port e 2014 m /v p a b u c p e - cloudinary

124
P PORT E EVERGLADES 2 2 0 0 1 1 4 4 M MASTER / / V VISION P PLAN A APPENDIX G G : : B BULKHEAD S STUDY U UPDATE AND C CATHODIC P PROTECTION S SYSTEM E EVALUATION PRESENTED BY

Upload: others

Post on 04-Dec-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

PPOORRTT EEVVEERRGGLLAADDEESS

22001144 MMAASSTTEERR//VVIISSIIOONN PPLLAANN

AAPPPPEENNDDIIXX GG::BBUULLKKHHEEAADD SSTTUUDDYY UUPPDDAATTEE AANNDD CCAATTHHOODDIICC

PPRROOTTEECCTTIIOONN SSYYSSTTEEMM EEVVAALLUUAATTIIOONN

PPRREESSEENNTTEEDD BBYY

BULKHEAD STUDY UPDATE AND

CATHODIC PROTECTION SYSTEM

EVALUATION FOR

PORT EVERGLADES

BERTHS 1 THROUGH 29

AUGUST 2010

PORT EVERGLADES

BERTHS 1 THROUGH 29

BULKHEAD STUDY UPDATE AND CATHODIC PROTECTION SYSTEM

EVALUATION

AUGUST 2010

Prepared by: Halcrow, Inc.

1101 Channelside Dr., Suite 400N

Tampa, FL 33602

1

EXECUTIVE SUMMARY

Halcrow, Inc. was contracted as a Sub Consultant to Craven Thompson &

Associates, Port Everglades General Engineering Consultant, to provide an update to

the 2007 “Port Everglades Toewall Improvements & Bulkhead Analysis” Report by

others.

This “Bulkhead Study Update and Cathodic Protection System Evaluation for

Port Everglades, Berths 1 through 29” provides recommended replacement phasing for

the over 25,100 linear feet of steel sheet pile bulkheads throughout Port Everglades.

The replacement order proposed is based upon coordination of the U.S. Army Corps of

Engineer’s future channel dredging, the proposed Port Everglades Master/Vision Plans,

and the current condition of the existing steel sheet pile bulkhead walls.

Existing conditions of the steel sheet pile walls were reviewed based upon

existing data provided by the Port. The data on toe embedment, steel section loss due

to corrosion and the age of the walls was compiled. Then an overall rating for discrete

segments of the bulkhead walls was developed. Proposed replacement schedules

were developed based upon the overall ratings and incorporation of market driven

components of the draft Master/Vision Plans.

In addition to developing the proposed replacement schedules, Halcrow

performed a site visit to review the remaining components of impressed current cathodic

systems at the Port. These systems are no longer in active service and have

deteriorated to the point that rehabilitation of these systems is not deemed suitable.

To assist the Port is comparing installation of impressed current and sacrifical

anode cathodic protection systems, Halcrow performed a life cycle cost analysis of both

systems on all the bulkhead walls in Port Everglades. This life cycle cost analysis

resulted in a lower installation and maintenance cost for sacrificial anodes. Therefore,

Halcrow recommends the installation of sacrificial anode cathodic protection on all

Berths not scheduled for replacement until after 2021 and implementing a replacement

schedule to replace all bulkhead walls in Port Everglades by 2041.

i

PORT EVERGLADES BULKHEAD STUDY UPDATE AND CATHODIC

PROTECTION SYSTEM EVALUATION

TABLE OF CONTENTS

Page No.

TRANSMITTAL LETTER

EXECUTIVE SUMMARY 1

LIST OF FIGURES iv LIST OF TABLES iv

1. INTRODUCTION 1-1

1.1 FACILITY DESCRIPTION 1-1

1.2 SCOPE 1-2

1.3 2007 TOEWALL IMPROVEMENTS & BULKHEAD ANALYSIS REPORT 1-6

2. COORDINATION WITH OTHER WORK 2-1

2.1 COORDINATION ON FUTURE DREDGING 2-1

2.2 COORDINATION WITH DRAFT MASTER/VISION PLANS 2-6

3. DEVELOPMENT OF THE RATING SYSTEM FOR WALL CONDITIONS 3-1

3.1 EMBEDMENT RATIO RATING 3-2

3.2 STEEL SECTION LOSS RATINGS 3-5

3.3 AGE RATING 3-8

3.4 COMBINED RATINGS 3-11

4. PROPOSED REPLACEMENT SCHEDULES 4-1

4.1 RECOMMENDED SCHEDULE WITHOUT MASTER/VISION PLAN 4-1

4.2 RECOMMENDED SCHEDULE WITH MASTER/VISION PLAN 4-4

TABLE OF CONTENTS (CONT’D)

Page No.

ii

5. CATHODIC PROTECTION 5-1

5.1 EVALUATION OF EXISTING IMPRESSED CURRENT EQUIPMENT 5-1

5.2 LIFE CYCLE COSTS OF CATHODIC PROTECTION SYSTEMS 5-1

6. PROBABLE CONSTRUCTION COSTS FOR PLANNING 6-1

6.1 PLANNING COSTS FOR SACRIFICIAL ANODES 6-1

6.2 PLANNING COSTS FOR IMPRESSED CURRENT 6-2

6.3 PLANNING COSTS FOR REPLACEMENT WALL CONSTRUCTION 6-2

6.4 PLANNING COSTS FOR TOE WALL CONSTRUCTION 6-3

7. CONCLUSION 7-1

TABLE OF CONTENTS (CONT’D)

Page No.

iii

APPENDIX A – 2007 “PORT EVERGLADES TOEWALL IMPROVEMENTS & A-1

BULKHEAD ANALYSIS” REPORT: VOLUME I

BY LAKDAS/YOHALEM ENGINEERING

APPENDIX B – DRAFT VERSIONS OF PORT EVERGLADES B-1

5, 10 AND 20 YEAR MASTER / VISION PLANS

BY AECOM (VIA EMAIL JULY 23, 2010)

APPENDIX C – MEMORANDUM ON APRIL 5, 2010 SITE VISIT TO C-1

REVIEW EXISTING IMPRESSED CURRENT

CATHODIC PROTECTION

APPENDIX D – SUMMARY OF ASSUMPTIONS USED IN D-1

CATHODIC PROTECTION SYSTEMS

FOR LIFE CYCLE ANALYSIS

APPENDIX E – SACRIFICIAL ANODE VS IMPRESSED CURRENT E-1

LIFE CYCLE COST SUMMARY AND YEARLY BREAKDOWN

IN DISCOUNTED DOLLAR TERMS

APPENDIX F – SACRIFICIAL ANODE VS IMPRESSED CURRENT F-1

LIFE CYCLE COST SUMMARY

IN REAL 2010 DOLLAR TERMS

APPENDIX G – SACRIFICIAL ANODE VS IMPRESSED CURRENT G-1

LIFE CYCLE COST SUMMARY AND YEARLY BREAKDOWN

IN NOMINAL DOLLAR TERMS

iv

LIST OF FIGURES

Figure No. Title Page No.

Figure 1-1 Vicinity Map 1-3

Figure 1-2 Location Plan 1-4

Figure 1-3 Existing Facility Plan 1-5

Figure 2-1 Conceptual Future Dredging Plan per Discussions with USACE 2-2

Figure 2-2 Recommended Offset for Proposed Dredging 2-5

Figure 2-3 Future Facility Plan per Draft 2010-2029 Master / Vision Plans 2-7

Figure 3-1 Section Loss Relative to Age 3-12

LIST OF TABLES

Table No. Title Page No.

Table 3-1 Summary of Embedment Ratio Rating Data 3-4

Table 3-2 Summary of Section Loss Ratings Data 3-7

Table 3-3 Summary of Age Rating Data 3-9

Table 3-4 Summary of Age Rating Data (Continued) 3-10

Table 4-1 Recommended Schedule without Master/Vision Plan (29 Years) 4-3

Table 4-2 Recommended Schedule including Master/Vision Plan (30 Yrs) 4-5

1-1

1. INTRODUCTION

In February 2010, Halcrow, Inc. was contracted as a Sub Consultant by

Craven Thompson & Associates, Inc. to perform a Bulkhead Study Analysis and

Cathodic Protection System Evaluation for Berths 1 to 29 at Port Everglades in

Broward County. The aforementioned study and analysis was associated with

Third Amendment to Agreement between Broward County and Craven

Thompson & Associates, Inc. for General Engineering Services at Port

Everglades, Task 2V, Capital Budget Org. # 6510. The purpose of the analysis

was to provide a sequencing and phasing plan for bulkhead replacement taking

into account both structural stability as well as Port Everglades’ updated

Master/Vision Plans. Additionally, Halcrow, Inc. was to perform a cost/benefit

analysis to evaluate the maintenance of the existing corrosion protection system

including restarting of all non-functioning systems compared to installation of new

corrosion protection.

1.1 FACILITY DESCRIPTION

Port Everglades is located on the southeastern coast of the Florida

peninsula in the cities of Fort Lauderdale, Hollywood, and Dania Beach as well

as portions of unincorporated Broward County. It encompasses 1,742 acres of

upland area and 448 acres of submerged land totaling 2,190 acres of seaport.

Berths 1 to 33 are comprised of over 25,100 linear feet of bulkhead which

accommodate liquid bulk, dry bulk, containerized cargo, Navy ship, and cruise

ship operations. The bulkhead is constructed mainly of steel sheet pile walls with

either a “Z” type or “H-Z” type configuration. A vicinity map, location plan, and

existing facility plan is shown on Figure 1-1, Figure 1-2, and Figure 1-3.

The seaport facility is geographically divided into three (3) separate areas,

Northport, Midport, and Southport. Since the limits of these areas can vary by

user, this report will use the limits for Northport, Midport, and Southport listed in

the Halcrow/HPA “Underwater Inspection and Assessment” reports from 2006,

2007, and 2009.

1-2

“Northport encompasses Berth 1 through 13 (including Berths 1A and 1D,

4A, 8A, and 13A) and supports various dry bulk, liquid bulk, and cruise

ship operations.”

“Midport encompasses Berths 14 through 29 (including the Florida Power

and Light (FP&L) cooling canal bulkhead adjacent to Berth 29) and

supports dry bulk, breakbulk, ro/ro, and cruise ship operations.”

“Southport encompasses Berths 30 through 33 (including Berth 33A

through 33C) and supports containerized cargo ships and ro/ro

operations.”

1.2 SCOPE

The scope of work associated with this report was based on Task Item 2V

of Capital Budget Org. # 6510 in the “Third Amendment Between Broward

County and Craven Thompson & Associates, Inc.” dated December 18, 2009.

The scope was inclusive of the following items:

Review and analysis of the 2007 “Port Everglades Toewall Improvements

and Bulkhead Analysis” performed by Lakdas/Yohalem Engineering, Inc.

and production of a summary update based upon the review and findings

of the Port Everglades 2009 Underwater Inspection Survey performed by

Halcrow, Inc.

Production of a sequencing and phasing plan for replacement of all Port

Everglades bulkheads. Sequencing is to account for structural stability,

age of bulkhead, and existing and future uses of each berth. Halcrow was

to coordinate with the Port’s Master Planning Consultant, the updated 5,

10, and 20 year Master/Vision Plans, and the future dredging plans.

Evaluation of the existing cathodic protection system for adequacy in

corrosion protection of the bulkhead system. Evaluation was to be

inclusive of a cost/benefit analysis to evaluate maintenance and repair of

the existing system versus installation of a new corrosion protection

system.

1-6

1.3 2007 TOEWALL IMPROVEMENTS & BULKHEAD ANALYSIS REPORT

The scope of this report is to provide an update to the 2007 “Port

Everglades Toewall Improvements and Bulkhead Analysis” report produced by

Lakdas/Yohalem Engineering, Inc (LYE). Therefore, a brief review of the LYE

report will be provided as a starting point for this report. Additionally, Volume I of

the 2007 LYE report is attached as Appendix A. This report scope included

analysis on sheet pile wall embedment depths, remediation type comparisons

including complete replacement, cost comparisons associated with those

remediation techniques, potential wall failure mechanisms, and proposed berth

remediation/replacement orders. The 2007 LYE report was concluded by noting

the replacement of all sheet pile bulkheads over 40 years of age is

recommended.

The following is a brief summary of the “Port Everglades Toewall

Improvements and Bulkhead Analysis, Volume I” report produced by Lakdas/

Yohalem Engineering, Inc. in 2007.

(A) AGE OF ORIGINAL BULKHEAD

The 2007 LYE report notes that 68% of the Port’s bulkhead linear footage

was installed prior to 1968. Page 21 of the LYE report quotes from an Arbed

Steel Sheet Pile Manual, “the service life of waterfront structures is expected

today to be 40 to 50 years in general... (Arbed, 1986, p. 60)”. The LYE report

goes on to conclude, “new sheet pile is recommended for all sheet piles over 40

years of age.”

(B) CORROSION AND SECTION LOSS

The 2007 LYE report included a review of the steel sheet pile section

losses noted in the 2006 “Underwater Inspection and Baseline Survey

Assessment of Port Everglades Berths 1 through 33” by HPA (now Halcrow).

These section losses were compared to the steel sheet pile wall’s year of

construction and it was noted that “corrosion loss of the bulkheads . . . typically

increase with age.”

1-7

(C) BULKHEAD FAILURE MECHANISMS

In the 2007 LYE report, six (6) potential sheet pile wall failure mechanisms

were noted, defined, and reviewed. A brief summary of these mechanisms

follows; additional information and diagrams can be found in the 2007 report

(attached as Appendix A).

Deep-seated Soil Failure – A large scale movement of the soil mass on

both sides and the entire height of the sheet pile wall; LYE rated this

mechanism as of minimal concern at Port Everglades.

Wale System Failure – A separation of the wall from the tie rod, allowing

movement at the top of the wall; rated as a minimal concern.

Anchor Passive Failure – A movement of the anchorage system through

the soil, allowing movement at the top of the wall; rated as a minor

concern.

Flexural Failure of Sheet Pile – The development of a plastic hinge in the

steel sheet pile, allowing movement of the middle portion of the wall; rated

as a minor concern.

Tie Rod Failure – The yielding and/or fracture of the steel tie rods

connecting the sheet pile wall, allowing movement at the top of the wall;

rated as a moderate concern.

Toe Failure – Loss of soil resistance at the dredge line due to insufficient

embedment of the sheet pile wall toe, allowing movement of the wall

embedded below the dredge line; rated as a moderate concern. To

review the potential for toe failure, LYE performed 28 computer analyses

of existing wall segments. Of these 28 computer analyses 12 produced

factors of safety less than 1.0 and an additional 8 were between 1.0 and

2.0 (a minimum factor of safety recommended for design).

1-8

(D) REMEDIATION RECOMMENDATIONS

In the Lakdas/Yohalem Engineering, Inc. 2007 report, four (4) repair

options were reviewed:

Cathodic Protection – LYE noted that the installation of cathodic protection

slows the progress of corrosion and deterioration, which would delay flexural

failure of the steel sheet piles. However, it fails to repair the damage previously

done and provides little protection against anchor passive failure, tie rod failure or

toe failure without additional remediation.

New Tie Rod and Anchorage – Installation of new tie rods and anchorage

systems resists wale system failure, anchor passive failure and tie rod failure.

However, it does not provide any protection against a flexural failure or toe failure

without additional remediation.

Toe Wall Installation – Installation of toe walls increases the effective

penetration of the existing wall and reduces the possibility of toe failure.

However, it does not provide protection against anchor passive failure, tie rod

failure or flexural failure without additional remediation.

Replacement Wall – Installation of a replacement wall in front of the

existing wall provides protection against flexural failure and toe failure. However,

it provides little protection against anchor passive failure, tie rod failure or toe

failure without additional remediation

The 2007 Lakdas/Yohalem report provided cost estimates for seleceted

repair options and recommended installation of new sheet pile with a new

anchorage system. “New sheet pile is expected to provide a longer design life

than toe wall repairs. This longer design life is typically expected to make up for

the price differential over the life of the work.” (LYE, 2007)

The following portions of this report, update the 2007 LYE report with

ratings for the existing walls and propose replacement sequencing based upon

these ratings and coordination with the Port’s Master/Vision Plans.

2-1

2. COORDINATION WITH OTHER WORK

Prior to the determination of a proposed bulkhead replacement order, the

potential impacts of future dredging on existing bulkheads and geometric

changes to the layout of bulkheads proposed in the Master/Vision Plans were

reviewed.

2.1 COORDINATION ON FUTURE DREDGING

Halcrow contacted the U.S. Army Corps of Engineers (USACE) to discuss

plans for future channel deepening in Port Everglades. Based upon these

discussions, in July 2010, the following description of the proposed channel

deepening was reviewed for potential impacts on the existing bulkheads. The

Future Dredging Concept Plan is shown in Figure 2-1.

The Entrance Channel shall be deepened to a maximum depth of 52 feet

(based upon a design depth of 50 feet plus 1 foot of required over depth plus 1

foot of allowable over depth). The Entrance Channel will then lead into the

deepened Main Turning Basin with a maximum depth of 52 feet.

In addition to the Entrance Channel and Main Turning Basin, the proposed

dredging will include the realignment and deepening of the Southport Access

Channel and deepening of the existing Turning Notch. The Southport Access

and exisiting Turning Notch will have a maximum depth of 52 feet. The

realignment of the Southport Access Channel will increase the distance from the

existing bulkheads to the channel for Midport Berths from approximately 110 feet

to a over 160 feet.

In addition to the USACE dredging, it is expected that Port Everglades will

extend the Turning Notch to the west and dredge the berth areas of Berths 30 to

32.

2-3

From the Turning Notch to the southern end of Berth 32, the dredging will

include the Southport Access Channel. In this area, dredging to be performed by

Port Everglades will extend the 52 foot maximum depth all the way to the face of

the existing steel sheet pile walls.

Based upon the information provided by the U.S. Army Corps of

Engineers, Halcrow preformed some conceptual calculations to estimate the

effect of the proposed dredging on existing walls for Berths 1 to 29. Based upon

the dredging plan described above, any dredging at these walls is not expected

to extend up to the existing walls. At these locations it is expected the proposed

dredging will remain at least 160 feet from the face of the wall. Most of this 160

foot width will remain at the existing berth depth, followed by a transition down to

the new 52 foot channel dredge depth.

To estimate the effect of this proposed dredge depth configuration,

analyses of a typical berth in the current configuration and the post dredge

configuration were run using the software CWALSHT (U.S. Army Corps of

Engineer’s Program #X0031, Version Date 2006/04/12). This software allows

the user to define the shape of either the dredge side of the model or the retained

soil.

For this analysis: the level of the retained soil was assumed as Elevation

+8.0 ft MLW; the existing dredge elevation was taken as -38 ft MLW; the tie rod

was assumed at Elevation 0.0 ft MLW; the proposed dredge elevation was taken

as -52.0 ft MLW; and the transition from the existing to proposed dredge depth

was assumed to be a 3 horizontal to 1 vertical slope. The analysis was run

assuming the soil friction angle ( ) was 30 degrees for the entire soil mass. This

soil friction angle was selected based upon the minimum soil angle for any layer

recommended by the geotechnical engineer for the 2007 Lakdas/Yohalem

Engineering Report. The angle of soil-wall interface friction ( ) was assumed as

one-third of the soil friction angle ( /3).

Initially, an analysis was run based upon the existing dredge depth only.

This was followed by a series of runs with the distance from the face of the wall

to the new dredge limits increasing on each run. When the distance from the

2-4

wall to the new dredge limit produced approximately equivalent results for wall

embedment, maximum wall bending moment, maximum wall deflection and

anchor force, the effects due to dredging were considered negligible.

For planning purposes, Halcrow recommends that dredge deepening be

maintained at least 100 feet from the existing bulkheads (See Figure 2-2).

Halcrow also recommends that before any dredge deepening a more detailed

dredge analysis be performed to evaluate the dredge deepening effects on the

individual bulkheads.

2-6

2.2 COORDINATION WITH DRAFT MASTER/VISION PLANS

In December 2007, the Broward County Board of County Commissioners

approved the Port Everglades Master Plan Report; including a 5-Year Master

Plan, a 10-Year Vision Plan and a 20-Year Vision Plan. Currently the Port is

updating the Master/Vision Plans with the assistance of their contracted

consultants AECOM USA, Inc.

These Master/Vision Plans call for several projects throughout Port

Everglades “to maximize market share and revenue.” The projects that have the

most direct impact on the existing Northport and Midport Berths are the

lengthening of Berth 4, widening of Slip 2, widening of Slip 1 and widening of Slip

3. In addition, the Master/Vision Plans call for the Expansion of the Turning

Notch and Lengthening of Berth 33 in Southport (these 2 projects are beyond the

limits of this study, but are listed for completeness).

The Port has requested that Halcrow coordinate with the Master/Vision

Plan consultant AECOM. This coordination allows the work of both Halcrow and

AECOM to produce reports that reflect their findings and provide the Port with a

cost-efficient plan for future work. As part of this coordination, Halcrow and

AECOM held a number of discussions. During the course of these discussions,

Halcrow provided AECOM with preliminary findings on the conditions of the

bulkheads and a draft version of this report. AECOM provided Halcrow with the

most current draft layout of the Master/Vision Plans (July 23, 2010). Based upon

this coordination, Halcrow adjusted the proposed wall replacement orders, shown

in Section 4.2, and AECOM modified the Master/Vision Plans to account for the

replacement of walls in the worst reported condition.

The most recent Master/Vision Plans provided by AECOM are attached

included in Appendix B. In addition, Figure 2-3 shows a summary of the

Conceptual Future Facility Plan used for sequencing and phasing of bulkhead

replacements.

3-1

3. DEVELOPMENT OF THE RATING SYSTEM FOR WALL CONDITIONS

To produce a relative ranking of the existing wall conditions, each steel sheet pile

wall segment was rated in 4 categories. The categories were embedment ratio,

average section loss, maximum section loss and age. These categories were selected

to review the potential for toe failure, the extent of sheet pile corrosion and potential

corrosion of non-visible portions of the wall system. The data sets for these categories

were compiled from previous studies, reports and existing drawings.

To produce the ratings for each category, the compiled data sets were initially

reviewed for outlier data. For instance, in the embedment ratio data, there were 2 data

points that were so significantly different than the other 42 points that rating all 42 on a

single scale might skew the ratings (embedment ratios of 2.074 and 1.713 while the

other 40 points were between 0.157 and 0.655 with an average – arithmetic mean – of

0.338). Once the outliers are identified, they are assigned ratings individually.

For the majority of the data points linear interpolation is used to assign ratings.

Initially, the worst case data point is assigned a rating of 1 and the best case data point

is assigned a rating of 49, based upon the total number of data points. Then all

intermediate data points are assigned ratings based upon linear interpolation between

the maximum and minimum ratings.

This methodology of assigning the maximum and minimum ratings manually

based upon the number of data points and using linear interpolation for all points in

between produces relative ratings that account for the relationships of the data points.

For instance, all walls that were constructed in the same year will have the same rating

and walls that were constructed only a year or two later will have a similar rating.

The first step in assigning ratings to the wall segments was to select and define

the limits of each wall segment. The initial definition of wall segments was based upon

the berth numbers used by Port Everglades. Since portions of walls in a single berth

were sometimes constructed at different times, these wall segments were broken into

smaller segments such that each segment would have only a single year of

construction, based upon Port Everglades Drawing 92S 3912 (dated 10/12/92).

Once the wall segments were selected, the available data was compiled to

produce each of the 4 ratings.

3-2

3.1 EMBEDMENT RATIO RATING

To account for the possibility of toe failure, the embedment ratio was used. This

ratio between the length of sheet pile (or king pile in a combination wall) below the

dredge line to the length of wall above the dredge line gives an approximate

representation of the resistance to toe failure. The further a sheet pile wall extends

below the dredge line, the greater the capacity of the wall to resist toe failure. While the

higher the wall extends above the dredge line the greater the toe force to be resisted by

the embedded portion of the wall. Therefore, this simple ratio based only upon the

geometry of the wall, provides a useful comparison for the resistance to toe failure for

walls with a number of different dredge depths.

To establish the length of sheet pile (or king pile) below the dredge line and

length of wall above the dredge line, three elevations are required; the top of wall cap

elevation, the dredge line elevation at the face of the wall and the sheet pile / king pile

tip elevation.

For the top of the wall cap elevation, the elevations shown in the HPA (Halcrow)

April 2006 “Underwater Inspection and Baseline Survey Assessment of Port Everglades

– Berths 1 through 33” were used.

For the sheet pile or king pile tip elevations, data shown on Port Everglades

Drawing 92S 3912 (dated 10/12/92) was used. When tip elevations varied along a wall

segment the length weighted average was used.

For the dredge line elevation, soundings taken by the HPA/Halcrow engineer-

dive team during their “Underwater Inspection and Assessment” performed in 2006,

2007 and 2009 were used. In 2006, soundings were taken every 100 feet. While in

2007 and 2009, soundings were taken approximately every 500 feet. The data from all 3

assessments was used to provide the maximum number of samples to estimate an

average dredge line along the entire length of wall segment.

Once the average length of embedment and average length of upstand were

calculated, the approximate embedment ratio was calculated by dividing the

embedment by the upstand.

3-3

After the embedment ratios were calculated, the data was reviewed for outlier

data points. Two outlier types were identified for the embedment ratio data; wall

segments with toe walls and wall segments not servicing active berths.

Several of the wall segments have had toe walls installed. The Halcrow October

2009 “Underwater Inspection and Assessment of Port Everglades – Berths 1 through

33” Report identifies the end stations for toe walls observed. Based upon this

information, the length of visible toe walls in front of each wall segment was reviewed.

For any wall segment with a visible toe wall running along 60% or more of the wall

length, the toe wall was assumed to provide adequate support to generate an effective

embedment ratio larger than the embedment ratio calculated based upon the tip

elevation shown on Port Everglades Drawing 92S 3912. Therefore, these 7 wall

segments were considered outliers and assumed to have a rating near the median of

the non-outlier wall segments.

When the calculated embedment ratios were reviewed, there were 2 wall

segments with embedment ratios significantly greater than the other 47 wall segments.

The wall along the FLP Canal and the wall along the Dania Cut Off Canal had

embedment ratios of 1.713 and 2.074, respectively. The embedment ratios of the 40

non-outlier wall segments were between 0.157 and 0.655 with a mean of 0.338. These

wall segments are along canals near the ends of active berths. It was therefore

assumed that these walls were constructed using sheet pile lengths similar to that of the

nearby berths for ease of construction; although these wall segments had average

water depths approximately 30 feet shallower than the adjacent berth wall segments.

The FPL and Dania Cut Off Canal segments were given the highest embedment ratio

ratings but were not used to determine the ratings for the other 40 non-outlier wall

segments.

Ber

thA

ppro

xim

ate

Leng

th

of E

xist

ing

SS

PY

ear

of

Con

stru

ctio

nA

ppro

xim

ate

Top

of C

ap E

LA

ppro

xim

ate

Ave

rage

Mud

line

EL

App

roxi

mat

eT

ip E

LA

ppro

x. A

vera

ge

Em

bed

App

rox.

Ave

rage

U

psta

ndLe

ngth

oW

alls

240

ft19

609.

0 ft

MLW

-11.

6 ft

MLW

-25.

1 ft

MLW

13.5

ft20

.6 ft

0.65

520

0 ft

1960

9.0

ft M

LW-1

7.4

ft M

LW-3

1.5

ft M

LW14

.1 ft

26.4

ft0.

534

100

ft19

609.

0 ft

MLW

-26.

0 ft

MLW

-31.

5 ft

MLW

5.5

ft35

.0 ft

0.15

710

0 ft

1956

9.0

ft M

LW-3

6.0

ft M

LW-4

9.0

ft M

LW13

.0 ft

45.0

ft0.

289

535

ft19

569.

0 ft

MLW

-34.

7 ft

MLW

-49.

0 ft

MLW

14.3

ft43

.7 ft

0.32

853

5 ft

1956

9.0

ft M

LW-3

7.1

ft M

LW-4

9.0

ft M

LW11

.9 ft

46.1

ft0.

257

on)

435

ft19

569.

0 ft

MLW

-33.

5 ft

MLW

-49.

0 ft

MLW

15.5

ft42

.5 ft

0.36

5on

)10

0 ft

1940

9.0

ft M

LW-3

8.0

ft M

LW-4

0.0

ft M

LW2.

0 ft

47.0

ft0.

043

*63

on)

700

ft19

767.

7 ft

MLW

-46.

5 ft

MLW

-67.

0 ft

MLW

20.5

ft54

.2 ft

0.37

7on

)20

0 ft

1978

7.7

ft M

LW-4

7.5

ft M

LW-6

1.0

ft M

LW13

.5 ft

55.2

ft0.

245

1329

0 ft

1978

7.7

ft M

LW-4

8.4

ft M

LW-6

1.0

ft M

LW12

.6 ft

56.1

ft0.

224

900

ft19

787.

7 ft

MLW

-43.

2 ft

MLW

-71.

0 ft

MLW

27.8

ft50

.9 ft

0.54

738

0 ft

1965

7.7

ft M

LW-3

9.6

ft M

LW-5

3.0

ft M

LW13

.4 ft

47.3

ft0.

284

*5 0

600

ft19

657.

7 ft

MLW

-40.

3 ft

MLW

-53.

0 ft

MLW

12.7

ft48

.0 ft

0.26

460

0 ft

1965

7.7

ft M

LW-4

2.9

ft M

LW-5

3.0

ft M

LW10

.1 ft

50.6

ft0.

200

305

ft19

657.

7 ft

MLW

-42.

8 ft

MLW

-53.

0 ft

MLW

10.2

ft50

.5 ft

0.20

260

0 ft

1965

7.7

ft M

LW-4

3.9

ft M

LW-5

3.0

ft M

LW9.

1 ft

51.6

ft0.

177

600

ft19

657.

7 ft

MLW

-44.

6 ft

MLW

-53.

0 ft

MLW

8.4

ft52

.3 ft

0.16

250

0 ft

1965

9.0

ft M

LW-3

6.8

ft M

LW-5

3.0

ft M

LW16

.3 ft

45.8

ft0.

355

615

ft19

849.

0 ft

MLW

-39.

8 ft

MLW

-71.

0 ft

MLW

31.2

ft48

.8 ft

0.63

961

5 ft

1984

9.0

ft M

LW-4

1.6

ft M

LW-7

1.0

ft M

LW29

.4 ft

50.6

ft0.

581

300

ft19

579.

0 ft

MLW

-36.

4 ft

MLW

-49.

0 ft

MLW

12.6

ft45

.4 ft

0.27

760

0 ft

1957

9.0

ft M

LW-3

9.3

ft M

LW-4

9.0

ft M

LW9.

7 ft

48.3

ft0.

201

*60

060

0 ft

1960

9.0

ft M

LW-3

9.8

ft M

LW-4

9.0

ft M

LW9.

3 ft

48.8

ft0.

190

*51

455

0 ft

1960

9.0

ft M

LW-3

8.6

ft M

LW-4

9.0

ft M

LW10

.4 ft

47.6

ft0.

220

ion)

325

ft19

609.

0 ft

MLW

-40.

1 ft

MLW

-49.

0 ft

MLW

8.9

ft49

.1 ft

0.18

035

ion)

225

ft19

649.

0 ft

MLW

-40.

4 ft

MLW

-53.

0 ft

MLW

12.6

ft49

.4 ft

0.25

555

0 ft

1964

9.0

ft M

LW-4

0.1

ft M

LW-5

3.0

ft M

LW12

.9 ft

49.1

ft0.

262

ion)

260

ft19

649.

0 ft

MLW

-36.

7 ft

MLW

-53.

0 ft

MLW

16.3

ft45

.7 ft

0.35

7io

n)39

0 ft

1966

9.0

ft M

LW-3

6.5

ft M

LW-5

3.0

ft M

LW16

.5 ft

45.5

ft0.

363

650

ft19

669.

0 ft

MLW

-39.

9 ft

MLW

-53.

0 ft

MLW

13.1

ft48

.9 ft

0.26

766

5 ft

1966

9.0

ft M

LW-4

0.4

ft M

LW-5

3.0

ft M

LW12

.6 ft

49.4

ft0.

255

660

ft19

669.

0 ft

MLW

-40.

9 ft

MLW

-53.

0 ft

MLW

12.1

ft49

.9 ft

0.24

324

0 ft

1966

9.0

ft M

LW-3

5.3

ft M

LW-5

3.0

ft M

LW17

.7 ft

44.3

ft0.

398

*20

0io

n)15

0 ft

1966

9.0

ft M

LW-3

6.3

ft M

LW-5

3.0

ft M

LW16

.7 ft

45.3

ft0.

368

*15

0io

n)57

0 ft

1967

9.0

ft M

LW-3

9.9

ft M

LW-4

9.0

ft M

LW9.

1 ft

48.9

ft0.

187

*50

665

0 ft

1967

9.0

ft M

LW-3

8.6

ft M

LW-5

0.1

ft M

LW11

.5 ft

47.6

ft0.

242

325

670

ft19

679.

0 ft

MLW

-44.

1 ft

MLW

-60.

0 ft

MLW

15.9

ft53

.1 ft

0.30

067

0 ft

1967

9.0

ft M

LW-4

0.6

ft M

LW-6

0.0

ft M

LW19

.4 ft

49.6

ft0.

392

1,45

0 ft

1967

9.0

ft M

LW-3

0.1

ft M

LW-4

6.2

ft M

LW16

.2 ft

39.1

ft0.

414

ion)

100

ft19

679.

0 ft

MLW

-36.

0 ft

MLW

-62.

0 ft

MLW

26.0

ft45

.0 ft

0.57

8io

n)72

0 ft

1983

9.0

ft M

LW-4

3.8

ft M

LW-7

2.0

ft M

LW28

.2 ft

52.8

ft0.

534

210

ft19

839.

0 ft

MLW

-11.

8 ft

MLW

-47.

5 ft

MLW

35.7

ft20

.8 ft

1.71

398

5 ft

1992

11.0

ft M

LW-4

2.9

ft M

LW-6

9.8

ft M

LW26

.9 ft

53.9

ft0.

499

1,00

0 ft

1992

11.0

ft M

LW-4

5.8

ft M

LW-7

7.0

ft M

LW31

.2 ft

56.8

ft0.

549

1,00

0 ft

1992

11.0

ft M

LW-4

5.0

ft M

LW-7

3.1

ft M

LW28

.1 ft

56.0

ft0.

502

800

ft19

9211

.0 ft

MLW

-46.

1 ft

MLW

-72.

0 ft

MLW

25.9

ft57

.1 ft

0.45

333

C51

0 ft

1992

11.0

ft M

LW-4

4.3

ft M

LW-7

2.0

ft M

LW27

.7 ft

55.3

ft0.

500

480

ft19

9211

.0 ft

MLW

-16.

0 ft

MLW

-72.

0 ft

MLW

56.0

ft27

.0 ft

2.07

4

App

rox.

Em

bed

Rat

io

3-5

3.2 STEEL SECTION LOSS RATINGS

Since section losses due to corrosion may vary from location to location on the

face of steel sheet pile walls, sampled thickness measurements and section losses

were used for 2 ratings. During the 2006, 2007 and 2009 “Underwater Inspections and

Assessments” performed by the HPA/Halcrow engineer-dive teams, field measurements

of the remaining steel thickness were taken. These thickness measurements were

taken using an underwater, ultrasonic thickness (UT) gauge.

At each thickness measurement station, the typical procedure included 27 UT

measurements. The procedure included 9 measurements taken near the top of the

exposed sheet pile (just below the concrete cap), 9 measurements taken near mid-

depth, and 9 measurements taken near the dredge line.

During the 2006 “Underwater Inspection and Assessment”, UT measurements

were performed at 270 station locations along the bulkheads or approximately every

100 feet. During the 2007 and 2009 “Underwater Inspections and Assessments”,

measurements were performed at 57 station locations or approximately every 500 feet.

This produced a total of 9,946 individual thickness measurements.

For each thickness measurement station location, the most likely steel sheet pile

manufacturer and sheet pile section was selected based upon Port Everglades

Drawing 92S 3912 (dated 10/12/92). For each sheet pile section, research was

performed to identify the original sheet pile flange and web catalog listed thicknesses.

Using these catalog thicknesses, the approximate section loss for each thickness

measurement was calculated.

The thickness losses were expressed as a percentage of the most likely catalog

thicknesses. These thickness loss percentages were then averaged for the upper

measurements, mid-depth measurements, near dredge line measurements and the all

depth measurements for each wall segment. In addition, for each wall segment, the

maximum percentage section loss was noted. The average section loss was selected

to represent the overall condition of the waterside face of the steel sheet pile walls. The

average section loss gives an indication of the reduction in flexural bending capacity

due to section loss. In contrast, the maximum recorded section loss indicates how

close the wall is to developing holes that could allow for fill loss behind the wall. Fill loss

3-6

behind the wall can lead to settlement and undermining of the pavement behind the

wall.

Once the average and maximum section losses for each wall segment were

generated, they were reviewed for outliers. The only outlier identified for the section

loss ratings was the 100 linear foot portion of Berth 3 listed as constructed in 1940. In

this segment of wall, only 3 thickness measurements from near the dredge line were

located with an average loss of 18.7%. Due to this small sample size, this segment was

assumed to have no thickness loss data. Due to the age of this segment, it was

assumed that this small segment would have the worst section loss and was assigned

an average section loss and maximum section loss rating of 1. The remaining 48 wall

segments were assigned section loss ratings using linear interpolation with the largest

loss assumed to have a rating of 2 and the smallest loss assumed to be rated at 49.

thE

xist

ing

SS

PC

onst

ruct

ion

Sec

tion

Los

sS

ectio

n Lo

ssU

pper

Los

sM

iddl

e Lo

ssB

otto

m L

oss

240

ft19

6030

.5%

55.6

%28

.8%

No

Dat

a32

.1%

200

ft19

6032

.2%

52.2

%28

.6%

38.1

%29

.3%

100

ft19

6035

.0%

52.2

%33

.9%

37.5

%33

.6%

100

ft19

5624

.0%

46.1

%29

.9%

23.6

%18

.4%

535

ft19

5621

.9%

49.2

%26

.6%

22.7

%16

.4%

535

ft19

5618

.8%

37.0

%22

.9%

20.5

%13

.1%

435

ft19

5620

.1%

46.1

%21

.1%

22.8

%16

.3%

100

ft19

40N

o D

ata

No

Dat

aN

o D

ata

No

Dat

a18

.7%

700

ft19

766.

8%37

.2%

11.3

%6.

6%2.

4%20

0 ft

1978

0.7%

10.4

%1.

4%0.

4%0.

3%29

0 ft

1978

0.5%

5.1%

0.7%

0.3%

0.4%

900

ft19

781.

6%13

.1%

2.3%

1.6%

0.8%

380

ft19

6519

.9%

60.0

%28

.6%

20.6

%11

.3%

600

ft19

6519

.9%

46.7

%25

.7%

22.8

%11

.3%

600

ft19

6519

.6%

45.3

%22

.1%

25.3

%10

.4%

305

ft19

6522

.5%

50.7

%27

.3%

27.0

%13

.2%

600

ft19

6520

.1%

65.3

%26

.1%

25.5

%8.

9%60

0 ft

1965

16.6

%56

.4%

19.4

%22

.0%

8.2%

500

ft19

6520

.4%

50.7

%25

.3%

24.7

%11

.1%

615

ft19

841.

2%11

.8%

2.3%

0.4%

0.8%

615

ft19

844.

5%51

.9%

6.3%

4.2%

2.9%

300

ft19

5715

.3%

66.6

%21

.3%

15.3

%7.

8%60

0 ft

1957

18.6

%46

.1%

19.5

%21

.9%

14.3

%60

0 ft

1960

18.2

%46

.1%

19.6

%20

.2%

14.8

%55

0 ft

1960

12.7

%37

.0%

16.4

%13

.1%

8.9%

325

ft19

609.

8%36

.0%

11.7

%10

.4%

7.2%

225

ft19

6413

.0%

32.2

%13

.3%

16.6

%9.

0%55

0 ft

1964

17.5

%49

.2%

20.5

%21

.2%

10.7

%26

0 ft

1964

16.5

%49

.2%

20.5

%19

.8%

9.4%

390

ft19

6617

.6%

42.9

%20

.8%

19.9

%12

.0%

650

ft19

6620

.8%

55.5

%25

.6%

27.1

%9.

9%66

5 ft

1966

19.4

%48

.0%

23.1

%22

.5%

12.6

%66

0 ft

1966

17.1

%41

.6%

20.1

%21

.5%

9.6%

240

ft19

6619

.5%

38.3

%25

.5%

19.6

%13

.4%

150

ft19

6616

.1%

32.7

%19

.1%

19.8

%9.

4%57

0 ft

1967

16.3

%42

.9%

16.4

%19

.1%

13.2

%65

0 ft

1967

12.6

%51

.8%

15.0

%13

.7%

9.2%

670

ft19

671.

6%74

.6%

4.6%

0.3%

0.0%

670

ft19

672.

1%55

.6%

3.5%

2.6%

0.2%

1,45

0 ft

1967

10.0

%69

.5%

11.2

%12

.0%

6.8%

100

ft19

675.

9%26

.9%

4.5%

8.8%

4.4%

720

ft19

8312

.4%

43.9

%14

.6%

12.3

%10

.2%

210

ft19

837.

7%13

.6%

8.0%

No

Dat

a7.

1%98

5 ft

1992

4.5%

26.4

%4.

7%4.

4%4.

4%1,

000

ft19

9211

.3%

49.2

%12

.5%

13.3

%8.

2%1,

000

ft19

9210

.5%

46.7

%10

.9%

12.6

%7.

9%80

0 ft

1992

11.3

%70

.8%

12.9

%12

.5%

8.5%

510

ft19

9213

.5%

45.4

%12

.4%

13.6

%14

.3%

480

ft19

9215

.3%

46.7

%17

.3%

13.6

%14

.9%

3-8

3.3 AGE RATING

In addition to the sheet pile wall, the bulkhead system depends upon its

anchorage system to function and remain stable. The anchorage system includes steel

tie rods, steel soil anchors, steel walers, concrete deadman anchors and steel sheet pile

anchor walls. The anchorage system provides the resistance for movement of the top

of the wall due to the soil pressure behind the wall.

Since the anchorage system is embedded in concrete and buried underground,

the anchorage system is not accessible for visual inspections and measurements.

Therefore, the age of the wall is used for an approximation of the condition of the

anchorage system and other elements not exposed to view. All else being equal, an

older anchorage system would be expected to be closer to its functional life than a

newer one.

All year of construction data was taken from Port Everglades Drawing 92S 3912

(dated 10/12/92).

The only wall segment assumed as an outlier was the 100 linear foot portion of

Berth 3 listed as constructed in 1940. Due to the small length of this segment, it seems

likely that at some point since 1940, this segment has received significant work but this

work was overlooked during the assembly of Port Everglades Drawing 92S 3912.

All other wall segments were rated using linear interpolation with 1956 assigned

a rating of 2 and 1992 assigned a rating of 48.8. The maximum rating of 48.8 was used

instead of the normal 49.0 to avoid rounding issues in the linear interpolation. With the

maximum rating of 48.8, each year of wall age reduces the rating by exactly 1.3.

3-9

Table 3-3 Summary of Age Rating Data

Year Wall Segment Approximate Length of Existing Wall Segment

Total Length of Wall for Each Year Age Rating

1940 Portion of Berth 3 100 LF 100 LF 1.0

Berth 1A 100 LF Berth 1 535 LF Berth 2 535 LF

1956

Portion of Berth 3 435 LF

1,605 LF 2.0

Berth 13A 300 LF 1957

Berth 14 600 LF 900 LF 3.3

Berth 1D 240 LF

Berth 1C 200 LF

Berth 1B 100 LF

Berth 15 600 LF

Berth 16 550 LF

1960

Portion of Berth 17 325 LF

2,015 LF 7.2

Portion of Berth 17 225 LF

Berth 18 550 LF 1964

Portion of Berth 19 260 LF

1,035 LF 12.4

Berth 6 380 LF

Berth 7 600 LF

Berth 8 600 LF

Berth 8A 305 LF

Berth 9 600 LF

Berth 10 600 LF

1965

Berth 11 500 LF

3,585 LF 13.7

Portion of Berth 19 390 LF

Berth 20 650 LF

Berth 21 665 LF

Berth 22 660 LF

Berth 23 240 LF

1966

Portion of Berth 24 150 LF

2,755 LF 15.0

Portion of Berth 24 570 LF

Berth 25 650 LF

Berth 26 670 LF

Berth 27 670 LF

Berth 28 Walls 1,450 LF

1967

Portion of Berth 29 100 LF

4,110 LF 16.3

1 All data taken from Port Everglades Drawing No. 92S 3912 (dated 10/12/92). 2 Wall Segments with Year of Construction after 1970 shown on Table 3-3.

3-10

Table 3-4 Summary of Age Rating Data (Continued)

Year Wall Segment Approximate Length of Existing Wall Segment

Total Length of Wall for Each Year Age Rating

1976 Portion of Berth 4 700 LF 700 LF 28.0

Portion of Berth 4 200 LF

Berth 4A 290 LF 1978

Berth 5 900 LF

1,390 LF 30.6

Portion of Berth 29 720 LF 1983

FPL Canal 210 LF 930 LF 37.1

Berth 12 615 LF 1984

Berth 13 615 LF 1,230 LF 38.4

Berth 30 985 LF

Berth 31 1,000 LF

Berth 32 1,000 LF

Berth 33 800 LF

Berths 33A to 33C 510 LF

1992

Dania Cut Off Canal 480 LF

4,775 LF 48.8

1 All data taken from Port Everglades Drawing No. 92S 3912 (dated 10/12/92). 2 Wall Segments with Year of Construction prior to 1970 shown on Table 3-2.

3-11

3.4 COMBINED RATINGS

To rank all of the wall segments for a recommended order of importance, the

individual ratings for embedment ratio, average section loss, maximum section loss and

age needed to be combined into a single rating.

It is expected that age, average section loss and maximum section loss would

exhibit relatively high levels of correlation. For instance, Figure 3-1 shows the average

section loss relative to a wall segment’s year of construction. The general trend of this

graph is that an older wall has more section loss than a younger wall segment.

Due to the correlation between age and the sampled section losses, a weighted

average was used to select an overall rating. The weights for the overall ranking were

selected such that the total effect of the wall’s age (25%), average section loss (15%)

and maximum section loss (10%) comprised half of the overall rating; while the

embedment ratio comprised the other half of the rating (50%).

If, instead of the weighted average, the arithmetic mean of the four ratings were

used, the overall rating would be skewed toward the correlation between age and

section losses. Calculating the arithmetic mean is equivalent to a weighted average

with each of the four ratings having a 25% weighting. As shown in Figure 3-1, an older

wall tends to have greater section loss than a younger wall due to more time for

corrosion to develop. Therefore, with an arithmetic mean, the corrosion related ratings

(age, average section loss and maximum section loss) would account for 75% of the

total rating and the embedment ratio would account for only 25% of the rating.

Therefore, the 25%-15%-10%-50% weighting was selected to ensure that the potential

for toe failure was weighted equally with the effects of corrosion.

The age rating was weighted heavier than the average or maximum section loss

because the age accounts for corrosion of all components of the wall and anchorage

system. The average and maximum section losses are measurements on only the

waterside face of the walls.

56 g300LF)-1957Berth14(600LF)-1957

19581959

Berths16and17(875LF)-1960Berth15(600LF)-1960

Berths1Ato1D(560LF)-1960196119621963

Berth19(260LF)-1964

Berths17and18(775LF)-1964

Berths9and10(1,200LF)-1965

Berths7and8(1,200LF)-1065

Berth6(130LF/Existing380LF)-1965

Berth11(75LF/Existing500LF)-1965

Berth8A(260LF/Existing300LF)-1965Berth24(155LF)-1966

Berths21and22(1,325LF)-1966Berth23(240LF)-1966

Berths19and20(1,050LF)-1966

Berths26and27(1,350LF)-1967Berth29(100LF)-1967

Berth28(560LF/Existing1,450LF)-1967

Berths24and25(1,215LF)-196719681969197019711972197319741975

Berth4(700LF)-19761977

Berth4A(475LF/Existing300LF)-1978Berth4(200LF)-1978Berth5(900LF)-1978

1979198019811982

FPLCanal(210LF)1983Berth29(780LF)-1983

Berths12&13(650LF)-1985

erth12-FutureBargeSlip(600LF)-198419851986

3-13

However, age does not tell the complete picture of corrosion effects. The

cathodic protection systems and the typical variability of corrosion rates, means that the

faces of some wall segments have experienced more corrosion than others. By

including the average section loss the variability of corrosion and the potential for

flexural overstress of the walls is included. Similarly, the maximum section loss best

accounts for the risk of holes leading to fill loss from behind the wall.

Since for each of the individual ratings 1 was considered the worst condition, the

weighted average is such that the lower the rating the sooner the wall segment should

be remediated.

Once the weighted average for all wall segments was established, wall segments

were grouped based upon geography and wall geometry. For example, Berths 1, 2 and

3 were grouped since these three berths provide a linear 1,600 feet of berthing space.

These groups were then reviewed to select the longest wall segments; these longer

segments were considered more critical to the need for remediation.

The berths at the east and west end of the Northport Slips 1, 2 & 3 (Berths 4A, 6,

8A, 11 and 13A) were grouped with one of the adjacent berths along the slips. For

instance, Berth 8A was grouped with Berth 8 and Berth 11 was grouped with Berth 12.

These groupings of wall segments at the ends of the slips were made to avoid

suggesting that major remediation be performed on a berth at the end of slip, which may

require significant geometric realignment according to the Master/Vision Plan, before

remediation was performed on the adjacent slip wall segments. This grouping of wall

segments allowed for an indirect inclusion of wall importance in the overall ratings.

Although the Southport Berths (Berths 30 to the Dania Cut Off Canal) were not

required to be included in this work, the data for these berths was available. Therefore,

these berths are included at the end of the ratings for completeness and comparison

purposes.

4-1

4. PROPOSED REPLACEMENT SCHEDULES

4.1 RECOMMENDED SCHEDULE WITHOUT MASTER/VISION PLAN

Once the weighted average for the grouped wall segments was finished, the

grouped wall segments were ordered such that those wall segments more in need of

remediation were listed first. Possible years for the start of wall replacement

construction were assigned to each group of wall segments based on a beginning

construction year of 2013.

These years of proposed replacement were selected based upon the weighted

rating of the segments, while also spreading apart the replacement of berths handling

petroleum products (Berths 5, 7-8, 9-10 and 12-13).

In an attempt to account for the need for design, unavoidable delays and periodic

review of the wall order during the replacement schedule, the replacement schedule

includes years where no construction is scheduled to commence. These scheduled

years with no construction stretched the 19 years of construction commencing out over

29 years (including the Southport Berths).

To give the best chance that the berths not scheduled until later in the order are

able to remain functional, it is recommended that cathodic protection be installed. To

minimize the chances that cathodic protection is installed on wall segments followed

closely by the wall being replaced, it is recommended that starting in 2012, all walls

scheduled for replacement in 2021 or later have cathodic protection installed.

Although this replacement schedule is considered realistic and addresses the

bulkhead replacement order based upon a weighted average rating, this proposed

replacement schedule is not without risk. The weighted average rating is based upon

the existing conditions of the wall segments using observations since 2006. This data

covers such a limited time frame that the different rates of deterioration between wall

segments was not reviewed or accounted for. In addition, this schedule assumes that

the average walls in Northport and Midport can, with cathodic protection, attain a length

weighted average age of 56 years before starting replacement construction (drops to 53

years when the Southport Berths are included). In addition, four of the wall segments,

totaling 1,380 linear feet of berthing (100 LF portion of Berth 3, 600 LF portion of Berth

4-2

14 & 15, all 300 LF of Berth 13A and all 380 LF of Berth 6), are expected to be 65 years

or older at the time of replacement construction commencing. To account impact of

different rates, the replacement order should be reviewed no less than every 5 years

and anytime wall movement or significant fill loss is observed.

Yea

rA

geB

erth

SS

PE

xist

ing

SS

PC

onst

ruct

ion

Em

bed

Wal

lS

ectio

n Lo

ssS

ectio

n Lo

ssR

atin

gR

atin

gLo

ss R

atin

gLo

sN

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

INS

TA

LL C

P48

Ber

th 9

600

ft19

659.

1 ft

0.17

720

.1%

65.3

%2.

813

.722

.348

Ber

th 1

060

0 ft

1965

8.4

ft0.

162

16.6

%56

.4%

1.4

13.7

27.1

NO

NE

W C

ON

ST

RU

CT

ION

TO

ST

AR

T59

Ber

th 1

535

ft19

5614

.3 ft

0.32

821

.9%

49.2

%16

.82.

019

.859

Ber

th 2

535

ft19

5611

.9 ft

0.25

718

.8%

37.0

%10

.22.

024

.159

Ber

th 3

(po

rtio

n)43

5 ft

1956

15.5

ft0.

365

20.1

%46

.1%

20.2

2.0

22.3

75B

erth

3 (

port

ion)

100

ft19

402.

0 ft

0.04

3*

63.0

%N

o D

ata

No

Dat

a18

.01.

01.

056

Ber

th 1

655

0 ft

1960

10.4

ft0.

220

12.7

%37

.0%

6.8

7.2

32.4

56B

erth

17

(por

tion)

325

ft19

608.

9 ft

0.18

010

.8%

9.8%

36.0

%3.

17.

236

.352

Ber

th 1

7 (p

ortio

n)22

5 ft

1964

12.6

ft0.

255

13.0

%32

.2%

10.1

12.4

32.0

52B

erth

18

550

ft19

6412

.9 ft

0.26

217

.5%

49.2

%10

.712

.425

.851

Ber

th 2

166

5 ft

1966

12.6

ft0.

255

19.4

%48

.0%

10.0

15.0

23.3

51B

erth

22

660

ft19

6612

.1 ft

0.24

317

.1%

41.6

%9.

015

.026

.4N

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

54B

erth

760

0 ft

1965

12.7

ft0.

264

19.9

%46

.7%

10.9

13.7

22.6

54B

erth

860

0 ft

1965

10.1

ft0.

200

19.6

%45

.3%

5.0

13.7

23.0

54B

erth

8A

475

ft30

5 ft

1965

10.2

ft0.

202

22.5

%50

.7%

5.2

13.7

19.0

NO

NE

W C

ON

ST

RU

CT

ION

TO

ST

AR

T64

Ber

th 1

460

0 ft

1957

9.7

ft0.

201

*10

0.0%

18.6

%46

.1%

18.0

3.3

24.3

61B

erth

15

600

ft19

609.

3 ft

0.19

0*

85.7

%18

.2%

46.1

%18

.07.

224

.958

Ber

th 1

9 (p

ortio

n)26

0 ft

1964

16.3

ft0.

357

16.5

%49

.2%

19.4

12.4

27.2

56B

erth

19

(por

tion)

390

ft19

6616

.5 ft

0.36

317

.6%

42.9

%20

.015

.025

.756

Ber

th 2

065

0 ft

1966

13.1

ft0.

267

20.8

%55

.5%

11.1

15.0

21.3

57B

erth

23

240

ft19

6617

.7 ft

0.39

8*

83.3

%19

.5%

38.3

%18

.015

.023

.157

Ber

th 2

4 (p

ortio

n)15

0 ft

1966

16.7

ft0.

368

*10

0.0%

16.1

%32

.7%

18.0

15.0

27.7

56B

erth

24

(por

tion)

570

ft19

679.

1 ft

0.18

7*

88.8

%16

.3%

42.9

%18

.016

.327

.556

Ber

th 2

565

0 ft

1967

11.5

ft0.

242

50.0

%12

.6%

51.8

%8.

916

.332

.5N

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

47B

erth

4E

255

ft70

ft19

7812

.6 ft

0.22

40.

5%5.

1%7.

230

.649

.047

Ber

th 5

900

ft19

7827

.8 ft

0.54

71.

6%13

.1%

37.0

30.6

47.5

60B

erth

613

0 ft

380

ft19

6513

.4 ft

0.28

4*

38.5

%19

.9%

60.0

%18

.013

.722

.6N

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

67B

erth

1D

240

ft19

6013

.5 ft

0.65

530

.5%

55.6

%47

.07.

28.

167

Ber

th 1

C20

0 ft

1960

14.1

ft0.

534

32.2

%52

.2%

35.8

7.2

5.8

67B

erth

1B

100

ft19

605.

5 ft

0.15

735

.0%

52.2

%1.

07.

22.

071

Ber

th 1

A10

0 ft

1956

13.0

ft0.

289

24.0

%46

.1%

13.2

2.0

17.0

61B

erth

26

670

ft19

6715

.9 ft

0.30

01.

6%74

.6%

14.2

16.3

47.5

61B

erth

27

670

ft19

6719

.4 ft

0.39

22.

1%55

.6%

22.7

16.3

46.8

53B

erth

4 (

port

ion)

700

ft19

7620

.5 ft

0.37

76.

8%37

.2%

21.3

28.0

40.4

51B

erth

4 (

port

ion)

200

ft19

7813

.5 ft

0.24

56.

5%0.

7%10

.4%

9.1

30.6

48.7

N/A

Ber

th 4

B35

5 ft

NE

WN

EW

NE

WN

EW

NE

WN

EW

NE

WN

EW

51B

erth

4C

220

ft19

7812

.6 ft

0.22

40.

5%5.

1%7.

230

.649

.0N

/AB

erth

4D

355

ftN

EW

NE

WN

EW

NE

WN

EW

NE

WN

EW

NE

W63

Ber

th 2

81,

450

ft19

6716

.2 ft

0.41

410

.0%

69.5

%24

.716

.336

.1N

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

67B

erth

11

75 ft

500

ft19

6516

.3 ft

0.35

520

.4%

50.7

%19

.313

.721

.948

Ber

th 1

261

5 ft

1984

31.2

ft0.

639

1.2%

11.8

%45

.638

.448

.0N

/AB

erth

12A

170

ftN

EW

NE

WN

EW

NE

WN

EW

NE

WN

EW

NE

W48

Ber

th 1

361

5 ft

1984

29.4

ft0.

581

4.5%

51.9

%40

.238

.443

.675

Ber

th 1

3A44

0 ft

300

ft19

5712

.6 ft

0.27

715

.3%

66.6

%12

.13.

328

.8N

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

42B

erth

33

800

ft19

9225

.9 ft

0.45

311

.3%

70.8

%28

.448

.834

.368

Ber

th 2

9 (p

ortio

n)10

0 ft

1967

26.0

ft0.

578

5.9%

26.9

%39

.916

.341

.652

Ber

th 2

9 (p

ortio

n)72

0 ft

1983

28.2

ft0.

534

12.4

%43

.9%

35.8

37.1

32.8

52F

PL

Can

al21

0 ft

1983

35.7

ft1.

713

7.7%

13.6

%48

.037

.139

.244

Ber

ths

33A

to 3

3C35

0 ft

510

ft19

9227

.7 ft

0.50

013

.5%

45.4

%32

.748

.831

.344

Dan

ia C

anal

300

ft48

0 ft

1992

56.0

ft2.

074

15.3

%46

.7%

49.0

48.8

28.8

NO

NE

W C

ON

ST

RU

CT

ION

TO

ST

AR

T46

Ber

th 3

11,

000

ft19

9231

.2 ft

0.54

911

.3%

49.2

%37

.248

.834

.346

Ber

th 3

21,

000

ft19

9228

.1 ft

0.50

210

.5%

46.7

%32

.948

.835

.447

Ber

th 3

098

5 ft

1992

26.9

ft0.

499

4.5%

26.4

%32

.648

.843

.6

No

tes:

1) F

or a

ll ra

tings

, a h

ighe

r ra

ting

valu

e re

pres

ents

bet

ter

curr

ent c

ondi

tions

.

Em

bed

Rat

io

4-4

4.2 RECOMMENDED SCHEDULE WITH MASTER/VISION PLAN

Once a proposed replacement order without the effects due to the Master/Vision

Plan Schedule was developed, the next step was to modify this proposed order to

account for the schedule of work shown on the drafts of the 5-Year Master Plan, 10-

Year Vision Plan and 20-Year Vision Plan, received by Halcrow on July 23, 2010. The

extension of Berth 4 to accommodate proposed future cruise vessels was moved from

2029 up to 2013, while the replacement of the existing Berth 4 remained in 2029. In

addition, by making some minor changes to off years and berth segment orders, the

remaining wall segments are all scheduled for within 2 years of the replacement year

listed in Table 4-1.

Since the order is quite similar to that shown in Table 4-1, a number of the

previous comments apply. Cathodic protection is still recommended to be installed

starting 2012 on wall segments scheduled for replacement in 2021 or later. The order

will still need to be reviewed no less than every 5 years and anytime wall movement or

significant fill loss is observed. The average length weighted age for the Northport and

Midport Berths remains about the same at 54 years (52 years when Southport Berths

are included) and the same four wall segments are being expected to be 65 years or

older at the time of replacement construction commencing (100 LF portion of Berth 3,

600 LF portion of Berths 14 & 15, Berth 13A and Berth 6).

NO

NE

W C

ON

ST

RU

CT

ION

TO

ST

AR

TIN

ST

ALL

CP

N/A

Ber

th 4

B35

5 ft

2010

-201

4Le

ngth

en B

erth

4N

EW

NE

WN

EW

NE

WN

EW

NE

WN

EW

35B

erth

4C

220

ft20

10-2

014

Leng

then

Ber

th 4

1978

0.22

40.

5%5.

1%7.

230

.649

.0N

/AB

erth

4D

355

ft20

10-2

014

Leng

then

Ber

th 4

NE

WN

EW

NE

WN

EW

NE

WN

EW

NE

W49

Ber

th 9

600

ft20

10-2

014

Ber

ths

9 &

10

1965

0.17

720

.1%

65.3

%2.

813

.722

.349

Ber

th 1

060

0 ft

2010

-201

4B

erth

s 9

& 1

019

650.

162

16.6

%56

.4%

1.4

13.7

27.1

NO

NE

W C

ON

ST

RU

CT

ION

TO

ST

AR

TN

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

61B

erth

153

5 ft

2015

-201

9B

erth

s 1,

2 &

319

560.

328

21.9

%49

.2%

16.8

2.0

19. 8

61B

erth

253

5 ft

2015

-201

9B

erth

s 1,

2 &

319

560.

257

18.8

%37

.0%

10.2

2.0

24.1

61B

erth

3 (

port

ion)

435

ft20

15-2

019

Ber

ths

1, 2

& 3

1956

0.36

520

.1%

46.1

%20

.22.

022

.377

Ber

th 3

(po

rtio

n)10

0 ft

2015

-201

9B

erth

s 1,

2 &

319

400.

043

*63

.0%

No

Dat

aN

o D

ata

18.0

1.0

1.0

58B

erth

16

550

ft20

15-2

019

Ber

ths

16, 1

7 &

18

1960

0.22

012

.7%

37.0

%6.

87.

232

.458

Ber

th 1

7 (p

ortio

n)32

5 ft

2015

-201

9B

erth

s 16

, 17

& 1

819

600.

180

10.8

%9.

8%36

.0%

3.1

7.2

36.3

54B

erth

17

(por

tion)

225

ft20

15-2

019

Ber

ths

16, 1

7 &

18

1964

0.25

513

.0%

32.2

%10

.112

.432

.054

Ber

th 1

855

0 ft

2015

-201

9B

erth

s 16

, 17

& 1

819

640.

262

17.5

%49

.2%

10.7

12.4

25.8

53B

erth

21

665

ft20

20-2

029

Ber

ths

21 &

22

1966

0.25

519

.4%

48.0

%10

.015

.023

.353

Ber

th 2

266

0 ft

2020

-202

9B

erth

s 21

& 2

219

660.

243

17.1

%41

.6%

9.0

15.0

26.4

NO

NE

W C

ON

ST

RU

CT

ION

TO

ST

AR

T56

Ber

th 7

600

ft20

20-2

029

Slip

1 R

ealig

nmen

t19

650.

264

19.9

%46

.7%

10.9

13.7

22.6

56B

erth

860

0 ft

2020

-202

9S

lip 1

Rea

lignm

ent

1965

0.20

019

.6%

45.3

%5.

013

.723

.056

Ber

th 8

A47

5 ft

305

ft20

20-2

029

Slip

1 R

ealig

nmen

t19

650.

202

22.5

%50

.7%

5.2

13.7

19.0

NO

NE

W C

ON

ST

RU

CT

ION

TO

ST

AR

T66

Ber

th 1

460

0 ft

2020

-202

9S

lip 3

Rea

lignm

ent

1957

0.20

1*

100.

0%18

.6%

46.1

%18

.03.

324

.363

Ber

th 1

560

0 ft

2020

-202

9S

lip 3

Rea

lignm

ent

1960

0.19

0*

85.7

%18

.2%

46.1

%18

.07.

224

.960

Ber

th 1

9 (p

ortio

n)26

0 ft

2020

-202

9B

erth

s 19

& 2

019

640.

357

16.5

%49

.2%

19.4

12.4

27.2

58B

erth

19

(por

tion)

390

ft20

20-2

029

Ber

ths

19 &

20

1966

0.36

317

.6%

42.9

%20

.015

.025

.758

Ber

th 2

065

0 ft

2020

-202

9B

erth

s 19

& 2

019

660.

267

20.8

%55

.5%

11.1

15.0

21.3

59B

erth

23

240

ft20

20-2

029

Ber

ths

23, 2

4 &

25

1966

0.39

8*

83.3

%19

.5%

38.3

%18

.015

.023

.159

Ber

th 2

4 (p

ortio

n)15

0 ft

2020

-202

9B

erth

s 23

, 24

& 2

519

660.

368

*10

0.0%

16.1

%32

.7%

18.0

15.0

27.7

58B

erth

24

(por

tion)

570

ft20

20-2

029

Ber

ths

23, 2

4 &

25

1967

0.18

7*

88.8

%16

.3%

42.9

%18

.016

.327

.558

Ber

th 2

565

0 ft

2020

-202

9B

erth

s 23

, 24

& 2

519

670.

242

50.0

%12

.6%

51.8

%8.

916

.332

.5N

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

49B

erth

4E

255

ft70

ft20

20-2

029

Slip

2 R

ealig

nmen

t19

780.

224

0.5%

5.1%

7.2

30.6

49. 0

49B

erth

590

0 ft

2020

-202

9S

lip 2

Rea

lignm

ent

1978

0.54

71.

6%13

.1%

37.0

30.6

47.5

62B

erth

613

0 ft

380

ft20

20-2

029

Slip

2 R

ealig

nmen

t19

650.

284

*38

.5%

19.9

%60

.0%

18.0

13.7

22.6

NO

NE

W C

ON

ST

RU

CT

ION

TO

ST

AR

T69

Ber

th 1

D24

0 ft

1960

0.65

530

.5%

55.6

%47

.07.

28.

169

Ber

th 1

C20

0 ft

1960

0.53

432

.2%

52.2

%35

.87.

25.

869

Ber

th 1

B10

0 ft

1960

0.15

735

.0%

52.2

%1.

07.

22.

073

Ber

th 1

A10

0 ft

1956

0.28

924

.0%

46.1

%13

.22.

017

.053

Ber

th 4

(po

rtio

n)70

0 ft

2020

-202

9S

lip 2

Rea

lignm

ent

1976

0.37

76.

8%37

.2%

21.3

28.0

40.4

51B

erth

4 (

port

ion)

200

ft20

20-2

029

Slip

2 R

ealig

nmen

t19

780.

245

6.5%

0.7%

10.4

%9.

130

.648

.763

Ber

th 2

667

0 ft

1967

0.30

01.

6%74

.6%

14.2

16.3

47.5

63B

erth

27

670

ft19

670.

392

2.1%

55.6

%22

.716

.346

.8N

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

65B

erth

28

1,45

0 ft

1967

0.41

410

.0%

69.5

%24

.716

.336

.141

Ber

th 3

380

0 ft

1992

0.45

311

.3%

70.8

%28

.448

.834

.369

Ber

th 1

175

ft50

0 ft

2020

-202

9S

lip 3

Rea

lignm

ent

1965

0.35

520

.4%

50.7

%19

.313

.721

.950

Ber

th 1

261

5 ft

2020

-202

9S

lip 3

Rea

lignm

ent

1984

0.63

91.

2%11

.8%

45.6

38.4

48.0

N/A

Ber

th 1

2A17

0 ft

2020

-202

9S

lip 3

Rea

lignm

ent

NE

WN

EW

NE

WN

EW

NE

WN

EW

NE

W50

Ber

th 1

361

5 ft

2020

-202

9S

lip 3

Rea

lignm

ent

1984

0.58

14.

5%51

.9%

40.2

38.4

43.6

77B

erth

13A

440

ft30

0 ft

2020

-202

9S

lip 3

Rea

lignm

ent

1957

0.27

715

.3%

66.6

%12

.13.

328

.8N

O N

EW

CO

NS

TR

UC

TIO

N T

O S

TA

RT

69B

erth

29

(por

tion)

100

ft19

670.

578

5.9%

26.9

%39

.916

.341

. 653

Ber

th 2

9 (p

ortio

n)72

0 ft

1983

0.53

412

.4%

43.9

%35

.837

.132

.853

FP

L C

anal

210

ft19

831.

713

7.7%

13.6

%48

.037

.139

.245

Ber

ths

33A

to 3

3C35

0 ft

510

ft20

20-2

029

Sou

thpo

rt B

ulkh

ead

Ext

.19

920.

500

13.5

%45

.4%

32.7

48.8

31.3

45D

ania

Can

al30

0 ft

480

ft20

20-2

029

Sou

thpo

rt B

ulkh

ead

Ext

.19

922.

074

15.3

%46

.7%

49.0

48.8

28.8

NO

NE

W C

ON

ST

RU

CT

ION

TO

ST

AR

T47

Ber

th 3

11,

000

ft19

920.

549

11.3

%49

.2%

37.2

48.8

34. 3

47B

erth

32

1,00

0 ft

1992

0.50

210

.5%

46.7

%32

.948

.835

.448

Ber

th 3

098

5 ft

1992

0.49

94.

5%26

.4%

32.6

48.8

43.6

No

tes:

1) F

or a

ll ra

tings

, a h

ighe

r ra

ting

valu

e re

pres

ents

bet

ter

curr

ent c

ondi

tions

.

5-1

5. CATHODIC PROTECTION

5.1 EVALUATION OF EXISTING IMPRESSED CURRENT EQUIPMENT

On April 5th, 2010 one of Halcrow’s electrical engineers experienced in the

cathodic protection design made a site visit to review the condition of existing impressed

current equipment at Berths 4, 5, 12, 13, 16, 17, 18 and 29. The original goal of this site

visit was to visually gauge the condition of the equipment and gather information to

prepare for a testing of the equipment on a future site visit, with the ultimate goal of

assessing the possibility of rehabilitating the existing equipment. However, the April

2010 visual assessment provided enough information to ascertain that the condition of

the existing equipment was not suitable for rehabilitation. The following is a brief

summary of the conditions observed during the site visit. A memo with more details,

including a berth by berth description and photographs, is included as Appendix C of

this report.

In review of the existing conditions, it was apparent that major portions of the

existing cathodic protection systems had not been active for a considerable time.

Rectifier and switch enclosures were partially, if not severely, corroded and in some

cases were even used for debris and food disposal. Several junction boxes were bolted

shut preventing inspection; however, the level of corrosion on the boxes themselves

suggested that the condition of the junction boxes would not be significantly better than

the rectifiers. In addition to the high levels of corrosion, some of the equipment was

found to be damaged. While some of the conduit and equipment were found to be in

good condition, the overall condition of the existing cathodic protection system was

deemed to be insufficient for rehabilitation.

5.2 LIFE CYCLE COSTS OF CATHODIC PROTECTION SYSTEMS

The protection of new and existing steel structures immersed in water can be

accomplished with either a sacrificial anode or an impressed current cathodic protection

system.

In a sacrificial anode cathodic protection system, the steel is protected by

installing a metal more susceptible to corrosion (anodic) than steel. Once installed the

electro-chemical reaction that causes steel to corrode will instead cause the sacrificial

anode to corrode, thus protecting the steel. Thus, in a sacrificial anode system, the

5-2

protection is dependant upon the size of the anode and the difference in galvanic

potential between the anode and the protected structure.

Alternatively, a similar process can be achieved by installing smaller anodes and

conducting a small current through the structure. The current in the structure causes

the steel to become more resistant to corrosion (or cathodic).

Either system can be used to protect sheet pile bulkhead systems, the major

difference between the systems is the use of the electrical current. The sacrificial

anode system generally requires larger and heavier anodes. However, once installed,

sacrificial anodes require only minimal maintenance. The anodes should be periodically

inspected to identify damage or irregular anode loss but, until the anodes require

replacement, no other maintenance cost is required. An impressed current system

requires paying for the electricity, additional testing to modify the protection levels over

time and repairs to the rectifiers or other equipment.

To provide an equitable comparison, life cycle costs for both systems at every

berth in Port Everglades were generated. These life cycle costs were generated for

approximate designs at each berth. A description of the assumptions used for the

approximate designs is included as Appendix D. Included in the life cycle costs were

the cost for installation of the cathodic protection systems; electricity costs for the

impressed current systems; estimations of regular maintenance costs (assumed

performed by a vendor under contract to the Port); above and below water inspections

every 3 years (assumed performed by a vendor under contract to the Port) and the

replacement of all anodes after 25 years. For the estimation of the life cycle costs, all

systems were assumed installed in 2012 and the costs were run out for a 50 year life

cycle. To account for inflation and the cost of money, the Construction Cost Index was

taken as 3.7% per Engineer News Record Historical Data; the Consumer Price Index

was taken as 3.0% per Engineer News Record Historical Data and the Discount Rate

was taken as 5.0% based upon Current South Florida Municipal Bonds.

The summary of the results for the 50 Year Life Cycle Costs in Discounted

Dollars are included in this report as Appendix E; the results in Real 2010 Dollar Terms

are included in Appendix F; and the results in Nominal Dollar Terms are included in

Appendix G. In addition to the summaries, Appendix E also includes the predicted

annual costs in discounted dollars for both systems and each berth segment (although

5-3

not included, annual cost break downs in either real dollar or nominal dollar terms can

be produced upon request).

For installation of cathodic protection on the existing sheet pile walls of Port

Everglades, the life cycle costs generated for this report clearly suggest that sacrificial

anode systems are the superior choice. Although the anodes required in a sacrificial

anode system are considerably larger, this cost is more than made up for by the costs

associated with cutting and repairing the upper deck surface to allow for the installation

of the conduit and wiring required to connect the rectifiers, anodes and sheets. During

the operation of both systems an underwater dive inspection every three years is

included in the life cycle costs. In addition, the impressed current system also includes

the cost for electricity, monthly load readings and an annual above-water equipment

inspection.

Since the impressed current system is expected to be more expensive to install

and operate, Halcrow recommends the use of sacrificial anode cathodic protection for

the existing walls of Port Everglades.

6-1

6. PROBABLE CONSTRUCTION COSTS FOR PLANNING

The following construction costs are provided for planning purposes only.

These costs are based upon approximate designs using assumed design

parameters. The requirements of a final design may vary and produce considerably

different construction costs. For instance, work performed on longer lengths of

bulkhead or combined together may produce lower cost per linear foot of berth as the

fixed costs are spread over a larger area. Similarly, restrictions on schedule or access

to the site would be expected to increase the costs per linear foot.

Finally, the costs listed below are based upon 2010 labor, equipment and

material costs. Due to variability of each of these factors, no effort to predict changes

for work performed in future years has been made for these probable construction costs

for planning purposes.

Therefore Halcrow recommends that during planning, an appropriate contingency

factor be selected by the Port and added to these planning costs.

6.1 PLANNING COSTS FOR SACRIFICIAL ANODES

Based upon the approximate sacrificial anode cathodic protection designs and

installation costs performed for the Life Cycle Cost comparison (described in Section

5.2 of this report); Halcrow estimates that the probable 2010 cost for installation of

sacrificial anodes on the existing bulkheads at Port Everglades would be approximately

$450 per linear foot of berth length. This cost includes the aluminum anodes,

underwater welding, installation of a test station at each berth and performing the initial

testing of the system.

In addition, the costs of the design can vary widely depending upon the specific

installation location. For instance, the various sheet pile sections and berth depths

throughout the Port produce different surface areas requiring protection (in this estimate

the costs varied from $350 per linear foot to $510 per linear foot due to the changes in

surface area requiring protection).

6-2

6.2 PLANNING COSTS FOR IMPRESSED CURRENT

During Halcrow’s Life Cycle Cost comparison (described in Section 5.2 of this

report), it was determined for the existing walls of Port Everglades sacrificial anode

cathodic protection was preferable to impressed current. Installation of impressed

current systems were found to be more expensive due to the extensive behind and

through the wall work required installing conduit for the electrical connections between

the rectifiers, the sheet piles and the anodes. In addition, the annual operating costs

due to electricity, increased testing and maintenance were higher than for sacrifical

anodes as well. Therefore, the planning costs for installation of impressed current

systems are provided for completeness only.

Based upon the approximate impressed cathodic protection designs and

installation costs performed for the Life Cycle Cost comparison, Halcrow estimates that

the probable 2010 cost for installation of impressed current on the existing bulkheads at

Port Everglades would be approximately $675 per linear foot of berth length. This cost

includes the installation of rectifiers along the berth, creating electrical continuity

between steel sheet pile sections with underwater welding, installation of the anodes,

installation of conduits and wiring to connect the rectifiers to the system, installation of

test stations along each berth and performing the initial testing of the system.

In addition, the costs of the design can vary widely depending upon the specific

installation location. For instance, the various sheet pile sections and berth depths

throughout the Port produce different surface areas requiring protection (in this estimate

the costs varied from $315 per linear foot to $925 per linear foot due to the changes in

surface area requiring protection).

6.3 PLANNING COSTS FOR REPLACEMENT WALL CONSTRUCTION

To produce planning costs for the installation of a replacement wall installed in

front of the existing bulkhead wall, several recent Opinions of Probable Costs (OPC) for

replacement steel pipe-sheet pile combination bulkheads were reviewed. These OPC’s

were generated by Halcrow cost estimators familiar with marine construction. The

designs and installation conditions for the bulkheads included in the OPC’s are similar

to those expected at Port Everglades.

6-3

Based upon these recent Opinions of Probable Costs for replacement steel pipe-

sheet pile combination bulkheads, Halcrow recommends a cost of approximately

$12,000 per linear foot of bulkhead be used for the replacement of steel sheet pile

bulkheads. This cost includes the cost for removal and storing of existing fenders,

installation of a pipe-sheet pile combination wall seaward of the existing wall, installation

of new soil or rock anchors to tie back the wall, installation of a concrete cap on the new

wall, filling the void between the new and existing wall with suitable fill and reinstalling

the existing fenders.

Please note that this planning cost is only for the bulkhead wall. The portions of

Berths 4, 5, 6, 7, 8, 9, 10, 11, 12, 33 and the Turning Notch where existing land is to be

excavated in front of the wall, the costs for excavation, remediation and disposal of this

soil is not included.

6.4 PLANNING COSTS FOR TOE WALL CONSTRUCTION

The 2007 “Port Everglades Toewall Improvements & Bulkhead Analysis” Report

by Lakdas/Yohalem Engineering included a cost for installation of a toe wall. However,

this 2007 report also noted:

“… the toe wall does not provide any additional resistance to failure modes other than

toe failure; while the installation of a new steel sheet pile bulkhead should increase

resistance to multiple failure mechanisms. Since the new SSP wall would provide an

increased resistance to multiple failure mechanisms, installation of new sheet pile would

be expected to provide a longer design life than toe wall repairs. This longer design life

is expected to make up for the price difference over the life of the work.”

Halcrow recommends installation of a replacement sheet pile wall over the installation of

a toe wall. However, for consistency, a planning cost for installation of toe wall is

included.

6-4

To produce planning costs for the installation of a toe wall installed in front of the

existing bulkhead wall, a recent Opinion of Probable Costs (OPC) for toe wall was

reviewed. This OPC was generated by a Halcrow cost estimator to provide an alternate

option to one of the OPC’s used for the replacement wall costs. Halcrow recommends

a cost of approximately $5,000 per linear foot of bulkhead be used for the installation of

a toe wall. This cost includes the cost for removing the existing fenders to allow for the

wall installation, installation of a sheet pile toe wall seaward of the existing wall, filling

the void between the existing wall and the toe wall with tremie concrete and reinstalling

the existing fenders.

7-1

7. CONCLUSION

Halcrow recommends that Port Everglades implement the Recommended

Schedule including Master/Vision Plan shown in Table 4-5. This schedule includes the

installation of replacement steel sheet pile bulkhead walls with new wall anchorage

systems throughout Port Everglades by 2041. To reduce the rate of ongoing corrosion

on those walls that are scheduled for later replacement, Halcrow also recommends that

sacrificial anode cathodic protection systems be installed and maintained on all existing

wall segments scheduled for replacement in 2021 or later. Installation of cathodic

protection should start no later than 2012.

This replacement order has been developed based upon the current conditions

of the walls and coordination with projects included in the current draft versions of Port

Everglades Master / Vision Plans. This replacement order should be reviewed no less

than every 5 years to address changes in the wall conditions and/or the latest Master /

Vision Plans.

To monitor any ongoing changes in the conditions of the walls, Port Everglades

should continue performing regular above and below water inspections of the walls

throughout the Port. Halcrow recommends that detailed underwater inspections be

performed no less than every two years. These detailed inspections should meet or

exceed the requirements of a Level II Routine Inspection, as described in ASCE’s

Underwater Investigations: Standard Practice Manual (2001). These detailed

inspections shall include a visual “swim-by” of all bulkheads in the Port and the cleaning

of marine growth and steel sheet pile thickness measurements at regular intervals along

the bulkhead walls. To better monitor the condition of the walls, it is recommended that

the interval between thickness measurement stations be 100 feet (similar to the 2006

inspection).

In addition, benchmarks on the cap or cap wall of each berth should be

established for monitoring possible movement of the top of the wall. Plane surveys of

these benchmarks should be performed no less than twice a year and compared to

previous surveys. Movement of the top of the wall will be evident by changes in the

plane surveys.

A-1

APPENDIX A 2007 Port Everglades “Toewall Improvements &

Bulkhead Analysis” Report: Volume Iby Lakdas/Yohalem Engineering

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 1 of 26

TABLE OF CONTENTS Table of Contents ..................................................................................................................1

List of Figures ...................................................................................................................1 List of Tables ....................................................................................................................2

Port Everglades .....................................................................................................................3 Scope of Work ......................................................................................................................5 Steel Sheet Pile Bulkheads ....................................................................................................6 Existing Bulkhead Performance...........................................................................................10

Deep-Seated Soil Failure .................................................................................................11 Wale System Failure........................................................................................................11 Anchor Passive Failure ....................................................................................................12 Flexural Failure of Sheet Piling .......................................................................................13 Tie Rod Failure ...............................................................................................................14 Rotational Failure Do To Inadequate Penetration (Toe Failure) .......................................15

Remediation and Cost Comparisons ....................................................................................18 Auger Cast Pile Toe Wall ................................................................................................19 New Steel Sheet Pile Bulkhead........................................................................................20

Recommendations ...............................................................................................................21 References...........................................................................................................................26

List of Figures Figure 1. Layout of Port Everglades .....................................................................................4 Figure 2. Example of a Z-type SSP.......................................................................................6 Figure 3. Example of an H-Z combi-wall..............................................................................6 Figure 4. Relationship between Age and Average Section Loss ............................................9 Figure 5. Deep-seated soil failure .......................................................................................11 Figure 6. Wale system failure .............................................................................................11 Figure 7. Anchor passive failure .........................................................................................12 Figure 8. Flexural failure of piling ......................................................................................13 Figure 9. Tie rod failure......................................................................................................14 Figure 10. Rotational failure due to inadequate penetration..................................................15

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 2 of 26

List of Tables Table 1. Northport Bulkhead Summary ................................................................................7 Table 2. Midport & Southport Bulkhead Summary...............................................................8 Table 3. Northport Embedment Computer Analysis Summary............................................16 Table 4. Midport and Southport Embedment Computer Analysis Summary........................17 Table 5. Conceptual Rehabilitation Options Comparison ....................................................18 Table 6. Conceptual Costs for Auger Cast Pile Toe Wall Installation..................................19 Table 7. Conceptual Costs for Installation of New Bulkhead, in front of Existing ...............20 Table 8. Proposed Steel Sheet Pile (SSP) Replacement Order.............................................22 Table 9. Northport Pile Tip and Dredge Elevation Summary ..............................................24 Table 10. Midport & Southport Pile Tip and Dredge Elevation Summary...........................25

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 3 of 26

PORT EVERGLADES Port Everglades is a major economic engine, providing more than 15,000 direct jobs

and generating $2.79 billion in business activity (Port Everglades Department, 2007, p. 6). Port Everglades ranks among the top 15 U.S. cruise and container ports with 534 cruise departures in 2006, #2 rank; 1,144,500 cruise passengers departed in 2006, #3 rank; 634,230 TEU’s of total container foreign trade in 2006, #12 rank; and 4,916,000 metric tones of containerized foreign trade (MARAD, 2007). In addition, the Port handled more than 123,479,901 barrels of petroleum products, 379,535 tons of breakbulk materials and 2,954,310 tons of dry bulk materials in 2006 (Port Everglades Department, 2007, p. 38).

The Port’s 25,222 linear feet of berthing space accommodated 5,510 total ship calls in 2006, (Port Everglades Department, 2007, p. 38 & 45). Currently, Port Everglades are grouped by geography into one of the designations; Northport, Midport and Southport. However, the limits of these designations are not precise and may vary from report to report. Therefore, in this report, the definitions of these zones are based upon those give in the HPA’s 2006 “Underwater Inspection and Baseline Survey Assessment of Port Everglades Berths 1 through 33” report:

• “Northport encompasses Berth 1 through 13 (including Berths 1A through 1D, 4A, 8A, and 13A) and supports various dry bulk, liquid bulk, and cruise ship operations.” (HPA, 2006)

• “Midport encompasses Berths 14 through 29 (including the Florida Power & Light (FP&L) cooling canal bulkhead adjacent to Berth 29) and supports dry bulk, breakbulk, ro/ro, and cruise ship operations.” (HPA, 2006)

• “Southport encompasses Berths 30 through 33 (including Berths 33A through 33C) and supports containerized cargo ships and ro/ro operations.” (HPA, 2006)

Fig

ure

1. L

a

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 5 of 26

SCOPE OF WORK Lakdas/Yohalem Engineering (LYE) has been tasked with performing a complete

analysis of the bulkheads at Port Everglades. As part of this work LYE, and its subconsultants, performed the following:

• Lakdas/Yohalem Engineering (LYE) reviewed previous drawings, reports and other information provided by Port Everglades staff; these reviews included, but were not limited to:

o Construction and As-Built Drawings for various Berths.

o Port Everglades Authority Drawing No. 92S 3912 – “Steel Sheet Piling and Bulkhead Data”

o “Bulkhead Structural and Cathodic Protection Study” by Bermello-Ajamil & Partners, Inc.; July 1997.

o “Southport Bulkhead Corrosion Study: Southport Berths 30, 31, 32, 33, Midport Berth 25 – Final Report” by Craven Thompson & Associates and Han-Padron Associates, Consulting Engineers; December 1999.

o “Underwater Inspection and Baseline Survey Assessment of Port Everglades Berths 1 through 33” by HPA; April 2006.

o Hydrographic Survey soundings performed between 3/24/2004 and 7/02/2007.

• Tierra, Inc. performed the geotechnical investigation. For more information on the Geotechnical Engineering Services performed by Tierra, see Volume II.

• LYE performed a top side structural survey. For more information on the Structural Survey of Docks performed by LYE, see Volume II.

• Southern Cathodic Protection Company (SCPC) performed condition surveys of the existing cathodic protection systems at Port Everglades. For more information on the Cathodic Protection Systems On-Site Condition Surveys performed by SCPC, see Volume II.

• LYE performed a series of engineering analyses of some of the SSP at the port. These analyses included reviews of existing condition, selected results included in Volume III-A, and after proposed COE future dredging, selected results included in Volume III-B.

• River Consulting, LLC provided consultation on analysis and technical writing.

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 6 of 26

STEEL SHEET PILE BULKHEADS The Port Everglades 25,222 linear feet of

berthing facilities (Port Everglades Department, 2007, p. 45) includes approximately 24,400 linear feet of steel sheet pile (SSP) bulkhead (Port Everglades Authority, 1992).

These bulkheads can be broken into broad categories: Z-type SSP and H-Z combi-walls. The Z-type SSP walls are composed exclusively of rolled steel, sheet pile sections (see Figure 2). While the H-Z combination walls, or combi-walls, are composed of pairs of Z-type SSP sections between rolled steel H-pile shapes (see Figure 3). The inclusion of the H shaped, king piles increases the stiffness of a wall when compared to a wall of only the Z-type shapes.

Like all metals exposed to saltwater and air, SSP sections tend to corrode due to rust oxidation. To delay the onset of corrosion, sheet pile sections are typically coated with an epoxy or other resilient material before installation. In addition, some of the Berths at Port Everglades were equipped with impressed current or sacrificial anode cathodic protection systems. However, over time all systems will eventually succumb to corrosion.

Southern Cathodic Protection’s review of the existing cathodic protection concludes that most of the cathodic protection systems have “reached… useful design life” (see Volume II for complete reports). Therefore any currently observed section loss will continue to increase, if left in the current condition. The typical recommendation from Southern Cathodic Protection is to abandon the impressed current systems and evaluate the viability of installing sacrificial aluminum anodes.

Tables 1 and 2 summarize the length, age, wall type and average section loss listed in HPA’s Underwater Inspection Report (2006). As can be seen in Figure 4, the corrosion section loss of the bulkheads in Northport and Southport typically increase with age and approximately 63% of the bulkhead linear footage was installed prior to 1968 (62% of Northport and 91% of Midport).

Figure 2. Example of a Z-type SSP (after Arcelor RPS)

Figure 3. Example of an H-Z combi-wall (after Arcelor RPS)

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 7 of 26

Table 1. Northport Bulkhead Summary Berths & Slips Approximate

Length 1

(ft)

Year of

Typical Construction 2

Typical Wall Type 3

Average of Section Losses Listed in 2006 HPA Report 4

Northport Berths

Berths 1A-1D 640 ft 1960 Z-type SSP 43%

Berths 1-3 1,600 ft 1956 Z-type SSP 35%

Berths 4, 4A & 5 (Slip 2)

2,100 ft 1976 H-Z Combi-wall 10%

Berth 6 378 ft 1956 Z-type SSP 37%

Berths 7, 8, 8A, 9 & 10 (Slip 1)

2,706 ft 1965 Z-type SSP 35%

Berth 11 497 ft 1965 Z-type SSP 39%

Berths 12, 13 & 13A (Slip 3)

1.531 ft 1984 H-Z Combi-wall 16%

Notes: 1. Lengths taken from Drawing 92S 3912 (Port Everglades Authority, 1992), unless otherwise noted.

2. “Typical Year of Construction” is the year the majority of the currently visible SSP installed; from Drawing 92S 3912, unless otherwise noted.

3. “Typical Wall Type” is the description of the majority of the currently visible SSP installed; Drawing 92S 3912, unless otherwise noted.

4. “Average of Section Loss Listed in 2006 HPA Report” is the average of the readings listed in HPA 2006 Report’s Detailed Inspection Findings Section. These readings appear to be the maximum reading from 9 thickness measurements taken at a given station. Therefore these values my not be representative of the entire wall.

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 8 of 26

Table 2. Midport & Southport Bulkhead Summary Berths & Slips Approximate

Length 1

(ft)

Year of

Typical Construction 2

Typical Wall Type 3

Average of Section Losses Listed in 2006 HPA Report 4

Midport Berths

Berths 14-15 (Slip 3)

1,201 ft 1960 Z-type SSP 30%

Berths 16-18 1,648 ft 1960 Z-type SSP 23%

Berths 19-20 1,300 ft 1966 Z-type SSP 33%

Berths 21-22 1,325 ft 1966 Z-type SSP 33%

Berth 23 240 ft 1966 Z-type SSP 34%

Berths 24-25 1,608 ft 1967 Z-type SSP 26%

Berths 26-27 668 ft 1967 Z-type SSP 24%

Berth 28 1,448 ft 1967 Z-type SSP 20%

Berth 29 789 ft 1983 H-Z Combi-wall 22%

FP&L Canal 107 ft 1983 Z-type SSP 7%

Southport Berths

Berth 30 1,003 ft 1992 H-Z Combi-wall 14%

Berths 31-32 2,000 ft 1992 H-Z Combi-wall 27%

Berth 33 798 ft 1992 H-Z Combi-wall 25%

Berths 33A-33C 5 800 ft 1992 H-Z Combi-wall 28%

Notes: 1. Lengths taken from Drawing 92S 3912 (Port Everglades Authority, 1992), unless otherwise noted.

2. “Typical Year of Construction” is the year the majority of the currently visible SSP installed; from Drawing 92S 3912, unless otherwise noted.

3. “Typical Wall Type” is the description of the majority of the currently visible SSP installed; Drawing 92S 3912, unless otherwise noted.

4. “Average of Section Loss Listed in 2006 HPA Report” is the average of the readings listed in HPA 2006 Report’s Detailed Inspection Findings Section. These readings appear to be the maximum reading from 9 thickness measurements taken at a given station. Therefore these values my not be representative of the entire wall.

5. Length, year and typical type for Berths 33A-33C taken from HPA 2006 Report.

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 9 of 26

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

50%

Berth

6 (1

956)

Berth

s 1-3

(195

6)

Berth

s 1A-1

D (196

0)

Slip 3

: Ber

ths 14

-15

(196

0)

Berth

s 16-

18 (1

960)

Berth

11 (1

965)

Slip 1

: Ber

ths 7

, 8, 8

A, 9 &

10

(196

5)

Berth

23 (1

966)

Berth

s 19-

20 (1

966)

Berth

s 21-

22 (1

966)

Berth

s 24-

25 (1

967)

Berth

s 26-

27 (1

967)

Berth

28 (1

967)

Slip 2:

Ber

ths 4

, 4A &

5 (1

976)

Berth

29 (1

983)

FP&L Can

al (1

983)

Slip 3

: Ber

ths 12

, 13

& 13A

(198

4)

Berth

s 33A

-33C

(199

2)

Berth

s 31-

32 (1

992)

Berth

33 (1

992)

Berth

30 (1

992)

Ave

rag

e S

ecti

on

Lo

sses

in 2

006

HP

A R

epor

t

Figure 4. Relationship between Age and Average Section Loss

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 10 of 26

EXISTING BULKHEAD PERFORMANCE Based upon reviewing the HPA’s “Underwater Inspection and Baseline Survey”

report (2006), existing drawings provided by Port Everglades and the sheet pile wall computer analysis performed by LYE; generalizations on the performance of the bulkheads can be made. These generalizations are based upon the current conditions of the bulkheads and do not account for any future improvements, deteriorations or other changes.

Anchored sheet pile walls have multiple potential structural failure mechanisms. For completeness, the failure mechanisms reviewed herein will be based upon the U.S. Army Corps of Engineer’s Design of Sheet Pile Walls (1994, p. 5-1 to 5-12). The “Modes of Failure” for anchored sheet pile walls presented by the Army Corps of Engineers are:

• Deep-seated soil failure

• Wale system failure

• Anchor passive failure

• Flexural failure of sheet piling

• Tie rod failure

• Rotational failure due to inadequate penetration (commonly called a toe failure)

Each mechanism will be rated based upon the general perceived probability of occurrence throughout the port over the short term. A five point scale will be used to represent various levels of the perceived probability of occurrence:

• Minimal concern

• Minor concern

• Moderate concern

• Significant concern

• Severe concern

These ratings are for generalizations of all sections of bulkhead throughout the port. Isolated incidences of increased corrosion, damage, and/or loading conditions are expected to occur and may lead to localized issues. Localized issues are to be expected in any system.

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 11 of 26

Deep-Seated Soil Failure A deep-seated soil failure is a large scale

movement of the soil mass on both sides of the sheet pile wall. As noted by the Army Corps of Engineers is “independent of the structural characteristics of the wall” and is due entirely to the resistance of the soil mass to shearing.

The geotechnical investigations of this area, both those preformed for this investigation and previously, describe the deeper geologic strata as sand, cemented sand, sandstone and limestone. All of these soil layers exhibit relatively high resistance to shearing. Therefore even without performing detailed soil stability analyses, the probability of a deep-seated soil failure occurring under the Port Everglades bulkheads is of minimal concern.

This conclusion is further strengthened by the wide spread use of sheet pile bulkheads throughout the deep water ports of Florida, without a large scale deep-seated soil failure.

Wale System Failure A wale system failure is a separation of the wall

from the tie rod. This type of failure mechanism is a function of the loading conditions and connection detailing.

A review of the typical section shown in HPA’s report and selected construction or “As-Built” drawings provided by the Port Everglades staff show that the typical wale system is encased in the concrete cap wall. Therefore for this mechanism to develop the steel connections between the tie rods, the wale and/or the sheet pile would need to be stressed to the point of yield. As these connections begin to deform the stress would be transferred to the surrounding concrete through bearing and bond transfer.

In most instances, the forces required for a wale system failure would exceed those required to produce other failure modes. Therefore, a wale system failure is estimated to be of only minimal concern.

Figure 5. Deep-seated soil failure (after U.S. Army Corps of Engineers)

Figure 6. Wale system failure (after U.S. Army Corps of Engineers)

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 12 of 26

Anchor Passive Failure Anchor passive failure is the movement of the

anchorage system. This type of failure mechanism is a function of soil strength, geometry and loading conditions.

During anchor passive failure, the tie back force required for wall stability is greater that the resistance provided by the soil in front of the anchor system. In new construction, this type of failure is typically due to inadequate sizing and/or geometry of the anchorage system. While in existing construction, this type of failure is typically due to an increased surcharge or lateral load.

During the analysis of the Port Everglades bulkheads, LYE estimated the soil passive capacity for a representative anchor system using classical soil mechanics methods. Then this capacity was compared the required anchor force determined during the sheet pile wall analyses. The estimated passive capacity was less than the required anchor force for a number of the wall systems reviewed.

However, if anchor passive failure was developing noticeable movement of the sheet pile would be expected, but this was not observed in the field. The HPA underwater inspection did not note any instances of the sheet pile wall tilting out. Nor did the LYE topside “Structural Survey of Docks” note distress that was consistent with the movement of the sheet pile wall.

Although the estimated passive capacity in the LYE analysis suggested this failure mechanism may be of concern, since no visible signs of wall movement were noted; the potential for anchor passive failure is estimated to be a minor concern.

Figure 7. Anchor passive failure (after U.S. Army Corps of Engineers)

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 13 of 26

Flexural Failure of Sheet Piling Flexural failure of the sheet piling occurs when

the stress in the steel sheet pile section is high enough to develop a plastic hinge. This type of failure mechanism is a function of the loading conditions, steel sheet pile properties and deterioration.

During flexural failure of the sheet piling, the stress in the sheet pile is such that at one location the entire cross section has reached the yield stress of the steel. At this point displacement of the wall will increase without a corresponding increase in loading. This condition is referred to a plastic hinge because the response of the wall behaves similarly to a beam with a hinge. Depending upon the embedment, this hinge may lead to instability of the wall. In existing construction, the stress in the sheet pile may be increased through either increased loading and/or section loss due to corrosion of the sheet pile.

The HPA underwater inspection included spot checks of steel sheet pile thickness measurements using an ultrasonic thickness gauge. As would be expected from sheet piles exposed to seawater for long durations, a significant number of the measurements listed in the HPA report would be classified as a state of “advanced” corrosion based upon the HPA defined damage grades (between 30-50% section loss).

However, if high flexural stresses were developing in the sheet pile noticeable movement of the sheet pile below mid water depth would be expected, but this was not observed in the field. The HPA underwater inspection did not note any instances of the sheet pile displacements.

Although “advanced” stages of sheet pile corrosion was observed by HPA in the diving inspection, no visible signs of wall displacement below the waterline were noted. Therefore, the potential for flexural failure of the sheet piling is estimated to be a minor concern.

Figure 8. Flexural failure of piling (after U.S. Army Corps of Engineers)

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 14 of 26

Tie Rod Failure Tie rod failure is the yielding and/or fracture of

the steel tie rods connecting the sheet pile wall and the anchor. This type of failure mechanism is a function of the loading conditions, steel rod properties and deterioration.

During tie rod failure, the anchor force required to support wall equilibrium exceeds the capacity of the tie rods. In existing construction this type of failure is typically do to corrosion decreasing the tie rod section area and/or new loadings increasing the stress on the tie rods.

If forces in the tie rods exceeded the yield stress of the tie rod steel noticeable movement of the sheet pile would be expected, but this was not observed in the field. The HPA underwater inspection did not note any instances of the sheet pile wall tilting out. Nor did the LYE topside “Structural Survey of Docks” note distress that was consistent with the movement of the sheet pile wall.

In addition the topside “Structural Survey of Docks”, LYE excavated and visually reviewed a limited number of tie rods. The review of tie rods was limited to a small sample since visual review of tie rods requires excavation at several locations behind the wall; a potential for significant impact on operations. The tie rods visually reviewed did not exhibit signs of significant section loss due to corrosion. However, the age of the bulkheads in Port Everglades (56.5% of the visible sheet pile wall was installed between 1960 and 1968 with an addition 10.2% installed prior to 1960) there is a distinct possibility of tie rod corrosion.

Due to the possibility of unseen corrosion but with no obvious signs of wall movement, the potential for tie rod failure is estimated to be of moderate concern.

Figure 9. Tie rod failure (after U.S. Army Corps of Engineers)

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 15 of 26

Rotational Failure Do To Inadequate Penetration (Toe Failure) Rotational failure due to inadequate penetration is

a large scale movement of the lower portion of the wall; commonly referred to as a toe failure. This type of failure mechanism is a function of the loading conditions, soil strength, and sheet pile embedment.

During a toe failure, the soil mass in front of the wall does not provide enough lateral resistance to resist the load applied due to the soil and surcharge loadings behind the wall. In existing construction, this type of failure is typically due to the reduction in SSP embedment from scour or subsequent dredging.

LYE performed a series of computer analyses to evaluate the resistance to toe failure. To best replicate the existing conditions: soil parameters were based upon the Tierra’s geotechnical investigation findings; SSP geometry was based upon reviews of drawings; and the dredge elevation was estimated based upon hydrographic survey soundings. Based upon this information the software, SupportIT (Version 2.13), calculates estimated pressure, moment and shear forces along the length of the SSP using classical design procedures.

The analyses representing the current conditions of the walls are included in Volume III-A and summaries of the results are provided in Tables 3 and 4. Included in these tables are the “factors of safety against rotation” calculated by SupportIT. The minimum factor of safety recommended for design is 2.0 (GTSoft, 2006, p. 48). In addition since the software does not calculate factors of safety less than 1.0 (shown as “FOS undefined”); a ratio between the analysis embedment and the minimum calculated embedment is shown allow for differentiation of those cases.

The SupportIT analyses suggest that rotational failure due to inadequate penetration may be a concern for the existing bulkheads at Port Everglades. Of the 28 analyses shown in Tables 3 and 4, 12 cases produced factors of safety less than 1.0 and an additional 8 cases were between 1.0 and 2.0.

Typically when sheet pile embedments near the point of toe failure the observation of visible movement near the dredge line would be expected; however, no signs of wall movement were noted in the HPA “Underwater Inspection and Baseline Survey” (2006).

The low factors of safety calculated in the computer analysis and the lack of early signs of wall movement, suggest that the bulkheads are currently stable but with less capacity to account for future conditions that current design criteria require. Due to this lack of reserve capacity, the potential for rotational (toe) failure is estimated to be of moderate concern.

Figure 10. Rotational failure due to inadequate penetration (after U.S. Army Corps of Engineers)

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 16 of 26

Table 3. Northport Embedment Computer Analysis Summary Berth Analysis

Analysis Dredge

Elevation (ft MLW)

Analysis Tip

Elevation (ft MLW)

Software Calculated Factor of

Safety

Minimum Tip

Elevation (ft MLW)1

Analysis Embedment / Minimum Embedment Ratio 1

Northport Berths

Berths 1-3 -38.5 ft -49.0 ft undefined -54.5 ft 10.5 ft / 16.0 ft = 0.66

Berth 4 -45.0 ft -67.0 ft 3.66 -------- -------- N/A

Berth 5 -45.0 ft -71.0 ft 5.47 -------- -------- N/A

Berth 6-7 -40.0 ft -53.0 ft undefined -60.0 ft 13.0 ft / 20.0 ft = 0.65

Berth 8 -40.0 ft -53.0 ft 1.22 -------- -------- N/A

Berth 9 -44.0 ft -53.0 ft undefined -61.5 ft 9.0 ft / 17.5 ft = 0.51

Berth 10 -44.0 ft -53.0 ft undefined -72.5 ft 9.0 ft / 19.5 ft = 0.46

Berth 11 -36.0 ft -53.0 ft 1.77 -------- -------- N/A

Berth 12-13 -42.0 ft -71.0 ft 6.32 -------- -------- N/A

Notes: 1. Minimum embedment ratio only calculated for cases where the software calculated Factor of Safety

was undefined. This ratio is used to allow for a rational comparison of the embedments in these cases.

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 17 of 26

Table 4. Midport and Southport Embedment Computer Analysis Summary Berth Analysis

Analysis Dredge

Elevation (ft MLW)

Analysis Tip

Elevation (ft MLW)

Software Calculated Factor of

Safety

Minimum Tip

Elevation (ft MLW)1

Analysis Embedment / Minimum Embedment Ratio 1

Midport Berths

Berth 14-15 -42.0 ft -53.0 ft undefined -61.0 ft 11.0 ft / 19.0 ft = 0.58

Berth 16 -42.0 ft -53.0 ft undefined -57.5 ft 11.0 ft / 15.5 ft = 0.71

Berth 17 -42.0 ft -53.0 ft undefined -57.5 ft 11.0 ft / 15.5 ft = 0.71

Berth 18 -40.0 ft -53.0 ft 1.63 -------- -------- N/A

Berth 19 -40.0 ft -53.0 ft 1.06 -------- -------- N/A

Berth 20 -40.0 ft -53.0 ft 1.45 -------- -------- N/A

Berth 21 -40.0 ft -53.0 ft undefined -58.0 ft 13.0 ft / 18.0 ft = 0.72

Berth 22 -45.0 ft -53.0 ft undefined -62.5 ft 8.0 ft / 17.5 ft = 0.46

Berth 23 -40.0 ft -53.0 ft 1.13 -------- -------- N/A

Berth 24 -40.0 ft -51.0 ft undefined -69.0 ft 11.0 ft / 18.0 ft = 0.61

Berth 25 -42.0 ft -51.0 ft undefined -70.0 ft 9.0 ft / 19.0 ft = 0.47

Berth 26 -44.0 ft -58.0 ft undefined -65.0 ft 14.0 ft / 21.0 ft = 0.67

Berth 27 -44.0 ft -62.0 ft 1.22 -------- -------- N/A

Berth 28 -43.0 ft -62.0 ft 2.28 -------- -------- N/A

Berth 29 -46.0 ft -62.0 ft 1.00 -------- -------- N/A

Southport Berths

Berth 30 -45.0 ft -72.0 ft 6.68 -------- -------- N/A

Berth 31 -46.0 ft -72.0 ft 3.90 -------- -------- N/A

Berth 32 -46.0 ft -72.0 ft 3.22 -------- -------- N/A

Berth 33 -46.0 ft -72.0 ft 3.73 -------- -------- N/A

Notes: 1. Minimum embedment ratio only calculated for cases where the software calculated Factor of Safety

was undefined. This ratio is used to allow for a rational comparison of the embedments in these cases.

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 18 of 26

REMEDIATION AND COST COMPARISONS Over the short term the failure mechanism discussed in the previous section are of

minimal to moderate concern. However, if no remedial measures are taken these concerns will only increase. For instance, the steel sheet piles (SSP) will continue to corrode; increasing the potential for flexural failure of the SSP. While deepening of the berths near the wall, through dredging and/or scour, increases the potential for toe failure, tie rod failure and anchor passive failure. Therefore, some form of remediation is recommended.

The various options for rehabilitation works focus on improving resistance to one or more of the previously discussed structural failure mechanisms. For instance cathodic protection improves resistance to flexural failure of the sheet piling by reducing the rate of section loss due to corrosion; while installation of a toe wall provides additional resistance to toe failure due to toe failure by increasing the effective penetration of the wall.

Table 5. Conceptual Rehabilitation Options Comparison Rehabilitation Option Advantages Disadvantages

Cathodic Protection of Steel Sheet Piles

• Expected to slow future wall section losses due to corrosion

• Expected to delay flexural failure of sheet piling

• When installed on existing walls requires less disruption of operations than other repair options

• Does not repair any damage previously done by corrosion

• Provides little to no additional protection against anchor passive failure, tie rod failure or toe failure without additional remediation

• Can increase corrosion rates of tie rods and connected items

New Tie Rods and Anchorage System

• Provides replacement or additional support for existing tie rods and anchorage system

• Expected to resist wale system failure, anchor passive failure and tie rod failure

• May require extensive excavation behind existing wall for installation

• Provides no additional protection against flexural failure of sheet piling or toe failure without additional remediation

Toe Wall • Increases effective penetration of existing wall

• Expected to resist toe failure at current berth depth

• Can be designed to resist toe failure at future berth depths

• Provides little or no additional protection against wale system failure, anchor passive failure, flexural failure of sheet piling or tie rod failure without additional remediation

• In conjunction with berth deepening may increase the risk of anchor passive failure, flexural failure of sheet piling or tie rod failure

Replacement Wall • Covers existing corroded wall with a new SSP

• Expected to resist flexural failure of sheet piling and toe failure at current berth depths

• Can be designed to resist flexural failure and toe failure at future berth depths

• Provides no additional protection against wale system failure, anchor passive failure or tie rod failure without additional remediation

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 19 of 26

The advantages and disadvantages of several rehabilitation options are discussed in Table 5. When multiple rehabilitation options are installed several potential failure mechanisms can be addressed; for instance installation of a toe wall to reduce the risk of toe failure with new tie rods and anchorages to reduce the risks of tie rod and anchor passive failure.

Although there are a number of combinations of rehabilitation options that can be used on the Port’s steel sheet pile walls, the conceptual costs of 2 options were developed for planning purposes by LYE. These 2 options are installation of am auger cast pile toe wall and installation of new SSP wall (including tie rods and cathodic protection). The selection of these two options allows for a brief comparison of the costs to continue to maintain the current wall compared to replacement with a new system.

Auger Cast Pile Toe Wall To develop the cost of a new toe wall installation, LYE made assumptions about the

design and function of the toe wall. Although other construction techniques are possible (SSP toe walls for instance), the use of auger cast piles for toe wall support was assumed. Additionally, it was assumed that the toe wall would extend only 5 feet above the auger cast piles. The actual costs will vary based upon the design parameters, construction requirements and current market construction costs for each toe wall repair. For this conceptual estimate, the installation was assumed to be composed of:

• Installation of 24” diameter underwater, auger cast piles. The auger piles were assumed 4 feet on center, 3 feet away from the existing wall and extending from the current bottom elevation down 35 feet.

• Reinforcing the auger cast piles with W10 structural steel sections, extending a minimum of 5 feet.

• Casting a reinforced concrete beam (approximately 3 feet x 5 feet) between each W10, using tremie construction techniques.

Table 6. Conceptual Costs for Auger Cast Pile Toe Wall Installation

Auger Cast Piles $2,500 per foot of wall

Steel Columns $1,000 per foot of wall

Concrete Reinforcing $1,000 per foot of wall

Tremie placed Concrete $875 per foot of wall

TOE WALL ESTIMATED COST $5,375 per foot of wall

Properly designed and installed toe walls would be expected to decrease the risk of tie rod failure and toe failure. However, this repair would not address the increasing risk of flexural failure. The existing sheet piles would still be exposed to further corrosion from the top of the toe wall upward. In addition, the flexural forces in the existing sheets may increase, depending upon any future increases in berth depth.

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 20 of 26

New Steel Sheet Pile Bulkhead The installation of new steel sheet pile bulkheads could reduce the risk of most of the

failure mechanisms discussed by the U.S. Army Corps of Engineers (1994, p. 5-1 to 5.12). The installation the new sheet pile wall, designed using current factors of safety, would reduce the risk of flexural failure and toe failure. The installation of new tie rods and anchorages would reduce the risk of anchor passive failure, tie rod failure and wale system failure. The only mechanism that would not have a reduced risk would be deep seated failure; however, as previously noted, this risk is entirely dependant upon the soil strengths.

For estimating the conceptual costs of installation of new steel sheet pile bulkhead, LYE referenced the recent work performed at Terminal 27. For comparison purposes, the new SSP was assumed to be installed in water with a dredged and scoured depth of 44 feet. The actual costs will vary based upon the design parameters, construction requirements and current market construction costs for each toe wall repair. For this conceptual estimate, the installation was assumed to be composed of:

• Vibratory and/or impact drive new SSP, approximately 65 feet long, directly in front of the existing bulkhead.

• Install a new deadman and connect to the new SSP with tie rods at approximately 8 feet on center.

• Cast a new reinforced concrete cap on the top of the new SSP.

Table 7. Conceptual Costs for Installation of New Bulkhead, in front of Existing

Install SSP $5,500 per foot of wall

New Tie Rods $2,500 per foot of wall

New Deadman with connection $2,500 per foot of wall

New Concrete Cap $4,500 per foot of wall

New Cathodic Protection $500 per foot of wall

NEW SSP ESTIMATED COST $15,500 per foot of wall

The auger cast pile toe wall cost is estimated to be 65% less expensive than the installation of a new sheet pile bulkhead, see Tables 6 and 7. However, the auger cast pile toe wall does not provide any additional resistance to failure modes other than toe failure; while the installation of a new steel sheet pile bulkhead should increase resistance to most failure mechanisms. Since the new SSP wall would provide an increased resistance to multiple failure mechanisms, installation of new sheet pile would be expected to provide a longer design life than toe wall repairs. This longer design life is expected to make up for the price differential over the life of the work.

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 21 of 26

RECOMMENDATIONS Port Everglades has retained a consultant team, headed by DMJM Harris, to update

the Master Plan. The Port’s consultant team issued a draft of the Master Plan Update, Phase I on March 3, 2007. At this time the consultant team is revising the Master Plan Update to include feedback.

It is recommended that sheet pile bulkhead installed in front of the existing bulkheads be included in the Master Plan. Since “the service life of waterfront structures is expected today to be 40 to 50 years in general…” (Arbed, 1986, p. 60), new sheet pile is recommended for all sheet piles over 40 years of age.

Currently there is considerable flexibility in the order of replacement. The HPA Underwater Inspection made no recommendations for “immediate” or “safety” repairs (2006, p. 3-2). Therefore, any rational method to determine replacement order can be used; so long as the conditions are monitored and modifications to the order are made as conditions change.

A proposed replacement order is summarized in Table 8. The Berths are grouped based upon their location within the port and wall configuration. The proposed order was then established based upon reviewing the potential for toe failures and the current section steel loss listed in the HPA Underwater Inspection (2006). The potential for toe failures based upon the embedment ratios and factors of safety presented in Tables 3 and 4 for the current water depths. This proposed replacement order did not include any consideration for future berth deepening.

However, the U. S. Army Corps of Engineers are presently assessing a future channel dredging program for Port Everglades. The Corps have proposed to increase the approach channel to a design depth of 54 feet below Mean Lower Low Water (MLLW), increase the turning basin to a design depth of 49 feet below MLLW and increase the Intracoastal Waterway to 49 feet below MLLW (DMJM Harris, 2007). After this proposed dredging, the channel design depths begin to approach the pile tip elevations. The pile tip elevations and channel depths get even closer once an addition 1 foot of pre-maintenance dredging and additional 1 foot of allowable over dredge are included (see Tables 9 and 10).

Due to the potential for increases in the risk of toe failure due to the channel dredging, it is recommended that bulkhead be replaced before dredging occurs in the vicinity. For those berths far enough from the new channel dredging to prevent effective decreases in embedments; the order may be determined by operational requirements, the Master Plan or the proposed order shown in Table 8.

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 22 of 26

Table 8. Proposed Steel Sheet Pile (SSP) Replacement Order

Proposed SSP Replacement Order 1

Embedment Ratios and Factors of

Safety 2

Section Losses Listed in 2006 HPA Report 3

Years of Construction and

Lengths (ft) 4

1 Berths 7, 8, 8A,

9, 10 & 11 0.46, 0.51, 0.65,

1.22, 1.77

Average 35% Maximum 49% Minimum 23%

1954 = 1965 =

23 ft 3,180 ft 3,203 ft

2 Berths 24, 25, 26 & 27 0.47, 0.61, 0.67

1.22

Average 25% Maximum 79%

Minimum 6%

1966 = 1967 =

153 ft 2,552 ft 2,705 ft

3 Berths 14 & 15 0.58 Average 30%

Maximum 45% Minimum 20%

1957 = 1960 =

600 ft 601 ft

1,201 ft

4 Berths 19, 20,

21, 22 & 23 0.46, 0.72,

1.06, 1.13, 1.45

Average 33% Maximum 55%

Minimum 1%

1966 = 2002 =

2,603 ft 601 ft

2,628 ft

5 Berths 1A, 1B,

1C, 1D, 1,2, 3 & 6 0.65, 0.66

Average 37% Maximum 100%

Minimum 17%

1940 = 1956 = 1960 = 1965 =

100 ft 1,579 ft

561 ft 378 ft

2,618 ft

6 Berths 16, 17 & 18 0.71, 0.71,

1.63

Average 23% Maximum 35% Minimum 13%

1960 = 1964 =

877 ft 1,008 ft 1,885 ft

7 Berth 28 including

the FP&L Canal 1.00

Average 19% Maximum 41%

Minimum 4%

1967 = 1983 =

100 ft 865 ft 965 ft

8 Berths 28A,

28B, 28E & 28F 2.28

Average 20% Maximum 28%

Minimum 9% 1967 = 1,448 ft

9 Berths 30, 31, 32 & 33A 3.22, 3.73, 3.90, 6.68 Average 25%

Maximum 54% Minimum 4%

1992 = 3,801 ft

10 Berths 12, 13 & 13A 6.32 Average 16%

Maximum 67% Minimum 0%

1984 = ?? =

1,231 ft 300 ft

1,531 ft

11 Berths 4, 4A & 5 3.66, 5.47 Average 7%

Maximum 36% Minimum 0%

1976 = 1978 =

700 ft 1,400 ft 2,100 ft

Notes: 1. Order of replacement is based upon current potential for toe failure, current section loss and age.

Impact of future dredging is not included in this order. 2. Embedment ratios and factors of safety computed by SupportIT give an approximation of the

resistance to toe failure at the current berth water depths. See Tables 3 & 4. 3. Section losses are based upon the summarized values given in HPA 2006 Report and are not based

upon the complete set of field measurements. 4. Lengths and year of construction taken from Drawing 92S 3912 (Port Everglades Authority, 1992).

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 23 of 26

To monitor the performance of the older bulkheads, the Port should undertake an inspection program comprised of the following suggested minimum frequencies:

• Multiple survey benchmarks on the cap or cap wall of each bulkhead should be established. Then plane surveys of these benchmarks should be undertake no less than twice a year. These surveys should focus on monitoring lateral movement of the top of the bulkhead.

• Underwater visual “swim-by” inspections, achieving the Level I scope described in Underwater Investigations (ASCE, 2001), should be performed no less than one a year. These inspections should focus on noting wall movements below water and/or new signs of distress.

• Detailed underwater inspections, achieving the Level II scope described in Underwater Investigations (ASCE, 2001), should be performed no less than every other year. These inspections should monitor the section loss due to corrosion.

If signs of movement, overstressing or severe deterioration is observed, the order of wall replacement should be revised.

Steel sheet pile installed after the date of this report should have condition surveys performed generally in accordance with Underwater Investigations (ASCE, 2001). An initial inspection should be performed after completion and the next survey performed no more than 5 years latter; with subsequent frequency determined based upon Underwater Investigations (ASCE, 2001).

and

Dre

dge

Ele

vati

on S

umm

ary

App

roxi

mat

e L

engt

h 1 (

ft)

Yea

r of

C

onst

ruct

ion1

Shee

t Pile

Se

ctio

n1

Shee

t Pile

Tip

E

leva

tion

(ft M

LW

)1,2,

3 K

ing

Pile

Se

ctio

n1

Kin

g P

ile T

ip

Ele

vatio

n

(ft M

LW

)1,2,

3

Cur

rent

L

iste

d D

epth

(f

t ML

W)3

App

roxi

mat

e C

urre

nt

Em

bedm

ents

(f

t)

Cur

rent

20%

E

mbe

dmen

t R

ule

of T

hum

b

CO

E P

ropo

sed

Des

ign

Dep

th

[ove

r-dr

edge

]

(ft M

LL

W)4

Em

bedm

with

CO

ver-

d (ft

79 f

t 19

56

BZ

IVR

-4

9 ft

--

--

??

??

??

--

--

344

ft

1960

H

oesc

h II

-3

1.5

ft

--

--

??

??

??

--

--

217

ft

1960

H

oesc

h I

-24.

5 ft

--

--

??

??

??

--

--

1,50

0 ft

19

56

BZ

IVR

-4

9 ft

--

--

-3

1 ft

18

ft

Yes

-4

9 ft

[-5

1 ft

] -2

100

ft

1940

Z

P32

-4

0 ft

--

--

-3

1 ft

9

ft

Yes

-4

9 ft

[-5

1 ft

] -1

1

700

ft

1976

B

Z9.

5 -4

9.5

ft

HZ

80

-67

ft

-43

ft

6.5

ft /

24 f

t N

O /

Yes

--

--

200

ft

1978

Z

H9.

5 -5

1.5

ft

HZ

800

-71

ft

-43

ft

8.5

ft /

28 f

t Y

es /

Yes

--

--

300

ft

1978

Z

H9.

5 -4

9.5

ft

HZ

600

-61

ft

-43

ft

6.5

ft /

18 f

t N

O /

Yes

--

--

900

ft

1978

Z

H9.

5 -5

1.5

ft

HZ

800

-71

ft

-43

ft

8.5

ft /

28 f

t Y

es /

Yes

--

--

378

ft

1965

B

ZII

IB

-53

ft

--

--

-38

ft

15 f

t Y

es

-49

ft [

-51

ft]

2 f

2,70

6 ft

19

65

BZ

IIIB

-5

3 ft

--

--

-3

8 ft

15

ft

Yes

--

--

23 f

t 19

54

ZP

32

??

--

--

-38

ft

??

??

-49

ft [

-51

ft]

??

474

ft

1965

B

ZII

IB

??

--

--

-38

ft

??

??

-49

ft [

-51

ft]

??

1,23

1 ft

19

84

ZH

9.5

-51.

5 ft

H

Z80

0 -7

1 ft

-3

8 ft

13

.5 f

t / 3

3 ft

Y

es /

Yes

--

--

300

ft

??

BZ

IVR

??

--

--

-3

8 ft

??

??

--

--

92S

3912

(Po

rt E

verg

lade

s A

utho

rity

, 199

2), u

nles

s ot

herw

ise

note

d.

orig

inal

she

et p

iles

neg

lect

ing

any

toe

wal

l rep

airs

.

glad

es F

acili

ties

Gui

de &

Dir

ecto

ry 2

007-

2008

.

pon

eith

er M

ean

Low

Wat

er (

ML

W)

or M

ean

Low

er L

ow W

ater

(M

LL

W).

The

dif

fere

nce

betw

een

thes

e da

tum

s is

0.1

61 f

t, pe

r N

OA

A d

ata

for

the

tidal

ben

ch m

ark

“Por

t Eve

rgla

des,

Lak

e M

abel

Fe

for

this

rev

iew

.

mbe

dmen

t rul

es o

f th

umb

for

SSP

vary

fro

m 1

0% f

or s

tiff

cla

y to

75%

for

sub

mer

ged

sand

s (G

TSo

ft, 2

006)

.

in J

uly

12, 2

007

emai

l. D

epth

s li

sted

are

pro

pose

d A

rmy

Cor

ps o

f E

ngin

eers

(C

OE

) “P

roje

ct D

epth

” an

d “P

roje

ct D

epth

+ 1

ft p

re-m

aint

enan

ce d

redg

ing

+ 1

ft a

llow

able

ove

r dr

edge

”.

d on

Dra

win

g 92

S 39

12; l

engt

h an

d sh

eet p

ile s

ecti

on ta

ken

from

HPA

200

6 R

epor

t.

App

roxi

mat

e L

engt

h 1 (

ft)

Yea

r of

C

onst

ruct

ion1

Shee

t Pile

Se

ctio

n1

Shee

t Pile

Tip

E

leva

tion

(ft M

LW

)1,2,

3 K

ing

Pile

Se

ctio

n1

Kin

g P

ile T

ip

Ele

vatio

n

(ft M

LW

)1,2,

3

Cur

rent

L

iste

d D

epth

(f

t ML

W)3

App

roxi

mat

e C

urre

nt

Em

bedm

ents

(f

t)

Cur

rent

20%

E

mbe

dmen

t R

ule

of T

hum

b

CO

E P

ropo

sed

Des

ign

Dep

th

[ove

r-dr

edge

]

(ft M

LL

W)4

Em

bedm

with

CO

ver-

d (ft

600

ft

1957

B

ZIV

R

??

--

--

-3

8 ft

--

??

--

--

601

ft

1960

B

ZIV

R

-4

9 ft

--

--

-3

8 ft

11

ft

Yes

--

--

877

ft

1960

B

ZIV

R

-4

9 ft

--

--

-3

8 ft

11

ft

Yes

-4

4 ft

[-4

6 ft

] 3

f

1,00

8 ft

19

64

Hoe

sch

III

-5

3 ft

--

--

-3

8 ft

15

ft

Yes

-4

4 ft

[-4

6 ft

] 7

f

25 f

t 20

02

??

??

--

--

-38

ft

--

??

-44

ft [

-46

ft]

??

2,36

3 ft

19

66

BZ

IVN

-53

ft

--

--

-38

ft

15 f

t Y

es

-44

ft [

-46

ft]

7 f

240

ft

1966

B

ZIV

N

-5

3 ft

--

--

-3

8 ft

15

ft

Yes

--

--

153

ft

1966

B

ZIV

N

-5

3 ft

--

--

-4

0 ft

13

ft

Yes

-4

9 ft

[-5

1 ft

] 4

f

1,01

8 ft

19

67

BZ

IVN

-47

& -

51 f

t --

--

-4

0 ft

7

ft /

11 f

t N

O /

Yes

-4

9 ft

[-5

1 ft

] -4

ft /

100

ft

1967

B

ZIV

N

-5

5 to

-62

ft

--

--

-40

ft

15 f

t to

22 f

t Y

es

-49

ft [

-51

ft]

4 ft

to

1,43

4 ft

19

67

BZ

IVN

-58

& -

62 f

t --

--

-4

0 ft

18

ft /

22

ft

Yes

/Y

es

-49

ft [

-51

ft]

7 ft

/

784

ft

1967

B

ZIV

N

-5

1 to

-62

ft

--

--

-27

ft

24 f

t to

35 f

t Y

es

--

--

561

ft

1967

B

ZIR

A

-3

5 to

-51

ft

--

--

-27

ft

8 ft

to 2

4 ft

Y

es

--

--

103

ft

1967

B

ZIV

N

-5

3 to

-62

ft

--

--

-27

ft

26 f

t to

35 f

t Y

es

--

--

100

ft

1967

B

ZV

N

-62

ft

--

--

-40

ft

22 f

t Y

es

-49

ft [

-51

ft]

11

758

ft

1983

Z

H9.

5/13

-53

ft

HZ

775B

-72

ft

-44

ft7

13 f

t / 3

2 ft

Y

es /

Yes

-4

9 ft

[-5

1 ft

] 2

ft /

2

107

ft

1983

B

Z20

-3

1 to

-50

ft

--

--

??

--

??

--

--

60 f

t 19

92

BZ

16.4

-12

to -

49 f

t --

--

??

--

??

??

??

883

ft

1992

P

Z 6

10

-5

6.75

ft

PSP

802

-72

ft

-44

ft

12.7

5 ft

/ 28

ft

Yes

/ Y

es

-49

ft [

-51

ft]

5.75

ft

60 f

t 19

92

PZ

610

-56.

75 f

t P

SP 1

002

-77

ft

-44

ft

12.7

5 ft

/ 33

ft

Yes

/ Y

es

-49

ft [

-51

ft]

5.75

ft

1,22

6 ft

19

92

PZ

610

-56.

75 f

t P

SP 1

002

-7

7 ft

-4

4 ft

12

.75

ft /

33 f

t Y

es /

Yes

-4

9 ft

[-5

1 ft

] 5.

75 ft

774

ft

1992

P

Z 6

10

-5

6.75

ft

PSP

802

-72

ft

-44

ft

12.7

5 ft

/ 28

ft

Yes

/ Y

es

-49

ft [

-51

ft]

5.75

ft

798

ft

1992

P

Z 6

10

-5

6.75

ft

PSP

802

-72

ft

-44

ft

12.7

5 ft

/ 28

ft

Yes

/ Y

es

-49

ft [

-51

ft]

5.75

ft

92S

3912

(Po

rt E

verg

lade

s A

utho

rity

, 199

2), u

nles

s ot

herw

ise

note

d.

orig

inal

she

et p

iles

neg

lect

ing

any

toe

wal

l rep

airs

.

glad

es F

acili

ties

Gui

de &

Dir

ecto

ry 2

007-

2008

, unl

ess

othe

rwis

e no

ted.

pon

eith

er M

ean

Low

Wat

er (

ML

W)

or M

ean

Low

er L

ow W

ater

(M

LL

W).

The

dif

fere

nce

betw

een

thes

e da

tum

s is

0.1

61 f

t, pe

r N

OA

A d

ata

for

the

tidal

ben

ch m

ark

“Por

t Eve

rgla

des,

Lak

e M

abel

Fe

for

this

rev

iew

.

mbe

dmen

t rul

es o

f th

umb

for

SSP

vary

fro

m 1

0% f

or s

tiff

cla

y to

75%

for

sub

mer

ged

sand

s (G

TSo

ft, 2

006)

.

in J

uly

12, 2

007

emai

l. D

epth

s li

sted

are

pro

pose

d A

rmy

Cor

ps o

f E

ngin

eers

(C

OE

) “P

roje

ct D

epth

” an

d “P

roje

ct D

epth

+ 1

ft p

re-m

aint

enan

ce d

redg

ing

+ 1

ft a

llow

able

ove

r dr

edge

”.

iA

t23

2007

il

Lakdas/Yohalem Engineering, Inc. Toewall Improvements & Bulkhead Analysis Draft Report – September 17, 2007

Page 26 of 26

REFERENCES Arbed. (January 1986). Steel sheet piles. (American engineering units edition).

Arcelor RPS. (January 2005). Piling handbook. (8th Edition).

ASCE. (2001). Underwater investigations: Standard practice manual.

DMJM Harris. 2006 Port Everglades master plan update. <http://www.portevergladesmasterplanupdate.com/index_files/03-09-07_PEV_Presentation.pdf> (July 31, 2007)

HPA, Inc.(April 2006). Underwater inspection and baseline survey assessment of Port Everglades Berths 1 through 33.

GTSoft, Ltd. (2006). SupportIT: Sheet pile wall design software manual.

MARAD. Data and Statistics. U.S. Department of Transportation: Maritime Administration. <http://www.marad.dot.gov/MARAD_statistics/index.html> (July 31, 2007).

Port Everglades Authority. (1992). Steel sheet piling and bulkhead data. Drawing 92S 3912.

Port Everglades Department. (2007). Port Everglades facilities guide & directory 2007-2008. Miramar, FL: Seaports Publications Group, Commonwealth Business Media, Inc.

U.S. Army Corps of Engineers. (31 March 1994). Engineering and design: Design of sheet pile walls. Manual EM 1110-2-2504. Washington, DC.

B-1

APPENDIX B Draft Versions of Port Everglades

5, 10 and 20 Year Master / Vision Plansby AECOM (via email July 23, 2010)

C-1

APPENDIX C Memorandum on April 5, 2010 Site Visit to Review Existing Impressed Current Cathodic Protection

Halcrow, Inc 22 Cortlandt Street

New York, NY 10007

Tel (212) 608-3990 Fax (212) 566-5059

www.halcrow.com

Memo

To: Andy Curtis

From: Amol Paranjape

Date: 14 April 2010

Subject: Port Everglades Site Visit on 5 April 2010

Halcrow Inc. conducted a preliminary site inspection of the existing Impressed

Current systems for Berths 4, 5, 12, 13, 16, 17, 18 & 29 at Port Everglades. The

purpose for this inspection was to visually gauge the current state of the existing

impressed current system and make assessments for testing of that system in the

future. The inspection was carried out during the site visit conducted on April 5th, 2010

and was assisted by Port Everglades representative (Gary Bogumill P.L.S.).

Following are the observations from the visual inspection of the impressed current system at individual berths.

At the time of inspection all the existing rectifiers were found to be NOT IN OPERATION.

Berth 4:

The rectifier (Photos # 1, 3, 4) and the disconnect switch enclosures (Photos # 5) were partially corroded. The in-coming and out-going conduits at the rectifier were in good condition (Photos # 2).

The power source and the meter for this rectifier were not accessible as it was located in the restricted passenger terminal area.

Some of the junction boxes indicated on the design drawings could not be located on the berth. The covers of the existing junction boxes could not be lifted

Memo (cont.)

2

as the necessary equipment was not available during the visit, thus the condition of the cable and conduits inside them could not be determined.

Photo # 1 (Rectifier on Pier 4)

Photo # 2 (Rectifier & Disconnect Switch)

Memo (cont.)

3

Photo # 3 (Interior of the Rectifier)

Photo # 4 (Interior of the Rectifier)

Memo (cont.)

4

Photo # 5 (Disconnect switch for the Rectifier)

Berth 5:

The rectifier enclosure, disconnect switch and the conduits were found to be partially corroded (Photos # 6 & 9).Oil tank of rectifier R2 (South Side) was found to be empty (Photos # 7 & 8); the oil in the tank was drained out from the tank some time in the past and was never refilled.

Covers of the junction boxes located on the curb of Berth 5 were bolted making interiors inaccessible (Photo # 10). The conduits and cables inside these junction boxes can only be inspected by cutting the bolts and then removing covers.

Covers of the junction boxes located on the edge of the Roll On/Off Ramp were bolted and corroded, making interiors inaccessible (Photos # 11 & 12). The conduits and cables inside these junction boxes can only be inspected by cutting the bolts and then removing covers.

The two rectifiers R1 & R2 were fed from the overhead wires and the meter at the source was found to be damaged. (Photos # 13 & 14)

Exterior of the rectifier ‘R1’ (North Side) enclosure, disconnect switch and conduits were found to be partially corroded (Photos # 15, 16, 17 & 18).

Exterior of the rectifier R3 (Near Bldg No. 6) enclosure, disconnect switch and conduits were recently painted and looked in good condition (Photos # 19, 20 & 21). The glass cover of the ammeter and voltmeter box mounted on this rectifier

Memo (cont.)

5

has been covered in paint (Photo # 22) and the readings from these meters can only be taken after cleaning out the paint from the glass.

The power source and the meter for rectifier R3 could not be identified due to lack of nameplate/ tag marks.

Photo # 6 (Partially corroded Rectifier – R2 on Pier 5)

Memo (cont.)

6

Photo # 7 (Interior of the Rectifier – R2)

Photo # 8 (Empty Oil tank of the Rectifier – R2)

Memo (cont.)

7

Photo # 9 (Disconnect switch & Meters for the Rectifier – R2)

Memo (cont.)

8

Photo # 10 (Junction Boxes on curb of Pier 5)

Photo # 11 (Junction Boxes on the edge of Roll On/Off Ramp)

Memo (cont.)

9

Photo # 12 (Junction Boxes on the edge of Roll On/Off Ramp)

Photo # 13 (Meter at the power source located on Berth 5)

Memo (cont.)

10

Photo # 14 (Damaged meter on Berth 5)

Photo # 15 (Rectifier – R1 on Pier 5)

Memo (cont.)

11

Photo # 16 (Interior of the Rectifier – R1)

Memo (cont.)

12

Photo # 17 (Interior of the Rectifier – R1)

Memo (cont.)

13

Photo # 18 (Disconnect switch & Meters for the Rectifier – R1)

Photo # 19 (Rectifier – R3 near Bldg. No.6)

Memo (cont.)

14

Photo # 20 (Interior of the Rectifier – R3)

Photo # 21 (Interior of the Rectifier – R3)

Memo (cont.)

15

Photo # 22 (Disconnect switch & Meters for the Rectifier – R3)

Berth 12:

Interior of the Rectifier R1 could not be inspected due to an active wasp’s nest adjacent to it (Photo # 23).

The power source and the meter were not present at the location indicated on the drawings. The meter must have been removed during a later contract.

Covers of the junction boxes located on the curb of Berth 12 were bolted making interiors inaccessible. The conduits and cables inside these junction boxes can only be inspected by cutting the bolts and then removing covers.

Memo (cont.)

16

Photo # 23 (Rectifier – R1 at Berth 12)

Berth 13:

Exterior of the rectifier R2 (Photo # 24), disconnect switch and conduits (Photo # 26) were found to be partially corroded. The oil in the rectifier tank was observed to be below the Oil-level mark (Photo # 25).

Exterior of the rectifier R3 (Photo # 27), disconnect switch (Photo # 30) and conduits were found to be partially corroded. The wires at the top of the rectifier were damaged, indicating a possible damage inside the rectifier (Photo # 28). The oil in the rectifier tank was observed to be below the Oil-level mark (Photo # 29).

The meter at the power source looked in a good condition. The enclosures of two disconnect switches near the meter are completely corroded.

Covers of the junction boxes located on the curb of Berth 13 were bolted making interiors inaccessible. The conduits and cables inside these junction boxes can only be inspected by cutting the bolts and then removing covers.

The 3 junction boxes shown between the berth 13 & 14 on the design drawings could not be located in field (Photos # 31 & 32).

Memo (cont.)

17

Photo # 24 (Rectifier – R2 at Berth 13)

Photo # 25 (Interior of the Rectifier – R2)

Memo (cont.)

18

Photo # 26 (Disconnect switch & Meters for the Rectifier – R2)

Photo # 27 (Rectifier – R3 at Berth 13)

Memo (cont.)

19

Photo # 28 (Ruptured cables visible in Rectifier – R3)

Photo # 29 (Interior of the Rectifier – R3)

Memo (cont.)

20

Photo # 30 (Disconnect switch & Meters for the Rectifier – R3)

Photo # 31 (Junction Boxes on curb of Pier 13)

Memo (cont.)

21

Photo # 32 (Junction Boxes on curb of Pier 12)

Berth 16-17-18:

All of the 4 rectifiers that are shown on the drawings for Berths 16 to 18 were removed sometime in the past.

Some of the junction boxes on these berths could not be located as they have been covered in asphalt during the latest re-pavement of the berths (Photos # 33, 34 & 35).

Photo # 33 (Junction Boxes on Pier 16)

Memo (cont.)

22

Photo # 34 (Junction Boxes on Pier 17)

Photo # 35 (Junction Boxes on Pier 18)

Memo (cont.)

23

Berth 29:

Exterior of the rectifier R2 (Photo # 36), disconnect switch (Photo # 38) and conduits were found to be partially corroded. The oil in the rectifier tank was observed to be below the Oil-level mark (Photo # 37).

Rectifier R1 was removed sometime in the past and thus could not be located in site.

The power source and the meter were not present at the location indicated on the drawings. The meter must have been removed during a later contract.

Some of the junction boxes located on the curb of Berth 29 were buried in the pavement making the interiors inaccessible (Photo # 39).

Photo # 36 (Rectifier – R2 at Berth 29)

Memo (cont.)

24

Photo # 37 (Interior of the Rectifier – R2)

Memo (cont.)

25

Photo # 38 (Disconnect switch & Meters for the Rectifier – R2)

Memo (cont.)

26

Photo # 39 (Partially buried Junction Box located on the curb of Berth # 29)

Memo (cont.)

27

It is reported that all the anodes that were installed along the bulkhead piles as a part of the impressed current system have been completely consumed some time in the past.

If the existing impressed current system is to be put into service the following points need to be considered:

1. One of the rectifier manufacturing companies, “Good All” has been out of business for many years; subsequently it will be difficult to find a shop that will be ready and able to repair the rectifiers from that manufacturer.

2. Some of the rectifiers could have used “selenium” diodes, which have become obsolete making it difficult to find replacements if required. Even if replacements were found, the diodes may not be compatible with the existing transformer voltages.

3. Some of the existing rectifiers were found to have low oil. The empty tank would have most certainly caused water damage to the transformer placed in that tank. The remaining rectifiers would need to have the winding resistances tested for water damage as water collected in the tank over a long time period is prone to become salty at a marine location.

4. The meters, shunts, etc. would have to be removed and checked for the proper operation. Wiring and defective or broken meters would be replaced.

5. Protective devices, circuit breakers, fuses would all have to be removed and tested for calibration, conditions, etc. All other electrical devices, wiring, etc. would also need careful inspection and replacement if necessary.

6. One of the rectifiers looks to be damaged, with some ruptured cables seen at the top.

7. The cost of shipping the rectifiers to and from the servicing location could make the rehabilitation of these existing rectifiers unfeasible.

8. Finally and more importantly, once the rectifiers are repaired, it is questionable if they could be guaranteed to work for another 15-20 yrs.

Looking a the present state of the impressed current systems on site and taking into consideration the above mentioned points, Halcrow does not see any need to conduct a 2nd site visit for further testing of the existing equipment.

D-1

APPENDIX D Summary of Assumptions Used in Cathodic Protection Systems for Life Cycle Analysis

D-2

Summary of Assumptions Used in Cathodic Protection Systems for Life

Cycle Analysis

For the generation of the life cycle costs for both sacrificial anode and impressed

current cathodic protection systems, approximate designs of each system were

generated based upon a series of design assumptions.

For both systems the design total design life was assumed as 50 years. A 50

year design life is a common industry standard for the design of cathodic protection

systems. The industry may use the 50 year standard based upon the idea that the

equipment used for the impressed current system has an approximate design life of 50

years (when monitored and maintained). For this work, it was assumed that anodes for

both systems would require replacement approximately 25 years after installation.

For this analysis, it was assumed that the environmental conditions were the

same at each berth location throughout Northport and Midport (Berths 1 to 29). The

average water and soil resistivities were taken as 22 ohm-cm and 100 ohm-cm

throughout Port Everglades. The average current densities in the water and soil were

assumed to be 8 ma/sq.ft. and 2 ma/sq.ft. After reviewing available “Underwater

Inspection and Assessment” reports and photos of the existing sheet pile walls, the

coating efficiency was assumed to be zero for all berths reviewed. Finally, only the

sheet pile wall surface area on the waterside of the berths was considered in the

estimation of required cathodic protection systems.

For both systems, it was assumed that underwater inspections of the walls and

anodes would be performed every 3 years. Additionally, at this time measurements

would be taken and recorded using the test stations installed with each system.

D-3

SACRIFICIAL ANODE SYSTEMS

For the sacrificial anode systems, 280-pound aluminum anodes were selected

for use at all berths in this analysis. The number of anodes required for each berth was

determined so as to provide adequate protection for the piles with a design life of 25

years. These anodes would be installed in a particular arrangement so as to provide

bonding between two adjacent piles and eliminate the necessity of additional bonding

procedures (i.e. seam welds at the interlocks or welding bonding bars to the piles) to

ensure electrical continuity. To allow for monitoring of the wall’s electrical potential and

the current supplied by the anode, each berth would be equipped with a test station and

a test anode.

IMPRESSED CURRENT SYSTEMS

For the impressed current systems, the number of rectifiers for each berth was

selected based upon the berth length and the total current estimated to protect the

sheet pile wall. In general, this equated to one rectifier for every 550 feet of berth

length. Unless the current requirement for that section exceeded 400 amps, in which

case the rectifier spacing was decreased. A platinum coated titanium element anode

with a maximum current output of 15 amps for the 25 year design life was assumed for

this analysis. Impressed current cathodic protection systems require wiring connecting

the rectifier(s) to the individual anodes and the sheet pile structure. Electrical continuity

of the steel sheet piles was assumed achieved with 2 inch seam welds at each

interlock, performed during the system installation. Test stations to periodically

measure the current requirements were assumed at 200 foot intervals along the berth.

These test stations would be connected to the walls with lead lines.

Some of the berths in Port Everglades have in the past had operational

impressed current systems. After reviewing the infrastructure (conduits, junction boxes,

etc.) that remains at these locations, it was determined that all new systems should be

installed at these locations. Therefore, included in the cost of installing impressed

current systems at all berths is the cost for saw cutting and patching of the existing

pavement for the installation of ducts, conduits and junction boxes.

E-1

APPENDIX E Sacrificial Anode vs Impressed Current

Life Cycle Cost Summary and Yearly Breakdownin Discounted Dollar Terms

Port Everglades Cathodic Protection SystemsJob No. DRSCT2120

Port Everglades, Ft. Lauderdale, FL 28-May-10

Location

Sacrificial Anode System - Present Value

Impressed Current System - Present Value

Difference During 50 Year Life Cycle

PercentageDifference

Berth 1 533.00 ft 409,816 608,962 199,146 33%Berth 2 533.00 ft 409,816 608,962 199,146 33%Berth 3 534.00 ft 409,816 609,160 199,344 33%Berth 4 900.00 ft 810,309 852,163 41,854 5%Berth 4A 300.00 ft 252,109 307,892 55,783 18%Berth 5 900.00 ft 810,309 786,907 (23,402) -3%Berth 6 378.00 ft 345,488 497,764 152,276 31%Berth 7-8 1,200.00 ft 953,491 1,366,785 413,294 30%Berth 8A 306.00 ft 291,536 448,952 157,417 35%Berth 9 -10 1,200.00 ft 953,491 1,370,025 416,534 30%Berth 11 497.00 ft 432,642 600,090 167,448 28%Berth 12-13 1,231.00 ft 750,132 785,020 34,889 4%Berth 14-15 1,231.00 ft 1,015,744 1,431,401 415,658 29%Berth 16 549.00 ft 488,670 648,300 159,630 25%Berth 17 550.00 ft 490,745 597,231 106,486 18%Berth 18 549.00 ft 488,670 596,957 108,287 18%Berth 19 650.00 ft 567,256 813,384 246,128 30%Berth 20 650.00 ft 588,007 832,515 244,508 29%Berth 21 663.00 ft 577,899 864,129 286,231 33%Berth 22 662.00 ft 577,899 863,539 285,640 33%Berth 23 240.00 ft 250,034 397,260 147,226 37%Berth 24 720.00 ft 648,452 914,100 265,648 29%Berth 25 648.00 ft 590,349 847,803 257,454 30%Berth 26 668.00 ft 604,875 870,199 265,324 30%Berth 27 668.00 ft 604,875 870,199 265,324 30%Berth 28 490.00 ft 347,563 534,556 186,993 35%Berth 28A 556.00 ft 384,915 584,197 199,282 34%Berth 28B 402.00 ft 295,686 478,951 183,266 38%Berth 29 799.00 ft 683,728 687,093 3,365 0%

Notes:Life Cycle costs are based on Recommended Replacement Order Including Master Plan Effects.Life Cycle costs of Sacrificial Anode System are based on a 25 year life over 50 years.Life Cycle costs of Impressed Current System are based on a 50 year life with anode replacement at 25 years.Construction Cost Index is 3.7%: as per Engineer News Record Historical Data Consumer Price Index is 3.0%: as per Engineer News Record Historical Data Discount Rate is 5%: Based on Current South Florida Municipal Bonds

Life Cycle Cost SummaryDiscounted Dollar Terms

Berth Length

rific

ialS

yste

m

h2

-PV

-Im

pres

sed

Syst

em

Ber

th3

-PV

-Sac

rific

ialS

yste

m

Ber

th3

-PV

-Im

pres

sed

Syst

em

Ber

th4

-PV

-Sac

rific

ialS

yste

m

Ber

th4

-PV

-Im

pres

sed

Syst

em

Ber

th4A

-PV

-Sac

rific

ialS

yste

m

Ber

th4A

-PV

-Im

pres

sed

Syst

em

Ber

th5

-PV

-Sac

rific

ialS

yste

m

Ber

th5

-PV

-Im

pres

sed

Syst

em

Ber

th6

-PV

-Sac

rific

ialS

yste

m

Ber

th6

-PV

-Im

pres

sed

Syst

em

Ber

th7-

8-P

V-S

acri

ficia

lSys

tem

Ber

th7-

8-P

V-I

mpr

esse

dSy

stem

Ber

th8A

-PV

-Sac

rific

ialS

yste

m

Ber

th8A

-PV

-Im

pres

sed

Syst

em

Ber

th9

-10

-PV

-Sac

rific

ialS

yste

m

Ber

th9

-10

-PV

-Im

pres

sed

Syst

em

Ber

th11

-PV

-Sac

rific

ialS

yste

m

Ber

th11

-PV

-Im

pres

sed

Syst

em

Ber

th12

-13

-PV

-Sac

rific

ialS

yste

m

Ber

th12

-13

-PV

-Im

pres

sed

Syst

em

Ber

th14

-15

-PV

-Sac

rific

ialS

yste

m

Ber

th14

-15

-PV

-Im

pres

sed

S

Ber

th16

-PV B

409,

816

60

9,16

0

810,

309

85

2,16

3

252,

109

30

7,89

2

810,

309

78

6,90

7

345,

488

49

7,76

4

953,

491

1,

366,

785

29

1,53

6

448,

952

95

3,49

1

1,37

0,02

5

432,

642

60

0,09

0

750,

132

78

5,02

0

1,01

5,74

4

1,43

1,40

1

488,

670

64

8,30

0-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

21

3,12

2

345,

421

44

4,30

3

417,

156

12

2,08

7

122,

283

44

4,30

3

351,

113

17

5,98

9

283,

256

52

6,95

3

876,

656

144,

845

25

3,04

6

526,

953

87

6,65

6

22

6,29

8

346,

397

40

9,56

6

388,

216

56

2,88

8

90

2,12

3

25

8,63

9

352,

747

-

5,

057

-

8,

731

-

3,

592

-

8,

731

-

4,

453

-

10

,065

-

3,96

2

-

10,0

65

-

5,

266

-

8,

192

-

10,6

41

-

5,

783

-

4,

961

-

8,

565

-

3,

524

-

8,

565

-

4,

368

-

9,

873

-

3,

886

-

9,

873

-

5,16

5

-

8,03

6

-

10

,438

-

5,67

3

4,

604

9,47

0

4,

604

8,40

2

4,

604

3,45

6

4,

604

8,40

2

4,

604

4,28

5

4,

604

9,68

5

4,

604

3,81

2

4,

604

9,68

5

4,60

4

5,

067

4,60

4

7,

883

4,60

4

10

,239

4,

604

5,56

5

-

4,77

4

-

8,24

2

-

3,39

1

-

8,24

2

-

4,20

4

-

9,50

1

-

3,74

0

-

9,50

1

-

4,

970

-

7,

733

-

10,0

44

-

5,

459

-

4,

683

-

8,

085

-

3,

326

-

8,

085

-

4,

124

-

9,

320

-

3,

668

-

9,

320

-

4,87

6

-

7,58

6

-

9,

853

-

5,

355

4,34

6

8,

939

4,34

6

7,

931

4,34

6

3,

263

4,34

6

7,

931

4,34

6

4,

045

4,34

6

9,

142

4,34

6

3,

599

4,34

6

9,

142

4,

346

4,78

3

4,

346

7,44

1

4,

346

9,66

5

4,

346

9,59

9

-

4,50

6

-

7,78

0

-

3,20

1

-

7,78

0

-

3,96

8

-

8,96

8

-

3,53

0

-

8,96

8

-

4,

692

-

7,

300

-

13,7

44

-

5,

153

-

4,

420

-

7,

632

-

7,

321

-

11

,813

-

3,

892

-

8,

797

-

3,

463

-

8,

797

-

4,60

2

-

7,16

1

-

9,

301

-

5,

055

4,10

2

8,

438

4,10

2

11

,588

4,10

2

3,

080

4,10

2

7,

486

4,10

2

3,

818

4,10

2

8,

630

4,10

2

3,

397

4,10

2

8,

630

4,

102

4,51

5

4,

102

7,02

4

4,

102

9,12

3

4,

102

9,06

1

-

4,25

3

-

7,34

4

-

3,02

1

-

7,34

4

-

3,74

6

-

8,46

5

-

3,33

2

-

8,46

5

-

4,

429

-

6,

890

-

12,9

74

-

4,

864

-

4,

172

-

7,

204

-

6,

911

-

11

,151

-

3,

674

-

8,

304

-

3,

269

-

8,

304

-

4,34

4

-

6,75

9

-

8,

779

-

4,

771

3,87

2

7,

965

3,87

2

10

,939

3,87

2

2,

907

3,87

2

7,

067

3,87

2

3,

604

3,87

2

8,

146

3,87

2

3,

206

3,87

2

12

,018

3,

872

4,26

2

3,

872

6,63

0

3,

872

8,61

2

3,

872

8,55

3

-

4,01

5

-

6,93

2

-

2,85

2

-

6,93

2

-

3,53

6

-

7,99

1

-

3,14

5

-

7,99

1

-

4,

181

-

6,

504

-

12,2

46

-

4,

591

-

3,

938

-

6,

800

-

6,

524

-

10

,526

-

3,

468

-

11

,565

-

6,81

2

-

7,83

9

-

4,

101

-

6,

380

-

8,28

7

-

4,50

4

3,

655

7,51

9

3,

655

10,3

26

3,

655

2,74

4

3,

655

6,67

0

3,

655

3,40

2

3,

655

7,68

9

3,

655

3,02

7

3,

655

11,3

44

3,65

5

4,

023

3,65

5

6,

259

3,65

5

8,

129

3,65

5

8,

073

-

3,

790

-

6,

543

-

2,

692

-

6,

543

-

3,

337

-

7,

543

-

2,

969

-

7,

543

-

3,94

6

-

6,13

9

-

11

,560

-

4,33

4

-

3,71

8

-

6,41

9

-

6,15

8

-

9,93

6

-

6,79

1

-

10,9

16

-

6,

430

-

7,

399

-

7,38

8

-

9,54

0

-

7,

822

-

4,

251

3,45

0

7,

097

3,45

0

9,

747

3,45

0

2,

590

3,45

0

6,

296

3,45

0

3,

211

3,45

0

7,

258

3,45

0

2,

857

3,45

0

10

,708

3,

450

3,79

7

3,

450

5,90

8

3,

450

7,67

3

3,

450

7,62

1

-

3,57

7

-

6,17

7

-

2,54

1

-

6,17

7

-

3,15

0

-

7,12

0

-

2,80

3

-

7,12

0

-

3,

725

-

5,

795

-

10,9

12

-

4,

091

-

3,

509

-

6,

059

-

5,

813

-

9,

379

-

6,

410

-

10

,304

-

6,06

9

-

6,98

4

-

6,

974

-

9,

005

-

7,38

4

-

4,01

3

3,

257

6,69

9

3,

257

9,20

0

3,

257

2,44

5

3,

257

5,94

3

3,

257

3,03

1

3,

257

6,85

1

3,

257

2,69

7

3,

257

10,1

08

3,25

7

3,

584

3,25

7

5,

577

3,25

7

7,

243

3,25

7

7,

193

-

56

,005

-

12

0,95

4

-

32

,002

-

12

0,95

4

-

45

,734

-

14

1,58

0

-

38,8

27

-

141,

580

-

59

,434

-

11

0,72

7

-

155,

027

-

69

,647

-

3,

312

-

5,

719

-

5,

487

-

8,

853

-

6,

051

-

9,

727

-

5,

729

-

6,

593

-

6,58

3

-

8,50

0

-

6,

970

-

3,

788

3,07

4

6,

324

3,07

4

8,

684

3,07

4

2,

308

3,07

4

5,

610

3,07

4

2,

861

3,07

4

6,

467

3,07

4

2,

546

3,07

4

9,

541

3,

074

3,38

3

3,

074

5,26

4

3,

074

6,83

7

3,

074

6,79

0

14

9,13

5

3,18

8

31

8,44

8

5,50

3

82

,463

2,26

4

31

8,44

8

5,50

3

12

1,94

0

2,80

7

37

8,97

9

6,34

4

99

,131

2,49

7

37

8,97

9

6,34

4

158,

785

3,

319

293,

007

5,

164

405,

297

9,72

3

18

2,47

1

3,64

5

-

3,12

7

-

5,39

9

-

5,17

9

-

8,35

7

-

5,71

2

-

9,18

1

-

5,40

8

-

6,22

3

-

6,

214

-

8,

024

-

6,57

9

-

3,57

6

2,

902

5,96

9

2,

902

8,19

8

2,

902

2,17

9

2,

902

5,29

6

2,

902

2,70

1

2,

902

6,10

5

2,

902

2,40

3

2,

902

9,00

6

2,90

2

3,

194

2,90

2

4,

969

2,90

2

6,

454

2,90

2

6,

409

-

3,

009

-

5,

195

-

2,

137

-

5,

195

-

2,

650

-

5,

988

-

2,

357

-

5,

988

-

3,13

3

-

4,87

4

-

9,

177

-

3,

441

-

2,

951

-

5,

096

-

4,

889

-

7,

888

-

5,

391

-

8,

667

-

5,

105

-

5,

874

-

5,86

6

-

7,57

4

-

6,

210

-

3,

375

2,73

9

5,

634

2,73

9

7,

738

2,73

9

2,

056

2,73

9

4,

999

2,73

9

2,

550

2,73

9

5,

762

2,73

9

2,

268

2,73

9

8,

502

2,

739

3,01

5

2,

739

4,69

0

2,

739

6,09

2

2,

739

6,05

0

-

2,84

0

-

4,90

4

-

2,01

7

-

4,90

4

-

2,50

1

-

5,65

3

-

2,22

5

-

5,65

3

-

2,

957

-

4,

601

-

8,66

3

-

3,24

8

-

2,78

6

-

4,81

0

-

4,61

5

-

7,44

6

-

5,08

9

-

8,18

1

-

4,81

8

-

5,54

5

-

5,

537

-

7,

149

-

5,86

2

-

3,18

6

2,

586

5,31

9

2,

586

7,30

4

2,

586

1,94

1

2,

586

4,71

9

2,

586

2,40

7

2,

586

5,43

9

2,

586

2,14

1

2,

586

8,02

5

2,58

6

2,

846

2,58

6

4,

427

2,58

6

5,

750

2,58

6

5,

711

-

2,

681

-

4,

629

-

1,

904

-

4,

629

-

2,

361

-

5,

336

-

2,

100

-

5,

336

-

2,79

1

-

4,34

3

-

8,

177

-

3,

066

-

2,

630

-

4,

541

-

4,

356

-

7,

029

-

4,

804

-

7,

722

-

4,

548

-

5,

234

-

5,22

6

-

6,74

8

-

5,

534

-

3,

007

2,44

1

5,

020

2,44

1

6,

895

2,44

1

1,

832

2,44

1

4,

454

2,44

1

2,

272

2,44

1

5,

134

2,44

1

2,

021

2,44

1

7,

575

2,

441

2,68

6

2,

441

4,17

9

2,

441

5,42

8

2,

441

5,39

1

-

2,53

1

-

4,36

9

-

1,79

7

-

4,36

9

-

2,22

8

-

5,03

7

-

1,98

3

-

5,03

7

-

2,

635

-

4,

100

-

7,71

9

-

2,89

4

-

2,48

2

-

4,28

6

-

4,11

2

-

6,63

5

-

4,53

5

-

7,28

9

-

4,29

3

-

4,94

1

-

4,

933

-

6,

370

-

5,22

3

-

2,83

9

2,

304

4,73

9

2,

304

6,50

8

2,

304

1,73

0

2,

304

4,20

4

2,

304

2,14

4

2,

304

4,84

7

2,

304

1,90

8

2,

304

7,15

0

2,30

4

2,

536

2,30

4

3,

945

2,30

4

5,

124

2,30

4

5,

089

-

2,

389

-

4,

124

-

1,

697

-

4,

124

-

2,

104

-

4,

754

-

1,

871

-

4,

754

-

2,48

7

-

3,87

0

-

7,

286

-

2,

732

-

2,

343

-

4,

046

-

3,

881

-

6,

263

-

4,

280

-

6,

881

-

4,

053

-

4,

664

-

4,65

7

-

6,01

3

-

4,

930

-

2,

680

2,17

5

4,

473

2,17

5

6,

143

2,17

5

1,

633

2,17

5

3,

969

2,17

5

2,

024

2,17

5

4,

575

2,17

5

1,

801

2,17

5

6,

750

2,

175

2,39

3

2,

175

3,72

4

2,

175

4,83

7

2,

175

4,80

3

-

2,25

5

-

3,89

3

-

1,60

2

-

3,89

3

-

1,98

6

-

4,48

8

-

1,76

6

-

4,48

8

-

2,

348

-

3,

653

-

6,87

8

-

2,57

9

-

2,21

2

-

3,81

9

-

3,66

4

-

5,91

2

-

4,04

0

-

6,49

5

-

3,82

5

-

4,40

2

-

4,

396

-

5,

676

-

4,65

4

-

2,52

9

2,

053

4,22

3

2,

053

5,79

9

2,

053

1,54

1

2,

053

3,74

6

2,

053

1,91

1

2,

053

4,31

8

2,

053

1,70

0

2,

053

6,37

1

2,05

3

2,

259

2,05

3

3,

515

2,05

3

4,

565

2,05

3

4,

534

-

2,

128

-

3,

675

-

1,

512

-

3,

675

-

1,

874

-

4,

236

-

1,

667

-

4,

236

-

2,21

6

-

3,44

8

-

6,

492

-

2,

434

-

1,

947

-

3,

464

-

3,

317

-

5,

439

-

3,

673

-

5,

990

-

3,

470

-

4,

014

-

4,00

8

-

5,21

7

-

4,

252

-

2,

247

-

3,

847

-

5,

335

-

1,

316

-

3,

398

-

1,

665

-

3,

938

-

1,

466

-

5,

876

-

1,99

4

-

3,18

0

-

4,

171

-

4,

141

-

1,

873

-

3,

333

-

1,

291

-

3,

333

-

1,

633

-

3,

863

-

1,

438

-

3,

863

-

1,95

6

-

3,11

9

-

5,

992

-

2,

162

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

tem Sa

crifi

cial

Syst

em

rth

18-P

V-I

mpr

esse

dSy

stem

Ber

th19

-PV

-Sac

rific

ialS

yste

m

Ber

th19

-PV

-Im

pres

sed

Syst

em

Ber

th20

-PV

-Sac

rific

ialS

yste

m

Ber

th20

-PV

-Im

pres

sed

Syst

em

Ber

th21

-PV

-Sac

rific

ialS

yste

m

Ber

th21

-PV

-Im

pres

sed

Syst

em

Ber

th22

-PV

-Sac

rific

ialS

yste

m

Ber

th22

-PV

-Im

pres

sed

Syst

em

Ber

th23

-PV

-Sac

rific

ialS

yste

m

Ber

th23

-PV

-Im

pres

sed

Syst

em

Ber

th24

-PV

-Sac

rific

ialS

yste

m

Ber

th24

-PV

-Im

pres

sed

Syst

em

Ber

th25

-PV

-Sac

rific

ialS

yste

m

Ber

th25

-PV

-Im

pres

sed

Syst

em

Ber

th26

-PV

-Sac

rific

ialS

yste

m

Ber

th26

-PV

-Im

pres

sed

Syst

em

Ber

th27

-PV

-Sac

rific

ialS

yste

m

Ber

th27

-PV

-Im

pres

sed

Syst

em

Ber

th28

-PV

-Sac

rific

ialS

yste

m

Ber

th28

-PV

-Im

pres

sed

Syst

em

Ber

th28

A-P

V-S

acri

ficia

lSys

tem

Ber

th28

A-P

V-I

mpr

esse

dSy

stem

Ber

th28

B-P

V-S

ac

Ber

th2

567,

256

81

3,38

4

588,

007

83

2,51

5

577,

899

86

4,12

9

577,

899

86

3,53

9

250,

034

39

7,26

0

648,

452

87

3,71

8

590,

349

84

7,80

3

604,

875

87

0,19

9

604,

875

87

0,19

9

347,

563

53

4,55

6

384,

915

58

4,19

7

295,

686

47

8,95

1

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

292,

178

50

7,30

5

304,

157

51

6,98

6

310,

146

52

5,74

3

310,

146

52

5,38

0

120,

889

22

1,34

6

350,

872

56

1,79

7

317,

333

52

2,56

3

325,

718

53

3,09

5

325,

718

53

3,09

5

177,

187

31

3,24

1

198,

748

34

5,09

4

147,

241

27

9,15

9

-

6,

310

-

6,

502

-

6,

595

-

6,

588

-

3,

582

-

7,

240

-

6,

703

-

6,

852

-

6,

852

-

4,

470

-

4,

820

-

4,

004

-

6,

190

-

6,

379

-

6,

469

-

6,

462

-

3,

514

-

7,

102

-

6,

575

-

6,

721

-

6,

721

-

4,

385

-

4,

728

-

3,

927

4,60

4

6,

072

4,60

4

6,

257

4,60

4

6,

346

4,60

4

6,

339

4,60

4

3,

447

4,60

4

4,

604

4,60

4

6,

450

4,60

4

6,

593

4,60

4

6,

593

4,60

4

4,

301

4,60

4

4,

638

4,60

4

3,

853

-

5,

956

-

6,

138

-

10

,742

-

10

,735

-

3,

381

-

-

-

6,

327

-

6,

468

-

6,

468

-

4,

219

-

4,

550

-

3,

779

-

5,

843

-

6,

021

-

6,

107

-

6,

100

-

3,

317

-

-

-

6,

207

-

6,

345

-

6,

345

-

4,

139

-

4,

463

-

3,

707

4,34

6

5,

732

4,34

6

5,

906

4,34

6

5,

990

4,34

6

5,

984

4,34

6

3,

254

4,34

6

4,

346

4,34

6

6,

088

4,34

6

6,

224

4,34

6

6,

224

4,34

6

4,

060

4,34

6

4,

378

4,34

6

3,

637

-

5,

623

-

5,

794

-

10

,139

-

10

,133

-

3,

192

-

-

-

5,

972

-

6,

105

-

6,

105

-

3,

983

-

4,

295

-

3,

567

-

5,

515

-

5,

683

-

5,

764

-

5,

758

-

3,

131

-

-

-

5,

859

-

5,

989

-

5,

989

-

3,

907

-

4,

213

-

3,

499

4,10

2

5,

410

4,10

2

5,

575

4,10

2

5,

655

4,10

2

5,

649

4,10

2

3,

071

4,10

2

4,

102

4,10

2

5,

747

4,10

2

5,

875

4,10

2

5,

875

4,10

2

3,

833

4,10

2

4,

133

4,10

2

3,

433

-

5,

307

-

5,

469

-

9,

571

-

9,

565

-

3,

013

-

-

-

5,

638

-

5,

763

-

5,

763

-

3,

760

-

4,

054

-

3,

367

-

5,

206

-

5,

365

-

5,

441

-

5,

435

-

2,

955

-

-

-

5,

530

-

5,

653

-

5,

653

-

3,

688

-

3,

977

-

3,

303

3,87

2

5,

107

3,87

2

5,

263

3,87

2

5,

338

3,87

2

5,

332

3,87

2

2,

899

3,87

2

3,

872

3,87

2

5,

425

3,87

2

5,

546

3,87

2

5,

546

3,87

2

3,

618

3,87

2

3,

901

3,87

2

3,

240

-

5,

010

-

5,

162

-

9,

034

-

9,

029

-

2,

844

-

-

-

5,

322

-

9,

238

-

9,

238

-

7,

347

-

7,

625

-

6,

977

-

4,

914

-

5,

064

-

5,

136

-

5,

131

-

2,

790

-

-

-

5,

220

-

5,

336

-

5,

336

-

3,

481

-

3,

754

-

3,

118

3,65

5

4,

821

3,65

5

4,

968

3,65

5

5,

038

3,65

5

5,

033

3,65

5

2,

737

3,65

5

3,

655

3,65

5

5,

121

3,65

5

5,

235

3,65

5

5,

235

3,65

5

3,

415

3,65

5

3,

682

3,65

5

3,

059

-

8,

314

-

8,

459

-

8,

528

-

8,

523

-

6,

270

-

-

-

8,

609

-

8,

720

-

8,

720

-

6,

935

-

7,

198

-

6,

586

-

4,

639

-

4,

780

-

4,

848

-

4,

843

-

2,

633

-

-

-

4,

928

-

5,

037

-

5,

037

-

3,

286

-

3,

543

-

2,

943

3,45

0

4,

550

3,45

0

4,

689

3,45

0

4,

756

3,45

0

4,

751

3,45

0

2,

583

3,45

0

3,

450

3,45

0

4,

834

3,45

0

4,

941

3,45

0

4,

941

3,45

0

3,

223

3,45

0

3,

476

3,45

0

2,

887

-

7,

848

-

7,

984

-

8,

050

-

8,

045

-

5,

919

-

-

-

8,

126

-

8,

232

-

8,

232

-

6,

547

-

6,

794

-

6,

217

-

4,

379

-

4,

512

-

4,

576

-

4,

572

-

2,

486

-

-

-

4,

651

-

4,

755

-

4,

755

-

3,

102

-

3,

345

-

2,

778

3,25

7

4,

295

3,25

7

4,

426

3,25

7

4,

489

3,25

7

4,

484

3,25

7

2,

438

3,25

7

3,

257

3,25

7

4,

563

3,25

7

4,

664

3,25

7

4,

664

3,25

7

3,

043

3,25

7

3,

281

3,25

7

2,

725

-

79

,772

-

83

,190

-

86

,541

-

86

,536

-

35

,190

-

-

-

86

,613

-

90

,002

-

90

,002

-

48

,940

-

55

,752

-

42

,050

-

4,

133

-

4,

259

-

4,

320

-

4,

315

-

2,

346

-

-

-

4,

391

-

4,

488

-

4,

488

-

2,

928

-

3,

157

-

2,

622

3,07

4

4,

055

3,07

4

4,

178

3,07

4

4,

238

3,07

4

4,

233

3,07

4

2,

302

3,07

4

3,

074

3,07

4

4,

307

3,07

4

4,

403

3,07

4

4,

403

3,07

4

2,

872

3,07

4

3,

097

3,07

4

2,

572

207,

035

6,

993

215,

807

7,

114

220,

194

7,

173

220,

194

7,

168

81,5

86

5,

274

250,

021

25

0,02

1

225,

457

7,

241

231,

598

7,

334

231,

598

7,

334

122,

817

5,

833

138,

608

6,

054

100,

886

5,

539

-

3,

902

-

4,

020

-

4,

078

-

4,

073

-

2,

215

-

-

-

4,

144

-

4,

237

-

4,

237

-

2,

764

-

2,

980

-

2,

475

2,90

2

3,

827

2,90

2

3,

944

2,90

2

4,

000

2,90

2

3,

996

2,90

2

2,

173

2,90

2

2,

902

2,90

2

4,

065

2,90

2

4,

156

2,90

2

4,

156

2,90

2

2,

711

2,90

2

2,

923

2,90

2

2,

428

-

6,

601

-

6,

715

-

6,

770

-

6,

766

-

4,

978

-

-

-

6,

835

-

6,

923

-

6,

923

-

5,

506

-

5,

714

-

5,

229

-

3,

683

-

3,

795

-

3,

849

-

3,

845

-

2,

091

-

-

-

3,

912

-

3,

999

-

3,

999

-

2,

609

-

2,

813

-

2,

337

2,73

9

3,

613

2,73

9

3,

723

2,73

9

3,

776

2,73

9

3,

772

2,73

9

2,

051

2,73

9

2,

739

2,73

9

3,

838

2,73

9

3,

923

2,73

9

3,

923

2,73

9

2,

559

2,73

9

2,

759

2,73

9

2,

292

-

6,

231

-

6,

339

-

6,

391

-

6,

387

-

4,

699

-

-

-

6,

451

-

6,

535

-

6,

535

-

5,

197

-

5,

394

-

4,

935

-

3,

476

-

3,

582

-

3,

633

-

3,

629

-

1,

973

-

-

-

3,

693

-

3,

775

-

3,

775

-

2,

463

-

2,

655

-

2,

206

2,58

6

3,

410

2,58

6

3,

514

2,58

6

3,

564

2,58

6

3,

560

2,58

6

1,

936

2,58

6

2,

586

2,58

6

3,

622

2,58

6

3,

703

2,58

6

3,

703

2,58

6

2,

416

2,58

6

2,

605

2,58

6

2,

164

2,53

6

5,

882

2,53

6

5,

984

-

6,

033

-

6,

029

-

4,

435

-

-

-

6,

090

-

6,

169

-

6,

169

-

4,

906

-

5,

092

-

4,

659

2,48

8

3,

281

2,48

8

3,

381

-

3,

430

-

3,

426

-

1,

863

-

-

-

3,

486

-

3,

563

-

3,

563

-

2,

325

-

2,

506

-

2,

082

2,44

1

3,

219

2,44

1

3,

317

2,44

1

3,

364

2,44

1

3,

361

2,44

1

1,

827

2,44

1

2,

441

2,44

1

3,

419

2,44

1

3,

495

2,44

1

3,

495

2,44

1

2,

280

2,44

1

2,

459

2,44

1

2,

042

2,39

4

5,

552

2,39

4

5,

648

-

5,

694

-

5,

691

-

4,

187

-

-

-

5,

748

-

5,

823

-

5,

823

-

4,

631

-

4,

806

-

4,

398

2,34

9

3,

098

2,34

9

3,

192

-

3,

237

-

3,

234

-

1,

758

-

-

-

3,

290

-

3,

363

-

3,

363

-

2,

194

-

2,

366

-

1,

965

2,30

4

3,

039

2,30

4

3,

131

2,30

4

3,

176

2,30

4

3,

172

2,30

4

1,

725

2,30

4

2,

304

2,30

4

3,

228

2,30

4

3,

299

2,30

4

3,

299

2,30

4

2,

152

2,30

4

2,

321

2,30

4

1,

928

2,26

0

5,

241

2,26

0

5,

331

-

5,

375

-

5,

372

-

3,

952

-

-

-

5,

426

-

5,

497

-

5,

497

-

4,

371

-

4,

537

-

4,

151

2,21

7

2,

924

2,21

7

3,

013

-

3,

056

-

3,

053

-

1,

660

-

-

-

3,

106

-

3,

175

-

3,

175

-

2,

071

-

2,

233

-

1,

855

2,17

5

2,

868

2,17

5

2,

956

2,17

5

2,

998

2,17

5

2,

994

2,17

5

1,

628

2,17

5

2,

175

2,17

5

3,

047

2,17

5

3,

114

2,17

5

3,

114

2,17

5

2,

032

2,17

5

2,

191

2,17

5

1,

820

2,13

3

4,

947

2,13

3

5,

033

-

5,

074

-

5,

071

-

3,

730

-

-

-

5,

122

-

5,

188

-

5,

188

-

4,

126

-

4,

282

-

3,

918

2,09

3

2,

760

2,09

3

2,

844

-

2,

885

-

2,

881

-

1,

567

-

-

-

2,

932

-

2,

997

-

2,

997

-

1,

955

-

2,

108

-

1,

751

2,05

3

2,

707

2,05

3

2,

790

2,05

3

2,

830

2,05

3

2,

827

2,05

3

1,

537

2,05

3

2,

053

2,05

3

2,

876

2,05

3

2,

940

2,05

3

2,

940

2,05

3

1,

918

2,05

3

2,

068

2,05

3

1,

718

2,01

4

4,

669

2,01

4

4,

750

-

4,

789

-

4,

786

-

3,

521

-

-

-

4,

835

-

4,

898

-

4,

898

-

3,

895

-

4,

042

-

3,

699

-

2,

464

-

2,

544

-

2,

582

-

2,

579

-

1,

338

-

-

-

2,

626

-

2,

688

-

2,

688

-

1,

704

-

1,

849

-

1,

512

-

2,

417

-

2,

495

-

2,

533

-

2,

530

-

1,

312

-

-

-

2,

576

-

2,

637

-

2,

637

-

1,

672

-

1,

814

-

1,

483

-

4,

272

-

4,

348

-

4,

385

-

4,

382

-

3,

188

-

-

-

4,

428

-

4,

487

-

4,

487

-

3,

541

-

3,

680

-

3,

356

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

F-1

APPENDIX F Sacrificial Anode vs Impressed Current

Life Cycle Cost Summary in Real 2010 Dollar Terms

Port Everglades Cathodic Protection SystemsJob No. DRSCT2120

Port Everglades, Ft. Lauderdale, FL 28-May-10

Location

Sacrificial Anode System - Present Value

Impressed Current System - Present Value

Difference During 50 Year Life Cycle

PercentageDifference

Berth 1 533.00 ft 503,364 779,914 276,550 35%Berth 2 533.00 ft 503,364 779,914 276,550 35%Berth 3 534.00 ft 503,364 780,230 276,866 35%Berth 4 900.00 ft 977,391 1,133,573 156,181 14%Berth 4A 300.00 ft 316,701 428,720 112,020 26%Berth 5 900.00 ft 977,391 1,065,863 88,472 8%Berth 6 378.00 ft 427,225 644,147 216,922 34%Berth 7-8 1,200.00 ft 1,146,862 1,695,086 548,224 32%Berth 8A 306.00 ft 363,367 582,283 218,917 38%Berth 9 -10 1,200.00 ft 1,146,862 1,700,155 553,293 33%Berth 11 497.00 ft 530,381 771,937 241,556 31%Berth 12-13 1,231.00 ft 906,164 1,045,058 138,894 13%Berth 14-15 1,231.00 ft 1,220,545 1,781,955 561,410 32%Berth 16 549.00 ft 596,696 841,244 244,548 29%Berth 17 550.00 ft 599,152 789,022 189,870 24%Berth 18 549.00 ft 596,696 788,605 191,909 24%Berth 19 650.00 ft 711,084 1,022,302 311,218 30%Berth 20 650.00 ft 735,645 1,047,430 311,785 30%Berth 21 663.00 ft 702,308 1,086,709 384,400 35%Berth 22 662.00 ft 702,308 1,085,967 383,659 35%Berth 23 240.00 ft 314,245 519,638 205,393 40%Berth 24 720.00 ft 785,816 1,152,520 366,704 32%Berth 25 648.00 ft 717,045 1,068,773 351,729 33%Berth 26 668.00 ft 734,238 1,097,599 363,362 33%Berth 27 668.00 ft 734,238 1,097,599 363,362 33%Berth 28 490.00 ft 429,681 685,895 256,213 37%Berth 28A 556.00 ft 473,891 747,154 273,263 37%Berth 28B 402.00 ft 368,279 616,296 248,017 40%Berth 29 799.00 ft 827,569 928,036 100,466 11%

Notes:Life Cycle costs are based on Recommended Replacement Order Including Master Plan Effects.Life Cycle costs of Sacrificial Anode System are based on a 25 year life over 50 years.Life Cycle costs of Impressed Current System are based on a 50 year life with anode replacement at 25 years.Construction Cost Index is 3.7%: as per Engineer News Record Historical Data Consumer Price Index is 3.0%: as per Engineer News Record Historical Data Discount Rate is 5%: Based on Current South Florida Municipal Bonds

Life Cycle Costs SummaryReal 2010 Dollar Terms

Berth Length

G-1

APPENDIX G Sacrificial Anode vs Impressed Current

Life Cycle Cost Summary in Nominal Dollar Terms

Port Everglades Cathodic Protection SystemsJob No. DRSCT2120

Port Everglades, Ft. Lauderdale, FL 28-May-10

Location

Sacrificial Anode System - Present Value

Impressed Current System - Present Value

Difference During 50 Year Life Cycle

PercentageDifference

Berth 1 533.00 ft 968,020 1,378,942 410,923 30%Berth 2 533.00 ft 968,020 1,378,942 410,923 30%Berth 3 534.00 ft 968,020 1,379,698 411,679 30%Berth 4 900.00 ft 1,855,017 2,109,712 254,695 12%Berth 4A 300.00 ft 618,736 857,622 238,886 28%Berth 5 900.00 ft 1,855,017 2,031,476 176,459 9%Berth 6 378.00 ft 825,549 1,163,363 337,815 29%Berth 7-8 1,200.00 ft 2,172,130 2,827,848 655,718 23%Berth 8A 306.00 ft 706,057 1,055,213 349,156 33%Berth 9 -10 1,200.00 ft 2,172,130 2,840,510 668,380 24%Berth 11 497.00 ft 1,018,574 1,377,485 358,911 26%Berth 12-13 1,231.00 ft 1,721,738 1,950,456 228,718 12%Berth 14-15 1,231.00 ft 2,310,005 2,991,976 681,971 23%Berth 16 549.00 ft 1,142,662 1,515,555 372,893 25%Berth 17 550.00 ft 1,147,257 1,459,895 312,637 21%Berth 18 549.00 ft 1,142,662 1,458,949 316,287 22%Berth 19 650.00 ft 1,429,215 1,757,443 328,227 19%Berth 20 650.00 ft 1,475,174 1,802,885 327,711 18%Berth 21 663.00 ft 1,340,283 1,862,571 522,288 28%Berth 22 662.00 ft 1,340,283 1,861,276 520,993 28%Berth 23 240.00 ft 614,140 961,495 347,355 36%Berth 24 720.00 ft 1,496,541 1,987,339 490,798 25%Berth 25 648.00 ft 1,367,858 1,844,825 476,967 26%Berth 26 668.00 ft 1,400,029 1,893,674 493,645 26%Berth 27 668.00 ft 1,400,029 1,893,674 493,645 26%Berth 28 490.00 ft 830,145 1,224,696 394,552 32%Berth 28A 556.00 ft 912,870 1,324,988 412,118 31%Berth 28B 402.00 ft 715,249 1,107,296 392,047 35%Berth 29 799.00 ft 1,574,671 1,771,697 197,026 11%

Notes:Life Cycle costs are assumed to be installed at all locations in 2012 for comparison purposes onlyLife Cycle costs of Sacrificial Anode System are based on a 25 year life over 50 years.Life Cycle costs of Impressed Current System are based on a 50 year life with anode replacement at 25 years.Construction Cost Index is 3.7%: as per Engineer News Record Historical Data Consumer Price Index is 3.0%: as per Engineer News Record Historical Data Discount Rate is 5%: Based on Current South Florida Municipal Bonds

Life Cycle Cost SummaryNominal Dollar Terms

Berth Length