CASE STUDY TEAM 3GRZEGORZ SWIATKOWSKI
ELIAS TEFADE
TAURAN BLAGGAN
VASILEIOS KARKANTZOS
SHOAIB AHMAD
Bradford Beck Catchment Area
Area Division
CONTROLLING FROM SOURCE @ UPSTREAM SOAKWAY PIT AND WATER BUTT
Water Butt
Capacity of each butt = 0.7 m3
Applying for 1,000 houses, 3 set per
house = 3,000 pcs
Total capacity = 630 m3
Est. Cost = £30,000.00
Soakaway Pit
Size – 40 x 4 x 2.5
Capacity = 5 * 400 m3
Est. Cost = £100,000.00
Proposed residential area with Water Butt
INFILTRATION BASIN & SWALES
Infiltration Basin
Ranging 0.5 m – 3.0 m deep
Drain half stored runoff in 48 hrs.
Capacity = 900 m3
Est. Cost = £585,000.00
Swales
Help in removing polluting solids
through infiltration, trap organic
mineral
Capacity = 500 m3
Integrated with wildlife habitat
GREEN ROOF & WATER RESERVOIR
Green Roof
Total Volume = Roof Thickness * Roof
Areas = 0.002 m * 3360 m2 = 67.2
m3
Est. Cost = £672,000.00
Underground Water Reservoir
Est. Size = 20 x 9 x 4 = 640 m3
Serves as temporary water treatment
tank
Est. Cost = £150,000.00 to
£255,000.00
Existing Pitched Roof
Water Reservoir
UNIVERSITY CAMPUS DEVELOPMENT
Features:
Green Area by the Beck
Solar Panels
Resting Area
University Campus Building
Est. Cost = £80 million
WESTHOLME PARK
Features:
Pool/Pond
Café/Restaurant
Bike Rental
Est. Cost = £3.5 million
FLOOD WARNING SYSTEM
System comprises of sensors which
measure the increase in velocity and
rising water levels
Sensors are connected to the
speakers that currently exist in the
town
Cleaning the Bradford Beck
Estimated Cost £350,000.00
North Complex Development
Features:
• Multipurpose Sports Centre
• Amphitheatre
• Children Care Facilities
• Youth Centre
• Restaurants
• Cafés
• Bars
• Retail
• Park
Video slide (removed due to excessive size)
North Park• Estimated cost:
Opening Beck = 10 million
Retail Buildings = 3 * 40 million
Sports Centre = 40 million
Park, Amphitheatre and Planting = 30 million
• Estimated footfall = 5,000 people per day
• Estimated revenue = £200 million spent per year
VALLEY ROAD PARKLandscaping Work
Features:
Open up culvert, provide accessibility to
the river
Creation of pond
Reservoir to control flow of water
Permeable pavement
Vegetation
Walkway, bicycle way
Picnic
River crossings
Estimated Cost: 20 million
Video slide (removed due to excessive size)
CULTURAL CENTRE
Location: between Hamm Strasse and Singleton street
Features:
Refurbishment of listed building, turn it to a multi-purpose cultural centre
Creation of wetland for the purpose of the cultural centre and vegetation to improve visibility and store water
Permeable pavement
Water fountain
Estimated cost: 10 million
DEVELOPMENT OF BECK @ DOWNSTREAM
Area of development = 35,100
m2
Area of existing beck = 633 m2
Demolition Cost @ 19 per m2
for 12,600 m2 = £240,000
Beck to be extended
surrounded by greenery (park)
Cycle and walkway paths
running along Canal Road and
onto the Park
Beck to either contain a Water
Storage System or a Meander
Canal
WATER STORAGE POOLMEANDER CANAL
Both techniques are able to
slow down the speed of water flow
Capacity of extended beck = 2,140
m2
Area of pool = 30 m x 20 m = 600 m2
Capacity of water storage = 1,200 m3
Est. Cost of pool = £500,000.00
Est. Cost to meander the canal =
£350,000
Est. Cost of open green space =
£62,200
Total Cost inc Demolition = £800,000
Our areas for development follow water drop path to include integrated water cycle
The designs create Broadway from University to Queen’s Road and further to Shipley
Water features take under account changing climate to provide safety for citizens and goods
Green areas, so widely included in the designs, create habitat for nature and bring whole communities together
Proposed developments will attract investors and make Bradford retail centre connected to water