progress summary

Upload: razanmrm

Post on 14-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Progress Summary

    1/1

    3.1 TABULAR PROGRESS

    xxxx

    xxxx

    Weekly Progress Report Rev. No.

    Period: xxx 0

    CONTRACTUAL INFORMATION

    Project Title

    Engineer

    Consultant

    Contractor

    Project Locations

    Original Start Date

    Original Completion Date

    Original Contract period

    1. PRELIMINARIES

    Reporting Period

    Time Elapsed (in days)

    Time elapsed (%)

    Revised Contract sum

    Advance Payment sum (10% of Contract sum)

    Approved Payment as of to date (Cumulative

    Net Amount Certified)Including the Down payment

    2.3

    FINANCIAL DETAILS

    Contract Value - QRs

    Total approved Variation orders

    3. POST CONSTRUCTION

    2.4

    OVERALL

    2. CONSTRUCTION

    2.1

    2.2