perpustakaan ump iii fl i

24
PERPUSTAKAAN UMP COMPARISON ( III fl I EG BOND STRENGTH BETWEEN C( 0000092694 PAIR MATERIALS NURULNIZAM BIN MOHAMED A report submitted in partial fulfillment of the requirement for the award of the degree of Bachelor in Civil Engineering Faculty of Civil Engineering and Earth Resources UNIVERSITI MALAYSIA PAHANG JUNE 2013

Upload: others

Post on 12-Jun-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PERPUSTAKAAN UMP III fl I

PERPUSTAKAAN UMP

COMPARISON ( III fl I

EG BOND STRENGTH

BETWEEN C( 0000092694

PAIR MATERIALS

NURULNIZAM BIN MOHAMED

A report submitted in partial fulfillment of the requirement for the award of the degree

of Bachelor in Civil Engineering

Faculty of Civil Engineering and Earth Resources

UNIVERSITI MALAYSIA PAHANG

JUNE 2013

Page 2: PERPUSTAKAAN UMP III fl I

V

ABSTRACT

Placing freshly mixed concrete against old existing concrete is a point of interest in repair applications, and can be sometimes a vital issue. Unless good bond is ensured at the interface, the concrete section may become improper and sometimes unsafe. An experimental study was performed to investigate the effect of testing methods on bond strength between concrete substrate and repair material. 27 numbers of sample with different dimension were prepared according to different type of testing. Sample with dimension of 150x150x150 mm cubes were required for spliting test. The cubes is constructed into two parts as old substrate concrete and repair material with a size of base size 75x150 mm and a height of 150mm. In the Bi-Surface shear method, the repair material constitutes one third of the samples which means the prisms with a base size of 100x150 mm and a height of 150 mm are cast as old or substrate concrete. Then the repair materials are cast in prisms with a base of 1 50x50 mm and a height of 150 mm and are bonded to the concrete substrate. Slant Shear Test samples were lOOxlOOx400 mm and it is cut at angle 60° to their cross sectional axis whereas the old substrate designed with a base size of lOOxlOOmm and height 1 13.5mm as well as the repaired material samples. Steel wire brush were rub to bonding surface in order to produce different surface roughness. The estimated amplitude of low roughness was 3-4 mm and using a similar approach, the high-roughness was roughened to amplitude of 7-8 mm. After two weeks, the new concrete was added to the substrate concrete. Splitting prism test, Bi-Surface direct shear test and Slant shear tests were performed to evaluate the bond strength at age 7 days, 14 days and 28 days The results shows sample with high roughness surface were produce more conpressive strength in all type of testing. Hence, direct shear test was develop greater comprasive strength compare to spliting prism test and slant sheat test.

Page 3: PERPUSTAKAAN UMP III fl I

VI

ABSTRAK

Kaedah meletakkan campuran konkrit segar terhadap konkrit lama sedia ada merupakan perkara utama dalam proses membaiki dan penambahbaikan, juga boleh menjadi satu isu penting dalam bidang pembinaan. Hal mi kerana struktur konkrit boleh menjadi tidak sekata dan kadang-kadang tidak selamat walaupun cantuman antara konkrit telah diyakini sepenuhnya. Satu ekperimen telah dijalankan untuk mengenalpasti keberkesanan kaedah kajian terhadap kekuatan ikatan antara konkrit sedia ada dan lapisan konkrit baru.. 27 bilangan sampel dengan dimensi yang berbeza telah disediakan mengikut berlainan j enis ujian. Kiub dengan dimensi 150x150x150 mm diperlukân bagi "Splitting prism test" dibina kepada dua bahagian sebagai konkrit substrat lama dan bahan baru dengan saiz asas 75x150 mm dan ketinggian 150mm. Dimensi ruang konkrit ham bagi kaedah Bi-Surface shear ialah satu pertiga daripada sampel yang bermaksud prisma dengan saiz asas 100x150 mm dan ketinggian 150 mm dinyatakan sebagai konkrit lama atau substrat. Kemudian konkrit barn digabungkan dalam prisma dengan asas mm 1 50x50 dan ketinggian 150 mm dan terikat kepada substrat konkrit. Dimensi Slant Shear Test pula adalah lOOxlOOx400 mm dan ia dipotong pada sudut 60 0 dengan paksi keratan rentas mereka manakala substrat lama direka dengan saiz asas 1 OOxl 00mm dan ketinggian 113.5mm termasuklah ruang konkrit barn. Berus kawat telah digunakan untuk menyapu ke permukaan ikatan untuk menghasilkan kekasaran permukaan yang berbeza. Kekasaran rendah dianggarkan antara 3-4 mm dan menggunakan pendekatan yang sama, kekasaran tinggi telah dianggarkan antara 7-8 mm di permukaan sampel. Proses penggabungan konkrit baru ke atas konkrit lama dilakukan dalam tempoh dua minggu kemudian. Ujian "Splitting prism", "Bi-Surface direct shear" dan "Slant shear" telah dijalankan untuk menilai kekuatan ikatan pada tempoh 7 han, 14 hari dan 28 han. Keputusan menunjukkan sampel dengan kekasaran permukaan tinggi telah menghasilkan kekuatan lebih lebih dalam semua jenis ujian. Oleh itu, ujian "direct shear" lebih kuat berbanding ujian "spliting prism test" dan "slant shear test".

Page 4: PERPUSTAKAAN UMP III fl I

TABLE OF CONTENTS

Page

SUPERVISOR'S DECLARATION j

STUDENT'S DECLARATION li

DEDICATION

ACKNOWLEDGEMENTS iv

ABSTRACT V

ABSTRAK vi

TABLE OF CONTENTS vii

LIST OF TABLES x

LIST OF FIGURES xi

CHAPTER 1 INTRODUCTION

1.1 General 1

1.2 Problem statement 2

1.3 Objective of the study 3

1.4 Scope of study 3

1.5 Important of study 5

CHAPTER 2 LITERATURE REVIEW

2.1 Introduction 6

2.2 Bond strength

6

2.3 Factors affecting bond strength

7

2.3.1 Surface preparation

7

2.3.2 Surface roughness 11

2.3.3.1 Interfacial transition zone 11

2.3.3.2 Effect of surface roughness on bond strength

12

2.3.3 Compaction and placement of the overlay

12

2.3.4 Overlay curing and temperature effect

14

Page 5: PERPUSTAKAAN UMP III fl I

viii

2.4 Secondary factors influencing bond 15

2.4.1 Pre-wetting 15

2.4.2 Traffic vibrations 15

2.4.3 Environmental factors 15

2.5 Compressive test experiment 16

2.5.1 The Splitting prism test 17

2.5.2 Slant Shear test 18

2.5.3 Direct shear test 19

CHAPTER 3 METHODOLOGY

3.1 Introduction 21

3.2 Research methodology 22

3.3 Formwork preparation 24

3.4 Preparation of material 26

3.4.1 Material used 26

3.4.1.1 Cement 26

3.4.1.2 Fine aggregate 27

3.4.1.3 Coarse aggregate 28

3.4.1.4 Water 28

3.4.2 The mix proportions 29

3.5 Roughness 30

3.6 Concreting 31

3.6.1 Casting substrate 31

3.6.2 Casting new fresh concrete 33

3.7 Curing 36

3.8 Testing method 37

3.8.1 Concrete compressive test 37

3.8.1.1 Concrete compression machine 38

3.8.1.2 Universal tensile/compression machine 39

Page 6: PERPUSTAKAAN UMP III fl I

lx

CHAPTER 4 RESULTS

4.1 Introduction 40

4.2 Compressive strength of different type of testing 40

4.3 Compressive strength of different roughness surface 46

4.4 Failure mode 51

4.4.1 Failure mode at 7 days curing age 52

4.4.2 Failure mode at 14 days curing age 55

4.4.3 Failure mode at 28 days curing age 60

CHAPTER 5 CONCLUSION AND RECOMMENDATION

5.1 Conclusion 65

5.2 Recommendation 66

REFERENCES 67

APPENDIXES 69

A Procedure of compression test 69

B Concrete mix design 70

Page 7: PERPUSTAKAAN UMP III fl I

LIST OF TABLES

Table No. Title Page

2.1 Methods of concrete removal 10

2.2 Types of experiment 20

3.1 Main compound of portland cement 27

3.2 Proportion of concrete samples 29

3.4 Concrete overlay process 36

4.1 Compressive test 42

4.2 Results of different testing 47

4.3 Results of failure mode 51

A

Page 8: PERPUSTAKAAN UMP III fl I

LIST OF FIGURES

Figure No. Title Page

1.1 Cube dimension of Splitting and Bi-Surface test 4

1.2 Prism dimension of Slant shear test 5

2.1 Modes of failure 7

2.2 Cleanliness surface of samples 8

2.3 Types of surface roughness 11

2.4 Placement of new concrete 13

2.5 Effect of curing duration on compressive strength 14

2.6 Set up for compression test 16

2.7 Set up for Splitting test 17

2.8 Slant shear test 18

2.9 Different shear test of bond strength 19

3.1 Flowchart of research methodology 23

3.2 Styrofoam for block-out (Slant shear test) 24

3.3 Styrofoam for block-out (Bi-surface Direct shear test) 25

3.4 Styrofoam for block-out (Splitting prism test) 25

3.5 Ordinary Portland Cement 26

3.6 Fine aggregate 27

3.7 Coarse aggregate 28

3.8 Cleaning process 30

3.9 Roughness surface process 31

3.10 Concrete mixing process 32

3.11 Concrete placed in mould 32

3.12 Curing age of substrate concrete 33

3.13 Drying process of substrate concrete 34

3.14 Cleaning surface of substrate 34

3.15 Concrete after overlay process 35

3.16 Curing process of bonding concrete 37

3.17 Concrete compressive machine 38

Page 9: PERPUSTAKAAN UMP III fl I

3.18 Universal tension/compressive machine 39

4.1 Compressive strength of no roughness due different testing 43

42 Compressive strength of low roughness due different testing 43

4.3 Compressive strength of high roughness due different testing 44

4.4 Compressive strength of different roughness (7 days) 48

4.5 Compressive strength of different roughness (14 days) 48

4.6 Compressive strength of different roughness (28 days) 49

4.7 Double failure of 7 days Splitting Prism test 52

4.8 Double failure of 7 days Direct Shear test 53

4.9 Concrete failure of 7 days Slant Shear test 54

4.10 Double failure of 14 days Splitting Prism test 55

4.11 Concrete failure of 14 days Splitting Prism test 56

4.12 Double failure of 14 days Direct shear test 57

4.13 Concrete failure of 14 days Direct shear test 58

4.14 Bond failure of 14 days Slant shear test 59

4.15 Double failure of 28 days Splitting Prism test 60

4.16 Bond failure of 28 days Splitting Prism test 61

4.17 Double failure of 28 days Direct shear test 62

4.18 Bond failure of 28 days Direct shear test 63

4.19 Bond failure of 28 days Slant shear test 64

xli

Page 10: PERPUSTAKAAN UMP III fl I

CHAPTER 1

INTRODUCTION

1.1 GENERAL

In the field of repair and strengthening of concrete structures, the need often

arises to place new concrete next to old, existing concrete. Examples of these applications

include highway structures where concrete overlays are used and repair of corrosion-

damaged concrete structures, where the deteriorated concrete must be replaced with new

concrete. Good bond strength between overlay and substrate is a key factor in

performance of concrete repairs. The bond strength mainly depends on adhesion in

interface, friction, aggregate interlock, and time-dependent factors. Each of these main

factors, in turn, depends on other variables. Adhesion to interface depends on bonding

agent, material compaction, cleanness and moisture content of repair surface, samples

age, and roughness of interface surface.

Concrete repairing mainly includes removing unsound concrete and replacing it

with repair or overlay materials. One of the key requirements for any kind of repair

system is to have adequate bond strength between the existing concrete substrate and

overlay throughout the service life. When a repair is performed, the differences in the

properties of two materials will affect bond strength and stress distribution. Of particular

relevance are differences in shrinkage, elastic modulus and thermal movement. The

1

repair system can be considered as three phase composite system which is substrate,

Page 11: PERPUSTAKAAN UMP III fl I

b

overlay and b6nd zone. Bond zone here refers to the interface and vicinity of bond plane.

The bond zone must capable of withstanding the stresses imposed on the system.

Different factors have effects on the bond strength and its integrity.

Roughness is usually assessed only qualitatively, by observing the substrate

surface and by classifying it from very smooth to very rough. It is usual to increase the

roughness of its surface with the purpose of improving the bond between both materials.

Surface treatments like wire-brushing, sandblasting, water jetting, and chipping are

usually adopted. Euro code 2 indicates that, for shear at the interface between concrete

cast at different times, "surfaces may be classified as very smooth, smooth, rough or

indented"

The quality assurance of bond strength requires test methods that can quantify

the bond strength as well as identify the failure mode. There have been numerous

investigations led to development of different test methods. The forces which are applied

in each test and the failure mode are important in order to choose the proper test. Tests

are defined both in laboratory and field. An interpretive study on test methods is

presented which classifies and compares the tests based on the applied force, failure mode

and practical importance of each test.

1.2 PROBLEM STATEMENTS

Repair and strengthening applications are routine tasks in building construction.

The transfer of internal stresses across the bond plane between new fresh concrete and

old concrete is a critical aspect in the design of such composite concrete elements. In

these applications, the bond between the old and new concrete usually presents a weak

link in the repaired structure. Poor bond may lead to improper and sometimes unsafe

section even if high strength concrete is utilized.

Concrete may be damaged due to many different reasons of which some of the

more important causes. Excessive water is basically one of the most common problems

that cause damages in concrete. It highly decreases the strength and the abrasion and

increases the shrinkage and creep. Placing the bars too close to the surfaces or corners,

Page 12: PERPUSTAKAAN UMP III fl I

lack of adequate contraction joints, slabs with insufficient expansion joints, dimensional

errors, finishing defects, improper compaction or curing and many other factors in design

and during construction, cause damages of concrete. Besides, corrosion of the

reinforcement can be dangerous for whole the structure as they have been designed to

carry forces. Corrosion can destroy the bonding between bars and concrete material so

the material cannot able to transfer the loads to the bars in case of corrosion. Lastly,

abrasion-erosion damage factor structure that transports water with silt, sand and rock are

faced with this problem especially in case that the water velocity is high or the structure

is on the slope.

1.3 OBJECTIVES OF THE STUDY.

The aim for this project is to study the effect of test methods on bond strength

between concrete substrate and repair material. Three test methods with cementitious

methods used were Slant Shear test, Splitting Prism test and a new direct shear named

Bi-Surface shear test and three types of surface roughness were studied. In order to do

so, the objectives of this study are:

i. To identify the effect of testing to concrete bonding strength.

ii. To determine the effect of surface roughness to the concrete bonding

strength.

iii. To observe the failure mode of samples.

1.4 SCOPE OF STUDY

This study focuses on evaluation of bond strength between repair material and

substrate at the interface. There is a need to compare different tests for measuring bond

strength and to establish a relationship among the values obtained from each test. There

are 27 samples were constructed and grouped into three types of roughness which are no

roughness, low roughness and high roughness to be tested into three types of experiment.

Page 13: PERPUSTAKAAN UMP III fl I

4

The dimension of the Splitting prism forms were 150x150x150 mm cubes. The

cubes is constructed into two parts as old substrate concrete and repair material with a

base size 75x1 50 mm and a height of 1 50mm. In the Bi-Surface shear method, the repair

material constitutes one third of the samples. Using 150 mm cube forms, prisms with a

base size of 100x150 mm and a height of 150 mm are cast as old or substrate concrete

then the repair materials are cast in prisms with a base of 1 50x50 mm and a height of 150

mm and are bonded to the concrete substrate. Slant Shear Test samples were

lOOxlOOx400 mm and it is cut at angle 60° to their cross sectional axis whereas the old

substrate designed with a base size of lOOxlOOmm and height 113.5mm as well as the

repaired material sampels. Figure 1.1 and Figure 1.2 show the cube dimension and prism

dimension respectively.

150mm

r/1 50 mm

150mm

Figure 1.1: Cube dimension

Page 14: PERPUSTAKAAN UMP III fl I

Figure 1.2: Prism dimension

The Splitting Test measures the bond under tension stress. The method was later

adopted as a standard test ASTM C496 and the tensile strength of concrete is regarded as

an indication of its tensile strength. The Slant Shear Test measures the bond strength

under a state of stress that combines shear and compression. It was standardized in ASTM

C882-99. Lastly, the Direct Shear tests measure the bond under shear stresses, and are

called direct shear methods. In most cases, the bond surface for a direct shear test is

actually subjected to shear stress and a small bending stress.

1.5 IMPORTANCE OF STUDY

The measured bond strength is greatly dependent on the test method. With the

proliferation of chemical bonding agents, the design engineers often faced with selecting

the bond strength of a particular product based on the data reported by the manufacturer.

Depending on the test method used, the reported bond strength may significantly

overestimate the true strength of the product for the desired applications. Therefore, there

is a need to compare different tests for measuring bond strength and to establish a

relationship among the values obtained from each test.

Page 15: PERPUSTAKAAN UMP III fl I

CHAPTER 2

LITERATURE REVIEW

2.1 INTRODUCTION

Concreting bonding is an important area particularly in construction using

prefabrication method namely precast and semi precast units. Precast and semi precast

concrete units are used widely in the construction industry because of advantages of labor

reduction, short construction duration and cost effectiveness. Many constructions have

failed due to the debonding that occurs in semi precast concrete slab. Abu-Tir et al.

(2000) and Bonaldo et al. (2005) stated that the bond performance between the old and

the new concrete plays an important role in the structural performance. Failing to bond

properly will cause shrinkage and finally crack that may promote the corrosion of steel

reinforcement due to the penetration of chloride ions, water and other hazardous

substances.

In this chapter, the effectiveness of different types of roughness in bonding the

new and the old concrete was studied. The experimental work included the method of

roughness the new and old concrete and also factor affecting the bond strength.

2.2 BOND STRENGTH

Beaupre (1999) mentioned that the bond strength is the adhesion between

overlay and substrate which can be the weakest link of the system. Good bond strength

is a key factor to have a monolithic system. Bond can be expressed by shear resistance or

tensile resistance. It is important to select the one which can better state the stresses

subjected to the structure in the field. The bond strength can be easily defined as

Page 16: PERPUSTAKAAN UMP III fl I

7

maximum force divided by the interface area, in the condition that failure occurs

completely at the interface. Bonaldo et a! (2005) stated that failure in the substrate

indicates that the bond strength is greater than the tensile strength of substrate and a

failure in the overlay indicates that the bond strength is greater than the tensile strength

of the overlay as referred in Figure 2.1.

(a) (b) (c)

Figure 2.1: Modes of failure (a) Concrete failure ,(b)Bond failure,

(c) Double failure

2.3 FACTORS AFFECTING BONDING STRENGTH

The bonding strength were affected by cleanliness and surface preparation of

the concrete surface. A bond must free from dust, oil, grease and other contaminants.

These have significant influence of the bond strength.

2.3.1 Surface preparation

In order to gain proper bond strength the surface must be prepared prior to

performing the overlay. In the repair works when the substrate is concrete before surface

preparation the deteriorated concrete must be removed since it may damage the new layer

and it does not have enough strength. It is also recommended when the substrate is rock,

to remove the layer of chemically or mechanically damaged rock before surface

preparation as in Figure 2.2.

Page 17: PERPUSTAKAAN UMP III fl I

8

Figure 2.2: Cleanliness surface of the sample

There are several methods to prepare the surface and it is quiet important to

choose the best way since it has a decisive influence on bond in the interface. Some

methods can only remove a thin layer of concrete, while others have the ability to remove

material to a significant depth as in Table 2.1. Silfwerbrand (1990) and Talbot eta! (1994)

stated that it is important to take into consideration that if the surface produced by a

vigorous method, i.e. hammering, the surface will be very rough but micro cracks will be

induced just beneath the prepared surface, making it weak.

Page 18: PERPUSTAKAAN UMP III fl I

Micro cracks reduce bond strength substantially and they have a detrimental

effect on the uppermost layer of the substrate. Micro cracks cause reduction in the

effective bond area. Also micro cracks develop due to the stress concentrated at their

tips. Knutson (1990) founded that distress like faulting, pumping and loss of support,

shattered slabs, transverse cracks, longitudinal cracks and joint deterioration needed to

be repaired by proper remedy before overlay placement.

Although mechanical methods i.e. hammers are likely to introduce micro

cracking, field tests however have shown that the bond strength can reach satisfactory

values if mechanical removal is followed by high pressure water cleaning. Based on

tests that have been done by Silfwerbrand (1990), water-jetting is one of the best

solutions both having the high roughness and not having micro cracks.

Page 19: PERPUSTAKAAN UMP III fl I

10

Table 2.1: Methods of concrete removal

Removal method Principle behaviour Advantages Disadvantages

Sand-blasting Blasting with sands No micro Not selective, cracking leaves considerable

sand.

Scrabbling Pneumatically driven No micro Not selective bits impaction cracking, no dust.

Shot blasting Blasting with steel No micro Not selective balls. cracking, no dust

Grinding Grinding with Removes uneven Dust development,

(planning) rotating lamella. parts. not selective.

Pneumatic (jack) Compressed-air- Simple and Micro cracking,

hammers operated chipping flexible use, large damages

(chipping) ones are effective, reinforcement, poor working

environment, slow production rate, not

selective.

Explosive blasting Controlled blasting Effective for large Difficult to limit to using small, densely removal volumes, solely damaged

spaced blasting concrete and safety, charges. not selective.

Water-jetting/ High pressure water Effective, Water handling,

hydro demolition jet from a unit with a selective, does not removal in frost movable nozzle damage degrees, costs for

reinforcement establishment

Page 20: PERPUSTAKAAN UMP III fl I

11

2.3.2 Surface roughness

The surface roughness is important to provide friction and aggregate interlock

but Silfwerbrand proved that roughness in its own does not have significant influent but

the method of surface preparation and the absence of micro cracks is more important as

in Silfwerbrand (1990). Within the first two days of casting, repairing surfaces were

roughened in one of three categories: no, low or high roughness. The low-roughness

category was obtained using a steel wire brush to remove slurry cement from external

surface of both fine and coarse aggregates. The estimated amplitude of roughness was 3-

4 mm; using a similar approach, the high-roughness category was roughened to an

amplitude of 7-8 mm.

No roughness Low roughness High roughness

(3-4 mm) (7-8 mm)

.-

-r

f-

;

Figure 2.3: Types of surface roughness

2.3.2.1 Interfacial transition zone (ITZ)

The modified volume is called interfacial transition zone (ITZ). Because of

"Wall Effect", which means inability of cement particles to pack efficiently around

embedment, the ITZ has a high porosity and reduction of unreacted cement near the

surface. Some other engineers have tended to objectively suggest that the ITZ is indeed

not the major influence on concrete properties. With respect to mechanical effects, Van

Page 21: PERPUSTAKAAN UMP III fl I

12

Mier and Vervuurt ,1999 concluded that the conventional physical model to treat the ITZ

as separated phase should be replaced.

2.3.2.2 Effect of surface roughness on bond strength

Knutson (1990) found that the bond strength between the old and new concrete

is affected by the surface texture and moisture conditions of existing concrete and

bonding agents. Milling and shot blasting are usually used to clean and roughen the

surface of the substrate. Several controversies still exist on the effects of bonding agents

and moisture condition of substrate.

By covering laboratory bond tests, experimental field projects, and survey of

projects in use, Felt (1956) found that the two main factors governing bond were: the

strength and integrity of the old base concrete, and the cleanness of old surface; a good

bond may be achieved without using a grout layer. However, he pointed out that the

chance of increasing bond strength can be improved by using grout and best bond could

be obtained with dry and grouted base concrete. By determined samples size, maximum

aggregate size of repair materials, types of repair materials, interface roughness and age

at loading as variables, Momayez (2004) pointed out that the bond strength was improved

with surface roughness, silica fume content, and age at testing.

2.3.3. Compaction and placement of the overlay

Compaction is an important factor for obtaining a dense and homogeneous

overlay as well as a good and even bond. Compaction helps the overlay fill and cover

cavities and voids at the surface which means to have more efficient contact area and

fewer caves. The other advantage is to have better and less permeable overlay which is

also helpful for durability of the bond. Silfwerbrand (1990) mentioned that on rough and

uneven surface, there is a risk for air pockets in the depressions of the surface.

Page 22: PERPUSTAKAAN UMP III fl I

Before Overlay (Substrate)

III

F ! -

After Overlay

13

Figure 2.4: Placement of new concrete

Page 23: PERPUSTAKAAN UMP III fl I

14

2.3.4 Overlay curing and temperature effect

Curing is the process of controlling the rate and extent of moisture loss from

concrete during cement hydration. Since the hydration of cement does take time, days

and even weeks curing must be undertaken for a reasonable period of time if the concrete

is to achieve its potential strength and durability. Concrete strength depends on the

growth of crystals within the matrix of the concrete. These crystals grow from a reaction

between Portland cement and water, a reaction known as hydration. Kosmatka et al

(2002) stated effect of curing duration on compressive strength development is presented

in Figure 2.5.

Figure 2.5: Effect of curing duration on compressive strength development

Source: (Kosmatka et a!, 2002).

Page 24: PERPUSTAKAAN UMP III fl I

15

2.4 SECONDARY FACTORS INFLUENCING BOND

2.4.1 Pre wetting

The moisture condition has influence on bonding strength and failure mode. The

moisture condition of both the surface and the substrate is important. If the surface and

substrate are too dry, part of mixing water of the top layer will be absorbed by the

substrate before any components in a cement paste are formed. This causes a risk for

heterogeneous and porous zone close to the bond surface. Referring to Austin.et a!, 1995,

if the surface and substrate are too wet and saturated, the capillary pores in the substrate

are filled and therefore the excess water will rise up to the surface and it make a layer

with high water cement ratio.

2.4.2 Traffic vibrations

Of course the heavy vibration and traffic can be harmful for newly cast overlay.

Although the vertical vibrations due to the traffic in some structures such as bridge decks

or concrete pavements can be useful, but in tunnel blasting the vibrations do not play a

positive role since vibrations which come from explosions in the vicinity are normally

heavy and the waves are both vertical and horizontal. So that they cause shear forces in

the interface make the early age bond weak as shown in Silfwerbrand (1990).

2.4.3 Environmental factors

Environmental factors such as temperature, temperature changes, thawing and

freezing, humidity can influence the bond durability. Medina et al (2007) found that

temperature had a significant effect on cracking and debonding behavior and tensile

debonding failure is shown to be a dominant failure mode at early ages between old

concrete pavement and new overlay. Both temperature and moisture gradients through

the depth of pavements cause curling and warping. An aggressive environment indirectly

has a negative effect on bond strength. It makes difficulties especially for curing and later

during the service time.