perdaman-attachment-b fire system

60
ATTACHMENT–B 1) FIREPROTECTIONSYSTEMPHILOSOPHY 2) FIREWATERUTILITYDESCRIPTION 3) SPECIFICATIONFORFIREWATERPUMPSYSTEM 4) P&IDFORFIREWATERPUMPSYSTEM 5) UNDERGROUNDFIREWATERPIPINGPLAN

Upload: lorena-davila

Post on 27-Sep-2015

231 views

Category:

Documents


0 download

DESCRIPTION

Perdaman-Attachment-B fire system

TRANSCRIPT

  • ATTACHMENTB

    1) FIREPROTECTIONSYSTEMPHILOSOPHY2) FIREWATERUTILITYDESCRIPTION3) SPECIFICATIONFORFIREWATERPUMPSYSTEM4) P&IDFORFIREWATERPUMPSYSTEM5) UNDERGROUNDFIREWATERPIPINGPLAN

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 1 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    FIRE PROTECTION SYSTEM PHILOSOPHY

    3 Feb. 19 , 2010 Revised as per PCF Comment J.K. Kim T.H. Oh T.H. Jung

    2 Dec. 14 , 2009 Revised as per PCF Comment J.K. Kim T.H. Oh T.H. Jung

    1 Nov. 13, 2009 Revised as per PCF Comment J.K. Kim T.H. Oh T.H. Jung

    0 Sep. 18, 2009 Issued for Review J.K. Kim T.H. Oh T.H. Jung

    REV DATE DESCRIPTION PREPARED REVIEWED APPROVED PCF

    G

    Perdaman Chemicals and Fertilisers (Perth , Australia)

    G

    PT. Inti Karya Persada Tehnik (Jakarta, Indonesia)

    G

    SAMSUNG ENGINEERING CO. LTD. (Seoul , Korea)

    DEPARTMENT: JOB NO: DOCUMENT NO:

    Piping SC2277 SC2277-SE-FA-760-4-1001

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 2 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    CONTENTS

    1. GENERAL 3

    2. REFERENCE 3

    3. DESIGN BASIS 5

    4. FIRE WATER SUPPLY AND DISTRIBUTION SYSTEM 5

    5. OUTDOOR FIRE HYDRANT AND MONITOR SYSTEM 8

    6. DRY RISERS 12

    7. FIXED WATER SPRAY SYSTEM 12

    8. FOAM EXTINGUISHING SYSTEM . 13

    9. FIRE PROTECTION SYSTEM FOR BUILDING 15

    10. PORTABLE AND MOBILE EXTINGUISHER 17

    11. FIRE ALARM AND GAS DETECTION SYSTEM 18

    12. BREATHING APPARTUS 24

    13. PASSIVE FIRE PROTECTION SYSTEM 24

    Attachments

    Attachment 1. SUMMARIZED MATRIX FOR FIRE FIGHTING FACILTIES OF BUILDING

    Attachment 2. SUMMARIZED MATRIX FOR F & G SYSTEM OF BUILDING

    Attachment 3. ESTIMATED FIRE WATER DEMAND CALCULATION

    Attachment 4. FIRE SINGLE ZONE DRAWING

    Attachment 5. OVERALL SCHEMATIC DIAGRAM FOR F & G SYSTEM

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 3 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    1. GENERAL This specification intended to provide the engineering requirements for fire fighting and protection system, including equipment, piping systems for the Perdaman Collie Urea Plant located in Shotts Industrial site, Collie city Australia as described under this section. The design shall be complied with the requirements of NFPA and local fire protection code.

    2. REFERENCE The latest editions of the following codes, specification and regulations shall be applied for the design.

    2.1 Local Fire Protection Codes

    This Australian standard code will include followings, but not limited:

    AS 1211 Fire Hose Reels AS 12239 Fire Detection and Alarm Systems AS 1603.5 Manual Alarm Call Points AS 1670 Automatic Fire Alarm Installation AS 1940 The storage and handling of flammable and combustible

    liquids AS 2118.1 Automatic Fire Sprinklers AS 2419 Fire Hydrant Installations AS 2441 Fire Hose Reel Installations AS 2444 Portable Fire Extinguishers and Fire Blankets Selection

    and Location AS 2941 Fixed Fire Protection Installations : Pump set Systems AS 4078 Fire Protection - Fire Extinguishing Media - Carbon

    Dioxide - ISO 5923: 1989

    2.2 National Fire Protection Association (NFPA)

    NFPA 10 Portable Fire Extinguishers NFPA 11 Standard for low, Medium-, and High-Expansion Foam NFPA 12 Standard on Carbon Dioxide Extinguishing Systems NFPA 13 Standard for the Installation of Sprinkler Systems

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 4 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    NFPA 14 Installation of Standard Pipe and Hose Systems NFPA 15 Standard for Water Spray Fixed Systems for Fire

    Protection,NFPA 16 Installation of Foam-Water Sprinkler and Foam-Water

    Spray System

    NFPA 20 Installation of Stationary Pumps for Fire Protection NFPA 24 Installation of Private Fire Service Mains and Their

    Appurtenances NFPA 30 Flammable and Combustible Liquids Code NFPA 70 National Electrical Code NFPA 72 National Fire Alarm Code NFPA 85 Boiler and Combustion System Hazards Code NFPA 850 Recommended Practice for Fire Protection for Electric

    Generating Plants and High Voltage Direct Current Converter Stations

    NFPA 1961 Fire Hose NFPA 1963 Fire Hose Connections NFPA 2001 Standard on Clean Agent Fire Extinguishing Systems

    2.3 American Petroleum Institute (API)

    API 2001 Fire Protection in Refineries API 2021 Guide for Fighting Fires in and Around Petroleum Storage

    Tanks API 2030 Guidelines for Application of Water Spray Systems for

    Fire Protection in the Petroleum Industry API 2218 Fire Proofing Practices in Petroleum and Petrochemical

    Processing Plants API 2510A Fire Protection Considerations for the Design and

    Operation of Liquefied Petroleum Gas (LPG) Storage Facilities

    G2.4 Others Project Specification

    SC2277-SE-IS-000-4-1002 Engineering Specification for DCS SC2277-SE-IS-000-4-1005 Engineering Specification for Fire and

    Gas Detection System

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 5 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    3. DESIGN BASIS 3.1 The fire fighting system shall be designed on the basis of only major fire with

    a single fire risk area at a time.

    3.2 No simultaneous occurrence of fire, either within a single fire area or in multiple locations in the plant, shall be considered.

    3.3 The fire areas shall be defined as areas which are bounded by the limits of a credible fire escalation event. In order to have a useful subdivision of the fire areas, the fire areas may be divided into fire zones. The fire zones in open plant section.

    The following area or facility is considered as one single fire risk zone.

    1) In the process area, all equipment located in an area separated to other equipment by means of pipe rack, roads or distance of at 15m.

    2) In the tank storage area, the one tank is considered as one fire risk area. 3) In the building area, the independent room enclosed by noncombustible

    materials is considered as one fire risk area Changes in Plot Plan layout during Detail Engineering must be checked carefully if they are influencing the layout of the fire zones.

    4. FIRE WATER SUPPLY AND DISTRIBUTION SYSTEM 4.1 Fire Water Demand

    The fire water demand shall be determined based on the largest single fire water demand from the respective area requirements in the plant.

    The estimated firewater demand shall be the sum of water required for fire protection fixed systems(e.g. water spray system, sprinkler system) and manual fire fighting equipment (e.g. fire monitor, hose stream) based on a single major fire breaking out in one fire risk area at any one time over the entirety of the site. The biggest firewater demand of one of the fire risk areas shall be the total firewater demand.

    For the purpose of estimating total firewater demand, followings shall be applied:

    Firewater demands for two (2) Fire monitors + two (2) Fire hydrants + fixed water spray system.

    For the purpose of estimating total firewater demand shall be 795 m3/hr. The estimated fire water demand calculation is summarized in Attachment # 3 (Estimated firewater demand calculation) When estimating firewater demand

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 6 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    for fire monitors, hose lines and fixed water spray system the following shall be used:

    (1) One (1) Fire monitor nozzle: 114 m3/hr (1,900 lpm)

    (2) One (1) Fire hydrant (2-1/2 hose line x 2): 114 m3/hr (1,900 lpm)

    (3) Fixed water spray system: Application Rate of exposed surface

    The fire water demand is estimated by considering several fire scenarios. The biggest incident scenario would be the following:

    The maximum firewater demand is estimated at 795 m3/hr for any single major fire case on the ammonia process area. Based on preliminary firewater estimates, the ammonia process area have been indicated as producing the higher firewater demand during a single fire incident.

    The maximum fire water requirement for the ammonia process area is calculated base on a deluge water density of 20.4 lpm/m2 for synthesis gas compressor surface area.

    The largest fixed water spray 2 gas compressors 292.5 m3 /hr

    fire water monitors,114 m3/hr each (1,900 lpm each) 228 m3 /hr

    2 fire hydrant, two hose stream 57 m3 /hr each (950 lpm each)

    228 m3 /hr

    Total fire water demand of single fire risk area 795 m3 /hr

    For estimated water demand of each single fire zone, refer to attachment #3.

    4.2 Fire Water Supply

    The water for fire fighting system shall be supplied a dedicate fire water storage tank and pump system and additionally have a back-up from the raw water pond under emergency condition.

    The fire water ring main will be sized to supply the estimated water demand of 795 m3/hr.

    The fire water storage tank shall be sized to a minimum storage capacity of 5,000m3 for 6 hours of continuous fire fighting operation.

    4.3 Firewater Pumps

    Firewater pumps can be electric motor, diesel engine driven. The design, installation, and acceptance test of firewater pumps shall conform to NFPA

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 7 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    20.

    The fire water shall be pumped from fire water storage tank and pressurized so that the system is ready to service with the minimum pressure of 10 barg (1.0MPag) at the design flow rate at any point on the ground level in the plant.

    Two (2) fire water pumps shall be required, one driven by electric motor (main) and the other by diesel driven (stand-by). They are horizontal split centrifugal types. The capacity of each pump is 795 m3/hr and therefore it is ensured the maximum fire water supply even if one of the pumps is out of service or when the electric power is unavailable.

    The fire water pumps will be operated as follows: - The jockey pump will maintain the general network pressure at 8barg.

    In the event that the network pressure drops below 7.5barg, Jockey will be automatically started.

    - In the event that the fire water network pressure falls below 7.0barg, the main fire water pump and stand-by fire water pump will be started automatically utilizing their respective pressure switched at pre-set points. In addition to, stand-by fire water pump will also start if main fire pump does not start, or having started, fail to build up the required pressure in the fire-water ring main system within 30 seconds.

    Manual starting of each pump unit shall be possible at the pump, and from the Control room. Manual stopping of each pump unit shall only be possible at the pump. The shutdown the firewater pumps shall only from local panel. One (1) fire water jockey pump, electric motor driven, in normal operation, are provided to maintain the system pressure against leakage and to allow automatic starting of main fire water pump sequentially in the event of fire water demand from the plant. The capacity of Jockey pump is 50 m3/h at 10 barg (1Mpag) discharge pressure.

    Booster pumps (1 working + 1 standby, motor operated) shall be provided for dry riser system of high elevation gasification areas, if adequate pressure is not the required design condition.

    Firewater pumps shall furnish 150% or above of rated capacity at not less than 65% of total rated head. The shutoff head shall not exceed 140% of rated head for any type of pump.

    4.4 Firewater Distribution Network

    The fire main network to be provided at the urea plant shall be fabricated

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 8 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    from Carbon Steel piping with Fusion Bonded Epoxy Coating and installed under ground at a buried with a minimum 1.1m cover. Where fire main necessitates installation above ground the piping shall be carbon steel.

    Where fire water main may be extended in the future, blinded flange shall be provided for future connection.

    Firewater main will be of minimum 10 diameter and single hydrant or fire monitor laterals shall not be less than 6 in diameter.

    The fire main shall be installed along the perimeter roadsides of each process block and coal yard storage area(s) including the Administration areas, ensuring firewater is made available throughout the urea plant.

    Block valves shall be incorporated in the ring main system so that sections can be isolated for maintenance. Each loop intersection, all branch line connections, and all lines with more than six (6) fire protection devices (e.g. hydrant, fire monitor and fixed water spray system) shall be provided with isolation valve. The isolation valves shall be of the positive indicating type showing clearly its open or closed positions. Valves shall be installed, as far as possible aboveground. The valve shall be Locked open during operation.

    The firewater mains network pipe sizes shall be calculated using an approved computer program and the complete calculation shall be based on design flow rates and a minimum pressure of 7barg being available at the most hydraulically remote take-off points from the firewater pump(s). The minimum diameter pipe used for the fire main network shall not be less than 6. Calculations shall be made to prove that pressure drop is acceptable with a blocked section of piping in the network. The maximum allowable velocity in the system should not exceed 4.6 m/s.

    5. OUTDOOR FIRE HYDRANT AND MONITOR SYSTEM 5.1 Fire Hydrants

    Hydrants spacing in process area shall be no more than 50 m along roadways or access-ways between the hydrants. Hydrants spacing of utility areas (including building area) shall be no more than 70 m as measured along roadways or access ways between the hydrants.

    Hydrants shall be positioned at least 1.5 m away from the edge of the road and not less than 10 m from the hazardous areas being protected.

    Hydrants shall be located so that the distance between the hydrant and fire truck will not exceed 3 m.

    Where large pipe banks or drainage ditches may hinder access between

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 9 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    hydrants and protected areas, access ways or walkways across such obstructions shall be provided near the hydrants.

    Pipe racks, sleepers, and drainage ditches shall not interfere with convenient access to hydrants. Where a nearby drainage ditch may present operational difficulties or a personnel safety hazard, an access platform with non-slipping surface extending a minimum 1.5 m on either side of the hydrant shall be installed.

    Requirements of hydrants are described as follows:

    (1) Hydrants shall be wet barrel type, steel body, rated for 7 barg (0.7 MPag) minimum working pressure. A block valve shall be provided above ground at the base of each hydrant.

    (2) Each hydrant shall be equipped with two (2) 2-1/2 inch flanged hose connections and one (1) 4 inch flanged pumper connection.

    (3) Each 2-1/2 inch hose connection shall be equipped with a 2-1/2 inch pressure reducing type quarter turn gate valve through flanged connection; actuating level shall be lockable in open and closed positions. Connection to hose shall be 2-1/2 inch male BS336 instantaneous couplings with rocker lug cap and chain.

    (4) The 4 inch pumper connection shall be equipped with a 4 inch NRS (Non-rising stem) gate valve. Gate valve outlet shall be provided with flanged 4 inch BS336 instantaneous couplings male hose connection with rocker lug cap and chain.

    (5) A 6 inch flanged raised face base connection, class 150, shall be provided for each hydrant.

    (6) All the connectors and couplings shall be stainless steel (SS) and not brass (Ammonia attack copper).

    Fire hydrant guards post shall be installed where the hydrants may be vulnerable to mechanical impact damage from road traffic. Such guards post shall be fabricated from 4-inch schedule 40 pipes, filled with concrete, and set in concrete.

    Such as hydrant valve, equipment shall be FM/UL listed.

    5.2 Fire Monitors

    Fire monitors shall be provided to adequately cover process units handling hydrocarbons.

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 10 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    Minimum reach of 40 m can be used for spacing fire monitors.

    Fire monitors shall be stand alone fire monitor type. Fire monitors shall be the types of lever operation with ball valve.

    Fire monitors shall be rated for minimum/maximum operating pressure to be respectively 7/12 barg (0.7/1.2 MPag). Monitors shall be capable of 360 of horizontal motion and minimum 120 of vertical motion (90 above and 30below). Monitors shall have the capability to be locked in position.

    The fire monitor shall have 4 inch flange inlet connection and 2-1/2 inch NH thread with a capacity of at least 120m3/hr at 7barg (0.7MPag).

    The adjustable monitors nozzle (full fog to straight stream) shall be provided and rated for 114m3/hr (1,900 lpm) at 7barg (0.7MPag) and be a design effective straight stream range of approximately 50 meters. Nozzle shall have fixed or swivel 2-1/2 inch NH female connection.

    Fire monitors shall be located at 1.5 m from edge of road and at least 10 m from road crossing.

    Such as monitor and monitor nozzle, equipments shall be FM/UL listed.

    5.3 Combination Hydrants/Monitors

    Combination hydrant/monitor shall have the monitor mounted on top of the hydrant. Hydrant shall be equipped with two (2) 2-1/2 inch flanged hose connections and one (1) 4 inch flanged pumper connection. Each 2-1/2 inch hose connection shall be equipped with a 2-1/2 inch pressure reducing type quarter turn gate valve through flanged connection; actuating level shall be lockable in open and closed positions. Connection to hose shall be 2-1/2 inch male BS336 instantaneous couplings with rocker lug cap and chain. A 4 inch quarter turn ball valve shall be provided between the hydrant and monitor for isolation of monitor stream. This ball valve shall be lockable in open and closed positions. Height of the adjusting lever for the monitor shall not exceed 1.3 meters from grade.

    Combination hydrant/monitor shall be preferred method of applying water to the risk during a fire incident process area to protect equipment handling hydrocarbons.

    The connecting parts between hydrant and monitor shall have the following (from top of hydrant to base of monitor): (1) 6 inch class 150, raised face, welded neck flange

    (2) 6 x 4 inch concentric reducer

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 11 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    (3) 4 inch class 150, flat face, welded neck flange

    (4) 4 inch quarter turn ball valve, lockable in 4 inch class 150, flat face, welded neck flange.

    (5) All the connectors and couplings shall be stainless steel (SS) and not brass (Ammonia attack copper).

    Combination hydrant/monitors guards post shall be installed where the hydrants may be vulnerable to mechanical impact damage from road traffic. Such guards post shall be fabricated from 4-inch schedule 40 pipes, filled with concrete, and set in concrete.

    Such as hydrant valve, monitor and monitor nozzle, equipment shall be FM/UL listed.

    5.4 Fire Hose Cabinet

    Hose cabinet shall be provided to each fire hydrant.

    Hose cabinet shall be fabricated in FRP finished red for self-standing and hinged door with lock and adequate ventilation.

    Hose cabinet shall be suitable to contain as specified below: (1) Four (4) sets of 2-1/2 inch synthetic hose of 20m length with 2-1/2 inch

    BS336 instantaneous couplings

    (2) Two (2) sets of 2-1/2 inch fog/straight/shut-off combination type pistol grip water nozzle.

    (3) One (1) ea of hose coupling wrench.

    (4) All the connectors and couplings shall be stainless steel (SS) and not brass (Ammonia attack copper).

    Such as hose and water nozzle, equipments shall be FM/UL listed.

    5.5 Hose reel

    Hose reel stations shall be provided in process units and coal pile areas. Two stations shall be positioned within 23 m (50ft.) (walking distance) from any point within the production facilities area.

    Hose reel stations shall be equipped with 31 m (100ft.) of 1-, 19-mm internal bore, 500# non-collapsible rubber hose and adjustable-flow, combination straight-stream fog-type (all brass) nozzles. Reels shall allow hose to be put into service without unwinding the reel.

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 12 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    All the connectors and couplings shall be stainless steel (SS) and not brass (Ammonia attack copper).

    6. DRY RISERS Dry risers shall be provided to platforms where equipment and process isolation valves are located and adequate access can be provided to allow safe use of hand lines/hoses on elevated working platforms above the first elevation of a structure.

    Each dry riser shall consist of an inlet with two-way flapper valve, 4 diameter riser pipe fabricated in carbon steel and minimum of two outlet landing valves at each of the respective working platform elevations.

    A two-way flapper valve (collecting breaching) shall be permanently installed at gruound floor level at a height of approximately 0.8 m above finished ground level. Where provided, the inlet to the dry riser shall be installed horizontally for easy access from fire truck only.

    Outlet landing valves shall be similar to hydrant outlet stainless steel ball valves, fitted with 2-1/2 inch BS336 instantaneous couplings. Outlet landing valve shall be rated for 3.5 barg (0.35 MPag) minimum working pressure and pressure reducing type. Outlet isolation valves shall be located near to the stairway access point to the respective elevated working platform.

    A hose box shall be provided adjacent to the landing valves on each landing. Each box shall contain 2 jet/spray nozzles and 2 hose (2-1/2 inch x 20 m), as minimum.

    Hose box shall be fabricated in FRP finished red.

    All the connectors and couplings shall be stainless steel (SS) and not brass (Ammonia attack copper).

    Such as hose and nozzle, equipments shall be FM/UL listed.

    7. FIXED WATER SPRAY SYSTEM Automatically operated water spray systems shall be actuated by heat/flame detection or fusible plug link. It shall also be possible to remotely operate these deluge valves from control room and local hand switch. Local hand switch shall be located minimum travel distance of 15meters from the protected equipment.

    Application of water spray systems are provided for the following: Gas compressors

    - Synthesis Gas / Recirculation Compressor(500-K-531) - Ammonia Compressor No. 1(500-K-541)

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 13 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    - Ammonia Compressor No. 2(500-K-551 A/B/C) Power transformers with handling flammable oil over 500gal.(1,890 liters)

    Application rate of water spray as indicated in NFPA 15 Exposure protection of 10.2 liters/minute/m2.

    Spray rate for compressors shall be in accordance with NFPA 15 with a minimum rate of 20.4 liters/minute/m2 of projected surface area of the equipment.Hydraulic program shall be used to size the water spray deluge system based on the given design criteria. For preliminary estimate purpose, flow rate of the water spray systems can be calculated based on the water spray density plus 10% design factor. The 10% design factor is to account for the overlap, wastage, and pressure balancing of the water spray system.

    Water velocity in the water spray deluge pipe shall not exceed 6 m/sec

    7.1 Water Spray Deluge Valve

    The deluge valve actuator shall be provided with a electric operator.

    Deluge valves shall be located at perimeter access-way or road sides at least 15 m from the equipment or area to be protected. An individual manual valve shall be provided upstream of each deluge valve to allow resetting/isolation for maintenance.

    Deluge Valve shall be FM/UL listed.

    7.2 Water Spray Nozzle

    The water spray nozzles shall be of the medium velocity spray type, with orifices of not less than 8mm.

    Minimum operating pressure for any spray nozzle shall be 2.0 barg (0.2MPag).

    The nozzles shall be spaced such that the spray patterns should be overlapped or at least meet.

    All nozzles shall be provided with blow-off caps. Water spray nozzles shall be FM/UL listed.

    8. FOAM EXTINGUISHING SYSTEM Foam systems shall be designs and installed in full compliance with NFPA 11 and NFPA 16. 8.1 Lube oil and seal oil consol for compressor

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 14 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    The foam extinguishing systems shall be actuated manual remote switch both from control room and local hand switch. Local hand switch shall be located minimum travel distance of 15meters from the protected equipment.

    Foam application should be maintained for 10 minutes; the net minimum foam/water rate shall be 6.5 liters/min./m2 areas to be protected.

    The following should be added to the aforementioned application rates: 20% due to water not reaching the equipment (because of wind or other factors), and in addition 10% as a flow balancing factor for discharge nozzle pressure variations.

    Where required foam concentrate and proportioning systems will consist of the bladder tank type, a foam ratio controller, foam water spray/sprinkler nozzle and piping.

    Foam concentrate shall be stored in the foam concentrate tank. The supplies of foam concentrate shall not be less than the largest to be protected by foam extinguishing system.

    Foam concentrate shall be aqueous film foaming foam (AFFF) 3%.

    Such as ratio controller and foam concentrate, equipments shall be FM/UL listed

    8.2 Coal pile and Strategic coal pile area

    The pick-up tube type firewater monitors with a foam drum (55gal.) shall be provided surrounding the coal pile and coal storage area. Minimum reach of 40 m can be used for spacing fire monitors. Fire monitors shall be the types of lever operation with ball valve. Fire monitors shall be rated for minimum/maximum operating pressure to be respectively 7/12 barg (0.7/1.2 MPag). Monitors shall be capable of 360 of horizontal motion and minimum 120 of vertical motion (90 above and 30below). Monitors shall have the capability to be locked in position. The fire monitor shall have 4 inch flange inlet connection and 2-1/2 inch NH thread with a capacity of at least 120m3/hr at 7barg (0.7MPag). The adjustable monitors nozzle (full fog to straight stream) shall be provided and rated for 114m3/hr (1,900 lpm) at 7barg (0.7MPag) and be a design effective straight stream range of approximately 50 meters. Nozzle shall have fixed or swivel 2-1/2 inch NH female connection with foam concentration pickup tube 3.8 cm (1-1/2 inch) by 365 cm (12 feet) hose plus drum pickup valve for 3% proportioning.

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 15 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    Foam concentrate shall be aqueous film foaming foam (AFFF) 3%. Such as monitors, monitor nozzles and foam concentrate, equipments shall be FM/UL listed.

    9. FIRE PROTECTION SYSTEM FOR BUILDING 9.1 General

    Fire protection system shall be installed in buildings. The protection of a building is based on fighting the fire from both the inside and from the outside of the building. Fire water shall be available close to and inside some buildings.

    The type of fire protection systems applied depends on location, equipment to be protected and the particular fire hazard. Equipment replacement and its replacement value shall also be considered when making an assessment for the design of the fire protection systems. For fire protection facilities of building, refer to attachment #1.

    9.2 Indoor Hydrant System

    In buildings such as the warehouse, workshop, chemical store, control building and administration building, indoor hydrants shall be provided such that any area of the building can be covered by hose streams. The design of these indoor hydrants shall be based on wall mounted rack hosed within suitable cabinets, recesses mounted where appropriate. The indoor hydrants will consist of with 30 metres of 1 1/2 inch hose.

    Indoor hydrants shall include integrated pressure reducing automatic stop valve on the inlet and hoses shall be fitted with shut-off/jet/spray nozzles.

    All the connectors and couplings shall be stainless steel (SS) and not brass (Ammonia attack copper).

    Such as hose and nozzle, equipment shall be FM/UL listed.

    9.3 Automatic Sprinkler System

    Automatic sprinkler systems shall be installed for the protection of the following types of equipment and designed to meet the requirements of NFPA13: Administration Building Building Warehouse

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 16 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    Chemical Storage House Enclosure Coal handling structure(I.e., Transfer tower)

    The enclosure coal handling structure each shall be provided with fixed automatic sprinkler systems. Fire water shall be applied at a minimum density of 10.2 lpm/m2 of the floor area.

    All equipment shall be UL/FM listed.

    9.4 Gaseous Fire Extinguishing Systems

    9.4.1 Carbon Dioxide Extinguishing System

    Fixed total flooding carbon dioxide fire suppression systems shall be provided for installation to cover the following areas: Coal pulverizer packages Coal dust collectors (if required). Fixed carbon dioxide fire suppression systems for the above areas will be provided by the coal silo and dust collector package suppliers. In each case these systems shall be designed and installed to meet the requirements of NFPA12. All equipment shall be UL/FM listed. The quantity of reserve (pre-connected CO2 agent) shall be 100% of the quantity supplied.

    The design of the systems shall incorporate all necessary personnel safety protection interlock systems and dedicated fire detection and alarm control panel with all necessary logic to control and monitor detection, local alarm and fire extinguishing system provide interface with plant e.g. HVAC shutdown where required.

    Confirmed fire condition will require a minimum alarm from two detectors within the zone requiring discharge of fire extinguishing agent, each detector providing a dedicated alarm condition. All alarm, fault and status indications shall be repeated to the site wide monitoring system.

    9.4.2 Clean Agent (HFC-227ea)Extinguishing System

    A fixed automatic gaseous fire suppression system utilizing clean agent (HFC-227ea) extinguishing shall be installed to cover the following buildings: Main Central Control Building U&O Substation Urea Substation

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 17 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    Urea Storage Substation Ammonia Synthesis Substation Gasification Substation Coal Handling Substation Remote Instrument Enclosure #1/2/3/4/5/6/7 Clean agent (HFC-227ea) gaseous fire suppression systems shall be designed and installed to meet the requirements of NFPA 2001. All equipment shall be UL/FM listed. The quantity of reserve (pre-connected clean agent (HFC-227ea)) shall be 100% of the quantity supplied.

    The design of the system(s) shall incorporate all necessary personnel safety protection interlock systems and include dedicated fire detection and alarm control panel with all necessary logic to control and monitor detection, local alarm and fire extinguishing system provide interface with plant e.g. HVAC shutdown where required.

    Confirmed fire condition will require a minimum alarm from two detectors within the zone requiring discharge of fire extinguishing agent, each detector providing a dedicated alarm condition. All alarm, fault and status indications shall be repeated to the site wide monitoring system.

    10. PORTABLE AND MOBILE EXTINGUISHER Hand held and wheeled dry chemical/CO2 extinguishers shall be installed strategically throughout the plant areas for first attack fire fighting. Fire extinguishers shall comply with latest NFPA 10 and shall be UL/FM listed. The following criteria shall be followed:

    10.1 9 kg capacity potassium bicarbonate BC dry chemical:

    The extinguishers shall be located at strategic points at grade and on the platforms of structures with a guide maximum travel distance of 15 m. Extinguisher cabinets shall be fabricated in carbon steel finished RED.

    10.2 4.5 kg capacity ammonium phosphate ABC dry chemical:

    The extinguishers are to be used on fires involving office room, corridor such as administration, maintenance, warehouses and etc..

    The extinguishers of 4.5kg capacity shall be installed in buildings where the risk necessitates and such that travel from the risk is 15m maximum.

    10.3 56.7 kg capacity potassium bicarbonate BC wheeled dry chemical extinguishers:

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 18 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    The wheeled extinguishers shall be located at strategic points near hazardous equipment such as transformer area, lube oil tank, turbine generator and hydrocarbon pumps

    The wheeled extinguishers shall be protected by a suitable identified, heavy-duty soft vinyl or vinyl-coated canvas cover.

    10.4 4.6 kg CO2 extinguishers:

    Carbon dioxide extinguishers are to be used on fires involving electric and/or electronic equipment such as panel room, control room, cable spreading room, etc..

    CO2 extinguishers of 4.6kg capacity shall be installed in buildings where the risk necessitates and such that travel from the risk is 15m maximum.

    11. FIRE ALARM AND GAS DETECTION SYSTEM This Section is only design concept. For detailed description of Fire and Gas Detection System refer to the Engineering Specification for Fire and Gas Detection System (Doc No. : SC2277-SE-IS-000-4-1005).

    11.1 Fire and Gas Detection System Requirements

    11.1.1 The Fire & Gas detection system (FGS) shall be employed to provide prompt and reliable detection of a developing hazard in order to allow for maximum benefit from personnel response. Centralized Fire & Gas system displays shall be installed in the control building to enable operators to take appropriate action and to indicate that a protection system has been activated. The FGS comply with Lloyds or Veritas insurance guidelines and be in accordance with the NFPA 72 and NFPA 70. Relevant Australian standard may take precedence over NFPA, which have to be recommended by Supplier, if applicable. The fire and gas detection system for scope of supply shall consist of below as; Fire Alarm Auxiliary Panel (FAAP) : One DCS Operator Console

    type dual LCD monitors and one DCS Aux Console type switches and Lamps

    Fire and gas detection system panel-Master (FGSP-M) at instrument rack room

    Work Station for FGSP-M at engineering room Fire and gas detection system panel-Slave (FGSP-S) within each

    RIE

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 19 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    Work Station for FGSP-S within each RIE Local Fire Alarm Control Panel (LFACP) within each RIE Local Fire Suppression System Panel (LFSSP) within each RIE

    complete with Beacon and Sounder, Addressable detectors, etc.

    11.1.2 FGS shall provide a summary printout of analog smoke detectors and all other alarm input devices and events when initiated by an operators command that includes the following information: Analog values of all points including initial and extended average

    value Points out of sensitivity compensation Points isolated Points tested & failed Event log contents

    11.2 Fire Alarm Auxiliary Panel(FAAP)

    The Fire Alarm Auxiliary Panel (FAAP) will consist of HMI Graphics Display and switchboard. Same furniture of DCS would be preferred. The Graphics Display shall monitor plant fire alarm and status conditions on screen displaying graphical representations of the site by means of colored symbols and be equipped with buzzer or bell and visual annunciation so that operator can easily find the cause and acknowledge the alarm point. The Graphics Display shall give detail information of the type of alarm (e.g. HC gas, H2 gas, fire, manual call point). For gas detectors pre alarm and gas alarm (LEL) shall be displayed. Annunciators will be only common indication per detected hazard for each fire zone, indicating the type of alarm. Switchboard will be used for manual audible alarming, deluge valve activation. Backlight override switches shall be driven by a separate in and output connected to the logics. Color of symbol shall be as follows: toxic gas: Blue combustible gas: Yellow flame detector: Red fire alarm: Red manual call point: Transparent deluge valve/alarm check valve open/close: Green/Red running signal of firewater pumps: Green discharge signal from Clean Agent or CO2 system: Orange

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 20 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    11.3 Fire and Gas Detection System Panel(FGSP)

    The FGSP shall be a stand-alone, floor mounted and shall be located in instrument rack room and have a redundant fail safe communication structure.Signal processing, circuit integrity and logics shall be implemented with the same hardware as used for the ESD. FGSP-M shall be provided for Main Control Room. This system shall collect the data from FAAP in Main Control Room and FGSP-S in each RIE. The data from LFACP of non RIE (e.g. Substation, other non process buildings) shall be first collected to the FAAP in Main Control Room, from where the data shall be transmitted to FGSP-M by serial interface. Each RIE shall have dedicated FGSP-S for the designated area, where field gas and fire detectors are connected. LFACP in each RIE shall interface with FGSP-S by serial connection and the collected data in FGSP-S shall be interfaced with FGSP-M. The number of hardwired interface between FGSP-S and LFACP are to be defined during detail design. Supplier shall state in the quotation the standard capability of hardwired I/O connection for the LFACP. The FGSP shall be powered from two separate AC supplies, one of which is from UPS system and the other one from an emergency supply system. The UPS system shall have an 8-hour battery back up capacity. Supplier shall recommend the Australian standard application, if there should be any deviation required. The FGSP shall be programmable on site. The programming software shall provide the following automated reports: Project history (changes made to the system, with date stamp) List of authorized system programmers Full system configuration data Engineering work station

    11.4 HMI at security guard house

    The HMI showing the overview of all FGS system shall be located at the guard house. (Graphic display is same as FAAP)

    11.5 Local Fire Alarm Control Panel(LFACP)

    The LFACP will receive signals from fire alarm manual-stations in buildings via the network. An activation signal based on the location of the activated

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 21 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    manual station shall be transmitted to FGSP-S or FAAP. In case of the activation of the manual stations in buildings, the fire alarm localized as per single fire zone shall be given through bells and horn/strobe located indoors. The LFACP shall be programmed to shutdown the building HVAC system during a fire and to close fresh air intake/to keep on re-circulation of HVAC system when a gas leak is detected at the relevant RIE and buildings. Signals from fire detectors and gas detectors in buildings are processed within the LFACP. A common alarm status from all detectors is routed from LFACP to FGSP-S for each RIE and from LFACP to FAAP for non-RIE buildings. The fire and gas detection and protection equipment for RIE are part of the MAC scope of supply. RIE and analyzer houses will be protected by theirs own system. LFACP for RIE will be connected to the FGSP-S via serial communication for fail-safe network.

    11.6 Local Fire Suppression System Panel(LFSSP)

    Local Fire Suppression System Panel (LFSSP) will be located at the adjacent location close to agent cylinder storage rooms or convenient and safe location to activate the fire suppression system such as Clean Agent (HFC-227ea) and CO2 system. These panels will control the operation of the fire suppression systems and report all alarms and faults to the Fire and Gas Detection System Panel (FGSP) located in the main central control building.

    11.7 Fire Alarm and Gas Detection Equipment

    All areas and buildings of the plant will be provided with automatic smoke/heat detectors and manual call points. Flashing lamps will supplement the audible alarms in noisy areas. The layout of detectors will be designed to meet the unique requirements of each occupancy. All field device used as a part of the FGS shall be suitable for permanent working within environmental condition. The device type and location within the plant will be available at the Fire and Gas Detection System Panel. (FGSP)

    (1) Electronic Siren

    Electronic sounders will operate on 24 VDC nominal.

    Electronic sounders will be field programmable without the use of special tools, at a sound level of at least 109 dBA measured at 3m from the device.

    Electronic sounders will be flush or surface mounted as shown on plans.

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 22 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    (2) Red Flash Light

    Strobes will operate on 24 VDC with field selectable candela settings.

    Strobes will produce a nominal sound output of 88 dBA and tone adjustable 800 1200 Hz.

    Strobes will produce 1 flash per second over the regulated voltage range.

    (3) Alarm Bell

    All alarm bells will operate on 24 VDC.

    Alarm bells will produce a nominal sound output of 85 dBA.

    Alarm bells will be 10 (254 mm) diameter for indoor installation.

    (4) Manual break glass call points

    Manual alarm call points shall be provided and located strategically along designated exit routes from process areas and at road sides in and around the peripheral of the process areas at intervals not exceeding 50m

    Within buildings, manual alarm call points shall be located in accordance to NFPA 72 ensuring that the maximum travel distance for an operator to activate an alarm is no more than 30m.

    (5) Manual Release Push button for CO2, HFC-227ea Fire Extinguishing Systems

    Release station will be non-coded, dual action operation.

    Release station will include abort switch, power-on indication, release indication.

    Release station will be made with durable polycarbonate.

    (6) Smoke Detectors

    Photoelectric electric or ionization smoke detectors shall be provided in required buildings such as substation, remote instrument building, analyzed shelter and main central control buildings.

    Each detector will contain a remote LED output and a built-in test switch.

    Detector will be provided on a twist-lock base.

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 23 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    Very Early Warning Smoke Detection (VESDA) shall be provided within electrical cabinets in the process buildings.

    (7) Heat Detectors

    Heat Detectors shall be provided for each deluge system for automatic actuation of the deluge system and initiation of a fire alarm.

    Heat detectors will have a combination rate of rise and fixed temperature rated at 135 F(57.2 C) for areas where ambient temperatures do not exceed 100 F (37.7 C), and 190 F(93.33 C) for areas where the temperature does not exceed 150 F (65.5 C).

    The rate of rise element will consist of an air chamber, a flexible metal diaphragm, and a factory calibrated, moisture-proof, trouble free vent, and will operate when the rate of temperature rise exceeds 15 F (9.4 C) per minute.

    (8) Heat Detectors, Explosion-proof type

    Explosion-proof heat detectors will have a combination rate of rise and fixed temperature rated at 194 F (90 C) for hazardous areas.

    The detector will be of hermetically sealed, shock resistant, corrosion-resistant, and tamper-proof.

    (9) Flame Detectors

    Flame detection devices shall be located to monitor select areas of the plant such as gas compressor seals, etc. Activation of a flame detector shall be indicated at the associated local control panel and simultaneously alarmed at the Control Room and Fire Station.

    Audible and visual alarms shall be actuated locally in the concerned area of the plant.

    (10) Flammable Hydrocarbon Gas Detection

    Flammable gas detectors shall be positioned near potential sources of hydrocarbon gas leaks, pumps, compressors, air intakes for HVAC, and turbines. Alarm levels shall be set at 10% and 25% of the Lower Flammable Limit (LFL). Flammable gas detectors that can be exposed to H2S releases (which include all areas within the gas plant) shall be designed for operation in atmospheres containing H2S.

    Hydrogen gas detectors shall be located in the battery rooms if H2 can be released when the batteries are used.

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 24 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    (11) Toxic Gas Detection

    Toxic gas detectors (such as NH3 and CO) shall be positioned near potential sources of toxic gas leakage and where toxic gas is likely to be detected when released such as pump/compressor seals, air intakes for HVAC, enclosures, and air outlets from enclosed classified areas.

    H2S detectors shall be located on two basic criteria: general coverage and specific location detectors in the process and utility areas. Alarm levels shall be set at both 10 ppm and 20 ppm.

    SO2 detectors shall be used in the sulphur handling areas as fire detectors. Another alarm will be initiated when 3 ppm is reached. Because of the limited sensitivity of SO2 sensors, an independent method of fire detection, such as ultraviolet sensors, will be used in addition to SO2 detection.

    Consider to provide detection equipment for coal pile/coal handling to early detection fires may occur from the bottom of coal pile. CO monitoring or hot spot detection may apply.

    12. BREATHING APPARATUS Self contained breathing apparatus sets each consisting but not limited to single cylinder air tank sized for 30 minutes operation, carrying harness, face mask and necessary regulator and hoses shall be provided and housed in weatherproof cabinets located in the following areas in pairs.

    Process unit walkways Externally at entrance to Operators Shelters Externally at entrance to Remote Instrument Enclosures Externally at entrance to Electrical Substations MCR

    13. PASSIVE FIRE PROTECTION For detailed description of passive fire protections refer to the "Specification for Passive Fire Protection (Doc No. : SC2277-SE-BS-000- 4-1002).

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 25 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    ATTACHMENT 1 : SUMMARIZED MATRIX FOR FIRE FIGHTING FACILITIES OF BUILDING

    Buildings Portable

    CO2Extinguisher

    Portable Dry Powder

    Extinguisher

    Mobile Dry Powder

    Extinguisher

    Indoor Hydrant System

    Water Sprinkler System

    Water Spray

    System

    FixedGaseous

    Extinguishing System

    Process buildings: Analyzer Houses X X X

    U&O Substation X X X X

    Urea Substation X X X X

    Ammonia Substation X X X X

    GasificationSubstation X X X X

    PowerTransformer Area X

    Remote Instrument Enclosures

    X X X

    Non-Process buildings: Guard Houses X X X Main Control Building X X X X

    AdministrationBuilding X X X X X

    Warehouse Bldg X X X X X X

    Chemical Storage Bldg X X X X X

    Building X X X X X X

    Canteen X X X

    Laboratory Building X X X

    U & O Substation X X X X

    Coal Handling Substation X X X X

    PowerTransformer Area X

  • COLLIE UREA PROJECT

    FIRE PROTECTION SYSTEM PHILOSOPHY

    DOCUMENT NUMBER SC2277-SE-FA-760-4-1001

    Revision 3

    Page 26 of 26

    G

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    G

    ATTACHMENT 2 : SUMMARIZED MATRIX FOR F&G SYSTEM OF BUILDING

    Buildings Smoke Detection Heat

    Detection

    Very Early Warning Smoke

    Detection

    Manual Call

    Points Fire Alarm Sounders

    GasDetectors

    GasAlarms

    Process Area Buildings:

    Analyser Houses X X X

    U&O Substation X X X X X X X

    Urea Substation X X X X X X X

    Ammonia Substation X X X X X X X

    GasificationSubstation X X X X X X X

    Power Transformer Area X

    Remote Instrument Enclosures X X X X X X X

    Plant Facilities Buildings:

    Guard Houses X X X

    Main Control Building X X X X X X X

    AdministrationBuilding X X X X X X X

    Warehouse Bldg X X X X X X

    Chemical Storage Bldg X X X X X X

    Building X X X X X X X

    Canteen X X X

    Laboratory Building X X X X X X X

    U & O Substation X X X X X X X

    Coal Handling Substation X X X X X X X

    Power Transformer Area X

    G

  • GESTIMATED FIREWATER DEMAND CALCULATION

    Doc. No Appendix #3

    Page 1 of 7

    G

    G

    G

    G

    G

    G

    G

    G

    G

    G

    ESTIMATED FIREWATER DEMAND CALCULATION

    ATTACHMENT #3

  • GESTIMATED FIREWATER DEMAND CALCULATION

    Doc. No Appendix #3

    Page 2 of 7

    G

    CONTENTS

    1.0G CALCULATION BASIC ................................................................................................................ 3G

    2.0G FIRE WATER DEMAND CALCULATION .................................................................................... 4G

    3.0G FIRE WATER DESIGN SELECTION ........................................................................................... 6G

    4.0G ATTACHMENTS ........................................................................................................................... 7G

  • GESTIMATED FIREWATER DEMAND CALCULATION

    Doc. No Appendix #3

    Page 3 of 7

    G

    1.0 CALCULATION BASIC

    1.1 Definition of single fire zone

    The fire protection system shall be designed on the basis of only major fire at a time. No simultaneous occurrence of fire, either within a single area or in multiple locations in multiple locations in the plant, shall be considered. The following area or facility is considered as a one single fire risk area.

    (1) In the process area, all equipment located in an area separated to other equipment by means of pipe rack, roads or distance of at 15m.

    (2) In the tank storage area, the one tank is considered as one fire risk area.

    (3) In the building area, the independent room enclosed by noncombustible materials is considered as one fire risk area.

    1.2 Code and Standards

    Description

    Code & Standard Required of

    Fire Water Demand

    Required Duration of Firewater

    Supply Remark

    NFPA-850 - Recommended Practice for Fire Protection for Electric Generating Plants and High Voltage Direct Current Converter Stations (Sec. 6.2.1)

    The largest fixed fire suppression system (or any fixed fire suppression system demands that could reasonably be expected to operate simultaneously during a single fire),plus the hose stream demand of not less than 500 gpm(1890 L/min)

    Min. 2 hours

    API RP 2001 - Fire Protection in Refineries (Sec. 4.2.1.2 and 4.2.1.4)

    Fixed water spray, sprinkler, or foam systems, the flow rate should be the sum of the flow rates required for proper operation of the fixed systems, plus an allowance for simultaneous operation of monitors and hose streams.

    Min. 4 to 6 hours

  • GESTIMATED FIREWATER DEMAND CALCULATION

    Doc. No Appendix #3

    Page 4 of 7

    G

    2.0 FIRE WATER DEMAND CALCULATION

    Fire Zone Application System & Firewater Demand Remark

    Fire Zone 1: Unit 100 Milling and Drying

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456m3/h

    Fire Zone 2: Unit 200 Gasification

    Fixed Deluge System, 142 m3/h(625 GPM) Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 598m3/h

    Fire Zone 3: Unit 300 CO Shift

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456m3/h

    Fire Zone 4: Unit 350 HCN-COS Hydrolysis & Cooling Section

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456m3/h

    Fire Zone 5: Unit 400 AGR

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456m3/h

    Fire Zone 6: Unit 410 H2 Purification

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456m3/h

    Fire Zone 7: Unit 420 CO2 Compression

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456m3/h

    - Lube Oil Console Fixed Deluge System, 44 m3/h(193 GPM)

    Total Flow Rate : 44 m3/h

    Fire Zone 8: Unit 500 Ammonia - 500-K-531 / 541

    Fixed Deluge System, 225 m3/h(990 GPM) Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Maximum Firewater Demand : 681 m3 /h (2,998 GPM)

    Total Flow Rate : 681 m3/h

    - 500-K-551

    Fixed Deluge System, 65 m3/h(285 GPM) Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 521 m3/h

    - Lube Oil Console Fixed Deluge System, 44 m3/h(193 GPM)

    Total Flow Rate : 44 m3/h

    - Transformer

    Fixed Deluge System, 43 m3/h(189 GPM) Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 499 m3/h

  • GESTIMATED FIREWATER DEMAND CALCULATION

    Doc. No Appendix #3

    Page 5 of 7

    GFire Zone Application System & Firewater Demand Remark

    Fire Zone 9: Unit 550 Urea

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456 m3/h

    Fire Zone 10: Unit 560 Urea granulation

    Fixed Deluge System, 159 m3/h(700 GPM) Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 615m3/h

    Fire Zone 11: Unit 570 Product storage & loading

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456 m3/h

    Fire Zone 12: Unit 440 Sulphur recovery

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456 m3/h

    Fire Zone 13: Unit 600 Power Generator

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456 m3/h

    Fire Zone 14: Unit 650 Air Separation

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456 m3/h

    Fire Zone 15: Unit 700 Air Separation

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456 m3/h

    Fire Zone 16: Unit 800 Other Utilities

    Fixed Deluge System, 37 m3/h(163 GPM) Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 439m3/h

    Fire Zone 17: Coal Pile Area-1

    Fixed water monitor, 4 EA x 114 m3/h(500 GPM)

    Total Flow Rate : 456 m3/h

    Coal Pile Area-2 Fixed water monitor, 4 EA x 114 m3/h(500 GPM)

    Total Flow Rate : 456 m3/h

    Coal Pile Area-3 Fixed water monitor, 4 EA x 114 m3/h(500 GPM)

    Total Flow Rate : 456 m3/h

    Coal Pile Area-4 Fixed water monitor, 4 EA x 114 m3/h(500 GPM)

    Total Flow Rate : 456 m3/h

    Coal Pile Area-5

    Hand hose streams , 228 m3/h (1000 GPM)

    Total Flow Rate : 228 m3/h

    Fire Zone 18: Building Area

    Automatic Sprinkler System,200 m3/h (881GPM) Hand hose streams , 228 m3/h (1000 GPM)

    Total Flow Rate : 428 m3/h

  • GESTIMATED FIREWATER DEMAND CALCULATION

    Doc. No Appendix #3

    Page 6 of 7

    GFire Zone Application System & Firewater Demand Remark

    Fire Zone 19: Unit 830 Slag Area

    Fixed water monitor, 2 EA x 114 m3/h(500 GPM) Hand hose streams , 228 m3/h(1000 GPM)

    Total Flow Rate : 456 m3/h

    Fire Zone 20: Stratefic Coal Pile

    Fixed water monitor, 4 EA x 114 m3/h(500 GPM)

    Total Flow Rate : 456 m3/h

    G

    3.0 FIRE WATER DESIGN SELECTION

    3.1 The Maximum Fire Water Demand is applies with 795 m3/hrFor safety reason, water demand of fixed deluge system shall be added 30% safety factor

    30% safety factor : 20% due to water not reaching the equipment(because of wind or other factors), and in addition 10% as a flow balancing factor for discharge nozzle pressure variations.

    Maximum Fire Single Zone : Unit 500 Ammonia

    Fixed Deluge System : 225 m3/hr (990 GPM) x 1.3 = 292.5 m3/hr (1,288 GPM) Fixed Water Monitor : 114 m3/hr x 2 EA = 228 m3/hr (1,000 GPM) Hand Hose Stream : 114 m3/hr x 2 EA = 228 m3/hr (1,000 GPM)

    Total Fire Water Demand of Maximum Single Fire Risk Area :

    713.4 m3/hr (3,133 GPM)

    Consequentlly, Fire Pump is required the least 795 m3/hr (3,500 GPM) of pump listed NFPA 20

    3.2 Fire Water Supply Storage Tank Capacity : 5,000 m3

    (Based on the maximum fire water demand of 795 m3/h, 3,500 m3 correspond to 6hours of fire water storage.)

    3.3 Fire Water Supply Ring Main Size : 12 inch (Based on the maximum allowable fire water velocity of 4.6 m/s and maximum fire water demand of 795 m3/h, fire water ring main size is calculated at 12 inch)

    3.4 Two (2) fire water pump shall be required, one driven by electric motor(main), one driven by diesel engine(stand-by). The capacity of each pump shall be 795 m3/hr(3,500 gpm) at the minimum pressure of 10 barg.One (1) fire water jockey pump, electric motor driven, capacity of 50 m3/h at 7 barg,shall be provided to maintain the system pressure against leakage

  • GESTIMATED FIREWATER DEMAND CALCULATION

    Doc. No Appendix #3

    Page 7 of 7

    G

    4.0 ATTACHMENTS

    4.1 Attachment #4 - Drawing for Single Fire Zone

  • COLLIE UREA PROJECT

    Fire Water Utility Description

    DOCUMENT NUMBER SC2277-IK-AI-760-4-1001

    Revision 2

    Page 2 of 4

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    CONTENTS

    1. GENERAL ................................................................................................................ 32. DESCRIPTION OF THE SYSTEM ........................................................................... 33. DESIGN BASIS ........................................................................................................ 44. SYSTEM EQUIPMENT AND AUXILIARY ................................................................. 4

  • COLLIE UREA PROJECT

    Fire Water Utility Description

    DOCUMENT NUMBER SC2277-IK-AI-760-4-1001

    Revision 2

    Page 3 of 4

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    1. GENERAL Fire water system facility will be provided for active Fire protection system of Collie

    Urea Plant supporting water based suppression. Fire water system consists of Fire

    Water Pump, Fire Water Tank and Fire Water System Distribution.

    2. DESCRIPTION OF THE SYSTEM Refer to Utility Flow Diagram Fire Water System No. SC2277-IK-AD-760-3-1001

    and Fire Protection System Philosophy No. SC2277-SE-FA-760-4-1001, the water

    for fire fighting system is a dedicated fire water tank (760-T-001) and additionally

    have back-up from the raw water pond under emergency condition. Fire water tank

    is sized to a minimum storage capacity of 5000 m3 for 6 hours of continuous fire

    fighting operation.

    Two (2) fire water pumps consist of one main pump driven by electric motor (760-

    P-001A M) and one stand-by pump driven by diesel driven (760-P-001B D). They

    are horizontal split centrifugal types. The capacity of each pump is 795 m3/hr

    (maximum fire water demand) and therefore it is ensured the maximum fire water

    supply even if one of the pumps is out of service or when the electric power is

    unavailable.

    One(1) jockey pump (760-P-002 M), electric motor driven, is provided to maintain

    the system pressure at 800 kPaG against leakage and to allow automatic starting

    of main fire water pump sequentially in the event of fire water demand from the

    plant. The capacity of jockey pumps is 50 m3/hr at 1000 kPaG.

    Pressure at the fire water distribution network shall be controlled by a pressure

    transmitter PT-0001 which is connected to Fire and Gas Detection System Panel

    (FGSP) and each fire water pump with four (4) setting point:

  • COLLIE UREA PROJECT

    Fire Water Utility Description

    DOCUMENT NUMBER SC2277-IK-AI-760-4-1001

    Revision 2

    Page 4 of 4

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    HIGH : Stop Jockey Pump (760-P-002 M) at 850 kPag

    LOW-1 : Start Jockey Pump (760-P-002 M) at 750 kPag

    LOW-2 : Start Main Fire Water Pumps (760-P-001A M) at 700 kPag

    LOW-3 : Start stand-by Fire Water Pump (760-P-001B D) at 650 kPag or if

    Main Fire Water Pump fail to build up pressure within 30 second

    Manual starting of each pump unit shall be possible at the pump and from the

    control room. The fire water pumps shall be designed for manual local stop only.

    Remote alarms for pump and controller status, power supply etc. is provided for

    the fire water pumps in accordance with AS 2941 and NFPA 20. The alarms

    should be connected into the DCS system and FGSP.

    3. DESIGN BASIS Fire water requirement for Collie Urea Plant is estimated based on Fire Protection

    System Philosophy No. SC2277-SE-FA-760-4-1001.

    4. SYSTEM EQUIPMENT AND AUXILIARY The Fire Water System equipments comprise:

    760-T-001 : Fire Water Tank

    760-P-001 A M : Fire Water Pump Electric Driven

    760-P-001 B D : Fire Water Pump Diesel Driven

    760-P-002 M : Jockey Pump Electric Driven

  • COLLIE UREA PROJECT

    Fire Water Pump System

    DOCUMENT NUMBER SC2277-IK-RS-760-4-1001

    Revision 3

    Page 1 of 18

    SPECIFICATION FOR

    FIRE WATER PUMP SYSTEM

    3 Jan 08, 2010 Issued as per PCF comments JC/MH US/EM SECL PCF

    2 Dec 29, 2009 Issued as per SECL comments JC/MH US/EM SECL PCF

    1 Dec 23, 2009 Issued as per SECL comments JC/MH US/EM SECL PCF

    0 Oct. 27, 2009 Issued for Review JC/MH US/EM SECL PCF

    REV DATE DESCRIPTION PREPARED REVIEWED APPROVED CLIENT APPROVAL

    Perdaman Chemicals and Fertilizers (Perth , Australia)

    PT. Inti Karya Persada Tehnik (Jakarta, Indonesia)

    SAMSUNG ENGINEERING CO. LTD. (Seoul , Korea)

    DEPARTMENT: JOB NO: DOCUMENT NO:

    Mechanical SC2277 SC2277-IK-RS-760-4-1001

  • COLLIE UREA PROJECT

    Fire Water Pump System

    DOCUMENT NUMBER SC2277-IK-RS-760-4-1001

    Revision 3

    Page 2 of 18

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    TABLE OF CONTENTS

    1. GENERAL ............................................................................................................ 3

    1.1. Purpose .................................................................................................... 31.2. Order of Precedence.31.3. Definitions3

    2. CODE, STANDARDS AND SPECIFICATIONS ............................................... 4

    3. DESIGN ................................................................................................................ 5

    3.1 General Design Basis ............................................................................... 5 3.2 Pump Performance Requirements ............................................................. 5 3.3 Pump Design and Rating .......................................................................... 7 3.4 Impeller, Bearing and Seals ...................................................................... 8 3.5 Pump Material .......................................................................................... 9 3.6 Drivers ..................................................................................................... 9 3.7 Skid and Accessories .............................................................................. 12 3.8 Control and Instrumentation ................................................................... 14

    4. INSPECTION AND TESTING .......................................................................... 16

    4.1 General requirements ............................................................................. 16 4.2 Pump Testing ......................................................................................... 16

    5. DOCUMENTATIONS ....................................................................................... 17

    6. PREPARATION FOR SHIPMENT .................................................................. 18

    6.1 Protective Coating .................................................................................. 18 6.2 Nameplate .............................................................................................. 18

  • COLLIE UREA PROJECT

    Fire Water Pump System

    DOCUMENT NUMBER SC2277-IK-RS-760-4-1001

    Revision 3

    Page 3 of 18

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    1. GENERAL

    1.1. PURPOSE The purpose of this specification is to define the minimum technical requirements for the design, supply, manufacture, and testing of Main Fire Water Pumps and jockey Pump for Collie Urea Project.

    1.2. ORDER OF PRECEDENCE In case of conflict between documents they shall take precedence in the following order: a. Australian National Law & Regulations b. Local Government / Statutory regulations. c. Data Sheets d. This specification. e. Other PCUP Project Specifications f. Referenced codes and standards.

    Any deviation or conflicts from the specifications and/or data sheets shall be presented in writing to the Purchaser for resolution. Written approval for any deviation is required prior to the start of any work. Compliance with the specifications and data sheets does not relieve the SUPPLIER/VENDOR of the responsibility to furnish equipment of safe and proper design, suited to meet the performance guarantees.

    1.3. DEFINITIONS The term used in this engineering specification are defined below, Owner : Perdaman Chemicals and Fertilizers Pty Ltd. EPC Contractor : Samsung Engineering Co. Ltd. as a Purchaser. Sub Contractor : Company doing construction activities at site this includes

    erection works and commissioning assistance. Supplier/Vendor : Equipment / Machinery or Package Supplier/Vendor also helps

    in supervision during erection by Sub Contractor and commissioning if required.

    Sub-Supplier : Sub-Supplier of package unit components

  • COLLIE UREA PROJECT

    Fire Water Pump System

    DOCUMENT NUMBER SC2277-IK-RS-760-4-1001

    Revision 3

    Page 4 of 18

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    2. CODE, STANDARDS AND SPECIFICATIONS The current versions complete with the latest amendments, of the following laws, statutory regulations, codes, standards and specifications shall form part of and shall be read in conjunction with this specification.

    Project Specifications & Documents

    SC2277-SE-FA-780-4-1001 Fire Protection System Philosophy SC2277-SE-RS-000-4-1001 Engineering Specification for Rotating Machinery and

    Package. SC2277-IK-AI-760-4-1001 Fire Water Utility Description SC2277-IK-AD-760-3-1001 UFD Fire Water System SC2277-IK-FF-760-3-1001 P&ID - Fire Water Storage Tank and Pumps SC2277-SE-ES-000-4-1001 Standard Engineering Specification Electrical Design

    Criteria SC2277-SE-IS-000-4-1001 Instrumentation for Package Equipment

    Australian National Law & Regulations AS 2941 Fixed Fire Protection Installations Pump set systems

    American Society of Mechanical Engineers (ASME) ASME B73.1M Specification for Horizontal End Suction Centrifugal

    Pumps for Chemical Process ASME B 1.1 Screw Threads. ASME 1.20.1 Pipe Threads. ASME B16.5 Pipe Flanges & Flanged Fittings

    National Fire Protection Association (NFPA) NFPA 20 Standard for the Installation of Centrifugal Fire Pumps NFPA 70 National Electric Code

    Underwriters Laboratories Classification Services (UL) UL 218 Fire Pump Controllers UL 448 Pumps for Fire Protection Service UL 508 Electric Industrial Control Equipment UL 1236 Electric Battery Chargers UL 1247 Diesel Engines for Driving Centrifugal Fire Pumps

    Hydraulic Institute Standard (HIS) Standard for Centrifugal, Rotary and Reciprocal Pumps-Centrifugal Pumps Test Code

    3

  • COLLIE UREA PROJECT

    Fire Water Pump System

    DOCUMENT NUMBER SC2277-IK-RS-760-4-1001

    Revision 3

    Page 5 of 18

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    American Gear Manufacturers Association (AGMA) AGMA A 420 Practice for Helical and Herringbone Gear Speed

    Reducers and Increasers AGMA A 421 Practice for High Speed Helical and Herringbone Gear

    Units

    3. DESIGN

    3.1 General Design Basis 1) The fire fighting system is designed on the basis of only major fire with a single risk

    area at a time. There is no simultaneous occurrence of fire, either within a single fire area or in multiple locations in the plant, is to be considered.

    2) The Fire water demand is therefore determined based on the largest single fire water demand from the respective area requirements in the plant.

    3) The total design of fire water demand is 795 m3/hr.

    4) The water for firefighting system shall be supplied by means of pumping from a fire water storage tank (760-T001) and additionally have back-up from the raw water pond under emergency condition.

    5) The fire water storage tank is sized to a minimum storage capacity of 5000 m3 for 6 hours of continuous fire fighting operation.

    6) All pumps, drivers, controlling equipment, power supply and arrangement shall be approved by the Western Australia authority having jurisdiction for the specific field conditions encountered.

    3.2 Pump Performance Requirements

    3.2.1. Fire Water Pumps

    Fire water pumps shall be electric motor(s) and diesel engine driven. The design, installation, and acceptance test of fire water pumps shall conform to NFPA 20.

    The fire water source is taken from fire-water storage tank located at site, close to the main firewater pumps.

    Two (2) fire water pumps shall be required, one driven by electric motor (760-MP001 A as a main) and the other by diesel engine (760-DP001 B as a stand-by). All pumps are horizontal split centrifugal types. The capacity of each pump is 795

  • COLLIE UREA PROJECT

    Fire Water Pump System

    DOCUMENT NUMBER SC2277-IK-RS-760-4-1001

    Revision 3

    Page 6 of 18

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    m3/hr and therefore it is ensured the maximum fire water supply even if one of the pumps is out of service or when the electric power is unavailable.

    The main fire water pumps shall provide fire water at specified pressure to the plant firewater networks, so that the system is ready to service with the minimum pressure of 1.0 MpaG at the design flow rate at any point on the ground level in the plant.

    The main fire water pumps shall be suitable for parallel operation. The mains pressure shall be controlled by bypass flow back to the fire water storage tank through a back pressure regulator valve.

    Fire water pumps shall capable to furnish 150% or above of the rated capacity at not less than 65% of total rated head. The shutoff head shall not exceed 140% of rated head for any type of pump.

    The fire pumps will be operate as follows:

    a. The jockey pump will maintain the general network pressure at 0.8 MpaG. In the event that the network pressure drops below 0.75 MpaG, jockey pump will be automatically started.

    b. In the event that the fire water network pressure falls below 0.7 MpaG, the main fire water pump and stand-by fire water pump will be started automatically utilizing their respective pressure switched at pre-set points. In addition to, stand-by fire water pump also start if main fire pump does not start, or having started, fail to build up the required pressure in the fire water ring main system within 30 seconds.

    Manual starting of each pump unit shall be possible at the pump and from the control room. Manual stopping of each pump unit shall only be possible at the pump.

    The fire water pumps shall be designed for manual local stop only.

    3.2.2. Jockey Pump

    One (1) Centrifugal type jockey pump (760-MP002) of either horizontal type is in operation and driven by electric motor shall be used to maintain the fire-water line system pressure against any possible leakage. The capacity of Jockey pumps is 50 m3/h at 1.0 MpaG discharge pressure.

  • COLLIE UREA PROJECT

    Fire Water Pump System

    DOCUMENT NUMBER SC2277-IK-RS-760-4-1001

    Revision 3

    Page 7 of 18

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    The Jockey pump will also be capable of starting and stopping manually from the local control and from the control room.

    The start and stop of the Fire Water Pump System and its setting hierarchy shall be follow the project document SC2277-IK-AI-760-4-1001_Rev.2 Fire Water Utility Description.

    3.3 Pump Design and Rating The firewater and jockey pumps shall comply with this specification, NFPA 20 and Hydraulic Institute Standard. Each component of the firewater pump package shall be NFPA / UL listed, whilst the jockey pump is considered to be unlisted. Where applicable, individual components require UL certification shall bear a classification marking (UL certification).

    The pump shall be designed for continuous base load at the rated conditions. The rated capacity and head specified on the data sheet is at the pump discharge flange.

    The pump characteristics shall be as defined in NFPA 20 and in accordance with the following:

    c. Flow versus head characteristics shall conform to the requirements of NFPA 20, figure A.6.2.

    d. Each pump shall be able to operate at the rated conditions for a minimum of 8,760 total operating hours before overhaul is required. The pump shall be capable of continuous operation at the rated conditions. A design life of 25 years shall be considered as a minimum.

    e. The pump shall be selected such that 5% change in capacity and head with respect to rated conditions shall be achieved.

    f. The pump shall be capable of operating at 150% of rated flow without the NPSH (R) exceeding the NPSH available.

    The horizontal pumps shall be axially split type and the pump rotation shall be clockwise (CW) when viewed from driver end.

    Each fire water pump unit shall consist of a pump, driver, controller, a common base-plate for each pump and driver and accessories, as required for operation by NFPA 20 and the corresponding data sheets.

  • COLLIE UREA PROJECT

    Fire Water Pump System

    DOCUMENT NUMBER SC2277-IK-RS-760-4-1001

    Revision 3

    Page 8 of 18

    No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including photocopying, recording, or by any information storage and retrieval system, without permission in writing from Samsung Engineering.

    The pump shall be furnished as a packaged unit by a single SUPPLIER/VENDOR. Fire Water Pump, pressure relief valve and controllers shall be UL listed or FM approved for fire water pump service with the pump manufacturer responsibility for the units listing or approval.

    The electric motor / di