pipelines installation

Upload: noor-azreen

Post on 14-Apr-2018

232 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Pipelines Installation

    1/24

    PIPELINEMuhammad kamilMuhammad najmi

    Noor azreen

  • 7/30/2019 Pipelines Installation

    2/24

    PIPELINEDESIGN

    SIZING

    WALLTHICKNESS

    DESIGNPRESSURE

    MATERIAL

  • 7/30/2019 Pipelines Installation

    3/24

    PIPE SIZE

    Calculate the head loss- When the fluid flow through the pipelinethere is a resistance to the flow due to thefriction force and the pressure is formcause the energy loss.

    Design flow rate

    Diameter of pipe is from 4 to 48 inches

  • 7/30/2019 Pipelines Installation

    4/24

    MATERIAL

    Type of material common used are steel,ductile iron, reinforced concrete and

    fiberglass Mechanical resistance consideration

  • 7/30/2019 Pipelines Installation

    5/24

    WALL THICKNESS

    Hoop stress

    Hoop stress must be less than the

    maximum allowable stress

  • 7/30/2019 Pipelines Installation

    6/24

    DESIGN PRESSURE

    Buried pressure pipe installation quite similarthe design method for gravity pipeinstallations

    For internal pressure: Hydrostatic pressureand surge pressure

    For low pressure:- nominal diameter= 114-630mm

    - internal pressure= 545kpa or less High pressure:

    - nominal pressure= 21-710mm- internal pressure= 550-2170kpa

  • 7/30/2019 Pipelines Installation

    7/24

    PIPELINE FAILURE

    Cause by natural disaster, lessmaintenance or human error.

    To avoid this failure:

    - modern welded steel pipe with buttelectric arc welded joints

    - Construct parallel pipelines inindependent alignments

  • 7/30/2019 Pipelines Installation

    8/24

    Balboa Neighborhood Burned by Exploding Gas Line inNorthridge Earthquake (left); Fire ball that Burned the

    Neighborhood.

  • 7/30/2019 Pipelines Installation

    9/24

    Crater Resulting from Williams 26inch

    Pipeline Explosion in Washington State,

  • 7/30/2019 Pipelines Installation

    10/24

    Wrinkled Pipeline

    Failed in

    Compression

  • 7/30/2019 Pipelines Installation

    11/24

    PIPELINES

    INSTALLATION

    ON-shore Pipeline installation

    Offshore pipeline

  • 7/30/2019 Pipelines Installation

    12/24

    On-Shore installation

    Pre construction of pipelines

    1) Acquisition/Requisition of LandAcquisition- permanent use of land for pipeline activitiesRequisition- temporary use of land for pipeline activities

    2) Submission of proposal

    Acquire permission from government to access the land

  • 7/30/2019 Pipelines Installation

    13/24

    On-Shore installation

    Construction of pipelines1) Cleaning the ROW(Rights Of Way)

    ROW rights to make a way over a piece of land for

    pipeline construction. Heavy equipments are used to clean up the ROW

    Bulldozer- to clean Excavator- used for SideBoom- lift pipe

    the ROW trenching and pipe lifting during welding activities

  • 7/30/2019 Pipelines Installation

    14/24

    On-Shore installation

    2) Stringing the Pipelinethe process of sorting the pipeline in a ROW so that the

    pipeline can be welded together

    Lift Boom are used to lift the pipe for welding process.

  • 7/30/2019 Pipelines Installation

    15/24

    On-Shore installation

    3) Bending and Welding Welding machine is used to join the pipe together

    3 or more layer of welding maybe necessary depends onthe pipe thickness

    Bending machine is used to slightly bend the pipelinesespecially when the pipes encounter changes in routeand topography.

  • 7/30/2019 Pipelines Installation

    16/24

    On-Shore installation

    4) Coating the pipelines Coating of pipe is mainly aimed to prevent any water and

    moisture from directly contact with the pipelines and causecorrosion to the pipes.

    Generally, pipeline are already coated before transferringto ROW.

  • 7/30/2019 Pipelines Installation

    17/24

    On-Shore installation

    5) Roads and railway crossing

    It is not economical to deviate pathway of pipelines if theroute encounter barrier such as the railway and roads.

    Thus engineer implies THRUST BORING METHOD where ahole is drilled underway without disurbing the roads

  • 7/30/2019 Pipelines Installation

    18/24

    On-Shore installation

    6) Set On Weight

    Once the pipeline lies on the land, weight is installed over

    the pipeline to provide a secure fit of the pipe.

    In other saying, a concrete is poured onto the pipeline to

    make it stable

  • 7/30/2019 Pipelines Installation

    19/24

    On-Shore installation

    7) Testing the Pipelines

    Pig Test- To clean internal rust inside pipe and dry theinternal surface of the pipe.

    Hydro test should be 1.5 times the design pressure ofthe pipes.

    - watch for any defects in the pipe.

  • 7/30/2019 Pipelines Installation

    20/24

    Off-Shore Pipelines Installation

    Construction of pipelines

    1) Towing the pipelines. Tow-in pipeline installation

    Basically, pipeline is suspended on water by using

    buoyancy modules, towed by boat and pipeline is settledon sea bed.

    there are 4 types of Tow-in installation.

    - Surface Tow

    - Mid- Depth Tow

    - Off- Bottom Tow

    - Bottom Tow

  • 7/30/2019 Pipelines Installation

    21/24

    Off-Shore Pipelines Installation

    S-Lay Pipeline InstallationPipeline is welded, part off the boat as the boat moves

    forward and drawn down the water.

    Stringer is used to support the pipe as it moves into water.

  • 7/30/2019 Pipelines Installation

    22/24

    Off-Shore Pipelines Installation

    J-Lay InstallationThis installation used tall tower instead of stringer to

    reduce tension or stress on the pipeline.

    Thus overcome problems with S-lay installation associatedwith the stress on the pipeline.

  • 7/30/2019 Pipelines Installation

    23/24

    Off-Shore Pipelines Installation

    2) Welding the Pipelines

    The pipeline usually will be welded on the build-in

    welding station and crane on the Barge carrying thepipeline such as S-Lay and J-Lay Barge.

    The pipeline is passed through 3 or more weldingstation and X-ray to detect any defects on the pipeline

  • 7/30/2019 Pipelines Installation

    24/24

    Off-Shore Pipelines Installation

    4) Anchoring the pipelineThe pipeline that lies on the seabed will then be

    anchored and pile down to the seabed to fix the pipeline sothat it will remains in places.