presentation by: alwyn laubscher pr. eng. pr. cpm report to municipal workshop 31 october 2013
TRANSCRIPT
Presentation by: Alwyn Laubscher Pr. Eng. Pr. CPM
REPORT TO MUNICIPAL WORKSHOP 31
OCTOBER 2013
PURPOSE OF THE PRESENTATION
• To explain the process previously followed at Swartland Municipality
• To highlight the lessons learnt through applying the system
CONTENTS• Introduction
• Process to determine DC’s
• Growth Model
• Bulk Services
• Implementation
• Lessons Learnt
• Questions
INTRODUCTION• It is the responsibility of Local
Government to pro-actively plan for growth and development of their town.
• First it should determine the potential for growth, and then the required bulk services to serve such growth.
• And to establish sources of funding for such services.
PROCESS TO DETERMINE DC’S
Need for Local Government to stimulate economic development
Need to pro-actively plan for growth and development
of City/Town
Development of a long term Growth Model for the Area
Compilation of master plans for bulk services to serve
Growth Model
Calculate the cost of each of the bulk services
Determine the contribution from each development opportunityto pay for bulk infrastructure
Negotiate with Developer to provide bulk services in lieu of
DC’s, where applicable
Pay DC’s into a dedicated account (per service) to be used
in future for the provision of bulk infrastructure
PROCESS TO DETERMINE DC’S
• Plan for estimated growth for different scenario’s (5; 10; 20 years)
• Assumed zoning; land use; and densities
• Brown Fields (densification) and Green Fields (new developments)
• Compile Excel Model for easy manipulation of What If questions
GROWTH MODEL
GROWTH MODEL - MALMESBURY 20 JAAR
GROWTH MODEL - 20 YEAR
BULK ROAD NETWORK
BULK ROAD NETWORK
WATER NETWORK
NETWERK
SEWERAGE NETWORK
BULK WATER & SEWERAGE PLANNING
STORMWATER NETWORK
STORMWATEROndersoek(Aanvaarding R30 000 per 500m lengte van
rivier)
R 1,020,000
Vloedlynstudie(Aanvaarding R15 000 per 100m rivier)
R 1,500,000
EIA(Aanvaarding R500 000)
R 500,000
Opgradering/Rehabilitering(Aanvaarding gebaseer op vorige projekte)
R50,000,000
Sub totaal R53,020,000
Onvoorsiene Uitgawes R 5,302,000
BTW (14%) R 8,165,080
Totaal R66,487,080
ELECTRICITY
DESCRIPTION
DENSITY OR
COVER-AGE
ADMD kVA AT 132/11 kVSUBSTATION
LEVEL
RATE PER kVA FOR 132/11 kV
SUB-STATION
“GREEN-FIELDS”CONTRI-BUTION
ADD “BROWN-FIELDS”
PRIMARY AND SECONDARY
11 KvINFRA-
STRUCTURE
TOTAL RATE FOR BULK
ELECTRICITYCONTRIBUTIONS(VAT EXCLUDED)
Low Density 4 u/ha 4 kVA per unit R1 405-00 R5 620-00 R2 526-32 per unit R8 146-32 per unit
Single Residential
15 u/ha 3 kVA per unit R1 405-00 R4 215-00 R2 526-32 per unit R6 741-32 per unit
Medium Density Residential
20–25 u/ha2.5 kVA per
unitR1 405-00 R3 512-50 R2 526-32 per unit R6 038-82 per unit
High Density Residential
30–60 u/ha2.5 kVA per
unitR1 405-00 R3 512-50 R2 526-32 per unit R6 038-82 per unit
Affordable Housing
30–40 u/ha1.5 kVA per
unitR1 405-00 R2 107-50 R1 263-16 per unit R3 370-66 per unit
Subsidised 30–40 u/ha1.0 kVA per
unitR1 405-00 R1 405-00 R0-00 per unit R1 405-00 per unit
Industrial and Commercial
Varies On Application R351-25 R1 405-00 R157-90 per kVA
R509-15 per kVA ofApplied for
MaximumDemand
Co-incidence factor of 25% used between Non-Residential and Residential peak loadsDirect connection costs such as mini-substations, metering, 11 kV secondary cables etc., excludedCredit will be given for 11 kV secondary cables installed on Municipality’s behalf and in accordance with the Electricity Master Plan
WASTE WATER TREATMENT WORKSLand Use UWD* USF*
m³/unit/day m³/ha/day % of UWD***
m³/unit/day m³/ha/day
Res Low Density 1.0 55 0.55
Res Single 0.7 60 0.42
Res Medium Density 0.6 60 0.36
Res High Density 0.5 65 0.325
Res Subsidy Housing 0.3 70 0.21
Industrial 20.0 60 12
Commercial Retail 20.0 60 12
Commercial Offices 15.0 60 9
WWTW = R94m for 10 000m³/day (10/12/2007)
Upgrade adds 4 600m³/day
Total Capital for refurbishment of existing WWTW = R30m
Total Cost for 4 600m³/day = R94m – R30m = R64m
Unit Cost = R64m/4 600m³/day = R13 894.57/m³/day
UWD*= Unit Water Demand/ USF**-Unit Sewer Flow/% of UWD***-UH + 5% (infiltration)
Principles:
• Responsible Planning
• Everybody must contribute
• Based on land value
SOCIAL INFRASTRUCTURE
TIMPLEMENTATION
• Liaise with Developers
• Approve as Council Policy
• Advertise with Tariffs
• Training of officials
• Guideline document (internal and external)
• Implementation across the board
QUESTIONS
Presentation by
Alwyn Laubscher Pr. Eng. Pr. CPM
REPORT TO MUNICIPAL WORKSHOP
31 OCTOBER 2013
PURPOSE OF THE PRESENTATION
• To share the considered key elements of such a policy
• To highlight the alignment between SDF; IDP; MTREF; and DC’s
LESSONS LEARNT - LEGISLATION
• LUPO provides for charging DC’s but is not very clear in its definitions
…include conditions in relation to the cession of land or the payment of money which is directly related to the requirements resulting from the said authorisation, exemption, application or appeal in respect of the provision of necessary services or amenities to the land concerned.
• This lead to court cases around the quantum charged
• Electricity has less of a problem - legislation allows them to charge DC’s as a tariff
• It is therefore important how LUPA will deal with DC’s
LESSONS LEARNT - FINANCIAL
• Plan for growth of Town and see DC’s as an additional source of revenue
• This is not just another tax - it is a planning exercise
• Do not hand it over to Treasury
• Quantum and When it is payable must be known upfront by Developers - certainty
• Follow proper process of collecting DC’s – big numbers at stake
LESSONS LEARNT - ECONOMY
• Be aware not to scare investors away - you are in the business of selling your town and draw investors
• Approach DC’s as a partnership with Private Sector
• Mitigate impact on job creation through subsidies – DC’s on Commercial and Industrial developments are high.
• LUPO requires regard to the various rates and levies paid in the past or to be paid in the future by the owner of the land concerned - WWTW
KEY ELEMENTS OF DC POLICY
• Must find a balance between need to stimulate economy and job creation; and funding the growth of the town
• Private Sector is running huge risks with low margins - need support and certainty (look at number of entities that left development)
• Beware of line departments treating DC’s as a cash cow – delivery of service for which money was collected must take place
• Proper system and policy is required for administration - big amounts at stake
ALIGNMENT BETWEEN SDF; IDP; MTREF; & DC’S• Planning for the future is responsible management
• In terms of the IDP it is a legal requirement
• In terms of MFMA a Medium Term Revenue and Expenditure Framework (MTREF) is a requirement
• Determination of your Spatial Development Framework is the starting point for compiling a Growth Model
• Engineers need to plan ahead for all bulk services (part of IDP): they can only do so if they have a Growth Model
• Planning by the Engineers must be budgeted for – back to MTREF
• MTREF relies on various sources of income - i.e. DC’s
QUESTIONS