project delivery approaches: "which one is right for my parking facility?" walter p moore

32
Project Delivery Approaches: “Which one is right for my facility?” March 27, 2014 Jacob Gonzalez, P.E. Brian Lozano, PMP ©

Upload: jacob-h-gonzalez-pe

Post on 15-Jul-2015

127 views

Category:

Engineering


0 download

TRANSCRIPT

Page 1: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

Project Delivery Approaches:

“Which one is right for my facility?”

March 27, 2014

Jacob Gonzalez, P.E.

Brian Lozano, PMP

©

Page 2: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

AGENDA

INTRODUCTION

DESIGN BID BUILD

DESIGN BUILD

CONSTRUCTION MANAGEMENT AT RISK

INTEGRATED PROJECT DELIVERY

OPEN DISCUSSION

©

Page 3: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

Which project delivery approach was utilized?

Marq-E Entertainment Garage

Buffalo Niagara Medical Campus MiGo GarageWoodlands Waterway Square Garage

©

Page 4: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN TEAM PROJECT MANAGER

©

Page 5: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

PROJECT MANAGER RESPONSIBILITIES

scope

budget schedule

©

Page 6: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN TEAM PROJECT MANAGER RESPONSIBILITIES

Scope

Budget Schedule

Scope

Budget Schedule

Scope

Budget Schedule

Scope

Budget Schedule

Scope

Budget Schedule

Scope

Budget Schedule

Landscape

Architecture

MEP/IT

Civil

Traffic

Parking Design

Scope

Budget Schedule

Structural

©

Page 7: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN TEAM CONSTRUCTION COST EXAMPLE

70.0%

15.0%

7.0%

5.0%

1.5%1.0% 0.5%

Structural

Architect

MEP/IT

Civil

Parking Consultant

Landscape

Traffic

©

Page 8: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

PROJECT ALIGNMENT

©

Page 9: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

PROJECT ALIGNMENT

DEFINE VISION AND GOALS

UNDERSTAND THE DELIVERY APPROACH

UNDERSTAND THE PROCUREMENT METHOD

PERFORM A SCOPE GAP ANALYSIS

PERFORM A PULL SCHEDULE

MAINTAIN ALIGNMENT THROUGHOUT

©

Page 10: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN BID BUILD

Terminal E FIS Garage Phasing

Marq-E Entertainment Garage Harris County Parking Garage

©

Page 11: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

The Construction Management Association of America

DESIGN BID BUILD

©

Page 12: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

OWNER

DTPM CONTRACTOR

SUB CONTRACTORSDESIGN TEAM

contractual obligation,

direct communication

& collaboration

Indirect communication

& minimal collaboration

DESIGN BID BUILD

STRUCTURE

©

Page 13: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

PROJECT SCHEDULE

DESIGN-BID-BUILD: 25 MONTHS

RFP Design Permit Procure Construction

2 5 2 142

©

Page 14: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN BID BUILD ADVANTAGES/DISADVANTAGES

• LONGER DURATION

• MORE RISK FOR OWNER

• CHANGE ORDERS

• OPEN COMMUNICATION

BETWEEN OWNERS AND

DESIGNERS

• DESIGN CONTROL

• COMPETITIVE PRICING

X

©

Page 15: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN BID BUILD PROJECT EXAMPLE

Rusk Garage Ramp Reconfiguration

©

Page 16: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN BUILD

500 South Main Garage, Las Vegas, NV

Buffalo Niagara Medical Campus MiGo Garage UTMDACC Braeswood Garage

©

Page 17: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN BUILD DEFINITION

The Construction Management Association of America

©

Page 18: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

OWNER

DESIGN

BUILDER

SUB CONTRACTORSDTPM / DESIGN TEAM

direct communication

& collaboration

contractual obligation, direct communication

& collaboration

DESIGN BUILD

STRUCTURE

©

Page 19: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

PROJECT SCHEDULE

DESIGN-BID-BUILD: 25 MONTHS

DESIGN-BUILD: 21 MONTHS

RFP Design Permit Construction

ConstructionRFP Design PermitBridging

Documents

2 5 2 14

122 22 3

2

Procure

©

Page 20: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN BUILD ADVANTAGES/DISADVANTAGES

• LESS DESIGN CONTROL

• DESIGN BUILDER CONTROLS

COMMUNICATION

• QUALITY OF MATERIALS

DICTATED BY DESIGN BUILDER

• RISK BY DESIGN BUILDER

• FASTER SCHEDULE

• LOWER COST

X

©

Page 21: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

DESIGN BUILD PROJECT EXAMPLE

500 South Main Garage, Las Vegas, NV

©

Page 22: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

CONSTRUCTION MANAGEMENT AT RISK

Texas Medical Center Garage 19

Texas Medical Center Garage 18Woodlands Waterway Square Garage

©

Page 23: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

OWNER

DTPM CONTRACTOR

SUB CONTRACTORSDESIGN TEAM

contractual obligation, direct communication

& collaboration

direct communication

& collaboration

CONSTRUCTION MANAGEMENT AT RISK STRUCTURE

©

Page 24: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

PROJECT SCHEDULE

DESIGN-BID-BUILD: 25 MONTHS

DESIGN-BUILD: 21 MONTHS

CM@RISK: 21 MONTHS

RFP Design Permit Construction

Construction

Construction

RFP

RFP

Design

Design

Permit

Permit

Bridging

Documents

2 5 2 14

12

12

2 5 2

2 22 3

2

Procure

©

Page 25: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

CMAR ADVANTAGES/DISADVANTAGES

• ADDITIONAL FEES PAID FOR CM

SERVICES

• ESTIMATES CARRY LARGER

CONTINGENCY

• REQUIRES STRONG PRECON

TEAM FROM CONTRACTOR

• MORE CONTROL OVER DESIGN

• CAN ESTABLISH GMP SOONER

• OPEN COMMUNICATION

BETWEEN ALL TEAM MEMBER

X

©

Page 26: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

CMAR PROJECT EXAMPLE

Texas Medical Center Garage 19

©

Page 27: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

George Washington University Hospital Renovations

INTEGRATED PROJECT DELIVERY

©

Page 28: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

INTEGRATED PROJECT DELIVERY

-The Construction Management Association of America

©

Page 29: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

OWNER

INTEGRATED PROJECT DELIVERY

DTPM CONTRACTOR

SUB CONTRACTORSDESIGN TEAM

Contractual obligation,

direct communication

& collaboration

©

Page 30: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

IPD ADVANTAGES/DISADVANTAGES

• TEAM SHOULD HAVE LONG

HISTORY OF WORKING

TOGETHER

• OWNER SACRIFICES FINANCIAL

STAKE IF TARGETS NOT MET

• BETTER FOR COMPLEX

PROJECTS

• REQUIRES STRONG

LEADERSHIP OR FACILITATORS

• INCENTIVE CONTRACTS

• RISK SHARED EQUALLY BY ALL

PARTIES

• HIGHLY COLLABORATIVE

• FASTER SCHEDULE

• LOWER COST

X

©

Page 31: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

OPEN DISCUSSION

©

Page 32: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore

Jacob H. Gonzalez, P.E.

[email protected]

713.410.6760

Brian Lozano, PMP

[email protected]

713.231.3417

Walter P Moore

1301 McKinney, Suite 1100

Houston, Texas 77010

©