pmp cross-cutting skills have been updated in the pmp exam ......pmp cross-cutting skills have been...

56
IILCERT5 Project Time Management The Project Management Cer8ficate Program 1 ©2014 Interna8onal Ins8tute for Learning, Inc. PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content Outline - June 2015 can be found under the Resources Tab). Learn about why the PMP exam is changing in 2016. Download the new Exam Content Outline to study cross-cutting skills here: http://www.brainshark.com/pmiorg/2015PMPExamChange

Upload: others

Post on 12-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

IIL-­‐CERT5  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

1  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content Outline - June 2015 can be found under the Resources Tab).

Learn about why the PMP exam is changing in 2016.

Download the new Exam Content Outline to study cross-cutting skills here:http://www.brainshark.com/pmiorg/2015PMPExamChange

Page 2: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

IIL-­‐CERT5  

Project  Time  Management  

2  

The  Project  Management  Cer8ficate  Program  

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 3: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes:

The  Project  Management  Cer8ficate  Program   Project  Time  Management  

3  IIL-­‐CERT5  

Page 4: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: Review  these  learning  objec8ves  carefully.      

The  learning  content  contained  within  this  module  is  based  on  these  learning  objec8ves.  

At  the  end  of  this  module  or  the  end  of  the  course,  you  should  be  able  to  answer  quiz  or  test  ques8ons  related  to  these  learning  objec8ves.    

If  you  are  par8cipa8ng  in  this  course  for  cer8fica8on,  you  will  be  beOer  prepared  to  pass  a  cer8fica8on  exam  by  recalling  these  learning  objec8ves.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   4  

Page 5: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: Project  Time  Management  includes  the  processes  required  to  manage  the  8mely  comple8on  of  the  project.  

PMBOK®  Guide  –  FiSh  Edi8on,  Glossary  

The  seven  processes  of  Project  Time  Management  typically  begin  aSer  the  project  team  has  ini8ated  the  project  planning  effort  and  the  scope  has  been  reasonably  developed.  The  Project  Time  Management  processes  add  the  element  of  how  8me  will  be  managed  to  the  project  management  plan.  It  also  describes  how  the  schedule  will  be  developed,  maintained  and  controlled.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   5  

Page 6: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiSh  Edi8on  describes  the  key  benefit  of  this  process  as  “providing  guidance  on  how  the  schedule  will  be  managed.”  

PMBOK®  Guide  –  FiSh  Edi8on,  p.  145  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   6  

Page 7: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiSh  Edi8on  defines  the  following  for  this  first  Project  Time  Management  process:  

Inputs  

•  Project  management  plan  •  Project  charter  

•  Enterprise  environmental  factors  

•  Organiza8onal  process  assets  Tools  &  Techniques  

•  Expert  judgment  

•  Analy8cal  techniques  •  Mee8ngs  

Outputs  

•  Schedule  management  plan    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   7  

Page 8: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  project  management  plan  feeds  input  into  the  8me  management  process  such  as  es8ma8ng  dura8ons  and  resources,  as  well  as  how  risks  will  be  managed  and  required  reports.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   8  

Page 9: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes:

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   9  

Page 10: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: Rules  of  performance  measurement  include:  

•  Which  percentage  complete  to  use?  •  What  control  accounts  to  roll  data  into?  

•  What  earned  value  measurement  techniques  to  use?  

•  What  tolerance  intervals  should  be  used?    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   10  

Page 11: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

The  PMBOK®  Guide  –  FiSh  Edi8on  describes  the  key  benefit  of  this  process  as  “breaking  down  work  packages  into  ac8vi8es.”  

PMBOK®  Guide  –  FiSh  Edi8on,  p.  149  

There  is  oSen  confusion  between  ac8vi8es  and  work  packages.  To  clarify,  work  packages  are  the  lowest  level  of  the  WBS.  Once  you  move  the  WBS  into  a  schedule,  they  may  further  be  broken  down  into  ac8vi8es.  Whether  work  packages  or  ac8vi8es  are  the  lowest  level  of  the  schedule,  this  is  the  level  at  which  es8ma8ng  takes  place.  Ac8vi8es  represent  the  work  of  the  project.  

Many  8mes,  soSware  such  as  MicrosoS®  Project,  Primavera  and  Artemis  (just  to  name  a  few)  are  used  to  collect  the  ac8vity  list,  es8mates,  dependencies  and  resources.  These  scheduling  ar8facts  are  later  developed  into  a  model  of  the  project.  Defining  the  ac8vi8es  is  the  first  step  in  working  with  project  schedules  as  defined  in  the  ac8on  steps  below.  

Ac8on  steps:  

•  Setup  the  scheduling  tool’s  op8ons  

•  Enter  Ac8vi8es  and  Enter  Dependencies  •  Enter  Es8mates  

•  Enter  and  Assign  Resources  

•  Enter  Deadlines/Constraints  •  Level  and  op8mize  (schedule  compression)  to  hit  the  deadlines/constraints  

•  Gain  Agreement  on  the  Schedule  •  Baseline  Schedule  

•  Enter  Actual  informa8on  on  start  and  finish  dates  and  dura8ons  

•  Report  variances  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   11  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 12: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiSh  Edi8on  defines  the  following  for  the  second  Project  Time  Management  process:  

Inputs  

•  Schedule  management  plan  •  Scope  baseline  

•  Enterprise  environmental  factors  

•  Organiza8onal  process  assets  Tools  &  Techniques  

•  Decomposi8on  

•  Rolling  wave  planning  •  Expert  judgment  

Outputs  

•  Ac8vity  list  •  Ac8vity  aOributes  

•  Milestone  list    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   12  

Page 13: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes:

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   13  

Page 14: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: A  prac8cal  considera8on  in  decomposi8on  to  the  ac8vity  level  is  to  determine  the  appropriate  ac8vity  list.  It  must  be  defined  in  sufficient  detail  to  assign  ac8vi8es  to  resources  that  will  perform  the  work,  as  well  as  enable  the  project  management  team  to  control  the  project,  during  execu8on.    

Ac8vity  aOributes  extend  the  descrip8on  of  the  ac8vity  by  iden8fying  the  mul8ple  components  associated  with  each  ac8vity,  which  may  include,  but  are  not  limited  to:  

•   Ac8vity  ID  •   WBS  ID  

•  Ac8vity  name  

•  Ac8vity  codes  •  Ac8vity  descrip8on  

•  Ac8vity  predecessor  and  successor  ac8vi8es,  logical  rela8onships,  leads  and  lags  

•  Ac8vity  resource  requirements  

•  Ac8vity  schedule  dates  

•  Ac8vity  constraints  and  assump8ons  Adapted  from:  PMBOK®  Guide  –  FiSh  Edi8on,    

p.  153  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   14  

Page 15: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  ac8vity  list  should  include  enough  detail  that  the  performers  can  successfully  complete  the  work  of  the  project.  It  should  also  be  at  a  level  that  es8ma8ng  resources  and  dura8ons  can  take  place.  

Ac8vity  aOributes  include  a  descrip8on  of  skills  required,  work  es8mates,  dependencies  and  other  ar8facts  to  help  the  performer  understand  the  work  that  needs  to  be  done.  

Milestones  represent  significant  events  in  the  life  of  a  project.  Typically  they  are  markers  that  signify  repor8ng  points,  beginning  and  ending  of  units  of  work  and  are  a  defined  moment  in  8me  that  requires  no  work  and  takes  no  dura8on.  Frequently  milestones  are  used  to  present  a  high  level  picture  of  the  projects  progression.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   15  

Page 16: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

The  PMBOK®  Guide  –  FiSh  Edi8on  describes  the  key  benefit  of  this  process  as  “defining  the  logical  sequence  of  work.”  

PMBOK®  Guide  –  FiSh  Edi8on,  p.  153  

In  building  the  logic  of  the  scheduling  model,  place  one  milestone  at  the  beginning  (represen8ng  the  start  of  the  project)  and  one  milestone  at  the  end  (represen8ng  the  end  of  the  project).  All  the  tasks  between  the  beginning  and  ending  milestone  should  be  connected  with  logical  dependencies.  This  creates  a  complete  network.  Without  a  complete  network  of  dependencies,  it  makes  it  very  difficult  to  understand  the  logic  of  the  model  or  to  trace  the  cri8cal  path.  If  the  scheduler  can’t  think  of  a  successor  to  a  task  it  should  be  connected  to  the  final  milestone.  

Different  scheduling  soSware  packages  have  specific  rules  on  dependencies.  OSen  in  these  packages,  if  a  complete  network  is  not  present  subsequent  tasks  will  not  respond  to  changes  in  preceding  tasks.  MicrosoS®  Project  doesn’t  require  a  single  star8ng  milestone.  It  allows  for  mul8ple  star8ng  points,  but  requires  a  single  ending  point.  Primavera  requests  a  single  milestone  at  the  beginning  and  ending  of  the  schedule.  

Logical  Dependencies  relate  to  the  predecessor  (driving)    and  successor  (driven)  tasks  that  determine  the  order  in  which  tasks  are  to  be  done.  Resource  dependencies  are  created  when  you  level  a  schedule  to  allow  for  resource  availabili8es.  

Some  tasks  may  not  require  logical  dependencies.  Examples  include  resource  dependencies,  recurring  tasks  that  are  short  in  dura8on  and  are  8me  dependent  rather  than  task  dependent  and  hammock  tasks  that  are  8ed  to  a  series  of  tasks  by  the  start  of  one  task  and  the  end  of  another  task.  

 

 

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   16  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 17: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiSh  Edi8on  defines  the  following  for  the  third  Project  Time  Management  process:  

Inputs  

•  Schedule  management  plan  •  Ac8vity  list  

•  Ac8vity  aOributes  

•  Milestone  list  •  Project  scope  statement  

•  Enterprise  environmental  factors  •  Organiza8onal  process  assets  

Tools  &  Techniques  

•  Precedence  diagramming  method  (PDM)  •  Dependency  determina8on  

•  Leads  and  lags  Outputs  

•  Project  schedule  network  diagrams  

•  Project  documents  updates    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   17  

Page 18: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: Once  the  method  and  the  tool  are  indicated  the  project  manager  will  combine  these  with  the  project  data  and  create  a  model  of  the  project.  The  end  product  of  this  effort  is  the  project  schedule.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   18  

Page 19: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: In  the  Precedence  Diagramming  Method  (PDM),  there  is  a  start  and  finish  point  with  all  ac8vi8es  taking  place  in  between.  The  nodes,  iden8fied  by  the  leOers  in  boxes,  are  the  ac8vi8es  to  be  performed.  

Precedence  diagramming  method  (PDM)  is  the  network  logic  diagram  method  of  choice  today.    PDM  is  used  in  the  Cri8cal  Path  Method  (CPM)  when  sequencing  ac8vi8es  to  diagram  a  project  schedule  network.    The  ac8vi8es  are  connected  by  arrows  that  show  the  logical  rela8onships  that  exist  between  the  ac8vi8es.  

This  diagramming  method  is  also  referred  to  as  Ac8vity-­‐On-­‐Node  (AON)  diagram.  It  can  u8lize  lags,  leads  and  all  four  types  of  dependencies  to  be  discussed  in  the  following  material.  

Historical  Note:  One  type  of  diagramming  method  rarely  used  today  is  called  the  Arrow  Diagramming  Method  (ADM),  also  known  as  Ac8vity-­‐On-­‐Arrow.    Here  the  ac8vi8es  are  listed  on  the  arrows  and  the  nodes  serve  as  connecters.  This  method  only  uses  the  Finish-­‐to-­‐Start  dependencies  (sequen8al  logic)  and  may  require  the  use  of  dummy  ac8vi8es  to  complete  the  logic.  

                         

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   19  

Page 20: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: PDM  includes  four  types  of  precedence  rela8onships  or  logical  dependencies.  In  PDM,  finish-­‐to-­‐start  (sequen8al  dependency)  is  the  most  commonly  used  type  of  precedence  rela8onship.    

Finish-­‐to-­‐start.  The  ini8a8on  of  the  successor  ac8vity  depends  on  the  comple8on  of  the  predecessor  ac8vity  

 Finish-­‐to-­‐finish.  The  comple8on  of  the  successor  ac8vity  depends  upon  the  comple8on  of  the  predecessor  ac8vity  

Start-­‐to-­‐start.    The  ini8a8on  of  the  successor  ac8vity  depends  upon  the  ini8a8on  of  the  predecessor  ac8vity  

Start-­‐to-­‐finish.    The  comple8on  of  the  successor  ac8vity  depends  upon  the  start  of  the  predecessor  ac8vity    

                         

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   20  

Page 21: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: In  addi8on  to  sequencing  ac8vi8es  using  logical  rela8onships,  three  types  of  dependencies  are  used  to  define  the  sequence  among  the  ac8vi8es:  

Mandatory  dependencies  are  referred  to  as  hard  logic,  and  oSen  involve  physical  limita8ons  that  makes  it  impossible  to  move  forward  without  comple8on  the  predecessor  ac8vity.    

Discre5onary  dependencies  are  referred  to  as  preferred  logic,  preferen8al  logic  or  soS  logic.  These  dependencies  should  be  fully  documented,  because  they  can  create  arbitrary  total  float  values  and  can  limit  scheduling  op8ons  that  may  be  posed  later  in  the  project  life  cycle.  

External  dependencies  represent  a  rela8onship  between  project  and  non-­‐project  ac8vi8es.    For  example,  delivery  of  compu8ng  hardware  from  an  external  source  is  an  external  dependency  for  a  soSware  developing  project’s  tes8ng  environment  configura8on  ac8vity.      

Internal  dependencies  show  the  rela8onships  between  ac8vi8es  within  the  project.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   21  

Page 22: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: Lag.  The  amount  of  8me  whereby  a  successor  ac8vity  is  required  to  be  delayed  with  respect  to  a  predecessor  ac8vity.  

Lead.  The  amount  of  8me  whereby  a  successor  ac8vity  can  be  advanced  with  respect  to  a  predecessor  ac8vity.  

PMBOK®  Guide  –  FiSh  Edi8on,  Glossary  

The  use  of  leads  and  lags  should  not  replace  schedule  logic;  however,  it  may  be  necessary  to  use  lead  or  lag  8me  between  ac8vi8es  to  support  a  realis8c  project  schedule.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   22  

Page 23: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: A  project  schedule  network  diagram  is  a  graphical  representa8on  of  the  logical  rela8onships  among  the  project  schedule  ac8vi8es.      

PMBOK®  Guide  –  FiSh  Edi8on,  Glossary  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   23  

Page 24: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiSh  Edi8on  describes  the  key  benefit  of  this  process  as  “iden8fying  the  resources  to  help  with  es8ma8ng  cost  and  dura8on.”  

PMBOK®  Guide  –  FiSh  Edi8on,  p.  160  

Es8mate  Ac8vity  Resources  process  is  necessary  for  the  Es8mate  Ac8vity  Dura8on  process  since  that  process  depends  on  es8mates  from  the  resources  that  are  going  to  do  the  work.  Resources  are  also  closely  related  to  the  process  Es8mate  Costs.    

Resource  es8mates  will  be  affected  by  the  availability  of  resources  to  do  the  work,  skill  level  required  and  cost.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   24  

Page 25: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiSh  Edi8on  defines  the  following  for  the  fourth  Project  Time  Management  process:  

Inputs  

•  Schedule  management  plan  •  Ac8vity  list  

•  Ac8vity  aOributes  

•  Resource  calendars  •  Risk  register  

•  Ac8vity  cost  es8mates  •  Enterprise  environmental  factors  

•  Organiza8onal  process  assets  Tools  &  Techniques  

•  Expert  judgment  

•  Alterna8ve  analysis  

•  Published  es8ma8ng  data  •  BoOom-­‐up  es8ma8ng  

•  Project  management  soSware  Outputs  

•  Ac8vity  resource  requirements  

•  Resource  breakdown  structure  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   25  

Page 26: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  amount  of  detail  and  the  level  of  specificity  of  the  resource  required  can  vary  by  applica8on  area.  Resource  requirements  should  include:  

•  The  basis  of  the  es8mate  for  each  resource  

•  The  type  of  resource  

•  The  quan88es  needed  

•  The  availability  or  when  the  resources  will  be  needed  

•  Working  assump8ons  

 

Snyder,  Cynthia  Stackpole,  A  User’s  Manual  to  the  PMBOK®  Guide,    John  Wiley  and  Sons  2013,  p.  67  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   26  

Page 27: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes:

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   27  

Page 28: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: These  tools  and  techniques  applied  to  the  inputs  are  intended  to  produce  ac8vity  resource  requirements,  a  resource  breakdown  structure  (RBS),  and  informa8on  required  to  update  project  documenta8on.    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   28  

Page 29: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: A  resource  breakdown  structure  is  similar  to  an  organiza8onal  chart,  except  the  rela8onships  diagrammed  reflect  the  repor8ng  of  stakeholders  on  a  project  as  opposed  to  formal  repor8ng  rela8onships.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   29  

Page 30: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiSh  Edi8on  describes  the  key  benefit  of  this  process  as  “providing  the  8me  each  ac8vity  will  take  to  complete.”  

PMBOK®  Guide  –  FiSh  Edi8on,  p.  165  

Dura8ons  are  arrived  at  by  determining  who  is  going  to  do  the  work,  how  much  effort  is  required,  the  cost  of  the  applied  resources  and  the  resource’s  availability.  Here  we  are  referring  to  all  types  of  resources  applied.  Human,  equipment,  material,  machinery,  facili8es,  cost,  etc.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   30  

Page 31: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

The  PMBOK®  Guide  –  FiSh  Edi8on  defines  the  following  for  the  fiSh  Project  Time  Management  process:  

Inputs  

•  Schedule  management  plan  •  Ac8vity  list  

•  Ac8vity  aOributes  

•  Ac8vity  resource  requirements  •  Resource  calendars  

•  Project  scope  statement  •  Risk  register  

•  Resource  breakdown  structure  

•  Enterprise  environmental  factors  •  Organiza8onal  process  assets  

Tools  &  Techniques  

•  Expert  judgment  •  Analogous  es8ma8ng  

•  Parametric  es8ma8ng  •  Three-­‐point  es8ma8ng  

•  Group  decision-­‐making  techniques  

•  Reserve  analysis  Outputs  

•  Ac8vity  dura8on  es8mates  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   31  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 32: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes:

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   32  

Page 33: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: There  is  a  difference  between  effort  and  dura8on.    Effort,  according  to  the  PMBOK®  Guide  –  FiSh  Edi8on,  is  the  number  of  labor  units  required  to  complete  a  schedule  ac8vity  or  work  breakdown  structure  component,  oSen  expressed  in  hours,  days,  or  weeks.      

Contrasted  with  effort,  dura8on  is  the  total  number  of  work  periods  (not  including  holidays  or  other  non-­‐working  periods)  required  to  complete  a  schedule  ac8vity  or  work  breakdown  structure  component.  It  is  usually  expressed  as  workdays  or  workweeks.  

PMBOK®  Guide  –  FiSh  Edi8on,  Glossary  

One  of  the  necessary  inputs  for  analysis  is  the  dura8on  es8mate  for  each  ac8vity.  Knowledge  of  when  an  ac8vity  can  start,  plus  its  dura8on,  allows  you  to  calculate  when  it  will  finish.  The  dura8on  es8mate  for  each  ac8vity  is  added  to  the  network  diagram.  This  allows  you  to  determine  the  start  and  finish  dates  for  each  ac8vity.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   33  

Page 34: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: Expert  judgment  can  provide  dura8on  es8mate  informa8on  or  recommended  maximum  ac8vity  dura8ons  from  similar  projects.  

Analogous  es8ma8ng  uses  parameters  such  as  dura8on,  budget,  size,  weight,  and  complexity  from  previous,  similar  projects  to  es8mate  the  dura8on  of  the  current  project.  

Parametric  es8ma8ng  uses  a  sta8s8cal  rela8onship  between  historical  data  and  other  variables  to  calculate  an  es8mate  for  ac8vity  parameters,  i.e.,  cost,  budget,  and  dura8on.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   34  

Page 35: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

Three-­‐Point  Es5mates  using  a  Beta  Distribu5on:  

Three(3)-­‐point  es8mates  were  first  used  by  the  government  and  a  contrac8ng  firm  for  a  defense  weapons  program.  The  technique  is  called  the  Program  Evalua8on  and  Review  Technique  (PERT).  The  resul8ng  es8mate  is  a  rough  sta8s8cal  representa8on  of  the  mean  of  a  beta  8me  distribu8on  weighted  towards  the  most  likely  informa8on  using  the  formula  shown.    Its  use  is  appropriate  when  there  is  uncertainty  (risk)  and  varia8on  associated  with  es8mates  for  the  ac8vity.  PERT  analysis  calculates  an  Expected  (tE)  ac8vity  dura8on  using  a  weighted  average  of  these  three  es8mates:  

tO  +  4tM  +  tP  

(tE)  =  -­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐  

6  

The  standard  devia8on  for  the  adapted  beta  distribu8on  formula  above  is:  

Tp  -­‐  tO  

(tσ)  =  -­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐  

6  

 

Three-­‐Point  Es5mates  using  a  Triangular  Distribu5on:  

This  calcula8on  needs  to  be  performed  using  the  three  es8mates  of  the  ac8vity  dura8on  and  is  used  in  planning  the  project  schedule.      

Triangular  es8ma8ng,  an  alterna8ve  three-­‐point  es8ma8ng,  averages  Op8mis8c,  Pessimis8c  and  Most  Like  es8mates.  Its  intent  is  to  provide  a  close  approxima8on  of  the  sta8s8cal  mean  of  a  triangular  distribu8on  instead  of  a  beta  distribu8on,  as  shown.          

+  ML  +  P  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   35  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 36: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: Dura8on  es8mates  do  not  include  lag  8me  that  is  needed  in  between  ac8vi8es.    

Ac8vity  Dura8on  es8mates  include  some  indica8on  of  range  of  possible  results.    For  example:  Developing  a  design  document  may  take  2  workweeks  +/-­‐  2  days;  or  there  is  a  low  probability,  10%,  that  the  ac8vity  will  take  more  than  2  workweeks.  

Project  documents  that  may  need  to  be  updated  include,  but  are  not  limited  to  the  ac8vity  aOributes  and  assump8ons  that  were  documented  when  engaged  in  the  ac8vity  to  es8mate  dura8ons.  

                       Adapted  from  Snyder,  Cynthia  Stackpole,  A  User’s  Manual  to  the  PMBOK®  Guide,    John  Wiley  

and  Sons  2013,  p.  72  

 

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   36  

Page 37: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes:

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   37  

Page 38: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

The  PMBOK®  Guide  –    FiSh  Edi8on  describes  the  key  benefit  of  this  process  as  “genera8ng  planned  dates  for  comple8ng  project  ac8vi8es.”  

PMBOK®  Guide  –  FiSh  Edi8on,  p.  172  

In  this  process,  all  the  major  outputs  from  the  previous  processes  are  used  to  assemble  a  project  schedule.  The  ini8al  schedule  can  be  based  on  dura8ons  and  dependencies.  This  is  the  best  es8mate  of  what  the  Subject  MaOer  Experts  (SMEs)  think  it  will  take  to  complete  the  project.  ASer  the  ini8al  schedule  is  developed  you  may  need  to  level  the  schedule  based  on  resources  constraints  and  availability.    OSen  8mes  you  will  need  to  use  schedule  compression  techniques  to  reduce  the  dura8on  to  meet  imposed  deadlines.  This  is  an  itera8ve  process.  

There  are  many  reasons  people  prepare  schedules  for  projects.  Four  of  the  most  compelling  are:  

•  To  sell  upper  management  on  an  idea.  To  do  so  may  require  a  high-­‐level  view  of  the  cost  and  8me  required.  

•  To  delegate.  When  you  have  a  detailed  WBS,  you  can  more  easily  assign  ac8vi8es  to  team  members.  

•  To  effec8vely  track  progress  by  entering  the  current  status  of  ac8vi8es  into  the  schedule.  •  To  forecast  the  project  end  date  and  total  cost.  

 

Adapted  from:  Dynamic  Scheduling  with  MicrosoA®  Project  2010    by  Rodolfo  Ambriz,  PMP,  PMI-­‐SP,    PMI-­‐RMP,  MCTS,  MCITP  and  John  White,  MA,  PMP,  MCT,  MCP,  MCTS,  MCITP  

 

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   38  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 39: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

The  PMBOK®  Guide  –  FiSh  Edi8on  defines  the  following  for  the  sixth  Project  Time  Management  process:  

Inputs  

•  Schedule  management  plan  •  Ac8vity  list  

•  Ac8vity  aOributes  

•  Project  schedule  network  diagrams  •  Ac8vity  resource  requirements  

•  Resource  calendars  •  Ac8vity  dura8on  es8mates  

•  Project  scope  statement  

•  Risk  register  •  Project  staff  assignments  

•  Resource  breakdown  structure  •  Enterprise  environmental  factors  

•  Organiza8onal  process  assets    

•  Tools  &  Techniques  ―  Schedule  network  analysis  ―  Cri8cal  path  method  

―  Cri8cal  chain  method  

―  Resource  op8miza8on  techniques  ― Modeling  techniques  

―  Lead  and  lags  ―  Schedule  compression  

―  Scheduling  tool  •  Outputs  ―  Schedule  baseline  ―  Project  schedule  ―  Schedule  data  ―  Project  calendars  ―  Project  management  plan  updates  

―  Project  documents  updates    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   39  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 40: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

The  cri8cal  path  is  determined  by  logical  dependencies,  it  does  not  consider  resource  dependencies.  The  Cri5cal  Path  Method  (CPM)  assumes  unlimited  resources.  This  means  that  resource  dependencies  (leveling  delays)  are  not  highlighted  as  driving  forces  in  the  schedule.  This  can  lead  to  delays  in  the  schedule  do  to  changes  in  resource  assignments  or  availability.  

SoSware  applica8ons  also  do  a  forward  and  backward  pass  

The  forward  and  backward  pass  calculate  the  following  items  on  each  ac8vity:  

Total  Float  (ac8vi8es  with  zero  total  float  are  considered  cri8cal).  

Free  Float  

Early  Start,  Early  Finish,  Late  Start  and  Late  Finish.  

•  Free  float:  The  amount  of  8me  that  a  schedule  ac8vity  can  be  delayed  without  delaying  the  early  start  date  of  any  successor  or  viola8ng  a  schedule  constraint.  

•  Total  float:  The  amount  of  8me  that  a  schedule  ac8vity  can  be  delayed  or  extended  from  its  early  start  date  without  delaying  the  project  finish  date  or  viola8ng  a  schedule  constraint.    

Calcula8ng  total  float:    

late  start  –  early  start  (or  late  finish  –  early  finish)  

Slack  and  Float  are  synonymous  terms.  Nega8ve  Float  occurs  when  you  have  a  deadline  or  constraint  before  (earlier  than)  the  scheduled  comple8on  of  the  project  schedule.  Ac8vi8es  with  nega8ve  float  are  considered  cri8cal  since  you  have  already  missed  a  deadline.  Also,  some8mes  you  will  see  Total  Float  referred  to  as  just  Float.  

The  cri8cal  paths  is  the  path  with  the  least  amount  of  float.  Usually  zero  float.    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   40  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 41: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: To  determine  the  project  cri8cal  path,  it  is  necessary  to  perform  a  forward  pass  and  a  backward  pass  through  the  network.  The  forward  pass  will  iden8fy  the  early  start  and  early  finish  8mes.  The  backward  pass  will  iden8fy  the  late  start  and  late  finish  8mes.  

These  processes  are  needed  to  be  able  to  calculate  the  float  on  each  ac8vity.  

Let’s  take  a  closer  look.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   41  

Page 42: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

A  forward  pass  is  performed  from  leS  to  right  through  the  network.  This  process  will  iden8fy  the  early  start  and  early  finish  for  each  ac8vity.    Start  with  one  for  the  first  ac8vi8es  to  get  the  ini8al  early  start  dates,  and  then  add  the  dura8on  to  the  early  start  and  subtract  one  to  get  the  early  finish  for  each  ac8vity.  

In  the  forward  pass  process,  the  greater  value  of  the  early  finish  for  all  predecessors  is  always  used  (and  incremented  by  one)  when  mul8ple  predecessors  converge  onto  one  successor.    Remember:  the  predecessor’s  early  finish  is  incremented  by  one  to  get  the  early  start  for  the  successor.  

The  early  finish  for  the  last  ac8vity  in  the  network  is  also  the  project  dura8on.    Therefore  the  dura8on  for  the  schedule  network  shown  is  24  work  periods.  

 

SPECIAL  NOTE:  In  previous  edi8ons  of  this  course,  we  used  the  following  method  for  the  forward  pass:  

A  forward  pass  is  performed  from  leS  to  right  through  the  network.  This  process  will  iden8fy  the  early  start  and  early  finish  for  each  ac8vity.    Start  with  zero  for  the  first  ac8vi8es  to  get  the  ini8al  early  start  dates,  and  then  add  the  dura8on  to  the  early  start  to  get  the  early  finish  for  each  ac8vity.  In  the  forward  pass  process,  the  greater  value  of  the  early  finish  for  all  predecessors  is  always  used  when  mul8ple  predecessors  converge  onto  one  successor.    The  early  finish  for  the  last  ac8vity  in  the  network  is  also  the  project  dura8on.    Therefore  the  dura8on  for  the  schedule  network  shown  is  24  work  periods.  (See  the  inset  on  the  slide)  

Because  the  PMBOK®  Guide  –  FiSh  Edi8on,  p.  177  demonstrates  the  forward  pass  in  the  manner  we  focus  on  in  this  slide…we  will  use  this  method  to  teach  the  forward  pass.  The  results  of  using  one  method  or  the  other  are  the  same,  with  the  excep8on  of  the  early  start.  

 

 

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   42  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 43: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

A  backward  pass  is  performed  star8ng  from  right  to  leS.    It  will  determine  the  late  start  and  late  finish  for  each  ac8vity.  Start  by  inheri8ng  the  early  finish  for  the  late  finish  in  the  last  ac8vity  (J),  and  then  subtract  the  dura8on  from  the  late  finish  (and  add  one)  for  the  late  start.  The  lesser  value  of  all  successor  tasks  that  converge  from  a  predecessor  (and  decremented  by  one)  is  used  as  the  late  finish  for  the  predecessor,  as  in  ac8vity  B.  Remember:  the  successor’s  late  start  is  decremented  by  one  to  get  the  late  finish  for  the  predecessor.  

SPECIAL  NOTE:  In  previous  edi8ons  of  this  course  we  used  the  following  method  for  the  backward  pass:  

A  backward  pass  is  performed  star8ng  from  right  to  leS.    It  will  determine  the  late  start  and  late  finish  for  each  ac8vity.  Start  by  inheri8ng  the  early  finish  for  the  late  finish  in  the  last  ac8vity  (J),  and  then  subtract  the  dura8on  from  the  late  finish  for  the  late  start.  The  lesser  value  of  all  successor  tasks  that  converge  from  a  predecessor  is  used  as  the  late  finish  for  the  predecessor,  as  in  ac8vity  B.  (See  the  inset  on  the  slide.)  

Because  the  PMBOK®  Guide  –  FiSh  Edi8on,  p.  177  demonstrates  the  backward  pass  in  the  manner  shown  on  in  this  slide  we  will  use  this  method  to  teach  the  backward  pass.  The  results  of  using  one  method  or  the  other  are  the  same,  with  the  excep8on  of  the  late  start.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   43  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 44: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

The  float,  denoted  in  parenthesis,  is  the  amount  of  8me  you  can  delay  a  task  without  affec8ng  the  project  end  date.    Float  (or  Total  Slack,  Slack  or  Total  Float)  can  then  be  calculated  as  follows:    

Total  float  =  Late  finish  –  Early  finish    

                                     or  

Total  float  =  Late  start  –  Early  start  

Calculate  the  total  float  using  both  formulas  as  a  way  of  checking  for  errors.    The  number  should  be  the  same  whether  using  start  or  finish  date  formulas.    A  difference  greater  than  zero  indicate  tasks  that  have  slack.  Zero  indicates  no  slack  and  a  “cri8cal  ac8vity”.  Less  than  zero  or  nega8ve  slack  are  ac8vi8es  that  do  not  meet  the  project  deadline  and  are  also  cri8cal.  The  cri8cal  path  is  comprised  of  all  ac8vi8es  that  have  the  least  amount  of  float.    

 

Note:  Scheduling  soSware  considers  two  other  elements  that  were  not  taken  into  considera8on  during  this  demonstra8on  of  the  forward  pass  and  backward  pass.  

1.  The  demonstra8on  assumed  that  everyday  was  a  working  day.  In  a  scheduling  tool,  the  precedence  diagram  will  take  into  considera8on  weekends  and  non-­‐working  days.  

2.  Scheduling  tools  will  also  consider  the  length  of  each  month.  Had  this  demonstra8on  been  done  on  a  project  covering  the  month  of  February  there  would  be  only  28  days  in  the  month.  This  demonstra8on  was  considering  only  days,  not  dates.  

To  replicate  the  demonstra8on  in  a  scheduling  tool:  

1.  Set  the  project  start  date  to  1/1/XX.  

2.  Create  a  project  calendar  that  has  no  holidays  and  shows  all  seven  days  of  the  week  as  working.  

3.  Insert  columns  for  Early  Start,  Early  Finish,  Late  Start,  Late  Finish  and  Total  Slack.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   44  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 45: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

The  cri8cal  chain  approach  to  project  management  is  based  on  the  theory  of  constraints  (TOC),  a  management  philosophy  developed  and  promoted  by  Eliyahu  M.  GoldraO.  TOC  began  in  manufacturing  where  the  objec8ve  is  to  produce  more  items  in  less  8me  through  the  effec8ve  use  of  resources  and  8me.  

Cri8cal  chain  is  used  in  the  project  environment  to  iden8fy  the  project’s  schedule  constraint  and  determine  how  to  “elevate”  or  in  some  way  improve  the  situa8on  to  relieve  or  eliminate  the  constraint.  

TOC  differs  from  the  tradi8onal  cri8cal  path  method  by  focusing  on  the  series  of  ac8vi8es  in  a  project  schedule  that  becomes  the  cri8cal  chain  aSer  all  resource  issues  have  been  addressed.  

Drum  resource:  The  boOleneck  which  is  used  to  schedule  an  en8re  project  team.  Also  refers  to  the  boOleneck  work  sta8on.  This  resource  availability  is  used  to  stagger  the  start  of  projects.  It  should  be  the  most  highly  used  resource,  and  one  that  is  not  easy  to  elevate.  

Drum  Buffer:  Buffer  placed  in  the  project  plan  immediately  in  front  of  the  first  use  of  the  drum  resource  in  a  project.  Its  purpose  is  to  enable  project  accelera8on  if  the  drum  resource  is  available  early.  Drum  buffers  are  used  in  a  porzolio  environment.    

•  Add  buffers  that  are  non-­‐work  schedule  ac8vi8es  to  manage  uncertainty.  

A  project  buffer  is  at  the  end  of  the  cri8cal  chain  and  protects  the  target  finish  from  slippage  A  feeding  buffer  is  placed  at  each  point  that  a  chain  of  dependency  ac8vi8es  that  feeds  into  the  

cri8cal  chain  and    protects  slippage  along  the  feeding  chains  •  Determine  the  size  of  the  buffer  based  on  dura8on  uncertainty  in  the  cri8cal  chain.  

•  Plan  for  latest  possible  start  and  finish  dates  and  focuses  on  managing  buffer  dura8ons.  The  theory  of  constraints  addresses  two  major  project  management  goals:  

•  Comple8ng  projects  more  quickly  

•  Funneling  more  projects  through  the  organiza8on  without  adding  resources.  To  reduce  project  cycle  8me  and  deliver  projects  more  quickly,  cri8cal  chain  focuses  on  the  longest    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   45  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 46: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

There  are  several  8mes  during  the  life  of  a  project  that  the  team  will  need  to  reduce  the  dura8on  of  the  project.  They  include:  

1.  If  aSer  building  an  unconstrained  schedule  (based  on  SME’s  es8mates  and  the  order  in  which  the  tasks  need  to  be  done),  a  shorter  dura8on  deadline  needs  to  be  met.  

2.  Once  the  schedule  is  baselined  and  updates  start  to  move  the  schedule  off  the  baseline,  the  project  team  may  need  to  re-­‐plan  (  compress)  the  schedule  to  get  back  on  the  baseline.  

3.  If    resources  become  over-­‐allocated  and  need  to  be  leveled.  Leveling  may  move  the  schedule  off  the  baseline  and  require  op8miza8on  (compression).  To  reduce  the  dura8on  of  a  project,  you  have  to  reduce  the  dura8on  of  ac8vi8es  on  the  cri8cal  path.  Reducing  the  dura8on  of  non-­‐cri8cal  tasks  only  adds  more  float  to  these  tasks.    

Schedule  Compression  is  divided  into  two  broad  categories,  Crashing  and  Fast  tracking.  In  the  simplest  terms,  crashing  is  throwing  money  (resources)  at  the  schedule  to  reduce  dura8on.  Fast  tracking  is  overlapping  tasks  to  reduce  dura8on.  A  combina8on  of  these  techniques  may  also  offer  a  workable  solu8on.  

More  specific  techniques  to  compress  the  project  schedule  include:  1.  Using  leads  and  parallelism  with  serial  ac8vi8es  2.  Breaking  down  a  long  ac8vity  and  reassigning  the  smaller  ac8vi8es  to  other  resources  3.  Removing  or  changing  constraints  4.  Reducing  scope  5.  Adding  more  resources  6.  Working  resources  over8me  7.  Spli{ng  ac8vi8es  around  constrained  ac8vi8es  8.  Ge{ng  an  updated  es8mate  from  the  SME  9.  U8lizing  a  newer  8me-­‐saving  technology  10.  Elimina8ng  non-­‐value  add  ac8vi8es  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   46  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 47: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: During  execu8on,  if  schedule  slippage  is  encountered,  there  are  a  few  sanc8oned  compression  techniques  to  consider.  

Crashing  adds  over8me  or  addi8onal  people  to  the  project.    

Fast-­‐tracking  adjusts  the  schedule  so  that  work  that  was  ini8ally  intended  to  be  done  in  sequence  is  worked  concurrently  or  in  parallel.    

Any  8me  a  project  manager  applies  one  of  these  techniques,  he  or  she  should  also  assess  the  risk  of  doing  so,  and  convey  that  informa8on  to  the  stakeholders.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   47  

Page 48: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

You  may  be  required  to  work  a  crashing  problem  on  the  PMP  exam.  If  so,  it  will  be  a  "least-­‐cost"  crashing  problem.  The  goal  in  these  type  of    problems  is  to  get  the  maximum  amount  of  compression  for  minimum  addi8onal  cost.  

Steps:  

Build  a  network  diagram  from  table  1.  

Iden8fy  the  cri8cal  ac8vi8es  in  diagram  2.  

Calculate  a  crashing  cost  per  unit  (cri8cal  ac8vi8es)  in  table  3.  

Calculate  the  benefit  in  8me  per  unit  (cri8cal  ac8vi8es)  in  table  3.  

Iden8fy  the  lowest  crashing  cost  per  ac8vity  

As  each  change  is  made,  ensure  that  the  cri8cal  path  has  not  changed.  

7.  Calculate  the  total  cost  of  crashing  and  the  benefit  gained.  

For  the  problems  on  the  exam,  this  would  be  sufficient.  In  a  work  environment,  you  would  want  to  evaluate  each  change  and  its  impact  on  the  compe8ng  constraints.  

In  the  example  above:  

Assuming  that  the  cri8cal  path  doesn’t  change….A,F,  E  and  B  would  be  crashed  in  that  order.  The  crashing  cost  would  increase  from  $120,000  to  $157,000  (net  increase  of  $37,500).  The  dura8on  would  be  decreased  from  twenty-­‐three  weeks  to  fiSeen  weeks.    

Crashing  the  non-­‐cri8cal  ac8vi8es  would  increase  the  cost  of  the  project  by  $7,500  without  reducing  the  total  project  8me.  

 

 

 

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   48  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 49: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: Develop  Schedule  Outputs:  

Milestone  chart,  bar  chart  or  network  diagram  can  be  very  effec8ve  in  displaying  the  project  schedule.  

•  Graphic  approach  (picture)  •  Easy  to  read  and  understand  

A  schedule  baseline  is  a  specific  version  of  the  project  schedule  developed  from  the  schedule  network  analysis.  

Schedule  data  for  the  project  schedule  includes  at  least  the  schedule  milestones,  schedule  ac8vi8es,  ac8vity  aOributes,  and  documenta8on  of  all  iden8fied  assump8ons  and  constraints.  

Project  documenta8on  updates  include:  

•  Ac8vity  resource  requirements  

•  Ac8vity  aOributes  

•  Calendar  •  Risk  register  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   49  

Page 50: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –    FiSh  Edi8on  describes  the  key  benefit  of  this  process  as  “recognizing  devia8on  from  the  plan  and  taking  appropriate  ac8ons.”    

PMBOK®  Guide  –  FiSh  Edi8on,  p.  185  

Schedule  control  is  concerned  with:    

•  Determining  the  current  status  of  the  project  schedule    

•  Influencing  the  factors  that  create  schedule  changes  

•  Determining  that  the  project  schedule  has  changed    

•  Managing  the  actual  changes  as  they  occur    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   50  

Page 51: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiSh  Edi8on  defines  the  following  for  the  seventh  Project  Time  Management  process:  Inputs  •  Project  management  plan  •  Project  schedule  •  Work  performance  data  •  Project  calendars  •  Schedule  data  •  Organiza8onal  process  assets  

Tools  &  Techniques  

•  Performance  reviews  •  Project  management  soSware  •  Resource  op8miza8on  techniques  •  Modeling  techniques  •  Lead  and  lags  •  Schedule  compression  •  Scheduling  tool  

Outputs  

•  Work  performance  informa8on  •  Schedule  forecasts  •  Change  requests  •  Project  management  plan  updates  •  Project  documents  updates  •  Organiza8onal  process  assets  updates  

 

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   51  

Page 52: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes:

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   52  

Page 53: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

Performance  reviews  measure,  compare,  and  analyze  schedule  performance.  Project  managers  can  develop  project  metrics  that  compare  planned  start  vs.  actual  start  dates,  planned  finish  vs.  actual  finish,  planned  effort  vs.  actual  effort  and  planned  dura8on  vs.  actual  dura8on.  Using  the  planned  vs.  actual  informa8on  and  analyzing  the  cri8cal  path  provides  a  good  way  to  track  performance  

Variance  analysis  requires  schedule  performance  measurements,  i.e.,  Schedule  Variance  (SV)  and  Planned  Value  (PV),  that  are  used  to  assess  the  magnitude  of  varia8on  to  the  original  schedule  baseline.  Comparing  the  planned  vs.  actual  work  and  analyzing  the  impact  to  the  cri8cal  path  (or  cri8cal  chain)  the  project  manager  can  analyze  the  variance  to  determine  if  the  schedule  is  within  the  defined  control  limits,  or  if  it  has  reached  or  passed  a  threshold.  If  the  schedule  has  exceeded  the  tolerance  limits  the  project  team  will  need  to  iden8fy  the  root  cause  of  the  variance  in  order  to  determine  the  appropriate  ac8on.  

PM  SoSware  and  Scheduling  Tools  are  used  on  most  projects  to  track  and  measure  progress  against  the  baseline  and  performance  metrics.  Scheduling  tools  can  also  perform  a  ‘what-­‐if  analysis’  to  iden8fy  trends.      

Resource  op8miza8on  techniques  include,  but  are  not  limited  to  leveling,  smoothing,  realloca8on,  etc.  

Modeling  techniques  can  include  porzolio  op8miza8on  under  resource  constraints.  The  effect  of  changing  out  different  resources  can  be  seen  in  cost,  composi8on  of  projects  selected  and  dura8on  of  a  project.  

Lags  and  leads  should  not  be  used  in  place  of  logical    dependencies  between  ac8vi8es,  but  can  augment  them  to  op8mize  the  project  schedule  or  to  model  the  project  in  a  more  effec8ve  manner.  

Frequently  when  we  create  the  unconstrained  schedule  we  need  to  compress  the  schedule  to  hit  a  deadline.  We  may  also  need  to  re-­‐plan  our  schedule  when  we  start  collec8ng  updates  in  order  to  stay  on  the  baseline.  In  both  these  cases  schedule  compression  techniques  are  useful.  

Scheduling  tools  can  facilitate  the  planning  and  analysis  of  project  8melines.  They  can  automate  the  various  calcula8ons  to  iden8fy  the  cri8cal  path,  slack,  network  logic,  and  slippage.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   53  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 54: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

Maintaining  the  schedule  baseline  is  important.  Re-­‐planning  is  the  way  to  accomplish  this.  

Work  performance  measurements  are  the  calculated  SV  and  the  Schedule  Performance  Index  (SPI).  

Organiza8onal  process  assets  that  could  be  updated  are:  causes  of  variances,  correc8ve  ac8on  chosen  and  the  ra8onale,  and  lessons  learned.  

Change  requests  could  be  generated  by  variance  analysis,  performance  measures,  or  requests  to  change  the  schedule  baseline  or  other  components  of  the  project  plan.  Change  requests  can  include  preven8ve  and  correc8ve  ac8ons  needed  to  bring  and  keep  the  schedule  performance  within  the  control  limits.  

Project  plan  updates  may  include,  but  are  not  limited  to,  schedule  baseline,  schedule  management  plan,  or  cost  baseline.  

Project  document  updates  include,  but  are  not  limited  to,  a  revised  network  diagram  and/or  schedule.  

Schedule  Forecasts  allow  project  managers  “drive  the  project  by  looking  through  the  windshield  rather  than  the  rear-­‐view  mirror.”    Earned  Value  calcula8ons  that  assist  with  this  include  Es8mate  to  Complete  (ETC),  Es8mate  at  Comple8on  (EAC)  and  To  Complete  Performance  Indicator  (TCPI)  and  all  of  their  varia8ons  to  reflect  differing  assump8ons.  

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   54  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 55: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

HONESTY  STANDARDS  

We  earnestly  seek  to  understand  the  truth.  

When  we  are  asking  for  status  informa8on  from  team  members  we  need  to  make  sure  we  are  clear  about  the  status  of  their  work.  Just  because  50%  of  the  8me  has  passed  does  not  mean  50%  of  the  work  is  done.  

We  are  truthful  in  our  communica8ons  and  in  our  conduct.  

When  we  report  status  we  discuss  the  good  work  we  have  done  as  well  as  the  challenges  we  face.  We  don’t  hide  bad  news  hoping  the  situa8on  will  improve.  

We  provide  accurate  informa8on  in  a  8mely  manner.  

When  we  determine  that  we  may  have  a  schedule  variance  we  need  to  communicate  the  situa8on  in  a  8mely  manner  while  there  is  s8ll  8me  to  take  correc8ve  ac8on  to  get  the  schedule  back  on  track.  

We  make  commitments  and  promises,  implied  or  explicit,  in  good  faith.  

When  we  are  building  our  schedules  we  do  our  best  to  build  a  realis8c  schedule.  We  use  good  faith  when  nego8a8ng  for  resources  and  developing  es8mates,  but  we  are  not  overly  aggressive  and  we  don’t  accept  an  unrealis8c  schedule.  If  we  are  forced  to  work  to  an  unrealis8c  deadline  we  tell  the  truth  about  the  risks  involved.  

We  do  not  engage  in  or  condone  behavior  that  is  designed  to  deceive  others,  including  but  not  limited  to,  making  misleading  or  false  statements,  sta8ng  half-­‐truths,  providing  informa8on  out  of  context  or  withholding  informa8on  that,  if  known,  would  render  our  statements  as  misleading  or  incomplete.    

Es8mates  and  schedules  can  be  complex  and  sensi8ve  aspects  of  the  project.  Regardless,  we  disclose  all  informa8on  and  are  transparent  in  how  we  develop  and  manage  the  schedule.    

Project  Time  Management  The  Project  Management  Cer8ficate  Program  

IIL-­‐CERT5   56  ©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Page 56: PMP cross-cutting skills have been updated in the PMP Exam ......PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content

©2014  Interna8onal  Ins8tute  for  Learning,  Inc.  

Participant’s Notes:

IIL-­‐CERT5  

Project  Time  Management  

57  

The  Project  Management  Cer8ficate  Program