pre – feasibility reportenvironmentclearance.nic.in/writereaddata/online/tor/13_jun_2016... ·...

60
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT APPLICANT : M/s STATUS IMPEX (P) LIMITED DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014 ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR SEPTEMBER’ 2014 1 PRE – FEASIBILITY REPORT

Upload: others

Post on 15-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 1

    PRE – FEASIBILITY

    REPORT

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 2

    INDEX

    1.0 EXECUTIVE SUMMARY ................................................................................................. 6

    1.1 SALIENT FEATURES OF THE PROJECT ..................................................................... 7

    1.2 PROPOSED PLANNING................................................................................................. 8

    2.0 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION ....................... 9

    2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT ................................... 9

    2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT ............................................. 10

    2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR

    REGION ........................................................................................................................ 10

    2.4 DEMAND - SUPPLY GAP ............................................................................................. 10

    2.5 IMPORTS VS. INDIGENOUS PRODUCTION ............................................................... 11

    2.6 EXPORT POSSIBILITY ................................................................................................ 11

    2.7 DOMESTIC/ EXPORT MARKETS ................................................................................ 11

    2.8 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT .. 11

    3.0 PROJECT DESCRIPTION ............................................................................................ 12

    3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT

    PROJECTS, IF ANY. .................................................................................................... 12

    3.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, AND

    PROJECT BOUNDARY AND PROJECT SITE LAYOUT) WITH COORDINATES ....... 12

    3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF

    SELECTING THE PROPOSED SITE, PARTICULARLY THE ENVIRONMENTAL

    CONSIDERATIONS GIVEN INTO SHOULD BE HIGHLIGHTED. ................................. 12

    3.4 SIZE OR MAGNITUDE OF OPERATION ...................................................................... 13

    3.4.1 REGIONAL GEOLOGY ................................................................................................ 13

    3.4.2 LOCAL GEOLOGY ....................................................................................................... 13

    3.4.3 HYDROGEOLOGY ....................................................................................................... 14

    3.4.4 MINERAL RESERVES .................................................................................................. 15

    3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC DIAGRAM/

    FLOW CHART SHOWING THE PROJECT LAYOUT, COMPONENTS OF THE

    PROJECT ETC. SHOULD BE GIVEN). ........................................................................ 15

    3.5.1 YEAR WISE PRODUCTION DETAILS ......................................................................... 16

    3.5.2 PROPOSED METHOD OF MINING .............................................................................. 16

    3.5.3 EXTENT OF MECHANIZATION .................................................................................... 16

    3.5.4 CONCEPTUAL MINING PLAN ..................................................................................... 17

    3.5.5 DRILLING ..................................................................................................................... 18

    3.5.6 BLASTING .................................................................................................................... 18

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 3

    3.5.6.1 Broad Blasting Parameters ......................................................................................... 18

    3.5.6.2 Explosive Used ............................................................................................................ 18

    3.5.6.3 Powder Factor ............................................................................................................. 18

    3.5.6.4 Storage of Explosive ................................................................................................... 19

    3.5.7 MINERAL TRANSPORTATION .................................................................................... 19

    3.6 RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY

    SOURCE, MARKETING AREA OF FINAL PRODUCT/S, MODE OF TRANSPORT

    OF RAW MATERIAL AND FINISHED PRODUCT ........................................................ 19

    3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE

    PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED .............................................. 19

    3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY / POWER REQUIREMENT

    AND SOURCE SHOULD BE GIVEN………………………. ............................................ 19

    3.8.1 WATER ......................................................................................................................... 19

    3.8.2 POWER ......................................................................................................................... 20

    3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND

    SCHEME FOR THEIR MANAGEMENT/ DISPOSAL. ................................................... 20

    4.0 SITE ANALYSIS ........................................................................................................... 20

    4.1 CONNECTIVITY ............................................................................................................ 20

    4.2 LAND FORM, LAND USE AND LAND OWNERSHIP ................................................... 21

    4.2.1 LANDFORM .................................................................................................................. 21

    4.2.2 LAND USE .................................................................................................................... 21

    4.2.3 LAND OWNERSHIP ..................................................................................................... 21

    4.3 TOPOGRAPHY (ALONG WITH MAP) .......................................................................... 21

    4.4 EXISTING LAND USE PATTERN (AGRICULTURE, NON-AGRICULTURE,

    FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ)), SHORTEST

    DISTANCES FROM THE PERIPHERY OF THE PROJECT TO PERIPHERY OF

    THE FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE

    AREAS, WATER BODIES (DISTANCE FROM THE HFL OF THE RIVER), CRZ. IN

    CASE OF NOTIFIED INDUSTRIAL AREA, A COPY OF THE GAZETTE

    NOTIFICATION SHOULD BE GIVEN. .......................................................................... 21

    4.5 EXISTING INFRASTRUCTURE .................................................................................... 22

    4.6 SOIL CLASSIFICATION ............................................................................................... 22

    4.8 SOCIAL INFRASTRUCTURE AVAILABLE .................................................................. 24

    5.0 PLANNING BRIEF ........................................................................................................ 24

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 4

    5.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, TRANSPORTATION

    ETC.) TOWN AND COUNTRY PLANNING/ DEVELOPMENT AUTHORITY

    CLASSIFICATION. ....................................................................................................... 24

    5.2 POPULATION PROJECTION ....................................................................................... 24

    5.2 LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT ETC.) ................... 24

    5.3 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL AND SOCIAL) .......... 25

    5.4 AMENITIES/ FACILITIES .............................................................................................. 26

    6.0 PROPOSED INFRASTRUCTURE ................................................................................ 26

    6.1 INDUSTRIAL AREA (PROCESSING AREA) ................................................................ 26

    6.2 RESIDENTIAL AREA (NON PROCESSING AREA) ..................................................... 26

    6.3 GREEN BELT ............................................................................................................... 26

    6.4 SOCIAL INFRASTRUCTURE ....................................................................................... 26

    6.5 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL / METRO /

    WATER WAYS ETC.) ................................................................................................... 26

    6.6 DRINKING WATER MANAGEMENT (SOURCE AND SUPPLY OF WATER) .............. 27

    6.7 SEWERAGE SYSTEM .................................................................................................. 27

    6.8 INDUSTRIAL WASTE MANAGEMENT ........................................................................ 27

    6.9 SOLID WASTE MANAGEMENT ................................................................................... 27

    6.10 POWER REQUIREMENT AND SUPPLY / SOURCE .................................................... 27

    7.0 REHABILITATION AND RESETTLEMENT (R & R PLAN) ........................................... 27

    7.1 POLICY TO BE ADOPTED (CENTRAL/ STATE) IN RESPECT OF THE PROJECT

    AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND OUSTEES AND

    LANDLESS LABOUR (A BRIEF OUTLINE TO BE GIVEN) ......................................... 27

    8.0 PROJECT SCHEDULE AND COST ESTIMATES ........................................................ 28

    8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF

    COMPLETION (TIME SCHEDULE FOR THE PROJECT WILL BE GIVEN). ................ 28

    8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF

    ECONOMIC VIABILITY OF THE PROJECT ................................................................. 28

    9.0 ANALYSIS OF PROPOSAL ......................................................................................... 29

    9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE

    BENEFITS TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF

    ANY, IN THE AREA ...................................................................................................... 29

    10.0 BASELINE ENVIRONMENT ......................................................................................... 30

    10.2 AIR ENVIRONMENT ..................................................................................................... 31

    10.3 WATER ENVIRONMENT .............................................................................................. 32

    10.4 NOISE ENVIRONMENT ................................................................................................ 34

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 5

    10.5 LAND ENVIRONMENT ................................................................................................. 36

    10.6 BIOLOGICAL ENVIRONMENT ..................................................................................... 37

    10.7 SOCIO-ECONOMIC ENVIRONMENT ........................................................................... 43

    11.0 ENVIRONMENTAL MANAGEMENT PLAN .................................................................. 57

    12.0 CONCLUSION .............................................................................................................. 60

    ************

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 6

    1.0 EXECUTIVE SUMMARY

    Lime Stone Mine (Minor Mineral) M.L. No.04/2010 of lessee Status Impex (P) Limited, is

    situated near Village – Kumbhkot; Khasara No. – 236, 241, 242, 243, 244, 245, 254,

    257, 258, 255, 266, 259, 349, Tehsil – Ramganjmandi, District - Kota, Rajasthan in an

    area of 4.5058 ha.

    Schedule 1 (a) Category - “B” as per MoEF EIA gazette Notification 14th Septmber 2006

    and its subsequent amendement and in consistant with the MoEF Notifiaction dated

    09.09.2013.

    The Project Proponent has obtained a letter by Mining Engineer, along with map

    showing the other mining leases falling within 500m from the periphery of the mine vide

    Enclosed as Annexure.

    Details are as given below:-

    S.

    No.

    Lease

    No.

    Name of the lease

    holder

    Name of the

    Mineral

    (Minor)

    Total Area

    (Ha.)

    Area of the

    mine falling in

    500m

    1. 04/ 2010 Status Impex (P) Limited

    Kota

    Lime stone /

    (Building stone)

    4.5058 4.5058

    2. 169/2008 Sampoorna Export (P)

    Limited, Kota

    Lime stone /

    (Building stone)

    4.0 4.0

    4. 05/ 2013 Sampoorna Export (P)

    Limited, Kota

    Lime stone /

    (Building stone)

    4.0 4.0

    5. 94/2008 ASI Kotah Ltd. Building Stone 916.611 51.59

    The mining lease was sanctioned in favour of Status Impex (P) Limited, copy of

    approved mining plan by Superintending Mining Engineer, Kota Circle, is enclosed as

    Annexure.

    The working will be carried out by opencast semi-mechanized method as per the

    approved Mining Plan. The entire lease area is classified as Khatedari land & Sawaichak

    Land (Govt. waste land). The proposed rate of production will be 2,10,118 TPA of ROM

    (700 TPD). The estimated project cost is Rs. 2.0 Crore. The validity of lease will be 20

    years (w.e.f. 19.10.2010 to 18.12.2030).

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 7

    1.1 SALIENT FEATURES OF THE PROJECT

    Particulars Details

    Latitude (N) & Longitude (E)

    Latitude (N) Longitude (E) Remark

    240 37' 28.20'' 76

    0 00' 02.00'' FRP

    240 37' 32.30'' 75

    0 59' 57.20'' 1

    240 37' 35.20'' 75

    0 59' 55.90'' A

    240 37' 34.60'' 75

    0 59' 53.10'' B

    240 37' 28.50'' 75

    0 59' 53.50'' C

    240 37' 28.20'' 75

    0 59' 50.80'' D

    240 37' 34.70'' 75

    0 59' 48.80'' E

    240 37' 34.60'' 75

    0 59' 50.70'' F

    240 37' 39.30'' 75

    0 59' 50.00'' G

    240 37' 39.50'' 75

    0 59' 55.20'' 4

    240 37' 34.80'' 75

    0 59' 57.20'' 5

    Toposheet No. 45P/14 & 54D/2.

    Total Mine Lease area 4.5058 ha.

    Geological Reserves 12,40,320 Tonnes

    Mineable Reserves 9,54,820 Tonnes

    Production 2,10,118 TPA

    Life of Mine 9 years

    Estimated Project Cost Rs 2.0 Crore

    Man Power 95 Persons

    Elevation 341 MSL - Highest

    340 MSL – Lowest

    Land Use Sawaichak Land (Govt. Waste Land: 0.4210 ha.) and

    Khatedari land (4.0848 ha.)

    Nearest Habitation / Town Ramganjmandi ~ 7.0 km, NW

    Nearest Airport Jaipur International Airport ~ 243 km, N

    Nearest Highway S. No. Name Distance (km) Direction

    (From Lease Boundary)

    1 RJ - SH - 9A 5.3 N

    2 RJ - SH - 9B 2.7 W

    3 NH - 12 5.3 E

    Nearest Railway Station S. No. Name Distance (km) Direction

    (From Lease Boundary)

    1 Ramganjmandi 5.39 WNW

    Power Supply 4 kW through JVVNL

    Nearest Dispensary and S. No. Name Distance (km) Direction

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 8

    Govt. Hospital (From Lease Boundary)

    1 Govt. Manglam Cement Hospital 4.59 WNW

    2 Community Health Care Center, Morak 9.9 N

    3 Kota Stone Mariam Hospital, Suket Road,

    Ramganj Mandi 1.3 W

    Educational Facility S. No. Name Distance (km) Direction

    (From Lease Boundary)

    1 Govt. Upper Primary School, Kundayla 3.3 NW

    2 Govt. Upper Primary School, Lakhariya 4.0 SSE

    3 Govt. Girls Upper Primary School Suket 4.3 ENE

    4 Govt. Sr. Sec. School, Suket 4.8 ENE

    5 Govt. Upper Primary School Suket 4.5 ENE

    6 Govt. Girls Senior Secondary School,

    Ramganj Mandi 5.57 WNW

    7 New Happy School, Ramganj Mandi 5.89 WNW

    8 Govt. Senior Secondary School, Lakhariya 4.9 SSE

    9 Bright Technical PG College, Ramganj

    Mandi 5.46 W

    Water Demand and Supply 10.0 KLD

    Water demand will be met from tanker supply.

    Defense Installations None within the Study Area

    Archeological Features None within the Study Area

    Ecological Sensitive Zones None

    Forest Name Distance (km) Direction

    Sahipur R.F. 7.47 ENE

    Kheemach PF 7.72 NE

    Mukunndgarh wild life hills 12.5 NE

    Nearest Streams/ Rivers/

    Water Bodies (From Mine

    Boundary)

    S. No. Name Distance (km) Direction

    (From Lease Boundary)

    1 Ahu River 4.05 E

    Seismic Zone Zone-II, Low Damage Risk Zone as per BMTPC, Vulnerability Atlas Seismic Zone

    of India IS: 1893-2002.

    1.2 PROPOSED PLANNING

    Mining Method: Semi-Mechanized Opencast Mine

    Project Cost : Rs. 2.0 Crore

    Production : 2,10,118 TPA of ROM

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 9

    Table 1.2: Land Use of lease area

    S. No. Land use Category Pre-operational

    (Ha.)

    Land-use after

    5th

    year (Ha.)

    End of the life of mine

    1 Pits -- 2.4707 4.2567*

    2 Dump area -- -- --

    3 Roads -- -- --

    4 Infrastructure -- -- --

    5 Mineral storage -- -- --

    6 Top soil storage -- -- -

    7 Plantation -- 0.2491 0.2491

    8 Un-worked 4.5058 1.7860 --

    Total 4.5058 4.5058 4.5058

    *Out of which 2.6311 ha. area will be backfilled and planted remaining area of 1.6256 ha., will be used

    as rain water storage.

    2.0 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION

    2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT

    The mining lease was sanctioned in favour of M/s Status Impex (P) Limited. The Mining

    Plan has been approved by Superintending Mining Engineer, Kota, vide letter no. SME/

    Kota/P-269 (2010) 4400 dated 19.10.2010 under RMMCR-1986 for 20 years.

    The lease area is situated near village – Kumbhkot; Khasra No. – 236, 241, 242, 243,

    244, 245, 254, 257, 258, 255, 266, 259, 349 Tehsil – Ramganjmandi, District- Kota,

    Rajasthan in an area of 4.5058 ha. The validity of the lease period is for 20 years. The

    lease area is mix of Sawaichak land (Govt. Waste Land) and Khatedari Land. The

    targeted production of mine will be 2,10,118 TPA of ROM with the estimated project cost

    as 2.0 crore. Life of the mine will be around 9 years.

    The Project Proponent is a private company and engaged in mining. The main objective

    to be pursued by the applicant is to carry the business of prospecting, exploring,

    operating and working on mines. The main market for mineral is nationwide and will be

    utilized as buildings stones.

    Name and address of the Applicant M/s Status Impex (P) Limited

    Bazar No. 1

    Tehsil: Ramganjmandi;

    District: Kota (Rajasthan)

    Pin-code: 326-519

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 10

    2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT

    It has been proposed to excavate approximately 709 TPD (2,10,118 TPA of ROM) of

    mineral (ML No. 04/ 2010) by open cast semi-mechanized method. The lease area is

    4.5058 ha. Total minable reserve available is 15,01,576 MT. The expected life of mine is

    9 years. Total waste generated during the plan period of the mine will be 9,56,652

    m3.The mineral will be transported through trucks/ tippers.

    At the conceptual stage, the total excavated area will be 4.5058 ha. Water requirement

    will be 10.0 KLD for the project and will be met by water tanker supply. The ultimate pit

    limit will be 277 MSL at conceptual stage. The water table is at 130 m below the general

    ground level at 210 MSL (ground water fluctuates between 210 MSL in Pre-monsoon

    and 213 MSL in Post – monsoon season). Thus, ground water table will not be

    intersecting during working till life of mine.

    2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND

    OR REGION

    Being a construction material, the mineral will be used in indigenous market. The

    excavated mineral will be dressed and polished as finished good made ready for use.

    The mining and associated activities in the mineral bearing areas will bring about gains

    in gross domestic product, i.e. there is though a minor contribution by the project but will

    add to the gains in G.D.P. (Gross Domestic Product). Sales in India have increased on

    an over the past ten years, exceeding both regional and global averages. A rapidly

    advancing economy and rising standards of living have helped increase overseas

    investment in India, stimulating large amounts of industrialization and infrastructure-

    related construction activity. However, Indian product demand (relative to construction

    spending and on a per capita basis) is substantially below regional and world averages.

    The mining project will provide employment to local people. Applicant will pay royalty for

    the mineral produced from the mine, direct and indirect taxes will be paid thereby

    contributing to the regional revenue. The public revenue so generated will further be put

    for use in infrastructural development and other sectors like health, education and social

    welfare. The applicant will spend 1% of profit for the development of the area i.e.

    medical facilities, schools, temples and other social work.

    2.4 DEMAND - SUPPLY GAP

    Lime stone (minor mineral) is splittable used in construction activities as raw material. It

    is available in the eastern part of the State near Kota and Jhalawar district. Most of the

    lessees are from rural areas. Rajasthan in India is the largest producer of building stones

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 11

    endowed with vast resources. The anticipated annual growth in consumption would be

    around 15%. The entry in the target market is easy and there is a narrow gap in the

    supply and demand, which is growing.

    2.5 IMPORTS VS. INDIGENOUS PRODUCTION

    The most commonly used product type is lime stone (Kota stone), is used for making

    titles, Pattis, for flooring, table tops, cladding of walls and roof top coverings.. Limestone

    (building stone) demand in India is expected to rise. Ongoing industrialization and

    government plans to expand and upgrade the country's physical infrastructure will fuel

    market growth.

    2.6 EXPORT POSSIBILITY

    Lime stone (Kota stone) production from the mine will cater to the needs of well

    established domestic markets. There is a potential of the mineral for exporting after

    meeting the indigenous requirements.

    2.7 DOMESTIC/ EXPORT MARKETS

    Domestic demand is one of the main reasons for the rapid growth of lime-stone (Kota

    stone) business in India. Thus, domestic market for the stone as building stone is well

    established.

    The market scope for stone is found to be encouraging in local market with the

    increased demand from construction fields

    2.8 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE

    PROJECT

    The proposed project generates employment for around 95 people. Priority for

    employment will be given to local persons. Following staff & workers are proposed to be

    employed:-

    Table 2.8: Provisional Number of Proposed Staff and Workers

    S. No. Particulars Proposed

    1. Managerial staff 05

    2. Operating staff 42

    3. Unskilled workers 26

    4. Semi-skilled worker 11

    5. Skilled 11

    6. Total 95

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 12

    3.0 PROJECT DESCRIPTION

    3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT

    PROJECTS, IF ANY.

    This will be a semi mechanized open cast limestone mining project. Mineral will be used

    / consumed as building stone.

    3.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION,

    AND PROJECT BOUNDARY AND PROJECT SITE LAYOUT) WITH

    COORDINATES

    The proposed Mine site is located at Khasara Nos. 236, 241, 242, 243, 244, 245,

    254, 257, 258, 255, 266, 259, 349; Village – Kumbhkot, Tehsil – Ramganjmandi,

    District – Kota, Rajasthan in an area of 4.5058 hectare. The project site falls in

    Survey of India Toposheet No. 45P/14 and 54D/2.

    The geographical location with respect to boundary pillars of the proposed project are:-

    Table 3.2: Geographical Position of the Boundary Pillars

    Latitude (N) Longitude (E) Remark

    240 37' 28.20'' 76

    0 00' 02.00'' FRP

    240 37' 32.30'' 75

    0 59' 57.20'' 1

    240 37' 35.20'' 75

    0 59' 55.90'' A

    240 37' 34.60'' 75

    0 59' 53.10'' B

    240 37' 28.50'' 75

    0 59' 53.50'' C

    240 37' 28.20'' 75

    0 59' 50.80'' D

    240 37' 34.70'' 75

    0 59' 48.80'' E

    240 37' 34.60'' 75

    0 59' 50.70'' F

    240 37' 39.30'' 75

    0 59' 50.00'' G

    240 37' 39.50'' 75

    0 59' 55.20'' 4

    240 37' 34.80'' 75

    0 59' 57.20'' 5

    The map showing location of the lease area is enclosed as Annexure.

    3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF

    SELECTING THE PROPOSED SITE, PARTICULARLY THE

    ENVIRONMENTAL CONSIDERATIONS GIVEN INTO SHOULD BE

    HIGHLIGHTED.

    No alternate site was considered as mining project is a mineral specific activity.

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 13

    3.4 SIZE OR MAGNITUDE OF OPERATION

    Salient features of the project are as follows:-

    Table 3.4: Size or Magnitude

    S. No. Particulars Proposed

    1. Lease Area 4.5058 hectare

    2. Mineable Reserves (lime Stone / building stone) 15,01,576 tonnes

    3. Production 700 TPD

    4. Mine Waste 1722 TPD

    5. Life of Mine 9

    6. Period of the Lease 20 yrs.

    7. Total Man Power (Nos.) 95

    3.4.1 REGIONAL GEOLOGY

    Most of the part of Kota district is occupied by rocks of Vindhyan Super Group which

    forms the part of Great-Vindhyan basin, extending from Rohtas in Bihar to the

    Chittorgarh area of Rajasthan. On the basis of different rock units the Vindhyan of the

    area have been divided in to Semri, Kaimur, Rewa, and Bhander groups comprising

    sandstones, shales and limestone. The Semri Group is separated from Kaimur by

    conglomerate horizon which marks the break in sedimentation before the deposition of

    Kaimur Group. The lime stone of Sirbu-Shale horizon; at places show the evidence of

    algal life in the form of arch shaped structures known as Stomatolites. Occurrence of

    Sandstone at different Stereographic horizons indicates fluctuation of the sea level due

    to transgression and regression of the sea several times during the Vindhyan period.

    The general Stratigraphic succession of rock types exposed in Kotah district is as under:

    Geologically the district comprises rocks belonging to Vindhyan Super Group. The

    generalized and modified litho stratigraphic sequence is as under:

    Table 3.4.1: Regional Geology

    Vindhyan Super

    Group

    Bhander Group Sandstone, Limestone & Shales

    Rewa Group Shales & Sandstone

    Delhi Super Group Kaimur Group Sandstone

    Semri Group Sandstone Shale and Limestone

    The rocks of the area belong to Vindhyan Super Group

    3.4.2 LOCAL GEOLOGY

    The rock formations occurring within mining lease area comprise of Semari Group

    (Lower Vindhyan). Reconnaissance of Geological aspect was done in the area and

    following geological sequence has been established.

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 14

    Recent Soil

    sub soil

    Lower Vindhyan Limestone (upper layer & lower layer)

    The limestone which is belonging to Suket Shale of Lower Vindhyan, occur near village

    Suket, Ramganjmandi, Chechat & Morak area in tehsil- Ramganjmandi, District- Kota.

    Figure 1: Geological Map (Source: GSI)

    The surface geological plan of the lease area is enclosed as Annexure.

    3.4.3 HYDROGEOLOGY

    The study area falls in Khairabad block of Kota district, which is under safe category

    according to CGWB Publication “Dynamic Ground Water Resources of India – 2009”.

    Rainfall plays a major role in groundwater availability of semi-arid region as it is the

    major source available for groundwater recharge. The area is largely occupied by quartz

    mica schist, phyllite along with granite & pegmatite intrusives as main aquifers.

    Movement of groundwater in these hard rocks is controlled by size, continuity and

    interconnectivity of weathered and fractured parts and due to other secondary porosities.

    Groundwater occurs mainly under unconfined condition to semi-confined in saturated

    zone of rock formation.

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 15

    The water level in the study area varies from 210 MSL to 213 MSL as per

    hydrogeological investigation. Seasonal fluctuation in the area is around -2 to 2 m as per

    CGWA district groundwater brochure. (Source: CGWB Report)

    3.4.4 MINERAL RESERVES

    The mineral is already being worked in neighboring mine adjacent to the proposed

    mining area under the supervision and control of the sister concern. The mineral is

    exposed and similar in nature as per the investigations. The mineral reserves have been

    estimated by plan area method. Based on the experience and the estimated reserves

    have been classified in to proved, probable & possible reserves. The quantity of

    reserves is arrived as per the details below:-

    Table 3.4.4: Reserve Estimation according to UNFC Classification

    S. No. Total Mineral Resources Code Reserves (Tonnes)

    A. Mineral Reserves

    1. Total Mineral (geological reserves) 111 18,72,160

    2. Statutory Barrier 121 1,03,501

    3. Reserve slope 211 2,67,083

    4. Total mineable reserve in tonnes 111 1872160 – (1,03,501 –

    2,67,083) = 15,01,576

    3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC

    DIAGRAM/ FLOW CHART SHOWING THE PROJECT LAYOUT,

    COMPONENTS OF THE PROJECT ETC. SHOULD BE GIVEN).

    The proposed mining operations will be carried out by open cast semi-mechanized

    method. The process flow diagram given below depicts the mining process:-

    Removal of Top Soil/ Overburden

    Excavation

    Loading & Transportation

    Stacking at Designated Areas

    Dispatch

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 16

    3.5.1 YEAR WISE PRODUCTION DETAILS

    The details of year wise production for the first five years are given below:-

    Table 3.5.1: Year wise production for the Five Years Period

    Year Total ROM

    in Tonne

    85% lime

    Stone (Tonne)

    Waste 15 %

    m3

    Soil m3 OB m

    3 Total OB +

    waste m3

    1st year Nil Nil Nil 7,730 3,12,344 3,20,074

    2nd

    year 2,10,118 1,78,601 11378 2,295 1,30,880 1,44,553

    3rd

    year 1,26,312 1,07,365 6840 2,340 1,37,280 1,46,460

    4th year 1,26,312 1,07,365 6840 2,850 1,48,740 1,58,430

    5th year 1,29,636 1,10,190 7020 3,315 1,76,800 1,87,135

    Total 5,92,378 5,03,521 32078 18,530 9,06,044 9,56,652

    The map showing working / composite plan is enclosed as Annexure.

    3.5.2 PROPOSED METHOD OF MINING

    Mine will be developed by semi mechanized opencast mining which includes drilling,

    blasting, loading, transport and dispatch.

    3.5.2.1 Open Cast Mining

    The mining will be done by open cast semi-mechanized method of mining. The bench

    height will be maintained at 7.0 m and width will not be less than the height. The face

    slope will be 85°, whereas ultimate pit slope is proposed at 45°.

    The drilling will be carried out by 110 mm rotator drill / Jack hammer pneumatically

    operated. Waste /O.B will be loaded by excavators/loaders. The mineral will be

    transported through tipper/ tractor trolleys/ trucks

    3.5.2.2 Salient Features of Mining Method

    The proposed mining operations will be carried out by open cast semi-mechanized

    method. The salient features of proposed mining method are:-

    � The height and width of the bench will be maintained at 7.0 m.

    � Face slope will be maintained 85°.

    � Ultimate pit slope is proposed 45°

    � Drilling will be done by Jack Hammer/110 mm drills.

    3.5.3 EXTENT OF MECHANIZATION

    The details of equipments proposed to be used in mining operation are listed below:-

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 17

    Table 3.5.3: List of Machineries

    3.5.4 CONCEPTUAL MINING PLAN

    The applied area is having mineral throughout the lease area. The mineable reserves as

    estimated are 15,01,576 MT. The annual production projected is estimated 2,10,118

    TPA of ROM. Life of the mine therefore is around 9 years. Ultimate pit level will be 277

    MSL.

    3.5.4.1 Land Use Pattern

    The land use for mining and allied purposes is given below:-

    S. No. Land use Category Pre-operational

    (Ha.)

    Land-use after

    5th

    year (Ha.)

    End of the life of

    mine

    1 Pits -- 2.4707 4.2567*

    2 Dump Area -- -- --

    3 Roads -- -- --

    4 Infrastructure -- -- --

    5 Mineral Storage -- -- --

    6 Top Soil Storage -- -- -

    7 Plantation -- 0.2491 0.2491

    8 Un-Worked 4.5058 1.7860 --

    Total 4.5058 4.5058 4.5058

    *out of which 2.6311 ha. area will be backfilled and partially planted remaining area

    of 1.6256 ha. will be used as rain water storage.

    The conceptual plan is enclosed as Annexure.

    S. No. Machine Type Capacity Nos.

    1. Jhiri Machine 30 hp 28

    2. Transformer 210 kVA 1

    3. Excavator 2.65 m3 range 1

    4. Pneumatic Drill 110 mm 1

    5. Water Tanker Trolley Mounted 10,000 liter 1

    6. Dumper 35 tonne 4

    7. Air Compressor 450 cfm 1

    8. Trucks 13 tonne 2

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 18

    3.5.5 DRILLING

    The hard strata (overburden) will be fragmented for ease handling by drilling and

    blasting as and when required. The material will be handled by loading equipments.

    Mineral will be loaded manually into the trucks and sent to the stock yards / destination.

    3.5.6 BLASTING

    The blasting is needed to excavate the over burden. The controlled blasting is proposed

    by adopting all the safety measures as per “M.M.R.1961” and with the permission of

    DGMS.

    3.5.6.1 Broad Blasting Parameters

    Table 3.5.6.1: Broad Blasting Parameters

    Deep Hole Blasting

    Hole depth : 7m Effective Length

    Burden : 3.5 m

    Spacing : 4.0 m

    Hole Diameter : 110 mm

    volume 98 m3

    Tonnage Yield (T) 98 x 2.7 = 264.6 Tonne

    3.5.6.2 Explosive Used

    Blasting will be done by ANFO along with booster and Slurry explosive viz. power

    gel, Acquadyne, Superdyne etc.

    3.5.6.3 Powder Factor

    Charge per hole is 0.125 kg of booster, 6.0 kg/m of explosive and one detonator.

    Table 3.5.6.3: Broad Blasting Parameters

    S. No. Particulars Details

    i Amount of charge per hole 17.5 kg

    Booster – slurry explosive 3.5 kg

    Column charge – ANFO (80%) 14 kg

    ii Yield per hole 264.6 ton

    iii expected powder factor yield / hole / charge / hole

    = 15.12 / tone of explosive

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 19

    3.5.6.4 Storage of Explosive

    The explosive will be procured from authorized license supplier through their duly

    licensed explosive vans.

    3.5.7 MINERAL TRANSPORTATION

    Mineral will be transported by trucks. However, 35 ton capacity dumper will be used for

    OB / waste transportation.

    Particulars Production

    (TPD)

    Vehicles Required

    (Trips / day)

    Mineral 700 35

    Waste 1722 50

    3.6 RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY

    SOURCE, MARKETING AREA OF FINAL PRODUCT/S, MODE OF

    TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT

    No raw material will be required for production of lime stone (Kota stone). The final

    product will be sent to consumer based on their demand. The mode of transportation of

    raw material and finished product will be by road. Tippers/ trucks will be used for

    transportation to the end users.

    3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE

    PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED

    Mineral will be utilized and sent for use to different end users. The OB/ waste will be

    used for the maintenance of roads and backfilling.

    Rainwater harvesting will be done using excavated pit void. Water conservation will

    thereby reduce exploitation of groundwater.

    3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY / POWER REQUIREMENT

    AND SOURCE SHOULD BE GIVEN

    3.8.1 WATER

    The total water requirement for the proposed will be 10.0 KLD. The detailed breakup of

    the same is given below:-

    Table 3.8.1: Water Demand

    S. No. Particulars Proposed

    1. Domestic 3

    2. Dust Suppression

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 20

    3. Plantation 7

    Total 10.0

    The water demand will be met from tanker supply from company’s boreholes for

    plantation and dust suppression sump / stored water in the old pit will also be utilized

    enclosed as Annexure.

    3.8.2 POWER

    The total power requirement will be 4.0 kW which will be provided by Jaipur Vidhyut

    Vitran Nigam Limited.

    3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND

    SCHEME FOR THEIR MANAGEMENT/ DISPOSAL.

    About 9,56,652 m3 will be generated at the end of five years period. This waste will be

    utilized in backfilling of the min pit. This waste will be used in maintenance of approach

    roads from time to time.

    The details as tabulated below:-

    Table 3.9 - Waste Generation (Liquid and Solid)

    4.0 SITE ANALYSIS

    4.1 CONNECTIVITY

    Table 4.1 – Connectivity

    Name Distance (km) Direction

    Ramganjmandi RS 6.15 WNW

    SH - 9B 2.7 N

    SH - 9A 6.35 W

    NH - 12 5.3 E

    Activity Quantity of waste Proposed Treatment /

    Disposal

    Mine Waste (TPD) 1722 backfilling

    Municipal

    Solid Waste

    No. of mine workers 95

    Municipality

    sites

    Total Waste Generation @ 0.15

    kg/day approx

    15

    Biodegradable Waste (kg /day) 11

    Non-biodegradable waste (kg /day) 4

    Domestic

    Wastewater

    Wastewater Generation (KLD) 2.0 Septic tank followed

    by soak pit

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 21

    4.2 LAND FORM, LAND USE AND LAND OWNERSHIP

    4.2.1 LANDFORM

    The mining lease area comprises flat terrain with highest and lowest elevation 341 MSL

    and 340 MSL. There is no water body or nallah within the lease area. However, the

    drainage of the lease area is towards east.

    4.2.2 LAND USE

    The land use pattern is given in point no. 1.2.

    4.2.3 LAND OWNERSHIP

    The land as per revenue records is Sawaichak Land i.e. Govt. Waste Land (0.4210 ha.)

    and Kharedari land (4.0848 ha.), the total lease is 4.5058 ha. The map showing land use

    of the lease area (Surface Plan) is enclosed as Annexure.

    4.3 TOPOGRAPHY (ALONG WITH MAP)

    Topographically, the applied area comprises of flat land having gently sloping towards

    east. The highest elevation of the lease area is 341 MSL.

    4.4 EXISTING LAND USE PATTERN (AGRICULTURE, NON-AGRICULTURE,

    FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ)), SHORTEST

    DISTANCES FROM THE PERIPHERY OF THE PROJECT TO PERIPHERY OF

    THE FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO

    SENSITIVE AREAS, WATER BODIES (DISTANCE FROM THE HFL OF THE

    RIVER), CRZ. IN CASE OF NOTIFIED INDUSTRIAL AREA, A COPY OF THE

    GAZETTE NOTIFICATION SHOULD BE GIVEN.

    Table 4.4: Land Use Pattern

    S. No. Land use Category Pre-operational

    (Ha.)

    Land-use after

    5th

    year (Ha.)

    End of the

    life of mine

    1 Pits -- 2.4707 4.2567*

    2 Dump area -- -- --

    3 Roads -- -- --

    4 Infrastructure -- -- --

    5 Mineral storage -- -- --

    6 Top soil storage -- -- -

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 22

    7 Plantation -- 0.2491 0.2491

    8 Un-worked 4.5058 1.7860 --

    Total 4.5058 4.5058 4.5058

    4.5 EXISTING INFRASTRUCTURE

    The same has been given in point no. 3.8 and 4.0.

    4.5.6 BASIC AMENITIES

    The details of basic amenities like schools, hospitals and community center located

    nearby the mine site are mention below:-

    Table 4.5.6: Basic Amenities

    Name Distance (km) Direction

    (From Lease Boundary)

    Govt. Upper Primary School, Kundayla 3.3 NW

    Government Upper Primary School, Lakhariya 4.0 SSE

    Government Girls Upper Primary School Suket 4.3 ENE

    Government Sr. Sec. School, Suket 4.8 ENE

    Government Upper Primary School Suket 4.5 ENE

    Govt. Girls Senior Secondary School, Ramganj

    Mandi 5.57 WNW

    New Happy School, Ramganj Mandi 5.89 WNW

    Govt. Senior Secondary School, Lakhariya 4.9 SSE

    Bright Technical PG College, Ramganj Mandi 5.46 W

    (Source: All distances are taken with respect to Google Earth)

    4.6 SOIL CLASSIFICATION

    According to the soil taxonomical classification, there are six categories of classification

    i.e. i. Order (the broadest category) ii. Suborder, iii. Great group, iv. Subgroup, v. Family

    and vi. Series (the most specific category). The soil of the Rajasthan state have been

    grouped under five orders, namely, Aridosols, Alfisols, Entisols, Inceptisols and

    Vertisols. Soils have further been subdivided at suborder and great group levels under

    these five orders as shown below.

    Table 4.6: Classification of Soils found in Rajasthan

    S. No. Order Suborder Great group Occurrence

    1. Aridisols Orthids a. Camborthids Parts of Jalore, Churu, Jodhpur, Pali, Barmer, Sikar

    and Jhunjhunu districts.

    b. Calciorthids Parts of Jalore, Jodhpur, Pali, Barmer, Nagaur, Sikar,

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 23

    Churu, Sriganganagar and Jhunjhunu districts.

    c. Salorthids Found scattered in Ghaggar floodplain in

    Sriganganagar; Near sambhar, Pachpadra,

    Deedwana lakes, little Rann of Kutch area in Jalore

    and in Barmer districts

    d. Paleorthids Scattered and cover a small area in Jaisalmer,

    Barmer and Nagaur districts.

    2. Alfisols Ustalfs a. Haplustalfs Eastern and south-eastern part of Rajasthan in

    Udaipur, Chittorgarh, Bhilwara, Ajmer and Jaipur

    districts.

    3. Entisols Psamments a. Torripsamments Cover upto 80% of the area at many places in

    western Rajasthan. Also cover a part of Jaipur, Alwar

    and Ajmer districts.

    b. Quartzipsamments Small part of Jaisalmer and barmer districts.

    Fluvents c. Torrifluvents Occur in Ghaggar floodplain area of Sriganganagar

    district.

    d. Ustifluvents Occur on the north-eastern and eastern portion of

    Rajasthan covering parts of Alwar and almost whole

    of Bharatpur districts.

    4. Inceptisols Ochrepts a. Ustochrepts Occur along the foothill slopes and cover extensive

    areas in Bhilwara, Udaipur, north-eastern

    Sawaimadhopur and in parts of Sirohi, Pali, Jaipur

    and Chittorgarh districts.

    5. Vertisols Usterts a. Chrom usterts Parts of Bundi, Kota & Jhalawar districts in south-

    eastern part of Rajasthan and to a lesser extent in

    Chittorgarh, Dungarpur, Banswara & Bharatpur

    districts.

    b. Pellusterts Cover a large are of Bundi, Kota, Jhalawar,

    Chittorgarh, Dungarpur, Banaswara and Bharatpur

    districts.

    One day monitoring of environmental attributes was carried out. The monitored values

    was used as a baseline data to identify, evaluate and predict the impacts due to

    proposed mining activities in the surrounding areas for preparing the Environmental

    Management Plan accordingly for the proposed activity.

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 24

    4.8 SOCIAL INFRASTRUCTURE AVAILABLE

    The well established social infrastructure like hospitals, educational facilities, temple,

    community centre, roads, bridges, telecommunication and others similar are available/

    existing within 15 km radius which is tabulated in point no. III of Form – 1.

    5.0 PLANNING BRIEF

    5.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES,

    TRANSPORTATION ETC.) TOWN AND COUNTRY PLANNING/

    DEVELOPMENT AUTHORITY CLASSIFICATION.

    It is a mining industry in which open cast semi-mechanized method will be practiced.

    The proposed mine will produce with the capacity of 2,10,118 TPA of ROM. It will be

    used as building material. Mineral will be transported by trucks/ tippers to final

    consumers.

    5.2 POPULATION PROJECTION

    The detail demographic profile of villages located in the study area is given in point no.

    4.7.7.

    5.2 LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT ETC.)

    As per year wise afforestation programme, plantation is proposed. The main aim of the

    green belt development is to improve the ecosystem to a maximum possible extent by

    designing the green cover with the same native species. The year wise plantation

    programme in five years is given below:-

    Table 5.2:- Green Belt Development Programme (Inside the lease area)

    The map showing greenbelt plan of the lease area is enclosed as Annexure.

    Table 5.2 i: Suggested Tree Species

    Year Un-worked Area Waste Dump

    (Outside)

    Inside Dump

    (Reclaimed Area)

    Top Soil

    Dumps

    Total

    Area

    (Ha.)

    No. of

    Trees

    Area

    (Ha.)

    No. of

    Trees

    Area

    (Ha.)

    No. of

    Trees

    Area

    (Ha.)

    No. of

    Trees

    Area

    (Ha.)

    No. of

    Trees

    I 0.04982 50 -- -- -- -- -- -- 0.04982 50

    II 0.04982 50 -- -- -- -- -- -- 0.04982 50

    III 0.04982 50 -- -- -- -- -- -- 0.04982 50

    IV 0.04982 50 -- -- -- -- -- -- 0.04982 50

    V 0.04982 50 -- -- -- -- -- -- 0.04982 50

    VI year onwards -- -- -- -- 1.2378 1238 -- -- 1.2378 1238

    Total 0.2491 250 -- -- 1.2378 1238 -- -- 1.4869 1488

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 25

    TREE

    S. No Species Name Binomial Name

    1 Mahua Madhuca indica

    2 Peepal Ficus religiosa

    3 Sal Shorea robusta

    4 Shesham Delbergia sissoo

    5 Gulmohar Delonix regiosa

    6 Siris Albizzia lebbek

    7 Palas Butea monosperma

    8 Satani Alstonia scholaris

    9 Neem Azadirachta indica

    10 Ashoka Ployalthia longifolia

    11 Mahaneem Melia azadirachta

    12 Khajoor Phoenix dactylifera

    13 Kadam Anthosephalus cadamba

    14 Bottle Brush Callistemon citrinus

    15 Shoe babool Luceana leucopholea

    16 Vilayati kikar Acacia farmesiana

    Table 5.2 ii. Suggested Shrub / Herb Species

    S. No Species Name Binomial Name

    1 Munja grass Saccharum munja

    2 Vilayati Babool Prosopis juliflora

    3 Kans grass Saccharum spontaneum

    4 Arandi Ricinus cummunis

    5 Kaner Nerium Indicum

    6 Peeli Kaner Thevetia peruviana

    7 "Red (Yellow, Wild) Sage" Lantana camara

    8 Buffel Grass Cenchrus ciliaris

    9 Sarphonka Tephrosia hamiltonii

    10 Makara or crowfoot grass Dactyloctenium aegyptium

    11 Bui Aerva tomentosa

    5.3 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL AND SOCIAL)

    On the basis of the preliminary site visit, the infrastructure demand in the nearby villages

    will be assessed on the basis of need and priority. Job opportunities are limited and

    newer avenues of skill development for income generation are required.

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 26

    5.4 AMENITIES/ FACILITIES

    Following facilities are provided for the smooth working of the mine:-

    Table 5.4: Facilities provided to workers

    S. No. Activities Capital Cost

    *Rs In thousands

    Recurring Cost

    *Rs In thousands

    1. Shelter 25.0 5.0

    2. Health Facility 40.0 20.0

    3. Drinking Water 10.0 10.0

    4. Sanitation Facilities 25.0 10.0

    5. Education 25.0 15.0

    Total 125.0 60.0

    6.0 PROPOSED INFRASTRUCTURE

    6.1 INDUSTRIAL AREA (PROCESSING AREA)

    The area is very well connected by road network to the mine, district headquarter etc.

    The area is self sufficient to cater the needs of the project. Hence, no infrastructure is

    proposed.

    6.2 RESIDENTIAL AREA (NON PROCESSING AREA)

    As the local person will be given employment, no residential area/ housing is proposed.

    6.3 GREEN BELT

    The same has been given in point 5.2.

    6.4 SOCIAL INFRASTRUCTURE

    Local population will be employed by the project proponent in the Mine. Further, indirect

    means of earnings have been created in the area of contractual jobs, vehicle driving,

    shops, construction etc. Therefore this project brought a positive impact on the adjoining

    society. The proponent will spend 1% of profit for the development of the area i.e.

    medical facilities, schools, temples and other social work. There is well developed social

    infrastructure in the area detail has been tabulated in section – III of Form – 1.

    6.5 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL / METRO /

    WATER WAYS ETC.)

    Given in point no. 4.0

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 27

    6.6 DRINKING WATER MANAGEMENT (SOURCE AND SUPPLY OF WATER)

    The drinking and other water demand will be sourced by the tanker supply.

    The water demand is given below:-

    6.7 SEWERAGE SYSTEM

    Toilet facilities will be provided. The generated sewage will be channelized to septic tank

    followed by soak pit.

    6.8 INDUSTRIAL WASTE MANAGEMENT

    There will be no industrial waste generation due to proposed project.

    6.9 SOLID WASTE MANAGEMENT

    The same has been given in point no. 3.9.

    6.10 POWER REQUIREMENT AND SUPPLY / SOURCE

    The total power requirement for the proposed will be 4.0 kW. This is being provided by

    Jaipur Vidhyut Vitran Nigam Limited.

    7.0 REHABILITATION AND RESETTLEMENT (R & R PLAN)

    7.1 POLICY TO BE ADOPTED (CENTRAL/ STATE) IN RESPECT OF THE

    PROJECT AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND

    OUSTEES AND LANDLESS LABOUR (A BRIEF OUTLINE TO BE GIVEN)

    There is no habitation in the lease area, therefore rehabilitation & resettlement plan is

    not required/ applicable.

    Daily Water Demand – 10.0

    Domestic – 3.0 KLD Mining – 7.0 KLD

    (Dust Suppression + Plantation)

    Septic Tank followed by soak pit

    2.0 KLD

    Consumption – 1.0 KLD

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 28

    8.0 PROJECT SCHEDULE AND COST ESTIMATES

    8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF

    COMPLETION (TIME SCHEDULE FOR THE PROJECT WILL BE GIVEN).

    The project will commence once Environmental Clearance and other necessary

    approvals will be obtained from the concern departments.

    Table 8.1: Expected Time Schedule for the Project

    S.

    No.

    Particulars Time Schedule

    (in month)*

    Remark If any

    1st

    2nd

    3rd

    4th

    1. Environmental Clearance

    2. Consent To Establish Project Establishment Period

    3. Consent To Operate Production Start Period

    *Time line may vary; subjected to rules & regulation / & other unforeseen circumstances

    8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF

    ECONOMIC VIABILITY OF THE PROJECT

    The proposed project cost will be Rs. 2.0 crore.

    Table 8.2 i: Estimated Project Cost and Economic Viability

    S. No. Particulars Details

    1. Estimated Project Cost (Fixed cost) 2.0 Cr. (including operational cost)

    2. Operation coast Rs. 5 – 10 / sq.feet

    3. Market cost Rs. 15 – 30 / sq.feet

    Expenditure Proposed for Environmental protection activities:-

    It is proposed to invest an amount of Rs. 1.0 Lac per annum towards environmental

    action plan and the details of the same are given below:-

    Table 8.2 ii: Expenditure Proposed for Environmental Protection Activities

    S. No. Description of Item Recurring Cost (Rs)

    1 Air Pollution Control - Water Sprinkling 20,000

    2 Water Pollution Control 10,000

    3 Environmental Monitoring and Management 50,000

    4 Green Belt Development 20,000

    Total 1,00,000/-

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 29

    9.0 ANALYSIS OF PROPOSAL

    9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE

    BENEFITS TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF

    ANY, IN THE AREA

    No tribal population is residing in the study area. There will be social benefits from the

    mining operations. The core benefit of the project is the availability of stone. The

    underlying benefits through the proposed project are:-

    Table 9.1 i: Financial & Social Benefits

    S. No. Activities

    1. It aims to provide additional employment to the local population of the proposed study area.

    Direct employment to locals: 95 Approx.

    Indirect Employment to locals : 30 Approx.

    2. The PP proposes to construct toilets and Rain Water Harvesting structures in the

    Government schools of nearby villages

    3. Health Camps will be organized for the local people.

    The appropriate amount of CSR is proposed to be Rs. 2.0 lacs capital cost and Rs.10,000/- as

    recurring cost till the life of the mine.

    As a Corporate Social Responsibility, following activities along with budget provision are

    proposed for improving the conditions in and around the project area.

    Table 9.1.ii: Corporate Social Responsibility

    S. No. Activity Capital Cost

    (in Rs.)

    Recurring Cost

    (In Rs.)

    1. Health Check Up Camps 25,000 2,500

    2. Assistance to Local Schools, Scholarships to Students 60,000 3,000

    3. Sanitations and Drinking Water Facilities 25,000 2,500

    4. Vocational Training to Persons for Income Generation 30,000 1,000

    5. Women Empowerment & Development Programme 60,000 1,000

    Total 2,00,000 10,000

    Table 9.1 iii: Action Plan

    S. No. Action Plan Expenditure Cost (in Rs.) Recurring

    Cost (in Rs.) Year I Year II Year III Year IV Year V

    1. Health Check up camps 20,000 5,000 5,000 5,000 5,000 2,500

    2. Assistance to local schools,

    scholarships to students

    30,000 5,000 5,000 5,000 5,000 3,000

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 30

    3. Sanitations and drinking water

    facilities

    20,000 5,000 5,000 5,000 5,000 2,500

    4. Vocational training to persons

    for income generation

    5,000 5,000 5,000 5,000 5,000 1,000

    5. Women Empowerment &

    Development Programme

    25,000 5,000 5,000 5,000 5,000 1,000

    Total 1,00,000 25,000 25,000 25,000 25,000 10,000

    Total 2,00,000

    10.0 BASELINE ENVIRONMENT

    The baseline environment quality represents the background environmental scenario of

    various environmental components such as air, noise, land, ecological and socio-

    economic status of the study area. Details of the sampling locations are given below:

    Table 10.0 : Monitoring Locations

    S.

    No.

    Location Latitude

    Longitude

    Distance (km) Direction Core /

    Buffer Zone

    Environmental

    Components From Lease Boundary

    1 ML No. 05/

    2013

    24037’43.32”

    75059’42.15”

    -- -- Core Zone Air (A),

    Water (GW),

    Noise (N),

    Soil (S)

    2 Vill.

    Satalkhei

    24039’05.65”

    75000’02.46”

    1.7 NNE Buffer Zone

    3 Vill. Narli 24037’38.00”

    75000’32.46”

    1.6 SE Buffer Zone

    4 Vill.

    Amerpura

    24037’50.07”

    75058’15.24”

    2.2 WSW Buffer Zone

    5 Vill.

    Kumbhkot

    24037’00.03”

    75000’08.99”

    2.6 SSE Buffer Zone

    10.1 Climate

    Kota has a semi arid climate with high temperatures throughout the year. Summers are

    long, hot and dry, starting in late March and lasting till the end of June. The monsoon

    season follows with comparatively lower temperatures, but higher humidity and frequent,

    torrential downpours. The monsoons subside in October and temperatures rise again.

    The brief, mild winter starts in late November and lasts until the last week of February.

    Temperatures hover between 26.7°C (max) to 12°C (min).The average annual rainfall in

    the Kota district is 660.6 mm. Most of the rainfall can be attributed to the southwest

    monsoon which has its beginning around the last week of June and may last till mid-

    September. Pre-monsoon showers begin towards the middle of June with post-monsoon

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 31

    rains occasionally occurring in October. The winter is largely dry, although some rainfall

    does occur as a result of the Western Disturbance passing over the region.

    10.2 AIR ENVIRONMENT

    The prime objective of the baseline air monitoring was to evaluate the existing air quality

    of the area. This will also be useful for assessing the conformity to standards of the

    ambient air quality during the operation of the proposed mine.

    Field monitoring studies for 24 hourly frequencies was carried out to evaluate the base

    line status of the project site.

    Wind Rose Pattern

    One day monitoring of environmental attributes was carried out. The monitored values

    was used as a baseline data to identify, evaluate and predict the impacts due to

    proposed mining activities in the surrounding areas for preparing the Environmental

    Management Plan accordingly for the proposed activity.

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 32

    Table 10.2 i: Ambient Air monitoring Instruments

    Instrument Make Model

    No.

    Instrument

    Identification No.

    Range and Sensitivity

    Respirable Dust

    Sampler (RDS)

    M/s

    Envirotech

    Instruments

    Pvt. Ltd

    APM-

    450BL

    SAL/RDS/01 0.40 – 1.5 m3/min

    ±0.02m3/min

    (PM10)

    0 – 3 LPM

    ± 0.2

    LPM(gases)

    Fine Particulate

    Sampler (FPS)

    APM

    550

    DTC-205 ±0.03 DGM m3

    (PM2.5)

    Table 10.2 ii: Testing Method to be followed for Ambient Air Quality

    Particular Testing Method to be Followed

    Ambient Air Monitoring Parameter

    A PM10 IS-5182 (part – 23) 2006

    B PM2.5 RTI (Research Triangle Institute) (Gravimetric Ana Revision-07 Aug14-

    2003)

    C SO2 (Sulfur Dioxide) IS 5182 (Part – II) 2001, with Improved West & Gaeke Method

    D NO2 ( Oxides of

    Nitrogen)

    Modified Jacobs – Hochheiser Method / Arsenite Method (IS 5182 Part 6)

    2011

    E Carbon Monoxide NDIR Spectroscopy method

    Table 10.2 iii: Ambient Air Quality Status

    S. No. Parameters Units NAAQS 2009 A1 A2 A3 A4 A5

    1. PM10 µg/m3 100 76.3 42.5 43.5 46.7 40.8

    2. PM2.5 µg/m3 60 42.8 23.1 21.6 24.5 21.3

    3. SO2 µg/m3 80 8.9 5.2 5.0 5.3 5.1

    4. NO2 µg/m3 80 36.7 16.5 14.3 15.9 14.9

    5. CO µg/m3 2000 892 423 512 431 436

    Ambient air monitoring results were found within the standards (NAAQS).

    10.3 WATER ENVIRONMENT

    The purpose of this study is to:-

    � Assess the water quality characteristics;

    � Predict the likely impacts on water quality due to the project and related activities.

    Table 10.3: Water Quality

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 33

    S.

    No.

    Parameter Drinking Water Standard

    (IS: 10500)

    GW1 GW2 GW3 GW4 GW5

    Desirable

    Limits

    Permissible

    Limits

    1 pH 6.5 – 8.5 NR 7.26 7.23 7.65 7.45 7.56

    2 Color (Hazen) < 5 < 25

  • PROJECT : LIME STONE (BUILDING STONE)

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014

    Inference:

    S.No. Location Name

    1. Mine site

    2. Vill. Satakheri

    3. Vill. Narli

    4. Vill. Amarpura

    5. Vill Kumbhkot

    WQI: Water Quality Index in range between; 101

    *Ref. 1. Ramakrishnaiah, et. al., 2009; Data in parenthesis is percentage change

    Anticipated Health risks associated due to ground water consumption &

    S.No. Contaminant

    1. TH Scaling of skin and hair loss

    2. TDS unpalatable taste

    3 Sulphate Gastrointestinal distress / diarrhea

    4 Chlorides Salty taste (impact on osmo

    impaired fluid dynamics etc)

    5. Fluoride Bone disease (pain and tenderness

    bones); Children may get mottled teeth

    Ref. USEPA; CPCB New Delhi

    10.4 NOISE ENVIRONMENT

    The main objective of noise monitoring in the study area is to establish the baseline noise

    levels and assess the impact of the total noise expected to

    operations in the project site.

    Instant sound level meter is used for the collection of data related to noise at an interval of

    one hour per reading. Noise level for 24 hours was conducted in a day. The details of the

    instrument used for the sampling are as given below:

    0

    50

    100

    150

    200

    Mine site

    LIME STONE (BUILDING STONE)

    M/s STATUS IMPEX (P) LIMITED

    169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    34

    WQI* Failed Parameters

    POOR (TDS, Fluoride, TH, Biogenic salts)

    POOR (TDS, Fluoride, TH, Biogenic salts)

    POOR (TDS, Fluoride, TH, Biogenic salts)

    POOR (TDS, Fluoride, TH, Biogenic salts)

    POOR (TDS, Fluoride, TH, Biogenic salts)

    WQI: Water Quality Index in range between; 101-200 hence POOR;

    *Ref. 1. Ramakrishnaiah, et. al., 2009; Data in parenthesis is percentage change

    Table

    Anticipated Health risks associated due to ground water consumption &

    Health risks Mitigation Measure & Management

    Scaling of skin and hair loss • Water pretreatment like filtration is

    required before consumption

    • Reverse Osmosis, activated

    carbon filters

    • Activated alumina, Nalgonda

    • Reverse Osmosis, Ion exchange

    water softeners

    unpalatable taste

    Gastrointestinal distress / diarrhea

    Salty taste (impact on osmo-regulation /

    impaired fluid dynamics etc)

    Bone disease (pain and tenderness of the

    bones); Children may get mottled teeth

    Ref. USEPA; CPCB New Delhi

    NOISE ENVIRONMENT

    The main objective of noise monitoring in the study area is to establish the baseline noise

    levels and assess the impact of the total noise expected to be generated during the project

    operations in the project site.

    Instant sound level meter is used for the collection of data related to noise at an interval of

    one hour per reading. Noise level for 24 hours was conducted in a day. The details of the

    instrument used for the sampling are as given below:-

    Mine site Vill.

    Satakheri

    Vill. Narli Vill.

    Amarpura

    Vill

    Kumbhkot

    water quality index

    PRE - FEASIBILTY REPORT

    % change

    (TDS, Fluoride, TH, Biogenic salts) (+ 6 to + 188)

    (TDS, Fluoride, TH, Biogenic salts) (+ 36 to + 264)

    (TDS, Fluoride, TH, Biogenic salts) (+ 10 to + 144)

    (TDS, Fluoride, TH, Biogenic salts) (+ 19 to + 161)

    Biogenic salts) (+ 3 to + 137)

    Anticipated Health risks associated due to ground water consumption & its mitigation

    Mitigation Measure & Management

    Water pretreatment like filtration is

    required before consumption

    Reverse Osmosis, activated

    carbon filters

    Activated alumina, Nalgonda

    Reverse Osmosis, Ion exchange

    water softeners

    The main objective of noise monitoring in the study area is to establish the baseline noise

    be generated during the project

    Instant sound level meter is used for the collection of data related to noise at an interval of

    one hour per reading. Noise level for 24 hours was conducted in a day. The details of the

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 35

    Table 10.4 i: Noise (Sound) Measuring Instrument

    Instrument Make Model No. Instrument Identification

    Detection Limit

    Integrated Sound Level Measurement

    Instrument Standard Accessories

    Lutron SL-4001 SAL/NOISE/INT/01 Lo 30-80dB

    Hi 80-130dB

    Table 10.4 ii: Testing Method to be followed

    Particular Testing Method to be Followed

    Noise Level Measurement

    A Noise Level in dB (A) for continuous

    24 hours at 1 hour interval

    Operational Manual of Noise level Meter, Model No.

    DT - 805 issued by Mextech

    Table 10.4 iii: Noise Monitoring

    Station Name N1 N2 N3 N4 N5

    06.00 48.9 43.5 46.5 45.9 47.9

    07.00 52.3 45.6 48.8 48.5 49.7

    08.00 54.5 46.9 49.9 49.3 50.3

    09.00 56.9 47.3 50.4 46.7 51.2

    10.00 58.7 48.9 48.9 48.3 49.8

    11.00 60.3 50.2 47.8 46.7 48.3

    12.00 61.5 48.8 46.9 43.9 47.2

    13.00 58.7 47.3 42.9 47.3 43.5

    14.00 59.3 46.3 44.5 46.9 45.8

    15.00 57.0 44.8 46.3 45.3 49.3

    16.00 59.4 46.3 48.7 46.9 47.3

    17.00 61.4 42.8 50.2 44.0 49.9

    18.00 63.0 48.6 46.9 41.6 50.2

    19.00 61.9 49.3 44.3 38.9 46.2

    20.00 58.7 45.5 41.9 36.4 44.7

    21.00 56.3 42.1 40.3 35.0 41.6

    22.00 54.2 40.9 38.9 36.9 38.5

    23.00 48.9 38.9 36.4 35.4 35.6

    24.00 42.3 36.0 35.1 35.1 35.0

    01.00 38.5 35.2 35.0 35.0 35.2

    02.00 36.3 35.0 36.3 35.6 36.9

    03.00 37.0 35.6 38.9 36.9 38.9

    04.00 43.5 38.9 40.2 38.6 41.6

    05.00 47.0 40.3 42.9 42.5 43.7

    Leq day dB(A) 59.2 47.1 47.4 45.9 47.8

    Leq Night dB(A) 47.5 38.2 38.8 37.8 38.8

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 36

    Inference:

    Noise levels were found within the prescribed standards.

    10.5 LAND ENVIRONMENT

    The objectives of the soil sampling are:-

    � To determine the baseline soil characteristics of the study area;

    � To determine the impact of existing as well as proposed activity on soil

    characteristics and;

    � To determine the impact on soil more importantly with agriculture production point of

    view.

    Table 10.5: Soil Analysis

    S.No. Parameters Units S1 S2 S3 S4 S5

    1 Texture - Sandy Clay Sandy Clay Sandy Clay Clay Sandy

    2 Particle size

    Distributions

    Sand % 52 50 36 22 50

    Silt % 16 12 24 30 16

    Clay % 32 38 40 48 34

    3 Appearance (Color) -- Light Brown Light Black Light Brown Brown Brown

    4 Sodium as Na mg/100g 1.23 1.26 1.13 1.14 1.09

    5 pH (10% Slurry) - 7.42 7.39 7.23 7.51 7.39

    6 Conductivity µS/cm 175 198 183 212 165

    7 Bulk density g/cc 1.32 1.36 1.25 1.12 1.46

    8 Porosity % v/v 20 26 31 42 12

    9 Total Organic Matter % 0.74 0.81 0.89 0.94 0.53

    10 Nitrogen as N mg/100g 165 204 215 264 132

    11 Potassium as K mg/100g 56 72 88 112 34

    12 Phosphorus as P mg/100g 29 59 72 68 22

    13 Zinc as Zn mg/ kg 2.69 4.2 4.66 4.36 1.31

    14 Cadmium as Cd mg/ kg 0.04 0.06 0.09 0.06 0.02

    15 Chlorides as Cl mg/100g 1.23 1.26 1.06 1.68 0.68

    16 Alkali Metals mg/ kg 0.26 0.23 0.22 0.36 0.2

    17 Permeability cm/ h 7.3 7.3 5.4 4.6 7.3

    18 Water Holding Capacity % 16.5 19.2 26.9 40 11.6

    19 Copper as Cu mg/ kg 0.06 0.13 0.06 0.06 0.03

    20 Iron as Fe mg/ kg 0.08 0.16 0.12 0.11 0.08

    21 Lithium mg/ kg

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 37

    10.6 BIOLOGICAL ENVIRONMENT

    Natural flora and fauna are important features of environment. They are organized into

    communities with mutual dependencies among their members and show various

    responses and sensitivities to outside influences. Therefore, nature of development and

    baseline characteristics of terrestrial flora and fauna around the site of existing/proposed

    activities is required to be assessed.

    The primary/ secondary study is to characterize the environmental components like flora

    and fauna, to assess the biological diversity of the region. Flora and fauna can be used

    for biological surveillance in assessing the environmental status.

    Flora: Core Zone

    Trees: Few trees were observed during the site visit in core zone.

    S. No. Common Name Botanical Name Family Core/ Buffer Zone

    1 Neem Azadirachta indica Meliaceae Core Zone

    2 Kiker or Babool Acacia nilotica Leguminosae Core Zone

    Shrubs

    S. No. Common Name Botanical Name Family Core/ Buffer Zone

    1 Kair Capparis decidua Capparaceae Core Zone

    2 Aak Calotropis procera Asclepiadaceae Core Zone

    3 Vilayati Babool Prosopis juliflora Fabaceae Core Zone

    4 Ber Zizyphus nummularia Rhamnaceae Core Zone

    5 Oontkateli Echinops echinatus Asteraceae Core Zone

    6 Bui Aerva tomentosa Amaranthaceae Core Zone

    Herbs

    S. No. Common Name Botanical Name Family Core/ Buffer Zone

    1 Kantakari Solanum xanthocarpum Solanaceae Core Zone

    2 Makara or crowfoot grass Dactyloctenium aegyptium Poaceae Core Zone

    3 Sarphonka Tephrosia purpurea Fabaceae Core Zone

    4 Bhurat Cenchrus biflorus Poaceae Core Zone

    5 Bermuda Grass or Doob Cynodon dactylon Poaceae Core Zone

    FLORA : Buffer Zone

    Trees

    S. No. Common Name Botanical Name Family Core/ Buffer Zone

    1. Siris tree Albizia lebbeck Fabaceae Buffer Zone

    2. Neem Azadirachta indica Meliaceae Buffer Zone

    3. Gum Arabic tree Acacia senegal Fabaceae Buffer Zone

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 38

    4. Khejri Prosopis cineraria Fabaceae Buffer Zone

    5. Kiker or Babool Acacia nilotica Leguminosae Buffer Zone

    6. Shisham Dalbergia sissoo Fabaceae Buffer Zone

    7. Ardu Ailanthus excelsa Simaroubaceae Buffer Zone

    8. Pipal Ficus relegiosa Moraceae Buffer Zone

    9. Reonja or Safed babool Acacia leucophloea Fabaceae Buffer Zone

    10. Bargad Ficus bengalenesis Moraceae. Buffer Zone

    11. Kankera Maytinus emarginata Celastraceace Buffer Zone

    12. Palash Butea monosperma Fabaceae Buffer Zone

    13. Indian Elm Holoptelea integrifolia Ulmaceae Buffer Zone

    14 Mahua Madhuca longifolia Sapotaceae Buffer Zone

    15 Kassod Tree Cassia samia Caesalpiniaceae Buffer Zone

    16 Safeeda Eucalyptus Myrtaceae Buffer Zone

    Shrubs

    S. No. Common Name Botanical Name Family Core/ Buffer Zone

    1. Ber Zyzipus nummularia Rhamnaceae Buffer Zone

    2. Dandathor Euforbia caducifolia Euphorbiaceae Buffer Zone

    3. Gajar grass Parthenium hysterophorus Asteraceae Buffer Zone

    4. Vilayati Babool Prosopis juliflora Fabaceae Buffer Zone

    5. Khimp Leptadenia pyrotechnica Apocynaceae Buffer Zone

    6. Gokharu Tribulus terrestris Zygophyllaceae Buffer Zone

    7. Damasa Tephrosia purpurea Fabaceae Buffer Zone

    8. Kaner Nerium oleander Apocynaceae Buffer Zone

    9. Arandi Ricinus cummunis Euphorbiaceae Buffer Zone

    10. Kair Capparis decidua Capparaceae Buffer Zone

    11. Aak Calotropis procera Asclepiadaceae Buffer Zone

    12 Munja grass Saccharum munja Poaceae Buffer Zone

    Herbs

    S. No. Common Name Botanical Name Family Core/ Buffer Zone

    1. Fiddler's spurge Euphorbia granulata Euphorbiaceae Buffer Zone

    2. Bermuda Grass or Doob Cynodon dactylon Poaceae Buffer Zone

    3. Bui Aerva tomentosa Amaranthaceae Buffer Zone

    4. Satyanasi Argemone maxicana Papaveraceae Buffer Zone

    5. Bhurat Cenchrus biflorus Poaceae Buffer Zone

    6. Buffel Grass Cenchrus ciliaris Poaceae Buffer Zone

    7. Bhurat Cenchrus biflorus Poaceae Buffer Zone

    8. Crowfoot grass Dactyloctenium aegyptium Poaceae Buffer Zone

  • PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT

    APPLICANT : M/s STATUS IMPEX (P) LIMITED

    DOCUMENT NO.: EESPL/ SIPL-169/ 002/ 169-EC/ MINE/ 2014

    ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR

    SEPTEMBER’ 2014 39

    9. Kantakari Solanum xanthocarpum Solanaceae Buffer Zone

    10. Ghamra Tridex procumbens Asteraceae Buffer Zone

    11. Barrut grass Sorghum halepense Poaceae Buffer Zone

    12. Motha Cyperus rotundus Cyperaceae Buffer Zone

    13. Gokharu herb Tribulus terrestris Zygophyllaceae Buffer Zone

    14. Sarphonka Tephrosia purpurea Fabaceae Buffer Zone

    15 Crabgrass Digitaria sanguinalis Poaceae Buffer Zone

    16 Chakvad Cassia Tora Fabaceae Buffer Zone

    17 Cocklebur or chota gokhuru Xanthium strumarium Asteraceae Buffer Zone

    FAUNA:

    Core Zone

    S. No. Common name Binomial name Family Schedule

    IW(P)A/ IUCN

    1 Pisces

    No aquatic land observed at the site of study area during survey.

    2 Amphibia

    No amphibian observed during survey of site visit in core zone.

    3. Reptilia

    1 Garden Lizard Calotes versicolor Agamidae LC

    4. Avis or Avifuana

    1 Common Bulbul Pycnonotus barbatus Pycnonotidae IV

    2 Rose-ringed Parakeet Psittacula krameri Psittacidae IV

    3 House crow Corvus splendens Corvidae V

    5. Mammalia

    1 Five stripped palm squirrel