1 Municipality of Prijedor Infrastructure Projects Facility in the Western Balkans – Implemented by WYG Infrastructure Projects Facility in the Western Balkans Podrška infrastrukturnim projektima u zemljama Zapadnog Balkana Albania Bosnia & Herzegovina Croatia FYRo Macedonia Kosovo Montenegro Serbia Prijedor Water and Wastewater Project Projekat razvoja vodovodnog i kanalizacionog sistema Opštine Prijedor Project Preparation Feasibility Study Studija izvodljivosti za finansiranje projekata 05 March 2013 EIB Water and Sanitation Project in Republika Srpska Projekat vodovodne i kanalizacione infrastrukture u Republici Srpskoj

Upload: ledung

Post on 06-Feb-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

1Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Infrastructure Projects Facility in the Western BalkansPodrška infrastrukturnim projektima u zemljamaZapadnog Balkana

Albania

Bosnia &Herzegovina

Croatia

FYRoMacedonia

Kosovo

Montenegro

Serbia

Prijedor Water and Wastewater ProjectProjekat razvoja vodovodnog i

kanalizacionog sistema Opštine Prijedor

Project Preparation Feasibility StudyStudija izvodljivosti za finansiranje projekata

05 March 2013

EIB Water and Sanitation Project in Republika SrpskaProjekat vodovodne i kanalizacione infrastrukture u Republici Srpskoj

Page 2: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

2Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Opening RemarksUvodne napomene

Marko PavićMayor of Prijedor

Gradonačelnik Prijedora

Sohail HassanEnvironment Sector Key Expert – WYG-IPF1

Ključni ekspert za sektor zaštite životne sredine – WYG-IPF1

Page 3: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

3Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Structure of presentation

Introduction

Water supply –findings/recommendations

Wastewater collection findings/recommendations

Wastewater treatment and sludge managementfindings/recommendations

Evaluation of developmentoptions

Environment analysis

Financial analysis and appraisal

Implementation strategy

Uvod

Vodosnabdijevanje –nalazi/preporuke

Prikupljanje otpadnih voda –nalazi i preporuke

Tretman otpadnih voda i upravljanje muljem – nalazi i preporuke

Analiza razvojnih projekata

Analiza životne sredine

Finansijska analiza

Strategija implementacije

Sadržaj prezentacije

Page 4: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

4Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Water supply and wastewater collection and treatmentVodosnabdevanje, kanalisanje i tretman otpadnih voda

Dejan AndjelkovicSenior Engineer – Water and Wastewater

Odgovorni Inženjer – Komunalna HidrotehnikaWYG-IPF1

Page 5: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

5Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Input data

Demographics (RS Statistics Institute, estimates from Municipality and local communities)

Valid planning documentation (urban, spatial, regulation)

Areal photos, cadastral maps

Vodovod billing and maintenance database

Existing and proposed design / planning documentation from Municipality and Vodovod

Industrial flow and load data

Other relevant environmental and water/sanitation documentation and strategic plans

Demografski podaci (RZS i procene po lokalnim zajednicama)

Postojeća planska dokumentacija (urbanistički, prostorni, regulacioni...)

Aero snimci i katastarske mape

Baza potrošača i održavanja iz Vodovoda

Postojeća i planirana projektna i planska dokumentacija iz Opštine i Vodovoda

Podaci o kvantitetu i kvalitetu industrijskih otpadnih voda

Druga relevantna dokumentacija vezana za životnu sredinu, vodovod i kanalizaciju

Ulazni podaci

Page 6: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

6Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

0

10000

20000

30000

40000

50000

60000

70000

80000

90000

100000

110000

120000

1948 1953 1961 1971 1981 1991 1993 2006 2011

Year

Popu

latio

n

Municipality Urban Rural

Overall population trends from 1948-2011Promene ukupnog stanovništva od 1948-2011

Last censusPoslednji popis

Page 7: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

7Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Long term population projections (2011-2040)Dugoročne demografske projekcije (2011-2040)

-

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

110,000

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

2035

2036

2037

2038

2039

2040

Popu

latio

n / P

opul

acija

Prijedor town / Grad Prijedor Urban area / Urbano područjeRural areas / Ruralna područja Municipality / Opština

Page 8: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

8Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Long term water demand projections (all sub-systems)Dugoročne projekcije potreba za vodom (svi podsistemi)

Prijedor - Water demand projections - Long term (all sub-systems)

-

2,500

5,000

7,500

10,000

12,500

15,000

17,500

20,000

22,500

25,000

27,500

30,00020

12

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

2035

2036

2037

2038

2039

2040

Wat

er d

eman

d / P

otre

be z

a vo

dom

[m3/

day]

Household sales / domacinstva fakturisano , m3/d Commercial sales / Industrija fakturisano, m3/d

Social institutions sales / Javna preduzeca fakturisano, m3/d Total NRW / Ukupna neobracunata voda, m3/d

Page 9: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

9Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Long term WW production projections (all sub-systems)Dugoročne projekcije otpadnih voda (svi podsistemi)

-

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

11,000

12,000

13,000

14,000

15,000

16,000

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

2035

2036

2037

2038

2039

2040

WW

pro

duct

ion

/ Pro

dukc

ija o

tpad

nih

voda

[ m

3/d]

-

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

50,000

55,000

60,000

65,000

70,000

75,000

80,000

85,000

Popu

latio

n co

nnec

ted

/ Prik

ljuce

na p

opul

acija

Household WW / Domacinstva, m3/d Commercial WW / Industrija, m3/dSocial institutions WW / Javna preduzeca, m3/d Infiltration / Infiltracija, m3/d Population connected / Prikljucena populacija

Page 10: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

10Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Key Water Supply Issues - 1Ključna pitanja vodosnabdevanja - 1

Advantages:Good urban coverageAvailability and capacity of water sourcesGood raw water quality requiring minimal water treatmentUpgraded and rehabilitated water intake and transmission components of the systemDeveloped SCADA and telemetry On-going development and extension of service coverageAwareness of system shortcomings and requirementsCompetent and skilled Water Utility personnel

Prednosti:Dobra urbana pokrivenostDostupnost i kapacitet izvorištaDobar kvalitet sirove vode koji zahteva minimalan tretmanUnapređeni i rekonstruisani vodozahvatni i transportni objekti u sistemuUvedena SCADA i telemetrijaKontinuirano širenje sistema za snabdevanje vodom i pokrivenostiSvest o nedostacima i potrebama sistemaKompetentno i obučeno osoblje Vodovoda

Page 11: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

11Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Key Water Supply Issues - 2Ključna pitanja vodosnabdevanja - 2

Disadvantages:Over aged water distribution pipelines Undersized water mains / bottlenecksExtremely high NRW (around 80%)High rate (30%) of unmeteredcustomers/service connections Problems related to customer meter accuracy, calibration and replacementLimited service coverage of Prijedorwater supply system (around 80% urban, 55% rural). 55% on Municipality levelFrequent pipe breaks, insufficient network hydraulic capacity, lack of network zoningDecreasing trend of high energy consumptionLack of GIS and asset management databaseLack of calibrated hydraulic model

Nedostaci:Starost distributivnih cevovodaPostojanje „uskih grla“ i pod dimenzionisanih distributivnih cevovodaVisoka stopa neobračunate vode (oko 80%)Visok stepen (30%) nemerenih (paušalnih) kućnih priključaka / potrošačaNedostaci vezani za tačnost kućnih vodomera, njihovu kalibraciju i zamenuOgraničena pokrivenost sistemom (oko 80% gradski, 55% seoski). 55% na nivou OpštineČesti kvarovi, nedovoljni hidraulički kapacitet mreže, nedostatak zona u mrežiTrend smanjenja utroška el. energijeNedostatak GIS-a i baze podataka o objektimaNedostatak kalibrisanog matematičkog modela

Page 12: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

12Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Prijedor Water Supply SystemsPrijedor Water Supply System Vodovodni sistem Prijedora

Page 13: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

13Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Existing water sourcesPostojeća izvorišta

Water SourceIzvorište

Reference WellsPripadajući bunari

Maximum Capacity

Maksimalni kapacitet

(l/s)

Operational CapacityRadni kapacitet

(l/s)

Tukovi B-1, B-2 20.0 -

Matarusko polje I B-3, B-3/2, B-4, B-5 342.0 235.0

Matarusko polje II EB-1, EB-2, EB-3 235.0 150.0

Prijedorcanka PB-1, PB-3 115.0 75.0

TOTAL 712.0 460.0

Main Water Treatment / Disinfection Locations in the SystemGlavne lokacije uređaja za tretman / hlorisanje vode u sistemu

Well EB-3Bunar EB-3

Well B-5Bunar B-5

Well B-3/2Bunar B-3/2

WT BarakovacR Barakovac

PrijedorcankaPrijedorcanka

Page 14: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

14Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Overview of existing water distribution networkPregled postojeće vodovodne mreže

Page 15: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

15Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Basic water production and consumption dataOsnovni podaci o proizvodnji i potrošnji vode

Page 16: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

16Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Water Balance for Prijedor Water Supply SystemBilans proizvodnje i potrošnje vode u vodovodnom sistemu Prijedor

Water Balance ComponentKomponenta bilansa 2009 2010 2011 2012

(6 months)

Water produced – Prijedor Service AreaProizvedena voda

m3 10,589,559 11,228,309 10,405,794 5,718,421

Billed Water ConsumptionFakturisana potrošnja m3 2,316,877 2,183,292 2,136,498 1,090,789

Non-Revenue WaterNeobračunata voda NRW m3 8,272,682 9,045,017 8,269,296 4,627,632

Non-Revenue Water ContributionZastupljenost NRW % 78.12 80.56 79.47 80.92

2009 2010 2011 2012(6 months)

Water produced - Prijedor Service Area (l/s)Proizvedena voda – vodovodni sistem Prijedor 335.8 356.0 330.0 367.7

Water invoiced - population (l/s)Fakturisana potrošnja - domaćinstva 63.1 59.3 57.9 60.5

Water invoiced - industry (l/s)Fakturisana potrošnja - privreda 7.6 6.5 6.9 6.3

Water invoiced - public services/institutions (l/s)Fakturisana potrošnja - institucije 2.8 3.5 2.9 3.3

Water invoiced - total (l/s)Ukupna fakturisana potrošnja 73.5 69.2 67.7 70.1

Non-Revenue water (l/s)Neobračunata voda NRW 262.3 286.8 262.2 297.6

NRW contribution (%)NRW zastupljenost 78.12% 80.56% 79.47% 80.92%

Page 17: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

17Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Water and Wastewater Development Project in Prijedor MunicipalityProjekat Vodosnabdevanja i Kanalisanja u Opštini Prijedor

Overview of Technical Performance IndicatorsPrikaz tehničkih indikatora vodovodnog sistema Prijedor

2009 2010 2011 2012 (6 months)

Total Population in PrijedorWater Supply Service Area Broj stanovnika u Prijedorskomvodovodnom sistemu

70,385 73,037 75,828 75,881

Urban Urbano 48,198 50,005 51,890 51,942

Rural Seosko 22,188 23,032 23,938 23,939

Number of service connections Broj kućnih priključaka 13,144 13,748 14,599 16,582

Metered Connections Sa vodomerom 8,136 9,350 10,570 11,660

Non metered Connections Bez vodomera 5,008 4,398 4,029 4,922

Contribution (%) ZastupljenostMetered Consumption Merena potrošnja 62% 68% 72% 70%

Non metered Consumption Paušalna potrošnja 38% 32% 28% 30%

Population connected in Prijedor Water Supply Service Area Broj priključenih stanovnika naPrijedorski vodovodni sistem

41,587 48,252 50,580 54,518

Urban Urbano 33,262 38,562 40,231 41,282

Rural Seosko 8,325 9,690 10,349 13,235

Connection Rate Total (%) Stepen priključenosti Ukupno 59.08% 66.06% 66.70% 71.85%

Connection Rate Urban (%) Stepen priključenosti Urbani 69.01% 77.12% 77.53% 79.48%

Connection Rate Rural (%) Stepen priključenosti Seoski 37.52% 42.07% 43.23% 55.29%

2009 2010 2011 2012 (6 months)

Length of network per connected capita (m/capita)* Dužina distributivne mreže popotrošaču

3.8

Number of consumers per km of network* Broj potrošača po km distributivne mreže

265

Number of service connections per km Broj kućnih priključaka po km

64.0 67.0 71.0 80.0

Water produced - PrijedorService Area (m3) Proizvedena voda (m3/god)

10,589,559 11,228,309 10,405,794 5,718,421

Energy Consumption-Water Production (kWh) Utrošena el. Energija -proizvodnja vode (kWh/god.)

6,667,693 6,544,456 5,505,183 2,302,848

Specific Energy Consumption - Water Production (kWh/m3) Specificna potrošnjaenergije - Proizvodnja vode

0.63 0.58 0.53 0.40

* Note: Based on length of water distribution mains as per 2008 (205,377 m) and connected population as per 2012.Vrednosti na osnovu podataka o dužini distributivne mreže iz 2008. i priključenom stanovništvu iz 2012. godine.

Page 18: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

18Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Unit Consumption RatesVrednosti specifične potrošnje

2009 2010 2011 2012 (6 months)

Unit consumption rate - gross (l/cap/day) Ukupna bruto specifična potrošnja (l/stan/dan) 697.6 637.5 563.6 582.7

Unit consumption rate - total (l/cap/day) Ukupna specifična potrošnja (l/stan/dan) 152.6 124.0 115.7 111.2

Unit consumption rate - population total (l/cap/day) Specifična potrošnja stanovništva - ukupna (l/stan/dan) 131.1 106.1 99.0 101.3

Unit consumption rate - population urban (l/cap/day) Specifična potrošnja stanovništva - urban (l/stan/dan) 132.2 109.7 103.3 101.8

Unit consumption rate - population rural (l/cap/day) Specifična potrošnja stanovništva - rural (l/stan/dan) 113.3 95.7 88.9 99.6

Unit consumption rate - industrial (l/cap/day) Specifična potrošnja privrede (l/stan/dan) 15.8 11.6 11.9 10.0

Unit consumption rate - institutional (l/cap/day) Specifična potrošnja institucija (l/stan/dan) 5.8 6.3 4.9 5.3

Unit rate - Non-Revenue water (l/cap/day) Specifična potrošnja NRW (l/stan/dan) 545.0 513.6 447.9 471.6

Page 19: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

19Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Improvement of Water Utility’s operational efficiency.Rehabilitation and replacement of

existing water distribution network.Extension of water distribution

network in the service area of existing water supply system.Construction of water distribution

network in the settlements of “CrnoVrelo” subsystem.Development of “Tomasica lakes”

water supply subsystem.Development of water sources.

Proposed water supply improvementsPredlozi za unapređenje vodosnabdevanja

Unapređenje operativne efikasnosti vodovodog sistema PrijedorRehabilitacija i rekonstrukcija

postojeće vodovodne distributivne mrežeProširenje distributivne mreže u okviru

postojećeg vodovodnog sistema.Izgradnja distributivne mreže u

naseljima vodovodnog podsistema “Crno Vrelo”Razvoj vodovodnog podsistema

„Tomašička jezera“Dodatna istraživanja i razvoj izvorišta

vode

Page 20: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

20Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Proposed water supply improvementsPredlozi za unapređenje vodosnabdevanja

Prijedor Water Supply SystemsPrijedor Water Supply System Vodovodni sistem Prijedora

Page 21: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

21Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Summary of Water Supply Development Options (Priority Investment Programme) Pregled razvojnih opcija za vodosnabdevanje (Prioritetni Investicioni Program)

Total costs include escalation throughout implementation period (2013-2016)Ukupne cene korigovane za inflaciju tokom perioda implementacije (2013-2016)

Cases used in financial appraisalRazvojne opcije korišćene za finansijsku ocjenu

5,007,7304,280,110Crno Vrelo – primary networks in settlementsCrno Vrelo – primarna mreža u naseljima

Minimum Case for Financial Appraisal Minimalni Slučaj za Finansijsku Ocjenu

KM exc VATKM bez PDV-a

KM inc VATKM sa PDV-om

Rehabilitation of Prijedor central water supply systemRehabilitacija mreže – Prijedorski sistem 3,296,690 3,857,130

Total for Minimum CaseUkupno za Minimalni Slučaj 7,576,800 8,864,860

Base Case for Financial AppraisalOsnovni Slučaj za Finansijsku Ocjenu

KM exc VATKM bez PDV-a

KM inc VATKM sa PDV-om

Total Investments - Minimum Case Ukupne Investicije – Minimalni Slučaj 7,576,800 8,864,860

Tomasica Lakes project (new source, primary and secondary networks)Tomašička jezera (novo izvorište, primarne i sekundarne mreže) 7,354,700 8,605,000

Total for Base Case Ukupno za Osnovni Slučaj 14,931,500 17,469,860

High Case for Financial AppraisalViši Slučaj za Finansijsku Ocjenu

KM exc VATKM bez PDV-a

KM inc VATKM sa PDV-om

Same as Base CaseIsto kao za Osnovni SlučajTotal for High CaseUkupno za Viši Slučaj 14,931,500 17,469,860

Page 22: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

22Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Existing wastewater systems within 1) urban and 2) Municipality areasPostojeći kanalizacioni sistemi u 1) urbanom 2) opštinskom području

Municipality border –Granica Opštine

Urban area border –Granica urbanog područja

Page 23: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

23Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Prijedor - Existing collection system Prijedor – Postojeći kanalizacioni sistem

1590 ha currently sewered (22% of wider urban area, and 2% of municipal area)Total existing population connected = 34,030 (62% of urban population, 34% of municipal population)Existing system comprises Prijedor centre, and urban areas of Urije, Cirkin Polje, Orlovaca, RaskovacCombined system (250 km, mostly concrete, AC and some recent PVC extensions)Single main outfall to open channel tributary to Sana River, no existing wastewater treatmentDirect discharges to Puharska and other streams, and Sana and Gomjenica rivers

1590 ha pokriveno kanalizacionim sistemom (22% površine šireg urbanog područja, i 2% površine Opštine) Ukupno priključeno 34,030 stanovnika (62% urbane populacije, i 34% opštinske populacije)Postojeći sistem pokriva Prijedor centar, Urije, Čirkin Polje, Orlovača, Raskovac...Opšti sistem (250 km, uglavnom betonske i AC cevi, noviji projekti od plastičnih cevi)Jedan glavni ispust u otvoreni kanal koji se uliva u Sanu, nema tretmana otpadnih vodaDirektni ispusti u Puharsku i druge potoke, kao i u Sanu i Gomjenicu

Page 24: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

24Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Existing wastewater system within Prijedor urban areaPostojeći kanalizacioni sistem u urbanom području Prijedora

Existing service areaObuhvat postojećeg sistema

Urban area border –Granica urbanog područja

Page 25: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

25Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Main collector, open wastewater channel, Puharska streamGlavni kolektor, otvoreni kanal, Puharska

Outfall of open channel to Sana

river

Outfall of main collector to

open channel

Sana River

Open wastewater channel

Novi Grad- Prijedor- Banja

Luka Road

Page 26: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

26Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Main collector, open wastewater channel, Puharska streamGlavni kolektor, otvoreni kanal, Puharska

Page 27: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

27Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Prijedor subsystem (long term expansions)Prijedorski podsistem (dugoročna proširenja)

Page 28: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

28Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Prijedor – Hydraulic model and analysisPrijedor – Hidraulički model i analiza

2009 flow data available for limited model calibration, best available population and water usage data usedPodaci merenja iz 2009 god. korišćeni za grubu kalibraciju modela, kao i realne procene populacije i potrošnje vodePrimary and main collectors are not more than 75% full during peak flows per section, in 2040 scenarioStepen ispunjenosti kolektora do 75% za maksimalne proticaje po deonici, na kraju projektnog perioda(2040)Self-cleaning velocities achieved for proposed diamaters even with existing average DWFSamočišćenje se postiže za predložene prečnike i sa trenutnim srednjim dnevnim proticajima u suvomperiodu

Page 29: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

29Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Alternative options for conveyance system to WWTPAlternative transporta otpadnih voda ka PPOV

Option 1Required main collector lengthL= 5 km

Option 2Required main collector lengthL= 2.45km (cost saving cca Eur 1 Million)

Page 30: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

30Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Proposed option for conveyance system to WWTPPredložena opcija transporta otpadnih voda ka PPOV

Overflow structure

Siphon under Puharska stream

Main collector to WWTP

Existing main collector and outfall

Page 31: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

31Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Alternative options for Gomjenica (least cost analysis)Alternativne opcije za Gomjenicu

OPTION 1 OPTION 2

UnitSeparate

Gomjenica and Prijedor WWTPs

Pump Gomjenica flows to single Prijedor WWTP

INVESTMENTS - KEY DATAWWTPCapacity (long term) - Prijedor + Gomjenica PE - 62,000 Capacity (long term) - Prijedor PE 57,000 - Capacity (long term) - Gomjenica PE 5,000 - Pumping stationsGomjenica main pumping station (H = 4m) l/s 25

INVESTMENT COSTSPrijedor WWTP (long term, including land costs) € x 1000 6,406 6,784 Gomjenica WWTP (long term, including land costs) € x 1000 925 - Gomjenica main pumping station and pressure main (incl. land) € x 1000 - 95

INVESTMENT COST TOTAL € x 1000 7,331 6,879 Land cost € x 1000 248 237 Civil cost € x 1000 2,834 2,669 M&E cost € x 1000 4,250 3,973 OPERATION & MAINTENANCE COSTS (Annual)Maintenance € x 1000 91 86 Energy costs € x 1000

Prijedor WWTP (long term) € x 1000 48 51 Gomjenica WWTP (long term) € x 1000 21 - Gomjenica main pumping station € x 1000 2

Staff costs € x 1000 112 88 Chemical/sludge disposal € x 1000 149 145 ANNUAL O&M COSTS TOTAL € x 1000 421 371 NET PRESENT VALUES (20 years, discounted @ 8%) € x 1000 11,022 10,117LONG-TERM AVERAGE INCREMENTAL COST €/m3 0.38 0.34

Page 32: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

32Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Conveyance schematic for Prijedor subsystem Šematski prikaz Prijedorskog podsistema

Page 33: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

33Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Population connected - Prijedor subsystem Priključeno stanovništvo – Prijedorski podsistem

Page 34: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

34Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

WWTP Prijedor – Designated area for proposed sitePPOV Prijedor – Šire područje za predviđenu lokaciju

Page 35: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

35Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

WWTP Prijedor – Incoming flows and loadsPPOV Prijedor – Ulazna hidraulička i organska opterećenja

565480l/sPeak flow to preliminary treatmentMaksimalni proticaj ka preliminarnom tretmanu

ParameterParametar

UnitJedinica

Phase 1 (2030)Faza 1 (2030)

Phase 2 (2040+)Faza 2 (2040+)

Population connectedPriključeni stanovnici - 43,500 52,000

Population equivalentEkvivalentni stanovnici

PEES 51,000 62,000

Average dry weather flow (total, including infiltration)Prosecni proticaj u suvom periodu (ukupni, sa infiltracijom) l/s 123 140

Peak flow to full treatmentMaksimalni proticaj ka punom tretmanu l/s 240 282

BODBPK kg/d 3,110 3,745

SSUkupne rastvorene materije kg/d 3,565 4,300

BODBPK mg/l 287 305

NitrogenAzot mg/l 53 56

PhosphorusFosfor mg/l 8.6 9.2

SSUkupne rastvorene materije mg/l 336 357

Page 36: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

36Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Prijedor Phase 1 WWTP – Process alternatives and cost summariesPPOV Prijedor Faza 1 – Procesne alternative i pregled troškova

92

103

103

102

94

98

Cost per PETrošak po ES

Eur

0.364645,316SBR (extended aeration)SBR (produžena aeracija)

Option - OpcijaInvestment Cost

Inv. Troškovi000 Eur

Annual Running Costs

Godišnji Op. Troškovi000 Eur

Average Incremental

CostSrednji

inkrementni trosakEur/m3

Conventional Activated Sludge with anaerobic sludge digestionKonvencionalni aktivni mulj sa anaerobnom digestijommulja

5,054 229 0.27

Activated Sludge (no primary settlement) with anaerobic sludge digestionAktivni mulj (bez primarnog taloženja) sa anaerobnomdigestijom mulja

4,878 270 0.28

Oxidation ditch (extended aeration)Oksidacioni jarak (produžena aeracija) 5,298 442 0.35

Activated Sludge (no primary settlement) with aerobic sludge stabilisationAktivni mulj (bez primarnog taloženja) sa aerobnomstabilizacijom mulja

5,340 390 0.34

SBR (primary settlement) with anaerobic sludge digestionSBR (sa primarnim taloženjem) sa anaerobnomdigestijom mulja

4,765 232 0.26

Page 37: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

37Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Prijedor Phase 1 WWTP – Process alternatives and cost summariesPPOV Prijedor Faza 1 – Procesne alternative i pregled troškova

117

95

108

82

89

Cost per PETrošak po ES

Eur

0.314244,263

Conventional Activated Sludge with lime sludge stabilisationKonvencionalni aktivni mulj sa stabilizacijom muljakrečom

0.292155,578

Biological filter with stone media and anaerobic digestionBiološki filter sa kamenom ispunom i anaerobnom digestijom

0.313664,938Biological filter with plastic media and lime stabilisationBiološki filter sa plastičnom ispunom i stabilizacijom krečom

Option - OpcijaInvestment Cost

Inv. Troškovi000 Eur

Annual Running Costs

Godišnji Op. Troškovi000 Eur

Average Incremental

CostSrednji

inkrementni trosakEur/m3

SBR (no primary settlement) with anaerobic sludge digestionSBR (bez primarnog taloženja) sa anaerobnomdigestijom mulja

4,603 258 0.27

Membrane Bioreactor (MBR)Membranski bioreaktor (MBR) 6,042 482 0.40

Page 38: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

38Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

WWTP Prijedor – Proposed layoutPPOV Prijedor – Predložena dispozicija

Page 39: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

39Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

WWTP Prijedor – Process flow diagramPPOV Prijedor – Procesni dijagram

Page 40: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

40Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

WWTP Prijedor – Main process unitsPPOV Prijedor – Glavne procesne jedinice

(2 duty + 1 standby) pumps, each @ Q=1017 m3/hInlet pumping stationUlazna pumpna stanica

UnitJedinica

Phase 1 (51,000 PE)Faza 1 (51,000 ES)

Phase 2 (62,000 PE)Faza 2 (62,000 ES)

Preliminary treatmentPreliminarni tretman

Screening, Grit Removal and Odour ControlFine rešetke, aerisani peskolov, kontrola mirisa

Primary settling tanksPrimarni taložnici 2 x D=23m 2 x D=23m

Biological treatmentBiološki tretman

4 SBR tanks (V tot=4,150 m³)

8 SBR tanks (V tot=8,300 m³)

Secondary settlementSekundarno taloženje

Not required with SBR processNije potrebno sa SBR procesom

Sludge thickeningUgušćivanje mulja

Primary thickener / Primarni ugušćivač

(1 x D=7m)

Primary thickener / Primarni ugušćivač

(1 x D=7m)

Sludge treatmentTretman mulja 2 x Anaerobic digestor (D=12m)2 x Anaerobic digestor (D=12m)

DewateringDehidracija mulja 1 x belt thickener / trakasti ugušćivač1 x belt thickener / trakasti ugušćivač

Sludge storageSkladištenje mulja

1 x sludge tank / tank za mulj(D=8 m)

1 x sludge tank / tank za mulj(D=8 m)

Page 41: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

41Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Rehabilitation – Prijedor subsystem Rehabilitacija – Prijedorski podsistem

Design horizon up to 2030, costs include design and physical contingency (10%)

Vremenski horizont do 2030, cene uključuju projektovanje i rezervu za nepredviđene troškove (10%)

29,271,65015,011,10025,018,50012,830,000TOTAL Rehabilitation - Prijedor sub-systemUKUPNO Rehabilitacija – Prijedorski podsistem

27,378,00014,040,00023,400,00012,000,000

Long term replacement programme for combined system -Prijedor (20 year programme)Dugoročni program rehabilitacije za kombinovan sistem (20 godina)

1,825,200936,0001,560,000800,000

Immediate rehabilitation measures (estimate, actual needs defined following system survey)Hitne mere za rehabilitaciju (stvarne potrebe će biti definisane nakon detaljnog snimanja)

68,45035,10058,50030,000

Survey of existing Prijedor wastewater system (Flows and loads, CCTV)Snimanje postojećeg sistema, merenje količina i sastava otpadnih voda

[KM][€][KM][€]

Amount inc VAT / Iznos sa PDV

Amount excl VAT / Iznos bez PDV

ComponentKomponenta

Page 42: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

42Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Sewage extensions – Prijedor subsystem Proširenje kanalizacione mreže – Prijedorski podsistem

Design horizon up to 2030, costs include design and physical contingency (10%)

Vremenski horizont do 2030, cene uključuju projektovanje i rezervu za nepredviđene troškove (10%)

26,963,53013,827,48023,045,73011,818,290TOTAL Sewage extensions –Prijedor sub-system

1,517,840778,3801,297,300665,280Remaining Prijedor secondary network and house connections

996,090510,820851,360436,590Gornja Puharska secondary network and house connections

1,043,520535,140891,900457,380Raskovac secondary network and house connections

806,360413,520689,190353,430Orlovaca secondary network and house connections

474,330243,250405,410207,900Donji Orlovci secondary network and house connections

112,94057,92096,53049,500Donja Puharska secondary network and house connections

1,438,790737,8401,229,730630,630Cejreci secondary network and house connections

996,090510,820851,360436,590Brezicani secondary network and house connections

11,167,9505,727,1509,545,2504,895,000Gomjenica primary, secondary networks and house connections

4,065,6402,084,9403,474,9001,782,000Tukovi secondary network and house connections

926,070474,910791,510405,900Primary collector Donja Puharska / Cejreci

911,010467,190778,640399,300Primary collector along Puharska stream left bank (GornjaPuharska, Gasica naselje)

1,352,710693,7001,156,160592,900Primary collector along Puharska stream right bank

1,154,190591,900986,490505,890Primary collectors from Brezicani to WWTP site

[KM][€][KM][€]

Amount inc VAT Amount excl VAT Component

Page 43: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

43Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Conveyance and treatment – Prijedor subsystem Transport i tretman otpadnih voda – Prijedorski podsistem

Design horizon up to 2030, costs include design and physical contingency (10%)

Vremenski horizont do 2030, cene uključuju projektovanje i rezervu za nepredviđene troškove (10%)

17,913,000 9,186,150 15,310,230 7,851,400 TOTAL Conveyance and treatment - Prijedor sub-system / UKUPNO Transport I tretman - Prijedorski podsistem

5,132,010 2,631,800 4,386,330 2,249,400 Prijedor WWTP - upgrade to Phase 2 (62,000 PE total ) / PPOV Prijedor - Faza 2 (ukupno 62,000 ES)

11,015,090 5,648,760 9,414,600 4,828,000 Prijedor WWTP - Phase 1 (51,000 PE) / PPOV Prijedor - Faza 1 (51,000 ES)

180,700 92,670 154,440 79,200 WWTP bypass pipeline to river / Obilazni vod oko PPOV

1,475,680 756,760 1,261,260 646,800 Main collector to WWTP site / Glavni kolektor do PPOV

75,290 38,610 64,350 33,000 Crossing under Puharska stream (dual inverted siphon)/ Prolaz ispod Puharske (sifon)

34,230 17,550 29,250 15,000 Overflow structure upstream of existing main outfall / Prelivna građevina uzvodno od postojećeg ispusta

[KM][€][KM][€]

Amount inc VAT / Iznos sa PDV

Amount excl VAT / Iznos bez PDV

ComponentKomponenta

Page 44: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

44Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Sewage extensions – Kozarac subsystemProširenje kanalizacione mreže – Podsistem Kozarac

Page 45: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

45Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Costs include design and physical contingency (10%)

Cene uključuju projektovanje i rezervu za nepredviđene troškove (10%)

Sewage extensions – Kozarac subsystemProširenje kanalizacione mreže – Podsistem Kozarac

30,009,51015,389,50025,649,13013,153,400TOTAL Sewage extensions - Kozarac sub-system

1,543,440791,5101,319,180676,500Kozarusa WWTP (2850 PE)

4,594,8602,356,3403,927,2302,013,970Kozarusa primary, secondary networks and house connections

1,392,860714,2901,190,480610,500Trnopolje WWTP (2400 PE)

8,008,3004,106,8206,844,7003,510,100Trnopolje primary, secondary networks and house connections

1,028,960527,670879,450451,000Kamicani WWTP (1500 PE)

5,411,4402,775,1004,625,1602,371,880Kamicani primary, secondary networks and house connections

903,480463,320772,200396,000Kevljani-Petrov Gaj WWTP (2000 PE)

1,310,040671,8201,119,690574,200Kevljani-Petrov Gaj primary, secondary networks and house connections

1,932,440990,9901,651,650847,000Kozarac WWTP (7000 PE)

3,883,6901,991,6403,319,3901,702,250Kozarac primary, secondary networks and house connections

[KM][€][KM][€]

Amount inc VAT Amount excl VAT Component

Page 46: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

46Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Sewage extensions – Omarska subsystemProširenje kanalizacione mreže – Podsistem Omarska

Page 47: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

47Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Costs include design and physical contingency (10%)

Cene uključuju projektovanje i rezervu za nepredviđene troškove (10%)

Sewage extensions – Omarska subsystemProširenje kanalizacione mreže – Podsistem Omarska

23,161,59011,877,74019,796,24010,151,910TOTAL Sewage extensions –Omarska sub-system

2,384,1701,222,6502,037,7501,045,000Omarska WWTP (7600 PE)

4,208,6902,158,3003,597,1701,844,700Nisevici primary, secondary networks and house connections

3,036,0501,556,9502,594,9201,330,730Donja Lamovita primary, secondary networks and house connections

3,236,8301,659,9102,766,5201,418,730Srednja Lamovita primary, secondary networks and house connections

2,766,8901,418,9202,364,8701,212,750Srednja Omarska primary, secondary networks and house connections

2,679,0601,373,8802,289,7901,174,250Donja Omarska primary, secondary networks and house connections

4,849,9002,487,1304,145,2202,125,750Omarska primary, secondary networks and house connections

[KM][€][KM][€]

Amount inc VAT Amount excl VAT Component

Page 48: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

48Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Costs include design and physical contingency (10%)

Cene uključuju projektovanje i rezervu za nepredviđene troškove (10%)

Sewage extensions – Rural systemsProširenje kanalizacione mreže – Ruralni sistemi

9,752,3205,001,2308,335,3204,274,510TOTAL Sewage extensions and treatment - Rural sub-systems

214,580110,040183,40094,050Rakovcani WWTP (300 PE)

282,340144,790241,320123,750Rakovcani sewage network and house connections

185,97095,370158,95081,510Rizvanovici WWTP (300 PE)

244,700125,490209,140107,250Rizvanovici sewage network and house connections

257,500132,050220,080112,860Biscani WWTP (400 PE)

338,810173,750289,580148,500Biscani sewage network and house connections

793,680407,020678,360347,880Hambarine WWTP (1200 PE)

1,082,290555,020925,040474,380Hambarine sewage network and house connections

472,070242,090403,480206,910Carakovo WWTP (600 PE)

621,140318,540530,890272,250Carakovo sewage network and house connections

472,070242,090403,480206,910Zecovi WWTP (600 PE)

621,140318,540530,890272,250Zecovi sewage network and house connections

1,443,050740,0301,233,380632,500Ljubija WWTP (2500 PE)

724,670371,630619,370317,630Ljubija secondary network and house connections

1,998,3101,024,7801,707,960875,880Ljubija primary network

[KM][€][KM][€]

Amount inc VAT Amount excl VAT Component

Page 49: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

49Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Proposed wastewater systems (Long term)Predviđeni kanalizacioni sistemi (Dugoročno)

Page 50: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

50Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Municipality of Prijedor – Long term strategic WW investment programmeOpština Prijedor – Dugoročni investicioni program za otpadne vode

137,071,60070,293,200117,155,15060,079,510TOTAL Long Term Strategic Investment ProgrammeUKUPNO Dugoročni Strateški Investicioni Program

9,752,3205,001,2308,335,3204,274,510TOTAL Collection and treatment – Rural sub-systemsUKUPNO Prikupljanje i tretman – Ruralni podsistemi

23,161,59011,877,74019,796,24010,151,910TOTAL Collection and treatment - Omarska sub-systemUKUPNO Prikupljanje i tretman – Podsistem Omarska

30,009,51015,389,50025,649,13013,153,400TOTAL Collection and treatment - Kozarac sub-systemUKUPNO Prikupljanje i tretman – Podsistem Kozarac

26,963,53013,827,48023,045,73011,818,290TOTAL Sewage extensions - Prijedor sub-systemUKUPNO Proširenja – Prijedorski podsistem

29,271,65015,011,10025,018,50012,830,000TOTAL Rehabilitation - Prijedor sub-systemUKUPNO Rehabilitacija – Prijedorski podsistem

17,913,0009,186,15015,310,2307,851,400TOTAL Conveyance and treatment – Prijedor sub-systemUKUPNO Glavni kolektor i tretman – Prijedorski podsistem

[KM][€][KM][€]

Amount inc VAT / Iznos sa PDV

Amount excl VAT / Iznos bez PDV

ComponentKomponenta

Costs include design and physical contingency (10%)

Cene uključuju projektovanje i rezervu za nepredviđene troškove (10%)

Page 51: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

51Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Wastewater - Priority Investment Programme (EIB project) Otpadne vode - Prioritetni Investicioni Program (Projekat EIB)

Page 52: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

52Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Wastewater - Priority Investment Programme Otpadne vode - Prioritetni Investicioni Program

8,301,8207,095,570Total Investments - Minimum Case Ukupne Investicije – Minimalni Slučaj

4,116,4603,518,340Tukovi - secondary network and house connections (Phase 2)Tukovi – sekundarna mreža i kućni priključci (Faza 2)

1,814,7251,551,050Conveyance system to Prijedor WWTP (overflow, main collector, bypass pipeline)Transportni sistem do PPOV Prijedor (preliv, glavni kolektor, obilazni vod)

Minimum Case for Financial Appraisal (from approved Project Fiche)Minimalni Slučaj za Finansijsku Ocjenu (po odobrenom Projektnom Fišeu)

KM exc VATKM bez PDV-a

KM inc VATKM sa PDV-om

Gomjenica - wastewater network (Phase 1)Gomjenica – kanalizacija (Faza 1)

3,577,230 4,185,360

Total for Minimum Case Ukupno za Minimalni Slučaj 7,095,570 8,301,820

Base Case for Financial Appraisal (from approved Project Fiche)Osnovni Slučaj za Finansijsku Ocjenu (po odobrenom Projektnom Fišeu)

KM exc VATKM bez PDV-a

KM inc VATKM sa PDV-om

Kozarac primary and secondary sewage and stormwater networksKozarac – primarna i sekundarna fekalna kanalizacija, kišna kanalizacija 3,422,135 4,003,900

Omarska and Donja Omarska - primary and secondary sewage and stormwater networksOmarska i Donja Omarska – primarna i sekundarna fekalna kanalizacija, kišna kanalizacija 7,674,000 8,978,580

Total for Base Case Ukupno za Osnovni Slučaj 18,191,705 21,284,300

High Case for Financial AppraisalViši Slučaj za Finansijsku Ocjenu

KM exc VATKM bez PDV-a

KM inc VATKM sa PDV-om

Total Investments – Minimum and Base CasesUkupne Investicije – Osnovni Slučaj 18,191,705 21,284,300

Prijedor WWTP (Phase 1 = 51000 PE)PPOV Prijedor (Faza 1 = 51000 ES) 9,845,360 11,519,075

Total for High Case Ukupno za Viši Slučaj 29,588,115 34,618,095

Page 53: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

53Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Summary of Priority Investment Programme for Financial AppraisalPregled razvojnih opcija za finansijsku ocjenu

38,754,16033,123,205Total Investments (water and wastewater) - Base Case Ukupne Investicije (vodovod i kanalizacija) – Osnovni Slučaj

17,166,68014,672,370Total Investments (water and wastewater) - Minimum Case Ukupne Investicije (vodovod i kanalizacija) – Minimalni Slučaj

8,605,0007,354,700Investments - Water supplyInvesticije – Vodosnabdevanje

8,864,8607,576,800Investments - Water supplyInvesticije – Vodosnabdevanje

Minimum Case for Financial Appraisal (from approved Project Fiche)Minimalni Slučaj za Finansijsku Ocjenu (po odobrenom Projektnom Fišeu)

KM exc VATKM bez PDV-a

KM inc VATKM sa PDV-om

Investments - WastewaterInvesticije – Otpadne vode

7,095,570 8,301,820

Total for Minimum Case Ukupno za Minimalni Slučaj 14,672,370 17,166,680

Base Case for Financial Appraisal (from approved Project Fiche)Osnovni Slučaj za Finansijsku Ocjenu (po odobrenom Projektnom Fišeu)

KM exc VATKM bez PDV-a

KM inc VATKM sa PDV-om

Investments - WastewaterInvesticije – Otpadne vode 11,096,135 12,982,480

Total for Base Case Ukupno za Osnovni Slučaj 33,123,205 38,754,160

High Case for Financial AppraisalViši Slučaj za Finansijsku Ocjenu

KM exc VATKM bez PDV-a

KM inc VATKM sa PDV-om

Investments - Water supplyInvesticije – Vodosnabdevanje 0 0

Investments - WastewaterInvesticije – Otpadne vode 11,396,410 13,333,800

Total for High Case Ukupno za Viši Slučaj 44,519,615 52,087,960Total costs include escalation throughout implementation period (2013-2016)Ukupne cene korigovane za inflaciju tokom perioda implementacije (2013-2016)

Cases used in financial appraisalRazvojne opcije korišćene za finansijsku ocjenu

Page 54: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

54Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

EnvironmentalZaštita životne sredine

Findings and recommendations in respect to proposed development project

Nalazi i preporuke predloženog razvojnog projekta

Karina ZachodniSenior Environmentalist – WYG-IPF1

Ekspert za zaštitu životne sredine – WYG-IPF1

Page 55: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

55Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Environmental Considerations –Pitanja životne sredine

Environmental review – contentLegal ReviewWater quality, healthWastewaterWWTP locationWater

•Impact of developments:•Benefits &• Summary Impact Assessment

Pregled životne sredine - sadržajPravni aspektiKvalitet vode i zdravljeZagađenje otpadnim vodamaAlternativne lokacije za PPOVKoristi i uticaj razvojaKratka procjena uticaja Vode

Page 56: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

56Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Existing legislativeEnvironment protection (EU Directive 85/337/EEC)Water (WFD)Nature (92/45/EEC and 79/409/EEC)Waste (WFD 2006/12/EC)Spatial PlanningCultural heritage

Drinking waterDischarges to surface watersDischarges to sewageWasteSewage sludge disposal

Postojeća regulativaZaštita životne sredine (Direktiva EU 85/337/EEC)Voda (ODV)Priroda (92/45/EEC i 79/409/EEC)Otpad (WFD 2006/12/EC)Prostorno uređenjeKulturno naslijeđe

Voda za pićeIspuštanje u površinske vodeIspuštanje u kanalizacijuOtpadOdlaganje kanalizacionog mulja

Key differences – Osnovne razlike

Page 57: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

57Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

EIA - PUŽS

Environmental Impact Assessment in Law on Protection of Environment (OGRS, no. 53/02)EIA contents (OGRS, 118/05), projects with obligatory EIA, criteria for obligation and scope of EIA (OGRS, 07/06)

Procedure (up to 285 days):ScreeningDeciding on need for EIAScope and contents of EIA studyPublic discussionRevision of EIA studyDecision on request for EIA consent

• Procjena uticaja na životnu sredinu u Zakonu o zaštiti životne sredine (SGRS; br, 53/02)

• Sadržaj PUŽS (SGRS, 118/05), projekti za koje se sprovodi PUŽS, obaveza sprovođenja i obim PUŽS (SGRS, 07/06)

• Procedura (do 285 dana):– Prethodna PUŽS– Odluka o potrebi za PUŽS– Sadržaj studije o PUŽS– Javna rasprava– Revizija studije o PUŽS– Odobravanje PUŽS

Page 58: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

58Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Pre-treatment of Industrial WW –Predtretman industrijskih otpadnih voda

Page 59: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

59Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Local level – Lokalni nivo

The Decision on Water Supply and Sewage (OG no. 05/07)Decision on Approval of Draft Version of Programme for Sanitary Protection of Water (OG no. 05/05) ) Decision on Approval of Final Version of Programme for Sanitary Protection of Water (OG no. 01/06)Decision on Protection of Water Intakes Matarusko polje –Tukovi, Matarusko polje II and Prijedorcanka (OG no. 09/06)Decision on Rural Public Drinking Water Supply Structures (OG no. 01/04)

Page 60: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

60Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Wastewater Producers -Proizvođači

otpadnih voda

Septic Tanks– Septičke

jame

Wastewater collection system –

Sistem za prikupljanje

otpadnih voda

Sana River and Streams – Rijeka Sana i pritokeGroundwater – podzemne vode

Downstream Users

- Nizvodni korisnici

polluted infiltration – zagađenje infiltracijom

untreated wastewater / solids / sludgenetretirane otpadne vode / čvrste materije / mulj

Existing Situation – Postojeće stanje

Page 61: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

61Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Sana River Water Quality Kvalitet vode reke Sane

0.001

0.01

0.1

1

10

100

1000

10000

100000

10000000.00

1

0.01 0.1 1 10 100

1000

1000

0

1000

00

1000

000

Value at Nov

i Grad

Value at Prijedor

Ukupni fosfor

Ortofosfati

NO2‐N

Kadmijum

Uk.br. koliformnih  fekalnih bakterija

Uk. br. koliformnih bakterija

Uk. br. fekalnih streptokoka

Uk. br. aerobnih organotrofa 26oC

Uk. br. aerobnih organotrofa 36 oC

No change

Novi Grad = Prijedor x 2

Novi Grad = Prijedor x 5

Novi Grad = Prijedor x 20

Page 62: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

62Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Water Quality and Flooding Kvalitet vode i poplave

Town supplied with chlorinated groundwaterNormally good qualityRising trend of failed samples as a percentage of the total taken for both raw water and, to a lesser degree, treated waterFlooding also a construction risk

Snabdjevanje hlorisanom vodom Pretežno dobar kvalitet vodePovećan stepen neadekvatnih uzoraka za sirovu vode, i manjim delom za tretiranu voduPoplave predstavljaju rizik za izgradnju

0%

2%

4%

6%

8%

10%

Jul‐10 Aug‐10 Oct‐10 Dec‐10 Mar‐11 May‐11 Jul‐11 Sep‐11 Nov‐11 Jan‐12 Mar‐12 May‐12 Jul‐12

Cumulative % of all sam

ples failing

Failed Raw Water Samples by Supply System

% Raw (failed)

% Ljubija – Hambarine subsystem (failed)

% Urban subsystem (failed)

0%

5%

10%

15%

20%

25%

Jul‐10 Aug‐10 Oct‐10 Dec‐10 Mar‐11 May‐11 Jul‐11 Sep‐11 Nov‐11 Jan‐12 Mar‐12 May‐12 Jul‐12

Cumulative

 % of all Sam

ples Failing

Failed Treated Water Samples by Distribution System

% Treated (failed)

% Donja Dragotinja (failed)

% Kozarac – Kamicani subsystem (failed)

% Ljubija – Hambarine subsystem (failed)

% Urban subsystem (failed)

Page 63: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

63Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Wastewater - Otpadne vode

Only 34 % of municipality is sewered, 62% of urban populationPercolating septic tanks in useDischarges to Sana riverTreatment –none

Oko 34% opštinskog stanovništvaspojeno na kanalizaciju, 62% gradskogPropusne septičke jameIspusti u Sanu i pritokeTretman ne postoji

Municipality of Teslic

Page 64: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

64Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Tomasica Lake and CatchmentTomašička jezera

Alluvial deposits

Fish ponds

Leisure Complex

Residential

development

Page 65: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

65Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

20 km from Tomasica to Prijedor20km of Tomašica do Prijedora

Pipeline will cross river and multiple streams

Cevovod prelazi reku i potoke

Page 66: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

66Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

WWTP Site 1 Too Close to HousesLokacija 1 – blizu kuća

Page 67: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

67Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

No houses within 500m radius of WWTP 2Nema kuća do 500m od PPOV lokacije 2

Page 68: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

68Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Proposed WWTP Touches Protection ZoneLokacija na samoj granici šire zone zaštite

Page 69: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

69Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Benefits of the Project - Koristi projekta

More reliable drinking water supplyRemoves groundwater pollution riskRemoves wastewater discharges to surface waterReduces health risks

Poboljšani nivo i pouzdanost vodosnabdevanjaZaštita vrednih vodnih resursa odzagadjivanjaPoboljšanje kvaliteta povrsinskih vodaSmanjenje rizika po zdravljestanovništva

Page 70: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

70Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Summary of impacts – PIP -Kratak pregled uticaja projekta

Summary of impacts – PIP - Kratak pregled uticaja projekta

PIP components C  O C O C O

Prijedor WWTPTreatment Capacity (pe) 0 0 51,000 ‐‐  ++ Gravity sewers (m)Tukovi secondary network and house connections (Phase 2) 19200

‐‐  ++ 19200

‐‐  ++ 19200

‐‐  ++ 

Gomjenica primary network (Phase 1) 13500 ‐‐  ++  13500 ‐‐  ++  13500 ‐‐  ++ Kozarac primary and secondary sewage and stormwater networks N 1800 1800

‐‐  ++ 

Omarska primary and secondary sewage and stormwater networks (Omarska and Donja Omarska) N

‐‐  ++ 17650

‐‐  ++ 17650

‐‐  ++ 

Conveyance system to Prijedor WWTP (overflow, main collector, bypass  N N 2800.0 ‐‐

Sewage pumping Gomjenica pumping station (l/s) 25 ‐‐  ++  25 ‐‐  ++  25 ‐‐  ++ 

Water supply investmentsNetwork extensions (m) 61200 ‐‐  ++  61200 ‐‐  ++  61200 ‐‐  ++ Crno Vrelo water supply project ‐ primary network in settlements 61200

‐‐  ++ 61200

‐‐  ++ 61200

‐‐  ++ 

Tomasica Lakes water supply project (new source, primary and secondary networks) N 86800

‐‐  ++ 86800

‐‐  ++ 

Network rehabilitation (replacement of existing pipes)Rehabilitation of Prijedor central water supply system 0 0 0

Sludge DisposalTo landfill or N N Y ‐‐ ‐‐Non‐agricultural use of sludge for soil conditioning and fertilisation N N

Y ‐‐ +++

HighMinimum Base

Page 71: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

71Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Conclusions - ZaključciSignificant beneficial impact No potential risks to public healthGood design and construction practice = no unacceptable environmental impact

Koristan učinak je znacajanBez projekta = veliki nepovoljni uticaji na zdravlje ljudiDobro projektovanje i izvođenje – nema neprihvatljiv ekološki utjecaj

Page 72: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

72Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Best Practicable Environmental Option – integrated evaluation of sludge treatment and use / disposal optionsPriority is to identify sludge outlets that:

Recycle nutrients and organic matter on land (agriculture, forestry, land reclamation)Recover energy (incineration, co-combustion)

Landfill disposal is the option of last resort

Sludge Management Strategic ApproachStrateški pristup upravljanju muljem

Najbolja izvodljiva ekološka opcija – integrisana evaluacija opcija za tretman mulja i njegovo korišćenje/odlaganjePriorit predstavlja identifikovanje upotrebe mulja kojom se postiže:

Recikliranje nutrienata I organskih materija na zemljištu(poljoprivreda, šumarstvo, obnavljanje zemljišta)Obnavljanje energije (spaljivanje, koinsineracija)

Odlaganje na deponiju je najmanje poželjna opcija

Page 73: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

73Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Sludge production at WWTP design capacity: 1080 t ds/y135 ha/y required (at 8 t ds/ha)2.5% of actually cultivated landMost farms too small for sludge spreading to be practicable19 farms have 644 haMarketing programme crucialStorage necessary (6 months)

Sludge Use in AgricultureUpotreba mulja u poljoprivredi

Proizvodnja mulja pri projektovanom kapacitetu PPOV: 1080 t SM/godPotrebno je 135 ha/god (za 8t SM/ha)2,5% realno obradivog zemljištaVećina farmi je previše mala da bi upotreba mulja bila prakticna19 farmi ima 644 haMarketinški program je od suštinske važnostiPotrebno je skladište mulja (6 mjeseci)

Page 74: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

74Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Large and long-term potential at Omarska mine250 ha currently planned to be rehabilitatedPotential demand 12,700 t ds10 years of sludge productionLong-term storage on mineOther periodic opportunities

Sludge Use in Land ReclamationUpotreba mulja u obnovi zemljišta

Značajan i dugoročni potencijal narudniku OmarskaTrenutno se planira da 250 ha budesaniranoPotencijalna potražnja je12.700 t SM10 godina proizvodnje muljaDugoročno skladištenje u rudnikuDruge periodične prilike

Page 75: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

75Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Regional sanitary landfill ‘Stara Pruga’ Kurevo10 year waste capacityGate fee (currently only 5 KM/t)Composting facility may be installed in the futureDisposal of sludge only if no other option available

Sludge DisposalOdlaganje mulja

Regionalna sanitarna deponija “Stara Pruga' KurevoKapacitet za odlaganje otpada je 10 godinaNaknada za odlaganje otpada (trenutno samo 5 KM/t)Objekat za kompostiranje se može instalirati u budućnostiOdlaganje mulja samo ako nijedna druga opcija nije dostupna

Page 76: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

76Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

ForestrySmall area afforested annuallyNo potential for sludge use

Energy recoveryPossible future potential Cement factory (proposed)Toplana (biomass project)

Other Options for Sludge UseUpotreba mulja za obnavljanje energije

ŠumarstvoGodišnje se pošumi mala površinaNema potencijala za upotrebu muljaDobijanje energije

Mogući budući potencijalCementara (predlozena)Toplana (projekat biomase)

Page 77: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

77Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Evaluation of Sludge Outlets in PrijedorOpcije za upotrebu/odlaganje mulja u Prijedoru

Outlet Opcija

Practicability Prakticnost

Capacity Kapacitet

Overall Feasibility Ukupna izvodljivost

Sludge Quality Kvalitet mulja

Agriculture Poljoprivreda

High Visoka

Large Visok

High Visoka

Stabilised, cake Stabilizovan, kolac

Land reclamation Obnavljanje zemljista

High Visoka

Large Visok

High Visoka

Stabilised, cake Stabilizovan, kolac

Forestry Sumarstvo

Low Niska

Small Male

Low Niska

Stabilised, dry Stabilizovan, suv

Energy recovery Obnovljiva energija

Nil - currently Nula – trenutno

Nil Nula

Nil Nula

- -

High – future Visoka - buducnost

Large Visok

High Visoka

Cake or dry Kolac ili suv

Landfill Deponija

High Visoka

Large Visok

High Visoka

Stabilised, >35% ds Stabilizovan, >35% SU

Page 78: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

78Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Maximise use of sludge in land rehabilitation by long-term agreement with ArcelorMittalMarket sludge to large farms and secure agreementEstablish local guidelines on sludge use as no national law yetMinimise disposal to landfill

Priorities for Sludge Strategy DevelopmentPrioriteti za razvoj strategije za mulj

Maksimalno korišćenje mulja u obnovi zemljišta kroz dugoročnisporazum sa ArcelorMittal-omUvesti mulj na tržište za velike farme i obezbijediti sporazumUspostaviti lokalne smjernice o korišćenju mulja jer još uvijek ne postoji nacionalni zakon Minimalno odlaganje na deponiju

Page 79: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

79Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Financial AppraisalFinansijska Ocena

Results of Financial Appraisal in respect to proposed development project

Rezultati finansijske ocene predloženog razvojnog projekta

Sohail HassanEnvironment Sector Expert – WYG-IPF1

Ključni ekspert za zaštitu životne okoline – WYG-IPF1

Vladimir SurlaSenior Financial Analyst – WYG-IPF1

Finansijski analitičar – WYG-IPF1

Page 80: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

80Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Operating financial resultOperativni finansijski rezultat

• In order to assess operating profitability of the company, bad debt costs have been estimated as difference between reported revenues and collected related amounts.•Kako bi utvrdili operativnu profitabilnost kompanije, izvršena je procena troškova rezervisanja na potraživanjima kao razlika između generisanih prihoda i odgovarajućih uporedivih iznosa naplate.

•It can be concluded that adjusted annual operating loss of the company is currently around KM 300-400 thousand. This is the additional amount needed in order for Vodovod to be able to cover all of its operating costs.•Može se zaključiti da korigovani operativni gubitak kompanije trenutno iznosi između KM 300-400 hiljada na godišnjem nivou. To predstavlja neophodan dodatni iznos sredstava kako bi Vodovod bio u mogućnosti da pokrije sve svoje tekuće operativne troškove.

•Vodovod is not able to finance significant CAPEX, while these activities are financed primarily by Municipality. •Vodovod nije u mogućnosti da finansira značajnija kapitalna ulaganja, pri čemu se finansiranje ovih aktivnosti vrši pre svega od strane Grada.

-700,000

-200,000

300,000

800,000

1,300,000

1,800,000

2,300,000

2,800,000

3,300,000

2009 2010 2011 1H2011 1H2012

Operating revenues after estimated bad debt costs Operating costs Adjusted operating lossOperativni prihodi nakon procenjenih troškova rezervisanja Operativni troškovi Korigovani operativni gubitak

Page 81: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

81Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Operating prihodiOperativni prihodi

• Main operating revenues are generated through water-supply activities, which account for around 81% of total operating revenues. Wastewater segment generates only around 13% of operating revenues, due to lower tariffs and lower number of customers.•Ključni operativni prihodi se generišu od vodosnabdevanja koje predstavlja 81% ukupnih operativnih prihoda. Usluge kanalizacije generišu svega 13% operativnih prihoda, usled nižih cena i manjeg broja potrošača.

•Increase in operating revenues in 2011 and 1H2012 are mainly caused by increase in tariffs, and also by extension of water-supply network which increased number of customers.•Povećanje operativnih prihoda u 2011 i prvoj polovini 2012 godine je uglavnom uzrokovano povećanjem cena, kao i proširenjem sistema vodosnabdevanja što je dovelo do povećanja broja potrošača.

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

2009 2010 2011 1H2011 1H2012Other operating revenues Waste water services Water servicesOstali operativni prihodi Usluge kanalizacije Usluge vodosnabdevanja

Page 82: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

82Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Present Tariff LevelsTrenutni tarifni nivo

WaterVoda

WastewaterOtpadne vode

CombinedKombinovano

From Jul 2011 in KM/m3

Od Jula 2011 u KM/m3

DomesticDomaćinstva

0.88 0.21 1.09

CommercialPrivreda

2.20 0.55 2.75

InstitutionalBudžetski potrošači

1.52 0.49 2.01

• Based on 2011 data, additional overall tariff increase of 20% would enable Vodovod to cover all current operating costs of the company. This is assuming all other things remain equal, including collection rate of 83%.•Na osnovu podataka iz 2011 godine, dodatno povećanje cena od 20% bi omogućilo Vodovodu da pokrije sve tekuće operativne troškove, pod pretpostavkom da svi ostali parametri ostanu nepromenjeni, uključujući stopu naplate od oko 83%.

•Future tariff levels should be used to cover OPEX, as well as to finance CAPEX maintenance and urgently needed investments in water and wastewater services.•Budući nivoi cena treba da se koriste za pokrivanje operativnih troškova, održavanje osnovnih sredstava, kao i za finansiranje hitno potrebnih investicija u oblasti vodosnabdevanja i otpadnih voda.

Page 83: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

83Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Operating costsOperativni rashodi

• Main company expenses are wages which represent around 63% of total operating costs. •Glavni trošak kompanije su zarade zaposlenih koje predstavljaju 63% ukupnih operativnih troškova.

•Net wages remained practically the same in past three years, while increase in total wages expense is due to increase in related taxes and contributions. •Neto zarade se praktično nisu menjale u zadnje tri godine, dok je porast ukupnih troškova zarada uzrokovan porastom poreza i doprinosa.•Material costs are also significant company expense and represent 22% of total operating costs. This is mainly caused by high electricity costs since water is pumped into the network.•Troškovi materijala su takođe značajni i predstavljaju 22% ukupnih operativnih troškova. Ovo je pre svega usled visokih troškova električne energije koji nastaju pumpanjem vode u distributivnu mrežu.

-

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

2009 2010 2011 6m2011 6m2012Other OPEX Depreciation Wages Material costs

Ostali operativni troškovi Amortizacija Zarade Troškovi materijala

Page 84: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

84Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

ObavezeLiabilities

• Inability to cover total operating costs leads to constant increase in liabilities of the company. Vodovod is not settling electricity bills in adequate manner which is the main reason for overall increase in liabilities.• Nemogućnost pokrivanja ukupnih operativnih troškova rezultira u konstantnom povećanju obaveza. Vodovod ne izmiruje adekvatno svoje obaveze po računima za struju što je osnovni razlog ukupnog povećanja obaveza.

•Key risk of the company is accumulated liabilities for electricity bills in total amount of KM 8.9 million. Vodovod and Municipality should immediately explore any possibilities for settling these liabilities in satisfactory manner or arranging repayment schedule.•Ključni rizik za kompaniju predstavljaju nagomilane obaveze za električnu energiju u ukupnom iznosu od KM 8.9 miliona. Vodovod i Grad bi trebalo da odmah istraže sve mogućnosti za regulisanje i/ili reprogramiranje ovihobaveza na zadovoljavajući način.•Other long-term liabilities represent debt for wages related taxes and contributions accumulated prior to 2007. Vodovod agreed with Tax Authorities to repay this debt over next 15 years, starting from 2013.•Ostale dugoročne obaveze predstavljaju dug za poreze i doprinose na zarade akumuliran u periodu pre 2007. Vodovod je sa Poreskom Upravom ugovorio otplatu ovog duga u narednih 15 godina počevši od 2013 godine.

-

2,000,000

4,000,000

6,000,000

8,000,000

10,000,000

12,000,000

14,000,000

2009 2010 2011 1H2012

Other long-term liabilities Wages liabilities Taxes and fees Financial liabilities Accounts payableOstale dugoročne obaveze Obaveze za zarade Porezi i naknade Finansijske obaveze Dobavljači

Page 85: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

85Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Municipality borrowing capacityMogućnost zaduživanja Grada

000 KM 2010 2011 2012

Current revenues from the previous year

Redovni prihodi iz prethodne godine

23,212 24,591 28,668

Debt service

Servisiranje duga1,945 2,644 N/A

Debt service as % of current revenues

Servisiranje duga kao % odredovnih prihoda

8.4% 10.8% N/A

Max allowed debt service (18% of current revenues)

Max za servisiranje duga (18% od redovnih prihoda)

4,178 4,426 5,160

Max capacity for additional debt service

Max kapacitet za dodatno servisiranje duga

2,232 1,782 N/A

Municipality is servicing all of its financial liabilities in timely manner,

and has no overdue liabilities.Grad servisira sve svoje finansijske obaveze na vreme, i nema dospelih

neplaćenih finansijskih obaveza.

Municipality has low level of debt and significant capacity for raising

additional financial loans.Grad ima nizak nivo zaduženosti i

značajan kapacitet za dodatno finansijsko zaduživanje.

In 2011, debt service represented10.8% of current revenues generated

in the previous year, which is significantly below legally allowed

amount of 18%.U 2011, servisiranje duga je

predstavljalo svega 10.8% redovnihprihoda iz prethodne godine, što je daleko ispod zakonski dozvoljenog

iznosa od 18%.

Page 86: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

86Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Municipality borrowing capacityMogućnost zaduživanja Grada

• If potential EIB loan in the amount of KM 15.75 million is included, debt service would be highest in 2021 when it would represent 11.2% of current revenues generated in 2011.• Uključujući potencijalni EIB kredit od KM 15.75 miliona, servisiranje duga bi bilo najviše u 2021 godini kada bi iznosilo 11.2% redovnih prihoda iz 2011 godine.

• Municipality originally estimated that EIB loan for the project would be KM 15.75 million. However, Municipality has significant capacity for raising additional debt above that level, and there would be no legal constraints if final financing structure includes higher EIB loan then initially estimated. Maximum borrowing capacity, assuming EIB loan terms, is KM 34 million.• Prvobitna procena Grada je bila da će za ovaj projekat biti potreban EIB kredit u iznosu od KM 15.75 miliona. Međutim, Grad poseduje značajan kapacitet za dodatno zaduživanje iznad tog nivoa, tako da neće biti zakonskih prepreka ukoliko konačna finansijska struktura bude uključivala veći iznos EIB kredita nego što je prvobitno procenjeno. Maksimalni zakonski kapacitet zaduživanja Grada, pretpostavljajući uslove kreditiranja EIB-a, iznosi KM 34 miliona.

Debt service schedule in KM – Raspored otplate duga u KM

-

1,000,000

2,000,000

3,000,000

4,000,000

5,000,000

6,000,000

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025Potential EIB loan Nova BL bank UniCredit bank NLB bank

Potencijalni EIB kredit Investiciono-Razvojna Banka RS Hypo bankaPotencijalni EIB kredit Nova BL banka UniCredit banka NLB banka

18% of current revenues in 2011 - 18% redovnih prihoda u 2011

Page 87: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

87Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Alternative Development OptionsAlternativne opcije razvoja

• Investment Costs:

• Prices including VAT and local inflation

Min Base High

KM 000 KM 000 KM 000

17,167 38,754 52,088

• Financing Plan:

Min Base High

Loan 50% 50% 50%

Equity Contribution 50% 50% 50%

• Good prospects for grant contributions

• Investicioni troškovi:

• Cijene uključuju PDV i lokalnu inflaciju

Min Osnovni Max

KM 000 KM 000 KM 000

17,167 38,754 52,088

• Finansijski plan:

Min Osnovni Max

Kredit 50% 50% 50%

Doprinos korisnika 50% 50% 50%

• Dobri izgledi za doprinose u vidu donacija

Page 88: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

88Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Assumed Terms and Conditions of EIB LoanPretpostavljeni uslovi kredita od EIB

Assumed conditions• 25 Loan maturity period• 8 years grace period• 4.5% fixed interest rate

Min Case: Loan 8.583 KM mEquity Contribution 8.583 KM m

Base Case: Loan 19.377 KM mEquity Contribution 19.377 KM m

High Case: Loan 26.044 KM mEquity Contribution 26.044 KM m

• Met from Vodovod Revenues• Debt Service Coverage Ratio of over

1.2

Pretpostavljeni uslovi• period dospijeća zajma 25 godina• grejs period 8 godina • fiksna kamatna stopa od 4.5%

Minim. projekat: Kredit 8.583 KM mDoprinos korisnika 8.583 KM m

Osnovni projekat:Kredit 19.377 KM mDoprinos korisnika 19.377 KM m

Maksim. Projekat:Kredit 26.044 KM mDoprinos korisnika 26.044 KM m

• Pokrivaju se iz prihoda Vodovoda • Koeficijent pokrivenosti servisiranja duga

preko 1.2

Page 89: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

89Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Debt Service Implications for VodovodImplikacije servisiranja duga po Vodovod

Annual Repayments in KM

Min Case - Max 891,152 in 2020

Base Case - Max 2,011,796 in 2020

High Case - Max 2,703,977 in 2020

Godišnje servisiranje kredita u KM

Minimalni projekat - Max 891,152 u 2020

Osnovni projekat - Max 2,011,796 u 2020

Max projekat - Max 2,703,977 u 2020

‐100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000 900,000 

1,000,000 

Loan repayment Interest Total financial fees

Min Case ‐Minimalni projekat

500,000 

1,000,000 

1,500,000 

2,000,000 

2,500,000 

Loan repayment Interest Total financial fees

Base Case ‐ Osnovni projekat

Page 90: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

90Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Summary of Financial Projections for Vodovod – Base CasePrikaz finansijskih projekcija za Vodovod – Osnovni slučaj

-500,000

-

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

Operating cash Total including fees, interest and principal

Discretionary Capex Cash after Discretionary Capex

Page 91: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

91Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Future Tariff LevelsBudući tarifni nivoi

Page 92: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

92Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Financial Internal Rate of Return (FIRR) – Base CaseFinansijska interna stopa povraćaja – Osnovni slučaj

Calculation criteriaIncremental investments and

operating costs

• Water supply investments

• Waste water investments

Incremental revenues

• Based on projected tariffsand volumes for water supply and wastewater

Results of the analysis

• FIRR: -1%

• Benefit costs ratio: 0.55

• Financing gap: 45%

Kriterijumi kalkulacijeInkrementalni investicioni i operativni

troškovi

• Investicije u vodosnabdevanje

• Investicije u otpadne vode

Inkrementalni prihodi

• Bazirano na projektovanim tarifama i količinama za vodosnabdevanje i otpadne vode

Rezultati analize

• FIRR: -1%

• Racio koristi/troškovi: 0.55

• Manjak finansiranja: 45%

Page 93: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

93Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Economic Internal Rate of Return (EIRR) – Base CaseEkonomska interna stopa povraćaja – Osnovni slučaj

Incremental project costs:• Water supply and wastewater

investment costs

• Water supply and wastewater incremental operating costs

• Cost of removal of septic tanks

Incremental project benefits:• Secured water supply services

• Health benefits

• Increased development potential

• Resource cost saving

Results of the analysis:

• EIRR: 7%

• Benefit costs ratio: 1.15

Inkrementalni troškovi projekta:

• Investicije u vodosnabdevanje i otpadne vode

• Inkrementalni operativni troškovi vodosnabdevanja i otpadnih voda

• Troškovi uklanjanja septičkih jama

Inkrementalne koristi projekta:

• Pouzdano vodosnabdevanje

• Zdravstvene koristi

• Povećanje razvojnog potencijala

• Ušteda troškova resursa

Rezultati analize:

• EIRR: 7%

• Racio koristi/troškovi: 1.15

Page 94: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

94Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Affordability for HouseholdsPriuštivost za domaćinstva

• Affordability Criteria – 3% to 4% of average household income for water and sewerage

• Current tariffs - account for about 1.5% of average household income

• Projected tariffs:

• Base Case would be 2.0% of household income in 2015

• Reducing to 1.6% of household income in 2025

• Kriterijum priuštivosti – 3% do 4% prosečnih prihoda domaćinstava za vodu i kanalizaciju

• Trenutne tarife – iznose oko 1.5% prosečnih prihoda domaćinstava

• Predviđene tarife:

• Osnovni projekat - 2.0% od prihoda domaćinstava u 2015. godini

• Smanjenje na 1.6% od prihoda domaćinstava u 2025. godini

Page 95: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

95Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Financial Analysis – Key Findings and Issues Finansijska analiza – Ključni zaključci i pitanja

• Real and inflation linked tariff increases are needed and services remain affordable

• Vodovod is financially sustainable, meeting all debt financing needs and operating costs

• Funding issues – availability of local and international finance

• Potrebna su određena realna povećanja tarifa (iznad stope inflacije) ali da pri tome usluge ostanu priuštive

• Vodovod je finansijski održiv, ispunjava sve obaveze otplaćivanja duga i pokriva operativne troškove

• Sporna pitanja finansiranja – dostupnost investicija na lokalnom i međunarodnom nivou

Page 96: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

96Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Indicative implementation plan – Base CaseIndikativni plan implementacije – Osnovni Slučaj

Page 97: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

97Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Indicative implementation plan – Base CaseIndikativni plan implementacije – Osnovni Slučaj

Page 98: Prijedor Water and Wastewater · PDF filesnabdevanje vodom i pokrivenosti Svest o nedostacima i potrebama sistema Kompetentno i obučeno osoblje Vodovoda. Infrastructure Projects Facility

98Municipality of PrijedorInfrastructure Projects Facility in the Western Balkans – Implemented by WYG

Thank you for your attention!Hvala na pažnji!