premium digest december 2010 inspection of gas pipelines with ultrasonic measurement techniques -...

Upload: argentinoar01

Post on 14-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Premium Digest December 2010 Inspection of Gas Pipelines With Ultrasonic Measurement Techniques - Practical A

    1/5

    5 PiPelines international digest | deCeMBer 2010

    integritY

    Inspection of gas pipelines withultrasonic measurement techniques:

    practical aspectsBy Dr Jochen Stratmann, Open Grid Europe GmbH, Pipeline Engineering Section (TLE), Essen, Germany

    Pipeline inspection tools based on ultrasonic measuring techniques are requently used or the assessment o oilpipeline integrity. Due to the requirement o a liquid being present between the detection device and the pipe wall,this technique is not readily applicable to gas pipelines. Recently, the inspection o gas pipelines with ultrasonicdevices has been conducted successully by completely flling the pipeline with a liquid (or example, water) beorethe inspection. As an alternative, a short section (batch) o liquid may be run through the pipe in order to avoidcompletely flling it. The liquid is separated by pigs rom the surrounding gas in the pipeline and the measurementdevice is kept within the liquid-flled section. Batches may, however, assume considerable velocities in the event o

    large slopes along the path o the pipeline, and this may inuence the probability o detection and, more practically,it constitutes a risk o pipeline damage i velocities become too high. This article ocuses on the method o calculatingthe batch velocity, predicting water batch movements in pipes as well as other practical aspects.

    Ultrasonic detection devices employed by in-line

    inspections (ILI) tools are used for the detection of

    pipeline defects such as corrosion, grooves, laminations,

    or cracks. These tools enable the detection of defects which

    cannot be achieved using other techniques such as magnetic-

    ux leakage (MFL), especially with respect to cracks due to

    fatigue or stress corrosion. However, the contact between the

    ultrasonic detector and the pipe internal wall needs to be

    established through an incompressible liquid, which rules outstraightforward use of these devices in gas pipelines.

    Filling the pipeline with a liquid before or while conducting

    the pigging provides the most intuitive solution to this

    challenge. However, typical sections of large gas pipelines may

    contain volumes of several tens of thousands of cubic metres.

    Any liquid employed for this use will experience a certain

    degree of contamination through the contents of the pipe,

    which may be a result of compressor station oil losses or the

    higher hydrocarbons contained in the gas itself. The disposal or

    the decontamination of the liquid may be extremely expensive,

    a condition which gives the pipeline operator reason to look for

    an alternative.

    Additionally, it presents a considerable challenge to obtain

    public and/or private permits to obtain water from rivers

    or lakes. The public water supply is generally insucient

    regarding capacity. To transport the water using temporary

    above-ground water lines to one of the sites where pig traps

    are located may also constitute a handicap. Furthermore, thedisposal of the water after its use, even after it being cleaned

    using activated carbon, may not always be allowed by local

    authorities.

    Symbol Property Unit

    a speed of propagation m/s

    di internal pipe diameter m

    E Youngs modulus N/m2

    k compressibility of liquid l/Pa

    l batch length m

    ow friction coecient

    ppressure dierences

    (e.g. from ow friction)Pa

    liquid density kg/m3

    s wall thickness m

    v velocity dierence m/s

    Figure 1: Example of a liquid batch set-up.

    Figure 2: Example of general set-up and boundary conditions (top)

    and photo of mobile air compressors (bottom).

  • 7/27/2019 Premium Digest December 2010 Inspection of Gas Pipelines With Ultrasonic Measurement Techniques - Practical A

    2/5

    6 PiPelines international digest | deCeMBer 2010

    integritY

    Set-up and goalsDue to the above-mentioned conditions, pigging of the gas

    pipeline using short liquid batches, of only several hundred

    metres length, is desirable. In this case, the batch consists of a

    liquid-lled section within the pipe while the liquid is separated

    from the gas by means of pigs at both ends. Figure 1 shows such

    a set-up.

    Depending on the pressure in front of and behind the batch

    (i.e. the boundary conditions), the batch may move more or less

    freely within the pipeline. In addition, the height prole of the

    pipeline inuences this movement.

    The set-up under consideration here is a short water batch

    with a length of approximately 600 m. The gas volume behind

    the batch is fed with air using multiple compressors in

    continuous or intermittent operation. Therefore, the amount

    of air in this section continuously increases; the pressure,

    however, varies depending on the position of the batch. The

    gas volume in front of the batch is vented to the atmosphere in

    such a fashion that the gas pressure in this volume remains at a

    constant level, while the volume continuously decreases as the

    batch moves in forward direction. Figure 2 illustrates this set-

    up, the questions associated with which may be subdivided into

    the following aspects:

    Operational

    There is a need to calculate the pressure needed to drivethe batch through the pipeline considering the local height

    dierences.

    The time at which the batch will be expected at a certain

    location within the pipeline needs to be known for general

    planning and for positioning pig detection teams along the

    pipeline if pig detection is done throughout the inspection at

    given locations.

    Measurement technique The ultrasonic device is operated at a certain detection

    frequency at which the measurement is conducted. If the

    velocity of the batch exceeds a certain value, for example1.5 m/s, the probability of detection for a specic size of crack

    will become too low to be acceptable for the assessment of

    pipeline integrity. Therefore, it becomes mandatory to nd a

    means of estimating the expected velocity for each location

    along the pipe. Exceeding the critical velocity with respect

    to detection in a small fraction of the total pipeline may be

    considered acceptable.

    Pipeline integrity and safety aspects Due to the density of water, a considerable hydrostatic

    pressure may act within the pipe. Naturally, the pressure in

    the pipe must not exceed the design pressure. This aspect

    is less relevant to short batches, but may become critical for

    batches of lengths in excess of a thousand metres depending

    on the height prole.

    At certain conditions discussed below, the batch may

    separate into two (or more) parts. This is entirely undesirable

    and induces the risk of a water hammer which may occur

    if two of these parts collide in the pipe at a considerable

    velocity. To avoid the batch separation, a certain pressure

    needs to be maintained within (and at the front) of the batch.

    Also, the question arises which collision velocity leads to a

    critical pressure shock in the pipeline.

    At high velocities, the batch may cause a considerable

    (centrifugal) force to act on bends of the pipe if the pipe is

    not straight at locations characterized by high velocities,

    i.e. downhill.

    In summary, it appears vital to rst calculate the pressure

    behind and in front of the batch as well as its velocity. From these

    parameters, conclusions regarding the integrity/safety aspects

    may consequently be drawn.

    Pressure calculationIn the following, the batch is considered merely as an amount

    of water within the pipe. The mass and volume of the individual

    pigs is not taken into account, since it is considered to result in a

    similar density as an equivalent section of water or less, and thus

    to behave accordingly.

    Three dierent characteristic pressures are discussed in this

    section. These are:

    The maximum pressure that occurs within the section in

    which the batch is located: this pressure must not exceed the

    maximum operating pressure/the design pressure of the pipe.

    The minimum pressure to be maintained in front of the batch:

    the reason why a certain pressure must be maintained infront of the batch is that the pressure at the highest point

    within the batch (the top in Figure 3) must not become

    lower than the vapour pressure of the liquid. If this is the

    maximum pressure

    600 m batch

    minimum pressure in front of batch

    pmax = 8.9 bar

    pdrive,max = 23.6 bar

    pmax = 23.6 bar

    pfront = 10.0 bar

    600 m batch

    driving pressure

    Figure 3: Illustration of relevant height dierences.

    Figure 4: Result for the three dierent characteristic pressures for

    a batch length of 600 m. The maximum pressure and the driving

    pressure are calculated on the basis of a pressure in front of the

    batch of 10 bar (abs). The height prole is given in each graph to

    enable comparison. The location is dened as the position of the

    front of the batch, see Figure 3.

  • 7/27/2019 Premium Digest December 2010 Inspection of Gas Pipelines With Ultrasonic Measurement Techniques - Practical A

    3/5

    7 PiPelines international digest | deCeMBer 2010

    integritY

    case, the liquid will become gaseous at this location and,

    consequently, the batch will fall apart into two separate

    parts. It is vital to avoid this, as it gives rise to the danger of

    a so-called water hammer if the two parts later collide in the

    pipeline. Even a low velocity may generate a high-pressureshock. The pressure caused by the collision is discussed in

    one of the following sections.

    The pressure needed to drive the batch through the pipeline

    (driving pressure, pressure behind the batch): this pressure

    must be generated by one or more compressors. It depends

    on the location of the batch within the height prole. This

    aspect may be critical as to the duration of the pigging

    process if a high pressure is needed in long sections of the

    pipeline. If lling this volume at high pressure takes too long,

    the pig battery capacity may become critical.

    The maximum pressure in the section of the pipeline filled

    by the batch exists at the very bottom of this section. It is

    influenced by the hydrostatic pressure resulting from the

    height profile as well as the pressure in front of the batch.

    Figure 3 shows an example of a height profile which includes

    an indication of the section filled with water. At this batch

    location, the maximum pressure occurs at the very front and

    is therefore identical to the gas pressure in front of the batch

    if pig friction is disregarded. It must be ensured that this

    pressure does not exceed the pipe design pressure. It must

    therefore be calculated for all possible batch locations. A result

    in Figure 4 shows that, for the case in hand, the maximum

    pressure does not constitute a critical issue. The maximum

    pressure aspect is most critical for long batches and large

    height differences.The minimum pressure in front of the batch is calculated on

    the basis of the following scenario: At any time or location,

    the gauge pressure in front of the batch must, as a minimum,

    match the hydrostatic pressure difference between the top

    and front locations as indicated in Figure 3. This ensures

    that the pressure at the top location never becomes lower

    than 1 bar and therefore not lower than the vapour pressure

    of water. This avoids the vaporisation of water at this point

    at low pressure. Naturally, a certain safety margin is added

    on top of this pressure. Since the height difference between

    the two locations varies significantly with the position of the

    batch, it must be calculated for each batch location. To ensuresafe operation of the batch run, it is easiest to maintain a

    constant pressure in front of the batch as indicated above in

    the section Set-up and goals. However, in some instances it

    may be appropriate to vary this pressure, for example to avoid

    an unnecessary operation of the compressors to create a high

    driving pressure or to avoid a critical level of pressure at the

    lowest point in the batch with respect to the design pressure of

    the pipe. Figure 4 shows the calculation results.The driving pressure may be estimated by adding the

    hydrostatic pressure dierence between front and rear of the

    batch as indicated in Figure 3 to the gas pressure in front of the

    batch as well as an equivalent pressure which corresponds to

    the pig friction. In the set-up discussed here, this pressure must

    be generated by means of air compressors as shown in Figure

    2. Figure 4 shows that, due to the necessary pressure in front of

    the batch of 10 bar and the pig friction, the maximum driving

    pressure gets close to 25 bar even for the short batch of 600 m

    length and this height prole example.

    An alternative to calculate the driving pressure is to use a mass

    balance of gas (air) in the volume behind the batch. Here, the

    mass ow rate of the compressors used to feed the gas/air to this

    volume must be considered as well as the actual, time-dependent

    location of the batch. The time-dependent location of the batch

    within the pipe is known after solving the problem described in

    the following section.

    Batch movement predictionand velocity calculation

    As stated above, the presence of pigs within the water batch

    is disregarded and the batch is treated as one continuous

    section of water. To calculate the velocity, a balance of forces

    acting on this lumped mass of water is considered.

    Primarily, the movement of the batch is inuenced by thepressure behind the batch (pressure 1) and in front of the

    batch (pressure 2), see Figure 5. These pressures depend on the

    location of the batch within the pipe and on time (for example,

    a compressor continuously feeds gas to the gas volume behind

    the batch). As an example, moving the batch to the right-hand

    side in Figure 5 will increase pressure 2 and decrease pressure

    1. Simultaneously, a compressor feeding gas into the section

    behind the batch increases pressure 1; venting gas from the

    volume in front of the batch (in the direction of movement) will

    decrease pressure 2.

    In addition, Figure 5 displays the height prole of a gas

    pipeline as an example. Due to the slopes associated with thisprole, a gravitational force acts on the batch. Therefore, this

    force depends on the batch location (intuitively, downhill

    means fast).

    Figure 5: Forces acting on the batch. Figure 6: Example of height prole and velocity.

  • 7/27/2019 Premium Digest December 2010 Inspection of Gas Pipelines With Ultrasonic Measurement Techniques - Practical A

    4/5

    8 PiPelines international digest | deCeMBer 2010

    integritY

    The force caused by friction between pig and pipe wall also

    needs consideration. This force may be assumed to be constant

    as it depends mainly on the geometry of pig and pipe, thematerials employed and other parameters, but not on the

    location. A pig in a dual-diameter pipeline may, however, behave

    dierently. Here, the friction force may be seen as constant for

    each section with a constant diameter. When compared to a

    pressure force, this force typically is the equivalent of 1 bar per

    pig or less.

    The force which has the largest inuence on the maximum

    batch velocity is, however, the friction force caused by the ow

    in the liquid-lled sections between the pigs. If the local ow

    eld at the ends of these sections near the pigs where the ow

    is reversed is disregarded (long batch), this ow has normal

    turbulent pipe ow characteristics. This means that it causes a

    pressure loss equivalent to such a ow. This pressure dierence

    (loss) acts as a force which decelerates the batch. Equation 1

    gives the relationship:

    p = l/di p/2 v2 (1)

    This pressure dierence is calculated using a constant ow

    friction coecient of = 0.01. For other cases, this coecient is

    readily obtained from textbooks on hydrodynamics.

    As is typical with pipe ow, the force increases with the square

    of the velocity. It is therefore most inuential at such conditions

    where the velocity is high, i.e. downhill, and acts as a natural

    limiter for the maximum velocity. If it is intended to reducebatch velocities, an appropriate means is to use longer batches.

    This is counter-intuitive, as one would assume longer batches to

    move downhill faster than short ones. Nevertheless, using this

    as a remedy causes a higher hydrostatic pressure within the pipe

    and creates the need for more water. The force balance results in

    an ordinary dierential equation (second order) which is solved

    using the numerical methods in MATLAB. The following section

    shows the results.

    Velocity prediction results and discussionIf applied to the given height prole example, the velocity

    calculation using the method described above results in avelocity prole as shown in Figure 6. It becomes obvious that a

    downhill scenario results in a high batch velocity. Due to this

    height prole, the velocities predicted by the calculation are,

    however, too high for the use of ultrasonic measuring devices.

    Therefore, a pipeline with such a height prole must be subject

    to a complete ll or a very long batch.Figure 7 shows the comparison between the calculation result

    (blue line) and a measurement of the velocity of one of the pigs

    from a real batch run, measured using a common odometer.

    An acceptable degree of agreement between prediction and

    measurement of the velocity is achieved.

    At some of the locations, primarily those with high velocities,

    the measurement shows higher velocity values than predicted.

    These values are considered a measurement error due to the

    behaviour of the odometer at high velocity for which it is not

    designed. This assumption will be veried in the future by using

    more advanced devices for measuring the pig velocity.

    Additionally, the measurement result may be the consequence

    of pig behaviour if gas is trapped within the batch causing an

    oscillation with high peak velocities of the individual pigs. This

    aspect will also be addressed in future simulations by solving

    the coupled dierential equations.

    Pipeline integrity and saety aspects

    Forces in pipe bends at high velocitiesThe forces acting on pipe bends are the result of the change

    of momentum of the liquid ow through the bend (centrifugal

    force). The total force depends on the ow velocity and the pipe

    cross-section area, but not on the radius of the bend. However,

    at larger radii, the force spreads over a larger area. Here, thecentrifugal force acts in addition to the force resulting from

    the pressure inside the curved pipe. Figure 8 shows the total

    force from both pressure and change of momentum. It becomes

    obvious that in the velocity range up to 20 m/s, pressure

    forces dominate. Also, the centrifugal force at a velocity of

    approximately 35 m/s has the same value (approximately

    900 kN) as a pressure force resulting from a pressure of

    10 bar. Due to this equivalence, centrifugal forces do not play a

    signicant role, if a velocity prole according to Figure 6 with a

    maximum velocity of 20 m/s is expected.

    Batch collision and water hammerDiscussion of the water hammer problem is needed to assess

    the consequences of a batch collision in the pipe as a what-

    if scenario. At the location of the collision, the pressure is

    Figure 7: Comparison between prediction and measurement.Figure 8: Total force on a pipe bend is dependent on pressure and

    batch velocity.

  • 7/27/2019 Premium Digest December 2010 Inspection of Gas Pipelines With Ultrasonic Measurement Techniques - Practical A

    5/5

    9 PiPelines international digest | deCeMBer 2010

    integritY

    increased immediately to a value described by the Joukowsky

    equation. This pressure may well exceed the pipe design

    pressure:

    p = p a v (2)

    This pressure shock then propagates at the speed of wave

    propagation along the pipe in the backward direction until theend of each of the two batches is reached. At the end, the pressure

    dierence reverses its sign (reection at open end) and the shock

    front begins to propagate in the forward direction. The pressure

    level in the batch may become extremely low during this process

    and may well cause the liquid to vaporise if the pressure falls

    below the vapour pressure.

    Both the pressure increase and the velocity of propagation

    of the shock wave depend on the compressibility of the water

    and the elasticity of the pipe. Figure 9 shows the solution of the

    Joukowsky equation for three dierent cases depending on the

    relative collision velocity. If the compressibility of water is taken

    into account and the pipe is regarded as entirely rigid, even low

    collision velocities lead to critical pressure levels since water

    reacts very stiy. Taking into account the elasticity of the pipe,

    a much higher velocity is needed to create pressure levels critical

    for a pipeline. It must be stressed that this pressure must be

    added to the initial pressure in the pipe.

    SummaryPractical aspects of relevance to gas pipeline inspection

    using pigs which employ ultrasonic measurement techniques

    are discussed in this article. To warrant the coupling between

    measurement device and pipe wall, it appears advantageous

    to move short sections of liquid (batches) through the pipe in

    which the measurement device is contained. Using this approach,

    the velocity of the batch in the pipeline needs to be predicted

    and certain characteristic pressures in the system have to be

    calculated. Consequently, key safety aspects are discussed on the

    basis of the results.

    A simple approach for the prediction of the velocity of liquid

    batches of any length in pipelines is developed. The comparison

    with measurements indicates that the approach is suitable

    for the prediction of the velocity as it occurs in the eld. If theheight prole of the pipeline exhibits large slopes, the velocity

    is expected to exceed a critical limit up to which the detection

    of pipe faults is possible. Hence, it is suitable for pipelines with

    minor height dierences only. The approach also enables the

    prediction of the location at which the batch is found in the

    pipeline over time.

    Another vital aspect is to ensure the integrity of the batch by

    maintaining a certain location-dependent pressure in front of the

    batch. The collision of two water batches in a pipeline results in a

    pressure level in excess of the design pressure if a certain velocity

    is exceeded. This critical velocity depends on the properties of the

    pipe.

    In addition, due to the high density of the liquid, it must be

    ensured that the maximum (hydrostatic) pressure in the pipe

    does not exceed the design pressure. This aspect is important for

    longer batches of several thousand metres length.

    The ow of water in sharp bends of the pipe at high velocity is

    found to be of minor importance when compared to the eects of

    internal pressure on the pipe.

    Figure 9: Pressure increase vs relative (collision) velocity, where:

    k = 4.8e-10 1/Pa (compressibility of liquid)p = 988 kg/m3 (liquid density)

    di = 0.9 m (internal diameter)

    s = 12.6 mm (wall thickness)

    E = 206,000 MN/m2 (Youngs modulus)

    This paper was presented at the Evaluation, Rehabilitation

    and Repair of Pipelines Conference held in Berlin, Germany,

    in October 2010, and organised by Tiratsoo Technical (a

    division of Great Southern Press) and Clarion Technical

    Conferences, Houston.