    chairman, hssi

    This book is specially dedicated to our late chairman Dato Ir. Haji Abu Bakar

    Bin Haji Mohd Amin and late Dato Ir C. Sivasubramaniam in GratefulAppreciation for their years of outstanding service and devotion.

    They set the foundation f or what we have become today

    They fortif ied the pillars to help us weather the storm

    They taught us to bri dge over insur mountable odds

    Th ey showed us the hi ghway to a better tomorr ow.

    Though sorely missed, be assured that their legacy lives on through all of usat the HSS Group.

    Dato Ir. Haji Abu Bakar Bin Haji Mohd Amin

    1941 - 2009

    Dato Ir. C. Sivasubramaniam

    1925 - 2009

  • 8/12/2019 Penang Bridge Widening booklet

    3/58

    contents1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    introduction

    design concept and key considerations

    design development

    award of contract

    scope of widening works

    construction challenges and innovations

    conclusion

    references

    appendices

  • 8/12/2019 Penang Bridge Widening booklet

    4/58

    key milestonedates

    15 10 2006

    Completion of

    toll plaza

    03 02 2006

    Starting of firstsoil investigation

    boreholes

    18 08 2006

    Driving of first

    bore piles

    06 11 2007

    First beam

    launched

    27 05 2009

    Completion ofstitching Prai side

    26 04 2009

    Completion of

    stitching Penangside

    1

  • 8/12/2019 Penang Bridge Widening booklet

    5/58

    introduction1.0

    2

  • 8/12/2019 Penang Bridge Widening booklet

    6/58

    The Penang Bridge is a 13.5 km crossing that

    connects Gelugor on the Penang Island to Seberang

    Perai on the mainland of Peninsular Malaysia. It

    comprises a 2.2 km length of cable-stayed bridge and

    high level approach viaducts (dual 3 lane) and 5.76km of low level approach viaducts (dual two-lane).

    Construction of this bridge started in 1982 and was

    officially opened to traffic in 1985. By 2002, the traffic

    demand on the bridge had increased to 98,000

    vehicles, reaching capacity during peak hours.

    Under the terms of the Concession Agreement, PBSB

    as the Concession Company was required to widen

    the existing dual two-lane low-level approach viaducts

    at an appropriate time in the Concession Period to

    enable traffic capacity and toll revenue to bemaximized.

    The Penang Bridge1.1

    3

  • 8/12/2019 Penang Bridge Widening booklet

    7/58

    The Consultants

    Penang Bridge Sdn Bhd engaged Consultants HSSI

    to provide the following professional engineering

    services for the Project, as the lead consultant:

    Preliminary engineering study Traffic studies

    Preliminary environmental impact screening

    study

    Detailed engineering design

    Tender documentation

    Pre-qualification of tenderers

    Construction and supervision works

    In engaging HSSI, Penang Bridge Sdn Bhd sought

    the following standards of services:

    Formulation and implementation of a cost-

    effective method of widening the bridge Minimization of construction impacts on traffic

    flows

    Project delivery on-time and to budget

    Rigorous application of QA standards

    Regular reporting to Penang Bridge Sdn Bhd

    HSSI was engaged in September 2003 and provided

    services through to August 2009. At the peak, HSSI

    had 70 professional staffs working on the project.

    This booklet records the design and construction

    work and, in the process, summarizes the main

    challenges faced by the consultant and contractor

    involved in widening the Penang Bridge.

    This Booklet1.2 1.3

    4

  • 8/12/2019 Penang Bridge Widening booklet

    8/58

    design concept2.0

    Design Concept And Key Considerations 5

  • 8/12/2019 Penang Bridge Widening booklet

    9/58

    Layout

    T h e l o c a t io n o f t h e l o w - l e v el a p p r o a c h v i a d u c t s i n

    r el at io n t o t h e o v er al l c r o ss i n g , i n c l u di n g t h e

    m ai n c ab le -s tay ed b ri dg e an d t he h ig h -l ev el

    approach spans, is shown in Fig 2.1.1.

    The eastern low-level viaduct, with a total length of

    3.96 km and referred to as the Prai Shore Approach,

    extends from the east abutment to pier 24E. It

    comprises nineteen five-span units, each 40 m in

    length. At the eastern end, there is one three-span

    unit, each 40 m in length, and one 38 m long single-

    span. The western low-level viaduct, with a total

    length of 1.8 km and referred to as the Middle Bank

    Bridge, extends from pier 24W to pier 69W. It

    comprises nine five-span units, each 40 m in length.

    Penang bridge general layout

    Fig 2.1.1

    2.1

    6

  • 8/12/2019 Penang Bridge Widening booklet

    10/58

    7

  • 8/12/2019 Penang Bridge Widening booklet

    11/58

    2.2

    The Penang Bridge carries a significant volume of

    motorcycles and scooters. At the feasibility study

    stage, Consultants HSSI examined options for adding

    a dedicated motorcycle lane to each side of the

    existing dual two-lane low level approach viaducts, onthe basis that this could significantly improve traffic

    capacity and in turn avoid widening works involving

    new foundations. However, it was concluded that a

    lower cost option of this form would only provide an

    interim solution and would not maximize the traffic

    capacity provided by the existing dual three-lane

    cable stayed bridge and high-level approach spans.

    It was therefore recommended that the low-level

    approach viaducts and Penang Island Interchange

    ramp bridges should be widened to dual three-lane

    standard in order to provide the same capacity as that

    available on the existing dual three-lane sections ofthe Penang Bridge.

    This recommendation was approved by LLM

    (Lembaga Lebuhraya Malaysia) on 11 November

    2003. Fig 2.2.1 shows the carriageway layout on the

    existing low-level viaducts and the final layout

    required with the widening.

    375 375 375 375

    35 355 35 355 2

    Existing cross-section

    New cross-section

    48 Widening48 Widening

    9 25 9 25

    3925 3925

    Bridge Cross-section

    Fig 2.2.1

    Cross-Section of widened carriageway

    8

  • 8/12/2019 Penang Bridge Widening booklet

    12/58

    2.3

    The present dual two lane arrangement of the low-level approach is to be widened to dual three lane. This will

    form the major component of the construction works.

    Several widening options were considered including symmetric widening, asymmetric widening and a new

    parallel, separate structure. Both asymmetric and parallel widening posed the problem of having to overcomemore difficult transition zones and for this reason they were not adopted. Symmetric widening was recommended

    on the basis that it would facilitate easier integration with the cable-stayed bridge, the high level approach spans

    and the existing interchanges, as well as minimizing the impacts on users during construction.

    Widening Options

    9

  • 8/12/2019 Penang Bridge Widening booklet

    13/58

    2.4

    The design concept for the low-level viaduct widening

    works envisaged that the widening would be achieved

    as follows:

    Extending the sub-structure on either side ateach pier location and providing two additional

    longitudinal beams with a composite deck slab

    on each side of the deck

    Adding two reinforced concrete bored piles, an

    extension to the pile cap, a new column and an

    extension of the crosshead on each side at each

    pier location, designed to support the extended

    deck

    Providing structural connections between the

    existing and new works at pile cap and deck

    level

    The basic design concept for widening of the low-level viaducts is shown in Fig 2.4.1

    The typical cross-section of the widened viaducts that

    was finally adopted is shown in Fig 2.4.2. In order to

    provide a harmonious solution for the widening, the

    new works incorporate structural elements of similar

    size and form to those of the existing structure

    F i g 2 .4 .2 Typical Cross-Section of Completed

    Viaduct Widening (symmetrical about existing viaduct

    centerline)

    Fig 2.4.1

    Design Concept for the Widening

    10

  • 8/12/2019 Penang Bridge Widening booklet

    14/58

    At layby locations, the design of the widening works

    follow a similar approach with two additional precast

    beams are placed to the outside of the existing layby

    in order to form a new layby at the same location. The

    design also provides for the controlled breaking-out of

    the existing deck in the vicinity of the existing

    longitudinal joints and the casting of concrete stitching

    in order to ensure that the deck is fully integral.

    So as to avoid any disruption to traffic, the design

    approach established by Consultants HSSI allowed

    all of the construction works related to widening of the

    bridge to be completed independently to the existing

    structure and outside of the existing parapets.

    Controlled traffic management was only required for

    the demolition of the existing parapets and the

    stitching of the new deck slab to the existing deck

    slab.

    By using precast concrete pile cap shells as

    permanent formwork to the in-situ structural concrete

    pile cap, a dry working environment was provided for

    the in-situ works once the shell was placed and

    positively located against the existing pile cap face.

    Fig 2.4.2

    11

  • 8/12/2019 Penang Bridge Widening booklet

    15/58

    The following options were considered for the

    additional beams required:

    Prestressed concrete I -beams (ie similar to the

    existing beams): Not recommended because it

    would detract from the visual appearance of the

    deck edge (refer Section 2.5)

    Prestressed concrete U -beams (therecommended arrangement refer Section 2.5):

    Results in a shorter edge overhang and also

    provides more elegant appearance to the edge

    of the superstructure (note that the addition of

    two precast U-beams on each was not adopted

    because it could not provide a standardized

    solution for all spans)

    Steel box girders: Offers the same advantages

    as the prestressed U-beam and is significantly

    lighter, thus reducing the magnitude of the

    additional load transferred to the existing

    foundations

    Steel I-beams: Offers the advantage of being

    light, but requires a long deck cantilever and

    would be more flexible than the existing precast

    concrete beams - in order to limit differential

    deflection effects between the new steel and

    existing concrete beams, it would be necessary

    to use a comparatively uneconomic section,

    working at low stresses, so as to provide

    adequate stiffness.

    Various options were considered for the new pile

    foundations, including:

    Driven precast concrete spun piles: Not

    recommended due to the risk of damage and/or

    differential settlement occurring to the existing

    spun pile foundations and viaduct structures

    during driving of such high-displacement piles. Driven open-ended tubular steel piles: Whilst

    this option provided a lower-displacement pile

    solution compared to drive spun piles, it was

    also not recommended on the grounds of risk of

    damage / differential settlement risk resulting

    either from vibration effects or from the

    densification of the soil during pile driving

    Bored / cast-in-situ reinforced concrete piles

    with permanent casings (recommended)

    12

  • 8/12/2019 Penang Bridge Widening booklet

    16/58

    2.5

    Aesthetics was given due importance in selecting the

    beam type. The Consultant recommended that post-

    tensioned precast U -beams should be used for the

    edge girders on the widening, rather than thestandard precast I-beams used in the original

    structure.

    This offered the following advantages:

    Improved visual appearance to the deck edge in

    elevation Higher flexural stiffness, which eliminated the

    need to provide intermediate in-span

    diaphragms between the new beams and the

    existing beams for the purposes of matching

    deflections across the deck width

    I - Beam U - Beam

    Aesthetics

    13

  • 8/12/2019 Penang Bridge Widening booklet

    17/58

    designdevelopment

    3.0

    14

  • 8/12/2019 Penang Bridge Widening booklet

    18/58

    Design and LoadingStandards for

    Widening Scheme

    The design criteria adopted for the new widening

    works are presented in Appendix A. The structural

    design of the components of the widened portion is inaccordance to the British Standard; BS 5400 and the

    loadings are according to BD37/01.

    3.2

    The construction sequence needed to account for the

    transfer of load between the new construction and the

    existing structure, along with the need to minimize

    disruption to traffic. This led to the sequence for the

    construction of the new works as indicated in Figs

    3.2.1 to 3.2.5.

    The staging of the construction was programmed in

    five stages, as follows:

    Stage 1: Construct new piles adjacent to the

    existing pier supports

    Stage 2: Construct the new column on top of the

    new pile cap extension

    Stage 3: Place the new precast beams and

    construct the in-situ concrete deck diaphragms

    Stage 4: Construct the new deck slab wideningand new parapet, and install street lighting on

    the new parapet

    Stage 5: Cast the in-situ concrete stitch between

    the existing and new pile caps

    Fig 3.2.1

    Fig 3.2.5

    Fig 3.2.4

    Fig 3.2.3

    Fig 3.2.2

    3.1

    Construction

    sequence

    15

  • 8/12/2019 Penang Bridge Widening booklet

    19/58

    16

  • 8/12/2019 Penang Bridge Widening booklet

    20/58

    3.3

    For the reasons given in Section 2.4, the use of driven prestressed spun concrete piles or low-displacement

    driven steel tabular pile were not recommended. Bored/cast-in-situ reinforced concrete piles would minimize the

    risk of differential settlement and the risk of damage to the existing spun concrete raked pile foundations during

    construction of any new piles. Correspondingly, this low-displacement pile solution was adopted for the design.

    Finalization of the pile location, size and number of new piles was constrained by the spacing, rake angle and

    rake direction of the existing piles. Further, the size of pile cap in the longitudinal direction was constrained by the

    fact that there was to be no additional obstruction to the tidal flow because this could result in excessive local

    scour at the pile group. It would also have made the pile caps more visually obtrusive than the existing simple

    rectangular plan shape.

    In addition, any new piles had to be located sufficiently far from the outer face of the existing bridge parapets to

    allow a piling rig and other piling equipment to work safely at all times, without disruption to traffic on the existing

    bridge.

    Figs 3.3.1 and3.3.2 show the typical layout of piles in the existing foundations - these illustrate the dimensional

    constraints applying to design and construction in adding new piles to extend the foundations.

    Fig 3.3.1

    Fig 3.3.2

    Constraints Imposed by the Existing Pile Foundations

    17

  • 8/12/2019 Penang Bridge Widening booklet

    21/58

    3.4

    The subsoil conditions at the Penang Bridge site are

    highly variable, but are generally characterized by a

    deep layer of soft marine clay (typically 15 m to 20m

    deep, but reaching depths of between 40m and 60 m

    at certain sections on the eastern side), overlyingmedium dense silty sands and silty clays. In some

    locations, the silty sands overlay residual soils formed

    from the weathering of the granite bedrock. The depth

    to the bedrock horizon varies considerably across the

    site and is deepest on the eastern side of the crossing

    where it occurs at depths of over of 100 m.

    On the western side of the crossing, the bedrock is

    found at shallower depths of between 50 m to 80 m.

    The silty sand layers are also denser on the western

    side of the crossing. The soil profile (as shown in

    Appendix B) indicates the variability of along length ofthe bridge.

    A total of 70 boreholes, to depths between 35 m and

    80 m, were drilled to establish the soil characteristics

    across the site.

    Sub-Soil Conditions

    18

  • 8/12/2019 Penang Bridge Widening booklet

    22/58

    Durability Considerations

    A design life of 120 years was specified for all

    elements of the bridge widening works. Durability of

    the piles, pile caps, piers and superstructure was

    ensured in the design by a combination of the

    following measures: Limiting the flexural crack width in reinforced

    concrete members

    Limiting the tensile stress in prestressed

    concrete

    Specifying appropriate values of minimum cover

    to the embedded steel reinforcement

    For concrete mixes, specifying maximum

    water/cement ratios and minimum proportions of

    pulverised fuel ash (pfa) or ground granulated

    blast furnace slag (ggbs) cement replacement

    For the bored piles and concrete structures exposed

    to aggressive marine conditions, dense and durable

    concrete was recommended. In order to ensure

    adequate durability, a minimum proportion of 60% of

    ggbs or 25% of pfa was specified to be mixed withOrdinary Portland Cement (OPC).

    For the deck stitch, silica fume and polypropylene

    fibres were specified in the mix design in order to

    provide early-age strength and resistance to early -

    age cracking.

    The steel casing to the bored piles was considered to

    be sacrificial in the original design of the bored piles

    constructed with short casings under bentonite.

    Structural

    Element

    Grade Cement

    Replacement

    Maximum

    Water:

    CementRatio

    Location Nominal

    Cover

    (mm)

    Design

    Crack

    Width(5)

    (mm)

    In -situ

    concretebored piles

    (cased)

    40 60% ggbs 0.35 Faces

    adjacentto casing

    75 N/A

    Pile capprecast

    shell(offshore)

    50 60% ggbs 0.40 Exposedfaces

    Internalfaces

    5045

    0.10n/a

    Pile cap in -situ pour(offshores)

    40 60% ggbs 0.45 Exposedfaces 65 0.13

    Piers (in -

    situ)

    40 60% ggbs 0.45 Exposed

    facesBearing

    plinths

    65

    65

    0.13

    0.13

    Deckbeams

    (precast)

    60 60% ggbs 0.35 Exposedfaces

    Internalfaces

    45 (1)

    45 (1)0 (2)

    0 (2)

    Deck slab

    (in - situ)

    50 60% ggbs 0.45 Top

    surface

    Soffit

    40 (3)

    35 (4)0.25

    0.15

    Parapetplinths (in -

    situ)

    40 60% ggbs 0.45 All faces 55 0.17

    The deck slab concrete uses cement with 5 8% silica fume and 25% pfa or 50% ggbs. Elsewhere, the cement

    includes either 60% ggbs or 25% pfa.

    3.5

    19

  • 8/12/2019 Penang Bridge Widening booklet

    23/58

    4.0 award of contract

    20

  • 8/12/2019 Penang Bridge Widening booklet

    24/58

    4.0

    Tenders for the construction of the proposed Penang

    Bridge widening works were invited in October 2005.

    In April 2006 the contract was awarded to UEM

    Construction Sdn Bhd in three packages, namely:

    Toll plaza Main approaches and ramps for Bridge Nos 3, 7

    & 8

    Two ramps over the North-South Highways

    Award Of Contract

    21

  • 8/12/2019 Penang Bridge Widening booklet

    25/58

    5.0 scope of widening

    works

    22

  • 8/12/2019 Penang Bridge Widening booklet

    26/58

    5.1

    In total, 620 1 m diameter bored piles were

    constructed for the main viaduct widening, with a

    further 92 1 m diameter bored piles constructed forthe Bridges 3, 7 and 8 widening works. The majority

    of these piles were constructed over water within full-

    depth permanent steel casings using barge-mounted

    Reverse Circulation Drill (RCD) rigs for pile

    excavation. Between Piers 114E and 123E (eastern

    abutment) on the Prai Shore approach viaduct, where

    the viaduct runs over land, piling was undertaken

    using land-based RCD machines, again using full-

    depth casings.

    Twenty land-based piles for the Bridges 3, 7 and 8

    widening works were constructed under bentonite,using a conventional rotary percussion drilling rig. A

    further 45 marine piles on the western low level

    viaduct (where full length casings could not be

    installed fully to the target geotechnical design depth

    due to ground conditions) were completed by RCD,

    using bentonite to stabilize the open bore below the

    partial-depth casing toe.

    In-situ reinforced concrete structural infill to the

    precast pile cap shells was then completed, followed

    by in-situ concrete construction of the new circularcolumns and new extensions to the existing

    crossheads.

    At the land area at the eastern end of the Prai Shore

    approach viaduct, wholly in-situ pile cap extensions

    were provided at nine of the pier supports.

    At the stitching gap between the existing and new pile

    caps, dowels were provided at regular intervals

    across the interface in order to prevent differential

    vertical displacement once the new pile cap extension

    was finally stitched to the existing structure. Holes forthe dowels were drilled into the existing pile cap side

    face, and galvanized dowel bars placed into the holes

    and secured using a proprietary chemical anchoring

    system. The dowel bars were then cast into the stitch

    concrete.

    Similar construction techniques were adopted for the

    widening of the sub-structure to Bridges 3, 7 and 8. A

    total of 24 precast concrete permanent formwork

    shells were placed at marine piers. Where two

    supports to Bridge 3 and seven supports at Bridge 7

    were located on land, wholly in-situ pile cap

    extensions were possible.

    5.1.1

    A total of 288 precast reinforced concrete pile capshells were cast for the low-level viaduct widening

    works. The shells, each weighing approximately 40 t,

    were precast on specially constructed casting beds at

    two separate precasting yards close to the Prai side

    of the bridge. At the marine piers the shells were

    installed using cranes mounted on barges. The shells,

    incorporating soffit holes at pile locations, were lifted

    over the pile tops and supported on steel brackets

    welded to the permanent steel pile casings.

    Temporary horizontal prestressing was then applied

    to locate the precast shells firmly to the existing pile

    cap, following by the installation of a steel bracketdesigned to allow relative vertical movement (but not

    relative horizontal movement) between the new shell

    and the existing pile cap.

    Sub-structure

    Longitudinal Precast Post-tensioned Beams

    The precast post-tensioned beams were cast at a

    precasting yard established adjacent to the bridge site

    on the Prai shore. The precasting yard included four

    casting beds for the I-beams and eight casting beds

    for the U-beams, along with stressing beds and a

    beam storage area. Each I-beam weighedapproximately 80 t, whilst each U-beam weighed

    approximately 130 t.

    For the beams required for the widening of Bridges 3,

    7 and 8, a separate precasting yard was set up on the

    Penang Island shore.

    5.1.3

    Bridge Structural Works

    Pile Foundations

    5.1.2

    Superstructure

    23

  • 8/12/2019 Penang Bridge Widening booklet

    27/58

    A total of 576 precast post tensioned beams were

    cast and stressed on site for the main bridge viaduct

    widening, along with 70 beams for the widening to

    Bridges 3, 7 and 8.

    For Bridges 3 and 7, the single-sided widening

    generally comprised an additional I-beam and U-

    beam. With the Bridge 7 widening width being

    tapered into the existing carriageway, the use of

    either single U-beam or single I-beam widening was

    adopted.

    24

  • 8/12/2019 Penang Bridge Widening booklet

    28/58

    constructionchallenges &innovations

    6.0

    25

  • 8/12/2019 Penang Bridge Widening booklet

    29/58

    Changes to Bored Pile Construction Method

    Following contract award, the Contractor submitted to

    the Employer an alternative proposal to the designapproach which involved under bentonite with short

    casings installed through the alluvial cohesive soils,

    This new proposal was to construct the piles using

    full-depth permanent steel casings (refer Fig 6.1.1.1).

    This proposal was accepted by the Employer on the

    basis of the Contractors advice that it would eliminate

    the risk of collapse of the pile shaft. This acceptance

    was given despite the reservations held by the

    Engineer that it would radically increase the length of

    the piles and would be likely to cause settlement and

    risk damage to the welded joints of the existing spun

    piles.

    6.1.1

    On the eastern side, many casings were prematurely

    stuck at dense residual soil at various depths before

    reaching required geotechnical length. Arising fromthis, extensive and rigorous monitoring of piers and

    existing sub-structure were implemented, comprising

    visual inspections, leveling of settlement monitoring

    pins and vibration meter recordings. These measures

    were essential in ensuring that any signs of damage

    or distress to the existing structure were detected

    before they became excessive.

    6.1.2 Casing Installation

    6.1

    Full Depth PermanentSteel Casings

    26

  • 8/12/2019 Penang Bridge Widening booklet

    30/58

    At locations where the casing could not be installed to the

    full geotechnical depth, a series of innovative solutions were

    adopted to overcome critical delays. These included the

    following:

    Additional soil investigations to further study the nature

    of dense layers and to revise the casing installationmethod accordingly

    Redesign of the new pile foundations to adopt a three-

    pile group, with shorter pile depths to achieve the

    equivalent design load capacity

    Changing from the original vibro-hammer installation

    method to drop hammer methods with controlled drop

    height and re-driving of stuck casings

    Partial boring and removal of soil within the stuck

    casing

    Use of additional inner casings

    27

  • 8/12/2019 Penang Bridge Widening booklet

    31/58

    For all marine piles, the pile shaft excavation was completed using RCD rigs. Initially, excavation of the pile shaft

    was completed using muddy seawater as a stabilizing fluid. This was done whilst maintaining a 3 m head above

    mean sea level, leaving a 3m to 5 m plug of soil undisturbed at the casing toe.

    In some cases, this construction method resulted in the plug blowing in before the concrete could be placed. Thisrisk of blow-in was avoided by raising the pile and toe level to leave a longer soil plug in the casing. However, this

    method was not satisfactory where the casings could not be installed to the target toe level for the pile and instead

    bentonite was used.

    6.1.2 Pile shaft excavation

    28

  • 8/12/2019 Penang Bridge Widening booklet

    32/58

    Installation of Reinforcement Cages for Piles

    The Grade 460 high yield reinforcement cages were

    assembled on land in 12 m lengths and transported to

    the pier location on barges, where they were lowered

    by crane into the pile shaft and spliced by lap welding.

    6.2

    29

  • 8/12/2019 Penang Bridge Widening booklet

    33/58

    Protecting the Existing Bridge against Damage

    The control limits defining refusal, as set out below,were imposed during casing driving in instances

    where dense/ hard layers were encountered. Casing

    driving activity was stopped immediately if refusal

    was encountered.

    Controls on CasingInstallation

    The following instrumentation and monitoring worksare carried out:

    Precise leveling

    Vibration monitoring

    Tilt meter monitoring

    Pier Monitoring andSettlement Mitigation

    6.3

    6.3.1 6.3.2

    7 t Vibro

    10 t Vibro

    13 t and 14 t Vibro

    20 t drop hammer

    500 mm / 10 minutes

    500 mm / 5 minutes

    500 mm / 5 minutes

    100 mm / 40 blows at 400 mm height drop

    Hammer Weight Minimum Penetration Rates before Refusal

    30

  • 8/12/2019 Penang Bridge Widening booklet

    34/58

  • 8/12/2019 Penang Bridge Widening booklet

    35/58

    32

  • 8/12/2019 Penang Bridge Widening booklet

    36/58

    Jacking sledge

    Fixed Gantry mounted on

    crosshead

    Fixed leg resting on existing parapet

    Beam Launching over Marine and Land

    With approved traffic management procedures in place, the precast I-beams and U-beams for the spans over land

    were transported to site by day, using multi-axle low loaders. The beams were erected on the same night as they

    were delivered, using two 100 t cranes located on the land adjacent to the bridge. This approach was applied in

    place of the initial proposals by the Contractor to deliver the beams for the land spans via the existing deck prior to

    placement.

    6.6.1

    The challenges in erection of the precast beams for the marine s pans involved detailed traffic management

    planning. These in turn included slow lane closures, contra flow and the delivery of beams every night for 12

    months. The whole operation was restricted to a 6-hour time window from 12 midnight to 6 am each weekday

    night, in accordance with restrictions imposed by LLM, in order not to disrupt traffic flow on the bridge.

    The Contractor planned and obtained permission to deliver all beams via the existing deck using a tractor unit and

    jinkers travelling in the cordoned-off slow lane for both the eastern and western viaducts.

    Two methods for launching the beams were planned, as listed below, but only method II proved to be successful:

    (i) Method I - Beam launching using Jacking Gantry System: For this method, the Contractor undertook full-scale

    trials using a purpose-fabricated gantry supported on an extended crosshead. The launching gantry comprised a

    fixed frame, a temporary moveable leg (prop), top beam, 60 t hydraulic jack and jacking sledge.

    Figures 6.6.2.1a to 6.6.2.1d Principal Details of Gantry and the Trials

    Beam erection on Marine Spans

    Installation of Gantry from

    Barge (Stage 1)

    Diagram 1 : Installation of TopBeam 1, Jacking Sledge and

    Fixed Leg

    6.6

    Beam erection on land spans

    6.6.2

    Fig 6.6.2.1a

    33

  • 8/12/2019 Penang Bridge Widening booklet

    37/58

    Moveable

    Leg

    Installation of Top Beam 2 &

    Moveable Leg

    Fig 6.6.2.1b

    Installation of Gantry and movable

    leg on bridge (Stage 2)

    Diagram 2 : Installation of Top Beam 2, Moveable Leg

    Folded Moveable Leg

    6.6

    Beam Launching From Deck

    Diagram 3 : Move the jacking sledge to beam lowering positionFig 6.6.2.1d

    Beam Launching over Marine and Land

    34

  • 8/12/2019 Penang Bridge Widening booklet

    38/58

    Stage 3 Delivery and Erection of Precast Beams

    (ii) Method II - Beam Launching by Marine Crane Barge: Beams for marine spans were successfully launched

    using two 350 t capacity crawler cranes mounted on a large modified barge. Each crane had a lifting capacity of

    78 t at a working radius of 17m. For this exercise, the barge was maneuvered and controlled by a 1600 hp tug

    boat and experienced crew to ensure safe mooring and launching of beams. In total, 544 out of 576 low-level

    viaduct marine span beams were transported over the bridge slow lane and successfully launched over a 12-

    month period from March 2008 to March 2009 in the 5-hour available time window each night. The maximumoutput achieved was six beams per night.

    35

  • 8/12/2019 Penang Bridge Widening booklet

    39/58

    Fig 6.6.3.1b

    Fig 6.6.3.1c

    36

  • 8/12/2019 Penang Bridge Widening booklet

    40/58

    Innovative Method Used to Shift Layby Beams

    The widening scheme included the removal and

    reconstruction of nine laybys on extended pier

    crossheads at locations on either side of the

    carriageway along the low-level viaducts. The original

    design involved demolition of part of the existing deckslab over water, breaking out the existing diaphragms

    and removal of the existing I-beams below the

    existing layby for temporary storage and re-use in the

    widened layby span. This method imposed critical

    time and cost constraints because the works involved

    barging, heavy lifting and marine logistics to handle

    and store the existing I -beams, and re-launching at

    the outer edge of the new deck after deck widening.

    An innovative alternative approach, proposed during

    the construction period by Consultants HSSI, and

    adopted after detail study by the Contractor, involved

    the retention, unmodified, of each complete layby

    deck unit. In this approach, the entire unit was shiftedsideways in order to allow the standard widening

    works to be constructed in the resulting gap. This

    process was facilitated by the structural

    independence of the layby deck unit and the

    existence of the longitudinal joint between the layby

    deck and the main deck. The adoption of this

    alternative approach resulted in the successful in-situ

    jacking and lateral shifting of nine complete layby

    span units with only minimal demolition to remove

    existing dowel bars at the layby diaphragms.

    6.7

    37

  • 8/12/2019 Penang Bridge Widening booklet

    41/58

    Each layby span unit weighed about 300 t and comprised two 40m long I-beams, complete with deck slab and

    parapet. The procedure applied was as follows:

    The whole layby unit was jacked up 300 mm above its existing position - the four lifting jacks and their

    supports had a maximum jacking capacity of 800 t, with a 500 t horizontal pushing capacity

    The unit was then moved horizontally into its new position on the extended crosshead, using a drag and

    skidding system working from temporary towers erected on the existing and extended pile caps

    The temporary works and jacking operations are shown below.

    38

  • 8/12/2019 Penang Bridge Widening booklet

    42/58

    Deck Stitching

    The new widening deck slab was progressively

    stitched to the existing deck once all additional dead

    load from the widening works was carried on the new

    piles, and after the extended pile caps were stitched

    to the existing pile caps. In this way, load transferfrom the new works construction to the existing

    structure was minimized.

    Prior to the start of the stitch concreting works, a

    vibration monitoring study was carried out by the

    Institute of Noise and Vibration, Universiti Teknologi

    Malaysia. For safety reasons, the monitoring was

    performed at layby areas. The UTM report indicated

    that PPV from vibrations due to ambient traffic are

    high (up to 22 mm/s maximum PPV) during the

    daytime, but with a marked reduction in both average

    PPV and maximum PPV values recorded during the

    hours from 12 midnight to 5 am.

    Further monitoring on newly extended sections was

    also carried out to confirm the initial monitoring and to

    ensure that vibration during and immediately after

    stitch concreting was maintained within the permitted

    limit of 5mm/s PPV.

    Vibration mitigation measures included traffic lane

    constriction, speed reduction measures, traffic

    management plans and providing a high early

    strength grade for the stitch concrete.

    6.8

    39

  • 8/12/2019 Penang Bridge Widening booklet

    43/58

    Challenges in relation to the deck stitching included

    the following:

    Vibration effects from traffic on the existing slow

    lane had the potential to impair the development

    of early bond strength of concrete if not

    mitigated

    Two lanes had to be kept opened through thedaytime on both carriageways at all times. Slow

    lane closures for stitching were only permitted

    between the hours of 11 pm to 6 am, although a

    slow lane closure would have been preferred for

    longer to keep traffic -induced vibration away

    from the concrete stitch area

    Vibration peak value is directly related to axle

    wheel load, vehicular speed and volume of

    traffic using the bridge

    Penang Bridge is heavily congested and traffic

    volume only reduces to low levels between 12

    midnight and 5 am each night. Heavy traffic

    volume at night was affected by the earlier

    partial closure of the slow lane to allow concrete

    delivery. This had impact on the Contractors

    planned stitching, since it was proposed to

    deliver the concrete via the deck. Therefore allstitching works were confined between 10 pm

    and 6 am

    It was observed that slow moving traffic during

    congested hours does not materially induce

    vibration in the deck. However, fast moving and

    heavy vehicles such as lorries and trailers cause

    deck vibrations that are of concern

    Demanding traffic management solutions were

    required to be implemented when stitch pours

    were carried out on both carriageways

    concurrently with transportation of beams forlaunching and other simultaneous deck slab

    works.

    40

  • 8/12/2019 Penang Bridge Widening booklet

    44/58

    The approach to vibration mitigation and solutions for stitch concreting can be summarized as follows:

    Slow lane constriction and control of vehicular speed limit approaching the particular section of deck stitch

    concrete pour were implemented. Controls were introduced to keep vehicular speed to below 40 kph. The

    imposition of speed humps as a means of slowing down traffic was also considered but not invoked

    Traffic vibration studies were carried out to understand the nature of traffic volume, speed and effect of axle

    loads causing vibration on the deck - this also assisted with planning timing of the night-time deck pours Deck vibrations were controlled to below 5mm/sec PPV, although occasional peaks exceeding 15mm/sec

    PPV were experienced from speeding vehicles over bridge deck joints

    Lane constriction assisted in keeping wheel loads away from the freshly poured deck stitch concrete,

    thuereby reducing the impact of transmitted vibration

    Comprehensive concrete setting time studies were carried out on the Grade 50 concrete for the stitching

    works. Initial and final set consistency and workability of design mixes had to be fine tuned to achieve the

    following:

    Initial set that could allow sufficient time for concrete delivery, compaction and placing without loss of

    workability - this was found to vary from 2 to 3 hours

    Final set that was consistent and guaranteed to be achieved before opening partial lane closures to heavy

    traffic - this was found to vary from 3 to 5 hours

    The use of polypropylene fibres in the deck stitch concrete mix was specified to protect concrete fromstresses at early age, given that this can cause cracking - 900 g/m3 of microfibre was used with a super-

    plasticizer to achieve high early strength and the required workability with a reduced water / cement ratio

    Silicafume at 27 kg/m3 (6% by weight of cement) was added to improve early age strength gain of the stitch

    concrete

    41

  • 8/12/2019 Penang Bridge Widening booklet

    45/58

    7.0 conclusions

    42

  • 8/12/2019 Penang Bridge Widening booklet

    46/58

    7.0

    Due to the increase of the traffic volume and to

    ensure the smooth traffic flow, the widening of the

    existing Penang Bridge was necessary. The approach

    adopted by the Consultants HSSI and the contractor

    embodied the following principles:

    Whilst the scheme for widening the low-level

    viaducts was simple in concept, both the detail

    engineering design and construction presented

    many challenges

    For the successful completion of the works, it

    was necessary to avoid compromising the

    structural integrity or appearance of the existing

    structure and with minimum disruption to traffic

    Innovative mitigation measures were developed

    and applied to overcome the constraints, whilst

    at the same time recognizing the need to avoid

    excessive construction risks and other thanminor traffic disruption

    This booklet summarizes the main challenges

    involved in widening the Penang Bridge. In doing so it

    not only records the work that was carried out but is

    also intended to provide useful information to others

    involved in the design and construction of bridge-

    widening projects.

    Conclusions

    43

  • 8/12/2019 Penang Bridge Widening booklet

    47/58

    references

    44

  • 8/12/2019 Penang Bridge Widening booklet

    48/58

    References

    UK Ministry of Transport Memorandum No.771,

    Standard Highway Loadings

    UK Ministry of Transport Memorandum No.785,

    Concrete Bridges and Structures

    UK Department of Transport Standard BE2/73,

    Prestressed Concrete for Highway Structures

    British Standard Code of Practice CP110, Structural

    Use of Concrete

    UK Department of Transport Standard BE5, TheDesign of Highway Bridge Parapets

    British Standard Code of Practice CP2004,

    Foundations

    Jabatan Kerja Raya Loading / Design Standards, JKR

    Specification for Bridge Live Loads

    UK Highways Agency Standard BD 37/01, Loads for

    Highway Bridges

    The Penang Bridge - Planning, Design andConstruction, Tan Sri Datuk Professor Ir Chin Fung

    Kee, Malaysian Highway Authority, 1988

    Report on Soil Investigation for Subsurface

    Exploration for Proposed Jambatan Pulau Pinang

    (Parts I and II), Malaysian Soil Investigation Sdn Bhd,

    Dec 1978

    Pile Design & Construction Practice, MJ Tomlinson,

    4th Edition E & FNSPON

    Terzaghi and Peck, Soil Mechanics in Engineering

    Practices, 1967

    Chang & Broms, Design of Bored Piles in Residual

    Soils based on Field Performance Data, Canadian

    Geotechnical Journal, Vol. 28, pp. 200 209, 1991

    A Brief Guide to the Design of Bored Piles under Axial

    Compression A Malaysian Approach, Ir Dr Gue

    See Sew, Tan Y.C and Liew S.S, Seminar on

    Bridges: Kuala Lumpur, Malaysia, 2003

    45

  • 8/12/2019 Penang Bridge Widening booklet

    49/58

    Appendix A

    The structural design of the Penang Bridge viaduct was carried o ut in accordance with the applicable British

    Standard, augmented as necessary by other internationally and locally recognized guidelines to suit site

    conditions. From this, the main design criteria can be summarized as follows:

    Both the mainline viaduct and the ramps were to be designed for live loads type HA and HB (both 45 units

    and 30 units, as appropriate) loading, as specified in the British Department Standard (DB 37/01)

    Collision loads on bridge supports in the proximity to highways were as per BD60/94

    The design temperature range was 13C to 37C, along with consideration of differential temperature as per

    BD37/01

    The design mean hourly wind speed is 27m/s

    No allowance for differential settlement was made in the design of the deck slab instead, the extended pile

    cap was rigidly connected to the existing structure (ie thereby eliminating any possibility of differential

    settlement between the new and existing deck slabs)

    Design Criteria for New Widening Works

    46

  • 8/12/2019 Penang Bridge Widening booklet

    50/58

    acknowledgement

    47

  • 8/12/2019 Penang Bridge Widening booklet

    51/58

    Acknowledgement

    HSS Integrated Sdn. Bhd. would like to thank the following for providing the necessary information,kind assistance and support in the implementation of this Project:

    Lembaga Lebuhraya Malaysia

    Lembaga Lebuhraya Malaysia

    Penang Bridge Sdn. Bhd.

    Penang Bridge Sdn. Bhd.

    OPUS Management Sdn. Bhd.

    OPUS Management Sdn. Bhd.

    Majlis Perbandaran Pulau Pinang

    Majlis Perbandaran Seberang Perai

    PLUS (Butterworth Kulim Expressway)Jabatan Alam Sekitar Pulau Pinang

    Tenaga Nasional Berhad, Pulau Pinang

    TNB Transmission Sdn. Bhd

    Jabatan Kerja Raya Pulau Pinang

    Jabatan Kerja Raya Bukit MertajamJabatan Laut Malaysia, Pulau Pinang

    Jabatan Pengairan dan Saliran, Pulau Pinang

    Jabatan Bekalan Air, Pulau Pinang

    Telekom Malaysia, Pulau Pinang

    GAS Malaysia Sdn Bhd

    Ketua Polis Daerah, IPD Seberang Perai

    Halcrow

    Halcrow

    Environment Asia Sdn. Bhd.

    Perunding Trafik Klasik Sdn. Bhd.

    TRARS Konsult Sdn. Bhd.

    CT Toh Consultant

    Jurukur Perunding Services

    Arkitek Shilpa

    Dato Ir.Hj. Ismail B. Md. Salleh

    Ir. Mohd. Shuhaimi B. Hassan

    Pn. Hjh Suhaina Bt. Baharudin

    Tn. Hj. Ir. Abd. Rahman Hassan

    Mr. Muhinder Singh

    Ir. Wan Meow Kwan

    Pn. Hajah Rosnani Bt. Mahmud

    En. Ku Jamil B. Zakaria

    Ir. Abdul Aziz B. Jaafar

    Ir. Hj. Husaini Hussin

    En. Nik Azhar B. Abd. Samad

    En. Izmal B. Ibrahim

    Tn. Hj. Mohd. Abu Bakar B. Othman

    En. Jamil B. Mohd. Nor

    En. Sukardi B. Sukarno

    Unit Trafik

    Mr. Roger Buckby

    Mr. Paul W Corbett

    Mr. Edward Wong

    Dr. Tai Tuck Leong

    Ir. Amran B. Alias

    Dr. Toh Cheng Teik

    Mr. Wong Kam Fai

    Mr. Lim Take Bane 48

  • 8/12/2019 Penang Bridge Widening booklet

    52/58

    Dato Ir. Haji Abu Bakar Haji Mohd Amin Datuk Ir. S Santhakumar /

    Datuk Ir. Kuna Sittampalam

    Co-Project Director

    Ir. Chan Kin Pooi

    Chief Executive Officer

    Ir. B Nitchiananthan

    Chief Operating Officer

    Ir. Chen Wai Peng

    Project Manager

    Ir. Kho Poh Teck

    Design Engineer

    Ir. Tan Wee Kong

    Design Engineer

    Mr. B Ramesh BalakrishnanQuantity Surveyor

    Mr. Anand Sharvanandan

    Project Coordinator

    Ir. Nor Afizza Bt. JuniProject Coordinator

    Ir. Mathew PhilipHighway

    Mr. RabindranathHighway

    Mr. Tan Joon Lye

    Highway

    Ir. Lee Yew Seng

    Drainage / Utilities

    Ir. Azman Abd RahmanMechanical & Electrical

    Ir. Kun Goon HongMechanical & Electrical

    Ir. Tan Seng Guan

    Mechanical & Electrical

    Ir. Khairul Anuar B. Mohd. Said

    Geotechnical

    Design and Supervision Team

    Ir. Wee Eng Leong

    Chief Resident Engineer

    Ir. Charles Low Boo Tean

    Resident Engineer

    Mr. Liew Sin KhoonDeputy Resident Engineer

    (Geotechnical)

    Mr. Teng Jit Poh

    Deputy Resident Engineer

    En. Shamsuri Salleh

    Deputy Resident Engineer

    Mr. M Marimuthu

    Deputy Resident Engineer

    En. Al-Rifae

    ARE Piling 1

    En. Rahim RejabARE Piling 1

    En. Ku Adenan Ku Ismail

    ARE Piling 2

    Mr. Law Peng Swee

    ARE Piling 2

    En. Hussin MuhammadARE Casting Yard

    En. Azmi MohamadARE Bridge 1

    En. Md. Fadzil Abd Rahman

    ARE Bridge 1

    Mr. P KumaranARE Bridge 2

    En. Zulkifli HusseinARE Measurement 2

    Mr. Woo Wooi Lim

    ARE M&E

    Cik. Norhabina Mohd ArisEnvironmental Officer

    Mr. Donny RamasamyInstrumentation Officer 49

  • 8/12/2019 Penang Bridge Widening booklet

    53/58

    Mr. Ashokumar RamasamySafety Officer

    Mr. Sivabalan Arumugam

    Safety Officer

    Mr. Mah Kim TongSurvey Technician 1

    Mr. Tee Yoke ChuanSurvey Technician 2

    En. Sabri Sharif

    Survey Technician 3

    Mr. K VijayanMaterial Technician 1

    En. Mohd. Salam NgajimanMaterial Technician 2

    Mr. Sophee Khoo B. Abdullah

    IOW Traffic 1

    Mr. S Seenivasan

    IOW Bridge 1

    Mr. Sunny Tan

    IOW Bridge 2

    Mr. Ramamurthy Letchumanan

    IOW Bridge 3/Piling

    Mr. Tan Teong Hin

    IOW Bridge/Piling 4

    En. Afraizal Abdul Aziz

    IOW Bridge 5

    Muaizam Abdul AzizIOW Bridge 6

    Robert King Amros

    IOW Bridge 7

    Mr. Tan Tong Siew

    IOW Piling 1

    Mr. Revindran Ramakrishnan

    IOW Piling 2

    En. Alzahari SaadIOW M&E 1

    Design and Supervision Team

    Mr. Yeoh Hun Poh

    IOW Casting Yard 1

    Mr. Silverster Douglas

    Draughtman

    Mr. S Kanathasan

    Draughtman

    Cik Nor Azlina Mohd. Saad

    Draughtwoman

    En. Fairuz Zamri IsmailDraughtman

    Mr. Jagjit SinghAdministrative Manager

    Ms. Nirmala Devi

    Administrative Manager

    Pn. Mazni Abdul WahabSecretary

    Ms. Mary Janet PasqualSecretary

    Pn. Badariah Rahmad

    Clerk

    Cik Khadijah Abdul Majid

    Clerk

    Pn. Emilia AzudinClerk

    Ms. Nanda Devi

    Clerk

    50

  • 8/12/2019 Penang Bridge Widening booklet

    54/58

    Design and Supervision Team

    51

  • 8/12/2019 Penang Bridge Widening booklet

    55/58

    Design and Supervision Team

    52