PROGRAM OVERVIEW
PROGRAM NEED
» Does not meet current interstate design standards
» System does not accommodate traffic needs
PROGRAM OVERVIEW
Program Progress
CURRENT FUNDING / CONTRACTING ALTERNATIVES
IOWA DOT’S LARGEST HIGHWAY FUNDING EFFORT
CONSTRUCTION COMPLETED
BY THE NUMBERS
2017 CONSTRUCTION PROJECTS
2017 CONSTRUCTION PROJECTS
2017 CONSTRUCTION PROJECTS
2017 CONSTRUCTION PROJECTS
2017 CONSTRUCTION PROJECTS
2017 CONSTRUCTION PROJECTS
FUTURE PROJECTS
I-29/I-480/WEST BROADWAY » Reconstruction will address capacity needs,
improve safety, and correct functional design issues.
» Currently conducting environmental studies and conceptual design to identify a single preferred alternative.
I-29/I-480/WEST BROADWAY – 2 CONCEPTS
MANAGING THE PROGRAM
WHY PROGRAM MANAGEMENT APPROACH?
» Program magnitude » Limited resources to implement program work » Proactive budget and schedule management » Wanted access to new tools & technologies » Effective Communication across program
PROGRAM APPROACH
Contracting Industry
Design Consultants
PARTNERSHIPS
PROGRAM TEAM
PROGRESS REPORTING
PROGRESS REPORTING
*Program-Wide
CONSTRUCTION SCHEDULING SPECIFICATION
CURRENT CBIS CONSTRUCTION SPECIFICATION » Resource Loaded Schedule with clear Critical Path required in
Primavera
» AGC coordination in development of spec
» Base Schedule and Monthly Updates
CONSTRUCTION SCHEDULING SPECIFICATION
SCHEDULING SPEC RESULTS TO DATE » Implemented on seven contracts ($355M total) to date
» Integral to Construction Project Controls
» Expanded focus - critical path project activities
» Provides Owner confidence in milestone dates (major traffic shifts, major interim completion dates)
» Spec has been modified based on contractor/DOT feedback
TRAFFIC PERFORMANCE MONITORING » Transportation
Management Plans » Purpose – Safety, Traffic
Flow, Minimize Impacts » Use – Design Through
Construction » Elements –Speeds, Lane
Widths, Incident Management, Work Restrictions, Closure Periods, Performance Criteria
TRAFFIC MONITORING: PERFORMANCE
» Daily Travel Time: I-29 NB / I-80 WB
Monday Congestion
Friday Afternoon Congestion
PORTABLE ITS DEVICES / INTELLIGENT WORK ZONES
IWZ Device
Queue Detection
COLOR DYNAMIC MESSAGE SIGNS
Monday Congestion
Friday Afternoon Congestion
TRAFFIC INCIDENT MANAGEMENT » Traffic Incident
Management brings emergency professionals and the public together so that everyone is aware of traffic incidents and they can be cleared to get traffic back to normal as quickly and safely as possible.
Monday Congestion
Friday Afternoon Congestion