power system modeling and analysiseebag/4.pdfnorth american interconnections the power system of...

28
POWER SYSTEM OPERATION AND CONTROL YAHIA BAGHZOUZ UNIVERSITY OF NEVADA, LAS VEGAS

Upload: others

Post on 06-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

POWER SYSTEM

OPERATION AND

CONTROL

YAHIA BAGHZOUZ

UNIVERSITY OF NEVADA, LAS VEGAS

Page 2: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

OVERVIEW

• Interconnected systems

• Generator scheduling/dispatching

• Load-generation balancing

• Area Control Error (ACE)

• Load following and regulation

• Unit and system ramping curves

Page 3: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

NORTH AMERICAN POWER GRID

• Utilities quickly learned the benefits in reliability and reduced operating reserves by connecting to neighboring systems.

• There are over 3,000 electric utilities in the US.

• Some provide service in multiple states.

• Over 1,700 non-utility power producers.

• Utilities are either investor-owned, publicly-owned, cooperatives, and Federal utilities.

• Electric utilities are regulated by local, State, and Federal authorities.

Page 4: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

NORTH AMERICAN INTERCONNECTIONS

The power system of North America is divided into four major Interconnections which can be thought of as independent islands.

• Western – Generally everything west of the Rockies.

• Texas - Also known as Electric Reliability Council of Texas (ERCOT).

• Eastern – Generally everything east of the Rockies except Texas and Quebec.

• Quebec.

Page 5: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

NORTH AMERICAN BALANCING AUTHORITIES

The actual operation of the Interconnections is handled by over 100

Balancing Authorities (BA’s). The BA’s dispatch generators in order to

meet their individual needs. Some BA’s also control load to maintain

balance.

Page 6: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

INTERCONNECTED OPERATION

• Each BA in an Interconnection is connected via high voltage transmission

lines (i.e., tie-lines) to neighboring Balancing Authorities.

• Overseeing the BA’s are wide-area operators called Reliability

Coordinators.

• The net power in/out of an area is the sum of the flow on its tie-lines.

One Nevada Line

Northern Nevada System

Page 7: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

GENERATION-LOAD BALANCE

• As electricity itself cannot presently be stored on a large scale, changes in customer demand throughout the day and over the seasons are met by controlling conventional generation, using stored fuels to fire generation plants when needed.

• The loads are not generally controlled directly, except for the case when there is insufficient generation available on peak days, at which point load may be reduced through DR programs.

• Frequency is maintained as long as there is a balance between resources and customer demand (plus losses). An imbalance causes a frequency deviation.

• The overall daily profile of load in a given area can be predicted reasonably well using forecasting tools.

• A day-ahead generating schedule can be developed based on the predicted next-day load profile.

Page 8: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

FREQUENCY: THE HEARTBEAT OF A POWER SYSTEM

• The figure below shows a sample time history of the frequency on the grid in the western United States, sampled six times a second. The slope of the frequency trace is a measure of the overall imbalance of generation and load at any given moment.

• The actual grid frequency tends to oscillate slightly around 60 Hz. The frequency error from 60 Hz is used to fine-tune the generation level through regulation.

Source: Alec Brooks, Ed Lu,Dan Reicher, Charles Spirakis, and Bill Weihl,”Demand Dispatch” IEEE Power & Energy magazine, May/June 2010

Page 9: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

OPTIMAL GENERATOR SCHEDULING

Given a power system with n generators, and a load forecast, the problem is to determine the optimal schedule of each generator (i.e., when to bring on-line and off-line) while recognizing generating unit limits and output capability.

0

1000

2000

3000

4000

5000

6000

1 2 3 4 5 6 7 8 910 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Syst

em L

oad

(MW

)

Hour of Day

Unit # z

Unit # y

Unit # x

Base Load

Page 10: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

GENERATION FLEET CHARACTERISTICS

Each generating unit has specific (fixed) physical characteristics that

determine the capability of each unit to respond to changes in system load

in the up or down direction:

• Minimum generation – Pmin (MW)

• Maximum generation – Pmax (MW)

• Maximum ramp rate – R (MW/min)

Time-specific characteristics are:

• Scheduled operating point - Psched (MW)

• Regulation reserve (MW)

• Load following reserve (MW)

• Contingency reserve – Pcont (MW)

Page 11: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

OPERATING RESERVE REQUIREMENTS

BA’s are required to maintain the following types of reserves to provide for regulation, balance against the load forecasting error and equipment forced and scheduled outages, and to maintain local area reliability (typically 10-15% of peak load):

• Spinning Reserve – Unloaded generation that is synchronized, automatically responsive to frequency deviations, and ready to serve an additional demand. It consists of regulating reserve and contingency reserve.

• Regulating Reserve – An amount of reserve responsive to automatic generation control (AGC), that is sufficient to provide normal regulating margin.

• Contingency Reserve – The capacity available to be deployed by a balancing authority (BA) to meet the North America Electric Reliability Corporation (NERC) and WECC contingency reserve requirements.

• Non-Spinning Reserve – (1) The generating reserve, which is not connected to the system but capable of serving the demand within a specified time from its activation; and (2) loads that can be removed from the system in a specified time.

Page 12: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

RESERVE ALLOCATION IN SCHEDULING PROCESS

Page 13: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

OPTIMAL GENERATOR DISPATCH (SUB-PROBLEM)

• Optimal Power Flow/Economic dispatch: Given a forecasted

load on the system at a particular hour, determine the optimal

power production from each generator that is committed such

that operating cost is minimized, while meeting numerous

constraints.

→ Conventional generators are dispatchable. On the other

hand, renewable resources are not dispatchable, hence cannot

be scheduled.

• Constraints include:

• Minimum transmission losses

• Generator limits (regulation, load following and

contingency reserves)

• Voltage limits at all system nodes

Page 14: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as
Page 15: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

MATHEMATICAL FORMULATION

• Cost function to minimize

• Generator limits

• Power flow constraints

• Voltage constraints

• Electric utilities use commercial software packages to solve the

problem.

)cos(||||||1

ijij

n

j

ijiji VVYP

)sin(||||||1

ijij

n

j

ijiji VVYQ

05.195.0 iV

Page 16: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

Red indicates under-

voltage at Bus 3

EXAMPLE OF POWER FLOW SOLUTION

Page 17: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

INTERCHANGE ERROR

Customer demand and generation are constantly changing within all BA’s. → BA’s will have some unintentional outflow or inflow at any given instant. • A Balancing Authority’s internal obligations is to control an instantaneous value

called the Area Control Error (ACE) by keeping it within acceptable limit that is proportional to the BA size (44 MW for NV Energy South?). ACE consists of the following:

• Interchange Error, which is the net outflow or inflow compared to what it is scheduled to be imported or exported.

• Frequency Bias, which is the Balancing Authority’s obligation to stabilize frequency: For example, if frequency goes low, each BA is asked to contribute a small amount of extra generation in proportion to its size.

• Conceptually, ACE is to a Balancing Authority what frequency is to the Interconnection. For example, over-generation makes ACE go positive and puts upward pressure on Interconnection frequency.

M

Scheduled net flow: 350 MW

Actual net flow: 340 MW

(due to load reduction)

ACE goes positive

Frequency goes up Reduce generation

Tie-line

Page 18: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

AREA CONTROL ERROR (ACE)

• (NIA - NIS) represents the ACE associated with meeting

schedules.

• 10ß (FA - FS) is the BA’s obligation to support frequency. ß is

in MW/0.1Hz (ß = -1,480 MW/.1 Hz for WSCC)

• IME is a correction factor for meter error. Normally this number

very small or zero.

Page 19: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

INITIAL RESPONSE TO A DISTURBANCE: PRIMARY CONTROL

Primary Control (also known as Frequency Response) occurs within

the first few seconds following a disturbance, and it is provided by

fast-acting generator governor actions (similar to cruise control on a

car). They sense a change in speed and adjust the energy input into

the generators’ prime mover. Primary control is provided by spinning

reserves.

Typical WSCC frequency response due to loss of a generator

(Source: NERC Report on Balancing and Frequency Control, July 5,2009)

Page 20: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

FOLLOWING RESPONSES: SECONDARY AND

TERTIARY CONTROL

• Secondary Control maintains the minute-to-minute balance throughout the day to restore frequency. This is accomplished using the BA’s Automatic Generation and Control (AGC) system and manual dispatch actions to maintain balance.

• NERC Control Performance Standards:

• CPS1 assigns each Control Area a slice of the responsibility for control of Interconnection frequency. CPS1 is a yearly standard that measures impact on frequency error - based on a specific formula.

• CPS2 is a monthly standard intended to limit unscheduled flows – also based on a specific formula.

• NERC does not mandate generation and load to be balanced 100% of the time. Each Balancing Authority shall operate such that its average ACE for at least 90% of its ten-minute periods over a calendar month is within a specific limit (L)

AVG10-minute(ACEi) < L

• Tertiary Control involves the generally manual actions taken by operators in response to disturbances. It includes the initial deployment of reserves and the actions taken to expeditiously restore reserves such that the system is able to withstand the next contingency.

Page 21: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

POWER SYSTEM OPERATION – REAL TIME

• In real time, the level of generation is adjusted to meet differences

between actual loads and the hourly schedules. This real-time

adjustment, can be separated into “load following” (within-hour

resource dispatching) and “regulation” (sub-minute adjustments of

generation) processes according to their respective time scales.

• Load following typically requires adjustments every 5-15 minutes.

This is accomplished through a re-dispatch of on-line generation via

automatic adjustments by computerized control systems. Load

following and regulation require sufficient capacity and ramp rates,

upward and downward, to respond to changes in load.

• Regulation, in turn, is effected by making sub-minute output

adjustments exclusively through an automatic generation control

(AGC) system.

• During real time operation, generators under AGC are adjusted every

2 or 4 seconds (although their actual responses are slower) to keep

the ACE close to zero.

Page 22: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

POWER SYSTEM OPERATION – REAL TIME

• The hourly day-ahead schedules (based on load forecast) are comprised of hourly energy blocks with 20-minute ramps between hours; the ramping process begins 10 minutes before the end of each hour.

• Hour-ahead adjustments are made to account for forecact errors

• Additional adjustments are conducted over regular intervals (5-15 minutes) to track changes in actual load, i.e., load following.

• Finally, adjustments are made at the sub-minute level to reduce the difference between the actual load and the real-time generation schedule . This must be matched by AGC to maintain system frequency.

Page 23: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

ILLUSTRATION OF REGULATION AND LOAD FOLLOWING

• Load following is the difference between 10-minute interval average and 60-minute average (both with ramps) of load, depicting the variation of load within the hour at a 10-minute time scale.

• Load Following = [real-time schedule] – [hourly schedule]

• Regulation = [actual load] – [ real-time schedule]

• Note that the regulation ramps (i.e. slopes) are significantly higher than those of load following

Page 24: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

ASSESSING ADEQUACY OF RAMPING CAPABILITY

• Insufficient ramping capability is identified when the ramp requirements exceed generation fleet ramping limits.

• The figure below illustrates how such a deficiency could occur: the area in red highlights the magnitude and duration of the interval when regulation ramp requirements exceed fleet capability.

• More units and capacity are needed if composite unit ramping capability is insufficient,

Page 25: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

GENERATION FLEET RAMPING CAPABILITY

The individual ramping capability of

each unit can be combined to calculate

total ramping capability of the entire

generation fleet. The top figure

illustrates the composite ramping

capability of the entire generation fleet.

The maximum available system

ramping capability versus duration is

derived from the angles of the red

dotted line and time axis. The result is

illustrated in the bottom figure.

Page 26: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

GENERATOR CYCLING AND MOVEMENTS

Generators providing load following and regulation services need to

move up or down frequently to balance load with generation.

Two effective metrics* that have been proposed to quantitatively

evaluate the cycling and movements (i.e., wear and tear) of

conventional generators for providing balancing services include

1. Mileage (MW) and number of direction changes in balancing

service (load following and regulation);

2. Ramp (or half-cycle) analysis: Half-cycle ramp rate = ratio

between half-cycle magnitude and half-cycle duration

Half-cycle duration

Half-cycle magnitude

Page 27: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

SYSTEM MONITORING & CONTROL

The possibility of measuring synchronized

voltage and current phasors using GPS/GIS

has led to new innovative ways of monitoring,

protecting, and controlling power systems.

Structure of a WAMPAC

Structure of a PMU

Page 28: Power System Modeling and Analysiseebag/4.pdfNORTH AMERICAN INTERCONNECTIONS The power system of North America is divided into four major Interconnections which can be thought of as

END!