change on completion of detailed engineering:

one new steel frame compressor building designed with noise attenuation equipment with capacity to house two gas turbine compressor packages

a skid-mounted electrical/control building to contain the motor control centre (MCC), station control panel and uninterruptible power supply (UPS)

a skid-mounted mechanical building to house air compressors, air dryers, air receiver and interconnecting piping

a skid-mounted mechanical building to house the glycol heating system (i.e., boilers, pumps, an expansion tank and interconnecting piping)

a skid-mounted personnel building to house the SCADA system and general office space

one skid-mounted building to house the power generating unit

a utility gas enclosure

a heated storage building for spare parts and equipment storage, where required

For preliminary plot plans showing the location of the proposed compressor unit additions, see Appendix 4-2.

4.4 INDUSTRY CODES AND STANDARDS

In addition to CSA Z662-11, various other industry codes and standards will be used in the design, construction and operation of the proposed compressor unit additions. For the major applicable codes and standards, see Table 4-3.

Table 4-3: Industry Standards for Compression Facilities

Organization Standard1,2 Title

NEB OPR-99 National Energy Board Onshore Pipeline Regulations

CSA CSA Z245.1-14 Steel Pipe

CSA CSA Z245.11-13 Steel Fittings

CSA CSA Z245.12-13 Steel Flanges

CSA CSA Z245.15-13 Steel Valves

CSA CSA B51-14 Boiler, Pressure Vessel and Pressure Piping Code

CSA CSA B149.1-10 Natural Gas and Propane Installation Code

CSA C 22.1-12 Canadian Electrical Code, Part 1, Safety Standard for Electrical Installations

PDF Page 3 of 37

Section 4 Compression

TransCanada PipeLines LimitedEastern Mainline Project Application

Page 4-4 October 2014

Table 4-3: Industry Standards for Compression Facilities (cont'd)

Organization Standard1,2 Title

ASME ASME B31.3-2012 Process Piping

ASME Boiler and Pressure Vessel Code, Section VIII, Division 1, 2010

Pressure Vessels

National Building Codes of Canada (NBC 2010)

Note: 1. The CSA standards in this table often incorporate other CSA standards and publications from other

organizations (e.g., ASME, ASTM, API, ISO, CGSB, NACE, SSPC and MSS). 2. Standards will be the latest edition.

4.5 COMPANY STANDARDS, PROCEDURES AND SPECIFICATIONS

For a current list of potentially applicable TransCanada standards and specifications, see Table 4-4.

A final list of applicable standards and specifications will evolve as Project planning progresses through detailed design and as individual specifications and procedures are added, updated or replaced to incorporate legislative and regulatory changes, and technological advances.

Table 4-4: Preliminary List of TransCanada Standards and Specifications

Document Number and Title EDMS Number Effective Date Rev Content Name

TED-2100-SITE Directive for Site Planning 6667 October 15, 2010 0 Site Planning

TED-2600-GRDS Directive for Grounds and Roads

3671234 October 15, 2010 0 Site Planning

TES-CIVIL-DES Civil Design Criteria – Facilities (CDN-US)

8040016 October 1, 2013 1 Design

TES-CIVIL-GEO Specification for Facility Geotechnical Investigation (CDN-US)

8040021 March 31, 2013 0 Geotechnical

TES-CIVIL-SURV Specification for Facility Site Surveying (CDN-US)

8040023 March 25, 2013 0 Survey

TES-COAT-EPU External Liquid Coating Systems for Below Ground Facilities (CDN-US-MEX)

3671710 August 1, 2013 11 Coating Protection

TES-COAT-FBE External Fusion Bond Epoxy for Steel Pipe (CDN-US-MEX)

3670892 November 15, 2012 6 Coating Protection

TES-COAT-P1 Paint Systems for Above Ground Facilities (Coastal and Non-Coastal) (CDN-US-MEX )

3694704 May 22, 2014 8 Coating Protection

TES-COMP-TURBO Turbo Compressor Package Specification (CDN-US-MEX)

6934 October 11, 2012 2 Turbo Compressor

PDF Page 4 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Section 4 Compression

October 2014 Page 4-5

Table 4-4: Preliminary List of TransCanada Standards and Specifications (cont'd)

Document Number and Title EDMS Number Effective Date Rev Content Name

TES-CP-MS Cathodic Protection Materials Specification (CDN-US)

3670944 April 8, 2014 6 Cathodic Protection

TES-DV02-3200 Geotechnical Investigations

6455 May 28, 2013 1 Geotechnical

TES-DV03-1000 Concrete Formwork 6464 June 3, 2013 3 Concrete

TES-DV03-2000 Concrete Reinforcement 6465 May 28, 2013 3 Concrete

TES-DV03-3000 Cast-in-Place Concrete 6466 June 3, 2013 3 Concrete

TES-DV03-3505 Concrete Floor Finishing 6467 May 30, 2013 3 Concrete

TES-DV03-6100 Grouting of Heavy Machinery

6468 June 5, 2013 3 Grouting

TES-DV05-1213 Structural Steel 6488 July 15, 2009 2 Steel

TES-DV05-5000 Miscellaneous Metals 6491 July 15, 2009 0 Steel

TES-DV13-3419 Pre-Engineered Compressor Building

6557 November 30, 2009 1 Building

TES-DV13-3420 Pre-Engineered Skid Building (CDN)

3690601 March 31, 2013 1 Building

TES-DV14-4300 Overhead Bridge Crane 3690593 July 15, 2009 0 Cranes

TES-DV31-2333 Excavation, Backfilling and Site Grading

6457 April 7, 2014 2 Excavation

TES-DV31-6216 Driven Steel Piles 6459 June 15, 2010 1 Steel

TES-DV31-6223 Bored Cast-in-Place Concrete Piles

6460 June 5, 2013 1 Concrete

TES-DV32-3113 Chain Link Fence 6462 February 28, 2011 2 Fencing

TES-DV33-4621 Building Foundations and Underslab Drainage

6461 June 6, 2013 1 Drainage

TES-FITG-CIF Specification for Contoured Insert Fittings (CDN-US-MEX)

4424021 March 25, 2013 2 Fitting

TES-FITG-EC1 Specification for End Closures (CDN)

3779256 March 26, 2013 2 Fitting

TES-FITG-LD Specification for Carbon Steel Buttwelding Fitting Rev 4

3671270 December 6, 2010 4 Fitting

TES-FITG-SAD Full Encirclement Reinforcing Saddles Specification (CDN)

3779258 January 31, 2014 3 Fitting

TES-FITG-T01 Instrument Tube Fitting, Instrument Pipe Fitting and Tubing Material Specification (CDN-US-MEX)

3697116 September 11, 2013 6 Fitting

TES-FLGE-LD Specification for Carbon Steel Buttwelding Flanges

3671966 November 22, 2010 4 Flange

TES-HYDRO-CDN Hydrostatic Testing Specification

7591539 October 22, 2013 1 Hydrostatic Testing

TES-MATL-MD1 Piping System Materials for Pipeline, Compression and Metering Facilities

3764909 December 30, 2002 0 Pipe

PDF Page 5 of 37

Section 4 Compression

TransCanada PipeLines LimitedEastern Mainline Project Application

Page 4-6 October 2014

Table 4-4: Preliminary List of TransCanada Standards and Specifications (cont'd)

Document Number and Title EDMS Number Effective Date Rev Content Name

TES-MATL-PV1 Specification for Pressure Vessels

6406 April 13, 2009 3 Pressure Vessel

TES-PIPE-EW Specification for Electric Welded Pipe

3670788 March 22, 2013 3 Pipe

TES-PIPE-SAW Specification for Double Submerged Arc Welded Pipe

3776714 March 22, 2013 2 Pipe

TES-PROJ-EXC Excavation Specification (CDN-US-MEX)

5890120 January 14, 2011 1 Excavation

TES-STRU-DES Structural Design Criteria 8040018 March 22, 2013 0 Design

TES-VALV-LD Specification for Steel Valves 3671277 October 22, 2010 4 Valve

TES-VOPR-GH Gas Hydraulic Valve Operator Specification

3671784 January 24, 1999 0 High-Pressure System

TES-WELD-AS Welding of Assemblies and Station Piping (003670962)_Rev 3

3670962 April 30, 2012 3 Welding

Note: Standards are current to September 19, 2014.

4.6 ENGINEERING DESIGN DETAILS

The proposed compressor unit additions will have a similar design, except for the changes necessary to accommodate any site-specific conditions. Geotechnical assessments are planned for Q3 2014 and will be submitted to the NEB as supplemental information, if required.

Although only one unit will be installed at Station 134, the design incorporates a two-unit building and additional piping and valves to accommodate a potential second unit expansion. All compressor packages will be the same type and model for standardization and consistency. Each site will be designed for unstaffed operation and will be accessible by road.

4.6.1 Power Type and Source

TransCanada will rely on third-party utility power to supply the compressor stations. Auxiliary power units (APUs) will also be installed at all compressor stations for backup electrical power when utility power is offline.

If the power supply to the compressor station is interrupted, a UPS system will provide continuous battery power to the critical control circuits. This UPS system will be capable of maintaining the compressor station control system for about six hours.

4.6.2 Fuel Type and Source

The fuel type is natural gas. The source of fuel will be the connecting pipeline system.

PDF Page 6 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Section 4 Compression

October 2014 Page 4-7

4.6.3 Station Piping Design

The station piping will include above- and below-ground piping and valves, as determined during detailed design. The station piping will be designed for:

station piping design pressure of 7240 kPa(g) maximum allowable operating pressure (MAOP) of 6450 kPa(g) station piping design temperature of -45ºC to +75ºC

For the piping materials for the compressor stations, see Table 4-5. The material types are appropriate for low-temperature (-45ºC) conditions as they are required to be notch toughness tested (fracture appearance and energy absorption) to a minimum test temperature of -45ºC.

All materials, such as pipe, valves and fittings, will follow TransCanada specification TES-MATL-MD1.

Table 4-5: Piping Materials for Compressor Station Sites

Compressor Station Location

Factor

Design Pressure[kPa(g)]

Pipe Diameter

(mm)

Wall Thickness

(mm) Grade (MPa)

Pipe Material Standard

Station 134 Proposed Compressor Unit Addition

0.625 7240 NPS 36 13.7 483 TES-PIPE-SAW and CSA Z245.1-07 NPS 30 11.4 483

NPS 24 9.2 483

NPS 20 8.2 448 TES-PIPE-EW and CSA Z245.1-07

Stations 136, 139, 142, 144 Proposed Compressor Unit Additions

0.625 7240 NPS 36 13.7 483 TES-PIPE-SAW and CSA Z245.1-07 NPS 30 11.4 483

NPS 24 9.2 483

NPS 20 8.2 448 TES-PIPE-EW and CSA Z245.1-07

4.6.4 Pipe Coatings

The station pipe coating will follow the TransCanada specifications listed in Table 4-4. The primary coating for the external surface of the below-ground pipe will be fusion-bonded epoxy (FBE). Girth welds will be coated in the field and will be protected with field-applied epoxy coating. Below-ground assembly piping will be protected with a suitable liquid-applied epoxy coating.

Above-ground piping will be primed and painted, and acoustically insulated.

4.6.5 Station Schematics

The proposed compressor unit additions will consist of a compressor building to house the gas turbine compressor packages, auxiliary buildings (electrical/control

PDF Page 7 of 37

Section 4 Compression

TransCanada PipeLines LimitedEastern Mainline Project Application

Page 4-8 October 2014

building, mechanical buildings, power unit generator skid, heated storage building, personnel skid and utility gas enclosure) and a skidded drum rack.

The compressor building will be a free-standing steel rigid-frame structure, supported by reinforced concrete grade beams and piles, complete with acoustically designed walls and roof, and will incorporate fire and gas detectors. The auxiliary buildings will be skid-mounted and supported on steel-driven piles. The buildings will be completed with heating and ventilation equipment.

The station suction relief valve will be installed downstream of the station suction isolation side valve and set at 6720 kPa(g) to provide thermal relief for the station suction piping and suction scrubber.

The station discharge relief function will be handled by the automated blowdown valve in accordance with the TransCanada Mainline System standard. The automated blowdown discharge relief valve will be installed upstream of the station discharge isolation side valve and will be sized for the compressor maximum flow rate at the relief valve set pressure of 6720 kPa(g). For the preliminary schematics, see Appendix 4-3.

4.6.6 Pressure Control System

The recycle (anti-surge) valve will be connected downstream of the compressor unit discharge valve and upstream of the unit discharge check valve. The recycle valve will increase the flow through the compressor, as required, to maintain the operating point away from surge by circulating more gas flow and reducing compressor head.

The equipment will monitor actual inlet flow and differential pressure across the compressor through a pressure differential transmitter, and is equipped with algorithms to detect and avoid surge.

The station pressure control will be maintained by increasing or decreasing the compressor speed. The station suction and discharge pressure will be monitored using pressure transmitters. The station pressure setpoints are set by TransCanada’s OCC.

The compressor station OPP system will consist of the pressure-control system as described above, the pressure-limiting system provided by the station controls and unit controls, and the pressure-relieving system provided by the station suction and discharge automated blowdown relief valves.

4.6.7 Station Suction Scrubber

The suction scrubber for the high-pressure gas system will be a swirl/centrifugal type designed to handle the maximum design flow. The scrubber will have automated liquid control to allow for accumulated liquids to be drained to an above-ground storage tank.

PDF Page 8 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Section 4 Compression

October 2014 Page 4-9

4.6.8 Emergency Shutdown System

An emergency shutdown (ESD) pushbutton will be installed at all exit doors in the compressor building and near the scrubber. Perimeter ESD pushbuttons will be added to all fence gates and tied-in to the single fence ESD. The site ESD pushbutton at the control panel in the control building will trigger a station ESD. Fire or gas detection in the compressor building will also trigger a station ESD. As such, the ESD system can be initiated from multiple locations throughout the compression facility and at each egress point from the compression facility.

The ESD system will trigger the following hard-wired functions during a station ESD:

The gas will be blocked out of the station by the triggered closure of both station suction side valve and discharge side valve, isolating the station from the mainline. Subsequently, the suction blowdown valve and the discharge blowdown valve will both be triggered open to blow down the station piping.

The gas compressor units will be triggered to stop immediately and depressurized throughout the station piping. The units will be completed with a control system that allows multiple types of shutdowns based on different events or scenarios (e.g., one level of shutdown will bring the unit to a complete stop as quickly as possible while maintaining auxiliaries, such as lube oil system).

The blowdown valves and blowdown piping will be installed in a location to discharge gas at a safe distance from the compressor building, auxiliary equipment and the surrounding area.

The ESD system will be capable of isolating the compression facility from the pipeline and depressurizing the compression facility.

The ESD system will be powered by a UPS system, but will be wired fail safe, so that in the event of power loss it will isolate and depressurize the facility to put it into a safe state.

4.6.9 Corrosion Control

The compressor station piping and facilities will be cathodically protected by impressed current CP systems. The systems will include appropriately located and sized anode groundbeds and power sources (i.e., rectifiers and thermoelectric generators) as determined by detailed design. The CP systems will be designed in conjunction with the upstream and downstream pipeline system. In addition, sacrificial anodes might be used at specific locations.

PDF Page 9 of 37

Section 4 Compression

TransCanada PipeLines LimitedEastern Mainline Project Application

Page 4-10 October 2014

4.7 CONSTRUCTION

This subsection provides an overview of the construction plans for the new compressor units, including:

construction procedures and execution safety inspection and monitoring

Information on the compressor construction workforce, as well as the likely construction timing and sequencing, is also provided.

The information in this subsection is based on preliminary planning. Construction plans will be further developed during detailed design and will incorporate input from the selected construction contractors.

4.7.1 Construction Strategy

At this stage in preliminary design, TransCanada plans to hire prime contractors to complete site clearing, rough grading, fabrication and main construction of the compressor unit additions.

4.7.2 Construction Contracts

The prime contractors for compressor unit additions construction will be chosen through a formal bidding process once detailed design is complete.

Separate contracts will be awarded for work outside of the scope of the construction contracts, such as construction surveying and NDE testing.

4.7.3 Construction Procedures and Execution

TransCanada will use conventional construction methods and industry best practices when constructing the compressor unit additions. Construction activities will include:

conducting pre-work for clearing surveying clearing removing upper surface material, and salvage, where required grading piling installing foundations installing compressor buildings and units installing generators installing auxiliary buildings and equipment piping and pressure testing conducting electrical work

PDF Page 10 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Section 4 Compression

October 2014 Page 4-11

installing the instrumentation system installing controls commissioning conducting pre-startup safety review conducting final site cleanup

Construction will be done in accordance with the applicable TransCanada specifications, standards and operating practices, and with the Compressor Station EPP as provided in the ESA.

4.7.4 Security Management

TransCanada’s corporate security policy and programs are aligned to CSA Standard Z246.1 for security management.

During construction of the Project, security management will be governed by those policies and programs, and through a TOP that govern construction security. The TOP details TransCanada’s security expectations and plan elements for the prime construction contractors on the Project. TransCanada will audit the prime contractor plans to ensure compliance with the TOP.

Consistent with this standard, ongoing security assessments will be conducted and documented, and security management plans will be developed and implemented for the Project.

The TOP will also be used to govern security management during the operations phase.

4.7.5 Construction Safety

During construction, the prime contractors will have overall responsibility for health and safety at the work site. A Project-specific construction SMP will be developed and implemented. The SMP outlines key safety guidelines for the prime contractors to use when developing their SSSP so that a collaborative commitment to Project safety is achieved.

TransCanada will review each prime contractor’s SSSP before construction to ensure compliance with company and regulatory requirements. The prime contractors will also prepare a security plan and ERP. These will be reviewed by TransCanada before construction starts. The SMP, SSSP and ERP will be included in site orientations and copies will be made available onsite for the duration of construction.

Qualified construction managers will be appointed to fulfill the requirements of the construction safety program. The construction managers will be authorized to halt any construction activity if the work is not being performed in a manner that meets all applicable safety policies and standards.

PDF Page 11 of 37

Section 4 Compression

TransCanada PipeLines LimitedEastern Mainline Project Application

Page 4-12 October 2014

Where required, the construction managers will coordinate obtaining all safe work permits, and all personnel will be required to complete a contractor safety orientation before working on the work site.

Safety requirements will include a daily safety meeting (or meetings), led and documented by the prime contractors, as well as the use of incident reporting forms and procedures that will include near-hit reporting. Where required, a detailed incident report form from the OPR will also be completed. TransCanada will inspect or audit the prime contractors to ensure strict compliance with the SMP.

For additional safety information during operations, see Section 5.1.2: Health, Safety and Environment.

4.7.6 Construction Inspection

Construction of the compressor unit additions will be supervised and inspected by qualified TransCanada construction inspectors to ensure compliance with all applicable regulations, standards and codes, and with conditions on regulatory authorizations. Inspection staff will be onsite during the entire construction period.

4.7.7 Construction Schedule

The construction of the compressor unit additions is expected to take about 10 to 12 months per station. Subject to regulatory approval, the main construction of the proposed compressor unit additions is proposed to begin in Q2 2016 and be complete by the end of Q1 2017.

4.7.8 Construction Resources

The construction of compressor unit additions will require resources with various skills, ranging from entry-level labourers to highly skilled trades and supervisory personnel. During construction, each station will require about 50 to 150 personnel at one time.

4.7.9 Construction Camps

Construction camps are not required for the compressor unit additions as local accommodations and services will be used for the workers.

4.7.10 Access Plan

Existing access to each of the five sites will be maintained and expanded as required for the compressor unit additions. The access roads will also be used during construction.

PDF Page 12 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Section 4 Compression

October 2014 Page 4-13

4.7.11 Quality Management

TransCanada will provide technical oversight for pipeline engineering and technical activities, and will also ensure coordination with prime contractors and other third-party engineering consultants to ensure that TransCanada’s engineering specifications are met.

All purchased items and contracted services will be obtained from suppliers and contractors that have been pre-qualified in accordance with TransCanada’s internal supplier management and pre-qualification procedures.

Moving into construction, the prime contractors will be responsible for ensuring the work being performed is in accordance with contract documents, the project design, applicable standards, specifications and procedures, and will comply with the project-specific quality plan. Inspectors will monitor activities, such as site mobilization, excavation, piling, welding, backfilling and grading, to ensure compliance.

Design changes during construction are managed in accordance with the appropriate change management procedures and in accordance with TransCanada’s standard engineering practices.

4.7.12 Joining Program

All welding and NDE testing of welds will be conducted in accordance with the requirements of CSA Z662-11, the OPR, and the welding procedures and specifications in Table 4-4.

The prime contractors will conduct welding in accordance with the welding procedures provided by TransCanada. Fabrication and assembly of welded pipe spools will take place at the contractor’s fabrication shop and final fit-up welds will be done at the site. TransCanada will hire an independent third party to conduct the NDE on all welds required for the Project.

4.7.13 Nondestructive Examination

For all high-pressure gas piping designed to CSA Z662-11, TransCanada will use 100% NDE coverage. For all other piping systems, TransCanada will select material and designs joints in accordance with ASME B31.3-2010, Chemical Plant and Petroleum Refinery Piping, as referenced in Clauses 4.14.2.11, 5.1.1, 7.2.4 and 8.1.7 of CSA Z662-11. TransCanada will ensure that joints are examined in accordance with Clause 7.10.3 of CSA Z662-11.

The NDE for facility piping will be carried out in accordance with TransCanada specifications TES-WELD-AS and TES-NDT-RT and, where applicable, TES-NDT-UT2. All butt joint welds will be inspected visually and radiographed or

PDF Page 13 of 37

Section 4 Compression

TransCanada PipeLines LimitedEastern Mainline Project Application

Page 4-14 October 2014

ultrasonically tested for 100% of their circumferences. All fillet welds are to be inspected for 100% of their circumference using magnetic particle inspection or, for non-magnetic welds, a liquid penetrant inspection process.

For lower-risk auxiliary piping systems, TransCanada proposes to conduct NDE on 15% of production welds per day during construction. This conforms to CSA Z662-11, Clause 7.2.5, and would not compromise the safety of the public or company personnel, nor would it affect the company policy of ensuring that all piping is pressure-tested before being placed into service.

For the auxiliary systems that are being proposed for 15% NDE coverage, see Table 4-6. These systems operate at low stress levels and, generally, have instrumentation that shuts down the system and limits any leaks if a release incident occurs.

Table 4-6: Piping Systems Specifications, Design Pressure and NDE Coverage

Piping System TransCanada Specification Design Code

Design Pressure

(kPa)

NDE Coverage

(%)

Instrument Air TES-MATL-MD1, Table 12 ASME B31.3 1035 15

Glycol/Water Heating TES-MATL-MD1, Table 11 ASME B31.3 414 15

Potable Water TES-MATL-MD1, Table 10 ASME B31.3 550 15

Drainage TES-MATL-MD1, Table 13 ASME B31.3 550 15

Lube Oil TES-MATL-MD1, Table 7 ASME B31.3 1035 15

Vents TES-MATL-MD1, Table 11 N/A N/A 15

Note: See TransCanada specification for NDE testing.

4.7.14 Commissioning

On successfully completing integrity validation, the compressor unit additions will be prepared for commissioning and startup. Commissioning will be conducted by qualified TransCanada representatives or third-party service providers.

4.7.15 Emergency Response

Each prime contractor will prepare a field ERP that will be reviewed by TransCanada and will be implemented in the event of an emergency during construction.

For additional information during operations, see Section 5.1.1: Emergency Response.

PDF Page 14 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application Appendix 4-1

October 2014

Appendix 4-1

Topographical Maps

PDF Page 15 of 37

LEGEND

MAP SCALE 1:150,000(NAD 1983 ONTARIO MNR LAMBERT)

DATE: Jul 25, 2014

DRAWN: DJ

PAGE : 1 of 1

CHKD : AE

OFFICE : Calgary

FIA NO. :

DWG NO. : APPD : BL

FILE : 48122EMLPXv006Station134_GMrev1.mxd

JOB NO. : 010048122-000

$1REVISION

Description0

1

2

3

4

5

Original Issue

Updated Pipeline Route

Jul 18, 2014

Jul 25, 2014

--

--

--

- -

Date

-

-

-

-

Route Rev.Rev.

www.focus.ca916 - 42nd Ave. SE, Calgary, Alberta T2G 1Z2

403.263.8200

6 - - -

NOTES:The Proposed Eastern Mainline Project Rev. 0 (July 21, 2014) is created by Focus Corporation, with Kilometre Posts derived using horizontal chainage.

PROPOSED EASTERN MAINLINE PROJECTSTN 134 UNIT ADDITION

0

6

ACTIVITY

Bowmanville- Newcastle

Oshawa

Columbus

GaudCorners

Hampton

Salem

Solina

Taunton

NorthOshawa

Mitchell'sCorners

MUNICIPALITYMUNICIPALITYOF CLARINGTONOF CLARINGTON

CITY OFCITY OFOSHAWAOSHAWA

TOWN OFTOWN OFWHITBYWHITBY

REGIONALREGIONALMUNICIPALITYMUNICIPALITYOF DURHAMOF DURHAM

£¤16

£¤33

£¤26

£¤55

£¤4

£¤35

£¤2

£¤52

£¤57

£¤3£¤14

£¤34

40 km 45 km

50 km 55 km60 km

Inset Scale : 1:150,000

150m

150m

Northing:4874549.40823Easting:193705.14197

Langmaid Road

Concession Road 6

Enfield Road

£¤34

45 km

MUNICIPALITYMUNICIPALITYOF CLARINGTONOF CLARINGTON

REGIONALREGIONALMUNICIPALITYMUNICIPALITYOF DURHAMOF DURHAM

STN 134 -BOWMANVILLE

52 km

0 100 200 300 40050

Metres

B

CULTURECemetery

Pit or Quarry

t t t t t

Ì Ì

Proposed Eastern MainlinePrimary Route

Urban Area

MUNICIPAL

Upper Municipality

Lower Municipality

First Nations

ENVIRONMENTAL

Wetland

Park

Ontario Greenbelt

IMAGE:

Var.

TRANSPORTATION

Secondary Highway

Primary Highway

Railway

Gravel Road

Paved Road

Cutline or Trail

Street

Bridge

UTILITIES

Existing TransCanada R/W

Existing Enbridge R/W

Existing Trans Northern R/W

Existing Station

Transmission Line ! !

Transformer Station dProposed Eastern MainlineKilometre Post (KPG)

5km

Original Montreal LateralKilometre Post (km)

5km

TCPL Property Limit

Proposed StationUnit Addtion

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-1 Topographical Maps

October 2014 Page 1 of 5

PDF Page 16 of 37

LEGEND

MAP SCALE 1:150,000(NAD 1983 ONTARIO MNR LAMBERT)

DATE: Jul 25, 2014

DRAWN: DJ

PAGE : 1 of 1

CHKD : AE

OFFICE : Calgary

FIA NO. :

DWG NO. : APPD : BL

FILE : 48122EMLPXv006Station136_GMrev1.mxd

JOB NO. : 010048122-000

$1REVISION

Description0

1

2

3

4

5

Original Issue

Updated Pipeline Route

Jul 18, 2014

Jul 25, 2014

--

--

--

- -

Date

-

-

-

-

Route Rev.Rev.

www.focus.ca916 - 42nd Ave. SE, Calgary, Alberta T2G 1Z2

403.263.8200

6 - - -

NOTES:The Proposed Eastern Mainline Project Rev. 0 (July 21, 2014) is created by Focus Corporation, with Kilometre Posts derived using horizontal chainage.

PROPOSED EASTERN MAINLINE PROJECTSTN 136 UNIT ADDITIONS

0

6

Colborne

Centreton

EddystoneTubbs

Corners

Vernonville

Greenleys Corners

GriffisCorners

TOWNSHIP OFTOWNSHIP OFHAMILTONHAMILTON

TOWNSHIPTOWNSHIPOF CRAMAHEOF CRAMAHE

TOWNSHIP OFTOWNSHIP OFALNWICK/HALDIMANDALNWICK/HALDIMAND

COUNTY OFCOUNTY OFNORTHUMBERLANDNORTHUMBERLAND

£¤22

£¤21

£¤25

£¤23

£¤31

£¤401

£¤45

£¤2

115 km

120 km

125 km

130 km

Inset Scale : 1:150,000

150m

150m

Northing:4881370.35684Easting:259116.83703

King Road

Lock

e R

oad

Pipeline R

oad

Shel ter V

alley Creek

Shelter Valley Creek

112 km

TOWNSHIP OFTOWNSHIP OFALNWICK/HALDIMANDALNWICK/HALDIMAND

COUNTY OFCOUNTY OFNORTHUMBERLANDNORTHUMBERLAND

STN 136 -COBOURG

122 km

0 100 200 300 40050

Metres

B

Urban Area

MUNICIPAL

Upper Municipality

Lower Municipality

First Nations

ENVIRONMENTAL

Wetland

Park

Ontario Greenbelt

IMAGE:

Var.

ACTIVITY

CULTURECemetery

Pit or Quarry

t t t t t

Ì Ì

Proposed Eastern MainlinePrimary Route

TRANSPORTATION

Secondary Highway

Primary Highway

Railway

Gravel Road

Paved Road

Cutline or Trail

Street

Bridge

UTILITIES

Existing TransCanada R/W

Existing Enbridge R/W

Existing Trans Northern R/W

Existing Station

Transmission Line ! !

Transformer Station dProposed Eastern MainlineKilometre Post (KPG)

5km

Original Montreal LateralKilometre Post (km)

5km

TCPL Property Limit

Proposed StationUnit Additions

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-1 Topographical Maps

October 2014 Page 2 of 5

PDF Page 17 of 37

LEGEND

MAP SCALE 1:5,000(NAD 1983 ONTARIO MNR LAMBERT)

DATE: Jul 25, 2014

DRAWN: DJ

PAGE : 1 of 1

CHKD : AE

OFFICE : Calgary

FIA NO. :

DWG NO. : APPD : BL

FILE : 48122EMLPXv006Station139_GMrev1.mxd

JOB NO. : 010048122-000

$1REVISION

Description0

1

2

3

4

5

Original Issue

Updated Pipeline Route

Jul 18, 2014

Jul 25, 2014

--

--

--

- -

Date

-

-

-

-

Route Rev.Rev.

www.focus.ca916 - 42nd Ave. SE, Calgary, Alberta T2G 1Z2

403.263.8200

6 - - -

NOTES:The Proposed Eastern Mainline Project Rev. 0 (July 21, 2014) is created by Focus Corporation, with Kilometre Posts derived using horizontal chainage.

PROPOSED EASTERN MAINLINE PROJECTSTN 139 UNIT ADDITIONS

0

6

Belleville

BlessingtonLonsdaleStation

Milltown

Shannonville

Melrose

Marysville

CITY OFCITY OFBELLEVILLEBELLEVILLE

TOWNSHIP OFTOWNSHIP OFTYENDINAGATYENDINAGA

COUNTY OFCOUNTY OFHASTINGSHASTINGS

£¤49£¤4010 km

5 km

10 km

Inset Scale : 1:150,000137m

150m

150m

157m

Northing:4899997.69085Easting:321813.63672

McF

arlane Road

Lazier Road

178 km

TOWNSHIP OFTOWNSHIP OFTYENDINAGATYENDINAGA

COUNTY OFCOUNTY OFHASTINGSHASTINGS

STN 139 -BELLEVILLE

0 km

0 100 200 300 40050

Metres

B

Urban Area

MUNICIPAL

Upper Municipality

Lower Municipality

First Nations

ENVIRONMENTAL

Wetland

Park

Ontario Greenbelt

IMAGE:

Var.

ACTIVITY

CULTURECemetery

Pit or Quarry

t t t t t

Ì Ì

Proposed Eastern MainlinePrimary Route

TRANSPORTATION

Secondary Highway

Primary Highway

Railway

Gravel Road

Paved Road

Cutline or Trail

Street

Bridge

UTILITIES

Existing TransCanada R/W

Existing Enbridge R/W

Existing Trans Northern R/W

Existing Station

Transmission Line ! !

Transformer Station dProposed Eastern MainlineKilometre Post (KPG)

5km

Original Montreal LateralKilometre Post (km)

5km

TCPL Property Limit

Proposed StationUnit Additions

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-1 Topographical Maps

October 2014 Page 3 of 5

PDF Page 18 of 37

LEGEND

MAP SCALE 1:5,000(NAD 1983 ONTARIO MNR LAMBERT)

DATE: Jul 25, 2014

DRAWN: DJ

PAGE : 1 of 1

CHKD : AE

OFFICE : Calgary

FIA NO. :

DWG NO. : APPD : BL

FILE : 48122EMLPXv006Station142_GMrev1.mxd

JOB NO. : 010048122-000

$1REVISION

Description0

1

2

3

4

5

Original Issue

Updated Pipeline Route

Jul 18, 2014

Jul 25, 2014

--

--

--

- -

Date

-

-

-

-

Route Rev.Rev.

www.focus.ca916 - 42nd Ave. SE, Calgary, Alberta T2G 1Z2

403.263.8200

6 - - -

NOTES:The Proposed Eastern Mainline Project Rev. 0 (July 21, 2014) is created by Focus Corporation, with Kilometre Posts derived using horizontal chainage.

PROPOSED EASTERN MAINLINE PROJECTSTN 142 UNIT ADDITIONS

0

6

Cushendall

FairmountGlenburnie

HemlockDowns

Ida Hill

Joyceville

MountChesney

Woodburn

PineHill

CITY OFCITY OFKINGSTONKINGSTON

TOWNSHIPTOWNSHIPOF SOUTHOF SOUTH

FRONTENACFRONTENAC

TOWNSHIPTOWNSHIPOF FRONTENACOF FRONTENAC

ISLANDSISLANDS

COUNTY OFCOUNTY OFFRONTENACFRONTENAC

£¤2

£¤15

£¤401

0 km

5 km

10 km

Inset Scale : 1:150,000

150m

150

m

McFarlane Road

Woo

ds S

ide

road

£¤15

River Styx

249 km

CITY OFCITY OFKINGSTONKINGSTON

STN 142 -KINGSTON

0 km

Northing:4910997.23605Easting:391321.79566

0 100 200 300 40050

Metres

B

Urban Area

MUNICIPAL

Upper Municipality

Lower Municipality

First Nations

ENVIRONMENTAL

Wetland

Park

Ontario Greenbelt

IMAGE:

Var.

ACTIVITY

CULTURECemetery

Pit or Quarry

t t t t t

Ì Ì

Proposed Eastern MainlinePrimary Route

TRANSPORTATION

Secondary Highway

Primary Highway

Railway

Gravel Road

Paved Road

Cutline or Trail

Street

Bridge

UTILITIES

Existing TransCanada R/W

Existing Enbridge R/W

Existing Trans Northern R/W

Existing Station

Transmission Line ! !

Transformer Station dProposed Eastern MainlineKilometre Post (KPG)

5km

Original Montreal LateralKilometre Post (km)

5km

TCPL Property Limit

Proposed StationUnit Additions

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-1 Topographical Maps

October 2014 Page 4 of 5

PDF Page 19 of 37

LEGEND

MAP SCALE 1:5,000(NAD 1983 ONTARIO MNR LAMBERT)

DATE: Jul 25, 2014

DRAWN: DJ

PAGE : 1 of 1

CHKD : AE

OFFICE : Calgary

FIA NO. :

DWG NO. : APPD : BL

FILE : 48122EMLPXv006Station144_GMrev1.mxd

JOB NO. : 010048122-000

$1REVISION

Description0

1

2

3

4

5

Original Issue

Updated Pipeline Route

Jul 18, 2014

Jul 25, 2014

--

--

--

- -

Date

-

-

-

-

Route Rev.Rev.

www.focus.ca916 - 42nd Ave. SE, Calgary, Alberta T2G 1Z2

403.263.8200

6 - - -

NOTES:The Proposed Eastern Mainline Project Rev. 0 (July 21, 2014) is created by Focus Corporation, with Kilometre Posts derived using horizontal chainage.

PROPOSED EASTERN MAINLINE PROJECTSTN 144 UNIT ADDITIONS

0

6

Brockville

Prescott

BlueChurch

Bethel

Algonquin

Fairfield

Maynard

Prescott

SouthAugusta

StonesCorners

Maitland

RiverviewHeights

Bisseltown

LordsMills

FairfieldEast

TOWN OFTOWN OFPRESCOTTPRESCOTT

TOWNSHIPTOWNSHIPOF EDWARDSBURGH/CARDINALOF EDWARDSBURGH/CARDINAL

TOWNSHIP OFTOWNSHIP OFELIZABETHTOWN-ELIZABETHTOWN-

KITLEYKITLEY

TOWNSHIPTOWNSHIPOF AUGUSTAOF AUGUSTA

UNITED COUNTIESUNITED COUNTIESOF LEEDS ANDOF LEEDS AND

GRENVILLEGRENVILLE£¤401

£¤2£¤26

£¤31

£¤6

£¤15

Inset Scale : 1:150,000

150m

150m

148m

145m

Northing:4948078.81835Easting:450720.79657

Lords Mills R

oad

Rocky R

oad

Coun

ty Road

26

£¤26

321 km

322 km

TOWNSHIPTOWNSHIPOF AUGUSTAOF AUGUSTA

UNITED COUNTIESUNITED COUNTIESOF LEEDS ANDOF LEEDS AND

GRENVILLEGRENVILLESTN 144 -

BROCKVILLE

0 100 200 300 40050

Metres

B

Urban Area

MUNICIPAL

Upper Municipality

Lower Municipality

First Nations

ENVIRONMENTAL

Wetland

Park

Ontario Greenbelt

IMAGE:

Var.

ACTIVITY

CULTURECemetery

Pit or Quarry

t t t t t

Ì Ì

Proposed Eastern MainlinePrimary Route

TRANSPORTATION

Secondary Highway

Primary Highway

Railway

Gravel Road

Paved Road

Cutline or Trail

Street

Bridge

UTILITIES

Existing TransCanada R/W

Existing Enbridge R/W

Existing Trans Northern R/W

Existing Station

Transmission Line ! !

Transformer Station dProposed Eastern MainlineKilometre Post (KPG)

5km

Original Montreal LateralKilometre Post (km)

5km

TCPL Property Limit

Proposed StationUnit Additions

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-1 Topographical Maps

October 2014 Page 5 of 5

PDF Page 20 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application Appendix 4-2

October 2014

Appendix 4-2

Preliminary Plot Plans

PDF Page 21 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-2 Preliminary Plot Plans

October 2014 Page 1 of 5

PDF Page 22 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-2 Preliminary Plot Plans

October 2014 Page 2 of 5

PDF Page 23 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-2 Preliminary Plot Plans

October 2014 Page 3 of 5

PDF Page 24 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-2 Preliminary Plot Plans

October 2014 Page 4 of 5

PDF Page 25 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-2 Preliminary Plot Plans

October 2014 Page 5 of 5

PDF Page 26 of 37

TransCanada PipeLines Limited Eastern Mainline Project Application Appendix 4-3

October 2014

Appendix 4-3

Preliminary Process Flow Diagrams

PDF Page 27 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 1 of 10

PDF Page 28 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 2 of 10

PDF Page 29 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 3 of 10

PDF Page 30 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 4 of 10

PDF Page 31 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 5 of 10

PDF Page 32 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 6 of 10

PDF Page 33 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 7 of 10

PDF Page 34 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 8 of 10

PDF Page 35 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 9 of 10

PDF Page 36 of 37

PRELIMINARY ONLY

CONSTRUCTIONNOT FOR

TransCanada PipeLines Limited Eastern Mainline Project Application

Appendix 4-3 Preliminary Process Flow Diagrams

October 2014 Page 10 of 10

PDF Page 37 of 37