project delivery update - california transportation commission...average number of bidders per...
TRANSCRIPT
Tab 47
Project Delivery Update by Mike Keever
Division of Project Management May 2019
Phases of Project Development
Capital Outlay Support (COS) COS Closeout Program Planning
PA&ED PID
PS&E (Design) Construction
Right of Way
Programming & Allocation
Allocation
Allocation Need & Priority
Identified
Prog
ram
med
PA&
ED
Com
plet
e
Con
stru
ctio
n C
ompl
ete
Des
ign
Com
plet
e
Ris
k an
d U
ncer
tain
ty
20% Known 80% Unknown
80% Known 20% Unknown
Low
High
Clo
seou
t Com
plet
e
Preliminary Engineering (15¢) Construction (85¢)
Project Cost Risk Management
Supplemental Funding and Greater Than 20% Allocation Requests
95-99% of Projects
Watch List
Caltrans District - Project Change Management
CTC
Caltrans HQ - Project Change Management
3
More Bidders Equals Lower Costs
Ave
rage
Num
ber
of B
idde
rs p
er P
roje
ct
Low Bidder Above or Below Estimate Average Number of Bidders per vs. Number of Bidders Project
9.0 20%
8.0
7.0
6.0
5.0
4.0
3.0
2.0
1.0 Ave
rage
Per
cent
age
Low
Bid
der w
as A
bove
or
Belo
w E
ngin
eer’s
Est
imat
e
10%
0%
-10%
-20%
-30%
-40%
-50%
-60%
Low Bid equals
Average Number of
-70% 0.0 0 2 4 6 8 10 12 14 16
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Number of Bidders per Project Year
(Projects Bid Opened from July 2004 to December 2017)
4
Data set is 476 projects awarded in the FY 17/18 FY
5
Bidding Environment
20
40
60
80
100
120
140
160
180
200
Construction Cost Index ( 2002 through 2019)
Rolling 12 month Quarterly CCI Data
2002 2004 2006 2008 2010 2012 2014 2016 2018
6
Bidding Environment Through April 2019
LowBid vs Engineer's Estimate (Monthly Tracking FY 18/19)
20.0%
15.0%
10.0%
5.0%
0.0%
-5.0%
-10.0%
-15.0%
-20.0%
Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19
7
Cost Estimating Improvement Initiative
Improved Estimating Tools Identification of Best Practices Quantification of Risk Training Business Intelligence Construction Cost Escalation Study
8
Supplemental and “Greater than 20%” Allocations
May 2019 CTC Meeting
Greater than 20% Tab # 48
Supplemental to Complete Construction Tab # 49
Thank You
Division of Project Management May 2019
Bidding Environment
20
40
60
80
100
120
140
160
180
200
Construction Cost Index ( 2002 through 2019)
2018 quarter to quarter comparison, shows more drastic changes per quarter
Rolling 12 month comparison to the quarterly CCI
2002 2004 2006 2008 2010 2012 2014 2016 2018
11
Supplemental and “Greater than 20%” Allocations
Supplemental to Award Supplemental PAED
Potential Items for June CTC Meeting
Greater than 20%
Supplemental to Re-Advertise
Five-Year Greater Than 120% vs Awarded FYs 13/14 to 17/18
13
Five-Year Number of Greater Than 120% vs Awarded FYs 13/14 - 17/18
14
Five-Year Supplementals to Award vs Awarded FYs 13/14 to 17/18
15
Five-Year Number of Supplementals to Award vs Awarded FYs 13/14 to 17/18
16
Five-Year Supplementals to Complete Construction vs Construction Contracts Completed-FYs 13/14-17/18
17
Five-Year Number of Supplementals to Complete Construction vs Contracts Completed-FYs 13/14-17/18
18
Risk Management
PIDs include Risk Training on Quantification of Risk Watch List
19
Bidding Environment
Construction Cost Index ( 2002 through 2018)
mpering.
2004 2006 2008 2010 2012
te
200
180
160
140
120
100
80
60
40
20
2018 quarter to quarter comparison, shows stgrowth in CCI.
eep
Rolling 12 month comparison of 2017 Q3 and 20
Don’t know if you want to have this slide… it is what was presented in January. This shows
18 Q3 shows
the yearly average curve and then the 2018 2002 2014 2016 2018 quarter to quarter to show the spike. I think
that the new slide covers it. I think you can delete this one.
20
Bidding Environment
Low Bid vs. Engineer's Estimate 10%
18/19 data through
-15%
-10%
-5%
0%
5%
11/12 12/13 13/14 14/15 15/16 16/17 17/18 18/19
Perc
enta
ge o
f Lo
w B
id v
s. En
gine
er's
Estim
ate
October 2018
18/19 data through December 2018
Fiscal Year
Don’t know if you want to have this slide… it -20% is what was presented in January. Could be
used to show “what we were seeing…” then show what happened). Remember this slide is the 12 monthly yearly average… the other slide is a month by month comparison. I vote
21