Page 1: Project control. Management

Project ManagementChapter 11 Project Control

Master student: Marius Miron2014

Page 2: Project control. Management

“Man does not plan to fail, he just fails to plan.”Anonymous

Murphy’s law: “If anything can go wrong, it will.”

Page 3: Project control. Management

The aim of this presentation is to answer the following questions:1 .W hat i s the purpose o f con t ro l ? To what i s i t

d i r ec ted?

-the purpose: the regulation of results through the alteration of activitiesthe stewardship of organizational assets

-control is the act of reducing the difference between plan and reality, hence it is in relation to physical assets, human and financial resources from initial planning and further to termination of a project.

Control

Performance

Cost Time

Page 4: Project control. Management

2.What are the three main types of control system? What question would a control system answer?

A. Cybernetic system control-negative feedback

loop

-path for correctionof deviation P from S

Page 5: Project control. Management

B. Go/no-go control system

A & B are directed to ongoing projects

Checkpoints

plan budget schedule

control

Pass=GO No pass=No-go

Page 6: Project control. Management

C. Postcontrol- applied after the fact-may become a problem if the specification of a

project have not being met-risk: “locking the barn after the horse has been

stolen”

-directed to improving the chances for future projects to meet their goals

OBS: whatever work is planned,

will also have to be controlled

Page 7: Project control. Management

3.What tools are available to the PM to use in controlling a project? Identify some characteristics of a good control system.

source: PMBOK

Page 8: Project control. Management

Tools: Critical ratio control chart(actual progress/scheduled progress) x

(budgeted cost/actual cost)

Page 9: Project control. Management

Tools: Critical ratio control limits

Page 10: Project control. Management

Tools: Cost/time chart

Page 11: Project control. Management

Tools: Cost control chart

Page 12: Project control. Management

Tools: Pareto-diagrams

Page 13: Project control. Management

4.What is the mathematical expression for the critical ratio? What does it tell a manager?(actual progress/scheduled progress) x

(budgeted cost/actual cost)“good” or “bad”?

Page 14: Project control. Management

5.Describe the relationship between motivation and control.

Control systems have a close relationship to motivation and should be well-balanced:

cost-effectiveappropriate to the desired end results not overdone.

Page 15: Project control. Management

6.How is creativity control?The approaches to the control of creativity are:process reviewpersonnel reassignment control of inputs.

Page 16: Project control. Management

7.What are go/no-go gauges?

-are tools that tell to an inspector if an object’s dimension is within certain limits.

-can be any measure that allows a manager to decide whether to continue, change, or terminate an activity or a project.

Page 17: Project control. Management

8.What is a champion?ChampionA person with organizational clout who takes on personal responsibility (though not usually

day-to-day management) for the successful completion of a project for the organization.

Page 18: Project control. Management

9. Describe a cybernetic control system.

Page 19: Project control. Management

10.What should the postcontrol report include?- Project objectives–Milestones and budgets–Final project results–Recommendations for improvement

Page 20: Project control. Management

11.How should change be controlled?

Acknowledge

Assess

Accept

Approve

Page 21: Project control. Management

12.Describe the quality(or phase)-gate process

Page 22: Project control. Management

“If you are solving problems faster than they are arriving to be solved, you have the project under

control. If not, you haven’t.”