Project Upscale Plant Feed Grade.TRANSCRIPT
![Page 1: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/1.jpg)
Project :
Project :
Upscale Probiont M1
Upscale Probiont M1
PT. Nugen Bioscience Indonesia
PT. Nugen Bioscience Indonesia
Human resources
technology material
equipment
processes
information
ConsultantManagement
Plant Lay Out DesignPlant Lay Out Design
www.rifloconsulting.comwww.rifloconsulting.com
![Page 2: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/2.jpg)
ABSTRAK
1. Rancangan Ruangan berdasarkan kebutuhan dan tingkat aseptic setiap proses
2. Optimal pemanfaatan ruangan dengan ketersediaan area secara efektif dan efisien untuk memenuhi target produksi 20 Ton/ Month dan kemungkinan peningkatan hingga 35 Ton/ Month
Riflo ConsultingIndustrial Management Consulting Expert
![Page 3: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/3.jpg)
Lay Out Pabrik
![Page 4: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/4.jpg)
Lay Out Ruangan
Expand Area INCUBATION
![Page 5: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/5.jpg)
Alur Masuk Karyawan
Alur karyawan ke area Hitam
Alur Karyawan ke area Abu-abu
Alur Karyawan ke area Putih
Legend
Black Area
Grey Area
Green Area
![Page 6: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/6.jpg)
Material & Process Flow
Material Receiving
Alur Bahan baku Media
Alur Bahan Baku Pengemas
Alur Process Produksi
Legend
Alur Pengiriman Finish Goods
![Page 7: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/7.jpg)
Flow Process “Kereta Tabung”
Legend
Kereta Setelah Dicuci
Kereta Berisi Tabung Plastik didorong ke area Inkubasi
Produksi Panen, Kereta di dorong ke area transfer untuk “Filling Process”
Kereta Setelah selesai Transfer didorong ke area washing
![Page 8: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/8.jpg)
NERACA MASS BALANCE
Note:1 day = 1 shift = 7 hour1 month = 22 days1 Kereta = 160 Liter
Plant Capacity = 28.160 Ltr/ Month
![Page 9: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/9.jpg)
Dimensi Ruangan & Kapasitas AC
Note:AC 1,5 PK = 5 Unit
AC 1 PK = 5 Unit
![Page 10: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/10.jpg)
Prakiraan Investasi
Plant Capacity = 28.160 Ltr/ Month
Investment 780.000.000 – 1.000.000.000
![Page 11: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/11.jpg)
Kereta Tabung
![Page 12: Plant Lay Out Design](https://reader033.vdocuments.net/reader033/viewer/2022061207/5485263ab4af9f640d8b4d3c/html5/thumbnails/12.jpg)
Upscale Probiont M1Upscale Probiont M1PT. Nugen Bioscience IndonesiaPT. Nugen Bioscience Indonesia
RIFLO GUNAWAN MITRA SOLUSI
Head Office:Sektor XIV/6 Blok ID. 7
Nusa Loka – BSDSerpong, Tangerang
Phone: (021) 92867816
Branch Office:Complex Riau Business Center
3rd Floor Block C-32Pekanbaru
Phone/Fax: (0761) 864089HP: 081 562 562 29