project enginner cv2
TRANSCRIPT
SHAHBAZ AHMAD Village Wahndo Tehsil Kamonke District Gujranwala
[email protected], +966546608456/+92-345-9466257
Career Summary
A Professional & Experienced Engineer having more than six years’ experience in project management in the brown and green fields of petrochemical, fertilizer ,power, oil and gas projects .A team leader with experience of management of multinational and multi skilled manpower.
Major Area of Experience:
Project Execution Planning and cost control Material inventory and store management Quality control and assurance Implementation of site safety Programs Liaison with client and design consultant /subcontractors
Work Experience
1. SENDAN INTERNATIONAL CO. Ltd, SAUDI ARABIA (Feb 2013 till to date).
Projects Client Position Duration
Implementation Of MOCs At EG1(Turn Around)
UNITED Project In-charge March 2016, till to date
DEG Aldehyde removal System(EPC)
UNITED Project In-charge Jan 2016 ,to March 2016
Installation of Additional NRVs at Olefin (EPC Turnaround)
Petrokemya Project In-charge April 2015, to Dec 2015
Import of CO2 Line from United Metering Skid (EPC)
Albayroni Project In-charge Nov 2014, to April 2015
Replacement of 127-CB Condenser (Turnaround)
Albayroni Project In-charge Sep2014, to Nov2014
Replacement of Glycol Condensers and Pre heaters
(Turn Around)
Sharq Project Engineer Dec 2013, to March 2014
Natural Gas Black Powder Filters (EPC)
Sadaf Project Engineer June 2013, to Dec 2013
Replacement of collection and blow off Header (Turn
Around)
Sadaf Project Engineer Feb 2013, to June 2013
2. JGC-DESCON INTEGRATED PROJECTS Ltd, LAHORE PAKISTAN (June 2010 to Feb 2013).
Projects Client Position Duration
Installation, Erection and Commissioning of 425 MW Power Plant (EPC).
HYUNDAI Site Engineer Nov 2011, to Feb2013
Installation, Erection and Commissioning of 225 MW Power Plant (EPC).
HALMORE-Pak Site Engineer Jun 2010, to Nov 2011
RESPONCIBILITIES
Study the job scope, contractual obligations and compliance in detail.
To plan, analyze and review all changes, variations and their impacts on milestones, overall progress and schedule and discuss the results with parties involved prior to implementing the design and schedule.
Ensure that project management functions are being clearly understood and implemented within all hierarchies and wings.
Monitor the design activities from third party consulting firms and ensure the clear objectives are set for design team members.
Direct the production of the detailed project’s plans and schedules which identifies the critical strings of the activities (critical paths) and the total project’s resource requirements.
Development of the S-CURVE for the tracking of planned vs. actual progress. Planning and calculation of required man power, equipments, tools and consumables
and streamlining of the resources.
Submission of the execution plans, method statements, rigging plans, job safety analysis, general safety plans and QA/QC documents.
Direct the preparation of the required material’s BOQs and ensure there on time availability by following up with procurement department.
Preparation of the bid clauses, work scope descriptions and comparative cost statements for the hiring of subcontracting services required during project execution.
Review and challenge the submission of contractor’s recourse histogram for man power and equipment during the mobilization and peak phase of construction activities
Monitor the pre-fabrication of piping spools, sand blasting and painting, civil excavations, onsite erections and welding of pipelines within agreed schedule from contractor.
Monitor the pneumatic testing for integrity checks and pigging for overall cleanness tests during the commissioning stages of pipelines
Ensure that all works done in accordance with the approved mechanical construction drawings, contract documents, project specification and all applicable standards.
Attending meetings with the client regarding the technical issues, performance and daily progress evaluations, risk assessments and HSE issues for safely execution of the jobs.
Take responsibility for quality of installation ensuring that both specification and design parameters are met on site. Liaise with the client's representatives in relation to inspections and ensure that their requirements are clearly understood and are being met.
Identifying bottlenecks and preparation of catch up plans. Direct the cost estimation of the change orders with maximum accuracy,
technical and commercial negotiations and ensure on time completion with in deadlines.
Coordinate with management on project control activities, project health and analytical summery and strategies the cost and man hours control during the onsite execution.
Manage and control the claims/change orders and Ensure that invoices are tracked, confirmed and handed off to accounts payable properly.
Computer Skills Software Primavera P6, MS Project ,Matlab ,Hysys , Operating System Windows Xp,2007 Others MS Office
Interpersonal Skills Good communication skills Ample experience of meeting dead lines Leadership qualities Proactive
Education
Degree Institution Division
B.sc Chemical Engineering U.E.T Lahore 1stF.sc(Pre-Engineering) National Science College
Gujranwala1st
Matric(Science) G.H.S.School Wahndo 1st
Personal Details
CNIC No: 34102-6168393-5 Gender Male Passport No FW1163931 Passport Expiry 07-August-2017
Saudi driving License 04003501201982 Saudi Iqama 2340466164
ReferencesLinkedIn profile: https://www.linkedin.com/in/shahbaz-ahmad-83524323?trk=nav_responsive_tab_profile