    The Pre-Tender Stage

    Health and Safety PlanBy

    John Johnston AIIRSM

    Health and Safety for Beginners

    www.healthandsafetytips.co.uk

  • 7/29/2019 Pre TenderPlan (1)

    2/11

    www.healthandsafetytips.co.uk

    What is the Pre-Tender Stage Health

    and Safety Plan?

    Essentially the plan is a collection ofinformation about the significant health andsafety risks of the construction project which the

    Principal Contractor will have to manage duringthe construction phase.

    The degree of detail and the time and effortinvolved in preparing it should be in proportionto the nature, size and level of risks involved inthe project.

  • 7/29/2019 Pre TenderPlan (1)

    3/11

    www.healthandsafetytips.co.uk

    Who Supplies the Information?

    The Client: will provide information relevant to

    health and safety to the Planning Supervisor. E.g.

    existing drawings, surveys of the site or premises,

    information on the location of services, etc. Designers: will provide information about risks which

    cannot be avoided at the design stage and will have to

    be controlled by the Principal Contractor and other

    contractors. Typically provided on drawings, written

    specifications or in outline method statements.

  • 7/29/2019 Pre TenderPlan (1)

    4/11

    www.healthandsafetytips.co.uk

    What is the Purpose of the Pre-

    Tender Health and Safety Plan?

    During its development, the plan can provide a focus atwhich the health and safety considerations of design arebrought together under the control of the PlanningSupervisor.

    The plan plays a vital role in the tender documentation.Prospective Principal Contractors are made fully awareof the projects health, safety and welfare requirements,giving a level playing field on which to provide tendersubmissions.

    The plan provides a template against which differenttender submissions can be measured.

  • 7/29/2019 Pre TenderPlan (1)

    5/11

    www.healthandsafetytips.co.uk

    Who Prepares the Plan?

    The Planning Supervisor is responsible for

    ensuring that the pre-tender stage health and

    safety plan is prepared.

    The Planning Supervisor is not necessarily

    responsible for producing the plan directly, but

    he must ensure that it is prepared.

  • 7/29/2019 Pre TenderPlan (1)

    6/11

    www.healthandsafetytips.co.uk

    What Should the Contents of the

    Pre-Tender Stage Health and Safety

    Plan Be? Nature of the project (location, nature of

    construction work, etc)

    The existing environment i.e. services,surrounding land use, ground conditions, etc.

    Existing drawings (available drawings and healthand safety file if there is one)

    The design (information on the significant riskwhich cannot be avoided)

    Wh Sh ld h C f h P

  • 7/29/2019 Pre TenderPlan (1)

    7/11

    www.healthandsafetytips.co.uk

    What Should the Contents of the Pre-

    Tender Stage Health and Safety Plan

    Be? Construction materials (health hazards which cannot be avoided) Site-wide elements (positioning of site access or egress points,

    location of unloading, layout and storage areas, traffic routes,etc)

    Overlap with the clients undertaking i.e. where work takes placeat the clients premises.

    Site rules i.e. emergency procedures, permit-to-work rules, etc setby the client when work takes place at the clients premises.

    Continuing liaison (procedures for dealing with design workprepared for construction phase)

  • 7/29/2019 Pre TenderPlan (1)

    8/11

    www.healthandsafetytips.co.uk

    Other Considerations for the Pre-

    Tender Health and Safety Plan

    A general description of the construction work that isin the project

    Details of any time scales, including the time scales forany intermediate stages of the project

    Details of any foreseeable risks to the health and safetyof anyone carrying out construction work on theproject

    Any other information needed by a contractor to show

    either that they are competent, or that they haveallocated enough resources to health and safety for theproject

  • 7/29/2019 Pre TenderPlan (1)

    9/11

    www.healthandsafetytips.co.uk

    Other Considerations for the Pre-

    Tender Health and Safety Plan

    Such information that the planning supervisor

    has, or can easily obtain, that a contractor would

    need in order to meet any of the requirements

    imposed on them by the Regulations

    Information that any contractor will need to

    know about any welfare provisions that will be

    required.

  • 7/29/2019 Pre TenderPlan (1)

    10/11

    www.healthandsafetytips.co.uk

    What Next?

    Once the Principal Contractor has been

    appointed, the Planning Supervisor hands the

    health and safety plan over to them.

    It is then their responsibility to develop it into a

    working document that will assist in the health

    and safety management of the project.

  • 7/29/2019 Pre TenderPlan (1)

    11/11

    www.healthandsafetytips.co.uk

    The Pre-Tender Stage

    Health and Safety PlanBy

    John Johnston AIIRSM

    Health and Safety for Beginnerswww.healthandsafetytips.co.uk