PEA Smart Grid Roadmap PEA Smart Grid Roadmap Mr. Pongsakorn Yutthagovit Mr. Pongsakorn Yutthagovit Manager of Project Planning Division Manager of Project Planning Division Manager of Project Planning Division Manager of Project Planning Division Smart Grid Seminar Smart Grid Seminar 2013 2013 February February 14 14, , 2013 2013 1

Upload: dohanh

Post on 14-Oct-2018

295 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid RoadmapPEA Smart Grid Roadmap

Mr. Pongsakorn YutthagovitMr. Pongsakorn Yutthagovit

Manager of Project Planning DivisionManager of Project Planning DivisionManager of Project Planning DivisionManager of Project Planning Division

Smart Grid Seminar Smart Grid Seminar 20132013

FebruaryFebruary 1414, , 20132013

1

yy ,,

Page 2: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid

PEA Smart Grid RoadmapPEA Smart Grid Roadmap

PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 thth

Smart Meter in Pattaya city, ChonburiSmart Meter in Pattaya city, Chonburi

Page 3: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid RoadmapPEA Smart Grid Roadmappp

3

Page 4: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

Driver PEA Smart Grid

Global Warming

EV&ChargingStation

RE&EnergyStorage

Smart Meter EnergyEfficiency

Global warming and development of technology

DRIVERGreater Investment Freedom

Structure of the buyer to the

The expansion of trade andIndustrial border

seller

Increasing customer satisfaction

Changes in transportation system

satisfaction

4

Page 5: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

10 Policy management and energy development of PEA

1. Beyond SMART GRID

2. Road to LED2. Road to LED

3. Green Investment

4. Green Office4. Green Office

6. ZERO Accident

5. 100% Electrified5. 100% Electrified

7. Community Partnership7. Community Partnership

8. Moving to AEC

9. High Quality & Qualified Labor9. High Quality & Qualified Labor

10. PEA Rebranding

5

Page 6: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid Roadmap

Stage : 3

Stage : 1

Stage : 2

2017 2021

2022-2026

Efficient Stage : 1

2012-2016

2017-2021

Project Expansion of all

Efficient Improvement of

electricity

Improvement of Infrastructure standard and

Expansion of all PEA customers

quality and service

6Pilot Project

Page 7: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid

Supply Side Network Demand Side

Renewable Energy

Renewable Energy

Smart Substation

Smart Substation Smart MeterSmart MeterEnergyEnergy

Micro GridMicro Grid

SubstationSubstation

Feeder Automation

Feeder Automation Smart HomeSmart Home

Community Power PlantCommunity Power Plant

AutomationAutomation

EnergyEfficiency

EnergyEfficiency

EV ChargingStation

EV ChargingStation

7

Page 8: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA S G id PEA S G id dd P d l l P d l l PEA Smart Grid PEA Smart Grid underunder Power development plan Power development plan

THE 11th NATIONAL ECONOMIC

( )AND SOCIAL DEVELOPMANT PLAN (2012-2016)

8

Page 9: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid under Power development plan 11 th

PEA Smart Grid Development (13,465 M.THB)

Smart Grid Development Project, Phase 1

AMI D l t P j t Ph 1

Micro Grid Development Project in

Mae Sareang District,

M H P iAMI Development Project, Phase 1

Power System Improvement Plan for Very

Mae Hongson Province

Micro Grid Development Project in y p y

Small Power Producer of Renewable

Energy

p j

Koh Kood and Koh Mak,

Trad Province

9

Page 10: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid under Power development plan 11 th

11. SMART GRID DEVELOPMENT PROJECT, PHASE I. SMART GRID DEVELOPMENT PROJECT, PHASE I

DurationDuration 2013 2013 ‐‐ 20172017

Project AreaProject Area ChiangmaiChiangmai province, province, NakornrachasimaNakornrachasima province, province, PhuketPhuket province and Pattayaprovince and Pattaya

Scope of workScope of work ‐‐ Advanced Meter Infrastructure installationAdvanced Meter Infrastructure installation 400400,,000  000  metersmeters‐‐ Smart Substation System InstallationSmart Substation System Installation 2020 setssetsyy‐‐ Solar Energy Rooftop Solar Energy Rooftop  2424 UnitsUnits‐‐ Energy Energy StorageStorage 12 12  UnitsUnits‐‐ Charging StationCharging Station 2424 UnitsUnits

BudgetBudget 44,,860 860 M.THBM.THB

10

Page 11: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid under Power development plan 11 th

22. AMI DEVELOPMENT PROJECT, PHASE I. AMI DEVELOPMENT PROJECT, PHASE I

DurationDuration 2014 2014 ‐‐ 20182018

,,

Project AreaProject Area 26 26 municipalities in PEA service areamunicipalities in PEA service areajj pp

Scope of workScope of work I t llI t ll Ad d M t I f t tAd d M t I f t t 11 000000 000000 ttScope of workScope of work ‐‐ Install Install Advanced Meter Infrastructure Advanced Meter Infrastructure 11,,000000,,000000 setssets

BudgetBudget 55,,350 350 M.THBM.THB

11

Page 12: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid under Power development plan 11 th

33. MICRO GRID DEVELOPMENT PROJECT . MICRO GRID DEVELOPMENT PROJECT 

DurationDuration 20142014 ‐‐ 20182018

(Mae (Mae SareangSareang district, Mae district, Mae HongsonHongson province)province)

DurationDuration 2014 2014 ‐‐ 20182018

P j AP j A SS di idi i iiProject AreaProject Area Mae Mae SareangSareang district, Mae district, Mae HongsonHongson ProvinceProvince

Scope of workScope of work ‐‐ Install Install Energy Energy StorageStorage 1 1 setset‐‐ Install Micro Grid ControllerInstall Micro Grid Controller 1 1 setset

BudgetBudget 330 330 M.THBM.THB

12

Page 13: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid under Power development plan 11 th

44. MICRO GRID DEVELOPMENT PROJECT . MICRO GRID DEVELOPMENT PROJECT ((K hK h K dK d dd K hK h M kM k T dT d ii

DurationDuration 2014 2014 ‐‐ 20182018

((KohKoh KoodKood and and KohKoh MaakMaak, , TradTrad provinceprovince

Project AreaProject Area KohKoh KoodKood andand KohKoh MaakMaak TradTrad ProvinceProvinceProject AreaProject Area KohKoh KoodKood and and KohKoh MaakMaak, , TradTrad ProvinceProvince

Install Hydro Power PlantInstall Hydro Power Plant 11 setsetScope of workScope of work ‐‐ Install Hydro Power PlantInstall Hydro Power Plant 1 1 setset‐‐ Install PV plantInstall PV plant 2 2 setset‐‐ Install Energy StorageInstall Energy Storage 2 2 setset

BudgetBudget 225 225 M.THBM.THB

13

Page 14: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grid under Power development plan 11 th

55. Power System Improvement supporting . Power System Improvement supporting ll dll d

DurationDuration 2014 2014 ‐‐ 20182018

very small power producer very small power producer 

Project AreaProject Area All over the countryAll over the countryProject AreaProject Area All over the countryAll over the country

Scope of workScope of work ‐‐22 22 kV andkV and 33 33 kV Distribution line   Construction  kV Distribution line   Construction  11,,800 800 cctcct‐‐km km ‐‐Voltage potential improvement with equipment  Voltage potential improvement with equipment  55 55 sets sets 

BudgetBudget 22,,730 730 M.THBM.THB

14

Page 15: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

Smart Meter in Pattaya city, ChonburiSmart Meter in Pattaya city, Chonburiy y,y y,

15

Page 16: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grids Project “Smart Meter in Pattaya city, Chonburi”

In Pattaya City Chonburi

Project AreaProject Area

In Pattaya City, Chonburi

It cover an area of 6 substation and 1 Island are Pattaya Nua, Pattaya Tai,

Pattaya Tai2, Banglamung, Chomtien, Khao Mai Kaeo and Lan-Island

16

Page 17: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

22 kV Existing Distribution

System in Pattaya City

Kratinglai

Intersection

Motor way

North Pattaya22 kV Existing Distribution System AreaN th P tt S b t ti (77 MW)

y y y

Banglamung (EGAT)(2x50 MVA)

North Pattaya(2x50 MVA)

North Pattaya Substation (77 MW)- Supply the customers in Naglua and

North Pattaya Area

B l S b t ti (F d N 1 10

Banglamung (PEA)South Pattaya 2 (Temp)

Banglamung Substation (Feeder No.1 – 10

: 51 MW)- Supply the customers in Middle Pattaya Area

South Pattaya

(2x50 MVA)

South Pattaya 2 (Temp)(1x50 MVA)

and Pattaya Beach

South Pattaya Substation (Feeder No.1 – 10

: 66 MW)P tt Cit - Supply the customers in South Pattaya Area,

Theprasit Road and Lan Island

South Pattaya 2 Substation (Temp)

Pattaya City

Area

(Feeder No.1 – 5 : 32 MW)- Supply the customers in South Pattaya Area

Chomtien Substation (Feeder No.1 – 10

Float MarketTheprasit Road

Chomtien(2x50 MVA)

: 33 MW)- Supply the customers in Chomtien Beach

Page 18: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grids Project “Smart Meter in Pattaya city, Chonburi”

Project Duration/ Scope of WorkProject Duration/ Scope of Work

The period of this project is 2 year(Between 2013-2014)

Installation is divided into three tasks

- Installation the Data Center System

- Installation Smart Meter

(I l di U i t ll ti El t h i l t )

Data Center

(Including Uninstallation Electromechanical meter)

- Installation the Infrastructure Communication

Smart MeterCommunication

18

Page 19: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grids Project “Smart Meter in Pattaya city, Chonburi”

1. Uninstall old meter and replace by Smart Meter, Amount 116,308 Unit

Scope of WorkScope of Work

• Smart Meter 3 Phase, Amount 13,844 Unit

• Smart Meter 1 Phase, Amount 102,464 Unit

• Data Concentrator Unit (DCU), Amount 2,834 UnitData Concentrator Unit (DCU), Amount 2,834 Unit

• Meter Interface Unit (MIU ), Amount 50 Unit

19

Page 20: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grids Project “Smart Meter in Pattaya city, Chonburi”

Installation Plan for Smart Meter in Each model.

20

Page 21: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grids Project “Smart Meter in Pattaya city, Chonburi”

Scope of WorkScope of Work

2. Installation and Data center’s software Development.

Main items as below-Database Server and Database’s software

MDMS S d MDMS ’ ft-MDMS Server and MDMS ’s software

-Server for support Other Application

-Network Equipment and Security Equipment

3. Install the Infrastructure communication equipment for AMI system.

21

Page 22: PEA Smart Grid Roadmap - cigre-thailand.org · PEA Smart Grid Roadmap PEA Smart Grid under Power development plan PEA Smart Grid under Power development plan 11 11 th Smart Meter

PEA Smart Grids Project “Smart Meter in Pattaya city, Chonburi”

InvestmentInvestment

Amount 917 Million Baht

Smart meter and Other equipment 600 Million Baht Smart meter and Other equipment 600 Million Baht

Data center 110 Million Baht

the Infrastructure Communication Equipment 207 Million Baht