pressure leaching of copper concentrates -...
TRANSCRIPT
1 October 25th, 2004
Pressure Leaching of Copper Concentrates
John O. MarsdenSenior Vice President – Technology & Product Development
2 October 25th, 2004
Presentation Outline
Safety share
Introduction
Global copper reserves/resources
Phelps Dodge production & reserves profile
Commercial drivers for copper concentrate leaching
The copper concentrate market and TC/RCs
Phelps Dodge copper pressure leaching developments
High temperature
Medium temperature
Critical success factors for commercialization
Conclusions
3 October 25th, 2004
Safety Share - Bagdad Concentrate Leach Project
Construction Safety Record (total project)
Total man hours 330,000
Lost time injuries 0
Recordable injuries 3
First aid treatment 9
Near miss incidents 7
Recordable Injury Frequency Rate = 1.86 (per 200,000 man hours)
Operations & Maintenance (project to date)
Lost time injuries 0
Recordable injuries 0
First aid treatment 2
Near miss incidents 18 (2004 YTD)
Recordable Injury Frequency Rate = 0
651 Zero days since project start
4 October 25th, 2004
Global Copper Industry by Process Type
80%
10%
10%
Mill, Smelt (cpy/cc)
Leach, SX/EW (cc)
Leach, SX/EW (ox)
80%
9%
11%
Mill, Smelt or Con Leach (cpy/cc)
Leach, SX/EW (cc)
Leach, SX/EW (ox)
2003 Production (Est.) Remaining Reserves (Est.)
5 October 25th, 2004
Potential Phelps Dodge Production Profile by Process Type
2%
34%
44%
20%
Mill, Con Leach (cpy/cc) Mill, Smelt (cpy/cc)
Leach, SX/EW (cc) Leach, SX/EW (ox)
24%
36%
22%
18%
2004 Production 2010 Production
6 October 25th, 2004
0
500
1,000
1,500
2,000
2,500
85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04F
Conventional SX/EW
Technology Transformation of Copper Production
(PDC share; millions of pounds)
1983 – 100% conventional
2003 – 70% SX/EW
7 October 25th, 2004
Phelps Dodge Mineral Reserves Profile by Process Type
59%24%
17%
Mill, Con Leach or Smelt (cpy/cc)
Leach, SX/EW (cc)
Leach, SX/EW (ox)
8 October 25th, 2004
Drivers for Concentrate Leaching
Cost effective alternative to conventional smelting & refining
Capital cost versus greenfield smelter/refinery projects
$1,000-2,000 versus $3,000-6,000/annual tonne
Ability to utilize existing SX capacity ($300-400/annual mt)
Ability to utilize spare EW capacity ($500-600/annual mt)
Ability to utilize existing infrastructure
TC/RCs – Commercial third party smelting & refining rates
Operating cost
Oxygen requirements & cost
Altitude
Acid balance
Freight rates, distances, handling
Copper recovery
By-products (Au, Ag, other)
Smelter penalty elements (As, Sb, Bi, other)
9 October 25th, 2004
Chalcopyrite Concentrate Pressure Leaching Options
Atmospheric sulfate media
Attrition grind & ferric leach
Silver-catalyzed ferric leach
Biological ferric leach
Pressure sulfate
High temperature (>200oC)
Medium temperature (>100oC <200oC)
Chloride-assisted
Halide system
Chloride
Chloride-bromide
Ammonia
10 October 25th, 2004
Factors Affecting Process Selection
Deposit characteristics
Concentrate mineralogy
Concentrate grade
Location
Stand-alone versus integrated at mine site
Site acid requirements
Regional acid market
Availability and cost
Acid neutralizing material
Availability and cost
11 October 25th, 2004
The Copper Processing Technology Today
Mine
Heap
Leaching(Oxide)
(Chalcocite)
Solution
Extraction
Milling(Chalcocite)
(Chalcopyrite)
SmeltingElectro-
Refining
Electro-
Winning
Acid
Flotation
Primary
Crushing
Stockpile
Leaching(Oxide)
(Chalcocite)
Sec/Tert
Crushing
Customers
12 October 25th, 2004
Real TC/RCs and Copper Prices ($2002)
0
50
100
150
200
250
300
1975
1977
1979
1981
1983
1985
1987
1989
1991
1993
1995
1997
1999
2001
2003
10
15
20
25
30
35
40
45
Copper Prices TC/RCs Linear (Copper Prices) Linear (TC/RCs)
Copper Prices (¢/lb) TC/RCs (¢/lb)Japanese TC/RCs
13 October 25th, 2004
TC/RCs versus Price
Long-term Japanese TC/RCs (1975 - 2003)
y = 0.1401x + 10.415
R2 = 0.7257
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
50.0
60 80 100 120 140 160 180 200 220 240 260
Copper Price - ¢/lb
(Constant 2002$)
TC
/RC
- ¢/lb
(C
on
sta
nt
2002$)
*
14 October 25th, 2004
Forecast Real TC/RCs as a Percentage of Copper Price
15%
17%
19%
21%
23%
25%
27%
29%
31%
33%
35%
1975
1977
1979
1981
1983
1985
1987
1989
1991
1993
1995
1997
1999
2001
2003
2005
2007
2009
Source: Brook Hunt
15 October 25th, 2004
Greenfield Smelter Developments (1991-2002)
0
200
400
600
800
1,000
1,200
1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002
Others (9%)
Indonesia (21%)
India (21%)
China (49%)
Tariff-Protection
Tariff-
Protection
TC/RC
Minimum
(Cu kmt)
Source: Brook Hunt
16 October 25th, 2004
Near-Term Shortfall in Copper Supply
0
5,000
10,000
15,000
20,000
25,000
1997
1998
1999
2000
2001
2002
e
2003
F
2004
F
2005
F
2006
F
2007
F
2008
F
2009
F
2010
F
Scrap/Other Concentrate ProductionSX/EW Production SX/EW New ProductionCopper Consumption
Source:
Brook Hunt
3.8 MMt/a
(Cu kmt)
Existing concentrate production w/ majority of
restarts & all financed projects
Shortfall in mine production expected
to be filled by concentrate production
17 October 25th, 2004
8,000
9,000
10,000
11,000
12,000
13,000
14,000
15,000
16,000
17,000
18,000
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
Smelter Capacity Smelter Production Mine Production
Primary Smelter Capacity vs. Mine Production
(Cu kmt)
82%
86%
84%
Source:
Brook
Hunt
19 October 25th, 2004
Phelps Dodge Copper Pressure Leaching Developments
Phelps Dodge (& Placer Dome) have developed a suite of
proprietary processes, including:
High temperature process (HT)
Converts essentially all sulfide sulfur to acid
Maximizes acid production
Suitable for locations where dilute acid can be used
beneficially
Medium temperature process (MT)
Converts a significant portion of sulfide sulfur to elemental
sulfur
Lower oxygen costs
Minimizes acid production
Suitable for locations where dilute acid cannot be used
beneficially
20 October 25th, 2004
Phelps Dodge Concentrate Leaching Milestones
2Q 1998 Sulfate-based concentrate leaching
development started
1999-2000 Batch testwork at Hazen Research, Dawson
and Phelps Dodge Process Technology Center
2000-2001 Continuous Pilot Plant Testing
3Q 2001 Technology Development Agreement
executed with Placer Dome
Nov 2001 Bagdad HT Project approved
Nov 2001 Engineering awarded to Kvaerner
Mar 25, 02 Construction started by KIC
Mar 6, 03 Wet commissioning begun
Mar 20, 03 Start-up: First concentrate feed
July 2003 All design parameters met, steady state operation
Four years from first testing to commercial demonstration
21 October 25th, 2004
Phelps Dodge Concentrate Leaching Milestones (cont.)
April 2004 Bagdad MT-DEW Conversion approved
July 2004 Construction of MT-DEW started
1Q05 Commissioning of MT-DEW scheduled
22 October 25th, 2004
Concentrate Leaching – Alternative to Smelting & Refining
Mine
Heap
Leaching(Oxide)
(Chalcocite)
Solution
Extraction
Milling(Chalcocite)
(Chalcopyrite)
Concentrate
Leaching
Electro-
Winning
Acid
Flotation
Primary
Crushing
Stockpile
Leaching(Oxide)
(Chalcocite)
Sec/Tert
Crushing
Customers
SmeltingElectro-
Refining
Offers full cost benefit of
$0.05-0.10/lb over
smelting & refining
23 October 25th, 2004
Bagdad Concentrate Leach Plant
August, 2003
24 October 25th, 2004
Concentrate Leach – Performance Summary
Operated since March 2003
18 months continuous operation
All key design criteria achieved
Above design throughput
Above design availability
Above design copper extraction
Operating costs in line with expectations
Demonstrated technical and economic viability of high
temperature process in the appropriate application, where the
dilute acid can be used beneficially
25 October 25th, 2004
Bagdad Concentrate Leach - Copper Production
0
200
400
600
800
1,000
1,200
1,400
1,600
1,800
Mar
-03
Apr
-03
May
-03
Jun-0
3
Jul-0
3
Aug
-03
Sep
-03
Oct
-03
Nov
-03
Dec
-03
Jan-0
4
Feb-0
4
Mar
-04
Apr
-04
May
-04
Jun-0
4
Jul-0
4
Aug
-04
Sep
-04
Pro
du
cti
on
(to
nn
es)
Production (metric tons) Design Basis Production
26 October 25th, 2004
Start-up Data (adapted from McNulty, 1998)
0%
20%
40%
60%
80%
100%
120%
140%
160%
0 5 10 15 20 25 30 35 40
Months Since Commissioning
% o
f D
esig
n C
ap
acit
y
Bagdad BCLP 3 Mo. Avg. Category 1
Category 2 Category 3 Category 4
27 October 25th, 2004
Concentrate Leaching & Direct Electrowinning
Mine
Heap
Leaching(Oxide)
(Chalcocite)
Solution
Extraction
Milling(Chalcocite)
(Chalcopyrite)
Concentrate
Leaching
Electro-
Winning
Flotation
Primary
Crushing
Stockpile
Leaching(Oxide)
(Chalcocite)
Sec/Tert
Crushing
Customers
Electro-
Winning
Potential to provide additional full cost benefits of up to $0.05/lb
copper over high temperature process (i.e. $0.10-0.15/lb total benefit)
28 October 25th, 2004
Concentrate Leach - MT-DEW-SX Process
Stockpile
Leach
Concentrate
Super-fine grind
DEW
Pressure Leach
SL
EW
SX
Cathode Cu
Tails
PLS from
stockpile
leach
29 October 25th, 2004
Concentrate Leach – The Path Forward
Conversion of Bagdad to medium-temperature and direct
electrowinning mode of operation under consideration
Construction started in 3Q04
Start up scheduled in 1Q05
Commercial demonstration complete by 4Q05
30 October 25th, 2004
Phelps Dodge Concentrate Leaching Developments
High temperature (>200oC) and medium temperature (140-180oC)
pressure leaching in sulfate media
Low cash cost alternative to smelting and refining
Safe, environmentally-sound
Acid balance is a critical cost driver
Concentrate, cathode and acid freight considerations
Ability to utilize existing SX and EW capacity
Utilize existing infrastructure
31 October 25th, 2004
Production Decisions Impacted by Concentrate/Acid Balance
Chino Smelter
650,000 tpy capacity
(off line)
North American Concentrate
• Bagdad
• Sierrita
• Chino (partial capacity)
• Cobre
• Morenci (off line)
North American Leach
• Morenci
• Bagdad
• Sierrita
• Chino
• Tyrone (partial capacity)
• Miami (partial capacity)
External
acid
source
Candelaria
concentrate
External
acid
consumer
Miami Smelter
750,000 tpy capacity
(operating)
External
concentrate
source
32 October 25th, 2004
Concentrate Leach – Potential Applications
Morenci
Preliminary feasibility study in progress
Scheduled for completion 4Q04
Cerro Verde primary sulfides
Preliminary feasibility study scheduled for 1Q05
El Abra primary sulfides
Other
33 October 25th, 2004
Copper Pressure Leaching – Critical Success Factors
TC/RC market conditions
Long term view?
Ability to understand and exploit acid balance at site(s)
Materials of construction
Operating control
Mineralogy
Competitive advantage
Speed of implementation
Scale of implementation
Ability to apply to greater proportion of production
Other technical developments
Improve capital and operating costs
Environmental permitting
Intellectual property
A complex environment