preservation process instruction (ppi) · pdf filepreservation process instruction (ppi) core...

32
CORE PPI 1 August 23, 2011 REV 27 PPI NBR: 63101- 000 (REV 27) DATE: August 23, 2011 PRESERVATION PROCESS INSTRUCTION (PPI) CORE

Upload: truongdien

Post on 06-Mar-2018

272 views

Category:

Documents


9 download

TRANSCRIPT

Page 1: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 1

August 23, 2011 REV 27

PPI NBR: 63101- 000 (REV 27) DATE: August 23, 2011

PRESERVATION PROCESS INSTRUCTION (PPI)

CORE

Page 2: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 2

August 23, 2011 REV 27

1. SCOPE: 1.1 Title: Cleaning, Surface Preparation and Painting Requirements for (area to be prepared). 2. REFERENCES: 2.a Systems and Specifications, Steel Structures Painting Council, Volume 2 2.b SSPC-PA 2, Measurement of Dry Coating Thickness with Magnetic Gages 2.c MSDS and NAVSEA approved manufacturer’s ASTM F 718 sheets, Shipbuilders and Marine Paints and Coating

Product / Procedure Data Sheet for (Applicable QPL) Coating System Being Applied. NAVSEA approved ASTM-F-718 sheets may be obtained by selecting the Navy Community Tab on the WWW.NSTCENTER.COM

website and following the directions to their location. 2.d. ASTM D 4417, Methods B and C, Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel 2.e OSHA 29 CFR 1915 Subparts C and Z 2.f SSPC-VIS-1 Visual Standard for Abrasive Blast Cleaned Steel 2.g SSPC-VIS-4 Visual Reference Photographs for Steel cleaned by Water Jetting 2.h SSPC-VIS-3 Visual Standard for Power and Hand Tool Cleaned Steel 2.i A-A-59316 Abrasive materials; for blasting 2.j Field Test Methods and Instruments Used by Coatings Inspectors 2.k ISO 8502-3 Assessment of dust on steel surfaces prepared for painting (pressure sensitive tape method) 2.l SSPC-VIS-5 Guide and Reference Photographs for Steel Surfaces Prepared by Wet Abrasive Blast Cleaning 2.m SSPC-AB 2, Cleanliness of Recycled Ferrous Metallic Abrasives 2.n SSPC-AB 3, Ferrous Metallic Abrasive 2.o NSTM 631, Preservation of Ships in Service 2.p MIL-A-22262, Abrasive Blasting Media Ship Hull Blast Cleaning 2.q A-A-1722, Grain, Abrasive (Soft Blasting) 2.r ASTM D-4285-83, Standard Test Method for Indicating Oil or Water in Compressed Air 2.s MIL-PRF-23236C, Performance Specification Coating Systems for Ship Structures 2.u SSPC –AB 4 Recyclable Encapsulated Abrasive Media List of other related preservation system documents for additional information if desired:

1.a ISO-8501-1: 1988 (E) Preparation of Steel Substrates Before Application of Paints and Related Products -- Visual assessment of Surface Cleanliness -- Part 1: Rust Grades And Preparation Grades Of Uncoated Steel Substrates And Of Steel Substrates After Overall Removal Of Previous Coatings. 1.b ISO-8503, Surface Roughness Characteristics of Blast-Cleaned Steel Substrates. 1.c ISO-2178, Measurement of Coating Thickness -- Magnetic Method (Magnetic Substrates).

Page 3: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 3

August 23, 2011 REV 27

1.d ISO-2360, Measurement of Coating Thickness -- Eddy Current Method (Non-Magnetic Substrates). 1.e ISO-8504-Series, Preparation of Steel Substrates before Application of Paints and Related Products – Surface Preparation Methods. 1.f ISO-12944, Paints and Varnishes -- Corrosion Protection of Steel Structures by Protective Paint Systems. 1.g ISO-9000: 2000, Quality Management Systems -- Fundamentals and Vocabulary. 1.h ISO-8502-6, Preparation of Steel Substrates before Application of Paints and Related Products -- Tests for the Assessment of Surface Cleanliness -- Part 6: Extraction Of Soluble Contaminants For Analysis -- The Bresle Method.

1.i ISO-8502-9, Preparation of Steel Substrates before Application of Paints and Related Products -- Tests for the Assessment of Surface Cleanliness -- Part 6: Field method for the conductometric determination of water-soluble salts.

1.j ISO-12944-8, Paint and Varnishes-Corrosion Protection of Steel Structures by Protective Paint System -Part 8: Development of specifications for new work and maintenance. 1.k ISO--8501-3, Preparation of Steel Substrates before Application of Paints and Related

Products- Visual assessment of surface cleanliness. Part 3, Preparation grades of welds, cut edges and other areas with surface imperfections.

1.l ISO-11124, Metallic blast-cleaning abrasives.

1.m ISO-11125, Test methods for metallic blast-cleaning abrasives. 1.n ISO-11126, Non-metallic blast-cleaning abrasives. 1.o ISO-11127, Test methods for non-metallic blast-cleaning abrasives. 1.p ISO-8501-2, Preparation of Steel Substrates before Application of Paints and Related Products-Visual

assessment of surface cleanliness. Part 2, Preparation grades of previously coated steel substrates after localized removal of previous coatings.

1.q ISO 8502-7, Preparation of steel substrates before application of paints and related products- Tests for the assessment of surface cleanliness. Part 7, Field method for the determination of oil and grease

3. APPENDICES AND ENCLOSURES:

APPENDICES

APPENDIX TITLE APPLICABLE TO

THIS PPI

1 QA INSPECTION FORM – ENVIRONMENTAL READINGS Y

2 QA INSPECTION FORM – CLEANLINESS CHECKPOINT Y

3 QA INSPECTION FORM – SURFACE PROFILE /PREPARATION & CLEANLINESS LOG Y

4 QA INSPECTION FORM - SURFACE CONDUCTIVITY LOG

Y

5 QA INSPECTION FORM - PRESSURE SENSITIVE TAPE SAMPLES Y

6 QA INSPECTION FORM - PAINT APPLICATION EQUIPMENT & PAINT CONSUMPTION LOG

Y

7 QA INSPECTION FORM – DRY FILM THICKNESS MEASUREMENTS Y

7A QA INSPECTION FORM – WET FILM THICKNESS MEASUREMENTS (For use with solvent coating systems)

N

8 COATING SYSTEM - CONTAINED IN INDIVIDUAL PPI's TO SPECIFY COATING SYSTEM AND COATING SYSTEM DFT's

N

ENCLOSURES

ENCLOSURE TITLE

1 SURFACE CONDUCTIVITY TESTING PROCEDURE Y

2 CHECKPOINTS & MILESTONES COMPLETION & SIGN OFF LOG Y

Page 4: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 4

August 23, 2011 REV 27

4. REQUIREMENTS: 4.1 SAFETY: Accomplish the safety precautions as specified in NSTM 631, Section 2, Ref. 2.e, and the Job

Order during surface preparation and the application of marine coatings.

4.2 WORK NOTICE: The contractor shall post the notice at the ship’s quarterdeck or other designated location for each job or separate area at least four hours, but not more than 24 hours, prior to the start of work. The notice shall contain the following information: ship’s name and hull number, work item number, compartment or frame number, identification of hazard, date and time of work process and identification of engineering and work practice controls. Deliver notification of work planned for a weekend or Monday following that weekend to the Commanding Officer’s representative not later than 0900 on the Friday immediately preceding that weekend. Deliver notification of work planned on a federal holiday and on the day following the federal holiday to the Commanding Officer’s representative not later than 0900 on the last working day preceding the federal holiday.

4.3 QUALITY ASSURANCE REQUIREMENTS: 4.3.1 REQUIREMENTS FOR COATED AREAS. Surface preparation shall be accomplished by certified blasters. Coating systems shall be applied by certified painters and test / inspection records maintained IAW the requirements of NAVSEA Standard Item 009-32. Checkpoints and final inspections shall be signed off by certified coating inspectors. 4.3.2 BLASTERS AND PAINTER CERTIFICATION. The implementing contractor shall maintain a current certification in accordance with the Society for Protective Coatings (SSPC) QP-1 program for the duration of the project. The implementing contractor shall maintain a certification program for blasters and painters working on the project IAW SSPC-C-7 NAVSEA Standard Item 009-32. . The company shall provide adequate records verifying the completion and currency of training for each painter involved in surface preparation and

application of the coating. Documentation shall be maintained verifying that only certified blasters and painters are used for preservation work. Training shall include all paint application techniques and procedures appropriate to the surface preparation and coating materials used.

4.3.3 COATING INSPECTOR CERTIFICATION: The implementing contractor shall maintain a certification program

for coating inspectors working on the project IAW the requirements of NAVSEA Standard Item 009-32. Documentation shall be maintained verifying that only certified paint inspectors are used for inspecting preservation work. Training shall include all techniques and procedures appropriate to inspecting the surface preparation and coating application being used. These techniques and procedures include determining the acceptability of surface preparation prior to commencement of paint application; determining the degree of compliance with painting procedures appropriate to the surface preparation and coating materials being used; and determining the acceptability of finished products IAW established standardized acceptance criteria. Coating inspectors shall be certified in accordance with the NAVSEA Basic Paint Inspector (NBPI) course, NACE International Coating Inspector Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector program (PCI). Coating inspectors shall also have a minimum of 2 years of marine coatings related work experience.

4.3.4 COATING INSPECTOR RESPONSIBILITIES: Coating inspectors are responsible for requirements listed in NSTM 631, Section 11.7. 4.3.4.1 The Government shall designate a certified coating inspector as the Responsible Government Representative, who shall verify checkpoints and sign all applicable Appendices. 4.3.4.2 The Implementing Contractor shall designate a certified coating inspector, who shall perform all in-process

inspections and checkpoints. 4.3.4.3 The Responsible Government Representative shall be present for and verify all in-process inspections /checkpoints. 4.3.4.4 The Implementing Contractor shall participate in a joint Ship’s Force and Contracting Regional Maintenance Center personnel safety brief, when directed by the Contracting Regional Maintenance Center. NOTE: ALTHOUGH SOME SPACES ARE NOT “CRITICAL COATED AREAS” AS LISTED IN 009-32, PPI’S SHALL USE

NAVSEA STANDARD ITEM 009-32 TO COVER CONTROLS ON THE PRESERVATION PROCESS.

Page 5: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 5

August 23, 2011 REV 27

4.3.5 IN-PROCESS INSPECTIONS: Inspections are to be completed in critical coated areas listed in NAVSEA Standard

Item 009-32. The Responsible Government Representative certified coating inspector shall be given prior notice and shall perform an inspection of each coated area when the following checkpoints are reached: pre-surface preparation & cleaning, contamination containment and masking, surface preparation, paint storage area, mixing, prime coat, between each successive coat of paint, topcoat of paint applied and area ready for final inspection. The Responsible Government Representative is also required to examine all data maintained by the paint foremen concerning environmental conditions, surface cleanliness, surface profile, and paint thickness. Data shall be verified, depending on the checkpoint in question, including surface cleanliness, surface profile, dry film thickness and workmanship. Environmental data, such as temperatures, relative humidity and dew point need only be verified if the inspector is doubtful of the recorded values. Deficiencies in personnel training, certification, record maintenance, equipment maintenance or any matter that is not IAW good painting practice shall be recorded. The coating inspector shall verify the successful completion of each checkpoint and sign and date the applicable spaces on Enclosure 2.

4.3.6 DEVIATIONS: All surface preparation and coating applications shall be IAW delineated guidance herein. Any deviation will require NAVSEA approval and Contracting Officer (or representative) sign-off. 4.3.7 A TYCOM / NAVSEA authorized representative shall provide QA oversight of this process. The Implementing Contractor shall provide the Government QA inspector a minimum of four (4) hour notification of all checkpoints prior to accomplishing the checkpoint. 4.4 RECORD KEEPING: NOTE: THE IMPLEMENTING CONTRACTOR IS RESPONSIBLE FOR RECEIVING AND MAINTAINING

DOCUMENTATION FROM ANY SUBCONTRACTOR THAT THE IMPLEMENTING CONTRACTOR HAS CONTRACTED TO PERFORM ANY PORTION OF SYSTEM INSTALLATION.

4.4.1 RECORD KEEPING DURING SURFACE PREPARATION / PAINT APPLICATION: A permanent record

of environmental conditions, surface preparation and paint application operations shall be maintained. Data shall be entered on Appendices 1 - 5. The record shall include dates and times of surface preparations and painting operations, air temperatures, surface temperature, relative humidity and dew point. Enter on Appendix 3 the abrasive blast media QPL, manufacturer, type and size of abrasive used (when used). All appendices and data logger information shall be provided to the Contracting Regional Maintenance Center upon completion of the coating system installation. This information shall be retained for 3 years.

4.4.2 REVIEW OF RECORDS FOR FINAL COATING EVALUATION: A certified coating inspector authorized to represent NAVSEA shall review paint records and Appendices of each critical area to ensure the coating installer has maintained adequate quality control of the painting process. Records shall include all the test and inspection data required by NAVSEA Standard Item 009-32. Failure to produce such records, or records which indicate that surface preparation and painting was not done IAW governing specifications/instructions, shall be grounds for rejection. 4.5 TEMPORARY SERVICES: The project shall require temporary services such as, but not limited to, lighting,

compressed air, ventilation, fresh water, electrical services, and crane service. Ensure all equipment is in compliance with safety requirements delineated in NSTM 631, Section 2. 4.5.1 Record and restore existing painted labels, compartment designations, hull markings, and other painted information that must be removed or covered during cleaning and painting operations. 4.6 FORWARDING APPENDICES AND RETENTION OF RECORDS: After the project is completed, forward two copies of the completed Appendix forms to the TYCOM, and Contracting Regional Maintenance Center. Records shall be maintained by the Contracting Regional Maintenance Center for a period of 3 years. 4.7 LOG OF EQUIPMENT & MATERIAL USED: Record equipment information and material used in Appendix 6. Compare materials used, to paint materials and abrasive blast media (when used), specified in work order or contract. 4.8 ENVIRONMENTAL CONDITION READINGS: Environmental information on Appendix 1 shall be manually measured and recorded every 24 hours. Environmental readings shall be posted at the job site at all times, and an updated copy provided to the coating inspector and the Responsible Government Representative at each checkpoint for review. At each 24-hour recording period the readings shall be reviewed to determine if

Page 6: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 6

August 23, 2011 REV 27

the environmental conditions are suitable for continued coating system installation. Additionally, a data logger shall be used to continuously monitor environmental conditions (air temperature, % relative humidity, and dew point) from just prior to, through 48 hours after the application of a coat of paint IAW Ref. 2.c and NAVSEA Standard Item 009-32. NOTE: IF DATA LOGERS ARE NOT USED ENVIRONMENTAL READINGS SHALL BE TAKEN MANUALLY EVERY 4 HOURS. 4.8.1 Do not exceed the Maximum Relative Humidity levels after satisfactory soluble salt conductivity level has been attained and satisfactory visual substrate surface condition has been achieved for specific areas as follows: ballast tanks, floodable and dry voids, fuel/compensating fuel tanks and vent plenums - 50% for 15-20 year service life - 85% for 10-12 year service life; CHT tanks 50% for 6-8 year service life - 85% for 4-6 year service life; all other areas - 85%. 4.8.2 The application of moisture tolerant coating systems (MIL-PRF-23236, Type VII, Class 17 or products listed on the latest NAVSEA approved coatings message as moisture tolerant) are exempt from relative humidity and dew point requirements since they may be applied on damp surfaces. NOTE: DATA LOGGERS ARE NOT REQUIRED WHEN INSTALLING MOISTURE TOLERANT COATING SYSTEMS. 4.8.3 If environmental conditions are not provided or are unclear, contact Contracting Regional Maintenance Center for resolution. 4.9 TEMPERATURES TO BE MAINTAINED FOR PAINT COATING SYSTEMS: Immediately prior to application of

each layer of the coating system substrate surface temperature shall be taken. Readings shall be taken in five randomly chosen locations on the layer within the space and the highest and lowest surface temperatures measured recorded in Appendix 1. Additionally, readings shall be taken in five randomly chosen locations on the layer within the space and the highest and lowest surface temperatures measured recorded prior to resuming application of a layer of the coating system when there has been a temporary work interruption. Application of the next layer of the coating system shall not commence (or recommence after a temporary work interruption) until all recorded surface temperature readings are within the required range as specified in Ref. 2.c and NAVSEA Standard Item 009-32. If any reading is outside of the required range, the contractor must take additional action to control the temperature in the space and return the surface temperature readings to within the required range. Additional readings shall be taken a minimum of hourly until the readings are returned to within the required range. If inconsistencies between the acceptable ambient and surface temperature ranges in Ref. 2.c and NAVSEA Standard Item 009-32 exist, the more stringent requirements shall be followed. If required ambient and surface temperatures are not provided or are unclear, contact Contracting Regional Maintenance Center for resolution.

4.10 CONTAMINATION CONTAINMENT AND MASKING FOR SURFACE PREPARATION AND PAINTING

OPERATIONS: The following requirements shall be observed, in addition to the specific requirements of the Job Order, for maintaining cleanliness of the ship, ship’s equipment, components, and spaces for the duration of the availability.

4.10.1 Prevent contamination and surface damage of the ship’s equipment, components, and spaces during contamination-

producing operations. 4.10.1.1 Plug, blank, wrap, cover, seal, and mask equipment, components, cables, wire ways, boats, and openings using fire

retardant/ water repellent materials, and prevent entry of contaminants to machinery, winches, rigging, machinery surfaces, weapons systems, electrical equipment, electronic equipment, valves, vents not in use, and other openings.

4.10.1.2 Install covering conforming to A-A-55308 and/or fire retardant plywood. 4.10.1.3 Install fire retardant industrial filter material on the intake of supply and exhaust end of ventilation systems that will be

in use. 4.10.1.4 Remove existing and install new filter or clean the filter material when airflow is restricted. 4.10.1.5 All protective measures are to be in place prior to start of any contamination-producing operations and shall remain in place until the contamination-producing operations are complete.

Page 7: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 7

August 23, 2011 REV 27

4.10.1.6 Install double curtain baffles at the entrances of each access where airborne contamination could occur during

contamination-producing operations. Install a dirt-collecting mat on the deck directly inside each access. The Contracting Regional Maintenance Center shall select a maximum of four doors. Tagout doors not designated for access.

4.10.1.7 Temporary coverings shall not be removed during contamination-producing operations without permission of the

Contracting Regional Maintenance Center. 4.10.2 PROTECTIVE COVERING: Inspect the integrity of the protective covering at the beginning of each shift in which

contamination-producing operations will be accomplished. Ensure that equipment and machinery have not been infiltrated by contaminants. Notify the Contracting Regional Maintenance Center immediately by verbal means, followed on the next workday in writing, if contamination or surface damage has occurred. Reseal to prevent further entry of contaminants or surface damage.

4.10.3 Maintain cleanliness of the work site free from accumulation of industrial debris caused by contractor and /or

subcontractor employees on a continuous basis throughout the availability. Workspaces include those areas immediately under and adjacent, and those areas where service lines are run.

4.10.3.1 Area cleaning shall be accomplished no later than at the end of each shift, on a daily basis and prior to any

checkpoints. 4.10.3.2 Remove and dispose of industrial debris from the ship on a daily basis. 4.10.4 The Contracting Regional Maintenance Center, Implementing Contractor and the ship’s Commanding Officer’s

representative shall accomplish a joint initial walk-through of all locations aboard ship where contractor responsible work will take place, to observe cleanliness conditions. The inspection shall take place prior to the commencement of any work by the contractor.

4.10.4.1 Submit four legible copies of a written report of any unclean sites/spaces to the Contracting Regional Maintenance

Center and Commanding Officer of the ship within 72 hours after completion of the inspection. 4.10.5 The Contracting Regional Maintenance Center, Implementing Contractor and the designated representative of the

ship’s Commanding Officer shall also accomplish a daily cleanliness inspection whenever work is in progress. During inspection the activity responsible for dirtying the space shall be determined. A written report of any unclean work sites/spaces shall be prepared by the contractor and copies distributed to the Contracting Regional Maintenance Center and Commanding Officer of the ship within four hours after completion of the inspection. The inspection

report shall list the responsible activity (contractor, ship, etc.) for each unclean site/area. Unclean sites/areas determined as contractor responsible shall be immediately cleaned.

4.10.5.1 Inspections and reporting shall be accomplished during the daily fire prevention and housekeeping inspections. 4.10.6 COVERING REMOVAL: Remove protective covering upon completion of contamination-producing operations and

inspect for presence of contamination or surface damage. Notify the Contracting Regional Maintenance Center immediately by verbal means, followed on the next workday in writing, if contamination or surface damage has occurred. The contamination shall be removed and damage repaired immediately after notifying the Contracting Regional Maintenance Center.

4.10.7 Remove from the ship and dispose of debris and foreign matter generated during contractor work on the ship at a

minimum of once per shift. Comply with the requirements of federal, state, and local laws, codes, regulations, and ordinances or as specified elsewhere in the Job Order.

4.11 ISOLATION, BLANKING AND TAGGING REQUIREMENTS: Notify the Commanding Officer’s representative in

writing of equipment, systems, circuits, components, piping, and valves that require isolation to accomplish work in the Work Item before any work is started on each individual Work Item so that tag-outs shall be accomplished as

required by ship’s instructions. 4.11.1 After ship’s force install tags; the Implementing Contractor shall verify use of sufficient tags to prevent operation of

equipment, systems, circuits, components, piping, or valves from all stations that could cause damage to equipment or personnel injury.

Page 8: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 8

August 23, 2011 REV 27

4.11.2 A contractor’s representative shall print name, badge number, identify company, and sign on a ship’s tag-out record sheet and tags after installation, indicating repair activity satisfaction with the completeness of the tag-out and

alerting personnel removing tags that contractor concurrence is required prior to clearing the tag. 4.12 Post warning signs and barriers and install temporary positive means to prevent closure or movement of components that may create a safety hazard. 4.13 Do not disturb, modify, remove, energize, or operate any switch, fitting, valve, or other equipment affixed with a ship’s isolation, CAUTION or DANGER tag. 4.13.1 Do not remove or relocate ship’s isolation, CAUTION or DANGER tags. 4.13.2 Notify the Commanding Officer’s representative immediately when the contractor’s work is complete and the system,

piping, or circuit is ready for removal of tags. 4.13.3 The contractor’s representative shall sign the ship’s tag-out log sheet to show concurrence in tag removal and

clearance before removal of any tag. 4.13.4 Verify removal and clearance of all isolation or DANGER tags in accordance with ship’s instruction before the

equipment is operationally tested or operated. 4.14 When performing QA inspections for holidays and DFT readings, for all areas where aesthetics are not an issue,

permanent markers conforming to ASTM D4236 (Paint and Related Coating Standards) are recommended to delineate defects, low DFT or other conditions. The markers can be applied to any coat in the system (not on bare substrate) and can be overcoated with any coat in the system. If the defect has been satisfactorily addressed, any bleed through or perimeter marking remaining can be ignored provided the coating is not visible to ship’s force during normal operations. Duct tape and masking tape with the exception of extended release type masking tape shall not be used to delineate defects, low DFT or other conditions.

5. PRE-SURFACE PREPARATION: 5.1 STRUCTURAL INSPECTION: Prior to commencement of work, the government shall provide an authorized

representative to conduct a structural inspection for the entire area to be prepared. Heavily rusted or corroded areas, damaged metal, and holes in the structure or piping shall be documented and provided to both ship’s force and the Contracting Regional Maintenance Center to determine if further structural evaluation or NDT is warranted, and for possible repair before surface preparation.

5.2 PRE-SURFACE CONDITIONING: Before surface preparation the Contracting Regional Maintenance Center shall

have all welds, protrusions, projections and spikes ground smooth and flush with the deck; pits in the welds shall be ground out; all weld splatter shall be removed. If using a non-edge retentive coating radius all edges, flanges, cutouts, angles, pipe hangers and foot/hand holds to a minimum radius of 3mm.

NOTE: RADIUSING OF EDGES, FLANGES, CUTOUTS, ANGLES, PIPE HANGERS, AND FOOT/HAND HOLDS IS NOT

REQUIRED WHEN USING APPROVED EDGE RETENTIVE COATINGS. 5.3 DEGREASE / FRESH WATER WASH DOWN: Prior to surface preparation by dry abrasive blasting, remove all

surface contaminants in accordance with SSPC-SP1 with 3,000 psi minimum at the nozzle fresh water wash down. Use vacuum to remove standing water followed by an adequate period of time to allow the surface to dry prior to surface preparation.

5.4 CHECKPOINT (Pre-Surface Preparation): NOTES: ULTRAVIOLET LIGHTS SHALL NOT BE USED IN MERCURY EXCLUSION AREAS. THE WATER-BREAK TEST

SHALL BE USED IN LIEU OF ULTRAVIOLET LIGHT IN MERCURY EXCLUSION AREAS. YELLOW OR AMBER TINTED GLASSESTHAT PROTECT THE EYES FROM ULTRAVIOLET LIGHT MUST BE

WORN WHEN CONDUCTING ULTRAVIOLET LIGHT INSPECTION. SEE ASTM E2501 FOR THE LIGHT TRANSMITTANCE SPECIFICATION FOR TINTED GLASSES AND HTTP://WWW.NSTCENTER.COM FOR A LIST OF SAFETY EYEWEAR MODELS THAT MEET THE SPECIFICATION.

Page 9: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 9

August 23, 2011 REV 27

5.4.1 (Visual and Ultraviolet (UV) Light or Water-Break Test): Conduct a visual inspection to verify all surfaces within the

scope of the project are free of hydrocarbons, and other contaminants such as sea salts, loose rust, mud, and marine growth, which could become imbedded in the surface to be prepared. Inspect surface using a UV light (approx. 60 Å) to detect hydrocarbons on the surface. The ultraviolet light will not allow the proper detection of hydrocarbons on the surface if the surface being inspected is exposed to day or artificial light. Therefore for proper UV light hydrocarbon

detection, lights must be off for interior spaces, and the inspection must be conducted during darkness for surfaces

exposed to sunlight. Take appropriate safety measures to prevent worker hazards in the darkened space. A Water-Break Test may be used in lieu of Ultraviolet Light and must be used in mercury exclusion areas.

5.4.1.1 When using the Ultraviolet (UV) Light Test and hydrocarbons are present, the hydrocarbons will fluoresce as bright

green, lime green, or blue/violet on the surface. 5.4.1.2 When performing the Water-Break test, spray a mist of atomized distilled water to form a uniform film on a 1 ft² surface area for every 200 ft² of surface area to be tested. After a period of one minute observe the film to

determine if it is still intact, or if it has separated due to the presence of hydrocarbons on the surface. 5.4.1.3 To remove detected contaminants or hydrocarbons, accomplish a solvent wipe on affected areas. Follow SSPC-SP-1

to remove contaminants and hydrocarbons. 5.4.1.4 If contaminants or hydrocarbons are detected on the surface after attempting to solvent spot repair, the entire surface

shall be de-greased again as directed in paragraph 5.3. 5.4.1.5 Document results of the Visual and Ultraviolet (UV) Light or Water-Break Test on Appendix 2 (CLEANLINESS CHECKPOINT).

5.4.2 (Structural and Pre-Surface Conditioning): Verify all surfaces within the scope of the project are IAW paragraphs 5.1 & 5.2. 5.4.3 (Contamination Containment and Masking): Verify all surfaces within the scope of the project are IAW paragraphs

4.10 through 4.11.

6. SURFACE PREPARATION:

6.1 Per paragraph 4.8, continuously monitor environmental conditions (surface and air temperature, % relative humidity, and dew point). Environmental readings are not required for surface preparation for nonskid.

NOTES: CONTRACTING REGIONAL MAINTENANCE CENTER SHALL DESIGNATE THE PPI FOR USE TO DETERMINE SSPC LEVEL OF SURFACE PREPARATION.

IN ADDITION TO THE SSPC LEVEL OF SURFACE PREPARATION STATED IN INDIVIDUAL PPI’S THE HEAT INDUCTION METHOD FOR SURFACE PREPARATION IS ALLOWED IN THE FOLLOWING AREAS. (1) WEATHER, FLIGHT, VERTICAL REPLENISHMENT, AND CATAPULT DECKS (2) UNDERWATER HULL (3) FREEBOARD (4) SUPERSTRUCTURE (5) VENT INTAKE PLENUMS (6) GAS TURBINE AND DIESEL INTAKES AND EXHAUSTS (7) BALLAST TANKS AND VOIDS (NOT RECOMMENDED IN TANKS AND VOIDS WHERE THERE IS A HIGH AMOUNT OF COMPLEX GEOMETRY. NOT FOR USE IN FUEL/COMPENSATING FUEL OR CHT TANKS) (8) BILGES (NOT RECOMMENDED IN BILGES WHERE THERE IS A HIGH AMOUNT OF COMPLEX GEOMETRY) THE HEAT INDUCTION METHOD OF SURFACE PREPARATION WILL PRODUCE A CLEANLINESS LEVEL EQUIVALENT TO CLEAN TO BARE SUBSTRATE. THE SURFACES, WHEN VIEWED WITHOUT MAGNIFICATION, SHALL BE FREE OF ALL VISIBLE OIL, GREASE, DIRT, DUST, PAINT, CORROSION PRODUCTS, AND OTHER FOREIGN MATTER, BUT THE SURFACE MAY SHOW LIGHT SHADOWS, SLIGHT STREAKS, OR MINOR DISCOLORATIONS, CAUSED BY STAINS OF CORROSION PRODUCTS OR STAINS OF PREVIOUSLY APPLIED PAINTS. PRESENTLY THE HEAT INDUCTION METHOD OF SURFACE PREPARATION IS ONLY EFFECTIVE ON STEEL

Page 10: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 10

August 23, 2011 REV 27

SUBSTRATES. CURRENTLY ONLY NAVAL SHIPYARDS ARE ALLOWED TO USE HEAT INDUCTION AS A METHOD FOR SURFACE PREPARATION. HEAT INDUCTION COATING REMOVAL SHALL BE USED IN ACCORDANCE WITH UNIFORM INDUSTRIAL PROCESS INSTRUCTION (UIPI) 1905-115. THE FOLLOWING INFORMATION PERTAINS TO BLASTOX ABRASIVE ADDITIVE. 1. BLASTOX SHALL NOT BE INCLUDED IN ANY MIL-A-22262 GRIT SUPPLIED TO U.S. NAVY FACILITIES

AND/OR CONTRACTORS WITHOUT AN EXPRESS, WRITTEN REQUEST FROM A NAVY PROGRAM, PROJECT, OR PRODUCTION MANAGER. THE WRITTEN REQUEST MUST STATE THAT LEAD (PB) HAS

BEEN FOUND IN A GIVEN PORTION OF THE SHIP AND THAT AS SUCH THE USE OF BLASTOX WILL REDUCE WASTE DISPOSAL COSTS AND LEAD EMISSION RISKS.

2. BLASTOX ADDITIONS TO MIL-A-22262 SHALL BE NOTED ON ALL SHIPPING, ORDERING, AND WASTE-

DISPOSAL DOCUMENTATION AND AN MSDS FOR BLASTOX SHALL BE PROVIDED WITH EACH LOT OF MATERIAL TO THE U.S. NAVY FACILITIES AND/OR CONTRACTOR FACILITY AT WHICH THE PRODUCT WOULD BE USED. 3. BLASTOX SHALL BE ADDED AT NO MORE THAN 15% BY WEIGHT TO THE MIL-A-22262 PRODUCT AS PER THE NAVSEA 05M1 1995 LETTER. 4. BLASTOX SHALL NOT BE USED ON SUBMARINES. 5. BLASTOX SHALL NOT BE ALLOWED TO BE USED IN JOBS THAT ARE RECOATING POTABLE WATER TANKS, RESERVE FEEDWATER TANKS, FRESHWATER DRAIN COLLECTING TANKS, OR ANY SPACES COVERED BY THE REACTOR PLANT PAINT SCHEDULE.

6.2 Accomplish the surface preparation requirements of NAVSEA Standard Item 009-32 for the location/area being prepared. Minimum requirement is SSPC-SP-10 for dry abrasive blasting. SSPC-SP-10 immediately after completion of blasting operations and light flash rust immediately prior to application of first coat of paint for wet abrasive

blasting and SSPC-SP-12 WJ-2 L for UHP water jetting. For dry and wet abrasive blasting for steel surfaces the blast media must meet the requirements specified in MIL-A-

22262 or A-A-1722, or A-A-59316. The abrasive blast medium must be listed on the Qualified Products List (QPL), or have written notification from NAVSEA indicating QPL approval.

Accomplish a surface profile of 2.0 - 4.0 mils (50-100µ) with the exception of flight and weather decks where nonskid is to be applied the surface profile is to be 3.0 – 6.0 mils (75-152.4µ).

6.2.1 If wet abrasive blasting is the method chosen for steel surface preparation then the following requirements apply: 1. Immediately after completion of blasting operations (before the surface has had a chance to flash rust), the surface

must be dried, inspected and verified to conform to SSPC-SP-10. SSPC-VIS-5, C-WAB-10 or D-WAB-10 may be used as a visual standard.

2. Immediately prior to application of first coat of paint, the surface must be inspected and verified to have no more

than "Light" flash rusting. SSPC-VIS-5 gives both a written definition of "Light" flash rusting, and C-WAB-10L may be used as a visual standard.

6.2.2 If dry or wet abrasive blasting is the method chosen for aluminum surface preparation then the following requirements

apply: Surface preparation required for all aluminum surfaces is a cleanliness level equivalent to the near-white level Required for steel surfaces. The aluminum surfaces, when viewed without magnification, shall be free of all visible oil,

grease, dirt, dust, paint, corrosion products, and other foreign matter, but the surface may show light shadows, slight streaks, or minor discolorations, caused by stains of corrosion products or stains of previously applied paints For dry and wet abrasive blasting for aluminum surfaces the blast media must be garnet or aluminum oxide that meet the requirements of MIL-A-22262 and must be listed on the QPL, or have written notification from NAVSEA indicating

Page 11: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 11

August 23, 2011 REV 27

QPL approval. Accomplish a surface profile of 2.0 - 4.0 mils (50-100µ) with the exception of flight and weather decks where nonskid is to be applied the surface profile is to be 3.0 – 6.0 mils (75-152.4µ).

NOTE: IF A MANUFACTURER REQUIRES A SURFACE PROFILE GREATER THAN 4 MILS FOR NON FLIGHT AND

WEATHER DECK SURFACES OR 6 MILS FOR FLIGHT AND WEATHER DECK SUBSTRATES THE MANUFACTURER’S REQUIREMENT SHALL TAKE PRECEDENCE.

6.2.3 Recyclable Encapsulated Abrasive Media material conforming to SSPC-AB 4 and process may be used as an

alternative to obtain SSPC-SP-10 or SSPC-SP-11 cleanliness.

6.2.4 Recyclable ferrous metallic abrasive materials conforming to SSPC-AB-3 of Ref. 2.a. may be used as an abrasive blast media for steel substrates. 6.2.4.1 Cleanliness of recyclable ferrous metallic abrasive materials shall be measured and maintained in accordance with the requirements of SSPC-AB-2 of Ref. 2.a. 6.2.4.2 Submit one legible copy to the Contracting Regional Maintenance Center, in hard copy or electronic media, of the results of the quality control requirements of paragraph 6 of SSPC-AB-2 and the quality assurance test required by paragraph 5 of SSPC-AB-3. 6.3 When a medium durability PPI specifies moisture tolerant system installation UHP water jetting shall be used for

surface preparation. Accomplish the surface preparation requirements of NAVSEA Standard Item 009-32 for the locations/area being prepared. Minimum requirement is SSPC-SP 12, UHP WJ-2L.

6.3.1 If difficulty is experienced meeting the required conductivity levels when UHP water jetting, ensure that water from the UHP water jetting is not allowed to sit or pool on the prepared surface. If difficulty is still experienced with no water allowed to remain on the prepared surface then consideration should be given to using water with conductivity

below 70 microsiemens/cm for non-immersed applications and 30 microsiemens/cm for immersed applications.

6.3.2 For UHP water jetted area a blow down is required; using dry, oil free compressed air, blow down all horizontal and vertical surfaces, starting at the top working downward. Perform blotter test for oil and water IAW Ref. 2.r.

6.3.3 For areas prepared to SSPC-SP-12, UHP water jetted surfaces will retain the surface profile prior to surface treatment. In areas where the substrate is below the required profile, use a profile producing power tool or abrasive blasting to achieve a minimum 2.0 mil surface profile for areas other than nonskid. For nonskid areas the minimum surface profile is 3.0 mils.

NOTES: GRINDERS AND SANDERS MAY BE USED TO PREPARE COATINGS OR REMOVE PAINT BUT ARE NOT

AUTHORIZED FOR SURFACE PREPARATION. FOR ALUMINUM DECKS: GRINDERS AND SANDERS SHALL BE EQUIPPED WITH 16-GRIT ALUMINUM OXIDE

ABRASIVE PADS. ABRASIVE MATERIALS (PADS, BELTS) SHALL NOT HAVE BEEN PREVIOUSLY USED TO PREPARE COPPER NICKEL METAL FOR PAINTING OR TO REMOVE COPPER BASE ANTI-FOULING PAINTS.

6.4.1 For low durability PPI's surface preparation shall be power tool cleaning to bare metal with a minimum surface profile

of 1.0 mil. If grinders or sanders that burnish, polish, or smooth a surface are used to produce a bare metal substrate and a 1.0 mil surface profile the expected coating system service life stated in the individual low durability PPI will be reduced by 50%.

6.4.2 POWER TOOL CLEANING ON STEEL SURFACE AREAS AS DETERMINED BY INSPECTION AND AGREED TO

BY THE REGIONAL CONTRACTING MAINTENANCE CENTER INACCESSIBLE TO ABRASIVE BLASTING OR UHP WATER JETTING:

6.4.2.1 For high and medium durability PPI's accomplish the requirements of SSPC-SP-11 Power Tool Cleaning to Bare Metal to remove all the existing coating and corrosion products. Surface preparation accomplished using a surface

preparation device such as a disk sander or power wire wheel that burnishes polishes or smoothes the surface is not authorized. A minimum 2.0 mil surface profile shall be achieved using surface profile producing tools such as

needle guns, star cutters, deck abraders, recyclable encapsulated abrasive media material conforming to SSPC-AB 4, etc.

6.4.2.2 Feather edges of adherent paint in adjacent areas remaining after cleaning.

Page 12: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 12

August 23, 2011 REV 27

6.4.2.3 The Contracting Regional Maintenance Center shall have the authority to reject this method in any area if the surface can be shown to have adequate accessibility for abrasive blasting or UHP water jetting.

6.4.3 POWER TOOL CLEANING ON ALUMINUM SURFACE AREAS AS DETERMINED BY INSPECTION AND AGREED

TO BY THE REGIONAL CONTRACTING MAINTENANCE CENTER INACCESSIBLE TO ABRASIVE BLASTING OR UHP WATER JETTING:

These areas shall be prepared to a surface cleanliness as follows:

The surface when viewed without magnification shall be free of all visible oil, grease, dirt, dust, mill scale, rust, paint, oxide, corrosion products, and other foreign matter. Slight residues of rust and paint may be left in the lower portion of pits if the original surface is pitted. Surface preparation devices such as disk

sanders or power wire wheels that burnish, polish or smooth the surface are not permitted. A minimum 2.0 mil surface profile shall be achieved using surface profile producing tools such as needle guns, star cutters, deck abraders, etc. Before work begins, the owner and contractor must agree on the areas where power tool cleaning is permitted.

6.4.3.1 Feather edges of adherent paint in adjacent areas remaining after cleaning.

6.4.3.2 The Contracting Regional Maintenance Center shall have the authority to reject this method in any area if the surface can be shown to have adequate accessibility for abrasive blasting or UHP water jetting.

6.5 CHECKPOINT (Surface Preparation): Accomplish IAW NAVSEA Standard Item 009-32. The record shall show the extent of the inspection and detailed results. The degree of surface cleanliness shall be IAW the NACE/SSPC surface preparation standard specified; surface profile, soluble salt measurements, and adequacy of cleanup operations shall be recorded. The inspections shall be conducted to standardized acceptance criteria. Visual aids provided in Ref. 2.f, Ref. 2.g, or Ref. 2.h may be used to ensure quality standards are met; however, the written descriptions in the NACE/SSPC standards shall govern. Enter data on all applicable Appendices.

NOTE: FLASH RUSTING ON A STEEL SURFACE SHALL NOT EXCEED A DEGREE EQUAL TO SSPC-VIS 4 (VISUAL

REFERENCE FOR STEEL CLEANED BY WATER JETTING) STANDARD WJ-2L FOR NONSKID SURFACES AND WJ-2M FOR ALL OTHER SURFACES. IF FLASH RUSTING OCCURS, THE EXTENT OF THE FLASH RUST SHALL DETERMINE THE CORRECT METHOD OF MANAGING THE FLASH RUST. METHODS TO REDUCE THE FLASH RUST TO ACCEPTABLE LEVELS INCLUDE UHP WATER JETTING TO WJ-2L, SSPC-SP-12, SOLVENT WIPING OR HAND WIRE BRUSHING THE SURFACE TO THE SATISFACTION OF THE CONTRACTING REGIONAL MAINTENANCE CENTER.

6.5.1 (Surface Profile Measurements): Surface peak-to-valley profile shall be checked. For each area of preparation, one profile reading shall be taken every 100 sq ft for the first 500 sq ft. Only one profile reading shall be taken for every 1,000 sq ft remaining. Profile readings shall be taken in accordance with Ref 2.d using either Method B or C. For profile readings taken in accordance with Method C of 2.7, use profile tape suitable to read subject profile (i.e., coarse to extra-coarse plus). One profile reading shall be the average (mean) of 3 individual tapes. If areas are found to be greater than 5 mils, use Method B of 2.7 in those areas to determine existing profile. The retention of Testex tape is not required. If minimum profile is not present, proper minimum profile shall be established. The abrasive manufacturer’s type and mesh size used, if applicable, shall be entered on Appendix 3. (SURFACE PROFILE /PREPARATION & CLEANLINESS LOG).

6.5.2 (Soluble Salt Measurements Conductivity Testing): Conductivity samples shall be collected using a product that

meets the requirements of NACE SP0508-2008, “Methods of Validating Equivalence to ISO 8502-9 on Measurement of the Levels of Soluble Salts” (such as the Soluble Salt Conductivity Measurement according to Bresle Method, ARP Soluble Salt Meter model RPCT-07-001, or SaltSmart from Innovative Productivity, Inc.) Enclosure 1 provides the procedure for the Bresle method using a 1250 mm

2 Bresle Sample Patch and a HORIBA B-173 meter or equivalent

NAVSEA approved test equipment . Measurements shall be made randomly over the prepared surface. Take 1 reading for each 200 ft

2 for the first 1,000 ft

2. Take 1 additional measurement for each additional 500 ft² or less. For

immersed applications, conductivity due to soluble salts (total ionic) shall not exceed 30µS/cm (microsiemens/cm). For non-immersed applications, conductivity due to soluble salts (total ionic) shall not exceed 70µS/cm (microsiemens/cm).

6.5.2.1 If conductivity measurements for surfaces prepared to an SSPC-SP-10 exceed the respective values, water wash the

area exceeding the required limit with fresh water. Soluble salt conductivity limit of the fresh water shall not exceed 200µS/cm (microsiemens/cm). If low pressure, 3000 psi, water washing is used, in order to ensure it is effective, the

Page 13: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 13

August 23, 2011 REV 27

operator shall maintain the wand within a maximum distance of 12 inches to the substrate. The angle of the wand relative to the substrate shall be maintained between 45º - 90º. Remove all standing water, dry the area, and retest.

If flash rusting has occurred, or/and soluble salt conductivity still exceed limits rewash, dry the area and retest. If the soluble salt conductivity limit is not reached after 2 washes, then perform water wash to the affected areas using water that is below 30µS/cm (microsiemens/cm) for immersed applications or below 70µS/cm (microsiemens/cm) for non-immersed applications. Repeat water wash and retest until satisfactory levels are obtained. If flash rusting has occurred, reblast the area and retest.

NOTE: IF AFTER A FRESHWATER WASH, THE MEASUREMENTS EXCEED REQUIRED LEVELS, A SALT REMOVER MAY BE USED; HOWEVER, THE ONLY SALT REMOVER PRODUCTS THAT MAY BE USED FOR A COATING SYSTEM ARE THOSE SPECIFIED ON THAT COATING'S NAVSEA-APPROVED ASTM F-718. 6.5.2.2 If conductivity measurements for surfaces prepared to an SSPC-SP-12 exceed the respective values, repeat SSPC-

SP-12 to the affected areas. Remove all standing water, dry the area, and retest. If flash rusting has occurred, reblast the area and retest. Repeat SSPC-SP-12 until satisfactory levels are obtained. If flash rusting has occurred,

reblast the area and retest. 6.5.2.3 If conductivity measurements for surfaces prepared to an SSPC-SP-11 in an isolated area exceed the respective

values, circle area and perform spot solvent cleaning (see table 631-2-1 in NSTM 631 for approved solvent for use) followed by retest6.5.2.4 For surfaces prepared by Power Tool Cleaning to Bare Metal that are not practical for the spot cleaning method, water wash these surfaces with fresh water, and scrub with hand scrub brush. Soluble salt conductivity limit of the fresh water shall not exceed 200µS/cm (microsiemens/cm). Immediately remove all standing water and dry the affected area. Immediately remove all flash rust developed. Anchor profile shall be re-established as required. Perform an SSPC-SP-1 solvent wipe on all sanded areas and retest. If the soluble salt conductivity limit is not reached after 2 washes, then perform water wash to the affected areas using water that is below 30µS/cm (microsiemens/cm) for immersed applications or below 70µS/cm (microsiemens/cm) for non-immersed applications. Repeat necessary steps until satisfactory levels are obtained.

6.5.3 (Environmental): Verify environmental conditions were monitored and maintained IAW paragraphs 4.8 and 4.9. 6.5.4 (Contamination Containment and Masking): Verify all surfaces within the scope of the project are IAW paragraph prior

4.10 to the application of paint. Surfaces must be clean and free of debris and dust. 6.5.5 (Test for Assessment of Surface Cleanliness): Immediately prior to primer coat application the substrate surface shall be checked for dust in accordance with Ref 2.k. The dust rating shall be no greater than Rating 2, Class 2. For structures up to 1,000 ft

2 other than UW hull and Flight deck nonskid, three

readings shall be taken. For every additional 1000 ft2 of area or increment thereof, one 100 ft

2 area shall be randomly

selected and sampled. For UW hull one reading for each 200 ft2 for first 1,000 ft

2 shall be taken. For every additional

500 ft2 of area or increment thereof, one 100 ft

2 area shall be randomly selected and sampled. For flight deck

nonskid, 3 individual readings are required every 100 ft2 for the first 500 ft

2; if the readings are satisfactory, 1

individual reading per 1000 ft2 remaining shall be taken. No reading shall be taken in the same 100 ft

2 area as

another reading. Document readings on Appendix 5 (PRESSURE SENSITIVE TAPE SAMPLES). 6.5.6 All tests and inspections noting unsatisfactory conditions shall result in the termination and rescheduling of the

checkpoint. At rescheduled checkpoint, QA shall document satisfactory corrective actions taken to correct discrepancy.

6.5.7 In order to pass the checkpoint, Appendices 1-5 and Enclosure 2 shall be up to date and submitted to QA. QA shall

sign in the appropriate areas on Enclosure 2. 7. PAINTING REQUIREMENTS: NOTES: CONTRACTING REGIONAL MAINTENANCE CENTER SHALL DESIGNATE COATING SYSTEM TO BE

APPLIED. TO MAINTAIN PROPER SURFACE CONDITIONS AFTER COMPLETION OF THE SURFACE PREPARATION

CHECKPOINT METHODS SUCH AS USE OF DEHUMIDIFICATION EQUIPMENT, ENVIRONMENTAL ENCLOSURES, AND SURVEILLANCE/MONITORING OF THE PREPARED SURFACE SHOULD BE EMPLOYED. COATING APPLICATION MUST START WITHIN 4 HOURS AFTER SURFACE PREPARATION CHECKPOINT COMPLETION AND ACCEPTANCE. COATING APPLICATION SHALL BE CONTINUOUS THROUGH COMPLETION OF THE AREA TO BE COATED. IF COATING APPLICATION HAS NOT STARTED WITHIN 4

Page 14: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 14

August 23, 2011 REV 27

HOURS OF SURFACE PREPARATION CHECKPOINT COMPLETION THE SURFACE PREPARATION CHECKPOINT WITH THE EXCEPTION OF SURFACE PROFILE MUST BE REPEATED.

PAINTING SHALL NOT BE PERFORMED WHEN SUSTAINED WINDS EXCEED 15 MPH, WITHOUT AN

ENCLOSURE. IF A SILICON ALKYD IS TO BE APPLIED DIRECTLY ON TOP OF A SOLVENT FREE COATING, THE SOLVENT

FREE COAT SHALL BE ALLOWED TO CURE FOR MINIMUM OF 24 HOURS BEFORE APPLICATION OF SILICON ALKYD.

WHEN INSTALLING MIL-PRF-23236, TYPE VII COATING SYSTEMS WITH AN AMBIENT TEMPERATURE

GREATER THAN 77F IT IS HIGHLY RECOMMENDED THAT PLURAL COMPONENT EQUIPMENT BE USED FOR COATING SYSTEM APPLICATION.

FOR REPAIRED PIPING SYSTEM WELDS THAT REQUIRE HYDROSTATIC TEST, NO COATINGS ARE TO BE

APPLIED PRIOR TO PERFORMANCE OF HYDROSTATIC TEST. PAINT CONTAINING OPTICALLY ACTIVE PIGMENT (OAP) SHALL BE VISUALLY INSPECTED USING VIOLET

LIGHT; WHEN THIS OCCURS, THE INSPECTOR SHALL USE A VIOLET-LIGHT FLASHLIGHT CONFORMING TO ASTM E2501 TO ENHANCE THE NORMAL VISUAL INSPECTION PROCESS. AN ASTM E2501 FLASHLIGHT PRODUCES VIOLET LIGHT THAT ACTIVATES THE FLUORESCENT OAP. THE INSPECTOR SHALL WEAR YELLOW OR AMBER-TINTED GLASSES THAT BLOCK ULTRAVIOLET AND VIOLET LIGHT TO ACCOMPLISH THE INSPECTION. SEE ASTM E2501 FOR THE LIGHT TRANSMITTANCE SPECIFICATION FOR TINTED GLASSES AND HTTP://WWW.NSTCENTER.COM FOR A LIST OF SAFETY EYEWEAR MODELS THAT MEET THE SPECIFICATION

7.1 WET FILM MEASUREMENTS: WFT readings are required in lieu of DFT readings for any coat that must be in a

tacky state (tacky is defined as that curing (drying) stage when a fingertip pressed lightly, without twisting, against the film meets slight resistance when removed, leaves only a slight impression on the surface of the film, and none of the film sticks to the finger) when the next coat is applied.

7.1.1 During application, a WFT gage shall be used to verify the application of proper paint thickness for each coat of the coating system being installed. Readings shall be taken to confirm this, but need not be recorded. 7.2 DRY FILM THICKNESS MEASUREMENTS: Accomplish IAW Ref 2.b, record measurements in Appendix 7 (DRY FILM THICKNESS MEASUREMENTS). If a MIL-PRF 23236 Type VII coating system is applied and a stripe coat is not installed, in addition to the required DFTs per SSPC-PA 2, a separate set of “edge” DFT readings shall be taken on the top coat in close proximity to corners and edges of area structural elements including, but not limited to stiffeners, “rat holes,” cut-outs, and frames. This data shall be taken in accordance with SSPC-PA 2 with the following modifications:

1) The “edge” gage readings shall be taken approximately ¼ inch (i.e., 0.5 cm) from edges using micro-probe gages

with a probe less than or equal to ½-inch in diameter (such as Elcometer 456 with T456FM3R90A probe or DeFelsko Positector 6000 series gauge with mini probe F90S or F0S). For “edge” readings taken on substrates less than ½-inch thick, readings shall be taken from the “middle” of the substrate. Microprobe gages shall be calibrated, in accordance with manufacturer’s direction, to measure paint thicknesses expected during application.

2) Welds not associated with corners or edges (i.e., a butt weld joining two flat plates) shall be inspected using

standard visual techniques. The inherent roughness of the weld precludes the collection of reproducible data from these areas. Inspectors may, if they choose, take a spot reading within ¼ inch (i.e., 0.5 cm) from a butt weld. Such a reading would be included in the normal, flat surface data set, not the edge or corner data set.

3) An "edge" spot measurement shall consist of 3 gage readings taken within a 1.5 inch (i.e., 4 cm) diameter circle.

Accomplish front, back, and edge DFT gage readings as shown in Figure 1. For each data set required for the flat surface data set the equivalent is required for the edge or corner data set. For example, if 20 spot DFT measurements are required for an area, then 20 DFT measurements are required using the front, back, edge method set and 20 for the flat surface set.

Paint thickness in close proximity to “edges’ will be documented, evaluated, and corrective action taken to satisfy coating application thickness requirements. Coatings thicknesses measured on the flat portions of coated areas in

Page 15: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 15

August 23, 2011 REV 27

accordance with IAW Ref 2.b, and coating thicknesses measured on “edges” shall be used to accept the areas for Navy service. The “flat portion” DFTs and “edge” DFTs shall be documented, and evaluated separately to ensure corrective actions (if necessary) target the appropriate area. Record measurements in Appendix 7 (DRY FILM

THICKNESS MEASUREMENTS).

Figure 1

7.3 RE-COAT PERIODS: Applicator shall conform to manufacturer’s minimum and maximum re-coat periods IAW Ref.

2.c. If the recoat window is exceeded, follow steps specified in paragraph 7.14.3 of this PPI. If the minimum recoat window is not conformed to, the coating must be removed and reapplied.

7.4 DRY PAINT FOR CHECKPOINTS: Paint shall be dry prior to all paint related checkpoints. Dry shall be defined as

fingernail hard. 7.5 LOW OUT OF SPECIFICATION DRY FILM THICKNESS: Failure to meet minimum dry film thickness requirements

shall result in application of an additional coat or coats of paint in deficient areas before the coat can pass the DFT checkpoints.

7.6 HIGH OUT OF SPECIFICATION DRY FILM THICKNESS: Excessive dry film thickness in a coat or cumulative coats

shall be determined IAW the coating table appendix found in the individual PPIs. If excessive DFT is determined, the Contracting Regional Maintenance Center shall be contacted on how to proceed. No sanding without Contracting Regional Maintenance Center approval for higher than specified DFT is to be done. For high solids, edge retentive coating systems, the following DFT information is provided: Total DFT > 30 mils is considered to be excessive. Total DFT up to 50 mils require no action.

7.7 RECEIPT INSPECTION OF COATING MATERIAL:

7.7.1 Receipt inspection of contractor-furnished coatings for non-critical areas shall be based on supplier performance history and one of the following: certificate of compliance or vendor material test certification data. Receipt inspection tests and their criteria may be found in the applicable specification for the paint or coating. Receipt inspection requirements for MIL-DTL-24441 and MIL-PRF-23236 coatings used in critical coated areas are described in paragraph 7.7.2.

7.7.2 Coating manufacturers shall test each batch of coating in accordance with NSTM 631, Table 631-11-1, subsection (1) and provide written documentation of satisfactory receipt inspection testing to each coating installer that purchases coatings for critical areas. As a minimum, receipt inspection conformance tests shall include: density (weight per gallon), consistency (viscosity), dry hard time (73°F), sag resistance, fineness of grind, appearance of dry film, color of dry film, and condition in container. In addition to the receipt inspection documentation the manufacturer shall provide written documentation that the product has been stored properly after receipt inspection testing until it is shipped to the coating installer. The coating installer shall require documentation from the transporting agent of the product that it has been maintained within the temperature range required in Ref. 2.c. A log containing the highest and lowest temperatures that the product was subjected to during transportation shall be sufficient for this purpose. If this documentation is not provided the coating installer can refuse receipt of the product or conduct receipt inspection testing. The responsible government authority shall require the documentation of receipt inspection testing as provided by the manufacturer to the coating installer along with the documentation verifying proper storage by the manufacturer after receipt inspection testing until coating installer receipt. If the coating installer does not provide the above-mentioned documentation, the coating shall not be installed in a critical area. In addition to providing the

Page 16: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 16

August 23, 2011 REV 27

responsible government authority the written receipt inspection testing and proper storage documentation from the coating manufacturer for coatings for critical areas, the coating installer shall also provide written documentation of the date of receipt of the coating from the manufacturer and that the coating has been properly stored from the date of receipt until use. If the coating installer does not provide the above-mentioned written documentation, or if there is evidence that the coating for critical coated areas has not been properly stored, the coating installer shall be required, at their expense, to have the coating in question undergo receipt testing by the manufacturer prior to installation of that coating.

7.7.3 MIL-DTL-24441 and MIL-PRF-23236 coatings for critical coated areas shall have receipt inspection conducted in accordance with paragraph 7.7.2 and NSTM 631, Table 631-11-1 (Quality Control Parameters for Preservation of Critical Coated Areas). (I don’t understand what info 7.7.3 is adding. It seems that this info is covered in 7.7.1 & 7.7.2.)

7.8 CHECKPOINT (Paint Storage): 7.8.1 (Shelf Life): Verify shelf life of material has not expired IAW Ref. 2.c. Record expiration date in Appendix 6 (PAINT

APPLICATION EQUIPMENT & PAINT CONSUMPTION LOG). NOTE: NONSKID PAST ITS SHELF LIFE CANNOT BE USED. PAINT REQUIRES AUTHORIZATION, IF IT IS PAST ITS

SHELF LIFE.

7.8.2 Accomplish a visual inspection of paint storage facilities 24 hours prior to paint being mixed to verify that the paint

storage area ambient temperature is within the minimum and maximum range, 50-90F for paint and nonskid products. The paint storage temperature shall be monitored and recorded every 8 hours for 24 hours prior to the paint being used or the user may do core temp where they measure temp of material of each individual component (after each is mixed but before components are combined) to confirm it is in range of acceptable storage temperatures stated above (50-90 °F). Record measured temperatures in Appendix 1 (ENVIRONMENTAL READINGS).

7.9 PAINT APPLICATION: The use of single or plural component spray equipment is acceptable for application of paint

coats specified below. NOTE: PER REF 2.S, SECTION 3.3, THE PRIMER SHALL BE A CONTRASTING COLOR TO THE BARE STEEL

SUBSTRATE. SUCCEEDING COATS OF THE COATING SYSTEM SHALL BE OF CONTRASTING COLOR. 7.10 When applying prime, stripe, intermediate and topcoat, each must be of a contrasting color. 7.11 MIXING: Mix all paint material thoroughly in their individual container to disperse pigments and assure homogeneity.

Combine and thoroughly mix epoxy components prior to use IAW Ref. 2.c. 7.12 CHECKPOINT (Mixing): Accomplish a visual inspection of paint material to verify proper mixing. 7.12.1 (Mixing): Verify material is mixed thoroughly prior to use IAW Ref. 2.c. Record satisfactory completion on Enclosure 2.

7.13 REPAIRS:

7.13.1 Repairs Made To Paint Within Manufacturer's Overcoating Time Period:

7.13.1.1 Surfaces in which mechanical damage extends into the substrate shall be prepared to SSPC-SP-11 Power Tool Cleaning. The power tool prepared surface shall be feathered into the surrounding intact paint, creating a smooth transition.

7.13.1.2 Surfaces in which the mechanical damage does not extend into the substrate shall be solvent wiped to clean.

7.13.1.3 Hand brush, or in larger areas airless spray the coating system IAW Ref. 2.c.

7.13.2 Repairs Made To Paint Beyond the Manufacturer's Overcoating Time Period:

7.13.2.1 Surfaces in which mechanical damage extends into the substrate shall be prepared to SSPC-SP-11 Power Tool Cleaning. The power tool prepared surface shall be feathered into the surrounding intact paint, creating a smooth transition.

7.13.2.2 The painted surfaces surrounding the Power Tool Cleaned surface that have exceeded the over coating time period must be roughened to provide a surface profile.

Page 17: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 17

August 23, 2011 REV 27

7.13.2.3 Painted surfaces in which the mechanical damage does not extend into the substrate must have the surrounding painted surface roughened to provide a surface profile.

NOTE: NO PAINT SHALL BE APPLIED TO A PAINTED SURFACE THAT HAS EXCEEDED THE OVERCOAT PERIOD WITHOUT THE PROPER REACTIVATING PROCEDURES BEING FOLLOWED.

NOTE: PAINT ONLY REACTIVATED PAINT SURFACES.

7.13.2.4 Hand brush or in larger areas airless spray the coating system IAW Ref. 2.c.

7.13.2.5 Allow for proper drying time as per the manufacturer's instructions after the application of each coat (including damaged touch-up areas).

7.13.3 Recoating Beyond Manufacturer's Overcoating Period:

7.13.3.1 If overcoat period is exceeded, (see Ref. 2.c for maximum and minimum overcoating times), the direction provided in the manufacturer’s ASTM F-718 sheet or the manufacturer’s specific instructions for repair shall be followed.

8. PRIMER COAT APPLICATION: 8.1 Apply prime coat specified in the coating table Appendix found in individual PPIs and IAW NAVSEA Standard Item

009-32. During application, immediately brush out any runs, drips, sags or puddles. 8.2 CHECKPOINT (Prime Coat): Verify prime coat is applied IAW NAVSEA Standard Item 009-32. 8.2.1 (Holiday Inspection): Accomplish a visual holiday inspection of prime coat. Coating containing Optically Active Pigment (OAP) shall be visually inspected using violet light; when this occurs the inspector shall use

a violet-light flashlight conforming to ASTM E2501 to enhance the normal visual inspection process. An ASTM E2501 flashlight produces violet light that activates the fluorescent OAP. The inspector shall wear yellow-tinted glasses that block ultraviolet and violet light to accomplish the inspection. Guidance regarding OAP inspection practices is available in SSPC TU-11.

8.2.2 (Dry Film Thickness): Accomplish dry film thickness measurements IAW Ref. 2.b. 8.2.3 All tests and inspections noting unsatisfactory conditions shall result in the termination and rescheduling of the

checkpoint. At rescheduled checkpoint, QA shall document satisfactory corrective actions taken to correct discrepancy.

8.2.4 In order to pass the checkpoint, Appendices 1, 6 and 7 and Enclosure 2 shall be up to date and submitted to QA. QA

shall sign Enclosure 2 in the appropriate places.

9. STRIPE COAT APPLICATION (if applicable): 9.1 CHECKPOINT (Test for Assessment of Surface Cleanliness): Immediately prior to stripe coat application the primer coat surface shall be checked for dust IAW Ref 2.k. The dust rating shall be no greater than Rating 2, Class 2. For structures up to 1,000 ft

2 other than UW hull and Flight deck nonskid, three

readings shall be taken. For every additional 1000 ft2 of area or increment thereof, one 100 ft

2 area shall be randomly

selected and sampled. For UW hull one reading for each 200 ft2 for first 1,000 ft

2 shall be taken. For every additional

500 ft2 of area or increment thereof, one 100 ft

2 area shall be randomly selected and sampled. For flight deck

nonskid, 3 individual readings are required every 100 ft2 for the first 500 ft

2; if the readings are satisfactory, 1

individual reading per 1000 ft2 remaining shall be taken. No reading shall be taken in the same 100 ft

2 area as another

reading. Document readings on Appendix 5 (PRESSURE SENSITIVE TAPE SAMPLES). (This check is not required when the primer coat is required to be tacky for stripe coat application.)

9.2 Check for evidence of Amine Bloom such as discoloration of paint coating or clear oily film. If evidence of Amine

Bloom is present, perform low-pressure water wash with deionized water or wipe surfaces clean using ethanol/deionized water mixture.

9.3 Apply stripe coat specified in the coating table Appendix found in individual PPIs with typical paint equipment and IAW NAVSEA Standard Item 009-32. Stripe coat by brush in areas not accessible by paint spray equipment. During

Page 18: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 18

August 23, 2011 REV 27

application, immediately brush out any runs, drips, sags or puddles. 9.4 CHECKPOINT (Stripe Coat): Verify stripe coat is applied IAW NAVSEA Standard Item 009-32. 9.4.1 (Holiday Inspection): Accomplish a visual holiday inspection of stripe coat. See section 8.2.1 9.4.2 All tests and inspections noting unsatisfactory conditions shall result in the termination and rescheduling of the

checkpoint. At rescheduled checkpoint, QA shall document satisfactory corrective actions taken to correct discrepancy.

9.4.3 In order to pass the checkpoint, Appendices 1, and 6 Enclosure 2 shall be up to date and submitted to QA. QA shall

sign Enclosure 2 in the appropriate places.

10. INTERMEDIATE COAT APPLICATION (if applicable):

10.1 CHECKPOINT (Test for Assessment of Surface Cleanliness): Immediately prior to intermediate coat application the

stripe coat surface shall be checked for dust IAW ref 2.k. The dust rating shall be no greater than Rating 2, Class 2. For structures up to 1,000 ft

2 other than UW hull and Flight deck nonskid, three readings shall be taken. For

every additional 1000 ft

2 of area or increment thereof, one 100 ft

2 area shall be randomly selected and sampled. For

UW hull one reading for each 200 ft2 for first 1,000 ft

2 shall be taken. For every additional 500 ft

2 of area or

increment thereof, one 100 ft2 area shall be randomly selected and sampled. For flight deck nonskid, 3

individual readings are required every 100 ft2 for the first 500 ft

2; if the readings are satisfactory, 1 individual

reading per 1000 ft2 remaining shall be taken. No reading shall be taken in the same 100 ft

2 area as another

reading. Document readings on Appendix 5 (PRESSURE SENSITIVE TAPE SAMPLES). (This check is not required when the stripe coat is required to be tacky for intermediate coat application.) 10.2 Check for evidence of Amine Bloom such as discoloration of paint coating or clear oily film. If evidence of Amine

Bloom is present, perform low-pressure water wash with deionized water or wipe surfaces clean using ethanol/ deionized water mixture.

10.3 Apply intermediate coat specified in the coating table Appendix found in individual PPIs and IAW NAVSEA Standard

Item 009-32. During application, immediately brush out any runs, drips, sags or puddles. 10.4 CHECKPOINT (Intermediate Coat): Verify intermediate coat is applied IAW NAVSEA Standard Item 009-32. . 10.4.1 (Holiday Inspection): Accomplish a visual holiday inspection of intermediate coat. 10.4.2 (Dry Film Thickness): Accomplish dry film thickness measurements IAW Ref. 2.b. 10.4.3 All tests and inspections noting unsatisfactory conditions shall result in the termination and rescheduling of the

checkpoint. At rescheduled checkpoint, QA shall document satisfactory corrective actions taken to correct discrepancy.

10.4.4 In order to pass the checkpoint, Appendices 1, 6, and 7 and Enclosure 2 shall be up to date and submitted to QA. QA shall sign Enclosure 2 in the appropriate areas.

11. 2nd

STRIPE COAT APPLICATION (if applicable):

11.1 CHECKPOINT (Test for Assessment of Surface Cleanliness): Immediately prior to 2nd stripe

coat application the intermediate coat surface shall be checked for dust IAW Ref 2.k. The dust rating shall be no greater than Rating 2, Class 2. For structures up to 1,000 ft

2 other than UW hull and Flight deck

nonskid, three readings shall be taken. For every additional 1000 ft2 of area or increment thereof, one 100 ft

2 area

shall be randomly selected and sampled. For UW hull one reading for each 200 ft2 for first 1,000 ft

2 shall be taken. For

every additional 500 ft2 of area or increment thereof, one 100 ft

2 area shall be randomly selected and sampled. For

flight deck nonskid, 3 individual readings are required every 100 ft2 for the first 500 ft

2; if the readings are satisfactory,

1 individual reading per 1000 ft2 remaining shall be taken. No reading shall be taken in the same 100 ft

2 area as

another reading. Document readings on Appendix 5 (PRESSURE SENSITIVE TAPE SAMPLES). (This check is not required when the intermediate coat is required to be tacky for 2nd stripe coat application.)

Page 19: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 19

August 23, 2011 REV 27

11.2 Check for evidence of Amine Bloom such as discoloration of paint coating or clear oily film. If evidence of Amine Bloom is present, perform low-pressure water wash with deionized water or wipe surfaces clean using ethanol/deionized water mixture.

11.3 Apply 2nd stripe coat specified in the coating table Appendix found in individual PPIs with typical paint equipment and IAW NAVSEA Standard Item 009-32. Stripe coat by brush in areas not accessible by paint spray equipment.

During application, immediately brush out any runs, drips, sags or puddles.

11.4 CHECKPOINT (2nd Stripe Coat): Verify stripe coat is applied IAW NAVSEA Standard Item 009-32 11.4.1 (Holiday Inspection): Accomplish a visual holiday inspection of 2

nd stripe coat.

11.4.2 All tests and inspections noting unsatisfactory conditions shall result in the termination and rescheduling of the checkpoint. At rescheduled checkpoint, QA shall document satisfactory corrective actions taken to correct discrepancy.

11.4.3 In order to pass the checkpoint, Appendices 1 and 6 and Enclosure 2 shall be up to date and submitted to QA. QA shall sign Enclosure 2 in the appropriate areas.

12. TOPCOAT APPLICATION: NOTE: PROTECT REMOVED SHIP COMPONENTS AND EQUIPMENT TOPCOATED WITH EPOXY PAINTS FROM

DIRECT UV EXPOSURE (EXPOSURE COULD RESULT IN SIGNIFICANT COLOR CHANGE).

12.1 CHECKPOINT (Test for Assessment of Surface Cleanliness): Immediately prior to topcoat

application the preceding coat surface will be checked for dust IAW Ref 2.k. The dust rating shall be no greater than Rating 2, Class 2. For structures up to 1,000 ft

2 other than UW hull and Flight deck nonskid, three readings shall be

taken. For every additional 1000 ft2 of area or increment thereof, one 100 ft

2 area shall be randomly selected and

sampled. For UW hull one reading for each 200 ft2 for first 1,000 ft

2 shall be taken. For every additional 500

ft2 of area or increment thereof, one 100 ft

2 area shall be randomly selected and sampled. For flight deck nonskid,

3 individual readings are required every 100 ft2 for the first 500 ft

2; if the readings are satisfactory,

1 individual reading per 1000 ft2 remaining shall be taken. No reading shall be taken in the same 100 ft

2 area as

another reading. Document readings on Appendix 5 (PRESSURE SENSITIVE TAPE SAMPLES). (This check is not required when the preceding coat is required to be tacky for topcoat application.)

12.2 Check for evidence of Amine Bloom such as discoloration of paint coating or clear oily film. If evidence of Amine

Bloom is present, perform low-pressure water wash with deionized water or wipe surfaces clean using ethanol/deionized water mixture.

12.3 Apply topcoat specified in the coating table Appendix found in individual PPIs and IAW NAVSEA Standard Item 009-32. During application, immediately brush out any runs, drips, sags or puddles.

12.4 CHECKPOINT (Topcoat): Verify topcoat is applied IAW NAVSEA Standard Item 009-32. .

12.4.1 (Holiday Inspection): Accomplish a visual holiday inspection of topcoat. 12.4.2 (Dry Film Thickness): Accomplish dry film thickness measurements IAW Ref. 2.b. 12.4.3 All tests and inspections noting unsatisfactory conditions shall result in the termination and rescheduling of the

checkpoint. At rescheduled checkpoint, QA shall document satisfactory corrective actions taken to correct discrepancy.

12.4.4 In order to pass the checkpoint, Appendices 1, 6, and 7 and Enclosure 2 shall be up to date and submitted to QA. QA shall sign Enclosure 2 in the appropriate areas. 13. FINAL INSPECTION: 13.1 CHECKPOINT (Finished Painted Surfaces): Accomplish IAW NAVSEA Standard Item 009-32. 13.1.1 (Dry Film Thickness): For steel surfaces perform dry film thickness measurements IAW Ref. 2.b. For a non-ferrous

substrate (aluminum) constant pressure eddy current gages (electromagnetic induction), similar to SSPC-PA2 Type 2 gages are to be used. Dry film thickness measurements should only be taken in those areas that were not done

Page 20: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 20

August 23, 2011 REV 27

at the initial topcoat completion inspection (i.e., those areas disturbed since topcoat installation or those areas completed since topcoat installation).

13.1.2 Coating imperfections found, which may cause premature coating failure, shall be corrected before the paint system is accepted using appropriate touch-up procedures specified in paragraph 7.14. Slight imperfections in the coating

system are allowable, as long as dry film thickness conforms to SSPC-PA2, and will not result in premature failure of the coating in the immediate vicinity of the imperfection. Such slight imperfections shall be left intact, as trying to correct them could result in damage to the surrounding coating system.

13.1.3 In order to pass the checkpoint, any Appendices required by the certified coating inspector shall be up to date,

completed, and submitted to QA. QA shall sign Enclosure 2 in the appropriate areas. All test inspections noting unsatisfactory conditions shall be corrected.

Page 21: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 21

August 23, 2011 REV 27

APPENDIX 1 QA INSPECTION FORM - ENVIRONMENTAL READINGS & PAINT/NONSKID STORAGE

SHIP NAME & HULL #: CONTRACT/TASK ORDER/CLIN/TWD: DATE/TIME:

LOCATION: WORK ITEM: PARA. NO.:

(I) (V) (G) PRODUCT BEING APPLIED:

REQ'T DOCUMENT: /FY: TABLE: LINE: COLUMN: (NSTM 631, 634, PPI, NSI 009-32 FY)

MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR COATED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

NOTE #1 FOR ANY UNSAT CONDITION FOUND, PROVIDE THE TECHNICAL ADJUDICATION AND CORRECTIVE ACTION TAKEN IN

THE COMMENTS BLOCK. NOTE #2 UNLESS OTHERWISE STATED IN SPECIFICATION, SURFACE TEMPERATURE MUST BE A MINIMUM OF 50 DEG F AND

AT LEAST 5 DEG F ABOVE DEW POINT. NOTE #3 ALL SPACES IN A SECTION ARE TO BE FILLED IN. IF NOT APPLICABLE, INSERT N/A. UNUSED SECTIONS SHALL BE

CROSSED OUT AND MARKED N/A.

ACCEPT CRITERIA: ENV: % RH: SURFACE TEMP: MIN: MAX: STORAGE TEMP: MIN: MAX:

Check for Ventilation Running:

Date Time Enter Activity/Process: Cleanliness Check, Surface Preparation, Prime Application, Prime Cure, Stripe Application, Stripe Cure, Intermediate Application, Intermediate

Cure, Tack Application, Top Coat Application, Top Coat Cure, etc.

Substrate Surface

Temp. (°F)

Dew Point (°F)

% RH Dry Bulb (Ambient

Temp) (°F)

Wet Bulb (°F)

Gage # Gage Cal Due Date: Condition of Reading SAT: UNSAT:

Gage # Gage Cal Due Date:

Contractor (Print): Contractor (Signature):

COMMENTS:

Date Time Enter Activity/Process: Cleanliness Check, Surface Preparation, Prime Application, Prime Cure, Stripe Application, Stripe Cure, Intermediate Application, Intermediate

Cure, Tack Application, Top Coat Application, Top Coat Cure, etc.

Substrate Surface

Temp. (°F)

Dew Point (°F)

% RH Dry Bulb (Ambient

Temp) (°F)

Wet Bulb (°F)

Gage # Gage Cal Due Date: Condition of Reading SAT: UNSAT:

Gage # Gage Cal Due Date:

Contractor (Print): Contractor (Signature):

COMMENTS:

Date Time Enter Activity/Process: Cleanliness Check, Surface Preparation, Prime Application, Prime Cure, Stripe Application, Stripe Cure, Intermediate Application, Intermediate

Cure, Tack Application, Top Coat Application, Top Coat Cure, etc.

Substrate Surface

Temp. (°F)

Dew Point (°F)

% RH Dry Bulb (Ambient

Temp) (°F)

Wet Bulb (°F)

Gage # Gage Cal Due Date: Condition of Reading SAT: UNSAT:

Gage # Gage Cal Due Date:

Contractor (Print): Contractor (Signature):

COMMENTS:

Paint/Nonskid Storage

Date

Time/ Time Range

Enter Product/Component & Prime, Stripe, Intermediate,

Tack, Top Coat

Min. & Max. Temp. for 24hr Period Prior to Initiation of

Application

--OR-- Storage Temp.

Manually Measured

--OR-- Core Temp. After Component Mixed

Method of Measurement

Min.: /Max.:

Contractor (Print): Contractor (Signature):

COMMENTS:

Page 22: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 22

August 23, 2011 REV 27

APPENDIX 2 QA INSPECTION FORM - SSPC-SP 1 CLEANLINESS CHECKPOINT

SHIP NAME & HULL #: CONTRACT/TASK ORDER/CLIN/TWD: DATE/TIME:

LOCATION: WORK ITEM: PARA. NO.:

(I) (V) (G) PRODUCT BEING APPLIED:

REQ'T DOCUMENT: /FY: SQFT OF AREA PRESERVED: PARTIAL AREA: /FINAL: (NSTM 631, 634, PPI, NSI 009-32 FY)

Accomplish SSPC-SP-1 degreasing/cleaning to ensure the removal of surface contaminants. Date/Time:

SAT: UNSAT:

Accomplish degreasing/cleaning a maximum of 4 hrs. prior to surface preparation, ensuring the adequate removal of surface contaminants. Date/Time: SAT: UNSAT:

If evidence of contamination exists, accomplish degreasing/cleaning a maximum of 4 hrs. prior to the application of each coat of paint to ensure removal of surface contaminants. Date/Time:

SAT: UNSAT:

COMMENTS:

Contractor (Print):

Contractor

(Signature):

Date/Time:

Subcontractor (Print):

Subcontractor

(Signature):

Date/Time:

Govt. Insp. (Print):

Govt. Insp.

(Signature):

Date/Time:

Page 23: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 23

August 23, 2011 REV 27

APPENDIX 3 QA INSPECTION FORM - SURFACE PROFILE / PREPARATION & CLEANLINESS LOG

SHIP NAME & HULL #: CONTRACT/TASK ORDER/CLIN/TWD: DATE/TIME:

LOCATION: WORK ITEM: PARA. NO.:

(I) (V) (G) PRODUCT BEING APPLIED:

REQ'T DOCUMENT: /FY: SQFT OF AREA PRESERVED: PARTIAL AREA: /FINAL: (NSTM 631, 634, PPI, NSI 009-32 FY)

MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR PAINTED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

NOTE #1 FOR PAINTS: 1 PROFILE READING REQUIRED FOR EVERY 200 SQFT (3 INDIVIDUAL TAPES FOR METHOD C) FOR THE

FIRST 1000 SQFT AREA (15 INDIVIDUAL TAPES TOTAL FOR METHOD C); 1 PROFILE READING REQUIRED FOR EACH ADDITIONAL 500 SQFT OR LESS AREA (3 INDIVIDUAL TAPES FOR METHOD C).

NOTE #2 FOR NONSKID: 1 PROFILE READINGS REQUIRED EVERY 100 SQFT (3 INDIVIDUAL TAPES FOR METHOD C) FOR THE

FIRST 500 SQFT AREA (15 INDIVIDUAL TAPES TOTAL FOR METHOD C); IF READINGS ARE SATISFACTORY, 1 PROFILE READING PER 1000 SQFT REMAINING (3 INDIVIDUAL TAPES FOR METHOD C).

NOTE #3 FOR ANY UNSAT CONDITION FOUND, PROVIDE THE TECHNICAL ADJUDICATION AND CORRECTIVE ACTION TAKEN IN

THE COMMENTS BLOCK. NOTE #4 IF SPACES ARE NOT APPLICABLE, INSERT N/A. UNUSED SECTIONS SHALL BE CROSSED OUT AND MARKED N/A.

ACCEPTANCE CRITERIA: PROFILE RANGE MILS TO MILS

Mils (Average

of 3 tapes)

Reading: mils Reading: mils Reading: mils

Reading: mils Reading: mils Reading: mils

Reading: mils Reading: mils Reading: mils

Reading: mils Reading: mils Reading: mils

Reading: mils Reading: mils Reading: mils

TOTAL AVG:

COMMENTS:

Abrasive Manufacturer: (If Applicable)

Type: (If Applicable)

Mesh Size: (If Applicable)

TYPE OF SURFACE PREPARATION:

GAGE # (Base Metal Reading) SURFACE PROFILE INSP: SURFACE PREP. INSP: CLEANLINESS INSP:

(Type 1 gage)

GAGE CAL DUE DATE: BMR SAT: UNSAT: SAT: UNSAT: SAT: UNSAT:

Contractor (Print):

Contractor

(Signature):

Date/Time:

Subcontractor (Print):

Subcontractor

(Signature):

Date/Time:

Govt. Insp. (Print):

Govt. Insp.

(Signature):

Date/Time:

Page 24: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 24

August 23, 2011 REV 27

APPENDIX 4 QA INSPECTION FORM - SURFACE CONDUCTIVITY / CHLORIDE LOG

SHIP NAME & HULL #: CONTRACT/TASK ORDER/CLIN/TWD: DATE/TIME:

LOCATION: WORK ITEM: PARA. NO.:

(I) (V) (G) PRODUCT BEING APPLIED:

REQ'T DOCUMENT: /FY: SQFT OF AREA PRESERVED: PARTIAL AREA: /FINAL: (NSTM 631, 634, PPI, NSI 009-32 FY)

MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR PAINTED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

MAXIMUM READING (IMMERSED SURFACES): CONDUCTIVITY (30) µS/cm CHLORIDE (3) µg/cm2

MAXIMUM READING (NON-IMMERSED SURFACES): CONDUCTIVITY (70) µS/cm CHLORIDE (5) µg/cm2

1 READING REQUIRED FOR EVERY 200 SQFT FOR FIRST 1000 SQFT, THEN 1 READING FOR EACH ADDITIONAL 500 SQFT OR LESS NOTE #1 FOR ANY UNSAT CONDITION FOUND, PROVIDE THE TECHNICAL ADJUDICATION AND CORRECTIVE ACTION TAKEN IN

THE COMMENTS BLOCK. NOTE #2 IF SPACES ARE NOT APPLICABLE, INSERT N/A. UNUSED SECTIONS SHALL BE CROSSED OUT AND MARKED N/A.

TEST LOCATIONS CHLORIDE (µg/cm2) CONDUCTIVITY (µS/cm) SAT UNSAT

COMMENTS:

GAGE # GAGE CAL DUE DATE: CONDITION OF CHECKPOINT: SAT: UNSAT:

Contractor (Print):

Contractor

(Signature):

Date/Time:

Subcontractor (Print):

Subcontractor

(Signature):

Date/Time:

Govt. Insp. (Print):

Govt. Insp.

(Signature):

Date/Time:

Page 25: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 25

August 23, 2011 REV 27

APPENDIX 5 QA INSPECTION FORM - SURFACE CLEANLINESS (DUST) TAPE

SHIP NAME & HULL #: CONTRACT/TASK ORDER/CLIN/TWD: DATE/TIME:

LOCATION: WORK ITEM: PARA. NO.:

(I) (V) (G) PRODUCT BEING APPLIED:

REQ'T DOCUMENT: /FY: SPECIFIC FEATURES OF AREA TO BE TESTED: (NSTM 631, 634, PPI, NSI 009-32 FY) ADHESIVE TAPE TYPE(S) FOR DUST MEASUREMENT:

MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR PAINTED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

NOTE #1 FOR UNDERWATER HULL, 1 PROFILE READING REQUIRED FOR EVERY 200 SQFT FOR THE FIRST 1000 SQFT AREA; IF

READINGS ARE SATISFACTORY, 1 INDIVIDUAL READING REQUIRED FOR EACH ADDITIONAL 500 SQFT OR LESS AREA.

NOTE #2 FOR FLIGHT DECK NONSKID, 3 INDIVIDUAL READINGS REQUIRED EVERY 100 SQFT FOR THE FIRST 500 SQFT; IF

READINGS ARE SATISFACTORY, 1 INDIVIDUAL READING PER 1000 SQFT REMAINING. NOTE #3 FOR ANY UNSAT CONDITION FOUND, PROVIDE THE TECHNICAL ADJUDICATION AND CORRECTIVE ACTION TAKEN IN

THE COMMENTS BLOCK. NOTE #4 IF SPACES ARE NOT APPLICABLE, INSERT N/A. UNUSED SECTIONS SHALL BE CROSSED OUT AND MARKED N/A.

Spot Measurement

Dust Quantity Rating

Dust Size Class

Approximate Location

Spot Measurement

Dust Quantity Rating

Dust Size Class

Approximate Location

Spot Measurement

Dust Quantity Rating

Dust Size Class

Approximate Location

Spot Measurement

Dust Quantity Rating

Dust Size Class

Approximate Location

Spot Measurement

Dust Quantity Rating

Dust Size Class

Approximate Location

CONDITION OF CHECKPOINT

SAT: UNSAT:

COMMENTS:

Contractor (Print):

Contractor

(Signature):

Date/Time:

Subcontractor (Print):

Subcontractor

(Signature):

Date/Time:

Govt. Insp. (Print):

Govt. Insp.

(Signature):

Date/Time:

Page 26: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 26

August 23, 2011 REV 27

APPENDIX 6 QA INSPECTION FORM - PAINT/NONSKID APPLICATION AND CONSUMPTION LOG

SHIP NAME & HULL #: CONTRACT/TASK ORDER/CLIN/TWD: DATE/TIME:

LOCATION: WORK ITEM: PARA. NO.:

(I) (V) (G) PRODUCT BEING APPLIED:

REQ'T DOCUMENT: /FY: TABLE: LINE: COLUMN: (NSTM 631, 634, PPI, NSI 009-32 FY)

MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR PAINTED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Prime Coat

Stripe Coat (if applicable)

Intermediate Coat

(if applicable)

Stripe Coat (if applicable)

Topcoat Other

Application Method: Plural Airless, Conventional Airless, Brush, Roller, Conventional Spray

Airless Pump Ratio (if Plural Component):

Fixed: Variable:

If Using Inline Heater, Temp. in °F

(Fahrenheit)

Temp. Setting At Heater

Temp. At Tip

Product Applied

Product Manufacturer

Color Applied

Base Portion Batch No # (Part A)

Expiration Date (Part A)

Hardener Portion Batch No # (Part B)

Expiration Date (Part B)

Gallons Used Per Coat

Square Feet Coated

Start (Date/Time)

Stop (Date/Time)

Page 27: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 27

August 23, 2011 REV 27

APPENDIX 7 QA INSPECTION FORM - DRY FILM THICKNESS MEASUREMENTS

SHIP NAME & HULL #: CONTRACT/TASK ORDER/CLIN/TWD: DATE/TIME:

LOCATION: WORK ITEM: PARA. NO.:

(I) (V) (G) PRODUCT BEING APPLIED:

REQ'T DOCUMENT: /FY: SQFT OF AREA PRESERVED: PARTIAL AREA: /FINAL: (NSTM 631, 634, PPI, NSI 009-32 FY)

MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR PAINTED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

NOTE #1 FOR ANY UNSAT CONDITION FOUND, PROVIDE THE TECHNICAL ADJUDICATION AND CORRECTIVE ACTION TAKEN IN COMMENTS BLOCK. NOTE #2 IF SPACES ARE NOT APPLICABLE, INSERT N/A. UNUSED SECTIONS SHALL BE CROSSED OUT AND MARKED N/A.

Select Type of Gage being used: Type 1 Type 2 Base Metal Reading (Type 1 gage):

Gage # Current Calibration Due Date: Accuracy Adjustment (Type 1 gage):

ACCEPTANCE CRITERIA

PRIMER COAT DFT TO MILS TOPCOAT DFT TO MILS

INTERMEDIATE COAT DFT TO MILS TOTAL SYSTEM DFT TO MILS

STRIPE COAT (for cleanliness & holiday QA)

Note: Each Spot Measurement = The AVG of Three Gage Readings. Note: Each Spot Measurement = The AVG of Three Gage Readings.

SPOT MEASUREMENT

DFT (Mils) AVG of 3 Gage Readings

Approximate Location SPOT

MEASUREMENT DFT (Mils) AVG of 3

Gage Readings Approximate Location

1 1

2 2

3 3

4 4

5 5

Average: Average:

Note: Each Spot Measurement = The AVG of Three Gage Readings. Note: Each Spot Measurement = The AVG of Three Gage Readings.

SPOT MEASUREMENT

DFT (Mils) AVG of 3 Gage Readings

Approximate Location SPOT

MEASUREMENT DFT (Mils) AVG of 3

Gage Readings Approximate Location

1 1

2 2

3 3

4 4

5 5

Average: Average:

Note: Each Spot Measurement = The AVG of Three Gage Readings. Note: Each Spot Measurement = The AVG of Three Gage Readings.

SPOT MEASUREMENT

DFT (Mils) AVG of 3 Gage Readings

Approximate Location SPOT

MEASUREMENT DFT (Mils) AVG of 3

Gage Readings Approximate Location

1 1

2 2

3 3

4 4

5 5

Average: Average:

HOLIDAY INSP.: SAT UNSAT DFT INSP.: SAT UNSAT N/A (for stripe coat)

CLEANLINESS INSP.: SAT UNSAT CHLORIDE/CONDUCTIVITY INSP.: SAT UNSAT

COMMENTS:

Contractor (Print): Contractor (Signature): Date/Time:

Subcontractor (Print):

Subcontractor

(Signature):

Date/Time:

Govt. Insp. (Print): Govt. Insp. (Signature): Date/Time:

Page 28: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 28

August 23, 2011 REV 27

APPENDIX 7A QA INSPECTION FORM - WET FILM THICKNESS MEASUREMENTS

SHIP NAME & HULL #: CONTRACT/TASK ORDER/CLIN/TWD: DATE/TIME:

LOCATION: WORK ITEM: PARA. NO.:

(I) (V) (G) PRODUCT BEING APPLIED:

REQ'T DOCUMENT: /FY: SQFT OF AREA PRESERVED: PARTIAL AREA: /FINAL: (NSTM 631, 634, PPI, NSI 009-32 FY)

MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR PAINTED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

NOTE #1 FOR ANY UNSAT CONDITION FOUND, PROVIDE THE TECHNICAL ADJUDICATION AND CORRECTIVE ACTION TAKEN IN

THE COMMENTS BLOCK WHERE REQUIRED IN LIEU OF DFT. NOTE #2 IF SPACES ARE NOT APPLICABLE, INSERT N/A. UNUSED SECTIONS SHALL BE CROSSED OUT AND MARKED N/A.

Indicate Coating System Sequence

Prime Coat Intermediate Coat (if applicable) Topcoat

Stripe Coat (if applicable) Stripe Coat (if applicable) Other Coat (specify) ( )

METALLIC SURFACES NON - METALLIC SURFACES

2 SPOT READINGS PER 1000 SQFT: 0 - 100 SQFT = 5 SPOTS REQUIRED

0 - 1000 SQFT = 2 SPOTS REQUIRED 101 - 200 SQFT = 10 SPOTS REQUIRED

1001 - 2000 SQFT = 4 SPOTS REQUIRED 201 - 1000 SQFT = 15 SPOTS REQUIRED

> 1000 SQFT = 5 SPOTS REQUIRED PER 1000 SQFT AREA

WFT Measurement Number Location of Readings WFT Measurement

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

COMMENTS:

Contractor (Print):

Contractor

(Signature):

Date/Time:

Subcontractor (Print):

Subcontractor

(Signature):

Date/Time:

Govt. Insp. (Print):

Govt. Insp.

(Signature):

Date/Time:

Page 29: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 29

August 23, 2011 REV 27

ENCLOSURE 1

Page 30: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 30

August 23, 2011 REV 27

ENCLOSURE 2

CHECKPOINTS & MILESTONES COMPLETION & SIGN OFF LOG SHIP: _____________________________________JOB ORDER: __________________ DATE: ________________

LOCATION: _________________________________WORK ITEM: ________________ PARA. NO.: ___________ PRODUCT BEING APPLIED: _________________________________________________________

MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR PAINTED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS MAINTAIN A SEPARATE LOG FOR EACH SECTION.

ACTIVITY TIME DATE

Date Pre-Surface Preparation and Cleaning Begins Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Pre-Surface Preparation and Cleaning Checkpoint --Date of Visual and UV Light or Water-Break Inspection Check --Date of Structural and Pre-Surface Conditioning (ensuring de-burring and grinding) Check --Date of Contamination Containment and Masking Check Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date Surface Preparation Begins Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Surface Preparation Checkpoint --Date of Surface Profile Measurement Check --Date of Soluble Salt Measurement Check --Date of Environmental Check --Date of Contamination Containment and Masking Check --Date of Inspection of Prepared area (ensuring all areas are properly prepared) Check --Date of Inspection of area cleanliness prior to paint application Check Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date Paint Storage Area Inspected Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date Paint Mixing Inspected --Date of Shelf Life Check --Date of Temperature Check --Date of Mixing Check Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date Prime Coat is Applied Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Prime Coat Checkpoint Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Page 31: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 31

August 23, 2011 REV 27

ENCLOSURE 2 (CONTINUED) CHECKPOINTS & MILESTONES COMPLETION LOG

SHIP: ____________________________________JOB ORDER: __________________ DATE: _________________ LOCATION: _______________________________WORK ITEM: ________________ PARA. NO.: ___________ PRODUCT BEING APPLIED: _________________________________________________________ MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR PAINTED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS MAINTAIN A SEPARATE LOG FOR EACH SECTION.

ACTIVITY TIME DATE

Date of Surface Cleanliness Inspection Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Amine Bloom Inspection Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date Stripe Coat Applied (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Stripe Coat Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Surface Cleanliness Inspection Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Amine Bloom Inspection Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date Intermediate Coat Applied (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Intermediate Coat Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Surface Cleanliness Inspection Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Amine Bloom Inspection Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Page 32: PRESERVATION PROCESS INSTRUCTION (PPI) · PDF filePRESERVATION PROCESS INSTRUCTION (PPI) CORE . CORE PPI 2 ... Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector

CORE PPI 32

August 23, 2011 REV 27

ENCLOSURE 2 (CONTINUED) CHECKPOINTS & MILESTONES COMPLETION LOG

SHIP: ___________________________________JOB ORDER: __________________ DATE: _________________ LOCATION: ______________________________WORK ITEM: ________________ PARA. NO.: ___________ PRODUCT BEING APPLIED: _________________________________________________________

MAINTAIN SEPARATE LOG FOR EACH AREA/LOCATION, PREPARED OR PAINTED SURFACE. WHEN AN AREA IS DIVIDED INTO SEPARATE SECTIONS MAINTAIN A SEPARATE LOG FOR EACH SECTION.

ACTIVITY TIME DATE

Date Stripe Coat Applied (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Stripe Coat Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Surface Cleanliness Inspection Checkpoint Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Amine Bloom Inspection Checkpoint (if applicable) Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date Topcoat Applied Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date of Topcoat Checkpoint Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________

Date Finished Painted Surfaces Checkpoint Implementing Contractor (Print/ Signature): __________________________________________ Certified Inspector (Print): ________________________________________________________ Certified Inspector (Signature): ____________________________________________________ NACE Session I Certification NBPI Certification Inspector #: _________________ Certification Expiration Date: ______________