    PROJECT AT A GLANCE

    3 X 660 MW Boilers and Auxiliary Installation

    Client - National Thermal Power Corporation Ltd.

    Supplier - Doosan Heavy Industries & Construction

    Co. Ltd. South Korea

    Erection AgencyLarsen & Toubro Limited, ECC Division

    LOI Issued - 15/04/04.

    Job Value - 296.36 Crores

  • 8/3/2019 Presentation21.1.06

    2/16

    Salient Features of the Project*3 X 660 MW POWER PLANT - First time in India

    * UNIQUE IN NATURE - Mega Power ProjectDeclared by Govt.

    * INDIVIDUAL BOILER RATING - 2225 MT / Hrs. (660 MW)

    * WORKING PRESSURE - 255 kg / sqcm

    * NO OF BOILERS - 3 NOS

    * CUSTOMS DUTY - Nil ( Decl. by Govt.due

    to Mega Power Project)

    * HEIGHT OF THE BOILER - 100 MTRS

    * NO OF FANS - 6 NOS

    *NO OF COAL FEEDERS - 10 NOS

    *NO OF MILLS - 10 NOS

  • 8/3/2019 Presentation21.1.06

    3/16

    All Structural Members are Bolted Type.

    No Boiler Drum in this Boiler.

    Boiler working press. (Sup. Steam) 255 kg/sqcm

    Furnace wall is Jacket Type.

    All Ceiling Girders will be erected from outside

    by using 750 MT crane Ringer mode.

    Furnace wall is being erected 28 mtrs in length

    after preassembly.

    Uniqueness of the Project

  • 8/3/2019 Presentation21.1.06

    4/16

    Extended floor Panel assembled with Header &

    Buckstays and will be erected.

    Furnace Bottom hopper with Ring header will be

    assembled and erected all together.

    Most of the Duct Pieces upto 15 mtrs will be

    assembled at ground and erected.

    Approx. 20000 nos welding joints will be done on

    ground for preassembly before erection out of

    42000 nos joints.

    Uniqueness of the Project

  • 8/3/2019 Presentation21.1.06

    5/16

    Safety Statistics

    Description

    Safety M/H record

    Accident records

    Minor

    First -aid injuries

    Fatalities

    Status of meeting & training

    Training

    Multi media safety show

    PROJECTED MANHOURS =

    CUMULATIVE

    (FROM MARCH 2005)

    1488374

    1

    10

    1

    58

    15

    15.50 Millions

  • 8/3/2019 Presentation21.1.06

    6/16

    Screening of the workers are being done before

    engaging on the job.

    Morning Pep-talk is being done before starting

    the work.100% PPEs are being implemented at erection

    site.

    Training for workers on weekly basis at training

    hall for better awareness.

    Usage of 100% full body harness at erection site.

    SAFETY AC

    TIVITIES

  • 8/3/2019 Presentation21.1.06

    7/16

    Usage of Double Safety net at erection site.

    Periodic inspection of Tools & Tackles.

    Method statement is being made and analysed

    jointly by Contractor and Client before all critical

    erection.

    Sub contractors Performance is being

    evaluated by Safety committee on Monthly basis.

    100% usage of GI Flat for earthing purpose.

    Total Safe Manhours upto Dec05 = 1488374

    Positive customer feed back.

    SAFETY ACTIVITIES

  • 8/3/2019 Presentation21.1.06

    8/16

    SCOPE OF WORK OF L&T

    Port Clearance,Inland Transportation From

    Vizag to Sipat & Insurance

    Material Management

    Erection

    Testing & Commissioning

  • 8/3/2019 Presentation21.1.06

    9/16

    MECHANICAL ERECTION : 147.90 CRORES

    E&I ERECTION : 11.00 CRORES

    INLAND TRANSPORTATION INCLUDING TRANSIT

    INSURANCE : 35.34 CRORES

    SUPERVISION OF ERECTION AND COMMISSIONING

    BY DOOSAN : 44.61 CRORES

    PORT CLEARANCE CHARGES ( 1.2% OF THE CIF

    VALUE) : 19.46 CRORES

    CONTRACT VALUE

  • 8/3/2019 Presentation21.1.06

    10/16

    ADDITIONAL COMPENSATION TO BE PAID BY DOOSAN

    (6.5 M US DOLLAR) : 29.64 CRORES

    INSURANCE CHARGES : 8.414 CRORES

    TOTAL CONTRACT VALUE INCLUDINGE&I : 296.36 CRORES

    CONTRACT VALUE

  • 8/3/2019 Presentation21.1.06

    11/16

    BOILER STRUCTURE : 20772 MT

    BOILER PRESSURE PART & ACCESSORIES : 21240 MT

    POWER CYCLE PIPING : 9096 MT

    COAL FIRING SYSTEM : 11469 MT

    DRAFT SYSTEM (INCLUDING DUCT & DAMPER) : 15012 MT

    REFRACTORY / INSULATION / C&I / MISC. : 6291 MT

    TOTAL TONNAGE OF 3 BOILERS(3 X 660 MW) : 83880 MT

    SUMMARY OF TOTAL TONNAGE OF BOILER 3 x 660 MW

  • 8/3/2019 Presentation21.1.06

    12/16

    MILESTONE EVENTS

    Description As per

    Contract

    Actual

    Unit # 1 Structure Erection 15-04-05 03-03-05

    Unit # 1 Pressure part Erection 15-09-05 15-09-05

    Unit # 2 Structure Erection 15-10-05 28-06-05

    Unit # 3 Structure Erection 15-04-06 20-01-06

  • 8/3/2019 Presentation21.1.06

    13/16

    Q lit A t

  • 8/3/2019 Presentation21.1.06

    14/16

    Involves Bolting and torquing of 102615 bolts per

    Boiler for main structure

    Welding of hand rails : 700 Mtrs per boiler

    Welding of 42656 joints in pressure parts per boiler

    Welding of 22283 joints in power cycle piping per

    boiler.

    Involves special P91/T91, T92, P23/T23 and Super

    304H materials in boiler pressure parts and piping.

    Involves Induction heating technique for above

    special materials

    Quality Aspects

  • 8/3/2019 Presentation21.1.06

    15/16

    100% implementation of Preparation & approvalFQP and Inspection test procedure prior to start of the

    job to erection.

    Stage wise inspection prior to erection andcompletion of job and proper documentation of the

    same.

    Reduction of repair % from 2.9 to 0.60 by stringentcontrol in welding conditions and welder performance.

    100% NDT & PWHT clearance of Preassembled

    items before erection.

    Quality Improvement

    QUALITATIVE IMPROVEMENTS

  • 8/3/2019 Presentation21.1.06

    16/16

    Pre assembly of most of the Pressure part

    members before erection. Thereby improving on

    the following parameters.

    1. Safety Improvement - Reduction of exposure of

    work at height and critical locations.

    2. Improvement of quality of welding as

    maximum welding is done at ground level.

    3. Reduction in total completion time by parallelworking on pre assembly.

    4. Reduction in installation cost by reducing the

    work in in-situ osition

    QUALITATIVE IMPROVEMENTS