Phase 2B In this slide show: Jackson Plaza Gumby Lamp Fixtures Installation May 5, 2012. Cast iron lamp posts were installed along the Jackson Plaza granite balustrade . . The 527 lbs lamp post was lifted by a crane to its location. . - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

Phase 2BIn this slide show:

Jackson Plaza Gumby Lamp Fixtures Installation

May 5, 2012

Page 2: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

Cast iron lamp posts were installed along the Jackson Plaza granite balustrade.

Page 3: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

The 527 lbs lamp post was lifted by a crane to its location.

Page 4: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

Each lamp post takes 4-5 hours to install.

Page 5: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

When complete with the spherical bulb housing the lamp will reach a height of 6.5 feet. The electrician next to the lamp post in the photo is 5’11” tall.

Page 6: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

All electrical connection are moisture sealed with solid filled epoxy for longevity.

Page 7: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

The lamp posts are nicknamed “gumbies”.

Page 8: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

Efficient and long lasting LED modules are used in each glass spherical bulb.

Page 9: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

Brick pavers have been installed on the west side walkway.

Page 10: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

Concrete foundation was cast for future planters .

Page 11: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

Baggage room and ticketing carousels are being installed.

Page 12: Phase  2B In this slide show:  Jackson Plaza  Gumby Lamp Fixtures Installation  May  5,  2012

Demolition in the old electrical room