Project preparation Niels-Erik Clausen Risø National Laboratory Training program in wind energy and project development Phuket, 11-15 September 2006 Module 1.1 Wind Energy Course, Phuket, 11-15 Sept 2006 2 The project cycle - Government Project preparation identification and formulation > ....> project proposal document feasibility study > revised project proposal appraisal > revised project proposal project document appropriation > Government Agreement Project implementation detailed design and construction (e.g. turn-key) monitoring and reviews Project completion performance verification, commissioning tests and Taking- over evaluation during liability period

Upload: msveng9691

Post on 01-Oct-2015

4 views

Category:

Documents


1 download

TRANSCRIPT

  • 1Project preparation Niels-Erik Clausen

    Ris National Laboratory

    Training program in wind energy and project development

    Phuket, 11-15 September 2006

    Module 1.1

    Wind Energy Course, Phuket, 11-15 Sept 20062

    The project cycle - GovernmentProject preparation identification and formulation > ....> project proposal

    document feasibility study > revised project proposal appraisal > revised project proposal project document appropriation > Government Agreement

    Project implementation detailed design and construction (e.g. turn-key) monitoring and reviews

    Project completion performance verification, commissioning tests and Taking-

    over evaluation during liability period

  • 2Wind Energy Course, Phuket, 11-15 Sept 20063

    Project Development Steps

    Measurements & data management Wind resource assessment Site selection Sketch design for power system analysis Feasibility study Environmental Impact Assessment (EIA) Power Purchase Agreement (PPA) EPC bidding and evaluation Construction Operation & Maintenance

    Wind Energy Course, Phuket, 11-15 Sept 20064

    Feasibility analysis

    Needs analysis Correspondence with national plans / policy Technology and site assessment Appropriate organisation Environmental analysis Public acceptability

  • 3Wind Energy Course, Phuket, 11-15 Sept 20065

    Financial analysis Budget / investments Investors Stakeholder analysis National energy

    policy supporting wind power

    Market analysis (the open power market)

    Power purchase agreement (PPA)

    Economic / financial analysis

    Internal rate of return (IRR)

    Cost Investments

    Land, wind turbine, foundation, grid connection

    Operation & maintenance Main overhauls Dismounting

    Benefit Production (kWh)

    Wind climate, siting, wind turbines performance

    Power sales price ($/kWh) Subsidies

    Wind Energy Course, Phuket, 11-15 Sept 20066

    Example: wind power economy

    Wind turbine: Rated power: 600 kW Rotor diameter: 43 m Hub height: 50 m

    Wind statistics: Height: 50 m Roughness length: 0,055

    m A = 7,9 m/s, k = 2,0 Air density: 1,225 kg/m3

    Production: Annual energy output:

    1,5 GWh

    Investment: Wind turbine: USD 450 000 Installation: 30% of USD 450000

    = USD135 000 Lifetime: 20 years Interest rate: 5 %

    Maintenance (annually): 1,5% of 450000 = USD 6750

    Land lease + insurance USD 7000 Electricity cost: 4,1 USc/kWh Income (annually): 1,5GWh @

    0,05USD = USD 75 000 Profit USD 14000

  • 4Wind Energy Course, Phuket, 11-15 Sept 20067

    Technical analysis

    Need for the power Wind resources Land available and

    accessible Wind power adaptable

    into the power system Sketch design

    Number of wind turbines

    Size of wind turbines Wind farm layout Grid connection

    Needs Energy / services needs Power demand

    development Alternatives

    Energy conservation Energy efficiency Alternative generation

    Thermal power plants Nuclear power

    generation Hydro power

    Wind Energy Course, Phuket, 11-15 Sept 20068

    Pre-project activities

    Carry out feasibility / financial / technical analysis

    Set up appropriate organisation Get legal project acceptance Ensure necessary capital (investors) Acquire land necessary Prepare tender documents Negotiate (turn key) supplier contract Supervise installation Take over the project

  • 5Wind Energy Course, Phuket, 11-15 Sept 20069

    (Turn key) supply

    Tender documents Contractual

    conditions Technical

    specifications Climate conditions Design wind

    conditions Grid connection

    requirements Power control

    requirements etc

    Contract (turn key) Civil works Foundation Equipment supply Erection Grid connection Warranty period Performance

    guarantee and test