PROJECTS IN PUNJAB
M-2
M-3
E-4
Murree
ISLAMABAD (00)
Rahimyar Khan (655)
Sadiqabad (637)
Okara (1134)
Bahawalpur (844)
Sahiwal (1102)
Rawalpindi (1540)
Kharian (1412)
Gujranwala (1328)
Gujrat (1380)
Jhelum (1432)
Km 608
Sardar Garh (693)
Zahirpir (707)
Ahmedpur East (792)
Khan Bela (734)
T. M. Panah (756)
Nurpur Nauranga (814)
Lodhran N-5 (860), E-5 (100)
Mianchannu (1026)Chichawatni (1062)
Pattoki (1180)
Renala Khurd (1151)
Bahi Pheru (1204)
Gujar Khan (1491)
Sohawa (1473)
Shahdara (1268)
Jampur (668)
Ramak (872)
Retra (824)
Taunsa (798)
Shadan Lund (767)
M-1
FaisalabadM-3 (53), E-4 (0)
Muzaffargarh (32)
Multa
n N-
5 (93
7), N
-70 (0
0)
LAHORE (1260)
M-6
E-5
N-75
N-5
Khan
ewal
N-5 (
980),
E-
4 (18
0), E-
5 (0)
Km 1630
Kamoke (1307)
Kashmor (495)
Rajanpur (604)
N-5
Sahianwala (32)
Millat (48)Thokar Niaz Baig
M-5
N-80
Lar (915)
Manga (1220)
Kala Shah Kaku
Wazirabad (1362)
Bewata (181)
N-55
N-55
M-2
Pindi BhattianM-2 (119), M-3 (0), E-3 (0)
E-3
Kot Sabzal (612)
Chakri (316)
Bhang Bhatar (25)
National Highway/Strategic Road
Expressway
Road Proposed for Federalization
Motorway (Operational)
Motorway (Under construction)
Motorway (Planned)
National Capital
Provincial Capital
City/Town
Interchange
Province Boundary
River
N-70
Km (868)
Road/
BridgeProject/Section Km
PC-1
Cost
Contract
CostPSDP
2012-13Progress
Expected
Completio
n
1. Sutlej Musa Pak Shaheed Bridge 0.6 2130 1616 150 Subst. Completed
2.Chena
bHead Muhammadwala Bridge 1 2508
712 (P1)
405 (P2)
970 (P3)
50 Subst. Completed
3. N-5 Jinnah Chowk - Bahawalpur Chowk 8 1078234 (P1)
532 (P2)70 Subst. Completed
4. Sutlej Baba Farid Bridge 8.6 1108 513 24 Subst. Completed
5. N-5 Wah Gate Underpass at Taxila 1.27 993 873 70 Subst. Completed
6. IMDC Islamabad Murree Dual Cariageway 4213,60
03414 50 Subst. Completed
7. N-5 Khiali Flyover at Gujranwala Bypass 1.1 996 888 RMA 90% Jun-2013
8. N-115 Nag Shah Chowk Flyover (4-Lane) 1 1530 835 1259 74% Jul-2013
9.Link to
BZU
Khanewal- Multan Inter District
Road (Bosan Road) (2x Packs)7.5 4570
461 (P1)
531 (P2)750 79% Jul-2013
Rs in Million
ONGOING DEVELOPMENT PROJECTS
PUNJAB
(Return……)
Road/
Bridg
e
Project/Section K
m
PC-1
Cost
Contract
Cost
PSDP
2012-
13
ProgressExpected
Completion
10.Link to
Jinnah
Chowk
Rasheedabad Flyover of Inner Ring
Road Multan-- 1204 1204 200 Subst. Completed
11. N-115
Tri District Link (Jalalpur Pirwala -
Uch Sharif) (total 3x packs,2
completed)
42 31711566
(Pack-3)550
44%
(Pack-3)Sep-2013
12.Chena
b
Sultan Bahoo Bridge (Shorkot - Garh
Maharaja) (4x Packs)1 1603
770 (P1)
570 (P2)
572 (P3)
150 53% Dec-2013
13 IndusNishtar Ghat Bridge (Shaheed Benazir
Bhutto) (2 x Packs)1.2 5459 929 70 33% Jun-2014
14
Link to
Muzafa
rGhad-
Jhang
2 Lane Link road Head Muhammad
wala to Band Bosan Road
3.8
5189 189 50 Subst. Completed
15 M-2 Hiran Minar Interchange 0.5 260 234 -- Subst. Completed
16 Ravi Syedwala Bridge -- 1164 829 500 Recently awarded
17 N-1156 Lane Highway from Double Phatak –
Chowk Naagshah (Old Shujabad Road)8 4160 1440 1000 2%
18
Link to
Northe
rn
bypass
Multan
Dehar Road (Khad Factory to Pul
Khadal) Multan (5.6 Km) 22 809 211 300 13% Jul-2013
Rs in Million
ONGOING DEVELOPMENT PROJECTS
PUNJAB
(Return……)
PROJECTS IN KP
Abbottabad (70)
Khunjrab Pass (806)
Gilgit (540)
Batgram(165)
BeshamN-35 (218), N-90 (64)
Batkhela (81)
Dir (200)
Chitral (309)
Drosh
Malakand (74)
Chakdara N-45 (91), N-95 (0)
Tamergara (129)
Sher Ghargh (52)
Jalkhad 162
Naran (127)
Passu (683)
Aliabad (630)
ChilasN15 (240), N-35 (416)
Sazin (352)
Dasu (294)
Sust (720)
Haripur (33)
Dambu Das (102)
Jaglot N-35 (500), S-1 (0)
Skardu (167)
MuzaffarabadS-2 (40), S-3 (0)
Kohala (0)
ISLAMABAD
Torkham (1756)
Mughal Kot (397)
Daraban (467)DI Khan N-50 (531), N-55 (931)
Bannu (1073)
Ramak (872)
Pezu (990)
Malana
Sarai Gambila (1032)
Latambar (1101)
Lachi (1169)
Dara Ademkhel (1220)
Khushal Garh (108)
MansehraN-15 (0), N-35 (94)
S-1
N-35
N-45
PESHAWARN-5 (1700), N-55 (1264)
M-1 (155)
NowsheraN-5 (1657), N-45 (0)
Kalam (135)
Chakothi (55)
S-2
N-35
N-5
N-50
Balakot (40)
Srinagar
Kohat N-55 (1196), N-80 (146)
N-90
N-95
Pattan (257)Madyan
Bahrain
Yarik (964)
Dhanasar (388)
N-80
N-55
S-3Hatian
Km (868)
Paroa (896)
Jehangira(1638)
Rahimabad (570)
Gulmit (669)
Sassi (26)
Shangash (51
Bagicha (114)
Swabi (72)
National Highway/Strategic Road
Expressway
Road Proposed for Federalization
Motorway (Operational)
Motorway (Under construction)
Motorway (Planned)
National Capital
Provincial Capital
City/Town
Interchange
Province Boundary
River
Road Project Km
PC-1
Cost Contract Cost PSDP
2012-13Progress
Expected
Completion
1. N-15 Naran - Jhalkhad 43 53451369
50 Subst. Completed
2. N-15Jhalkhad - Babusar Top - Chillas
(2x Sections)66 4017
1206 (P1)
1313 (P2) 175 75% Sep-2014
3. M-14x Interchanges on M-1
(1 completed)- 1067
212 (Ghazi)
148 (Chach)
259 (Capt. Col
Sher Khan)
1205 (N-5)
50 80% Jul-2013
4. N-45 Lowari Tunnel 9 18,132 5450 1200 45% Jul-2017
5. E-2 Peshawar Northern Bypass (Pack-I) 7.6 1960 2219 1318 42% Jun-2013
6. N-80 Khushalgarh Bridge (Pack-I, Indus) 2.9 1,538 981 100 68% Oct-2013
7.Pak –
AfghanTorkham Jalalabad ACW 73 4,341 4341 -- 58%
FWO
Demobilized
8. N-45 Takht Bhai – Shergarh-Dargai 30 917 917 5093%
Subst. Completed
9. KKH Shatial Thor Nala Bypass (KKH) 37 3844 3518 DW 3% Sep-2014
Rs in Million
ONGOING DEVELOPMENT PROJECTS
KHYBER PAKHTUNKHWA
(Return……)
Road/
RiverConstruction Project Km Cost
PSDP
2012-13Progress
Expected
Completion
1. N-105 Larkana-Naudero-Lakhi (2 Packs) 61 4000 250Completed, Inaugurated
by President of Pakistan
on 28th Dec, 20122. N-305 Sakrand-Benazirabad (DCW) 20 1419 100
3. N-655 Ratodero -Naudero (Rehab) 14.7 847 100
4. DWHyderabad – Badin Road to Mir Wah Sanjar
Chang Road (2 Packs)52 1385 400
Completed,
Inaugurated by
President of Pakistan
5. N-155Larkana- Mohenjodaro upto Airport
(2 Packs)28 3041 500 82% May-2013
6.N-455
Larkana- Kamber 20.5 829 70 72% June-2013
7. Kamber- Shahdadkot 29 1043 250 38% Sep-2013
8. N-110 Gharo-Keti Bunder (3 Packs) 84 3300 350 74% May-2013
9. Indus Qazi Ahmed - Amri Bridge (2 Packs) 18 3683 500 59% Jun-2013*
10. N-255 Larkana-Nasirabad (Rehab) 34 1214 250 35% Dec-2013
11. LEP Lyari Expressway 32 10443 1200 74% Dec-2013
Rs in MillionONGOING GoP FUNDED PROJECTS
•Main Bridge is expected to be completed by June 2013
(Return……)
ONGOING DEVELOPMENT PROJECTS
BALOCHISTAN
Road/
BridgeProject/Section Km
PC-I
Cost
Contract
Cost
PSDP
2012-
13
Date of
start
Progres
s
Expected
Comp
1 N-65Nuttal - Sibbi –
Dhaddar 106 3,262
P-I 1,575
P-II 452
P-III 180
5 Dec-01 Completed
2 N-65Jacobabad &
Dera Allahyar 27 671 526 5 Jun-03 Completed
3 N-10Lyari- Gwadar-
Gabd (MCH)653 17,262 13,886 175 Jul-00 Completed
4 N-65 Kolpur Bypass 5.7 696 659 116.7 Dec-10 50% Jun-2013
5 N-70Waigum Rud -
Khajuri132 3473 1331 750 Sep-07 49% Sep-2013
6 M-8
Gwadar -Turbat-
Hoshab (3
Packs)
193 18379
P-I 2494
P-II 3687
P-III 3166
3302.5 Sep-04 68% Dec-2013
7 M-8
Khuzdar-
Ratodero
(3 Packs)
143 6672P-I 2207
P-II 1908
P-III 2306
1100 Apr-04 73% Dec-2013
8 N-85Hoshab- Basima
- Sorab454 22412 17,454 1100 Sep-07 22% Jun-2014
Rs in Million
(Return……)
ISSUES
Delay in completion of the projects is
mainly due to:
Shortage of Funds.
Law & order issues (Balochistan Projects).
Land Acquisition problems.
10
Multan
Shujaabad
Uch
Jalalpur Pirwala
TMP
Lodhran
Bahawalpur
Ahmedpur East
Chani Goth
Moosa Pak Shaheed Bridge
Moosa Pak
Shaheed Bridge
Khanewal
DISTANCE SAVING 41 KM
CONSTRUCTION OF TWO LANE MOOSA PAK SHAHEED BRIDGE AND APPRACH ROADS OVER RIVER SUTLEJ AT AIMANWALA, DISTT. BAHAWALPUR
Length (KM) : 610 m (approach length 2.8 km and 1.7 km)PC-I Cost (Original) : Rs. 1,148 M
(Revised) : Rs. 2,131 MContract Cost (Original) : Rs. 1,415 M
(Revised) : Rs. 1,616 MPSDP Allocations (2012-13) : Rs. 150 MConsultant : M/s REC (Pvt.) LtdContractor : M/s Karcon / Mishal Sania (JV)Date of Start : Jul - 2009Date of Completion (Original) : May – 2011
Overall Progress (Actual) : Subst. Completed
Current Status:
Project completed and open to traffic.
Multan
Khanewal
Kabirwala
Abdul Hakim
Garh Maharaja
Atharan Hazari
Layyah
Muzaffargarh
Shorkot11km
1.5km
2.4km
N-70
Chowk Azam
Head MuhammadwalaBridge
Chaubara
Existing Sher Shah Bridge
Head Muhammadwala Bridge Project
DISTANCE SAVING 40 KM
CONSTRUCTION OF TWO LANE BRIDGE OVER RIVER CHENAB AT HEAD MUHAMMAD WALA DISTT. MULTAN
Length (KM) : 1.010 Km (Bridge)3.34 Km (Right Approach)7.37 Km (Left Approach)
PC-I Cost (Original) : Rs 2,377 M (Global)(Revised) : Rs 2,508 M (Global)
PSDP Allocations (2012-13) : Rs. 50 M (Global) Contract Cost (Original) : Rs 755.638 M (Pkg-I)
Rs 457.117 M (Pkg-II)Rs 940.742 M (Pkg-III)
(Revised) : Rs 712.078 M (Pkg-I)Rs 405.568 M (Pkg-II)Rs 907.74 M (Pkg-III)
Consultant : M/s EA ConsultingContractor : M/s GRC (Pkg-I)
M/s Hidayatullah & Co. (Pkg-II)M/s Zarghoon (Pkg-III)
Date of Start : Jun - 2009Date of Completion (Original) : Dec – 2011Overall Progress (Actual) : Completed (All packages)
Current Status:Project completed and open to traffic.
14
N-5
N-5
JINNAH Chowk
(kumharawal)
KUMHARANWALA–VEHARI–BAHAWALPUR CHOWK (N-5)
(DUALIZATION / STRENGTHENING OF N-5, DISTRICT MULTAN)
Length (KM) : 8.2 KmPC-I Cost (Original) : Rs. 966 M (Global)
(Revised) : Rs. 1078 M (Global)PSDP Allocations (2012-13) : Rs. 70 M (Global)Contract Cost (Original) : Rs. 120.834 M (Pkg-I: Jinah Chowk-Vehari Chowk)
Rs. 532 M (Pkg-II: Bahawalpur Chowk-Vehari Chowk)(Revised) : Rs. 234.371 (Pkg-I)
N/A (Pkg-II)Consultant : M/s Asif Ali & AssociatesContractor : M/s Watan Builders (Pkg-I)
M/s CH. Abdul Latif & Co. (Pkg-II)Date of Start : Jul - 2008Date of Completion (Original) : Jul - 2009
(Revised) : Dec - 2010(Actual) : Jun - 2011
Overall Progress : Completed
Current Status:Project completed.
PAKPATTAN
MINCHINABAD
Location of
Pakpattan Bridge
Harunabad
Chishtian Mandi
Hasilpur
VIHARI
Mandi Burewala
Arifwala
SAHIWAL
OKARA
Dipalpur
LOCATION OF BABA FARID BRIDGE ACROSS RIVER SUTLEJ
LINKING PAKPATTAN WITH MINCHINABADA
nnex-A
BRIDGE OVER RIVER SUTLEJ CONNECTING PAKPATAN WITH MINCHINABAD (BABA FARID BRIDGE)
Length : 572 Meter (Main Bridge) 8 Km (Approach Road)PC-I Cost (Original) : Rs. 453.6 M
(Revised) : Rs. 1,108 M PSDP Allocations (2012-13) : Rs. 24.128 MContract Cost (Original) : Rs. 912.575 M
(Revised) : Rs. 913.470 M Consultant : M/s EA Consulting (Pvt) LtdContractor : M/s Kingcrete Builders Date of Start : Feb-2008Date of Completion (Original) : Jan-2010
(Revised) : Sep-2010(Actual) : Jan-2010
Overall Physical Progress : 87 % (Subst. Completed)
Project Status:
Bridge completed in Jan 2010. Work on approaches is in progress.
Hattar Road
Thatta Khalil Road
POF WahGate-1
Peshawar
4-LANE UNDERPASS AT WAH GATE NO. 1 (1286 M)
LOCATION MAP
CONSTRUCTION OF 4-LANE UNDERPASS AT WAH GATE NO. 1
Length (KM) : 1.286 Km (Barrel 127 m, Underpass 760 m)PC-I Cost (Original) : Rs 493 M
(Revised) : Rs 993 M (Approval under process)
Contract Cost (Original) : Rs 758.966 M(Revised) : Rs 872.500 M
PSDP Allocations (2012-13) : Rs 70 M Consultant : M/s EA ConsultingContractor : M/s GRCDate of Start : Dec - 2008Date of Completion (Original) : Jun - 2010
(Revised) : Feb - 2011(Actual) : Oct - 2011
Overall Progress (Actual) : Subst. Completed
Current Status:
Project has been completed and opened to traffic.
ISLAMABAD – MUZAFFARABAD ROAD PROJECT SATRA
MILE – LOWER TOPA SECTION
Jhika Gali
ISLAMABAD – MUZAFFARABAD DUAL CARRIAGEWAYSATRA MILE TO LOWER TOPA SECTION (N-75)
Length (KM) : 43KmPC-I Cost (Original) : Rs 8,242 M
(Revised) : Rs 12,666 M (approval under process)
Contract Cost (Original) : Rs 2,187 M(Revised) : Rs 3,414 M
PSDP Allocations (2012-13) : Rs 200 MConsultant : M/s NESPAKContractor : M/s HAKASDate of Start : Sep - 1999Date of Completion (Original) : July - 2001
(Actual) : Dec - 2010Overall Progress : Subst. Completed
Project Status:Project Section (Km 0 ~ 33) : Operational since May, 2008 (Taken over by Operation Wing NHA)
Project Section (Km 33 ~ 43) : Operational since Jan, 2011
Remarks:Project has been completed and opened to traffic.
KHIYALI FLYOVER PLAN
CONSTRUCTION OF KHIALI FLYOVER BRIDGE AT GUJRANWALA BYPASS (N-5)
Bridge Length : 330 MRamps Length : 359 MTotal length of flyover : 689 MApproach/Slip Roads Length : 850M PC-I Cost : Rs. 996 Million (under process)Contract Cost (Original) : Rs. 498 Million
(Revised) : Rs. 888.9 Million (VO # 1 yet to be concurred by Finance wing)
Consultant : M/s KNKContractor : M/s RECDate of Start : Nov-09Date of Completion (Original) : Feb-11
(Revised) : Sep-13PSDP Allocations (2012-13) : Nil (RMA Funded)
Overall Progress : 90%
Current Status:
Project has been completed and opened to traffic in May, 2013.
ROAD BETWEEN DOUBLE PHATTAK
AND NAAG SHAH CHOWK FLYOVERS
N-70/M-4 LINK INTERCHANGE (NAAG SHAH CHOWK FLYOVER)
PC-I Cost (Original) : Rs 364 M(Revised) : Rs 1,734 M
Contract Cost (Original) : Rs 602.940 M(Revised) : Rs 834.50 M
PSDP Allocations (2012-13) : Rs 1259 MConsultant : M/s NESPAKContractor : M/s Ch. Abdul Latif & Co.Date of Start : Jul - 2010Date of Completion (Original) : Jul - 2011
(Revised) : Dec - 2011(Expected) : Jul- 2013
Overall Progress (Actual) : 76%
Current Status:
Project is completed in May 2013. Asphaltic work on service roads is in progress.
LOCATION PLAN
BOSAN ROAD MULTAN
KHANEWAL – MULTAN INTER DISTRICT (BOSAN) ROAD MULTAN
Length (KM) : 7.5 KmPC-I Cost (Original) : Rs 4570.022 M (Global)PSDP Allocations (2012-13) : Rs 750 M (Global)Contract Cost (Original) : Rs 460.82 M (Pkg-IA)
Rs 530.60 M (Pkg-IB)(Revised) : N/A
Design Consultant : M/s Loya / ZeerukContractor : M/s Khalid Rauf & Co. (Pkg-IA)
M/s FWO (Pkg-IB)Date of Start : Mar - 2011 Date of Completion (Original) : Oct - 2011
(Revised) : Mar – 2013(Expected) : Jul- 2013
Overall Progress (Actual) : 75% (Pkg-1A)87% (Pkg-1B)
Issues & Impediments:
Pending liabilities.
6 x INTERCHANGES ON INNER RING ROAD MULTAN
Pack Flyover Rs in M Progress
I.Jinnah Chowk
1204Completed
Rasheedabad Chowk Completed
II. Chungi 81210 Completed
Chungi 9
III.Kalma Chowk
1597 CompletedDouble Phatak
Total 4011
INNER RING ROAD MULTAN WITH 6 X INTERCHANGES
PC-I Cost (Original) : Rs 6,445 M (Global)(Revised) : Rs 7,909 M (Global)
PSDP Allocations (2012-13) : Rs 200 M (Global)Contract Cost (Original) : Rs 1144.04 M (Pkg-I: Flyover at Jinah chowk &
Rasheedabad Chowk)
Rs. 1209.45 M (Pkg-II: Flyover at chungi # 8&9)Rs. 1262.19 M (Pkg-III: Flyover at Kalma chowk & Double phatak chowk)
(Revised) : Rs 1203.72 M (Pkg-I)N/a (Pkg-II)Rs. 1596.07 M (Pkg-III)
Consultant : M/s EA (Pvt.) Ltd.Contractor : M/s RMC (Pvt.) Ltd (Pkg-I)
M/s Maqbool Associate (Pkg-II)M/s Sarco-MSL (JV) Pkg-III)
Date of Start : Feb - 2010Date of Completion (Original) : Aug - 2011
(Actual) : Jan - 2013Overall Progress : Subst. Complete (Pkg-I)
Subst. Complete (Pkg-II)Subst. Complete (Pkg-III
Current Status:Project has been completed and opened to traffic.
Multan
Shujaabad
Uch
Jalalpur Pirwala
TMP
Lodhran
Bahawalpur
Ahmedpur East
Chani Goth
MULTAN - SHUJAABAD - JALALPUR
PIRWALA - UCH - TM PANAH ROAD (138 KM)
Aminwala Bridge
Khanewal
JALALPUR PIRWALA – UCH ROAD (N-115)
(REHABLITATION/UP GRADATION OF TRI DISTRICT LINK, SOUTHERN PUNJAB)
Length (KM) : 42 KmPC-I Cost (Original) : Rs 2,289.29 M (Global)
(Revised) : Rs 3,171 M (Global)PSDP Allocations (2012-13) : Rs 550 M (Global)Contract Cost (Original) : Rs 641.849 M (Pkg-I)
Rs 774.633 M (Pkg-II)Rs 1,565.570 M (Pkg-III)
(Revised) : Rs 827.526 M (Pkg-I)Rs 796.692 M (Pkg-II)N/A (Pkg-III)
Consultant : M/s ACCContractor : M/s Friends Enterprises (Pkg-I)
M/s RMC (Pkg-II)M/s SKB (Pkg-III)
Date of Start : Dec - 2009Date of Completion (Original) : Nov - 2010
(Revised) : Jun - 2012(Expected) : Sep - 2013
Overall Progress (Actual) : Subst. Complete (Pkg-I)Subst. Complete (Pkg-II)44% (Pkg-III)
Issues & Impediments:Package III delayed due to pending liabilities.
SHORKOT- GARH MAHARAJA BRIDGE ACROSS RIVER CHENAB
PROPOSED BRIDGE
SHORKOT
FAISALABAD
LAHOREJHANG
GARH MAHARAJA
CONSTRUCTION OF BRIDGE ACROSS RIVER CHENAB LINKING SHORKOT AND GARH MAHARAJA
Length (Package-I) : 855 M(Package-II) : 3.2 Km(Package-III) : 4.097 Km
PC-I Cost (Original) : Rs. 1603 MPSDP Allocations (2012-13) : Rs. 150 MContract Cost (Package-I) : Rs. 770 M (Main Bridge)
(Package-II) : Rs. 678 M (Revised) Rs. 570 M (Garh Maharaja Side Approach Rd) (Package-III) : Rs. 572 M (Shorkot side Approach Road & Drainage & Erosion Work)
Supervisory Consultant : M/s REC (Pvt) LtdContractor (Package-I) : M/s SARCO-Mishal Sania (JV)
(Package-II) : M/s Hidayat-Ullah Khan & Co.(Package-III) : M/s Friends Enterprise &HNAC (JV)
Date of Start (Package-I) : June, 2010(Package-II) : September, 2010 (Package-III) : September, 2011
Date of Completion : Dec, 2013 (Expected)Overall Progress (Package-I) : 76 %
(Package-II) : 42% (Package-III) : 40 %
Issues & Impediments:
Project suffered due to paucity of funds and resultant delay in payment to contractors.
34
BENAZIR SHAHEED BRIDGE ACROSS
RIVER INDUS AT NISHTAR GHAT
SHAHEED BENAZIR BHUTTO BRIDGE OVER RIVER INDUS LINKING N-5 WITH N-55 AT NISHTAR GHAT
PC-I Cost (Original) : Rs. 5459 M PSDP Allocations (2012-13) : Rs. 70 MContract Cost (Package-II) : Rs. 929 M (Main Bridge)
(Package-III) : Rs. 594 M (Approach Rd Zahir Pir To Chachran Sharif)Design Consultant : M/s EA Consulting (Pvt) LtdSupervisory Consultant : M/s REC (Pvt) LtdContractor (Package-II) : M/s FWO (Main Bridge)
(Package-III) : M/s RMC (Approach Rd ZP to CS)Date of Start : Jan 2012Expected Date of Completion : Jun 2014Overall Progress (Package-II) : 35% (Main Bridge)
(Package-III) : 30% (Approach Rd ZP to CS)
Current Status:Procurement of approach road from Rajanpur & River bed approx. 18 Km and Guide Banks / Training Works yet to be completed.
LINK ROAD FROM MUHAMMADWALA
BRIDGE – BUND BOSAN ROAD
CONSTRUCTION OF 2 LANE LINK ROAD FROM HEAD MUHAMMAD WALA BRIDGE TO BAND BOSAN ROAD
PC-I Cost (Original) : Rs. 189 M PSDP Allocations (2012-13) : N/AContract Cost : Rs. 189 MSupervisory Consultant : M/s EA Consulting (Pvt) LtdContractor : M/s Hidayat Ullah Khan & Co.Date of Start : Dec 2011Date of Completion (Original) : Jun 2012
(Expected) : Dec-2012Overall Progress : Subst. completed
Project Status:
Substantially completed.
1a: Location Plan
HIRAN MINAR INTERCHANGE ON M-2
PC-I Cost (Original) : Rs. 260 M(Revised) : N/A
Contract Cost (Original) : Rs. 234.073 M(Revised) : N/A
PSDP Allocations (2011-12) : Rs. 50 MPSDP Allocations (2012-13) : NilConsultant : M/s RECContractor : M/s Luqman BrothersDate of Commencement : Jul - 2010Date of Completion (Original) : Jan - 2011
(Revised) : Apr - 2011(Expected) : Dec – 2012 (Subject to availability of funds)
Overall Progress (Actual) : 83% (Substantially completed)
Present Status:
Project is completed in Dec-2012.
KKH
THAKOT (190)
PATTAN (257)
Chillas(417)
BATGRAM (160)
BARSEEN (307) RAIKOT
JAGLOT (500)
DANYORE(545)
HASSANABAD (624)
MARKHUN
(712)
DIH (750)
KHUNJERAB (806)
HASSAN ABDAL (0)
Jhalkhad (162)Babusar Pass
TATTAPANI
(468)
BESHAM (218)
DASSU (290)
Balakot (40)Attarshisha (14.5)
Kaghan (99)
Naran (122)
Ganool (57)
BATAKUNDI
(228)
Ht 14000 ft
DHODIAL
GARHI HABIBULLAH (28)
MUZAFFARABAD (62)
MansehraHAZARA UNIVERSITY
PROPOSED ALIGNMENTLEGEND
8 Kms
12 Kms
MANSEHRA - NARAN - JHALKHAD - CHILLAS (N-15)
Section Km Rs in M Progress
Mansehra – Naran 123 2741 Completed
Naran - Jhalkhad 40 1369 Subst.
Completed
Jhalkhad Babusar 29 1206 68%
Babusar Top-Chillas 38 1643 82%
Total 230 6959
Mansehra-Naran-Jalkhad Road
Naran-Jhalkhad Section
Length (KM) : 43.30PC-I Cost (Original) : Rs. 5346MContract Cost (Original) : Rs. 992M
(Revised) : Rs. 1,369MPSDP Allocations (2012-13) : Rs. 50 MConsultant : M/s RECContractor : M/s FWODate of Start : May-2002Date of Completion (Original) : Dec-2006
(Actual) : Dec-2008Overall Progress (Actual) : Subst. Complete
Current Status:
Substantially completed. Asphaltic Work and construction of drainage structure is in progress.
Jalkhad–Chillas Road (N-15)
Jhalkhad-Babusar Top Section
Length (KM) : 28.5PC-I Cost (Original) : Rs. 4,017 MContract Cost (Original) : Rs. 977M
(Revised) : Rs. 1206 MPSDP Allocations (2012-13) : Rs. 175 MConsultant : M/s RECContractor : M/s FWODate of Start : Oct-2004Date of Completion (Original) : Dec-2006
(Revised) : Dec-2010(Expected) : Dec-2014
Overall Progress (Actual) : 68.4%
Issues & Impediments:
FWO demobilized from site in 2009 due to non-release of funds to FWO and they have served notice to re-start thework on Jhalkhad – Chillas Section of Kaghan Valley road (N-15) and work is expected to complete by Dec-2014.
Jalkhad–Chillas Road (N-15)
Babusar Top-Chillas Section
Length (KM) : 38PC-I Cost (Original) : Rs. 4,017 MContract Cost (Original) : Rs. 1313M
(Revised) : N/APSDP Allocations (2012-13) : Rs. 175 MConsultant : M/s RECContractor : M/s FWODate of Start : Jan-2005Date of Completion (Original) : Dec-2006
(Revised) : Dec-2010(Expected) : Dec-2014
Overall Progress (Actual) : 82.5%
Issues & Impediments:
FWO demobilized from site in 2009 due to non-release of funds to FWO and they have served notice to re-start thework on Jhalkhad – Chillas Section of Kaghan Valley road (N-15) and work is expected to complete by Dec-2014.
LOWARI TUNNEL PROJECT (8.5 KM)
• Rail Tunnel excavation completed in Jan-2009
• Highway Tunnel (1.9 km) completed in Oct-2010
• North & South access roads (18 km) completed in 2007 & 2009
• Rail Tunnel converted into Road Tunnel
• PC-I cost is Rs 18 B
• Physical progress is 45%
SOUTH PLATFORMNORTH PLATFORM
SNOW
South Link Access Road
(0.8 Km)
Lowari Top
South Platform
North Platform
North Road Bridge
South Road Bridge
Main Road Tunnel (8500 M)Highway Tunnel
(1900 M)
CHITRAL DIR
North Link Bridge
North Link Access Road
Baradam Bridge
Highway Tunnel BridgeNorth Link
Access Road (4 Km)
South Access Road (7.3
Km)
North Access Road (6.9
Km)
Deleted from M/s SAMBU Contract
LEGEND:
Tunnel Works
LOWARI TUNNEL PROJECT (8.5 KM)
See next slide…….
Lowari Tunnel Project/N-45
Length (Tunnels) : 8.5 Km + 1.9 KmPC-I Cost (Original) : Rs. 7,984M
(Revised) : Rs. 18,132MContract Cost (Original) : Rs. 5,429M
(Revised) : Rs. 6,047MPSDP Allocations (2012-13) : Rs. 1200MConsultant : Geo-ConsultContractor : Geo-Consult/Typsa JVDate of Start : Sep-2005Date of Completion (Original) : Sep-2008
(Revised) : May-2012(Expected) : Jul-2017
Overall Progress (Civil works) : 44.5%(Whole Project) : 36.7%
Issues & Impediments:
Excuvation of 8.5 Km Tunnel has been completed as 14th Jan, 2009 and that of 1.9 Km on 2nd Oct, 2010. The Governmentof Pakistan has conveted Lowari Rail Tunnel into Road Tunnel in anticipation of traffic from Central Asian State owing topropose extension of road from Chitral to Tajikistan.Revised PC-I accordingly approved by ECNEC on 11th Nov, 2011. Conversely the contract between NHA and M/s SAMBU isunder dispute due to funds shortage. Amicable settlement between the parties are underway.
PESHAWAR NORTHERN BYPASS (32 KM)
NOWSHERA
JAMRUD
Railway line
(N-5)
START
GRAVE
YARD
TEHKAL
PAYANPESHAWAR
CITY
NASIR BAGH
REFUGEES
CAMP
HAYATABAD
TOWN UNIVERSITY
TOWN
RAILWAY TRACK
SURKAMAR
END
PESHAWAR
CANT
N
(N-55)
2.
• Bypass will reduce congestion in Peshawar City
• Project cost is Rs 9 billion
• Work on first 8 km is ongoing
• Current progress is 42%
• Land acquisition for balance 26 km ongoing
Peshawar Northern Bypass
(Package-I)
Length (KM) : 7.6 PC-I Cost (Original) : Rs. 9,003 M
(Revised) : N/AContract Cost (Original) : Rs. 1,962 M
(Revised) : Rs. 2,219 MPSDP Allocations (2012-13) : Rs. 1,318 MConsultant : M/s EAContractor : M/s MatraconDate of Start : Feb-2010Date of Completion (Original) : May-2011
(Revised) : Jul-2012(Expected) : Jul-2013
Overall Progress (Actual) : 47%
Issues & Impediments:
Rs. 300 million released against to Land of Mouza Nassapa.
Loya Associates, Karachi. 49Wednesday, June 19, 2013
KHUSHALGARH BRIDGE ACROSS RIVER INDUS (N-80)
• Existing rail-cum-road Bridge constructed in 1905
• Work on New Bridge commenced in Nov-2011
• Project cost is Rs 1.5 B
• Physical progress is 50%
NEW KHUSHALGARH BRIDGE ACROSS RIVER INDUS
Khushal Garh Bridge over River Indus
(N-80), (Bridge 0.358 Km, approach 2.46 Km)
Length (KM) : 0.35 + 2.4PC-I Cost (Original) : Rs. 1,538 Million
Contract Cost (Original) : Rs. 981 Million(Revised) : Rs. 1008 Million
PSDP Allocations (2012-13) : Rs. 100 MillionConsultant : M/s Loya AssociatesContractor : M/s Usmani Associates Date of Start : Oct -2011Date of Completion (Original) : Oct-2013 Expenditure todate : 694 Million
Overall Physical Progress (Actual) : 70%
Current Status:
Progress of work is satisfactory.
TORKHAM- JALALABAD ACW (75 KM)
Landi Kotal
F A T A
JALALABAD
Start PointECW
ACW
• Progress: 58%
• Cost: Rs 4.9 B
• Start: Jan-2007
• Work suspended since Aug-2008
• Non payment issue
• PSDP 2012-13: Nil
TORKHAM JALALABAD ADDITIONAL CARRIAGEWAY
AFGHANISTAN
Length (KM) : 73.69Contract Cost (Original) : Rs. 4341 M
(Revised) : NilConsultant : M/s NESPAKContractor : M/s FWO Date of Start : Jan - 2007Date of Completion (Original) : Jul - 2009
(Revised) : N/A(Expected) : --
Overall Progress (Actual) : 58%
Issues & Impediments:
Work was stopped by the contractor since Aug 2008 due to non payment of their bills. Meeting has been arrange inP&D Division for re-mobilization of Contractor M/s FWO and Minutes of Meeting has also been issued. Re-mobilizationplan is submitted by M/s FWO on 13th of December, 2012.
Chitral
Drosh
Mirkhani
Lowari PassUpper Dir
Lower Dir
Timergarah
Bajur
Malakand
DargaiTakhtbai
Chakdara
UP-GRADATION OF N-45 (NOWSHERA – DIR - CHITRAL)
Mardan
Nowshehra-Chakdara-Dir-Chitral N-45
PACKAGE-I, Dualization of Takht Bahi-Shergarh-Dargai Section
Length (KM) : 30PC-I Cost (Original) : Rs. 1,620M
(Revised) : Rs. 2,399MContract Cost (Original) : Rs. 622 M
(Revised) : Rs. 933 MPSDP Allocations (2012-13) : Rs. 50 MConsultant : M/s ACEContractor : M/s NLCDate of Start : Aug-2010Date of Completion (Original) : June-10
(Revised) : Nov-12 (approval Under process)(Actual) : Dec-12
Overall Progress (Actual) : 93% (Subst. Completed)
Issues & Impediments:
Subst. completed.Only 11 km Asphalt Wearing Course is left. EOT of Contractor M/s NLC is in process.
Nowshehra-Chakdara-Dir-Chitral N-45
PACKAGE-II, Rehab.of Dargai-Chakdara Section
Length (KM) : 25PC-I Cost (Original) : Rs. 1,620M
(Revised) : Rs. 2,399MContract Cost (Original) : Rs. 622M
(Revised) : NilPSDP Allocations (2012-13) : Rs. 50 MConsultant : M/s ACEContractor : M/s NLCDate of Start : Dec-2005Date of Completion (Original) : May-2006
(Revised) : Mar-2009(Actual) : Mar-2009
Overall Progress (Actual) : Substantially Complete
Current Status:
Substantially completed.
Nowshehra-Chakdara-Dir-Chitral N-45
PACKAGE-III, Improvement and widening of Timergara-Akhagram Road
Length (KM) : 25PC-I Cost (Original) : Rs. 1,620M
(Revised) : Rs. 2,399MContract Cost (Original) : Rs. 501M
(Revised) : Rs. 570 MPSDP Allocations (2012-13) : Rs. 50 MConsultant : M/s KCEIContractor : M/s NLCDate of Start : Jun-2006Date of Completion (Original) : Nov-2007
(Revised) : Dec-2009(Actual) : Sep-2010
Overall Progress (Actual) : Subst. Complete
Current Status:
Substantially completed.