policy, tariff regime and incentives for solar energy

Upload: hassanshahji11

Post on 07-Jul-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    1/21

    Policy, tariff regime, and incentives

    for solar energy

    Waqas Bin Najib

    1 Solarenergie in Pakistan –  Munich; September 11 2012

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    2/21

    Contents

    Solarenergie in Pakistan - Waqas Bin Najib2

    Overview of situation Power sector –  Institutional structure

    Grid-connected Independent Power Projects (IPPs)

    Tariff structure for grid-connected IPPs

    Fiscal incentives for RE IPPs

    Status of solar power projects

    Market opportunity overview

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    3/21

    Overview of situation

    Solarenergie in Pakistan - Waqas Bin Najib3

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    4/21

    An attractive market

    4

    Fast track - project development at highestPriority

    Guaranteed purchase of electricity backed byGovernment of Pakistan

    Modes of ownership Public Private Partnershipmodels available ‘OR ‘ 

    Independent power producer (IPP)

    Price setting model employed - “Cost plustariff” over 18% ROE guaranteed net of taxes 

    (USD based) Many of the variable operating cost are

    passed-on in the tariff model

    Special incentives Tax benefits (capital-gains tax,

    income tax and turnover tax exemption)

    Grid interconnection is the responsibility of powerpurchaser

    Policy Document can be found at:

    http://www.aedb.org/Policy/REpolicy.pdf  

    Energy deficit is 5000MW and rising

     World Class Power Policy

    Source: Private Power & Infrastructure Board –  Supply & Demand Position 2020

    Solarenergie in Pakistan - Waqas Bin Najib

    http://www.aedb.org/Policy/REpolicy.pdfhttp://www.aedb.org/Policy/REpolicy.pdf

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    5/21

    Excellent Solar Resource

    5

    2,000 hectares land

    for a cluster of solar

    power projects

    Solarenergie in Pakistan - Waqas Bin Najib

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    6/21

    Power sector – 

     Institutionalstructure

    Solarenergie in Pakistan - Waqas Bin Najib6

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    7/21

    Power sector  –  Institutional structure

    7 Solarenergie in Pakistan - Waqas Bin Najib

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    8/21

    Power sector  –  Institutional structure

    8

    Direct sale todistribution companiespossible

    Wheeling and

    distributed generationcode is beingapproved

    Roadblocks to REpower projects arebeing removed bywind IPPs

    Solarenergie in Pakistan - Waqas Bin Najib

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    9/21

    Power policies

    Solarenergie in Pakistan - Waqas Bin Najib9

    Conventional Power Projects Policy for Power Generation Projects 2002

    Renewable Energy Power Projects

    Policy for Development of Renewable Energy for PowerGeneration –  2006 (Short-term policy)

    Alternative and Renewable Energy Policy 2011 –  DRAFT

    (Medium-term policy) Medium-term policy has beenmade more attractive than the

    short-term policy

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    10/21

    Grid-connected IndependentPower Projects (IPPs)

    Solarenergie in Pakistan - Waqas Bin Najib10

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    11/21

    Unsolicited RE-IPP processing route

    11

    UnsolicitedExpression of

    InterestIssuance of LoI

    Submission offeasibility study

    Indicative/referencetariff approval

    Energy PurchaseAgreement

    Issuance of LoS

    Execution ofsecurity package

    and power/energypurchase agreement

    Financial Close

    Final tariff approvalStart of

    construction

    Solarenergie in Pakistan - Waqas Bin Najib

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    12/21

    Unsolicited RE-IPP processing route

    12

    Activity Indicative Process time 

    Submission of proposal on raw site by sponsors 

    Review of proposal and intimation of

    qualification of sponsors by AEDBWithin 30 days from date of receipt of complete proposal  

    Issuance of LOI for an initial period of 24

    months Within 7 days of receipt of acceptable bank guarantee 

    Completion of Feasibility Study Within the time specified in LOI (Maximum of 18 Months) 

    Procurement of Generation License Any time within the validity period of LOI 

    Procurement of tariff from NEPRAAny time within the validity period of LOI.

    NEPRA announces its determination within 90 days 

    Issuance of LOS by AEDB for a period of 18

    months 

    Within 7 days of receipt of acceptable Performance

    Guarantee

    Execution of Security Package 

    Any time during validity of LOS 

    Financial Close  Within the time allowed in the LOS 

    Achieve Construction Start  Within the time allowed in the LOS/Security Package 

    Commissioning of Project  Within the time allowed in the LOS/Security

    Package 

    Solarenergie in Pakistan - Waqas Bin Najib

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    13/21

     Tariff structure for grid-connectIPPs

    Solarenergie in Pakistan - Waqas Bin Najib13

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    14/21

    Cost-Plus tariff model

    14

    Energy Tariff

    (PKR/kWh)

    Non-escalablecomponent

    Debt servicing

    Floating interestrate

    Exchange ratevariation (PKR-

    US$)

    Return onequity (ROE)

    Exchange rate

    variation (PKR-US$)

    Escalablecomponent

    Fixed O&Mcosts

    Inflation (WPI)

    Variable O&Mcosts

    Inflation (WPI)

    80:20 Debt to

    Equity ratio

    >18% Return

    on Equity

    Coverage of

    currency risk

    Cost escalation

    coverage

    Solarenergie in Pakistan - Waqas Bin Najib

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    15/21

     Tariff for solar PV based power projects

    Solarenergie in Pakistan - Waqas Bin Najib15

    A feed-in/upfront tariff is being considered by theregulator (NEPRA)

    Negotiated tariff (cost-plus) would still be available for

    project sponsors, if preferred

    Upfront tariff for solar-PV based power projects is

    expected to be around 0,22 US$/kWh

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    16/21

    Overview of fiscal incentives forIPPs

    Solarenergie in Pakistan - Waqas Bin Najib16

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    17/21

    Incentives

    Solarenergie in Pakistan - Waqas Bin Najib17

    An attractive tariff model with sound guarantee structures for the

    RE power projects Additional guarantee structures being put up my multilateral agencies for

    RE power projects in the country

    Guaranteed power purchase (100% of produced electricity ismandatory for Power Purchaser to off-take)

    State Bank of Pakistan (SBP) has soft credit line for small renewableenergy power projects

    Zero rated import of all renewable energy plant, machinery,equipment, and spares (including electronics, batteries, and othermachinery)

    Exemption from income tax, including turnover rate tax andwithholding tax on imports.

    Repatriation of equity along with dividends freely allowed, subject torules and regulations prescribed by the State Bank of Pakistan.

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    18/21

    Status of solar power projects

    Solarenergie in Pakistan - Waqas Bin Najib18

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    19/21Information Source(s): AEDB, PPDB

    Status of solar power projects

    19

    Growing electricity supply-demand gap. Over 5,000 MWpower shortage

    Policy/regulations well

    established

    Cost-plus tariff model withminimum 18% ROE guaranteednet of taxes (US$ based); 30-50years concession

    Solar grid code, draft EPA, andother documents alreadyprepared

    Licenses for 5 solar powerprojects issued and feasibility isbeing conducted (LoIs)

    International companies part of

    the project consortiumimplementing the solar powerprojects DACC (US)

    CWE (China)

    Wellbeing Green (Aus)

    TechAccess (UAE)

    Solarenergie in Pakistan - Waqas Bin Najib

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    20/21

    Market opportunity overview

    Solarenergie in Pakistan, Waqas Bin Najib20

  • 8/19/2019 Policy, Tariff Regime and Incentives for Solar Energy

    21/21

    Understanding the market opportunities

    21

    Understanding the market opportunities Solar PV

    Grid connected power projects

    Off-grid rural electrification programs

    On/Off-grid urban market scenario

    Solar Thermal

    Solar water heating program