problems on piles

42
PROBLEMS ON PILES/DEEP FOOTING Problem # 01 A cast in place concrete pile in medium sand is 0.5 m in dia and 10 m long. The water table is 2 m below the top of the pile. The bulk density of sand above the water table is 1.8 t/m 3 . and below the water table the density is 1.95 t/m 3 . Angle of shearing resistance is 38 o . Assume N qp = 60 and k s tan = 0.5, D c /B = 8. Determine the ultimate load and the safe load for a pile with F.S = 3.

Upload: engineer-fozeb-ali

Post on 17-Nov-2014

878 views

Category:

Documents


9 download

TRANSCRIPT

Page 1: Problems on Piles

PROBLEMS ON PILES/DEEP FOOTING

Problem # 01A cast in place concrete pile in medium sand is 0.5 m in dia and 10 m long. The water table is 2 m below the top of the pile. The bulk density of sand above the water table is 1.8 t/m3 . and below the water table the density is 1.95 t/m3 . Angle of shearing resistance is 38o . Assume Nqp = 60 and ks tan = 0.5, Dc /B = 8. Determine the ultimate load and the safe load for a pile with F.S = 3.

Page 2: Problems on Piles

SolutionQf = Qb + Qs

(1) Base resistence (Qb )

B = 0.5 m Lp= 10 m

Nqp = 60 Dc = ? From table

for medium sand, Dc = 8 x B = 8 x 0.5 = 4 m

Lp > Dc .

fb = o Nqp Where o = Effective vertical pressure at Dc .

o = (1.8 x 9.8 x 2) + ( (1.95-1) x 9.8 x 2) = 53.9 kPa.

fb = 53.9 x 60 = 3234 kPa.

Qb = Ab x fb = /4 B2 x fb . = /4 x (0.5)2 x 3234 = 635 kN.

2 mDc = 4 m

Page 3: Problems on Piles

• (ii) Frictional resistence, Qs

Qs = As x fs

fs =?

The frictional resistence is calculted by considering the pile in three parts, 0-2m, 2 m - 4 m (Dc ) and 4 m –

10 m. The frictional resistence will increase upto Dc only = 4 m.

at 2 m = 2 x 1.8 x 9.8 = 35.28 kPa. at 4 m = (35.28 + ( 1.95- 1) x 9.8 x 2) = 53.9 kPa.Average vertical stress for 0-2 m = 17.64 kPa. ( 0+ 35.28/2) Av. fs1 =17.64 x ks tan = 17.64 x 0.5 = 8.82 kPa.

Av. Stress for 2 m to 4 m = 53.9 + 35.28/2 = 44.59 kPa. Av. fs2 = s x ks tan = 44.59 x 0.5 = 22.3 kPa.

Page 4: Problems on Piles

• Vertical stress below Dc is assumed constant and equal to 53.9 kPa.

• fs3 = 53.9 x 0.5 = 26.95 ( unit skin friction)

• Qs = fs1 x B x D1 + fs2 x B (Dc – D1) + fs3 B (Lp - Dc )• = 8.82 x x 0.5 x 2 + 22.3 x x 0.5 x 2 +26.95

x 0.5 x 6 = 352 kN.• Qf = Qb + Qs = 635 + 352 = 987 kN.

• Qa = Qf /3 = 987/3 = 329 kN.

Page 5: Problems on Piles

Problem # 02

• A cased concrete pile, 0.42 m outside diameter, is driven through 11 m of loose sand and for a depth of 3 m into underlying medium dense sand. The skin friction is measured with a static cone fitted with a friction sleeve; fs = fc(av) = 20 kPa in loose sand and fs = fc(av) = 55 kPa in medium dense sand. The cone resistence at base level is 12000 kPa. Determine the safe load for a pile, using F.S = 2.5.

Page 6: Problems on Piles

Solution

• Qf = Qb + Qs

• Qb = /4 B2 x fb fb = qc = 12000 kPa but limit is 11000 kPa

• Qb = /4 (0.42)2 x 11000 = 1524 kN.

• Qs = Qs1 + Qs2 ,Qs1 = through loose sand = 11m• Qs2 = through medium dense sand =3 m.• Qs = B x 11 x 20 + B x 3 x 55• = x 0.42 x 11 x 20 + x 0.42 x 3 X 55 = 290.28 + 217.71• Qf = Qb + Qs = 1524 + 290.28 + 217.71= 2032.0 kN.

• Qa = Qf /2.5 = 2032/2.5 = 812.8 kN.

Page 7: Problems on Piles

Problem # 03

• Determine the penetration depth for a 40 cm dia. Concrete pile which is required to carry load of 900 kN at a safety factor of 2.5. The soil consists of silty sand upto a depth of 10 m in which the average cone resistance (qc)av = 4000 kPa. Silty sand is underlain by dense sand. The average cone resistance increases to 13000 kPa within the depth 10 m to 10.5 m and to 18000 kPa below 10.5 m. to reach full base resistance the pile must be driven to at least 5B, i-e 2 m, in bearing stratum of dense sand.

Page 8: Problems on Piles

Solution

• Try the allowable load for a pile, embedded length 12m. Min.

• Qf = Qb + Qs

• Qb = fb x Ab

• fb = qc = 18000 kPa But limit of fb =11000 kPa

• Qb = fb x /4 B2 = 11000 x (0.42)2 x /4 = 1381.6 kN.

• Now Qs = Qs1 +Qs2 +Qs3.

0-10m 10-10.5m + > 10.5.\ fs1 = 0-10m = qc av /200 = 4000/200 =20 kPa.

Page 9: Problems on Piles

• fs2 = 10 – 10.5 = qc av /200 = 13000/200 =65 kPa.

• fs3 = 10.5 – 12 = qc av /200 = 18000/200 = 90 kPa. (< 100 kPa)

• Qs = B [(10x20) + (0.5x65) + (1.5x90)]

D1 x fs1 D2 x fs2 D3 x fs3

= x 0.4 ( 200 + 32.5 + 135) = 461.81 kN.Qf = Qb + Qs = 1381.6 + 461.81 = 1 843.41

fs3 x B x D = 407

D = 407/90 x x 0.4 = 3.6m. 12 + 3.6 = 15.6 mQa = Qf /F.S. 1843.41/2.5 =737.36

Qf = Qa x F.S = 900 x 2.5 = 2250.

Receiving Load = 2250 – 1843 = 407 kN

Page 10: Problems on Piles

Problem # 04

• A bored concrete pile 30 cm in dia. And 6.5m long, passes through stiff fissured clay, subjected to seasonal shrinkage and swelling upto a depth of 1.5m. The average undrained strength of clay varies linearly from 50 kPa at 1.5m to 186 kPa at 10m. Find the ultimate load capacity. Assume = 0.3.

Page 11: Problems on Piles

Solution

• 1.5m top is ignored as the shrinkage may cause all adhesion to be lost.

• Cu at 1.5m depth = 50 kPa.

• Now cu at base = 50 + 186- 50/8.5 x 5 = 130 kPa

• Average cu = 50 + 130 /2 = 90 kPa.

• Qf = fb x Ab + fs As

• 1170 x /4 (0.3)2 + 27 x x 0.3 x 5• =82.7 + 127.27 = 210 kN.

Page 12: Problems on Piles

Problem # 05(uplift Resistance)

• Find the uplift resistance and the safe uplift resistance (F.S = 2.5) of the under reamed pile installed in clay with the following data. (if the top 2m clay is active and subjected to swelling)

• Dia of shaft = 40 cm, dia. of bulb at base = 100cm.

• Length of shaft above bulb = 5m cu av along shaft = 115 kPa. Cu at base = 150 kPa and adhesion factor = 0.4

Page 13: Problems on Piles

Solution

• Projected area of bulb = /4 (Bb – B2)= 0.659 m2 .• Neglecting top 2m of activeness• As = B x 3 = 3.77 m2

• Qup = 0.659 fb + 3.77 fs [ fb =Nc x cu =9x150=135

fs = cu = 0.4x 115 = 46] = 0.659x 1350 + 3.77 x 46 = 1063 kN Safe uplift resistance = 1063/2.5 = 425 kN

Page 14: Problems on Piles

Problem # 06

• Find the penetration depth for a 35cm square R.C pile driven through sea bed for a jetty structure to carry a maximum compressive load of 500 kN and a net uplift load of 300 kN. The soil below sea bed consists of a 10m thick layer of saturated medium dense sand overlying dense sand and gravel. The average corrected SPT blows in the top 10m sand are 12 and on bottom sand gravel layer 40. No erosion is expected. The minimum safety factor should be 2.5 on the uplift load and 4 on the compressive load.

Page 15: Problems on Piles

Solution• Nav for top10m = 12 (sandy layer)• N in sand –gravel = 40• Total ultimate uplift resistance required = 2.5x 300 = 750 kN• Now fs (medium dense sand)= 2 Nav = 2x12=24 kPa.

• Qs (uplift ) in top 10m = (4x0.35x10)24 = fs x As =336 kN.• Remaiing uplift resistance = 750 – 336 = 44 kN.• Friction resistance per meter length in sand gravel = fs xAs (one meter)

• fs (dense gravel) = 2 Nav = 2x 40 = 80 kPa.

Friction resistance /meter length = 80 x 4 x 0.35x1 =112 kN/m.Further penetration required in dense gravel to resist the uplift of 414 kN.

= 414/112 = 3.7mTotal Penetration = 10 + 3.7 = 13.7m for uplift.

Page 16: Problems on Piles

Check for compressive load.Qf =Qb + Qs.

Qb = fb x Ab.

fb (dense gravel) = 40 N Lp /B ≤ 400 N. ≤400x40 ≤ 16000 kPa.

=40x4x 3.7/0.35= 16914.3 ≤ 16000 kPa.But maximum value of fb which could be adopted = 11000 kPa.

fb = 11000.

Now Qb = 11000 x (0.35)2 = 1347.5 kN.

Qs is same for compression as for uplift.\ Qf = 1347 + 750 = 2097 kN.\ F = Qf /Qa = 2097/500 = 4.2 > 4 safe.

this indicates that the required penetration is governed by uplift resistance. Penetration depth = 13.7 m below sea bed level

Page 17: Problems on Piles

Problem # 07(Pile load test)

• The following data refers to a cyclic pile load test carried out on a 300mm dia. pile 10m long.

• Plot the load settlement curves (total and net) and estimate the allowable load by different methods/criterians.

Load on pile top (kN) 150 200 250 300 400 500 600Total settlement on pile top (mm)

1.45 2.25 2.75 3.6 5.75 10.75

30.00

Net settlement on pile top (mm)

0.40 0.65 0.80 1.0 1.70 5.25 22.80

Page 18: Problems on Piles

Solution• Plot the load vs settlement ( Arithmatic graph)• Plot the load vs Net settlement(Arth. graph)• (a) Two third of the load causing 12 mm settlement, that is• Qa = 2/3 x 500 = 333.33 kN• (b) 50% of the load causing• Total settlement equal to 10%• Of the pile dia. i.e settlement of• 30mm (i.e 600 kN)• Qa = 1/2 x 600 = 300 kN.• (c) Net settlement 6mm 2/3 rd of that• 2/3 x 550 = 1100/3 = 366.66 kN• (d) Falling to striaght line Qu 600 kN, use F.S =2.• 600/2 = 300• Least of the above is 300 kN

Load

Sett

lem

ent

Page 19: Problems on Piles

Problem # 08

• Two independent loading tests on 300mm dia. Short bored piles in clay for which = 0, yielded the following results.

• Embedded length of pile Added load at failure (kN)• 2.15 100• 2.75 110• Assuming the adhesion is effective over the whole of the

embedded length, estimate the mean cohesion of the soil and the shaft adhesion factor to be used in extrapolating the test results to larger piles. The densities of the soil and concrete are 1.92 Mg/m3 and 2.40 Mg/m3 respectively.

Page 20: Problems on Piles

Solution:

• At point of failure v =0• s = 1.92 Mg/m3

• c = 2.4 Mg/m3. Qb + Qs = P + • (wt. of pile – wt. of excavated material)• Now P = 100 kN Lp = 2.15m.• Qb + Qs = c Ncp x Ab + c As = c Ncp x /4xd2

+ c x x d x Lp.

• = c x 9x /4 x 0.32 + c x x 0.3 x 2.15 = 0.636 c + 2.027 c • Ncp = 9 (Lp /d > 4)• P = 100 + wt. of pile – wt. of excavated material• = 100 + (2.4- 1.92) x 9.81 (/4 x 0.32 x 2.15)• = 100 + 0.715

Wt.

P

Qs

Qb

Page 21: Problems on Piles

• v = 0• 100.715 = 0.636 c + 2.027 c -----------(i)• Similarly for 2nd test results v = 0• Qb + Qs =9x c x /4 (0.3)2

+ c x x 0.3 x2.75• = 0.636 c + 2.592 c• Load = 110 + (2.4 – 1.92) x 9.81 (/4 x 0.32 x 2.75)• = 110 + 0.915 = 110.915• 110.915 = 0.636 c + 2.592 c ---------------------(ii)• Solve equation simultaneously• c = 18.06 , c = 100 and = 0.18

Page 22: Problems on Piles

Problem # 09

• A free standing, square group of 16 piles extends to a depth of 12 m in stiff clay which is underlain by rock at 24 m depth. The piles are 0.5 m in diameter and are spaced at 1.5 m centres. cT at base = 140 kPa, average (cT)av along shaft = 90 kPa, adhesion = 0.45, coefficient of volume decrease mv below base = 0.08 m2/MN, remoulded cT along shaft = 50 kPa. Assume group efficiency Eg = 0.65. Find the allowable load for the group with F = 2.5. Also estimate the settlement under the allowable load.

Page 23: Problems on Piles

Solution:

• (a) Considering individual piles. fb = cT Ncp = 140 x 9 = 1260 kPa

fs = cT = 0.45 x 90 = 40.5 kPa

Qf = /4 B2 fb + B Lp fs

= /4 0.52 x 1260 + x 0.5 x 12 x 40.5 = 247.4 + 763.4 = 1010.8 kN Qg = Eg .n Qf = 0.65 x 16 x 1010.8 = 10512 kN

(b) Considering block failure. QB = Bo Lo fb + 2 Lp ( Bo +Lo) fB ; Bo = Lo = 5 m, Lp = 12 m

fb = cT Ncp = 140 x 9 =1260 kPa

fs = cT ( remolded) = 50 kPa

QB = 43500 kN > Qg (31500 + 12000)

Qa = 1/2.5 Qg = 10512/2.5 = 4205 kN

Page 24: Problems on Piles

• For a settlement the load is assumed to act at an equivalent raft (5 m x 5 m) located at 12/3 = 4 m above the base. The compressible zone of 16 m thickness is divided into 4 layers, each 4 m thick. Pressure increase at the middle of each layer is calculated by assuming 2:1 spread of load Qs. The calculations are given in table. The total settlement is 48 mm.

Page 25: Problems on Piles

Layer Mid-depth (m)

Area (m2 )

(kPa) mv H (mm)

1 2 49 85.80 27.45

2 6 121 34.75 11.12

3 10 225 18.68 5.97

4 14 361 11.65 3.73

48.28

Page 26: Problems on Piles

Problem # 10

• A 40-ft-long precast pile is fully embedded in sand. The cross section of pile measures 12 in x 12 in. The allowable working load for the pile is 80 kip and 54 kip is contributed by skin friction. Determine the elastic settlement of the pile. Ep = 3 x 106 lb/in2 , Es = 4500 lb/in2 , and s = 0.3.

Page 27: Problems on Piles

Solution:

2

22

31

2

2326p

1

/18.0144

26

,.82.0,27.3

)1(

.065.0)103)(144(

)1240()54)(6.0(26

.1441212

26,54,/103/103E 0.6, Let

inkipA

Qq

AlsoIFigureFrom

IE

Dqs

ins

TheninxA

kipQkipQinkipxinlbx

EA

LQQs

p

wpwp

wp

wpss

wp

p

wpws

pp

wswp

Page 28: Problems on Piles

.71.0287.0358.0065.0

.287.021.4)3.01(

1000450012

40124

54

21.40.1

4035.0235.02

)1(

.38.082.03.01

10004500

1218.0

23

23

22

ins

issettlementtotaltheHence

ins

SoD

LI

IE

D

pL

Qs

ins

So

ws

wsss

ws

Page 29: Problems on Piles

Problem # 11

Refer to Figure 8.47 which shows the plan of a pile group. Each pile has a square cross section measuring 12 in x 12 in. the center-to-center spacing of the piles is 30 in.Determine the group efficiency of the piles by using:a. Eq. (8.112)b. Eq. (8.114)

Page 30: Problems on Piles

30 in.

12in

Fig. 8.47

Page 31: Problems on Piles

Solution:

• Part a: Using Eq. (8.112)•

%4.60604.0

3418

48302342

.,484,12,3,4

422

21

21

21

inDpandinDnnFor

npn

Ddnn

Page 32: Problems on Piles

• Part b: Using Eq. (8.114)

%.7.65657.08.21

4390

42331

8.2130

12tantan

tan90

111

11

1

21

1221

o

o

So

d

D

d

D

nn

nnnn

Page 33: Problems on Piles

Problem #13

• Refer to Figure 8.41a. For this group pile, n1=4,n2= 3, D = 305 mm, d = 1220 mm, and L= 15 m. The piles are square in cross section and are embedded in a homogenous clay with cu = 70 kN/m2. Use FS = 4 and determine the allowable load-bearing capacity of the group pile. Assume = 0.63

Page 34: Problems on Piles

Solution:

• From Eq. (8.116),

kN

Q

So

mkNcforFigureFrom

mp

mA

LpccAnnQ

u

u

p

upupu

1038703.80759.5812

157022.163.070093.0934

.63.0,/7019.8

22.1305.04

093.0305.0305.0

9

2

2

2

)(21

Page 35: Problems on Piles

• Again from Eq. (8.117), the ultimate block capacity is Lg Bg cu(p) Nc*+2(Lg +Bg) cu L, So

• Lg = (n1 – 1)d +2(D/2) = (4-1)(1.22)+ 0.305=3.965 m

• Bg = (n2-1)d + 2(D/2) = (3-1)(1.22)+ 0.305= 2.745 m

• L/Bg = 15/2.745= 5.46

• Lg /Bg = 3.965/2.745 = 1.44

• From Figure 7.16, Nc* 8.6. Thus • Block capacity = (3.965)(2.745)(70)(8.6) + 2(3.965 + 2.745)

(70)(15) = 6552 + 14091 = 20643 kN• So• Qg(u) 10,387 kN < 20,643 kN

• Qg(all) = Qg(u) /FS = 10,387/4 2597 kN.

Page 36: Problems on Piles

Problem # 14

• A group pile in clay is shown in Fig. Determine the consolidation settlement of the pile groups. All clays are normally consolidated.

Page 37: Problems on Piles

6 ft

48 ft

3 ft

27 ft

21 ft

12 ft

6 ft

2v:1H2v:1H

z

45 ft30 ft

Water table

Qg = 500 kip

Clay

sat = 115 lb/ft3

eo = 0.82 Cc = 0.3

sat = 120lb/ft3

eo = 0.7 Cc = 0.2sat = 122 lb/ft3

eo = 0.75 Cc = 0.25

Clay

Clay

sand

= 105 lb/ft3

Rock

Po(1),

p(1)

Po(2),

p(2)

Po(3),

p(3)

Pile group: Lg = 9ft; Bg = 6ft

Page 38: Problems on Piles

Solution:• The stress distribution pattern is shown in

Figure 8.49. Hence•

.45.87.0

2603

15542603log

82.01

213.0

/26034.621152

21271056

log1

/265366369

1000500

/421276279

1000500

/1554

221

6221

9

1000500

1

2)1(

)1(

)1()1(

)1(

1)1(1

2)3(

2)2(

2

11)1(

infts

ftlbp

p

pp

e

HCs

ftlbp

ftlbp

ftlbzBzL

Qp

o

o

o

o

c

gg

g

Page 39: Problems on Piles

.58.929.084.045.8,

29.0024.04025

2654025log

75.01

625.0

/40254.621223

4.62120124.62115481056

84.03500

4213500log

7.01

122.0

/35004.6212064.6211521271056

log1

3

2

)3(

2

2)2(

)2(

)2()2(

)2(

2)2(2

inssettlementTotal

infts

ftlb

p

ins

ftlbp

p

pp

e

HCs

g

o

o

o

o

o

c

Page 40: Problems on Piles

Problem # 15 • It is proposed to carry the load from a column on 350 mm

diameter bored piles. The total load to be carried is 2000 kN and the soil consists of a deep deposit of clay having the following properties:

• If the piles are • about 9 m long, • Estimate the • Number reqired • And suggest how • they should be• arranged

Depth (m)

Undrained shear strength (kN/m2)

0 100

3 110

6 125

9 125

12 135

Page 41: Problems on Piles

Solution:• Consider the ultimate load carried on pile:• Qf = Qb + Qs

• Taking average cu on shaft of pile as = 115 kN/m2 and an adhesion factor of 0.45 for a bored pile:

• Qf = 125 x 9 x (/4 x 0.352) + 115 x 0.45 x ( x0.35 x 9)• = 108 + 512 = 620 kN• Using a factor of safety of 3: Qa = 620/3 = 207 kN• No of piles required to carry 2000 kN = 2000/207 = 9.6• Say 9 piles which reduces the factor of safety slightly.•

Page 42: Problems on Piles

• Bored piles should be spaced at about 3 times their diameter and a suggested arrangement is shown on Fig.

• The action of the group• Must be checked for

stability.Consider a pier 2.35 m square:Qfg = 125 x 9 x 2.352 +115 x 0.45 x (4 x 2.35 x 9)

= 6212 + 4378 = 10590 kN

1 m

2.35 m1 m