Power Sector Report: Energy Generated and Sent Out and Consumed and Load Allocation (Q3 2017) Report Date: December 2017 Data Source: National Bureau of Statistics / Nigerian Electricity Regulatory Commission NATIONAL BUREAU OF STATISTICS

Upload: others

Post on 26-Jul-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Sector Report:Energy Generated and Sent Out and Consumed and Load Allocation

(Q3 2017)

Report Date: December 2017

Data Source: National Bureau of Statistics / Nigerian Electricity Regulatory Commission

NATIONAL BUREAU OF STATISTICS

Page 2: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Contents

Executive Summary..................................................................................... 1Power Generation Statistics - Q3 2017AFAM V I ....................................................................................................................................................................................... 2

ALAOJI NIPP................................................................................................................................................................................ 3

DELTA ......................................................................................................................................................................................... 4

EGBIN ......................................................................................................................................................................................... 5

GEREGU....................................................................................................................................................................................... 6

IBOM POW ER............................................................................................................................................................................. 7

GEREGU N IPP............................................................................................................................................................................. 8

IHOVBOR NIPP........................................................................................................................................................................... 9

JE B B A ........................................................................................................................................................................................ 10

K A IN JI....................................................................................................................................................................................... 11

OKPAI ....................................................................................................................................................................................... 12

OLORUNSOGO......................................................................................................................................................................... 13

OLORUNSOGO-INIPP................................................................................................................................................................ 14

OMOKU..................................................................................................................................................................................... 15

OMOTOSHO.............................................................................................................................................................................. 16

OMOTOSHO. N IPP..................................................................................................................................................................... 17

SAPELE....................................................................................................................................................................................... 18

SAPELE- N IP P ............................................................................................................................................................................ 19

SHIRO RO .................................................................................................................................................................................... 20

TRANS AMADI............................................................................................................................................................................ 21

GBARAIN..................................................................................................................................................................................... 22

ODUKPANI................................................................................................................................................................................. 23

PARAS EN ERGY......................................................................................................................................................................... 24

ALL STATIONS............................................................................................................................................................................ 25Energy Generated MWh and Sent Out MWh - July 2017.......................................................................................................... 26

Energy Generated MW and Sent Out MW - July 2017 ............................................................................................................ 27

Energy Generated MWh and Sent Out MWh - August 2017 ................................................................................................... 28

Energy Generated MW and Sent Out MW - August 2017.......................................................................................................... 29

Energy Generated MWh and Sent Out MWh - September 2 0 1 7 .............................................................................................. 30

Energy Generated MW and Sent Out MW - September 2017................................................................................................... 31

Prepaid Meter by Disco and Load Allocation.............................................................................................................................. 32

Load Allocation - Energy Sent Out (Gwh).................................................................................................................................... 54

Total Monthly Actual Consumption........................................................................................................................................... 79

MethodologyAppendix......................................................................................................94

Acknowledgment and Contact..................................................................... 98

Page 3: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Executive Summary

The power generation statistics for Q3 2017 reflected that a total average of 82,266 MWh of energy was generated daily by power stations.

Daily energy generation attained a peak of 3,880 MW on the 1st September, 2017 and daily energy sent out on same date was 3,825 MW. Similarly, the highest daily energy generated per hour attained a peak of 93,118 MWh on 1st September, 2017 and daily energy sent out per hour on same date was 91,801 MWh. This represents the highest level of energy generated and sent out in the month of September 2017 and in Q3 2017.

However, the lowest daily energy generation, 2,354 MW, in Q3 2017 was attained on 14th September, 2017 and daily energy sent out on that date was 2,310 MW. The lowest daily energy generation per hour was also attained on same date. 56,486 MWh was generated and 55,444 MWh was sent out.

Power Generation Statistics - Q3 2017

Page 4: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- AFAM-VI

2Power Generation Statistics - Q3 2017

Page 5: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- ALAOJI NIPP

3Power Generation Statistics - Q3 2017

Page 6: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- DELTA

4Power Generation Statistics - Q3 2017

Page 7: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- EGBIN

5Power Generation Statistics - Q3 2017

Page 8: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- GEREGU

6Power Generation Statistics - Q3 2017

Page 9: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- IBOM POWER

7Power Generation Statistics - Q3 2017

Page 10: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- GEREGU NIPP

8Power Generation Statistics - Q3 2017

Page 11: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

HIGHESTPOWER GENERATED IN Q3 2017

è' I '

3,604 MwhDate Achieved

3 July 2017

LOWESTPOWER GENERATED IN Q3 2017

5' I '

650 MwhDate Achieved

ft A

4 August 2017

AVERAGEPOWER GENERATED IN Q3 2017

1,941 Mwh

Power Generation Statistics - Q3 2017

Page 12: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- JEBBA

10Power Generation Statistics - Q3 2017

Page 13: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- KAINJI

11Power Generation Statistics - Q3 2017

Page 14: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- OKPAI

12Power Generation Statistics - Q3 2017

Page 15: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- OLORUNSOGO

13Power Generation Statistics - Q3 2017

Page 16: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations - OLORUNSOGO NIPP

14Power Generation Statistics - Q3 2017

Page 17: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- OMOKU

15Power Generation Statistics - Q3 2017

Page 18: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- OMOTOSHO

16Power Generation Statistics - Q3 2017

Page 19: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations - OMOTOSHO NIPP

17Power Generation Statistics - Q3 2017

Page 20: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- SAPELE

18Power Generation Statistics - Q3 2017

Page 21: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- SAPELE NIPP

19Power Generation Statistics - Q3 2017

Page 22: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

HIGHESTPOWER GENERATED IN Q3 2017

Ò' I '

12,265 MwhDate Achieved

29 July 2017

LOWESTPOWER GENERATED IN Q3 2017

5' I '

4,747 MwhDate Achieved

ft A

9 July 2017

AVERAGEPOWER GENERATED IN Q3 2017

9,071 Mwh

20Power Generation Statistics - Q3 2017

Page 23: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- TRANS AMADI

21Power Generation Statistics - Q3 2017

Page 24: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- GBARAIN

22Power Generation Statistics - Q3 2017

Page 25: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

HIGHESTPOWER GENERATED IN Q3 2017

è' I '

4,930 MwhDate Achieved

1 July 2017

LOWESTPOWER GENERATED IN Q3 2017

5' I '

147 MwhDate Achieved

ft A

25 August 2017

AVERAGEPOWER GENERATED IN Q3 2017

2,439 Mwh

23Power Generation Statistics - Q3 2017

Page 26: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- PARAS ENERGY

24Power Generation Statistics - Q3 2017

Page 27: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Power Generation - Q 3 2017

Power Generation by Stations »- ALL STATIONS

25Power Generation Statistics - Q3 2017

Page 28: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Generated Mwh and Sent Out Mwh - July 2017

Power Generation - Q3 2017

Highest Power Generated and Sent Out in July 2017

Lowest Power Generated and Sent Out in July 2017

Average Power Generated and Sent Out in July 2017

26Power Generation Statistics - Q3 2017

Page 29: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Generated MW and Sent Out MW - July 2017

Power Generation - Q3 2017

Highest Power Generated and Sent Out in July 2017

Lowest Power Generated and Sent Out in July 2017

Average Power Generated and Sent Out in July 2017

27Power Generation Statistics - Q3 2017

Page 30: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Generated Mwh and Sent Out Mwh - August 2017

Power Generation - Q3 2017

Highest Power Generated and Sent Out in August 2017

Lowest Power Generated and Sent Out in August 2017

Average Power Generated and Sent Out in August 2017

28Power Generation Statistics - Q3 2017

Page 31: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Generated MW and Sent Out MW - August 2017

Power Generation - Q3 2017

Highest Power Generated and Sent Out in August 2017

Lowest Power Generated and Sent Out in August 2017

Average Power Generated and Sent Out in August 2017

29Power Generation Statistics - Q3 2017

Page 32: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Generated Mwh and Sent Out Mwh - September 2017

Power Generation - Q3 2017

Highest Power Generated and Sent Out in September 2017

Lowest Power Generated and Sent Out in September 2017

Average Power Generated and Sent Out in September 2017

30Power Generation Statistics - Q3 2017

Page 33: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Generated MW and Sent Out MW - September 2017

Power Generation - Q3 2017

Highest Power Generated and Sent Out in September 2017

Lowest Power Generated and Sent Out in September 2017

Average Power Generated and Sent Out in September 2017

31Power Generation Statistics - Q3 2017

Page 34: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Abuja Disco

Power Generation - Q3 2017

INHERITEDTOTAL

POST PRIVATIZATION (CAPMI)

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

32Power Generation Statistics - Q3 2017

Page 35: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER B Y DISCO AN D LOAD ALLO CATIO N - A BU JA DISCO

SU CCESSO R D ISCO

Abuja Disco

STATES CO V ER ED / FR A N CH ISE A R EA S

2017 MYTO ALLOCATION

*11.50%

FCT, Niger, Nassarawa, KogiA b u ja D isco

2017 ACTUAL ALLOCATION %

January February March April

13.88% 13.10% 13.52% 14.07%

May June July August

12.83% 13.30% 13.45% 13.01%

33Power Generation Statistics - Q3 2017

Page 36: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Benin Disco

Power Generation - Q3 2017

INHERITED

TOTAL

POST PRIVATIZATION (CAPMI)i

SINGLE PHASE THREE PHASE

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

34Power Generation Statistics - Q3 2017

Page 37: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER B Y DISCO AN D LOAD ALLO CATIO N - BENIN DISCO

SU CCESSO R D ISCO

Benin Disco

STATES CO V ER ED / FR A N CH ISE A R EA S

2017 MYTO ALLOCATION

%9.00%

Edo, Delta, Ekiti, OndoB en in D isco

2017 ACTUAL ALLOCATION %

January February March April

9.82% 8.84% 7.85% 8.79%

May June July August

9.20% 8.22% 9.13% 8.88%

35Power Generation Statistics - Q3 2017

Page 38: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Enugu Disco

Power Generation - Q3 2017

INHERITEDTOTAL

POST PRIVATIZATION (CAPMI)i

SINGLE PHASE THREE PHASE

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

36Power Generation Statistics - Q3 2017

Page 39: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER BY DISCO AN D LOAD ALLO CATIO N - ENUGU DISCO

SU CCESSO R D ISCO

Enugu Disco

STATES CO V ER ED / FR A N CH ISE A R EA S

2017 MYTO ALLOCATION

%9.00%

Imo, Anambra, Ebonyi, Abia, EnuguEnugu D isco

2017 ACTUAL ALLOCATION %

January February March April

10.20% 10.69% 10.99% 8.79%

May June July August

9.30% 8.53% 9.34% 9.04%

37Power Generation Statistics - Q3 2017

Page 40: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Eko Disco

Power Generation - Q3 2017

INHERITED

TOTAL

POST PRIVATIZATION (CAPMI)

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

38Power Generation Statistics - Q3 2017

Page 41: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER BY DISCO AN D LOAD ALLO CATIO N - ENUGU DISCO

SU CCESSO R D ISCO

Eko Diso

2017 MYTO ALLOCATION

STATES CO V ER ED / FR A N CH ISE A R EA S

11.00%

Lagos State (Victoria Island, Lekki, Lagos Island, Apapa, Epe, Ikoyi, etc)

Eko D isco

2017 ACTUAL ALLOCATION %

January February March April

9.58% 11.81% 11.74% 12.01%

May June July August

12.53% 13.44% 11.11% 11.78%

39Power Generation Statistics - Q3 2017

Page 42: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Kaduna Disco

Power Generation - Q3 2017

INHERITED

TOTAL

POST PRIVATIZATION (CAPMI)i

SINGLE PHASE THREE PHASE

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

40Power Generation Statistics - Q3 2017

Page 43: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER BY DISCO AN D LOAD ALLO CATIO N - KAD U N A DISCO

SU CCESSO R D ISCO

Kaduna Disco

STATES CO V ER ED / FR A N CH ISE A R EA S

2017 MYTO ALLOCATION

*8.00%

Kaduna, Sokoto, Kebbi and ZamfaraK ad u n a D isco

2017 ACTUAL ALLOCATION %

January February March April

8.34% 8.44% 9.42% 9.06%

May June July August

8.70% 7.87% 6.73% 7.10%

41Power Generation Statistics - Q3 2017

Page 44: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Jos Disco

Power Generation - Q3 2017

INHERITEDTOTAL

POST PRIVATIZATION (CAPMI)

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

42Power Generation Statistics - Q3 2017

Page 45: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER BY DISCO AN D LOAD ALLO CATIO N - JO S DISCO

SU CCESSO R D ISCO

Jos Disco

STATES CO V ER ED / FR A N CH ISE A R EA S

2017 MYTO ALLOCATION

15.50%

Plateau, Bauchi, Benue, GombeJo s D isco

2017 ACTUAL ALLOCATION %

January February March April

4.92% 5.04% 5.38% 5.28%

May June July August

5.23% 5.83% 6.18% 5.30%

43Power Generation Statistics - Q3 2017

Page 46: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Ikeja Disco

Power Generation - Q3 2017

INHERITEDTOTAL

POST PRIVATIZATION (CAPMI)

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

44Power Generation Statistics - Q3 2017

Page 47: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER BY DISCO AN D LOAD ALLO CATIO N - IK EJA DISCO

SU CCESSO R D ISCO

Ikeja Disco

STATES CO V ER ED / FR A N CH ISE A R EA S

2017 MYTO ALLOCATION

Lagos State (Ikeja, Surulere, Ikorodu, etc)Ike ja D isco

2017 ACTUAL ALLOCATION %

January February March April

12.19% 10.93% 10.77% 11.21%

May June July August

11.23% 11.02% 11.28% 11.80%

45Power Generation Statistics - Q3 2017

Page 48: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Ibadan Disco

Power Generation - Q3 2017

INHERITED

TOTAL

POST PRIVATIZATION (CAPMI)i

SINGLE PHASE THREE PHASE

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

46Power Generation Statistics - Q3 2017

Page 49: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER B Y DISCO AN D LOAD ALLO CATIO N - IBADAN DISCO

SU CCESSO R D ISCO

Ibadan Disco

STATES CO V ER ED / FR A N CH ISE A R EA S

2017 MYTO ALLOCATION

13.00%

Oyo, Ogun, Osun, KwaraIbadan D isco

2017 ACTUAL ALLOCATION %

January February March April

13.86% 13.37% 11.91% 13.38%

May June July August

13.16% 13.74% 13.54% 13.28%

47Power Generation Statistics - Q3 2017

Page 50: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Yola Disco

Power Generation - Q3 2017

INHERITED

TOTAL

POST PRIVATIZATION (CAPMI)

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

48Power Generation Statistics - Q3 2017

Page 51: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER BY DISCO AN D LOAD ALLO CATIO N - Y O LA DISCO

SU CCESSO R D ISCO

Yola Disco

2017 MYTO ALLOCATION

1

STATES CO V ER ED / FR A N CH ISE A R EA S

3.50%

Adamawa, Borno, Taraba and YobeY o la D isco

2017 ACTUAL ALLOCATION %

January February March April

2.54% 2.89% 3.37% 2.68%

May June July August

2.83% 3.33% 3.53% 3.57%

49Power Generation Statistics - Q3 2017

Page 52: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Port Harcourt Disco

Power Generation - Q3 2017

INHERITEDTOTAL

POST PRIVATIZATION (CAPMI)

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

50Power Generation Statistics - Q3 2017

Page 53: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER BY DISCO AN D LOAD ALLO CATIO N - PORT HARCO URT DISCO

SU CCESSO R D ISCO

Port Harcourt Disco

STATES CO V ER ED / FR A N CH ISE A R EA S

2017 MYTO ALLOCATION

16.50%

Rivers, Bayelsa, Cross Rivers, Akwa IbomP o rt H a rco u rt D isco

2017 ACTUAL ALLOCATION %

January February March April

8.94% 8.21% 7.35% 7.77%

May June July August

7.95% 7.66% 8.54% 8.66%

51Power Generation Statistics - Q3 2017

Page 54: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Prepaid Meter by Disco and Load Allocation Kano Disco

Power Generation - Q3 2017

INHERITED

TOTAL

POST PRIVATIZATION (CAPMI)

TOTAL

POST PRIVATIZATION (NON-CAPMI)

TOTAL

NB: Credited Advance Payment for Metering Implementation Scheme (CAPMI)

52Power Generation Statistics - Q3 2017

Page 55: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

PREPAID M ETER BY DISCO AN D LOAD ALLO CATIO N - KANO DISCO

SU CCESSO R D ISCO

Kano Disco

STATES CO V ER ED / FR A N CH ISE A R EA S

2017 MYTO ALLOCATION

%8.00%

Kano, Jigawa and KatsinaK a n o D isco

2017 ACTUAL ALLOCATION %

January February March April

5.73% 6.68% 7.70% 6.97%

May June July August

7.04% 7.06% 7.17% 7.59%

53Power Generation Statistics - Q3 2017

Page 56: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) AFAM (I-V)

Power Generation - Q3 2017

A A A

AFAM (I-V)

January February March April

May June July August

September

0

54Power Generation Statistics - Q3 2017

Page 57: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) GEREGU

Power Generation - Q3 2017

GEREGU

January February March April

92 102 99 132

May June July August.• .a .,

148 182 157 114

September_s_i_a

121

55Power Generation Statistics - Q3 2017

Page 58: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) EGBIN

Power Generation - Q3 2017

EGBIN

January February March April

200 201 249 218

May June July August.• .a .,

258 317 327 374

September_s_i_a

233

56Power Generation Statistics - Q3 2017

Page 59: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) SAPELE

Power Generation - Q3 2017

SAPELE

January February March April

36 31 5 20

May June July August.• .a .,

26 38 39

September_s_i_a

29

57Power Generation Statistics - Q3 2017

Page 60: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) UGHELLI

Power Generation - Q3 2017

UGHELLI

January February March April

157 209 215 191

May June July August.• .a .,

217 266 283 285

September_s_i_a

288

58Power Generation Statistics - Q3 2017

Page 61: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) AES BARGE

Power Generation - Q3 2017

A A A

AES BARGE

January February March April

May June July August

SeptembermSSm.

59Power Generation Statistics - Q3 2017

Page 62: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) OKPAI

Power Generation - Q3 2017

OKPAI

January February March April

177 170 261 225

May June July August.• .a .,

231 186 174 162

September_s_i_a

157

60Power Generation Statistics - Q3 2017

Page 63: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) AFAM VI

Power Generation - Q3 2017

AFAM VI

January February March April

300 294 254 167

May June July August.• .a .,

282 83 77 69

September_s_i_a

106

61Power Generation Statistics - Q3 2017

Page 64: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) OMOKU

Power Generation - Q3 2017

OMOKU

January February March April

47 28 39 44

May June July August.• .a .,

58 60 56 56

September_s_i_a

39

62Power Generation Statistics - Q3 2017

Page 65: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) TRANS- AMADI

Power Generation - Q3 2017

A A A

TRANS- AMADI

January February March April

May June July August

12 14

September

2 7

63Power Generation Statistics - Q3 2017

Page 66: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) RI VERS IPP

Power Generation - Q3 2017

A A A

RI VERS IPP

January February March April

May June July August

Septemberm S S m .

64Power Generation Statistics - Q3 2017

Page 67: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) I BOM POWER

Power Generation - Q3 2017

A A A

I BOM POWER

January February March April

32 61 53

May June July August

59 51 50 7

September

4 0

65Power Generation Statistics - Q3 2017

Page 68: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) OLORUNSOGO

Power Generation - Q3 2017

A A A

OLORUNSOGO

January February March April

56 72 94 108

May June July August

116 127 86 79

September

8 9

66Power Generation Statistics - Q3 2017

Page 69: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) OMOTOSHO

Power Generation - Q3 2017

A A A

OMOTOSHO

January February March April

67 94 129 106

May June July August

92 114 80 62

September

7 4

67Power Generation Statistics - Q3 2017

Page 70: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) OLORUNSOGO NI PP

Power Generation - Q3 2017

A A A

OLORUNSOGO NIPP

January February March April

9 6 9 6

May June July August

25 107 74 66

September

8 6

68Power Generation Statistics - Q3 2017

Page 71: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) OMOTOSHO NIPP

Power Generation - Q3 2017

A A A

OMOTOSHO NI PP

January February March April

53 89 110 98

May June July August

70 86 71 63

September

72

69Power Generation Statistics - Q3 2017

Page 72: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) ALAOJI NI PP

Power Generation - Q3 2017

A A A

ALAOJ I NI PP

January February March April

31 57 78 32

May June July August

74 30 38 30

September

3 7

70Power Generation Statistics - Q3 2017

Page 73: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) SAPELE NI PP

Power Generation - Q3 2017

A A A

SAPELE NI PP

January February March April

44 69 128 103

May June July August

77 49 58 47

September

5 7

71Power Generation Statistics - Q3 2017

Page 74: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) I HOVBOR NI PP

Power Generation - Q3 2017

A A A

I HOVBOR NI PP

January February March April

48 102 75 89

May June July August

96 85 66 53

September

5 6

72Power Generation Statistics - Q3 2017

Page 75: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) GEREGU NI PP

Power Generation - Q3 2017

A A A

GEREGU NI PP

January February March April

42 65 65 73

May June July August

69 91 79 71

September

65

73Power Generation Statistics - Q3 2017

Page 76: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Al location - Energy Sent Out (Gwh) CAL ABAR NI PP

Power Generation - Q3 2017

A A A

CALABAR NIPP

January February March April

75 89 125 179

May June July August

184 124 87 58

September

7 8

74Power Generation Statistics - Q3 2017

Page 77: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) SHIRORO

Power Generation - Q3 2017

SHIRORO

January February March April

209 177 189 129

May June July August. • . a . ,

51 122 250 307

September_s_i_a

275

75Power Generation Statistics - Q3 2017

Page 78: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) KAINJI

Power Generation - Q3 2017

KAINJI

January February March April

246 232 272 252

May June July August. • . a . ,

233 150 134 185

September_s_i_a

226

76Power Generation Statistics - Q3 2017

Page 79: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) JEBBA

Power Generation - Q3 2017

JEBBA

January February March April

244 223 243 225

May June July August. • . a . ,

219 165 214 272

September_s_i_a

246

77Power Generation Statistics - Q3 2017

Page 80: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Load Allocation - Energy Sent Out (Gwh) NESCO

Power Generation - Q3 2017

NESCO

January February March April

7 7 7 6

May June July August. • . a . ,

7 6 7 7

September

7

78Power Generation Statistics - Q3 2017

Page 81: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

June 2016

POPULATION

♦WH#♦♦♦♦♦♦

4,921,407

ZONE

RESIDENTIAL

POPULATION

MMM♦MM#

656,980

ZONE

<0 >COMMERCIAL

POPULATION

♦♦♦♦♦♦♦MM#

23,381

ZONE

< © >INDUSTRIAL

POPULATION

MMM♦MM#

769

ZONE

STREET LIGHTING

POPULATION

MMM♦MM#

29,377

ZONE

SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

4,115,286

TOTAL BILLED(KWH)

61,326,206

5,631,914 TOTAL 1,094,335,641NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

79Power Generation Statistics - Q3 2017

Page 82: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption July 2016

Power Generation - Q3 2017

POPULATIONWWW♦MM#4,897,264

ZONE

RESIDENTIAL

POPULATIONWWWWWW680,676

ZONE

<0>COMMERCIAL

POPULATIONWWWWWW23,413

ZONE

<@>INDUSTRIAL

=#

•=

§•

g

co

c

>*

-=9

" * ZONE

STREET LIGHTING

POPULATION♦WW#WWW30,604

ZONE

<©>SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

3,229,414

TOTAL BILLED(KWH)

53,475,230

5,632,774 TOTAL 980,792,020NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

80Power Generation Statistics - Q3 2017

Page 83: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption August 2016

Power Generation - Q3 2017

POPULATIONWWW♦MM#4,948,057

ZONE

RESIDENTIAL

POPULATIONWWWWWW664,908

ZONE

<0>COMMERCIAL

POPULATIONWWWWWW20,262

ZONE

<@>INDUSTRIAL

POPULATIONWWWWWW750

ZONE

STREET LIGHTING

POPULATION♦WW#WWW29,828

ZONE

<©>SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

247,429,734

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

3,369,898

TOTAL BILLED(KWH)

60,408,422

5,663,805 TOTAL 1,246,517,945NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

81Power Generation Statistics - Q3 2017

Page 84: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

September 2016

POPULATIONWWW♦MM#4,987,471

ZONE

RESIDENTIAL

POPULATIONWWWWWW679,469

ZONE

COMMERCIAL

POPULATIONWWWWWW19,698

ZONE

<0>INDUSTRIAL

POPULATIONWWWWWW707

ZONE

STREET LIGHTING

POPULATION♦WW#WWW28,983

ZONE

<©>SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

3,370,907

TOTAL BILLED(KWH)

60,774,501

5,716,328 TOTAL 1,376,757,582NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

82Power Generation Statistics - Q3 2017

Page 85: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

October 2016

POPULATION♦WH#♦♦♦♦♦♦4,923,897

ZONE

RESIDENTIAL

POPULATIONMMM♦MM#672,037

ZONE

<0>COMMERCIAL

POPULATION♦♦♦♦♦♦♦MM#20,313

ZONE

<@>INDUSTRIAL

POPULATIONMMM♦MM#753

ZONE

STREET LIGHTING

POPULATIONMMM♦MM#29,411

ZONE

<©>SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

4,621,326

TOTAL BILLED(KWH)

68,531,796

5,646,411 TOTAL 1,413,760,600NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

83Power Generation Statistics - Q3 2017

Page 86: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

November 2016

POPULATION

W W W♦ M M #

5,765,665

ZONE

RESIDENTIAL

POPULATION

W W WW W W

810,013

ZONE

< 0 >COMMERCIAL

POPULATION

W W WW W W

27,952

ZONE

< © >INDUSTRIAL

=#

•=

§•

g

co

c io

X

=-

r =#

•=§•

?=§

•=#•

o z ZONE

STREET LIGHTING

POPULATION

♦ W W #W W W

32,838

ZONE

< © >SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

6,723,969

TOTAL BILLED(KWH)

77,160,626

6,637,293 TOTAL 1,484,150,374NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

84Power Generation Statistics - Q3 2017

Page 87: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

December 2016

POPULATION

W W W♦MM#

5,515,598

ZONE

RESIDENTIAL

POPULATION

W W WW W W

776,606

ZONE

<0 >COMMERCIAL

POPULATION

W W WW W W

26,037

ZONE

< © >INDUSTRIAL

POPULATION

W W WW W W

839

ZONE

STREET LIGHTING

POPULATION

♦WW#W W W

33,233

ZONE

< © >SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

144,415,800

TOTAL BILLED(KWH)

5,099,582

TOTAL BILLED(KWH)

81,995,627

6,352,313 TOTAL 1,541,605,746NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

85Power Generation Statistics - Q3 2017

Page 88: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

January 2017

POPULATIONWWW♦MM#5,546,419

ZONE

RESIDENTIAL

POPULATIONWWWWWW776,263

ZONE

<0>COMMERCIAL

POPULATIONWWWWWW26,355

ZONE

<©>INDUSTRIAL

POPULATIONWWWWWW793

ZONE

STREET LIGHTING

POPULATION♦WW#WWW33,839

ZONE

SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

4,459,009

TOTAL BILLED(KWH)

70,686,977

6,383,669 TOTAL 1,463,186,553NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

86Power Generation Statistics - Q3 2017

Page 89: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

February 2017

POPULATION

W W W♦MM#

5,652,401

ZONE

RESIDENTIAL

POPULATION

W W WW W W

782,400

ZONE

<0 >COMMERCIAL

POPULATION

W W WW W W

27,044

ZONE

<0 >INDUSTRIAL

=#

•=

§•

g

co

c

>e-=

9> * ZONE

STREET LIGHTING

POPULATION

♦WW#W W W

34,800

ZONE

< © >SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

4,398,540

TOTAL BILLED(KWH)

73,288,967

6,497,464 TOTAL 1,398,611,181NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

87Power Generation Statistics - Q3 2017

Page 90: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

March 2017

POPULATION

♦WH#♦♦♦♦♦♦

5,678,104

ZONE

RESIDENTIAL

POPULATION

MMM♦MM#

786,424

ZONE

<0 >COMMERCIAL

POPULATION

♦♦♦♦♦♦♦MM#

27,352

ZONE

< © >INDUSTRIAL

POPULATION

MMM♦MM#

830

ZONE

STREET LIGHTING

POPULATION

MMM♦MM#

35,649

ZONE

< © >SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

4,601,030

TOTAL BILLED(KWH)

82,112,594

6,528,359 TOTAL 1,574,752,264NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

88Power Generation Statistics - Q3 2017

Page 91: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

April 2017

POPULATION

W W W♦ M M #

5,692,269

ZONE

RESIDENTIAL

POPULATION

W W WW W W

777,578

ZONE

< 0 fCOMMERCIAL

POPULATION

W W WW W W

31,597

ZONE

< © >INDUSTRIAL

=#

•=

§•

g

co

c ZONE

STREET LIGHTING

POPULATION

♦ W W #W W W

36,274

ZONE

< © >SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

5,474,228

TOTAL BILLED(KWH)

90,038,111

6,538,535 TOTAL 1,707,886,511NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

89Power Generation Statistics - Q3 2017

Page 92: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption May 2017

Power Generation - Q3 2017

POPULATIONWWW♦MM#5,743,814

ZONE

RESIDENTIAL

POPULATIONWWWWWW772,441

ZONE

<0>COMMERCIAL

POPULATIONWWWWWW29,685

ZONE

<@>INDUSTRIAL

POPULATIONWWWWWW846

ZONE

STREET LIGHTING

POPULATION♦WW#WWW37,269

ZONE

<©>SPECIAL

TOTAL BILLED(KWH)

995,897,949

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

5,996,363

TOTAL BILLED(KWH)

83,302,466

6,584,055 TOTAL 1,570,935,119NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

90Power Generation Statistics - Q3 2017

Page 93: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption Average

Power Generation - Q3 2017

POPULATIONWWW♦MM#5,356,031

ZONE

RESIDENTIAL

POPULATIONWWWWWW736,316

ZONE

<0>COMMERCIAL

POPULATIONWWWWWW25,257

ZONE

<@>INDUSTRIAL

POPULATIONWWWWWW797

ZONE

STREET LIGHTING

POPULATION♦WW#WWW32,675

ZONE

<©>SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

4,621,629

TOTAL BILLED(KWH)

71,925,127

6,151,077 TOTAL 1,404,440,961NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

91Power Generation Statistics - Q3 2017

Page 94: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Total Monthly Actual Consumption

Power Generation - Q3 2017

7 month Average

POPULATION

♦MM#5,656,324

ZONE

RESIDENTIAL

POPULATION

783,104

ZONE

<0 >COMMERCIAL

POPULATION

28,003

ZONE

<@>INDUSTRIAL

=#•=

§• g

co

c ro

"

T

C

=§•=

#• o z ZONE

STREET LIGHTING

POPULATION

34,843

ZONE

<© >SPECIAL

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

TOTAL BILLED(KWH)

5,250,389

TOTAL BILLED(KWH)

79,797,910

6,503,098 TOTAL 1,534,446,821NB: Commercial consumption refers to consumption from business users eg business centers, office buildings, plazas and the likes. Industrial consumption is for

places where there is heavy machinery usage or where some manufacturing process is taking place like factories, or processing plants. Special is for places that

require dedication connectivity because of the nature of their work, places like Hospitals and airports.

92Power Generation Statistics - Q3 2017

Page 95: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Methodology

Data is supplied administratively by Nigerian Electricity Regulatory Commission (NERC) and verified and validated by the National Bureau of Statistics, Nigeria (NBS).

93Power Generation Statistics - Q3 2017

Page 96: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

D a ily E n e rg y E n e rg y G e n e ra te d S e n t O u t

D ate G e n e ra te d M W h S e n t O ut M W M W30 -S e p 30,267 79,236 3r344 3,301

29 -S e p 82,633 31,538 3,445 3,397

23 -S e p 71,029 70,274 2,960 2,92827 -S e p 35,423 34,370 3,559 3,515

26 -S e p 79,722 7 S r311 3,322 3,263

25 -S e p 87,901 36,517 3,563 3,605

24 -S e p 80,513 79,123 3,355 3,29723 -S e p 33,434 37,251 3,635 3,635

22 -S e p 87,793 36,639 3,653 3,610

21 -S e p 83,204 32,011 3,467 3,41720 -S e p 34,337 33,207 3,516 3,467

19 -S e p '91,439 90,246 3,812 3,760

13 -S e p 76,806 73,332 3,200 3,07617 -S e p 86,221 85,026 3,593 3,543

16 -S e p 83,060 32,103 3,461 3,421

15 -S e p 86,023 85,124 3,584 3,54714 -S e p 56,436 55,444 2,354 2,310

13 -S e p 34,903 83,520 3,533 3,430

12 -S e p 89,849 33,509 3,744 3,63311 -S e p 73,063 77,080 3,253 3,212

10-£ep 34,240 33,329 3,510 3,472

G 9-Sep 86,535 35,722 3,606 3,572

O S-Sep 81,051 79,853 3,378 3,3270 7 -S e p 73,985 77,663 3,291 3,236

0 6 -S e p 90,359 39,213 3,765 3,717

05-5 ep 31,447 90,220 3,310 3,75904 -S e p 37,356 36,159 3,640 3,590

0 3 -S e p 80,365 79,242 3,349 3,302

0 2 -S e p 90,470 89,182 3,770 3,716O l-S e p 93,118 91,301 3,880 3,825

31-A u g 35,754 34,334 3,573 3,514

30-A u g 83,113 31,859 3,463 3,411

29-A u g 89,130 37,304 3,714 3,65323-A u g 34,242 32,963 3,510 3,457

27-A u g 73,475 77,231 3,270 3,213

26- A u g 77,277 76,006 3,220 3,16725-A u g 74,723 73,463 3,113 3,061

24-A u g 86,539 35,217 3,606 3,551

23-A u g 85,307 34,051 3,554 3,50222-A u g 80,991 73,974 3,375 3,291

21-A u g 34,023 32,604 3,501 3,442

20-A u g 83,610 37,020 3,692 3,62619-A u g 86,853 35,480 3,619 3,562

13-A u g 84,433 32,903 3,520 3,454

17-A u g 74,910 73,634 3,121 3,06316-A u g 34,575 83,236 3,524 3,463

15-A u g 86,765 85,395 3,615 3,558

14-A u g 73,345 77,503 3,285 3,230

13-A u g 73,955 77,571 3,290 3,23212-A u g 30,629 79,270 3,360 3,303

11-A u g 34,476 83,060 3,520 3,461

10-A u g 83,610 32,273 3,484 3,4280 9 -A u g 83,646 82,177 3,435 3,424

OS-Aug 83,071 31,621 3,461 3,40107-A u g 73,900 77,514 3,237 3,23006-A u g 79,855 73,573 3,327 3,27405-A u g 73,206 71,929 3,050 2,99704-A u g 72,707 71,112 3,029 2,96303-A u g 80,465 79,303 3,353 3,30402-A u g 82,605 31,245 3,442 3,33501-A u g 70,497 69,635 2,937 2,901

31-Jul 70,861 69,831 2,953 2,91030-Jill 73,500 77,091 3,271 3,21229-Jul 30,847 79,643 3,369 3,31928-J ill 86,405 85,144 3,600 3,54827-Jlll 35,931 34,545 3,530 3,52726-Jul 30,170 78,879 3,340 3,23725-Jul 80,233 79,071 3,343 3,29524-J nl 73,520 77,305 3,272 3,22123-Jul 71,139 69,782 2,964 2,90822-Jul 74,590 73,196 3,103 3,05021-Jul 34,939 83,442 3,541 3,47720-Jill 90,645 89,201 3,777 3,71719-Jlll 80,443 79,106 3,352 3,29618-Jul 83,774 82,403 3,491 3,43417-Jul 79,694 78,190 3,321 3,25316-Jlll 77,470 75,971 3,228 3,16515-Jul 83,583 82,075 3,483 3,42014-Ju l 35,033 83,472 3,545 3,47313-Jlll 86,603 85,252 3,603 3,55212-Jul 90,643 89,343 3,777 3,72311-Jul 39,892 83,614 3,745 3,69210-Jill 34,754 83,543 3,531 3,43109-Jul 75,869 74,740 3,161 3,114OS-Jul 81,634 80,427 3,401 3,35107-Jlll 34,653 83,510 3,523 3,43006-Jlll 78,274 77.215 3,261 3,21705-Jlll 30,623 79,557 3,359 3,31504-Jlll 83,022 31,633 3,459 3,40203-Jul 84,665 83,180 3,523 3,46602-Jlll 32,465 31,150 3,436 3,33101-Jul 77,029 76,039 3,210 3,168

94Power Generation Statistics - Q3 2017

Page 97: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

TOTAL ENERGY* G EN E RAT EDDMOTCSHC 0K13TC5HC- NIPP 5APELE SAPELE NIPP SHIRORO TRANS AMACI A ECO SEAR.ÛJN COUKFANI PARAS PARAS ENERGY r iv e r ì ipp PER DAY ir.HVhl

/.Ai? 1453 246 6,764 » ,9 8 91,353 2415 263 231 7,668 205 2,14= 3~ 40 1,640 82,4652, 434 2423 934 2,427 6,471 432 76.2E92,352 247» 1,361 2,362 7,691 470 2,153 2,226 1,594 81,0222,123 2651 1,366 2,424 8,245 421 71,8422,416 2676 1,395 1,995 5,603 407 2,535 3,133 1,582 75,2742,42» 1343 1,370 2,239 7,184 355 75,6111S47 1614 1,361 2,208 6,561 425 2 4 5 3 3.137 1,479 81,6141,526 1611 1,388 2,229 4,747 425 » ,6 8 82,153 1957 1,486 2,293 6,517 335 2.430 3,108 1,530 84,7142.513 1527 842 2,192 7,487 14= 82,1512,420 2,625 459 2,254 8,370 3&ï 441 44 4 1 1,563 90,6432,523 1347 1,308 2,120 6,761 321 81,4232.623 1315 1,291 2,078 8,451 46= 2.409 1,618 81,0582,207 1257 1,362 2,072 9,785 463 80,1292,256 2253 1,309 2,059 8,356 333 2,470 427 77,4702.673 1352 1,416 363 10,142 361 7 1 ,9 »2,02» 1013 1,413 2,131 9,940 493 2.727 1,730 81,7742,015 135-5 1,488 2,221 8,928 232 76,2132,222 1017 2,128 1,979 8,998 492 2.C94 2,518 1,747 9D.6452,220 1253 1,306 1,994 8,663 =02 &:>,624

2.520 1 2 :3 1,334 194 6,008 493 2.727 1,715 74,5*02.120 2107 1,325 745 5,782 =01 67,7492.570 2453 1,310 1,397 7,474 = » : • 1,727 1,736 75,5202.613 2757 1,280 2,103 9,005 =02 77.IKO2,022 2213 1,243 2,134 7,394 293 1,595 1,219 80,1702,213 227» 1,274 2,651 8,467 81,8713.157 2413 1,275 2,142 9,360 235 3,226 1,686 S E - ,«2.413 1357 1,282 2,133 12,265 495 75,7391.317 1310 1,282 2,185 11,107 433 1,349 1,623 75, SCO1.314 1953 1,281 2,189 10,758 435 65,1-581.253 197» 1,305 2,130 10,329 472 1 4 7 2 1,666 70,4*71.312 1074 1,306 2,393 6,611 465 75,6182.222 1074 1,298 2,017 9,113 333 2,ceo 1,217 808 &D.4551.311 1055 1,298 159 8,840 3?s 69,1781.742 1441 1,266 9,633 25= ■541 1,210 849 71 ,2 :6

1,313 1143 1,290 10,033 282 7 7 ,074

1,320 1023 1,310 499 9,770 1,215 1,073 7 5 ,9 :0

1,3 :3 2123 1,317 2,133 11,733 IO : 7 5 ,1 :0

1,321 1345 1,990 2,022 9,001 415 2..C91 2,290 1,310 8 3 ,040

1,0 :3 1443 1,132 024 11,303 4 0 : 7 5 ,751

1,324 1723 1,300 2,213 10,033 4 3 : 1,475 1,531 1,524 3 4 ,470

1,324 1320 1,424 2,033 9,311 597 7 5 ,443

2 4 4 5 1 0 :7 1,472 1,933 9,339 401 1,272 2,232 1,497 7 5 ,910

2272 1 0 :3 1,449 333 9,039 432 7 4 ,525

1,3 :0 132-7 1,405 2,101 11,323 4 7 : a i 2,120 1,500 8 5 ,735

1 3 :0 1043 1,174 1,973 10,279 101 93,9932,034 217 2 1,301 392 9,792 4 7 : 2,103 1,440 7 4 ,910

2123 1223 1,017 2,130 9,931 355 8 3 ,043

2125 1212 353 2,071 10,713 711 2,190 1,313 8 5 ,333

2 0 :1 212 7 1,437 2,037 10,001 73: 3 4 ,8 :0

2020 2343 1,300 2,034 10,330 ^ 2 2,430 1,319 3 4 ,013

2113 2343 1,233 1,320 10,302 4 4 : 7 7 ,151

2W 3 1032 1,293 2,031 11,194 533 2,237 1,313 3 5 ,937

2371 1412 1,334 2,100 9,324 532 32,933

2151 2043 1,305 1,003 7,885 591 - _ _ _ _ _ _ _ _ _ _ _ _ _ - I 147 1,644 74,7232014 2023 1,316 9,094 ■689 74,6532122 2076 1,197 9,712 711 1,570 1,519 75,4752126 2,924 1,143 956 9,965 705 K',3202411 2211 1,191 2,185 11,166 510 2,115 1,678 89,1102373 1 4 :0 1,119 2,131 9,138 33 75.3-ZO2246 1613 1,092 2,112 10,030 125 2.265 1,666 81,7542321 4,112 1,114 2,450 11,956 523 85,5711314 4,350 1,081 4,061 10,778 SX» 331 4,482 1,654 90,4701524 l i c e 1,096 2,687 8,516 705 71,3431524 1023 1,114 2,935 9,886 475 1,195 2,772 1,665 87,3562451 1524 1,116 3,984 10,990 755 81,9 :02247 1322 1,136 2,468 11,466 35 2.C62 2.546 1,664 90.3E92410 2371 612 153 9,409 75,6562620 2455 1,320 1,890 9,695 a i 2,214 1,615 81,9512,240 1945 1,251 3,921 11,216 i , m 82,8142,055 1346 1,274 2,267 10,524 1,252 2,224 1,709 84-, 2402421 1517 510 2,732 9,352 1,242 71,7142720 2,751 324 3,359 10,952 1,225 2,747 1,620 85,849

2 4 1 6 1 0 :6 536 3,706 10,451 1,114 93,0741521 1240 2,742 0,201 1,105 1,203 771 554501443 242 4 310 3,043 11,304 1,205 83, 329

1 5 :0 1324 1,070 3,234 9,304 1,375 3,031 1,004 33,0501313 1324 1,134 3,093 3,072 1,447 33,0331357 1213 1,293 1,390 3,919 1,245 2,190 1,240 75,3301 4 :1 1177 1,331 2,139 11,032 1,431 8 7 ,551

1420 1 3 :0 1,154 2,714 9,203 1-422 32 2,204 1,493 3 4 ,357

1325 1243 197 9,104 731 7-3,3301323 2412 1,301 3,074 :o 5 23 2,230 1,031 37,7931312 1324 1,321 7,027 1,432 33,7331 4 :3 1324 1,103 0,230 1,435 202 2,100 1,330 33,513142-7 1373 1,144 0,921 1,205 32,5201 2 :2 2173 1,107 0,333 275 2,733 1,030 7-3,7221 4 :0 1421 1,024 0,390 7-3,3531370 1 3 :3 1,111 3,173 134 2,507 1,427 7 i , o a

1217 1033 1,131 9,233 20: 7-3,3534,12-1 1 Ï2 2 1,319 7,300 205 2,200 1,013 33,2574,323 1420 1,424 371 10,337 201 34,2104,723 237 1 1,432 2,391 10,273 202 2,237 1,013 32,7594,072 2424 1,399 2,405 8,566 =62 33,7542,755 2179 1,431 2,317 8,410 274 2,516 1,442 34,0692,716 2210 1,445 3,234 7,811 =95 874492.414 2323 1,443 4,231 8,239 1.405 7 ,0 1 3 485 93,5132,347 1912 1,460 2,874 3,885 1,275 73,3304,010 2312 1,447 2,198 5,342 1,245 5,155 1,552 84,6774,212 2559 1,450 2,362 7,926 1.262 81,6334,476 4,379 969 2,054 7,928 ICO: 2.162 3,599 1,497 916432.424 4,354 634 2,130 7,339 1,'5S2 816184,212 2559 1,450 2,362 7,926 1.262 £60 5,123 1,519 93,9:i42,357 2,656 1,494 2,168 6,540 1,234 81,2722,2-26 4,255 1,446 2,257 6,824 1,255 2.487 3,294 1,367 87 ,5 :92,377 4,35-9 1,460 2,160 7,647 1.424 84,5682,224 4,151 1,387 3,031 7,269 1442 1,702 4,511 1,518 94,5=81314 2,913 722 3,225 5,538 1,233 754162,526 2,357 3,146 5,451 1.417 1,510 6,233 589 71,247

135,639 162331 131,071 206,028 968,306 76.121 16.521 151,664 80,602

Page 98: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Abuja Benin Eko Enugu I badan Ikeja Jos Kaduna Kano PH YolaInherited Single phase prepaid 231,803 171,296 71,127 100,617 113,590 97,473 47,472 88,237 38,951 27,099 28,018

Three phase prepaid 26,748 44,743 15,005 2 1,326 3 7 ,5 66 4,55 0 6,471 22,272 20,765 7,004Total 231,803 198,044 115,870 115,622 13 4,916 13 5 ,039 52,0 22 94,708 61,223 47,864 35,022

Post Privatization (CAPMI)

Single phase pre p a id 16,583 74,385 17,435 8 51 80,482 1 5 9,100 6,319 1 ,657

Three phase pre p a id 10,702 4,861 15,912 138 5 ,863 1 1,905 1,863 595Total 27,285 79,246 33,347 989 86,345 - 16 11,005 - 8, 182 2 ,252

Post Privatization (NON-CAPMI) Single phase prepaid 1,238 5,500 4,850 8 26,000 20,688 2,357 22,374 360 10,324

Three phase prepaid 341 78 4,090 4 7,000 2,070 10,077 1,454 137 55Total 1,57 9 5,578 8,940 12 33,000 2 2 ,7 5 8 2,357 32,451 1,814 10,461 55

Credited Advance Payment for Metering Implementation Scheme (CAPMI)NOTE: THE DATA AVAILABLE IS CATEGORIZED BY DISCO AND NOT BY STATEPlease refer to the table below:

Successor Disco States Covered / Franchise AreasAbuja Disco FCT, Niger, Nassarawa, KogiBenin Disco Edo, Delta, Ekiti, OndoEnugu Disco Imo, Anambra, Ebonyi, Abia, Enugu

Eko Diso Lagos State (Victoria Island, Lekki, Lagos Island, Apapa, Epe, Ikoyi, etc)

P ort H a rco u rt D isco Rivers, Bayelsa, Cross Rivers, Akwa IbomIbadan Disco Oyo, Ogun, Osun, KwaraIkeja Disco Lagos State (Ikeja, Surulere, Ikorodu, etc)Jos Disco Plateau, Bauchi, Benue, GombeKano Disco Kano, Jigawa and KatsinaKaduna Disco Kaduna, Sokoto, Kebbi and ZamfaraYola Disco Adamawa, Borno, Taraba and Yobe

Page 99: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

2017 ACTUAL ALLOCATION %2017 M YTO ALLO CATIO NDISCO ALLO CATIO NAbuja 11.50%Benin 9.00%Enugu 9.00%Ibadan 13.00%Jos 5.50%Kaduna 8.00%Kano 8.00%Eko 11.00%Ikeja 15.00%P/H 6.50%Yola 3.50%

DISCO Jan Feb Mar Apr May Jun Jul AugA BU JA 13.88 13.10 13.52 14.07 12.83 13.30 13.45 13.01BENIN 9.82 8.84 7.85 8.79 9.20 8.22 9.13 8.88EKO 9.58 11.81 11.74 12.01 12.53 13.44 11.11 11.78ENUGU 10.20 10.69 10.99 8.79 9.30 8.53 9.34 9.04IBADAN 13.86 13.37 11.91 13.38 13.16 13.74 13.54 13.28IKEJA 12.19 10.93 10.77 11.21 11.23 11.02 11.28 11.80JOS 4.92 5.04 5.38 5.28 5.23 5.83 6.18 5.30KADU N A 8.34 8.44 9.42 9.06 8.70 7.87 6.73 7.10KANO 5.73 6.68 7.70 6.97 7.04 7.06 7.17 7.59P/HARCOURT 8.94 8.21 7.35 7.77 7.95 7.66 8.54 8.66YO LA 2.54 2.89 3.37 2.68 2.83 3.33 3.53 3.57

2017Energy Sent Out (GWh) Jan Feb Mar Apr May Jun Jul Aug SepAFAM (I-V) - - - - - - - - 0GEREGU 92 102 99 132 148 182 157 114 121EGBIN 200 201 249 218 258 317 327 374 233SAPELE 36 31 5 20 26 38 39 29UGHELLI 157 209 215 191 217 266 283 285 288AES BARGE - - - - - - - - -

OKPAI 177 170 261 225 231 186 174 162 157AFAM VI 300 294 254 167 282 83 77 69 106OMOKU 47 28 39 44 58 60 56 56 39TRANS-AMADI - - - - - - 12 14 27RIVERS IPP - - - - - - - - -

IBOM POWER - 32 61 53 59 51 50 7 40OLORUNSOGO 56 72 94 108 116 127 86 79 89OMOTOSHO 67 94 129 106 92 114 80 62 74OLORUNSOGO NIPP 9 6 9 6 25 107 74 66 86OMOTOSHO NIPP 53 89 110 98 70 86 71 63 72ALAOJI NIPP 31 57 78 32 74 30 38 30 37SAPELE NIPP 44 69 128 103 77 49 58 47 57IHOVBOR NIPP 48 102 75 89 96 85 66 53 56GEREGU NIPP 42 65 65 73 69 91 79 71 65CALABAR NIPP 75 89 125 179 184 124 87 58 78SHIRORO 209 177 189 129 51 122 250 307 275KAINJI 246 232 272 252 233 150 134 185 226JEBBA 244 223 243 225 219 165 214 272 246NESCO 7 7 7 6 7 6 7 7 7

Page 100: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Jun-16 Ju l-16 A ug-16 Sep-16 O ct-16 Nov-16

Zone Population TotalB illed(KW H )

Population TotalB illed(KW H )

Population Total B illed(KW H ) Population Total B illed(KW H ) Population TotalB illed(KW H )

Population Total B illed(KW H )

Reside nti al 4,921,407 679,014, 0 69 4,897,26 4 590,381,706 4,948,057 783,907,977 4 , 987,471 889,554,931 4,9 23,897 912, 9 72,754 5,765,66 5 934,91 9,0 1 6

Com m erci a l 656,980 215,554,980 680,676 199,140,695 664,908 247,429,734 679,469 273,425,422 672,037 285,106,163 810,013 317,753,847

Industri al 23,381 134,325,100 23,413 134,564,974 20,262 151,401,913 19,698 149,631,820 20,313 142,528,562 27,95 2 147,592,916

Street Li gh ti ng 7 69 4,115, 2 86 81 7 3,229,414 750 3,369,898 7 0 7 3,370,907 7 5 3 4 , 6 21 , 3 26 82 5 6,72 3,9 6 9

Special 29,377 61,326,206 30,604 53,475,230 29,828 60,408,422 28,983 60,774,501 29,411 68,531,796 32,838 77,160,626

5,631,914 1,094,335,641 5,632,774 980,792,020 5,663,805 1,246,517,945 5,716,328 1,376,757,582 5,646,411 1,413,760,600 6,637,293 1,484,150,374

Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17

Population Total Billed(KWH) Population TotalBilled(KWH) Population Total

Billed(KWH) Population Total Billed(KWH) Population Total Billed(KWH) Population Total Billed(KWH)

5 ,5 1 5 ,5 9 8 9 8 6 ,9 2 7 ,7 3 0 5 ,5 4 6 ,4 1 9 9 4 5 ,2 3 5 ,5 7 5 5 ,6 5 2 ,4 0 1 8 8 9 ,7 6 6 ,2 4 1 5 ,6 7 8 ,1 0 4 1 ,0 0 3 ,2 7 4 ,3 5 0 5 ,6 9 2 ,2 6 9 1 ,1 0 0 ,6 0 2 ,1 1 3 5 ,7 4 3 ,8 1 4 9 9 5 ,8 9 7 ,9 4 9

7 7 6 ,6 0 6 3 2 3 ,1 6 7 ,0 0 6 7 7 6 ,2 6 3 3 0 0 ,9 2 8 ,7 6 9 7 8 2 ,4 0 0 2 8 4 ,5 1 5 ,3 8 2 7 8 6 ,4 2 4 3 1 5 ,6 8 5 ,3 3 4 7 7 7 ,5 7 8 3 3 6 ,7 3 9 ,9 8 1 7 7 2 ,4 4 1 3 2 2 ,1 8 8 ,0 1 1

2 6 ,0 3 7 1 4 4 ,4 1 5 ,8 0 0 2 6 ,3 5 5 1 4 1 ,8 7 6 ,2 2 3 2 7 ,0 4 4 1 4 6 ,6 4 2 ,0 5 1 2 7 ,3 5 2 1 6 9 ,0 7 8 ,9 5 6 3 1 ,5 9 7 1 7 5 ,0 3 2 ,0 7 8 2 9 ,6 8 5 1 6 3 ,5 5 0 ,3 3 0

8 3 9 5 ,0 9 9 ,5 8 2 7 9 3 4 ,4 5 9 ,0 0 9 8 1 9 4 ,3 9 8 ,5 4 0 8 3 0 4 ,6 0 1 ,0 3 0 8 17 5, 4 7 4 ,2 2 8 8 4 6 5 ,9 9 6 ,3 6 3

3 3 ,2 3 3 8 1 ,9 9 5 ,6 2 7 3 3 ,8 3 9 7 0 ,6 8 6 ,9 7 7 3 4 ,8 0 0 7 3 ,2 8 8 ,9 6 7 3 5 ,6 4 9 8 2 ,1 1 2 ,5 9 4 3 6 ,2 7 4 9 0 ,0 3 8 ,1 1 1 3 7 ,2 6 9 8 3 ,3 0 2 ,4 6 6

6,352,313 1,541,605,746 6,383,669 1,463,186,553 6,497,464 1,398,611,181 6,528,359 1,574,752,264 6 ,538,535 1 ,707,886,511 6,584,055 1,570,935,119

Average 7 month Average

Population Total Billed(KWH) Population Total Billed(KWH)

5,356,031 892,704,534 5 ,6 5 6 ,3 2 4 9 7 9 ,5 1 7 ,5 6 8 8 7 .0 % 6 3 .8 %

736,316 285,136,277 7 8 3 ,1 0 4 3 1 4 ,4 2 5 ,4 7 6 1 2 .0 % 2 0 .5 %

25,257 150,053,394 2 8 ,0 0 3 1 5 5 ,4 5 5 ,4 7 9 0 .4 % 1 0 .1 %

797 4,621,629 8 2 4 5 ,2 5 0 ,3 8 9 0 .0 % 0 .3 %

32,675 71,925,127 3 4 ,8 4 3 7 9 ,7 9 7 ,9 1 0 0 .5 % 5 .2 %

6,151,077 1,404,440,961 6,503,098 1,534,446,821 1 0 0 .0 % 1 0 0 .0 %

Page 101: Power Sector Report: Energy Generated and Sent Out and ......- JEBBA 10 Power Generation Statistics - Q3 2017 Power Generation - Q3 2017 Power Generation by Stations » - KAINJI 11

Acknowledgements/Contacts

A ckn o w led gem en tsWe acknowledge the contributions of our strategic partner Nigerian Electricity Regulatory Commission and our technical partner, Proshare in the design, concept and production of this publication.

proshare

C o n ta ct Us

@nigerianstat NBSNigeria @ www.nigerianstat.gov.ng

Head Office AddressPlot 762,IndependenceAvenue,Central Business District,FCT, Abuja Nigeria.

J +234 803 386 5388 [email protected]

98Power Generation Statistics - Q3 2017