    Al-Qassim UniversityCollege of engineering

    General Engineering DepartmentGE 402 Project Management

    by

    Sultan Sannat Alotaibi

    Submitted To

    Prof.Tomas U. Ganiron Jr

    426035210

    25-5-2010

    PROJECT CONTROL PROCESS

  • 7/30/2019 Project Control Process in Management

    2/13

    8-1 PROJECT CONTROL

    PROCESSPurpose : to ensure that project objectives are met by monitoringand

    measuring progress and taking corrective actions when necessary

  • 7/30/2019 Project Control Process in Management

    3/13

    8-2 Progress Measurement

    Traditional Approaches to Progress Measurement

    Budget vs. actualPercent completeTrust meModern ApproachesSmaller projects or projects with unstable scope:

    If we dont change our direction, we are likely to end up wherewere headed.

    AnonymousWeekly or biweekly deliverables

    Done or not done

    Larger projects:Earned value

  • 7/30/2019 Project Control Process in Management

    4/13

    8-3 Earned Value Concepts

    Earned Value Mechanics

    Build (and plot) your baseline

    Record (and plot) the actuals

    Measure (and plot) progress

  • 7/30/2019 Project Control Process in Management

    5/13

    Example

    Information developed by planning:

    WBS with 108 technical activities and 18management activities.

    Estimates show that all 126 activities will require 1person for 1 week.

    You are constrained to have three full-time staffers

    plus one half-time project manager.Staff and PM both cost $1,000 per week.

    Build Your Baseline

  • 7/30/2019 Project Control Process in Management

    6/13

    Solution

    1- Build Your Baseline

    Month Staff PM Total1

    $12,000

    $2,000

    $14,000

    2 $12,000 $2,000 $14,000

    9 $12,000 $2,000 $14,000Total $108,000 $18,000 $126,000

  • 7/30/2019 Project Control Process in Management

    7/13

    2-Plot Your Baseline

    Scheduled Cost($126,000)

    Cumulat

    ive

    Value

    s

    Time

  • 7/30/2019 Project Control Process in Management

    8/13

    3-Record Your Actuals

    Month # Staff Staff $ PM Total1 3.5 $12,000 $2,000 $14,0002 3.5 $12,000 $2,000 $14,0003 4.7 $16,000 $3,000 $19,0004 4.5 $16,000 $2,000 $18,000Total n/a $56,000 $9,000 $65,000

  • 7/30/2019 Project Control Process in Management

    9/13

    4- Plot Your Actuals

    Cumulative

    Value

    s

    Time

    ActualCost

    ($65,000)

    Scheduled Cost

    ($126,000)

  • 7/30/2019 Project Control Process in Management

    10/13

    5-Measure Your Progress

    Mo. DoneNot Staff PM Total1 10+2 2 $10,000 $2,000 $12,0002 9+2 5 $9,000 $2,000 $11,0003 13+2 4 $13,000 $2,000 $15,0004 16+2 0 $16,000 $2,000 $18,000Tot. 56 n/a $48,000 $8,000 $56,000

  • 7/30/2019 Project Control Process in Management

    11/13

    6-Plot Your Progress

    Cumulative

    Value

    s

    Time

    ActualCost

    ($65,000)

    Earned Value ($56,000)

    Scheduled Cost($126,000)

  • 7/30/2019 Project Control Process in Management

    12/13

    8-7 Monitor and Control

    During all of the phases and the process groups, regularmonitoring and controls are required. These include : scope change management, change management, quality control, time management, budget management, risk management and contract administration.

  • 7/30/2019 Project Control Process in Management

    13/13

    Activities in this group are:

    Monitor and Control Project Work Integrated Change Control Scope VerificationScope Control Schedule Control

    Cost Control Perform Quality Control Manage Project Team Performance Reporting

    Manage Stakeholders Risk Monitoring and Control Contract Administration