power scenario of india-final -2012
DESCRIPTION
it is final report of power scenario of india by national thermal power plant anta.TRANSCRIPT
04/08/23 1
04/08/23 2
ISSUES & CHALLENGES IN INDIA’S POWER SECTOR
Power Shortage and Capacity Addition
Fuel Choice
Improving Efficiency
Promoting Competition
04/08/23 3
ELECTRICITY AS PRIVATE ENTERPRISE
Pre-1948, all generation privately-owned. Total
installed capacity:1300 MW
• Retail distribution only around generating stations.
• No transmission.
Licensed & regulated by Govt. under Indian
Electricity Act, 1910.
Govt’s role as regulator only.
04/08/23 4
ELECTRICITY NATIONALIZED• Post–Independence, Electricity( Supply) Act, 1948, aimed
to increase access to electricity.
• Transmission to wider hinterland of generating stations – creation of grid.
• All privately-owned generating stations nationalized with some exceptions.
• Creation of vertically-integrated SEBs as quasi-commercial entities.
• Govt.becomes owner and operator in addition to being regulator. Conflict of interest.
04/08/23 5
DOWNWARD SLIDE• Large demand-supply gap (2009-10) -
Energy shortage:10% Peak shortage:12.7%• Low per capita consumption: 672 kwh per annum• By early 90’s, State Electricity Boards were bankrupt. • Accumulated losses of the SEBs exceeded Rs.26,000
crores in 2000-01. • Unpaid dues to central power generating companies
alone exceeded Rs. 40,000 crores.• Total return of SEBs in 2005-06 was (-) 26%.• Financial collapse leading to operational collapse
04/08/23 6
INDIA’S INSTALLED CAPACITY BY FUEL(as on 30 APRIL 2012)
INDIA'S INSTALLED CAPACITY
Fuel MW % age
TOTAL THERMAL 131703.36 65.86
COAL 112022.38 56.02
GAS 18481.05 9.24
DIESEL 1199.93 0.60
NUCLEAR 4780 2.39
HYDRO 38990.4 19.50
RES 24503.46 12.25
199977.22 100.00
INDIA’S INSTALLED CAPACITY FUEL WISE AS ON 30 APRIL 2012
04/08/23 8
ELECTRICITY GENERATION IN SELECTED COUNTRIES 2007 & 2009
COUNTRY GENERATION
2007 (in Twh)
%age of total
GENERATION
2009 (in Twh)
%age of total
U.S.A 4367.0 22.0 4149.6 20.7
China 3277.7 16.5 3725.1 18.5
Japan 1160.0 5.8 1115.1 5.5
Russian Fed.
1014.9 5.1 993.1
4.9
India 774.7 3.9 869.8 4.3
Germany 636.5 3.2 596.8
3.0
04/08/23 9
PER CAPITA CONSUMPTION OF ELECTRICITY (in Kwh per annum)
World Average
OECD countries
Middle East
Latin America
China
2596
8365
2980
1695
1802
Asia
Africa
India
646
563
612
SOURCE : WEC WORLD ENERGY STATISTICS,2007
04/08/23 10
PER CAPITA CONSUMPTION OF ELECTRICITY IN INDIA
YEAR PER CAPITA CONSUMPTION
1950 15 KWh / per year
2007 672 KWh / per year
2012 - Target 1000 KWh / per year
04/08/23 11
ELECTRICITY & GROWTH
04/08/23 12
PAYING FOR POWER IS KEY Poor metering - only 40% of total sale metered. Billing on presumptive / assessed consumption.
Poor billing & collection – only 55% of energy generated is billed & only 41% realised.
High T&D losses( 40- 50 % approx ) – No serious attempt to address issue.
Tariff recovers on an average 69% of the cost of supply. Domestic recovery : 56%. Agriculture recovery : 15%
Distribution segment losing Rs. 47,000 crores annually. ( MoP estimates )
04/08/23 13
POWER FOR ALL BY 2012
Required capacity addition–from 100,000 MW in 2000 to 200,000 MW and per capita consumption to go up from 672 KWh to 1000 KWh by 2012.
From 1300 MW in 1947 to 100,000 MW in 2000 – 53 years. Only 12 years for another 100,000 MW. Is it feasible?
Funds required – Rs. 9,00,000 crores including transmission systems at 2002-03 prices ( CEA estimates ).
04/08/23 14
CHALLENGE OF CAPACITY ADDITION
Plan Period Addition
(in MW)
Percentage of Plan target
Eighth Plan 16,422 53.8
Ninth Plan 19,015 < 50
Tenth Plan 23,250 56.6
Eleventh Plan
(target)
78,530 Thermal– 58,597Hydro – 16,553Nuclear – 3,380
04/08/23 15
FUEL CHOICE - COAL• Coal reserves, at current level of consumption, can
last some 80 years.
• If all inferred reserves materialize, coal & lignite can last for more than 140 years.
• If domestic coal production continues to grow at 5 percent per year, total extractable reserves would run out in about 40 years.
• In-situ coal gasification can increase energy from domestic resources significantly.
04/08/23 16
FUEL CHOICE - GAS
• Poor natural gas reserves till discovery in Krishna-
Godavari basin by Reliance
• Recent large discovery by GSPC also in Krishna-
Godavari basin
• Coal Bed Methane reserves estimated to be between
1400 BCM (1260 mtoe) to 2600 BCM (2540 mtoe).
• Proved gas and CBM together can last for some 50
years.
04/08/23 17
FUEL CHOICE - HYDRO
• Present installed capacity is 36,877 MW.
• At the last 5 years’ average of 30% load factor,
1,50,000 MW of installed capacity justified.
Accelerated hydro development plan aims to add
50,000 MW of new capacity.
• Problems of environment and ecology and social
problems of resettlement of project affected people are
barriers to large-scale exploitation of hydro resources.
04/08/23 18
FUEL CHOICE - NUCLEAR• India poorly endowed with uranium, just enough to fuel
10,000 MW.
• India’s uranium reserves are of low grade, extraction
percentage being 0.1% compared to 12-14% abroad.
Therefore 3-4 times costlier than international supplies.
• Substantial thorium reserves has to be converted to fissile
material through Fast Breeder Reactors.
• India has to import uranium fuel and FBR technology.
04/08/23 19
POWER PURCHASE COST AS %AGE OF COST OF SUPPLY
357
469
365 349
Power purchase cost►
Other cost►
Power purchase cost as %age of cost
of supply 62 77 73 66
Maharashtra Delhi Gujarat All India
Paise per kwH
04/08/23 20
COST-PLUS FALL-OUT
While differences in power cost of generating stations
can be due to differences in fuel type, technology, location
and vintage, most differences are attributable to differing
generation efficiencies
Cost-plus tariff system does not adequately encourage /
incentivise generators to improve operational efficiencies
04/08/23 21
PURCHASE PRICE DIFFERENCES
Power plant Type MUs Rs/Kwh
•Salal
•Baira Siul
•Tanakpur
•Singrauli
•Chamera
•Rihand
•Anta
•Auraiya
•Unchahar-I
•Dadri
•Badarpur BTPS
•Hydro
•Hydro
•Hydro
•Thermal
•Hydro
•Hydro
•Thermal
•Thermal
•Thermal
•Thermal
•Thermal
358
86
58
1,370
132
850
375
0.59
0.63
1.04
1.09
1.32
1.47
1.61
1.62
1.88
2.27
600
190
4,6005,065
2.37
04/08/23 22
POWER PURCHASE CONTRACTS
•Upto one year duration contracts form small part of total power procured. SEBs propose power purchase from third parties in their ARRs, prior to actual contract
Long term
Short term
•Real time power requirement (in excess or deficit of scheduled drawls) drawn directly from grid without any prior permission from regulator
Real time/day to day
•No clear process for bridging medium term requirements (more than a year and less than 15 years
–Self generation (SEB owned generators);
–capacity cleared by SERC
–Allocation from central generating stations ; CERC
determines tariffs
–Independent power producers; Bid/MOU route for projects;
CERC/SERC vets the tariff
Medium term
04/08/23 23
LEGISLATIVE FRAMEWORK FOR COMPETITION
Gencos free to supply electricity to any licensee or to any consumer
Non-discriminatory open access to Gencos, licensees & consumers in transmission & distribution.
Open access enables non-discriminatory sale/purchase of electric power/energy between two parties utilizing the system of an in-between (third party), and latter not blocking it on unreasonable grounds.
04/08/23 24
FRAMEWORK FOR COMPETITION Section 63 of the Act moves away from the
existing regulated cost-plus tariff to tariff determination through competitive bidding route.
“Notwithstanding anything contained in section 62, the Appropriate Commission shall adopt the tariff if such tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government.”(Section 63 of the Electricity Act, 2003)
04/08/23 25
COMPETITION IN GENERATION The Central Government guidelines issued
for tariff-based bidding process for procurement of electricity by DISCOMS for medium term (one to seven years) and for long-term (for more than seven years).
Section 66 of the Act provides for development of electricity market for price determination/price discovery.
A well functioning power market leading to free competition provides national-level access to all buyers and sellers for transparent price discovery, rewards more efficient generators and reduces power procurement cost.
04/08/23 26
TOWARDS A COMPETITIVE MARKET STRUCTURE
Electricity Act 2003
Electricity Act 2003
Comp. Bidding Guidelines -2004/5
Comp. Bidding Guidelines -2004/5
National ‘Tariff’ Policy
-2006
National ‘Tariff’ Policy
-2006
Open Access Open Access
Competitive & Contestable Price Discovery in New
Generation
Competitive & Contestable Price Discovery in New
Generation
•Open access•Competitive bidding•Separating wires•Enforcing USO
•Open access•Competitive bidding•Separating wires•Enforcing USO
Wholesale andRetail Competition
Wholesale andRetail Competition
04/08/23 2727
A NEW STRUCTUREWholesale power purchase model
Reformed structure for power purchase
•Single buyer model - SEB/TRANSCO pools
distribution utility requirements to procure
power
•Multiple buyer model (e.g., each distribution
company procuring for its own requirements)
•Primarily long duration contracts 15 -25 years or
more
•Suitable mix of long, medium and short term
contracts
•Limited incentives to improve efficiency
•Market rewards players with lower costs and higher efficiencies
04/08/23 28
COMPETITIVE BIDDING
04/08/23 29
COMPETITIVE BIDDING
04/08/23 30
04/08/23 31
SEB MODEL
04/08/23 32
FIRST STAGE REFORM MODEL
04/08/23 33
PRESENT REFORM MODEL
04/08/23 34
FINAL REFORM MODEL
04/08/23 35
04/08/23 36
04/08/23 37
04/08/23 38
04/08/23 39
POWER SUPPLY REGIONS
INDIA IS ADMINISTRATIVELY DIVIDED INTO FIVE REGIONS FOR SUPPLY OF ELECTRICITY.
1. NORTHERN REGION2. SOUTHERN REGION 3. EASTERN REGION4. WESTERN REGION5. NORTH EASTERN REGION
04/08/23 40
NORTHERN REGION•Largest in geographical area amongst the five regions covering 30.7% of the area and 28% of the country’s population.
•Largest number of constituents (9 states/UT’s, 3 Central Generating Companies, one Central Transmission Utility and Bhakra Beas Management Board).
•Largest sized hydro unit (250 MW at Nathpa Jhakri) in the country.
•Establishment of the first super thermal power station (Singrauli STPS) and 400 kV transmission system in the country.
04/08/23 41
NORTHERN REGION•Establishment of the first High Voltage Direct Current (HVDC) long distance transmission system in the country (2x750 MW, + 500 kV Rihand-Dadri HVDC bipole).
•First HVDC back-to-back interconnection with Western Region (2x250 MW back-to-back HVDC station at Vindhyachal).
•First 400 kV Static Var Compensators (SVC’s) in the country (2x + 140 MVAR SVC at Kanpur).
•Largest capacity of combined cycle gas power stations amongst the five regions (2939.50 MW) located along the 700 Kms. long Hazira-Bijaipur-Jagdishpur (HBJ) natural gas pipeline of GAIL.
04/08/23 42
NRLDC
NRLDC is the apex body to ensure integrated operation of the power system in the Northern Region. The main responsibilities of NRLDC are: •Monitoring of system parameters and security. •To ensure the integrated operation of the power system grid in the region. •System studies, planning and contingency analysis. •Analysis of tripping/disturbances and facilitating immediate remedial measures. •Daily scheduling and operational planning.
04/08/23 43
NRLDC
•Facilitating bilateral and inter-regional exchanges. •Computation of energy dispatch and drawl values using SEMs. •Augmentation of telemetry, computing and communication facilities
04/08/23 44
Brief details about the Northern Regional power system i) Northern regional grid is an electrical system comprising of over 10,00,000 sq. km of area with nine States/Union Territories namely Punjab, Haryana, Rajasthan, Delhi, Uttar Pradesh, Himachal Pradesh, Uttaranchal, Jammu Kashmir and Union territory of Chandigarh, Generating Stations at Central and State Sector Independent Power producing stations, State DISCOMS, STU etc.
04/08/23 45
ii) The Northern region has an installed capacity of 33,785 MW as on 31.03.2006 with 16,295 MW in State Sector and 17,490 MW in Central Sector including BBMB.
iii) The States are inter-connected with each other through 400kV/220 kV network. Northern Region is connected to Western and Eastern regions through a few radial 220 kV/132 kV HVAC and HVDC Back to Back links to facilitate exchange of power from surplus to deficit region / State as well as wheeling of power.
04/08/23 46
iv) Northern Region has catered a maximum peak demand of 25,362 MW on 19.08.2005 with an average energy consumption of 462.96 MU during the year 2005-06.
04/08/23 47
04/08/23 48
INCREASE IN POWER GENERATION DUE TO INCREASE IN PLANT LOAD FACTOR
04/08/23 49
04/08/23 50
04/08/23 51
04/08/23 52
04/08/23 53
04/08/23 54
04/08/23 55
04/08/23 56
04/08/23 57
INSTALLED CAPACITY OF NORTHERN GRID AS ON 30.04.12
DESCRIPTION UNIT TOTAL CAPACITY
THERMAL (INCL. GAS) MW 32791.75
NUCLEAR MW 1620
HYDRO MW 15122.75
RENEWABLE ENERGY SOURCES
MW
4391.4
TOTAL MW 53925.9
04/08/23 58
INSTALLED CAPACITY OF WESTERN GRID AS ON 30.04.12
DESCRIPTION UNIT TOTAL CAPACITY
THERMAL (INCL. GAS) MW 47296.79NUCLEAR MW 1840HYDRO MW 7447.5RENEWABLE ENERGY SOURCES MW
7909.95TOTAL MW 64494.24
04/08/23 59
INSTALLED CAPACITY OF SOUTHERN GRID AS ON 30.04.12
DESCRIPTION UNIT TOTAL CAPACITY
THERMAL (INCL. GAS) MW 28512.6NUCLEAR MW 1320HYDRO MW 11338.03RENEWABLE ENERGY SOURCES
MW
11569.3TOTAL MW 52739.93
04/08/23 60
INSTALLED CAPACITY OF EASTERN GRID AS ON 30.04.12
DESCRIPTION UNIT TOTAL CAPACITY
THERMAL (INCL. GAS) MW 22005.08NUCLEAR MW 0HYDRO MW 3882.12RENEWABLE ENERGY SOURCES
MW
398.71TOTAL MW 26285.91
04/08/23 61
INSTALLED CAPACITY OF NORTH EASTERN GRID AS ON 30.04.12
DESCRIPTION UNIT TOTAL CAPACITY
THERMAL (INCL. GAS) MW 1026.94NUCLEAR MW 0HYDRO MW 1200RENEWABLE ENERGY SOURCES
MW
228TOTAL MW 2454.94
04/08/23 62
INSTALLED CAPACITY OF ISLANDS GRID AS ON 30.04.11
DESCRIPTION UNIT TOTAL CAPACITY
THERMAL (INCL. GAS) MW 70.2NUCLEAR MW 0HYDRO MW 0RENEWABLE ENERGY SOURCES
MW
6.1TOTAL MW 76.3
04/08/23 63
INSTALLED CAPACITY OF INDIA AS ON 30.04.2011
DESCRIPTION UNIT TOTAL CAPACITY
THERMAL (INCL. GAS) MW 131703.4NUCLEAR MW 4780.0HYDRO MW 38990.4RENEWABLE ENERGY SOURCES
MW
24503.46TOTAL MW 199977.2
04/08/23 64
FUEL WISE INSTALLED CAPACITY OF INDIA AS ON 30.04.12
DESCRIPTION UNIT TOTAL CAPACITY
COAL BASED MW 112022.4GAS MW 18481.05DIESEL MW 1199.93HYDRO MW 4780NUCLEAR MW 38990.4RENEWABLE ENERGY SOURCES MW
24503.46TOTAL MW 199977.2
04/08/23 65
COST OF GENERATION FOR THE YEAR 2006-07
04/08/23 66
COST OF GENERATION FOR THE YEAR 2006-07
04/08/23 67
NTPC INSTALLED CAPACITYCOAL BASED
(Owned by NTPC)STATE
COMMISSIONEDCAPACITY(MW)
1. SINGRAULI Uttar Pradesh 2,0002. Korba Chhattisgarh 2,6003. Ramagundam Andhra Pradesh 2,6004. Farakka West Bengal 2,1005. Vindhyachal Madhya Pradesh 3,2606. Rihand Uttar Pradesh 2,0007. Kahalgaon Bihar 2,340
8. NCTPP, Dadr Uttar Pradesh1,820
9. Talcher Kaniha Orissa 3,000
10. Feroze Gandhi, Unchahar Uttar Pradesh 1,050
11. Talcher Thermal Orissa 46012. Simhadri Andhra Pradesh 2,00013. Tanda Uttar Pradesh 44014. Badarpur Delhi 70515. Sipat Chhattisgarh 2,32016 Mauda Maharashtra 500
Total 29,195
04/08/23 68
NTPC INSTALLED CAPACITY
Gas based State Commissioned
Capacity(MW)
16. Anta Rajasthan 413
17. Auraiya Uttar Pradesh 652
18. Kawas Gujarat 645
19. Dadri Uttar Pradesh 817
20. Jhanor-Gandhar Gujarat 648
21. Rajiv Gandhi CCPP Kayamkulam Kerala 350
22. Faridabad Haryana 430
Total (Gas) 3,955
04/08/23 69
NTPC INSTALLED CAPACITYGAS Power Plants with Joint
Ventures COAL
BASED (Owned by
JVs)
STATE COMMISSIONED
CAPACITY
1. RGPPL Maharashtra 1940Total 1940
04/08/23 70
NTPC INSTALLED CAPACITYPower Plants with Joint Ventures
COAL BASED (Owned by JVs)
STATE COMMISSIONED
CAPACITY
1. Durgapur West Bengal 120
2. Rourkela Orissa 120
3. Bhilai Chhattisgarh 574
4. Kanti Bihar 110
5. IGSTPP, Jhajjar Haryana 1000
6. Vallur Tamil Nadu 500
Total 2,424
FUTURE CAPACITY ADDITIONS
PROJECT STATE MW
Coal
1. Indira Gandhi STPP- JV with IPGCL & HPGCL (500) Haryana 500
2. Sipat I (660) Chhattisgarh 660
3. Simhadri II Unit - IV( 500) Andhra Pradesh 500
3. Vallur I -JV with TNEB ( 500) Tamilnadu 500
4. Vallur Stage-I Phase-II -JV with TNEB ( 1 x 500) Tamilnadu 500
5. Bongaigaon(3 x 250) Assam 750
6. Mauda Maharashta 500
7. Rihand III(2X500) Uttar Pradesh 1000
8. Vindhyachal-IV (2X500) Madhya Pradesh 1000
9. Muzaffarpur Expansion (2x195) – JV with BSEB Bihar 390
10. Nabinagar TPP-JV with Railways (4 x 250) Bihar 1000
11. Barh II (2 X 660) Bihar 1320
12. Barh I (3 X 660) Bihar 1980
Hydro
1. Koldam HEPP ( 4 x 200) Himachal Pradesh 800
2. Tapovan Vishnugad HEPP (4 x 130) Uttarakhand 520
3. Singrauli CW Discharge(Small Hydre) Uttar Pradesh 8
Total 11,428
PERFORMANCE STATISTICS
YEARGeneration
(BU)PLF(%)
Availability Factor(%)
2011-12 222.07 85.00 89.73
2010-11 220.54 88.29 91.62
2009-10 218.84 90.81 91.76
2008-09 206.94 91.14 92.47
2007-08 200.86 92.24 92.12
2006-07 188.67 89.43 90.09
2005-06 170.88 87.52 89.91
Bulk Electricity Tariff in India
• ABT as Implemented (Beneficiary)– A true two part tariff with supplementary adjustment for Net Exchange
deviations from schedule• Fixed cost recovered from customers in proportion to capacity allocation • Energy Charges recovered against requisitioned (scheduled, ex-bus) energy at
normatively computed rates, on the respective drawal schedule– Actual Energy Generation (AG, measured ex-bus) would be different
from scheduled and the deviations positive or negative settled at a price linked to system sufficiency, in that time slice.
• Time slice of 15 minutes each in use• Average Frequency of operation in the time slice used as an index of system
sufficiency• Settlement through a UI pool account
– Promotes better market perception• Encourages Economy in Dispatch• Avoided cost of service by rogue beneficiary is prevented.
COMPONENTS OF ABT
1. CAPACITY CHARGE2. ENERGY CHARGE3. UI CHARGE
4. INCENTIVE
5. TAXES & CESS
FUELS BEING USEDTYPE SOURCE
APM ONGC GAS FROM MUMBAI HIGH, UNDER GOI ADMINISTERED PRICE.
PMT JV OF ONGC+RELIANCE+BRITISH GAS, PRESENTLY UNDER GOI ADMINISTERED PRICE.
GAIL SPOT-RLNG
LIQUIFIED NATURAL GAS PURCHASED FROM SPOT MARKET BY GAIL.
GSPCL-RLNG LIQUIFIED NATURAL GAS PURCHASED FROM SPOT MARKET BY GSPCL.
NAPHTHA LIQUID FUEL PURCHASED FROM MAJOR OIL COMPANIES & GAIL
DAILY DC DECLARATION AT ANTA
DAILY DC DECLARATION STARTS WITH THE FOLLOWING ASSUMPTIONS:-
1. GAS ALLOCATION SHALL BE SAME AS YESTERDAY.2. AMBIENT TEMPERATURE SHALL BE SAME AS YESTERDAY.3. OTHER LOSSES SHALL BE SAME AS PREVIOUS DAY.4. GCV OF GAS SHALL BE SAME AS PREVIOUS DAY.
KNOWING THE GAS ALLOCATION AND AMBIENT TEMPERATURE, THE MAX EX-BUS CAPABILITY FOR THE NEXT DAY, BOTH ON GAS FUEL AND NAPHTHA FUEL SEPARATELY IS ESTIMATED FOR 96 TIME BLOCKS AND SENT TO RCC AT NCR-HQ FOR ONWARD TRANSMISSION TO RLDC AT 09:00 HRS.
FOR ANY CHANGE IN THE ASSUMED CONDITIONS, REVISIONS IN DC ARE SENT AS PER ABT.
Rs/Unit Gen.Cost (ECR)LANDED COST(RS/SMC)&
Rs/Ltr.
APM/PMT 1.899 8.303
NAPHTHA 8.036 31.08
GAIL1-(RLNG) 3.809 16.674
GAIL2-(SPOT) 5.955 26.070
RELIANCE 2.748 12.018
APM+PMT+RIL 2.485 10.837
RLNG+NEW SPOT 4.015 17.575
Remarks:- 1.The APM/PMT price was hiked by GOI to $4.2/MMBTU in June 2010
2.Dut to above the ECR of APM/PMT became almost double.
3.RIL gas was started from 01st Nov'09.
4.Additional RIL Gas Was started from Feb'10 & equivalent amount of APM/PMT is diverted from NCR to WR as per NTPC Management decision.
BREAK EVEN FREQUENCY
BREAK EVEN FREQUENCY ON ANY FUEL IS THE FREQUENCY AT WHICH;VARIABLE CHARGE = UI CHARGE.
PRESENT BREAK EVEN FREQUENCY :NATURAL GAS :- HZNAPHTHA :- HZ
04/08/23 79