PROJECT AT A GLANCE
3 X 660 MW Boilers and Auxiliary Installation
Client - National Thermal Power Corporation Ltd.
Supplier - Doosan Heavy Industries & Construction
Co. Ltd. South Korea
Erection AgencyLarsen & Toubro Limited, ECC Division
LOI Issued - 15/04/04.
Job Value - 296.36 Crores
-
8/3/2019 Presentation21.1.06
2/16
Salient Features of the Project*3 X 660 MW POWER PLANT - First time in India
* UNIQUE IN NATURE - Mega Power ProjectDeclared by Govt.
* INDIVIDUAL BOILER RATING - 2225 MT / Hrs. (660 MW)
* WORKING PRESSURE - 255 kg / sqcm
* NO OF BOILERS - 3 NOS
* CUSTOMS DUTY - Nil ( Decl. by Govt.due
to Mega Power Project)
* HEIGHT OF THE BOILER - 100 MTRS
* NO OF FANS - 6 NOS
*NO OF COAL FEEDERS - 10 NOS
*NO OF MILLS - 10 NOS
-
8/3/2019 Presentation21.1.06
3/16
All Structural Members are Bolted Type.
No Boiler Drum in this Boiler.
Boiler working press. (Sup. Steam) 255 kg/sqcm
Furnace wall is Jacket Type.
All Ceiling Girders will be erected from outside
by using 750 MT crane Ringer mode.
Furnace wall is being erected 28 mtrs in length
after preassembly.
Uniqueness of the Project
-
8/3/2019 Presentation21.1.06
4/16
Extended floor Panel assembled with Header &
Buckstays and will be erected.
Furnace Bottom hopper with Ring header will be
assembled and erected all together.
Most of the Duct Pieces upto 15 mtrs will be
assembled at ground and erected.
Approx. 20000 nos welding joints will be done on
ground for preassembly before erection out of
42000 nos joints.
Uniqueness of the Project
-
8/3/2019 Presentation21.1.06
5/16
Safety Statistics
Description
Safety M/H record
Accident records
Minor
First -aid injuries
Fatalities
Status of meeting & training
Training
Multi media safety show
PROJECTED MANHOURS =
CUMULATIVE
(FROM MARCH 2005)
1488374
1
10
1
58
15
15.50 Millions
-
8/3/2019 Presentation21.1.06
6/16
Screening of the workers are being done before
engaging on the job.
Morning Pep-talk is being done before starting
the work.100% PPEs are being implemented at erection
site.
Training for workers on weekly basis at training
hall for better awareness.
Usage of 100% full body harness at erection site.
SAFETY AC
TIVITIES
-
8/3/2019 Presentation21.1.06
7/16
Usage of Double Safety net at erection site.
Periodic inspection of Tools & Tackles.
Method statement is being made and analysed
jointly by Contractor and Client before all critical
erection.
Sub contractors Performance is being
evaluated by Safety committee on Monthly basis.
100% usage of GI Flat for earthing purpose.
Total Safe Manhours upto Dec05 = 1488374
Positive customer feed back.
SAFETY ACTIVITIES
-
8/3/2019 Presentation21.1.06
8/16
SCOPE OF WORK OF L&T
Port Clearance,Inland Transportation From
Vizag to Sipat & Insurance
Material Management
Erection
Testing & Commissioning
-
8/3/2019 Presentation21.1.06
9/16
MECHANICAL ERECTION : 147.90 CRORES
E&I ERECTION : 11.00 CRORES
INLAND TRANSPORTATION INCLUDING TRANSIT
INSURANCE : 35.34 CRORES
SUPERVISION OF ERECTION AND COMMISSIONING
BY DOOSAN : 44.61 CRORES
PORT CLEARANCE CHARGES ( 1.2% OF THE CIF
VALUE) : 19.46 CRORES
CONTRACT VALUE
-
8/3/2019 Presentation21.1.06
10/16
ADDITIONAL COMPENSATION TO BE PAID BY DOOSAN
(6.5 M US DOLLAR) : 29.64 CRORES
INSURANCE CHARGES : 8.414 CRORES
TOTAL CONTRACT VALUE INCLUDINGE&I : 296.36 CRORES
CONTRACT VALUE
-
8/3/2019 Presentation21.1.06
11/16
BOILER STRUCTURE : 20772 MT
BOILER PRESSURE PART & ACCESSORIES : 21240 MT
POWER CYCLE PIPING : 9096 MT
COAL FIRING SYSTEM : 11469 MT
DRAFT SYSTEM (INCLUDING DUCT & DAMPER) : 15012 MT
REFRACTORY / INSULATION / C&I / MISC. : 6291 MT
TOTAL TONNAGE OF 3 BOILERS(3 X 660 MW) : 83880 MT
SUMMARY OF TOTAL TONNAGE OF BOILER 3 x 660 MW
-
8/3/2019 Presentation21.1.06
12/16
MILESTONE EVENTS
Description As per
Contract
Actual
Unit # 1 Structure Erection 15-04-05 03-03-05
Unit # 1 Pressure part Erection 15-09-05 15-09-05
Unit # 2 Structure Erection 15-10-05 28-06-05
Unit # 3 Structure Erection 15-04-06 20-01-06
-
8/3/2019 Presentation21.1.06
13/16
Q lit A t
-
8/3/2019 Presentation21.1.06
14/16
Involves Bolting and torquing of 102615 bolts per
Boiler for main structure
Welding of hand rails : 700 Mtrs per boiler
Welding of 42656 joints in pressure parts per boiler
Welding of 22283 joints in power cycle piping per
boiler.
Involves special P91/T91, T92, P23/T23 and Super
304H materials in boiler pressure parts and piping.
Involves Induction heating technique for above
special materials
Quality Aspects
-
8/3/2019 Presentation21.1.06
15/16
100% implementation of Preparation & approvalFQP and Inspection test procedure prior to start of the
job to erection.
Stage wise inspection prior to erection andcompletion of job and proper documentation of the
same.
Reduction of repair % from 2.9 to 0.60 by stringentcontrol in welding conditions and welder performance.
100% NDT & PWHT clearance of Preassembled
items before erection.
Quality Improvement
QUALITATIVE IMPROVEMENTS
-
8/3/2019 Presentation21.1.06
16/16
Pre assembly of most of the Pressure part
members before erection. Thereby improving on
the following parameters.
1. Safety Improvement - Reduction of exposure of
work at height and critical locations.
2. Improvement of quality of welding as
maximum welding is done at ground level.
3. Reduction in total completion time by parallelworking on pre assembly.
4. Reduction in installation cost by reducing the
work in in-situ osition
QUALITATIVE IMPROVEMENTS