  • Xstrata Technology

    10 th Floor, 700 West Pender St, Vancouver, BC, V6C 1G8

    Telephone: +1 604-699-6400 Facsimile: +1 604-689-4719 www.xstratatech.com

    XSTRATA TECHNOLOGY

    EQUIPMENT SPECIFICATION PMC06-XT-SP0012

    LAS BAMBAS REGRIND PLANT - ISAMILL PLATFORM STEELWORK, WALKWAYS & HANDRAILS

    Revision Date Revised

    Description/Comment Signatures

    Originator Checked Apprvd

    A 5-May-2012 Issued for Enquiry K. Kaminski 0 26/06/2012 Issued for Construction K. Kaminski C Hanna D Prescott

  • EQUIPMENT SPECIFICATION ANTAPACCAY REGRIND PLANT - ISAMILL PLATFORM

    STEELWORK, WALKWAYS & HANDRAILS

    Specification No.

    PMC03-XT-SP0012

    Rev No. 0

    Xstrata Technology

    PMC03-XT-SP0012 26 June 12 Page 2 of 6

    TABLE OF CONTENTS

    1.0 SCOPE OF SPECIFICATION ............................................................................................................... 3

    2.0 GENERAL REQUIREMENTS .............................................................................................................. 3

    2.1 GENERAL ............................................................................................................................................... 3 2.2 COMPLETENESS OF SUPPLY ........................................................................................................................ 3

    3.0 XSTRATA SPECIFICATIONS AND SPECIAL INSTRUCTIONS .............................................................. 3

    3.1 PMA-XT-SP0009 REV0 - QUALITY ASSURANCE REQUIREMENTS FOR PROCURED ITEMS ........................................ 3 3.2 PMA-XT-SP0010 REV0 - PACKING AND LOADING REQUIREMENTS .................................................................. 4 3.3 PMA-XT-SP0012 REV0 - SURFACE PREPARATION AND PROTECTIVE COATING REQUIREMENTS .............................. 4 3.4 PMA-XT-SP0013 REV2 - APPROVED PROTECTIVE COATING SYSTEMS .............................................................. 4 3.5 PMA-XT-0-000-6-0003 REV1 - GENERAL FABRICATION NOTES .................................................................... 5

    3.5.1 Structural Steelwork...................................................................................................................................... 5 3.5.2 Shop Structural Details ................................................................................................................................. 5

    3.6 PMA-XT-SP0025 REV 2 EQUIPMENT TAGGING................................................................................. ......... 5

  • EQUIPMENT SPECIFICATION ANTAPACCAY REGRIND PLANT - ISAMILL PLATFORM

    STEELWORK, WALKWAYS & HANDRAILS

    Specification No.

    PMC03-XT-SP0012

    Rev No.

    A

    Xstrata Technology

    PMC03-XT-SP0012 5-May-2012 Page 3 of 6

    1.0 SCOPE OF SPECIFICATION

    This specification sets out the minimum requirements for the supply, detailed shop drawings, fabrication and shop assembly where required, application of protective coatings, packing and loading of the Platform Structure for the Las Bambas Regrind Plant.

    2.0 GENERAL REQUIREMENTS

    2.1 General

    The Fabricator shall consider the specified performance requirements for this structure and where no fabrication method has been specified, use their most effective fabrication methods to construct this structure.

    2.2 Completeness of Supply

    All members shall be supplied complete and operational except as specifically excluded, and shall include all necessary accessories and the incorporation of all miscellaneous material, minor parts and other such items, whether or not the items are specified, where it is clearly the intention that they should be supplied or where they are obviously required and necessary to complete and commission the equipment.

    3.0 XSTRATA SPECIFICATIONS AND SPECIAL INSTRUCTIONS

    Refer to the listing below for the specifications that shall be used for the construction of the Platform Structure the bullet point items shown below each specification indicate where there are deviations from the standard specification or where additional items are required for this particular piece of equipment.

    Should any components of the fabrication not be covered by the XT specifications listed below, then, these components should, as a minimum, comply with the latest issues, addenda and supplements of the relevant Peruvian Standards, Regulations or Statutory Codes.

    3.1 Quality Assurance Requirements for Procured Items - PMA-XT-SP0009 Rev 0

    Quality plan Level B Partial Traceability shall be used.

    The following are additional documents required for Quality Plan Level B traceability:

    1. Manufacturers certificates of compliance with the relevant standards shall be supplied for all steel used in the fabrication of the structural members. Test certificates shall be supplied as required in PMA-XT-SP0009. Any steel for which compliance certificates cannot be supplied will be liable for rejection.

    2. Welding Procedure Qualification Records

    3. Dimensional Verification Records

    XT and the End user maintain the right to perform quality inspection visits at the manufacturers facilities at any reasonable time.

    All quality related documentation must be made available to XT for review when requested.

  • EQUIPMENT SPECIFICATION ANTAPACCAY REGRIND PLANT - ISAMILL PLATFORM

    STEELWORK, WALKWAYS & HANDRAILS

    Specification No.

    PMC03-XT-SP0012

    Rev No. 0

    Xstrata Technology

    PMC03-XT-SP0012 26 June 12 Page 4 of 6

    The manufacturer shall provide XT with 6 working days advance notice before the occurrence of every Hold point (H) and Witness point (W).

    The manufacturer shall have a current, audited Quality Control and Assurance program meeting the requirements of ISO9000 series and/or ASME quality program specifications.

    Welding shop and operators, equipment, materials and methods employed on the Work are certified in accordance with AWS 1.1. Certification of such qualification must be made available 2 weeks prior to commencing work. Where welding is required using special techniques, ensure certification is to include the welding of such metals and using such techniques.

    Weld inspectors must be AWS, or ISO certified.

    The manufacturer shall submit the following, within one week of contract award, for XT review and approval:

    o ITPs, weld procedures and welder qualification records. o Name of the person responsible for the inspection and testing. o Name of the person responsible for the implementation of the manufacturers

    Quality Assurance program.

    o Qualification papers for all welding and non destructive examination personnel. 3.2 PMA-XT-SP0010 Rev 0 - Packing and Loading Requirements

    As materials are to be painted, care must be taken, during the packing, so that the transportation, offloading and storage, do not damage the protective coatings.

    The Handrails, Kickboards and Stanchions are to be painted after hot dipped galvanizing and must be packed with carpet , conveyor belting or similar to minimize damage.

    The Contractor is to prepare a detailed packing list, detailing all the equipment being shipped.

    The required Craneage, Forklifts, plus Labour including Riggers and Dogmen etc to load all this equipment is to be supplied by the Contractor.

    Transport will be provided by others and load securing and restraints, once equipment is loaded will be the responsibility of others.

    3.3 PMA-XT-SP0012 Rev 0 - Surface Preparation And Protective Coating Requirements

    No deviations to this specification.

    3.4 PMA-XT-SP0013 Rev 2 - Approved Protective Coating Systems

    All grating, handrails, kickboards and stanchions must be galvanized according to ASTM A123-09.

    After galvanizing, all handrails, kickboards, and stanchions shall be painted to System 8, AS2700-Y14 Golden Yellow (RAL1004-Golden Yellow).

    All structural steel is to be painted according to System 16, AS2700-N52 Mid Grey (RAL7005- Mouse Grey).

  • EQUIPMENT SPECIFICATION ANTAPACCAY REGRIND PLANT - ISAMILL PLATFORM

    STEELWORK, WALKWAYS & HANDRAILS

    Specification No.

    PMC03-XT-SP0012

    Rev No. 0

    Xstrata Technology

    PMC03-XT-SP0012 26 June 12 Page 5 of 6

    3.5 General Fabrication Notes - PMA-XT-0-000-6-0003

    3.5.1 Structural Steelwork

    The notes on drawing no.: 11-VA-0130-S-0100 supersedes the relevant section of PMA-XT-0-000-6-0003 (General Fabrication Notes Canada).

    The project structural notes shall be used for all handrail, grating cutout and stair tread detailing. These structural notes are given on drawings number: 25580-220-S0-000-00002, 25580-220-S0-000-00003, 25580-220-S0-000-00004, 25580-220-S0-000-00005 and 25580-220-S0-000-00014.

    All steel shapes, plates and bars used in fabricating this structure must be Plain Carbon Steel to ASTM A572, Grade 50.

    Fabrication will be done in accordance with AISC 303-05 Code of Standard Practice for Steel Buildings and Bridges, and AISC 360-05 Specification for Structural Steel Buildings.

    General Welding requirements deviate as follows:

    Welding shall be done to AWS D1.1.

    All Welds are to be tested in accordance with AWS D1.1 to the following extent:

    o All welding shall be subject to 100% close visual inspection and 10%radiographic testing. The selection of the joints for radiographic testing shall be done by XT. Should the inspections reveal unacceptable weld defects, then the contractor shall be responsible for all the necessary rework, including retesting.

    Acceptance criteria will be in accordance with AWS D1.1.

    All Lifting Lugs shall be welded by means of full penetration butt welds. In addition to the visual inspection of the welds, these butt welds must be tested to the following extent:

    Additional 100% ultrasonic testing.

    Acceptance criteria will be in accordance with AWS D1.1

    3.5.2 Shop Structural Details

    Shop Structural Detail Drawings shall provide all cleats and holes for fixing structural members whether shown or not on the Design Drawings.

    3.6 PMA-XT-SP0025 Rev 2 Equipment Tagging

    Each structural member shall be allocated a unique mark number during detailing of structural members, which shall be used in all related schedules and documents. These mark numbers shall be arranged in a logical sequence to assist identification and location of members.

    The mark for each member shall be stamped in alphanumeric characters 3/8 high.

    Small items such as shims shall be securely wired together and tagged. The tag shall bear all the necessary marking information.

    Beams shall be marked on the web at the north-west end.

    Columns shall be marked on the north face, approximately 300mm above the base plate.

  • EQUIPMENT SPECIFICATION ANTAPACCAY REGRIND PLANT - ISAMILL PLATFORM

    STEELWORK, WALKWAYS & HANDRAILS

    Specification No.

    PMC03-XT-SP0012

    Rev No. 0

    Xstrata Technology

    PMC03-XT-SP0012 26 June 12 Page 6 of 6

    Horizontal bracing shall be marked on the north end.

    Vertical bracing shall be marked at the top.

    1.0 SCOPE OF SPECIFICATION2.0 General Requirements2.1 General2.2 Completeness of Supply

    3.0 XSTRATA SPECIFICATIONS AND SPECIAL INSTRUCTIONS3.1 Quality Assurance Requirements for Procured Items - PMA-XT-SP0009 Rev 03.2 PMA-XT-SP0010 Rev 0 - Packing and Loading Requirements3.3 PMA-XT-SP0012 Rev 0 - Surface Preparation And Protective Coating Requirements3.4 PMA-XT-SP0013 Rev 2 - Approved Protective Coating Systems3.5 General Fabrication Notes - PMA-XT-0-000-6-0003

    1233.5.1 Structural Steelwork3.5.2 Shop Structural Details3.6 PMA-XT-SP0025 Rev 2 Equipment Tagging

    456